The Gemini project Dorit Jackisch, Jens Møller and David Molenaar
May 22, 2014
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 2 NNOW
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 3 NNOW
Before I start …
We are very pleased to be here today
Jens Møller
Project Manager Dorit Jackisch
Project Controller
David Molenaar
Country Division Head
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 4 NNOW
Before I start …
And are looking forward to a long-term collaboration
Jens Møller
Project Manager Dorit Jackisch
Project Controller
David Molenaar
Country Division Head
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 6 NNOW
Gemini Offshore Wind Farm
Some key facts
150 turbines of 4 MW
600 MW
First offshore wind order
Transport from Esbjerg to
directly to the site
15 years of maintenance
Onshore site in
Eemshaven
Service operating vessel
with helicopter
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 7 NNOW
Gemini Offshore Wind Farm
Some key facts
Service Operating Vessel illustrative example
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 8 NNOW
Gemini Offshore Wind Farm
Some key facts
“Pushing On” with a CTV at Baltic 1
Dropping of a service team @ Greater Gabbard
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 9 NNOW
Gemini is the first project in a series ….
300 300
600 700
800 900
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
OWEZ (2006) 36 x Vestas V-90 | 108 MW
PAWP (2008) 60 x Vestas V-80 | 120 MW
450
144
129
Energy Agreement
September 6, 2013
Gemini 150 x SWT-4.0-130 | 2 x 300 MW
120 108
Westermeerwind 48 x SWT-3.0-108 | 144 MW
Luchterduinen 43 x Vestas V-112 | 129 MW
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 10 NNOW
... provided that the cost will be cut by EUR 5 per MWh
= LCOE
+
Lifecycle
electricity
output
OPEX CAPEX
Primary target: 40% by 2020*)
*) http://www.nwea.nl/greendeal
Offshore wind industry target:
-40% in less than a decade
2010 2020
€ /
MW
h
100
130
160 Direct drive
Larger rotor blades
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 11 NNOW
... so we must make it a success. Together!
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 12 NNOW
Basiskwalificaties leveranciers
• Registratie en toetsing (‘click4supplier easy’)
• Gedragscode voor Siemens leveranciers
Certificaten:
• ISO9001, ISO14001, VCA* (of vergelijkbaar)
• Medewerkers vereiste certificaten; leidinggevenden VCA VOL
Projectspecifieke eisen:
• QHSE en documentatierichtlijnen
• Monitoring 24/7, Service uitvoering 12/7
Finally, how to become a Siemens supplier?
2014-05-22
Restricted © Siemens AG 2013 All rights reserved.
Page 13 NNOW
Thank you very much for your attention!
Restricted © Siemens AG 2013 All rights reserved.
2014-05-22- Page 14 David Molenaar
How to we make sure that we can hire the required number of techniciancs
My question to you: