+ All Categories
Home > Documents > Materials Handling and Wastage Control

Materials Handling and Wastage Control

Date post: 07-Apr-2018
Category:
Upload: ghintsay
View: 225 times
Download: 0 times
Share this document with a friend

of 74

Transcript
  • 8/6/2019 Materials Handling and Wastage Control

    1/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    ADDIS ABABA

    UNIVERSITY

    FACULTY OF TECHNOLOGY SOUTH

    DEPARTMENT OF CONSTRUCTION TECHNOLOGY AND

    MANAGEMENT

    THESIS FOR UNDER GRADUATE PROGRAM (BSc.)

    TITLE: MATERIAL HANDLING AND WASTAGE CONTROL IN ADDIS

    ABABA LOW COST HOUSING PROJECTS

    ADVISOR: Belay Yitayew (Ato.)

    PREPARED BY:

    1. Dechasa Haile

    2. Gebrehiwot Hintsay

    3. Saron Anteneh

    Prepared by: Dechasa, Gebrehiwot, Saron 1

  • 8/6/2019 Materials Handling and Wastage Control

    2/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    February 2010

    APPROVED BY BOARD OF EXAMINERS

    ADVISOR: ______________________________

    SIGNITURE: _____________________________

    DATE: ______________________________

    EXTERNAL EXAMINER: __________________

    SIGNITURE: ______________________________

    DATE: ______________________________

    INTERNAL EXAMINER: ___________________

    SIGNITURE: ______________________________

    DATE: _______________________________

    Prepared by: Dechasa, Gebrehiwot, Saron 2

  • 8/6/2019 Materials Handling and Wastage Control

    3/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Prepared by: Dechasa, Gebrehiwot, Saron 3

  • 8/6/2019 Materials Handling and Wastage Control

    4/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    ACKNOWLEDGEMENT

    This research would have been impossible to realize without the tremendous

    assistance and cooperation of various individuals and construction

    companies. It is therefore our great pleasure to acknowledge and thank them

    for their collaboration and helpful support.

    We sincerely thank and express deep gratitude to our advisor Ato Belay

    Yitayew for providing valuable advice, continuous support and guidance andfor his comments and suggestions during the progress of the research in a

    more realistic way.

    Our special credit also goes to those contractors, consultants and employer

    for giving their precious time to respond our survey questioners and

    interviews.

    The Ministry of Works and Urban Development, the Ethiopian Association of

    Civil Engineers also deserves our acknowledgement for the ease access of

    the important information for this study.

    And finally we are highly indebted to all site engineers, and supervisors, who

    have shown their keen interest of cooperation by providing us with the

    necessary information and data required for the thesis work.

    Prepared by: Dechasa, Gebrehiwot, Saron 4

  • 8/6/2019 Materials Handling and Wastage Control

    5/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    TABLE OF CONTENT

    Acknowledgement I Table of content .. II , IIIAbbreviation .. IVAbstract .. V

    CHAPTER ONE

    1. INTRODUCTION 1

    1.1 Research back ground ... 1

    1.2 Objective of this research .. 3

    1.3 Methodology .. 3

    1.4 Scope and limitation .. 4

    1.5 Structure of the paper .. 4

    CHAPTER TWO

    2. LITERATURE REVIEW

    . 52.1 Construction Management 5

    2.2 Construction Resource Management 6

    2.3 Construction Materials Management 7

    2.3.1 Materials Planning 8

    2.3.2 Materials Procurement Process 10

    2.3.3 Inventory Control 11

    2.3.4 Store-Keeping and Warehousing

    12

    2.3.5 Handling and Transportation 12

    2.3.6 Codification and Standardization

    13

    2.3.7 Disposal of surpluses .. 14

    Prepared by: Dechasa, Gebrehiwot, Saron 5

  • 8/6/2019 Materials Handling and Wastage Control

    6/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    2.4 Construction Materials Wastage Management .. 15

    2.4.1 Definition .. 15

    2.4.2 Materials wastage standard .. 15

    2.4.3 Causes of material wastage 17

    2.4.4 Side effect of the problem 19

    2.4.4.1 Side effect due to poor material handling . 19

    2.4.4.2 Side effect due to material wastage . 20

    2.4.5 System of material wastage control .. 22

    2.4.5.1 Accounting for construction materials .. 22

    2.4.5.2 Material wastage analysis .. 22

    CHAPTER THREE

    3. ANALYSIS

    3.1. Profile of the questionnaires 24

    3.2. The respondents 25

    3.3. Data presentation, Analysis and Discussion .. 26

    3.3.1 Section one Existence of the problem 26

    3.3.2 Section two Major causes .. 27

    3.3.3 Section three Side effects . 38

    3.3.4 Section four Proposed systems ..

    41

    CHAPTER FOUR

    4. CONCLUSION AND RECOMMENDATION

    4.1. Conclusion .. 44

    4.2. Recommendation .. 45References .. 46

    Appendix A Research proposal

    Prepared by: Dechasa, Gebrehiwot, Saron 6

  • 8/6/2019 Materials Handling and Wastage Control

    7/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Appendix B Research questionnaires

    ABBRIVATIONS

    LCH Low Cost HouseMSE Micro and Small Enterprises4Ms Materials, Money, Manpower and Machineries4Rs Review, Reduce, Reuse and RecycleMSM Material Storage ManagementAAHDPO Addis Ababa Housing DevelopmentHCB Hollow Concrete Block

    Prepared by: Dechasa, Gebrehiwot, Saron 7

  • 8/6/2019 Materials Handling and Wastage Control

    8/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    ABSTRACT

    In any construction project especially in Low Cost Housing there should be a

    great concern for construction material wastage control system in order to

    avoid maximum material wastage generation. Since construction industry is

    one of the emerging economy of our country which consumes larger

    percentage of the annual budget, construction material handling and

    wastage control system desires serious consideration and due attention.

    Based on this assumption, we have conducted our research on construction

    material handling and wastage control systems in LCH projects with in Addis

    Ababa. And we attempted to answer the following questions. What are the

    most recent material handling systems in these projects? What are the main

    causes for material wastage and their consequence? And what are the

    systems adopt to reduce the wastage generated?

    In this thesis we have explored construction material handling systems,

    wastage control mechanisms, and tried to identify wastage causes and their

    remedial measures to decrease wastages. Data were collected using

    questioner survey distributed randomly to selected and concerned stake

    holders for those operating in Addis Ababa LCH projects. In this research

    work, all questions are grouped and analyzed according to their relationship,

    discussed and possible conclusions and recommendations forwarded.

    Generally, 100% of the cost efficient LCH construction stake holders proved

    that, the existences of material wastage, therefore implementing effectivewastage control system, early identification and awarenesss on wastage

    causes and use of some sort of material plan and management systems are

    vital to minimize the unavoidable material wastages.

    Prepared by: Dechasa, Gebrehiwot, Saron 8

  • 8/6/2019 Materials Handling and Wastage Control

    9/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    CHAPTER - ONE

    1. INTRODUCTION

    1.1 Research back ground

    "Low-Cost-Housing Technology (LCH)" was instituted for the first time in

    Tigray province and then in other regions of Ethiopia [7]. The city of Addis

    Ababa, being the capital of the nation, is facing numerous challenges in

    trying to meet the demands aroused by the ever increasing population and

    high rate of urbanization. Consequently, the need for an increase in quantity

    and quality of shelter, infrastructure, employment and various social services

    become crucial to sustain the city life.

    Accordingly the city government has planned to address these challenges

    strategically with the help of the National Integrated Urban Development

    Plans along with other municipal administration of Addis Ababa Grand

    Housing Program. Since September 2003, the municipal administration of

    Addis Ababa has been working on the planning and implementation of the

    Addis Ababa Grand Housing Program, which is an action program for the

    construction of living space. The national plan on housing has allocated about

    50% of its 2006 - 2010 plans, which are about 200,000 housing units, to be

    executed in the city of Addis Ababa.

    The long term objective of housing program is to improve the living standard

    of citizens, especially low-income citizens of the city, which are the majority,

    through the creation of employment opportunities and the provision of the

    decent affordable housing.

