+ All Categories
Home > Documents > MBR_BANG_01

MBR_BANG_01

Date post: 14-Apr-2018
Category:
Upload: deyprasen
View: 213 times
Download: 0 times
Share this document with a friend

of 18

Transcript
  • 7/29/2019 MBR_BANG_01

    1/18

    Technical and Engineering Details

    - Basis of Design

    This proposal is based on the following design values to

    be used for design MBR system.

    - Influent Quality

    The design solution proposed is based on the values as

    presented in Table 3.1. All concentrations refer to max

    concentrations to be used for the system's design.

    Fluctuations in feed composition and hydraulics will be

    appropriately equalized to allow for optimum biologicaltreatment.

    Table 3.1: Influent Quality to MBR

    Parameter Unit Design Concentration

    pH NU 6 - 8

    Oil & Grease mg/L < 10Chemical Oxygen Demand (COD) mg/L 600

    Biological Oxygen Demand - 5-day mg/L 300

    Total Suspended Solids mg/L 200

    Ammonia, as NH3 mg/L < 40

    TKN, as N mg/L < 70

    Total Phosphorous mg/L 10

    Total Alkalinity mg/L 400

    Total Dissolved Solids mg/L 1500 2100

    Note (1) All solids are assumed to be < 2 mm in any dimension;

    otherwise, larger solids, such as hair and fibrous material, have to

    be removed by others prior to entering the MBR to avoid any

  • 7/29/2019 MBR_BANG_01

    2/18

    harm to the membranes.

    3.3 Influent Flow DataFlow rate at the inlet to the proposed MBR as well as the resultingbioreactor temperature is shown in Table 3.2.

    Parameter Unit Design

    Max. flow rate, both membranetrains in operation

    m3/d 2500SeeNote1 (Total

    Phase) 1000 (Phase I)1750 (Phase II) 2500(Phase III)

    Assumed Feed Temperature C 20-28

    Design Bioreactor Temperature C 20-28 See Note 2

    Note (1) It is required that feed flow be properly equalized

    by others and during N-1 condition the flow will be

    produced with subsequent trains. For the Phase I, the

    flow has to be equalized during cleaning.

    Note (2) Biological and membrane process is designed for

    a temperature operating range of 20 to 28 C. Higher

    temperatures > 35 C have to be avoided as they

    exceed the tolerance for the biology and membranes;

    otherwise appropriate cooling (by others) will be

    required.

  • 7/29/2019 MBR_BANG_01

    3/18

    3.4 Operation Basis

    Hours Per Day of 24 hrs

    Days Per Year of Operation 365 days NOTE: Consider Maintenance Time

    3.5 Expected Effluent Quality

    Table 3.4 shows the expected effluent quality upon

    equipment start-up based on the data listed in section 3.1 and

    3.2.

    Parameter Unit ExpectedChemical Oxygen Demand (COD) mg/L < 100 SeeNote1

    Biological Oxygen Demand - 5-day (BOD5) mg/L < 5

    Total Suspended Solids mg/L < 3

    Turbidity NTU < 1

    Ammonia, as NH3 mg/L < 1

    TKN mg/L < 2

    TP mg/L < 1

    PH NU 6 - 8

    Note (1) Expected effluent quality assumes soluble fractions of COD are

    biodegradable to this degree.

    Note (2) Since "3" is the minimum detection limit of TSS measurement

  • 7/29/2019 MBR_BANG_01

    4/18

    by Standard Methods, there is a potential for analytical error of TSS

    at such low levels. is able to provide TSS guarantees of < 3 mg/L

    95% of the time, provided that the TSS measurement is performed

    by a certified lab approved by with < 3 mg/L TSS measuring

    capabilities. Any samples with results greater than 2 will be

    retested to confirm that the accuracy of the analytical method.

  • 7/29/2019 MBR_BANG_01

    5/18

    4 MBR Plant General Scope Of Equipment

    Process Description

    The following sections describe additional equipment that is

    required for the system and will be supplied by GEWPT and

    Customer.

    1 Equalization Tank

    Equalization is required for any system with variable flow

    rates. An equalization (EQ) tank is normally installed upstream

    of the biological tank. The required equalization volume can

    also be incorporated into the biological tank under certain

    circumstances. A minimum equalization capacity of 10 hours

    is recommended.

