+ All Categories
Home > Documents > Materials Planning - Forecasting

Materials Planning - Forecasting

Date post: 06-Apr-2018
Category:
Upload: vinaycool12344150
View: 221 times
Download: 0 times
Share this document with a friend

of 35

Transcript
  • 8/3/2019 Materials Planning - Forecasting

    1/35

    Materials Planning

  • 8/3/2019 Materials Planning - Forecasting

    2/35

    Dealing with the Problem Complexitythrough Decomposition

    AggregatePlanning

    Master ProductionScheduling

    Materials RequirementPlanning

    AggregateUnit Demand

    End Item (SKU) Demand

    Capacity and Aggregate Production

    Plans

    SKU-level ProductionPlans

    Manufacturing

    andProcurement lead times Component Production lots and due

    datesPartprocess

    plans

    (Plan. Hor.: 1 year, Time Unit: 1month)

    (Plan. Hor.: a few months, Time Unit: 1week)

    (Plan. Hor.: a few months, Time Unit: 1week)

    Shop floor-level ProductionControl

    (Plan. Hor.: a day or a shift, Time Unit: real-

    time)

    Forecasting

  • 8/3/2019 Materials Planning - Forecasting

    3/35

    Forecasting

  • 8/3/2019 Materials Planning - Forecasting

    4/35

    Costs of Forecasting

    IBM continues to struggle with shortagesin the Think Pad line. WSJ 5/2/94

    Dell stock plunges. Dellwas sharplyoff in its forecast of demand WSJ 8/93

    Toyota believes it can save $100M [with] accurate ordering and inventory

    management.

  • 8/3/2019 Materials Planning - Forecasting

    5/35

    Importance of forecasting

  • 8/3/2019 Materials Planning - Forecasting

    6/35

    Methods of Forecasting

    Qualitative Approaches Quantitative Approaches

  • 8/3/2019 Materials Planning - Forecasting

    7/35

    Qualitative Approaches

    intuitive hunches Executive committee consensus Delphi method Survey of sales force Survey of customers Market research

    scientifically conducted surveys

  • 8/3/2019 Materials Planning - Forecasting

    8/35

    Quantitative Approaches

    Time Series Methods use historical dataextrapolated into the future. They are bestsuited for stable environments.

    EG - Moving averages, exponentialsmoothing methods. Causal Methods assume demand is

    highly correlated with certainenvironmental factors (indicators). EG - Regression models, and econometricmodels.

  • 8/3/2019 Materials Planning - Forecasting

    9/35

    Time Series Methods

    (Simple) Moving Average Weighted Moving Average Exponential Smoothing

  • 8/3/2019 Materials Planning - Forecasting

    10/35

    SIMPLE MOVING AVERAGE

    In a moving average, the forecast would be calculatedas the average of the last few observations. If we let Mequal the number of observations to be included in themoving average, then:

    Zt+1 =1/M i=t+M -1 Zi For example, if we let M=3, we have a "three period

    moving average", and so, for example, at t = 7: Z8= (Z7+Z6+Z5) /3

  • 8/3/2019 Materials Planning - Forecasting

    11/35

    T Z M=2 M=3 M=4 M=5 M=6 M=7

    1 982 1103 100 1044 94 105 1035 100 97 101 1016 92 97 98 101 1007 96 96 95 97 99 998 102 94 96 96 96 99 999 105 99 97 98 97 97 9910 96 104 101 99 99 98 98

  • 8/3/2019 Materials Planning - Forecasting

    12/35

    Weighted Moving Average

    This is a variation on the simple movingaverage where the weights used tocompute the average are not equal.

    This allows more recent demand datato have a greater effect on the movingaverage, therefore the forecast.

    . . . more

  • 8/3/2019 Materials Planning - Forecasting

    13/35

    Weighted Moving Average

    The weights must add to 1.0 andgenerally decrease in value with the ageof the data.

    The distribution of the weights determinethe impulse response of the forecast.

  • 8/3/2019 Materials Planning - Forecasting

    14/35

    The weights used to compute theforecast (moving average) areexponentially distributed.

    The forecast is the sum of the oldforecast and a portion ( ) of theforecast error (A t-1 - F t-1).

    F t = F t-1 + (A t-1 - F t-1)

    Exponential Smoothing

  • 8/3/2019 Materials Planning - Forecasting

    15/35

    Exponential Smoothing

    The smoothing constant, , must bebetween 0.0 and 1.0.

    A large provides a high impulseresponse forecast.

    A small provides a low impulseresponse forecast.

  • 8/3/2019 Materials Planning - Forecasting

    16/35

    Example: Central Call Center

    Moving Average CCC wishes to forecast the number of incomingcalls it receives in a day from the customers of oneof its clients, BMI. CCC schedules the appropriate

    number of telephone operators based on projectedcall volumes. CCC believes that the most recent 12 days of callvolumes (shown on the next slide) are

    representative of the near future call volumes.

  • 8/3/2019 Materials Planning - Forecasting

    17/35

    Example: Central Call Center

    Moving Average o Representative Historical Data

    Day Calls Day Calls 1 159 7 203 2 217 8 195 3 186 9 188 4 161 10 168 5 173 11 198 6 157 12 159

  • 8/3/2019 Materials Planning - Forecasting

    18/35

    Example: Central Call Center

    Moving Average Use the moving average method with an AP= 3 days to develop a forecast of the callvolume in Day 13. F13 = (168 + 198 + 159)/3 = 175.0 calls

  • 8/3/2019 Materials Planning - Forecasting

    19/35

    Example: Central Call Center

    Weighted Moving Average Use the weighted moving average method with an AP = 3days and weights of .1 (for oldest datum), .3, and .6 todevelop a forecast of the call volume in Day 13.