    The specific immediate objectives of the program are to be serving the

    purpose of:

    Prepared by: Dechasa, Gebrehiwot, Saron 9

  • 8/6/2019 Materials Handling and Wastage Control

    10/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Regenerating the slum area of the inner city,

    Increasing the land delivery amount in the inner city as a process

    of densification and vertical growth,

    Promotion of micro and small-scale enterprise, which can absorb

    more labor force and operate at a lower overhead cost,

    Promotion of cost efficient housing construction technology,

    Empowering citizens of the city through ownership of houses and

    possession security,

    Changing the image of the city [6].

    Construction is proceeding on the basis of LCH technology with prefabricated

    components. People wishing to move in to the apartment buildings and

    become owners, by paying some 30% of the construction costs. The

    remainders are financed through building loans with a 15-year term, pre-

    financing being advanced by the city municipal administration. In the socially

    integrated settlements, complete with municipal infrastructure facilities, the

    residents themselves are to take responsibility for maintaining their houses

    [7].

    Following the first successful LCH pilot projects in 2004, Addis Ababa city

    government administration under "Grand Housing Program" allocated huge

    sum of budget to alleviate shortage of housing and also reduce house slum in

    the city [8]. Besides it is part of the national government plan for the

    reduction of poverty in the new millennium particularly in the capital city of

    Ethiopia. Since huge investments are deployed to construct LCH projects,

    implementation of the existing material handling and wastage control

    systems and further study will be crucial to save the extra lost cost due to

    material wastages.

    Prepared by: Dechasa, Gebrehiwot, Saron 10

  • 8/6/2019 Materials Handling and Wastage Control

    11/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    1.2 Objective of this research

    The main objectives of this research are:

    Assess whether material handling and wastage control problems

    exist or not?

    Find out the main causes of material wastage and poor material

    handling.

    Explore the side effects of material wastage and poor material

    handling.

    Forward appropriate material wastage reducing techniques and

    poor material handling corrective procedures to alleviate problems

    faced on different stages of the project.

    1.3 Methodology

    The methodology adopted for this research is based on actual survey. In this

    process data has been collected and discussion has been made with different

    professionals from the low cost housing construction sector.

    For the data collection survey, construction industry stakeholders like

    contractors, consultants and employer, local firms that actively participating

    in low cost housing construction projects have been selected to fill our

    questionnaires.

    Analysis of the collected survey data and interviews are used to answer thefollowing four vital questions:

    Is material handling and wastage control problem exist or not in LCH

    projects?

    What are the major causes of material wastage and handling

    problems?

    Prepared by: Dechasa, Gebrehiwot, Saron 11

  • 8/6/2019 Materials Handling and Wastage Control

    12/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    What are the side effects of the problems in the project?

    What are the proposed systems used to minimize poor material

    handling and wastage?

    The following procedure were used in order to prepare the research

    Procedure DescriptionTopic SelectionResearch proposal We discussed with our advisor on the contents of

    research proposal.Literature review Referring different literatures and assessing different

    web sites through internet then supervised by our

    advisor.Research instrument Questionnaire survey and desk study were done.Data collection Questionnaire were collected from respondentsSample identification Taking all samplesAnalysis Analysis were done on the collected questionnaireThesis writingSubmission

    1.4 Scope and limitation

    The scope of this research bases only to Low Cost Housing projects in Addis

    Ababa. The limitations are time for the research, and absence of conducted

    researches on construction material handling and wastage control system,

    since LCH projects have been started in recent times and due to lack of

    properly collected and documented datas.

    1.5 Structure of the paper

    This paper comprises of four chapters:

    Chapter two present an overview of different literatures on construction

    materials management and causes of poor material handling and

    wastage in construction industry, chapter three deals with the analysis of

    the collected data, and chapter four explains the conclusion and

    recommendations of the findings.

    Prepared by: Dechasa, Gebrehiwot, Saron 12

  • 8/6/2019 Materials Handling and Wastage Control

    13/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    CHAPTER TWO

    2. LITERATURE REVIEW

    2.1 CONSTRUCTION MANAGEMENT

    Different writers define construction management on their own ways as;

    Construction management is defined as the art of arranging and/or

    organizing various activities, operating equipment and group of people in

    a suitable manner to create systematic operation with continuity to

    achieve a common goal. Management can also be defined as the use of

    people and other resources to accomplish objectives. That is,management by necessity involves the creation of an environment in

    which people can use resources to reach the stated goal. It also involves

    the implementation of the function of management: - planning,

    organizing, implementing and controlling. These functions are the very

    essence of management [3 ].

    Construction management is dealing with the system of how

    relationships among stakeholders, resources and activities are planned,

    implemented and monitored for the successful completion of any

    construction work or activities.

    Construction management addresses how the resources available to the

    manager can be best applied. Typically when speaking of resources for

    construction, we think of the four Ms of construction: Manpower,

    Machine, Material and Money. Management involves the timely and

    efficient application of the four Ms to construct a project. Many issues

    should be considered when managing a project and successfully

    applying the four Ms [2].

    Prepared by: Dechasa, Gebrehiwot, Saron 13

  • 8/6/2019 Materials Handling and Wastage Control

    14/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    2.2 CONSTRUCTION RESOURCE MANAGEMENT

    Construction resource management is a concept of strategically

    managing basic resources for the successful completion of construction

    project.

    A complete resource study identifies when and how many of each trade

    will be on the job site each day of the project. This allows management

    to ensure that work scheduled concurrently is compatible and that

    adequate supervision is provided.

    Efficient & effective implementation of construction project require good

    management of relationships for and among resources, activities and

    stakeholders as applied to the context where such projects are

    implemented. Materials, money, manpower & machineries (the 4M's)

    are usual resources.

    The principal resource involved in construction project is material. The

    correct management of this resource ensures that the stakeholders keeptheir profit and complete the project according to required quality, cost

    and time.

    In our world construction resources are scarce, hard to obtain easily and

    becoming expensive every day in spite of the fact that their demand is

    high. It is this reality which obliged us to utilize them efficiently and

    effectively.

    Prepared by: Dechasa, Gebrehiwot, Saron 14

  • 8/6/2019 Materials Handling and Wastage Control

    15/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    2.3 CONSTRUCTION MATERIALS MANAGEMENT

    Materials management is a process: It is how a building is designed

    and how materials are estimated. It is how materials are acquired and

    even how the packaging is specified. It is how the delivery schedule is

    designed. It is how contractors plan materials use and how they manage

    previously used materials and cuts. It is how waste is managed for use

    elsewhere or recycling rather than being discarded in a landfill [9].

    It is a culture how the customer expects the contractor and the

    contractor its subcontractors and the subcontractors its workers to care

    for and properly manage the materials provided.

    Material Management can be defined as integrated management

    system for planning, controlling or redirecting efforts to achieve a

    smooth, timely, efficient flow of materials to the project in the required

    quality, the required time, and at an acceptable price and quality.

    In building construction projects, materials account for more than 50% of

    the project total cost. A small saving in materials cost through efficient

    management of materials can result in a large contribution.

    A great opportunity for the construction industry to reduce cost and

    increase profit and competitiveness is in the area of materials

    management. Better materials use can, additionally, result in improved

    project economy, conservation of natural resources and reduced

    pollution. Therefore, the opportunity to reduce cost and increase profits

    is also the Opportunity to protect the environment.

    Efficient materials management in project environment calls for an

    integrated approach covering numerous functions such as materials

    Prepared by: Dechasa, Gebrehiwot, Saron 15

  • 8/6/2019 Materials Handling and Wastage Control

    16/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    planning, purchasing, inventory control, store keeping and ware

    housing, handling and transportation, codification and standardization,

    and the disposal of surpluses[1].

    2.3.1 MATERIAL PLANNING

    Materials planning is the key function of materials management, is

    closely linked with project planning and control set up. Both these work

    together to develop a plan for procurement and stocking of construction

    materials so as to provide at site materials of the right quality in right

    quantity at the right prices from the right sources at the right time.

    A few hours spent in planning can produce project cost savings through:* Reducing the amount of materials purchased

    * Better use of the materials purchased

    * Reduced labor in handling materials and having to purchase

    Make-up materials

    * Reduced waste and disposal costs.

    Construction materials planning involves identifying materials,

    estimating quantities, defining specifications, forecasting requirements,

    locating sources of materials approved, designing materials inventory,

    developing procurement plans, and monitoring flow of materials till the

    connected construction works are completed.

    A Materials Management Plan, formulated through the process of these

    guidelines, consist of procedures guiding all the professionals and trades

    involved in the entire process of the building creation from design

    through finish. It is a two-phase plan corresponding to the Design Phase

    and the

    Construction Phase of your project. Within each of these phases there

    are four sections -Review, Reduce, Reuse and Recycle [9].

