Date post: | 20-Dec-2015 |
Category: |
Documents |
View: | 214 times |
Download: | 1 times |
Materials Management
BUS 3 – 141
Ensuring Continuous Supply and Optimizing Inventory Levels
Feb 11, 2008
Page 2 2
Agenda
– Questions from Last Week
– Forming Teams
– “Ensuring Continuous Supply
– Optimizing Inventory Levels
– Continued MRP overview
Page 3 3
Case: Connecticut Circuit Manufacturers p 173 Due Feb 181. FACTS OF THE CASE
Quantitative data (Revenue, Inventory, Costs, Employees, Divisions, etc….)
Approx. 20% of Total Effort / Grade
2. BUSINESS ISSUES IDENTIFIED Customers, Suppliers, Internal Measurement Systems, Organization, Competitors, Supply Shortages, Price Increases, Cash Flow, etc…)
Approx. 20% of Total Effort / Grade
3. CONCLUSIONS What has been going well? What needs improvement?
Approx. 25% of Total Effort / Grade
4. RECOMMENDATIONS What improvements should be made? What (if any?) activities should be stopped? How can the improvements be implemented?
Approx. 35% of Total Effort / Grade Be concise. Use a format equivalent to what you would use in writing a persuasive email to your boss. Try to limit your report to no more than one page, single-spaced. Longer will be accepted, but is not required.
Page 4 4
Reasons for Carrying Inventory
– Revenue Have what Customers want, when they want it Compensate for non-linear demand that doesn’t match your
capacity Buffer for upside demand Buffer for when competitors cannot deliver Buffer against unexpected internal supply problems
Carrying Buffer inventory is necessary, but continuous, relentlessefforts to minimize variability, and thus eliminate the need for
the Buffers is greatly preferred
Page 5 5
Reasons for Carrying Inventory
– Cost Minimize shortages, to avoid delays and idle time Optimize plant, people, and equipment utilization Obtain volume discounts for favorable unit pricing Hedge against future price increases
Optimizing utilization and unit pricing are valuable only whenthe goods made or purchased will SOLD to a paying Customer
in a reasonable time
The cost of a STOCKOUT is hard to quantify,but is to be AVOIDED at all times
Page 6 6
Types of Inventory
RawMaterials
WorkIn Process
(WIP)
FinishedGoods(FGI)
Maintenance,Repair, & Operating
Supplies (MRO)
ResaleItems
Manufacturing All
Egg Mix Water
Cake Icing
ChocolateCake
Finished Goods
Subassembly (WIP) Raw Material
Raw
MRO
Page 7 7
ABC Classification – the 80/20 Rule Applied
* From Leenders, Johnson, Flynn, and Fearon, Purchasing and Supply Management, Thirteenth Edition, McGraw Hill Irwin
Page 8 8
ABC Classification is not based on unit cost
Unit Cost Annual Volume Annual SpendA High High HighA High Medium HighA Medium High HighA Low Very High HighB High Low MediumB Medium Medium MediumB Low High MediumC Medium Low LowC Low Medium LowC Low Low Low
C Items can still stop a production lineand cause Customer Shipments to be missed!
Page 9 9
Costs of Inventory
– Carrying Costs Capital (Interest and Opportunity Costs) Warehouses and Stock rooms Personnel Insurance Damage and Loss Theft Insurance Taxes
– Other Costs Ordering Costs Setup Costs Stockout Costs
• Lost Sales• Idle labor and equipment• Expedite fees
Page 10 10
Lead Time
PlanningOrderingMaterials
Set upProduction
Production TransitPackaging Receipt
Will be addressed directly in Later Chapters
Page 11 11
Lot Sizing: The Economic Order Quantity (EOQ)
Annual C
ost
($)
Quantity Ordered
ordering costs
carrying costs
EOQ
total cost
CTmin
A conceptual model that balances Carrying Costs and Ordering Costs.Somewhat limited, but often useful for C Items
* From Leenders, Johnson, Flynn, and Fearon, Purchasing and Supply Management, Thirteenth Edition, McGraw Hill Irwin
Page 12 12
Lot Sizing: Order Quantities
Fixed Quantity P/D 1 2 3 4 5 6 7 8 9 10 11 12 13Requirement 872 500 400 500 400 500 400 400 400 400 400 500 500Planned Order 1,000 1,000 1,000 1,000 1,000 1,000 1,000Projected Available 128 628 228 728 328 828 428 1,028 628 228 828 328 828
P/D 1 2 3 4 5 6 7 8 9 10 11 12 13Requirement 872 500 400 500 400 500 500 400 400 400 400 500 500Planned Order 2,272 1,800 1,700 500Projected Available 1,400 900 500 0 1,400 900 400 0 1,300 900 500 0 0
P/D 1 2 3 4 5 6 7 8 9 10 11 12 13Requirement 872 500 400 500 400 500 400 400 400 400 400 500 500Planned Order 872 700 700 700 700 700 700 700 700Projected Available 0 200 500 0 300 500 100 400 0 300 600 100 300
P/D 1 2 3 4 5 6 7 8 9 10 11 12 13Requirement 872 500 400 500 400 500 400 400 400 400 400 500 500Planned Order 1,000 500 500 500 500 500 500 500 500 500 500 500Projected Available 128 128 228 228 328 328 428 28 128 228 328 328 328
P/D 1 2 3 4 5 6 7 8 9 10 11 12 13Requirement 872 500 400 500 400 500 400 400 400 400 400 500 500Planned Order 872 500 400 500 400 500 400 400 400 400 400 500 500Projected Available 0 0 0 0 0 0 0 0 0 0 0 0 0
TIME PERIODSame quantity whenever material is needed
Fixed PeriodCalculates requirements for n periods. Example = 4 periods
E O QCalculated to balance Inventory & Ordering Costs
Supplier Multiple
Similar to Fixed
Lot-For-Lot
Maps exactly to Requirements
Page 13 13
Example of how Inventory is Consumed and Reordered
lead time (L)
ROP
cyclestock
INVENTORY
TIMEROP = L × d
* From Leenders, Johnson, Flynn, and Fearon, Purchasing and Supply Management, Thirteenth Edition, McGraw Hill Irwin
Page 14 14
Forecasting
– Estimate of future events
• Weather• Future Sales• Stock Prices• Other
– Several Methods
• Quantitative• History and Patterns• Leading Indicators (Housing Starts & Furniture)
• Qualitative• Judgment• Consensus
Forecasts WILL be wrong – the goal is to predict as closely as possible
Page 15 15
A Forecast serves many Purposes
RegionProduct
LineChannel Features Product Customer
Scheduling Factory VolumesMaterials Planning Balancing Factory CapacityAssessing Direct Cost @ MixesAnalyzing Absorption implications
Revenue Planning Revenue Scenarios Allocation CriteriaCommissions & Quotas
Estimating TAM and SharePricing TargetsPrograms & PromotionsMargins @ MixesMessage to Analysts
Business Need / Benefit
WHAT is done and WHY?
