Prepared by
Capital CostMethodology andEstimate Report
August 2014
Capital Cost Methodology and Estimate ReportAugust 2014
Prepared by:The San Diego Association of Governments (SANDAG)
THIS PAGE INTENTIONALLY LEFT BLANK
Capital Cost Methodology and Estimate ReportTable of Contents
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TiAugust 2014
Table of Contents
1.0 INTRODUCTION .............................................................................................................. 1-11.1 Purpose of the Report ...................................................................................... 1-11.2 Description of the Mid-Coast Corridor .............................................................. 1-21.3 Description of the Mid-Coast Corridor Transit Project....................................... 1-4
2.0 FEDERAL TRANSIT ADMINISTRATION STANDARD COST CATEGORIES ................................. 2-12.1 Capital Cost Categories ................................................................................... 2-12.2 SCC 10—Guideway and Track Elements......................................................... 2-1
2.2.1 Guideway ............................................................................................. 2-12.2.2 Track .................................................................................................... 2-3
2.3 SCC 20—Stations, Stops, Terminals, and Intermodal ...................................... 2-42.4 SCC 30—Support Facilities: Yards, Shops, and Administration Buildings ........ 2-62.5 SCC 40—Sitework and Special Conditions ...................................................... 2-62.6 SCC 50—Systems ........................................................................................... 2-82.7 SCC 60—Right-of-Way, Land, and Existing Improvements ............................ 2-102.8 SCC 70—Vehicles ......................................................................................... 2-102.9 SCC 80—Professional Services ..................................................................... 2-112.10 SCC 90—Unallocated Contingency ............................................................... 2-112.11 SCC 100—Finance Charges .......................................................................... 2-11
3.0 ESTIMATING METHODOLOGY .......................................................................................... 3-13.1 General Approach ............................................................................................ 3-23.2 Cost Estimating Assumptions........................................................................... 3-23.3 Estimating Procedures ..................................................................................... 3-33.4 Allocated Contingency ..................................................................................... 3-43.5 Organization and Management of Cost Data ................................................... 3-73.6 Cost Estimating Results Format ....................................................................... 3-73.7 Cash Flow and Escalation ................................................................................ 3-83.8 Annualized Cost Factors .................................................................................. 3-93.9 Unit Pricing .................................................................................................... 3-10
4.0 CAPITAL COST ESTIMATE ............................................................................................... 4-1
5.0 ESTIMATE LIMITATIONS .................................................................................................. 5-15.1 Standard Design Criteria .................................................................................. 5-15.2 Scope and Quantity Definition .......................................................................... 5-15.3 Commodity Pricing ........................................................................................... 5-15.4 Unforeseen Challenges.................................................................................... 5-1
6.0 REFERENCES ............................................................................................................ 6-1
List of Appendices
APPENDIX A CAPITAL COST ESTIMATE DETAILED REPORT ....................................... A-1
Capital Cost Methodology and Estimate ReportTable of Contents
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 2014ii
List of Figures
Figure 1-1. Mid-Coast Corridor ........................................................................................... 1-3Figure 1-2. Refined Build Alternative .................................................................................. 1-5Figure 1-3. Conceptual Plan and Profile of Refined Build Alternative ................................. 1-7
List of Tables
Table 3-1. Approximate Level of Design for Each SCC ..................................................... 3-4Table 3-2. Allocated Contingency Percentages for the Final SEIS/SEIR Cost
Estimate (Refined Build Alternative) ................................................................ 3-6Table 3-3. Annualization Factors ...................................................................................... 3-9Table 3-4. Unit Prices ..................................................................................................... 3-22Table 4-1. Summary of the Capital Cost for the Refined Build Alternative ......................... 4-1Table 4-2. Mid-Coast Capital Cost Estimate – Refined Build Alternative ........................... 4-3
Capital Cost Methodology and Estimate ReportTable of Contents
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TiiiAugust 2014
Abbreviations
The following acronyms, initialisms, and short forms are used in this report.
BMPs Best Management Practices
Caltrans California Department of Transportation
FTA Federal Transit Administration
I- Interstate
LOSSAN Los Angeles-San Diego-San Luis Obispo Rail Corridor Agency
LRT light rail transit
LRV light rail vehicle
MSE Mechanically stabilized earth
MTDB Metropolitan Transit Development Board
MTS Metropolitan Transit System
MVE LRT Extension Mission Valley East Light Rail Extension
OCS Overhead Catenary System
OTTC Old Town Transit Center
PE preliminary engineering
ROM Rough Order of Magnitude
SANDAG San Diego Association of Governments
SCC Standard Cost Category
SEIS/SEIR Supplemental Environmental Impact Statement and SubsequentEnvironmental Report
TPSS Traction Power Substation
SR State Route
UCSD University of California, San Diego
UTC University Towne Centre
VA Veterans Administration
YOE Year of Expenditure
Capital Cost Methodology and Estimate ReportTable of Contents
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 2014iv
THIS PAGE INTENTIONALLY LEFT BLANK
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-1August 2014
1.0 INTRODUCTIONThe Federal Transit Administration (FTA) and the San Diego Association of Governments(SANDAG) have prepared a Supplemental Environmental Impact Statement andSubsequent Environmental Impact Report (SEIS/SEIR) for the Mid-Coast Corridor TransitProject in San Diego, California. The SEIS/SEIR supplements the following environmentaldocuments: the Mid-Coast Corridor Alternatives Analysis/Draft Environmental ImpactStatement/Draft Environmental Impact Report (Metropolitan Transit Development Board[MTDB], 1995a); the Final Environmental Impact Report for the Mid-Coast Corridor(MTDB, 1995b); and the Mid-Coast Corridor Project Balboa Extension and Nobel DriveCoaster Station Final Environmental Impact Statement (MTDB, 2001). The FTA is servingas lead agency for the SEIS in accordance with the National Environmental Policy Act of1969, and SANDAG is serving as lead agency for the SEIR in accordance with theCalifornia Environmental Quality Act of 1970.
The Final SEIS/SEIR includes an analysis of the affected environment and potential impactson the social, economic, cultural, and natural environment that will result from constructingand operating the alternatives under consideration within the Mid-Coast Corridor. Thealternatives being considered and analyzed for potential impacts include a No-BuildAlternative and a Refined Build Alternative. The No-Build Alternative is the same asdescribed in the Mid-Coast Corridor Transit Project Draft Supplemental EnvironmentalImpact Statement/Subsequent Environmental Impact Report (SANDAG, 2013a).
The Refined Build Alternative is the Mid-Coast Corridor Transit Project, or project, approvedby the SANDAG Board of Directors for evaluation in the Final SEIS/SEIR on November 15,2013. The project consists of extending the existing San Diego Trolley (Trolley) Blue Linefrom the Santa Fe Depot north to the Old Town Transit Center (OTTC), via the existingTrolley tracks, and then north along new tracks to the University Towne Centre (UTC)Transit Center in University City, with nine new stations at Tecolote Road, Clairemont Drive,Balboa Avenue, Nobel Drive, Veterans Administration (VA) Medical Center, University ofCalifornia, San Diego (UCSD) West Campus, UCSD East Campus, Executive Drive, andthe UTC Transit Center.
The Refined Build Alternative generally reflects the Build Alternative with the VA MedicalCenter Station Option evaluated in the Draft SEIS/SEIR; however, it also includes someadditional refinements. Section 2.4 in Chapter 2.0 of the Final SEIS/SEIR provides adetailed description of the Refined Build Alternative. The process of developing therefinements is discussed in Section 2.3 of Chapter 2.0 of the Final SEIS/SEIR, as well as inthe Mid-Coast Corridor Transit Project Final Refined Build Alternative Report (SANDAG,2014e).
1.1 Purpose of the ReportThis report describes the methodology used to determine capital costs associated withthe Refined Build Alternative. It also presents the capital cost estimates developed forthe Refined Build Alternative.
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-2
This report is organized into the following chapters:
· Introduction
· FTA Standard Cost Categories
· Estimating Methodology
· Capital Cost Estimate
· Estimate Limitations
· References
1.2 Description of the Mid-Coast CorridorThe Mid-Coast Corridor is the area centering on Interstate (I-) 5 and extending fromDowntown San Diego on the south to University of California, San Diego (UCSD) andUniversity City on the north (Figure 1-1). Located entirely within the City of San Diego,the corridor is bounded by the Pacific Ocean on the west and by I-805 and State Route(SR) 163 on the east. The Mid-Coast Corridor is topographically diverse, with terrainranging from coastal beaches and bays to inland areas containing steep hillsides andnarrow canyons.
The Mid-Coast Corridor is characterized by dense urban centers and an abundance ofregional activity centers and other major trip generators. Dense population andemployment centers currently anchor both the northern and southern ends of the Mid-Coast Corridor. The UCSD campus, the Westfield UTC shopping center, and regionalhospitals are clustered in the north part of the corridor and represent the second mostdense land uses in the county. At the south end of the corridor is the region’s onlyidentified Metropolitan Center—Downtown San Diego—with the region’s densest landuses and high-rise development.
Other major land uses within or immediately adjacent to the corridor (Figure 1-1) include:
· Regional hospitals: Scripps Green Hospital, Scripps Memorial Hospital La Jolla(Scripps Hospital), UCSD Thornton Hospital, VA Medical Center, UCSD MedicalCenter Hillcrest, and Scripps Mercy Hospital
· Major colleges and universities: UCSD, University of San Diego, San Diego MesaCollege, and San Diego City College
· Regional shopping centers: Westfield UTC, Fashion Valley, and Westfield HortonPlaza
· Major parks and visitor attractions: Mission Bay Park, San Diego Zoo, SeaWorldSan Diego, Old Town San Diego State Historic Park, Balboa Park, the GaslampQuarter, San Diego Convention Center, Petco Park, Rose Canyon Open SpacePark, and Marian Bear Memorial Park
· San Diego International Airport
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-3August 2014
Figure 1-1. Mid-Coast Corridor
Source: SANDAG, 2012Note: The Trolley lines shown represent the 2010 Trolley operating plan.
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-4
1.3 Description of the Mid-Coast Corridor Transit ProjectThe Refined Build Alternative, or project, is described in detail in Section 2.4 in Chapter2.0 of the Final SEIS/SEIR (SANDAG, 2014a). Plan drawings of the project are containedin Final SEIS/FEIR Plan Set (SANDAG, 2014b).
The project will extend the Trolley Blue Line from Santa Fe Depot in Downtown SanDiego to the UTC Transit Center in University City. The project will use the existingTrolley tracks for approximately 3.5 miles, from the Santa Fe Depot to north of the OTTCand south of the San Diego River. The Trolley Blue Line trains will share the existingtracks with the Trolley Green Line trains. The project also will include construction of10.9 miles of new double track that would extend from south of the San Diego River tothe terminus at the UTC Transit Center.
The new extension will follow the Los Angeles—San Diego—San Luis Obispo RailCorridor Agency (LOSSAN) tracks within existing Metropolitan Transit System and Cityof San Diego right-of-way from the Santa Fe Depot to north of the I-5/SR 52 interchange.The alignment will then leave the LOSSAN right-of-way and parallel the east side of theI-5 corridor traveling north partially within Caltrans right-of-way and partially on privateproperty. South of Nobel Drive, the alignment will transition to an aerial structure andcross over to the west side of I-5. From Nobel Drive, the alignment will continue north tothe UCSD West Campus, cross back over to the east side of I-5 and along the southside of Voigt Drive to Genesee Avenue, and continue south in the median of GeneseeAvenue to the UTC Transit Center.
The project includes 9 new stations (4 at grade and 5 elevated); 5 park-and-ride facilitieswith 1,070 parking spaces; 14 new and 2 upgraded traction power substations (TPSS);and 36 new low-floor light rail transit vehicles. No new maintenance facilities areneeded. New stations will be located at Tecolote Road, Clairemont Drive, BalboaAvenue, Nobel Drive, the VA Medical Center, UCSD West, UCSD East, Executive Drive,and the UTC Transit Center.
Figure 1-2 shows the project alignment and station locations under the Refined BuildAlternative, and Figure 1-3 shows the plan and profile along with locations of stationsand TPSSs.
With the extension of the Trolley Blue Line from Santa Fe Depot to UTC Transit Center,continuous service would be provided from the San Ysidro Transit Center at the U.S.–Mexico international border to University City. The service would be provided every 7.5minutes during peak and off-peak periods in 2030.
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-5August 2014
Figure 1-2. Refined Build Alternative
Source: SANDAG, 2014
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-6
THIS PAGE INTENTIONALLY LEFT BLANK
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-7August 2014
Figure 1-3. Conceptual Plan and Profile of Refined Build Alternative
Source: SANDAG, 2013
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-8
THIS PAGE INTENTIONALLY LEFT BLANK
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-9August 2014
Figure 1-3. Conceptual Plan and Profile of Refined Build Alternative (continued)
Source: SANDAG, 2014
Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-10
THIS PAGE INTENTIONALLY LEFT BLANK
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-1August 2014
2.0 FEDERAL TRANSIT ADMINISTRATION STANDARD COSTCATEGORIESThe methodology used for generating capital cost estimates will be consistent with theFederal Transit Administration (FTA) guidelines for estimating capital costs. The basisof the FTA guidance is the Standard Cost Categories (SCC), which enables all FTA-funded projects to develop budget baselines that summarize SCCs. This cost structurewill be used for developing capital cost detail and summary sheets, as described below.
2.1 Capital Cost CategoriesIn accordance with the latest version of the FTA’s SCC, the capital cost components ofthe Refined Build Alternative will be classified into the following cost categories:
10 Guideway and Track Elements20 Station, Stops, Terminals, and Intermodal30 Support Facilities: Yards, Shops, and Administration Buildings40 Sitework and Special Conditions50 Systems60 Right-of-Way, Land, and Existing Improvements70 Vehicles80 Professional Services90 Unallocated Contingency100 Finance Charges
The following sections provide brief descriptions of these cost categories and theirconstituent elements.
2.2 SCC 10—Guideway and Track ElementsGuideway and track elements are portions of the transit system that can be assigned costsat a fairly aggregate level with an acceptable level of accuracy. Most commonly, theseelements are linear and can be represented by typical cross sections. Guideway and trackelements are subdivided into a number of subcategories, as described below.
2.2.1 GuidewayThe guideway cost category is comprised of the following subcategories:
10.01 Guideway: At-grade exclusive right-of-way10.02 Guideway: At-grade semi-exclusive (allows cross-traffic) (not used)10.03 Guideway: At-grade in mixed traffic (not used)10.04 Guideway: Aerial structure10.05 Guideway: Built-up fill (not used)10.06 Guideway: Underground cut and cover
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-2
10.07 Guideway: Underground tunnel (not used)10.08 Guideway: Retained cut or fill
These cost categories include all construction elements up to the point where trackconstruction typically begins at the top of subballast. The guideway cost estimates arebased on parametric unit cost information specifically developed for each constructiontype. In general, all of the parametric guideway cost estimates provide for the followingconstruction elements, as appropriate:
10.01 At-Grade Construction
· Excavation and embankment· Permanent Best Management Practices (BMPs)· Drainage systems for the guideway· Cross drainage for off-site flow· Open channels paralleling the tracks· Subgrade preparation and base for ballasted track construction· Fencing· Landscape and Irrigation
10. 04 Aerial Structures Construction· Permanent BMPs· Drainage systems for the aerial guideway· Structural excavation and backfill· Foundation support, including piling, drilled piers, etc.· Structural concrete· Steel reinforcement· Catenary poles foundations· Sound walls on bridges· Emergency walkways· Architectural treatment· Stray current monitoring (Bridge)· Hydromodification
10.06 Underground Structures (Cut and Cover) Construction
· Approach U-sections· Structural excavation and backfill (including U-sections)· Structural concrete· Steel reinforcement· Architectural treatment and anti-graffiti coating· Stray current monitoring
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-3August 2014
· Water proofing· Water diversion· Permanent BMPs· Drainage systems for the guideway· Temporary Shoring
10.08 Retained Cut or Fill Construction
· Structural excavation and backfill· Guideway excavation and embankment· Pervious Backfill· MSE Wall· Tieback Wall· Structural concrete (retaining wall)· Steel reinforcement (retaining wall)· Concrete Barrier· Permanent BMPs· Drainage systems for the guideway· Subgrade preparation and base for ballasted track construction· Fencing and railings· Sound walls on retaining walls· Architectural treatment and anti-graffiti coating· Stray current monitoring· Landscape and Irrigation
Earthwork quantities are generated from a comparison of existing terrain conditions withproposed subgrade elevations. Sections are evaluated at 50-foot intervals, and showrequirements for guideway excavation and embankments, and structural excavation andbackfill. Retaining wall quantities are generated from the analysis of wall height,thickness, and footing requirements.
2.2.2 TrackThe track cost categories include the running rails, ties, ballast, direct fixation concreteplinth, embedded track, and special track components (turnouts, crossovers, etc.)associated with the type of track construction. The following is a list of the subcategoriesassociated with this cost category:
10.09 Track: Direct fixation10.10 Track: Embedded (not used)10.11 Track: Ballasted10.12 Track: Special (switches and turnouts)10.13 Track: Vibration and noise dampening
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-4
The cost of constructing the supporting subgrade, subballast, or concrete supportingstructure normally will be included in the guideway cost categories. The standard railsection for ballasted and direct-fixation track is continuous welded 115RE rail for LRTand 136RE rail for Los Angeles–San Diego–San Luis Obispo Rail Corridor Agency(LOSSAN) tracks. For ballasted track, the unit cost includes rail, rail welding, railfasteners, and rail anchors. For direct fixation track, the concrete ties and ballast arereplaced with rail attached on a second-pour reinforced concrete plinth pad with a directfixation rail fastener. Special trackwork typically includes turnouts, single and doublecrossovers, wyes, pocket tracks, and bumping posts. The costs for special trackworkare applied on a per unit basis at specific locations. The track costs for the storage yardor maintenance shop facility are typically included in Cost Category 30, SupportFacilities. However, for the Mid-Coast Corridor Transit Project, the existing track storageand maintenance facilities are adequate and improvements to the MTS maintenanceyard are not required.
2.3 SCC 20—Stations, Stops, Terminals, and IntermodalStation costs represent the fixed facilities and amenities for transit stations. Thepassenger station cost estimates are based on historical costs of similar facilities. Thestation cost category is comprised of the following subcategories:
20.01 At-grade station20.02 Aerial station20.03 Underground station, stop, shelter, mall, terminal, and platform (not used)20.04 Other stations, landings, and terminals: intermodal, ferry, trolley, etc. (not
used)20.05 Joint development (not used)20.06 Automobile parking multi-story structure20.07 Elevators and escalators
20.01 At-Grade StationsAt-grade stations will have side platforms. Station costs will include the following:
· Station striping (thermoplastic and markers)· Bike locker· Informational kiosk· Screen wall (8 feet high with footing where applicable)· Station plumbing· Station water· Metal panel screen wall· Chain link fence· Excavation and embankment· Permanent BMPs· Drainage
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-5August 2014
· Concrete footings, walls, and platform slab· Canopy(ies) including foundation and seating, covering a portion of the
platform· Track paving, architectural surface treatment of platform with pavers and
tactile warning strips· Station furnishings, ornamental fencing and signage· Lighting, electrical, telecommunication, and mechanical allowances· Artwork· Planting and Irrigation
20.02 Aerial StationsAerial stations will have side platforms. Station costs will include the following:
· Stainless steel and glass screen wall· Guard railing—stainless steel with glass panel· Station striping (thermoplastic and markers)· Bike locker· Informational kiosk· Station plumbing· Permanent BMPs· Drainage· Platform pre-cast concrete panels and pedestrian railing· Canopy(ies) covering a portion of the platform· Architectural surface treatment of platform with pavers and tactile warning
strips· Station furnishings and signage· Lighting, electrical, and mechanical allowances· Vertical circulation elements (i.e., stairs or structural elements to support
elevators and escalators. Equipment purchase and installation is includedunder item 20.07)
· Equipment rooms or operator welfare structures· Artwork· Planting and irrigation
20.06 Automobile Parking Multi-story Structure· Excavation and rough grading· Structural excavation and backfill· Foundation support, including piling, drilled piers, etc.· Concrete footings, columns, pier caps, decking and superstructure
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-6
· Steel reinforcement· Pedestrian access and protection for parking structures· Lighting, electrical, and mechanical allowances
20.07 Elevators and EscalatorsSingle and double elevators are used for all aerial stations and at parkingstructures. Escalators are not used in this project.
At-grade pedestrian access to transit stations and surface parking lots associated withpassenger stations are accounted for under other cost categories described below.
2.4 SCC 30—Support Facilities: Yards, Shops, and Administration BuildingsThis cost category includes vehicle storage and maintenance buildings, trackwork for thestorage of rail vehicles, vehicle cleaning and painting facilities, office support areas,maintenance-of-way facilities, and general and major shop equipment. The following isa list of the subcategories under this cost category:
30.01 Administration building: office, sales, storage, and revenue counting30.02 Light maintenance facility30.03 Heavy maintenance facility30.04 Storage or maintenance-of-way building30.05 Yard and yard track
For this project, the existing light rail transit (LRT) maintenance and storage facility iscapable of handling a fleet size of 200 light rail vehicles. The present fleet size is 158vehicles. Thirty of these vehicles have completed their design life and are slated to besold, leaving MTS with a fleet of 128 vehicles. The Mid-Coast Coast Corridor TransitProject will add an additional 36 vehicles to that fleet. Therefore, no costs for expansionof the yard will be incurred in this category.
2.5 SCC 40—Sitework and Special ConditionsThe development of a functional transit system often requires that a number of ancillarymitigation requirements, which may or may not be directly related to the transit systemservice, be addressed. These sitework and special conditions often include utilityrelocation, surface parking facilities at stations, station access facilities, and temporaryconstruction improvements and facilities. The sitework and special conditions costcategory is subdivided into the following:
40.01 Demolition, clearing, and fine grading40.02 Site utilities and utility relocation40.03 Hazardous materials, contaminated soil removal/mitigation, and ground
water treatments40.04 Environmental mitigation (e.g., wetlands, historic/archaeological, and parks)40.05 Site structures, including retaining walls and sound walls
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-7August 2014
40.06 Pedestrian/bike access and accommodation, including landscaping40.07 Automobile, bus, and van accessways, including roads and parking lots40.08 Temporary facilities and other indirect costs during construction
40.01 Demolition, Clearing, and EarthworkThis cost category includes the project-wide cost of demolition, including thosestructures outside of the track or road bed. This includes, but is not limited to,removal of existing track elements, loading docks and their canopies, and pavedsurfaces. The cost of removal of street elements, such as curb and sidewalk, isincluded in Cost Category 40.07. Cost for abandoning, demolishing, or removingutility features is included in Cost Category 40.02. The cost of abandoning,demolishing, or removing drainage features is included in the various categoriesthat include drainage cost. The cost for removal and relocation of trees, clearingand grubbing, and fine grading also are included in this cost category.
40.02 Utility RelocationThis cost category includes the project-wide cost of utility relocation, includingthose utilities outside of the track or road bed. Generally one of the largest costelements within this cost category is the relocation of existing utilities from withinthe guideway construction envelope. These relocations can include both publicand private utilities, subject to any agreements that may apply to franchisedutilities that exist within public rights-of-way. Preliminary wet utility relocationplans were prepared and used to develop cost estimates. Preparation ofrelocation plans involved site visits, review of probable utilities as shown on Cityof San Diego Geographical Information System database, as-builts, potholing ofcertain existing utilities, and field survey information.
Preliminary dry utility relocation costs were developed based on identification ofpotential conflict locations, site visit, review of as-built plans, and discussions withutility owners. Unit prices were developed either on a linear foot basis or on alump sum basis for each relocation. The relocation cost did not include anyadditional right-of-way that may be required.
The cost associated with relocation of existing LOSSAN tracks has beenincluded in Cost Category 10.
40.03 and 40.04 Hazardous Material and Environmental MitigationAny special hazardous material handling cost such as contaminated soil orground water handling would be included in this category. Sites of concern havebeen identified in the Mid-Coast Corridor Transit Project Hazardous MaterialsTechnical Report (SANDAG, 2014c). Mitigation costs for removal of suchmaterial are project reserves that may or may not be used. Further studies willbe required to determine the extent of required mitigation, if any. The cost ofmitigation for noise and vibration is included under Cost Category 10.
Similarly, environmental mitigation for wetland impacts would also be includedunder this category. Sites of concern have been identified in the Mid-Coast
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-8
Corridor Transit Project Biological Resources Technical Report (SANDAG,2014d). This allowance includes funds for purchase of properties to be used aswetlands and for their maintenance until the establishment of the wetlands.
40.05 Site StructuresThis cost category typically includes structures, such as retaining walls, soundwalls, etc., that are outside of the guideway construction envelope. Thesestructures generally are located at stations but are located outside of the platformarea. Structures such as retaining walls for retained cut or fill along the at-gradesections of the guideway and bridges are included in Cost Category 10.
40.06 Pedestrian Access and LandscapingPedestrian access and landscaping information has not been developed fully at thisphase of the project; therefore, average unit costs based on historical experiencehas been used. Landscaping costs associated with parking facilities are included inthe composite costs developed for those particular items and are included in CostCategory 40.07.
40.07 Automobile Accessways and Parking LotsThis cost category includes new and reconstructed roadways, streets, at-gradesurface parking areas, sidewalks, curbs and gutters, and related roadwayfacilities, all associated with the construction of rail guideways. Roadway andparking area cost estimates will be based on unit costs applied to quantitiesdeveloped on location-specific data taken from the Final SEIS/SEIR Plan Set.
40.08 Temporary FacilitiesUnless otherwise specified, this cost category includes costs for mobilization,demobilization, construction vehicles, traffic control, temporary BMPs, security,small tools and equipment, project phasing, temporary construction associatedwith weather, or temporary site access and mitigation. For the current phase ofproject development, some of these costs typically would be included as apercentage allowance mark-up.
2.6 SCC 50—SystemsThis cost category includes the following cost elements:
50.01 Train control and signals50.02 Traffic signals and crossing protection50.03 Traction power supply: substations50.04 Traction power distribution50.05 Communications50.06 Fare collection system and equipment50.07 Central control
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-9August 2014
50.01 Train Control and SignalsThis cost category includes the signaling and control systems required for safeand efficient operations of the transit system and chosen technology. It includesautomatic wayside signals and automatic train stop circuitry in the track and onvehicles.
This category also includes the cost of modification to the LOSSAN signalingsystem required as part of relocation of the LOSSAN tracks.
Miscellaneous updates to core systems that include items such as system-wide routemap changes at stations and on the existing fleet are also included in this costcategory.
50.02 Traffic Signals and Crossing ProtectionFor transit systems that are constructed to operate either within existing streets or withat-grade crossings at existing roadways, there is often a need to modify existing trafficsignals or gated crossings or construct new traffic signals or add additional crossingprotection, such as signs and quad gates. This cost category includes the signalingand control systems required for items such as vehicle and pedestrian signals, trafficsignal pre-emption, and protection at all guideway/highway at-grade crossings(flashing lights, bells, and signs).
50.03 Traction Power Supply: SubstationsThe traction power supply system provides the power for all train operations. Thiscost category consists primarily of the civil, structural, and architectural infrastructurealong with the mechanical and electrical equipment needed to construct tractionpower substations (TPSSs). This includes the ductbank and cabling from theTPSSs to the overhead catenary system (OCS) interface and the ductbank andcabling to the substation from the outside electrical utilities source.
50.04 Traction Power DistributionThe traction power distribution system is based on a direct current OCS. The OCSconsists primarily of support poles, OCS foundations for at-grade segments,brackets arms and hardware, feeder cables, contact wire, and a messenger wire.Signal and communication power needs also are included in the traction powercosts. Power supply or distribution requirements for buildings associated with thestorage and maintenance facilities, or power for passenger stations, are not includedin this cost category.
50.05 CommunicationsThe communications system provides the necessary subsystems to support thetotal operational requirements of the transit system and chosen technology. Thecommunications system costs provide for subsystems, such as two-way radios,the public address system, telephone systems, variable message signs,interfaces with the fare collection and ticket vending equipment, and equipment
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-10
for the hearing impaired, as well as closed-circuit television. The subsystemsscope includes equipment static testing by the contractor.
50.06 Fare Collection System and EquipmentCosts for elements in this category are based upon a self-service, barrier-free,proof of payment fare collection system. Ticket vending machine costs shall bebased on a microprocessor controlled coin or bill accepting machine capable ofoptionally accepting credit, debit, and stored value cards. The unit cost for farecollection includes all equipment costs, installation costs, and testing costs. Thehardware includes provisions for fare vending facilities, including ticket validatorsand Compass Card readers.
50.07 Central ControlThis cost category includes all civil, structural, architectural, mechanical, electrical, andsystems costs required for the remote monitoring of train operations, track conditions,substations, and station support facilities. The need for an upgraded central controlfacility or expansion of existing facilities is dependent upon the operational analysisand assumptions to be determined for the given transit system and chosentechnology. Per discussions with MTS, the existing facility can handle the addition ofthe Mid-Coast Corridor Transit Project with minimal additional expansion. Costcategory 50.07 provides an allowance for such minor expenses.
2.7 SCC 60—Right-of-Way, Land, and Existing ImprovementsThis cost category covers all land acquisition and acquisition-related costs required toobtain various real property interests required for the construction, operation, andmaintenance of the proposed alignments. Costs include the acquisition of permanentfee, easement and temporary construction easements, relocation costs, businessdamages, professional services related to the acquisitions, and other miscellaneouscosts. Sub-categories include the following:
60.01 Purchase or lease of real estate60.02 Relocation of existing households and businesses
2.8 SCC 70—VehiclesThis cost category is generally subdivided into revenue (identified by transit mode) andnon-revenue vehicles (where non-revenue vehicles include maintenance-of-way vehiclesand agency trucks and automobiles). During this phase of project development, the unitcosts for vehicles typically will include costs for engineering, procurement, spare parts,etc. and is based on current quotes received by the Metropolitan Transit System (MTS)or other transit authorities with similar vehicles. This cost category is subdivided into thefollowing categories:
70.01 Light rail (including streetcar)70.02 Heavy rail (not used)70.03 Commuter rail (not used)
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-11August 2014
70.04 Bus (not used)70.05 Other (not used)70.06 Non-revenue vehicles (not used)70.07 Spare parts
2.9 SCC 80—Professional ServicesThis cost category includes estimates and allowances for Project Development,Engineering, project and construction management, agency program management,project insurance, surveys and testing, and start-up costs. For Project Development andEngineering, estimates of anticipated costs were developed. For all other categories,allowances are computed by applying a percentage to the total construction costsestimated for each cost category (excluding right-of-way and vehicle costs). Insurancein this category includes the cost of professional liability and other non-constructionrelated insurances. Right-of-way and vehicle costs are typically calculated to include themanagement and administration costs associated with these activities and therefore areexcluded from the calculation of professional services. The following is a list of thepercentage multipliers being applied to the total construction costs to cover these items:
80.01 Project Development 12.9%80.02 Engineering 5.7%80.03 Project Management for Design and Construction 5.0%80.04 Construction Administration and Management 10.0%80.05 Insurance 1.0%80.06 Legal: Permits, Review Fees, Etc. 2.0%80.07 Surveys, Testing, Investigation, and Inspection 1.0%80.08 Start up 1.5%
Total Professional Services Costs 39.1%
2.10 SCC 90—Unallocated ContingencyAn unallocated contingency is intended to cover project risks that cannot reasonably beallocated to specific SCC codes, including change orders during construction (allocatedcontingencies are covered in each of the construction subcategories). It is intended tocover unknowns that cannot be anticipated, but nonetheless are prudent to include forplanning purposes. The unallocated contingency is calculated at 9.5 percent of theconstruction costs, right-of-way, vehicles, and professional services. This would be aproject reserve, a portion of which would be carried into construction to cover changeorders.
2.11 SCC 100—Finance ChargesFinance charges represent interest cost and upfront costs associated with a long-termbond issuance that will be repaid with TransNet revenues. The bond proceeds willprovide funding for the majority of the local share of project funding for Fiscal Year 2012to Fiscal Year 2020 to cover year-of-expenditure dollar costs.
Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-12
THIS PAGE INTENTIONALLY LEFT BLANK
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-1August 2014
3.0 ESTIMATING METHODOLOGYThe estimating methodology for preparation of the capital cost estimate for the RefinedBuild Alternative for the Final Supplemental Environmental Impact Statement andSubsequent Environmental Impact Report (SEIS/SEIR) has been developed in generalconformance with the Federal Transit Administration (FTA) guidelines for estimatingcapital costs for New Starts projects. The FTA guidelines call for cost estimates to beprepared and reported using the latest version of FTA’s Standard Cost Category (SCC)worksheet. The most current version of the SCC workbook is Revision 15, dated August5, 2013. These cost categories form the basis of the format and structure that will beused for the capital cost detail and summary sheets.
Cost data generally were developed using the most recent and applicable San DiegoAssociation of Governments (SANDAG), California Department of Transportation(Caltrans), and other transit systems’ related bid results in California. Caltrans annuallypublishes a cost database for project bid results for all districts in California, with the SanDiego area located within District 11. For the purposes of the Final SEIS/SEIR estimate,similar items with similar quantities were queried from the Caltrans cost database, whichcompiles cost data from projects throughout the state of California. The average weightedunit price was rounded up to the nearest whole dollar and used in the Final SEIS/SEIRestimate. The unit prices from Caltrans cost data are bid prices that include insurance,markups, tax, profit, overhead, contractor contingencies, and in some cases, as applicableto the item reviewed, time related overhead is added to the unit prices. Depending on theparticulars of the contract document, cost data from SANDAG may or may not includeinsurance costs. Overall, insurance costs for items obtained from SANDAG historicalprices constitute a small percentage of overall project cost and will be well within thecontingency factors provide in the estimate. Cost sources such as the PB transit projectsdatabase, which includes the recent projects in Hawaii, Seattle, and the Bay Area RapidTransit will be footnoted and cited as to the bid date and escalated to 2013 dollars.
For items of work where historical data from these sources were not available or wereunreliable because of the age of such data, data from other transit agencies were used.Adjustments were made to these sources to account for differences between thepublished date of the historical cost data and the current base year of the cost estimates.Escalation factor adjustments were made to these unit price data based on theConstruction Cost Index value, as published in the Engineering News Record. The RSMeans Location Factor also may be considered in adjusting unit costs to reflectconstruction economic conditions within California. Rough Order of Magnitude (ROM)cost was developed for items of work where detailed quantity take off cannot beperformed. The ROM costs constitute an allowance for the particular item of work untilsuch time that the project is further defined. For example, depending on defined scope ofwork, elevators can have a wide fluctuation in actual unit cost. Hence, the dollar amountfor elevators would be an allowance until the specification of each elevator is determined.
Where items of work can be quantified at the current phase of the project, the unit costswill be verified using historical cost data. At the end of the preliminary engineering (PE)phase of the project, a “bottoms up” estimate will be used on most items of work. All unitcosts include the contractor’s direct construction costs, plus all taxes, general expenses,
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-2
overhead, and profit. The unit costs for items of construction do not include items such asengineering, construction management, and owner’s administrative costs. These costswill be included as percentage add-ons to the cost estimate under Cost Categories 80 and90. Allowances for contingencies are added separately to each of the cost subcategories.
3.1 General ApproachIn general, the Final SEIS/SEIR Plan Set (SANDAG, 2014b) formed the basis for thequantity take offs and were used to identify the various infrastructure elements that wereused to prepare the capital cost estimates.
As more detailed plans become available during the later stages of project development,additional quantity take offs will be performed to verify and update the ROM unit costs. Theupdated unit costs may include items of work that did not originally appear in the ROM unitcosts.
3.2 Cost Estimating AssumptionsThe basic assumptions and criteria used in developing the cost data are as follows:
· Unit prices are expressed in 4th quarter 2013 dollars.
· No hazardous or contaminated material is present in the subgrade or is contained inbuildings estimated for demolition.
· Unit prices used in the estimate assumes the best price procured from theConstruction Management/General Contractor. Because the majority of unit priceswere obtained from Caltrans database, competitive bidding has been assumed.
· Year-of-expenditure costs were based on inflation factors developed in 2013 and arebased on the target revenue operation date of 2019.
· Unit prices assume that labor costs are based on an eight-hour work day duringnormal working hours using the current general prevailing wage requirementspublished by the State of California Department of Industrial Relations.
· Adequate, experienced craft labor is available.
· Normal productivity rates, as historically experienced, will be used.
· Compatible trade agreements exist in the region.
· No strike impacts will be experienced by the project.
· There are sufficient, experienced contractors available to perform the work.
· The materials required by the scope of work are readily available in sufficientquantities to meet construction schedule requirements.
· Normal San Diego area weather has been considered in the development of theconstruction schedule and costs.
· Existing state-of-the-art construction technology and equipment will be available.
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-3August 2014
3.3 Estimating ProceduresTypically, the capital cost estimate is developed using a combination of the stochastic orhistorical and deterministic or “bottom-up” approaches. However, during the currentdevelopment phase of the Mid-Coast Corridor Transit Project where many engineeringdetails still remain to be developed, the historical unit price method is used almostexclusively. As the project continues further into the PE and final design phases, a mixof detailed bottom-up pricing and historical unit pricing will be used.
In the historical method, an order-of-magnitude or composite cost is determined, usuallyderived using data from similar projects. This cost is used directly or converted to somecomponent unit measure (such as dollar per vehicle, dollar per route feet, etc.) andapplied as a unit cost. This method is less detailed than the bottom-up approach and,for certain items, the resulting comparative cost estimates can be sufficiently accurate.As an example, the cost for transit vehicles is generally derived using data from recenttransit agency procurements using similar vehicle types and is based upon a totalprocurement price that is divided by the number of vehicles purchased. Other system-wide elements, such as traction power distribution, also may use historical unit costs.Historical bids for traction power distribution contracts, typically composed of a hundredor more construction elements and unit prices, are used to develop composite unit costson a dollar-per-route-foot basis.
Alternatively, where a large set of historical data is available, and where these unit pricesgenerally fall within a reasonable range, the mean or average of the historical unit pricescan provide acceptable cost estimates. For the case of the Mid-Coast Corridor TransitProject, heavy reliance has been placed on historical unit prices from Caltrans. Thisproject intends to use Caltrans Standard Specification and unit prices for common itemsof work that would be comparable to those that would be obtained by Caltrans.
In the bottom-up approach, major work element costs, as generally defined by typicalsections, are determined by totaling the costs of all component parts. Sufficientengineering data are required to reasonably define the scope of work and quantitiesrepresented by each typical section. Unit prices are developed and combined with theestimated quantities to determine the costs for each major category of work, such asguideway elements, stations, and system elements. The advantage of this approach isthe ability to adjust costs for minor changes to the scope, as well as the higherconfidence level inherent in a bottom-up estimate. The drawback is the level ofengineering and estimating effort required to produce a bottom-up estimate and theadditional time required to adjust the estimate for revisions.
The quantities were derived from conceptual engineering drawings. These drawingshave been developed to various levels of completion. To the extent that design hadadvanced, detailed quantities were developed for each item of work. Earthworkquantities were developed by cross sections cut at 50-foot intervals. Most of thestructural quantities were developed from Advanced Planning Studies and TypeSelection. Most other quantities were developed from conceptual engineering drawings.
Where design had not adequately advanced, unit prices were based on a more broadset of historical prices. Items where the design has not adequately progressed to enable
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-4
detailed quantity take-off include features such as environmental mitigation andelevators
Table 3-1 shows the level of plan development for each SCC.
Table 3-1. Approximate Level of Design for Each SCC
Description
Level ofCompletion
(approximatepercentage)
10.01 Guideway: At-grade exclusive right-of-way 40%10.04 Guideway: Aerial structure 20%10.06 Guideway: Underground cut and cover 30%10.08 Guideway: Retained cut or fill 40%10.09 Track: Direct fixation 50%10.11 Track: Ballasted 50%10.12 Track: Special (switches and turnouts) 40%10.13 Track: Vibration and noise dampening 10%20.01 At-grade station, stop, shelter, mall, terminal, and platform 15%20.02 Aerial station, stop, shelter, mall, terminal, and platform 15%20.06 Automobile parking multi-story structure 10%20.07 Elevators and escalators 5%40.01 Demolition, clearing, and earthwork 40%40.02 Site utilities and utility relocation 35%40.03 Hazardous materials, contaminated soil removal/mitigation, and ground water treatments 0% (Allowance)40.04 Environmental mitigation (e.g., wetlands, historic/archaeological, and parks) 0% (Allowance)40.06 Pedestrian/bike access and accommodation, including landscaping 30%40.07 Automobile, bus, and van accessways, including roads and parking lots 30%40.08 Temporary facilities and other indirect costs during construction 10%50.01 Train control and signals 20%50.02 Traffic signals and crossing protection 30%50.03 Traction power supply: Substations 20%50.04 Traction power distribution: Catenary and third rail 20%50.05 Communications 20%50.06 Fare collection system and equipment 5%50.07 Central control 0% (Allowance)
Source: SANDAG, 2014
3.4 Allocated ContingencyAn allocated contingency is typically included in an estimate to address a lack of scopeand quantity definition during the in-progress design stages. This is now a required stepin the preparation of cost estimates in the SCC cost format. In the early stages, anallocated contingency may represent a significant portion of the estimate for anyparticular SCC. As the design progresses and more detailed quantity take-offs can bemade, the allowance is reduced. At 100 percent design completion, the allocated
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-5August 2014
contingency, by definition, will be zero. Beyond 100% design, the lack of scope andquantity definition will be addressed by the unallocated contingency.
For the Final SEIS/SEIR estimate, quantity take-offs were possible for most of the itemsof work. However, there still remain items of work that lack adequate definition.Variability in quantities can occur within a single subcategory of the SCC worksheet. Toaccount for this, the methodology for assigning the allocated contingency has beenenhanced to consider the design development for items that are better defined at thisstage, with sound sources for the unit prices, at the same time addressing the lack ofscope definition and inability to measure exact quantities or procure unit prices for itemsthat are still conceptual.
For each item, a quantity contingency is assigned based on the level of confidence inestimating the quantity, as well as the scope definition for that item. For example, theallocated quantity contingency for Special Trackwork is zero percent, as this item issimple to quantify and there is a well-defined scope for this item.
Similarly, a unit cost contingency is assigned based on the level of confidence in thesources used for obtaining the unit prices for each item. Where unit prices could beobtained from the Caltrans cost database, a 10 percent unit cost contingency has beenused. The unit cost has also been compared to other similar projects within the PBTransit database, which validates the level of allocated contingency.
