Mary Lin Elementary School 586 Candler Park Drive Phasing Plan. March 25, 2010. Site Plan. Phasing. Phase 1 Site Utilities (Storm Drainage System, Fire Line, Water Line) Phase 2A Construction of New 2-Story Classrooms and Support Spaces Paving and Landscaping Improvements. Phase 2B - PowerPoint PPT Presentation
Popular Tags:
5
Mary Lin Elementary School 586 Candler Park Drive Phasing Plan March 25, 2010
Transcript
Page 1: Mary Lin Elementary School 586 Candler Park Drive Phasing Plan

Mary Lin Elementary School586 Candler Park Drive

Phasing Plan

March 25, 2010

Page 2: Mary Lin Elementary School 586 Candler Park Drive Phasing Plan

Site Plan

PhasingPhase 1Site Utilities (Storm Drainage System, Fire Line, Water Line)

Phase 2AConstruction of New 2-Story Classrooms and Support SpacesPaving and Landscaping Improvements.

Phase 2BRenovation of Cafeteria/Kitchen, and Classrooms

Phase 3Select Renovations on Main and Upper Levels, Classrooms and RestroomsGym Renovations

Phase 4AConstruction of New Administration, Media Center, and Connecting CorridorSite Utilities, Paving and Landscaping Improvements

Phase 4BSelect Renovations on the Main Level, Chorus, Band, and Classrooms

Page 3: Mary Lin Elementary School 586 Candler Park Drive Phasing Plan

Project LocationAerial View of Existing Site

Page 4: Mary Lin Elementary School 586 Candler Park Drive Phasing Plan

Project LocationAerial View with Phases 1 and 2

Phase 1North SiteSite Utilities (storm, fire, water)Sep 23,2013 - Dec 18, 2013

Phase 2ANew 2-Story Classroom AdditionNov 4, 2013 – Jul 1, 2014

Phase 2BRenovation of Cafeteria/Kitchen and ClassroomJul 21, 2014 – Feb 23, 2015

Page 5: Mary Lin Elementary School 586 Candler Park Drive Phasing Plan

Project LocationAerial View with Phases 3 and 4

Phase 3Classroom, Restroom Renovation, and GymMay 28, 2014 - Jul 30, 2014

Phase 4ANew 1-Story AdministrationAddition and RenovationJul 21, 2014 – Feb 23, 2015

Phase 4BChorus Band Classroom RenovationsOct 6, 2014 – Feb 23, 2015