Page 16 16
Forecast accuracy varies over time
0 +1 +2 +3 +4 ………………………………………… +n
Exp
ecte
d E
rro
rs
Over
Under
Time in Future (Weeks)
The further into the future, the harderto predict details with accuracy
Page 17 17
Relationship of Lead Time, Forecast, Inventory, and Cost
Need toForecast
InventoryLevels inPipeline
Cost toManage
Risk ofExcess
Long Lead Time
Short Lead Time
High High Higher Higher
Low Low Lower Lower
Page 18 18
Just-In-Time (JIT)
Will be addressed directly in Later Chapters
Material Requirements Planning Introduction and Overview
Page 20 20
Highest Level MRP Logic
ProductPlanning
DemandPlanning
MaterialPlanning
MasterProductionScheduling
ProductionDelivery
& Service
Will haveItalian Food
Dinner onSaturday
Recipes &Ingredients
Menu Cooking Eating!
Business Terms:
Life Terms:
Page 21 21
MRP Logic is Constantly Balancing Supply & Demand
What you NEED (Demand)
• Final Assemblies– Sales Orders– Forecast
• Components and Subassemblies:– Higher level Starts– Higher level Work Order Shortages
What you HAVE (Supply)
• Stockroom Inventory• WIP Stores Inventory• Open Work Orders• Open Purchase Orders
What you NEED TO GET and WHEN you need to get it (MRP output)
• Planned Purchase Orders• Planned Work Orders• Rescheduled Work Orders• Rescheduled Purchase Orders
Page 22 22
MRP “Nets” Inventory Balance On Hand just like a Checkbook
Item/Descr. Where Used QPA OH LT Past Due 31-Jan 7-Feb 14-Feb 21-Feb 28-FebSJSU141 MB1234 1 0 1 Gross Requirement 0 50 50 70 100 40Mother Board On Order 0 70 100 10 0 0
Projected Available 0 20 70 10 -90 -130Planned Order Complete 0 0 0 0 90 40Planned Order Starts 0 0 0 90 40 0Cum Planned Order 0 0 0 0 90 130
is Equivalent to:
DATE TRANSACTION SUBTRACT ADD BALANCE31-Jan-07 BEGINNING BALANCE 031-Jan-07 RECEIVE WORK ORDER 70 702-Feb-07 SHIP TO CUSTOMER 50 207-Feb-07 RECEIVE WORK ORDER 100 1209-Feb-07 SHIP TO CUSTOMER 50 70
14-Feb-07 RECEIVE WORK ORDER 10 8016-Feb-07 SHIP TO CUSTOMER 70 1023-Feb-07 SHIP TO CUSTOMER 100 (90)2-Mar-07 SHIP TO CUSTOMER 40 (130)
Page 23 23
MRP Netting Logic Illustration
MV2002 SJSU141 1 80 2 Gross Requirement 0 0 0 90 40 0Processor On Order 0 0 0 0 0 0
Projected Available 80 80 80 -10 -50 -50Planned Order Complete 0 0 0 10 40 0Planned Order Starts 0 10 40 0 0 0Cum Planned Order 0 10 50 50 50 50
MV2004 SJSU141 2 80 3 Gross Requirement 0 0 0 180 80 0Power Supply On Order 0 0 150 0 0 0
Projected Available 80 80 230 50 -30 -30Planned Order Complete 0 0 0 0 30 0Planned Order Starts 0 30 0 0 0 0Cum Planned Order 0 30 30 30 30 30
Quantity Per
Assembly Quantity On Hand
Lead Time
Item/Descr. Where Used QPA OH LT Past Due 31-Jan 7-Feb 14-Feb 21-Feb 28-FebSJSU141 MB1234 1 0 1 Gross Requirement 0 50 50 70 100 40Mother Board On Order 0 70 100 10 0 0
Projected Available 0 20 70 10 -90 -130Planned Order Complete 0 0 0 0 90 40Planned Order Starts 0 0 0 90 40 0Cum Planned Order 0 0 0 0 90 130
Page 24 24
MRP is EXTREMELY DEPENDENT on ACCURATE DATA
OpenPurchase
Orders
InReceiving
OpenWork
Orders In a higherAssemblies
In theStockroom
InFinishedGoods
Shipped
In a WIPLocation
In WIP
EVERY time inventory is moved, a TRANSACTION must be executed
The system MUST see ALL inventory in ALL of these categoriesat ALL times