For each SCC subcategory, the allocated contingency is the sum of the contingency forquantities and contingency for unit costs. The weighted average of the contingency forall items in each SCC category is then assigned to the categories in the SCC form. Theamount of allocated contingency will depend upon the complexity of any particular SCC,as well as the stage of engineering completion, but will typically be in the 5 to 30 percentrange. The percentages shown in Table 3-2 are the weighted averages for eachcategory for the Refined Build Alternative.
The light rail transit (LRT) vehicle would be a Siemens low floor, S70 Ultra Short (S70US) light rail vehicle (LRV). The vehicles will be purchased in a fleet of 36, thus offeringeconomies to the overall procurement. The vehicle procurement includes both designand agency costs. The contingency costs are expressed as a percentage of vehiclecapital cost. Vehicle design/procurement and agency costs associated with the vehiclesare included in the unit cost. Since the vehicles are specified, the vehicle contingency isstated at 5 percent and will be added to account for unforeseen costs associated withvehicle fleet procurement.
A contingency factor is applied to the right-of-way costs so that sufficient funds areidentified to secure necessary right-of-way. The following two items are recommendedadditives to the base right-of-way estimate to arrive at a final cost figure:
· For the purchase or lease of real estate, total right-of-way contingency isrecommended at 57.12 percent, which would be applied to the estimated cost of theproject right-of-way. This contingency was developed based on potential damages.
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-6
Table 3-2. Allocated Contingency Percentages for the Final SEIS/SEIR Cost Estimate(Refined Build Alternative)
Description
AllocatedContingencyPercentage
10.01 Guideway: At-grade exclusive right-of-way 23.7410.04 Guideway: Aerial structure 24.8610.06 Guideway: Underground cut and cover 23.6810.08 Guideway: Retained cut or fill 20.1810.09 Track: Direct fixation 20.0010.11 Track: Ballasted 20.9010.12 Track: Special (switches and turnouts) 12.5810.13 Track: Vibration and noise dampening 30.0020.01 At-grade station, stop, shelter, mall, terminal, and platform 16.4620.02 Aerial station, stop, shelter, mall, terminal, and platform 22.0220.06 Automobile parking multi-story structure 16.6920.07 Elevators and escalators 11.8240.01 Demolition, clearing, and earthwork 20.9340.02 Site utilities and utility relocation 25.0740.03 Hazardous materials, contaminated soil removal/mitigation, and ground water treatments 30.0040.04 Environmental mitigation (e.g., wetlands, historic/archaeological, and parks) 28.2940.06 Pedestrian/bike access and accommodation, including landscaping 26.4440.07 Automobile, bus, and van accessways, including roads and parking lots 21.7340.08 Temporary facilities and other indirect costs during construction 15.9350.01 Train control and signals 23.5050.02 Traffic signals and crossing protection 25.0050.03 Traction power supply: Substations 18.1150.04 Traction power distribution: Catenary and third rail 25.5350.05 Communications 29.9950.06 Fare collection system and equipment 30.0050.07 Central control 30.0050.08 Existing System Updates 27.7860.01 Purchase or lease of real estate 57.1260.02 Relocation of existing households and businesses 15.0070.01 Light rail vehicles 5.0070.07 Spare Parts 5.0080.01 Preliminary Engineering 20.0080.02 Final Design 20.0080.03 Project Management for Design and Construction 20.0080.04 Construction Administration and Management 20.0080.05 Professional Liability and other Non-Construction Insurance 20.0080.06 Legal, Permits, Review Fees by other agencies, cities etc. 20.0080.07 Surveys, Testing, Investigation, Inspection 20.0080.08 Start up 20.00
Source: SANDAG, 2014
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-7August 2014
· For relocation of existing business and households, right-of-way contingency isrecommended at 15 percent. Contingency for damages would not apply to thisscenario.
With the exception of Project Development and Engineering, the cost of professionalservices was developed using standard percentages that are similar to other FTAprojects. For these two items, the cost of professional services were estimated basedon current and anticipated expenditures during these phases of the project.
3.5 Organization and Management of Cost DataThe organization of the capital cost estimates for the Final SEIS/SEIR will follow that ofFTA’s SCC. Within the SCC spreadsheet, a summary of the backup data has beenprovided for each category. Some items of work may appear under more than onecategory. A more detailed supporting calculation for each quantity or cost estimate alsohas been provided.
3.6 Cost Estimating Results FormatThe cost estimate for the Final SEIS/SEIR uses three levels of cost presentation toprovide cost information results in increasing levels of detail. The first level is the SCCform itself, where the cost and contingency for each category are presented. Thesecond level is provided within the SCC spreadsheet, where a detailed list of quantitiesfor each category has been provided. Each item listed has its own quantity, unit price,total cost, and contingency for both quantity and unit price. This second level, with thelist of quantities within the SCC spreadsheet, will enable the user to perform a quickreview and check of the data.
The third level is a more detailed calculation of the quantities provided in the backup datawhere each item listed in the SCC spreadsheet is broken down into its component parts,with the unit prices that was derived from different sources. This third and more detailedestimate enables the users to perform a thorough review of quantities with respect to theplan and profile drawings, typical cross sections, and other details developed for theFinal SEIS/SEIR.
These levels provide an efficient and logical flow of data from the most detailed level to thesummary level. The SCC workbook estimate is the summary level that provides a quickreview of cost per mile or per station. The list of quantities within the SCC workbookprovides an overview of the type of items that has been considered in the development ofthe estimates. In addition, the detailed estimate presents all the component parts fromwhich the estimate was developed. It is at this level that changes to the quantities areaccounted for. The detailed quantity backup also would provide an indication of thepercentage of contingency that should be assigned to the various items of work. The moredetailed estimate would be an indication of the level project definition. Where detailedquantity take-off has been performed and additional scope is not anticipated, the quantitycontingency factors can be reduced.
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-8
3.7 Cash Flow and EscalationThe current FTA SCC workbook includes several worksheets that assist in thepreparation of a cash flow projection for the project, as well as the calculation of theyear-of-expenditure value of the total project cost. The cash flow reflects a reasonabledistribution of the incurred project costs for the various Standard Cost Categories inaccordance with the approved Master Project Schedule, dated December 31, 2013.
Once the cash flow projection is developed, the results are placed into the SCC inflationworksheet. Escalation factors for this worksheet are then calculated using the projectedinflation developed at the time of this report.
For each year of capital expenditure activity, the SCC Worksheet allows for a singleescalation rate that is used to convert costs for all items of work from base year dollarsto YOE dollars. However, the Mid-Coast Corridor Transit Project Construction CostEscalation Forecast 2014-2023 report (SANDAG, 2013b) had recommended separateescalation rates for each of SCCs 10—50 (construction activities), SCC 60 (right-of-way), SCC 70 (vehicles), and SCC 80 (professional services). Based on thisrecommendation, a composite escalation rate was calculated for use in the SCCWorksheet. The following steps were taken to develop the composite rate:
· Step 1 – Capital costs were developed in 2013 dollars and spread by year for eachSCC (excluding SCC 100, finance charges).
· Step 2 – Annual escalation rates for SCCs 10—50, SCC 60, SCC 70, and SCC 80from the Construction Cost Escalation Forecast report were applied to base yeardollar costs for those respective categories to convert the costs to YOE dollars.
· Step 3 – An annual escalation rate for SCC 90 (unallocated contingency) wasassumed to be the same as those for SCCs10-50.
· Step 4 – The annual costs (in YOE dollars) for SCCs 10—90 were then summed upto calculate the total annual Project escalated cost (excluding finance charges).
· Step 5 – A composite escalation rate was developed for each year, by dividing thetotal Project escalated cost calculated in Step 4 by the total Project base year dollarcost developed in Step 1.
· Step 6 – The process (Step 1 through 5) was repeated for each year in which capitalcosts are incurred.
As noted in the SCC Workbook, the development of capital cost for each year wasbased on SANDAG’s fiscal year (July 1 through June 30), rather than on calendar year.
The above methodology provided for a composite escalation rate for each year. Theresults where then compared with a constant escalation rate of 3.5% for every year.Whereas the project YOE cost without finance charges were estimated to be$1,687,721, the YOE cost based on a constant 3.5% escalation rate was estimated to be$1,673,801. This estimate is only slightly lower than the variable composite escalationrate developed by the above methodology. For estimating purposes, the variablecomposite escalation rate has been used.
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-9August 2014
3.8 Annualized Cost FactorsThe evaluation of the cost effectiveness of the Refined Build Alternative requires that allevaluation measures (capital costs, operating and maintenance costs, non-federalfunding, and user benefits) be expressed in annual terms. Since capital costs areestimated as a total expenditure of constant (base year) dollars, an annual payment willbe computed that is equivalent to what is, in reality, a one-time expenditure of capitalfunds. For each capital cost item, the annualized equivalent will be computed byapplying the following annualization factor:
Annualization Factor = i x (1+ i)n where i = discount rate and (1+i)n – 1 n = economic life
The annualized cost of the line item is the total cost of that line item multiplied by itsannualization factor. The summation of all annualized line-item costs provides theoverall annualized cost for the alternative. Table 3-3 lists the various cost categoriesand their respective economic lifetime and annualization factors. These annualizationfactors have been determined based on a FTA-prescribed 2 percent discount rate.
Table 3-3. Annualization Factors
DescriptionLifetime(Years)
AnnualizationFactor
10.01 Guideway: At-grade exclusive right-of-way 125 0.02210.02 Guideway: At-grade semi-exclusive (allows cross-traffic) 30 0.04510.03 Guideway: At-grade in mixed traffic 20 0.06110.04 Guideway: Aerial structure 80 0.02510.05 Guideway: Built-up fill 80 0.02510.06 Guideway: Underground cut and cover 125 0.02210.07 Guideway: Underground tunnel 125 0.02210.08 Guideway: Retained cut or fill 125 0.02210.09 Track: Direct fixation 30 0.04510.10 Track: Embedded 20 0.06110.11 Track: Ballasted 35 0.04010.12 Track: Special (switches and turnouts) 30 0.04510.13 Track: Vibration and noise dampening 30 0.04520.01 At-grade station, stop, shelter, mall, terminal, and platform 70 0.02720.02 Aerial station, stop, shelter, mall, terminal, and platform 70 0.02720.03 Underground station, stop, shelter, mall, terminal, and platform 125 0.02220.04 Other stations, landings, terminals: Intermodal, ferry, trolley, etc. 70 0.02720.05 Joint development 70 0.02720.06 Automobile parking multi-story structure 50 0.03220.07 Elevators and escalators 30 0.045
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-10
Table 3-3. Annualization Factors (continued)
DescriptionLifetime(Years)
AnnualizationFactor
30.01 Administration building: Office, sales, storage, and revenue counting 50 0.03230.02 Light maintenance facility 50 0.03230.03 Heavy maintenance facility 50 0.03230.04 Storage or maintenance-of-way building 50 0.03230.05 Yard and yard track 80 0.02540.01 Demolition, clearing, and earthwork 125 0.02240.02 Site utilities and utility relocation 125 0.02240.03 Hazardous materials, contaminated soil removal/mitigation, and ground
water treatments125 0.022
40.04 Environmental mitigation (e.g., wetlands, historic/archaeological, and parks) 125 0.02240.05 Site structures, including retaining walls and sound walls 80 0.02540.06 Pedestrian/bike access and accommodation, including landscaping 20 0.06140.07 Automobile, bus, and van accessways, including roads and parking lots 20 0.06140.08 Temporary facilities and other indirect costs during construction 100 0.02350.01 Train control and signals 30 0.04550.02 Traffic signals and crossing protection 30 0.04550.03 Traction power supply: Substations 50 0.03250.04 Traction power distribution: Catenary and third rail 30 0.04550.05 Communications 20 0.06150.06 Fare collection system and equipment 25 0.05150.07 Central control 30 0.04560.01 Purchase or lease of real estate 125 0.02260.02 Relocation of existing households and businesses 125 0.02270.01 Light rail 25 0.05170.02 Heavy rail 25 0.05170.03 Commuter rail 25 0.05170.04 Bus 12 0.09570.05 Other 12 0.09570.06 Non-revenue vehicles 12 0.09570.07 Spare parts 12 0.095
Source: FTA, 2014
3.9 Unit PricingIn general, historical unit prices were applied to obtain cost estimates for each line itemor component parts of a line item. All unit prices include the contractor’s constructioncosts, general expenses, overhead, taxes, and profit. As noted in Section 3.0, the unitprices presented in this report are gathered from a variety of sources: the Caltrans costdatabase, published Caltrans bid tabulations, the Parsons Brinckerhoff transit database,and other similar transit projects. Information gathered from Caltrans is annotated towhere cost factors, such as time related overhead and mobilization, were applied or notapplied in the unit prices. If the factors were not applied in the unit prices, then 13 percent
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-11August 2014
was added into the unit price. For projects where mobilization was not a separate biditem, 10 percent was deducted from the item unit price. In addition, for unit prices thatwere taken from other regions in California, the RS Means location factor was used toadjust for the San Diego region cost allowance. Other transit projects unit price data thatwere used in this project estimate applied the same methodology of factoring prices intothe San Diego region by using location factors as published in RS Means. These unitprices were also adjusted based on the bid date and the anticipated project duration totheir respective midpoint of construction. A brief discussion of the key unit price for eachitem of work follows.
Above and Below Grade Parking StructureParking structures are proposed at the Nobel Drive Station. Unit prices for above-ground and below-ground parking were obtained from the PB transit database, whereseveral similar parking structures were constructed for other large transit projects. Unitprices were also compared with the RS Mean database and resulted within anacceptable range and allowance. Location factors from the RS Means for labor andmaterial are included in the unit price for the San Diego region. The resulting unit priceof $21,000 per stall for above-ground and $30,000 per stall for below-ground includeslabor and materials with a 15 to 20 percent allowance.
Aerial StructuresThe cost for aerial structures were developed from Advanced Planning Studies (APS)and Type Selection (TS) Memoranda. The foundation type, falsework requirements,straddle bents, construction access, consideration for area geology, fault rupture, andarchitectural treatments are factored into the structure costs. Bridge costs are reportedby their component parts such as steel and concrete.
For pedestrian bridges, where plans were not developed to the levels noted above, aunit price of $400 per square foot was used.
Architectural TreatmentArchitectural treatments would be applied to the exposed face of retaining walls,including MSE walls and aerial bridge columns. Based on a review of the retaining wallsand their locations, certain walls were identified for architectural treatment, and thesurface area of these walls was computed. In addition, it is assumed that approximately25 percent of the facial area of the U-section would receive architectural treatment. TheCaltrans unit price of $40 per square foot is the weighted average from one contract, butthe unit price could vary significantly depending on the complexity and repetitive natureof the architectural treatment. It is expected that the project will adopt approximatelythree architectural themes along the corridor and there will be significant repetitivenessin the type of wall treatment where the walls are visible to the public. Therefore, a unitprice of $14 per square foot has been used. For mechanically stabilized earth (MSE)retaining walls, the cost of standard architectural treatment of $4 per square foot used bythe manufacturer is readily available and is assumed to be used for the Mid-CoastCorridor Transit Project MSE walls.
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-12
BallastBallast quantities are generated from typical sections along the at-grade segments of thealignment. Sections have been evaluated at 50-foot intervals. Unit price is developedfrom the PB transit database, primarily from the most recent LA Metro projects thatincluded ballast. A unit price of $53 per cubic yard has been used for construction ofLRT. This is typical of current ballast prices in Southern California.
For temporary relocation of the Los Angeles-San Diego-San Luis Obispo Rail CorridorAgency (LOSSAN) tracks, it was assumed that the neat quantities of ballast estimatedfrom typical sections would not be required and portions of the existing ballast can beutilized. For this temporary relocation, a unit price of $35 per cubic yard has been used.
Bar Reinforcing Steel for Earth Retaining StructuresThe steel reinforcement required for all items of work has been quantified using CaltransStandard Plans based on the design height of the retaining wall. This quantity of steelmay be revised as the design is further developed. The Caltrans cost database containsan extensive set of data on steel reinforcement. For bar reinforcing steel (retaining wall),the weighted average of $1.00 per pound has been used. Steel reinforcement forretaining walls, cut-and-cover, depressed sections, and other minor items of work havebeen estimated at the cost of bar reinforcing steel (retaining wall). Bar reinforcing for theopen channel uses an average weighted unit price of $1.00 per pound due to the natureof long longitudinal bar and minimal fabricated bar needed at that location.
Bumping PostA bumping post (permanent terminal direct fixation) would be required at the northerlyproject terminus, which is at the end of the Genesee viaduct to prevent any accidentalovershooting of the LRT vehicle from the aerial tracks. A project allowance of $20,855per item has been assigned to this item. A bumping post for at-grade track is alsorequired at the end of storage track located south of SR 52.
Cable RailingCable railing would be applied to the top of retaining walls for safety, where onlymaintenance crew will have access. Where pedestrian activity near the top of aretaining wall is expected or where aesthetics are important, handrails or ornamentalrailing will be used. Many Caltrans projects require cable railing, and the weightedaverage from the Caltrans cost database provides a good estimate for this item of work.A unit price of $25 per foot has been used.
Catenary Pole FoundationThe unit pricing for the at-grade catenary pole foundations were based on theapproximate foundation depth and the type of overhead catenary system (OCS)foundation pole. Pricing was obtained from the PB transit database which containspricing from various transit projects. An average unit price of $5,000 was used toaccount for the various types of poles and loadings. The cost of foundation assembly onaerial structures in included in the cost of miscellaneous metal for each of the aerialstructures.
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-13August 2014
Catenary SystemCapital cost for the OCS is based on the conceptual scope of OCS items. The costincludes installation of poles, wires, insulators, jumpers, hangers, OCS supports,disconnect switches, and termination and down guys. These items were priced from thePB transit database, which includes pricing from similar transit projects. Minormodification to the catenary system also would be required along the existing line fromSanta Fe Depot to the San Diego River due to the increase in operations through thissegment.
Central ControlIn discussion with the Metropolitan Transit System (MTS), the existing central controlfacility has been designed to accommodate the Mid-Coast extension. However, anallowance of $1.0 million has been used in the current estimate to accommodate anyminor improvements to the existing central control facility. Additionally an allowance of$200,000 was allocated to upgrade the central control computer system.
Chain-Link Fence (Type CL-3 thru CL 7)Chain-link fence would be required throughout the at-grade portion of the alignment.The Caltrans cost database provides a good indication of the probable cost for this itemof work. The unit price varies from $16 per linear foot to $24 per linear foot in the costestimate.
Class 2 Aggregate BaseClass 2 aggregate base would be applied below the ballast for a depth of 6 inches andat various thicknesses for roadway structural sections. The Caltrans cost databaseprovides a reliable estimate for this item of work as many of Caltrans’ projects includeClass 2 aggregate base. The weighted average from the Caltrans cost database is $45per cubic yard.
Clearing and GrubbingClearing and grubbing of the site would include removal of all items from the project sitethat are not paid for elsewhere in the contract. Possible examples of such items wouldbe removal of vegetation, and abandonment of various existing facilities (with theexception of drainage, utilities, and trackwork facilities). Adequate project definition hasnot been developed at this time to quantify all work to be performed under this category.Therefore, an allowance for this work has been used. The amount used for thisallowance was rounded up from that listed in the Caltrans cost database. An allowanceof $4,022 per acre has been used.
Concrete BarrierSeveral types of concrete barrier would be required at various locations along the entirealignment. The Caltrans cost database provides a good indication of the probable costfor this item of work. The unit price from the database varying from $46 per linear foot to$100 per linear foot has been used.
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-14
Concrete PlinthConcrete plinth would be required at all direct fixation track locations. The unit cost forthis item was developed by estimating the required size of the plinth and formworkrequired for each plinth. The PB transit database includes plinth concrete from severaltransit projects. A unit cost of $44.10 per cubic foot has been used.
CommunicationCommunication costs include closed-circuit television, the public address system,variable message signs, and Supervisory Control and Data Acquisition at each station.In addition, a fiber optic line would have to be run along the entire alignment. The PBtransit database has provided an average unit price for communications facilities at eachstation. The cost for communication equipment installed in various station locations isestimated to range from $420,000 to $480,000.
Demolish Pedestrian BridgeThe existing pedestrian bridges on Genesee Avenue at the Executive Drive Station andnear La Jolla Village would be demolished as part of the Refined Build Alternative. Theunit price for bridge demolition from the Caltrans cost database was increased to $27per square foot to account for demolition work in a busy business and commercial areas.
DrainageDrainage systems were designed for the at-grade and aerial guideway, at stations, andalong roadways impacted by the project. The scope of work includes modification tocross drainage systems carrying off-site storm flows and an on-site drainage systemconsisting of underdrains and ditches. Although the low point of tracks at the La JollaColony Drive overhead structure falls within the limits of the U-section, the flow line ofthe invert of the structure would be designed to allow for a minimum slope of 0.3 percentto convey the flow to a point outside of the structure. This design would avoid the needfor a pump system within the structure.
Construction of tracks at SR 52 would require construction of a box culvert along RoseCreek. The box culvert is estimated to be approximately 700 feet long by 26 feet wide.The cost of the box culvert was estimated from its component parts of structuralconcrete and bar reinforcing steel.
DuctbankDuctbanks are planned in the vicinity of each substation. The unit price for ductbankswas developed from the estimated amount of concrete required per linear foot ofductbank. The concrete for ductbanks need not be structural concrete, and a limitedamount of formwork would be required to construct the ductbank. A unit cost that variesfrom $112 to $161 per linear foot has been used based on the number and size ofconduits in the cross-section.
ElevatorsElevators will be required at all aerial stations. The estimate used for this item of work isa project allowance until such time that adequate project definition is developed. Prices
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-15August 2014
for elevators vary widely depending on the size, number of stops, rise, enclosure, andother features. An allowance of $710,000 per single elevator to $810,000 per doubleelevators has been used for the elevators depending on the height and set configuration.
Environmental MitigationBased on the preliminary limits of environmental mitigation identified in the Mid-CoastCorridor Transit Project Biological Resources Technical Report (SANDAG 2014d),wetland creation and wetland restoration/enhancement are assigned an allowance of$200,000 per acre, with $2 million allocated for the purchase of land. Shading impactsare assigned an allowance of $150,000 with $500,000 for the purchase of land. Otherconstruction-related impacts are assigned an allowance of $150,000. Tree removal andreplacement are also included in this category, with tree removal estimated at $400 to$600 depending on the size of the tree, and tree replacement at $2,000 per tree.
Fare Collection System and EquipmentEach platform would be required to have a ticket vending machine and a Compass Cardvalidator. In addition, some of the aerial stations also may have ticket vending machinesand validators at ground level to encourage riders to purchase tickets prior to enteringthe fare paid zone on the platforms. The cost of the vending machines and ticketvalidators were developed from recent data from MTS. The ticket vending machine unitcost is $140,000 each and includes contractor testing and installation. The ticketvalidators are $20,000 each, which also includes contractor testing and installation. Thecost for the fare collection infrastructure (conduits, pull boxes, and fiber) is included ineach station in 20.01 and 20.02.
Hazardous MaterialsPreliminary sites of concern for hazardous materials have been identified in theMid-Coast Corridor Transit Project Hazardous Materials Technical Report (SANDAG,2014c). An allowance of $4,400,000 for mitigation was developed based on possiblelocations where mitigation could be required rather than a cost per mile.
Hot Mix Asphalt (Type A)The unit price for this item was developed from the Caltrans cost database. Theweighted average for the San Diego region for this item of work is about $90 per ton, butthere is wide fluctuation in prices. A unit price of $102 per ton has been used due tocommodity price fluctuation.
Landscape and IrrigationTransit station site work and street improvement work have discrete items forlandscaping and irrigation. The unit price for this item of work was developed from theCaltrans cost database. The weighted average unit price for the San Diego region forthis item of work is about $4.70 for landscape and $1.40 for irrigation.
MobilizationMobilization is preparatory work that must be performed or costs incurred before startingwork on the various items on the job site. Mobilization is factored at 8.5 percent of the
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-16
total construction costs. This allowance is based on an average of mobilizationallowance from various transit projects around the state, as well as those in San Diego.
Mud SlabMud slab would be used at the open channel, cut-and-cover and depressed section andwould be constructed below the bottom of the structure. The intent of the mud slab is toprovide a firm and workable surface for construction of the structure above. The unitprice was taken from the PB Transit database and factored for the San Diego region. Aunit price of $327 per cubic yard has been used.
PartneringThe need and scope for partnering effort have not been determined at this time. A$300,000 allowance is used for possible partnering efforts during the construction phaseof the project.
Pervious Backfill (Retaining Wall)The unit cost for pervious backfill was used to develop the estimate for retaining walls.The unit price was obtained from the Caltrans cost database and a value of $49 percubic yard has been used.
Remove Existing Track and TurnoutThe cost of removing trackwork items were developed from the PB transit database andfactored to San Diego regional cost. .
Earth Retaining Structure—Mechanically Stabilized EarthMSE walls would be required along the Mid-Coast Corridor at locations identified on theMid-Coast Corridor Transit Project Final SEIS/SEIR Plan Set (SANDAG, 2014b). Theunit price for MSE walls was developed from the Caltrans cost database. A unit cost of$72 per square foot has been used, which includes the MSE panel, the structuralbackfill, the straps, the coping, and the leveling pad.
Right-of-WayRight-of-way costs are based on market data research and estimates provided by anappraiser, although an actual appraisal was not performed. At this time, these prices area conservative estimate. The cost includes acquisition of private property interests (feeand easement), relocation costs for businesses and residences displaced by the project,damages to properties, and other administrative costs involved in the acquisition.Residences would not be permanently displaced by the project.
Roadway/Guideway ExcavationRoadway and guideway excavation would be required throughout the at-grade portion ofthe guideway and at at-grade stations. Because of the proximity of the existing activerailroad and the potential impact to construction efficiencies, a premium has been placedon guideway excavation when compared to the Caltrans cost database.. A unit price of$18 per cubic yard has been used for this item of work.
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-17August 2014
Roadway excavation will generally be performed in narrow strips, as required forroadway widening and reconstruction. The estimated construction price was increasedto account for constrained construction work areas. A unit price of $28 per cubic yardhas been used for this item of work.
Roadway Improvements and Parking LotsVarious street improvements would be required along the Mid-Coast Corridor given theproximity and impacts of the LRT tracks on existing streets. Street improvement planshave been prepared and used for estimation purposes. Detailed cost breakdowns foreach street have been prepared. In addition, several at-grade parking lots would berequired to serve the parking needs near transit stations. The detailed cost breakdownsfor each street improvement utilized unit prices developed from the Caltrans costdatabase for the San Diego region..
Roadway Improvements (Allowance for Mitigation)Because of the reduced headways from the Santa Fe Depot to the San Diego River andthe additional activation of the crossing gates, it is expected that some roadwayimprovements may be required on streets with at-grade crossings, as well as on streetsparallel to the tracks. These improvements are generally limited to modification tosignalized intersections and minor striping. The exception would be improvements tothe Pacific Highway/Rosecrans/Taylor Street intersection. The allowance noted here isto account for the potential additional improvements that the City of San Diego mayrequire as part of modification to traffic signalized south of Taylor Street. An allowanceof $200,000 has been allocated for minor roadway improvements.
Sound WallsSound walls would be required at two locations along the Mid-Coast Corridor wherenoise impacts would be caused by the project. These are located in the vicinity of the LaPaz Condominiums located east of I-5 and the Sheraton Hotel located west of I-5.These walls are assumed to be of similar design and would have a similar cost persquare foot. A unit price of $35 per square foot (i.e., not requiring footings) and $35 persquare foot (i.e., requiring footings) has been used, which was developed from theCaltrans cost database for the San Diego region.
Special TrackworkThe cost of various special trackwork items were developed from bid results of the PBtransit database and quotes from vendors. Those bid prices were extrapolated to covervarious special trackwork that would be used for this project and were escalated by 15percent to obtain current dollar values. Various unit prices have been used, rangingfrom $133,046 for a No. 14 turnout on ballasted track to $1,119,716 for a No. 20crossing diamond on direct fixation.
Station—At GradeThe Refined Build Alternative alignment has four at-grade stations: the Tecolote Road,Clairemont Drive, Balboa Avenue, and VA Medical Center Stations. The cost of each at-grade station was broken down by the components and included the platform and
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-18
furnishings, canopies, architectural treatments, lighting, signage, and landscaping ateach station.
Station—AerialThe project has five aerial stations: the Nobel Drive, UCSD West, UCSD East,Executive Drive, and UTC Transit Center Stations. The cost of each aerial station wasbroken down by the components and included the furnishings, canopies, architecturaltreatments, lighting, and signage at each station. The cost of pedestrian walkways,pedestrian bridges, ramps, elevators, and other station access facilities are included inother items of work, such as Section 40.06 and 40.07. Concrete panels will be locatedbetween the platform edges and would provide a continuous surface between theplatforms. The cost of the concrete panels for the aerial stations is included in the bridgecosts.
Stray Current MonitoringThe intent of stray current monitoring is to detect any leakage of current so problemareas are identified and subsequently corrected. It is not intended to provide protectionagainst stray current. As such, it is imperative that any flow of current in barreinforcement be accurately measured. Measurement of current in bar reinforcementwould require positive electrical connectivity between various bar reinforcement. Toarrive at a unit price for this item of work, assumptions were made regarding bar spacingalong retaining walls, depressed sections, and cut-and-cover sections. The bars werethen assumed to be tack welded in such a way that all bars would be connectedelectrically to a monitoring device. For long structures, such as retaining walls, it wasassumed that monitoring wells would be located at 500-foot spacing. The cut-and-coverand U-section structures were assumed to have one monitoring well. Using theseassumptions, a unit price was developed for this item of work. The average price forstray current protection for all structures is $2.00 per square foot of structure.
Structure Backfill (Retaining Wall)Structural backfill (retaining wall) has been used for retaining walls, cut and cover, anddepressed sections. It is assumed that the quantity of excavated material that isgenerated from the site can be screened and re-used as structural backfill and import ofstructural backfill material would not be required. A unit price of $52 per cubic yard hasbeen used for structural backfill at retaining walls, and $73 per cubic yard has been usedfor cut-and-cover structures and depressed sections.
Structural Concrete (Retaining Wall)The unit cost for structural concrete was used in developing the estimate for retainingwalls and U-sections. The unit price was obtained from the Caltrans cost database anda value of $470 per cubic yard has been used.
Structural Concrete BridgeThe cost for aerial structures was developed from the Advanced Planning Studies andType Selection Memorandums prepared for various bridges. The foundation type,falsework requirements, straddle bents, maintenance of traffic, and architectural
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-19August 2014
treatments are factored into the structure costs. Unit prices for the bridge cost itemswere taken from the Caltrans cost database. Whenever possible District 11 (San Diegoarea) was used as a basis for the unit prices. When other districts’ unit prices wereused, a RS Means database location factor was applied to approximate cost to the SanDiego area to account for the regional labor and material differentials. To develop aunified price for all aerial structures, the various estimates for all bridges were evaluatedand an average unit price was developed. An average unit price of $850 per cubic yardfor structural concrete bridge was used. This item has a higher unit price than structuralconcrete (retaining wall), and it is used for the more difficult construction of structures,where falsework is over highways and/or will require work at night.
Structure ExcavationThe Caltrans cost database was used for this item of work. Structural excavation wasused to estimate the cost of structures, including retaining walls, bridges, open channel,cut-and-cover structure, and depressed sections. The unit price obtained from theCaltrans cost database has been rounded to $60 per cubic yard for this project.
SubstationsUp to 16 substations would be required from the Santa Fe Depot to the UTC TransitCenter. Of these, 4 would be located south of Taylor Street and 12 would be locatednorth of Taylor Street. Each substation is estimated to cost approximately $1.5 to $3.3million per substation. The cost was determined by estimating all the civil and electricalimprovements required for construction of each substation site.
Temporary Crash Cushion ModuleTemporary cushion modules would be required whenever construction activities occur inclose proximity to existing roadways at the ends of the temporary railing. The unit pricefrom the Caltrans cost database has been rounded up to $4,000 per array.
Temporary Pavement MarkingTemporary pavement marking would be required during reconstruction of existingroadways or whenever construction activities occur in close proximity to existingroadways. The Caltrans cost database provides a good indication of the probable costof this item of work. A unit price of $3.50 per square foot has been used. The unit priceincludes placement and removal of temporary pavement markings.
Temporary Railing (Type K)Temporary railing (Type K) would be required whenever construction activities occur inclose proximity to existing roadways. The Caltrans cost database provides a goodindication of the probable cost of this item of work. A unit price of $17 per linear foot hasbeen used.
Temporary ShoringTemporary shoring would be required for cut-and-cover and depressed sectionconstruction. The prices from the Caltrans cost database have a wide range for thisitem. Because of the complexity of cut-and-cover and depressed section construction
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-20
adjacent to La Jolla Colony Drive and the open channel near SR 52, the maximum bidprice from the cost database was used. A unit price of $70 per square foot has beenassigned.
Temporary Traffic SignalTemporary traffic signals would be required at the Balboa Avenue/Morena Boulevardramp, at the La Jolla Colony Drive/I-5 ramps, and at multiple locations on GeneseeAvenue during construction. These locations will require multi-directional changes to theexisting traffic signals. A project allowance of $150,000 to $300,000 per intersection hasbeen assigned.
Temporary Traffic StripeTemporary striping would be required during reconstruction of existing roadways orwhenever construction activities occur in close proximity to existing roadways. Workwould be done in small segments, and some striping may have to remain in place formore than six months. The removal of the temporary traffic strip is included in the unitprice. Therefore, the unit price from the Caltrans cost database has been increased to$2.50 per linear foot for this item of work.
Track ConstructionTrack construction has been estimated by procurement of material and then by the workrequired to place the tracks. Each component of track structure is estimated separately.These include subballast, ballast, ties, rails, direct fixation fasteners, and finally,placement of the tracks. A separate rail estimate is provided for LRT (115RE rail) andLOSSAN tracks (136RE rail). Also, material prices for standard and high-strength railshave been provided. Track placement is estimated to cost between $85 to $150 pertrack foot. The low range is used for ballasted track and the high range is used for directfixation track.
Track Slab (Structure Concrete approach slab)Track slab would be required at the approach to the San Diego River Bridge to preventany differential track movement. A comparable item from the Caltrans cost database ofapproach slab was used to derive the unit cost for this item. A unit price of $850 percubic yard has been used.
Traffic SignalsBecause of the reduced headways from the Santa Fe Depot to the San Diego River andthe additional activation of the crossing gates, it is expected that some improvementsmay be required on streets adjacent to the existing grade crossings. The traffic signalsat streets parallel to the tracks would be preempted with each crossing gate activation.Modification to the traffic signals at these intersections is expected to cost between$75,000 and $275,000 per location.
Train Control and SignalsCapital costs for train control and signals were based on recent bids on recent SANDAGprojects to rehabilitate existing tracks. These prices were adjusted to account for the
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-21August 2014
fact that along 10.9 miles of improvements, there is no current track or revenue service.The cost includes installation along the extension of the system and upgrades to existingfacilities from the Santa Fe Depot to the San Diego River. The cost for this item of workwas broken down into its component parts and separately tabulated.
UtilitiesThe wet utilities—sewer and water—were analyzed to identify impacts from the LRTtracks. The length of relocation, abandonment, and reconstruction of these utilities weredetermined based on the Final SEIS/SEIR Plan Set (SANDAG, 2014b). The cost forutilities also includes the earthwork, trench, sewer/water pipe, appurtenances, fittings,other materials, and rehabilitation of existing pavement.
Preliminary dry utility relocation costs were developed based on identification of potentialconflict locations, site visits, review of as-built plans, and discussions with utility owners.Unit prices were developed either on a linear foot basis, or on a lump sum basis for eachrelocation. The relocation cost did not include any additional right-of-way that may berequired. Relocation of franchise utilities includes relocation of some gas and electrictransmission lines, as well as highly sensitive telephone, cable, and fiber optics lines. Itis anticipated that fiber optics lines belonging to about nine companies could beimpacted by the project. The capital cost estimate for relocation of utilities assumes thatthe full cost of relocation would be borne by SANDAG.
Vehicle CostIn 2010, MTS procured 57 new vehicles at a cost of approximately $3.5 million pervehicle. This cost did not include sales tax, spare parts, and other minor improvements.For this project, a unit cost of $3.7 million was used. With the addition of professionalservices, taxes and other minor improvements, the cost of each vehicle is estimated atapproximately $4.1 million. This cost includes design, bonding, insurance, tools,training, manuals, construction management, testing, and project administration. Thisproject intends to place an order for the opening year for 36 vehicles.
WaterproofingWaterproofing would be required behind the walls of cut-and-cover structures anddepressed sections and select bridges. The Caltrans cost database and the PB transitdatabase each provided only one source for this item of work. A unit prices of $15 persquare foot was used for the bridges on the project and $14 per square foot was usedfor the cut-and-cover structure
Water DiversionDiversion of water around construction activities may be required during the constructionof the La Jolla Colony Drive overhead structure and the Rose Creek open channel.Although such diversion can be accommodated relatively inexpensively, water qualityregulations may require treatment of diverted water. The Caltrans cost databaseindicated that Temporary Active Treatment on its projects averaged about $92,000. Anallowance of $100,000 per depressed/cut-and-cover section has been assumed for thisproject.
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-22
A summary of unit costs used to develop the capital cost estimate is shown in Table 3-4.Unit Prices . Detailed quantity take-off and complete unit prices for all items are shownin Appendix A.
Table 3-4. Unit Prices
Item Unit Cost SourceAbove-ground parking Space $21,000 6Aerial structures - Used component parts 1Architectural treatment SF $4 1Ballast CY $53 1Bar reinforcing steel LB $1.00 1Below-ground parking Space $30,000 6Bumping post (DF) EA $20,855 4Cable railing LF $25 1Catenary pole foundations EA $5,000 2/6Catenary System - Used component parts 6Central control LS $1,000,000 4Chain link fence (Type CL-6) LF Varies: $16 to $24 1Class 2 aggregate base CY $45 1Clearing and grubbing Ac $4,022 1Concrete barrier LF Varies: $46 to $100 1Concrete plinth CF $44.10 3/6Communication (Station) LS Varies 3Demolish pedestrian bridge SF $27 1Drainage system LS Varies 3Ductbank LF Varies: $112 to $161 3Elevators EA Varies: $710,00 to
$810,0004
Environmental mitigation LS $6,500,000 4Fare collection system and equipment EA Varies: $20,000 to
$140,0005
Hazardous materials LS $4,400,000 4Hot mix asphalt (Type A) Ton $102 1Landscaping and irrigation SF $6.10 2Mobilization LS 8.5% 4/6Mud slab CY $327 6Ornamental fence LF $72 1Partnering EA $300,0000 6Pervious Backfill (retaining wall) CY $49 1Remove & Salvage Exist Track &Turnout EA Varies: $12,948 to $23,304 6Roadway/Guideway excavation CY $28 / $18 1Right of Way LS Varies 3/4Roadway improvements LS Varies 3/4Roadway improvements (allowance for mitigation) LS $200,000 4/6
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-23August 2014
Table 3-4. Unit Prices (continued)
Item Unit Cost SourceSound wall SF Varies: $25 to $35 1Special Trackwork EA Varies: $130,000
to1,120,0002/6
Station—at grade LS Varies 3Station—aerial LS Varies 3Stray current monitoring SF $2 6Structure backfill (retaining wall) CY $52 1Structural concrete (retaining wall) CY $470 1Structural concrete (bridge) CY $850 1Structure excavation (retaining wall) CY $60 1Substation (Traction power supply) LS Varies 3/6Temporary crash cushion module EA $4,000 1Temporary pavement marking SF $3.50 1Temporary railing (Type K) LF $17 1Temporary shoring SF $70 1Temporary traffic signal LS Varies: $150,000 to
$300,0004
Temporary traffic stripe LF $2.50 1Track slab CY $850 1Train Control and Signals LS Varies 6Utilities LS Varies 3/5Vehicle EA $4,090,922 5/6Water proofing SF Varies: $14 to $15 1Water Diversion LS $100,000 1
Sources of unit costs:1 – Caltrans cost database2 – Mission Valley East Light Rail Transit Extension Project bid data3 – See Quantities/Unit Cost Workbook4 – Allowance for item of work lacking adequate scope and/or definition5 – SANDAG/MTS6 – Parsons Brinckerhoff transit databaseDF = direct fixation; MSE = mechanically stabilized earth; C&C = cut-and-cover; SF = square foot;CY = cubic yard; RF = route foot; LB = Pound; EA = each; LF = linear foot; Ac = acre; LS = lump sum;TF = track foot
Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-24
THIS PAGE INTENTIONALLY LEFT BLANK
Capital Cost Methodology and Estimate ReportChapter 4.0 – Capital Cost Estimate
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T4-1August 2014
4.0 CAPITAL COST ESTIMATETable 4-1 summarizes capital costs for the Refined Build Alternative. Table 4-2 showsthe detailed capital cost estimate for the Refined Build Alternative.
