+ All Categories
Home > Documents > Masterclass Activity Summary

Masterclass Activity Summary

Date post: 03-Jan-2016
Category:
Upload: colby-riley
View: 22 times
Download: 0 times
Share this document with a friend
Description:
Masterclass Activity Summary. Focus – Layout improvement, 5C, Vis Mgt. Company Address. Products and Customers. Issue Date. Pharmaceuticals. Company Information. Turnover : £ Profit : n/a Ownership: Number of Employees:450. Mark McGurk. Engineer Names. Team Members. Contract No. - PowerPoint PPT Presentation
Popular Tags:
12
1. Expectations 6. Learning Points & Countermeasures 4. Focus Area 9. Evaluation and Future Needs 8. Financials 7. Results 3. Current Situation TEAM Edgefield Avenue Fawdon Newcastle upon Tyne NE3 3TT Pharmaceuticals. Turnover : £ Profit : n/a Ownership: Number of Employees:450 Mark McGurk Diane Storey Daniel Stokes Dan Billany Keith Currie Michael Hodgson Company Address Products and Customers Team Members Engineer Names Company Information Issue Date Contract No. Focus – Layout improvement, 5C, Vis Mgt. COMPANY 5. Activity Structure Masterclass Activity Summary Wave 1 2009 Action Plan Do Check Process Mapping Identify Focus Area Data Analysis 22/06/09 2. QCD 7 Measures Create a Plan LEARNING POINTS: - Waste elimination, Process mapping, 5C, Visual Management. Review Activity and Develop Roll Out Plan Map process streams 7 Wastes Calculate ideal WIP levels Identify location of Para stream WIP Allocate IBC’s to each steam based on calculations 5C para stream WIP locations Visual Management Plan Run simulation to check para stream WIP is correct •Optimise and rationalise utilisation of IBC’s by type and process. •Better control of IBC’s •Reduce WIP if possible. •Ensure IBC’s are available. •Improve organisation in area. •Have Fun. •Maximise/optimise use of existing IBC’s •Reduce further investment in IBC’s. •Improve control of IBC’s. •Upskill team in CI techniques. •Method/system for IBC’s. •Precursor to witness exercise. From the diagnosis of the current situation the following workshop focus was developed :- 1Quantify the required number and type of IBC’s required to maintain the process flow. 2. Implement visual management systems for use of IBC’s 3. Designate specific locations for IBC’s within the complete process. 4. Investigate current versus future process flows. 5. Agree para WIP levels. 6. Generate 20 large buck valve IBC’s from Epilim and non-para processes. A visual system was developed to show which IBC’s belonged to each process stream. Process stream WIP levels Cycle time data from each process was used to estimate optimum WIP levels, this include the para stream. The team then calculated the optimum work in progress levels for each of the process streams. To prove the calculation the team ran a small simulation on the para stream process, this confirmed the correct number of IBC for the para stream. To support the new working methods Job detail sheets would be introduced in:- The bin wash area. The service operators role. The team identified all of the process streams that they needed to analyse. They documented cycle times and current and proposed WIP levels at each stage of the process for each stream. The team worked on para and any stream which used buck valve IBC’s as a priority. 5C The potential savings from this Masterclass are :- A reduction in additional IBC’s which was originally calculated as 20 outside of this team can now be achieved by utilising IBC’s from the current process more efficiently. As the number IBC’s has been optimised there is a reduction of batches in WIP within the para and other process streams. Other benefits include a better flow of IBC’s, more floor space available and the manufacturing area being less congested and more availability of the bin wash. This should also lead to less time spent looking for IBC’s and therefore an improvement in productivity due to IBC’s being more available for the process. The Potential financial savings from this activity are :- The elimination of an unnecessary spend for additional IBC’s to support the change on the para process stream equipment of £420,000. A reduction in para stream WIP due to optimising the usage the IBC’s of £68,755 due to a reduction in pangran and paracodeine WIP. Robin Barras Janice Hurst Tim Scott Steve Eaton-Hall Current system (Using butterfly IBC’s) Future system (Using buck valve IBC’s) As an improvement to the equipment the paracetamol process is being converted from butterfly valve docking station to a fully automatic buck valve system. This is superior system as the principle reduces the risk of contamination during operation of the process. This means that there is a requirement for additional buck valve IBC’s to support the paracetamol process stream. The level 1 chart shows the total number of IBC’s found, when compared to the on- site records 7.5% of the IBC’s were not located. The level 2 chart shows how many of the bins fall into each of the 5 categories:- 70 (38% were large butterfly), 45 (24.5% were large buck valve) 21% of all IBC’s were being used by the paracetamol process stream (all large butterfly IBC’s.) 19% of all IBC’s were being used by the Epilim process stream, the majority being Large buck valve IBC’s, the remainder small butterfly IBC’s. The team were interested in WIP levels in the para process and any process which used large buck valve IBC’s. These processes were identified and process mapped. The appropriate number of IBCS was recorded. The team then concentrated on the Para stream process as this was the main focus of the intervention due to the process change. The team identified and allocated the correct number of spaces for the para stream process ensuring transportation waste was kept to a minimum. Standardised Work Visual management Para Stream Simulation Allocation of IBC’S Previous floor markings removed. New locations for WIP identified from bin allocation and layout drawing. Areas configured and identified with signs. •The team did an excellent job during a challenging intervention which was very heavy on data and classroom based activity. •Feedback from management was well received. •The team are continuing with meetings and are on target to free up. •Regular team reviews must continue to ensure the IBC’s are at the required level. •Detailed roll out plan has been developed by team to assist intervention. Visual Management of IBC’s to process stream Draft Standardised work documents produced
Transcript
Page 1: Masterclass Activity Summary

