+ All Categories
Home > Documents > Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

Date post: 07-Aug-2018
Category:
Upload: yoseph-birru
View: 228 times
Download: 2 times
Share this document with a friend

of 6

Transcript
  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    1/12

     

    2008

    KUNDAN SINGH CONSTRUCTION

    KENSETSU KAIHATSU CONSULTANTS

    4/1/2008

    EXECUTIVE SUMMARY

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    2/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 2 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    CONFIDENTIALITY AND © COPYRIGHT

    This document is for the sole use of the addressee (Kundan Singh Construction Ltd.) and KensetsuKaihatsu Consultants. The document contains proprietary and confidential information that shall not bereproduced in any manner or disclosed to or discussed with any other parties without the expresswritten permission of Kensetsu Kaihatsu Consultants. Information in this document is to be consideredthe intellectual property of Kensetsu Kaihatsu Consultants. in accordance with Kenyan copyright law.This report was prepared by Kensetsu Kaihatsu Consultants. for the account of Kundan SinghConstruction Ltd. The material in it reflects Kensetsu Kaihatsu Consultants.’s best judgement, in thelight of the information available to it, at the time of preparation. Any use which a third party makes ofthis report, or any reliance on or decisions to be made based on it, are the responsibility of such thirdparties. Kensetsu Kaihatsu Consultants. accepts no responsibility for damages, if any, suffered by anythird party as a result of decisions made or actions based on this report.

    ©2008 Kensetsu Kaihatsu Consultants

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    3/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 3 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    EXECUTIVE SUMMARY

    ES1 Introduction

    In 2004, the Government of Tanzania (GoT)

    through its agency TANROADS signed a contractwith BCEOM France in association with M-

    Konsult Tanzania for consulting services for

    Detailed Design for upgrading of Mbeya-

    Chunya-Makongolosi Road. With the intention

    to upgrade the road to tarmac grade through

    MoW and TANROADS, the GoT retained

    BCEOM/M-Konsult Ltd. To carry out both

    detailed design  work including environmental 

    and social impact assessment and preparation

    of Tender Dossier.

    Fig. 1 Location Map

    The Project road is about 115km long and lies

    between 08025’00 – 08053’36”S and 33000’48”

     – 34007’12”E. The altitude for the Project road

    ranges from 1200 to 2450 metres above sea

    level (m.a.s.l). The project road traverses the

    highest point of trunk roads in Tanzania,

    standing at 2457 m.a.m.s.l at Kawetele and

    about 18km away from Mbeya Municipality.

    The Works contract for the upgrading of Section

    I of the Project Road was signed in August 2007

    between TANROADS and Kundan Singh

    Construction Ltd. Kenya (KSC). The Section runs

    from Mbeya town at km 0+000 to km 36+000

    and rises from 1688 masl at Mbeya to 2456

    masl at km 17+625 and then drops to 2008 masl

    at km 26+000. The alignment of the road

    undulates along a meandering horizontal pathwith some sharp hair pin bends and several

    sections lying on the edge of ridges or at times

    dangerously on slopes where severe

    hydrological hazards are bound to cause faults.

    Fig. 2a Some problematic sections of the Project

    Road

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    4/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 4 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    Fig. 2b Some problematic sections of the Project

    Road

    Significant deficiencies in the Design leading to

    seriously impacted on the engineering

    feasibility leading to a decision by the

    Contractor to seek consultant an independent

    third opinion.

    Site visit by independent consultant

    One of the sections within the landslide zone

    identified during the visit

    ES2 Geotechnical Consultant Team

    The Contractor KSC having encountered major

    technical difficulties in terms of implementing

    the required sound engineering standardsbased on the original design, decided to engage

    the services of a highly qualified Geotechnical

    Engineering Consultant with comprehensive

    knowledge and specialization of the

    geotechnical and hydrogeological conditions of

    Africa, particularly the EA Region (including

    Sudan, Burundi) and on problematic soils.

    Kensetsu Kaihatsu Consultants (KKC) is a Kenyan

    firm of Consultants led by a worldwide

    recognized Geotechnical Engineer, Dr. JN

    Mukabi who is reputed to have offered many

    innovative solutions for major problematic

    areas and designs. He is a recognized and highly

    honored engineer/scientist with international

    awards and accolades having contributed

    immensely to top geotechnical, soil mechanics

    and civil engineering societies and forums. It

    was upon the site visit that the Consultant

    advised the Contractor that Kensetsu Kaihatsu

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    5/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 5 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    Consultants undertake a Comprehensive

    Geotechnical Engineering Analysis and Review

    of the Original Design to offer

    recommendations and possible designs/method

    of construction to benefit the Client by realizing

    a cost-effective Value Engineeering (VE)

    structure that would be durable, while being

    sensitive to the environment, as well as offering

    possible mitigation mesures for geohazards that

    are more than likely to happen.

