of 18
7/29/2019 MBR_BANG_01
1/18
Technical and Engineering Details
- Basis of Design
This proposal is based on the following design values to
be used for design MBR system.
- Influent Quality
The design solution proposed is based on the values as
presented in Table 3.1. All concentrations refer to max
concentrations to be used for the system's design.
Fluctuations in feed composition and hydraulics will be
appropriately equalized to allow for optimum biologicaltreatment.
Table 3.1: Influent Quality to MBR
Parameter Unit Design Concentration
pH NU 6 - 8
Oil & Grease mg/L < 10Chemical Oxygen Demand (COD) mg/L 600
Biological Oxygen Demand - 5-day mg/L 300
Total Suspended Solids mg/L 200
Ammonia, as NH3 mg/L < 40
TKN, as N mg/L < 70
Total Phosphorous mg/L 10
Total Alkalinity mg/L 400
Total Dissolved Solids mg/L 1500 2100
Note (1) All solids are assumed to be < 2 mm in any dimension;
otherwise, larger solids, such as hair and fibrous material, have to
be removed by others prior to entering the MBR to avoid any
7/29/2019 MBR_BANG_01
2/18
harm to the membranes.
3.3 Influent Flow DataFlow rate at the inlet to the proposed MBR as well as the resultingbioreactor temperature is shown in Table 3.2.
Parameter Unit Design
Max. flow rate, both membranetrains in operation
m3/d 2500SeeNote1 (Total
Phase) 1000 (Phase I)1750 (Phase II) 2500(Phase III)
Assumed Feed Temperature C 20-28
Design Bioreactor Temperature C 20-28 See Note 2
Note (1) It is required that feed flow be properly equalized
by others and during N-1 condition the flow will be
produced with subsequent trains. For the Phase I, the
flow has to be equalized during cleaning.
Note (2) Biological and membrane process is designed for
a temperature operating range of 20 to 28 C. Higher
temperatures > 35 C have to be avoided as they
exceed the tolerance for the biology and membranes;
otherwise appropriate cooling (by others) will be
required.
7/29/2019 MBR_BANG_01
3/18
3.4 Operation Basis
Hours Per Day of 24 hrs
Days Per Year of Operation 365 days NOTE: Consider Maintenance Time
3.5 Expected Effluent Quality
Table 3.4 shows the expected effluent quality upon
equipment start-up based on the data listed in section 3.1 and
3.2.
Parameter Unit ExpectedChemical Oxygen Demand (COD) mg/L < 100 SeeNote1
Biological Oxygen Demand - 5-day (BOD5) mg/L < 5
Total Suspended Solids mg/L < 3
Turbidity NTU < 1
Ammonia, as NH3 mg/L < 1
TKN mg/L < 2
TP mg/L < 1
PH NU 6 - 8
Note (1) Expected effluent quality assumes soluble fractions of COD are
biodegradable to this degree.
Note (2) Since "3" is the minimum detection limit of TSS measurement
7/29/2019 MBR_BANG_01
4/18
by Standard Methods, there is a potential for analytical error of TSS
at such low levels. is able to provide TSS guarantees of < 3 mg/L
95% of the time, provided that the TSS measurement is performed
by a certified lab approved by with < 3 mg/L TSS measuring
capabilities. Any samples with results greater than 2 will be
retested to confirm that the accuracy of the analytical method.
7/29/2019 MBR_BANG_01
5/18
4 MBR Plant General Scope Of Equipment
Process Description
The following sections describe additional equipment that is
required for the system and will be supplied by GEWPT and
Customer.
1 Equalization Tank
Equalization is required for any system with variable flow
rates. An equalization (EQ) tank is normally installed upstream
of the biological tank. The required equalization volume can
also be incorporated into the biological tank under certain
circumstances. A minimum equalization capacity of 10 hours
is recommended.
2 Equalization Transfer Pumps
Transfer Pumps transport wastewater from the equalization
tank or lift station to the process tank. The transfer pumps are
automatically activated by the Level Switch in a lead/lag
arrangement according to the level in the tank.