Table 4-1. Summary of the Capital Cost for the Refined Build Alternative
Refined Build Alternative$’000
10-50 Construction Subtotal $753,96860 ROW, Land, Existing Improvements $145,95370 Vehicles $169,74280 Professional Services $290,45390 Unallocated Contingency $129,211Subtotal: Base Year (2013) Dollars Total $1,489,326Subtotal: YOE Dollars Total $1,687,721100 Finance Charges-Base Year (2013) $349,269100 Finance Charges-YOE $424,394Base Year (2013) Dollars Total $1,838596YOE Dollars Total $2,112,115
Source: SANDAG, 2014
Capital Cost Methodology and Estimate ReportChapter 4.0 – Capital Cost Estimate
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20144-2
THIS PAGE INTENTIONALLY LEFT BLANK
Capital Cost Methodology and Estimate ReportChapter 4.0 – Capital Cost Estimate
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T4-3August 2014
Table 4-2. Mid-Coast Capital Cost Estimate – Refined Build AlternativeM A I N W O R K S H E E T – R E F I N E D B U I L D A L T E R N A T I V E (Rev.15, August, 2013)
Refined Build Alternative (Final SEIS/SEIR) (Using SANDAG Fiscal Year) Today's Date 1/16/14Mid-Coast Corridor Transit Project, San Diego, California Yr of Base Year $ 2013
Yr of Revenue Ops 2019
Quantity Base YearDollars w/oContingenc
y(X000)
Base YearDollars
AllocatedContingency
(X000)
Base YearDollarsTOTAL(X000)
Base YearDollars Unit Cost
(X000)
Base YearDollars
Percentageof
ConstructionCost
Base YearDollars
Percentageof
TotalProjectCost
YOE DollarsTotal
(X000)
10 GUIDEWAY & TRACK ELEMENTS (route miles) 10.93 270,884 61,189 332,073 $30,382 44% 18% 381,49810.01 Guideway: At-grade exclusive right-of-way 1.71 13,939 3,309 17,248 $10,087 19,81510.02 Guideway: At-grade semi-exclusive (allows cross-traffic) 0 010.03 Guideway: At-grade in mixed traffic 0 010.04 Guideway: Aerial structure 4.04 133,925 33,296 167,221 $41,391 192,11010.05 Guideway: Built-up fill 0 010.06 Guideway: Underground cut & cover 0.04 6,799 1,610 8,409 $210,225 9,66110.07 Guideway: Underground tunnel 0 010.08 Guideway: Retained cut or fill 5.14 55,208 11,140 66,348 $12,908 76,22310.09 Track: Direct fixation 27,768 5,554 33,321 38,28110.10 Track: Embedded 0 010.11 Track: Ballasted 22,206 4,641 26,847 30,84310.12 Track: Special (switches, turnouts) 9,599 1,208 10,807 12,41510.13 Track: Vibration and noise dampening 1,440 432 1,872 2,15120 STATIONS, STOPS, TERMINALS, INTERMODAL (number) 9 87,374 16,607 103,981 $11,553 14% 6% 122,18220.01 At-grade station, stop, shelter, mall, terminal, platform 4 12,539 2,064 14,603 $3,651 17,15920.02 Aerial station, stop, shelter, mall, terminal, platform 5 47,405 10,438 57,843 $11,569 67,96820.03 Underground station, stop, shelter, mall, terminal, platform 0 020.04 Other stations, landings, terminals: Intermodal, ferry, trolley, etc. 0 020.05 Joint development 0 020.06 Automobile parking multi-story structure 17,700 2,955 20,655 24,27020.07 Elevators, escalators 9,730 1,151 10,881 12,78530 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS 10.93 0 0 0 $0 0% 0% 030.01 Administration Building: Office, sales, storage, revenue counting 0 #DIV/0!30.02 Light Maintenance Facility 0 #DIV/0!30.03 Heavy Maintenance Facility 0 #DIV/0!30.04 Storage or Maintenance of Way Building 0 #DIV/0!30.05 Yard and Yard Track 0 #DIV/0!40 SITEWORK & SPECIAL CONDITIONS 10.93 155,511 32,383 187,894 $17,191 25% 10% 214,05840.01 Demolition, Clearing, Earthwork 1,402 294 1,696 1,93240.02 Site Utilities, Utility Relocation 37,105 9,300 46,405 52,86740.03 Haz. mat'l, contam'd soil removal/mitigation, ground water
treatments4,400 1,320 5,720 6,516
40.04 Environmental mitigation, e.g. wetlands, historic/archeologic, parks 9,888 2,797 12,685 14,45240.05 Site structures including retaining walls, sound walls 0 040.06 Pedestrian / bike access and accommodation, landscaping 3,885 1,027 4,912 5,59640.07 Automobile, bus, van accessways including roads, parking lots 32,773 7,122 39,895 45,45040.08 Temporary Facilities and other indirect costs during construction 66,058 10,523 76,581 87,24450 SYSTEMS 10.93 105,959 24,060 130,019 $11,896 17% 7% 151,84750.01 Train control and signals 31,686 7,505 39,192 45,77250.02 Traffic signals and crossing protection 6,145 1,536 7,681 8,97150.03 Traction power supply: substations 38,909 7,047 45,957 53,67250.04 Traction power distribution: catenary and third rail 17,732 4,526 22,258 25,99550.05 Communications 7,106 2,131 9,237 10,78850.06 Fare collection system and equipment 3,380 1,014 4,394 5,13250.07 Central Control 1,000 300 1,300 1,518Construction Subtotal (10 - 50) 10.93 619,727 134,240 753,968 $68,981 100% 41% 869,58460 ROW, LAND, EXISTING IMPROVEMENTS 10.93 93,429 52,524 145,953 $13,353 8% 155,15660.01 Purchase or lease of real estate 91,429 52,224 143,653 152,71160.02 Relocation of existing households and businesses 2,000 300 2,300 2,44570 VEHICLES (number) 36 161,659 8,083 169,742 $4,715 9% 195,70670.01 Light Rail 36 147,273 7,364 154,637 $4,295 178,29170.02 Heavy Rail 0 070.03 Commuter Rail 0 070.04 Bus 0 070.05 Other 0 070.06 Non-revenue vehicles 0 070.07 Spare parts 14,386 719 15,105 17,41580 PROFESSIONAL SERVICES (applies to Cats. 10-50) 10.93 242,044 48,409 290,453 $26,574 39% 16% 319,04580.01 Project Development 80,000 16,000 96,000 105,45080.02 Engineering 35,000 7,000 42,000 46,13480.03 Project Management for Design and Construction 30,986 6,197 37,184 40,84480.04 Construction Administration & Management 61,973 12,395 74,367 81,68880.05 Professional Liability and other Non-Construction Insurance 6,197 1,239 7,437 8,16980.06 Legal; Permits; Review Fees by other agencies, cities, etc. 12,395 2,479 14,873 16,33880.07 Surveys, Testing, Investigation, Inspection 6,197 1,239 7,437 8,16980.08 Start up 9,296 1,859 11,155 12,253Subtotal (10 - 80) 10.93 1,116,859 243,256 1,360,115 $124,439 74% 1,539,49190 UNALLOCATED CONTINGENCY 129,211 7% 148,231Subtotal (10 - 90) 10.93 1,489,326 $136,260 81% 1,687,721100 FINANCE CHARGES 349,269 19% 424,394Total Project Cost (10 - 100) 10.93 1,838,596 $168,216 100% 2,112,115Allocated Contingency as % of Base Yr Dollars w/o Contingency 21.78%Unallocated Contingency as % of Base Yr Dollars w/o Contingency 11.57%Total Contingency as % of Base Yr Dollars w/o Contingency 33.35%Unallocated Contingency as % of Subtotal (10 - 80) 9.50%YOE Construction Cost per Mile (X000) $79,559YOE Total Project Cost per Mile Not Including Vehicles (X000) $175,335YOE Total Project Cost per Mile (X000) $193,240
Capital Cost Methodology and Estimate ReportChapter 4.0 – Capital Cost Estimate
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20144-4
THIS PAGE INTENTIONALLY LEFT BLANK
Capital Cost Methodology and Estimate ReportChapter 5.0 – Estimate Limitations
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T5-1August 2014
5.0 ESTIMATE LIMITATIONSSignificant uncertainties exist during the early stages of design. Uncertainties inherent inthe estimate include project definition, quantities, establishment of design criteria, projectschedule, escalation rates, and unknown items of work that can only be defined as theproject progresses further into design. As the project is further defined and the capitalcost estimate is refined, the project contingencies can be reduced.
5.1 Standard Design CriteriaThe San Diego Association of Governments (SANDAG) Draft Light Rail Transit (LRT)Design Criteria (SANDAG, 2010b), which reflects the attributes of previously completedLRT projects, will be adopted for estimating the Refined Build Alternative. The NorthCounty Transit District and the Southern California Rail Road Authority design criteriawill be followed in estimating costs for the relocation of existing Los Angeles–SanDiego–San Luis Obispo Rail Corridor Agency tracks. Should the Mid-Coast CorridorTransit Project require upgrades to existing facilities, such as modifications to signaling,fare collection, vehicle configuration, and other systems, these costs will be included inthe overall cost of this project.
5.2 Scope and Quantity DefinitionThe confirmation of the project scope by the SANDAG Board of Directors, coupled withthe need to perform additional design to allow precise quantity take offs, will result inchanges to the cost of the project as the design evolves. Issues relating to bridge typeand station design can result in significant swings in estimated costs. Changes in thescope assumptions will be incorporated into the estimate as the engineering progresseswith each iteration documenting the changes made. Although the contingencies areintended to mitigate some of these impacts, cost risks still remain in this regard.
5.3 Commodity PricingOver the past several years, commodities, such as petroleum, concrete, and steel, haveexperienced extreme price fluctuations, both rising and falling based on constructiondemand. This fluctuation has placed an extra burden on grantees as they endeavor toestablish reliable estimates and budget baselines that will reflect contractor bids. TheU.S. economy is slowly recovering from the recession, but prices have remained soft.This may be short-term to the extent that many of these commodities may remainmercurial as the project prepares for construction in the future. Additionally, the SanDiego region has seen a depletion of its active quarries. Should additional quarries beapproved for development in the future, the cost of ballast and aggregates couldfluctuate as a result of variable transportation costs.
5.4 Unforeseen ChallengesPerhaps one of the largest sources of uncertainty is the difficulty associated withanticipating problems that only are uncovered during the later stages of projectdevelopment. Areas that appear to be most susceptible are right-of-way acquisitions,utility relocations, hazardous materials, soil conditions, and bid/market risks.
Capital Cost Methodology and Estimate ReportChapter 5.0 – Estimate Limitations
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20145-2
Over the past several years, many projects have seen substantial variations in bidscompared to engineer estimates. More recently, most project engineer estimates arehigher than contractor bids. Generally, this is the result of extreme competition by morecontractors bidding on fewer projects. To address appropriate project risk, the allocatedcontingency approximates the project risks and aides the estimate as the projectadvances to final design. In addition, prudent contingency levels allocated to theestimate are not designed to address extreme volatility in market conditions.
The estimating methods described in Section 3.0 represent professionally acceptedstandards for preparing capital cost estimates to a level of accuracy that is consistentwith the level of project definition. Accuracy is traditionally expressed as a +/-percentage range around the point estimate that has been produced. The percentagevariance factors are greatest during the early stage of project definition andprogressively decrease as project definition increases. For example, for typical transitprojects, the expected accuracy range of an estimate prepared from final designdocuments is approximately +10/-5 percent. For projects at a level of project definitionfrom 1 to 15 percent complete, the expected accuracy range is approximately +30/-25percent.
One of the primary techniques used to address the uncertainties inherent in theestimating process at this phase of project development is the application of appropriateallocated contingencies. The use and application of allocated contingencies also isdiscussed in Section 3.0. As a project progresses through subsequent phases, the levelof detail in the design will increase and the type, quantity, and location of systemelements can be better estimated. As this occurs, the accuracy of the cost estimates willimprove and the allocated contingency will decrease. Unallocated contingencies willremain the same up to the start of construction and then drawn down through theconstruction phase. In addition, the Federal Transit Administration’s mandated riskassessment process will address both allocated and unallocated contingences and setsminimum guidelines for agencies to follow.
Capital Cost Methodology and Estimate ReportChapter 6.0 – References
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T6-1August 2014
6.0 REFERENCESCalifornia Department of Transportation (Caltrans), 2013. Caltrans District 8 database,
accessed at: http://sv08data.dot.ca.gov/contractcost/
Metropolitan Transit Development Board (MTDB). 1995a. Mid-Coast CorridorAlternatives Analysis/Draft Environmental Impact Statement/Draft EnvironmentalImpact Report. February 1995.
Metropolitan Transit Development Board (MTDB). 1995b. Final Environmental ImpactReport for the Mid-Coast Corridor. December 1995.
Metropolitan Transit Development Board (MTDB). 2001. Mid-Coast Corridor ProjectBalboa Extension and Nobel Drive Coaster Station Final Environmental ImpactStatement. June 2001.
San Diego Association of Governments (SANDAG), 2010a. Mid-Coast Corridor TransitProject Construction Cost Escalation Forecast 2014-2023.
San Diego Association of Governments (SANDAG), 2010b. Draft Light Rail TransitDesign Criteria. January 2010.
San Diego Association of Governments (SANDAG), 2013a. Mid-Coast Corridor TransitProject Draft Supplemental Environmental Impact Statement/SubsequentEnvironmental Impact Report.
San Diego Association of Governments (SANDAG), 2013b, Mid-Coast Corridor TransitProject Construction Cost Escalation Forecast 2014-2023 Report
San Diego Association of Governments (SANDAG), 2014a. Mid-Coast Corridor TransitProject Final Supplemental Environmental Impact Statement/SubsequentEnvironmental Impact Report.
San Diego Association of Governments (SANDAG), 2014b. Mid-Coast Corridor TransitProject Final SEIS/SEIR Plan Set.
San Diego Association of Governments (SANDAG), 2014c. Mid-Coast Corridor TransitProject Hazardous Materials Technical Report.
San Diego Association of Governments (SANDAG), 2014d. Mid-Coast Corridor TransitProject Biological Resources Technical Report.
San Diego Association of Governments (SANDAG), 2014e. Mid-Coast Corridor TransitProject Final Refined Build Alternative Report.
Capital Cost Methodology and Estimate ReportChapter 6.0 – References
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20146-2
THIS PAGE INTENTIONALLY LEFT BLANK
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 2014
Appendix ACapital Cost Estimate
Detailed Report
M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 2014
THIS PAGE INTENTIONALLY LEFT BLANK
Mid-coast Corridor Transit ProjectCapitol Cost Estimate - Item DetailSan Diego Association of Governments (SANDAG)San Diego, California
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Section 10 GUIDEWAY AND TRACK ELEMENTS
Sub Section 10.01 GUIDEWAY: AT-GRADE EXCLUSIVE RIGHT-OF-WAY
Group 10.01.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GUIDEWAY EXCAVATION Contingency
10.01.01 GUIDEWAY EXCAVATION 13,937.00 CY $18.00 $250,866 10.00% 5.00% 15.00% $37,630 $288,496
10.01.01.190101 GUIDEWAY EXCAVATION 8,470.00 CY $18.00 $152,460 10.00% 5.00% 15.00% $22,869 $175,329
10.01.01.190101 GUIDEWAY EXCAVATION 44.00 CY $18.00 $792 10.00% 5.00% 15.00% $119 $911
10.01.01.190101 GUIDEWAY EXCAVATION 15,260.00 CY $18.00 $274,680 10.00% 5.00% 15.00% $41,202 $315,882
Sum
Average
37,711.00 $678,798
10.00% 5.00% 15.00%
$101,820 $780,618Summary for Group: 10.01.01
Group 10.01.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PERMANENT BMP (AT-GRADE GUIDEWAY) Contingency
10.01.02 PERMANENT BMP (AT-GRADE GUIDEWAY) 1.00 LS $350,000.00 $350,000 0.00% 20.00% 20.00% $70,000 $420,000
Sum
Average
1.00 $350,000
0.00% 20.00% 20.00%
$70,000 $420,000Summary for Group: 10.01.02
Group 10.01.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GUIDEWAY DRAINAGE SYSTEMS Contingency
10.01.03.01 UNDERDRAIN (GUIDEWAY) 12,280.00 LF $30.00 $368,400 15.00% 15.00% 30.00% $110,520 $478,920
10.01.03.01 UNDERDRAIN (GUIDEWAY) 2,475.00 LF $30.00 $74,250 15.00% 15.00% 30.00% $22,275 $96,525
10.01.03.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 765.00 LF $27.00 $20,655 15.00% 15.00% 30.00% $6,197 $26,852
10.01.03.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 9,955.00 LF $27.00 $268,785 15.00% 15.00% 30.00% $80,636 $349,421
10.01.03.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 1,875.00 LF $27.00 $50,625 15.00% 15.00% 30.00% $15,188 $65,813
10.01.03.101 18" RCP STORM DRAIN 20.00 LF $120.00 $2,400 15.00% 15.00% 30.00% $720 $3,120
10.01.03.101 18" RCP STORM DRAIN 45.00 LF $120.00 $5,400 15.00% 15.00% 30.00% $1,620 $7,020
10.01.03.101 18" RCP STORM DRAIN 55.00 LF $120.00 $6,600 15.00% 15.00% 30.00% $1,980 $8,580
10.01.03.101 18" RCP STORM DRAIN 65.00 LF $120.00 $7,800 15.00% 15.00% 30.00% $2,340 $10,140
10.01.03.101 18" RCP STORM DRAIN 140.00 LF $120.00 $16,800 15.00% 15.00% 30.00% $5,040 $21,840
Monday, January 27, 2014 Page 1 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.01.03.101 18" RCP STORM DRAIN 30.00 LF $120.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680
10.01.03.101 18" RCP STORM DRAIN 35.00 LF $120.00 $4,200 15.00% 15.00% 30.00% $1,260 $5,460
10.01.03.101 18" RCP STORM DRAIN 35.00 LF $120.00 $4,200 15.00% 15.00% 30.00% $1,260 $5,460
10.01.03.101 18" RCP STORM DRAIN 15.00 LF $120.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.01.03.102 24" RCP STORM DRAIN 35.00 LF $170.00 $5,950 15.00% 15.00% 30.00% $1,785 $7,735
10.01.03.102 24" RCP STORM DRAIN 30.00 LF $170.00 $5,100 10.00% 15.00% 25.00% $1,275 $6,375
10.01.03.102 24" RCP STORM DRAIN 85.00 LF $170.00 $14,450 15.00% 15.00% 30.00% $4,335 $18,785
10.01.03.102 24" RCP STORM DRAIN 360.00 LF $170.00 $61,200 15.00% 15.00% 30.00% $18,360 $79,560
10.01.03.102 24" RCP STORM DRAIN 90.00 LF $170.00 $15,300 15.00% 15.00% 30.00% $4,590 $19,890
10.01.03.103 30" RCP STORM DRAIN 30.00 LF $210.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
10.01.03.103 30" RCP STORM DRAIN 30.00 LF $210.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
10.01.03.104 36" RCP STORM DRAIN 45.00 LF $230.00 $10,350 15.00% 15.00% 30.00% $3,105 $13,455
10.01.03.104 36" RCP STORM DRAIN 30.00 LF $230.00 $6,900 15.00% 15.00% 30.00% $2,070 $8,970
10.01.03.104 36" RCP STORM DRAIN 70.00 LF $230.00 $16,100 15.00% 15.00% 30.00% $4,830 $20,930
10.01.03.104 36" RCP STORM DRAIN 35.00 LF $230.00 $8,050 15.00% 15.00% 30.00% $2,415 $10,465
10.01.03.105 42" RCP STORM DRAIN 30.00 LF $260.00 $7,800 15.00% 15.00% 30.00% $2,340 $10,140
10.01.03.106 48" RCP STORM DRAIN 35.00 LF $290.00 $10,150 15.00% 15.00% 30.00% $3,045 $13,195
10.01.03.106 48" RCP STORM DRAIN 30.00 LF $290.00 $8,700 15.00% 15.00% 30.00% $2,610 $11,310
10.01.03.106 48" RCP STORM DRAIN 60.00 LF $290.00 $17,400 15.00% 15.00% 30.00% $5,220 $22,620
10.01.03.106 48" RCP STORM DRAIN 30.00 LF $290.00 $8,700 15.00% 15.00% 30.00% $2,610 $11,310
10.01.03.106 48" RCP STORM DRAIN 10.00 LF $290.00 $2,900 15.00% 15.00% 30.00% $870 $3,770
10.01.03.115 12" PVC STORM DRAIN 20.00 LF $100.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
10.01.03.131 6' X 4' RCB STORM DRAIN 30.00 LF $1,027.00 $30,810 15.00% 15.00% 30.00% $9,243 $40,053
10.01.03.132 6' X 6' RCB STORM DRAIN 75.00 LF $1,270.00 $95,250 15.00% 15.00% 30.00% $28,575 $123,825
10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
Monday, January 27, 2014 Page 2 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.01.03.204 TYPE B CURB INLET 1.00 EA $5,200.00 $5,200 10.00% 15.00% 25.00% $1,300 $6,500
10.01.03.204 10' MOD TYPE B-1 CURB INLET 1.00 EA $6,900.00 $6,900 15.00% 15.00% 30.00% $2,070 $8,970
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.01.03.206 TYPE G CATCH BASIN 1.00 EA $6,750.00 $6,750 10.00% 15.00% 25.00% $1,688 $8,438
10.01.03.206 MOD TYPE G CATCH BASIN 1.00 EA $6,750.00 $6,750 10.00% 15.00% 25.00% $1,688 $8,438
10.01.03.210 TYPE A STRAIGHT HEADWALL 1.00 EA $7,000.00 $7,000 10.00% 15.00% 25.00% $1,750 $8,750
10.01.03.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250
10.01.03.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250
10.01.03.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250
10.01.03.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250
10.01.03.214 CULVERT INLET (SPECIAL DETAIL) 1.00 EA $4,130.00 $4,130 0.00% 15.00% 15.00% $620 $4,750
Monday, January 27, 2014 Page 3 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.01.03.214 CULVERT INLET (SPECIAL DETAIL) 1.00 EA $4,130.00 $4,130 0.00% 15.00% 15.00% $620 $4,750
10.01.03.216 CURTAIN WALL 1.00 EA $10,650.00 $10,650 15.00% 15.00% 30.00% $3,195 $13,845
10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.01.03.502 PIPE COLLAR 2.00 EA $1,800.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680
10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.01.03.503 PIPE TO CHANNEL TRANSITION 1.00 EA $6,230.00 $6,230 15.00% 15.00% 30.00% $1,869 $8,099
10.01.03.512 CULVERT EXTENSION JOINT, SDRSD D-81 (CY OF CONC) 0.65 CY $400.00 $260 15.00% 15.00% 30.00% $78 $338
10.01.03.700 ABN EXIST 18" ACP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878
10.01.03.700 ABN EXIST 8" PVC STORM DRAIN 3.00 EA $675.00 $2,025 15.00% 15.00% 30.00% $608 $2,633
10.01.03.701 ABN EXIST CATCH BASIN 1.00 EA $1,240.00 $1,240 15.00% 15.00% 30.00% $372 $1,612
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236
10.01.03.702 REMOVE EXIST DROP INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST CURB INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379
10.01.03.702 REMOVE EXIST ENDWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 3.00 EA $860.00 $2,580 15.00% 15.00% 30.00% $774 $3,354
10.01.03.702 REMOVE EXIST ENDWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST CURB INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
Monday, January 27, 2014 Page 4 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST ENDWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST ENDWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236
10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.01.03.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236
Sum
Average
29,028.65 $1,470,165
12.76% 15.00% 27.76%
$422,737 $1,892,902Summary for Group: 10.01.03
Group 10.01.03.800
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LA JOLLA RCB Contingency
10.01.03.800.192025 STRUCTURE EXCAVATION (CULVERT) 780.00 CY $60.00 $46,800 15.00% 10.00% 25.00% $11,700 $58,500
10.01.03.800.193004 STRUCTURAL BACKFILL (CULVERT) 448.00 CY $73.00 $32,704 15.00% 10.00% 25.00% $8,176 $40,880
10.01.03.800.510090 STRUCTURAL CONCRETE (CULVERT) 245.00 CY $620.00 $151,900 15.00% 10.00% 25.00% $37,975 $189,875
10.01.03.800.518002 3" MUD SLAB (CULVERT) 18.00 CY $327.00 $5,886 15.00% 10.00% 25.00% $1,472 $7,358
10.01.03.800.518002 WATER DIVERSION 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000
10.01.03.800.520107 BAR REINFORCING STEEL (CULVERT) 49,100.00 LB $1.00 $49,100 15.00% 10.00% 25.00% $12,275 $61,375
10.01.03.800.520122 STRAY CURRENT PROTECTION (CULVERT) 1,827.00 SF $2.00 $3,654 15.00% 10.00% 25.00% $914 $4,568
10.01.03.800.838521 CABLE RAILING 56.00 LF $25.00 $1,400 10.00% 10.00% 20.00% $280 $1,680
Sum
Average
52,475.00 $391,444
14.38% 10.00% 24.38%
$97,791 $489,235Summary for Group: 10.01.03.800
Group 10.01.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROSE CREEK OPEN CHANNEL Contingency
10.01.04.1000095 CONCRETE (RIPRAP BASIN - OPEN CHANNEL) 200.00 CY $544.00 $108,800 15.00% 10.00% 25.00% $27,200 $136,000
10.01.04.192025 STRUCTURE EXCAVATION (OPEN CHANNEL) 16,034.00 CY $60.00 $962,040 15.00% 10.00% 25.00% $240,510 $1,202,550
10.01.04.193004 STRUCTURAL BACKFILL (OPEN CHANNEL) 8,041.00 CY $73.00 $586,993 15.00% 10.00% 25.00% $146,748 $733,741
10.01.04.480600 TEMPORARY SHORING (OPEN CHANNEL) 22,190.00 SF $70.00 $1,553,300 15.00% 10.00% 25.00% $388,325 $1,941,625
10.01.04.490604 30" CIDH CONCRETE PILING 1,714.00 LF $370.00 $634,180 15.00% 10.00% 25.00% $158,545 $792,725
10.01.04.510090 STRUCTURAL CONCRETE (OPEN CHANNEL) 6,052.00 CY $620.00 $3,752,240 15.00% 10.00% 25.00% $938,060 $4,690,300
10.01.04.518002 WATER DIVERSION 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000
Monday, January 27, 2014 Page 5 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.01.04.518002 3" MUD SLAB (OPEN CHANNEL) 229.00 CY $327.00 $74,883 15.00% 10.00% 25.00% $18,721 $93,604
10.01.04.520107 BAR REINFORCING STEEL (OPEN CHANNEL) 1,206,000.00 LB $1.00 $1,206,000 15.00% 10.00% 25.00% $301,500 $1,507,500
10.01.04.520122 STRAY CURRENT PROTECTION (OPEN CHANNEL) 21,745.00 SF $2.00 $43,490 15.00% 10.00% 25.00% $10,873 $54,363
10.01.04.838521 CABLE RAILING 1,373.00 LF $25.00 $34,325 10.00% 10.00% 20.00% $6,865 $41,190
Sum
Average
1,283,579.00 $9,056,251
14.55% 10.00% 24.55%
$2,262,347 $11,318,598Summary for Group: 10.01.04
Group 10.01.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBBALLAST Contingency
10.01.08 SUBBALLAST (LOSSAN) 3,576.00 CY $45.00 $160,920 10.00% 5.00% 15.00% $24,138 $185,058
10.01.08 SUBBALLAST 20,050.00 CY $45.00 $902,250 10.00% 5.00% 15.00% $135,338 $1,037,588
10.01.08 SUBBALLAST (SHOOFLY) 3,322.00 CY $45.00 $149,490 10.00% 5.00% 15.00% $22,424 $171,914
Sum
Average
26,948.00 $1,212,660
10.00% 5.00% 15.00%
$181,899 $1,394,559Summary for Group: 10.01.08
Group 10.01.11
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CHAIN LINK FENCE Contingency
10.01.11.01 CHAIN LINK FENCE (CL-6) 7,316.70 LF $19.00 $139,017 10.00% 10.00% 20.00% $27,803 $166,821
10.01.11.01 CHAIN LINK FENCE (CL-6) 13,486.50 LF $19.00 $256,244 10.00% 10.00% 20.00% $51,249 $307,492
10.01.11.01 CHAIN LINK FENCE (CL-6) 10,897.80 LF $19.00 $207,058 10.00% 10.00% 20.00% $41,412 $248,470
10.01.11.02 6 FT CL GATE 2.00 EA $2,225.00 $4,450 10.00% 10.00% 20.00% $890 $5,340
10.01.11.02 6 FT CL GATE 1.00 EA $2,225.00 $2,225 10.00% 10.00% 20.00% $445 $2,670
10.01.11.02 6 FT CL GATE 4.00 EA $2,225.00 $8,900 10.00% 10.00% 20.00% $1,780 $10,680
Sum
Average
31,708.00 $617,894
10.00% 10.00% 20.00%
$123,579 $741,473Summary for Group: 10.01.11
Group 10.01.14
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GUIDEWAY EMBANKMENT Contingency
10.01.14.193001 GUIDEWAY EMBANKMENT SEGMENT 1 25,424.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
10.01.14.193001 GUIDEWAY EMBANKMENT SEGMENT 3 11,218.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
10.01.14.193001 GUIDEWAY EMBANKMENT SEGMENT 2 25,439.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
Sum
Average
62,081.00 $0
15.00% 10.00% 25.00%
$0 $0Summary for Group: 10.01.14
Group 10.08.29
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SOUND/SCREEN WALL Contingency
Monday, January 27, 2014 Page 6 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.29.580.86 SOUND WALL (WALL 580R-F) 6,480.00 SF $25.00 $162,000 20.00% 10.00% 30.00% $48,600 $210,600
Sum
Average
6,480.00 $162,000
20.00% 10.00% 30.00%
$48,600 $210,600Summary for Group: 10.08.29
Sum
Average
1,530,011.65 $13,939,212
12.75% 13.52% 26.27%
$3,308,772 $17,247,984Summary for Sub Section: 10.01
Sub Section 10.04 GUIDEWAY: AERIAL STRUCTURE
Group 10.04.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PERMANENT BMP (AERIAL STRUCTURE) Contingency
10.04.01 PERMANENT BMP (AERIAL STRUCTURE) 1.00 LS $1,450,000.00 $1,450,000 0.00% 20.00% 20.00% $290,000 $1,740,000
Sum
Average
1.00 $1,450,000
0.00% 20.00% 20.00%
$290,000 $1,740,000Summary for Group: 10.04.01
Group 10.04.03.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SAN DIEGO RIVER BRIDGE Contingency
10.04.03.01.15XXXX REMOVE AND REPLACE CONCRETE BERM 100.00 CY $198.00 $19,800 15.00% 10.00% 25.00% $4,950 $24,750
10.04.03.01.192003 STRUCTURE EXCAVATION (BRIDGE) 100.00 CY $60.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500
10.04.03.01.193003 STRUCTURAL BACKFILL (BRIDGE) 50.00 CY $73.00 $3,650 15.00% 10.00% 25.00% $913 $4,563
10.04.03.01.199XXX GROUND IMPROVEMENT 7.00 EA $380,000.00 $2,660,000 0.00% 10.00% 10.00% $266,000 $2,926,000
10.04.03.01.490607 48" CIDH CONCRETE PILING 360.00 LF $701.00 $252,360 15.00% 20.00% 35.00% $88,326 $340,686
10.04.03.01.490620 108"CIDH CONCRETE PILING 720.00 LF $1,967.00 $1,416,240 15.00% 20.00% 35.00% $495,684 $1,911,924
10.04.03.01.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 98,100.00 LB $1.85 $181,485 15.00% 20.00% 35.00% $63,520 $245,005
10.04.03.01.510053 STRUCTURAL CONCRETE (BRIDGE) 1,930.00 CY $850.00 $1,640,500 15.00% 20.00% 35.00% $574,175 $2,214,675
10.04.03.01.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 15.00 CY $850.00 $12,750 15.00% 10.00% 25.00% $3,188 $15,938
10.04.03.01.511035 ARCHITECT TREATMENT 360.00 SF $14.00 $5,040 15.00% 10.00% 25.00% $1,260 $6,300
10.04.03.01.518051 PTFE SPHERICAL BEARING 3.00 EA $6,191.00 $18,573 0.00% 10.00% 10.00% $1,857 $20,430
10.04.03.01.519093 JOINT SEAL ASSEMBLY (MR=3") 30.00 LF $211.00 $6,330 0.00% 10.00% 10.00% $633 $6,963
10.04.03.01.519095 JOINT SEAL ASSEMBLY (MR=4") 30.00 LF $265.00 $7,950 0.00% 10.00% 10.00% $795 $8,745
10.04.03.01.519099 JOINT SEAL ASSEMBLY (MR=6") 30.00 LF $737.00 $22,110 0.00% 10.00% 10.00% $2,211 $24,321
10.04.03.01.520102 BAR REINFORCING STEEL (BRIDGE) 774,000.00 LB $1.00 $774,000 15.00% 20.00% 35.00% $270,900 $1,044,900
10.04.03.01.520122 STRAY CURRENT PROTECTION (BRIDGE) 27,498.00 SF $2.00 $54,996 15.00% 10.00% 25.00% $13,749 $68,745
10.04.03.01.7351XX MINOR CONCRETE (CURB) 1,803.00 LF $28.00 $50,484 15.00% 10.00% 25.00% $12,621 $63,105
10.04.03.01.750501 MISCELANEOUS METAL (BRIDGE) 3,600.00 LB $4.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000
Monday, January 27, 2014 Page 7 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.04.03.01.750505 BRIDGE DECK DRAINAGE SYSTEM 5,000.00 LB $5.00 $25,000 15.00% 10.00% 25.00% $6,250 $31,250
10.04.03.01.833000 METAL RAILING (PIPE) 1,803.00 LF $125.00 $225,375 15.00% 10.00% 25.00% $56,344 $281,719
10.04.03.01.XXXXXX CONSTRUCT TEMPORARY ACCESS TRESTLE 65.00 LF $2,250.00 $146,250 15.00% 20.00% 35.00% $51,188 $197,438
Sum
Average
915,604.00 $7,543,293
11.43% 12.86% 24.29%
$1,919,662 $9,462,955Summary for Group: 10.04.03.01
Group 10.04.03.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TECOLOTE CREEK BRIDGE Contingency
10.04.03.02.153220 REMOVE CONCRETE (CHANNEL) 25.00 CY $67.00 $1,675 15.00% 10.00% 25.00% $419 $2,094
10.04.03.02.192003 STRUCTURE EXCAVATION (BRIDGE) 70.00 CY $60.00 $4,200 15.00% 10.00% 25.00% $1,050 $5,250
10.04.03.02.193003 STRUCTURAL BACKFILL (BRIDGE) 45.00 CY $73.00 $3,285 15.00% 10.00% 25.00% $821 $4,106
10.04.03.02.490604 30" CIDH CONCRETE PILING 880.00 LF $370.00 $325,600 15.00% 10.00% 25.00% $81,400 $407,000
10.04.03.02.510053 STRUCTURAL CONCRETE (BRIDGE) 258.00 CY $850.00 $219,300 15.00% 10.00% 25.00% $54,825 $274,125
10.04.03.02.520120 BAR REINFORCING STEEL (BRIDGE) 88,711.00 LB $1.00 $88,711 15.00% 10.00% 25.00% $22,178 $110,889
10.04.03.02.520122 STRAY CURRENT PROTECTION (BRIDGE) 2,249.00 SF $2.00 $4,498 15.00% 10.00% 25.00% $1,125 $5,623
10.04.03.02.540104 WATERPROOFING AND COVER 2,220.00 SF $15.00 $33,300 15.00% 10.00% 25.00% $8,325 $41,625
10.04.03.02.833000 METAL RAILING (PIPE) 185.00 LF $125.00 $23,125 15.00% 10.00% 25.00% $5,781 $28,906
Sum
Average
94,643.00 $703,694
15.00% 10.00% 25.00%
$175,924 $879,618Summary for Group: 10.04.03.02
Group 10.04.03.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROSE CREEK SOUTH BRIDGE Contingency
10.04.03.03.153220 REMOVE CONCRETE (CHANNEL) 26.00 CY $67.00 $1,742 15.00% 10.00% 25.00% $436 $2,178
10.04.03.03.192003 STRUCTURE EXCAVATION (BRIDGE) 85.00 CY $60.00 $5,100 15.00% 10.00% 25.00% $1,275 $6,375
10.04.03.03.193003 STRUCTURAL BACKFILL (BRIDGE) 45.00 CY $73.00 $3,285 15.00% 10.00% 25.00% $821 $4,106
10.04.03.03.490605 36" CIDH CONCRETE PILING 300.00 LF $507.00 $152,100 15.00% 10.00% 25.00% $38,025 $190,125
10.04.03.03.490608 54" CIDH CONCRETE PILING 80.00 LF $880.00 $70,400 15.00% 10.00% 25.00% $17,600 $88,000
10.04.03.03.490611 72" CIDH CONCRETE PILING 150.00 LF $1,113.00 $166,950 15.00% 10.00% 25.00% $41,738 $208,688
10.04.03.03.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 20,000.00 LB $1.85 $37,000 15.00% 10.00% 25.00% $9,250 $46,250
10.04.03.03.510053 STRUCTURAL CONCRETE (BRIDGE) 725.00 CY $850.00 $616,250 15.00% 10.00% 25.00% $154,063 $770,313
10.04.03.03.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 30.00 CY $850.00 $25,500 15.00% 10.00% 25.00% $6,375 $31,875
10.04.03.03.519100 JOINT SEAL (MR=2") 63.00 LF $145.00 $9,135 0.00% 10.00% 10.00% $914 $10,049
10.04.03.03.520102 BAR REINFORCING STEEL (BRIDGE) 255,000.00 LB $1.00 $255,000 15.00% 10.00% 25.00% $63,750 $318,750
Monday, January 27, 2014 Page 8 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.04.03.03.520122 STRAY CURRENT PROTECTION (BRIDGE) 9,250.00 SF $2.00 $18,500 15.00% 10.00% 25.00% $4,625 $23,125
10.04.03.03.720XXX ROCK SLOPE PROTECTION 70.00 CY $593.00 $41,510 15.00% 10.00% 25.00% $10,378 $51,888
10.04.03.03.7351XX MINOR CONCRETE (CURB) 592.00 LF $28.00 $16,576 15.00% 10.00% 25.00% $4,144 $20,720