    Kensetsu Kaihatsu Consultants therefore made

    and makes an undertaking to partake this

    assignment under the guidelines of geo-

    professionals within the provisions of the

    International Society of Soil Mechanics and

    geotechnical Engineering (ISSMGE), and Sub-

    Clause 2.6 of the Fourth Edition of The FIDICConditions of Contract presented in the Table

    below in ES4 and ES9.

    ES3 Analysis and Review Objective

    The Project Area has the following factors that

    contribute immensely to geohazards:

      high rainfall

      prone to landslides

      seismic activity

    Mbeya and a better part of Tanzania which lies

    in the Rift receives significant seismic activity as

    indicated in the above figure 

    Some of the factors that must be seriously

    considered in design for the area include slope

    failure/slope stability, slope protection, cut

    versus fill, material stability,

    hydrology/hydrogeological assessment/design

    and environment/ppp (locals involvement).

    The overall objective of the Study is to establish

    the actual existing geotechnical problems

    including slope stability, the hydrogeological

    conditions and engineering impediments thatcould culminate in failure of the road and long-

    term cost in-effectiveness  rendering the

    Contract non-viable.

    The specific objectives of the Study are:

    (1)  To undertake a Comprehensive

    geotechnical soil and materials study of

    the Mbeya~Lwanjilo Trunk Road.

    (2)  To comprehensively review the original

    design in relation to the soils, materials

    and geotechnical engineering aspects.

    (3)  To determine the ground stability vide

    comparative analysis of cut and fill

    areas along the Project Road.

    (4)  To propose a cost-effective value

    engineering based approach that will

    realize a sound and durable road

    pavement structure.

    ES4 Brief Analysis of Relevant Contractual

    Clauses

    An analytical digest of the relevant contractual

    clauses is given under Sub-section 1.1.3 of the

    Main report (Comprehensive Geotechnical

    engineering Analysis and Review of the Original

    Design). KKC reviewed the Contract and has

    noted the various Clauses/Sub-Clauses

    pertaining to the process of construction and

    necessity to analyze and review the design. The

    implications in liability, costs and risks of both

    the Client and/or the Contractor have been

    analyzed and determined. The pragmatic

    approach to resolving the current situation will

    be both contractual and value engineering

    based. KKC noted Sub-Clause 8.1 of the FIDIC

    Conditions of Contract and noted that:

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    6/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 6 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    ES5 Contractor’s Concern and need for

    Independent Professional Consultation

    The Contractor on various occasions raised the

    issues of the problems encountered and

    deficiencies in both the Documentation anddesign. In minutes of various Site Meetings and

    that held on Thursday, 13th

      March 2008, in

    particular, this is noted. It was due to the

    Contractor’s concern and the decision to

    engage an independent expert was reached.

    The copy of minutes attached as Appendix to

    the Main report refers.

    ES6 Strategic Direction

    The decision to have a comprehensive analysis

    and review has led to the compilation of the

    Main Report, of which this is the Executive

    Summary. A presentation is also to be made on

    the scheduled date. The innovative solutions

    and recommendations will lead to a cost-

    effective and highly viable and beneficial

    project if all parties concerned appreciate the

    problems and deficiencies encountered while

    agreeing mutually to accept and expedite the

    implementation of the recommended

    approach.

    ES7 Current Design of Mbeya and Method of

    Construction (Analysis)

    The Original design stipulates the extensive use

    of fills and gabions in construction of the road

    for Section 1 (km1~km36). Considering the

    topography of the existing Project Road, the

    rolling hilly land, slopes and environment, the

    original (current) design fails to properly

    address the most appropriate, suitable and

    optimum engineering solutions for a sound

    design of the Project Road.

    Furthermore, there is no evidence that adetailed and comprehensive study was

    undertaken, as is depicted in Figure 6.1 in

    Chapter 6 of the pavement Design Manual-1999

    (ref. to Sub-section 4.4.4 of the Main Design

    Review Report).