3 Screening System
Trash and non-biodegradable solids, such as hair, lint, grit and
plastics may foul or damage the membranes if allowed to pass
into the membrane chamber.
An internally-fed screen with mesh or punched-hole openings
7/29/2019 MBR_BANG_01
6/18
less than or equal to 2 mm in diameter with no possibility of
bypass or carryover is absolutely required to maintain both
membrane warranty, and optimal MBR operation.
4 Process Mixers
Process mixers can be used to mix the anoxic and post-
anoxic chambers (if included) to prevent solids from settling in
the anoxic chamber.
5 Process Aeration System
The process aeration blowers provide air for the biological tank
and ensure that sufficient oxygen is available to maintain the
biological processes in the tank. The aeration compartments
will be fully aerated and mixed by a fine bubble aeration grid.
Dissolved oxygen will be monitored in each aerobic tank to
achieve a desired set point of 2 mg/L. For the Phase I, there
will be One (1) duty blower and one standby blower providing
process air to the aerobic zone of the bioreactor and for the
Phase II & Phase III, there will be additional One (1) duty blower
per Phase to provide process air to the aerobic zone of the
bioreactor.
6 Fine Bubble Diffusers
A fine bubble diffused aeration system delivers air from the
aeration blowers to the aerobic zone of the process tank.
7 Permeate/Backpulse Pump Equipment
One permeate pump is employed to draw water through the
membranes. The permeate pump, associated valves and
7/29/2019 MBR_BANG_01
7/18
piping for the system are mounted on a factory assembled,
epoxy-coated carbon steel skid. Treated water flows from the
permeate skid to the final disposal point.
Under normal operation and average day flow conditions,
permeation is stopped for a specific period of time at regular
intervals. This membrane relaxation period, combined with air
scouring, effectively removes solids that have accumulated on
the membrane surface or within the fibers and reduces
electrical costs.
Same permeate pump is provided for backpulsing the
membranes. Under increased flow or adverse sludge
conditions, the operator is able to select a "backpulse" mode.
In this instance, the Backpulse pump will reverse the flow of
permeate through the membrane fibers to dislodge solids that
have accumulated on the membrane surface or within the
fibers.
From membrane tanks, Permeate pump draws treated
effluent through the pores of the membrane fibers and into the
backpulse tank. Once full, the treated effluent is automatically
diverted away from the backpulse tank to a final disposal
point. Clean water (permeate) is suctioned through ZW500D
membranes by variable-speed centrifugal permeate pumps.
Permeate flow rate is controlled to keep up with the demand
placed on the system by influent flow.
8 Membrane System
7/29/2019 MBR_BANG_01
8/18
In Phase I, One train1 with 46 modules will produce permeate
of 1MLD, The Cassette is Consisting of Modules 4-50 quantity
9 Membrane Scour Aeration System
The membranes are air scoured with one duty membrane
aeration blowers for Phase I and additional One-duty
membrane aeration blowers for Phase II and additional One-
duty membrane aeration blowers for Phase III. The membrane
blower capacity for the respective phases can be adjusted by
pulley arrangement.
10 Mixed Liquor Recirculation Equipment
Recirculation pumps are used to transfer mixed liquor from
the Membrane Tank to Bioreactor at the rate of 4 x ADF. The
effluent overflows by gravity from Bio-Reactor tank to the
Membrane tank at a rate of 5 x ADF.
The sludge recirculation transfers solids away from themembranes and provides proper distribution within the
bioreactor.
The mixed liquor is pumped from the Bioreactor Splitter by
Three (3) duty and one common standby to Membrane Tank
Splitter. Any of the membrane trains can be isolated from the
others to allow for cleaning or maintenance.
11 Sodium Hypochlorite Dosing System
The Sodium Hypochlorite Dosing system is used during
membrane cleaning applications to remove organic fouling
from the membrane surface.