1. Expectations 6. Learning Points & Countermeasures

4. Focus Area 9. Evaluation and Future Needs8. Financials7. Results

3. Current Situation

TEAM

Edgefield AvenueFawdon

Newcastle upon TyneNE3 3TT

Pharmaceuticals.

Turnover : £Profit : n/aOwnership:Number of Employees:450

Mark McGurkDiane StoreyDaniel StokesDan BillanyKeith CurrieMichael Hodgson

Company Address Products and Customers Team MembersEngineer NamesCompany Information Issue DateContract No.

Focus – Layout improvement, 5C, Vis Mgt.

COMPANY

5. Activity Structure

Masterclass Activity Summary

Wave 12009

Action Plan Do Check

Process Mapping

Identify Focus Area

Data Analysis

22/06/09

2. QCD 7 Measures

Create a Plan

LEARNING POINTS: - Waste elimination, Process mapping, 5C, Visual Management.

Review Activity and Develop Roll Out Plan

Map process streams

7 Wastes

Calculate ideal WIP levels

Identify location of Para stream WIP

Allocate IBC’s to each steam based on

calculations

5C para stream WIP locations

Visual Management Plan

Run simulation to check para stream WIP is correct

•Optimise and rationalise utilisation of IBC’s by type and process.•Better control of IBC’s•Reduce WIP if possible.•Ensure IBC’s are available.•Improve organisation in area.•Have Fun.

•Maximise/optimise use of existing IBC’s•Reduce further investment in IBC’s.•Improve control of IBC’s.•Upskill team in CI techniques.•Method/system for IBC’s.•Precursor to witness exercise.

From the diagnosis of the current situation the following workshop focus was developed :-

1Quantify the required number and type of IBC’s required to maintain the process flow.2. Implement visual management systems for use of IBC’s3. Designate specific locations for IBC’s within the complete process.4. Investigate current versus future process flows.5. Agree para WIP levels.6. Generate 20 large buck valve IBC’s from Epilim and non-para processes.

A visual system was developed to show which IBC’s belonged to each process stream.

Process stream WIP levelsCycle time data from each process was used to estimate optimum WIP levels, this include the para stream.

The team then calculated the optimum work in progress levels for each of the process streams. To prove the calculation the team ran a small simulation on the para stream process, this confirmed the correct number of IBC for the para stream.

To support the new working methods Job detail sheets would be introduced in:-

•The bin wash area.

•The service operators role.

The team identified all of the process streams that they needed to analyse. They documented cycle times and current and proposed WIP levels at each stage of the process for each stream.

The team worked on para and any stream which used buck valve IBC’s as a priority.

5C

The potential savings from this Masterclass are :-

•A reduction in additional IBC’s which was originally calculated as 20 outside of this team can now be achieved by utilising IBC’s from the current process more efficiently.

•As the number IBC’s has been optimised there is a reduction of batches in WIP within the para and other process streams.

•Other benefits include a better flow of IBC’s, more floor space available and the manufacturing area being less congested and more availability of the bin wash.

•This should also lead to less time spent looking for IBC’s and therefore an improvement in productivity due to IBC’s being more available for the process.

The Potential financial savings from this activity are :-

•The elimination of an unnecessary spend for additional IBC’s to support the change on the para process stream equipment of £420,000.

•A reduction in para stream WIP due to optimising the usage the IBC’s of £68,755 due to a reduction in pangran and paracodeine WIP.

Robin Barras Janice Hurst

Tim Scott Steve Eaton-Hall

Current system (Using butterfly IBC’s)

Future system (Using buck valve IBC’s)

As an improvement to the equipment the paracetamol process is being converted from butterfly valve docking station to a fully automatic buck valve system. This is superior system as the principle reduces the risk of contamination during operation of the process. This means that there is a requirement for additional buck valve IBC’s to support the paracetamol process stream.

