Integrated Port Masterplanning
43rd International Port Seminar, April 2007
Prof. Han Ligteringen
8/10/2019 Masterplanning Process
2/29
April 26, 2007 2
Integral Port Planning
Longterm: horizon 20 years
Masterplan National/ Regional
Individual port
Medium term: 3-5 years
Short term: 1 year
8/10/2019 Masterplanning Process
3/29
April 26, 2007 3
Rolling masterplan
8/10/2019 Masterplanning Process
4/29
April 26, 2007 4
8/10/2019 Masterplanning Process
5/29
April 26, 2007 5
Lay-out design aspects
Nautical requirements
Hydraulic requirements
Quay and Terminal dimensions
Hinterland connections
In addition: technical considerations
environmental/ legal requirements
8/10/2019 Masterplanning Process
6/29
April 26, 2007 6
Technical considerations
Balance of cut and fill
8/10/2019 Masterplanning Process
7/29
April 26, 2007 7
8/10/2019 Masterplanning Process
8/29
April 26, 2007 8
Technical considerations
Balance of cut and fill
Angle between approach channel and mainwave direction
8/10/2019 Masterplanning Process
9/29
April 26, 2007 9
8/10/2019 Masterplanning Process
10/29
April 26, 2007 10
Technical considerations
Balance of cut and fill
Angle between approach channel and main wavedirection
Breakwater alignment
8/10/2019 Masterplanning Process
11/29
April 26, 2007 11
8/10/2019 Masterplanning Process
12/29
April 26, 2007 12
Technical considerations
Balance of cut and fill
Angle between approach channel and main wavedirection
Breakwater alignment
Bends in the approach channel
8/10/2019 Masterplanning Process
13/29
April 26, 2007 13
Technical considerations
Balance of cut and fill
Angle between approach channel and main wavedirection
Breakwater alignment
Bends in the approach channel
Morphological aspects
8/10/2019 Masterplanning Process
14/29
April 26, 2007 14
Technical considerations
Balance of cut and fill
Angle between approach channel and main wavedirection
Breakwater alignment
Bends in the approach channel
Morphological effects
Safety of berth locations
8/10/2019 Masterplanning Process
15/29
April 26, 2007 15
Environmental/ legal requirements
Masterplan process (Fig. 4-2) shows only the
technical side How does this fit in the overall process of planning,
(political) decision making, financing and realisation?
Example: Expansion Rotterdam port.
8/10/2019 Masterplanning Process
16/29
8/10/2019 Masterplanning Process
17/29
April 26, 2007 17
Realisation Basic Infrastructure
Port Authority Government
Finalisation Masterplan
Phase 1
Designs Permit appl.
Detailed EIA Submit
Tender Doc. Bid Process
Selection Contract
Construction - Completion
Approval
8/10/2019 Masterplanning Process
18/29
April 26, 2007 18
Design Permit appl.
Tender Doc. Bid Process
Selection Contract
Construction - Completion
Operator Government
Approval
Realisation Terminal Facilities
8/10/2019 Masterplanning Process
19/29
April 26, 2007 19
Port of Rotterdam expansion project
Maasvlakte 2
History of the project
Decision-making process
Project studies
8/10/2019 Masterplanning Process
20/29
April 26, 2007 20
Western Europe
8/10/2019 Masterplanning Process
21/29
April 26, 2007 21
Existing Maasvlakte
8/10/2019 Masterplanning Process
22/29
April 26, 2007 22
8/10/2019 Masterplanning Process
23/29
April 26, 2007 23
Evolvement port lay-out
Plan Studies: 3 basic alternatives
EIA for maximum area C/B only acceptable for minimum development
8/10/2019 Masterplanning Process
24/29
April 26, 2007 24
Basic Alt. A
8/10/2019 Masterplanning Process
25/29
April 26, 2007 25
Basic Alt. B
8/10/2019 Masterplanning Process
26/29
April 26, 2007 26
Basic Alt. C
8/10/2019 Masterplanning Process
27/29
April 26, 2007 27
Evolvement Port lay-out
Plan Studies: 3 basic alternatives
EIA for maximum area C/B only acceptable for minimum development
Gov. Decision and Financing: revised minimum lay-out
Finalisation Masterplan: ?
8/10/2019 Masterplanning Process
28/29
April 26, 2007 28
Present
MasterplanLay-out
8/10/2019 Masterplanning Process
29/29
April 26, 2007 29
Environmental Requirements
Gov. Decision end 1996: dual purpose (economic
development and 750 ha nature) EIA procedure: compensation of lost sea area with
sea reserve area.
Governement finalapproval in 2003, but rejection inhighest legal body (State Council).
Further EIA studies to refute objections,
approval mid-2006, poject delay of about 1 year.