Master’s ThesesMarch 2007
Civil Engineering
Stevinweg 1
PO Box 5048
2600 GA Delft
The Netherlands
Telephone: +31-(0)15-2788234
Telefax: +31-(0)15-2784889
2
Table of Contents
�
Master’s Theses 1
March 2007 1
Table of Contents 3
Preface 9
What is the graduation book exactly? 10
Civil Engineering ThesesStructural Engineering 13
Structural design of reinforced concrete pile caps 14
Student: A.V.vandeGraaf
Geboorde tunnels in ultra hoge sterkte beton 15
Student:T.W.Groeneweg
Application of high strength steel in Steel pin connections and Double shear timber joints 16
Student:R.D.Hieralal
De drijvende fundering 17
Student:MaartenKuijper
Externally bonded carbon fibre reinforced polymers 18
Student:R.H.Ringers
Vloeistofreservoirs: Maximale afmetingen ten aanzien van vloeistofdichtheid 19
Student:L.Stapper
Civil Engineering ThesesBuilding Engineering 21
Een Living Bridge voor Amsterdam 22
Student: L.Dietz
Waarde van het ontwerp in relatie tot de waarde van het proces 23
Student: T.J.Duvivier
Ondergrondse kleine infrastructuur 24
Student:M.P.Franken
Research of the functional and technical feasibility of a floating football stadium 25
Student: N.T.N.Groenendijk
Optimization of Dome Housing in Sri Lanka 26
Student:C.Hammer
Design tools for the Virtual Wind Tunnel 27
Student: R.A.G.Kerklaan
Functioneel Specificeren bij projecten van Rijkswaterstaat 28
Student: A.W.Lever
Variantenonderzoek Onderbouw Parkhaventoren 29
Student: O.Los
Progressive Collapse Assessment 30
Student: M.Smith
0307I Inhoudsopgave�
Optimisation of structural transfer zones in multi-use buildings 31
Student: R.vandeStraat
Parametric Associative Design for Free Form Architecture 32
Student: P.Vermeij
Civil Engineering ThesesHydraulic & Geo Engineering 33
Gabion Stability 34
Student: R.H.P.A.Beekx
Veldproeven op steenzettingen 35
Student:J.A.H.Blom
“Sandwich wall as the quay wall for the future” 36
Student: P.Bonte
“Dynamic behaviour of jetty structures under seismic conditions“ 37
Studente:H.deBrabander
Effects of softwood vegetation within groyne fields 38
Student: M.T.B.vandenBroek
Floating Breakwater 39
Student: M.W.Fousert
Feasibility Study on Tidal Power Barrages 40
Including plant design and site selection 40
Student:J.J.vanHarn
The sandhunger of the Oosterschelde 41
Student:M.L.E.B.vanderHoeven
The influence of flow acceleration on the stability of stones 42
Student:M.Huijsmans
Scour around an offshore wind turbine 43
Student:W.F.Louwersheimer
Dealing with uncertainties in the design of bottom protection near quay walls 44
Student: A.A.Roubos
“Computational modelling on the final closure gaps in the Saemangeum dam, South Korea” 45
Student:M.vanderSande
Hydraulic fracture grouting 46
Laboratory experiments in sand 46
Student:M.P.M.Sanders
The influence of flow acceleration on the stability of stones 47
Student:T.Schweckendieck
An analysis of friction by microtunneling (N.Verburg; 1041363) 48
Student:N.Verburg
0307
Civil Engineering ThesesWatermanagement 49
Probabilistic modeling of sewer deterioration 50
Student:J.Dirksen
Risk Assessment for Floods Due to Precipitation Exceeding Drainage Capacity 51
Student: U.Karamahmut
The impact of the deep water extraction at the position of the fresh-salt interface 52
Student: N.L.Kramer
Integrated water quantity and water quality control of lowland water systems 53
Student: B.vanRossum
A distributed stream temperature model using high resolution temperature observations 54
Student: M.Westhoff
Civil Engineering ThesesTransport & Planning 55
Dynamisch Railverkeersmanagement op knelpunten 56
Student: M.vanDijk
De oorzaken van de verslechterde doorstroming bij 80 km zones 57
Student: H.J.Harms
Systematische herinrichting van zwarte punten in Vlaanderen 58
Student: M.van‘tHof
Modeling interaction between pedestrians and revolving doors 59
Student: R.Landman
Applied Earth Sciences ThesesResource Engineering 61
The recyclability of ultra light car designs 62
Student:M.Gadziala
Applied Earth Sciences ThesesPetroleum Engineering and Geosciences 63
Using Real Data to test Reservoir Model Updating with the Ensemble Kalman Filter 64
Student: H.J.deBoer
Sediment Mass Balance Study of the late-Holocene Prodelta on the Northern Adriatic Shelf 65
Student: W.Bron
An Integrated Study into the Reservoir Characteristics of Miocene Mangrove Deposits of Mallorca 66
Student: H.Coppes
Enhanced mass transfer of CO2 gas into water by density driven natural convection 67
Student: H.A.Delil
Simultaneous Measurements of Capillary Pressure and Dielectric Constant in Porous Media from 50 Hz to 3 MHz 68
Student: L.M.MorenoTirado
Recovery Enhancement by Injection of Low Quality Steam with Volatile Oil 69
Student: M.N.Guy
Inhoudsopgave �
� 0307
Stress estimation and gas detection from seismic reflection coefficients at a non-welded interface 70
Student:J.vanderNeut
Produced Water Re-Injection 71
Student: C.C.Obeta
Modeling sediment storage in a tidal dominated delta, the Fly River, Papua New Guinea 72
Student: NawienR.Sheombarsing
Applied Earth Sciences ThesesEngineering Geology 73
The investigation on the formulation of a new design code for MV-piles 74
Student: R.L.vanHof
Influence of spatial correlation length on predicted settlements of a road embankment 75
Student: S.Kalamatas
Plaxis Soft Soil Creep: de toepassing van een isotroop kruipmodel op de anisotrope ondergrond 76
Student: R.Servais
Offshore Engineering ThesesConceptual Design of a Tension Leg Platform Optimized for the Heerema Group capabilities 78
Student:H.T.Brinkhuis
Development of the Yoke Quay Mooring Concept (YQM) 79
Student:E.W.Heerema
A Practical Assessment of Lateral Buckling Sensitivity of Subsea Pipelines 80
Student:M.vanHeel
Feasibility study of the use of the Ampelmann in Shell 81
Student:J.M.L.Koch
Fsru processes 82
Student:R.C.J.Lagers
Structural analysis of impact on guides and bumpers 83
Student:P.J.Maas
Basic design of hydrate mining equipment 84
Student;W.J.Overes
The upgrade of “Noble to Van Langeveld” to 1500 m water depth capacity 85
Student:A.Smit
Structural optimization of monopile foundations for offshore windturbines handled by integrated analysis 86
Student:RoelSwinkels
A probabilistic approach to jack-up leg penetration in stratified soils 87
Student:T.vanderWal
Last year’s Theses 89
Research groups and professors within the faculty of Civil Engineering and Geosciences 99
70307
0307�
0307
Preface
Once again a group of students from the Faculty of
Civil Engineering and Applied Earth Sciences has
successfully completed their study; once again the
faculty has every reason to be proud of the high
calibre of its engineers. You will share this opinion
when you read the summaries of the proficiency
tests which our students have passed to acquire the
title of Master of Science (Engineer).
The summaries clearly reflect the extensiveness and
societal relevance of our education programmes.
Civil Engineering with specialisations in, amongst
others, Transport & Planning, Water Management,
Hydraulic Engineering, Building and Structural
Engineering; and Applied Earth Sciences, with
its own specialisations, give our engineers the
knowledge and skills that will enable them to rise
to the challenge posed by the future problems of
society. They will be the people here and abroad
who will ensure that there is clean drinking water,
meet the energy demands, develop new modes of
transport and build with sustainable resources.
The faculty itself will continue to engage in scientific
research on the same societal issues and look for
new ways of solving the problems of the future.
�
Society has nothing to gain if our ideas remain
ensconced within the walls of the university. We can
only contribute substantially when the professionals
take our ideas on board, apply them effectively,
and create safety and sustainability. Our graduates
play a leading role in this process. Their practical
experience and knowledge of the real world will
make them our clients and ambassadors in the
future.
I wish our new Masters of Science an interesting
and challenging future.
L.deQuelerij
Dean
030710
What is the graduation book exactly?
“Master’s Theses February 2007” contains
summaries of the theses produced by various
students who obtained a Master of Science degree
at the Delft University of Technology. The students
in question graduated in “Civil Engineering”,
“Applied Earth Sciences”, “Transport, Infrastructure
and Logistics” or “Offshore Engineering”.
The purpose of this publication is to inform
professionals working in these fields about recent
developments in teaching and research at the
Faculty of Civil Engineering and Geosciences. In
many cases, the subject of the Master’s thesis is
based on a request from professionals working
in the field in question. In other cases, such
individuals will collaborate in the realisation of a
Master’s thesis. Alternatively, the thesis may be part
of a wider research project within the department
itself. The primary goal of the Master’s thesis is
to round-off a student’s course of study at the
TU, and to enable them to graduate as a Master
of Science. As the regulations stand, this requires
an investment of 22 to 26 weeks of study. The
summary of every completed thesis is published in
“Master’s Theses February 2007”, whether they are
merely average or truly outstanding.
The book’s layout
The summaries of the various theses are published
per Master’s programme and specialisation:
• The Civil Engineering Master’s programme has five
specialisations:
• Structural Engineering
• Building Engineering
• Hydraulic and Geo Engineering
• Water Management
• Transport & Planning
The Applied Earth Sciences Master’s programme has
three specialisations:
• Resource Engineering
• Petroleum Engineering and Geosciences
• Engineering Geology
The Offshore Engineering Master’s programme
The Transport, Infrastructure and Logistics Master’s
programme
All of the summaries have a similar layout. Call the
department in question if you require further details
about a specific thesis (the phone number is given
at the end of each summary).
The section containing the new summaries is
followed by a comprehensive list of those produced
last year. The layout of these summaries reflects
that of the previous publications.
A Master’s programme spans several different
departments, each of which corresponds to a
specialisation within the programme in question.
At the end of this book is a comprehensive list of
specialisations, which includes the names of their
respective professors.
The aim of the book
The main purpose of publishing these Master’s
theses is to ensure that the outside world is better
informed about the research that is carried out at
the Faculty of Civil Engineering and Geosciences.
It is also hoped that this book will enhance
communication with professionals working in this
field, and help them to become better informed
about the capacities of current graduates.
0307
Further details
Contact the department in question if you require
further details about one or more of the published
summaries (the phone number is given at the end
of each summary). A small charge is sometimes
levied to cover the costs of printing and posting
a thesis. It is not always possible for us to send
complete theses. If you so wish, you can also make
an appointment to view a particular thesis.
Department of Education & Student Affairs
015-27 85444 / 81765
Department of Marketing & Communication
015-27 87685 / 84694
Further information:
Delft University of Technology
Faculty of CEG, Department of Communications
PO Box 5048
2600 GA Delft
The Netherlands
11
030712
0307 1�
Structural Engineering
Civil Engineering Theses
Structural Engineering1� 0307
Many foundations in the Netherlands, mainly those
in coastal areas, are on piles. These piles are
often over 15 m long at distances of 1 to 4 m. If
possible, these piles are driven into the soil at the
positions of walls and columns of a building. The
presence of piles of a previous building may restrict
the positions of new piles to be designed freely.
Removing the old piles is not a solution because
this leaves holes in deep clay layers through which
saline groundwater may penetrate into the upper
soil. Moreover, the old piles cannot be reused
because their quality cannot be guaranteed. As a
consequence, pile caps often have to cover piles
that are positioned in an irregular pattern.
The objective of this graduation project was to
develop a design model for calculating the pile
loading and reinforcement stresses for pile caps
on irregularly positioned foundation piles. This
model has been based on the strut-and-tie method,
however, the ties have been replaced by another
model consisting of stringer elements and shear
panel elements (see the figure above). This model
predicts vertical pile reactions, reinforcement
stresses and shear stresses in concrete. For
practical application, it has been implemented in
a computer program called Pile Cap Applet (PCA),
which can be found at: http://www.mechanics.citg.
tudelft.nl/pca. This applet was designed to be user-
friendly, to require only a moderate amount of data
and to execute fast.
PCA has been validated in two ways. Firstly, it
has been shown that the design model meets all
equilibrium requirements. This has been tested for
two pile caps. Both cases revealed that the design
model complies with horizontal and vertical force
equilibrium and moment equilibrium. From the
theory of plasticity it then follows that this model
gives a safe approximation of the ultimate load.
Secondly, the ultimate load predicted by PCA has
been compared to the ultimate load predicted by a
non-linear finite element analysis. This comparison
yielded several interesting conclusions whereof the
most important ones are included in this summary.
The ultimate load predicted by PCA is very
conservative. Clearly, the real structure can carry
the load in more ways than an equilibrium system
(PCA) assumes. Furthermore, for the considered
pile cap the design model predicted another failure
mechanism than the finite element analysis. PCA
predicted that the considered pile cap ‘collapsed’
because of reaching the yield strength in one of
the reinforcing bars. In the finite element analysis,
the pile cap collapsed because of a shear failure.
This failure mechanism cannot be predicted by
PCA. For the considered pile cap the vertical pile
reactions predicted by PCA are approximately equal
to those predicted by the non-linear finite element
analysis. However, the reinforcement stresses
at serviceability load according to PCA are much
higher than those determined by the finite element
analysis. This implies that the stresses calculated by
PCA are not useful for checking the maximum crack
width.
But the most important conclusion is that a rational
and safe design model has been developed and
implemented for pile caps on irregularly positioned
foundation piles.
Structural design of reinforced concrete pile capsThe strut-and-tie method extended with the stringer-panel method
Student: A.V. van de Graaf
Committee: Prof.dr.ir. J.G. Rots, Dr.ir. P.C.J. Hoogenboom, Ir. W.J.M. Peperkamp,
Ir. J.W. Welleman, Ir. L.J.M. Houben
For more information about this thesis project, please contact the department, tel (+31)15-2784578
Structural Engineering 1�0307
Uit de bouwpraktijk van geboorde tunnels in slappe
grond is gebleken dat een vaste verhouding tussen
de tunnels diameter en vereiste liningdikte (wand-
dikte) bestaat. De dikte is hierdoor gelijk aan 1/20-
ste deel van de diameter. Bij zeer grote diameters
worden de tunnelsegmenten zodoende zeer zwaar.
Dit levert problemen op in de logistiek (het produc-
tieproces, vervoer naar de bouwplaats en de plaat-
sing van segmenten in de tunnel), die de totale
kosten sterk opdrijven.
De wens blijft echter bestaan om boortunnels met
zeer grote diameters te maken. Hierdoor zal het
mogelijk worden ook snelwegen, zoals de toekom-
stige snelweg A13/16 in het noorden van Rotterdam,
in zo’n type tunnel aan te leggen. In deze studie is
onderzocht of de nieuwe staalvezel versterkte beton-
soorten, zeer hogesterkte beton C100/115 en ultra
hogesterkte beton C180/210, kunnen bijdragen aan
een reductie van de liningdikte voor boortunnels met
een zeer grote diameter.
Verschillende mechanismen kunnen bij een boortun-
nel tot schade en daardoor mogelijk tot bezwijken,
leiden. In deze studie zijn voor een mogelijke boor-
tunnel voor de snelweg A13/16, met een binnendi-
ameter van 14,9 m, de volgende vier mechanismen
uitvoerig onderzocht:
1. Algemene ringwerking van de tunnel ingebed in
grond (gebruiksfase)
2. Ringwerking na injectie van grout rond de tunnel
(bouwfase)
3. Introductie van vijzelkrachten vanuit de tunnel-
boormachine in de segmenten (bouwfase)
4. Torsie in de tunnelsegmenten door vervormingen
ten gevolge van de groutinjectie, ook bekend als
het trompeteffect (bouwfase)
De genoemde mechanismen resulteerden elk in een
grenswaarde aan de vereiste liningdikte. Het bleek
dat de gebruiksfase nooit maatgevend wordt. De
sterkte-eisen door de ringwerking bij de groutin-
jectie en de introductie van vijzelkrachten dicteren
de vereiste liningdikte. Deze zorgen ook voor de
liningdikte uit de standaard vuistregel van 1/20 D
voor conventioneel beton. De bouwfase mag in het
ontwerp van een boortunnel daarom nooit buiten
beschouwing worden gelaten.
Zeer grote liningdikten zijn vereist om scheurvorming
door torsie in het trompeteffect te voorkomen. Deze
dikten liggen voor conventioneel beton boven de
standaarddikte van 1/20 D. Hierdoor zijn scheuren
tijdens de bouw te verwachten, wat in de praktijk ook
inderdaad is waargenomen.
Door toevoeging van conventionele wapening aan
een tunnellining van ultra hoge sterkte beton is
het mogelijk gebleken zeer dunne liningdikten toe
te passen. Het benodigde wapeningspercentage is
sterk afhankelijk van de diepteligging van de tunnel.
Hierdoor kan de liningdikte worden gereduceerd tot
slechts 260 mm (1/58 D). Voor een vermindering van
de maatgevendheid van de groutinjectie kan een
tijdelijke massa (bijvoorbeeld met zand) in de tunnel
worden aangebracht. Eventueel kan deze massa na
de bouwfase probleemloos worden verwijderd. Door
zulke tijdelijke maatregelen tijdens de bouwfase
kunnen zelfs liningdikten onder de 1/60 D worden
gerealiseerd, of kan een lager wapeningspercentage
worden toegepast.
Geboorde tunnels in ultra hoge sterkte betonReductie van de tunnels liningdikte
Student: T.W. Groeneweg
Committee: prof.dr.ir. J.C. Walraven, dr.ir. C.B.M. Blom (Ingenieursbureau GW Rotterdam),
dr.ir.drs. C.R. Braam, dr.ir. O.M. Heeres (Ingenieursbureau GW Rotterdam/TU Delft) en
ir. L.J.M. Houben
For more information about this project, please contact the department, tel (+31)15-2784578
Structural Engineering1� 0307
The use of high strength steel has increased in the
last few years. Although the prices of steel increase
with increasing yield strength, the use of high
strength steel may give economical gains in terms of
less material use or new applications.
The field of application of these design rules
however is limited to the conventional mild steel
grades.
This is an obstacle for the application of high
strength steel in civil engineering applications.
Connections can be the weakest link in civil
constructions, so it is desirable to design the
connection and its components as reliable as
possible.
The main goal is to determine whether the design
rules for calculating the load-carrying capacity of
both double shear timber joints (EC 5) and the steel
pin connections (EC 3) can also be used when high
strength steel dowels and/or plates are used as part
of the joints.
Steel dowels and pins have been used with
strengths of up to 1200 N/mm2.
Steel members were fabricated from steel with
yield strength of up to 600 N/mm2, whereas for the
timber joints high density hardwood (1100 kg/m3)
Azobé was used.
From the test results can be concluded that in case
of the Azobé specimens the design rules are very
conservative (38% higher test results) and in the
case of the softwood specimens (Spruce) the design
rules predicted the test results accurate enough.
For the load-distribution model for the steel pin
connections it can be concluded that this model
describes the real load-distribution in the pin
connection accurate enough.
Application of high strength steel in Steel pin connections and Double shear timber joints
Student: R.D. Hieralal
Committee: Prof.ir. F.S.K. Bijlaard, Dr.ir. J-W.G. van de Kuilen, Ir. P.A. de Vries,
Dr.ir. P.C.J. Hoogenboom, Ing. P. Zanen (Groot Lemmer BV), Ir. L.J.M. Houben
For more information about this thesis project, please contact the department, tel (+31)15-2784578
Structural Engineering 170307
De drijvende funderingEen stabiele basis voor waterwonen in de 21ste eeuw
De commissie waterbeheer 21ste eeuw stelt
dat het voor een duurzaam waterbeleid nodig is
om meer ruimte voor water te reserveren. Deze
ruimteclaim kan in de toekomst niet zondermeer
worden ingevuld zonder dat ruimtelijke problemen
ontstaan. Een van de oplossingen hiervoor is het
meervoudig gebruiken van de ruimte. Drijvend
bouwen is hierbinnen een van de manieren om
invulling te geven aan meervoudig ruimtegebruik
waarbij wonen, werken en waterbergen met elkaar
gecombineerd worden. In dit afstudeerproject
is voor deze manier van bouwen een breed
toepasbare, modulaire, drijvende fundering
ontworpen.
Voordat begonnen is met het daadwerkelijk
ontwerpen zijn enkele belangrijke mechanische
aspecten beschouwd. Een parameterstudie naar
de stabiliteit van drijflichamen, met een drielaagse
opbouw en met gangbare waarden voor de positie
van het zwaartepunt, wijst uit dat bij een breedte
tot circa 6 meter het zwaartepunt de bepalende
factor wat betreft de stabiliteit is. Bij een breedte
vanaf circa 9 meter heeft de positie van het
zwaartepunt nog nauwelijks invloed op de stabiliteit.
Daarnaast is het belangrijk dat opslingering ten
gevolge van excitatie in de eigenfrequenties van
het drijflichaam voorkomen wordt. Het blijkt bij
een drijflichaam met een geheel waterdoorsnijdend
oppervlak en variabele afmetingen niet goed
mogelijk om eigenfrequenties in het gebied van
de golffrequenties te voorkomen. Dit gegeven en
de onderkenning dat dynamische aspecten, in het
rustige water waar de drijvende fundering voor
ontworpen wordt, van ondergeschikt belang zijn
heeft geleid tot de beslissing dat geen rekening
wordt gehouden met dynamische aspecten. Indien
nodig kan om de drijvende wijk een drijvende
golfbreker worden geplaatst.
Het ontwerpproces, waarbij verschillende
varianten zijn opgesteld die vervolgens op basis
van een multi-criteria analyse met elkaar zijn
vergeleken, heeft geleid tot een drijflichaam van
EPS en hoogwaardig beton (HPC). Het modulaire
basiselement is, met afmetingen van 3 bij 12 meter,
vergunningsvrij te transporteren over de weg. Een
basiselement wordt gevormd door HPC tussen
tegen elkaar geplaatste malgevormde EPS-blokken
te storten. Vezels in het HPC maken conventionele
wapening overbodig. De basiselementen kunnen
worden voorzien van een dek uitgevoerd als
cassettevloer. De basiselementen worden onderling
gekoppeld door voorspanning.
Met behulp van een niet lineair eindige-
elementenprogramma is het ontwerp
verder uitgewerkt: de constructievevorm is
geoptimaliseerd, het HPC-gedrag is gemodelleerd
en de constructie is voor een specifieke situatie
gedimensioneerd.
Uit het afstudeeronderzoek kan geconcludeerd
worden dat de combinatie van EPS met HPC een
lichte en sterke drijvende constructie oplevert en
dat op eenvoudige wijze met weinig arbeid complexe
constructies gerealiseerd kunnen worden.
Student: M. Kuijper
Committee: Prof.dr.ir. J.C. Walraven, ir. J.A. den Uijl, ir. D. Tirimanna, ir. T. Rijcken
For more information about this thesis project, please contact the department, tel (+31)15-2784578
Structural Engineering1� 0307
Externally bonded carbon fibre reinforced polymersDebonding caused at shear cracks
Recent developments in ecological engineering have
put an emphasis on re-using structures. A relative
new technique is the use of Carbon Fibre Reinforced
Polymers (CFRP). With this technique FRP laminates
(strips or plates) are attached to the structure,
which strengthen the structure in flexure.
Current design recommendations generally
set acceptable levels of safety. The design
recommendations take in to account the loss
of composite action, only differ in the way they
categorise different failure mechanisms.
A mechanism of failure causes that the ultimate
strength of full composite action will not be reached,
because debonding occurs. Of great importance
was found the way the bond between concrete and
adhesive was modelled. Several relations have been
introduced to describe the bond-slip in this layer.
Three shear-models have been tested, brittle, plastic
and an energy-fracture based model.
The discrete shear crack opens
The moment the discrete crack opens a compressive
stress occurs to the left and a tensile stress at
the right side. This is caused by a small vertical
displacement. By adding additional loading, both
stresses increase, but horizontal tensile stresses
cause compression in the perpendicular direction.
Close to the discrete shear crack the compression
reduces the tensile stresses in the layer (closes the
gap) and prevents debonding.
Debonding initiation
Once the shear stress has reached its maximum, the
compressive stresses do not increase anymore, and
the interface layer to the right of the shear crack
is loaded in tension (the vertical displacements
still increase). The moment that this normal stress
reaches the maximum tensile strength of concrete,
the layer fails. This is the start of the debonding.
The strip still hasn’t failed, but a small part of the
strip has lost its connection to the concrete beam.