    The process and results of the planning done in the design Phase

    corresponds directly to the site materials management plan.

    Prepared by: Dechasa, Gebrehiwot, Saron 16

  • 8/6/2019 Materials Handling and Wastage Control

    17/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Design and Construction Phase

    The Plan that design should consider the "Four R's":

    Review: Reconsider the design philosophies and practices. Review the

    company's policies regarding estimating and purchasing and the site

    construction practices. And review the sources of those policies and are

    they valid in today's economy or procedures: ecology?

    Reduce: Reduce quantities purchased as well as waste. A way of looking

    at the estimator's and purchaser's "fudge factor" is that they are actually

    Specifying the waste amounts. More care taken on the jobsite and

    different cleanup practices could dramatically reduce waste. Then finally

    create a substantial list of waste-reducing practices.

    Reuse: Reuse materials as possible. For instance form lumber is used

    more than once, but generally for another concrete form, and used

    plastic film can be stored and used to cover exposed work in case of

    inclement weather.

    Recycle: Plan the recycling of the construction waste before the project

    starts at the site. Once the project is underway, treat the waste recycling

    as rigorously as quality of the construction.

    Prepared by: Dechasa, Gebrehiwot, Saron 17

  • 8/6/2019 Materials Handling and Wastage Control

    18/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    2.3.2 MATERIALS PROVISIONING (PROCUREMENT) PROCESS

    Construction materials needed for a project work vary with the nature

    of the project. The determination of the type, quantity and specifications

    of the construction materials needs a detailed study of the contract

    documents, including the bill of quantities, drawings, specification,

    pretender estimates, and preliminary vendor enquires. Such a study

    consumes considerable time, and is a systematic and gradual process[1].

    Materials Procurement

    Preliminary investigations for developing sources for procurement of

    materials are made by floating enquiry indents, containing quantities,

    specifications and delivery times are jointly prepared by the project

    planning cell and materials procurement department. These are

    processed by the materials procurement department for invitingquotations with samples of materials, where applicable.

    On receipt of quotations, a comparative study of the price, quality,

    delivery time, terms of delivery and payment terms is made jointly by

    both materials and project planning in charges. During the course of this

    study, vendors proposals are compared with enquiry specifications and

    stipulated requirements, and the resulting deviations are examined for

    acceptability. The key criteria for evaluating the potential of the supplier

    to deliver the right quantity product at the right time should include

    quality of material, companys financial status, companys management

    team and their professional competence and engineering skills, and

    support services.

    Prepared by: Dechasa, Gebrehiwot, Saron 18

  • 8/6/2019 Materials Handling and Wastage Control

    19/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    The quotation comparison sheet can be best termed as a summary of

    the alternative proposals for given materials. These proposals undergo

    further processing before making a decision about placing of purchase

    order. The various stages encountered prior to the purchase decisions

    are approval in principle for processing proposals, clients approval of

    proposed materials and negotiations of terms of supply. And the final

    step in the procurement of materials is monitoring materials delivery

    schedule.

    2.3.3 INVENTORY CONTROL

    The term inventory implies the cost of materials in stock at a given

    time. This stock of materials is held to act as a cushion between supply

    and demand. The monetary value of inventory indicates the extent of

    investment required to maintain minimum stock of materials for the

    smooth running of the project. Higher inventory implies higher

    investment, and fewer inventories carry the risk of supplies falling

    behind demand. A balanced inventory acts as a cushion between supply

    and site requirement till supplies are received. It includes pre-

    determined safety stock to cater for slippages in delivery schedules [1].

    Inventory control not only looks into the physical balance of various

    materials but also looks into aspects of minimizing the inventory cost.

    Another aspect of inventory control is control of the inventory carrying

    cost. Avoiding shortage, avoiding excessive stocking and increasing

    inventory turnover, are some of the main issues concerning inventory

    control. Further, methods of reducing the component of materials cost in

    the product cost is an important consideration in cost reduction. This

    means that the purchase of materials should be for the quantity needed

    and the purchase quantity should be neither more nor less. Purchases

    have to be made at the right time and at the most economic cost.

    Prepared by: Dechasa, Gebrehiwot, Saron 19

  • 8/6/2019 Materials Handling and Wastage Control

    20/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Inventory control is therefore a strong management tool for cost

    reduction.

    2.3.4 STORE KEEPING AND WAREHOUSING

    Store keeping: means whereby goods are received, identified, stored,

    issued, account for and replenished in accordance with defined servicelevels and with due regard of legal requirements for health and safety.

    Store keeping is both a science and an art. Some of the essentials of

    good store keeping are assigning and placing each item in a proper

    place, providing protection against damage and pilferage, using proper

    method of identifying and coding, and keeping record and inventory of

    stores up-to-date.

    Warehouse: is a place where items are housed or a building designed

    for storage purposes and constructed with roof and complete side and

    end walls.

    Warehouses must be seen as providing services to the rest of the

    organization in which they operate. The levels of these services will

    affect the overall efficiency of the organization. Therefore, the

    relationship between warehouses and other Departments (or functional

    areas) within the organization are very important aspects of store

    management.

    2.3.5 HANDLING AND TRANSPORTATION

    Materials handling: refers to techniques employed to move, transport,

    Prepared by: Dechasa, Gebrehiwot, Saron 20

  • 8/6/2019 Materials Handling and Wastage Control

    21/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    and store or distribute store items with or without the aid of mechanical

    appliances. The movements of materials to, through, or from productive

    process, and in receiving and shipping areas. Transportation

    encompasses all activities involved in the movement and flow of

    materials from the time they are received to the time they are shipped.

    The transportation costs are affected by shipment sizes and other

    factors. Shipment by the full load of a carrier often reduces prices and

    assures quicker delivery, as the carrier can travel from the origin to the

    destination of the full load without having to stop for delivering part of

    the cargo at other stations. Avoiding transshipment is anotherconsideration in reducing shipping cost. While the reduction in shipping

    costs is a major objective, the requirements of delicate handling of some

    items may favor a more expensive mode of transportation to avoid

    breakage and replacement costs.

    2.3.6 CODIFICATION AND STANDARDIZATION

    The received of goods should be identified by a clear way of

    identification. Without identification it is impossible to uniquely identify

    the materials needed. This problem can be solved using codification.

    The code must be developed to identify all items held in store. All

    materials should be given a code identifying the material specifically,

    definitely, and unambiguously. Adopting a well designed codification

    system enables the stores manage to have a unique, precise (i.e. exact),

    simple and consistent method of identifying stocks. Code should be

    compact, concise, and flexible enough to accommodate future addition.

    The primary purpose of classifying materials is to control quality, cost

    and timely supply. There are many factors that need consideration while

    classifying materials. These include storage space, shelf life, supply

    Prepared by: Dechasa, Gebrehiwot, Saron 21

  • 8/6/2019 Materials Handling and Wastage Control

    22/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    reliability, inventory costs, ease of identification, construction sequence,

    transportation requirement, price, procurement time, procurement

    source and project life.

    2.3.7 DISPOSAL OF SURPLUSES

    Construction activity leads to generate of solid wastes, which include

    sand, gravel, concrete, stone, bricks, wood, metal, paper etc.Construction waste can occur at every stage of the activities but most of

    those involved in the operation do not aware of that. Waste level for

    initial stage of construction activities can be low and the most significant

    waste level can be observed during the construction phase especially on

    site where most of the resources are being used in this stage.

    Construction waste is bulky and heavy and is mostly unsuitable for

    disposal by incineration or composting. Due to continuing shortage of

    dumping sites and increase in transportation cost, the disposal of

    surpluses is very expensive.

    Prepared by: Dechasa, Gebrehiwot, Saron 22

  • 8/6/2019 Materials Handling and Wastage Control

    23/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    2.4 CONSTRUCTION MATERIALS WASTAGE MANAGEMENT

    2.4.1 DEFINITION

    Construction material wastages can be defined as the difference

    between the value of materials delivered and accepted on site and those

    properly used as specified and accurately measured in the work, after

    deducting the cost saving of substituted materials transferred elsewhere

    in which unnecessary cost and time may be incurred by materials

    wastage [4].