The level 1 chart shows the total number of IBC’s found, when compared to the on-site records 7.5% of the IBC’s were not located.

The level 2 chart shows how many of the bins fall into each of the 5 categories:- 70 (38% were large butterfly), 45 (24.5% were large buck valve)

21% of all IBC’s were being used by the paracetamol process stream (all large butterfly IBC’s.)

19% of all IBC’s were being used by the Epilim process stream, the majority being Large buck valve IBC’s, the remainder small butterfly IBC’s.The team were interested in WIP levels in

the para process and any process which used large buck valve IBC’s. These

processes were identified and process mapped.

The appropriate number of IBCS was recorded.

The team then concentrated on the Para stream process as this was the main focus of the intervention due to the process change.

The team identified and allocated the correct number of spaces for the para stream process ensuring transportation waste was kept to a minimum.

Standardised WorkVisual management

Para Stream Simulation Allocation of IBC’S

Previous floor

markings removed.

New locations for WIP identified from bin allocation and layout drawing.

Areas configured and identified with signs.

•The team did an excellent job during a challenging intervention which was very heavy on data and classroom based activity.

•Feedback from management was well received.

•The team are continuing with meetings and are on target to free up.

•Regular team reviews must continue to ensure the IBC’s are at the required level.

•Detailed roll out plan has been developed by team to assist intervention.

Visual Management of IBC’s to process stream

Draft Standardised work documents produced

Page 2: Masterclass Activity Summary

Expectations and 7 Measures

Team Expectations

• Optimise and rationalise utilisation of IBC’s by type and process.

• Better control of IBC’s• Reduce WIP if possible.• Ensure IBC’s are available.• Improve organisation in

area.• Have Fun.

Company Expectations

• Maximise/optimise use of existing IBC’s

• Reduce further investment in IBC’s.

• Improve control of IBC’s.• Upskill team in CI

techniques.• Method/system for IBC’s.• Precursor to witness

exercise.

Return to A3 Summary

Page 3: Masterclass Activity Summary

Current Situation and Focus

Return to A3 Summary

Para-stream Feed system

Current system (Using butterfly IBC’s) Future system (Using buck valve IBC’s)

Butterfly valve Butterfly valve IBC uses a IBC uses a manually manually operated valve operated valve which the which the operator must operator must actuateactuate

A cradle must A cradle must also be used also be used to enable the to enable the IBC to connect IBC to connect with the with the docking docking stationstation

Butterfly valve Butterfly valve IBC is then IBC is then positioned positioned over the over the docking docking station and the station and the valve valve actuated.actuated.

Buck valve IBC Buck valve IBC mates directly to mates directly to the docking the docking station ready for station ready for the process to the process to actuate the actuate the valve.valve.

Buck valve IBC Buck valve IBC is an is an automatically automatically actuated valve actuated valve that is that is controlled by controlled by the process.the process.

As an improvement to the equipment the As an improvement to the equipment the paracetamol process is being converted from paracetamol process is being converted from butterfly valve docking station to a fully butterfly valve docking station to a fully automatic buck valve system. This is superior automatic buck valve system. This is superior system as the principle reduces the risk of system as the principle reduces the risk of contamination during operation of the process. contamination during operation of the process. This means that there is a requirement for This means that there is a requirement for additional buck valve IBC’s to support the additional buck valve IBC’s to support the paracetamol process stream.paracetamol process stream.

Page 4: Masterclass Activity Summary

Current Situation

Return to A3 Summary

The level 1 chart shows the total number of IBC’s found, when compared to the on-site records 7.5% of the IBC’s were not located.

The level 2 chart shows how many of the bins fall into each of the 5 categories:- 70 (38% were large butterfly), 45 (24.5% were large buck valve)

A complete count of all the IBC’s within the process was conducted and this was then used to identify the current situation.

21% of all IBC’s were being used for paracetamol and they were all large butterfly IBC’s.

19% of all IBC’s were being used by the Epilim process stream, the majority being Large buck valve IBC’s.

The team were interested in WIP levels in the para process and any process which used large buck valve IBC’s. These processes were identified and process

mapped.

The number of IBC’s was then analysed by type and process to identify the quantity and type of IBC allocated to each process.

Page 5: Masterclass Activity Summary

Current Situation

SUMMARY

080.20.60.119.1Percentage.

7479305Grand Total.

6074606051780Total Time.

161014Total No.

Dist(m)

T (secs)

OP INSP TRANS DELAY STOR

SUMMARY

0621037Percentage.

293024266Grand Total.

0149982539015Total Time.

11125013Total No.

