Date post: | 16-Feb-2017 |
Category: |
Design |
Upload: | informa-australia |
View: | 942 times |
Download: | 1 times |
Context
Urban centre with large rural hinterland c 125,000 people, including 23,000 students Heritage, culture and biodiversity
Before the Strategy
Previous strategy focussed on water and wastewater quality
Single issue; Single solution;
High service; High cost
Identified gap in strategic planning capability
Integrated improvement strategy •Departmental restructure
• 3 Waters Strategy project
Development Approach
Review strategic drivers
Review technical constraints of existing infrastructure
Engaged with the community on their concerns and priorities
Produced strategic timeline of issues and potential solutions
Developed strategic principles to guide future decision making
Dunedin’s Water Challenges Limited growth
Shift in economy away from water intensive industry
Excess capacity in parts of our infrastructure
Gravity fed water supplies
Climate change predicted to increase catchment yield (although more seasonal)
Dunedin’s Water Challenges
Increasing flood risk
Sea level rise – rising groundwater
Vulnerable to single point failures in our critical infrastructure.
Relative isolation requires greater resilience
Dunedin’s Water Challenges
Infrastructure is ageing
Some pre 1900 infrastructure still in use.
Renewals peak is looming
Renewals forecast as at 2010
Dunedin’s Challenges
High sunk infrastructure costs
Looming renewals requirements
Slow growth
Environmental and other pressures
= Affordability challenges
Strategic Priorities
7 high level statements
Outline long term principles and commitments to guide future planning and decision making.
Deals with uncertainty by allowing us to adjust and respond as change happens
How does this affect decision making?
Change of thinking
•More focus on using and rationalising existing assets
• Integrated approaches to give multiple benefits
• Flexibility and resilience for different potential futures
• Improved cross council planning e.g. 2nd generation district plan
Security of Supply Strategy
2008 - Previously unrelated problems and projects
Serious lifelines risk – 2 main raw water supply pipes over same, vulnerable, 1936 bridge.
Only one source of water supply for the Hill suburbs
Deep Creek Pipeline Renewal programme ($15m+ budget)
High future costs to maintain and renew two raw water pipelines (gravity fed = low OPEX).
Ross Creek Dam Stability problems
Risk of losing consents for un-utilised water resources
2014 - One Integrated Solution
2008 : Second Taieri Crossing
Initial budget c$6m
Cost estimates escalating up to $15m
Time for a rethink!
Ross Creek Dam Stability
Disused water reservoir Well used community recreation asset Dam stability problems have led to lowering of water levels
2014: Integrated thinking
What we are doing
•Stabilise Ross Creek Dam (in progress)
•Build pumping station from Southern Treatment plant to Mount Grand Treatment Plant (in progress)
•Bring some redundant water infrastructure back into supply (2018-2020)
• Future rationalisation of 2 supply pipelines to one (c2036)
What we are NOT doing
No second crossing across the Taieri Required
Not renewing the Deep Creek Raw Water Pipeline (decommission when Deep Stream pipeline requires renewal)
• The criticality of the infrastructure will be reduced to such a level that we can provide continuous supply without them (at higher cost, and with some restrictions)
Benefits All parts of metropolitan Dunedin can be served
by 2 treatment plants and any of 4 water supply sources
Resilience to loss of any single part of the supply system, including the Taieri Bridge Crossing or either one of the treatment plants.
High level of resilience to catchment drought or fire
Dam stabilised and Ross Creek amenity value restored
Asset lifecycle costs significant reduced
Savings of $12m in the first 10 years.