+ All Categories
Home > Documents > MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement...

MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement...

Date post: 29-Jun-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
31
MATANUSKA ELECTRIC ASSOCIATION, INC. MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 JOE GRIFFITH, GENERAL MANAGER OCTOBER 21, 2014
Transcript
Page 1: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

MATANUSKA ELECTRIC ASSOCIATION, INC. M A Y O R ’ S E N E R G Y T A S K F O R C E

U P D A T E - F A L L 2 0 1 4

JOE GRIFFITH, GENERAL MANAGER OCTOBER 21, 2014

Page 2: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

MATANUSKA ELECTRIC ASSOCIATION, INC.

• Over 60,000 accounts (47,320 members)

• 22 substations

• Over 4,200 miles of power lines

2

Transmission, 125 miles

Overhead distribution, 2,227 miles

Underground distribution, 1,832 miles

Page 3: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

MEA POWER PORTFOLIO (CAPACITY)

3

80%

20% 80% Natural Gas(Currently ChugachElectric - Transition to EGSin 2015)

20% Hydro (Bradley Lake,Eklutna Hydro, Southforkof Eagle River, McRobertsCreek in Palmer)

Page 4: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

Eagle River

Palmer Wasilla Matanuska Glacier

Point MacKenzie

Denali State Park

Talkeetna

Matanuska Electric Association Service Territory (Certificate 18)

Honolulu Creek

>100 Miles

~100 Miles

Page 5: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

SERVICE AREA CHALLENGES

• Over 4200 miles of power lines covering only 59,000 customers

• Service area the size of West Virginia • Challenging terrain and narrow rights-of-way • Growing demand • Aging and inadequate infrastructure

5

Page 6: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

MEA’S GROWING LOAD Driving significant upgrades to our system to meet member demand

8000090000

100000110000120000130000140000150000160000

Year20112006200119961991

Page 7: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

TRANSMISSION UPGRADES – EGS TO WASILLA

• Provides reliable power from EGS to the heart of our service area

• Supports significant commercial and residential growth

• Provides reliability and redundancy to vulnerable system

Page 8: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

MEA TRANSMISSION UPGRADES

8

Phase 1: EGS to Hospital • Poles in place • Lines connected from EGS • Completion anticipated this week • Tie to Eklutna Hydro Project

transmission line halted by EOC.

Wasilla Hospital

Substation

Palmer

EGS

Page 9: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

MEA TRANSMISSION UPGRADES

9

Phase 2: Hospital Substation to Herning (Wasilla)

• Supports significant commercial and residential growth in Wasilla

• Progress stalled due to Wasilla Planning Commission decision

• Interim step – build transmission to LaZelle substation

• MEA working with stakeholders on alternate overhead routes

Wasilla Hospital

Substation

Palmer

EGS

Herning Substation

Page 10: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

OTHER SYSTEM UPGRADES – A FOCUS ON RELIABILITY Substation improvements –

• Reduce outages, improve power quality, account for growth

• 5 substations currently undergoing upgrades, including Parks (Chugiak)

Clearing to reduce outages

• Chugiak/Birchwood

• Willow to Talkeetna

New meters

• More accurate bills

• Reduce outage time

• Improve efficiency of workforce

Page 11: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

MEA LONG RANGE PLANNING Development of a comprehensive growth and maintenance plan

• Proactive assessment of current system compared to projected growth

• Coordination with other planning efforts at MoA and Mat-Su Borough

• Several new substations identified, including Powder Reserve (N Eagle River)

• Will likely result in the purchase of corridors and substation property for future use

• Target completion: Summer 2015

Page 12: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

EKLUTNA GENERATION STATION Online Early 2015

Page 13: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

DECISION FACTORS LEADING TO EKLUTNA GENERATION STATION (EGS)

13

• 2004: 10-year notice to Chugach that MEA would not be customer after Dec. 31, 2014 • MEA Integrated Resource Plan, MEA power supply studies, Technology Evaluation Report • Financial and hourly dispatch modeling • Load-flow study, pooling studies • Conversations with Chugach and ML&P on joint effort Other considerations

o Railbelt generation suite o Lack of meaningful work between 2004 and 2009 o Cook Inlet fuel situation o Pipeline configuration o Air regulations o Load characteristics

Page 14: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

EKLUTNA GENERATION STATION DESIGN

14

• 171mW Capacity (Ten 17.1mW engines)

• Dual-fuel (Natural gas & diesel)

• Reciprocating engines o Efficiency over power range

• Why Wärtsilä? o Industry leader o 10 smaller engines to better follow our primarily residential load o Proven and efficient technology o Price

Page 15: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

STRATEGIC LOCATION

15

AK Railroad Enstar 20”