10.04.03.03.750505 BRIDGE DECK DRAINAGE SYSTEM 1,200.00 LB $5.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500
10.04.03.03.83300 METAL RAILING (PIPE) 592.00 LF $125.00 $74,000 15.00% 10.00% 25.00% $18,500 $92,500
Sum
Average
288,208.00 $1,499,048
14.06% 10.00% 24.06%
$373,392 $1,872,440Summary for Group: 10.04.03.03
Group 10.04.03.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROSE CREEK NORTH BRIDGE Contingency
10.04.03.04.192003 STRUCTURE EXCAVATION (BRIDGE) 147.00 CY $60.00 $8,820 20.00% 15.00% 35.00% $3,087 $11,907
10.04.03.04.193003 STRUCTURAL BACKFILL (BRIDGE) 91.00 CY $73.00 $6,643 20.00% 15.00% 35.00% $2,325 $8,968
10.04.03.04.490604 30" CIDH CONCRETE PILING 240.00 LF $370.00 $88,800 20.00% 15.00% 35.00% $31,080 $119,880
10.04.03.04.490609 60" CIDH CONCRETE PILING 180.00 LF $935.00 $168,300 20.00% 15.00% 35.00% $58,905 $227,205
10.04.03.04.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 22,300.00 LB $1.85 $41,255 20.00% 15.00% 35.00% $14,439 $55,694
10.04.03.04.510053 STRUCTURAL CONCRETE (BRIDGE) 749.00 CY $850.00 $636,650 20.00% 15.00% 35.00% $222,828 $859,478
10.04.03.04.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 30.00 CY $850.00 $25,500 20.00% 15.00% 35.00% $8,925 $34,425
10.04.03.04.519100 JOINT SEAL (MR=2") 63.00 LF $145.00 $9,135 20.00% 15.00% 35.00% $3,197 $12,332
10.04.03.04.520102 BAR REINFORCING STEEL (BRIDGE) 252,000.00 LB $1.00 $252,000 20.00% 15.00% 35.00% $88,200 $340,200
10.04.03.04.520122 STRAY CURRENT PROTECTION (BRIDGE) 10,563.00 SF $2.00 $21,126 20.00% 15.00% 35.00% $7,394 $28,520
10.04.03.04.720XXX ROCK SLOPE PROTECTION 70.00 CY $593.00 $41,510 20.00% 15.00% 35.00% $14,529 $56,039
10.04.03.04.7351XX MINOR CONCRETE (CURB) 716.00 LF $28.00 $20,048 20.00% 15.00% 35.00% $7,017 $27,065
10.04.03.04.750041 ISOLATION CASING 2,700.00 LB $3.00 $8,100 20.00% 15.00% 35.00% $2,835 $10,935
10.04.03.04.750505 BRIDGE DECK DRAINAGE SYSTEM 2,630.00 LB $5.00 $13,150 20.00% 15.00% 35.00% $4,603 $17,753
10.04.03.04.833000 METAL RAILING (PIPE) 716.00 LF $125.00 $89,500 20.00% 15.00% 35.00% $31,325 $120,825
Sum
Average
293,195.00 $1,430,537
20.00% 15.00% 35.00%
$500,688 $1,931,225Summary for Group: 10.04.03.04
Group 10.04.03.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROSE CANYON LRT OH BRIDGE Contingency
10.04.03.05.192003 STRUCTURE EXCAVATION (BRIDGE) 433.00 CY $60.00 $25,980 15.00% 10.00% 25.00% $6,495 $32,475
10.04.03.05.193003 STRUCTURAL BACKFILL (BRIDGE) 488.00 CY $73.00 $35,624 15.00% 10.00% 25.00% $8,906 $44,530
10.04.03.05.490605 36" CIDH CONCRETE PILING 600.00 LF $507.00 $304,200 15.00% 10.00% 25.00% $76,050 $380,250
Monday, January 27, 2014 Page 9 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.04.03.05.490620 108" CIDH CONCRETE PILING 1,275.00 LF $1,967.00 $2,507,925 15.00% 10.00% 25.00% $626,981 $3,134,906
10.04.03.05.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 250,000.00 LB $1.85 $462,500 15.00% 10.00% 25.00% $115,625 $578,125
10.04.03.05.510053 STRUCTURAL CONCRETE (BRIDGE) 6,400.00 CY $850.00 $5,440,000 15.00% 10.00% 25.00% $1,360,000 $6,800,000
10.04.03.05.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 30.00 CY $850.00 $25,500 15.00% 10.00% 25.00% $6,375 $31,875
10.04.03.05.518051 PTFE SPHERICAL BEARING 12.00 EA $6,191.00 $74,292 0.00% 10.00% 10.00% $7,429 $81,721
10.04.03.05.519092 JOINT SEAL ASSEMBLY (MR=2.5") 31.00 LF $189.00 $5,859 0.00% 10.00% 10.00% $586 $6,445
10.04.03.05.519094 JOINT SEAL ASSEMBLY (MR=3.5") 31.00 LF $227.00 $7,037 0.00% 10.00% 10.00% $704 $7,741
10.04.03.05.519095 JOINT SEAL ASSEMBLY (MR=4") 31.00 LF $265.00 $8,215 0.00% 10.00% 10.00% $822 $9,037
10.04.03.05.519099 JOINT SEAL ASSEMBLY (MR=6") 31.00 LF $737.00 $22,847 0.00% 10.00% 10.00% $2,285 $25,132
10.04.03.05.519105 JOINT SEAL ASSEMBLY (MR=7") 62.00 LF $1,218.00 $75,516 0.00% 10.00% 10.00% $7,552 $83,068
10.04.03.05.520102 BAR REINFORCING STEEL (BRIDGE) 2,074,000.00 LB $1.00 $2,074,000 15.00% 10.00% 25.00% $518,500 $2,592,500
10.04.03.05.520122 STRAY CURRENT PROTECTION (BRIDGE) 63,438.00 SF $2.00 $126,876 15.00% 10.00% 25.00% $31,719 $158,595
10.04.03.05.7351XX MINOR CONCRETE (CURB) 4,328.00 LF $28.00 $121,184 15.00% 10.00% 25.00% $30,296 $151,480
10.04.03.05.750501 MISCELANEOUS METAL (BRIDGE) 10,000.00 LB $4.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
10.04.03.05.750505 BRIDGE DECK DRAINAGE SYSTEM 7,500.00 LB $5.00 $37,500 15.00% 10.00% 25.00% $9,375 $46,875
10.04.03.05.833000 METAL RAILING (PIPE) 4,328.00 LF $125.00 $541,000 15.00% 10.00% 25.00% $135,250 $676,250
Sum
Average
2,423,018.00 $11,936,055
10.26% 10.00% 20.26%
$2,954,949 $14,891,004Summary for Group: 10.04.03.05
Group 10.04.03.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NOBEL VIADUCT Contingency
10.04.03.06.192003 STRUCTURE EXCAVATION (BRIDGE) 1,670.00 CY $60.00 $100,200 15.00% 10.00% 25.00% $25,050 $125,250
10.04.03.06.480600 TEMPORARY SHORING 12,300.00 SF $70.00 $861,000 15.00% 10.00% 25.00% $215,250 $1,076,250
10.04.03.06.490605 36" CIDH CONCRETE PILING 750.00 LF $507.00 $380,250 15.00% 10.00% 25.00% $95,063 $475,313
10.04.03.06.490611 72" CIDH CONCRETE PILING 440.00 LF $1,113.00 $489,720 20.00% 10.00% 30.00% $146,916 $636,636
10.04.03.06.490618 96" CIDH CONCRETE PILING 570.00 LF $1,344.00 $766,080 15.00% 10.00% 25.00% $191,520 $957,600
10.04.03.06.490620 108" CIDH CONCRETE PILING 220.00 LF $1,967.00 $432,740 15.00% 10.00% 25.00% $108,185 $540,925
10.04.03.06.490622 120" CIDH CONCRETE PILING 1,025.00 LF $2,310.00 $2,367,750 15.00% 10.00% 25.00% $591,938 $2,959,688
10.04.03.06.4906xx 144" CIDH CONCRETE PILING 110.00 LF $3,170.00 $348,700 15.00% 10.00% 25.00% $87,175 $435,875
10.04.03.06.4906xx 132" CIDH CONCRETE PILING 80.00 LF $2,923.00 $233,840 15.00% 10.00% 25.00% $58,460 $292,300
10.04.03.06.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 615,040.00 LB $1.85 $1,137,824 15.00% 10.00% 25.00% $284,456 $1,422,280
Monday, January 27, 2014 Page 10 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.04.03.06.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 434.00 CY $440.00 $190,960 15.00% 10.00% 25.00% $47,740 $238,700
10.04.03.06.510051 STRUCTURAL BACKFILL (BRIDGE) 1,240.00 CY $73.00 $90,520 15.00% 10.00% 25.00% $22,630 $113,150
10.04.03.06.510053 STRUCTURAL CONCRETE (BRIDGE) 15,050.00 CY $850.00 $12,792,500 15.00% 10.00% 25.00% $3,198,125 $15,990,625
10.04.03.06.511035 ARCHITECT TREATMENT 1,500.00 SF $14.00 $21,000 15.00% 10.00% 25.00% $5,250 $26,250
10.04.03.06.518002 SOUND WALL 3,000.00 SF $25.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
10.04.03.06.518051 PTFE SPHERICAL BEARING 36.00 EA $6,191.00 $222,876 0.00% 10.00% 10.00% $22,288 $245,164
10.04.03.06.519092 JOINT SEAL ASSEMBLY (MR=2.5") 32.00 LF $189.00 $6,048 0.00% 10.00% 10.00% $605 $6,653
10.04.03.06.519093 JOINT SEAL ASSEMBLY (MR=3") 32.00 LF $211.00 $6,752 0.00% 10.00% 10.00% $675 $7,427
10.04.03.06.519099 JOINT SEAL ASSEMBLY (MR=6") 64.00 LF $737.00 $47,168 0.00% 10.00% 10.00% $4,717 $51,885
10.04.03.06.519105 JOINT SEAL ASSEMBLY (MR=7") 64.00 LF $1,218.00 $77,952 0.00% 10.00% 10.00% $7,795 $85,747
10.04.03.06.519109 JOINT SEAL ASSEMBLY (MR=6.5") 96.00 LF $1,085.00 $104,160 0.00% 10.00% 10.00% $10,416 $114,576
10.04.03.06.519XX JOINT SEAL ASSEMBLY (MR=8") 32.00 LF $1,650.00 $52,800 0.00% 10.00% 10.00% $5,280 $58,080
10.04.03.06.519xxx JOINT SEAL ASSEMBLY (MR=7.5") 32.00 LF $1,451.00 $46,432 0.00% 10.00% 10.00% $4,643 $51,075
10.04.03.06.520102 BAR REINFORCING STEEL (BRIDGE) 6,085,900.00 LB $1.00 $6,085,900 15.00% 10.00% 25.00% $1,521,475 $7,607,375
10.04.03.06.520122 STRAY CURRENT PROTECTION (BRIDGE) 155,061.00 SF $2.00 $310,122 15.00% 10.00% 25.00% $77,531 $387,653
10.04.03.06.7351xx MINOR CONCRETE (CURB) 9,321.00 LF $28.00 $260,988 15.00% 10.00% 25.00% $65,247 $326,235
10.04.03.06.750041 ISOLATION CASING 53,000.00 LB $3.00 $159,000 15.00% 10.00% 25.00% $39,750 $198,750
10.04.03.06.750501 MISCELANEOUS METAL (BRIDGE) 3,000.00 LB $4.00 $12,000 15.00% 10.00% 25.00% $3,000 $15,000
10.04.03.06.750505 BRIDGE DECK DRAINAGE SYSTEM 18,650.00 LB $5.00 $93,250 15.00% 10.00% 25.00% $23,313 $116,563
10.04.03.06.833000 METAL RAILING (PIPE) 9,321.00 LF $125.00 $1,165,125 15.00% 10.00% 25.00% $291,281 $1,456,406
Sum
Average
6,988,070.00 $28,938,657
11.17% 10.00% 21.17%
$7,174,522 $36,113,179Summary for Group: 10.04.03.06
Group 10.04.03.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UCSD VIADUCT Contingency
10.04.03.07.192003 STRUCTURE EXCAVATION (BRIDGE) 692.00 CY $60.00 $41,520 15.00% 10.00% 25.00% $10,380 $51,900
10.04.03.07.193003 STRUCTURAL BACKFILL (BRIDGE) 461.00 CY $73.00 $33,653 15.00% 10.00% 25.00% $8,413 $42,066
10.04.03.07.490603 24" CIDH CONCRETE PILING 12,098.00 LF $306.00 $3,701,988 15.00% 10.00% 25.00% $925,497 $4,627,485
10.04.03.07.490620 108" CIDH CONCRETE PILING 1,183.00 LF $1,967.00 $2,326,961 15.00% 10.00% 25.00% $581,740 $2,908,701
10.04.03.07.4906xx 132" CIDH CONCRETE PILING 662.00 LF $2,923.00 $1,935,026 15.00% 10.00% 25.00% $483,757 $2,418,783
10.04.03.07.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 1,187,110.00 LB $1.85 $2,196,154 15.00% 10.00% 25.00% $549,038 $2,745,192
Monday, January 27, 2014 Page 11 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.04.03.07.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 1,405.00 CY $440.00 $618,200 15.00% 10.00% 25.00% $154,550 $772,750
10.04.03.07.510053 STRUCTURAL CONCRETE (BRIDGE) 20,729.00 CY $850.00 $17,619,650 15.00% 10.00% 25.00% $4,404,913 $22,024,563
10.04.03.07.511035 ARCHITECT TREATMENT 2,066.00 SF $14.00 $28,924 15.00% 10.00% 25.00% $7,231 $36,155
10.04.03.07.518051 PTFE SPHERICAL BEARING 68.00 EA $6,191.00 $420,988 0.00% 10.00% 10.00% $42,099 $463,087
10.04.03.07.519097 JOINT SEAL ASSEMBLY (MR=5") 531.00 LF $638.00 $338,778 0.00% 10.00% 10.00% $33,878 $372,656
10.04.03.07.520102 BAR REINFORCING STEEL (BRIDGE) 6,798,000.00 LB $1.00 $6,798,000 15.00% 10.00% 25.00% $1,699,500 $8,497,500
10.04.03.07.520122 STRAY CURRENT PROTECTION (BRIDGE) 203,000.00 SF $2.00 $406,000 15.00% 10.00% 25.00% $101,500 $507,500
10.04.03.07.7351xx MINOR CONCRETE (CURB) 38,111.00 LF $28.00 $1,067,108 15.00% 10.00% 25.00% $266,777 $1,333,885
10.04.03.07.750041 ISOLATION CASING 42,500.00 LB $3.00 $127,500 15.00% 10.00% 25.00% $31,875 $159,375
10.04.03.07.750501 MISCELANEOUS METAL (BRIDGE) 5,360.00 LB $4.00 $21,440 15.00% 10.00% 25.00% $5,360 $26,800
10.04.03.07.750505 BRIDGE DECK DRAINAGE SYSTEM 33,600.00 LB $5.00 $168,000 15.00% 10.00% 25.00% $42,000 $210,000
10.04.03.07.833000 METAL RAILING (PIPE) 12,976.00 LF $125.00 $1,622,000 15.00% 10.00% 25.00% $405,500 $2,027,500
Sum
Average
8,360,552.00 $39,471,890
13.33% 10.00% 23.33%
$9,754,007 $49,225,897Summary for Group: 10.04.03.07
Group 10.04.03.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE VIADUCT Contingency
10.04.03.08.192003 STRUCTURE EXCAVATION (BRIDGE) 356.00 CY $60.00 $21,360 15.00% 10.00% 25.00% $5,340 $26,700
10.04.03.08.193003 STRUCTURAL BACKFILL (BRIDGE) 176.00 CY $73.00 $12,848 15.00% 10.00% 25.00% $3,212 $16,060
10.04.03.08.490618 96" CIDH CONCRETE PILING 882.00 LF $1,344.00 $1,185,408 15.00% 10.00% 25.00% $296,352 $1,481,760
10.04.03.08.490620 108" CIDH CONCRETE PILING 1,323.00 LF $1,967.00 $2,602,341 15.00% 10.00% 25.00% $650,585 $3,252,926
10.04.03.08.490622 120" CIDH CONCRETE PILING 147.00 LF $2,310.00 $339,570 15.00% 10.00% 25.00% $84,893 $424,463
10.04.03.08.4906xx 132" CIDH CONCRETE PILING 243.00 LF $2,923.00 $710,289 15.00% 10.00% 25.00% $177,572 $887,861
10.04.03.08.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 982,000.00 LB $1.85 $1,816,700 15.00% 10.00% 25.00% $454,175 $2,270,875
10.04.03.08.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 38.00 CY $440.00 $16,720 15.00% 10.00% 25.00% $4,180 $20,900
10.04.03.08.510053 STRUCTURAL CONCRETE (BRIDGE) 20,000.00 CY $850.00 $17,000,000 15.00% 10.00% 25.00% $4,250,000 $21,250,000
10.04.03.08.511035 ARCHITECT TREATMENT 40,400.00 SF $14.00 $565,600 15.00% 10.00% 25.00% $141,400 $707,000
10.04.03.08.518051 PTFE SPHERICAL BEARING 52.00 EA $6,191.00 $321,932 0.00% 10.00% 10.00% $32,193 $354,125
10.04.03.08.519097 JOINT SEAL ASSEMBLY (MR=5") 438.00 LF $638.00 $279,444 0.00% 10.00% 10.00% $27,944 $307,388
10.04.03.08.520102 BAR REINFORCING STEEL (BRIDGE) 6,800,000.00 LB $1.00 $6,800,000 15.00% 10.00% 25.00% $1,700,000 $8,500,000
10.04.03.08.520122 STRAY CURRENT PROTECTION (BRIDGE) 177,672.00 SF $2.00 $355,344 15.00% 10.00% 25.00% $88,836 $444,180
Monday, January 27, 2014 Page 12 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.04.03.08.7351xx MINOR CONCRETE (CURB) 32,850.00 LF $28.00 $919,800 15.00% 10.00% 25.00% $229,950 $1,149,750
10.04.03.08.750041 ISOLATION CASING 27,500.00 LB $3.00 $82,500 15.00% 10.00% 25.00% $20,625 $103,125
10.04.03.08.750501 MISCELANEOUS METAL (BRIDGE) 4,700.00 LB $4.00 $18,800 15.00% 10.00% 25.00% $4,700 $23,500
10.04.03.08.750505 BRIDGE DECK DRAINAGE SYSTEM 28,900.00 LB $5.00 $144,500 15.00% 10.00% 25.00% $36,125 $180,625
10.04.03.08.833000 METAL RAILING (PIPE) 11,442.00 LF $125.00 $1,430,250 15.00% 10.00% 25.00% $357,563 $1,787,813
Sum
Average
8,129,119.00 $34,623,406
13.42% 10.00% 23.42%
$8,565,645 $43,189,051Summary for Group: 10.04.03.08
Group 10.04.03.09
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BALBOA AVE UP Contingency
10.04.03.09.192003 STRUCTURE EXCAVATION (BRIDGE) 468.00 CY $60.00 $28,080 15.00% 10.00% 25.00% $7,020 $35,100
10.04.03.09.193003 STRUCTURAL BACKFILL (BRIDGE) 311.00 CY $73.00 $22,703 15.00% 10.00% 25.00% $5,676 $28,379
10.04.03.09.490603 24" CIDH CONCRETE PILING 2,520.00 LF $306.00 $771,120 15.00% 10.00% 25.00% $192,780 $963,900
10.04.03.09.490611 72" CIDH CONCRETE PILING 120.00 LF $1,113.00 $133,560 15.00% 10.00% 25.00% $33,390 $166,950
10.04.03.09.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 34,940.00 LB $1.85 $64,639 15.00% 10.00% 25.00% $16,160 $80,799
10.04.03.09.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 227.00 CY $440.00 $99,880 15.00% 10.00% 25.00% $24,970 $124,850
10.04.03.09.510053 STRUCTURAL CONCRETE (BRIDGE) 834.00 CY $850.00 $708,900 15.00% 10.00% 25.00% $177,225 $886,125
10.04.03.09.519094 JOINT SEAL ASSEMBLY (MR=3.5") 85.00 LF $227.00 $19,295 0.00% 10.00% 10.00% $1,930 $21,225
10.04.03.09.520102 BAR REINFORCING STEEL (BRIDGE) 298,000.00 LB $1.00 $298,000 15.00% 10.00% 25.00% $74,500 $372,500
10.04.03.09.520122 STRAY CURRENT PROTECTION (BRIDGE) 9,295.00 SF $2.00 $18,590 15.00% 10.00% 25.00% $4,648 $23,238
10.04.03.09.540104 WATERPROOFING AND COVER 6,875.00 SF $15.00 $103,125 15.00% 10.00% 25.00% $25,781 $128,906
10.04.03.09.7351XX MINOR CONCRETE (CURB) 440.00 LF $28.00 $12,320 15.00% 10.00% 25.00% $3,080 $15,400
10.04.03.09.750505 BRIDGE DECK DRAINAGE SYSTEM 2,300.00 LB $5.00 $11,500 15.00% 10.00% 25.00% $2,875 $14,375
10.04.03.09.833020 CHAIN LINK RAILING 440.00 LF $150.00 $66,000 15.00% 10.00% 25.00% $16,500 $82,500
10.04.03.09.833088 METAL RAILING (PIPE) 220.00 LF $125.00 $27,500 15.00% 10.00% 25.00% $6,875 $34,375
Sum
Average
357,075.00 $2,385,212
14.00% 10.00% 24.00%
$593,409 $2,978,621Summary for Group: 10.04.03.09
Group 10.04.03.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CHARMANT SOUTH BRIDGE Contingency
10.04.03.10.192003 STRUCTURE EXCAVATION (BRIDGE) 320.00 CY $60.00 $19,200 15.00% 10.00% 25.00% $4,800 $24,000
10.04.03.10.193003 STRUCTURAL BACKFILL (BRIDGE) 270.00 CY $73.00 $19,710 15.00% 10.00% 25.00% $4,928 $24,638
10.04.03.10.490605 36" CIDH CONCRETE PILING 590.00 LF $507.00 $299,130 15.00% 10.00% 25.00% $74,783 $373,913
Monday, January 27, 2014 Page 13 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.04.03.10.490618 96" CIDH CONCRETE PILING 80.00 LF $1,344.00 $107,520 15.00% 10.00% 25.00% $26,880 $134,400
10.04.03.10.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 31,500.00 LB $1.85 $58,275 15.00% 10.00% 25.00% $14,569 $72,844
10.04.03.10.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 105.00 CY $440.00 $46,200 15.00% 10.00% 25.00% $11,550 $57,750
10.04.03.10.510053 STRUCTURAL CONCRETE (BRIDGE) 780.00 CY $850.00 $663,000 15.00% 10.00% 25.00% $165,750 $828,750
10.04.03.10.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 15.00 CY $850.00 $12,750 15.00% 10.00% 25.00% $3,188 $15,938
10.04.03.10.511035 ARCHITECT TREATMENT 65.00 SF $14.00 $910 15.00% 10.00% 25.00% $228 $1,138
10.04.03.10.519100 JOINT SEAL ASSEMBLY (MR=2") 62.00 LF $145.00 $8,990 0.00% 10.00% 10.00% $899 $9,889
10.04.03.10.520102 BAR REINFORCING STEEL (BRIDGE) 276,520.00 LB $1.00 $276,520 15.00% 10.00% 25.00% $69,130 $345,650
10.04.03.10.520122 STRAY CURRENT PROTECTION (BRIDGE) 8,695.00 SF $2.00 $17,390 15.00% 10.00% 25.00% $4,348 $21,738
10.04.03.10.7351xx MINOR CONCRETE (CURB) 664.00 LF $28.00 $18,592 15.00% 10.00% 25.00% $4,648 $23,240
10.04.03.10.750505 BRIDGE DECK DRAINAGE SYSTEM 1,113.00 LB $5.00 $5,565 15.00% 10.00% 25.00% $1,391 $6,956
10.04.03.10.833000 METAL RAILING (PIPE) 632.00 LF $125.00 $79,000 15.00% 10.00% 25.00% $19,750 $98,750
Sum
Average
321,411.00 $1,632,752
14.00% 10.00% 24.00%
$406,840 $2,039,592Summary for Group: 10.04.03.10
Group 10.04.03.11
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CHARMANT NORTH BRIDGE Contingency
10.04.03.11.192003 STRUCTURE EXCAVATION (BRIDGE) 286.00 CY $60.00 $17,160 15.00% 10.00% 25.00% $4,290 $21,450
10.04.03.11.193003 STRUCTURAL BACKFILL (BRIDGE) 127.00 CY $73.00 $9,271 15.00% 10.00% 25.00% $2,318 $11,589
10.04.03.11.490605 36" CIDH CONCRETE PILING 600.00 LF $507.00 $304,200 15.00% 10.00% 25.00% $76,050 $380,250
10.04.03.11.490618 96" CIDH CONCRETE PILING 160.00 LF $1,344.00 $215,040 15.00% 10.00% 25.00% $53,760 $268,800
10.04.03.11.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 40,320.00 LB $1.85 $74,592 15.00% 10.00% 25.00% $18,648 $93,240
10.04.03.11.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 72.00 CY $440.00 $31,680 15.00% 10.00% 25.00% $7,920 $39,600
10.04.03.11.510053 STRUCTURAL CONCRETE (BRIDGE) 1,012.00 CY $850.00 $860,200 15.00% 10.00% 25.00% $215,050 $1,075,250
10.04.03.11.511035 ARCHITECT TREATMENT 100.00 SF $14.00 $1,400 15.00% 10.00% 25.00% $350 $1,750
10.04.03.11.519092 JOINT SEAL ASSEMBLY (MR=2.5") 32.00 LF $189.00 $6,048 0.00% 10.00% 10.00% $605 $6,653
10.04.03.11.519093 JOINT SEAL ASSEMBLY (MR=3") 32.00 LF $211.00 $6,752 0.00% 10.00% 10.00% $675 $7,427
10.04.03.11.520102 BAR REINFORCING STEEL (BRIDGE) 392,300.00 LB $1.00 $392,300 15.00% 10.00% 25.00% $98,075 $490,375
10.04.03.11.520122 STRAY CURRENT PROTECTION (BRIDGE) 13,047.00 SF $2.00 $26,094 15.00% 10.00% 25.00% $6,524 $32,618
10.04.03.11.7351xx MINOR CONCRETE (CURB) 879.00 LF $28.00 $24,612 15.00% 10.00% 25.00% $6,153 $30,765
10.04.03.11.750505 BRIDGE DECK DRAINAGE SYSTEM 1,650.00 LB $5.00 $8,250 15.00% 10.00% 25.00% $2,063 $10,313
Monday, January 27, 2014 Page 14 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.04.03.11.833000 METAL RAILING (PIPE) 879.00 LF $125.00 $109,875 15.00% 10.00% 25.00% $27,469 $137,344
Sum
Average
451,496.00 $2,087,474
13.00% 10.00% 23.00%
$519,949 $2,607,423Summary for Group: 10.04.03.11
Group 10.04.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
HYDROMODIFICATION Contingency
10.04.04.601 HYDROMODIFICAITON-UNDERGROUND STORAGE (NOBEL VIADUC 24,104.60 CF $2.45 $59,056 15.00% 15.00% 30.00% $17,717 $76,773
10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (LRT OH BRIDGE) 16,767.40 CF $2.45 $41,080 15.00% 15.00% 30.00% $12,324 $53,404
10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (ROSE CREEK SO 2,405.00 CF $2.45 $5,892 15.00% 15.00% 30.00% $1,768 $7,660
10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (ROSE CREEK NO 2,753.40 CF $2.45 $6,746 15.00% 15.00% 30.00% $2,024 $8,770
10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD VIADUCT) 18,730.40 CF $2.45 $45,889 15.00% 15.00% 30.00% $13,767 $59,656
10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (CHARMANT NO 3,738.80 CF $2.45 $9,160 15.00% 15.00% 30.00% $2,748 $11,908
10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (CHARMANT SO 2,641.60 CF $2.45 $6,472 15.00% 15.00% 30.00% $1,942 $8,413
10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD VIADUCT) 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (NOBEL VIADUCT) 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (CHARMANT NORT 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (CHARMANT SOUT 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (LRT OH BRIDGE) 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (ROSE CREEK SOUT 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (ROSE CREEK NOR 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
Sum
Average
71,148.20 $223,296
15.00% 15.00% 30.00%
$66,989 $290,285Summary for Group: 10.04.04
Sum
Average
28,693,540.20 $133,925,313
13.29% 11.04% 24.32%
$33,295,975 $167,221,288Summary for Sub Section: 10.04
Sub Section 10.06 GUIDEWAY: UNDERGROUND CUT & COVER
Group 10.06.00
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LA JOLLA COLONY OH Contingency
10.06.00.01 FACTOR FOR STAGE CONSTRUCTION (10%) 1.00 LS $418,573.64 $418,574 15.00% 15.00% 30.00% $125,572 $544,146
10.06.00.02 PERMANENT BMP (UNDERGROUND C&C) 1.00 LS $200,000.00 $200,000 0.00% 20.00% 20.00% $40,000 $240,000
10.06.00.480600 TEMPORARY SHORING 22,500.00 SF $70.00 $1,575,000 15.00% 15.00% 30.00% $472,500 $2,047,500
10.06.00.511035 ARCHITECTURAL TREATMENT 5,000.00 SF $14.00 $70,000 15.00% 10.00% 25.00% $17,500 $87,500
10.06.00.520122 STRAY CURRENT PROTECTION 16,238.00 SF $2.00 $32,476 15.00% 10.00% 25.00% $8,119 $40,595
Monday, January 27, 2014 Page 15 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.06.00.540101 ASPHALT MEMBRANE WATERPROOFING 26,091.00 SF $14.00 $365,274 15.00% 15.00% 30.00% $109,582 $474,856
10.06.00.598001 ANTI-GRAFFITI COATING 10,850.00 SF $1.20 $13,020 15.00% 10.00% 25.00% $3,255 $16,275
10.06.00.601 HYDROMODIFICATION-UNDERGROUND STORAGE (LA JOLLA COLO 12,020.00 CF $2.45 $29,449 15.00% 15.00% 30.00% $8,835 $38,284
10.06.00.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (LA JOLLA COLONY 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
10.06.01.192037 STRUCTURE EXCAVATION (U SECTION) 7,878.00 CY $60.00 $472,680 10.00% 10.00% 20.00% $94,536 $567,216
10.06.01.193013 STRUCTURAL BACKFILL (U SECTION) 443.00 CY $73.00 $32,339 10.00% 10.00% 20.00% $6,468 $38,807
10.06.01.510060 STRUCTURAL CONCRETE (U SECTION) 2,211.00 CY $470.00 $1,039,170 10.00% 10.00% 20.00% $207,834 $1,247,004
10.06.01.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 30.00 CY $850.00 $25,500 15.00% 10.00% 25.00% $6,375 $31,875
10.06.01.520103 BAR REINFORCING STEEL (U SECTION) 302,472.00 LB $1.00 $302,472 10.00% 10.00% 20.00% $60,494 $362,966
10.06.01.833020 CHAIN LINK RAILING 495.00 LF $150.00 $74,250 15.00% 10.00% 25.00% $18,563 $92,813
10.06.02.192025 STRUCTURE EXCAVATION (CUT N COVER) 7,270.00 CY $60.00 $436,200 10.00% 10.00% 20.00% $87,240 $523,440
10.06.02.193004 STRUCTURAL BACKFILL (CUT AND COVER) 1,285.00 CY $73.00 $93,805 10.00% 10.00% 20.00% $18,761 $112,566
10.06.02.510090 STRUCTURAL CONCRETE (CUT N COVER) 2,100.00 CY $620.00 $1,302,000 10.00% 10.00% 20.00% $260,400 $1,562,400
10.06.02.520107 BAR REINFORCING STEEL (CUT AND COVER) 309,702.00 LB $1.00 $309,702 10.00% 10.00% 20.00% $61,940 $371,642
Sum
Average
726,588.00 $6,798,911
12.11% 11.84% 23.95%
$1,610,074 $8,408,985Summary for Group: 10.06.00
Sum
Average
726,588.00 $6,798,911
12.11% 11.84% 23.95%
$1,610,074 $8,408,985Summary for Sub Section: 10.06
Sub Section 10.08 GUIDEWAY: RETAINED CUT OR FILL
Group 10.08.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
STRUCTURE EXCAVATION Contingency
10.08.01.211.20 STRUCTURE EXCAVATION 1,360.00 CY $60.00 $81,600 10.00% 10.00% 20.00% $16,320 $97,920
10.08.01.215.20 STRUCTURE EXCAVATION 6,665.00 CY $60.00 $399,900 10.00% 10.00% 20.00% $79,980 $479,880
10.08.01.271.20 STRUCTURE EXCAVATION 2,151.00 CY $60.00 $129,060 10.00% 10.00% 20.00% $25,812 $154,872
10.08.01.332.20 STRUCTURE EXCAVATION 12,645.00 CY $60.00 $758,700 10.00% 10.00% 20.00% $151,740 $910,440
10.08.01.376.20 STRUCTURE EXCAVATION 2,191.00 CY $60.00 $131,460 10.00% 10.00% 20.00% $26,292 $157,752
10.08.01.381.20 STRUCTURE EXCAVATION 373.00 CY $60.00 $22,380 10.00% 10.00% 20.00% $4,476 $26,856
10.08.01.388.20 STRUCTURE EXCAVATION 12,670.00 CY $60.00 $760,200 10.00% 10.00% 20.00% $152,040 $912,240
10.08.01.402.20 STRUCTURE EXCAVATION 5,802.00 CY $60.00 $348,120 10.00% 10.00% 20.00% $69,624 $417,744
10.08.01.416.20 STRUCTURE EXCAVATION 2,346.00 CY $60.00 $140,760 10.00% 10.00% 20.00% $28,152 $168,912
Monday, January 27, 2014 Page 16 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.01.446.20 STRUCTURE EXCAVATION (MSE WALL) 2,972.00 CY $60.00 $178,320 10.00% 10.00% 20.00% $35,664 $213,984
10.08.01.449.20 STRUCTURE EXCAVATION (MSE WALL) 295.00 CY $60.00 $17,700 10.00% 10.00% 20.00% $3,540 $21,240
10.08.01.457.20 STRUCTURE EXCAVATION (MSE WALL) 1,029.00 CY $60.00 $61,740 10.00% 10.00% 20.00% $12,348 $74,088
10.08.01.465.20 STRUCTURE EXCAVATION 9,520.00 CY $60.00 $571,200 10.00% 10.00% 20.00% $114,240 $685,440
10.08.01.472.20 STRUCTURE EXCAVATION (MSE WALL) 2,721.00 CY $60.00 $163,260 10.00% 10.00% 20.00% $32,652 $195,912
10.08.01.475.20 STRUCTURE EXCAVATION (MSE WALL) 267.00 CY $60.00 $16,020 10.00% 10.00% 20.00% $3,204 $19,224
10.08.01.485.20 STRUCTURE EXCAVATION 1,712.00 CY $60.00 $102,720 10.00% 10.00% 20.00% $20,544 $123,264
10.08.01.498L.20 STRUCTURE EXCAVATION 3,980.00 CY $60.00 $238,800 10.00% 10.00% 20.00% $47,760 $286,560
10.08.01.498R.20 STRUCTURE EXCAVATION 6,812.00 CY $60.00 $408,720 10.00% 10.00% 20.00% $81,744 $490,464
10.08.01.500.20 STRUCTURE EXCAVATION (MSE WALL) 5,186.00 CY $60.00 $311,160 10.00% 10.00% 20.00% $62,232 $373,392
10.08.01.507.20 STRUCTURE EXCAVATION 686.00 CY $60.00 $41,160 10.00% 10.00% 20.00% $8,232 $49,392
10.08.01.510.20 STRUCTURE EXCAVATION 211.00 CY $60.00 $12,660 10.00% 10.00% 20.00% $2,532 $15,192
10.08.01.512.20 STRUCTURE EXCAVATION 169.00 CY $60.00 $10,140 10.00% 10.00% 20.00% $2,028 $12,168
10.08.01.516.20 STRUCTURE EXCAVATION 644.00 CY $60.00 $38,640 10.00% 10.00% 20.00% $7,728 $46,368
10.08.01.524.20 STRUCTURE EXCAVATION (MSE WALL) 8,629.00 CY $60.00 $517,740 10.00% 10.00% 20.00% $103,548 $621,288
10.08.01.526.20 STRUCTURE EXCAVATION 2,987.00 CY $60.00 $179,220 10.00% 10.00% 20.00% $35,844 $215,064
10.08.01.547.20 STRUCTURE EXCAVATION 86.00 CY $60.00 $5,160 10.00% 10.00% 20.00% $1,032 $6,192
10.08.01.550.20 STRUCTURE EXCAVATION (MSE WALL) 2,833.00 CY $60.00 $169,980 10.00% 10.00% 20.00% $33,996 $203,976
10.08.01.560.20 STRUCTURE EXCAVATION 2,204.00 CY $60.00 $132,240 10.00% 10.00% 20.00% $26,448 $158,688
10.08.01.580.20 STRUCTURE EXCAVATION 13,690.00 CY $60.00 $821,400 10.00% 10.00% 20.00% $164,280 $985,680
10.08.01.592.20 STRUCTURE EXCAVATION 722.00 CY $60.00 $43,320 10.00% 10.00% 20.00% $8,664 $51,984
10.08.01.598L.20 STRUCTURE EXCAVATION 247.00 CY $60.00 $14,820 10.00% 10.00% 20.00% $2,964 $17,784
10.08.01.598R.20 STRUCTURE EXCAVATION 554.00 CY $60.00 $33,240 10.00% 10.00% 20.00% $6,648 $39,888
10.08.01.648.20 STRUCTURE EXCAVATION 3,739.00 CY $60.00 $224,340 10.00% 10.00% 20.00% $44,868 $269,208
Sum
Average
118,098.00 $7,085,880
10.00% 10.00% 20.00%
$1,417,176 $8,503,056Summary for Group: 10.08.01
Group 10.08.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
STRUCTURAL BACKFILL Contingency
10.08.07.00 STRUCTURAL BACKFILL (MSE WALL) 2,100.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
10.08.07.211.10 STRUCTURAL BACKFILL 1,111.00 CY $52.00 $57,772 10.00% 10.00% 20.00% $11,554 $69,326
Monday, January 27, 2014 Page 17 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.07.215.10 STRUCTURAL BACKFILL 5,359.00 CY $52.00 $278,668 10.00% 10.00% 20.00% $55,734 $334,402
10.08.07.271.10 STRUCTURAL BACKFILL 1,504.00 CY $52.00 $78,208 10.00% 10.00% 20.00% $15,642 $93,850
10.08.07.332.10 STRUCTURAL BACKFILL 9,666.00 CY $52.00 $502,632 10.00% 10.00% 20.00% $100,526 $603,158
10.08.07.376.10 STRUCTURAL BACKFILL 1,559.00 CY $52.00 $81,068 10.00% 10.00% 20.00% $16,214 $97,282
10.08.07.381.10 STRUCTURAL BACKFILL 238.00 CY $52.00 $12,376 10.00% 10.00% 20.00% $2,475 $14,851
10.08.07.388.10 STRUCTURAL BACKFILL 9,094.00 CY $52.00 $472,888 10.00% 10.00% 20.00% $94,578 $567,466
10.08.07.402.10 STRUCTURAL BACKFILL 3,752.00 CY $52.00 $195,104 10.00% 10.00% 20.00% $39,021 $234,125
10.08.07.416.10 STRUCTURAL BACKFILL 1,653.00 CY $52.00 $85,956 10.00% 10.00% 20.00% $17,191 $103,147
10.08.07.446.10 STRUCTURAL BACKFILL (MSE WALL) 5,174.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
10.08.07.449.10 STRUCTURAL BACKFILL (MSE WALL) 872.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
10.08.07.457.10 STRUCTURAL BACKFILL (MSE WALL) 2,322.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
10.08.07.465.10 STRUCTURAL BACKFILL 7,219.00 CY $52.00 $375,388 10.00% 10.00% 20.00% $75,078 $450,466
10.08.07.472.10 STRUCTURAL BACKFILL (MSE WALL) 10,045.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
10.08.07.475.10 STRUCTURAL BACKFILL (MSE WALL) 777.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
10.08.07.485.10 STRUCTURAL BACKFILL 1,211.00 CY $52.00 $62,972 10.00% 10.00% 20.00% $12,594 $75,566
10.08.07.498L.10 STRUCTURAL BACKFILL 3,035.00 CY $52.00 $157,820 10.00% 10.00% 20.00% $31,564 $189,384
10.08.07.498R.10 STRUCTURAL BACKFILL 5,011.00 CY $52.00 $260,572 10.00% 10.00% 20.00% $52,114 $312,686
10.08.07.500.10 STRUCTURAL BACKFILL (MSE WALL) 13,366.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
10.08.07.507.10 STRUCTURAL BACKFILL 418.00 CY $52.00 $21,736 10.00% 10.00% 20.00% $4,347 $26,083
10.08.07.510.10 STRUCTURAL BACKFILL 152.00 CY $52.00 $7,904 10.00% 10.00% 20.00% $1,581 $9,485
10.08.07.512.10 STRUCTURAL BACKFILL 116.00 CY $52.00 $6,032 10.00% 10.00% 20.00% $1,206 $7,238
10.08.07.516.10 STRUCTURAL BACKFILL 382.00 CY $52.00 $19,864 10.00% 10.00% 20.00% $3,973 $23,837
10.08.07.524.10 STRUCTURAL BACKFILL (MSE WALL) 12,558.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
10.08.07.526.10 STRUCTURAL BACKFILL 2,114.00 CY $52.00 $109,928 10.00% 10.00% 20.00% $21,986 $131,914
10.08.07.547.10 STRUCTURAL BACKFILL 66.00 CY $52.00 $3,432 10.00% 10.00% 20.00% $686 $4,118
10.08.07.550.10 STRUCTURAL BACKFILL (MSE WALL) 3,909.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
10.08.07.560.10 STRUCTURAL BACKFILL 1,559.00 CY $52.00 $81,068 10.00% 10.00% 20.00% $16,214 $97,282
10.08.07.580.10 STRUCTURAL BACKFILL 18,454.00 CY $52.00 $959,608 10.00% 10.00% 20.00% $191,922 $1,151,530
10.08.07.592.10 STRUCTURAL BACKFILL 792.00 CY $52.00 $41,184 10.00% 10.00% 20.00% $8,237 $49,421
Monday, January 27, 2014 Page 18 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.07.598L.10 STRUCTURAL BACKFILL 224.00 CY $52.00 $11,648 10.00% 10.00% 20.00% $2,330 $13,978
10.08.07.598R.10 STRUCTURAL BACKFILL 668.00 CY $52.00 $34,736 10.00% 10.00% 20.00% $6,947 $41,683
10.08.07.648.10 STRUCTURAL BACKFILL 5,448.00 CY $52.00 $283,296 10.00% 10.00% 20.00% $56,659 $339,955
Sum
Average
131,928.00 $4,201,860
10.00% 10.00% 20.00%
$840,372 $5,042,232Summary for Group: 10.08.07
Group 10.08.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PERVIOUS BACKFILL Contingency
10.08.08.211.30 PERVIOUS BACKFILL 69.00 CY $49.00 $3,381 10.00% 10.00% 20.00% $676 $4,057
10.08.08.215.30 PERVIOUS BACKFILL 408.00 CY $49.00 $19,992 10.00% 10.00% 20.00% $3,998 $23,990
10.08.08.271.30 PERVIOUS BACKFILL 159.00 CY $49.00 $7,791 10.00% 10.00% 20.00% $1,558 $9,349
10.08.08.332.30 PERVIOUS BACKFILL 746.00 CY $49.00 $36,554 10.00% 10.00% 20.00% $7,311 $43,865
10.08.08.376.30 PERVIOUS BACKFILL 190.00 CY $49.00 $9,310 10.00% 10.00% 20.00% $1,862 $11,172
10.08.08.381.30 PERVIOUS BACKFILL 33.00 CY $49.00 $1,617 10.00% 10.00% 20.00% $323 $1,940
10.08.08.388.30 PERVIOUS BACKFILL 512.00 CY $49.00 $25,088 10.00% 10.00% 20.00% $5,018 $30,106
10.08.08.402.30 PERVIOUS BACKFILL 413.00 CY $49.00 $20,237 10.00% 10.00% 20.00% $4,047 $24,284
10.08.08.416.30 PERVIOUS BACKFILL 101.00 CY $49.00 $4,949 10.00% 10.00% 20.00% $990 $5,939
10.08.08.465.30 PERVIOUS BACKFILL 311.00 CY $49.00 $15,239 10.00% 10.00% 20.00% $3,048 $18,287
10.08.08.485.30 PERVIOUS BACKFILL 71.00 CY $49.00 $3,479 10.00% 10.00% 20.00% $696 $4,175
10.08.08.498L.30 PERVIOUS BACKFILL 281.00 CY $49.00 $13,769 10.00% 10.00% 20.00% $2,754 $16,523
10.08.08.498R.30 PERVIOUS BACKFILL 530.00 CY $49.00 $25,970 10.00% 10.00% 20.00% $5,194 $31,164
10.08.08.507.30 PERVIOUS BACKFILL 35.00 CY $49.00 $1,715 10.00% 10.00% 20.00% $343 $2,058
10.08.08.510.30 PERVIOUS BACKFILL 12.00 CY $49.00 $588 10.00% 10.00% 20.00% $118 $706
10.08.08.512.30 PERVIOUS BACKFILL 10.00 CY $49.00 $490 10.00% 10.00% 20.00% $98 $588
10.08.08.516.30 PERVIOUS BACKFILL 33.00 CY $49.00 $1,617 10.00% 10.00% 20.00% $323 $1,940
10.08.08.526.30 PERVIOUS BACKFILL 198.00 CY $49.00 $9,702 10.00% 10.00% 20.00% $1,940 $11,642
10.08.08.547.30 PERVIOUS BACKFILL 11.00 CY $49.00 $539 10.00% 10.00% 20.00% $108 $647
10.08.08.560.30 PERVIOUS BACKFILL 123.00 CY $49.00 $6,027 10.00% 10.00% 20.00% $1,205 $7,232