7/29/2019 MBR_BANG_01
9/18
12 Citric Acid Dosing System
The Citric Acid Dosing system is used during membrane
cleaning applications to remove inorganic scaling from the
membrane surface.
13 Effluent Turbidity Analyzer
An effluent turbidity analyzer can monitor effluent water quality
and alert operators if effluent turbidity rises beyond acceptable
parameters. For optimal performance monitoring, one turbidity
analyzer per train is recommended.
14 Sludge Wasting System
Sludge wasting is accomplished by periodically diverting
mixed liquor from the recirculation return line, via manual
control or by pulling directly from the bioreactor. The
frequency of wasting is a function of influent characteristics,
reactor design and operator preference. In certain operating
circumstances, bioreactors can be designed to accommodate
client preferences with regards to wasting frequencies
15 Coagulant dosing System
The Coagulant Dosing system will be used to feed a metal salt
(Ferric Chloride) to assist in precipitating phosphorus in the
mixed liquor. This precipitate is then filtered by the
ZeeWeed 500 ultrafiltration membranes, preventing
phosphorus from entering the effluent.
16 Control Equipment
7/29/2019 MBR_BANG_01
10/18
Programmable Logic Controller (PLC) and Panel HMI with a
Human Machine Interface (HMI), installed in the main NEMA
12 control panel, monitors and manages all critical process
operations.
The control panel includes all motor control hardware for the
equipment.
17 Backpulse or Backwash
Under certain fouling conditions or when experiencing poor
sludge characteristics, the ability to ackpulse is essential to
maintaining clean membranes. This feature allows for flexibleand reliable system performance during unexpected influent
or process operating scenarios. Applying the ackpulse
cleaning option is one of the simplest methods to ensure
that immersed membranes retain optimum permeability
throughout all operating conditions.
Backpulsing involves reversing the flow through the
membranes to slightly expand the membrane pores and
dislodge any particles that may have adhered to the
membrane fiber surface. Permeate used for backpulsing is
taken from the ackpulse tank.
An optimized ackpulse-cleaning schedule can ensure that the
plant benefits from:
High membrane permeability;
Efficient plant operation with minimal downtime;
Reduced frequency of chemical cleans;
Lower consumption of cleaning chemicals.
7/29/2019 MBR_BANG_01
11/18
For this project system design, dedicated ackpulse pumps
will provide the reverse flow at low pressures.
When operating in Backpulse mode the system backpulses
for 30 seconds at 34 lmh, every 12 to 15 minutes. No
chemicals are used during a Backpulse.
In addition to the normal filtration cycle, regular chemical
cleaning is essential to maintain the performance of the
membrane. philosophy is to always maintain the membrane in
state of readiness to effectively handle peak events when they
occur. This is achieved by using automatic in-situ maintenance
cleans as described below.
18 Maintenance Clean
Sodium hypochlorite is used to oxidize organic foulants and
citric acid is used to remove inorganic scaling.
For this project, maintenance cleaning is recommended up to
twice per week using sodium hypochlorite and once per week
using citric acid.
The maintenance cleaning procedure incorporates the
following features;
fully automated and the frequency is set by the operator;
Performed with full membrane tank (i.e. no tank drain
required);
(1) Hour duration per clean per train
Based on the site-specific requirements, cleaning procedures
can be modified to obtain effective cleaning and maximize
7/29/2019 MBR_BANG_01
12/18
chemical savings.
19 Recovery Clean
Recovery cleaning is required to restore the permeability of
the membrane once the membrane becomes fouled. A
recovery clean should be initiated when permeability declines
to less than 50% of initial stable permeability. This will
generally occur when the trans-membrane pressure (TMP)
consistently exceeds 4-5 psi (vacuum) under normal flow
conditions. The recovery cleaning procedure consists of a
chemical ackpulse sequence, followed by a chemical soak
period. The cleaning chemical concentrations typically used to
soak the membranes are 1,000-mg/L sodium hypochlorite
(NaOCl) for the removal of organic foulants and 2,000-mg/L
citric acid for the removal of inorganic foulants.