This small part extends in the next phase, resulting
in complete loss of composite action.
It is concluded that this model gives insight in the
behaviour of the interface layer surrounding the
shear cracks in concrete. Still research is needed to
come to a formula with which the failure load can be
predicted.
Student: R.H.Ringers
Committee: Prof.dr.ir. J.C. Walraven, ir. A. de Boer (RWS), Dr. G.N. Wells, ir. W.J.M. Peperkamp,
ir. E. Klamer (TU/e), ir. L.J.M. Houben
For more information about this thesis project, please contact the department, tel (+31)15-2784578
Structural Engineering 1�0307
Vloeistofreservoirs: Maximale afmetingen ten aanzien van vloeistofdichtheid
Bij het gebruik van gewapende of voorgespannen
vloeistofreservoirs kunnen problemen op het gebied
van vloeistofdichtheid ontstaan. Deze problemen
ontstaan met name door verhinderde opgelegde
vervormingen als gevolg van de temperatuur,
maar ook door krimp. Hierbij treedt scheurvorming
op wanneer er sprake is van een daling van de
gemiddelde temperatuur ten opzichte van de
referentietemperatuur. Er wordt gekeken naar
cilindrische en rechthoekige vloeistofreservoirs.
Om te bepalen of een vloeistofreservoir
daadwerkelijk vloeistofdicht zal zijn, is het
onderzoek op de hieronder beschreven wijze
opgezet. Ten eerste is geprobeerd om de
krachten als gevolg van de vloeistofbelasting op
een analytische wijze te berekenen. Dit is bij de
cilindrische reservoirs gedaan met behulp van
differentiaalvergelijkingen. Bij de rechthoekige
reservoirs is dit geprobeerd met behulp van het
boek “Plates and Shells” van Timoshenko. Dit werd
echter te complex en er is uiteindelijk voor gekozen
om deze reservoirs in een rekenprogramma uit te
rekenen. Voor de berekening van de spanningen
ten gevolge van de verhinderde opgelegde
vervormingen is van dezelfde rekenmethoden
uitgegaan. Hiervoor zijn bij de cilindrische reservoirs
aparte differentiaalvergelijkingen opgesteld voor de
verandering van de gemiddelde temperatuur en de
krimp. Voor de rechthoekige reservoirs worden de
krachten als gevolg van de verhinderde opgelegde
vervormingen weer met het eerder gebruikte
rekenprogramma berekend. Vervolgens wordt voor
de verticale scheurvorming het scheurenpatroon
bepaald aan de hand van een normaalkracht-
vervorming diagram. Voor de horizontale scheur-
vorming zal het scheurenpatroon bepaald worden
met behulp van een moment-kromming diagram. Nu
kan de optredende scheurwijdte berekend worden.
Deze dient bij doorgaande scheuren getoetst
te worden aan de hand van het criterium van
Lohmeijer. Wanneer er sprake is van buigscheuren
dient de drukzone minimaal 50 mm hoog te zijn.
Hierbij is enigszins rekening gehouden met de
invloed van de vloer op de scheurvorming in de
onderzijde van de wand. Maar naar de werkelijke
invloed dient nog extra onderzoek gedaan te
worden.
Uit het onderzoek blijkt dat de verhinderde
opgelegde vervormingen grote invloed hebben op
de vloeistofdichtheid van de reservoirs. Er zullen
echter alleen problemen optreden wanneer de wand
afkoelt ten opzichte van de referentietemperatuur.
Hierbij moet er gekeken worden naar het verschil
in afkoeling tussen de wand en de vloer. Er zullen
problemen optreden wanneer het verschil in
afkoeling tussen de vloer en de wand groter is
dan -7,5 0C. Door de opgelegde vervormingen
zullen er verticale doorgaande scheuren ontstaan
en zal er getoetst moeten worden aan de hand
van het criterium van Lohmeijer. De resultaten
van het onderzoek geven aan dat wanneer er
doorgaande scheurvorming optreedt als gevolg van
verhinderde opgelegde vervormingen reservoirs veel
kleiner uitgevoerd kunnen worden, dan wanneer
er geen scheurvorming optreedt als gevolg van
de verhinderde vervormingen. Met behulp van
voorspanning kunnen ook weer hogere reservoirs
gerealiseerd worden.
Student: L. Stapper
Committee: Prof.dr.ir. J.C. Walraven, Dr.ir. C. van der Veen, Dr.ir. P.C.J. Hoogenboom
For more information about this thesis project, please contact the department, tel (+31)15-2784578
Hydraulic & Geotechnical EngineeringBuilding Engineering20 030720 0307
Hydraulic & Geotechnical EngineeringBuilding Engineering 210307 210307
Building Engineering
Civil Engineering Theses
Hydraulic & Geotechnical EngineeringBuilding Engineering22 030722 0307
Een Living Bridge voor AmsterdamOntwerpstudie naar een vaste oeververbinding over het IJ
Amsterdam probeert al jaren om zowel Noord als
de oevers van het IJ te betrekken bij het stadsle-
ven, maar Noord wordt pas echt een onderdeel van
de stad wanneer er een visuele verbinding wordt
gemaakt. Om mensen uit het centrum naar de andere
kant van het Centraal Station te krijgen, moet er
een reden zijn om over te steken. Wanneer dit extra
programma op de brug wordt geplaatst, wordt de
brug een living bridge. Het ontwerp van deze living
bridge was het hoofddoel van dit afstudeerproject.
In het technische vooronderzoek is de nadruk gelegd
op de scheepvaart. Het vervoer van gevaarlijke
stoffen over het IJ zal moeten worden gereguleerd
om voldoende veiligheid te garanderen op de living
bridge. De scheepvaart wordt daarvoor gescheiden
in verschillende vaargeulen. Het vervoer van gas
wordt beperkt tot de nacht, brandbare vloeistoffen
kunnen ook overdag vervoerd blijven worden. Om de
living bridge te beschermen tegen aanvaringen is een
systeem ontwikkeld van geleidewerken, dat schepen
veilig langs de brug geleidt.
In de ontwerpstudie is toegewerkt naar een master-
plan. De living bridge bestaat hierbij uit een hoofd-
verkeersader, met daaraan toegevoegd extra func-
ties. De oversteek wordt opgedeeld in vier sprongen
tussen bebouwde eilanden. De brug wordt bij de
centrale oversteek uitgevoerd als hefbrug. De hefto-
rens vervullen daarbij niet alleen een constructieve
functie, maar behuizen ook de extra functies van
de living bridge. Ook in geheven stand is de brug
toegankelijk.
De eilanden bestaan uit een kade, een onderbouw
tot aan het brugdekniveau en een bovenbouw. De
gevels van de bovenbouw worden beschermd door
een systeem van louvres, die dichtklappen bij brand.
Door het funderen op een steigerconstructie wordt
de uitvoering vereenvoudigd, en worden grote
zakkingen voorkomen.
Dit afstudeerproject laat zien dat er harde randvoor-
waarden gelden ten aanzien van de scheepvaart en
de veiligheid. Maar ook met deze randvoorwaarden
is een brug over het IJ wel degelijk mogelijk. De
living bridge als geheel, met de bruggen, eilanden en
torens is een interessante en waardevolle toevoeging
aan de stad Amsterdam.
Student: L. Dietz
Committee: Prof. ir. L.A.G. Wagemans, Prof. dipl-ing. J.N.J.A. Vamberský, Prof. ir. A.P.J.M. Verheijen
(Faculteit Bouwkunde, afdeling Bouwtechnologie)
For more information you can contact the section Structural and Building Engineering, tel. 015-2783990
Hydraulic & Geotechnical EngineeringBuilding Engineering 2�0307 2�0307
Waarde van het ontwerp in relatie tot de waarde van het proces
Een studie naar de verbeterpunten in het ontwerp-
proces van technisch complexe projecten in de
Utiliteitsbouw voor een betere afstemming tussen
vraag en aanbod, uitgevoerd bij Royal Haskoning.
Achtergrond
Het ontwerpproces speelt een belangrijke rol in
de totstandkoming van gebouwen. Gedurende het
ontwerpproces worden belangrijke keuzes gemaakt
ten aanzien van de uiteindelijke waarde en de
uiteindelijke kosten van het gebouw. De waarde
refereert hier aan de mate waarin het ontwerp van
het gebouw ‘het aanbod’ voldoet aan de behoeften
van opdrachtgever en eindgebruiker ‘de vraag’. Een
succesvol ontwerpproces is een proces dat leidt tot
een ontwerp, dat voldoet aan deze behoeften, op het
juiste moment gereed is en waarvan de onnodige
kosten tot een minimum beperkt zijn. Echter, in de
praktijk blijkt niet altijd sprake te zijn van een dusda-
nige effectiviteit en efficiency van het ontwerppro-
ces, aangeduid als ‘waarde’ van het ontwerpproces,
dat dit leidt tot de genoemde resultaten. Dit speelt
binnen de Utiliteitsbouw bij technisch complexe
projecten in het bijzonder een rol. De adviesgroep
project Management van Royal Haskoning wil inzicht
krijgen in de invloedsfactoren c.q. knelpunten in het
ontwerpproces van technisch complexe projecten in
de Utiliteitsbouw én in de bijbehorende sturingsmo-
gelijkheden vóór de projectmanager.
Onderzoeksopzet
Om inzicht te verkrijgen in de knelpunten is gebruik
gemaakt van een literatuurstudie en van het houden
van interviews. Voor de praktijkstudie is een bouw-
project als case genomen en is gesproken met alle bij
het ontwerpproces betrokken partijen. Deze inzichten
hebben geleid tot de keuze van een primair knelpunt.
Hiervoor is intern bij Royal Haskoning in samenwer-
king met een multidisciplinaire vertegenwoordiging,
door het houden van oplossingsgerichte interviews
een oplossingrichting ontwikkeld.
Resultaten
De onvoldoende kwaliteit van het PVE is door de
participanten gewaardeerd als een primair knelpunt.
Een oplossingsrichting is ontwikkeld met betrekking
tot het PVE tezamen met de inrichting van het vroege
ontwerpproces, omdat daar de beïnvloeding op de
waarde en kosten het grootst is.
De belangrijkste aanpassingen in de voorgestelde
oplossingsrichting inzake het PVE en de inrichting van
het vroege ontwerpproces zijn:
- Van aftrap met architect naar aftrap met ontwerp-
team
- Van samen ontwerpen naar gezamenlijk ontwer-
pen én programmeren
- Van Programma van Eisen & Wensen naar
Programma van Eisen & Programma van Wensen
Student: T.J. Duvivier
Committee: Prof. Dr. Ir. H.A.J. de Ridder, Dr. Ir. G.A. van Nederveen, Ir. F.A.M. Soons,
Ir. K. Th. Veenvliet (UTwente), Ir. P.C.M. Zwinkels (Royal Haskoning)
For more information you can contact the section Building Engineering, tel. 015-2786636
Hydraulic & Geotechnical EngineeringBuilding Engineering2� 03072� 0307
Ondergrondse kleine infrastructuurNut en noodzaak van ordening
In stedelijke gebieden doen zich steeds vaker compli-
caties voor in samenhang met ondergrondse kleine
infrastructuur (netwerken voor het transport en de
distributie van signalen, elektriciteit, vloeistoffen of
gassen). Deze complicaties lijken voort te komen
uit de explosieve toename van het aantal verschil-
lende netwerken en de trend tot het verdichten van
steden enerzijds en de traditionele wijze waarop
deze netwerken in de ondergrond zijn aangebracht
anderzijds. Het onderzoek geeft ter onderbouwing
hiervan een aantal trends aan en geeft de achter-
grondinformatie bij de verschillende netwerken. Het
onderzoek richt zich op de vraag waarom er bij het
(her)ontwikkelen van gebieden ondanks de ervaring
met het optreden van dergelijke complicaties zelden
wordt gekeken naar de mogelijkheid om de onder-
grondse kleine infrastructuur op een andere manier
aan te brengen.
Hiervoor is IJburg 1e fase als casus uitgewerkt.
Hieruit kwamen twee knelpunten naar voren, name-
lijk: de manier waarop ondergrondse kleine infra-
structuur in het ontwerp- en besluitvormingsproces
van IJburg 1e fase meegenomen is (knelpunt 1) en
de manier waarop de kosten die voortkomen uit de
verschillende manieren van aanbrengen van kleine
infrastructuur gekwantificeerd kunnen worden (knel-
punt 2).
Bij uitwerking van knelpunt 1 blijkt dat ondergrondse
kleine infrastructuur op dit moment erg laat in het
ontwerp- en besluitvormingsproces van te ontwik-
kelen gebieden betrokken wordt. Hierdoor komen
conflicterende situaties of belangen (ook tussen
boven- en ondergrond) pas tijdens de uitvoeringsfase
naar voren. Ook ontbreekt een regievoerder die de
verschillende belangen onderling kan afwegen en
sturing geeft.
Uit het onderzoek komt naar voren dat de boven-
en ondergrond op elkaar dienen te worden afge-
stemd voordat de bovengrondse inrichting in een
Stedenbouwkundig Plan wordt vastgelegd. Op dat
moment kan bijvoorbeeld in de grondexploitatie-
begroting ook nog budget vrijgemaakt worden om
voor ordening in een ordeningssysteem (integrale
leidingen tunnels (ILT’s), utility ducts, bundeling van
kabel en/of leidingen en kabel- en/of leidinggoten) te
kiezen.
Van de drie te onderscheiden actoren op het gebied
van ondergrondse kleine infrastructuur (gemeente,
kabel- en leidingbeheerders en gebruikers) is de
gemeente de meest aangewezen actor om als regie-
voerder op te treden. De gemeente dient namelijk te
waken over het maatschappelijk belang en beschikt
over voldoende sturingsmogelijkheden om grip op
het proces te kunnen houden.
Bij het bestuderen van knelpunt 2 kwam naar voren
dat de maatschappelijke kosten en baten vaak buiten
beschouwing gelaten worden, wanneer de kosten
behorend bij verschillende manieren van aanbren-
gen (traditioneel of in een ordeningssysteem) van
ondergrondse kleine infrastructuur gekwantificeerd
worden. Hierdoor is het onwaarschijnlijk dat er geko-
zen wordt voor een oplossing waar de samenleving
als geheel het meest baat bij heeft.
Om die reden is er tijdens het onderzoek een
omvangrijk rekenmodel ontwikkeld waarin alle
verschillende (maatschappelijke) kosten aan de hand
van parameters zijn opgenomen. Dit model geeft
daardoor alle factoren weer die het besluit hoe de
ondergrondse kleine infrastructuur het best geordend
kan worden beïnvloeden, zodanig dat de maatschap-
pelijke kosten en baten het positiefst uitvallen. Het
model is daardoor goed geschikt om deze kosten op
een hoger (politiek) abstractieniveau inzichtelijk te
maken.
Student: M.P. Franken
Committee: Prof.dr.ir. H.A.J. de Ridder, Ir. G. Arends, Prof.ir. J.W. Bosch, K.B. Braat, MSc, BSc,
Drs. F.M. Taselaar (Ingenieursbureau Amsterdam)
For more information you can contact the section Building Engineering, tel. 015-2786636
Hydraulic & Geotechnical EngineeringBuilding Engineering 2�0307 2�0307
Research of the functional and technical feasibility of a floating football stadium
Introduction
Caused by the media and new sources of income
increasing demands are made on new stadiums.
They have to be more flexible, tailor-made for one
function and need an increasing capacity. At the
same time for events like Olympic Games or football
Championships the demanded capacity exceeds the
after-event demand for sports venues leading to
misinvestments.
Problem Definition
A moveable floating stadium could be a solution.
Such a stadium could be moved to the location
where temporary a high capacity is needed. In
coastal cities or cities next to navigable rivers a
floating stadium could be moved to very attractive
inner city locations. In the past years a lot of
research on floating structures like houses or even
airports has been done but never the feasibility
of a floating stadium was analysed. The problem
of this report can be defined as follows: There
is not enough information about the design,
the construction and functional and economical
consequences of a floating stadium.
Objective
The goal of this thesis is a research of the
requirements and the technical and functional
major problems of a floating stadium followed by
the implementation of the derived solutions into a
preliminary design.
Research
The main bottle necks for the realisation of a
floating stadium that resulted from an extensive
literature research were analysed and solved in an
iterative way.
Results
The maximum
dimensions for possible
berthing locations
together with the
functional requirements
resulted in a stadium that is split
up into six elements; two playing field elements and
four surrounding grandstand elements. A design tool
was made that linked the structural design with its
hydro-mechanical properties.
In the preliminary design the results of the design
research were implemented into a structural
context. The main structure of the floating stadium
elements were designed and the attention points
regarding the floating character of the stadium like
the construction and the connection of the floating
stadium elements, were highlighted.
Conclusions and recommendations
• A floating stadium that during operation berths
in a port of a river quay is technically and
functionally feasible.
• The capacity of the stadium is limited to a
maximum of 50.000 spectators.
• A stabilizing system is necessary to maintain
a zero degree angle of the stadium during
operation.
• It should be analyzed which standards and
regulations have to be suited for a floating
stadium.
Student: N.T.N. Groenendijk
Committee: Prof. ir. L.A.G. Wagemans, Prof. Dr. Dipl. Ing. J.N.J.A. Vamberský, Ir. H. Mihl, R. Jansma
(Zwarts & Jansma Architecten)
For more information you can contact the section Structural and Building Engineering, tel. 015-2783990
Hydraulic & Geotechnical EngineeringBuilding Engineering2� 03072� 0307
Optimization of Dome Housing in Sri Lanka
The Solid House Foundation aims at contributing
to an enduring development of housing projects
in poor communities. The intention is to enable
local inhabitants to independently prepare and
build successful housing projects. The Solid House
Foundation uses re-usable inflatable hemispherical
formwork to build reinforced concrete dome
dwellings. In this thesis a study is made of possible
optimization of costs, simplicity and durability of this
building concept. Main occasion is the increasing
price of rebar and the bad availability of rebar in
most regions where the SHF is active. As SHF is now
involved in a large housing project in Sri Lanka, a
first focus is on this region.
To have an idea of threads and opportunities in
dome building a literature study was made on
dome shapes in nature, domes in other cultures,
the history of concrete shells built with inflatable
formwork and of domes in general. As a result
several form-related possibilities were identified that
could reduce the tension stress in the shell and thus
the amount of reinforcement needed.
Also, research on alternative materials for dome
building was done. This resulted in several options
of which ferrocement was considered the most
suitable. The latter from both a cost point of view as
from the fact that there is a lot of experience with
this easy applicable material in Asia.
Currently half of the material turns out to be
used for the foundation of the dome. After some
calculations could be concluded that this heavy
foundation is required to anchor the uplifting forces
of the inflatable formwork. Consequently research
has been done on alternative anchorage of the form,
resulting in ideas for formwork that does not need
anchorage at all. The research phase was rounded
off with a study of the climatic circumstances in Sri
Lanka. Matching building responses to the climate
were studied and applied on dome designs.
The conclusions drawn from structural analyses in
the finite element program ANSYS have resulted
in a proposal for alternative material use in
combination with the currently applied formwork.
A design for a ferrocement shell has been made
and an experiment is carried out. This has resulted
in a construction manual for application of the
current inflatable formwork in combination with the
material ferrocement. Costs of raw materials for this
alternative turn out to be considerably lower than
for the reinforced concrete shells that have been
built so far.
However to improve issues such as the heavy
foundation and the dependency on electricity,
a different design of the formwork is required.
Therefore possibilities for an alternative design of
the formwork are studied and evaluated.
Student: C. Hammer
Committee: Prof.ir.L.A.G.Wagemans, Dr.ir.P.C.J.Hoogenboom, Dr.ir.E.Schlangen,
Ing W.J.H.Stroecken (Solid House Foundation)
For more information you can contact the section Structural and Building Engineering, tel. 015-2783990
Hydraulic & Geotechnical EngineeringBuilding Engineering 270307 270307
Design tools for the Virtual Wind TunnelSetting up the geometry for CFD calculations
Momenteel kan de windbelasting op gebouwen op
twee manieren worden bepaald: met behulp van de
norm (NEN 6702, Eurocode) of door middel van wind-
tunnelproeven. De norm is echter alleen bruikbaar
voor eenvoudige vormen; complexe gebouwvormen
vereisen windtunnelonderzoek. Dit onderzoek is
echter erg duur en zeer tijdrovend, waardoor het
nauwelijks gebruikt wordt in het vroege ontwerp-
proces. Toch is het juist deze fase waarin belangrijke
ontwerpbeslissingen worden genomen en meer
inzicht in de effecten als gevolg van wind is dan
ook wenselijk. Numerieke methoden zijn geïntro-
duceerd om de windeffecten te bepalen middels
Computational Fluid Dynamics (CFD).
In recent afstudeeronderzoek aan het Structural
Design Lab is een Virtuele Windtunnel voorgesteld
waarmee constructieve ingenieurs de windbelasting
in een vroeg stadium van het ontwerpproces kunnen
bepalen door gebruik te maken van CFD. Dit onder-
zoek heeft geleid tot een algemene aanpak voor
het uitvoeren van CFD berekeningen en een domein
waarin de berekeningen kunnen worden uitgevoerd.
Het zogenoemde Van Nalta domein geeft veelbe-
lovende resultaten voor eenvoudige vormen, zoals
kubussen en cilinders. De eisen aan de geometrie
voor CFD berekeningen zijn echter zeer hoog en het
genereren van bruikbare modellen van met name
complexe gebouwvormen blijkt zeer lastig.
Tijdens dit afstudeeronderzoek zijn verschillende
ontwerptools ontwikkeld waarmee de geometrie
voor CFD berekeningen kan worden gegenereerd.
Met deze toolbox kan de windbelasting op een
gebouw of constructie worden bepaald en verschil-
lende ontwerpen worden vergeleken in een relatief
korte tijd zonder veel tussenkomst van de gebruiker.
Optimalisatie van vorm en constructie wordt hiermee
mogelijk. Om de windbelasting te bepalen op een
gebouw dat is geplaatst in een bebouwde omge-
ving, is een ontwerptool ontwikkeld waarmee een
3D model van de omgeving kan worden gecreëerd,
gebruik makend van GIS technologie. Een andere tool
is ontwikkeld waarmee het centrale gebouw-model
kan worden vereenvoudigd door het verwijderen
van niet-relevante elementen en kleine details. De
rekentijd van de CFD software kan hiermee aanzien-
lijk worden verkort. Omdat de afmetingen van het
domein waarin de berekeningen worden uitgevoerd
afhangen van de dimensies van het onderzoeksge-
bied, is een laatste tool ontwikkeld waarmee het
domein kan worden gegenereerd, afhankelijk van de
afmetingen van het onderzoeksgebied.
Er is geconcludeerd dat de ontwerptools goed werken
voor CFD toepassingen. In de meeste gevallen
worden veelbelovende resultaten verkregen en de
gegenereerde geometrie blijkt zeer goed bruikbaar
voor CFD simulaties. Voor enkele test cases zijn bere-
keningen uitgevoerd in het Van Nalta domein. Het
blijkt momenteel erg lastig om nauwkeurige resulta-
ten te verkrijgen van de berekeningen, mede door de
geringe capaciteit van de huidige computers. Echter,
rekening houdend met de continue ontwikkeling van
de computer hardware, is het de verwachting dat het
in de nabije toekomst mogelijk zal zijn de windeffec-
ten op complexe gebouwmodellen, die zijn geplaatst
in een bebouwde omgeving, nauwkeurig te voorspel-
len.
Student: R.A.G. Kerklaan
Committee: Prof.dipl.-ing. J.N.J.A. Vamberský, prof.ir. L.A.G. Wagemans, ir. J.L. Coenders,
dr. dipl-ing. S. Zlatanova (OTB onderzoeksinstituut, GIS), dr. ir. L.L.M. Veldhuis (Lucht- en
Ruimtevaarttechniek, Aerodynamica)
For information on the report of the Master’s thesis please contact the Building Engineering section, telephone: 015-2783174
Hydraulic & Geotechnical EngineeringBuilding Engineering2� 03072� 0307
Functioneel Specificeren bij projecten van RijkswaterstaatOntwikkeling van een kader voor evaluatie en advisering
Achtergrond
Rijkswaterstaat is in Nederland verantwoordelijk voor
beheer, onderhoud en aanleg van een groot deel
van de infrastructurele bouwwerken. De aanbeste-
ding van werkzaamheden werd tot voor kort gedaan
door het opstellen van een bestek aan de hand van
een ontwerp. Sinds enkele jaren bestaat de tendens
meer werkzaamheden aan de markt uit te besteden,
bijvoorbeeld door Design & Construct contracten.
Het gebruiken van de kennis van de markt, bijvoor-
beeld op het gebied van uitvoering van projecten of
van een specifiek product, door het uitbesteden van
(delen van) het ontwerpproces kan leiden tot betere
en/of goedkopere oplossingen.