    2.4.2 MATERIALS USAGE STANDARDS

    Generally, the materials and labor costs in a project are conceptualized

    during the inception stage by using past experience. While contracting

    the quantities of work involved in a project are detailed in the contract

    bill of quantities. These are derived from the design and drawings. But

    there is inherent materials wastage associated with all types of

    materials.

    Some wastage is inevitable in actual work. This wastage in materials is

    generally expressed as percentage of materials calculated theoretically

    from the quantities of work involved, and is termed as Standard

    Wastage.

    Prepared by: Dechasa, Gebrehiwot, Saron 23

  • 8/6/2019 Materials Handling and Wastage Control

    24/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    The total quantity of materials to be provisioned should cater for the

    standard wastage by increasing the theoretical quantity proportionately.

    Materials to be provisioned

    = Theoretical quantity of materials * (100 + standard wastage

    (%))/100

    Standard wastage of the construction materials depends upon many

    variables such as the nature of work, type of materials, method of

    application, etc.

    It may be noted that standard wastage caters for wastage during

    utilization only for causes considered beyond control at site. In addition

    to the uncontrollable wastage, there is wastage/pilferage which falls in

    the category of controllable wastage. The main causes of controllable

    wastage at various stages can be due to the following:-

    a. Wastage during design and supervision.

    b. Wastage during materials procurement.

    c. Wastage during handling and storage.

    d. Wastage during utilization.

    Since, controllable wastage falls under the purview of the materials

    management staff the additional provisions to compensate for such

    wastage should be made by them so as to ensure that the right quantity

    and right quantity of materials are available at the right time.

    Table 2.1 Construction Materials Wastages Planning Norms [4].

    Item No. Types of Materials Planned Wastage ( % )1 Cement 22 Sand 103 Aggregate 54 Reinforcement steel bars 3

    Prepared by: Dechasa, Gebrehiwot, Saron 24

  • 8/6/2019 Materials Handling and Wastage Control

    25/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    5 Stone masonry 56 Steel sheet roofing 27 Tile roofing 58 Floor tiling 2-59 Marble lining 2010 Reinforced concrete 211 Lean concrete 1012 Painting 5

    2.4.3 CAUSES OF MATERIAL WASTAGE

    Wastage of materials can take place during various stages of the project.

    1. Wastage arising from design may result from the following reasons -

    Dimension dis-coordination.

    Variations in design at the construction stage (demolishing).

    Discrepancies in drawings and specifications.

    Over design.

    Specification failing to match the quality of the building

    required.

    Resistance to adopt alternative materials.

    2. Wastage during procurement can result from one or more of the

    following main causes -

    Buying materials of wrong specification.

    Buying more than the actual requirement.

    Unnecessary buying of items to cater for unrealistic and

    unforeseen eventualities.

    Untimely buying of short-life materials.

    Prepared by: Dechasa, Gebrehiwot, Saron 25

  • 8/6/2019 Materials Handling and Wastage Control

    26/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Improper and unnecessary handling of materials.

    Wastage in transportation.

    3. Wastage during storage can occur due to the following reasons -

    Damaged and breakages during handling.

    Deterioration due to incorrect storage, incorrect maintenance

    and short-shelf life.

    Losses due to fire, thefts and exposure to climatic conditions.

    4. Wastage during utilization (usage) can be attributed to one or more of

    the following reasons -

    Excess quantity estimation.

    Shortage in delivery.

    Theft and pilferage.

    Breakages and damages during handling.

    Lack of pre-work preparation and coordination.

    Inferior quality of materials.

    Improper accounting and poor store keeping.

    Negligent and careless attitude of the supervisor.

    Unforeseen circumstances like accidents, fire, etc.

    High rate of deterioration due to long storage at the place of

    work.

    Over-issues from the central stores and failures to return

    unused surplus materials.

    Prepared by: Dechasa, Gebrehiwot, Saron 26

  • 8/6/2019 Materials Handling and Wastage Control

    27/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    2.4.4 SIDE EFFECT DUE TO MATERIAL HANDLING AND WASTAGE

    CONTROL PROBLEMS

    2.4.4.1. Side effects due to poor materials handling

    a) High level of materials wastage

    Due to poor storage system, materials are exposed to damage, loss,

    vandalism etc. Higher level of wastage may be occurring due to over

    order or under supply of materials. A lot of materials are being wasted

    due to poor handling system and poor workmanship.

    b) Poor materials storage

    When the materials are not in properly arranged, it may cause damage

    to materials and obstruct the handling of mechanical plant. Materials

    should be unloaded and stored near to the point of use to prevent double

    handling of work. Without proper planning a location of materials

    storage, the site may be congested and affect site accessibility. There is

    always a tendency for some of materials to be stored in wrong place. For

    Prepared by: Dechasa, Gebrehiwot, Saron 27

  • 8/6/2019 Materials Handling and Wastage Control

    28/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    example small and valuable items like door closers and lockset, which

    are always stolen by workers or sub-contractors when stored in an open

    store.

    c) Materials shortage or excesses on site

    Without proper planning of ordering and delivering of materials, there is

    a high tendency facing the shortage of materials in site. Excess of

    materials delivered to site creates lot storage problems, if the materials

    are delivered too early on site; the risk of materials damaged by

    progressing works is high.

    2.4.4.2. Side effects due to materials wastage

    a) Low profitability

    The profitability of a project can be influenced by the cost of materials.Large costs can be saved from the materials since it contributes to a

    substantial value of a project. As a rule of thumb, the higher level of

    wastage, the lower profitability of the project. Therefore, sound Material

    Storage Management is needed to maximize profitability of a project.

    b) Construction time delay

    The delay of construction work may occur when wrong types or quality of

    materials are used and the time spent for the re-construction and

    replacement for the goods. Another cause of delays is damages during

    the transit of materials, shortage of materials, and late delivery of

    materials and so on. Without proper planning in Material Storage

    Management, the project is likely to be delayed.

    Prepared by: Dechasa, Gebrehiwot, Saron 28

  • 8/6/2019 Materials Handling and Wastage Control

    29/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    c) Low productivity

    Poor Materials Storage Management will affect productivity. For

    example, a congested site with materials not properly allocated will

    create a lot of double handling works and obstruct the operation works.

    The productivity of the work will be reduced with shortages and delay of

    materials supply that disrupt program.

    d) Environmental impact

    Since the environmental issue is in concern globally, waste generated by

    industrial operations need to be categorized in list of concern too as

    waste levels indicate the appreciation of use of environment natural

    resources. Among those industry operations, construction industry also

    contributes a significant waste to the overall waste volume annually for

    majority country.

    The impact of construction operations on natural conservation is

    cumulative and collective in most situations, such as disturbance ofsensitive habitats and species by water pollution. In addition, where

    large amounts of waste are generated, loss of grassland can result from

    the need for landfill sites.

    New concepts of waste control are being applied in many countries

    nowadays. Material Storage Management (MSM) is in great concern.

    These are all done to ensure the waste is being controlled as well as the

    environmental condition is being protected.

    Prepared by: Dechasa, Gebrehiwot, Saron 29

  • 8/6/2019 Materials Handling and Wastage Control

    30/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    2.4.5 SYSTEM OF MATERIAL WASTAGE CONTROL

    Some unavoidable wastage is inherent during utilization, but it is the

    excessive wastage which is of concern to the management. Excessive

    wastage during the utilization stage affects the productivity adversely,

    and consequently results in extra costs. Productivity control aims at

    minimizing wastage in usage. Productivity control at the construction

    responsibility center level can be broadly divided into accounting for

    materials, analyzing usage variances to determine the causes of

    wastage and implementing measures to minimize wastage [1].

    2.4.5.1 Accounting for Construction Materials

    Materials accounting system documents the materials data, it provides

    the materials procurement status. It shows the holding of materials

    Prepared by: Dechasa, Gebrehiwot, Saron 30

  • 8/6/2019 Materials Handling and Wastage Control

    31/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    inventory for the incoming works. It identifies and quantifies issues of

    materials to the site and it reveals the materials costs.

    Project planners are especially concerned with materials-flow data for

    ensuring the timely procurement of materials, and site availability of

    materials of right quantity and quality at the required time and place.

    They also aim at minimizing wastage during usage, evaluating

    implications of variations from the acceptable wastage standard,

    updating costs, estimates and expenditures of materials, and

    formulating materials costing norms for future works.