    2 Equalization Transfer Pumps

    Transfer Pumps transport wastewater from the equalization

    tank or lift station to the process tank. The transfer pumps are

    automatically activated by the Level Switch in a lead/lag

    arrangement according to the level in the tank.

    3 Screening System

    Trash and non-biodegradable solids, such as hair, lint, grit and

    plastics may foul or damage the membranes if allowed to pass

    into the membrane chamber.

    An internally-fed screen with mesh or punched-hole openings

  • 7/29/2019 MBR_BANG_01

    6/18

    less than or equal to 2 mm in diameter with no possibility of

    bypass or carryover is absolutely required to maintain both

    membrane warranty, and optimal MBR operation.

    4 Process Mixers

    Process mixers can be used to mix the anoxic and post-

    anoxic chambers (if included) to prevent solids from settling in

    the anoxic chamber.

    5 Process Aeration System

    The process aeration blowers provide air for the biological tank

    and ensure that sufficient oxygen is available to maintain the

    biological processes in the tank. The aeration compartments

    will be fully aerated and mixed by a fine bubble aeration grid.

    Dissolved oxygen will be monitored in each aerobic tank to

    achieve a desired set point of 2 mg/L. For the Phase I, there

    will be One (1) duty blower and one standby blower providing

    process air to the aerobic zone of the bioreactor and for the

    Phase II & Phase III, there will be additional One (1) duty blower

    per Phase to provide process air to the aerobic zone of the

    bioreactor.

    6 Fine Bubble Diffusers

    A fine bubble diffused aeration system delivers air from the

    aeration blowers to the aerobic zone of the process tank.

    7 Permeate/Backpulse Pump Equipment

    One permeate pump is employed to draw water through the

    membranes. The permeate pump, associated valves and

  • 7/29/2019 MBR_BANG_01

    7/18

    piping for the system are mounted on a factory assembled,

    epoxy-coated carbon steel skid. Treated water flows from the

    permeate skid to the final disposal point.

    Under normal operation and average day flow conditions,

    permeation is stopped for a specific period of time at regular

    intervals. This membrane relaxation period, combined with air

    scouring, effectively removes solids that have accumulated on

    the membrane surface or within the fibers and reduces

    electrical costs.

    Same permeate pump is provided for backpulsing the

    membranes. Under increased flow or adverse sludge

    conditions, the operator is able to select a "backpulse" mode.

    In this instance, the Backpulse pump will reverse the flow of

    permeate through the membrane fibers to dislodge solids that

    have accumulated on the membrane surface or within the

    fibers.

    From membrane tanks, Permeate pump draws treated

    effluent through the pores of the membrane fibers and into the

    backpulse tank. Once full, the treated effluent is automatically

    diverted away from the backpulse tank to a final disposal

    point. Clean water (permeate) is suctioned through ZW500D

    membranes by variable-speed centrifugal permeate pumps.

    Permeate flow rate is controlled to keep up with the demand

    placed on the system by influent flow.

    8 Membrane System

  • 7/29/2019 MBR_BANG_01

    8/18

    In Phase I, One train1 with 46 modules will produce permeate

    of 1MLD, The Cassette is Consisting of Modules 4-50 quantity

    9 Membrane Scour Aeration System

    The membranes are air scoured with one duty membrane

    aeration blowers for Phase I and additional One-duty

    membrane aeration blowers for Phase II and additional One-

    duty membrane aeration blowers for Phase III. The membrane

    blower capacity for the respective phases can be adjusted by

    pulley arrangement.

    10 Mixed Liquor Recirculation Equipment

    Recirculation pumps are used to transfer mixed liquor from

    the Membrane Tank to Bioreactor at the rate of 4 x ADF. The

    effluent overflows by gravity from Bio-Reactor tank to the

    Membrane tank at a rate of 5 x ADF.

    The sludge recirculation transfers solids away from themembranes and provides proper distribution within the

    bioreactor.

    The mixed liquor is pumped from the Bioreactor Splitter by

    Three (3) duty and one common standby to Membrane Tank

    Splitter. Any of the membrane trains can be isolated from the

    others to allow for cleaning or maintenance.

    11 Sodium Hypochlorite Dosing System

    The Sodium Hypochlorite Dosing system is used during

    membrane cleaning applications to remove organic fouling

    from the membrane surface.