Dist(m)

T (secs)

OP INSP TRANS DELAY STOR

The data from the physical IBC count lead the team to identify how many IBC’s were in the para process, this was process mapped to identify delays and waste.

The data also identified which processes were using the required buck valve IBC’s, these processes were mapped to identify opportunities for releasing IBC’s.

SUMMARY

082.20.50.117.2Percentage.

120510220

Grand Total.

0839055151760Total Time.

181126Total No.

Dist(m)

T (secs)

OP INSP TRANS DELAY STOR

82.2 6280.2

High percentages in non-value added activities (delay)

Saw tooth identifies that material is being transported from one delay to another delay

instead of directly to operation.

Page 6: Masterclass Activity Summary

Workshop Focus

Return to A3 Summary

From the diagnosis of the current situation the following workshop focus was developed :-

1. Quantify the required number and type of IBC’s to maintain the process.

2. Implement management systems for use of IBC’s.

3. Designate specific locations for IBC’s within the complete process.

4. Investigate current verses future process flows.

5. Agree para stream WIP levels.6. Generate 20 large buck valve

IBC’s from Epilim and non-para processes.

Page 7: Masterclass Activity Summary

Countermeasures :- Process stream analysis

To gain a better understanding on the process stream and WIP level requirements the process streams were mapped

Predicted weekly demand

Blending operation required

Moisture test required to determine route

Process Data

Cycle time

Shift Pattern

Observed WIP

Predicted WIP

Acceptable process range

Preferred range

Within the para stream process the team identified a moisture test. This determines whether the base grain will go to pangran or paracodeine processes. This was thought to be a major issue when the team analysed the data virtually all of the product could be used for either process.

Page 8: Masterclass Activity Summary

Countermeasures :- Ideal para stream WIP level

Plan:- Each process stream was isolated. From this ideal WIP levels were calculated for each process.

Do:- Calculate optimum WIP levels.

Check:- Run a simulation to check that WIP levels are ok and start condition is reached at end of cycle.

Each team member was designated a process and a scale of 2 secs = 1 hour was used, a weekly cycle of 105 hours was ran

Act:- Once WIP levels were verified to be ok the team then had to identify where to place the required WIP using 5C.

P

A D

C

Page 9: Masterclass Activity Summary

Countermeasures :- 5C

Return to A3 Summary

After all the WIP levels within each process stream had

been analysed and the optimum levels calculated

and simulated the team proposed an allocation for

buck valve IBC’s.

After optimisation the team identified that there would be 6 spare IBC’s. The optimum level for para stream was 14, 6 less than the 20 originally estimated by the company.

The spaces for the para-stream IBC

locations was identified on a layout.

The team considered:-

•Keeping the Distance travelled to a minimum.

•Ensuring the flow of material was good.

Old locations removed.

IBC’s moved to newly configured

locations.

New locations configured from

layout.

Visual locations identified on area

walls.

New locations configured next to

processes.PARA –STREAM

FEED FLOOR.

Page 10: Masterclass Activity Summary

Countermeasures :- Visual Management

Process stream allocation monitor,

this show which IBC’s are allocated to each individual process stream

Identification tag for each

IBC to identify which

process stream it

belongs to.

Action sheet for identifying if a bin

is swapped or some of the spares are required due to stock building etc.

Page 11: Masterclass Activity Summary

Results and Financials

Return to A3 Summary

•Results

•Financials

The financial savings from this activity are :-

•A reduction in capital investment in buck valve IBC’s which was originally allocated as £420,000 has been reduced to £0 = £420,000 saving.

•Estimated reduction in paracetamol stock from £59,824 to £26,173 = £33,651 saving.

•Estimated reduction in paracodeine stock from £87,760 to £52,656 = £35,109 saving.

•Total potential savings from activity = £488,660.

The savings from this Masterclass are :-

•A reduction in additional IBC’s which was originally calculated as 20 outside of this team can now be achieved by utilising IBC’s from the current process more efficiently.

•As the number IBC’s has been optimised there is a reduction of batches in WIP within the para and other process streams.

•Other benefits include a better flow of IBC’s, more floor space available and the manufacturing area being less congested and more availability of the bin wash.

Page 12: Masterclass Activity Summary

Evaluation and Future Needs

Return to A3 Summary

•The Team did an excellent job during a challenging intervention which was very heavy on data and classroom based activity.

•Feedback to management was well received.

•The team are continuing to have regular team meetings and are on target to free up the required number of IBC’s required.

•Regular team meetings must continue to ensure the IBC’s are available when the new para stream system goes live.

•A detailed roll out plan has been developed by the team to assist the intervention and ensure key activities have been completed by critical dates.

•This activity is now live and the team have exceeded the estimated reduction in IBC’s to approx. 12


Recommended