    2.4.5.2 Materials Wastage Analysis

    The first step in materials wastage analysis is to quantify standard

    quantity and type of direct material needed for each work item. The

    actual materials consumed for each work item can be complied from the

    material issues and return notes transacted between supervisors and

    stockholders. In case of materials delivered directly to the construction

    sites by the supplier, such as ready-mix concrete from site batching

    plant of fabricated steel for reinforcement from the site steel yard, or

    aggregate from the crusher, the suppliers delivery note along with

    materials return note can be used to determine the quantity consumed

    for a given work item. These issue slips and delivery notes, when

    consolidated from the start to completion of the work-item can give the

    quantities of materials consumed. The difference between the standard

    materials requirement and the materials usually consumed indicates the

    excess (if any) from the accepted materials wastage standard prepared

    at the time of estimation.

    Material usage variance

    Prepared by: Dechasa, Gebrehiwot, Saron 31

  • 8/6/2019 Materials Handling and Wastage Control

    32/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    = standard acceptable materials wastage - Actual materials

    wastage.

    CHAPTER THREE

    3. ANALYSIS

    3.1. PROFILE OF THE QUESTIONNAIRES

    As discussed in the methodology part of this paper, the second approach to

    assess the existence of material handling and wastage problems, the main

    causes of wastage, their side effects and proposed methods is the use of

    questionnaires survey based on firms experience. The questionnaires were

    Prepared by: Dechasa, Gebrehiwot, Saron 32

  • 8/6/2019 Materials Handling and Wastage Control

    33/74

  • 8/6/2019 Materials Handling and Wastage Control

    34/74

  • 8/6/2019 Materials Handling and Wastage Control

    35/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    1

    Is there any material handlingand wastage problem directlyconnected to low cost housingprojects? Yes or No

    A. Contractor

    Yes 100 100

    No 0 0

    B. Consultant

    Yes 100 100

    No 0 0

    C. Employer

    Yes 100 100

    No 0 0

    Fig. 3.1, Existence of materials handling and wastage problems.

    Discussion - The above Table 3.2 and Fig. 3.1 indicated that the

    existence of material handling and wastage problem in projects.

    According to the result found from the survey study, 100% of the

    stakeholders respondents believe that; the materials poor handling and

    wastage problem exist in Addis Ababa Low Cost Housing projects.

    3.3.2 Section two - is related to the major causes of materials poor

    handling and wastage.

    Prepared by: Dechasa, Gebrehiwot, Saron 35

  • 8/6/2019 Materials Handling and Wastage Control

    36/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Table 3.3, Major causes of poor materials handling and wastage.

    Item

    No.Questions

    Respondents

    In No. In %

    2What are the major causes of poor materialhandling and wastage in LCH projects?

    1. Poor workman ship

    A. Contractor 4 50

    B. Consultant 5 63

    C. Employer 4 67

    2. Improper material handling and storagesystem

    A. Contractor 3 38

    B. Consultant 4 50

    C. Employer 4 67

    3. Utilization

    A. Contractor 4 50

    B. Consultant 5 63

    C. Employer 5 83

    4. Design problem

    A. Contractor 6 75 B. Consultant 4 50

    C. Employer 2 33

    5. Variation in design at construction stage

    A. Contractor 4 50

    B. Consultant 2 25

    C. Employer 2 33

    6. Incorrect procurement of materials

    A. Contractor 2 25

    B. Consultant 2 25

    C. Employer 1 177. In bulk material supply by the owner

    A. Contractor 4 50

    B. Consultant 3 38

    C. Employer 3 50

    Prepared by: Dechasa, Gebrehiwot, Saron 36

  • 8/6/2019 Materials Handling and Wastage Control

    37/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Fig. 3.2, Major causes for materials handling and wastage.

    Discussion - Table 3.3 and Fig. 3.2 shows that, the major causes for

    poor material handling and wastage in LCH project. According to the

    survey data, some of the main causes of materials poor handling and

    wastage are poor workmanship, lack of appropriate handling and

    storage, utilization, design problems, variations in design at construction

    stage, incorrect procurement of materials and material supply in bulk

    quantity.

    1. Poor workmanship

    According to the result found from the study, averages of 60% of the

    respondents believe that; poor workmanship is one of the major causes

    of material wastage in LCH project. Besides, most LCH projects are

    awarded on fixed price bases for selected qualified consultants and

    contractors; this makes the contractors unable to employ qualified

    Prepared by: Dechasa, Gebrehiwot, Saron 37

  • 8/6/2019 Materials Handling and Wastage Control

    38/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    professionals and skilled manpowers. In addition to this, since the

    contractor employ laborers with low basic salary, mostly workers seek

    another company which pays better. Thus poor and non-sustainable

    workmanship contributes for the increase of material wastage.

    Photo 1: Material wastage due to poor workmanship, utilization ofimproper quality materials and improper supervision.

    The problem may rise due to poor workmanship during production stage

    and lack of supervision.

    Under supervision the following steps should be properly implemented.

    During production stage; right vibration, quality material selectionand correct mix ratio should be kept.

    The mould has to be cheeked and properly prepared for fixingreinforcement bars and to pour concrete.

    After casting it has to be properly dismantled and get propercuring.

    Until precast beams attain its comprehensive strength, it should beproperly cured. After that it should be well transported to workingsite and properly handled.

    Prepared by: Dechasa, Gebrehiwot, Saron 38

  • 8/6/2019 Materials Handling and Wastage Control

    39/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    This grade beam bulge out is due to lack of quality material selectionand Skilled laborers. As a result of this, the entire bulge out concreteamount increases the wastage limit to become out of standard.

    Photo 3: Excess voids observed on casted grade beam and foundationcolumn junctions due to poor workmanship.

    Prepared by: Dechasa, Gebrehiwot, Saron 39

    Photo 2: Material wastage due to poor workmanship.

  • 8/6/2019 Materials Handling and Wastage Control

    40/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Photo 4: Forwarded recommendations.As observed in photo 3 & 4, materials are wasted due to poorworkmanship; in addition the contractor incurs additional labor cost. Here

    also the employer loses the on time functioning of the building due todelays of project completion time unless some compensation mechanismsimplemented here.

    2. Lack of appropriate handling and storage

    Prepared by: Dechasa, Gebrehiwot, Saron 40

  • 8/6/2019 Materials Handling and Wastage Control

    41/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    As the result of the study shows, nearly 67% of the employer and 50% of

    the consultant believes that, lack of appropriate handling and storage of

    materials by the contractors (sub-contractors) contribute for the wastage

    of materials in the project. Some problems associated with this, are

    damages and breakages during loading and un-loading, deterioration

    due to incorrect storage, losses due to theft and exposure to extreme

    climatic condition. As they replied, wastages are more in cases of labor

    based contracting system, this is because; mostly sub-contractors are

    not sensitive to materials rather, they focus on outputs. Hence the client

    should provide close supervision in order to make the subcontractors

    give attention to material handling and control their negligence.

    Inaddtion to this the owner should provide material handling and

    wastage control item in the contract document.

    Photo 5: Inappropriate material (cement) storage.

    As observed in photo 5, cements are stored directly in contact with floor

    and it is stockpiled randomly.

    Prepared by: Dechasa, Gebrehiwot, Saron 41

  • 8/6/2019 Materials Handling and Wastage Control

    42/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Employer always not supply newly produced reinforcement bars. As it is

    easily observed in the picture, the reinforcement bars get corroded from

    the very beginning. In addition the reinforcement bars not stockpiled

    properly; which means it is placed directly in contact with earth and

    which is not under shed, due to this the corrosion extent enhanced a lot.As a result, it creates a direct additional cost to the contractor and

    delays on project completion time.

    3. Utilization

    As the result of the study shows, 66% of the stakeholders respondent

    believes that; improper utilization (usage) is one of the major causes for

    material wastage. Some of the improper utilization problems mentioned

    is; excess mortar/concrete preparation, poor handling of materials,

    misuse of ratio to various grades, using unsuitable tools and machines,

    and use of dry cement etc.

    Prepared by: Dechasa, Gebrehiwot, Saron 42

    Photo 6: Inappropriate reinforcement stockpiling.

  • 8/6/2019 Materials Handling and Wastage Control

    43/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Prepared by: Dechasa, Gebrehiwot, Saron 43

    Photo 7: Material wastage during concretetransportation to cast a structure.

  • 8/6/2019 Materials Handling and Wastage Control

    44/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Photo 8: Material wastage during concrete mixing.