Het gebruik van geïntegreerde contractvormen
vraagt een andere wijze van het opstellen van de
vraag door de opdrachtgever. Binnen Rijkswaterstaat
is hier de werkwijze “Functioneel Specificeren” voor
ontwikkeld, die steeds vaker wordt toegepast. Hierbij
is Rijkswaterstaat vooral betrokken bij de voorkant
van het ontwerpproces en wordt het verdere verloop
hiervan gemonitord. De specificatie van eisen bestaat
zoveel mogelijk uit functionele eisen en er worden zo
min mogelijk eisen gesteld, zodat een zo groot moge-
lijke oplossingsruimte voor marktpartijen overblijft
om binnen te ontwerpen.
Onderzoeksopzet
Het ontbreekt op dit moment aan inzicht in de
toepassing van de werkwijze in de praktijk. Dit zou
kunnen worden gebruikt om de werkwijze beter te
implementeren. De doelstelling van dit afstudeer-
onderzoek luidt dan ook als volgt: “Het ontwikkelen
van een kader voor het evalueren van en adviseren
over het “Functioneel Specificeren” bij projecten van
Rijkswaterstaat, ten behoeve van het verbeteren van
de toepassing ervan tijdens individuele projecten en
mogelijk de uniforme werkwijze van Rijkswaterstaat.”
Het dient hierbij te gaan om een quick-scan die
toepasbaar is op verschillende soorten projecten en
snel duidelijk kan maken hoe het binnen een project
met het “Functioneel Specificeren” gaat.
Het onderzoek bestaat uit een studie naar theorieën
en achtergronden van de werkwijze “Functioneel
Specificeren”, een korte studie naar evaluatieme-
thoden en een praktijkonderzoek door middel van
interviews en een enquête naar toepassing van de
werkwijze in projecten.
Resultaten
Het onderzoek heeft geleid tot de basis voor een
kader voor evaluatie van de werkwijze “Functioneel
Specificeren”. Bij gebrek aan een duidelijke praktijk-
handleiding is een overzicht gemaakt van de activitei-
ten die bij de werkwijze (kunnen) worden uitgevoerd.
Daarnaast zijn er diverse factoren onderscheiden die
van belang zijn voor het succesvol toepassen van
de werkwijze, resulterend in een check-list en een
aantal Kritieke Succes Factoren. Naast het opstellen
van het kader voor evaluatie in projecten bleek het
goed mogelijk in het onderzoek ook een evaluatie
van toepassing van de werkwijze zelf uit te voeren.
Dit heeft geresulteerd in een duidelijk beeld over
de stand van zaken wat betreft de ontwikkeling van
“Functioneel Specificeren” en adviezen over moge-
lijke verbeteringen.
Student: A.W. Lever
Committee: Prof.dr.ir. H.A.J. de Ridder, Ir. R.M. Bosch (Rijkswaterstaat), Ir. A. van der Kuilen,
Ir. G. Arends
For information on the report of the Master’s thesis please contact the Building Engineering section, telephone: 015-2783174
Hydraulic & Geotechnical EngineeringBuilding Engineering 2�0307 2�0307
Variantenonderzoek Onderbouw Parkhaventoren
Eind 2001 presenteerde een consortium van twee
ontwikkelingsmaatschappijen het “Masterplan
Parkhaven”. Het plan voorziet in de herontwikke-
ling van het Parkhavengebied in Rotterdam door
uitbreiding van het Park, de bouw van kantoren
en woningen en de realisatie van een entertain-
mentcenter. Hoogtepunt vormt de 392 meter
hoge Parkhaventoren; een nieuwe blikvanger voor
Rotterdam met een recordhoogte in Europa.
Het Masterplan Parkhaven werd door de gemeen-
teraad van Rotterdam verworpen en de ontwikke-
ling van de Parkhaventoren werd bij het bouwkun-
dig ontwerp stopgezet. Het verrichte onderzoek
beschrijft het proces van bouwkundig ontwerp naar
voorontwerp en richt zich daarbij op de onderbouw
van de Parkhaventoren.
De onderbouw vormt de ondersteuning voor de
bovenbouw en draagt zorg voor de afdracht van
krachten naar het fundament. In het onderzoek
zijn een drietal vragen gesteld; hoe wordt de
Parkhaventoren gefundeerd, hoe worden de krachten
uit de bovenbouw geïntroduceerd in het fundament
en op welke wijze kan dit gedaan worden opdat de
functie van gebruiksruimtes niet belemmerd wordt?
Alle drie de vragen afzonderlijk kennen een groot
aantal oplossingsrichtingen. Door het vraagstuk inte-
graal te benaderen wordt dat aantal verkleind. Daarin
blijkt vooral de laatste vraag over de functie-uitvoe-
ring van bepaalde ruimtes bepalend te zien. Vanuit
de mogelijke oplossingsrichtingen zijn twee vooront-
werpen voor de onderbouw van de Parkhaventoren
ontwikkeld. De bovenbouw is daarbij geïnventari-
seerd en als een gegeven beschouwd.
Om de voorkeur te geven aan één van de twee
voorontwerpen voor verder uitwerking tot definitief
ontwerp zijn beide beoordeeld. Een beoordeling van
de voorontwerpen op alleen het constructieve vlak is
een te krappe benadering. Wanneer er verschillende
oogpunten ingenomen worden, worden er verschei-
dene belangen zichtbaar die tegenstrijdig met elkaar
kunnen zijn. Door de belangen goed af te wegen
wordt tot een evenwichtige beoordeling gekomen die
de basis vormt voor een keuze voor één van de twee
voorontwerpen.
Student: O. Los
Committee: Prof. dipl.-ing. J.N.J.A. Vamberský, Ing. H.J. Everts, Ir. G. Arends
For information on the report of the Master’s thesis please contact the Building Engineering section,
telephone: 015-2783174
Hydraulic & Geotechnical EngineeringBuilding Engineering�0 0307�0 0307
Progressive Collapse AssessmentNon-linear behaviour of concrete structures in damaged state
Progressive collapse is a collapse where local failure
leads to a disproportionate collapse (Fig. 1). Due
to a focus on ease of erection in the construction
process and more and more optimisation of design
through advanced analysis techniques, buildings
are believed to have become more vulnerable to
progressive collapse over the past decades.
To design a building resistant to progressive collapse
in a cost efficient and aesthetically attractive way,
consideration of non-linear effects is required. The
purpose of this research is to investigate structural
non-linear behaviour of building structures and
develop design rules or strategies to economically
design building structures resistant to progressive
collapse. Focus is on reinforced concrete structures
in static loading conditions.
First the progressive collapse phenomenon itself
was considered. Three design approaches were
distinguished: the event control approach aimed
at improving the level of protection of a building,
the specific local resistance approach aimed at
increasing the hardness of a building and the
alternate load path approach which aims at
improving the robustness of building (Fig. 2). The
latter approach has been elaborated.
Alternate load paths can be developed in roughly
four manners: by arch action, suspension action,
Vierendeel action and catenary action. Ductility of
the structure and its connections is important to
enable these alternate load paths. For arch and
catenary action special detailing of structural ties is
needed, especially catenary action depends highly
on the elongation capacity of these ties.
To assess the influence of non-linear effects,
numerical determination of limit loads upon
column removal through advanced non-linear
EEM calculation was performed for a simple office
building. Three non-linear effects creating an
overcapacity compared to linear assessment were
distinguished in this case study: strain hardening of
the reinforcement steel, moment redistribution and
a load bearing floor slab contribution.
The magnitude of these effects depends on the
actual amount of reinforcement and its lay-out and
the structural geometry. For three investigated
cases of column removal the available non-linear
overcapacity was in the order of magnitude of 1.8.
A linear procedure of notional element removal was
performed for the entire building. Each column was
removed one by one, one at a time and the required
strength was assessed through the calculated
overcapacity-factor.
It was concluded that via this approach the design
of the studied building can be adjusted adequately
and economically to enhance the robustness.
The right detailing is of primary importance in
enhancement of robustness.
Student: M. Smith
Committee: Prof. dipl.-ing. J.N.J.A. Vamberský, ir. J.L. Coenders, ir. A.M. de Roo (Arcadis Bouw &
Vastgoed), prof. ir. A.C.W.M. Vrouwenvelder, ir. J.W. Welleman
For more information about this thesis project please contact the department, tel. (+31) 15-2783174
Hydraulic & Geotechnical EngineeringBuilding Engineering �10307 �10307
Optimisation of structural transfer zones in multi-use buildingsIntroduction
One of the main problems of designing multi-use
buildings is the transfer of loads between the
structural grid systems of the different functions. In
lieu of making compromises in the design of these
systems per function in order to vertically align the
grid lines or grid bands, a structural transfer zone in
an intervening floor can be designed. By designing
an optimal allocation of vertical oriented structural
elements, loads can be transferred between the
different structural grid systems, without adversely
affecting the functionality and usability of the
intervening floor.
Structural design tool
The Master’s thesis ‘Optimisation of structural
transfer zones in multi-use buildings’ deals with the
development of a computational structural design
tool based on the artificial intelligence method
genetic algorithms, that can determine the optimal
solution for the allocation of columns between two
structural grid systems. This tool, implemented
in VBA and using AutoCAD as a visualisation tool,
allows the user to generate and optimise the
configuration of the load bearing elements for an
arbitrary design, with the rules following from the
demands of several aspects of a structural and
functional design.
Features of the design tool
In the AutoCAD environment, the user needs to
give the starting and end point of the structural grid
line graphically in both the bottom and top layer
of the intervening floor to determine the possible
location of the columns. Subsequently, the vertical
point load, the horizontal point loads, and the
moments in the centre of gravity acting on the load
transferring structure need to be given numerically.
Based on the user input, the tool then randomly
generates several solutions in what is called the first
generation. By determining the fitness, or in other
words the overall compliance with the prescribed
desired conditions, the genetic algorithm will use
the best solutions to create a new population. This
process, including several other genetic algorithm
operators, will be repeated until the fittest or best
solution per population remains unaltered during a
number of generations.
Concluding remarks
This Master’s thesis shows the capability of an
artificial based design optimisation tool in a
predefined setting of the allocation problem of
columns in a structural transfer zone. At the same
moment, it is made clear that progress can be made
for the presented design tool and in scripting design
tools for the building practise in general. This also
means that it can be expected that tools similar
to the tool presented in the Master’s thesis will be
used more often in the near future. This, however,
does not mean that the structural engineer will lose
his or her position, as hand calculations and logical
interpretations of the result of the design tools will
always have to be made.
Student: R. van de Straat
Committee: Prof. dipl.-ing. J.N.J.A. Vamberský, Ir. J.W. Welleman, Ir. J.L. Coenders, Ir. S. Boer
(Mecanoo Architecten)
For more information about this thesis project please contact the department, tel. (+31) 15-2783174
generations.jpg ?????
Hydraulic & Geotechnical EngineeringBuilding Engineering�2 0307�2 0307
Parametric Associative Design for Free Form Architecture
Over the last decade, the computer has become a
tool a structural designer cannot do without. For
an efficient structural design processes however,
computational power is not yet being used in the
most efficient manner. Structural engineers still
have difficulties with using available software in an
efficient structural design process. Coenders and
Wagemans [2005] have proposed a new approach
toward use of computers in the structural design
process: the Structural Design Tools approach.
The Structural Design Tools concept doesn’t strive
to be an all-comprising model, but a collection of
simple tools that can be chosen by the designer to
build his design. Instead of using the computer for
engineering purposes, the computer can be used for
design purposes.
An important aspect of the Structural Design Tools
concept is the parametric associative character
of the design tools. Parametric design is used
for the rapid generation of computable design
representations describing design alternatives.
Potential design alternatives are generated and
evaluated in order to obtain insight into the impact
of the structural parameters on the final integral
design. With adding associativity to the structural
design process, design steps are linked and the
possibility of adjusting the parameters in the end
of the design process is reached. With designing
structures for Free Form Architecture, this ability is
very valuable. Since there is little design experience
with these kind of structures, it is hard to predict
what the impact of a design decision on the final
design is. The ability of defining the values of the
structural parameters at the end of the design
process leads to a more efficient structural design
process.
The goal of the graduation project was to research
methods for developing structural design for Free
Form Architecture in a parametric associative
process, whereby elaborating one specific
combination of researched methods into one system
of parametric associative tools. Where a parametric
associative design process differs from a traditional
design process is that with a design process
according to the Structural Design Tools approach,
the quantitative characteristics of the design can
change in the end of the process. The design logic
behind the generation algorithms defines the range
in which the design can be varied in the end of
the generation process. This logic cannot easily be
changed in the end of the process. With setting an
accurate design direction in the beginning of the
process, the freedom of the final design is restricted
soon in the development process. Like a traditional
design process, the discrepancy between having no
design knowledge and having to make governing
design decisions still is present in a parametric
associative design process. With a system of
parametric associative design tools however, the
structural designer is able to generate a range of
possible design representations in a fast way. By
a combination of a qualitative and quantitative
comparison of the generated designs, insight into
the consequences of parameter variation can be
obtained.
In a real life design process, a large benefit
of using parametric associative design tools is
the fact that interaction between architect and
structural engineer is stimulated. A structural
engineer can, without losing a lot of time doing
repetitive calculations, show the architect what
consequences of design choices are. When a
common understanding on all design relations
is reached, the total design team can come to a
well considered, well founded set of values for the
design parameters. Instead of delivering the optimal
design object, a system of parametric associative
design tools offers the possibility for an optimal
design process in which interaction between the
architect and the structural designer is put central.
Student: P. Vermeij
Committee: Prof. dipl-ing. J.N.J.A. Vamberský, Ir. J.L. Coenders, Ir. J.W. Welleman, Ir. M. Veltkamp
(Faculty of Architecture)
For more information you can contact the section Building Engineering, tel. 015-2783174
Hydraulic & Geotechnical Engineering ��0307
Hydraulic & Geo Engineering
Civil Engineering Theses
Hydraulic & Geotechnical Engineering�� 0307
Gabion Stability
In 1932 the Dutch ‘Afsluitdijk’, stretching over
30 kilometres, was completed. This made it
possible to reclaim land in the former ‘Zuiderzee’
by means of constructing the ‘Flevopolder’ and
the ‘Noordoostpolder’. Since then technological
developments have made it possible to build even
larger dams in more difficult circumstances.
One of the countries that is also reclaiming land
by constructing dams and polders is South Korea.
Because of the large mountainous areas and
the growing population in this country, arable
land is becoming rare and land reclamation may
offer a solution. The large tidal differences along
the Korean coast make building these dams a
challenging job.
One of the solutions in South Korea to cope with the
high flow velocities in closure projects is to apply
sack gabions. These are steel nets with rocks inside
them that weigh up to 3 tons. It is not clear how
stable these sack gabions are exactly. The objective
of this report is to make a preliminary study on the
stability of sack gabions.
In 2006, after a 20 year preparation, the
Saemangeum estuary in South Korea was closed
with a dam. During the closure sack gabions were
used in the bed protection, sill construction and
dam heads. In corporation with Delft University of
Technology, Rijkswaterstaat and the Korea Rural
Community & Agriculture Corporation a field trip
to the Saemangeum project was made, in order
to collect useful data on the stability of gabions.
Also the experimental data of RRI (Korean Rural
Research Institute) on model tests on the stability
of gabions was obtained. As an addition to the
data from the Saemangeum project and the model
tests performed by RRI, also model tests in Delft
were done. All this information combined leads to a
stability relation for the applied sack gabions.
Student: R.H.P.A. Beekx
Committee: Prof.drs.ir. J.K. Vrijling, ir. H.J. Verhagen, drs. R. Booij, ir. K. Dorst
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering ��0307
Veldproeven op steenzettingen
Uitvoering en resultatenanalyse van onderzoek
naar de klemming van gazette stenen op dijken
Steenzettingen worden van oudsher gebruikt om het
aangevallen front van dijken te bekleden. De mecha-
nische achtergronden en de materiaaleigenschappen
van deze constructie zijn nog niet volledig beschre-
ven. In dit afstudeeronderzoek is met name de klem-
ming van de stenen door de zwaartekracht in de rich-
ting van het talud onderzocht. Deze inklemming kan
ervoor zorgen dat de losse elementen als een plaat
gaan samenwerken en dus als zodanig beschreven
kunnen worden.
Op drie lokaties in Zeeland zijn veldproeven uitge-
voerd om data te verzamelen over de plaatwerking
van de zettingen. De zettingen waren opgebouwd
met Basalton en Hydroblock zuilen en allemaal onge-
veer 1:3 steil. Er is op verschillende manieren een
belasting loodrecht op de zetting opgelegd (trekproe-
ven). Tegelijkertijd is met verplaatsingssensoren de
responsie van het omliggende veld gemeten. Ook zijn
er schuifproeven uitgevoerd, waarbij een stuk zetting
tegen het talud op werd gedrukt.
De analyse van de gegevens is aan de hand van de
veronderstelde plaatanalogie gedaan. Hiervoor is een
model noodzakelijk dat de elastische responsie van
een homogeen orthotroop materiaal kan beschrijven.
Het plaatgedrag van de zetting vertoont verschillende
eigenschappen in de onderling loodrechte richtingen
(de zwaartekracht werkt maar in één richting).
Met het model en de meetresultaten als input is het
mogelijk de materiaaleigenschappen van de zetting
te berekenen. Deze eigenschappen kunnen in het
vervolg worden gebruikt om het gedrag van de
zetting onder natuurlijke omstandigheden te beschrij-
ven.
De belangrijkste conclusies uit het onderzoek zijn:
1. De zetting reageert altijd als een plaat op de
belasting. Dit geldt voor de trekproeven en bij
loklale verschildrukken bij golfbelasting
2. Alle beproefde stenen zijn visueel geselecteerd als
geklemd en dit bleek bij beproeving in alle geval-
len grote sterkte op te leveren.
3. Er is meestal op twee peilniveau`s gemeten.
Tussen deze niveau`s is geen significant verschil
in sterkte of stijfheid gemeten en berekend. Er is
een reductie van de sterkte nabij de teen vastge-
steld.
4. De geometrie van de stenen heeft geen invloed op
de vorm van het verplaatsingsgebied.
5. Een slecht ingewassen zetting scoort lager op
verschillende sterkte criteria.
6. Indien wordt voldaan aan een aantal criteria levert
dit onderzoek een belangrijke onderbouwing voor
het rekenen op enige klemming bij toetsing en
ontwerp.
Student: J.A.H. Blom
Committee: Prof.ir.drs. J.K. Vrijling, ir. DJ Peters, ir. H.J. Verhagen, ir. J.A. den Uijl, ir. R. ’t Hart (DWW,
RWS), ir. A.J.E.J. van Casteren (BAS bv)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering�� 0307
“Sandwich wall as the quay wall for the future”
In this report an attempt is made to develop a
new design method for quay walls. Previous quay
walls designs are being analysed and an attempt is
made to find relations between external conditions
and design parameter of the structure. When such
relations exist they can be used as design graphs.
The new design method will be called reference
based design. In this thesis this new method has
been applied to block walls and to sheet pile walls.
The discovered relations can be used to make an
estimate of the material quantities in a very short
time.
The block wall designs have been examined for the
following relations:
• Retaining height vs. number of blocks in a cross
section;
• Retaining height vs. concrete volume per meter
wall;
• Dimensions of the separate blocks vs. elevation of
the blocks;
The sheet pile wall designs have been investigated
for the following relations.
• Retaining height vs. embedded length;
• Retaining height vs. steel volume per meter wall;
The second part of this thesis focuses on the
development of a new type of quay wall, which
will be designed for the expected future situation.
In the last couple of decades ship sizes have been
increasing and the loads on quay walls have also
become larger. These changes have an effect on
the quay walls at which these ships can be moored.
When these two trends continue container ships
will have to become very large and very strong in
the future. A new quay wall concept may be more
economical in case of this extreme situation. Several
new types of
quay walls have been considered of which a
sandwich quay wall is the most promising.
The sandwich wall consists of two rows of steel
piles and a jet grout mass between these two pile
rows. The steel piles are equipped with steel rings
to be able to transfer a certain shear force from the
piles into the grout. These steel rings facilitate a
shear connection, which causes the wall to behave
as a composite structure. This composite action
has a favourable effect on both the strength and
the stiffness of the wall. On top of the sandwich
wall a relieving floor structure will be constructed;
this is very common for large wall structures. An
impression of the sandwich quay wall can be seen in
the figure below.
The designed configuration of the sandwich wall has
been compared to a reference design to investigate
the economic potential of the sandwich wall. A combi
wall has been selected for the reference design,
as this type of quay wall is generally the cheapest
solution for wall structures in sandy soil with a large
retaining height. The combi wall is designed for equal
load conditions.
The costs of both the combi wall and the sandwich
wall have been estimated. Although the sandwich
wall requires a much smaller amount of steel than
the combi wall the sandwich wall proves to be more
expensive. The largest contribution in the costs of the
sandwich wall results from the welding of the steel
rings around the piles. It may be possible that in the
future the sandwich wall becomes more attractive. As
the amount of steel in the sandwich wall is relatively
small an increase in the price of steel makes the
sandwich wall economically more attractive.
Student: P. Bonte
Committee: Prof. drs. ir. J.K. Vrijling, ir. W.F. Molenaar, ir. W.J.M. Peperkamp, ir. L.A.M. Groenewegen
(Delta Marine consultants)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering �70307
“Dynamic behaviour of jetty structures under seismic conditions“
Jetty structures are relatively long structures.
Codes applied to seismic engineering, e.g. eurocode
8, do not make a differentiation to relatively
long structures. So, what is the effect of uneven
excitation on relatively long structures? Is there an
effect at all? Do the structural stresses increase/
decrease?
The earthquake load, according to the eurocode
8, is modelled by a modal analysis spectrum.
Consequently, this modal response spectrum is
applied on a modal analysis. The only information
a modal response spectrum contains, is the
information about the maximum response of a
single degree of freedom model during a design
earthquake event. The modal response spectrum
does not contain information about the time delay in
excitation. Therefore it is not possible to implement
the effect of uneven excitation when applying the
modal analysis.
This research investigates the effect of uneven
excitation on a jetty structure by the time history
method. A model has been set up according the
Euler- Bernoulli beam model. The calculation is done
for the Alkion earthquake for variable angles of
incidence. For particular angles of incidence does
the maximum bending moment peak. The cause
of this response amplification is discovered in the
transfer functions.
Time delay in excitation turns out to be important
for the occurring maximum forces/ bending
moments. Building codes should contain this
information.
Studente: H. de Brabander
Committee: Prof. Drs. Ir. J.K. Vrijling, Dr. Sc. A. Metrikine, Ir. W.F. Molenaar, Ir. L.A.M. Groenewegen
(Delta Marine Consultants B.V.)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering�� 0307
Effects of softwood vegetation within groyne fields
Softwood vegetation can be found within a
significant number of groyne fields along the River
Waal. Vegetation is commonly known to decrease
flow, attenuate waves, alter sediment properties
and trap sediment. The total effect of these
characteristics on groyne field morphology however
is still unknown.
Within this thesis the effect of softwood vegetation
on groyne field morphology is described. The
morphological development of three test locations
along the River Waal have been determined based
on elevation measurements from 1990 until 1995
and newly conducted measurements from 2005 and
2006. At each of the test locations one groyne field
has been used for the plantation of willows while
the upstream and downstream groyne field has
been used as reference.
At each location the species, common osier (Salix
viminalis), purple willow (Salix purpurea) and gray
willow (Salix cinerea) were planted in an alternating
pattern on the upper bank of the study groyne
field. From these species the survival percentages
and yearly averaged mortality rates have been
determined.
Furthermore, hydraulic conditions (water level and
discharge) have been determined at each location
from 1990 until 2005 at each location. These
conditions have been determined by using a 1D-
model, SOBEK.
The data obtained from elevation measurements
has been used to create detailed Digital Elevation
Models to describe the morphological situation at
the time of measuring. In order to create these
models, several interpolation methods have been
assessed to determine which technique would be
best suited for this study. Elevation Difference
Maps and series of Riverbank Profiles were derived
from the Digital Elevation Models. These were used
to describe the morphological development per
location over time. Volumetric calculations were also
made to determine the effect on the total sediment
balance within each groyne field.
At each of the three test locations, the presence
of softwood vegetation has caused erosion of
the lower bank and accretion at the upper bank.
The morphological development within the
corresponding reference groyne fields differ from
the test groyne field but are consistent with each
other. It can therefore be concluded that the
found effect at the test locations is induced by
the presence of softwood vegetation. From the
calculated volumetric differences, it can be seen
that at locations were erosion has taken place at the
reference groyne fields the presence of vegetation
at the test groyne field has caused less erosion
compared to the reference fields. At the locations
were sedimentation has taken place at the reference
groyne fields, the presence of softwood vegetation
within the study groyne field has caused erosion.