Key features of the recovery cleaning procedure for
ZeeWeed membrane filtration
system are:
Fully automated and initiated by the operator;
Cleans all membrane cassettes in a train at the same time;
Recommended two times per annum
Requires moderate chemical concentration Spent cleaning chemicals can be neutralized if required
7/29/2019 MBR_BANG_01
13/18
Estimated Cleaning Chemical ConsumptionTable provides the estimated yearly chemical consumptionrelated to maintenance cleans. The chemical consumption isbased on installed number of membranes.
Table 4.1: Maintenance Cleaning Su mmary
Parameters (for N Operating Trains) NaOCl Citric Acid
Phase I TotalPhas
e
Phase I Total
PhaseFrequency 2/week 1/week
Dosing Concentration of Chemical 200 200 2000 2000
Concentration (% by weight) 10.3 10.3 50 50
Average Volume ofChemical Required(liters/Train/Clean)
7.4 10.53 14.36 20.43
Estimated Volume of ChemicalConsumed Per Year in the Plant forMaintenance Cleans (L)
374 936 363 603
Preliminary Biological Process Design
The biological design is based on the design parameters as
described in Sections 3.1 and 3.2 of this proposal.
Table 4.1 presents GEWPT's recommended
biological process design parameters.
7/29/2019 MBR_BANG_01
14/18
Table 4.1: Preliminary Biological Process DesignParameter
Design Parameters Unit Values
Design Flow m
3
/d 2500Number of Biological Train - 3
Working Volume of each Anoxic m3 200
Working Volume of each Aerobic m3 270
Number of Membrane Tank - 3
Volume of Each Membrane Tank m3 23.2
Total bioreactor volume including m3 1480
Design HRT hr 14
Design SRT at min. design Temperature d 20
Design MLSS in Bioreactor g/L 8000
Aerobic Tank Working Depth (a minimum
of 0.5 meter is recommended to address
m 4.5
Oxygen requirements at max Temperature kg/d 1190Air required for process Note1 m3/hr 2170
Total Sludge Wasting per day @ max
Temp and MLSS (10 g/L) (wasting from
m3/d 50
Note (1) Air quantity mentioned above are approximate needs
confirmations from diffuser manufacturers
One membrane filtration train will be provided for each
phase. The membrane system design is summarized in
Parameter Values
7/29/2019 MBR_BANG_01
15/18
T e of Membrane ZW 500DNumber of Membrane 1Number of Cassettes 1Total No of cassettes in the 1Number of Membrane
modules installed per train
48
Total No of modules in the 48% free S are s ace -Surface area of each 34.37 m2
Net Flux N condition 25.25 lmhMembrane Tank
Dimensions per Train
(Preliminary dimensions)
L 2.57 x W 3.05 x TD 3.96
: MBR Operating Parameters
Parameter DesignValue
AcceptedOperating Range Units
Membrane tank MLSS 10,000 8,000 - 10,000 m /LBioreactor MLSS 8,000 6,000 - 8,000 mg/L
Bioreactor MLVSS 67 > 70 % MLSSDissolved oxygen 2.0 1.5 - 3.0 mg/LBioreactor H 7 6.5 - 7.5 SUTotal solids retention time 20 20-25 da sTotal time to filter of 200 2mm in size 0
7/29/2019 MBR_BANG_01
16/18
Table 2A: Guaranteed Membrane Permeate Quality forMembrane Warranty Duration
Parameter Guaranteed Values
Maximum MBR Treatment 2500 m3/day for all
Turbidity < 1 NTU,100% of theTotal Suspended Solids
7/29/2019 MBR_BANG_01
17/18
TKN < 3 mg/L
Total Phosphorus < 1 mg/L
GENERAL NOTES:1. The guaranteed effluent quality is based on a non-toxicand non-inhibitory wastewater composition in the inflow.The presence of such material in the wastewater will inhibitor kill the bacteria seriously impeding the efficiency of theMBR, and in this case the limits cannot be guarantEEd
7/29/2019 MBR_BANG_01
18/18