    4. Design problems

    As the result of the study shows,

    75% of the contractors and 50% of

    the consultants believe that; design

    problems as the major cause for

    material wastage. Some problems associated with this, are over design,

    dimension dis-coordination, and design without soil test. In this case,

    larger material volumes are mandatory for construction than should be

    the case, and this become a cause for material wastages. A good design

    can reduce wastages by considering dimensional coordination and grid

    system of designing.

    5. Variations in design at construction stage

    Prepared by: Dechasa, Gebrehiwot, Saron 44

    Material wastage mostly observedin LCH project to a maximumdegree than other high scale projects. This is due to variousreasons:-

    - LCH projects are labor basedcontract from the verybeginning. Beside this thecontractor not handle thematerials by using propertechniques and mostly the

  • 8/6/2019 Materials Handling and Wastage Control

    45/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    In this section, the study indicates that, 50% of the contractors accept

    variations in design at the construction stage have effect for the increase

    of material wastage in the project. The effect is manifested by not having

    complete design and design change order given to the contractor by the

    consultant or/and employer at the construction stage. Design change

    (modification) at construction stage which leads to the additional

    wastage in the form of demolishing of faulty design works.

    6. Incorrect procurement of materials

    As the result of the study shows, almost 75% of the respondents replied

    that, incorrect procurement of materials does not have an influence on

    material wastage. However, during our site visit and discussion with the

    employees of stakeholders; we have reached to a common

    understanding of its existence, since it is observed on contractors when

    procuring and delivering incorrect materials which are inferior in quality,

    however they remove it from site when it is understood by theconsultant.

    7. In bulk material supply by the owner

    It is agreed by nearly 55% of stakeholders that, bulk supply of materials

    by the owner (AAHDPO) and MSE has influence to the increase of

    material wastage in the project. They have explained the impact of its

    influence as follows:

    a. The supply of materials by the owner (AAHDPO) is not conceding with

    the project material delivery schedule, which facilitates untimely bulk

    supply of materials.

    Prepared by: Dechasa, Gebrehiwot, Saron 45

  • 8/6/2019 Materials Handling and Wastage Control

    46/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    b. Due to lack of supervision, MSEs produce poor quality materials and

    supply materials with out keeping the required quantity and right time.

    Table 3.4, Does the involvement of MSEs increase wastage

    Item

    No.Questions

    Respond

    Respondents

    In No. In %

    3

    Does the involvement of MSE'S havecontribution for the increase ofmaterial wastage in LCH projects?

    Yes or No, if yes what are the side

    effects in your context? Pleaseforward possible justification?

    A. ContractorsYes 6 75

    No 2 25

    B. ConsultantYes 7 88

    No 1 13

    C. EmployerYes 1 17

    No 5 83

    Prepared by: Dechasa, Gebrehiwot, Saron 46

  • 8/6/2019 Materials Handling and Wastage Control

    47/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Fig. 3.3, Does the involvement of MSEs increase wastage

    Discussion - Table 3.4 and Fig. 3.3 shows that, whether the existence of

    MSEs (Micro and Small Enterprises) have contribution for the increase of

    material wastage in the project.

    As the result shows 83% of the employers believe that, the involvement

    of MSEs in this sector does not contribute for the increase of wastage

    while; 75% of the contractors and 87.5% of the consultants replied that,

    their participation in producing and supplying materials has large effect

    on wastages of materials. They have explained the impact of their

    influence as follows:

    a) Production error and lack of perfection on materials like precast

    beams, slab and HCB walls.

    b) Due to lack of supervision, MSEs produce and supply poor quality

    materials.

    Prepared by: Dechasa, Gebrehiwot, Saron 47

  • 8/6/2019 Materials Handling and Wastage Control

    48/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    The main problem we have understood here is that, the MSEs not yet

    got enough training and knowledge which enables them to produce

    materials with required quality and dimension. Due to this reason,

    materials with poor quality and incorrect dimension produced and

    wastages generated.

    3.3.3 Section three - is related to the major side effects of materials

    poor handling and wastage in Low Cost Housing projects.

    Table 3.5, side effects of the problems in the project.

    Item

    No.Questions

    Respondents

    In No. In %

    4What are the side effects of theproblems in LCH projects?

    1. Cost overrun

    A. Contractor 5 63

    B. Consultant 4 50

    C. Employer 4 67

    2. Delay in project completion time

    A. Contractor 3 38

    B. Consultant 4 50

    C. Employer 4 67

    3. Ineffective resource utilization

    A. Contractor 4 50

    B. Consultant 5 63

    C. Employer 5 83

    4. Environmental impact

    A. Contractor 3 38

    B. Consultant 5 63

    C. Employer 3 50

    Prepared by: Dechasa, Gebrehiwot, Saron 48

  • 8/6/2019 Materials Handling and Wastage Control

    49/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Fig. 3.4, Side effects of the problems in the project.

    Discussion - Table 3.5 and Fig. 3.4 shows that the major side effects of

    poor materials handling and wastage in the low cost housing projects.

    Some of the main side effects according to the survey data are cost

    overrun, delay in project completion time, ineffective resource utilization,

    and environmental impact.

    1. Cost overrun

    According to the result found from the study, averages of 60% of the

    stakeholders respondents believe that materials poor handling and

    wastage affects the expected project cost planned by employer and

    contractor. More over as stated in the literature review section 2.3 in

    building construction projects materials account for more than 50% of

    the project total cost. The effect is manifested by not using proper

    handling during procurement, transportation, storage, and utilization.

    Prepared by: Dechasa, Gebrehiwot, Saron 49

  • 8/6/2019 Materials Handling and Wastage Control

    50/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    2. Delay in project completion time

    As the result of the study shows nearly 53% of the stakeholders

    respondents believe that project completion time is affected having

    materials poor handling and wastage in projects. During our discussion

    with the project engineers the delay of construction work may occur

    when wrong types or quality of materials are used and the time spent for

    the re-construction and replacement for the goods. Another cause of

    delays is damages during the transit of materials, shortage of materials,

    and late delivery of materials and so on.

    3. Ineffective resource utilization

    As the result of the study shows nearly 83% of the employer and 63% of

    the consultants believe that materials poor handling and wastage affects

    the planned quantity of material to complete a project. Lack of

    appropriate handling and storage of materials by the contractors

    (subcontractors) contribute for wastage of materials in projects.

    4. Environmental impact

    According to the result found from the study shows nearly 50% of the

    stakeholders respondents believe that wastes due to materials poor

    handling and wastage is easily affect the environment. The impact of

    construction operations on natural conservation is cumulative and

    collective in most situations, such as disturbance of sensitive habitats

    and species by water pollution. In addition, where large amounts of

    waste are generated, loss of grassland can result from the need for

    landfill sites.

    Prepared by: Dechasa, Gebrehiwot, Saron 50

  • 8/6/2019 Materials Handling and Wastage Control

    51/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    3.3.4 Section Four: proposed systems and methodologies used to

    minimize materials wastage and to maintain proper material handling

    from the three stakeholders point of view.

    Material is the large portion of the project cost; our profit is highly

    depending on proper utilization of material resources at different stage

    of the project time. Because of this reason, stakeholders forward the

    following systems to minimize material wastage and poor material

    handling.

    Table 3.6, proposed systems to minimize poor material handling and wastages.

    Stake holders Proposed and practiced systemsA.

    Contractors

    Assignment of follow up engineer by preparing

    checklists.

    Training is forwarded to engineers (senior and

    fresh) and to other relevant skilled laborers with in

    some interval or as it need.

    Regular meeting evaluation which obtain one major

    agenda about material handling and its standard

    utilization.

    Providing bonuses, position increment, preparing

    scheduled recreational time to efficient laborers and

    professionals as per their position and

    encouragement on different aspect.

    Bar schedule preparation, finance budgeting; break

    downed material schedule preparation before

    forced to executions.

    Recycling, for example wastage created during

    plastering, concrete placing and mixing. All these

    material wastage will be processed again to use for

    ordinary works.

    Prepared by: Dechasa, Gebrehiwot, Saron 51

  • 8/6/2019 Materials Handling and Wastage Control

    52/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    The contractor should take care on handling of

    materials during loading, unloading, transportation

    and utilization periods.

    The contractor should have taken right mix, quality

    material and properly staffed human resource.

    Stake holders Proposed and practiced systemsB.