The total of the processes and factors, which are
mentioned throughout this report to have an effect
on groyne field morphology, are bundled into a
conceptual riverbank model for groyne fields with
the presence of softwood vegetation. From this
model a list of desired improvements for future
riverbank models has been derived.
Student: M.T.B. van den Broek
Committee: Prof.dr.ir. H.J. de Vriend, Dr.ir. M.J. Baptist, Dr.ir. E. Mosselman, Drs. M.M. Schoor
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering ��0307
Ever since progressive engineers came up with the
idea of creating floating structures in the sea, many
studies and models tests were performed in order to
develop the optimal floating breakwater. Although
the advantages of a floating structure seem to be
rather obvious, the use of these structures is limited,
mainly due to the complex hydrodynamic behavior,
the reliability and the costs of these structures.
International container shipping is one of the most
dynamic economic sectors of the past years. Higher
efficiency of the loading and unloading processes
and the increase in size of container vessels
contributed to the development of the Floating
Transhipment Container Terminal (FTCT).
The objective of this thesis was to analyse the
hydrodynamic behavior of the floating breakwater
and to improve the performance of the floating
breakwater. A model, the so-called Rectangular
Floating Breakwater Design Model (ReFBreak-Model),
had to be developed that served as a general design
tool to determine the dimensions of the floating
breakwater.
First of all, the calculation parameters, requirements
and boundary conditions had to be determined.
The harbour efficiency puts demands on the
performance of the floating breakwater and is an
important factor to determine whether the floating
breakwater concept is successful or not. The
hydrodynamic coefficients for rectangular floating
bodies, measured by Vugts (1970) are used in the
calculations and were extrapolated to a wider wave
frequency range. Two-dimensional calculations were
performed to determine the influence of several
structural variables on the hydrodynamic behavior
of the floating breakwater. The calculations were
performed in regular, sinus-shaped beam-on waves.
The hydrodynamic behavior of floating breakwaters
is influenced by many factors. However, only a
limited number could be analyzed in the underlying
Floating BreakwaterA Theoretical study of a dynamic wave attenuating system
thesis work. Therefore, a rectangular floating
body with varying width, draft and mass has
been assumed as the basic shape of the floating
breakwater. Hydrodynamic behavior as calculated
by the ReFBreak-model has been checked with
the three dimensional potential-theory computer
model DELFRAC to determine the reliability of the
calculations. Wave transmission to the harbour side
of the floating breakwater has been calculated for
several floating breakwater layouts as is shown in
the figure for a floating breakwater with a variable
width, draft and screen draft.
The theoretical study proves that a floating
breakwater is able to attenuate waves when the
structural layout is optimal.
- The floating breakwater is able to attenuate
regular beam waves with 17 second periods
- This kind of floating breakwater must be able
to adapt its structural appearance on the prevalent
wave periods.
- The draft-width relation is the most important
factor for the performance of the breakwater.
Since the results of this model are based on
pure theoretical calculations, further research is
necessary to investigate the influence of irregular,
oblique (Ocean) waves on the performance of the
adaptable floating breakwater.
Student: M.W. Fousert
Committee: Prof.drs.ir. J.K.Vrijling, ir. W.F.Molenaar, ir. J.L.F. van Kessel
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering�0 0307
Feasibility Study on Tidal Power BarragesIncluding plant design and site selection
Tidal power is a proven technology to produce
electricity and has the potential to generate
significant amounts of electricity at certain sites
around the world. However, only limited guidance
is available for a cost efficient tidal power plant
design and the selection of a suitable site. Both
items are addressed in this study, together with a
comparison of the tidal power costs to the costs of
other (renewable) energy sources. Within this study
the possible concepts for tidal barrages have been
analysed, from which a single basin layout showed
to be the most attractive plant layout. This layout
could be combined with three generation modes;
One-way generation, Two-way generation and
generation with additional pumping.
For these concepts, a general plant design has been
analyzed, to determine the general dimension of the
essential plant components, including; powerhouse,
sluice gates, barrage dam, bed protection and
transmission lines. Aspects like cavitation and
required excavation are taken into account. The
construction costs for these components are mainly
estimated by multiplying the defined volume of
material by the unit costs.
As the turbines and further electromechanical
equipment required further detailed study, this is
studied separately from the general plant design.
From this, a turbine diameter of 5-8 m is suggested
for all sites and a method is introduced to determine
the optimum number of turbines and sluice gates.
By studying the efficiencies and costs, for One-
way generation the single regulated Bulb turbine
was proven to be the most attractive turbine type.
For Two-way generation the double regulated Bulb
turbine is suggested. This study showed that Two-
way generation is the most attractive generation
mode.
With the use of the Dynamic Tidal Power Model
the optimum plant capacity is defined together,
with the required head difference for generating.
As little was known about the effect of pumping
at tidal power barrages, this has been worked
out. Pumping water out or into the basin is shown
to be not profitable at constant electricity costs
over a day as it consumes more power than it
produces, but gains potential when electricity rates
are lower (i.e. at night). After the general tidal
power plant and turbine design were defined, the
site selection process could be worked out. The
essential parameters resulting in a valuable site
selection were determined. With this, a method
was introduced to define the attractiveness of a
site. A site that does not meet the required mean
tidal range criterion of 7 m, can not reach the most
economic design for tidal power barrages and will
lose attractiveness.
To define the economical position of tidal power
in relation to other electricity sources, the costs
of tidal power were determined. This included the
investment costs as well as the operational and
maintenance costs during its life time. Compared to
the other electricity sources, tidal power showed to
have high investment costs and low operational and
maintenance costs. From this it can be concluded
that tidal power has the potential to compete with
other electricity sources.
One of the most important recommendations which
can be made on the basis of this study is further
research in the possible environmental aspects
of tidal power barrages regarding morphology,
water level changes and impact on fish habitats. In
addition, this thesis shows that this subject should
be further elaborated as this could increase the total
feasibility.
Student: J.J. van Harn
Committee: Prof.dr.ir. M.J.F. Stive, Ir. J. van Duivendijk, Ir. H.J. Verhagen, Dr.ir. P.J.A.T.M. van
Overloop, Ir. E. ten Oever (Delta Marine Consultancy)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering �10307
The sandhunger of the OosterscheldeCase study: The development of the morphology of the Galgeplaat
After the realisation of the Deltaworks, the
morphologic balance of the Oosterschelde (see
picture) has severely been disrupted. Due to the
Deltaworks the tidal prism in the basin has been
reduced sharply. The tidal trenches became to wide
and need sand to get to a new morphologic balance.
The stormflood barrier stops sediment entering the
basin from sea, a redistribution of sand from the
sandbars takes place. This explains the lowering of
the sandbar de Galgeplaat.
The goal of this research is to get more
understanding of the loweringproces of the sandbar.
In the period 1983-2001 the changing in height
of the sandbar de Galgeplaat was measured at
43 locations. In combination with the wind data
collected in that period, a data-analysis has been
carried out. This analysis learns us that after
the realisation of the Deltaworks there is still
sedimentation at de Galgeplaat, but to small to
realise a net sedimentation. The data-analysis gives
a lot of information about the deciding factors of
the erosion of de Galgeplaat. Besides that we look
at the influence of a closed barrier on the erosion
of de Galgeplaat. The data-analysis together with
several computer simulations, makes it possible to
give a prediction of the lowering of the sandbar de
Galgeplaat in the future.
Student: M.L.E.B. van der Hoeven
Committee: Prof Dr. Ir. M.J.F. Stive, Dr. Ir. Z.B. Wang, Dr. Ir. M. Zijlema, Drs. E. van Zanten.
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering�2 0307
The influence of flow acceleration on the stability of stones
Bed protections are often made of granular material
and are used to prevent erosion of the bottom or
to prevent the development of scour holes near
hydraulic structures. Failure of the bed protection
can undermine the foundations of a hydraulic
structure and in the worst case lead to total failure
of the hydraulic structure.
In situations where the uniform flow is interrupted,
velocity gradients develop. It is found in
experiments and in practice that when a flow is
accelerated stones start to move before the critical
velocity has been reached. This movement is
ascribed to the existence of flow accelerations.
To find out more about this phenomenon
experiments were carried out in a flume containing
a locally tapered section in the labortatory for
Fluid Dynamics of the Department of Hydraulic and
Geotechnical Engineering.
In the tapered section the flow is accelerated
and flow conditions can be created, so that the
threshold of motion is reached. If the assumptions
are correct the stones should move before the
critical flow velocity is reached.
An attempt is made to quantify the difference
in velocity of the accelerated situation with the
velocity of a uniform situation for which the same
amount of stone movement would occur.
With the help of the 7 stages of transport defined
by Breusers (DHL, 1969) a translation can be
made from the amount of stones, that moved in
the experiments, to a Shields parameter. With this
Shields (1936) parameter the critical velocity can be
calculated for which this amount of stone movement
occurs under uniform flow conditions.
Student: M. Huijsmans
Committee: Prof. dr. ir. M.J.F. Stive, Ir. H.J. Verhagen, Dr. Ir. H.L. Fontijn
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering ��0307
Scour around an offshore wind turbine
During the construction of the first near-shore wind
farm in the Netherlands near Egmond aan Zee,
prototype measurements are performed with the
aim to monitor the behaviour of the scour protection
around the mono-pile foundation of the wind
turbines (Dpile=4.6 m).
The sea bed around the monopile is protected
with a two-layer rock protection. Interest
goes to the scour process on the first layer,
the filter construction, under influence of the
surrounding environment. For this purpose velocity
measurements, wave characteristics and multi-beam
depth soundings are gathered to give an overall
impression of both the acting forces on as well as
the strength of the structure.
In the design phase unfamiliarity with the exact
scour process influenced by the interaction of waves
and currents was reason to carryout scale model
tests at WL|Delft Hydraulics laboratory. The present
prototype measurements serve as a reference,
verification and calibration of the scale model tests.
The filter stones have a size of Dn50F = 0.05 m,
with a layer thickness of 0.4 m to 0.7 m directly
on top of the sand of the sea bed (Dn = 250 μm).
Local conditions during the measurement are a tidal
current velocity of about 0.7 m/s and a wave height
of order Hs < 3.6 meter.
Near the pile a lowering of the filter material is
found of 0.4 m until a distance of 2 meter from
the mono-pile. For the whole filter construction an
evenly distributed average lowering of about 0.07
meter was observed, mainly influenced by tidal
current and waves. The lowering that followed by
the design formulas show a comparative lowering,
depending on the assumption for the addition of
shear stress accounts by currents and waves.
Student: W.F. Louwersheimer
Committee: Prof. dr. ir. M.J.F. Stive, ing. H.T. Van Lieshout, ir. J. Olthof, ir. H.J. Verhagen, dr.ir. A.J.H.M.
Reniers
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering�� 0307
Dealing with uncertainties in the design of bottom protection near quay walls
During a design of bottom protection near a
quay wall a civil engineer has to deal with several
uncertainties. Therefore practical experience and
insight in the consequences of the choice of the
input variables in the present design formulas is a
condition to guaranty an optimal design. To enlarge
this insight in the present design formulas several
bottom protections in the port of Rotterdam have
been investigated. Because one of the bottom
protections did not satisfy the demands of stability
required to guarantee a stable bottom protection,
this bottom protection is studied with soundings.
Using these soundings the actual level of stability
can be compared with the present design formulas.
The loads on this bottom protection differ, because
of diversity in shipping and tidal motion. Therefore
a better comparison can be made by resembling
the results of the soundings with a probabilistic
approach.
The probabilistic model is calibrated by the
sounding results and by registrations of mooring
and unmooring vessels. Out of these probabilistic
approaches insight in the influence of each input
variable can be derived. By using a combination of
probabilistic results and a fault-tree the probability
of a scour hole near a quay wall can be calculated.
With these results it is still not possible to choose
one strategy for designing bottom protections. The
impact of a scour hole on the environment of a quay
wall needs to be investigated. Therefore a study to
the interaction between a scour hole and the quay
wall is enclosed. With these results a risk based
analysis is made to evaluate the different strategies
and their consequences.
Student: A.A.Roubos
Committee: Ir. T. Blokland, Drs. R. Booij, Ir. J.G. de Gijt, Ir. H.J. Verhagen, Prof.drs.ir J.K. Vrijling
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
◊
Hydraulic & Geotechnical Engineering ��0307
“Computational modelling on the final closure gaps in the Saemangeum dam, South Korea”
The flow velocities through a closure gap in the
final construction stage can be relatively high
because the total basin fills and empties through
this closure gap. The flow velocities in this final
stage are often normative for the design of the
construction and the closing method. The stability
of the bottom protection is of main importance
during the last construction phase because scour
holes that develop too close to the construction may
cause the total construction to fail. The stability of
a bottom protection not only depends on the mean
flow velocity but on the turbulent properties of the
flow as well.
EFD.lab is a three-dimensional fluid flow model that
calculates a detailed pattern of the flow through a
closed system, like a tube or a pipeline. EFD.lab is
capable of calculating the turbulent properties in a
flow. A free water surface cannot be calculated with
this model but by using a pressure ceiling, a free
surface flow can be modelled. To investigate the
suitability of the EFD.lab model for situations with
a free water surface like a closure gap, one of the
final closure gaps in the Saemangeum dam has been
modelled with the EFD.lab model.
Because no measurements could be executed during
the closure of the dam, data about water levels at
both sides of the dam, which are needed for the
input of the EFD.lab model, needed to be estimated.
With a storage area approach, a first estimate of the
varying water level inside the basin has been made.
Subsequently the water level variation during the
closing period has been calculated in more detail
with a two-dimensional model called Waqua. The
predicted water levels have been used as input data
for the three-dimensional EFD.lab model.
Closure gap number 1 has been modelled with the
EFD.lab model. The geometry of the closure gap has
been scaled with a factor 2.5 in both the vertical as
the horizontal direction, because the computational
area in EFD.lab may not exceed 1 by 1 km. Because
the EFD.lab model does not calculate the water
level, a water level had to be imposed beforehand.
After every calculation, this imposed water level has
to be adapted to the results. The flow above the
sill appeared to be super critical and this instigated
problems in modelling the flowThe changing of
the gravitational acceleration did not influence
the results of the calculation. To investigate the
turbulence in the model calculation, the turbulent
parameters at the boundary of the model have been
changed. Changing the turbulent parameters at the
boundary of the model did influence the results.
Lowering the turbulent values at the boundaries
of the model implied less turbulence in the fluid
flow. By adapting the turbulence parameters at
the boundary of the model as well as in initial
values in the general settings, the results were
influenced in such a way that the results were no
longer plausible. Finally, the influence of changing
the roughness of the bottom surface has been
investigated. The results of the calculation with an
extra bottom roughness showed a higher maximum
mean flow velocity above the sill and higher
turbulence fluctuations.
The EFD.lab model appeared to be not very suitable
for the modelling of fluid flows with free surfaces.
Adapting the water level was time consuming and
when the flow became super critical, problems
arose. The parameters for the turbulent kinetic
energy and the turbulent dissipation in the general
settings are start values for the calculation and
therefore it had not been expected that changing
them would influence the results as much as
they were. Before the EFD.lab model is used for
turbulent calculations in a free surface flow, further
investigations are recommended.
Student: M. van der Sande
Committee: Prof.drs.ir. J.K. Vrijling, Ir. H.J. Verhagen, Drs. R. Booij, Dr.ir. A. Vrijburcht
(Rijkswaterstaat), Ir. T.J. Zitman
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
◊
Hydraulic & Geotechnical Engineering�� 0307
Hydraulic fracture grouting Laboratory experiments in sand
Introduction and objectives
When a tunnel is bored under buildings, those
buildings may settle because of an over cut of
soil under the foundations by the tunnel bore
machine (TBM). A mitigation measure to reduce
these settlements is compensation grouting, which
means compensating the settlements by injection of
grout under the settled foundations. Compensation
grouting occurs in two types, compaction grouting
and fracture grouting. Fracture grouting is preferred
when settlements over a larger area have to be
compensated. Especially under a piled foundation,
fracturing is more advantageous than compaction,
because of the lower occurring local stresses with
the method of fracture grouting. Research has
shown that fractures occurred in clay and silty
soils, but the realization of fractures in sand is
more difficult. This research is meant to create
fractures in sand by grout injection, if necessary
with different grout properties. Further it is meant
to gain more insight in fracturing in sand, especially
for the implementation of the tunnelling project in
Amsterdam, where this technique has to be used
in sand. Besides those two objectives it is tried to
give insight in the efficiency and processibility of the
grout mortar.
Implementation
The test series is carried out with the same set-up
as used in the test series of Kleinlugtenbelt, 2005.
The set-up simulates the fracture grouting technique
in the field. The grout injections are carried out with
changing grout properties. Pressures, efficiency,
drainage and shape of the fractures are measured
and examined to find relations between these
results and various grout properties.
Results
The results show that grout can fracture sand. It
appears that there is an optimum of grout efficiency
and fracture geometry using various cement
entities. There are three conflicting grout properties
which occur during hydraulic fracture grouting:
- The amount of leak off
- The bleeding capacity
- The amount of particles
Between those properties there has to be found a
balance to make fracture grouting in sand possible
and most effective.
Student: M.P.M.Sanders
Committee: prof. ir. A.F. van Tol, prof. ir. J.W. Bosch, ing. H.J.Everts, ir. A.Bezuijen (GeoDelft), Dr.ir. A.
Fraaij and ir. F. Kaalberg (Witteveen+Bos)
For more information about this thesis project, please contact the department, tel. (+31) 15 27 81880.
Hydraulic & Geotechnical Engineering �70307
The influence of flow acceleration on the stability of stones
There is a trend in the development of safety
concepts as well as in economical approaches
to structural design to imply more probabilistic
concepts. In this thesis work an attempt is made
to contribute to this development by describing
how structural reliability analysis can be carried out
in Geotechnics, a discipline that deals with large
uncertainties in the properties of its most important
building material - the soil. As specific subject
the structural reliability of deep excavations was
chosen, for which several examples will demonstrate
the applicability of the presented theoretical
framework. Furthermore, the Finite Element Method,
as state of the art structural analysis tool, will be
applied for the reliability assessment.
The combination of advanced models and relatively
high parameter uncertainty make the use of
uncertainty respectively reliability analysis methods
in combination with the Finite Element method
very attractive. It is a way of dealing with the
present uncertainties in a rational manner and using
advanced modeling techniques at the same time.
For this thesis work special attention was paid to
the use of Finite Element Analysis in structural
reliability concepts. It is demonstrated that, in
contrast to the common opinion, probabilistic
analyses can be carried out with an acceptable
number of calculations and that not always 100.000
samples from a Monte Carlo simulation are needed
to obtain reasonable estimates of the reliability of
a structure. The application of advanced and more
efficient concepts was part of the research.
Student: T. Schweckendieck
Committee: Prof. drs. ir. JK Vrijling, Dr.ir. PHAJM. van Gelder, Dr.ir. RBJ Brinkgreve, Ir. Ed Calle
(GeoDelft), Dr.ir. Paul Waarts (TNO)
For more information please contact the department of Hydraulic Engineering: (+31) 15 2783345
Hydraulic & Geotechnical Engineering�� 0307
An analysis of friction by microtunneling
Characteristic of microtunnelling is that the TBM
(Tunnel Boring Machine) and the tunnel are pushed
through the ground from the starting shaft to the
receiving shaft. Inherent to this technique is that
the friction forces grow with an increasing length of
the tunnel. In current practice it is not possible to
accurately predict the friction by microtunnelling. The
objective of this research is to improve the prediction
of wall friction by microtunnelling in common Dutch
soils.
The primary factor for higher jacking loads after a
standstill is the dissipation of water overpressures
in the layers surrounding the tunnel. Due to the
existence of arching mechanisms, the weight of the
soil layers above the tunnel is less important for the
encountered friction.
In a case project (WRK II) the influence of arching
mechanisms and lubrication is shown. Ten borings
under almost similar boundary conditions are inves-
tigated. The borings are constructed in a sand layer
covered by approximately 8 meters of peat. The
borings consist of a welded continuous steel pipe.
Two of these borings crossed a highway. Locally the
peat is replaced by sand and here the weight of the
ground column has increased. These two borings
started and ended under the peat layer. Under the
highway the wall friction was twice as high as under
the peat layers, while the weight of the ground
column was four times larger. This indicates that
arching mechanisms do occur and the influence of
the weight above the tunnel is limited.
Another boring of WRK II revealed the importance
of lubrication. During a problem with the lubrication
injection system a very significant increase in wall
friction is recorded. The influence of the lubrication is
far larger then the influence of the increase in weight
of the ground column.
In segmented microtunnels misalignment has a large
influence. This is explained as follows:
• Constant steering actions are necessary to correct
small deviations in the obtained alignment of the
boring, even at straight borings.
• Small rotations (< 0.3°) could give rise to high
stresses in the soil-tunnel interface. Theoretically
this is explained in this report by considering the
segments as blocks. In normal curves up to 50 %
of the friction can be attributed to curved boring.
In misaligned curves this percentage is higher.
• Jamming of segments which are longer then the
longest part of the TBM may occur under certain
conditions. Borings in very stiff soils (compacted
sand) and with a small overcut are vulnerable for
jamming.
The most important conclusion of this report is that
construction related factors, such as standstills, poor
lubricant injection and misalignments have a large
influence on the friction. Especially in stiff soils, in
which the TBM reacts very well onto steering actions,
the influence of misalignment and steer corrections
on the friction can be significant.
The regular friction in a microtunnel varies between
1 to 5 kN/m2. Steering actions can cause locally 150
kN/m2 or more of extra friction. Depending on the
amount of steer corrections, this leads to an increase
of several kN/m2’s averaged over the entire tunnel.
Student: N. Verburg
Committee: Prof.ir A.F. van Tol, e.a
For more information about this thesis project, please contact the department, tel. (+31) 15 27 81880.
Watermanagement ��0307
Watermanagement
Civil Engineering Theses
Watermanagement�0 0307
Probabilistic modeling of sewer deterioration
Traditionally, Dutch municipalities apply theoretical
deterioration models without any form of validation
or calibration. This practice may result in incorrect
decisions and a cost ineffective sewer management
policy. The focus of my research was the application
of sewer inspection data for the development of a
sewer deterioration model.
Since the mid 1990s sewer inspections in
the Netherlands are daily practice for most
municipalities. Most inspections are carried out by
CCTV (closed circuit television) camera, the footage
is consequently interpreted by qualified/certified
inspectors. Regulations determine the aspects
on which the condition of the inspected pipes is
rated. For this particular research only inspection
data till 2004 is used. After 2004 a new European
sewer inspection regulation was imposed. Despite
the fact that this new regulation shows great
similarities with the ‘old’ Dutch sewer inspection
regulation, combining the two distinct datasets was
not feasible. Although inspections based on the two
regulations are not alike, the results of the research
are indicative for the application of inspection data
based on European regulations for deterioration
modeling.
A literature study on probabilistic deterioration
models learned that the failure rate model, the
Markov model and the semi-Markov model reflect
the non-continuous classification system as applied
when inspecting sewers. It was further found that
numerous models are developed for deterioration
modeling. However, most models were not
confronted with field data. In this research a first
step is made towards the application of such models
to the Dutch sewer system using field data.
Sewer inspections of the municipality of Goirle,
the Netherlands, were assessed on suitability for
sewer deterioration modeling. It was found that
most aspects, on which the sewer is assessed when
inspected, are not of interest for deterioration
modeling because:
- some aspects are hardly present in the sewer
inspection files, these aspect depends on the case
study at hand (e.g. intruding sealing material);
- some aspects do not solely assign to the structural
condition and therefore do not necessary
deteriorate over time (e.g. intruding connection);
- some aspects have a very large probability
(>50%) of not being identified when inspecting a
pipe, these aspects are longitudinal displacement
and radial displacement.
Two aspects remain, these are, ‘surface damage by
corrosion or mechanical action’ and ‘fissure’.
A case study was performed on the modeling of the
aspect ‘surface damage by corrosion or mechanical
action’ using a Markov model. The results show
that the Markov model is a good starting point for
modeling sewer deterioration.
Student: J. Dirksen
Committee: prof. dr. ir. F.H.L.R. Clemens, dr. ir. J.L. Korving, ir. W.M.J. Luxemburg, ir. M.J. Kallen (TU Delft, faculty
of Electrical Engineering, Mathematics and Computer Science), drs. ir. E.C. Ottenhoff (Witteveen+Bos)
For further information please contact the secretary of the section Water management: (+31) 15 2781646
Watermanagement �10307
Risk Assessment for Floods Due to Precipitation Exceeding Drainage Capacity
Studies on flood protection and flood damage
modeling were mostly concentrated on the floods
caused by breaches of dunes and levees since a
flood resulting from these would be sudden and
extensive and combined effects may be catastrophic
but recently attention was also given to floods
due to precipitation exceeding capacity of the
drainage canals and pumping stations of polders.