10.08.08.580.30 PERVIOUS BACKFILL 1,584.00 CY $49.00 $77,616 10.00% 10.00% 20.00% $15,523 $93,139
10.08.08.592.30 PERVIOUS BACKFILL 90.00 CY $49.00 $4,410 10.00% 10.00% 20.00% $882 $5,292
10.08.08.598L.30 PERVIOUS BACKFILL 25.00 CY $49.00 $1,225 10.00% 10.00% 20.00% $245 $1,470
Monday, January 27, 2014 Page 19 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.08.598R.30 PERVIOUS BACKFILL 70.00 CY $49.00 $3,430 10.00% 10.00% 20.00% $686 $4,116
10.08.08.648.30 PERVIOUS BACKFILL 472.00 CY $49.00 $23,128 10.00% 10.00% 20.00% $4,626 $27,754
Sum
Average
6,487.00 $317,863
10.00% 10.00% 20.00%
$63,573 $381,436Summary for Group: 10.08.08
Group 10.08.09
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
STRUCTURAL CONCRETE Contingency
10.08.09.211.40 STRUCTURAL CONCRETE (RETAINING WALL) 306.00 CY $470.00 $143,820 10.00% 10.00% 20.00% $28,764 $172,584
10.08.09.215.40 STRUCTURAL CONCRETE (RETAINING WALL) 1,564.00 CY $470.00 $735,080 10.00% 10.00% 20.00% $147,016 $882,096
10.08.09.271.40 STRUCTURAL CONCRETE (RETAINING WALL) 773.00 CY $470.00 $363,310 10.00% 10.00% 20.00% $72,662 $435,972
10.08.09.332.40 STRUCTURAL CONCRETE (RETAINING WALL) 3,165.00 CY $470.00 $1,487,550 10.00% 10.00% 20.00% $297,510 $1,785,060
10.08.09.376.40 STRUCTURAL CONCRETE (RETAINING WALL) 708.00 CY $470.00 $332,760 10.00% 10.00% 20.00% $66,552 $399,312
10.08.09.381.40 STRUCTURAL CONCRETE (RETAINING WALL) 188.00 CY $470.00 $88,360 10.00% 10.00% 20.00% $17,672 $106,032
10.08.09.388.40 STRUCTURAL CONCRETE (RETAINING WALL) 3,613.00 CY $470.00 $1,698,110 10.00% 10.00% 20.00% $339,622 $2,037,732
10.08.09.402.40 STRUCTURAL CONCRETE (RETAINING WALL) 2,278.00 CY $470.00 $1,070,660 10.00% 10.00% 20.00% $214,132 $1,284,792
10.08.09.416.40 STRUCTURAL CONCRETE (RETAINING WALL) 759.00 CY $470.00 $356,730 10.00% 10.00% 20.00% $71,346 $428,076
10.08.09.465.40 STRUCTURAL CONCRETE (RETAINING WALL) 2,529.00 CY $470.00 $1,188,630 10.00% 10.00% 20.00% $237,726 $1,426,356
10.08.09.485.40 STRUCTURAL CONCRETE (RETAINING WALL) 525.00 CY $470.00 $246,750 10.00% 10.00% 20.00% $49,350 $296,100
10.08.09.498L.40 STRUCTURAL CONCRETE (RETAINING WALL) 1,106.00 CY $470.00 $519,820 10.00% 10.00% 20.00% $103,964 $623,784
10.08.09.498R.40 STRUCTURAL CONCRETE (RETAINING WALL) 2,359.00 CY $470.00 $1,108,730 10.00% 10.00% 20.00% $221,746 $1,330,476
10.08.09.507.40 STRUCTURAL CONCRETE (RETAINING WALL) 182.00 CY $470.00 $85,540 10.00% 10.00% 20.00% $17,108 $102,648
10.08.09.510.40 STRUCTURAL CONCRETE (RETAINING WALL) 62.00 CY $470.00 $29,140 10.00% 10.00% 20.00% $5,828 $34,968
10.08.09.512.40 STRUCTURAL CONCRETE (RETAINING WALL) 49.00 CY $470.00 $23,030 10.00% 10.00% 20.00% $4,606 $27,636
10.08.09.516.40 STRUCTURAL CONCRETE (RETAINING WALL) 167.00 CY $470.00 $78,490 10.00% 10.00% 20.00% $15,698 $94,188
10.08.09.526.40 STRUCTURAL CONCRETE (RETAINING WALL) 809.00 CY $470.00 $380,230 10.00% 10.00% 20.00% $76,046 $456,276
10.08.09.547.40 STRUCTURAL CONCRETE (RETAINING WALL) 56.00 CY $470.00 $26,320 10.00% 10.00% 20.00% $5,264 $31,584
10.08.09.560.40 STRUCTURAL CONCRETE (RETAINING WALL) 684.00 CY $470.00 $321,480 10.00% 10.00% 20.00% $64,296 $385,776
10.08.09.580.40 STRUCTURAL CONCRETE (RETAINING WALL) 7,152.00 CY $470.00 $3,361,440 10.00% 10.00% 20.00% $672,288 $4,033,728
10.08.09.582.40 STRUCTURAL CONCRETE (RETAINING WALL) 350.00 CY $470.00 $164,500 10.00% 10.00% 20.00% $32,900 $197,400
10.08.09.598L.40 STRUCTURAL CONCRETE (RETAINING WALL) 106.00 CY $470.00 $49,820 10.00% 10.00% 20.00% $9,964 $59,784
10.08.09.598R.40 STRUCTURAL CONCRETE (RETAINING WALL) 254.00 CY $470.00 $119,380 10.00% 10.00% 20.00% $23,876 $143,256
Monday, January 27, 2014 Page 20 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.09.648.40 STRUCTURAL CONCRETE (RETAINING WALL) 2,172.00 CY $470.00 $1,020,840 10.00% 10.00% 20.00% $204,168 $1,225,008
Sum
Average
31,916.00 $15,000,520
10.00% 10.00% 20.00%
$3,000,104 $18,000,624Summary for Group: 10.08.09
Group 10.08.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BAR REINFORCING STEEL (RETAINING WALL) Contingency
10.08.10.211.60 BAR REINFORCING STEEL 38,614.00 LB $1.00 $38,614 10.00% 10.00% 20.00% $7,723 $46,337
10.08.10.215.60 BAR REINFORCING STEEL 186,260.00 LB $1.00 $186,260 10.00% 10.00% 20.00% $37,252 $223,512
10.08.10.271.60 BAR REINFORCING STEEL 93,098.00 LB $1.00 $93,098 10.00% 10.00% 20.00% $18,620 $111,718
10.08.10.332.60 BAR REINFORCING STEEL 508,332.00 LB $1.00 $508,332 10.00% 10.00% 20.00% $101,666 $609,998
10.08.10.376.60 BAR REINFORCING STEEL 84,988.00 LB $1.00 $84,988 10.00% 10.00% 20.00% $16,998 $101,986
10.08.10.381.60 BAR REINFORCING STEEL 24,349.00 LB $1.00 $24,349 10.00% 10.00% 20.00% $4,870 $29,219
10.08.10.388.60 BAR REINFORCING STEEL 400,965.00 LB $1.00 $400,965 10.00% 10.00% 20.00% $80,193 $481,158
10.08.10.402.60 BAR REINFORCING STEEL 463,226.00 LB $1.00 $463,226 10.00% 10.00% 20.00% $92,645 $555,871
10.08.10.416.60 BAR REINFORCING STEEL 62,851.00 LB $1.00 $62,851 10.00% 10.00% 20.00% $12,570 $75,421
10.08.10.465.60 BAR REINFORCING STEEL 210,009.00 LB $1.00 $210,009 10.00% 10.00% 20.00% $42,002 $252,011
10.08.10.485.60 BAR REINFORCING STEEL 42,113.00 LB $1.00 $42,113 10.00% 10.00% 20.00% $8,423 $50,536
10.08.10.498L.60 BAR REINFORCING STEEL 216,106.00 LB $1.00 $216,106 10.00% 10.00% 20.00% $43,221 $259,327
10.08.10.498R.60 BAR REINFORCING STEEL 414,163.00 LB $1.00 $414,163 10.00% 10.00% 20.00% $82,833 $496,996
10.08.10.507.60 BAR REINFORCING STEEL 16,773.00 LB $1.00 $16,773 10.00% 10.00% 20.00% $3,355 $20,128
10.08.10.510.60 BAR REINFORCING STEEL 5,858.00 LB $1.00 $5,858 10.00% 10.00% 20.00% $1,172 $7,030
10.08.10.512.60 BAR REINFORCING STEEL 4,679.00 LB $1.00 $4,679 10.00% 10.00% 20.00% $936 $5,615
10.08.10.516.60 BAR REINFORCING STEEL 15,731.00 LB $1.00 $15,731 10.00% 10.00% 20.00% $3,146 $18,877
10.08.10.526.60 BAR REINFORCING STEEL 94,255.00 LB $1.00 $94,255 10.00% 10.00% 20.00% $18,851 $113,106
10.08.10.547.60 BAR REINFORCING STEEL 5,026.00 LB $1.00 $5,026 10.00% 10.00% 20.00% $1,005 $6,031
10.08.10.560.60 BAR REINFORCING STEEL 91,479.00 LB $1.00 $91,479 10.00% 10.00% 20.00% $18,296 $109,775
10.08.10.580.60 BAR REINFORCING STEEL 781,440.00 LB $1.00 $781,440 10.00% 10.00% 20.00% $156,288 $937,728
10.08.10.592.60 BAR REINFORCING STEEL 53,908.00 LB $1.00 $53,908 10.00% 10.00% 20.00% $10,782 $64,690
10.08.10.598L.60 BAR REINFORCING STEEL 13,490.00 LB $1.00 $13,490 10.00% 10.00% 20.00% $2,698 $16,188
10.08.10.598R.60 BAR REINFORCING STEEL 47,505.00 LB $1.00 $47,505 10.00% 10.00% 20.00% $9,501 $57,006
10.08.10.648.60 BAR REINFORCING STEEL 237,135.00 LB $1.00 $237,135 10.00% 10.00% 20.00% $47,427 $284,562
Monday, January 27, 2014 Page 21 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
4,112,353.00 $4,112,353
10.00% 10.00% 20.00%
$822,471 $4,934,824Summary for Group: 10.08.10
Group 10.08.11
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MSE WALL Contingency
10.08.11.00 EARTH RETAINING STRUCTURE (MSE WALL-TEMP SHOOFLY) 9,060.00 SF $82.00 $742,920 10.00% 10.00% 20.00% $148,584 $891,504
10.08.11.446.91 EARTH RETAINING STRUCTURE (MSE WALL) 16,439.00 SF $72.00 $1,183,608 10.00% 10.00% 20.00% $236,722 $1,420,330
10.08.11.449.91 EARTH RETAINING STRUCTURE (MSE WALL) 2,598.00 SF $72.00 $187,056 10.00% 10.00% 20.00% $37,411 $224,467
10.08.11.457.91 EARTH RETAINING STRUCTURE (MSE WALL) 6,490.00 SF $72.00 $467,280 10.00% 10.00% 20.00% $93,456 $560,736
10.08.11.472.91 EARTH RETAINING STRUCTURE (MSE WALL) 16,060.00 SF $72.00 $1,156,320 10.00% 10.00% 20.00% $231,264 $1,387,584
10.08.11.475.91 EARTH RETAINING STRUCTURE (MSE WALL) 2,801.00 SF $72.00 $201,672 10.00% 10.00% 20.00% $40,334 $242,006
10.08.11.500.91 EARTH RETAINING STRUCTURE (MSE WALL) 28,658.00 SF $72.00 $2,063,376 10.00% 10.00% 20.00% $412,675 $2,476,051
10.08.11.524.91 EARTH RETAINING STRUCTURE (MSE WALL) 30,752.00 SF $72.00 $2,214,144 10.00% 10.00% 20.00% $442,829 $2,656,973
10.08.11.550.91 EARTH RETAINING STRUCTURE (MSE WALL) 5,649.00 SF $72.00 $406,728 10.00% 10.00% 20.00% $81,346 $488,074
Sum
Average
118,507.00 $8,623,104
10.00% 10.00% 20.00%
$1,724,621 $10,347,725Summary for Group: 10.08.11
Group 10.08.13
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PERMANENT BMP (RETAINED CUT/FILL) Contingency
10.08.13 PERMANENT BMP (RETAINED CUT/FILL) 1.00 LS $1,550,000.00 $1,550,000 0.00% 20.00% 20.00% $310,000 $1,860,000
Sum
Average
1.00 $1,550,000
0.00% 20.00% 20.00%
$310,000 $1,860,000Summary for Group: 10.08.13
Group 10.08.17
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MINOR CONCRETE (RETAINING WALL) Contingency
10.08.17.446.70 MINOR CONCRETE (COPING) 117.00 CY $365.00 $42,705 10.00% 10.00% 20.00% $8,541 $51,246
10.08.17.449.70 MINOR CONCRETE (COPING) 17.00 CY $365.00 $6,205 10.00% 10.00% 20.00% $1,241 $7,446
10.08.17.457.70 MINOR CONCRETE (COPING) 34.00 CY $365.00 $12,410 10.00% 10.00% 20.00% $2,482 $14,892
10.08.17.472.70 MINOR CONCRETE (COPING) 57.00 CY $365.00 $20,805 10.00% 10.00% 20.00% $4,161 $24,966
10.08.17.475.70 MINOR CONCRETE (COPING) 20.00 CY $365.00 $7,300 10.00% 10.00% 20.00% $1,460 $8,760
10.08.17.500.70 MINOR CONCRETE (COPING) 137.00 CY $365.00 $50,005 10.00% 10.00% 20.00% $10,001 $60,006
10.08.17.509.70 MINOR CONCRETE (GUTTER) 7.00 CY $365.00 $2,555 10.00% 10.00% 20.00% $511 $3,066
10.08.17.509.70 MINOR CONCRETE (SLOPE PAVING) 22.00 CY $365.00 $8,030 10.00% 10.00% 20.00% $1,606 $9,636
10.08.17.514.70 MINOR CONCRETE (SLOPE PAVING) 24.00 CY $365.00 $8,760 10.00% 10.00% 20.00% $1,752 $10,512
10.08.17.514.70 MINOR CONCRETE (GUTTER) 10.00 CY $365.00 $3,650 10.00% 10.00% 20.00% $730 $4,380
Monday, January 27, 2014 Page 22 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.17.524.70 MINOR CONCRETE (COPING) 162.00 CY $365.00 $59,130 10.00% 10.00% 20.00% $11,826 $70,956
10.08.17.550.70 MINOR CONCRETE (COPING) 23.00 CY $365.00 $8,395 10.00% 10.00% 20.00% $1,679 $10,074
Sum
Average
630.00 $229,950
10.00% 10.00% 20.00%
$45,990 $275,940Summary for Group: 10.08.17
Group 10.08.18
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CABLE RAILING Contingency
10.08.18.00 TEMPORARY RAILING - SHOOFLY 906.00 LF $25.00 $22,650 20.00% 10.00% 30.00% $6,795 $29,445
10.08.18.211.70 CABLE RAILING 359.00 LF $25.00 $8,975 10.00% 10.00% 20.00% $1,795 $10,770
10.08.18.215.70 CABLE RAILING 1,439.00 LF $25.00 $35,975 10.00% 10.00% 20.00% $7,195 $43,170
10.08.18.271.70 CABLE RAILING 822.00 LF $25.00 $20,550 10.00% 10.00% 20.00% $4,110 $24,660
10.08.18.332.70 CABLE RAILING 2,613.00 LF $25.00 $65,325 10.00% 10.00% 20.00% $13,065 $78,390
10.08.18.376.70 CABLE RAILING 193.00 LF $25.00 $4,825 10.00% 10.00% 20.00% $965 $5,790
10.08.18.381.70 CABLE RAILING 261.00 LF $25.00 $6,525 10.00% 10.00% 20.00% $1,305 $7,830
10.08.18.388.70 CABLE RAILING 1,242.00 LF $25.00 $31,050 10.00% 10.00% 20.00% $6,210 $37,260
10.08.18.402.70 CABLE RAILING 1,023.00 LF $25.00 $25,575 10.00% 10.00% 20.00% $5,115 $30,690
10.08.18.416.70 CABLE RAILING 450.00 LF $25.00 $11,250 10.00% 10.00% 20.00% $2,250 $13,500
10.08.18.446.70 CABLE RAILING 1,652.00 LF $25.00 $41,300 10.00% 10.00% 20.00% $8,260 $49,560
10.08.18.449.70 CABLE RAILING 233.00 LF $25.00 $5,825 10.00% 10.00% 20.00% $1,165 $6,990
10.08.18.457.70 CABLE RAILING 484.00 LF $25.00 $12,100 10.00% 10.00% 20.00% $2,420 $14,520
10.08.18.465.70 CABLE RAILING 1,416.00 LF $25.00 $35,400 10.00% 10.00% 20.00% $7,080 $42,480
10.08.18.472.70 CABLE RAILING 806.00 LF $25.00 $20,150 10.00% 10.00% 20.00% $4,030 $24,180
10.08.18.475.70 CABLE RAILING 276.00 LF $25.00 $6,900 10.00% 10.00% 20.00% $1,380 $8,280
10.08.18.485.70 CABLE RAILING 319.00 LF $25.00 $7,975 10.00% 10.00% 20.00% $1,595 $9,570
10.08.18.498L.70 CABLE RAILING 513.00 LF $25.00 $12,825 10.00% 10.00% 20.00% $2,565 $15,390
10.08.18.498R.70 CABLE RAILING 1,240.00 LF $25.00 $31,000 10.00% 10.00% 20.00% $6,200 $37,200
10.08.18.500.70 CABLE RAILING 1,925.00 LF $25.00 $48,125 10.00% 10.00% 20.00% $9,625 $57,750
10.08.18.507.70 CABLE RAILING 144.00 LF $25.00 $3,600 10.00% 10.00% 20.00% $720 $4,320
10.08.18.510.70 CABLE RAILING 40.00 LF $25.00 $1,000 10.00% 10.00% 20.00% $200 $1,200
10.08.18.512.70 CABLE RAILING 32.00 LF $25.00 $800 10.00% 10.00% 20.00% $160 $960
10.08.18.516.70 CABLE RAILING 128.00 LF $25.00 $3,200 10.00% 10.00% 20.00% $640 $3,840
Monday, January 27, 2014 Page 23 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.18.524.70 CABLE RAILING 2,283.00 LF $25.00 $57,075 10.00% 10.00% 20.00% $11,415 $68,490
10.08.18.526.70 CABLE RAILING 749.00 LF $25.00 $18,725 10.00% 10.00% 20.00% $3,745 $22,470
10.08.18.547.70 CABLE RAILING 53.00 LF $25.00 $1,325 10.00% 10.00% 20.00% $265 $1,590
10.08.18.550.70 CABLE RAILING 323.00 LF $25.00 $8,075 10.00% 10.00% 20.00% $1,615 $9,690
10.08.18.560.70 CABLE RAILING 781.00 LF $25.00 $19,525 10.00% 10.00% 20.00% $3,905 $23,430
10.08.18.580.70 CABLE RAILING 852.00 LF $25.00 $21,300 10.00% 10.00% 20.00% $4,260 $25,560
10.08.18.592.70 CABLE RAILING 243.00 LF $25.00 $6,075 10.00% 10.00% 20.00% $1,215 $7,290
10.08.18.598L.70 CABLE RAILING 128.00 LF $25.00 $3,200 10.00% 10.00% 20.00% $640 $3,840
10.08.18.598R.70 CABLE RAILING 128.00 LF $25.00 $3,200 10.00% 10.00% 20.00% $640 $3,840
Sum
Average
24,056.00 $601,400
10.30% 10.00% 20.30%
$122,545 $723,945Summary for Group: 10.08.18
Group 10.08.19
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ARCHITECTURAL TREATMENT Contingency
10.08.19.211.50 ARCHITECTURAL TREATMENT 1,077.00 SF $14.00 $15,078 10.00% 10.00% 20.00% $3,016 $18,094
10.08.19.215.50 ARCHITECTURAL TREATMENT 4,317.00 SF $14.00 $60,438 10.00% 10.00% 20.00% $12,088 $72,526
10.08.19.271.50 ARCHITECTURAL TREATMENT 2,466.00 SF $14.00 $34,524 10.00% 10.00% 20.00% $6,905 $41,429
10.08.19.332.50 ARCHITECTURAL TREATMENT 7,839.00 SF $14.00 $109,746 10.00% 10.00% 20.00% $21,949 $131,695
10.08.19.376.50 ARCHITECTURAL TREATMENT 1,824.00 SF $14.00 $25,536 10.00% 10.00% 20.00% $5,107 $30,643
10.08.19.381.50 ARCHITECTURAL TREATMENT 783.00 SF $14.00 $10,962 10.00% 10.00% 20.00% $2,192 $13,154
10.08.19.388.50 ARCHITECTURAL TREATMENT 3,727.00 SF $14.00 $52,178 10.00% 10.00% 20.00% $10,436 $62,614
10.08.19.402.50 ARCHITECTURAL TREATMENT 15,975.00 SF $14.00 $223,650 10.00% 10.00% 20.00% $44,730 $268,380
10.08.19.416.50 ARCHITECTURAL TREATMENT 1,350.00 SF $14.00 $18,900 10.00% 10.00% 20.00% $3,780 $22,680
10.08.19.446.50 ARCHITECTURAL TREATMENT (MSE WALL) 16,439.00 SF $4.00 $65,756 10.00% 10.00% 20.00% $13,151 $78,907
10.08.19.449.50 ARCHITECTURAL TREATMENT (MSE WALL) 2,598.00 SF $4.00 $10,392 10.00% 10.00% 20.00% $2,078 $12,470
10.08.19.457.50 ARCHITECTURAL TREATMENT (MSE WALL) 6,490.00 SF $4.00 $25,960 10.00% 10.00% 20.00% $5,192 $31,152
10.08.19.465.50 ARCHITECTURAL TREATMENT 5,232.00 SF $14.00 $73,248 10.00% 10.00% 20.00% $14,650 $87,898
10.08.19.472.50 ARCHITECTURAL TREATMENT (MSE WALL) 16,060.00 SF $4.00 $64,240 10.00% 10.00% 20.00% $12,848 $77,088
10.08.19.475.50 ARCHITECTURAL TREATMENT (MSE WALL) 2,801.00 SF $4.00 $11,204 10.00% 10.00% 20.00% $2,241 $13,445
10.08.19.485.50 ARCHITECTURAL TREATMENT 956.00 SF $14.00 $13,384 10.00% 10.00% 20.00% $2,677 $16,061
10.08.19.498L.50 ARCHITECTURAL TREATMENT 1,538.00 SF $14.00 $21,532 10.00% 10.00% 20.00% $4,306 $25,838
Monday, January 27, 2014 Page 24 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.19.498R.50 ARCHITECTURAL TREATMENT 3,719.00 SF $14.00 $52,066 10.00% 10.00% 20.00% $10,413 $62,479
10.08.19.500.50 ARCHITECTURAL TREATMENT (MSE WALL) 28,658.00 SF $4.00 $114,632 10.00% 10.00% 20.00% $22,926 $137,558
10.08.19.507.50 ARCHITECTURAL TREATMENT 1,171.00 SF $14.00 $16,394 10.00% 10.00% 20.00% $3,279 $19,673
10.08.19.510.50 ARCHITECTURAL TREATMENT 353.00 SF $14.00 $4,942 10.00% 10.00% 20.00% $988 $5,930
10.08.19.512.50 ARCHITECTURAL TREATMENT 290.00 SF $14.00 $4,060 10.00% 10.00% 20.00% $812 $4,872
10.08.19.516.50 ARCHITECTURAL TREATMENT 1,036.00 SF $14.00 $14,504 10.00% 10.00% 20.00% $2,901 $17,405
10.08.19.524.50 ARCHITECTURAL TREATMENT (MSE WALL) 30,752.00 SF $4.00 $123,008 10.00% 10.00% 20.00% $24,602 $147,610
10.08.19.526.50 ARCHITECTURAL TREATMENT 7,965.00 LB $14.00 $111,510 10.00% 10.00% 20.00% $22,302 $133,812
10.08.19.547.50 ARCHITECTURAL TREATMENT 159.00 SF $14.00 $2,226 10.00% 10.00% 20.00% $445 $2,671
10.08.19.550.50 ARCHITECTURAL TREATMENT (MSE WALL) 5,649.00 SF $4.00 $22,596 10.00% 10.00% 20.00% $4,519 $27,115
10.08.19.560.50 ARCHITECTURAL TREATMENT 2,344.00 SF $14.00 $32,816 10.00% 10.00% 20.00% $6,563 $39,379
10.08.19.580.50 ARCHITECTURAL TREATMENT 46,862.00 SF $14.00 $656,068 10.00% 10.00% 20.00% $131,214 $787,282
10.08.19.592.50 ARCHITECTURAL TREATMENT 3,281.00 SF $14.00 $45,934 10.00% 10.00% 20.00% $9,187 $55,121
10.08.19.598L.50 ARCHITECTURAL TREATMENT 1,114.00 SF $14.00 $15,596 10.00% 10.00% 20.00% $3,119 $18,715
10.08.19.598R.50 ARCHITECTURAL TREATMENT 2,341.00 SF $14.00 $32,774 10.00% 10.00% 20.00% $6,555 $39,329
10.08.19.648.50 ARCHITECTURAL TREATMENT 14,586.00 SF $14.00 $204,204 10.00% 10.00% 20.00% $40,841 $245,045
Sum
Average
241,752.00 $2,290,058
10.00% 10.00% 20.00%
$458,012 $2,748,070Summary for Group: 10.08.19
Group 10.08.21
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GUIDEWAY EXCAVATION Contingency
10.08.21.190101 GUIDEWAY EXCAVATION 21,718.00 CY $18.00 $390,924 10.00% 5.00% 15.00% $58,639 $449,563
10.08.21.190101 GUIDEWAY EXCAVATION 19,564.00 CY $18.00 $352,152 10.00% 5.00% 15.00% $52,823 $404,975
10.08.21.190101 GUIDEWAY EXCAVATION 19,250.00 CY $18.00 $346,500 10.00% 5.00% 15.00% $51,975 $398,475
10.08.21.190101 GUIDEWAY EXCAVATION 3,798.45 CY $18.00 $68,372 10.00% 5.00% 15.00% $10,256 $78,628
Sum
Average
64,330.45 $1,157,948
10.00% 5.00% 15.00%
$173,692 $1,331,640Summary for Group: 10.08.21
Group 10.08.26
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CHAIN LINK FENCE Contingency
10.08.26 CHAIN LINK FENCE (CL-7) 820.00 LF $24.00 $19,680 10.00% 10.00% 20.00% $3,936 $23,616
10.08.26.465.87 CHAIN LINK FENCE (CL-6) 101.00 LF $19.00 $1,919 10.00% 10.00% 20.00% $384 $2,303
10.08.26.547.87 CHAIN LINK FENCE (CL-6) 53.00 LF $19.00 $1,007 10.00% 10.00% 20.00% $201 $1,208
Monday, January 27, 2014 Page 25 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.26.550.87 CHAIN LINK FENCE (CL-6) 323.00 LF $19.00 $6,137 10.00% 10.00% 20.00% $1,227 $7,364
10.08.26.567.87 CHAIN LINK FENCE (CL-6) 1,314.00 LF $19.00 $24,966 10.00% 10.00% 20.00% $4,993 $29,959
Sum
Average
2,611.00 $53,709
10.00% 10.00% 20.00%
$10,742 $64,451Summary for Group: 10.08.26
Group 10.08.29
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SOUND/SCREEN WALL Contingency
10.08.29.648.71 BLOCK WALL (8' HIGH) (WALL 648R-F) 4,935.00 SF $25.00 $123,375 10.00% 10.00% 20.00% $24,675 $148,050
Sum
Average
4,935.00 $123,375
10.00% 10.00% 20.00%
$24,675 $148,050Summary for Group: 10.08.29
Group 10.08.30
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CONCRETE BARRIER Contingency
10.08.30.465.73 CONCRETE BARRIER 328.00 LF $53.00 $17,384 10.00% 10.00% 20.00% $3,477 $20,861
Sum
Average
328.00 $17,384
10.00% 10.00% 20.00%
$3,477 $20,861Summary for Group: 10.08.30
Group 10.08.31
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TIEBACK WALLS Contingency
10.08.31.509.12 STRUCTURAL BACKFILL (TIEBACK WALL) 44.00 CY $73.00 $3,212 10.00% 10.00% 20.00% $642 $3,854
10.08.31.509.22 STRUCTURE EXCAVATION (TIEBACK WALL) 499.00 CY $60.00 $29,940 10.00% 10.00% 20.00% $5,988 $35,928
10.08.31.509.42 STRUCTURAL CONCRETE (TIEBACK WALL) 147.00 CY $620.00 $91,140 10.00% 10.00% 20.00% $18,228 $109,368
10.08.31.509.52 ARCHITECTURAL TREATMENT (TIEBACK WALL) 4,759.00 SF $14.00 $66,626 10.00% 10.00% 20.00% $13,325 $79,951
10.08.31.509.62 BAR REINFORCING STEEL (TIEBACK WALL) 57,301.00 LB $1.00 $57,301 10.00% 10.00% 20.00% $11,460 $68,761
10.08.31.509.70 CABLE RAILING 208.00 LF $25.00 $5,200 10.00% 10.00% 20.00% $1,040 $6,240
10.08.31.509.80 TIEBACK ANCHORS 119.00 EA $2,160.00 $257,040 10.00% 10.00% 20.00% $51,408 $308,448
10.08.31.509.81 SHOTCRETE 169.00 CY $623.00 $105,287 10.00% 10.00% 20.00% $21,057 $126,344
10.08.31.514.12 STRUCTURAL BACKFILL (TIEBACK WALL) 64.00 CY $73.00 $4,672 10.00% 10.00% 20.00% $934 $5,606
10.08.31.514.22 STRUCTURE EXCAVATION (TIEBACK WALL) 493.00 CY $60.00 $29,580 10.00% 10.00% 20.00% $5,916 $35,496
10.08.31.514.42 STRUCTURAL CONCRETE (TIEBACK WALL) 145.00 CY $620.00 $89,900 10.00% 10.00% 20.00% $17,980 $107,880
10.08.31.514.52 ARCHITECTURAL TREATMENT (TIEBACK WALL) 4,697.00 SF $14.00 $65,758 10.00% 10.00% 20.00% $13,152 $78,910
10.08.31.514.62 BAR REINFORCING STEEL (TIEBACK WALL) 57,638.00 LB $1.00 $57,638 10.00% 10.00% 20.00% $11,528 $69,166
10.08.31.514.70 CABLE RAILING 304.00 LF $25.00 $7,600 10.00% 10.00% 20.00% $1,520 $9,120
10.08.31.514.80 TIEBACK ANCHORS 134.00 EA $2,160.00 $289,440 10.00% 10.00% 20.00% $57,888 $347,328
10.08.31.514.81 SHOTCRETE 160.00 CY $623.00 $99,680 10.00% 10.00% 20.00% $19,936 $119,616
Monday, January 27, 2014 Page 26 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.31.567.12 STRUCTURAL BACKFILL (TIEBACK WALL) 182.00 CY $73.00 $13,286 10.00% 10.00% 20.00% $2,657 $15,943
10.08.31.567.22 STRUCTURE EXCAVATION (TIEBACK WALL) 1,273.00 CY $60.00 $76,380 10.00% 10.00% 20.00% $15,276 $91,656
10.08.31.567.40 STRUCTURAL CONCRETE BACKFILL (TIEBACK WALL) 510.00 CY $470.00 $239,700 10.00% 10.00% 20.00% $47,940 $287,640
10.08.31.567.42 STRUCTURAL CONCRETE (TIEBACK WALL) 995.00 CY $620.00 $616,900 10.00% 10.00% 20.00% $123,380 $740,280
10.08.31.567.43 LEAN CONCRETE BACKFILL 1,273.00 CY $172.00 $218,956 10.00% 10.00% 20.00% $43,791 $262,747
10.08.31.567.52 ARCHITECTURAL TREATMENT (TIEBACK WALL) 26,858.00 SF $14.00 $376,012 10.00% 10.00% 20.00% $75,202 $451,214
10.08.31.567.62 BAR REINFORCING STEEL (TIEBACK WALL) 174,079.00 LB $1.00 $174,079 10.00% 10.00% 20.00% $34,816 $208,895
10.08.31.567.70 CABLE RAILING 1,314.00 LF $25.00 $32,850 10.00% 10.00% 20.00% $6,570 $39,420
10.08.31.567.80 TIEBACK ANCHORS 450.00 EA $2,160.00 $972,000 10.00% 10.00% 20.00% $194,400 $1,166,400
10.08.31.567.82 STEEL SOLDIER PILE (HP 14X73) 8,651.00 LF $80.00 $692,080 10.00% 10.00% 20.00% $138,416 $830,496
10.08.31.567.83 48" DRILLED HOLE 3,830.00 LF $100.00 $383,000 10.00% 10.00% 20.00% $76,600 $459,600
10.08.31.567.84 TIMBER LAGGING 121.00MFBM $1,194.00 $144,474 10.00% 10.00% 20.00% $28,895 $173,369
10.08.31.567.85 CLEAN AND PAINT SOLDIER PILE 1.00 LS $6,083.00 $6,083 10.00% 10.00% 20.00% $1,217 $7,300
Sum
Average
346,418.00 $5,205,814
10.00% 10.00% 20.00%
$1,041,163 $6,246,977Summary for Group: 10.08.31
Group 10.08.32
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
RETAINING WALL 648R-F REINFORCED DESIGN (DIFF.) Contingency
10.08.32.648.460210 GROUND ANCHOR 99.00 EA $11,490.00 $1,137,510 10.00% 10.00% 20.00% $227,502 $1,365,012
10.08.32.648.490605 36" CIDH CONCRETE PILING 2,156.00 LF $507.00 $1,093,092 10.00% 10.00% 20.00% $218,618 $1,311,710
10.08.32.648.510060 STRUCTURAL CONCRETE (RETAINING WALL) -403.00 CY $470.00 ($189,410) 10.00% 10.00% 20.00% ($37,882) ($227,292)
10.08.32.648.520103 BAR REINFORCING STEEL -43,661.00 LB $1.00 ($43,661) 10.00% 10.00% 20.00% ($8,732) ($52,393)
10.08.32.648.520122 STRAY CURRENT PROTECTION -802.00 SF $2.00 ($1,604) 10.00% 10.00% 20.00% ($321) ($1,925)
Sum
Average
-42,611.00 $1,995,927
10.00% 10.00% 20.00%
$399,185 $2,395,112Summary for Group: 10.08.32
Group 10.08.33
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GUIDEWAY DRAINAGE SYSTEMS Contingency
10.08.33.01 UNDERDRAIN (GUIDEWAY) 1,225.00 LF $30.00 $36,750 15.00% 15.00% 30.00% $11,025 $47,775
10.08.33.01 UNDERDRAIN (GUIDEWAY) 11,775.00 LF $30.00 $353,250 15.00% 15.00% 30.00% $105,975 $459,225
10.08.33.01 UNDERDRAIN (GUIDEWAY) 6,315.00 LF $30.00 $189,450 15.00% 15.00% 30.00% $56,835 $246,285
10.08.33.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 4,660.00 LF $27.00 $125,820 15.00% 15.00% 30.00% $37,746 $163,566
10.08.33.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 8,455.00 LF $27.00 $228,285 15.00% 15.00% 30.00% $68,486 $296,771
Monday, January 27, 2014 Page 27 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.33.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 4,320.00 LF $27.00 $116,640 15.00% 15.00% 30.00% $34,992 $151,632
10.08.33.101 18" RCP STORM DRAIN 95.00 LF $120.00 $11,400 15.00% 15.00% 30.00% $3,420 $14,820
10.08.33.101 18" RCP STORM DRAIN 10.00 LF $120.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
10.08.33.101 18" RCP STORM DRAIN 70.00 LF $120.00 $8,400 15.00% 15.00% 30.00% $2,520 $10,920
10.08.33.101 18" RCP STORM DRAIN 60.00 LF $120.00 $7,200 15.00% 15.00% 30.00% $2,160 $9,360
10.08.33.102 24" RCP STORM DRAIN 35.00 LF $170.00 $5,950 15.00% 15.00% 30.00% $1,785 $7,735
10.08.33.102 24" RCP STORM DRAIN 120.00 LF $170.00 $20,400 15.00% 15.00% 30.00% $6,120 $26,520
10.08.33.102 24" RCP STORM DRAIN 20.00 LF $170.00 $3,400 15.00% 15.00% 30.00% $1,020 $4,420
10.08.33.102 24" RCP STORM DRAIN 10.00 LF $170.00 $1,700 15.00% 15.00% 30.00% $510 $2,210
10.08.33.103 30" RCP STORM DRAIN 35.00 LF $210.00 $7,350 15.00% 15.00% 30.00% $2,205 $9,555
10.08.33.103 30" RCP STORM DRAIN (JACKED) 25.00 LF $1,050.00 $26,250 15.00% 20.00% 35.00% $9,188 $35,438
10.08.33.103 30" RCP STORM DRAIN 21.00 LF $210.00 $4,410 15.00% 15.00% 30.00% $1,323 $5,733
10.08.33.103 30" RCP STORM DRAIN 30.00 LF $210.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
10.08.33.103 30" RCP STORM DRAIN 40.00 LF $210.00 $8,400 15.00% 15.00% 30.00% $2,520 $10,920
10.08.33.104 36" RCP STORM DRAIN 85.00 LF $230.00 $19,550 15.00% 15.00% 30.00% $5,865 $25,415
10.08.33.104 36" RCP STORM DRAIN 220.00 LF $230.00 $50,600 15.00% 15.00% 30.00% $15,180 $65,780
10.08.33.104 36" RCP STORM DRAIN 40.00 LF $230.00 $9,200 15.00% 15.00% 30.00% $2,760 $11,960
10.08.33.104 36" RCP STORM DRAIN 35.00 LF $230.00 $8,050 15.00% 15.00% 30.00% $2,415 $10,465
10.08.33.104 36" RCP STORM DRAIN 80.00 LF $230.00 $18,400 15.00% 15.00% 30.00% $5,520 $23,920
10.08.33.104 36" RCP STORM DRAIN 100.00 LF $230.00 $23,000 15.00% 15.00% 30.00% $6,900 $29,900
10.08.33.106 48" RCP STORM DRAIN 100.00 LF $290.00 $29,000 15.00% 15.00% 30.00% $8,700 $37,700
10.08.33.107 54" RCP STORM DRAIN 60.00 LF $470.00 $28,200 15.00% 15.00% 30.00% $8,460 $36,660
10.08.33.107 54" RCP STORM DRAIN 100.00 LF $470.00 $47,000 15.00% 15.00% 30.00% $14,100 $61,100
10.08.33.115 12" PVC STORM DRAIN 40.00 LF $100.00 $4,000 15.00% 15.00% 30.00% $1,200 $5,200
10.08.33.115 12" PVC STORM DRAIN 45.00 LF $100.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
10.08.33.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.08.33.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.08.33.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.08.33.204 4' MOD TYPE B CURB INLET 1.00 EA $5,200.00 $5,200 10.00% 15.00% 25.00% $1,300 $6,500
Monday, January 27, 2014 Page 28 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913
10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.08.33.205 TYPE F CATCH BASIN 1.00 EA $5,120.00 $5,120 10.00% 15.00% 25.00% $1,280 $6,400
10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650
10.08.33.210 EXTEND HEADWALL 1.00 EA $2,800.00 $2,800 15.00% 15.00% 30.00% $840 $3,640
10.08.33.210 MOD HEADWALL WITH WINGWALLS 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.08.33.210 TYPE A STRAIGHT HEADWALL 1.00 EA $7,000.00 $7,000 10.00% 15.00% 25.00% $1,750 $8,750
10.08.33.210 MOD HEADWALL WITH WINGWALLS 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625
10.08.33.210 TYPE A STRAIGHT HEADWALL 1.00 EA $7,000.00 $7,000 10.00% 15.00% 25.00% $1,750 $8,750
10.08.33.211 MOD TYPE A STRAIGHT HEADWALL 1.00 EA $5,500.00 $5,500 10.00% 15.00% 25.00% $1,375 $6,875
10.08.33.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250
10.08.33.215 WALL DRAIN 1.00 EA $2,000.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
10.08.33.215 WALL DRAIN 1.00 EA $2,000.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
10.08.33.501 CONCRETE LUG, SDRSD SDD-113 1.00 EA $1,100.00 $1,100 15.00% 15.00% 30.00% $330 $1,430
10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.08.33.502 PIPE COLLAR 2.00 EA $1,800.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680
10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.08.33.502 PIPE COLLAR 3.00 EA $1,800.00 $5,400 15.00% 15.00% 30.00% $1,620 $7,020
Monday, January 27, 2014 Page 29 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340
10.08.33.502 PIPE COLLAR 2.00 EA $1,800.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680
10.08.33.503 PIPE TO CHANNEL TRANSITION 1.00 EA $6,230.00 $6,230 15.00% 15.00% 30.00% $1,869 $8,099
10.08.33.505 MOD TYPE 2 RIP RAP ENERGY DISSIPATION 1.00 EA $1,840.00 $1,840 10.00% 15.00% 25.00% $460 $2,300
10.08.33.514 INLET APRON 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
10.08.33.700 ABN EXIST 36" RCP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878
10.08.33.700 ABN EXIST 24" CMP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878
10.08.33.700 ABN EXIST 36" CMP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878
10.08.33.700 ABN EXIST 24" RCP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878
10.08.33.700 ABN EXIST 30" RCP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878
10.08.33.700 ABN EXIST 24" ACP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878
10.08.33.701 ABN EXIST CATCH BASIN 1.00 EA $1,240.00 $1,240 15.00% 15.00% 30.00% $372 $1,612
10.08.33.701 ABN EXIST CATCH BASIN 1.00 EA $1,240.00 $1,240 15.00% 15.00% 30.00% $372 $1,612
10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236
10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236
10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236
10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.08.33.702 REMOVE EXIST CURB INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379
10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.08.33.702 REMOVE HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236
10.08.33.702 REMOVE EXIST CURB INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379
10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118
10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236
10.08.33.703 ABANDON EXIST 12" PVC STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878
Monday, January 27, 2014 Page 30 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.33.703 REMOVE EXIST 36" RCP STORM DRAIN 15.00 LF $80.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
10.08.33.703 6' MOD TYPE B CURB INLET 1.00 EA $5,200.00 $5,200 15.00% 15.00% 30.00% $1,560 $6,760
Sum
Average
38,313.00 $1,615,500
13.62% 15.05% 28.67%
$477,539 $2,093,039Summary for Group: 10.08.33
Group 10.08.34
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GUIDEWAY EMBANKMENT Contingency
10.08.34.193001 GUIDEWAY EMBANKMENT SEGMENT 3 27,038.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
10.08.34.193001 GUIDEWAY EMBANKMENT SEGMENT 1 14,440.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
10.08.34.193001 GUIDEWAY EMBANKMENT SEGMENT 2 43,540.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
10.08.34.193001 GUIDEWAY EMBANKMENT (LOSSAN) 12,495.58 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
Sum
Average
97,513.58 $0
15.00% 10.00% 25.00%
$0 $0Summary for Group: 10.08.34
Group 10.08.35
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ANTI-GRAFFITI COATING Contingency
10.08.35.211.598001 ANTI-GRAFFITI COATING 3,118.00 SF $1.20 $3,742 10.00% 10.00% 20.00% $748 $4,490
10.08.35.215.598001 ANTI-GRAFFITI COATING 16,047.00 SF $1.20 $19,256 10.00% 10.00% 20.00% $3,851 $23,108
10.08.35.271.598001 ANTI-GRAFFITI COATING 8,196.00 SF $1.20 $9,835 10.00% 10.00% 20.00% $1,967 $11,802
10.08.35.332.598001 ANTI-GRAFFITI COATING 32,540.00 SF $1.20 $39,048 10.00% 10.00% 20.00% $7,810 $46,858
10.08.35.376.598001 ANTI-GRAFFITI COATING 7,266.00 SF $1.20 $8,719 10.00% 10.00% 20.00% $1,744 $10,463
10.08.35.381.598001 ANTI-GRAFFITI COATING 1,813.00 SF $1.20 $2,176 10.00% 10.00% 20.00% $435 $2,611
10.08.35.388.598001 ANTI-GRAFFITI COATING 1,813.00 SF $1.20 $2,176 10.00% 10.00% 20.00% $435 $2,611
10.08.35.402.598001 ANTI-GRAFFITI COATING 15,975.00 SF $1.20 $19,170 10.00% 10.00% 20.00% $3,834 $23,004
10.08.35.416.598001 ANTI-GRAFFITI COATING 4,876.00 SF $1.20 $5,851 10.00% 10.00% 20.00% $1,170 $7,021
10.08.35.446.598001 ANTI-GRAFFITI COATING 16,439.00 SF $1.20 $19,727 10.00% 10.00% 20.00% $3,945 $23,672
10.08.35.449.598001 ANTI-GRAFFITI COATING 2,598.00 SF $1.20 $3,118 10.00% 10.00% 20.00% $624 $3,741
10.08.35.457.598001 ANTI-GRAFFITI COATING 6,490.00 SF $1.20 $7,788 10.00% 10.00% 20.00% $1,558 $9,346
10.08.35.465.598001 ANTI-GRAFFITI COATING 16,624.00 SF $1.20 $19,949 10.00% 10.00% 20.00% $3,990 $23,939
10.08.35.472.598001 ANTI-GRAFFITI COATING 16,060.00 SF $1.20 $19,272 10.00% 10.00% 20.00% $3,854 $23,126
10.08.35.475.598001 ANTI-GRAFFITI COATING 2,801.00 SF $1.20 $3,361 10.00% 10.00% 20.00% $672 $4,033
10.08.35.485.598001 ANTI-GRAFFITI COATING 3,430.00 SF $1.20 $4,116 10.00% 10.00% 20.00% $823 $4,939
10.08.35.498L.598001 ANTI-GRAFFITI COATING 9,392.00 SF $1.20 $11,270 10.00% 10.00% 20.00% $2,254 $13,524