    Consultants

    Giving orientation and briefing for the cause of

    wastages to construction materials in LCH projects

    such as slab & wall HCB's, Precast beam & onmajor raw materials such as cement, reinforcement

    bar, sand & gravel.

    Filling inspections on materials before they brought

    in to the building to construct slab or HCB wall.

    Preparing checklists, material handling procedure

    and systems on storing, placing and on how

    material management can be handled. Providing special training to supervisors, how they

    should handle the project to the extent low cost

    demands with in some intervals to create

    awareness.

    Assisting the contractors in how & where to store

    materials when supplied by the client.

    Warning contractors by writing on site book to

    create a good management after repeated oral

    communication and that obliged the contractors to

    proceed by full filling their responsibility.

    Consulting offices are trying to prepare trainings for

    most stakeholders like Engineers under Consulting

    Prepared by: Dechasa, Gebrehiwot, Saron 52

  • 8/6/2019 Materials Handling and Wastage Control

    53/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    offices, contractors, suppliers & MSE's about how to

    accomplish the project with appropriate quality,

    relative completion time & better profit with less

    wastage.

    The consulting office should properly asses the

    project site before rushing to the design work and

    forces the contractor to implement it. Here soil

    exploration must be the first mandatory and helpful

    data for design work.

    Stake holders Proposed and practiced systemsC. Employer The organization should take random follow up and

    supervision not only on materials production but

    also due attention should be taken during loading,

    un loading, transportation and usage of materials.

    Appreciate position rewarding to efficient

    professionals to acquire better knowledge, here

    rewarding goes to the degree of additional work

    provisions to the constructing parties.

    All stake holders should keep their responsibilities

    to achieve targets.

    Discussion - Table 3.6 shows the systems practiced and proposed

    techniques used to minimize poor material handling and wastage. To

    avoid these problems, majorly all stakeholders agreed on staff training,

    close supervision, proper work force staffing, and utilization of different

    wastage reduction mechanisms including innovations are the basics. Out

    of them, specifically clients have weaknesses in supervising MSEs. In

    addition to this all the stakeholders should try to have good relationship

    among others in order to minimize materials poor handling and wastage

    in low cost house projects.

    Prepared by: Dechasa, Gebrehiwot, Saron 53

  • 8/6/2019 Materials Handling and Wastage Control

    54/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    CHAPTER - FOUR

    4. CONCLUTION AND RECOMMENDATION

    4.1. Conclusion

    The research on Material handling and wastage control in Addis Ababa Low

    Cost Housing projects is concluded with the following points:

    1. Stakeholders should know how projects properly managed

    concerning materials.

    2. The client and MSEs do not use proper material delivery system.3. From observation, material wastage is mostly created due to

    utilization, poor workmanship, design problem and improper

    material handling and storage systems.

    4. From the research findings, training and workshop requirement is

    mandatory for the reduction of material wastage.

    5. On most observed sites, poor quality materials exist due to lack of

    strong supervision on the production of materials like precast beams, slabsand wall HCBs.

    6. Building participants are often lacking skill and knowledge in applying

    wastage minimization techniques in their daily work. Hence, there is a

    natural tendency among architects, engineers and contractors to use the

    more familiar conventional methods.

    7. Unless we familiarized and go in to practice on wastage reduction

    techniques, the following major out comings will be observed widely on

    most project sites. Major out comings are project cost increase, great lost

    for the owner and to other participated stake holders, work will be delayed

    due to the overall material shorten and environment risk.

    8. Wastage is unavoidable in construction work; but by applying

    appropriate controlling system, we can minimize it.

    Prepared by: Dechasa, Gebrehiwot, Saron 54

  • 8/6/2019 Materials Handling and Wastage Control

    55/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    4.2 Recommendation

    1. A proper way to handle the project is early planning.2. The client should follow proper material delivery system.

    3. Developing staff training, Staffs or workers have to be consulted to

    ensure they know how to handle the materials correctly and try to

    reduce wastage.

    4. Proper design should be implemented which considers material

    wastage reduction.

    5. Communication between the designer and contractor is important

    so that each realizes how the design decisions will affect on site

    operations and wastage generation.

    6. Implementation of environmentally friendly construction methods.

    7. Selections of the best reputation contractor have to be made to

    insure the wastages are minimized.

    8. Try to implement innovations like low-wastage building

    technologies by avoiding obstacles.

    9. Technical problems of a few new construction methods have to be

    overcome before they can be widely adopted.

    10. Developing Information and record management system.

    11. Use appropriate wastage minimizing techniques for LCH projects.

    12. Further study is recommended on material handling and wastage

    control system.

    Prepared by: Dechasa, Gebrehiwot, Saron 55

  • 8/6/2019 Materials Handling and Wastage Control

    56/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    APPENDIX - A

    RESEARCH PROPOSAL

    Research title :

    Material Handling and wastage control in Addis Ababa low cost

    housing projects.

    Research goal :

    To investigate any existing material wastage and poor materialhandling, studying their causes and side effects and for forwarding

    improved systems to minimize wastages and correct poor material

    handling systems to LCH projects.

    Research objectives :

    To investigate the presence of material handling and

    wastage control problem on LCH project including its extent.

    To find out the main causes of material wastage and poor

    material handling.

    To explore the side effects of material wastage and poor

    material handling on LCH project.

    To forward latest material wastage reducing techniques and

    poor material handling corrective procedures to alleviate

    problems faced on different stages of the project.

    Research background :

    Prepared by: Dechasa, Gebrehiwot, Saron 56

  • 8/6/2019 Materials Handling and Wastage Control

    57/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    In order to respond the high demand of population housing problem in

    respect to economy and land resource utilization, the Ethiopian

    government has give due attention for low cost housing. Besides it is

    believed that it creates better urbanization, job opportunity to

    unemployed large number of young people and become fair living

    sites especially to low-income citizens of the city. Since building

    construction materials account more than 50% of the total project

    cost and LCH projects target cost-efficient house construction, and

    using effective wastage control systems and proper material handling

    is vital for the reduction of cost expenditure due to poor material

    handling and problems on material wastages. The research is tried to

    describe different crucial systems to avoid excess wastages.

    Research problems :

    1. Problem statement:-

    Identify and use appropriate systems to minimize

    material wastages and poor material handlings available in

    LCH projects.

    2. Research questions:-

    What is material handling and wastage control system?

    Is materials handling and wastage problem exist? If it

    exists, what are the main causes and to what extent itappears?

    To what degree, the stake holders share and give

    outstanding solution for the problems appear associated

    with wastage?

    Prepared by: Dechasa, Gebrehiwot, Saron 57

  • 8/6/2019 Materials Handling and Wastage Control

    58/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    What are the effects of excess wastage and materials

    poor handling to the project and what are the proposed

    remedial measures to reduce these problems?

    Research context :

    Out of the construction materials, Cement, Reinforcement bar, slab

    and wall HCBs, prefabricated concrete elements etc are the main

    inputs for the construction of LCH buildings. However, since we are

    not using the materials properly, we obliged to face different type

    of wastages in degree. These wastages are:

    Wastage during design and supervision.

    Wastage due to incorrect purchasing.

    Wastage during transportation, handling and storage.

    Wastage during utilization (construction).

    And these again, will lead to have maximum wastages for most

    items of works. Which shows stake holders are not yet give due

    attention for wastages created in different stages of the project. So

    we try to explore in depth the menses and strengthening

    mechanisms to reduce wastages.

    Research concept :

    Weakness to minimize controllable wastage of materials and attain

    the permissible percentage of construction material wastage is a

    Prepared by: Dechasa, Gebrehiwot, Saron 58

  • 8/6/2019 Materials Handling and Wastage Control

    59/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    big problem. Therefore the research will find out causes and

    weaknesses to reduce wastage and give appropriate solutions.

    Research Methodology :

    Survey & Desk study

    1. Survey:-

    Research data type is Qualitative (problem solving & case

    study approach).

    Research instrument; postal questioners.

    Data Source; study population will be taken from the

    following categories of project stake holders:

    Employers

    contractors

    consultants

    Data collection

    Data analysis

    2. Desk Study:-

    For contextual concept development.