This kind of flood is neither life threatening nor as
catastrophic as the floods due to breaches of dunes
and levees but as a result of the increase in the
extreme precipitation events due to climate change
and increased land value, the risk due to this kind
of floods increased considerably, and must be
calculated.
This study aims to investigate and improve current
situation in risk assessment of floods due to rainfall
exceeding capacity of the drainage system of
polders by working on following objectives.
- To figure out if any of the commercially available
models are capable of solving this problem
considering the different nature of rainfall induced
floods in low lands.
- To prove the correlation between flood depth and
flood duration. This correlation is rather important
because proof of such a correlation will allow us to
eliminate one of these parameters, reducing the
vast workload and enabling us to calculate risk.
- To investigate the applicability of a new risk
analysis tool for calculation of risk for rainfall
induced regional floods in low lands.
Results of an extensive study on the subject showed
that none of the existing models were capable of
solving this problem. Yet due to the correlation
between flood depth and duration, it was possible
to calculate the risk. And the “risk analysis method”
was an applicable approach to this case but it
requires further improvement.
Student: U. Karamahmut
Committee: Prof.dr.ir. N.C. van de Giesen, Dr.ir. P.E.R.M. van Leeuwen, Ir. O.A.C. Hoes
For more information you can contact the section Water Management, tel. 015-2781646
Watermanagement�2 0307
The impact of the deep water extraction at the position of the fresh-salt interface
The ground surface above sea level and a
precipitation surplus are the main conditions for
the formation of a fresh water lens under the dune
area. Because fresh water is lighter than salt water,
the fresh water lens is in a dynamic equilibrium with
the surrounded brackish and salt water. (Figure
1) The dune water company South-Holland (DZH)
extracts fresh water from the dunes for drinking
water. With artificial recharge DZH tries to maintain
a dynamical equilibrium of the fresh water lens. DZH
wants to extract as many water as possible from
the deeper aquifers without reducing the size of the
fresh water. However, there is still little knowledge
about the flows and displacement of the water in
the deeper aquifers, nor is there an accurate model
of the interface and its brackish transition zone. The
research objective is to determine the sustainable
extraction capacity for the deep wells in the region
Meijendel preventing intrusion and upconing of salt
water in the wells. A second objective is to establish
the reliability of the predictions to determine the
extraction capacity.
The software that was used in order to simulate this
complex three-dimensional groundwater system is
Triwaco. This software programme was chosen out
of a comparison of available models. The advantage
of using Triwaco is that a good working model is
available and that there is experience with this
model at DZH. The disadvantage is that it does not
take into account displacement of the fresh-salt
interface.
In this study, the fresh-salt interface is represented
by two interfaces, the 300 mg Clˉ/l and 10.000
mg Clˉ/l. These iso-concentration layers are
implemented in the model as resistance layers. The
level of 300 mg/l was chosen from the perspective
of maximum tolerable chloride for drinking water
production. To determine the overall behaviour of
the fresh water lens a 10.000 mg Clˉ/l interface was
defined by DZH. Nine model layers and 8 resistance
layers are necessary to model the interface and all
presented aquifers and aquitards (Figure 2)
Because Triwaco lacks facilities to automatically
move the interface; this would have to be done by
hand. To automate this otherwise very cumbersome
process, in this study a batch-file script was
developed. This DOS script runs the program
automatically and adapts the interface elevations
and all effected parameters after each time step.
Furthermore the effect of the extra resistance layers
in Triwaco, the density distribution and the effect
on fully penetrating wells is studied to improve the
model.
After running the model for a period of 20 years,
the conclusion was drawn that the model did not
give the desired results. For instance at the well
locations Waalsdorp the interface moved to an
unrealistic high position. One reason for this is the
absence of clay layers in the Triwaco model. To
determine the reliability of the model predictions
the model is calibrated on the interface position.
The uncertainty of the newly calculated interface
depth is too large to give a plausible estimation of
the change of the interface. The predictions of the
model are unreliable due to the large error in the
calculated head and due to the low sensitivity of
the parameters, which are used to carry out the
calibration.
The conclusion is drawn that this model can not be
used for calculation of the interface displacement.
A better solution is to use the Triwaco model only
for calculation in the shallow aquifer. The data can
be transferred into Modflow for making calculations
in the deeper aquifers. The advantage of Modflow
is that all model layers can easily be included and it
takes into account automatic interface displacement
in time and the transition zone for the density
distribution.
Student: N.L.Kramer
Committee: Prof.Dr.ir.T.N.Olsthoorn, Dr.ir.C.Maas, Dr.ir.G.J.M.Uffink, J.B.Fritz
For more information you can contact the section Water Management, tel. 015-2781646
Watermanagement ��0307
Integrated water quantity and water quality control of lowland water systems
Water systems are continuously charged by a
diversity of loads. These loads differ from water
that flows into the system, like precipitation and
infiltration, to water that flows out of the system,
like drainage and evapotranspiration. To maintain
the water level and prevent inundation these
systems are equipped with pumps and inlets, which
are mainly controlled, based on the knowledge and
experience of the supervisor. This is a very effective
way to manage water systems. When these water
systems are in the Western part of the Netherlands
they may suffer from salt intrusion. As a result
of salt intrusion the surface water may become
brackish. To prevent this, the system is flushed
continuously with large amounts of water, which are
larger than necessary. The salinity of the inlet water
varies continuously. These variations combined with
the constant flush rate and varying precipitation,
cause the systems salinity levels to vary over
time. Because the salinity in the water system has
to remain lower than an absolute maximum, the
amount of water that is let in, is on the safe side,
meaning larger than necessary. This conservative
control is based on steady state calculations of
the water systems behavior. It is a low-tech, but
cheap and effective way to solve the water quality
problem. Increasing the efficiency of these system
and maintaining the effectiveness should be
possible with advanced control systems.
Therefore the objective of this master thesis is to
‘Develop a generic control system that can fulfill
the water quantity requirements of a water system
in combination with the water quality requirements
and minimizes the effort required to fulfill these
requirements.’
Several steps are taken to develop this control
system. The two most important factors, water
quality and water quality, are quite different.
Therefore water quantity and quality are separated.
For both factors the relevant processes are
described, then these processes are modeled and
at last the control methodology is being described
for the separate factors. Combining the control
methods generates several control principles, which
can be used for combined water quantity and
quality control.
A theoretical case has been created to test the
developed control principles and compare these
principles with standard control. In several cases
the developed control outperformed standard
control. The best control principles was tested on a
model of the Haarlemmermeerpolder, since real life
testing was not possible. The model was created
with data of the Hoogheemraadschap Rijnland and
Sobek, which is software from WL|Delft Hydraulics.
Advanced control works very well on the
Haarlemmermeer polder, although not as good
as was the case with the theoretical case. The
quantitative control performed as well as standard
management. Water quality levels at measuring
points were the roughly the same with advanced
control and standard management. Some
improvement were evident. There was a reduction
of flushing water and salinity level in the system
lowered as a result of redirections of saline water.
Concluding it can be noted that Model Predictive
Control performs much better than standard
management in the theoretical case on quantitative
as well as qualitative demands and shows good
salinity predictions. Some additional fine tuning of
Model Predictive Control will allow this system to
operate on its maximum. It may be concluded that
Model Predictive Control works very well in theory.
In the Haarlemmermeerpolder, Model Predictive
Control performs as good as or even better than
standard management in terms of quantitative and
qualitative demands with 10% less inlet water for
MPC. The goal of this master thesis has been partly
achieved. Unfortunately, Model Predictive Control
cannot fully fulfill the water quality requirements as
a result of model inaccuracies in some basins, but
still improves the salinity control of the system.
Student: B. van Rossum
Committee: Prof.dr.ir. N.C. van de Giesen, Dr.ir. P.J. van Overloop, Dr. B. van der Wateren – De Hoog
(Hoogheemraadschap Rijnland)
For more information you can contact the section Water Management, tel. 015-2781646
Watermanagement�� 0307
A distributed stream temperature model using high resolution temperature observations
Highly distributed temperature data are used as
input and as calibration data for a
temperature model of a subcatchment of the
Maisbich, a first order stream in
Luxembourg. A DTS (Distributed Temperature
Sensing) fiber optic cable with a length
of 1500m is used to measure stream water
temperature with a spatial resolution of 0.5
meter and a temporal resolution of 2 minutes. The
measurements are done during one
week in April 2006. In the measured temperature
profile four jumps in temperature are
seen (see Fig 1). This is caused by groundwater
sources. Using two profiles and the
assumption that the discharge and temperature of a
groundwater source is constant, these
sources can be quantified.
The four sources are used as input for a distributed
physical based temperature model. In
the model the total energy balance including solar
radiation (with shading effects),
longwave radiation, latent heat, sensible heat and
river bed conduction is calculated.
The simulated temperature along the whole stream
is compared with the measured
temperature at all points along the stream. It shows
that proper knowledge of the lateral
inflow is crucial to simulate the temperature
distribution along the stream, and, the other
way around stream temperature can be used
successfully to identify runoff components.
The DTS fiber optic is an excellent tool to provide
this knowledge.
Student: M. Westhoff
Committee: Prof.dr.ir. H.H.G. Savenije e.a.
For more information you can contact the section Water Management, tel. 015-2781646
Transport & Planning ��0307
Transport & Planning
Civil Engineering Theses
Transport & Planning�� 0307
Dynamisch Railverkeersmanagement op knelpunten
Dynamisch Railverkeersmanagement (DVM) is
bedoeld om op het spoorwegnet effectief om te
gaan met variaties in de uitvoering. Met een groei
van het aantal treinen en hogere kwaliteitseisen die
worden gesteld biedt DVM mogelijkheden voor een
betere benutting van de bestaande infrastructuur. Dit
gebeurt door het opstellen van een beter betrouw-
baar plan of door meer vrijheden voor het regelen
van treinverkeer in de uitvoering te bieden. DVM
biedt mogelijkheden om flexibeler om te gaan met
variaties in vertrektijden en volgordewisselingen en
desondanks toch meer betrouwbaarheid biedt in de
rijtijden en aankomsttijden, en daarmee een betere
afhandeling van het treinverkeer.
Tot nu toe werd DVM alleen situationeel toegepast,
waardoor veel aandacht werd geschonken aan de
lokale omstandigheden en de plaatselijke mogelijk-
heden van DVM. Bij wijziging van deze omstandig-
heden tijdens het onderzoek gaat een deel van het
onderzoek naar de mogelijkheden van DVM verloren.
Een typologie van knelpunten zorgt ervoor dat knel-
punten van een zelfde type sneller kunnen worden
onderzocht, omdat onderzoek van naar de effecten
van DVM voor vergelijkbare situaties kunnen worden
gebruikt.
Voor één knelpunttype, een meersporig baanvak met
inhaalmogelijkheden, is voor de case Utrecht – ’s-
Hertogenbosch onderzocht wat de effecten van DVM
zijn. In verschillende scenario’s is gevarieerd met het
aantal inhaalmogelijkheden, het aantal treinen en
DVM maatregelen voor de keuze van plan- en regel-
strategie.
Uit de simulatieresultaten is gebleken dat in de
huidige situatie een uitbreiding van de infrastructuur
niet noodzakelijk is. Slechts wijziging van de plans-
trategie zorgt voor aanzienlijke verbetering. Dit geldt
voor zowel stoptreinen als intercity’s.
Bij toename van het aantal treinen blijkt dat uitbrei-
ding van de infrastructuur onafwendbaar is. De keuze
van regelstrategie wordt daarin ook steeds belangrij-
ker, terwijl ook de gekozen planstrategie nog steeds
een grote invloed heeft. Uit de simulatieresultaten
blijkt dat juist in deze situatie DVM maatregelen
een effectieve bijdrage kunnen leveren om de rij-
en aankomsttijden te verbeteren. Bij een groeiend
aantal treinen zullen de planstrategie, regelstrategie
en het aantal inhaalmogelijkheden dus steeds meer
moeten worden geoptimaliseerd.
Student: M. van Dijk
Committee: Prof.dr.ing. I.A. Hansen, dr.ir. T.J.J. van den Boom, dr. R.M.P. Goverde, ir. R. Hemelrijk
(ProRail), Ir. J. van den Top
For more information please contact the department of Transport & Planning: (+31) 15 2781681
Transport & Planning �70307
De oorzaken van de verslechterde doorstroming bij �0 km zones
In november 2005 is ter verbetering van de lucht-
kwaliteit op vier trajecten op de snelwegen rond de
grote steden in de Randstad de snelheid verlaagd
naar 80 km/u in combinatie met trajectcontrole.
Gebleken is dat na invoering van de 80 km/u maat-
regel de filezwaarte op drie van deze vier trajecten
is toegenomen. Als gevolg van deze toename is de
vraag gerezen waarom de doorstroming op deze
trajecten is veranderd na invoering van de maatre-
gel. Het afstudeeronderzoek was erop gericht om te
onderzoeken welke aspecten van het rijgedrag na de
invoering van de 80 km/u maatregel zijn veranderd
en wat voor effect dit heeft gehad op de doorstro-
ming. Voor het onderzoek is gebruik gemaakt van
geaggregeerde lusdata (1 en 15 minuten gemiddel-
den), lusdata op voertuigniveau en gedigitaliseerde
videobeelden opgenomen vanuit een helikopter. Alle
vier de (nieuwe) 80 km locaties zijn onderzocht.
In de eerste fase van het onderzoek is de capaciteit
voor en na invoering van de 80 km zones bepaald.
Hiervoor zijn verschillende methodes toegepast en
vergeleken, waaronder de empirische distributie-
methode, de productlimietmethode en het funda-
menteeldiagram. Hieruit blijkt dat de capaciteit van
de bestaande knelpunten op de trajecten significant
is gedaald na invoering van de verlaagde maximum
snelheid in combinatie met de trajectcontrole. Op
basis van de individuele voertuigdata uit de induc-
tielussen en de helikopterdata is vervolgens het
rijgedrag op de 80 km zones onderzocht. Hierbij is
gekeken naar de snelheid, het rijstrookgebruik, het
volggedrag en het rijstrookwisselgedrag.
Uit het onderzoek is naar voren gekomen dat de
verlaging van de maximumsnelheid van 100 km/u
naar 80 km/u op zichzelf niet de grootste oorzaak
is van de veranderingen in de verkeerssituatie. De
daling van de capaciteit wordt juist vroorzaakt door
de veranderingen van het rijgedrag van de wegge-
bruikers als gevolg van de snelheidsverlaging in
combinatie met trajectcontrole.
De belangrijkste oorzaken van de geconstateerde
capaciteitsdaling zijn:
• De snelheid op de wegvakken ligt als gevolg van
de invoering van de trajectcontrole onder de 80
km/h. De capaciteitssnelheid van de bottlenecks
liggen in de voorsituatie echter allemaal boven de
80 km/h, waardoor de capaciteitswaarde van de
voorsituatie niet meer kan worden bereikt.
• Door de geringere snelheidsverschillen tussen
de verschillende rijstroken en de (wettelijke)
verplichting om rechts te houden, is het percen-
tage verkeer op de rechterrijstrook toegenomen
en wordt de linkerrijstrook minder optimaal benut
dan in de situatie zonder de 80 km/u maatregel.
• Het is voor het verkeer dat de hoofdrijbaan wil
betreden moeilijker geworden om in te voegen,
omdat de gemiddelde lengte van een voertuigco-
lonne is toegenomen.
• Vanwege de strenge handhaving van de snelheid
remmen bestuurders eerder af bij het zoeken van
een geschikt hiaat dan dat ze gas geven voordat
de van rijstrook (kunnen) wisselen. Ook de door-
gaande bestuurders voeren voornamelijk rembe-
wegingen uit om een geschikt hiaat te creëren
Op basis van de resultaten van het onderzoek zijn
aanbevelingen gedaan voor de verbetering van de
doorstroming op de huidige 80 km zones en ter
verbetering van de besluitvorming omtrent nieuwe
locaties voor de 80 km/ maatregel.
Student: H.J. Harms
Committee: prof. dr. H.J. van Zuylen, prof.dr.ir. S.P. Hoogendoorn, prof.ir. F.M. Sanders, ir. J.W.
Goemans (Witteveen+Bos), drs. O.G.P. Tool (RWS Adviesdienst Verkeer en Vervoer), drs.
R. Dekker (Faculteit TBM)
For more information please contact the department of Transport & Planning: (+31) 15 2781681
Transport & Planning�� 0307
Systematische herinrichting van zwarte punten in Vlaanderen Een beslisboom en een kosten-batenanalyse
De Vlaamse overheid investeert 500 miljoen euro
voor de herinrichting van 800 zwarte punten. Dat
zijn kruispunten en wegvakken waar veel verkeers-
slachtoffers zijn geregistreerd. In dit MSc-eindwerk
zijn twee aspecten van de herinrichting van zwarte
punten in Vlaanderen beschouwd.
Ten eerste werd een beslisboom samengesteld waar-
mee systematisch bepaald kan worden wat het meest
geschikte kruispunttype op een bepaalde locatie
is. Deze beslisboom bestaat uit een tabel en negen
stroomschema’s. Met de tabel kan bepaald worden
welk stroomschema gevolgd moet worden om het
meest geschikte kruispunttype te vinden. Welk
stroomschema dat is, hangt af van de functies (of
de daarvan afgeleide categorieën) van de wegen die
elkaar op het kruispunt ontmoeten. In het te volgen
stroomschema worden vervolgens ja/nee-vragen
gesteld over de intensiteit op die wegen en over de
ruimtelijke inpasbaarheid van de mogelijke kruis-
punttypen. Aan het eind van het stroomschema is
bepaald wat het meest geschikte kruispunttype is.
Ten tweede werd een maatschappelijke kosten-baten-
analyse uitgevoerd voor de herinrichting van een zwart
punt. Als voorbeeldproject is een lichtengeregeld
kruispunt in Lier gekozen, waar een Haarlemmermeer-
aansluiting aangelegd zal worden. De belangrijkste
baten bestaan uit de in geld uitgedrukte waarde van
vermeden verkeersslachtoffers. Op basis van histori-
sche ongevalgegevens is een prognose gemaakt van
het aantal ongevallen en slachtoffers dat geregistreerd
zal worden als het zwarte punt niet heringericht wordt.
Ook werd beredeneerd met hoeveel procent het aantal
ongevallen en slachtoffers zal afnemen door de herin-
richting. Vervolgens is voor elk jaar berekend hoeveel
ongevallen, doden, zwaargewonden en lichtgewon-
den er vermeden worden door de herinrichting. Deze
baten worden in geld uitgedrukt, net als het vermeden
brandstofverbruik. De contante waarde van de totale
baten blijkt ongeveer tweemaal zo hoog te zijn als de
contante waarde van de kosten, dus het voorbeeldpro-
ject wordt maatschappelijk rendabel geacht.
Student: M. van ‘t Hof
Commissie: Prof.Dr.-Ing. I.A. Hansen, Prof.ir. L.H. Immers(K.U.Leuven), Dr.ir. J.A.A. Stoop, Ir. J. Van
Den Bossche (TV �V), Ir. P.B.L. Wiggenraad
For more information please contact the department of Transport & Planning: (+31) 15 2781681
Transport & Planning ��0307
Modeling interaction between pedestrians and revolving doors
This research implements a submodel in the
microscopic pedestrian simulation model NOMAD,
with which the functioning of revolving doors can
be analysed. Based on laboratory experiments
the model has been validated and calibrated. Two
conclusions can be drawn: firstly, a simple physical
model fits well the observed performance of the
door. Secondly, the capacity is not constant but
shown to be dependent on the flow.
Laboratory experiments
For the validation and calibration of the model, data
on pedestrian behaviour is essential. To get this
data, laboratory experiments have been performed.
The influence on the system performance was
considered by systematically changing the
experimental variables: initial revolving door speed,
flow composition, obstacles and walking direction.
By means of software that can recognize and follow
the different coloured caps, pedestrians inside the
walking area are automatically tracked. In this way
trajectories are gathered containing microscopic
walking characteristics of all observed pedestrians
like speeds, accelerations and headways.
The video images of the revolving door are used to
gather information concerning segment occupancy
and the actual revolving door speed due to
breakdowns, caused by pedestrians activating the
safety sensors.
Analysis
To analyse the performance of the different
scenarios, arrival-departure curves are made,
describing the in and outflow from the walking area.
This gives a first impression of travel times and
travel time losses.
By slanting the curves, information concerning
the capacity of the door and intensities of the
flow become visible. The derivative of the slanted
departure curve describes the throughput of
the entrance. Kinks in the curves reveal that the
capacity of a revolving door is not a constant
value. In other words, revolving doors do interact
with pedestrian behaviour, because of the safety
sensors. In order to describe the interaction
between pedestrians and revolving door, a logistic
relation was found between the number of
pedestrians in the walking area and the speed of the
revolving door.
Vrotation = Vmin + (Vmax - Vmin) * (1 / (1 + exp((-
Nped + mu) / s)))
Results
After the implementation of the behavioural
parameters and relations, the interaction can be
simulated. One of the means by which entrances
can be assessed is the level-of-service plot.
Student: R. Landman
Committee: Prof.dr.ir. P.H.L. Bovy, Prof.dr.ir. S.P. Hoogendoorn, Ir. P. Wiggenraad, Dr.ir. W. Daamen,
Dr.ir. S. Silvester(Industrial Design, DDI), H. v. Wijngaarden (Boon Edam Nederland B.V.)
For more information please contact the department of Transport & Planning: (+31) 15 2781681
Transport & Planning�0 0307
Resource Engineering �10307
Applied Earth Sciences Theses
Resource Engineering
Resource Engineering�2 0307
The recyclability of ultra light car designs
European Union legislation (Directive 2000/53/
EC) introduces high recycling targets (95% reuse
and recovery plus 85% reuse and recycling in
2015) on automotive industry especially car
recyclers. For that reason automotive engineers
and environmental specialists are looking for
technological solutions to fulfill recycling targets.
It became clear that automotive plastic recycling
need to be investigated to find out new technologies
where as much as possible different plastics can be
recovered and therefore increase total car recycling
rate (if possible). Plastics and composites applied
in a car and expanding car recycling model with
new recycling options where exergy analysis can be
calculated was the subjects in this thesis work.
Next aim of this thesis was to minimize recycling
losses occurring in car recycling system during
metallurgical processing of metals by applying
exergy concept (Chapter 6) as new tool which can
be used in design phase to avoid incompatible
material combination according to thermodynamic
constraints crucial for metallurgical treatment of
car scrap. Car recycling system was discussed not
only due to recoveries of parts or materials using
car recycling model (M.A. Reuter et al. 2006) but
also due to exergy concept and its application to
calculate quality losses within the system. Exergy
concept application within all end-of-life recycling
system was a main objective in this thesis work.
It was considered due to metallurgical processes,
physical separation unit operations and plastic
recycling options.
All objectives were related to recyclability of future
car designs and use of exergy concept and exergy
analysis to fully describe car recycling as a dynamic
system. By applying exergy concept to each unit
operation existing in one of five main parts of a
flowsheet of the recycling system optimization
model (M.A. Reuter et al. 2006) it is possible
to perform exergy balance over one of the five
main parts. At the end general exergy losses over
whole car recycling system can be calculated. This
approach allows identifying and quantifying quality
losses in the system what became crucial to truly
understand car recycling system and improve future
ultra light car designs from recycling point of view.
Student: M. Gadziala
Supervisors: Prof.dr. M.A. Reuter, Dr.ir. A. van Schaik
For further information about this master theses report you can contact the faculty of Resource Engineering: + 31 15 27 81328
Petroleum Engineering and Geosciences ��0307
Petroleum Engineering and Geosciences
Applied Earth Sciences Theses
Petroleum Engineering and Geosciences�� 0307
Using Real Data to test Reservoir Model Updating with the Ensemble Kalman Filter
On average only one third of the oil in a reservoir
is recovered, the majority is left behind in the
subsurface. A promising method for increasing the
recovery from a reservoir is by applying a closed-
loop reservoir management strategy [13]. This
strategy uses an optimisation procedure and a
model updating procedure (updating the reservoir
model on the basis of measurements to improve its
predictive capacity).
In previous research the Ensemble Kalman Filter, a
model updating method, is used to update reservoir
models on the basis of synthetic data. The objective
of this research is to assess the performance of the
Ensemble Kalman Filter when it is used for reservoir
model updating on the basis of real production
data. The source of this real data is the X field. In
this field three out of four wells are equipped with
permanent downhole pressure gauges. The X field
data includes well tests, interference tests and
production log tests.
