MAXIMIZING THE VALUE OF PROJECT-LEVEL
PROGRAMMATIC AGREEMENTS IN SECTION 106
CONSULTATION
Antony Opperman, Cultural Resources Program Manager
2018 Joint AASHTO Committee Meeting, Spokane, Washington
July 19, 2018
• 36 CFR 800.14(b): “…resolution of adverse effects from
certain complex project situations …”
• 36 800.14(b)(1)(ii): “When effects on historic properties cannot be
fully determined prior to approval of an undertaking …”
• 36 CFR 800.14(b)(1)(iii): “When nonfederal parties are delegated
major decision making responsibilities …”
• 36 CFR 800.14(b)(3): “Developing programmatic agreements for
complex or multiple undertakings” refers back to 36 CFR 800.6,
“Resolution of Adverse Effects”
Authorities
Virginia Department of Transportation
• Statewide Federal PA
• Stipulation II.B.4.c: VDOT has standing to resolve adverse effects viz.
36 CFR 800.6, including preparation and execution of agreements.
• Stipulation II.B.3.e: VDOT may perform phased identification of
historic properties for projects with “multiple alternatives,
alignments, or corridors”, specifically deferring archaeology, usually
after a preferred alternative is identified (also 36 CFR 800.4(b)(2)).
• When Used
• Typically for large, multiple alternative projects (NEPA: EA or EIS).
• Use assumes that adverse effects could occur even if they do not.
Consistency with Statewide Federal PA; When Used
Virginia Department of Transportation
• Multiple-alternative harbor crossing expansion, including new
bridge-tunnel
• Multiple historic properties adjacent to corridor including
National Historic Landmarks, significant constraints
• Major PA Elements:• Avoidance commitments to avoid adverse effects
• Deferred terrestrial and underwater archaeological surveys, preferred alternative
only
• Design-builder or P-3 concessionaire given standing to consult directly with SHPO,
FHWA and consulting parties in carrying out commitments (with VDOT oversight)
• Reassessment of effects as design proceeds
Example: Hampton Roads Crossing Study (HRCS)
Virginia Department of Transportation
HRCS Location
Virginia Department of Transportation
HRCS: Emancipation Oak
Virginia Department of Transportation
July 10, 2015: Section 106 consultation initiated
April 2016: Architecture survey & archaeological assessment complete;
SHPO agrees that any archaeological sites would satisfy 4(f) exemption
July 2016: Draft SEIS issued
November 2016: Effects determination (archaeological effects unknown) PA
proposed
February 2017: Draft PA to SHPO and CPs for comment; ACHP copied and
notified viz. 36 CFR 800.6(a)(1)
April 11, 2017: PA executed
April 2017: Final SEIS issued
June 2017: ROD issued
Total Section 106 Time: 21 Months
HRCS Timeline
Virginia Department of Transportation
• Multi-state (District of Columbia and Maryland)
• Multi-agency (FHWA, FRA, National Park Service)
• Complex: The Boring Company (Elon Musk)
• Two parallel hyperloop tunnels under public ROW, 35.3 miles
• “Autonomous electric scates”, 8-16 passengers, 125-150 mph
• DC-Baltimore: 15 minutes (ultimate DC-NYC in 29 minutes)
• Privately funded, construction in 12-20 months
• Federal action: Approval of ROW use
• NEPA: EA
• Section 106: Project-Level PA
Example: Loop Tunnel Project (Maryland/FHWA)
Virginia Department of Transportation
Loop Tunnel Project Location
Virginia Department of Transportation
• Authority: 36 CFR 800.14(b); consultation initiated March 2018
• Content: Section 106 Activities as Post-106 Commitments• Consultation principals
• Professional qualifications
• Roles of agency participants
• Tribal consultation
• Participation of consulting parties and the public
• Phased identification of historic properties
• Assessment and resolution of adverse effects (MOAs as commitment)
• Post-review discoveries, human remains, disputes, etc.
• PA to be executed Summer 2018 (4-5 months)
Loop Tunnel Project Draft PA Content
Virginia Department of Transportation
• Advantages
• Saves time: Section 106 completed faster for larger, complex
projects; 106 component of NEPA completed faster.
• Saves money: Archaeological survey expenses reduced (Virginia).
• Commitments to avoid adverse effects defined for use in
construction technical requirements.
• Disadvantages
• Final effects on historic properties might not be adverse.
• Overkill for most simple or single-alternative projects.
Project Level PAs Summary
Virginia Department of Transportation