  • 7/29/2019 MBR_BANG_01

    9/18

    12 Citric Acid Dosing System

    The Citric Acid Dosing system is used during membrane

    cleaning applications to remove inorganic scaling from the

    membrane surface.

    13 Effluent Turbidity Analyzer

    An effluent turbidity analyzer can monitor effluent water quality

    and alert operators if effluent turbidity rises beyond acceptable

    parameters. For optimal performance monitoring, one turbidity

    analyzer per train is recommended.

    14 Sludge Wasting System

    Sludge wasting is accomplished by periodically diverting

    mixed liquor from the recirculation return line, via manual

    control or by pulling directly from the bioreactor. The

    frequency of wasting is a function of influent characteristics,

    reactor design and operator preference. In certain operating

    circumstances, bioreactors can be designed to accommodate

    client preferences with regards to wasting frequencies

    15 Coagulant dosing System

    The Coagulant Dosing system will be used to feed a metal salt

    (Ferric Chloride) to assist in precipitating phosphorus in the

    mixed liquor. This precipitate is then filtered by the

    ZeeWeed 500 ultrafiltration membranes, preventing

    phosphorus from entering the effluent.

    16 Control Equipment

  • 7/29/2019 MBR_BANG_01

    10/18

    Programmable Logic Controller (PLC) and Panel HMI with a

    Human Machine Interface (HMI), installed in the main NEMA

    12 control panel, monitors and manages all critical process

    operations.

    The control panel includes all motor control hardware for the

    equipment.

    17 Backpulse or Backwash

    Under certain fouling conditions or when experiencing poor

    sludge characteristics, the ability to ackpulse is essential to

    maintaining clean membranes. This feature allows for flexibleand reliable system performance during unexpected influent

    or process operating scenarios. Applying the ackpulse

    cleaning option is one of the simplest methods to ensure

    that immersed membranes retain optimum permeability

    throughout all operating conditions.

    Backpulsing involves reversing the flow through the

    membranes to slightly expand the membrane pores and

    dislodge any particles that may have adhered to the

    membrane fiber surface. Permeate used for backpulsing is

    taken from the ackpulse tank.

    An optimized ackpulse-cleaning schedule can ensure that the

    plant benefits from:

    High membrane permeability;

    Efficient plant operation with minimal downtime;

    Reduced frequency of chemical cleans;

    Lower consumption of cleaning chemicals.

  • 7/29/2019 MBR_BANG_01

    11/18

    For this project system design, dedicated ackpulse pumps

    will provide the reverse flow at low pressures.

    When operating in Backpulse mode the system backpulses

    for 30 seconds at 34 lmh, every 12 to 15 minutes. No

    chemicals are used during a Backpulse.

    In addition to the normal filtration cycle, regular chemical

    cleaning is essential to maintain the performance of the

    membrane. philosophy is to always maintain the membrane in

    state of readiness to effectively handle peak events when they

    occur. This is achieved by using automatic in-situ maintenance

    cleans as described below.

    18 Maintenance Clean

    Sodium hypochlorite is used to oxidize organic foulants and

    citric acid is used to remove inorganic scaling.

    For this project, maintenance cleaning is recommended up to

    twice per week using sodium hypochlorite and once per week

    using citric acid.

    The maintenance cleaning procedure incorporates the

    following features;

    fully automated and the frequency is set by the operator;

    Performed with full membrane tank (i.e. no tank drain

    required);

    (1) Hour duration per clean per train

    Based on the site-specific requirements, cleaning procedures

    can be modified to obtain effective cleaning and maximize

  • 7/29/2019 MBR_BANG_01

    12/18

    chemical savings.

    19 Recovery Clean

    Recovery cleaning is required to restore the permeability of

    the membrane once the membrane becomes fouled. A

    recovery clean should be initiated when permeability declines

    to less than 50% of initial stable permeability. This will

    generally occur when the trans-membrane pressure (TMP)

    consistently exceeds 4-5 psi (vacuum) under normal flow

    conditions. The recovery cleaning procedure consists of a

    chemical ackpulse sequence, followed by a chemical soak

    period. The cleaning chemical concentrations typically used to

    soak the membranes are 1,000-mg/L sodium hypochlorite

    (NaOCl) for the removal of organic foulants and 2,000-mg/L

    citric acid for the removal of inorganic foulants.