Specific goals are: to identify what kind of
performance can be expected based on the
theoretical formulation of the EnKF, to identify
what preparation the data and the reservoir model
require before it can be used in a data assimilation
experiment, to identify what settings and choices
are critical in a data assimilation experiment with
the EnKF and to identify problem areas and to come
up with possible solutions.
In this research two experiments are conducted in
which the EnKF is used to update reservoir models
on the basis of real data. Based on the procedure
of setting up these experiments and on the results
that were generated, conclusions on the goals and
objective of this research are formulated.
The main conclusion is that updating reservoir
models with the EnKF on the basis of real data can
improve the match of the model to the historical
production data. Updating the skin for every
interval while assimilating well test and production
log test data is an example of a case where the
EnKF perform well. When too many parameters are
updated the performance of the EnKF weakens due
to poor statistics from the ensemble. An example
is updating the permeability in every gridblock in
addition to the skin.
The definitions of the initial ensemble and of the
output uncertainty are critical in the set up of the
experiments. The definition of the initial ensemble
includes the choices of the parameters to update,
their range of uncertainty and the number of
ensemble members. The output uncertainty is a new
defined parameter in the EnKF that combines the
effect of the measurement error, the model error
and the non-linear terms in the relation between
model parameters and measurements.
Reducing the model error in the prior model by
including more physics and by modelling in more
detail will result in a different and likely better
parameter update.
The recommendations for further research are to
look for techniques of improving the quality of the
initial ensemble and to look for ways of reducing
(the effect of) non-linearity in the relation between
a model parameter and a measurement.
Student: H.J. de Boer
Supervisor: Prof.dr.ir. J.D. Jansen
For further information please contact the secretary of the section Petroleum Engineering: (+31) 15 2781328
Petroleum Engineering and Geosciences ��0307
Sediment Mass Balance Study of the late-Holocene Prodelta on the Northern Adriatic Shelf
The late Holocene stratigraphic record in the
Adriatic Basin developed during a relatively stable
highstand of the sea level. Among the highstand
deposits, preserved in the stratigraphic record, are
the modern Po delta and an elongated prodelta
on the Adriatic shelf. The base of these deposits is
dated at 5.500 years BP.
This study demonstrates a stochastic simulation that
derives sediment mass estimates from seismic travel
time data of the prodelta. The simulation shows
that data density and porosity are the main factors
contributing to uncertainty in the estimates.
This study shows a match between the mass of the
stratigraphic record and calculated sediment flux
into the basin. Sediment flux simulations of rivers,
draining Alpine and Apennine source areas, result
in an estimated 3.2 x 105 Mt. (with uncertainty, σ =
0.64 x 105 Mt.) of sediment delivered to the Adriatic
Basin for the past 5.500 years. The mass of the
prodelta is estimated at 2.0 x 105 Mt. (σ = 0.1441 x
105 Mt.) and the calculated mass of the Po delta is
0.7 x 105 Mt. (σ = 0.1441 x 105 Mt.)
Within the range of uncertainties, the sediment
supply matches the mass of the prodelta and Po
delta. This match implies that for the past 5.500
years, virtually all of the delivered sediments are
preserved in the stratigraphic record. The Adriatic
Basin can therefore be considered as a semi-
enclosed basin.
Student: W. Bron
Supervisors: Dr. G.J. Weltje, Drs. M. Brommer
For further information please contact the secretary of the section Reservoir Geology: (+31) 15 2781328
Petroleum Engineering and Geosciences�� 0307
An Integrated Study into the Reservoir Characteristics of Miocene Mangrove Deposits of Mallorca
Several oil reservoirs around the world are
producing from carbonate mangrove deposits.
Little previous research has been undertaken on
fossil mangroves, especially regarding their lateral
heterogeneity, structure, permeability and porosity.
This has resulted in a relatively poor understanding
of reservoir mechanisms and consequent reservoir
performance of such reservoirs. This integrated
study on outcropping mangrove deposits provides
insight into the properties of mangrove carbonate
reservoirs.
A series of Miocene carbonate outcrops along
the south eastern coast of Mallorca include fossil
mangrove deposits. These rooted intervals are
part of the Santanyi Limestone and subject of this
integrated study. First, a literature study was done
on the geology of Mallorca. This was followed by
a literature study on mangrove environments in
order to understand the depositional environment
of the Santanyi Limestone and its resulting specific
reservoir characteristics.
Three weeks of fieldwork were undertaken during
which sedimentological and petrographical data
were collected from 12 logged outcrops in order
to examine petrophysical properties and lateral
heterogeneities. Rock samples were taken and were
analysed to elucidate their porosity, permeability
and petrophysic characteristics. From these data, a
sedimentological model was established.
The outcrop data were used as a framework to build
a three-dimensional static reservoir model using the
software package Petrel. Rock properties measured
from the rock samples were used to populate the
facies model with porosity and permeability data.
The Petrel model was then imported into Eclipse in
order to make a dynamic model. In this software
package several well placement scenarios were
simulated as if the Santanyi Limestone and
surrounding facies would have been a reservoir.
The main outcome of the study was that the low
horizontal and high vertical permeabilities of the
mangrove facies strongly favour field development
using horizontal wells.
Student: H. Coppes
Supervisors: Dr. J. Noad, Prof.dr. S.M. Luthi
For further information please contact the secretary of the section Reservoir Geology: (+31) 15 2781328
Petroleum Engineering and Geosciences �70307
Enhanced mass transfer of CO2 gas into water by density driven natural convection
Global warming has increased interest in
quantification of the dissolution of CO2 in (sub)-
surface water. In all cases of practical interest CO2
is present above the water. Dissolution of CO2
into water causes a density increase, with respect
to pure water. This density effect causes natural
convection, which enhances the mass transfer rate
across the interface. To our knowledge, only a few
studies have been carried out to experimentally
investigate this mechanism.
This article describes, a series of experiments done
in a cylindrical PVT-cell, where an over pressured
volume of CO2 gas was brought into contact with
a column of distilled water. The Rayleigh number
is of the order of one million whereas the Schmidt
number is of the order of five hundred. The results
show that the mass transfer rate across the
interface is much faster than predicted by Fick’s
second law. This mass transfer rate turned out to
increase with increasing gas pressure.
A theoretical interpretation of the observed effects
has been proposed, based on diffusion and
natural convection phenomena. The ensuing
equations have been solved for the steady state case.
Convection effects are no longer dominant in the
long term and the mass transfer rate becomes a
diffusion process. The experimental data allow the
determination of the diffusion coefficient. Its value
agrees with values presented in the literature.
Student: H.A. Delil
Supervisors: Dr. J. Bruining
For further information please contact the secretary of the section Petroleum Engineering: (+31) 15 2781328
Petroleum Engineering and Geosciences�� 0307
Simultaneous Measurements of Capillary Pressure and Dielectric Constant in Porous Media from �0 Hz to � MHz
An experimental procedure is presented with which
the capillary pressure (P¬¬c) and the dielectric
constant (ε) of a porous medium can be measured
simultaneously. The equipment is designed to
conduct measurements under constant pressures
(up to 20 bar) and constant temperature conditions
for the unconsolidated sand- water-gas (N2 and
CO2) system. Pc is defined as the averaged
pressure difference between the bulk gas and
water pressures within the system and ε is obtained
utilizing an impedance tool. The tool design consists
of a porous medium sample holder acting as a
parallel plate capacitor. A precision component
analyzer measures the complex impedance and
phase angle as function of frequency during
displacement processes and its value is directly
related to the effective dielectric constant of
the mixture of grains, water and gas phase.
We have validated the set-up for reproducible
capillary pressure curves with the different gases
injected. Moreover, the accuracy of the dielectric
measurements is higher than 96% using calibration
substances with known dielectric properties. The
aim of this study is to get an understanding of the
hysteresis in Pc and ε between the drainage and
imbibition processes in terms of phase distributions,
frequency dependence, and interfacial area factors
which may exert influence on it. We propose that
there is a direct relationship between the interfacial
interactions within the systems and ε. The capillary
pressure and the dielectric constant are functions
of the water saturation therefore there is a direct
relation between both physical properties and their
hysteretic behavior is the evidence of this.
Student: L.M. Moreno Tirado
Supervisors: Dr. J. Bruining, Dr.ir. E.C. Slob, Ir. W.J. Plug
For further information please contact the secretary of the section Petroleum Engineering: (+31) 15 2781328
Petroleum Engineering and Geosciences ��0307
Recovery Enhancement by Injection of Low Quality Steam with Volatile Oil
It is generally expected that consideration of non-
conventional oil resources and new technologies
in exploitation and exploration will enhance the
future oil reserves. Different sources quote different
values for these increased reserves. However,
it is generally agreed that the same order of
recoverable heavy oil exists as remaining reserves
of conventional oil.
Several methods are used in the production of
heavy oil, such as hydrocarbon gas injection and
thermal methods, e.g., hot water, steam and in-situ
combustion. Steam injection into heavy oils has
been applied over the last 40 years; however, the
mechanisms and effectiveness of this process are
poorly understood. It is possible to improve the
efficiency of the steam recovery process by adding
distillable oil to the injected steam and tested in the
field successfully in 2005.
In this study, steam drive recoveries of oil with
and without volatile oil (alkanes) are compared.
As opposed to previous studies where high quality
steam is used, this study is focused on the low
quality steam injection. The most interesting result
of this study is that the recovery enhancement due
to volatile oil, which is clear for high quality steam,
is much less for low quality steam. For the modeling
of the experiments the STARS simulator is used.
Student: M.N. Guy
Supervisors: Dr. J. Bruining
For further information please contact the secretary of the section Petroleum Engineering: (+31) 15 2781328
Petroleum Engineering and Geosciences70 0307
Stress estimation and gas detection from seismic reflection coefficients at a non-welded interface
We investigate the possibility to estimate effective
stress and detect gas from seismic reflection
coefficients at a non-welded interface. The
interface is represented by a planar distribution
of penny-shaped cracks, resulting in a linear slip
boundary condition with a normal and a tangential
compliance. These compliances change as the
planar crack density decreases exponentially (due
to crack closure) with increasing effective stress.
The media above and below the interface are
vertical transverse isotropic (due to horizontal
inclusions, fractures or fine layering) and their
elastic coefficients are taken from empirical data
(dependent on effective stress and pore infill). We
compute quasi-PP, -SvP, -SvSv and -PSv reflection
coefficients for several realistic scenarios with
varying angles of incidence at different stress
states with different pore infill (brine or gas). Both
effective stress and pore infill affect the model in
two ways: a) through the elastic coefficients of the
upper and lower media, and b) through the interface
compliances. Both effects have significant impact
on the computed reflection coefficients and their
interplay can easily cause misinterpretations. We
show how the slip induced effects can approximately
be separated by taking the imaginary part of the
reflection coefficients. Alternatively, taking the real
part of reflection coefficients can correct for slip
effects in AVO. We invert the synthetic reflection
coefficient data as generated by the forward model
for the vertical effective stress component and
for the compliance ratio, being an indicator for
crack infill properties. Our analysis reveals that
the inversion requires a priori measurements of
the vertical wave velocities at each stress state,
an estimation of anisotropy and some (theoretical
or empirical) relation between fracture compliance
and effective stress. We introduce error bars in the
estimated stress considering errors in the input
wave velocities. Our inversion results demonstrate
that we are able to estimate both compliance ratio
and effective stress, assuming that an accurate
stress-compliance relation is available. Both
estimations yield best results at normal incidence,
where the inversion can be approximated by a
simple linear expression, relating the imaginary part
of the AVO intercept directly to the compliance.
Realistic changes in crack infill have more influence
than realistic changes in effective stress; thus the
suggested approach has more potential for gas
detection than for stress estimation.
Student: J. van der Neut
Supervisors: prof. dr. ir. C.P.A. Wapenaar and prof. M.K. Sen, PhD
For further information please contact the secretary of the section Applied Geophysics and Petrophysics: (+31) 15 2781328
Petroleum Engineering and Geosciences 710307
Produced Water Re-InjectionExperimental Investigation of the Effect of Flow Rate on Filter Cake Build-up in Fractures
Attempt has been made by means of laboratory
investigation to quantify the effect of standard flow
parameters on the formation of external filter cake
in water-injection fractures. The approach was to
simulate three flow regimes in fractures during
produced water re-injection. The simulated zones
are the entrance to the fracture adjacent to the
wellbore; a region in between the wellbore and the
fracture tip; and finally the region at the fracture tip
where leak-off is least. All the parameters of interest
were kept more or less constant except for the
permeate and crossflow velocity that were varied
to see what the impact would be on the process of
cake formation.
Five experiments were conducted with different
combinations of crossflow and permeate velocity.
Results indicate that at regions in the fracture close
to the wellbore, decrease in injectivity could be
dominated by external filter cake formation. The
low permeate rate relative to the crossflow flow
rate ensures that formation damage is gradual. A
comparison of the result of the last two experiments
underscores the relevance of crossflow flow on
external cake formation and the associated erosion.
Based on the experimental conditions, it was
concluded that a relatively high crossflow flow rate
will result in accelerated external filter cake erosion.
Student: C.C. Obeta
Supervisors: Prof.dr. P.K. Currie, Ir. A.H. de Zwart
For further information please contact the secretary of the section Petroleum Engineering: (31) 15 2781328
Petroleum Engineering and Geosciences72 0307
Modeling sediment storage in a tidal dominated delta, the Fly River, Papua New Guinea
Tide dominated deltas are not studied so
extensively as river-dominated and wave-dominated
deltas. Through modeling of a tide dominated delta,
insight will be achieved about the influences of tidal
and fluvial processes on sediment transport and
deposition in these tide dominated environments.
Process based modeling of tide dominated deposits
makes it possible to distinguish the controls of
tidal depositional processes on the depositional
architecture in terms of reservoir properties. Due
to the fact that tide-dominated deposits are very
heterogeneous, process based modeling of these
deposits could support high resolution correlation
and delineation of reservoir flow units.
The objective of this research was to model the
sediment storage in the tide dominated delta and to
study morphological changes in the delta at annual
conditions and due to variable river discharge and
sediment load.
The research method involves process based
modeling with the Delft3D modeling software.
Here several scenarios have been executed while
varying parameters, which control river and tidal
influences. The simulation results were used to
study the sedimentation pattern development and
morphological changes within a tide dominated
delta. This research uses the Fly delta, in Papua
New Guinea as case study area, with the focus
on the area between the apex and the mouth
of the delta. Depth average velocity and yearly
sedimentation rates were used as criteria to select
the most suitable scaled sediment load scenario
for the simulations. Bed level study shows that the
sedimentation rates varies within the delta, with
highest sedimentation in the mid-delta area, and
lowest at the channel mouth. Decrease in sediment
deposition during low flow conditions was relatively
larger, while the high flow conditions causes a
smaller increase in sediment deposition. The El
Niño extreme low flow scenario shows a predictable
result of only sediment deposition at the delta
apex, due to low velocity and low river discharge,
sediment has not been transported towards
downstream area. With tide and without tide
scenarios, resulted into differences in sedimentation
patterns, based on grainsize characteristics. The
morphological development shows that changes
around a specific island has resulted scouring of the
channel bottom at tidal conditions and deposition
of coarse grained sediments along the sides of
the channel. Further it was distinguished that the
highest sand accumulation has been occurred at
the upstream part of the island and the highest clay
sedimentation at the downstream part of the island.
This characterizes an important difference between
more fluvial-dominated deltas and tide-dominated
deltas. The main problem during modeling was
related to the scaling of the model according to
the Fly delta geometry and flow conditions. This
was caused by the Delft3D model limitations, for
size and resolution of the model grid. Overall we
conclude that longer-term simulations create the
possibility to study the morphological development
within the delta in more detail.
Student: N.R. Sheombarsing
Supervisors: Prof.dr. S.B. Kroonenberg, Dr.ir. I. Overeem, Dr. J. Storms, Dr. G.J. Weltje
For further information please contact the secretary of the section Applied Geology: (+31) 15 2781328
Engineering Geology 7�0307
Engineering Geology
Applied Earth Sciences Theses
Engineering Geology7� 0307
The investigation on the formulation of a new design code for MV-piles
This thesis investigates, whether the current
design code for MV-piles is still valid or needs to
be updated, because these days the used piles are
much larger, than the time when the current code
was formulated. In order to check if the current
code is still valid, the t-factor in the formula below
was calculated for forty-seven piles, using the
bearing capacity derived from the pile load-tests.
In which:
• Fpile = Bearing capacity
• qav = Average cone resistance over the length
where shaft resistance is mobilised
• L = The active length of the pile
• O = Circumference of the pile
• αt = coefficient for the shaft friction = 1.4 %
From the analysis of the dataset it followed that the
current design code does not fit this dataset, since
no constant value of 1.4% for the αt-factor was
found. In stead of a constant value for the αt-factor
a negative relation between the circumference and
the αt-factor found. This leads to an overestimation
for the piles with large circumferences and
thus to dangerous situations. Therefore various
modifications of the current design code where
investigated in order to give a better prediction for
also the larger piles.
The following method gave the best predictions for
the dataset:
This formula differs from the old one on the
following two aspects:
• CV = Calculation value for the circumference of
the pile
• W = width of the pile
• H = height of the pile
• t = 2.5 %
The final conclusion of this thesis is to use the
lowest value for the bearing capacity that is
predicted with either the formula above or the
existing formula. The differences in correctly
predicted bearing capacities between both methods
where too small to replace the current formula by
the new one. But since the new formula does not
overpredict the bearing capacity of the larger piles,
this will lead to safer design of MV-piles.
Student: R.L. van Hof
Supervisors: Prof.ir. A.F. van Tol
For further information please contact the secretary of the section Engineering Geology: (+31) 15 2781328
FPile
qcav
L⋅ CV⋅ α t⋅ qcav
L⋅ 2 W⋅ 0.38 H⋅+( )⋅ 0.025⋅
FPile
qcav
L⋅ O⋅ α t⋅
Engineering Geology 7�0307
Influence of spatial correlation length on predicted settlements of a road embankment
In the common geotechnical engineering practice
the shallow subsurface is often modelled in several
layers by assigning to each of these average
material properties. However the reality is quite
different. The soil properties are characterized
by spatial variability within each homogeneous
lithological unit. This variability can be taken into
account by incorporating the value of the spatial
correlation length on the simulation results. The
spatial correlation length describes the distance
over which a random variable tends to be correlated
in the underlying Gaussian field. A large value of
spatial correlation length describes a smoothly
varying field, while a small value implies a ragged
field.
The objectives of this Graduation project are to
extract the value of the spatial correlation length
for a specific case study and to investigate its
influence in the settlement calculations of a road
embankment. The study area deals with the A2
highway connecting Amsterdam and Utrecht. A
representative section of 8,5Km was analyzed and
data were gathered from 248 Cone Penetration
Tests, 35 Boreholes and a Geophysical survey of
2,5Km length (Consoli Test). The project consists
of 4 major sections. Firstly the methodology used
for the processing of the data set is given (CPT,
Borelogs and Geophysical outcomes). In the second
section a literature review is performed and three
different techniques for the quantification of the
spatial variability are presented (Moving Average
Window Technique, Autocorrelation Function, and
Semivariogram Function). Based on the evaluation
of these techniques the Semivariogram technique
was the one selected for the extraction of the
spatial correlation length. By implementing the
semivariogram function in every lithological unit
50 different three dimensional lithological maps of
the Holocene deposits were made. By importing
that lithological information in the settlements
calculations (Finite Element Method) 300 hundred
simulations were performed along and across the
road axis for three representative locations. The
methodology of creating a lithological random
field is followed. Furthermore the outcomes of
the realization technique are compared with the
outcomes of the classical approach which is used in
the common Civil/Geotechnical Engineering practice.
(This work was supported by TUDelft and TNO-
NITG/Nederland’s Institute for Applied Geosciences)
Student: S. Kalamatas
Supervisors: Prof.dr.ir. F. Molenkamp, Dr.ir. D.J.M. Ngan Tillard
For further information please contact the secretary of the section Engineering Geology: (+31) 15 2781328
Engineering Geology7� 0307
Plaxis Soft Soil Creep: de toepassing van een isotroop kruipmodel op de anisotrope ondergrond
In met name West-Nederland bestaat de ondergrond
voornamelijk uit slappe klei- en veenlagen. Bij het
aanbrengen van een maaiveld belasting zullen er in
deze slappe grondsoorten verticale en horizontale
vervormingen optreden. Voor het berekenen
van de vervormingen zijn verschillende modellen
beschikbaar. Het 3-dimensionale SSC model is
echter het eerste materiaalmodel in Plaxis waarin
kruip is geïntroduceerd. Dit model is gebaseerd op
het 1-dimensionale a,b,c-Isotachenmodel.
Uit praktijk ervaring blijkt dat bij de aanbevolen
omrekening van de a,b,c-Isotachen in SSC
samendrukkingsparameters de zetting van het a,b,c-
Isotachenmodel niet in overeenstemming is met de
zetting volgend uit een 1D SSC berekening. Dit is de
belangrijkste rede dat dit onderzoek is opgesteld.
Er is onderzoek gedaan naar de oorzaak van dit
verschil, hetgeen vervolgens is gevalideerd a.d.h.v.
een samendrukkingsproef en een case. Verder is
het SSC model beschreven en gevalideerd aan 2D
vervormingen. Het algemene doel van dit onderzoek
is het verbeteren van de praktische toepasbaarheid
van het SSC model.
Uit modeltechnisch onderzoek blijkt dat de zetting
van het SSC- en a,b,c-Isotachenmodel bij een
1D berekening exact met elkaar overeen moeten
komen onder de voorwaarde dat de verhouding
horizontale / verticale spanning constant is. Bij een
niet constante verhouding ontstaan er verschillen
die normaliter te verwaarlozen zijn. De simulatie
van een samendrukkingsproef bevestigt dit, de
No-Recess case echter niet. De oorzaak hiervan is
het op een andere wijze in rekening brengen van
onderwaterzakken (bij de samendrukkingsproef
speelt onderwaterzakken geen rol). In Plaxis (SSC)
is onderwaterzakken correct geïmplementeerd,
MSettle (a,b,c-Isotachenmodel) benadert
onderwaterzakken. De verschillen tussen de
modellen ontstaan dus t.g.v. de implementatie in
verschillende rekenprogramma’s.
Bij het beschrijven van het SSC model voor
2D vervormingen blijkt de K0nc-afhankelijke
M parameter een belangrijke modelparameter.
Aandacht is daarom besteed aan de bepaling
van deze parameter. Een K0-C.R.S. proef geeft
realistischere waarden voor M(K0nc) dan de
vuistregel van Jaky. Verder heeft de geometriekeuze
(axisymmetrisch of plane strain) en de bepaling
van de doorlatendheid significante invloed op de
resultaten.
Bij de No-Recess case is de anisotrope ondergrond
gemodelleerd met het isotrope SSC model. De
gevonden horizontale vervormingen sluiten bij
een juiste parameter- (doorlatendheid en M) en
geometriekeuze (axisymmetrisch of plane strain)
goed aan bij de gemeten vervormingen. Voor
de zettingen geldt dit echter niet. Het model
overschat de zettingen vooral in het begin van de
ophoogfase. Niettemin lijkt het model de horizontale
en verticale kruip én horizontale / verticale
vervormingsverhouding goed in te schatten. Bij de
gekozen parameters is de anisotrope ondergrond
daarmee goed met het isotrope SSC model te
simuleren.
Student: R. Servais
Supervisors: Prof. ir. A.F. van Tol, Ing. H.J. Everts, Dr. ir. R.B.J. Brinkgreve, Ir. H. L. Jansen
(Fugro), Ir. W.H.J. van der Velden (Fugro), Dr. ir. D. J. M. Ngan-Tillard (coördinator
Ingenieursgeologie)
For further information please contact the secretary of the section Engineering Geology: (31) 15 2781328
Offshore Engineering 770307
Offshore Engineering Theses
Offshore Engineering7� 0307
Conceptual Design of a Tension Leg Platform Optimized for the Heerema Group capabilities
In the search for offshore hydrocarbons many
platform concepts have been developed over the
years. One of those concepts is the Tension Leg
Platform (TLP), a floating platform connected to
the seabed by vertical tubulars, called tendons,
which are under permanent tension using excess
buoyancy of the platform. The three companies
within the Heerema Group have been involved in
the engineering, fabrication, transportation and/or
installation of more than 70% of all TLP projects
since the installation of the first TLP by the Semi-
Submersible Crane Vessels (SSCVs) Balder and
Hermod.