Monday, January 27, 2014 Page 31 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.35.498R.598001 ANTI-GRAFFITI COATING 18,636.00 SF $1.20 $22,363 10.00% 10.00% 20.00% $4,473 $26,836
10.08.35.500.598001 ANTI-GRAFFITI COATING 28,658.00 SF $1.20 $34,390 10.00% 10.00% 20.00% $6,878 $41,268
10.08.35.507.598001 ANTI-GRAFFITI COATING 1,171.00 SF $1.20 $1,405 10.00% 10.00% 20.00% $281 $1,686
10.08.35.509.598001 ANTI-GRAFFITI COATING 4,759.00 SF $1.20 $5,711 10.00% 10.00% 20.00% $1,142 $6,853
10.08.35.510.598001 ANTI-GRAFFITI COATING 353.00 SF $1.20 $424 10.00% 10.00% 20.00% $85 $508
10.08.35.512.598001 ANTI-GRAFFITI COATING 290.00 SF $1.20 $348 10.00% 10.00% 20.00% $70 $418
10.08.35.514.598001 ANTI-GRAFFITI COATING 4,697.00 SF $1.20 $5,636 10.00% 10.00% 20.00% $1,127 $6,764
10.08.35.516.598001 ANTI-GRAFFITI COATING 1,036.00 SF $1.20 $1,243 10.00% 10.00% 20.00% $249 $1,492
10.08.35.524.598001 ANTI-GRAFFITI COATING 30,752.00 SF $1.20 $36,902 10.00% 10.00% 20.00% $7,380 $44,283
10.08.35.526.598001 ANTI-GRAFFITI COATING 7,965.00 SF $1.20 $9,558 10.00% 10.00% 20.00% $1,912 $11,470
10.08.35.547.598001 ANTI-GRAFFITI COATING 425.00 SF $1.20 $510 10.00% 10.00% 20.00% $102 $612
10.08.35.550.598001 ANTI-GRAFFITI COATING 5,649.00 SF $1.20 $6,779 10.00% 10.00% 20.00% $1,356 $8,135
10.08.35.560.598001 ANTI-GRAFFITI COATING 7,040.00 SF $1.20 $8,448 10.00% 10.00% 20.00% $1,690 $10,138
10.08.35.567.598001 ANTI-GRAFFITI COATING 26,858.00 SF $1.20 $32,230 10.00% 10.00% 20.00% $6,446 $38,676
10.08.35.580.598001 ANTI-GRAFFITI COATING 46,862.00 SF $1.20 $56,234 10.00% 10.00% 20.00% $11,247 $67,481
10.08.35.592.598001 ANTI-GRAFFITI COATING 7,040.00 SF $1.20 $8,448 10.00% 10.00% 20.00% $1,690 $10,138
10.08.35.598L.598001 ANTI-GRAFFITI COATING 1,114.00 SF $1.20 $1,337 10.00% 10.00% 20.00% $267 $1,604
10.08.35.598R.598001 ANTI-GRAFFITI COATING 2,341.00 SF $1.20 $2,809 10.00% 10.00% 20.00% $562 $3,371
10.08.35.648.598001 ANTI-GRAFFITI COATING 14,586.00 SF $1.20 $17,503 10.00% 10.00% 20.00% $3,501 $21,004
10.08.35.999.598001 ANTI-GRAFFITI COATING 10,989.00 SF $1.20 $13,187 10.00% 10.00% 20.00% $2,637 $15,824
Sum
Average
386,699.00 $464,039
10.00% 10.00% 20.00%
$92,808 $556,847Summary for Group: 10.08.35
Group 10.08.36
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
STRAY CURRENT PROTECTION Contingency
10.08.36.211.520122 STRAY CURRENT PROTECTION 3,118.00 SF $2.00 $6,236 10.00% 10.00% 20.00% $1,247 $7,483
10.08.36.215.520122 STRAY CURRENT PROTECTION 16,047.00 SF $2.00 $32,094 10.00% 10.00% 20.00% $6,419 $38,513
10.08.36.271.520122 STRAY CURRENT PROTECTION 8,196.00 SF $2.00 $16,392 10.00% 10.00% 20.00% $3,278 $19,670
10.08.36.332.520122 STRAY CURRENT PROTECTION 32,540.00 SF $2.00 $65,080 10.00% 10.00% 20.00% $13,016 $78,096
10.08.36.376.520122 STRAY CURRENT PROTECTION 7,266.00 SF $2.00 $14,532 10.00% 10.00% 20.00% $2,906 $17,438
10.08.36.381.520122 STRAY CURRENT PROTECTION 1,813.00 SF $2.00 $3,626 10.00% 10.00% 20.00% $725 $4,351
Monday, January 27, 2014 Page 32 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.08.36.388.520122 STRAY CURRENT PROTECTION 19,718.00 SF $2.00 $39,436 10.00% 10.00% 20.00% $7,887 $47,323
10.08.36.402.520122 STRAY CURRENT PROTECTION 15,975.00 SF $2.00 $31,950 10.00% 10.00% 20.00% $6,390 $38,340
10.08.36.416.520122 STRAY CURRENT PROTECTION 4,876.00 SF $2.00 $9,752 10.00% 10.00% 20.00% $1,950 $11,702
10.08.36.465.520122 STRAY CURRENT PROTECTION 16,624.00 SF $2.00 $33,248 10.00% 10.00% 20.00% $6,650 $39,898
10.08.36.485.520122 STRAY CURRENT PROTECTION 3,430.00 SF $2.00 $6,860 10.00% 10.00% 20.00% $1,372 $8,232
10.08.36.498L.520122 STRAY CURRENT PROTECTION 9,392.00 SF $2.00 $18,784 10.00% 10.00% 20.00% $3,757 $22,541
10.08.36.498R.520122 STRAY CURRENT PROTECTION 18,636.00 SF $2.00 $37,272 10.00% 10.00% 20.00% $7,454 $44,726
10.08.36.498R.520122 STRAY CURRENT PROTECTION (SOLDIER PILE WALL) 26,858.00 SF $2.00 $53,716 10.00% 10.00% 20.00% $10,743 $64,459
10.08.36.507.520122 STRAY CURRENT PROTECTION 1,171.00 SF $2.00 $2,342 10.00% 10.00% 20.00% $468 $2,810
10.08.36.509.520122 STRAY CURRENT PROTECTION (TIEBACK) 4,759.00 SF $2.00 $9,518 10.00% 10.00% 20.00% $1,904 $11,422
10.08.36.510.520122 STRAY CURRENT PROTECTION 353.00 SF $2.00 $706 10.00% 10.00% 20.00% $141 $847
10.08.36.512.520122 STRAY CURRENT PROTECTION 290.00 SF $2.00 $580 10.00% 10.00% 20.00% $116 $696
10.08.36.514.520122 STRAY CURRENT PROTECTION (TIEBACK) 4,697.00 SF $2.00 $9,394 10.00% 10.00% 20.00% $1,879 $11,273
10.08.36.516.520122 STRAY CURRENT PROTECTION 1,036.00 SF $2.00 $2,072 10.00% 10.00% 20.00% $414 $2,486
10.08.36.526.520122 STRAY CURRENT PROTECTION 7,965.00 SF $2.00 $15,930 10.00% 10.00% 20.00% $3,186 $19,116
10.08.36.547.520122 STRAY CURRENT PROTECTION 425.00 SF $2.00 $850 10.00% 10.00% 20.00% $170 $1,020
10.08.36.560.520122 STRAY CURRENT PROTECTION 7,040.00 SF $2.00 $14,080 10.00% 10.00% 20.00% $2,816 $16,896
10.08.36.580.520122 STRAY CURRENT PROTECTION 46,862.00 SF $2.00 $93,724 10.00% 10.00% 20.00% $18,745 $112,469
10.08.36.592.520122 STRAY CURRENT PROTECTION 3,281.00 SF $2.00 $6,562 10.00% 10.00% 20.00% $1,312 $7,874
10.08.36.598L.520122 STRAY CURRENT PROTECTION 1,114.00 SF $2.00 $2,228 10.00% 10.00% 20.00% $446 $2,674
10.08.36.598R.520122 STRAY CURRENT PROTECTION 2,341.00 SF $2.00 $4,682 10.00% 10.00% 20.00% $936 $5,618
10.08.36.648.520122 STRAY CURRENT PROTECTION 14,586.00 SF $2.00 $29,172 10.00% 10.00% 20.00% $5,834 $35,006
Sum
Average
280,409.00 $560,818
10.00% 10.00% 20.00%
$112,164 $672,982Summary for Group: 10.08.36
Sum
Average
5,964,674.03 $55,207,502
10.82% 11.06% 21.88%
$11,140,307 $66,347,809Summary for Sub Section: 10.08
Sub Section 10.09 Track: Direct fixation
Group 10.09.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
DF TRACK CONSTRUCTION Contingency
10.09.01 DF FASTENERS (FURNISH AND INSTALL) 4,263.00 EA $50.00 $213,150 5.00% 15.00% 20.00% $42,630 $255,780
Monday, January 27, 2014 Page 33 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.09.01 DF FASTENERS (FURNISH AND INSTALL) 19,536.00 EA $50.00 $976,800 5.00% 15.00% 20.00% $195,360 $1,172,160
10.09.01 DF FASTENERS (FURNISH AND INSTALL) 2,055.00 EA $50.00 $102,750 5.00% 15.00% 20.00% $20,550 $123,300
10.09.01 DF FASTENERS (FURNISH AND INSTALL) 10,618.00 EA $50.00 $530,900 5.00% 15.00% 20.00% $106,180 $637,080
10.09.01.01 115RE DF HIGH STRENGTH RAIL (INSTALL) 21,386.12 TF $150.00 $3,207,918 5.00% 15.00% 20.00% $641,584 $3,849,502
10.09.01.01 115RE DF HIGH STRENGTH RAIL (INSTALL) 15,408.00 TF $150.00 $2,311,200 5.00% 15.00% 20.00% $462,240 $2,773,440
10.09.01.01 115RE DF HIGH STRENGTH RAIL (INSTALL) 5,250.58 TF $150.00 $787,587 5.00% 15.00% 20.00% $157,517 $945,104
10.09.01.01 115RE DF HIGH STRENGTH RAIL (INSTALL) 2,568.00 TF $150.00 $385,200 5.00% 15.00% 20.00% $77,040 $462,240
10.09.01.02 115RE DF HIGH STRENGTH RAIL (FURNISH) 98.40TON $1,550.00 $152,520 5.00% 15.00% 20.00% $30,504 $183,024
10.09.01.02 115RE DF HIGH STRENGTH RAIL (FURNISH) 590.60TON $1,550.00 $915,430 5.00% 15.00% 20.00% $183,086 $1,098,516
10.09.01.02 115RE DF HIGH STRENGTH RAIL (FURNISH) 201.30TON $1,550.00 $312,015 5.00% 15.00% 20.00% $62,403 $374,418
10.09.01.02 115RE DF HIGH STRENGTH RAIL (FURNISH) 819.80TON $1,550.00 $1,270,690 5.00% 15.00% 20.00% $254,138 $1,524,828
10.09.01.03 115RE DF STANDARD STRENGTH RAIL (INSTALL) 1,268.00 TF $135.00 $171,180 5.00% 15.00% 20.00% $34,236 $205,416
10.09.01.04 115RE DF STANDARD STRENGTH RAIL (FURNISH) 48.60TON $1,350.00 $65,610 5.00% 15.00% 20.00% $13,122 $78,732
Sum
Average
84,111.40 $11,402,950
5.00% 15.00% 20.00%
$2,280,590 $13,683,540Summary for Group: 10.09.01
Group 10.09.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CONCRETE PLINTH Contingency
10.09.02 CONCRETE PLINTH 28,801.00 CF $44.10 $1,270,124 5.00% 15.00% 20.00% $254,025 $1,524,149
10.09.02 CONCRETE PLINTH 11,562.00 CF $44.10 $509,884 5.00% 15.00% 20.00% $101,977 $611,861
10.09.02 CONCRETE PLINTH 5,573.00 CF $44.10 $245,769 5.00% 15.00% 20.00% $49,154 $294,923
10.09.02 CONCRETE PLINTH 52,992.00 CF $44.10 $2,336,947 5.00% 15.00% 20.00% $467,389 $2,804,337
Sum
Average
98,928.00 $4,362,725
5.00% 15.00% 20.00%
$872,545 $5,235,270Summary for Group: 10.09.02
Group 10.09.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SLAB TRACK Contingency
10.09.03.01 SLAB TRACK (CONCRETE) 1,134.00 CY $850.00 $963,900 5.00% 15.00% 20.00% $192,780 $1,156,680
10.09.03.02 CLASS 2 AGGREGATE BASE 600.00 CY $45.00 $27,000 5.00% 15.00% 20.00% $5,400 $32,400
Sum
Average
1,734.00 $990,900
5.00% 15.00% 20.00%
$198,180 $1,189,080Summary for Group: 10.09.03
Group 10.09.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
WALKWAY AT DF TRACK Contingency
10.09.04.01 WALKWAY AT DF TRACK 2,568.00 LF $240.00 $616,320 5.00% 15.00% 20.00% $123,264 $739,584
Monday, January 27, 2014 Page 34 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
10.09.04.02 WALKWAY AT DF TRACK 6,518.00 LF $240.00 $1,564,320 5.00% 15.00% 20.00% $312,864 $1,877,184
10.09.04.03 WALKWAY AT DF TRACK 15,408.00 LF $240.00 $3,697,920 5.00% 15.00% 20.00% $739,584 $4,437,504
10.09.04.04 WALKWAY AT DF TRACK 21,386.00 LF $240.00 $5,132,640 5.00% 15.00% 20.00% $1,026,528 $6,159,168
Sum
Average
45,880.00 $11,011,200
5.00% 15.00% 20.00%
$2,202,240 $13,213,440Summary for Group: 10.09.04
Sum
Average
230,653.40 $27,767,775
5.00% 15.00% 20.00%
$5,553,555 $33,321,330Summary for Sub Section: 10.09
Sub Section 10.11 Track:Ballasted
Group 10.11.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BALLASTED TRACK CONSTRUCTION (DOUBLE TRACK) Contingency
10.11.01.01 115RE BALLASTED HIGH STRENGTH RAIL (INSTALL) 6,567.56 TF $85.00 $558,243 5.00% 10.00% 15.00% $83,736 $641,979
10.11.01.01 136RE BALLASTED STANDARD STRENGTH RAIL (FURNISH) LOSSAN 559.00TON $1,950.00 $1,090,050 5.00% 10.00% 15.00% $163,508 $1,253,558
10.11.01.01 115RE BALLASTED HIGH STRENGTH RAIL (INSTALL) 5,134.00 TF $85.00 $436,390 5.00% 20.00% 25.00% $109,098 $545,488
10.11.01.01 115RE BALLASTED HIGH STRENGTH RAIL (INSTALL) 2,588.31 TF $85.00 $220,006 5.00% 20.00% 25.00% $55,002 $275,008
10.11.01.01A 136RE BALLASTED STANDARD STRENGTH RAIL (INSTALL) LOSSAN 12,335.50 TF $100.00 $1,233,550 5.00% 10.00% 15.00% $185,033 $1,418,583
10.11.01.02 115RE BALLASTED HIGH STRENGTH RAIL (FURNISH) 251.80TON $1,550.00 $390,290 5.00% 10.00% 15.00% $58,544 $448,834
10.11.01.02 115RE BALLASTED HIGH STRENGTH RAIL (FURNISH) 99.20TON $1,550.00 $153,760 5.00% 10.00% 15.00% $23,064 $176,824
10.11.01.02 115RE BALLASTED HIGH STRENGTH RAIL (FURNISH) 196.80TON $1,550.00 $305,040 5.00% 10.00% 15.00% $45,756 $350,796
10.11.01.03 115RE BALLASTED STANDARD STRENGTH RAIL (INSTALL) 25,356.00 TF $85.00 $2,155,260 5.00% 20.00% 25.00% $538,815 $2,694,075
10.11.01.03 115RE BALLASTED STANDARD STRENGTH RAIL (INSTALL) 28,085.10 TF $85.00 $2,387,234 5.00% 20.00% 25.00% $596,808 $2,984,042
10.11.01.03A 136RE BALLASTED STANDARD STRENGTH RAIL (INSTALL) SHOOFLY 7,640.00 TF $100.00 $764,000 5.00% 10.00% 15.00% $114,600 $878,600
10.11.01.04 115RE BALLASTED STANDARD STRENGTH RAIL (FURNISH) 1,076.60TON $1,350.00 $1,453,410 5.00% 10.00% 15.00% $218,012 $1,671,422
10.11.01.04 115RE BALLASTED STANDARD STRENGTH RAIL (FURNISH) 972.00TON $1,350.00 $1,312,200 5.00% 10.00% 15.00% $196,830 $1,509,030
10.11.01.04A 136RE BALLASTED STANDARD STRENGTH RAIL (FURNISH) SHOOFLY 346.30TON $1,950.00 $675,285 5.00% 10.00% 15.00% $101,293 $776,578
10.11.01.10 CONCRETE TIES 2,628.00 EA $100.00 $262,800 15.00% 10.00% 25.00% $65,700 $328,500
10.11.01.10 CONCRETE TIES 13,490.00 EA $100.00 $1,349,000 15.00% 10.00% 25.00% $337,250 $1,686,250
10.11.01.10 CONCRETE TIES 11,712.00 EA $100.00 $1,171,200 5.00% 10.00% 15.00% $175,680 $1,346,880
10.11.01.10A CONCRETE TIES (SHOOFLY) 3,820.00 EA $130.00 $496,600 15.00% 10.00% 25.00% $124,150 $620,750
10.11.01.12 CONCRETE TIES (LOSSAN) 6,168.00 EA $130.00 $801,840 15.00% 10.00% 25.00% $200,460 $1,002,300
Sum
Average
129,026.17 $17,216,157
7.11% 12.11% 19.21%
$3,393,337 $20,609,494Summary for Group: 10.11.01
Monday, January 27, 2014 Page 35 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Group 10.11.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BALLAST Contingency
10.11.02 BALLAST 71,559.00 CY $53.00 $3,792,627 15.00% 10.00% 25.00% $948,157 $4,740,784
10.11.02 BALLAST (LOSSAN) 11,181.00 CY $53.00 $592,593 15.00% 10.00% 25.00% $148,148 $740,741
10.11.02A BALLAST (SHOOFLY) 7,672.00 CY $35.00 $268,520 15.00% 10.00% 25.00% $67,130 $335,650
Sum
Average
90,412.00 $4,653,740
15.00% 10.00% 25.00%
$1,163,435 $5,817,175Summary for Group: 10.11.02
Group 10.11.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BALLAST CURB Contingency
10.11.08 BALLAST CURB 101.93 LF $42.00 $4,281 15.00% 10.00% 25.00% $1,070 $5,351
10.11.08 BALLAST CURB 6,175.64 LF $42.00 $259,377 15.00% 10.00% 25.00% $64,844 $324,221
10.11.08 BALLAST CURB 1,218.39 LF $42.00 $51,172 15.00% 10.00% 25.00% $12,793 $63,965
10.11.08.01 GUIDEWAY EXCAVATION 116.01 CY $18.00 $2,088 15.00% 10.00% 25.00% $522 $2,610
10.11.08.01 GUIDEWAY EXCAVATION 1,069.34 CY $18.00 $19,248 15.00% 10.00% 25.00% $4,812 $24,060
10.11.08.01 GUIDEWAY EXCAVATION 9.97 CY $18.00 $179 15.00% 10.00% 25.00% $45 $224
10.11.08.02 BACKFILL (BALLAST CURB) 982.80 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
10.11.08.02 BACKFILL (BALLAST CURB) 172.69 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
10.11.08.02 BACKFILL (BALLAST CURB) 11.35 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0
Sum
Average
9,858.12 $336,346
15.00% 10.00% 25.00%
$84,087 $420,433Summary for Group: 10.11.08
Sum
Average
229,296.29 $22,206,244
10.16% 11.29% 21.45%
$4,640,858 $26,847,102Summary for Sub Section: 10.11
Sub Section 10.12 TRACK: SPECIAL (SWITCHES, TURNOUT)
Group 10.12.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NO. 10 SINGLE CROSSOVER (BALLASTED) Contingency
10.12.01 NO. 10 SINGLE CROSSOVER WITH RBM (BALLASTED) 1.00 EA $243,661.00 $243,661 0.00% 12.50% 12.50% $30,458 $274,119
Sum
Average
1.00 $243,661
0.00% 12.50% 12.50%
$30,458 $274,119Summary for Group: 10.12.01
Group 10.12.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NO. 10 DOUBLE CROSSOVER (DF) Contingency
10.12.03 NO. 10 DOUBLE CROSSOVER W/RBM FROGS (DF) 4.00 EA $711,589.00 $2,846,356 0.00% 12.50% 12.50% $355,795 $3,202,151
Sum
Average
4.00 $2,846,356
0.00% 12.50% 12.50%
$355,795 $3,202,151Summary for Group: 10.12.03
Monday, January 27, 2014 Page 36 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Group 10.12.03A
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NO. 10 SINGLE CROSSOVER WITH SPRING FROGS (BALLASTED) Contingency
10.12.03A NO. 10 SINGLE CROSSOVER WITH SPRING FROGS (BALLASTED) 1.00 EA $314,401.00 $314,401 0.00% 12.50% 12.50% $39,300 $353,701
10.12.03A NO. 10 SINGLE CROSSOVER WITH SPRING FROGS (BALLASTED) - SP 1.00 EA $314,401.00 $314,401 0.00% 12.50% 12.50% $39,300 $353,701
Sum
Average
2.00 $628,802
0.00% 12.50% 12.50%
$78,600 $707,402Summary for Group: 10.12.03A
Group 10.12.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BUMPING POST Contingency
10.12.04.02 HYDRAULIC BUMPING POST 3.00 EA $20,855.00 $62,565 12.50% 12.50% 25.00% $15,641 $78,206
Sum
Average
3.00 $62,565
12.50% 12.50% 25.00%
$15,641 $78,206Summary for Group: 10.12.04
Group 10.12.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NO. 10 TURNOUT (BALLASTED) Contingency
10.12.05 NO. 10 TURNOUT WITH RBM (BALLASTED) - SPARE PARTS 1.00 EA $158,394.00 $158,394 0.00% 12.50% 12.50% $19,799 $178,193
10.12.05 NO. 10 TURNOUT WITH RBM (BALLASTED) 1.00 EA $158,394.00 $158,394 0.00% 12.50% 12.50% $19,799 $178,193
Sum
Average
2.00 $316,788
0.00% 12.50% 12.50%
$39,599 $356,387Summary for Group: 10.12.05
Group 10.12.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CROSSING DIAMOND 11DEG-26'-58" Contingency
10.12.06 CROSSING DIAMOND 11DEG-26'-58" - SPARE PARTS 1.00 EA $671,866.00 $671,866 0.00% 12.50% 12.50% $83,983 $755,849
10.12.06 NO. 20 CROSSING DIAMOND (DF/SLAB TRACK) - SPARE PARTS 1.00 EA $1,119,716.00 $1,119,716 0.00% 12.50% 12.50% $139,965 $1,259,681
10.12.06 NO. 20 CROSSING DIAMOND (DF/SLAB TRACK) 1.00 EA $1,119,716.00 $1,119,716 0.00% 12.50% 12.50% $139,965 $1,259,681
Sum
Average
3.00 $2,911,298
0.00% 12.50% 12.50%
$363,912 $3,275,210Summary for Group: 10.12.06
Group 10.12.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NO. 20 TURNOUT (DF/SLAB TRACK) Contingency
10.12.07 NO. 20 TURNOUT WITH RBM FROGS (DF/SLAB TRACK) 2.00 EA $147,051.00 $294,102 0.00% 12.50% 12.50% $36,763 $330,865
10.12.07 NO. 20 TURNOUT (DF/SLAB TRACK) - SPARE PARTS 1.00 EA $147,051.00 $147,051 0.00% 12.50% 12.50% $18,381 $165,432
Sum
Average
3.00 $441,153
0.00% 12.50% 12.50%
$55,144 $496,297Summary for Group: 10.12.07
Group 10.12.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NO. 10 DOUBLE CROSSOVER (BALLASTED) Contingency
10.12.10 NO. 10 DOUBLE CROSSOVER (BALLASTED) 3.00 EA $671,866.00 $2,015,598 0.00% 12.50% 12.50% $251,950 $2,267,548
Monday, January 27, 2014 Page 37 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
3.00 $2,015,598
0.00% 12.50% 12.50%
$251,950 $2,267,548Summary for Group: 10.12.10
Group 10.12.11
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NO. 14 TURNOUT (BALLASTED) Contingency
10.12.11 NO. 14 TURNOUT (BALLASTED) 1.00 EA $133,046.00 $133,046 0.00% 12.50% 12.50% $16,631 $149,677
Sum
Average
1.00 $133,046
0.00% 12.50% 12.50%
$16,631 $149,677Summary for Group: 10.12.11
Sum
Average
22.00 $9,599,267
0.89% 12.50% 13.39%
$1,207,729 $10,806,996Summary for Sub Section: 10.12
Sub Section 10.13 VIBRATION MITIGATION
Group 10.13.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
VIBRATION MITIGATION (FLOATING SLAB TRACK) Contingency
10.13.01 FLOATING SLAB TRACK 720.00 TF $2,000.00 $1,440,000 0.00% 30.00% 30.00% $432,000 $1,872,000
Sum
Average
720.00 $1,440,000
0.00% 30.00% 30.00%
$432,000 $1,872,000Summary for Group: 10.13.01
Sum
Average
720.00 $1,440,000
0.00% 30.00% 30.00%
$432,000 $1,872,000Summary for Sub Section: 10.13
Sum
Average
37,375,505.57 $270,884,223
11.39% 11.63% 23.02%
$61,189,270 $332,073,493Summary for Section 10
Section 20 STATIONS, STOPS, TERMINALS, INTERMODAL
Sub Section 20.01 AT-GRADE STATION, STOP, SHELTER, MALL, TERMINAL, PLATFORM
Group 20.01.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PERMANENT BMP (AT-GRADE STATION) Contingency
20.01.01 PERMANENT BMP (AT-GRADE STATION) 1.00 LS $700,000.00 $700,000 0.00% 20.00% 20.00% $140,000 $840,000
Sum
Average
1.00 $700,000
0.00% 20.00% 20.00%
$140,000 $840,000Summary for Group: 20.01.01
Group 20.01.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TECOLOTE STATION Contingency
20.01.02.02370.27 STATION STRIPING (THERMO PLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253
20.01.02.09000.01 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600
20.01.02.09000.02 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000
20.01.02.09000.03 ARCHITECTURAL CONCRETE FINISH (ANCILLARY SPACE) 500.00 SF $20.00 $10,000 15.00% 10.00% 25.00% $2,500 $12,500
20.01.02.09000.05 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313
Monday, January 27, 2014 Page 38 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.01.02.09000.07 INFORMATIONAL KIOSK 2.00 EA $7,973.00 $15,946 0.00% 10.00% 10.00% $1,595 $17,541
20.01.02.100 STATION ELECTRICAL (SITE TO WITHIN 5' OF ENTRY) 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000
20.01.02.1000 BLOCK WALL (8' High w/footing) 3,840.00 SF $35.00 $134,400 0.00% 10.00% 10.00% $13,440 $147,840
20.01.02.10100.01M SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
20.01.02.10500.05 LARGE SHELTER (INCL. FOUNDATION & SEATING) 6.00 EA $207,000.00 $1,242,000 0.00% 10.00% 10.00% $124,200 $1,366,200
20.01.02.12000.02M STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
20.01.02.15300.01A STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000
20.01.02.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
20.01.02.2000 METAL PANEL SCREEN WALL (8' X 6') 192.00 SF $32.00 $6,144 15.00% 10.00% 25.00% $1,536 $7,680
20.01.02.2820.01 CHAIN LINK FENCE (CL-4) 484.00 LF $16.00 $7,744 15.00% 10.00% 25.00% $1,936 $9,680
20.01.02.300 PLATFORM CONCRETE 400.00 CY $750.00 $300,000 15.00% 10.00% 25.00% $75,000 $375,000
20.01.02.400 GUIDEWAY EXCAVATION 800.00 CY $18.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000
20.01.02.500 CLASS 2 AGGREGATE BASE 400.00 CY $45.00 $18,000 15.00% 10.00% 25.00% $4,500 $22,500
20.01.02.600 STATION LIGHTING 32.00 EA $5,000.00 $160,000 0.00% 10.00% 10.00% $16,000 $176,000
20.01.02.601 THREE-BAY TELECOMMUNICATION CABINET 1.00 EA $140,000.00 $140,000 15.00% 15.00% 30.00% $42,000 $182,000
20.01.02.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545
20.01.02.604 TRACKWAY PAVING AT PLATFORM 1,954.00 SF $36.00 $70,344 15.00% 10.00% 25.00% $17,586 $87,930
Sum
Average
31,825.00 $2,882,666
10.91% 10.23% 21.14%
$450,415 $3,333,081Summary for Group: 20.01.02
Group 20.01.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CLAIREMONT STATION Contingency
20.01.03.02370.27 STATION STRIPING (THERMO PLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253
20.01.03.09000.01 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600
20.01.03.09000.02 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000
20.01.03.09000.03 ARCHITECTURAL CONCRETE FINISH (ANCILLARY SPACE) 500.00 SF $20.00 $10,000 15.00% 10.00% 25.00% $2,500 $12,500
20.01.03.09000.05 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313
20.01.03.09000.07 INFORMATIONAL KIOSK 2.00 EA $7,973.00 $15,946 0.00% 10.00% 10.00% $1,595 $17,541
20.01.03.100 STATION ELECTRICAL (SITE TO WITHIN 5' OF ENTRY) 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000
20.01.03.1000 BLOCK WALL (8' High w/footing) 2,880.00 SF $35.00 $100,800 0.00% 10.00% 10.00% $10,080 $110,880
20.01.03.10100.01M SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
Monday, January 27, 2014 Page 39 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.01.03.10500.05 LARGE SHELTER (INCL. FOUNDATION & SEATING) 6.00 EA $207,000.00 $1,242,000 0.00% 10.00% 10.00% $124,200 $1,366,200
20.01.03.12000.02M STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
20.01.03.15300.01A STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000
20.01.03.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
20.01.03.2000 METAL PANEL SCREEN WALL (8' X 6') 192.00 SF $32.00 $6,144 15.00% 10.00% 25.00% $1,536 $7,680
20.01.03.2820.01 CHAIN LINK FENCE (CL-4) 484.00 LF $16.00 $7,744 15.00% 10.00% 25.00% $1,936 $9,680
20.01.03.300 PLATFORM CONCRETE 400.00 CY $750.00 $300,000 15.00% 10.00% 25.00% $75,000 $375,000
20.01.03.400 GUIDEWAY EXCAVATION 800.00 CY $18.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000
20.01.03.500 CLASS 2 AGGREGATE BASE 400.00 CY $45.00 $18,000 15.00% 10.00% 25.00% $4,500 $22,500
20.01.03.600 STATION LIGHTING 32.00 EA $5,000.00 $160,000 0.00% 10.00% 10.00% $16,000 $176,000
20.01.03.601 THREE-BAY TELECOMMUNICATION CABINET 1.00 EA $140,000.00 $140,000 15.00% 15.00% 30.00% $42,000 $182,000
20.01.03.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545
20.01.03.604 TRACKWAY PAVING AT PLATFORM 2,225.00 SF $36.00 $80,100 15.00% 10.00% 25.00% $20,025 $100,125
Sum
Average
31,136.00 $2,858,822
10.91% 10.23% 21.14%
$449,494 $3,308,316Summary for Group: 20.01.03
Group 20.01.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BALBOA STATION Contingency
20.01.04.02370.27 STATION STRIPING (THERMO PLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253
20.01.04.09000.01 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600
20.01.04.09000.02 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000
20.01.04.09000.03 ARCHITECTURAL CONCRETE FINISH (ANCILLARY SPACE) 500.00 SF $20.00 $10,000 15.00% 10.00% 25.00% $2,500 $12,500
20.01.04.09000.05 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313
20.01.04.09000.07 INFORMATIONAL KIOSK 2.00 EA $7,973.00 $15,946 0.00% 10.00% 10.00% $1,595 $17,541
20.01.04.100 STATION ELECTRICAL (SITE TO WITHIN 5' OF ENTRY) 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000
20.01.04.1000 BLOCK WALL (8' High) 2,880.00 SF $25.00 $72,000 0.00% 10.00% 10.00% $7,200 $79,200
20.01.04.10100.01M SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
20.01.04.10500.05 LARGE SHELTER (INCL. FOUNDATION & SEATING) 6.00 EA $207,000.00 $1,242,000 0.00% 10.00% 10.00% $124,200 $1,366,200
20.01.04.12000.02M STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
20.01.04.15300.01A STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000
20.01.04.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
Monday, January 27, 2014 Page 40 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.01.04.2000 METAL PANEL SCREEN WALL (8' X 6') 192.00 SF $32.00 $6,144 15.00% 10.00% 25.00% $1,536 $7,680
20.01.04.2820.01 CHAIN LINK FENCE (CL-4) 484.00 LF $16.00 $7,744 15.00% 10.00% 25.00% $1,936 $9,680
20.01.04.300 PLATFORM CONCRETE 400.00 CY $750.00 $300,000 15.00% 10.00% 25.00% $75,000 $375,000
20.01.04.400 GUIDEWAY EXCAVATION 800.00 CY $18.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000
20.01.04.500 CLASS 2 AGGREGATE BASE 400.00 CY $45.00 $18,000 15.00% 10.00% 25.00% $4,500 $22,500
20.01.04.600 STATION LIGHTING 32.00 EA $5,000.00 $160,000 0.00% 10.00% 10.00% $16,000 $176,000
20.01.04.601 THREE-BAY TELECOMMUNICATION CABINET 1.00 EA $140,000.00 $140,000 15.00% 15.00% 30.00% $42,000 $182,000
20.01.04.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545
20.01.04.604 TRACKWAY PAVING AT PLATFORM 1,954.00 SF $36.00 $70,344 15.00% 10.00% 25.00% $17,586 $87,930
Sum
Average
30,865.00 $2,820,266
10.91% 10.23% 21.14%
$444,175 $3,264,441Summary for Group: 20.01.04
Group 20.01.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
VA MEDICAL CENTER STATION Contingency
20.01.05.02370.27 STATION STRIPING (THERMO PLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253
20.01.05.09000.01 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 9,200.00 SF $20.00 $184,000 0.00% 10.00% 10.00% $18,400 $202,400
20.01.05.09000.02 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000
20.01.05.09000.03 ARCHITECTURAL CONCRETE FINISH (ANCILLARY SPACE) 5,000.00 SF $20.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000
20.01.05.09000.05 BIKE LOCKER 10.00 EA $2,450.00 $24,500 15.00% 10.00% 25.00% $6,125 $30,625
20.01.05.09000.07 INFORMATIONAL KIOSK 2.00 EA $7,973.00 $15,946 0.00% 10.00% 10.00% $1,595 $17,541
20.01.05.100 STATION ELECTRICAL (SITE TO WITHIN 5' OF ENTRY) 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000
20.01.05.10100.01M SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
20.01.05.10500.05 LARGE SHELTER (INCL. FOUNDATION & SEATING) 6.00 EA $207,000.00 $1,242,000 0.00% 10.00% 10.00% $124,200 $1,366,200
20.01.05.12000.02M STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
20.01.05.15300.01A STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000
20.01.05.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
20.01.05.2000 METAL PANEL SCREEN WALL (8' HIGH STAINLESS STEEL PICKET FEN 2,400.00 SF $45.00 $108,000 15.00% 10.00% 25.00% $27,000 $135,000
20.01.05.300 PLATFORM CONCRETE 400.00 CY $750.00 $300,000 15.00% 10.00% 25.00% $75,000 $375,000
20.01.05.400 GUIDEWAY EXCAVATION 800.00 CY $18.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000
20.01.05.500 CLASS 2 AGGREGATE BASE 400.00 CY $45.00 $18,000 15.00% 10.00% 25.00% $4,500 $22,500
20.01.05.600 STATION LIGHTING 32.00 EA $5,000.00 $160,000 0.00% 10.00% 10.00% $16,000 $176,000
Monday, January 27, 2014 Page 41 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.01.05.601 THREE-BAY TELECOMMUNICATION CABINET 1.00 EA $140,000.00 $140,000 15.00% 15.00% 30.00% $42,000 $182,000
20.01.05.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545
20.01.05.604 TRACKWAY PAVING AT PLATFORM 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900
Sum
Average
39,480.00 $3,159,804
11.25% 10.25% 21.50%
$544,659 $3,704,463Summary for Group: 20.01.05
Group 20.01.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ART FEATURES (AT GRADE) Contingency
20.01.10 ART FEATURES (1% AT GRADE) 1.00 LS $117,215.58 $117,216 15.00% 15.00% 30.00% $35,165 $152,380
Sum
Average
1.00 $117,216
15.00% 15.00% 30.00%
$35,165 $152,380Summary for Group: 20.01.10
Sum
Average
133,308.00 $12,538,774
10.91% 10.40% 21.31%
$2,063,907 $14,602,680Summary for Sub Section: 20.01
Sub Section 20.02 AERIAL STATION, STOP, SHELTER, MALL, TERMINAL, PLATFORM
Group 20.02.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PERMANENT BMP (AERIAL STATION) Contingency
20.02.01 PERMANENT BMP (AERIAL STATION) 1.00 LS $550,000.00 $550,000 0.00% 20.00% 20.00% $110,000 $660,000
Sum
Average
1.00 $550,000
0.00% 20.00% 20.00%
$110,000 $660,000Summary for Group: 20.02.01
Group 20.02.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UCSD EAST STATION Contingency
20.02.02.02 STAINLESS STEEL & GLASS SCREEN WALL (8' X 6') 3,072.00 SF $60.00 $184,320 15.00% 10.00% 25.00% $46,080 $230,400
20.02.02.03 GUARD RAILING - STAINLESS STEEL W/GLASS PANEL 52.00 LF $60.00 $3,120 15.00% 10.00% 25.00% $780 $3,900
20.02.02.04 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600
20.02.02.05 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000
20.02.02.06 ARCHITECTURAL CONCRETE PAVERS (ANCILLARY SPACES) 22,871.00 SF $20.00 $457,420 15.00% 15.00% 30.00% $137,226 $594,646
20.02.02.06 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES) 2,831.00 SF $15.00 $42,465 15.00% 10.00% 25.00% $10,616 $53,081
20.02.02.08 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
20.02.02.09 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253
20.02.02.10 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200
20.02.02.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) (UCSD EAST STATION) 385,813.00 LB $2.15 $829,498 15.00% 10.00% 25.00% $207,374 $1,036,872
20.02.02.11 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
20.02.02.12 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313
Monday, January 27, 2014 Page 42 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.02.02.14 INFORMATIONAL KIOSK 3.00 EA $7,973.00 $23,919 0.00% 10.00% 10.00% $2,392 $26,311
20.02.02.19 STAIR RAILING (STAINLESS STEEL W/GLASS PANEL) 1,077.00 LF $360.00 $387,720 15.00% 10.00% 25.00% $96,930 $484,650
20.02.02.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
20.02.02.25 LANDSCAPING 35,535.00 SF $4.70 $167,015 15.00% 10.00% 25.00% $41,754 $208,768
20.02.02.26 IRRIGATION 35,535.00 SF $1.40 $49,749 15.00% 10.00% 25.00% $12,437 $62,186
20.02.02.28 STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000
20.02.02.490605 36'' CIDH CONCRETE PILING 3,404.00 LF $507.00 $1,725,828 15.00% 15.00% 30.00% $517,748 $2,243,576
20.02.02.50 CIP CONCRETE ELEVATED WALKWAYS 16.37 CY $1,275.00 $20,872 15.00% 10.00% 25.00% $5,218 $26,090
20.02.02.52 STAIR (METAL PAN W/ CONCRETE FILL) 3,059.00 SF $25.00 $76,475 15.00% 10.00% 25.00% $19,119 $95,594
20.02.02.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 640.00 CY $440.00 $281,600 15.00% 10.00% 25.00% $70,400 $352,000
20.02.02.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 134,400.00 LB $1.00 $134,400 15.00% 10.00% 25.00% $33,600 $168,000
20.02.02.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250
20.02.02.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125
20.02.02.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000
20.02.02.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 15.00% 30.00% $114,000 $494,000
20.02.02.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 2.00 EA $1,109.00 $2,218 15.00% 10.00% 25.00% $555 $2,773
20.02.02.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900
20.02.02.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500
Sum
Average
661,188.37 $8,512,890
12.50% 10.50% 23.00%
$1,861,597 $10,374,487Summary for Group: 20.02.02
Group 20.02.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UCSD WEST STATION Contingency
20.02.03.02 STAINLESS STEEL & GLASS SCREEN WALL (8' X 6') 2,736.00 SF $60.00 $164,160 15.00% 10.00% 25.00% $41,040 $205,200
20.02.03.03 GUARD RAILING - STAINLESS STEEL W/GLASS PANEL 209.00 LF $60.00 $12,540 15.00% 10.00% 25.00% $3,135 $15,675
20.02.03.03 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600
20.02.03.05 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000
20.02.03.06 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES/ANCILLARY SPA 15,291.00 SF $15.00 $229,365 15.00% 10.00% 25.00% $57,341 $286,706
20.02.03.08 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
20.02.03.09 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253
20.02.03.10 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200
Monday, January 27, 2014 Page 43 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.02.03.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) (UCSD WEST STATION) 188,097.50 LB $2.15 $404,410 15.00% 10.00% 25.00% $101,102 $505,512
20.02.03.11 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
20.02.03.12 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313
20.02.03.14 INFORMATIONAL KIOSK 1.00 EA $7,973.00 $7,973 0.00% 10.00% 10.00% $797 $8,770