    The overview of the review presented in

    Chapter 4 of the Main Design Analysis and

    Review Report. While the recently developed

    State-of-the-Art methods of investigation,

    study, survey, analysis and design areextensively discussed in Chapters 5, 6, 7 and 9

    of the Main Review Report.

    On the other hand, the Consultant who

    undertook the design states, on page 4-10 of

    the Detailed design Final report and page 10 of

    the Bidding Documents Volume 3 under the

    sub-topic “Improved Subgrade Layers” and

    “Areas of Low Strength (Expansive/Dispersible)

    Soils”, that:-

    (1)  It was established that the first 45kilometres of the Project road contain

    low strength in-situ subgrade soils

    (2)  The remaining portion of the road has

    relatively good subgrade soils, which do

    not require improvement. This section

    also is mainly located on cut areas.

    (3)  The first 45 kilometres of the Project

    Road Contains Soils, which exhibit high

    plasticity and low strength

    characteristics. This soils are termed as

    “problem soils” since they have high

    shrinkage and swelling properties which

    usually affects the overall performance

    of the pavement structure.

    Contents Brief Analytical Remarks

    Clause 8.1 Contractors GeneralResponsibilitiesThe Contractor shall, with due care anddiligence, design(to the extent provided forby the Contract), execute and completethe Works and remedy any defects thereinin accordance with the provisions of theContract. The Contractor shall provide allsuperintendence, labour, materials, Plant,Contractors Equipment and all otherthings, whether of a temporary orpermanent nature, required in and for suchdesign, execution, completion andremedying of any defects, so far as the

    necessity for providing the same isspecified in or is reasonably to be inferredfrom the Contract.The Contractor shall give prompt notice tothe Engineer, with a copy to t he Employer,of any error, omission, fault or other defectin the design of or Specification for theWorks which he discovers when reviewingthe Contract or executing the Works.

    This Clause clearly indicates that it is the Contractorwho is liable to the proper execution of andcompletion of the Works as provided for in theContract.On the other hand in accordance with Sub-Clause8.3 part a) i) on page No.11 of the conditions ofParticular Application for this Contract, the Contractoris responsible for ensuring that sound Engineeringpractice is observed at all times and f or all aspects ofthe project.Essentially therefore paragraph 1of this Sub-clauseprovides that the Contractor takes f ull responsibility ofensuring the proper and practical implementation ofthis project.

    The foregoing fact is emphasized by paragraph 2 ofthe same sub-clause, which requires that theContractor should have the ability to detect any error,omission, fault or other defect in the design orspecification for the works, upon which the Contractorhas the obligation to notify the Engineer andEmployer promptly.The main pragmatic interpretation and implicationhere is that:

    1) The Contractor has the full responsibility ofreviewing the design and all other associated,corresponding and/or otherwise relevantdocuments, in the post-bidding stage (Contract

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    7/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 7 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    Furthermore, the possibility of dangerous slope

    failures seems to have been completely omitted

    in the engineering analysis of the detailed

    design. The time needed to compact some of

    the high fill areas was not properly computed.

    The use of gabions as slope protection in fill

    areas without considering the hydrology,

    seepage that must occur and instability of the

    fill material is considered an engineering

    oversight. The eventual collapse of the gabions

    and slope from the slip that will eventually form

    in the fill will prove catastrophic. Designing over

    10metres of fill! should show that this is highly

    unstable and a time consuming construction

    method as demonstrated in figures below.

    ES8 Analysis of the Effect of Moisture, Slope

    failure /Landslides and Seismicity – 

    Geohazards Monitoring

    Rainfall: Mbeya region has high rainfall that can

    reach a maximum of 2700mm.

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    8/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 8 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    Effect of rainfall on Landslides:  Perhaps the

    most common trigger of a landslide, water

    reduces the friction between the bedrock and

    the overlying sediment, and gravity sends thedebris sliding downhill. In sand and clay soils, a

    small amount of water may increase stability.

    You've likely seen this when building a sand

    castle or working with clay. However, too much

    water causes the sediment to flow, which is

    why many landslides occur after rainstorms.

    Gravity is the primary factor in a landslide. Soil on a flat surface does not

    move. On a slope, gravity alone also may not t rigger a landslide. But when

    another disrupting factor -- like rain -- comes into play, gravity will pull

    sediment downhill.