In general, two different installation methods for
TLPs can be distinguished: self-installation and
installation assisted by a crane vessel. Self-installable
TLPs are usually considered to be integrated TLPs,
i.e. the mating of the hull and the topsides has been
completed in the yard and the integrated TLP is
transported to the installation site. The impact of
stability requirements on the hulls of self-installable
TLPs during the installation can be significant and
may result in a hull design which is not optimal for
in-place conditions. By suspending the TLP in a crane
during the installation, i.e. crane-assisted installation,
the impact of the stability requirements on the hull
can be reduced and more optimised hull designs can
be achieved. As a consequence, these optimised
hull designs have insufficient stability for a freely
floating hull with integrated topsides. Therefore the
installation is split into two phases: first the hull is
installed, followed by the offshore installation of
the topsides. This leads to a considerable increase
in installation time. A combination of these two
installation methods is presented in this study as
the preferred installation method for the Heerema
Group: crane assisted installation of an integrated
TLP.
A basis of design has been developed for a TLP in
West-Africa in 500m water depth. The boundary
conditions have been based on a reference TLP in
Equatorial Guinea, an integrated TLP which has been
self-installed. Finally a conceptual design for the
Heerema Tension Leg Platform (HTLP) is presented.
The installation of HTLP has been investigated
for sea states with a probability of exceedence
around 50% in both Equatorial Guinea and Angola.
The dynamic hook load fluctuations in the cranes
have been investigated for several installation
configurations of the HTLP and the SSCV Thialf. A
dual crane installation proved to be preferable over
a single crane installation. Brinkhuis.
jpg
Both the hull and the transportation and installation
process of the HTLP have been compared to
competitive TLP designs. Compared to the reference
TLP, the hull efficiency can be increased, which can
result in a decrease in the hull mass of 11%. The
total time of transportation and installation can be
reduced by 16% compared to separate hull and
topsides installation. This can result in a reduction
of 23% on the installation and transportation costs.
For water depths ranging from 500m to 2000m the
HTLP can compete with existing TLP designs, with
respect to displacement. The influence of composite
tendons on the displacement of the HTLP has also
been investigated. For depths exceeding 1200m,
composite tendons can result in a significant
decrease of the displacement of the HTLP.
Although the conceptual design presented in this
study is by no means an optimal design for the given
environmental conditions, it does provide insight in
the potential of a TLP optimised for both in-place
conditions and the capabilities of the Heerema
Group. It is concluded that such a TLP can be
advantageous compared to competitive TLP designs
and it is recommended that more research will be
conducted in the feasibility of a Heerema Tension
Leg Platform.
Student: H.T. Brinkhuis
Sponsor: Heerema Marine Contractors
Committee: prof.ir. J. Meek, ir. G.H.G. Lagers, ir. H. Boonstra, ir. R. Zoontjes
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Offshore Engineering 7�0307
Development of the Yoke Quay Mooring Concept (YQM)Weathervaning LNG Terminal in Shallow Water
Introduction
The objective is of the thesis study was to develop
a concept design for a freely weathervaning LNG
terminal in a water depth of 16 meters, in a West-
African environment (Nigeria), which survives the
100-year conditions and which is operable up to the
1-year extreme conditions.
The terminal must be suitable for non-dedicated
LNG carriers with a mid-ship manifold and
conventional mooring line facilities. The LNG carrier
has a capacity of 135000 cubic meters. Submerged
cryogenic swivels or flexible cryogenic hoses are
not permitted in the terminal design. Proven LNG
loading arms are to be used.
In operational conditions, the relative motions
between the mid-ship manifold on the LNG carrier
and the LNG loading arms on the terminal must
remain below the allowable limits. The loads in the
mooring lines may not exceed the maximum safe
working load. In survival conditions the minimum
allowable keel clearance is 1 meter.
Yoke Quay Mooring Concept
Three terminal concepts have been developed
and analyzed using the AQWA software for
hydrodynamic calculations. The selected concept is
Yoke Quay Mooring (YQM) Concept 1 (see figure 1).
The concept consists of three main elements; the
floating quay structure, the connection method of
the quay to a fixed tower and the mooring system
for LNG carriers.
A semi-submersible structure was selected as
a quay structure. The quay has a limited width
in order to make the loading arms suitable for
operation at both sides. Eight quay designs have
been analyzed. The seventh quay design has the
best motion behavior in survival conditions and the
smallest loads in the mooring lines in operational
conditions. This quay design is shown in figure 2.
The Soft Yoke Mooring and Offloading system
(SYMO) developed by SBM for the application of
LNG offloading, was selected as the most suitable
method to moor the quay to the fixed tower. The
SYMO allows a “soft” response and consequently
the quay follows the motions of the LNG carrier.
In this way the motions of the loading arms under
operation and the loads in the mooring lines are
limited.
The solution of a side-by-side mooring arrangement
was selected to moor the LNG carrier to the quay.
No adjustments to the carriers are required.
Conclusion
The technical feasibility of the Yoke Quay Mooring
Concept has been established. However the
operability in 1-year extreme conditions is limited
in case of cross environments. The results of the
operability study will be improved by including
damping coefficients and shielding effects in the
AQWA calculations.
Student: E.W. Heerema
Sponsor: GustoMSC
Committee: prof.dr.ir. J.A. Pinkster, A. Metrikine PhD MSc, ir. G.H.G. Lagers, ir. A.J. van der Spek
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Offshore Engineering�0 0307
A Practical Assessment of Lateral Buckling Sensitivity of Subsea Pipelines
Increasing numbers of subsea pipelines are required
to operate at very high pressures and temperatures.
A subsea pipeline operated at temperatures and
pressures above ambient will expand. If the pipeline
is restrained, e.g. by soil friction, axial compressive
stresses will develop as temperatures and pressures
increase. In case these axial compressive stresses
reach a critical value and the pipeline is not buried,
they may lead to lateral movement of the pipeline.
This phenomenon is called lateral buckling and
may be a problem if the stresses and strains in
the pipeline exceed the design criteria. As a result
lateral buckling has to be considered during the
design of subsea pipelines where high pressures and
temperatures occur.
Buckling theories have produced several methods
and models to assess the susceptibility of
pipelines to lateral buckling. However, results of
these methods and models are felt to be very
conservative. If a discrepancy between theory and
reality does indeed exist, unnecessary costs deriving
from conservative designs are incurred during
construction of pipelines. The objective of this
study is to develop a tool, which is able to compare
theoretical results with actual operational data
with respect to the initiation of lateral buckling, to
confirm the theoretical discrepancy (if any) and help
to identify the causes. This tool has been called the
Buckle Indices – Method (BIM).
Based on literature studies a number of key
parameters has been identified that influence the
initiation of lateral buckling. These are: effective
axial force at which buckling occurs (Sbuckle), lateral
resistance (Rl_breakout), axial resistance (Ra_
breakout) and the actual out of straightness (O0).
All key properties of the pipeline with respect to
lateral buckling are described by the axial stiffness
(EA) and bending stiffness (EI). Combining the key
parameters with the key properties by means of
dimensional analysis, leads to four dimensionless
parameters. They are: πforce, πlateral_friction,
πaxial_friction and πOOS. These dimensionless
parameters characterise the initiation of buckling
and are called Buckle Indices.
Finite Element Modelling (FEM) has been used to
analyse the relationships between the different
Buckle Indices. This analysis demonstrated that the
force at which buckling is initiated is independent
of the axial resistance. Therefore the initiation
of buckling can be described by means of three
Buckle Indices. Combining these Buckle Indices
in a graph enables identification of the following
areas : no buckling, buckling possible and buckling
taking place. The combination of Buckle Indices has
been chosen such that the area “buckling possible”
is reduced to a minimum. This has been done by
plotting πforce / πlateral_friction as a function of
πOOS.
The operational data of the pipelines used in this
study have been provided by NAM or Shell Expro.
Predetermined criteria have been used to select
pipelines which were thought to be most susceptible
to lateral buckling. From this selection of eight
pipelines, only one was reported to have actually
buckled laterally. Part of the operational data needed
to calculate the input parameters of the BIM was not
available. Therefore the results of the BIM based on
operational data, should be treated with care.
By comparing the results of the BIM based on FEM
and based on operational data, a discrepancy has
been shown, indicating that FEM is conservative.
Reasons for this may be an incomplete soil model
in FEM, errors in the results of the BIM based on
operational data due to lack of accurate actual soil
data or an overestimation of the actual effective
axial force in a pipeline due to free spanning.
Student: M. van Heel
Sponsor: Shell Int. Exploration & Production
Committee: prof.ir. J. Meek, dr.ir. S. van Baars, ir. G.H.G. Lagers, ir. S. Draaisma
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Offshore Engineering �10307
Feasibility study of the use of the Ampelmann in Shell
For the winter production of hydrocarbons at sub-
arctic Sakhalin Island (Russia), Shell has applied
a dedicated vertical chute system for the use as
emergency evacuation method to escape directly
from the top deck of the offshore installations down
to the deck of an Ice Breaking Standby Vessel. This
chute, named Skyscape (left figure), is a set of nets
and rings that folds-up at the deck of the vessel
to compensate for the wave-induced motions of
the vessel. By the nets, the personnel encounter a
decelerated fall to the vessel underneath.
In this thesis study, the reliability of this Skyscape
is investigated with respect to several (sub arctic)
environmental conditions: swell-in-ice events, wind
affecting the alignment of the chute, deviating
ice-drift directions and the formation of ice-rubble
around the offshore structure. The findings of
this reliability review is that the environmental
conditions will limit the safe operation of this chute
significantly, resulting in an unavailable evacuation
method for over 12 days per winter.
To improve the availability of this Skyscape (concept
1), the use of an Ampelmann system in between the
vessel and the chute is studied. By canceling out all
wave-induced motions of the vessel, the Ampelmann
eliminates the risks encountered by the hazardous
folding characteristics of the Skyscape chute (concept
2). To prevent misalignment of the chute, a guidance
line in between the vessel and the suspension point
of the chute is suggested (concept 3).
With respect
to deviating
ice-drift
directions and
the presence
of ice-rubble
formations
around the
legs, the
chute is finally
substituted by
a suspended
gangway design
(concept 4:
see figure
above). This
gangway design
leads over
the ice-rubble
formations and
can be directed into any likely wake direction behind
the platform. As a result, the use of this suspended
gangway design in combination with an Ampelmann
system improves the workability from 12 days lost
due to environmental conditions (Skyscape) down
to only 2 days of unavailability (extreme swell in ice
conditions) per winter.
In order to compare the effectiveness of all
concepts, the risks and the related costs of each
concept are assessed and compared in an ALARP
demonstration. As a systematical approach for this
demonstration, the EER-triangle suggested by the
ISO standards has been applied. In this triangular
approach, the ‘hardware integrity’, ‘procedures
and controls’ and the ‘personnel competences’ of
each concept are valued. It is concluded by this
ALARP demonstration that the suspended gangway,
supported by the Ampelmann, demonstrates to be
ALARP for sub arctic conditions: concept 4 meets
the lowest risks that are reasonably practicable in
terms of costs.
Student: J.M.L. Koch
Sponsor: Shell E&P
Committee: prof.ir. J. Meek, ir. G.H.G. Lagers, dr. ir. J. van der Tempel, ir. C. Brummelkamp
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Offshore Engineering�2 0307
Fsru processes
The liquefaction and regasification terminals for
natural gas are traditionally located onshore.
With the increasing demand for natural gas, new
locations could be located offshore for various
reasons (e.g. safety, financial). One alternative of an
onshore liquefied natural gas (LNG) import terminal
is called a Floating Storage Regasification Unit
(FSRU) and is a permanently moored offshore LNG
import terminal.
The two main activities on board an FSRU are
storage and vaporization of LNG. These activities
introduce the following challenges:
Boil-off gas (BOG) has to be removed from the
cargo storage tanks in order to avoid overpressure.
Except for in emergency situations, the BOG should
not be wasted for environmental and commercial
reasons.
An FSRU has to
reliably vaporize
LNG at a constant
rate after it has
been boosted to
send-out pressure.
Boil-off gas handling systems
Three different methods exist to handle the BOG
that is in excess of the fuel gas requirement: (i) Mix
the BOG with regasified send-out gas; (ii) Mix the
BOG with subcooled LNG in order to dissolve the
gas into the liquid phase; (iii) Reliquefy the BOG
by cooling it down and send it back into the cargo
tanks.
This study has identified the use of jet pumps as
the ‘best value’ BOG management solution. The jet
pump system does not require any compression of
the BOG, which makes it attractive in view of the
safety, environmental impact and operating costs.
The main disadvantage is that the solution is not
yet proven technology and that a pilot plant will be
required to test and validate its capability to deal
with BOG.
Regasification systems
The vaporization of LNG requires a substantial
amount of heat that can be withdrawn from three
main sources (directly or indirectly): (i) Combustion;
(ii) Sea water; (iii) Air.
In the best value system natural draught ambient
air vaporizers (AAV) use air to vaporize LNG. They
can provide a large percentage of the required heat
without power consumption. This aspect makes the
AAV attractive in view of the safety, environmental
impact and operating costs.
AAV’s have been used before in small scale
applications, but never in the quantities required
on an FSRU or grouped together as on the deck
of vessel. Some additional source of heat will be
required to bring the NG up to the required send-
out temperature.
Conclusions & Recommendations
The preferred solution will depend on project
specific data. The study report presents an overview
of the feasible options and discusses the main
features, pros and cons for different scenarios. (See
chapter 2 for the overview.)
Each FSRU project should start with an identification
of possible alternatives in order to continue with a
systematic comparison, in which the project specific
data are taken into consideration to select the
preferred solution(s).
The conclusions and recommendations of the study
report can be used in the initial phase of FSRU
design development in order to aid the selection
process for the preferred BOG management and
vaporization systems.
Student: R.C.J. Lagers
Sponsor: SBM Inc
Committee: prof.ir. J. Meek, prof.dr. J.A. Moulijn, dr.ir. S.A. Miedema, ir. K. Hoving, ir. M. Ubas
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Offshore Engineering ��0307
Structural analysis of impact on guides and bumpers
To provide for accurate positioning, during offshore
lift-operations, generally use is being made of guides
on the receiving support structure and bumpers on the
topsides that is being installed. During a certain stage
of the lift process, in which initial contact between
topside and support structure takes place, impact
loads are a common phenomenon, which makes this
stage the most critical with respect to damage to both
structures.
Therefore an analysis has been performed in order
to asses the risk of possible impact loads and the
magnitude thereof. Normally this is done with a
multibody dynamics program (LiFSiM) which can
accurately predict motions of a floating support
structure and of a crane vessel with a deck hanging
from its crane(s). The modeling of the contact stage
between guides and bumpers during impact may
be adequate to derive realistic motion behaviour
of the system but is considered inadequate for the
assessment of the magnitude of impact forces.
Furthermore, modeling of the impact process itself
is completely dependent on the choices made by the
responsible engineer. The linear single-spring model
which is generally being used seems not sophisticated
enough to fully describe the structural behaviour
of “guide & bumper” during impact. Refining this
(structural) model, describing the contact stage, is
expected to be necessary to achieve more accurate
predictions of the magnitude of impact loads.
Based on a finite element model of a typical guide and
bumper design which was previously used by HMC
on an offshore removal project, a different and more
accurate contact-stage model has been created. This
was done by analysing the FEM model with the explicit
time domain solver LS-DYNA. The resulting contact-
model was then incorporated in the user-defined part
of LiFSiM and a comparison was made with the results
obtained with a contact-model constructed in the
conventional way. The LS-Dyna analyses learned that
the impact velocity hardly has any influence on the
development of the impact force, only on the eventual
maximum magnitude of the impact force; the higher
the velocity, the higher the maximum impact force
will be. The results also showed that during an impact
no velocity dependent viscous damping is present,
but only elastic-plastic damping through plastic
deformation. Implementing both contact-models in a
LiFSiM model resulted in simulations which revealed
that the conventional contact model resulted in highly
unstable simulations, whereas the new contact-model
resulted in more stable simulations. However, both
types of LiFSiM simulations required an extra velocity
dependent viscous damping force in the contact
model, in order to be able to complete simulations
without them becoming numerically unstable.
As a result of uncertainties introduced when
considering damping as a part of both contact-
models, two more LiFSiM simulations (2BODY), with
and without damping, have been conducted. Now
a direct comparison could be made between the
performance of LiFSiM and LS-Dyna. This learned that
LiFSiM correctly calculates the impact forces when
no damping is applied and can underestimate the
impact force and displacement when (for numerical
reasons) extra damping is applied. Thus, at this point
a relatively simple 2BODY impact analysis can be
performed, but a more complex LiFSiM simulation can
not yet be conducted. It can therefore be concluded
that a new analysis method to calculate impact loads
is not yet available. This research also showed that
guides & bumpers designed on the basis of standard
guidelines appear to be very stiff and only utilize their
elastic capacity, which results in relatively high impact
loads. Less stiff guide design and allowing for plastic
deformations can lead to lower impact loads and
subsequently more cost efficient solutions.
Student: P.J. Maas
Sponsor: Heerema Marine Contractors
Committee: prof.ir. J. Meek, ir. G.H.G. Lagers, ir. G. Hommel, ir. A.W. Vredeveldt, ir. R. Zoontjes
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Offshore Engineering�� 0307
Basic design of hydrate mining equipment
The growing demand for oil and gas leads to an
increase of exploration and exploitation as well
as to research in alternative ways of hydrocarbon
production out of natural resources. The predictions
of huge amounts of gas hydrate dispersed in artic
and ocean sediments make this a potential future
energy source. Recent studies and experiments
to retrieve gas from gas hydrates focussed on
depressurization and/or thermal stimulation of
the hydrate bearing sediments. The drawbacks of
these methods are low reservoir permeability and
dissociation of gas hydrates during production.
This causes production rates to stagnate and
induces bore hole instability. A combination of
excavation and pressurization during the production
of hydrate bearing sediments is proposed to avoid
these problems. The generation, basic design and
challenges of gas hydrate mining equipment are
presented in this study.
The generation of hydrate mining concept designs
has been executed by using a morphological
matrix. The most promising concept design has
been worked out in more detail. A computational
simulation and analysis of the selected concept
design has been executed for various reservoir
conditions. Based on different production and
reservoir scenarios, energetic and economic
analyses were executed to provide first insight in
the feasibility of hydrate mining.
This concept design of a hydrate mining tool
exists of two rotating cutterarms. The mining
tool is lowered from an ordinary drill rig by a drill
string until it hits the ocean floor. From there, it
bores itself to the hydrate bearing sediment and
production is started. Upon termination of the
production, the mining tool is able to excavate itself
out of the ocean floor from where it is lifted to the
drill rig.
The proposed design of hydrate mining equipment
is driven and controlled by a pressurized fluid. The
fluid is circulated through the mining equipment
by a pressure difference over the injection and
export means of the mining tool. The driving of
the cutterarms is achieved by a set of Positive
Displacement Motors (PDM), The PDM’s are driven
by a pressure difference over their inflow and
outflow channels. Pressure release valves control
the production rate, and an actuation cylinder
determines the position of the cutterarms.
The simulation demonstrates the importance of
pressure release valves for maintaining a constant
production rate under irregular reservoir conditions.
The energy balance showed a positive net
production of energy for each reservoir scenario and
production sequence. The economic balance showed
a negative net profit for all scenarios at the current
gas price. The current day rate of a drill rig has
major impact on the net profit. The net profit will
become positive for a gas price that equals three
times the current gas price. The layout and working
method of this concept mining equipment creates
the possibility of mining other valuable minerals
from ocean sediments.
Student; W.J. Overes
Sponsor: Huisman-Itrec
Committee: Prof.dr.ir. J. Meek, Prof.ir. W.J. Vlasblom, ir. G.H.G. Lagers, ir. J.J. De Ruiter, ir. R.F. Van
Kuilenburg
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Offshore Engineering ��0307
The upgrade of “Noble to Van Langeveld” to 1�00 m water depth capacity
The drilling semi-submersible “Noble Ton van
Langeveld” (NTvL) currently works in the UK sector
of the North Sea. As future work is limited due
to the shift towards deeper water, a study of the
upgrade of the NTvL to deeper water to ensure work
in the (near) future has been carried out.
From the current main deepwater areas, West
Africa and South East Asia are selected as the most
promising locations to upgrade the NTvL for.
The environmental loads in both areas (West Africa
and South East Asia) are formulated, resulting
in a set of design loads, which the NTvL should
be capable of withstanding. The environmental
conditions in West Africa are benign, compared to
South East Asia. In South East Asia tropical storms
(typhoons) are present. These occur throughout
most of the year and impose especially large wind
loads on the platform. In case of a typhoon the rig
is abandoned as safe work is not possible anymore.
The environmental loads are divided into wind, wave
drift and current loads. The wave drift loads are
composed of potential wave drift loads and viscous
wave drift loads. The potential wave drift loads
are computed using DELFRAC. The viscous wave
drift loads are computed using the model created
by A.K. Dev in his PhD-thesis and are caused by
the presence of a wake behind a cylinder in a flow.
Viscous wave
drift loads
are found by
integrating
the drag
component of
the Morison
equation over
the structure
height and
averaging
this over one
wave period.
The mooring design is based on the design loads
in both areas and is analysed using the mooring
program Seamoor. The modifications to the mooring
system currently installed are minimized, resulting in
an additional 200 m of anchor chain to be added to
each winch. This adds up to a total of 280 tons. The
design mooring system for each winch consists of a
chain-wire-chain connection as follows :
• 1280 m bottom chain length
• 2020 m wire insert length
• 200 m top chain length
• The chain-wire-chain connection is subject to a
top tension of 150 tons.
On the NTvL, the Noble Drilling aluminum alloy
riser (AAR) will be used. This greatly reduces the
suspended weight of the riser. Therefore, only minor
modifications to the riser tensioner system are
required. The required number of riser tensioners
can be reduced by installing more buoyancy on the
riser.
The riser motions result from the mooring system
characteristics and the environmental conditions as
well as the wave and current loads on the riser. The
resulting bending and tensile stresses in the riser do
not exceed the yield stress of the aluminum.
In conclusion, the upgrade of the NTvL to West
Africa and SE Asia conditions is well possible with
relatively minor modifications to the mooring and
riser systems.
Student: A. Smit
Sponsor: Noble Drilling
Committee: prof.dr.ir. J.A. Pinkster, dr.ir. S.A. Miedema, ir. G.H.G. Lagers, dr.sc. A. Metrikine, G.J.
Windhorst
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Offshore Engineering�� 0307
Structural optimization of monopile foundations for offshore windturbines handled by integrated analysis
Wind energy is a clean renewable source of
energy and currently undergoing major growth in
application. Although the vast majority of newly
installed wind farms are still onshore, offshore wind
energy has the advantage of greater average wind
speeds and lacks the nuisance problems associated
with implementation of wind energy nearby people’s
homes. The higher cost of offshore wind energy
is the major barrier for larger implementation;
increased cost of the foundation structure of
offshore wind turbines is the main reason for the
higher investment cost. Consequently lowering
these costs has a high priority to increase the
competitiveness of offshore wind energy.
In the design process for monopile foundations
for the Kentish Flats wind park Rambøll made the
decision to deviate from the approach of using
standardised foundation structures throughout
the wind farm. Using advanced analyses, detailed
data and individually designed monopiles resulted
in a significant weight and cost reduction for the
foundation structures. Ever increasing size of wind
farms increases potential gains from individualised
design, but the manual work involved rises as
well. Development of automated tools will thus
be necessary. The development of an automated
optimization procedure for this purpose has been
the subject of this thesis.
Student: R. Swinkels
Sponsor: Rambøll Denmark
Committee: Prof.ir. Meek, dr.ir. J. van der Tempel, ir. G.H.G. Lagers, dr. A. Romeijn, Henrik Carstens
(Rambøll)
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Offshore Engineering �70307
A probabilistic approach to jack-up leg penetration in stratified soils
When jack-up platforms are installed at their
temporary site of operation, geotechnical engineers
gather soil samples in order to determine the soil
property values. If the soil property values indicate
a soil profile with sufficient bearing capacity,
preloading of the jack-up can start by filling the hull
compartments with seawater. The preload forces
the leg footings, or spudcans as they are called,
to penetrate the soil to a depth where adequate
bearing capacity is encountered. It is the preloading
phase in which a hazard known as punch-through
is present. If the soil profile consists of a strong
layer overlying a weaker layer (e.g. sand on clay),
a spudcan can punch through the strong layer and
plunge into the weaker layer before the intended
preload is reached. This may lead to damage to the
legs and/or platform.
Predicting the leg penetration and punch-through
risk is complicated due to three areas of uncertainty.
They are the spatial variability in both vertical
and horizontal direction as well as the uncertainty
incorporated in the models used to predict the soil
bearing capacity. The models consider three main
failure mechanisms. They are general shear of both
sand and clay, squeezing of clay and punch-through
of both sand-over-clay as clay-over-clay soil profiles.