20.02.03.20 STAIR RAILING (STAINLESS STEEL W/GLASS PANEL) 3,330.00 SF $360.00 $1,198,800 15.00% 10.00% 25.00% $299,700 $1,498,500
20.02.03.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
20.02.03.26 LANDSCAPING 34,800.00 SF $4.70 $163,560 15.00% 10.00% 25.00% $40,890 $204,450
20.02.03.27 IRRIGATION 34,800.00 SF $1.40 $48,720 15.00% 10.00% 25.00% $12,180 $60,900
20.02.03.29 STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000
20.02.03.490605 36'' CIDH CONCRETE PILING 3,957.00 LF $507.00 $2,006,199 15.00% 15.00% 30.00% $601,860 $2,608,059
20.02.03.50 CIP CONCRETE ELEVATED WALKWAYS 26.10 CY $1,275.00 $33,278 15.00% 10.00% 25.00% $8,319 $41,597
20.02.03.51 STRUCTURAL STEEL ELEVATED WALKWAY SUPPORT (F&I) 120,865.00 LB $2.95 $356,552 15.00% 10.00% 25.00% $89,138 $445,690
20.02.03.52 STAIR (METAL PAN W/ CONCRETE FILL) 3,573.00 SF $25.00 $89,325 15.00% 10.00% 25.00% $22,331 $111,656
20.02.03.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 549.63 CY $440.00 $241,837 15.00% 10.00% 25.00% $60,459 $302,297
20.02.03.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 115,422.22 LB $1.00 $115,422 15.00% 10.00% 25.00% $28,856 $144,278
20.02.03.56 STRUCTURAL STEEL GATEWAY (F&I) 199,525.00 LB $2.75 $548,694 15.00% 10.00% 25.00% $137,173 $685,867
20.02.03.57 METAL ROOF (F&I, GATEWAY) 3,000.00 SF $10.00 $30,000 15.00% 10.00% 25.00% $7,500 $37,500
20.02.03.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250
20.02.03.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125
20.02.03.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000
20.02.03.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 10.00% 25.00% $95,000 $475,000
20.02.03.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 2.00 EA $1,109.00 $2,218 15.00% 10.00% 25.00% $555 $2,773
20.02.03.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900
20.02.03.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500
Sum
Average
759,062.45 $9,779,324
12.66% 10.16% 22.81%
$2,152,745 $11,932,069Summary for Group: 20.02.03
Group 20.02.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NOBEL STATION Contingency
20.02.04.01 STAINLESS STEEL & GLASS SCREEN WALL (8' X 6') 5,760.00 SF $95.00 $547,200 15.00% 10.00% 25.00% $136,800 $684,000
20.02.04.02 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 9,200.00 SF $20.00 $184,000 0.00% 10.00% 10.00% $18,400 $202,400
Monday, January 27, 2014 Page 44 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.02.04.03 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000
20.02.04.04 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES/ANCILLARY SPA 9,102.00 SF $15.00 $136,530 15.00% 10.00% 25.00% $34,133 $170,663
20.02.04.06 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
20.02.04.07 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253
20.02.04.08 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200
20.02.04.10 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
20.02.04.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) (NOBEL STATION) 213,930.00 LB $2.15 $459,950 15.00% 10.00% 25.00% $114,987 $574,937
20.02.04.11 BIKE LOCKER 10.00 EA $2,450.00 $24,500 15.00% 10.00% 25.00% $6,125 $30,625
20.02.04.13 INFORMATIONAL KIOSK 4.00 EA $7,973.00 $31,892 0.00% 10.00% 10.00% $3,189 $35,081
20.02.04.20 STAIR RAILING (STAINLESS STEEL W/GLASS PANELS) 2,484.00 SF $60.00 $149,040 15.00% 10.00% 25.00% $37,260 $186,300
20.02.04.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
20.02.04.32 STATION PLUMBING 9,200.00 SF $20.00 $184,000 15.00% 10.00% 25.00% $46,000 $230,000
20.02.04.490605 36'' CIDH CONCRETE PILING 3,612.00 LF $507.00 $1,831,284 15.00% 15.00% 30.00% $549,385 $2,380,669
20.02.04.50 CIP CONCRETE ELEVATED WALKWAYS 91.24 CY $1,275.00 $116,331 15.00% 10.00% 25.00% $29,083 $145,414
20.02.04.52 STAIR (METAL PAN W/ CONCRETE FILL) 3,750.00 SF $25.00 $93,750 15.00% 10.00% 25.00% $23,438 $117,188
20.02.04.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 900.74 CY $440.00 $396,326 15.00% 10.00% 25.00% $99,081 $495,407
20.02.04.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 189,155.56 LB $1.00 $189,156 15.00% 10.00% 25.00% $47,289 $236,444
20.02.04.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250
20.02.04.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125
20.02.04.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000
20.02.04.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 10.00% 25.00% $95,000 $475,000
20.02.04.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 3.00 EA $1,109.00 $3,327 15.00% 10.00% 25.00% $832 $4,159
20.02.04.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900
20.02.04.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500
Sum
Average
458,475.54 $8,029,307
12.12% 10.19% 22.31%
$1,707,707 $9,737,014Summary for Group: 20.02.04
Group 20.02.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
EXECUTIVE STATION Contingency
20.02.05.01 STAINLESS STEEL PICKET FENCE SCREEN WALL (8' X 6') 3,328.00 SF $95.00 $316,160 15.00% 10.00% 25.00% $79,040 $395,200
20.02.05.02 STAINLESS STEEL & GLASS SCREEN WALL (8' X 6') 2,592.00 SF $60.00 $155,520 15.00% 10.00% 25.00% $38,880 $194,400
Monday, January 27, 2014 Page 45 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.02.05.03 STAINLESS STEEL & GLASS SCREEN WALL (8' X 3') - PED BRIDGE 2,688.00 SF $112.00 $301,056 15.00% 10.00% 25.00% $75,264 $376,320
20.02.05.04 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 9,200.00 SF $20.00 $184,000 0.00% 10.00% 10.00% $18,400 $202,400
20.02.05.05 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000
20.02.05.06 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES/ANCILLARY SPA 11,317.00 SF $15.00 $169,755 15.00% 10.00% 25.00% $42,439 $212,194
20.02.05.08 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
20.02.05.09 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253
20.02.05.10 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200
20.02.05.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) 468,116.40 LB $2.15 $1,006,450 15.00% 10.00% 25.00% $251,613 $1,258,063
20.02.05.11 SMALL CANOPY (7' X 20') - STAINLESS STEEL 1.00 EA $45,000.00 $45,000 0.00% 10.00% 10.00% $4,500 $49,500
20.02.05.12 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
20.02.05.13 BIKE LOCKER 6.00 EA $2,450.00 $14,700 15.00% 10.00% 25.00% $3,675 $18,375
20.02.05.15 INFORMATIONAL KIOSK 4.00 EA $7,973.00 $31,892 0.00% 10.00% 10.00% $3,189 $35,081
20.02.05.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
20.02.05.22 STAIR RAILING (STAINLESS STEEL W/GLASS PANELS) 1,028.00 LF $360.00 $370,080 15.00% 10.00% 25.00% $92,520 $462,600
20.02.05.29 LANDSCAPING 3,500.00 SF $4.70 $16,450 15.00% 10.00% 25.00% $4,113 $20,563
20.02.05.30 IRRIGATION 3,500.00 SF $1.40 $4,900 15.00% 10.00% 25.00% $1,225 $6,125
20.02.05.32 STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000
20.02.05.490605 36'' CIDH CONCRETE PILING 4,785.00 LF $507.00 $2,425,995 15.00% 15.00% 30.00% $727,799 $3,153,794
20.02.05.50 CIP CONCRETE ELEVATED WALKWAYS 149.98 CY $1,275.00 $191,225 15.00% 10.00% 25.00% $47,806 $239,031
20.02.05.52 STAIR (METAL PAN W/ CONCRETE FILL) 1,896.00 SF $25.00 $47,400 15.00% 10.00% 25.00% $11,850 $59,250
20.02.05.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 1,034.52 CY $440.00 $455,189 15.00% 10.00% 25.00% $113,797 $568,986
20.02.05.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 217,248.89 LB $1.00 $217,249 15.00% 10.00% 25.00% $54,312 $271,561
20.02.05.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250
20.02.05.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125
20.02.05.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000
20.02.05.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 10.00% 25.00% $95,000 $475,000
20.02.05.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545
20.02.05.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900
20.02.05.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500
Monday, January 27, 2014 Page 46 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
752,471.79 $9,855,478
12.10% 10.16% 22.26%
$2,187,236 $12,042,714Summary for Group: 20.02.05
Group 20.02.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UTC STATION Contingency
20.02.06.01 PICKET FENCE SCREEN WALL (8' X 6') 3,328.00 SF $32.00 $106,496 15.00% 10.00% 25.00% $26,624 $133,120
20.02.06.02 GLASS SCREEN WALL (8' X 6') 2,592.00 SF $112.00 $290,304 15.00% 10.00% 25.00% $72,576 $362,880
20.02.06.03 GLASS SCREEN WALL (8' X 3') - PED BRIDGE 3,552.00 SF $112.00 $397,824 15.00% 10.00% 25.00% $99,456 $497,280
20.02.06.04 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 9,200.00 SF $20.00 $184,000 0.00% 10.00% 10.00% $18,400 $202,400
20.02.06.05 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000
20.02.06.06 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES/ANCILLARY SPA 10,490.00 SF $15.00 $157,350 15.00% 10.00% 25.00% $39,338 $196,688
20.02.06.08 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
20.02.06.09 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253
20.02.06.10 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200
20.02.06.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) 554,519.00 LB $2.15 $1,192,216 15.00% 10.00% 25.00% $298,054 $1,490,270
20.02.06.11 SMALL CANOPY (7' X 20') - STAINLESS STEEL 2.00 EA $45,000.00 $90,000 0.00% 10.00% 10.00% $9,000 $99,000
20.02.06.12 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750
20.02.06.15 INFORMATIONAL KIOSK 4.00 EA $7,973.00 $31,892 0.00% 10.00% 10.00% $3,189 $35,081
20.02.06.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
20.02.06.22 STAIR RAILING (STAINLESS STEEL W/GLASS) 1,085.00 LF $360.00 $390,600 15.00% 10.00% 25.00% $97,650 $488,250
20.02.06.29 LANDSCAPING 3,500.00 SF $4.70 $16,450 15.00% 10.00% 25.00% $4,113 $20,563
20.02.06.30 IRRIGATION 3,500.00 SF $1.40 $4,900 15.00% 10.00% 25.00% $1,225 $6,125
20.02.06.31 OPERATOR SHELTER 100.00 SF $33.00 $3,300 15.00% 10.00% 25.00% $825 $4,125
20.02.06.34 STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000
20.02.06.490605 36'' CIDH CONCRETE PILING 4,850.00 LF $507.00 $2,458,950 15.00% 15.00% 30.00% $737,685 $3,196,635
20.02.06.50 CIP CONCRETE ELEVATED WALKWAYS 121.33 CY $1,275.00 $154,696 15.00% 15.00% 30.00% $46,409 $201,104
20.02.06.52 STAIR (METAL PAN W/ CONCRETE FILL) 3,340.00 SF $25.00 $83,500 15.00% 10.00% 25.00% $20,875 $104,375
20.02.06.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 1,156.15 CY $440.00 $508,706 15.00% 10.00% 25.00% $127,177 $635,883
20.02.06.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 242,791.11 LB $1.00 $242,791 15.00% 10.00% 25.00% $60,698 $303,489
20.02.06.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250
20.02.06.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125
Monday, January 27, 2014 Page 47 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.02.06.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000
20.02.06.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 10.00% 25.00% $95,000 $475,000
20.02.06.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 2.00 EA $1,109.00 $2,218 15.00% 10.00% 25.00% $555 $2,773
20.02.06.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900
20.02.06.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500
Sum
Average
866,205.59 $10,214,215
12.10% 10.32% 22.42%
$2,279,552 $12,493,767Summary for Group: 20.02.06
Group 20.02.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ART FEATURES (AERIAL) Contingency
20.02.10 ART FEATURES (1% AERIAL) 1.00 LS $463,912.14 $463,912 15.00% 15.00% 30.00% $139,174 $603,086
Sum
Average
1.00 $463,912
15.00% 15.00% 30.00%
$139,174 $603,086Summary for Group: 20.02.10
Sum
Average
3,497,405.74 $47,405,126
12.24% 10.36% 22.60%
$10,438,011 $57,843,137Summary for Sub Section: 20.02
Sub Section 20.06 AUTOMOBILE PARKING MULTI-STORY STRUCTURE
Group 20.06.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PARKING STRUCTURE (NOBEL STATION) Contingency
20.06.01.01 PARKING STRUCTURE, ABOVE GROUND (NOBEL STATION) 700.00STALL $21,000.00 $14,700,000 5.00% 10.00% 15.00% $2,205,000 $16,905,000
20.06.01.02 PARKING STRUCTURE, BELOW GROUND (NOBEL STATION) 100.00STALL $30,000.00 $3,000,000 5.00% 20.00% 25.00% $750,000 $3,750,000
Sum
Average
800.00 $17,700,000
5.00% 15.00% 20.00%
$2,955,000 $20,655,000Summary for Group: 20.06.01
Sum
Average
800.00 $17,700,000
5.00% 15.00% 20.00%
$2,955,000 $20,655,000Summary for Sub Section: 20.06
Sub Section 20.07 ELEVATORS, ESCALATORS
Group 20.07.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SINGLE ELEVATORS Contingency
20.07.01.05 SINGLE ELEVATOR (EXECUTIVE STATION) 2.00 EA $710,000.00 $1,420,000 0.00% 15.00% 15.00% $213,000 $1,633,000
20.07.01.06 SINGLE ELEVATOR (UTC STATION) 3.00 EA $710,000.00 $2,130,000 0.00% 15.00% 15.00% $319,500 $2,449,500
Sum
Average
5.00 $3,550,000
0.00% 15.00% 15.00%
$532,500 $4,082,500Summary for Group: 20.07.01
Group 20.07.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
DOUBLE ELEVATORS Contingency
20.07.02.02 DOUBLE ELEVATOR (UCSD EAST STATION) 2.00 EA $810,000.00 $1,620,000 0.00% 10.00% 10.00% $162,000 $1,782,000
Monday, January 27, 2014 Page 48 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
20.07.02.03 DOUBLE ELEVATOR (UCSD WEST STATION) 1.00 EA $810,000.00 $810,000 0.00% 10.00% 10.00% $81,000 $891,000
20.07.02.04 SINGLE ELEVATOR (NOBEL STATION) 3.00 EA $710,000.00 $2,130,000 0.00% 10.00% 10.00% $213,000 $2,343,000
20.07.02.05 DOUBLE ELEVATOR (EXECUTIVE STATION) 1.00 EA $810,000.00 $810,000 0.00% 10.00% 10.00% $81,000 $891,000
20.07.02.06 DOUBLE ELEVATOR (UTC STATION) 1.00 EA $810,000.00 $810,000 0.00% 10.00% 10.00% $81,000 $891,000
Sum
Average
8.00 $6,180,000
0.00% 10.00% 10.00%
$618,000 $6,798,000Summary for Group: 20.07.02
Sum
Average
13.00 $9,730,000
0.00% 11.43% 11.43%
$1,150,500 $10,880,500Summary for Sub Section: 20.07
Sum
Average
3,631,526.74 $87,373,900
11.37% 10.44% 21.81%
$16,607,417 $103,981,317Summary for Section 20
Section 40 SITEWORK AND SPECIAL CONDITIONS
Sub Section 40.01 DEMOLITION, CLEARING, EARTHWORK
Group 40.01.01A
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
DEMOLISH PEDESTRIAN BRIDGE (750+50) Contingency
40.01.01A DEMOLISH PEDESTRIAN BRIDGE (750+50) 7,332.00 SF $27.00 $197,964 10.00% 10.00% 20.00% $39,593 $237,557
Sum
Average
7,332.00 $197,964
10.00% 10.00% 20.00%
$39,593 $237,557Summary for Group: 40.01.01A
Group 40.01.01B
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
DEMOLISH PEDESTRIAN BRIDGE (760+50) Contingency
40.01.01B DEMOLISH PEDESTRIAN BRIDGE (760+50) 9,490.00 SF $27.00 $256,230 10.00% 10.00% 20.00% $51,246 $307,476
Sum
Average
9,490.00 $256,230
10.00% 10.00% 20.00%
$51,246 $307,476Summary for Group: 40.01.01B
Group 40.01.02A
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
REMOVE EXISTING CANOPY AND LOADING DOCK Contingency
40.01.02A REMOVE EXISTING CANOPY AND LOADING DOCK 2,304.00 SF $70.00 $161,280 10.00% 10.00% 20.00% $32,256 $193,536
Sum
Average
2,304.00 $161,280
10.00% 10.00% 20.00%
$32,256 $193,536Summary for Group: 40.01.02A
Group 40.01.02B
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
REMOVE & SALVAGE EXISTING TRACK (TYPE 136RE) Contingency
40.01.02B REMOVE & SALVAGE EXISTING TRACK (TYPE 136RE) 1,486.00 LF $27.00 $40,122 10.00% 15.00% 25.00% $10,031 $50,153
Sum
Average
1,486.00 $40,122
10.00% 15.00% 25.00%
$10,031 $50,153Summary for Group: 40.01.02B
Group 40.01.02C
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
REMOVE & SALVAGE EXISTING TURNOUT Contingency
Monday, January 27, 2014 Page 49 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.01.02C REMOVE & SALVAGE EXISTING TURNOUT (NO 15) 1.00 EA $12,948.00 $12,948 0.00% 15.00% 15.00% $1,942 $14,890
40.01.02C REMOVE & SALVAGE EXISTING TURNOUT (NO 20) 1.00 EA $23,304.00 $23,304 0.00% 15.00% 15.00% $3,496 $26,800
Sum
Average
2.00 $36,252
0.00% 15.00% 15.00%
$5,438 $41,690Summary for Group: 40.01.02C
Group 40.01.02D
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
REMOVE & SALVAGE EXISTING SPUR AND TURNOUT Contingency
40.01.02D REMOVE & SALVAGE EXISTING TURNOUT (NO 15) 1.00 EA $12,948.00 $12,948 0.00% 15.00% 15.00% $1,942 $14,890
Sum
Average
1.00 $12,948
0.00% 15.00% 15.00%
$1,942 $14,890Summary for Group: 40.01.02D
Group 40.01.02E
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SALVAGE EXISTING TURNOUT Contingency
40.01.02E SALVAGE EXISTING TURNOUT 1.00 EA $11,771.00 $11,771 10.00% 15.00% 25.00% $2,943 $14,714
Sum
Average
1.00 $11,771
10.00% 15.00% 25.00%
$2,943 $14,714Summary for Group: 40.01.02E
Group 40.01.02F
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
REMOVE & SALVAGE OH SIGNAL SYSTEM Contingency
40.01.02F REMOVE & SALVAGE OH SIGNAL SYSTEM 1.00 EA $50,000.00 $50,000 0.00% 15.00% 15.00% $7,500 $57,500
Sum
Average
1.00 $50,000
0.00% 15.00% 15.00%
$7,500 $57,500Summary for Group: 40.01.02F
Group 40.01.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PARTIAL BRIDGE REMOVAL Contingency
40.01.03.157560 BRIDGE REMOVAL (PARTIAL, SAN DIEGO RIVER) 1.00 LS $25,000.00 $25,000 10.00% 10.00% 20.00% $5,000 $30,000
Sum
Average
1.00 $25,000
10.00% 10.00% 20.00%
$5,000 $30,000Summary for Group: 40.01.03
Group 40.01.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CLEARING AND GRUBBING (GUIDEWAY) Contingency
40.01.04 CLEARING AND GRUBBING 10.21 AC $4,022.00 $41,065 10.00% 15.00% 25.00% $10,266 $51,331
40.01.04 CLEARING AND GRUBBING 38.52 AC $4,022.00 $154,927 10.00% 15.00% 25.00% $38,732 $193,659
40.01.04 CLEARING AND GRUBBING 18.50 AC $4,022.00 $74,407 10.00% 15.00% 25.00% $18,602 $93,009
40.01.04 CLEARING AND GRUBBING 0.69 AC $4,022.00 $2,771 10.00% 15.00% 25.00% $693 $3,464
Sum
Average
67.92 $273,170
10.00% 15.00% 25.00%
$68,293 $341,463Summary for Group: 40.01.04
Group 40.01.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PERMANENT BMP (DEMOLITION, CLEARING, EARTHWORK) Contingency
Monday, January 27, 2014 Page 50 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.01.05 PERMANENT BMP (DEMOLITION, CLEARING, EARTHWORK) 1.00 LS $50,000.00 $50,000 0.00% 20.00% 20.00% $10,000 $60,000
Sum
Average
1.00 $50,000
0.00% 20.00% 20.00%
$10,000 $60,000Summary for Group: 40.01.05
Group 40.01.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
DEMOLISH TEMPORARY WALL Contingency
40.01.06 DEMOLITION OF TEMPORARY WALL (SHOOFLY) 906.00 LF $40.00 $36,240 10.00% 15.00% 25.00% $9,060 $45,300
Sum
Average
906.00 $36,240
10.00% 15.00% 25.00%
$9,060 $45,300Summary for Group: 40.01.06
Group 40.01.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
REMOVE EXIST RAMP AND STAIRS Contingency
40.01.07 REMOVE EXIST RAMP AND STAIRS 715.00 SF $70.00 $50,050 10.00% 10.00% 20.00% $10,010 $60,060
Sum
Average
715.00 $50,050
10.00% 10.00% 20.00%
$10,010 $60,060Summary for Group: 40.01.07
Group 40.01.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
REMOVE EXIST OPEN CHANNEL Contingency
40.01.08 REMOVE EXIST OPEN CHANNEL 36,555.00 SF $5.50 $201,053 5.00% 15.00% 20.00% $40,211 $241,263
Sum
Average
36,555.00 $201,053
5.00% 15.00% 20.00%
$40,211 $241,263Summary for Group: 40.01.08
Sum
Average
58,862.92 $1,402,080
6.94% 13.89% 20.83%
$293,521 $1,695,601Summary for Sub Section: 40.01
Sub Section 40.02 SITE UTILITIES, UTILITY RELOCATION
Group 40.02.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
WET UTILITY RELOCATION Contingency
40.02.01.1101 CONNECT TO Exist 30" RCSC WATER 1.00 EA $9,344.00 $9,344 15.00% 10.00% 25.00% $2,336 $11,680
40.02.01.1102 CONNECT TO Exist 24" SCRW WATER 2.00 EA $8,721.00 $17,442 15.00% 10.00% 25.00% $4,361 $21,803
40.02.01.1102 CONNECT TO Exist 24" SCRW WATER 2.00 EA $8,721.00 $17,442 15.00% 10.00% 25.00% $4,361 $21,803
40.02.01.1103 CONNECT TO Exist 20" ACP WATER 1.00 EA $4,361.00 $4,361 15.00% 10.00% 25.00% $1,090 $5,451
40.02.01.1104 CONNECT TO Exist 16" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1104 CONNECT TO Exist 16" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1105 CONNECT TO Exist 12" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1105 CONNECT TO Exist 12" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1105 CONNECT TO Exist 12" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1106 CONNECT TO Exist 10" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
Monday, January 27, 2014 Page 51 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.1106 CONNECT TO Exist 10" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1107 CONNECT TO Exist 8" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1107 CONNECT TO Exist 8" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1108 CONNECT TO Exist 6" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1110 CONNECT TO Exist 16" PVC RECLAIMED WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1111 CONNECT TO Exist 12" PVC WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1112 CONNECT TO Exist 8" PVC WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1113 CONNECT TO Exist 16" CIP WATER 3.00 EA $3,474.00 $10,422 15.00% 10.00% 25.00% $2,606 $13,028
40.02.01.1114 CONNECT TO Exist 12" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1114 CONNECT TO Exist 12" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1114 CONNECT TO Exist 12" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1114 CONNECT TO Exist 12" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1115 CONNECT TO Exist 10" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1116 CONNECT TO Exist 8" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1116 CONNECT TO Exist 8" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1117 CONNECT TO Exist 6" FH LEAD 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685
40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343
40.02.01.1118 CONNECT TO Exist 8" WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584
40.02.01.1119 CONNECT TO Exist 6" WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584
40.02.01.1120 CONNECT TO Exist 4" WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584
40.02.01.1121 CONNECT TO Exist 2" WATER SERVICE 2.00 EA $2,867.00 $5,734 15.00% 10.00% 25.00% $1,434 $7,168
40.02.01.1122 CONNECT TO Exist 1 1/4" COPPER WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584
40.02.01.1123 CONNECT TO Exist 1" COPPER WATER SERVICE 4.00 EA $2,867.00 $11,468 15.00% 10.00% 25.00% $2,867 $14,335
40.02.01.1123 CONNECT TO Exist 1" COPPER WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584
Monday, January 27, 2014 Page 52 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.1124 CONNECT TO Exist xx" WATER LATERAL 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584
40.02.01.1125 CONNECT TO Exist 36" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.1126 CONNECT TO Exist 24" WSP CASING WITH WELDED JOINT 1.00 EA $935.00 $935 15.00% 10.00% 25.00% $234 $1,169
40.02.01.1127 CONNECT TO Exist 22" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.1128 CONNECT TO Exist 18" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.1129 CONNECT TO Exist 16" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.1130 CONNECT TO Exist 14" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.1131 CONNECT 26" HDPE WATER TO 20" PVC WATER 2.00 EA $7,475.00 $14,950 15.00% 10.00% 25.00% $3,738 $18,688
40.02.01.1202 24" 22.5^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690
40.02.01.1202 24" 22.5^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690
40.02.01.1203 20" 45^ BEND 6.00 EA $3,738.00 $22,428 15.00% 10.00% 25.00% $5,607 $28,035
40.02.01.1204 20" 22.5^ BEND 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673
40.02.01.1205 16" 45^ BEND 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673
40.02.01.1205 16" 45^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690
40.02.01.1205 16" 45^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690
40.02.01.1205 16" 45^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690
40.02.01.1206 12" 90^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1207 12" 45^ BEND 4.00 EA $1,247.00 $4,988 15.00% 10.00% 25.00% $1,247 $6,235
40.02.01.1207 12" 45^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1207 12" 45^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1207 12" 45^ BEND 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118
40.02.01.1208 12" 11.25^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1209 10" 45^ BEND 4.00 EA $1,247.00 $4,988 15.00% 10.00% 25.00% $1,247 $6,235
40.02.01.1209 10" 45^ BEND 4.00 EA $1,247.00 $4,988 15.00% 10.00% 25.00% $1,247 $6,235
40.02.01.1210 10" 11.25^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1211 8" 45^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1211 8" 45^ BEND 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118
40.02.01.1212 8" 11.25^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1213 6" 45^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
Monday, January 27, 2014 Page 53 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.1214 20" X 30" TEE 1.00 EA $4,361.00 $4,361 15.00% 10.00% 25.00% $1,090 $5,451
40.02.01.1216 20" X 12" TEE 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673
40.02.01.1217 20" X x" TEE 2.00 EA $3,738.00 $7,476 15.00% 10.00% 25.00% $1,869 $9,345
40.02.01.1218 16" X 12" TEE 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673
40.02.01.1219 16" X 6" TEE 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673
40.02.01.1220 12" X 12" TEE 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1221 12" X 6" TEE 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1222 10" X 8" TEE 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118
40.02.01.1223 10" X 6" TEE 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1223 10" X 6" TEE 8.00 EA $1,247.00 $9,976 15.00% 10.00% 25.00% $2,494 $12,470
40.02.01.1224 10" X 4" TEE 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1301 36" WSP CASING 24.00 LF $779.00 $18,696 15.00% 10.00% 25.00% $4,674 $23,370
40.02.01.1302 28" WSP CASING - JACK CONSTRUCTION 120.00 LF $1,496.00 $179,520 15.00% 10.00% 25.00% $44,880 $224,400
40.02.01.1303 24" WSP CASING 44.00 LF $413.00 $18,172 15.00% 10.00% 25.00% $4,543 $22,715
40.02.01.1304 22" WSP CASING 30.00 LF $413.00 $12,390 15.00% 10.00% 25.00% $3,098 $15,488
40.02.01.1304 22" WSP CASING 48.00 LF $413.00 $19,824 15.00% 10.00% 25.00% $4,956 $24,780
40.02.01.1305 20" WSP CASING 49.00 LF $339.00 $16,611 15.00% 10.00% 25.00% $4,153 $20,764
40.02.01.1306 18" WSP CASING 37.00 LF $305.00 $11,285 15.00% 10.00% 25.00% $2,821 $14,106
40.02.01.1307 16" WSP CASING 38.00 LF $200.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500
40.02.01.1308 14" WSP CASING 50.00 LF $182.00 $9,100 15.00% 10.00% 25.00% $2,275 $11,375
40.02.01.1402 24" SCRW WATER 66.00 LF $812.00 $53,592 15.00% 10.00% 25.00% $13,398 $66,990
40.02.01.1402 24" SCRW WATER 130.00 LF $812.00 $105,560 15.00% 10.00% 25.00% $26,390 $131,950
40.02.01.1403 26" HDPE WATER - TRENCHLESS CONSTRUCTION 120.00 LF $498.00 $59,760 15.00% 10.00% 25.00% $14,940 $74,700
40.02.01.1404 20" PVC WATER 458.00 LF $207.00 $94,806 15.00% 10.00% 25.00% $23,702 $118,508
40.02.01.1405 16" PVC RECLAIMED WATER 41.00 LF $166.00 $6,806 15.00% 10.00% 25.00% $1,702 $8,508
40.02.01.1406 16" PVC WATER 54.00 LF $166.00 $8,964 15.00% 10.00% 25.00% $2,241 $11,205
40.02.01.1406 16" PVC WATER 54.00 LF $166.00 $8,964 15.00% 10.00% 25.00% $2,241 $11,205
40.02.01.1406 16" PVC WATER 1,645.00 LF $166.00 $273,070 15.00% 10.00% 25.00% $68,268 $341,338
40.02.01.1407 12" PVC WATER 166.00 LF $129.00 $21,414 15.00% 10.00% 25.00% $5,354 $26,768
Monday, January 27, 2014 Page 54 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.1407 12" PVC WATER 185.00 LF $129.00 $23,865 15.00% 10.00% 25.00% $5,966 $29,831
40.02.01.1407 12" PVC WATER 24.00 LF $129.00 $3,096 15.00% 10.00% 25.00% $774 $3,870
40.02.01.1407 12" PVC WATER 43.00 LF $129.00 $5,547 15.00% 10.00% 25.00% $1,387 $6,934
40.02.01.1407 12" PVC WATER 30.00 LF $129.00 $3,870 15.00% 10.00% 25.00% $968 $4,838
40.02.01.1408 10" PVC WATER 157.00 LF $104.00 $16,328 15.00% 10.00% 25.00% $4,082 $20,410
40.02.01.1408 10" PVC WATER 56.00 LF $104.00 $5,824 15.00% 10.00% 25.00% $1,456 $7,280
40.02.01.1408 10" PVC WATER 1,561.00 LF $104.00 $162,344 15.00% 10.00% 25.00% $40,586 $202,930
40.02.01.1409 8" PVC WATER 83.00 LF $94.00 $7,802 15.00% 10.00% 25.00% $1,951 $9,753
40.02.01.1409 8" PVC WATER 49.00 LF $94.00 $4,606 15.00% 10.00% 25.00% $1,152 $5,758
40.02.01.1409 8" PVC WATER 57.00 LF $94.00 $5,358 15.00% 10.00% 25.00% $1,340 $6,698
40.02.01.1410 6" PVC WATER 10.00 LF $94.00 $940 15.00% 10.00% 25.00% $235 $1,175
40.02.01.1411 6" DIP FH HEAD 8.00 LF $351.00 $2,808 15.00% 10.00% 25.00% $702 $3,510
40.02.01.1411 6" DIP FH HEAD 10.00 LF $351.00 $3,510 15.00% 10.00% 25.00% $878 $4,388
40.02.01.1411 6" DIP FH HEAD 79.00 LF $351.00 $27,729 15.00% 10.00% 25.00% $6,932 $34,661
40.02.01.1411 6" DIP FH HEAD 62.00 LF $351.00 $21,762 15.00% 10.00% 25.00% $5,441 $27,203
40.02.01.1411 6" DIP FH HEAD 13.00 LF $351.00 $4,563 15.00% 10.00% 25.00% $1,141 $5,704
40.02.01.1411 6" DIP FH HEAD 7.00 LF $351.00 $2,457 15.00% 10.00% 25.00% $614 $3,071
40.02.01.1411 6" DIP FH HEAD 6.00 LF $351.00 $2,106 15.00% 10.00% 25.00% $527 $2,633
40.02.01.1411 6" DIP FH HEAD 202.00 LF $351.00 $70,902 15.00% 10.00% 25.00% $17,726 $88,628
40.02.01.1412 8" PVC WATER SERVICE 40.00 LF $351.00 $14,040 15.00% 10.00% 25.00% $3,510 $17,550
40.02.01.1413 4" PVC WATER SERVICE 10.00 LF $351.00 $3,510 15.00% 10.00% 25.00% $878 $4,388
40.02.01.1414 2" PVC WATER SERVICE 8.00 LF $189.00 $1,512 15.00% 10.00% 25.00% $378 $1,890
40.02.01.1415 1" COPPER WATER SERVICE 106.00 LF $187.00 $19,822 15.00% 10.00% 25.00% $4,956 $24,778
40.02.01.1416 XX" WATER SERVICE 21.00 EA $351.00 $7,371 15.00% 10.00% 25.00% $1,843 $9,214
40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531
40.02.01.1417 FIRE HYDRANT 4.00 EA $8,425.00 $33,700 15.00% 10.00% 25.00% $8,425 $42,125
40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531
40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531
40.02.01.1417 FIRE HYDRANT 2.00 EA $8,425.00 $16,850 15.00% 10.00% 25.00% $4,213 $21,063
Monday, January 27, 2014 Page 55 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531
40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531
40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531
40.02.01.1418 1 1/4" CORPORATION STOP 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.1419 1" CORPORATION STOP 4.00 EA $1,670.00 $6,680 15.00% 10.00% 25.00% $1,670 $8,350
40.02.01.1419 1" CORPORATION STOP 1.00 EA $1,670.00 $1,670 15.00% 10.00% 25.00% $418 $2,088
40.02.01.1420 8" ABOVE GROUND METER INSTALLATION WITH BYPASS PER SDRS 1.00 EA $8,645.00 $8,645 15.00% 10.00% 25.00% $2,161 $10,806
40.02.01.1421 2" POLYMERE Conc METER BOX AND APPURTENANCES PER SDRSD 1.00 EA $1,200.00 $1,200 15.00% 10.00% 25.00% $300 $1,500
40.02.01.1422 1" POLYMERE Conc METER BOX AND APPURTENANCES PER SDRSD 2.00 EA $1,200.00 $2,400 15.00% 10.00% 25.00% $600 $3,000
40.02.01.1424 Abn Exist 24" SCRW WATER 63.00 LF $19.00 $1,197 15.00% 10.00% 25.00% $299 $1,496
40.02.01.1424 Abn Exist 24" SCRW WATER 126.00 LF $19.00 $2,394 15.00% 10.00% 25.00% $599 $2,993
40.02.01.1425 Abn Exist 20" WATER 619.00 LF $19.00 $11,761 15.00% 10.00% 25.00% $2,940 $14,701
40.02.01.1426 Abn Exist 16" ACP WATER 47.00 LF $19.00 $893 15.00% 10.00% 25.00% $223 $1,116
40.02.01.1426 Abn Exist 16" ACP WATER 1,622.00 LF $19.00 $30,818 15.00% 10.00% 25.00% $7,705 $38,523
40.02.01.1427 Abn Exist 10" ACP WATER 147.00 LF $19.00 $2,793 15.00% 10.00% 25.00% $698 $3,491
40.02.01.1427 Abn Exist 10" ACP WATER 1,538.00 LF $19.00 $29,222 15.00% 10.00% 25.00% $7,306 $36,528
40.02.01.1428 Abn Exist 8" ACP WATER 83.00 LF $19.00 $1,577 15.00% 10.00% 25.00% $394 $1,971
40.02.01.1428 Abn Exist 8" ACP WATER 15.00 LF $19.00 $285 15.00% 10.00% 25.00% $71 $356
40.02.01.1429 Abn Exist 16" PVC RECLAIMED WATER 34.00 LF $19.00 $646 15.00% 10.00% 25.00% $162 $808
40.02.01.1430 Abn Exist 12" PVC WATER 18.00 LF $19.00 $342 15.00% 10.00% 25.00% $86 $428
40.02.01.1431 Abn Exist 12" CIP WATER 183.00 LF $19.00 $3,477 15.00% 10.00% 25.00% $869 $4,346
40.02.01.1431 Abn Exist 12" CIP WATER 176.00 LF $19.00 $3,344 15.00% 10.00% 25.00% $836 $4,180
40.02.01.1432 Abn Exist 6" FH LEAD 17.00 LF $19.00 $323 15.00% 10.00% 25.00% $81 $404
40.02.01.1432 Abn Exist 6" FH LEAD 206.00 LF $19.00 $3,914 15.00% 10.00% 25.00% $979 $4,893
40.02.01.1432 Abn Exist 6" FH LEAD 52.00 LF $19.00 $988 15.00% 10.00% 25.00% $247 $1,235
40.02.01.1432 Abn Exist 6" FH LEAD 55.00 LF $19.00 $1,045 15.00% 10.00% 25.00% $261 $1,306
40.02.01.1432 Abn Exist 6" FH LEAD 14.00 LF $19.00 $266 15.00% 10.00% 25.00% $67 $333
40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24
40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24
Monday, January 27, 2014 Page 56 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24
40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24
40.02.01.1433 REMOVE Exist FIRE HYDRANT 2.00 LF $19.00 $38 15.00% 10.00% 25.00% $10 $48
40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24
40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24