    F13 = .1(168) + .3(198) + .6(159) = 171.6 calls

    Note: The WMA forecast is lower than the MA forecastbecause Day 13s relatively low call volume carries almost

    twice as much weight in the WMA (.60) as it does in the MA(.33).

  • 8/3/2019 Materials Planning - Forecasting

    20/35

    Example: Central Call Center

    Exponential Smoothing

    If a smoothing constant value of .25 is used and theexponential smoothing forecast for Day 11 was180.76 calls, what is the exponential smoothing

    forecast for Day 13?

    F12 = 180.76 + .25(198 180.76) = 185.07 F13 = 185.07 + .25(159 185.07) = 178.55

  • 8/3/2019 Materials Planning - Forecasting

    21/35

    Causal Methods

  • 8/3/2019 Materials Planning - Forecasting

    22/35

    Simple Linear Regression

    Linear regression analysis establishes arelationship between a dependent variableand one or more independent variables.

    In simple linear regression analysis thereis only one independent variable.

  • 8/3/2019 Materials Planning - Forecasting

    23/35

    Simple Linear Regression

    Regression Equation This model is of the form: Y = a + bX

    Y = dependent variable

    X = independent variable a = y-axis intercept b = slope of regression line

  • 8/3/2019 Materials Planning - Forecasting

    24/35

    Simple Linear Regression

    Constants a and b The constants a and b are computed usingthe following equations:

  • 8/3/2019 Materials Planning - Forecasting

    25/35

    Simple Linear Regression

    Once the a and b values are computed, afuture value of X can be entered into theregression equation and a corresponding

    value of Y (the forecast) can becalculated.

    E l C ll g E ll t

  • 8/3/2019 Materials Planning - Forecasting

    26/35

    Example: College Enrollment Simple Linear Regression

    At a small regional college enrollments have grown steadilyover the past six years, as evidenced below. Use timeseries regression to forecast the student enrollments for thenext three years. Students Students Year Enrolled (1000s) Year Enrolle(1000s) 1 2.5 4 3.22 2.8 5 3.3 3 2.9 6 3.4

  • 8/3/2019 Materials Planning - Forecasting

    27/35

    Example: College Enrollment

    Simple Linear Regression x y x2 xy 1 2.5 1 2.5 2 2.8 4 5.6 3 2.9 9 8.7 4 3.2 16 12.8 5 3.3 25 16.5

    6 3.4 36 20.4 x=21 y=18.1 x 2=91 xy=66.5

  • 8/3/2019 Materials Planning - Forecasting

    28/35

    Example: College Enrollment

    Simple Linear Regression

    Y = 2.387 + 0.180X

  • 8/3/2019 Materials Planning - Forecasting

    29/35

    Example: College Enrollment

    Simple Linear Regression Y7 = 2.387 + 0.180(7) = 3.65 or 3,650 students Y8 = 2.387 + 0.180(8) = 3.83 or 3,830 students

    Y9 = 2.387 + 0.180(9) = 4.01 or 4,010 students Note: Enrollment is expected to increase by 180students per year.

  • 8/3/2019 Materials Planning - Forecasting

    30/35

    Simple Linear Regression

    Simple linear regression can also be usedwhen the independent variable Xrepresents a variable other than time.

    In this case, linear regression isrepresentative of a class of forecastingmodels called causal forecasting models.

  • 8/3/2019 Materials Planning - Forecasting

    31/35

    Example: Railroad Products Co.

    Simple Linear Regression Causal Model The manager of RPC wants to project the firmssales for the next 3 years. He knows that RPCslong-range sales are tied very closely to nationalfreight car loadings. On the next slide are 7 years ofrelevant historical data. Develop a simple linear regression model betweenRPC sales and national freight car loadings.Forecast RPC sales for the next 3 years, given thatthe rail industry estimates car loadings of 250, 270,and 300 million.

    E l R il d P d t C

  • 8/3/2019 Materials Planning - Forecasting

    32/35

    Example: Railroad Products Co. Simple Linear Regression Causal Model

    RPC Sales Car Loadings Year ($millions) (millions) 1 9.5 120

    2 11.0 135 3 12.0 130 4 12.5 150 5 14.0 170

    6 16.0 190 7 18.0 220

  • 8/3/2019 Materials Planning - Forecasting

    33/35

    Example: Railroad Products Co.

    Simple Linear Regression Causal Model

    x y x2 xy 120 9.5 14,400 1,140 135 11.0 18,225 1,485 130 12.0 16,900 1,560 150 12.5 22,500 1,875 170 14.0 28,900 2,380 190 16.0 36,100 3,040 220 18.0 48,400 3,960

    1,115 93.0 185,425 15,440

  • 8/3/2019 Materials Planning - Forecasting

    34/35

    Example: Railroad Products Co.

    Simple Linear Regression Causal Model

    Y = 0.528 + 0.0801X

  • 8/3/2019 Materials Planning - Forecasting

    35/35

    Example: Railroad Products Co.

    Simple Linear Regression Causal Model Y8 = 0.528 + 0.0801(250) = $20.55 million Y9 = 0.528 + 0.0801(270) = $22.16 million

    Y10 = 0.528 + 0.0801(300) = $24.56 million Note: RPC sales are expected to increase by$80,100 for each additional million national

    freight car loadings.


Recommended