    Research processes :

    Topic

    Proposal Literature review

    Research instrument

    Data collection

    Analysis

    Thesis writing

    Prepared by: Dechasa, Gebrehiwot, Saron 59

  • 8/6/2019 Materials Handling and Wastage Control

    60/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Research time schedule :

    Advisor: - Ato Belay Yitayew

    Submitted by: - Dechasa Haile

    Gebrehiwot Hintsay

    Saron Anteneh

    APPENDIX - B

    Addis Ababa UniversityFaculty of Technology

    Department of Construction Technology andManagement

    Questioner on Material handling and wastage control in AddisAbaba low cost housing projects

    Prepared for Contractors

    Profile

    Name:

    Profession:

    Organization: .

    Years of Experience: ..

    Position:

    Prepared by: Dechasa, Gebrehiwot, Saron 60

  • 8/6/2019 Materials Handling and Wastage Control

    61/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    1. Is there any material handling and wastage problem directlyconnected to low cost

    housing ( ) ?

    Yes No2. If your answer is yes, what are the consequences?A) Cost over run.B) Delays of project completion time.C) Ineffective material resource utilization.D) Environmental impact.Please, brief all how it affects.

    A)

    B).C)

    D).

    3. Is there any material handling problem and causes for constructionmaterial wastage due to delivering of construction material in bulk

    amount to the site by the client?

    Yes No4. If yes, please mention the impacts of its influence?

    Prepared by: Dechasa, Gebrehiwot, Saron 61

  • 8/6/2019 Materials Handling and Wastage Control

    62/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    ..

    5. Is the involvement of micro & small enterprises (MSE), havecontribution for the increase of wastage in producing and supplyingmaterials such as HCB, precast elements etc?

    Yes No6. If your answer is yes, please describe it?

    ..

    7. What is your recommendation to minimize material handling &wastage control system in LCH projects with respect to MSEs materialdelivery system?

    ..

    8. In your opinion, which creates cost over run and delays on projectcompletion time due to material wastage and poor material handling inLCH projects?A) Over design during design period,B) Contractors negligence,

    Prepared by: Dechasa, Gebrehiwot, Saron 62

  • 8/6/2019 Materials Handling and Wastage Control

    63/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    C) Delay in material selection and approval,D) Delay in material supply by the owner,Please, brief how it affects.A)

    B).C)D).

    9. What is your opinion, on the effect of workmanship quality duringutilization of materials on site with respect to wastage of constructionmaterials?..

    10. Lack of sufficient stock area for construction materials on site, couldit be a cause for material wastage?

    Yes No11. If yes, how it will be modified?

    Prepared by: Dechasa, Gebrehiwot, Saron 63

  • 8/6/2019 Materials Handling and Wastage Control

    64/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    ..

    12. What are the major causes that enhancing material wastages in yourcompany? Please circle one or two and illustrate.A) Lack of appropriate attention for handling and storing,B) Poor workmanship at site,C) Improper material procurement,D) Inexperienced project managers,E) Variations in design at the construction stage (demolishing),F) Delay in material selection and approval,( )( )( )

    13. What kind of methodology you adopt to your company for minimizingmaterial handling and wastage problems?

    ..

    Prepared by: Dechasa, Gebrehiwot, Saron 64

  • 8/6/2019 Materials Handling and Wastage Control

    65/74

  • 8/6/2019 Materials Handling and Wastage Control

    66/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    ..

    3. If your answer is yes, what problems your companies observe duringsupervision period?..

    4. Based on question no 1, is there any remedial measures taken by yourcompany to resolve problems, if problems come in to view?..

    5. Is there any design modification made by your company to reduce

    material wastages in low cost house (LCH) project?

    Yes No6. If your answer is yes, please describe it?

    Prepared by: Dechasa, Gebrehiwot, Saron 66

  • 8/6/2019 Materials Handling and Wastage Control

    67/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    ..

    7. What are the major causes that enhancing material wastages in yourcompany? Please circle one or two and illustrate.A) Over design,B) Dimension dis-coordination during design stage,C) Variations in design at the construction stage (demolishing),D) Inexperienced project supervisors,E) Delay in material selection and approval,F) Resistance to adopt alternative materials.( )( )( )

    8. Is the involvement of micro & small enterprises (MSE), havecontribution for the increase of wastage in producing and supplyingmaterials such as HCB, precast elements etc?

    Yes No9. If your answer is yes, please describe it?

    ..

    10. In your observation, which one lead to create maximum materialwastage in LCH projects?A) Contractors negligence,

    Prepared by: Dechasa, Gebrehiwot, Saron 67

  • 8/6/2019 Materials Handling and Wastage Control

    68/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    B) Poor workman ship,C) Improper material handling and storage,D) Delay in material supply by the owner,E) Unconcerned supervisory staff,

    Please circle one or two and illustrate.( )( )

    11. What kind of methodology and system you adopt to your company,in minimizing material handling problem and wastage controls for LCHprojects?..

    Prepared by: Dechasa, Gebrehiwot, Saron 68

  • 8/6/2019 Materials Handling and Wastage Control

    69/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Addis Ababa UniversityFaculty of Technology

    Department of Construction Technology andManagement

    Questioner on Material handling and wastage control in AddisAbaba low cost housing projects

    Prepared for Employers

    Profile

    Name:

    Profession:

    Organization: .

    Years of Experience: ..

    Position:

    1. Is there any material handling and wastage problem directlyconnected to low cost

    housing ( ) ?

    Yes No

    Prepared by: Dechasa, Gebrehiwot, Saron 69

  • 8/6/2019 Materials Handling and Wastage Control

    70/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    2. If your answer is yes, what are the side effects?A) Cost over run.B) Delays of project completion time.

    C) Ineffective material resource utilization.D) Environmental impact.

    Please, brief all how it affects.

    A)

    B).

    C)D).

    3. Which type of material wastage problem is mostly your organizationfaced in LCH projects?A) Due to designB) Due to procurement of materials

    C) Due to material storage & handlingD) Due to utilization

    Please, brief all how it affects.A)

    Prepared by: Dechasa, Gebrehiwot, Saron 70

  • 8/6/2019 Materials Handling and Wastage Control

    71/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    B)

    .

    C)

    D)..

    4. What are the main causes that enhancing material wastages yourorganization observe in LCH projects?A) Contractors negligenceB) Poor workman shipC) Improper material handling and storageD) Variations in design at the construction stageE) Unconcerned supervisory staffPlease circle one or two and illustrate.

    ( )( )

    ( )

    5. Is the involvement of micro & small enterprises (MSE), havecontribution for the increase of wastage in producing and supplyingmaterials such as HCB, precast elements etc?

    Prepared by: Dechasa, Gebrehiwot, Saron 71

  • 8/6/2019 Materials Handling and Wastage Control

    72/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    Yes No6. If your answer is yes, please describe it?

    7. Is there any mechanisms designed by your organization for wastage

    control?

    Yes No8. If your answer is yes, what are the mechanisms?

    Prepared by: Dechasa, Gebrehiwot, Saron 72

  • 8/6/2019 Materials Handling and Wastage Control

    73/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    REFERENCES:

    1. K.K Chitkara: Construction Project Management. Planning,

    Scheduling and Controlling - Second reprint 2000.

    2. Er. D. Lall: Construction Management Reprint 2004.

    3. Wubishet Jekale Mengesha (Dr.Ing), Principles of Construction

    Management

    4. Management Development Program (MDP) in Professional

    Project Management Course Material, Organized by Sileshi

    Consult, in association with Nehru Institute of Construction and

    Enterprise, INDIA.

    5. Matiwos Ensermu, Material Handling and Stores Management,

    Addis Ababa University College of Commerce, hand out 2006.

    6. Document (terms of reference) prepared for lideta urban

    renewal, AAHDPO, Unpublished.

    7. Ingo Becker, Successes in Capacity Development Low Cost

    Housing Program 2003.

    8. Technical Manual for Low Cost Housing Volume 2, GTZ IS,

    2003

    Prepared by: Dechasa, Gebrehiwot, Saron 73

  • 8/6/2019 Materials Handling and Wastage Control

    74/74

    Material handling and wastage control in Addis Ababa low cost housing projects

    9. Construction Materials Management. Guide lines for economy

    and ecology in design and construction. Prepared by, AIA

    Houston, a chapter of the American Institute of Architect.

    10. M. Osmani, Reducing Waste Through Architectural Design

    Practices 2007.

    11. http://[email protected] Construction Waste

    Minimization.htm, accessed on December 15, 2009.

    http://[email protected]/http://[email protected]/

Recommended