May 28 2009 – August 14 2009
Highway 51 Parking Lot Project
The Board of Regents approved replacing the asphalt parking lot by Highway 51 with a concrete parking lot during its meeting on May 18th 2009
Construction should start by May 28th with substantial completion by August 7th and the punch list completed by August 14th
A Fire Lane must remain open at all times
Highway 51 Parking Lot ProjectPhase 1 (Estimated State date: May 28
2009):See the White area of map on the next slideProject will remove asphalt and replace parking spaces
closest to buildings, including parking between 300 and 400 building
Open a new entrance/exit from Bonner Road that is closer to Hays Hall with three lanes (1 entrance, 1 exit to left, 1 exit to right)
Close current entrance/exit from Bonner Road that is closer to 100 Building
Students and employees will need to park in Phase 2 area or in other parking lots around campus
For safety reasons, people will not be able to cross the construction area; please walk around the barricades
The parking lots by the Career & Technology Center and Visual Arts Center will be closed during Phase 1 due to road and new parking lot construction
Phase 1
Phase 2
Highway 51 Parking Lot ProjectPhase 2 (Estimated State Date: early July 2009):
Shaded area of mapReplace asphalt parking spaces closest to Highway
51Close Entrance/Exit from Bonner Road that is close
to Highway 51Students and employees will need to park in Phase
1 area or in other parking lots around campusPeople will not be able to cross the construction
area; please walk around the barricadesThe new parking lots by the Career & Technology
Center and Visual Arts Center are scheduled to open by
mid-July