By using probabilistic methods, the spatial variability
as the model uncertainties can be taken into
account. Due to the non-linear behaviour of soils,
the probabilistic method of Monte Carlo simulation
has been used to predict the probability of punch-
through failure.
Although this study provides an effective
probabilistic tool for the geotechnical assessment of
jack-up platforms, one of the conclusions was that
the models used in the prediction of the bearing
capacity of stratified soils, should be improved if
possible.
Student: T. van der Wal
Sponsor: Fugro
Committee: prof.ir. A.C.W.M. Vrouwenvelder, dr.ir. S. van Baars, ir. G.H.G. Lagers, ir. J. Peuchen, ir. D.
Bouwmeester
For more information please contact the department of Offshore Engineering: (31) 15 2781328
Last year’s Theses�� 0307
Last year’s Theses ��0307
Last year’s Theses
Last year’s Theses�0 0307
Master’s Theses October 200�
Civil Engineering Theses
Structural Engineering
Amsterdam ArenA Ontwerp en constructieve
uitwerking veld ophangen aan dakconstructie.
Student:J.M.G.Huijbregts
Non-linear FEM modelling of steel fibre reinforced
concrete for the analysis of tunnel segments in the
thrust jack phase
Student:R.A.Burgers
Drijvende achterlandverbinding in zeer hoge sterkte
beton
Student:E.D.Pinas
Zettingsgedrag van blokkenmuren bij een variabele
grindlaag
Student:P.J.H.Renders
Comparison between the VBC/VBB and the Euro
code Design of incremental launching Box Girder
Bridge using high strength of concrete
Student:K.Sinnadurai
Onderzoek naar autogene vervorming van
cementpasta en beton.
Student:G.A.Leegwater
Sea Ice – Offshore Structure Interaction: Steady
State Downward Bending
Student:P.vanderMale
Ground vibrations induced by a high-speed train
running over inhomogeneous subsoil
Student:K.N.vanDalen
Gedrag Staal-beton kokerliggerbrug met
geprofileerde lijven
Student:A.ElHadji
Ontwikkeling van een methode om het mechanische
gedrag van ASR gels te meten.
Student:P.C.Crucq
Effects of nano-clay modification on rheology of
bitumen and performance of asphalt mixes
Student:D.B.Ghile
Predicting time dependent reinforcement corrosion
due to chloride ingress
Student:I.Mele
Building Engineering
Deuvelwerking van randbalken als onderdeel van
vloeren in prefabbouw
Student:E.A.Pieterse
CO2 emissie modelering van de gebouwschil
Student:H.Staal
Lightweight cold rolled steel construction systems
Student:C.vanZandwijk
Bouworganisatievormen voor infrastructuur
projecten voor gemeente Den Haag
Student:H.J.deGraaf
Ontwikkeling Life Cycle Management Model voor
Kademuurconstructies
Student:G.H.S.Weisz
Energie uit afvalwater
Student:J.D.Spronk
De samenwerking tussen uitvinder en ondernemer
bij technologische Start Ups met een patent
Student:O.J.Meijer
Adaptieve Temperatuurgrenswaarden
Student:M.vanBeek
Hydraulic & Geo Engineering
Abstract
Student:T.M.Caus
Comparative analysis of design recommendations for
quay walls
Student:E.Meijer
Summary
Student:E.A.vanBlaaderen
Wave characteristics derived from video
Student:C.Bos
Influence of foreshore steepness on wave velocity
Last year’s Theses �10307
and acceleration at the breakwater interface
Student:N.J.Oortman
Surfability of an ASR in irregular waves
Student:R.W.J.Over
Morphodynamic modeling of a schematic barrier
island
Student:B.deSonneville
Het effect van erosie en grondeigenschappen op het
dynamische gedrag van offshore windturbines
Betreffende stalen en betonnen mono paal
funderingen
Student:J.VanGinhoven
Cost-Estimating of Heineken Breweries Worldwide
A Probabilistic Framework
Student:M.Groeneveld
Uretek Deep Injection Method. Lifting of settled
foundations Analysis of full scale test results
Student:R.vanReenen
Verticaal evenwicht van damwandconstructies
Student:M.deKoning
a,b,c- Isotachenmodel (van a,b,c tot zetting)
Student:D.Sipkema
Masterplan for the Port of Azzawiya, Libya
Student:P.J.J.Groenewegen
“De In- en Uitbreiding van het Haven- en
Industriegebied Moerdijk”
Student:D.B.deBondt
Samenvatting
Student:E.vanderMaaten
Watermanagement
‘Measurability of hydrological processes by means of
gravimetrical measurements’
Student:J.E.J.deGoffau
Predicting Ulva growth in a saline Volkerak-
Zoomlake
Student:R.P.Hulsbergen
MeteoLook – a physically based regional distribution
model for measured meteorological variables
Student:M.P.Voogt
Flood Control? An Evaluation of the Impacts of
Flood Control and Drainage Projects in Bangladesh
Student:M.L.Drost
Nalevingsmetingen in het waterbeheer
Een casestudy naar de Wet beheer
rijkswaterstaatswerken
Student:M.Hofstra
Risicoanalyse binnen het regionale waterbeheer
Student:G.F.Verhoeven
“Vasthouden, bergen, afvoeren” onder de loep;
Onderzoek van de effectiviteit van maatregelen
tegen wateroverlast door neerslag, toegepast op
polder Eijerland
Student:G.J.Zegwaard
UV/H2O2 behandeling bij drinkwaterbereiding:
Onderzoek en ontwerp
Student:D.deRidder
Treatment Techniques for Combined Sewer
Overflows
Student:S.M.Scherrenberg
New process of drinking water production in 21st
century
Student:S.Li
Sediment Resuspension Effect on Water Quality in
Drinking Water Distribution System
Student:Q.Wang
Transport & Planning
Rijgedrag bij werkzaamheden Zicht op versmalde
stroken vanuit de helikopter
Student:R.J.terKuile
Systematische herinrichting van zwarte punten
in Vlaanderen Een beslisboom en een kosten-
batenanalyse
Student:M.van‘tHof
Last year’s Theses�2 0307
Paramaribo op orde; Structuurvisie Groot-
Paramaribo 2020
Student:Y.Blufpand
Werken aan vitale wijken
Student:E.Martens
Applied Earth Sciences Theses
Resource Engineering
Experimental study on the vitrification of bottom
ash from municipal waste incinrators
Student:M.Oorsprong
Prediction of ore mixture grinding behavior
Student:A.ScheltemaBeduin
An Experimental study on the thermal behavior of
heavy metals and minor elements in fly ash from a
municipal solid waste incinerator
Student:N.R.Wilson
Petroleum Engineering and Geosciences
Analysis of Geochemical data from Wells and
Outcrops, in the Permian Tanqua subbasin fan
complex, southwestern Karoo, South Africa
Student:R.vandenBrink
Turbidite Slope Channel deposits, a Reservoir
Simulation Study based on Field Data
Student:R.vandenHam
The use of modern analogues in shared earth
modeling (Case study of the Cook Formation,
Oseberg Field, offshore Norway)
StudentR.Thomassen
Analysis of Salt-Induced Stress Anomalies
Student:A.Vogelaar
Temperature Dependent Sorption of Carbon dioxide
on coal
Student:R.M.S.vanLier
Effect of sorption induced swelling on coal cleat
permeability
Student:I.J.P.Moors
Screening of Reservoir Characteristics for the
Applicability of Smart Field Technology to Dynamic
Water Flood Optimisation
Student:A.Altintas
Fluid front detection from time-lapse pressure
propagation test
Student:R.Formoso-RaffertyCastilla
Feasibility Study of WAG Injection in Naturally
Fractured Reservoirs
Student:J.Heeremans
Trapping Sequence Determination in Deep-bed
Filtration using Colored Particles during Produced
Water Reinjection
Student:B.Turekhanov
Engineering Geology
Massive Flank Collapse at La Palma Numerical slope
stability models of the Cumbre Vieja Volcano
Student:J.M.C.vanBerlo
The accuracy of the interpretation of CPT-based soil
classification methods for soft soils.
Student:J.Mollé
Swelling and shrinkage characteristics of soils in
the northern Netherlands and Restrained clay ring
shrinkage
Student:M.Zandbergen
Offshore Engineering Theses
Motion compensated float-over installation with the
use of the Ampelmann
Student:F.W.B.Gerner
Simulation of ship motions and probalistic design of
Ampelmann platforms
Student:A.J.Göbel
Safety and Reliability of Partly Jacked Vessels
Student:P.A.vanderGraaf
Calibration of SQM model tests
Student:N.P.Haakman
Last year’s Theses ��0307
Cryogenic Floating Hoses for Liquefied Natural Gas
Transfer
Student:T.Klieverik
Numerical approach for predicting heave motion
coefficients for a Tophat Design
Student:A.deLeeuw
Ships going semi?
Student:D.A.Manschot
Environmental Load Calculations on Space Frame
Support Structures for Offshore Wind Turbines
Student:A.H.vanderPol
Deep water riser concepts offshore Angola
Student:S.vanderPuttem
LNG export and shipping in Arctic seas – a new way
of LNG shipping in Arctic seas
Student:Y.Shu
Operability of a floating LNG Terminal -
Development of a new approach and berthing
concept for an exposed location
Student:J.Wolff
Implementing a frequency domain approach for the
fatigue analysis of offshore wind turbine support
structures
Student:W.E.deVries
Master’s Theses June 200�
Civil Engineering Theses
Structural engineering
Possible use of C-Fix in Porous Asphalt
Student:R.N.Khedoe
Spoorvernieuwing in de London Underground
Student:A.M.P.vanRossum
Damping of vibrations in slender tubes of arch
bridges
Student:R.Gerbranda
Lifespan enlargement of deck plates of movable
steel bridges
Student:M.C.Schrieks
Technische haalbaarheidsstudie van een ultra-hoge-
sterkte betonnen boogbrug
Student:J.denHollander
Connections Pile with Upper Structure for Concrete
Jetty
Numerical analysis and design proposal
Student:W.Xia
Flexvloer – Onderzoek naar de constructieve
aspecten van een nieuw vloersysteem
Student:H.G.Burggraaf
On Isogeometric Analysis for Crack Modelling
Student:W.M.Swolfs
A Very Large Floating Container Terminal
Student:G.V.P.deRooij
Laser welded steel bridge decks
Student:H.Stam
Haalbaarheidsonderzoek vervanging verslechterde
houten brugdekken door middel van VVK
Brugdekken
Student:D.Leliveld
Design of an integral bridge by FE modelling
Student:J.E.Göttgens
Larch Round Wood and its applications
Student:R.Schuch
Adaptive Anticlastic Membrane Structures
Prestressed by Edge Cables and Actuators
Student:P.C.Oltheten
Building Engineering
Gekromde Hoogbouw
Student:M.Wiersma
Last year’s Theses�� 0307
Optimizing future risk management at Fluor based
on historical project data
Background
Student:F.C.P.vanRoij
Verhoging van de haalbaarheid van
weginfrastructurele projecten door toepassing van
een publiek privaat samenwerkingsmodel
Student:R.M.Schunck
Shaping the Virtual Wind Tunnel
Student:D.P.Snijders
Construction of Prefab Concrete Shells
Student:M.vanRoosbroeck
Kinetic Space Frames
Student:P.A.vandeRotten
Hydraulic & Geo Engineering
Smoothed Particle Hydrodynamics
Student:L.deWit
Feasibility of IGW technology in offloading hoses
Student:S.Nooij
“3D numerical simulation of a harbour flow, applied
to Waalhaven, Port of Rotterdam”.
Student:H.H.Schonewille
Estimating Freak Wave Occurrence Probability in the
Agulhas Current
Student:A.J.Lansen
Influence of a secondary channel on bed
morphology and sediment distribution at a river
bifurcation
Student:J.J.deNooijer
Smart Nourishment of the Frisian Inlet
Student:T.M.Kluyver
Sand Balance “Loswal Noord” - The Net Contribution
of “Loswal Noord” to the Sand Budget of the Dutch
Coastal Foundation
Student:M.Slee
Geomatrically open filters in breakwaters
Student:E.F.Uelman
Vetiver grass as bank protection against vessel-
induced loads
Student:D.J.JaspersFocks
Design of granular near-bed structures in waves and
currents
Student:J.vandenBos
Run-up Reduction through Vetiver grass
Student:A.Algera
Equilibrium and stability of a double inlet system
Student:R.Brouwer
Siltation of Incheon Terminal basin and the
Approach Channel
Student:J.J.M.vanderLans
Uncertainty in the application of Bay Shape
Equations
Student:R.Lausman
Verbetering Zeetoegang IJmuiden: Systeem met
keersluis, open tijdens laagwater
Student:N.vanderZwan
Stormvloedkering in de Westerschelde
Student:J.M.vanderMeer
Door grond horizontaal belaste palen
Student:Is.Cherqaoui
Capacity study for the port of Buenos Aires,
Argentina
Student:R.Smits
Dynamic Response of a Transatlantic Tunnel to a
Hypersonic Train
Student:W.Verdouw
Watermanagement
Studie naar de bandbreedte van een Q(h)-relatie bij
de koppeling tussen SOBEK en SIMGRO
Student:J.Hornschuh
The influence of compartmentalisation on flooding
in Central Holland
Student:E.P.deBruine
Last year’s Theses ��0307
Suitability of natural tracers for determination of
runoff generation
A study in the Maisbich catchment (Luxembourg)
Student:M.Jasperse
Land Subsidence and Water Management in
Shanghai
A study into the reason, prevention methods and
future development of land subsidence in Shanghai.
Student:Q.Wei
Hergebruik van Afvalwater: Duurzame bron of
onnodig risico?
Student:L.Meijer
Substandard Supply Minutes in relation to risk
management for water supply
Student:S.C.Alberga
Development of Indirect Potable Reuse in impacted
areas of the United States
Student:H.P.Jansen
Transport & planning
Netwerkconcepten in Ruimtelijke Planning
Student:M.C.vanBreukelen
Machine Learning en het voorspellen van de
individuele schadekans
Student:C.P.J.vanHinsbergen
Openbaar Vervoer Paramaribo:
Een netwerk en lijnennet ontwerp
Student:S.Ferrier
Verkeerscirculatieplan voor Hoek van Holland op
drukke stranddagen.
Student:A.Meurs
Verkenning naar de toepasbaarheid van
microsimulatie bij beslissingsondersteuning
Student:J.R.deVos
Applied Earth Sciences Theses
This publication there were no Applied Earth
Sciences theses available
Offshore Engineering Theses
Concrete LNG FPSO
Student:K.Loijen
Availability of a weathervaning LNG import import
terminal
Student:A.vanderPijl
Extension of pipelay capacity on Allseas’ Solitaire by
S-lift implementation
Student:M.Dikkers
Master’s Theses March 200�
Samenvattingen Civiele Techniek
Structural Engineering
Voorontwerp en dynamische analyse van een
hardhouten tuibrug voor langzaam verkeer
Student:J.J.M.vanderAsdonk
BOUW - Software voor bepaling tuikabel-
voorspankrachten
Student:P.A.Brongers
Bouw - Voorgespannen Spoorbrug in Hogere Sterkte
Beton
Student:H.J.deBruijn
Experimenteel onderzoek naar de RCM-methode
Student:S.M.vanDalen
Phenomenological Modelling of Vortex-Induced
Vibrations of Deep-Water Risers
Student:W.Hoogkamer
BOUW - Minimum wapening in gewapend betonnen
platen
Student:J.Keijnemans
Bouw - IJmeerverbinding
Student:R.L.J.Maes
Joint behaviour in microtunnelling processes
Student:MohammedAbdelkarimTaher
Innovation of stress and damage reduction in bored
tunnels during construction,
based on a shield equilibrium model
Student:Q.C.deRijke
Last year’s Theses�� 0307
Discontinuous Galerkin methods for elastoplasticity
Student:D.RomagosaSanchez-Monge
Building Engineering
Hoogbouw op ‘Stapeldok’
Student:M.Bahri
De “Rotonde”
Student:J.M.Brouns
Waardevol verleden...
Student:R.M.Burer
Koelkast of broeikas?
Student:M.D.vanDonselaar
Deployable Structures based on Mechanisms in
Nature
Student:W.L.Dumans
Constructief ontwerp van het nieuwe stadhuis van
Gouda
Student:T.E.deGraaff
Constructief glazen element
Student:J.F.vanHeusden
Constructief Ontwerp ‘VandenEnde Musicaltheater’
Student:S.T.Kiefte
“Bridge to China”
Student:K.T.Lee
Lightness in glass constructions
Student:J.Luttmer
De Haagsche Zwaan
Student:G.J.Roos
Een snel wegneembare overkapping van tentdoek
Student:N.Roovers
Techniek in Mijnbouwkunde
Student:R.Sanders
Hydraulic & Geo Engineering
Large-scale coherent structures in turbulent shallow
flows
Student:W.vanBalen
The evaluation of piping at existing flood defence
constructions
Student:A.J.Boer
Erosion resistance of a grass top layer against wave
overtopping
Student:W.vandenBos
Klimaatverandering en Binnenvaart
Student:C.G.Bosschieter
Admittance policy tidal bound ships
Student:R.Bouw
Side channels to improve navigability on the river
Waal
Student:C.A.J.vanDam
Design of a cooling water outfall system
Student:V.N.vanDijk
Nourishment Behaviour Delray Beach
Student:W.M.Hartog
Probabilistic analysis of typhoon induced hydraulic
boundary conditions for Suo-nada Bay, Japan
Student:E.N.Klaver
Compensation Grouting Experiments in Sand
Student:R.M.Kleinlugtenbelt
Humplike nourishing of the shoreface
Student:L.Koster
The Irrigation System as an Open System; Proyecto
Rio Dulce and the Rio Dulce Basin
Student:C.N.Lieveld
Jetgrouten
Student: R.M. Loeffen
Theoretical and Experimental study on the
placement of Xbloc
Student:E.tenOever
Last year’s Theses �70307
Itapocú Inlet, Brazil
Student:L.M.Perk
Planning and technical feasibility study deepwater
port ‘Zona Portuaria Simon Bolivar’, Venezuela
Student:S.vanPoeteren
Transverse slope effects on widely graded sediment
Student:P.E.M.Schoonen
Drifting Sea Ice
Student:T.J.Segboer
A probabilistic flood risk assessment and the impact
of compartmentation
Student:R.P.G.J.Theunissen
Watermanagement
Saturation in the New York City Watershed
Student:M.A.Borst
Voorwaarden buitendijkse bebouwing langs rivieren
Student:L.A.C.vanGenugten
Hydrological modelling for a micro hydro-power dam
in the Panato creek, Suriname
Student:T.Lieuw
Application of a semi-distributed hydrological model
based on the REW approach to the Collie River
Basin, Western Australia
Student:E.Tromp
Model Predictive Control on Irrigation Canals;
application of various internal models
Student: R.M.J. Wagemaker
”De provincie Zuid-Holland zit er warmpjes bij”
Student:B.G.vandeWeerdhof
Use of culverts in dikes in the floodplain
Student:T.Wilms
Estimating the influence of on-farm Conservation
Practices on the Water Balance,
Case of the Mzinyathini Catchment in Zimbabwe
Student:L.Woltering
Transport & Planning
Functionele eisen voor beweegbare bruggen
Student:C.Hofma
Financieel-economische haalbaarheid van
ontwikkeling van meervoudig ruimtegebruik bij
railinfrastructuur in stedelijk gebied
Student:M.Kokshoorn
Woonmilieus aan de Zuiderzeelijn
Student:H.N.Vuong
Optimal utilization of capacity
Student:H.J.J.Wieringa
Applied Earth Sciences Theses
Resource Engineering
Development of a CFD model for a phosphorus
producing submerged arc furnace
Student:A.T.Adema
The effects of surfactants on the efficiency of
solution gas drive
Student:AliBarati
An emf cell to measure thermodynamic properties of
the magnesium – salt flux – impurity system
Student:M.Goense
Modelling of Recycling Systems - Applied to Car
Recycling
Student:G.J.deHaan
Dynamic Interaction between Slag and Coke in the
Blast Furnace
Student:A.Hoogervorst
The prediction of dross formation and the
containment of dross on an Industrial
Aluminium Recycling Plant
Student:V.A.deRoode
Petroleum Engineering and Geosciences
Deposition of Colored Tracer Latex Particles in
Sandstone
Student:H.Bennaceur
Last year’s Theses�� 0307
Sensitivity Study of Fracture Properties, Related to
the Production of Hydrocarbons
Student:M.W.N.vanGalen
Engineering Geology
Numerical modelling of rock mass decay in road cuts
88
Student:W.Tegtmeier
Offshore Engineering Theses
An analytical, numerical and experimental approach
of parametric roll of a tophat in irregular seas
Student:F.W.Blaauw
Standardised wave data bases on power level
Student:M.F.Burger
Deep water buoys – review study
Student:C.R.E.deGroot
Pipeline rotation during installation of inline
structures
Student:J.Mulder
Development of a compliant cone for solid tubular
expansion
Student:R.SchoonShell
Last year’s Theses ��0307
Research groups and professors within the faculty of Civil Engineering and Geosciences
Last year’s Theses100 0307
Specialisation Name Telephone 01�-27...
Design and Construction
Construction Mechanics Research Group
Construction mechanics vacancy
Dynamics Prof. A.C.W.M. Vrouwenvelder 84782
Numerical mechanics vacancy
Materials Science and Sustainable Construction Research Group
Acting chairman Prof. K. van Breugel 84954
Fund. and Applied Materials Science vacancy
Road and Rail Construction Research Group
Road Construction Prof. A.A.A. Molenaar 84812
Rail Construction Prof. C. Esveld 87122
Building and Civil Engineering Structures Research Group
General Construction Design Prof. L.A.G. Wagemans 84752
Concrete structures Prof. J.C. Walraven 85452
Concrete modelling & materials Prof. K. van Breugel 84954
Building physics and installations Prof. J.J.M. Cauberg 83387
Timber structures vacancy
Steel structures Prof. J. Wardenier 82315
Steel structures Prof. F.S.K. Bijlaard 84581
Steel construction of buildings Prof. J.W.B. Stark 82303
Building Technology vacancy
Utility buildings Prof. J.N.J.A. Vamberský 85488
Product Design Research Group
Methodical Design Prof. H.A.J. de Ridder 84921
Building Informatics vacancy
Hydraulic Engineering
Fluid Mechanics Research Group
Fluid Mechanics Prof. G.S. Stelling 85426
Environmental hydro informatics Prof. A.E. Mynett
General Fluid Mechanics Prof. J.A. Battjes 85060
Hydraulic and Offshore Engineering Research Group
Probabilistic design and Hydraulic Structures Prof. J.K. Vrijling 85278
Coastal Engineering Prof. M.J.F. Stive 84285
Ports and Inland Waterways Prof. H. Ligteringen 84285
River morphology & River Engineering Prof. H.J. de Vriend 81541
Offshore Engineering Prof. J. Meek 84777
Last year’s Theses 1010307
Specialisation Name Telephone 01�-27...
Water Management
Sanitary Engineering Research Group
Sewerage Prof. F.H.L.R. Clemens 85227
Waste Water treatment Prof. J.H.J.M. van der Graaf 81615
Drinking Water Prof. J.C. van Dijk 85227
Water Resources Research Group
Hydrology Prof. H.H.G. Savenije 81433
Water Resources Prof. N.C. van de Giesen 87180
Geohydrology Prof. Th. N. Olsthoorn 87346
Transport & Planning
Transport Planning Prof. P.H.L. Bovy 84611
Traffic and Transport Management Prof. H.J. van Zuylen 82761
Traffic and Transport Facilities Prof. I.A. Hansen 85279
Infrastructure Planning Prof. F.M. Sanders 81780
Applied Earth Sciences
Applied Geology Research Group
General Geology Prof. S.B. Kroonenberg 86025
Production Geology Prof. S.M. Luthi 86019
Resource Engineering Research Group
Petroleum Engineering Research Group
Oil- and Gas production systems Prof. P.K. Currie 86033
Reservoir Engineering vacancy
Applied Geophysics and Petrophysics
Geophysical Imaging Methods Prof. W.A. Mulder 83666
Integrated Time-Lapse Methods Prof. R.J. Arts 85190
Technical Geophysics Prof. C.P.A. Wapenaar 82848
Geo Engineering Research Group
Soil mechanics Prof. F. Molenkamp 85280
Groundwater mechanics Prof. F.B.J. Barends 85423
Foundation Engineering Prof. A.F. van Tol 85478
Underground Space Technology Prof. J.W. Bosch 82844
Geo environmental engineering vacancy
Last year’s Theses102 0307
Ontwerp en Lay-out:
MultiMedia Services TU Delft
Druk:
Sieca Repro bv, Delft
© 2006