    Gravity has a very major role to play in

    ground/slope stability. Flat surfaces are usually

    stable while slopes have gravity force acting on

    the mass. Where there is much rainfall the

    tendency for the mass to creep or worse slumpis high after rain effect.

    Example of slope failure (landslide) on a similarenvironment to the Project Road

    A Rotational Slide or Slump 

    Creep 

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    9/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 9 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    -  Effect of Moisture as analyzed from

    Project road

    -  Permeability and Seepage

    Slope failure and Gabions: The slopes at the fill

    areas protected by gabions are technically at a

    potential risk because of the dam effect that

    the gabions will cause if there is seepage into

    the fill. This has the effect of higher stress levels

    and seepage forces and will lead to the

    possibility of different stress-strain properties

    resulting in some zones being highly stressed

    than imagined.

    Possible Slip failure along the Project road

    CASE STUDY:  Slope failure on the Goha Tsion

    road in Addis Ababa.

    Dam effect of gabions on the Project road

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    10/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 10 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    It can be noted from the above computations

    that the Factor of Safety ( ) is extremely low

    implying that the gabions cannot provide the

    resistance required.

    -  Proof Rolling Results

    Seismicity:  Mbeya Region lies within a highly

    seismic zone of the East African Rift system. The

    are is considered a goe-hazard prone area and

    combined with it being flood prone too and thatthe rainfall is very high, this could eventually

    lead to liquefaction.

    Seismicity within and around Mbeya

    ES9 – Construction Problems and Contractor’s

    Liability / Client’s Liability 

    The Contractor’s/Client’s liability in relation to

    the original (current) design problems are

    Normal fault 

     

     

     

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    11/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 11 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    summarized in the Clause below and the

    following table.

      Clause 20.4 Employer’s risk 

      The employers risk are

    g)  Loss or damage to the extent that it is

    due to the design of works, other than

    any part of the design provided by the

    contractor or for which the contractor is

    responsible, and

    h)  Any operation of the forces of nature

    against which an experienced

    contractor could not reasonably have

    been expected to take precautions.

    Relevant Clauses Based On ExceptsFrom The Fourth Edition 1987 of TheFIDIC Conditions Of Contractor-Part IGeneral Conditions

    ES10 – Typical Design for Mbeya Environment,

    Design Development, Implementation

    A design based on the Comprehensive Method

    of Design is recommended. An example is given

    under Chapter 9 of the main Report.

    E11 – Cost – Benefit Analysis

    11.1 Benefits from Structural Durability

    As was demonstrated in chapters 6, 7, as well as

    in sections 9.9 of chapter 9 and chapter 10, the

    Employer is certainly bound to benefit

    immensely if the road is constructed to

    withstand the prevailing external forces and

    environmental factors to a reasonably

    sustainable standard, the structural durability

    factor will then contribute greatly to the

    sustenance of the socio  –  economic activities

    with the regions through which the road

    traverses due to the longevity of its design life.

    11.2 Enhanced Road Safety

    The current geometric design with section 1 of

    the Project Road posses enormous dangers due

    to the acute blind curves, ridges, and frequent

    meandering. The re-design would have toconsider cost-effective realignments that

    ensure the enhancement of road safety.

    11.3 Extended Performance of the Contractor

    Contractual Clauses pertaining to these issues

    and the repercussions that are likely to prevail

    as a result of the failure of the pavement

    structure and/or slopes have been analytically

    discussed under Sub-section 1.1.3 of this

    Report.

    11.4 Direct Cost Savings

    Direct cost savings will mainly be realized

    through commercial activities and social

    institutions such as schools, hospitals,

    community centres etc, in terms of the drastic

    reduction in travel time, trade etc.

    Clause/Sub-Clause: Contents Brief Analytical RemarksClause 8.1 Contractors GeneralResponsibilitiesThe Contractor shall, with due care anddiligence, design(to the extent provided forby the Contract), execute and completethe Works and remedy any defects thereinin accordance with the provisions of theContract. The Contractor shall provide allsuperintendence, labour, materials, Plant,Contractors Equipment and all otherthings, whether of a temporary orpermanent nature, required in and for suchdesign, execution, completion andremedying of any defects, so far as thenecessity for providing the same isspecified in or is reasonably to be inferred

    from the Contract.The Contractor shall give prompt notice tothe Engineer, with a copy to the Employer,of any error, omission, fault or other defectin the design of or Specification for theWorks which he discovers when reviewingthe Contract or executing the Works.