Gas Pipeline

Eklutna Generation Station

EGS - Strategic Location

Page 16: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

EGS POWER BLOCK CONTRACTOR AND MAJOR SUBS

16

Page 17: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

EGS PROJECT IMPACT

17

o Nearly 300 jobs at peak of construction

o 28 permanent O&M positions filled – majority Alaska hire

o Estimate over $100M in Alaskan economic impact to date

Page 18: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

18

Eklutna Generation Station – as of Summer 2014

Page 19: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

EGS PROJECT UPDATE

19

• Mechanical Substantially complete - equipment placed, attached & plumbed in

• Connection to Enstar pipeline complete • Wärtsilä finalizing engine prep – oil and coolant

filled • Electrical cable pulls and terminations in

process • Testing, flushing and commissioning plan

crafted and underway

Page 20: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

EGS PROGRESS

20

Page 21: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

% Complete

Summer 2013

Fall 2013

Winter 2013

Spring 2014

Summer 2014

Fall 2014

Winter 2014

Spring 2015

EGS Switchyard 100

Field Erected Tanks 100

Administration Building 100

Warehouse 100

Power Block 90 - 95

Testing and Commissioning 20

2014 EGS CONSTRUCTION ACTIVITIES

Complete In Progress Today

Page 22: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

EGS COMMISSIONING PLAN

22

• Commissioning agent - Universal Energy, Inc. • Plan for testing, verification and power

delivery • Commissioning dispatch agreement with

Chugach Electric signed • Filling of liquid fuel, oil, coolant, and ammonia

tanks scheduled • Goal -

oFour engines online December 31, 2014 oAll 10 engines online Spring 2015

Page 23: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

IMPORTANT COORDINATION WITH RAILBELT UTILITIES

23

• Interim sales agreement with Chugach Electric signed for Q1 2015 • Coordination for power produced during commissioning • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna Hydro, EGS, Plant 2

(ML&P), Teeland Substation (Chugach)

• Agree to a plan to capitalize on new opportunities for economic dispatch of power for significant savings

Page 24: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

IMPACT TO MEMBERS • EGS transforms the way we serve our members.

• Increased control over decisions that impact our membership.

• Allows us to more closely and efficiently serve our load.

• Projecting an initial rate increase (15-20%) over the next 18 months oLargely driven by new, more expensive gas contracts oProjections were for a similar increase with Chugach, but one year

later.

Page 25: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

ROLE IN THE RAILBELT ENERGY PICTURE

25

• 10 smaller engines for load following

• Dual-fuel in case of natural gas supply interruption

• Improves grid stability throughout the system

• Can help integrate variable power

• Component of a single transmission operator and economic dispatch

• May help meet proposed EPA regs by offsetting less efficient generation

Page 26: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

CURRENT RAILBELT ISSUES Infrastructure Problem o Inadequate transmission systems o Solution - Upgrade and construct new infrastructure

New generation facilities o 5 new facilities on the Railbelt o Solution - Single, economic dispatch of power

New organizational structure o 6 vertically integrated utilities o Solution - Single transmission operator (TRANSCO)

26

Page 27: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

RAILBELT UTILITY NATURAL GAS CONCERNS

27

• Current market is 200 bcf per year. Too small to encourage exploration.

• Inadequacy of current gas infrastructure o Mismatch of supply delivery

infrastructure with demand centers o Long and vulnerable distribution

system o Limited and expensive storage

• Transport costs and ownership

Page 28: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

ARCTEC – A CONSORTIUM OF RAILBELT UTILITIES

28

Prioritizing upgrades to fragile Railbelt transmission infrastructure • Support for infrastructure development plan • Funding options limited

TRANSCO/ISO development • Goal – coordination of assets for benefit of the entire Railbelt • Identify best model for Alaska • Feedback from other stakeholders (Legislators, IPP’s) • Legislative $250k to RCA at ARCTEC’s request

Page 29: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

MEA IN THE COMMUNITY • Involved in events and organizations throughout our

service area

• MEA Charitable Foundation supports service area with approx. $125K annually from Round Up funds

• Award $20,000 in scholarships annually to area youth

Page 30: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

ENERGY EDUCATION (K-12) • The Energy Hog teaches our youth about energy efficiency.

• Safety City presentations educate youth on safe practices around electricity.

• MEA offers school visits, tours and presentations

• AK EnergySmart Curriculum – Energy Efficiency lessons for K-12.

Page 31: MAYOR’S ENERGY TASK FORCE UPDATE - FALL 2014 Presentation M… · • Interconnection agreement necessary – EOC stop work order • Complete control communications loop – Eklutna

THAT’S ALL FOLKS.

31


Recommended