    Key features of the recovery cleaning procedure for

    ZeeWeed membrane filtration

    system are:

    Fully automated and initiated by the operator;

    Cleans all membrane cassettes in a train at the same time;

    Recommended two times per annum

    Requires moderate chemical concentration Spent cleaning chemicals can be neutralized if required

  • 7/29/2019 MBR_BANG_01

    13/18

    Estimated Cleaning Chemical ConsumptionTable provides the estimated yearly chemical consumptionrelated to maintenance cleans. The chemical consumption isbased on installed number of membranes.

    Table 4.1: Maintenance Cleaning Su mmary

    Parameters (for N Operating Trains) NaOCl Citric Acid

    Phase I TotalPhas

    e

    Phase I Total

    PhaseFrequency 2/week 1/week

    Dosing Concentration of Chemical 200 200 2000 2000

    Concentration (% by weight) 10.3 10.3 50 50

    Average Volume ofChemical Required(liters/Train/Clean)

    7.4 10.53 14.36 20.43

    Estimated Volume of ChemicalConsumed Per Year in the Plant forMaintenance Cleans (L)

    374 936 363 603

    Preliminary Biological Process Design

    The biological design is based on the design parameters as

    described in Sections 3.1 and 3.2 of this proposal.

    Table 4.1 presents GEWPT's recommended

    biological process design parameters.

  • 7/29/2019 MBR_BANG_01

    14/18

    Table 4.1: Preliminary Biological Process DesignParameter

    Design Parameters Unit Values

    Design Flow m

    3

    /d 2500Number of Biological Train - 3

    Working Volume of each Anoxic m3 200

    Working Volume of each Aerobic m3 270

    Number of Membrane Tank - 3

    Volume of Each Membrane Tank m3 23.2

    Total bioreactor volume including m3 1480

    Design HRT hr 14

    Design SRT at min. design Temperature d 20

    Design MLSS in Bioreactor g/L 8000

    Aerobic Tank Working Depth (a minimum

    of 0.5 meter is recommended to address

    m 4.5

    Oxygen requirements at max Temperature kg/d 1190Air required for process Note1 m3/hr 2170

    Total Sludge Wasting per day @ max

    Temp and MLSS (10 g/L) (wasting from

    m3/d 50

    Note (1) Air quantity mentioned above are approximate needs

    confirmations from diffuser manufacturers

    One membrane filtration train will be provided for each

    phase. The membrane system design is summarized in

    Parameter Values

  • 7/29/2019 MBR_BANG_01

    15/18

    T e of Membrane ZW 500DNumber of Membrane 1Number of Cassettes 1Total No of cassettes in the 1Number of Membrane

    modules installed per train

    48

    Total No of modules in the 48% free S are s ace -Surface area of each 34.37 m2

    Net Flux N condition 25.25 lmhMembrane Tank

    Dimensions per Train

    (Preliminary dimensions)

    L 2.57 x W 3.05 x TD 3.96

    : MBR Operating Parameters

    Parameter DesignValue

    AcceptedOperating Range Units

    Membrane tank MLSS 10,000 8,000 - 10,000 m /LBioreactor MLSS 8,000 6,000 - 8,000 mg/L

    Bioreactor MLVSS 67 > 70 % MLSSDissolved oxygen 2.0 1.5 - 3.0 mg/LBioreactor H 7 6.5 - 7.5 SUTotal solids retention time 20 20-25 da sTotal time to filter of 200 2mm in size 0

  • 7/29/2019 MBR_BANG_01

    16/18

    Table 2A: Guaranteed Membrane Permeate Quality forMembrane Warranty Duration

    Parameter Guaranteed Values

    Maximum MBR Treatment 2500 m3/day for all

    Turbidity < 1 NTU,100% of theTotal Suspended Solids

  • 7/29/2019 MBR_BANG_01

    17/18

    TKN < 3 mg/L

    Total Phosphorus < 1 mg/L

    GENERAL NOTES:1. The guaranteed effluent quality is based on a non-toxicand non-inhibitory wastewater composition in the inflow.The presence of such material in the wastewater will inhibitor kill the bacteria seriously impeding the efficiency of theMBR, and in this case the limits cannot be guarantEEd

  • 7/29/2019 MBR_BANG_01

    18/18