    This Clause clearly indicates that it is the Contractorwho is liable to the proper execution of andcompletion of the Works as provided for in theContract.On the other hand in accordance with Sub-Clause8.3 part a) i) on page No.11 of the conditions ofParticular Application for this Contract, the Contractoris responsible for ensuring that sound Engineeringpractice is observed at all times and for all aspects ofthe project.Essentially therefore paragraph 1of this Sub-clauseprovides that the Contractor takes full responsibility ofensuring the proper and practical implementation ofthis project.The foregoing fact is emphasized by paragraph 2 ofthe same sub-clause, which requires that t he

    Contractor should have the ability to detect any error,omission, fault or other defect in the design orspecification for the works, upon which the Contractorhas the obligation to notify the Engineer andEmployer promptly.The main pragmatic interpretation and implicationhere is that:

    1) The Contractor has the full responsibility ofreviewing the design and all other associated,corresponding and/or otherwise relevantdocuments, in the post-bidding stage (Contract

    Clause/Sub-Clause: Contents Brief Analytical Remarks

    8.2 Site operations and methods of

    constructionThe contractor shall take full responsibilityfor the adequacy, stability and safety of allsite operations and methods ofconstruction .provided that the contractorshall not be responsible (except as stated

    here under or as may be otherwiseagreed) for the design or specification of

    permanent works, or for the design orspecification of any temporary works notprepared by the contractor. Where thecontract expressly provides that part of the

    permanent works shall be designed by thecontractor, ha shall be fully responsible forthat part of such works, notwithstandingany approval by the engineer.

    This sub-clause basically qualifies the first paragraph

    of sub-clause 8.1 above and the corresponding briefanalytical RemarksIt is therefore interpreted that it is imperative for theContractor to take the initiative, which iscommensurate with his responsibilities , liabilities andobligations, to review any documents related to the

    execution successful completion of the Works whereadequacy, stability and safety factors are upheld in

    the design and the construction Works, failure towhich the Contractor is obligated to notify theEngineer and the Employer (client).

  • 8/20/2019 Mbeya Lwanjilo Trunnnk Road Project REPORT Executive Summary

    12/12

    EXECUTIVE SUMMARY

    Comprehensive Engineering Analysis and Review of Original (Current) Design Page 12 

     © 2 0 0 8 K E N S E

     T S U

     K A I H A T S U

     

    11.5 Indirect Cost Savings

    Indirect cost savings would mainly be as a result

    of external trade and tourism activities within

    the vicinity of the Project Road.

    E12 – Conclusions

    Detailed investigations, survey, in-situ and

    laboratory testing were undertaken during this

    Study. Subsequently, the results were

    comprehensively analysed by adopting

    powerful state-of-the-art analytical tools that

    have been developed and tailored for most

    tropical soils that exist within this region. Based

    on the findings of this Study, the following

    conclusions are made:

    (1)  The original (current) design was not

    based on detailed and comprehensive

    studies. This culminated in some serious

    flaws within the Fundamental design

    Concept.

    (2)  Contrary to the normal engineering

    practice, the original (current) design

    specifies the construction of high fills

    and purging in problematic soil areas

    instead of cutting into the hilly sides.This indeed is not only an expensive

    method of construction but also

    renders the pavement structure

    susceptible to slope failure. The

    adoption of this design would be costly

    and disastrous.

    (3)  From the evaluation made during this

    Study (Comprehensive Geotechnical

    and Engineering Analysis and Review of

    the Original (Current) Design for

    Mbeya-Lwanjilo-Chunya-Makogolosi

    Road Upgrading), it is apparent that

    comprehensive Environmental and

    Impact Assessment (EIA) was not made.

    E13 – Recommendations

    The following recommendations are made on

    the basis of the results obtained in this Study.

    (1)  It is imperative that the pavement

    structural design is reconsidered in

    order to alleviate the potential Client’s

    Liability problems.

    (2)  It would be advisable that the redesign

    is based on the Comprehensive Method

    of design for purposes of achieving a

    cost-effective Value Engineering based

    Structure that fosters sound

    engineering practice.

    (3)  Based on the analysis of the relevant

    contractual clauses during this Study, it

    is highly advisable that the employer

    takes expeditious action in resolving the

    current design problem, contrary to

    which the Project is likely to suffer

    enormous losses and socio-economic

    benefits or otherwise disastrous failureof the pavement structure.


Recommended