40.02.01.1433 REMOVE Exist FIRE HYDRANT 4.00 LF $19.00 $76 15.00% 10.00% 25.00% $19 $95
40.02.01.1434 Abn Exist MH 2.00 LF $1,237.00 $2,474 15.00% 10.00% 25.00% $619 $3,093
40.02.01.1435 Abn Exist 8" WATER SERVICE 48.00 LF $19.00 $912 15.00% 10.00% 25.00% $228 $1,140
40.02.01.1436 Abn Exist 6" WATER SERVICE 15.00 LF $19.00 $285 15.00% 10.00% 25.00% $71 $356
40.02.01.1437 Abn Exist 1 1/4" COPPER WATER SERVICE 20.00 LF $19.00 $380 15.00% 10.00% 25.00% $95 $475
40.02.01.1438 Abn Exist 1" COPPER WATER SERVICE 75.00 LF $19.00 $1,425 15.00% 10.00% 25.00% $356 $1,781
40.02.01.1438 Abn Exist 1" COPPER WATER SERVICE 14.00 LF $19.00 $266 15.00% 10.00% 25.00% $67 $333
40.02.01.1439 Abn Exist XX" WATER SERVICE 12.00 LF $19.00 $228 15.00% 10.00% 25.00% $57 $285
40.02.01.1501 20" BUTTERFLY VALVE 2.00 LF $12,583.00 $25,166 15.00% 10.00% 25.00% $6,292 $31,458
40.02.01.1502 16" BUTTERFLY VALVE 1.00 EA $347.00 $347 15.00% 10.00% 25.00% $87 $434
40.02.01.1503 12" GATE VALVE 2.00 EA $2,866.00 $5,732 15.00% 10.00% 25.00% $1,433 $7,165
40.02.01.1503 12" GATE VALVE 1.00 EA $2,866.00 $2,866 15.00% 10.00% 25.00% $717 $3,583
40.02.01.1504 10" GATE VALVE 2.00 EA $2,368.00 $4,736 15.00% 10.00% 25.00% $1,184 $5,920
40.02.01.1505 8" GATE VALVE 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.1505 8" GATE VALVE 2.00 EA $1,870.00 $3,740 15.00% 10.00% 25.00% $935 $4,675
40.02.01.1506 6" GATE VALVE 6.00 EA $1,558.00 $9,348 15.00% 10.00% 25.00% $2,337 $11,685
40.02.01.1506 6" GATE VALVE 1.00 EA $1,558.00 $1,558 15.00% 10.00% 25.00% $390 $1,948
40.02.01.1506 6" GATE VALVE 1.00 EA $1,558.00 $1,558 15.00% 10.00% 25.00% $390 $1,948
40.02.01.1506 6" GATE VALVE 2.00 EA $1,558.00 $3,116 15.00% 10.00% 25.00% $779 $3,895
40.02.01.1506 6" GATE VALVE 1.00 EA $1,558.00 $1,558 15.00% 10.00% 25.00% $390 $1,948
40.02.01.1507 XX" GATE VALVE 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.1601 8" WATER SERVICE TEMPORARY LOWERING 1.00 EA $6,229.00 $6,229 15.00% 10.00% 25.00% $1,557 $7,786
40.02.01.1602 6" WATER SERVICE TEMPORARY LOWERING 1.00 EA $6,229.00 $6,229 15.00% 10.00% 25.00% $1,557 $7,786
40.02.01.1603 CONC PROTECTION FOR Exist PIPE 3.00 CY $249.00 $747 15.00% 10.00% 25.00% $187 $934
Monday, January 27, 2014 Page 57 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.1604 COVER BERM GRADING 1.00 LS $6,229.00 $6,229 15.00% 10.00% 25.00% $1,557 $7,786
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 3.00 EA $998.00 $2,994 15.00% 10.00% 25.00% $749 $3,743
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 9.00 EA $998.00 $8,982 15.00% 10.00% 25.00% $2,246 $11,228
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 6.00 EA $998.00 $5,988 15.00% 10.00% 25.00% $1,497 $7,485
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 1.00 EA $998.00 $998 15.00% 10.00% 25.00% $250 $1,248
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 1.00 EA $998.00 $998 15.00% 10.00% 25.00% $250 $1,248
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 15.00 EA $998.00 $14,970 15.00% 10.00% 25.00% $3,743 $18,713
40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 1.00 EA $998.00 $998 15.00% 10.00% 25.00% $250 $1,248
40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 2.00 EA $1,370.00 $2,740 15.00% 10.00% 25.00% $685 $3,425
40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 1.00 EA $1,370.00 $1,370 15.00% 10.00% 25.00% $343 $1,713
40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 1.00 EA $1,370.00 $1,370 15.00% 10.00% 25.00% $343 $1,713
40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 5.00 EA $1,370.00 $6,850 15.00% 10.00% 25.00% $1,713 $8,563
40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 2.00 EA $1,370.00 $2,740 15.00% 10.00% 25.00% $685 $3,425
40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 2.00 EA $1,370.00 $2,740 15.00% 10.00% 25.00% $685 $3,425
40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 1.00 EA $1,370.00 $1,370 15.00% 10.00% 25.00% $343 $1,713
40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 2.00 EA $1,370.00 $2,740 15.00% 10.00% 25.00% $685 $3,425
40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1607 END SEAL 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118
40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
Monday, January 27, 2014 Page 58 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.1608 PRESSURE CONTROL STATION FACILITY 1.00 LS $59,000.00 $59,000 15.00% 10.00% 25.00% $14,750 $73,750
40.02.01.2101 CONNECT Exist Conc CASING WITH Conc COLLAR 1.00 CY $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.2102 CONNECT TO Exist 16" CIP Swr WITH ECCENTRIC REDUCER 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2104 CONNECT TO Exist MH PER CSD Std SM-04 1.00 EA $1,172.00 $1,172 15.00% 10.00% 25.00% $293 $1,465
40.02.01.2104 CONNECT TO Exist MH PER CSD Std SM-04 1.00 EA $1,172.00 $1,172 15.00% 10.00% 25.00% $293 $1,465
40.02.01.2104 CONNECT TO Exist MH PER CSD Std SM-04 1.00 EA $1,172.00 $1,172 15.00% 10.00% 25.00% $293 $1,465
40.02.01.2105 CONNECT TO Exist 48" WSP CASING WITH WELDED JOINT 1.00 EA $998.00 $998 15.00% 10.00% 25.00% $250 $1,248
40.02.01.2106 CONNECT TO Exist 42" WSP CASING WITH WELDED JOINT 1.00 EA $935.00 $935 15.00% 10.00% 25.00% $234 $1,169
40.02.01.2107 CONNECT TO Exist 24" WSP CASING WITH WELDED JOINT 1.00 EA $935.00 $935 15.00% 10.00% 25.00% $234 $1,169
40.02.01.2108 CONNECT TO Exist 18" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.2108 CONNECT TO Exist 18" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338
40.02.01.2201 74" WSP CASING 45.00 LF $2,742.00 $123,390 15.00% 10.00% 25.00% $30,848 $154,238
40.02.01.2202 48" WSP CASING 72.00 LF $1,389.00 $100,008 15.00% 10.00% 25.00% $25,002 $125,010
40.02.01.2203 42" WSP CASING 70.00 LF $1,370.00 $95,900 15.00% 10.00% 25.00% $23,975 $119,875
40.02.01.2204 28" WSP CASING 34.00 LF $690.00 $23,460 15.00% 10.00% 25.00% $5,865 $29,325
40.02.01.2205 24" WSP CASING 45.00 LF $413.00 $18,585 15.00% 10.00% 25.00% $4,646 $23,231
40.02.01.2206 18" WSP CASING 72.00 LF $305.00 $21,960 15.00% 10.00% 25.00% $5,490 $27,450
40.02.01.2206 18" WSP CASING 58.00 LF $305.00 $17,690 15.00% 10.00% 25.00% $4,423 $22,113
40.02.01.2207 60" CLASS 145-20 STEEL Swr 588.00 LF $2,180.00 $1,281,840 15.00% 10.00% 25.00% $320,460 $1,602,300
40.02.01.2208 45" PLASTIC LINED RCP Swr 57.00 LF $873.00 $49,761 15.00% 10.00% 25.00% $12,440 $62,201
40.02.01.2209 42" PLASTIC LINED RCP Swr 69.00 LF $738.00 $50,922 15.00% 10.00% 25.00% $12,731 $63,653
40.02.01.2209 42" PLASTIC LINED RCP Swr 875.00 LF $738.00 $645,750 15.00% 10.00% 25.00% $161,438 $807,188
40.02.01.2210 21" ESVC Swr 752.00 LF $142.00 $106,784 15.00% 10.00% 25.00% $26,696 $133,480
40.02.01.2212 30" VCP Swr 70.00 LF $162.00 $11,340 15.00% 10.00% 25.00% $2,835 $14,175
40.02.01.2213 15" VCP Swr 34.00 LF $142.00 $4,828 15.00% 10.00% 25.00% $1,207 $6,035
40.02.01.2214 8" VCP Swr 45.00 LF $77.00 $3,465 15.00% 10.00% 25.00% $866 $4,331
40.02.01.2215 27" PVC Swr 92.00 LF $142.00 $13,064 15.00% 10.00% 25.00% $3,266 $16,330
40.02.01.2216 24" PVC Swr 33.00 LF $142.00 $4,686 15.00% 10.00% 25.00% $1,172 $5,858
Monday, January 27, 2014 Page 59 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.2217 12" PVC Swr 36.00 LF $116.00 $4,176 15.00% 10.00% 25.00% $1,044 $5,220
40.02.01.2217 12" PVC Swr 129.00 LF $116.00 $14,964 15.00% 10.00% 25.00% $3,741 $18,705
40.02.01.2218 10" PVC Swr 100.00 LF $116.00 $11,600 15.00% 10.00% 25.00% $2,900 $14,500
40.02.01.2219 8" CIP Swr 58.00 LF $187.00 $10,846 15.00% 10.00% 25.00% $2,712 $13,558
40.02.01.2301 TEMPORARY 42" RCP Swr 86.00 LF $498.00 $42,828 15.00% 10.00% 25.00% $10,707 $53,535
40.02.01.2302 TEMPORARY 30" PVC Swr 100.00 LF $142.00 $14,200 15.00% 10.00% 25.00% $3,550 $17,750
40.02.01.2303 TEMPORARY 27" PVC Swr 118.00 LF $180.00 $21,240 15.00% 10.00% 25.00% $5,310 $26,550
40.02.01.2304 TEMPORARY 24" PVC Swr 42.00 LF $180.00 $7,560 15.00% 10.00% 25.00% $1,890 $9,450
40.02.01.2305 SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000
40.02.01.2305 SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000
40.02.01.2306 SEWER MH 1.00 EA $4,400.00 $4,400 15.00% 10.00% 25.00% $1,100 $5,500
40.02.01.2306 SEWER MH 3.00 EA $4,400.00 $13,200 15.00% 10.00% 25.00% $3,300 $16,500
40.02.01.2306 SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000
40.02.01.2306 SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000
40.02.01.2306 SEWER MH 3.00 EA $4,400.00 $13,200 15.00% 10.00% 25.00% $3,300 $16,500
40.02.01.2306 SEWER MH 3.00 EA $4,400.00 $13,200 15.00% 10.00% 25.00% $3,300 $16,500
40.02.01.2307 TEMPORARY SEWER MH 3.00 EA $4,400.00 $13,200 15.00% 10.00% 25.00% $3,300 $16,500
40.02.01.2307 TEMPORARY SEWER MH 4.00 EA $4,400.00 $17,600 15.00% 10.00% 25.00% $4,400 $22,000
40.02.01.2307 TEMPORARY SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000
40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2402 45" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2403 30" PLUG 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118
40.02.01.2404 27" PLUG 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118
40.02.01.2405 24" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
Monday, January 27, 2014 Page 60 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.2405 24" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2406 21" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2407 12" PLUG 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118
40.02.01.2407 12" PLUG 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118
40.02.01.2408 8" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559
40.02.01.2409 CONC ENCASEMENT 150.00 CY $249.00 $37,350 15.00% 10.00% 25.00% $9,338 $46,688
40.02.01.2901 REMOVE Exist MH 1.00 EA $1,978.00 $1,978 15.00% 10.00% 25.00% $495 $2,473
40.02.01.2901 REMOVE Exist MH 2.00 EA $1,978.00 $3,956 15.00% 10.00% 25.00% $989 $4,945
40.02.01.2902 Abn Exist MH 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546
40.02.01.2902 Abn Exist MH 2.00 EA $1,237.00 $2,474 15.00% 10.00% 25.00% $619 $3,093
40.02.01.2902 Abn Exist MH 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546
40.02.01.2902 Abn Exist MH 2.00 EA $1,237.00 $2,474 15.00% 10.00% 25.00% $619 $3,093
40.02.01.2902 Abn Exist MH 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546
40.02.01.2902 Abn Exist MH 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546
40.02.01.2903 Abn TEMOPORARY MH 4.00 EA $1,978.00 $7,912 15.00% 10.00% 25.00% $1,978 $9,890
40.02.01.2903 Abn TEMOPORARY MH 3.00 EA $1,978.00 $5,934 15.00% 10.00% 25.00% $1,484 $7,418
40.02.01.2903 Abn TEMOPORARY MH 3.00 EA $1,978.00 $5,934 15.00% 10.00% 25.00% $1,484 $7,418
40.02.01.2904 Abn Exist 60" CLASS 145-20 STEEL Swr 627.00 LF $153.00 $95,931 15.00% 10.00% 25.00% $23,983 $119,914
40.02.01.2905 Abn Exist 42" PLASTIC LINED RCP Swr 72.00 LF $102.00 $7,344 15.00% 10.00% 25.00% $1,836 $9,180
40.02.01.2905 Abn Exist 42" PLASTIC LINED RCP Swr 875.00 LF $102.00 $89,250 15.00% 10.00% 25.00% $22,313 $111,563
40.02.01.2906 Abn Exist 21" ESVC Swr 754.00 LF $63.00 $47,502 15.00% 10.00% 25.00% $11,876 $59,378
40.02.01.2907 Abn Exist 21" VCP Conc ENCASED Swr 92.00 LF $63.00 $5,796 15.00% 10.00% 25.00% $1,449 $7,245
40.02.01.2908 Abn Exist 12" VCP Swr 117.00 LF $17.00 $1,989 15.00% 10.00% 25.00% $497 $2,486
40.02.01.2908 Abn Exist 12" VCP Swr 25.00 LF $17.00 $425 15.00% 10.00% 25.00% $106 $531
40.02.01.2909 Abn Exist 10" VCP Swr 63.00 LF $17.00 $1,071 15.00% 10.00% 25.00% $268 $1,339
40.02.01.2910 Abn Exist 8" VCP Swr 80.00 LF $17.00 $1,360 15.00% 10.00% 25.00% $340 $1,700
40.02.01.2910 Abn Exist 8" VCP Swr 50.00 LF $17.00 $850 15.00% 10.00% 25.00% $213 $1,063
40.02.01.2911 Abn Exist 24" PVC Swr 66.00 LF $17.00 $1,122 15.00% 10.00% 25.00% $281 $1,403
40.02.01.2912 Abn Exist 8" LATERAL 31.00 LF $17.00 $527 15.00% 10.00% 25.00% $132 $659
Monday, January 27, 2014 Page 61 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.02.01.2913 Abn Exist 6" LATERAL 26.00 LF $17.00 $442 15.00% 10.00% 25.00% $111 $553
40.02.01.2913 Abn Exist 6" LATERAL 24.00 LF $17.00 $408 15.00% 10.00% 25.00% $102 $510
40.02.01.2913 Abn Exist 6" LATERAL 25.00 LF $17.00 $425 15.00% 10.00% 25.00% $106 $531
40.02.01.2915 Abn TEMPORARY 42" RCP Swr 86.00 LF $63.00 $5,418 15.00% 10.00% 25.00% $1,355 $6,773
40.02.01.2916 Abn TEMPORARY 30" PVC Swr 100.00 LF $63.00 $6,300 15.00% 10.00% 25.00% $1,575 $7,875
40.02.01.2917 Abn TEMPORARY 27" PVC Swr 118.00 LF $63.00 $7,434 15.00% 10.00% 25.00% $1,859 $9,293
40.02.01.2918 Abn TEMPORARY 24" PVC Swr 44.00 LF $63.00 $2,772 15.00% 10.00% 25.00% $693 $3,465
40.02.01.2919 ADJUST MH BARREL SECTION 1.00 EA $1,100.00 $1,100 15.00% 10.00% 25.00% $275 $1,375
40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358
40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358
40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358
40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358
40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358
40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358
40.02.01.2921 RELOCATE Exist 8" LATERAL 33.00 LF $21.00 $693 15.00% 10.00% 25.00% $173 $866
40.02.01.2922 RELOCATE Exist 6" LATERAL 26.00 LF $21.00 $546 15.00% 10.00% 25.00% $137 $683
40.02.01.2922 RELOCATE Exist 6" LATERAL 27.00 LF $21.00 $567 15.00% 10.00% 25.00% $142 $709
40.02.01.2922 RELOCATE Exist 6" LATERAL 26.00 LF $21.00 $546 15.00% 10.00% 25.00% $137 $683
Sum
Average
18,791.00 $5,562,691
15.00% 10.00% 25.00%
$1,390,673 $6,953,364Summary for Group: 40.02.01
Group 40.02.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
DRY UTILITY RELOCATION Contingency
40.02.02 DRY UTILITY RELOCATION 1.00 LS $31,300,000.00 $31,300,000 5.00% 20.00% 25.00% $7,825,000 $39,125,000
40.02.02A TEMPORARY RELOCATION OF PCT F/O 2,850.00 LF $85.00 $242,250 25.00% 10.00% 35.00% $84,788 $327,038
Sum
Average
2,851.00 $31,542,250
15.00% 15.00% 30.00%
$7,909,788 $39,452,038Summary for Group: 40.02.02
Sum
Average
21,642.00 $37,104,941
15.00% 10.03% 25.03%
$9,300,460 $46,405,401Summary for Sub Section: 40.02
Sub Section 40.03 HAZ MAT/CONTAMINATED SOIL REMOVAL/MITIGATION, GROUND WATER TREATMENTS
Group 40.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
HAZARDOUS MATERIAL REMOVAL/MITIGATION Contingency
Monday, January 27, 2014 Page 62 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.03 HAZARDOUS MATERIAL REMOVAL/MITIGATION 1.00 LS $4,400,000.00 $4,400,000 0.00% 30.00% 30.00% $1,320,000 $5,720,000
Sum
Average
1.00 $4,400,000
0.00% 30.00% 30.00%
$1,320,000 $5,720,000Summary for Group: 40.03
Sum
Average
1.00 $4,400,000
0.00% 30.00% 30.00%
$1,320,000 $5,720,000Summary for Sub Section: 40.03
Sub Section 40.04 ENVIRONMENTAL MITIGATION/WETLAND RESTORATION
Group 40.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ENVIRONMENTAL MITIGATION/WETLAND RESTORATION Contingency
40.04.01 ENVIRONMENTAL MITIGATION/WETLAND RESTORATION 1.00 LS $6,500,000.00 $6,500,000 0.00% 30.00% 30.00% $1,950,000 $8,450,000
40.04.02.01 TREE REMOVAL (<6") 188.00 EA $400.00 $75,200 15.00% 10.00% 25.00% $18,800 $94,000
40.04.02.01 TREE REMOVAL (>6") 78.00 EA $600.00 $46,800 15.00% 10.00% 25.00% $11,700 $58,500
40.04.02.01 TREE REMOVAL (>6") 155.00 EA $600.00 $93,000 15.00% 10.00% 25.00% $23,250 $116,250
40.04.02.01 TREE REMOVAL (<6") 71.00 EA $400.00 $28,400 15.00% 10.00% 25.00% $7,100 $35,500
40.04.02.01 TREE REMOVAL (<6") 7.00 EA $400.00 $2,800 15.00% 10.00% 25.00% $700 $3,500
40.04.02.01 TREE REMOVAL (<6") 36.00 EA $400.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000
40.04.02.01 TREE REMOVAL (>6") 21.00 EA $600.00 $12,600 15.00% 10.00% 25.00% $3,150 $15,750
40.04.02.01 TREE REMOVAL (>6") 325.00 EA $600.00 $195,000 15.00% 10.00% 25.00% $48,750 $243,750
40.04.02.02 TREE REPLACEMENT 227.00 EA $2,000.00 $454,000 15.00% 10.00% 25.00% $113,500 $567,500
40.04.02.02 TREE REPLACEMENT 657.00 EA $2,000.00 $1,314,000 15.00% 10.00% 25.00% $328,500 $1,642,500
40.04.02.02 TREE REPLACEMENT 346.00 EA $2,000.00 $692,000 15.00% 10.00% 25.00% $173,000 $865,000
40.04.02.02 TREE REPLACEMENT 230.00 EA $2,000.00 $460,000 15.00% 10.00% 25.00% $115,000 $575,000
Sum
Average
2,342.00 $9,888,200
13.85% 11.54% 25.38%
$2,797,050 $12,685,250Summary for Group: 40.04
Sum
Average
2,342.00 $9,888,200
13.85% 11.54% 25.38%
$2,797,050 $12,685,250Summary for Sub Section: 40.04
Sub Section 40.06 PEDESTRIAN/BIKE ACCESS AND ACCOMODATIONS
Group 40.06.00
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROSE CANYON BIKE PATH (DETOUR) Contingency
40.06.00.190101 ROADWAY EXCAVATION 52.00 CY $28.00 $1,456 15.00% 15.00% 30.00% $437 $1,893
40.06.00.260203 CLASS 2 AGGREGATE BASE 691.00 CY $45.00 $31,095 15.00% 10.00% 25.00% $7,774 $38,869
40.06.00.390132 HOT MIX ASPHALT (TYPE A) 677.00TON $102.00 $69,054 15.00% 15.00% 30.00% $20,716 $89,770
Monday, January 27, 2014 Page 63 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.06.00.566011 ROADSIDE SIGN - ONE POST 2.00 EA $750.00 $1,500 15.00% 15.00% 30.00% $450 $1,950
40.06.00.800360 CHAIN LINK FENCE (CL-6) 9,331.00 LF $19.00 $177,289 15.00% 15.00% 30.00% $53,187 $230,476
Sum
Average
10,753.00 $280,394
15.00% 14.00% 29.00%
$82,563 $362,957Summary for Group: 40.06.00
Group 40.06.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROSE CANYON BIKE PATH (BK1) Contingency
40.06.01.01 ASPHALT PAVEMENT REMOVAL 26,823.00 SF $1.60 $42,917 15.00% 15.00% 30.00% $12,875 $55,792
40.06.01.01 DEMOLISH EXISTING RETAINING WALL 730.00 LF $40.00 $29,200 15.00% 15.00% 30.00% $8,760 $37,960
40.06.01.160101 CLEARING AND GRUBBING 0.51 AC $4,022.00 $2,051 10.00% 15.00% 25.00% $513 $2,564
40.06.01.190101 ROADWAY EXCAVATION 5,310.00 CY $28.00 $148,680 15.00% 15.00% 30.00% $44,604 $193,284
40.06.01.260203 CLASS 2 AGGREGATE BASE 283.00 CY $45.00 $12,735 15.00% 10.00% 25.00% $3,184 $15,919
40.06.01.390132 HOT MIX ASPHALT (TYPE A) 369.00TON $102.00 $37,638 15.00% 15.00% 30.00% $11,291 $48,929
40.06.01.566011 ROADSIDE SIGN - ONE POST 2.00 EA $750.00 $1,500 15.00% 15.00% 30.00% $450 $1,950
Sum
Average
33,517.51 $274,721
14.29% 14.29% 28.57%
$81,677 $356,398Summary for Group: 40.06.01
Group 40.06.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROSE CANYON BIKE PATH (BK2) Contingency
40.06.02.01 ASPHALT PAVEMENT REMOVAL 38,398.00 SF $1.60 $61,437 15.00% 15.00% 30.00% $18,431 $79,868
40.06.02.160101 CLEARING AND GRUBBING 1.32 AC $4,022.00 $5,309 10.00% 15.00% 25.00% $1,327 $6,636
40.06.02.190101 ROADWAY EXCAVATION 975.00 CY $28.00 $27,300 15.00% 15.00% 30.00% $8,190 $35,490
40.06.02.260203 CLASS 2 AGGREGATE BASE 592.00 CY $45.00 $26,640 15.00% 10.00% 25.00% $6,660 $33,300
40.06.02.390132 HOT MIX ASPHALT (TYPE A) 773.00TON $102.00 $78,846 15.00% 15.00% 30.00% $23,654 $102,500
40.06.02.566011 ROADSIDE SIGN - ONE POST 2.00 EA $750.00 $1,500 15.00% 15.00% 30.00% $450 $1,950
Sum
Average
40,741.32 $201,032
14.17% 14.17% 28.33%
$58,712 $259,744Summary for Group: 40.06.02
Group 40.06.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GRAVITY RETAINING WALL Contingency
40.06.03.2 STRUCTURE EXCAVATION 1,318.00 CY $60.00 $79,080 15.00% 15.00% 30.00% $23,724 $102,804
40.06.03.3 STRUCTURAL BACKFILL (GRAVITY WALL) 466.00 CY $52.00 $24,232 15.00% 15.00% 30.00% $7,270 $31,502
40.06.03.510062A STRUCTURAL CONCRETE (GRAVITY RETAINING WALL) 522.00 CY $650.00 $339,300 15.00% 15.00% 30.00% $101,790 $441,090
Sum
Average
2,306.00 $442,612
15.00% 15.00% 30.00%
$132,784 $575,396Summary for Group: 40.06.03
Monday, January 27, 2014 Page 64 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Group 40.06.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PEDESTRIAN BRIDGES Contingency
40.06.04.01 VOIGT PED OC 2,520.00 SF $400.00 $1,008,000 15.00% 10.00% 25.00% $252,000 $1,260,000
40.06.04.02 EXECUTIVE PED OC 1,835.00 SF $400.00 $734,000 15.00% 10.00% 25.00% $183,500 $917,500
40.06.04.03 UTC PED OC 2,360.00 SF $400.00 $944,000 15.00% 10.00% 25.00% $236,000 $1,180,000
Sum
Average
6,715.00 $2,686,000
15.00% 10.00% 25.00%
$671,500 $3,357,500Summary for Group: 40.06.04
Sum
Average
94,032.83 $3,884,759
14.58% 13.75% 28.33%
$1,027,236 $4,911,995Summary for Sub Section: 40.06
Sub Section 40.07 AUTOMOBILE, BUS, VAN ACCESS WAYS INCLUDING ROADS, PARKING LOTS
Group 40.07.00
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.00.00 ALLOWANCE FOR ROADWAY IMPROVEMENTS (CEDAR,SASSAFRAS, 1.00 LS $200,000.00 $200,000 0.00% 30.00% 30.00% $60,000 $260,000
40.07.00.00 ALLOWANCE FOR ROADWAY IMPROVEMENTS (VOIGT DRIVE) 1.00 LS $1,300,000.00 $1,300,000 0.00% 30.00% 30.00% $390,000 $1,690,000
Sum
Average
2.00 $1,500,000
0.00% 30.00% 30.00%
$450,000 $1,950,000Summary for Group: 40.07.00
Group 40.07.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TECOLOTE STATION SITEWORK Contingency
40.07.01.101 CLEARING AND GRUBBING 1.50 AC $4,022.00 $6,033 10.00% 10.00% 20.00% $1,207 $7,240
40.07.01.102 CONCRETE PAVEMENT DEMOLITION 3,126.00 SY $14.00 $43,764 10.00% 10.00% 20.00% $8,753 $52,517
40.07.01.103 CONCRETE PAVEMENT REMOVAL 1,090.00TON $23.00 $25,070 10.00% 10.00% 20.00% $5,014 $30,084
40.07.01.104 ASPHALT PAVEMENT DEMOLITION 5,846.00 SY $14.00 $81,844 10.00% 10.00% 20.00% $16,369 $98,213
40.07.01.105 ASPHALT PAVEMENT REMOVAL 1,907.00TON $34.00 $64,838 10.00% 10.00% 20.00% $12,968 $77,806
40.07.01.106 BUILDING FOOTING REMOVAL 8,250.00 SF $0.40 $3,300 10.00% 10.00% 20.00% $660 $3,960
40.07.01.106 MILL AND OVERLAY (TECOLOTE STATION) 42,400.00 SF $1.90 $80,560 10.00% 10.00% 20.00% $16,112 $96,672
40.07.01.107 BUILDING REMOVAL 8,250.00 SF $2.40 $19,800 10.00% 10.00% 20.00% $3,960 $23,760
40.07.01.201 ROADWAY EXCAVATION 3,295.00 CY $28.00 $92,260 10.00% 10.00% 20.00% $18,452 $110,712
40.07.01.204 ROADWAY EMBANKMENT 7,368.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
40.07.01.302 CURB AND GUTTER 429.00 CY $365.00 $156,585 10.00% 10.00% 20.00% $31,317 $187,902
40.07.01.304 HOT MIX ASPHALT (TYPE A) 3,830.00TON $102.00 $390,660 10.00% 10.00% 20.00% $78,132 $468,792
40.07.01.306 MINOR CONCRETE (ADA RAMPS) 87.00 CY $765.00 $66,555 10.00% 10.00% 20.00% $13,311 $79,866
40.07.01.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 108.00 SF $22.00 $2,376 15.00% 15.00% 30.00% $713 $3,089
Monday, January 27, 2014 Page 65 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.01.309 DECORATIVE CONCRETE PAVEMENT 1,370.00 SF $20.00 $27,400 10.00% 10.00% 20.00% $5,480 $32,880
40.07.01.310 CONCRETE SIDEWALKS 11,306.00 SF $12.00 $135,672 10.00% 10.00% 20.00% $27,134 $162,806
40.07.01.311 CONCRETE STAIRS 25.00 CY $525.00 $13,125 10.00% 10.00% 20.00% $2,625 $15,750
40.07.01.312 CLASS 2 AGGREGATE BASE 2,040.00 CY $45.00 $91,800 15.00% 10.00% 25.00% $22,950 $114,750
40.07.01.313 CLASS 2 AGGREGATE BASE 2,182.00 CY $45.00 $98,190 10.00% 10.00% 20.00% $19,638 $117,828
40.07.01.314 DRIVEWAY 360.00 SF $20.00 $7,200 10.00% 10.00% 20.00% $1,440 $8,640
40.07.01.401 RETAINING WALLS 3,160.00 SF $80.00 $252,800 15.00% 15.00% 30.00% $75,840 $328,640
40.07.01.501 LIGHTING AREA 150,630.00 SF $1.50 $225,945 15.00% 15.00% 30.00% $67,784 $293,729
40.07.01.901 METAL RAILING (PIPE) 1,171.00 LF $125.00 $146,375 15.00% 10.00% 25.00% $36,594 $182,969
40.07.01.902 STRIPING 4,866.00 LF $2.00 $9,732 10.00% 10.00% 20.00% $1,946 $11,678
40.07.01.903 PAVEMENT MARKERS 3,954.00 SF $3.00 $11,862 10.00% 10.00% 20.00% $2,372 $14,234
40.07.01.904 SIGNAGE 4.00 EA $278.00 $1,112 15.00% 10.00% 25.00% $278 $1,390
40.07.01.905 FOUNDATIONS (MONUMENT SIGNS) 12.00 CY $441.00 $5,292 10.00% 10.00% 20.00% $1,058 $6,350
40.07.01.906 FENCING 566.00 LF $117.00 $66,222 10.00% 10.00% 20.00% $13,244 $79,466
40.07.01.907 GATES 1.00 EA $1,850.00 $1,850 10.00% 10.00% 20.00% $370 $2,220
40.07.01.909 LANDSCAPING 32,842.00 SF $4.70 $154,357 15.00% 10.00% 25.00% $38,589 $192,947
40.07.01.911 IRRIGATION 32,842.00 SF $1.40 $45,979 10.00% 10.00% 20.00% $9,196 $55,175
40.07.01.913 BUS SHELTERS 2.00 EA $36,800.00 $73,600 10.00% 10.00% 20.00% $14,720 $88,320
40.07.01.914 WHEEL STOPS 253.00 EA $86.00 $21,758 10.00% 10.00% 20.00% $4,352 $26,110
40.07.01.920 ONSITE VEHICULAR CIRCULATION SIGNAGE 6.00 EA $750.00 $4,500 10.00% 10.00% 20.00% $900 $5,400
Sum
Average
333,579.50 $2,428,416
11.03% 10.44% 21.47%
$553,478 $2,981,894Summary for Group: 40.07.01
Group 40.07.01.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TECOLOTE STATION DRAINAGE IMPROVEMENTS Contingency
40.07.01.03.101 18" RCP STORM DRAIN 102.00 LF $120.00 $12,240 15.00% 10.00% 25.00% $3,060 $15,300
40.07.01.03.101 18" RCP STORM DRAIN 78.00 LF $120.00 $9,360 15.00% 10.00% 25.00% $2,340 $11,700
40.07.01.03.102 24" RCP STORM DRAIN 690.00 LF $170.00 $117,300 15.00% 10.00% 25.00% $29,325 $146,625
40.07.01.03.103 30" RCP STORM DRAIN 243.00 LF $210.00 $51,030 15.00% 10.00% 25.00% $12,758 $63,788
40.07.01.03.104 36" RCP STORM DRAIN 248.00 LF $230.00 $57,040 15.00% 10.00% 25.00% $14,260 $71,300
40.07.01.03.105 42" RCP STORM DRAIN 239.00 LF $260.00 $62,140 15.00% 10.00% 25.00% $15,535 $77,675
Monday, January 27, 2014 Page 66 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.01.03.112 4" NON-PERFORATED PVC 220.00 LF $20.00 $4,400 15.00% 10.00% 25.00% $1,100 $5,500
40.07.01.03.121 3" PERFORATED PVC 240.00 LF $14.00 $3,360 15.00% 10.00% 25.00% $840 $4,200
40.07.01.03.122 4" PERFORATED PVC 1,078.00 LF $20.00 $21,560 15.00% 10.00% 25.00% $5,390 $26,950
40.07.01.03.201 WASH WATER CLEANOUT 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625
40.07.01.03.201 TYPE A-8 SD CLEANOUT, SDRSD D-9 2.00 EA $6,000.00 $12,000 10.00% 10.00% 20.00% $2,400 $14,400
40.07.01.03.201 TYPE A-5 SD CLEANOUT, SDRSD D-9 3.00 EA $4,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
40.07.01.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
40.07.01.03.204 10' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $6,900.00 $6,900 15.00% 10.00% 25.00% $1,725 $8,625
40.07.01.03.204 21' TYPE B-1 CURB INLET, SDRSD SDD-116 3.00 EA $8,100.00 $24,300 15.00% 10.00% 25.00% $6,075 $30,375
40.07.01.03.204 15' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500
40.07.01.03.207 TYPE I CATCH BASIN, SDRSD D-29 6.00 EA $6,450.00 $38,700 10.00% 10.00% 20.00% $7,740 $46,440
40.07.01.03.501 CONCRETE LUG, SDRSD SDD-113 1.00 EA $1,100.00 $1,100 15.00% 10.00% 25.00% $275 $1,375
40.07.01.03.503 PIPE TO CHANNEL CONNECTION 1.00 EA $6,230.00 $6,230 15.00% 10.00% 25.00% $1,558 $7,788
40.07.01.03.506 3" UNDERDRAIN CLEANOUT 2.00 EA $46.00 $92 15.00% 10.00% 25.00% $23 $115
40.07.01.03.508 4" UNDERDRAIN CLEANOUT 23.00 EA $60.00 $1,380 15.00% 10.00% 25.00% $345 $1,725
40.07.01.03.510 TRENCH DRAIN 751.00 LF $35.00 $26,285 15.00% 10.00% 25.00% $6,571 $32,856
40.07.01.03.515 6" TRENCH DRAIN CLEANOUT 1.00 EA $80.00 $80 15.00% 10.00% 25.00% $20 $100
40.07.01.03.610 BIORETENTION PLANTER SOIL 889.00 CY $35.00 $31,115 15.00% 10.00% 25.00% $7,779 $38,894
40.07.01.03.611 BIORETENTION 3/4" CRUSHED ROCK 148.00 CY $50.00 $7,400 15.00% 10.00% 25.00% $1,850 $9,250
40.07.01.03.612 BIORETENTION 1-1/2" CRUSHED ROCK 296.00 CY $30.00 $8,880 15.00% 10.00% 25.00% $2,220 $11,100
40.07.01.03.613 BIORETENTION LINER 16,000.00 SF $0.80 $12,800 15.00% 10.00% 25.00% $3,200 $16,000
40.07.01.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 6.00 EA $675.00 $4,050 15.00% 10.00% 25.00% $1,013 $5,063
Sum
Average
21,275.00 $554,342
14.29% 10.00% 24.29%
$134,926 $689,268Summary for Group: 40.07.01.03
Group 40.07.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CLAIREMONT STATION SITEWORK Contingency
40.07.02.101 CLEARING AND GRUBBING 0.55 AC $4,022.00 $2,212 10.00% 10.00% 20.00% $442 $2,655
40.07.02.102 CONCRETE PAVEMENT DEMOLITION 1,429.00 SY $14.00 $20,006 10.00% 10.00% 20.00% $4,001 $24,007
40.07.02.103 CONCRETE PAVEMENT REMOVAL 498.00TON $23.00 $11,454 10.00% 10.00% 20.00% $2,291 $13,745
40.07.02.104 ASPHALT PAVEMENT DEMOLITION 11,851.00 SY $14.00 $165,914 10.00% 10.00% 20.00% $33,183 $199,097
Monday, January 27, 2014 Page 67 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.02.105 ASPHALT PAVEMENT REMOVAL 3,866.00TON $34.00 $131,444 10.00% 10.00% 20.00% $26,289 $157,733
40.07.02.106 BUILDING FOOTING REMOVAL 37,485.00 SF $0.40 $14,994 10.00% 10.00% 20.00% $2,999 $17,993
40.07.02.201 ROADWAY EXCAVATION 2,248.00 CY $28.00 $62,944 10.00% 10.00% 20.00% $12,589 $75,533
40.07.02.204 ROADWAY EMBANKMENT 6,918.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
40.07.02.302 CURB AND GUTTER 272.00 CY $365.00 $99,280 10.00% 10.00% 20.00% $19,856 $119,136
40.07.02.304 HOT MIX ASPHALT (TYPE A) 2,190.00TON $102.00 $223,380 10.00% 10.00% 20.00% $44,676 $268,056
40.07.02.305 PORTLAND CEMENT CONCRETE PAVEMENT 310.00 CY $603.00 $186,930 10.00% 10.00% 20.00% $37,386 $224,316
40.07.02.306 MINOR CONCRETE (ADA RAMPS) 22.00 CY $765.00 $16,830 10.00% 10.00% 20.00% $3,366 $20,196
40.07.02.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 144.00 SF $22.00 $3,168 15.00% 15.00% 30.00% $950 $4,118
40.07.02.309 DECORATIVE CONCRETE PAVEMENT 13,200.00 SF $20.00 $264,000 10.00% 10.00% 20.00% $52,800 $316,800
40.07.02.310 CONCRETE SIDEWALKS 28,110.00 SF $12.00 $337,320 10.00% 10.00% 20.00% $67,464 $404,784
40.07.02.311 CONCRETE STAIRS 30.00 CY $525.00 $15,750 10.00% 10.00% 20.00% $3,150 $18,900
40.07.02.312 CLASS 2 AGGREGATE BASE 2,200.00 CY $45.00 $99,000 10.00% 10.00% 20.00% $19,800 $118,800
40.07.02.313 CLASS 2 AGGREGATE BASE 210.00 CY $45.00 $9,450 10.00% 10.00% 20.00% $1,890 $11,340
40.07.02.401 RETAINING WALLS 2,900.00 SF $80.00 $232,000 15.00% 15.00% 30.00% $69,600 $301,600
40.07.02.501 LIGHTING AREA 145,080.00 SF $1.50 $217,620 15.00% 15.00% 30.00% $65,286 $282,906
40.07.02.901 METAL RAILING (PIPE) 655.00 LF $125.00 $81,875 15.00% 10.00% 25.00% $20,469 $102,344
40.07.02.902 STRIPING 2,200.00 LF $2.00 $4,400 10.00% 10.00% 20.00% $880 $5,280
40.07.02.903 PAVEMENT MARKERS 4,212.00 SF $3.00 $12,636 10.00% 10.00% 20.00% $2,527 $15,163
40.07.02.904 SIGNAGE 6.00 EA $278.00 $1,668 15.00% 10.00% 25.00% $417 $2,085
40.07.02.905 FOUNDATIONS (MONUMENT SIGNS) 18.00 CY $441.00 $7,938 10.00% 10.00% 20.00% $1,588 $9,526
40.07.02.906 FENCING 350.00 LF $117.00 $40,950 10.00% 10.00% 20.00% $8,190 $49,140
40.07.02.907 GATES 1.00 EA $1,850.00 $1,850 10.00% 10.00% 20.00% $370 $2,220
40.07.02.909 LANDSCAPING 34,490.00 SF $4.70 $162,103 15.00% 10.00% 25.00% $40,526 $202,629
40.07.02.911 IRRIGATION 34,490.00 SF $1.40 $48,286 10.00% 10.00% 20.00% $9,657 $57,943
40.07.02.913 BUS SHELTERS 4.00 EA $36,800.00 $147,200 10.00% 10.00% 20.00% $29,440 $176,640
40.07.02.914 WHEEL STOPS 156.00 EA $86.00 $13,416 10.00% 10.00% 20.00% $2,683 $16,099
40.07.02.920 ONSITE VEHICULAR CIRCULATION SIGNAGE 15.00 EA $750.00 $11,250 10.00% 10.00% 20.00% $2,250 $13,500
Monday, January 27, 2014 Page 68 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
335,560.55 $2,647,268
10.94% 10.47% 21.41%
$587,015 $3,234,283Summary for Group: 40.07.02
Group 40.07.02.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CLAIREMONT STATION DRAINAGE IMPROVEMENTS Contingency
40.07.02.03.101 18" RCP STORM DRAIN 210.00 LF $120.00 $25,200 15.00% 10.00% 25.00% $6,300 $31,500
40.07.02.03.102 24" RCP STORM DRAIN 39.00 LF $170.00 $6,630 15.00% 10.00% 25.00% $1,658 $8,288
40.07.02.03.112 4" NON-PERFORATED PVC 680.00 LF $20.00 $13,600 15.00% 10.00% 25.00% $3,400 $17,000
40.07.02.03.121 3" PERFORATED PVC 23.00 LF $14.00 $322 15.00% 10.00% 25.00% $81 $403
40.07.02.03.122 4" PERFORATED PVC 574.00 LF $20.00 $11,480 15.00% 10.00% 25.00% $2,870 $14,350
40.07.02.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
40.07.02.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500
40.07.02.03.204 10' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $6,900.00 $6,900 15.00% 10.00% 25.00% $1,725 $8,625
40.07.02.03.207 TYPE I CATCH BASIN, SDRSD D-29 2.00 EA $6,450.00 $12,900 10.00% 10.00% 20.00% $2,580 $15,480
40.07.02.03.501 CONCRETE LUG, SDRSD SDD-113 1.00 EA $1,100.00 $1,100 15.00% 10.00% 25.00% $275 $1,375
40.07.02.03.508 4" UNDERDRAIN CLEANOUT 45.00 EA $60.00 $2,700 15.00% 10.00% 25.00% $675 $3,375
40.07.02.03.510 TRENCH DRAIN 16.00 LF $35.00 $560 15.00% 10.00% 25.00% $140 $700
40.07.02.03.610 BIORETENTION PLANTER SOIL 342.00 CY $35.00 $11,970 15.00% 10.00% 25.00% $2,993 $14,963
40.07.02.03.611 BIORETENTION 3/4" CRUSHED ROCK 57.00 CY $50.00 $2,850 15.00% 10.00% 25.00% $713 $3,563
40.07.02.03.612 BIORETENTION 1-1/2" CRUSHED ROCK 114.00 CY $30.00 $3,420 15.00% 10.00% 25.00% $855 $4,275
40.07.02.03.613 BIORETENTION LINER 6,160.00 SF $0.80 $4,928 15.00% 10.00% 25.00% $1,232 $6,160
40.07.02.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 4.00 EA $675.00 $2,700 15.00% 10.00% 25.00% $675 $3,375
40.07.02.03.701 ABANDON DRAINAGE STRUCTURE 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546
40.07.02.03.702 REMOVE EXIST DRAINAGE STRUCTURE 4.00 EA $1,829.00 $7,316 15.00% 10.00% 25.00% $1,829 $9,145
Sum
Average
8,276.00 $130,013
14.47% 10.00% 24.47%
$31,408 $161,421Summary for Group: 40.07.02.03
Group 40.07.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BALBOA STATION SITEWORK Contingency
40.07.03.101 CLEARING AND GRUBBING 3.95 AC $4,022.00 $15,887 10.00% 10.00% 20.00% $3,177 $19,064
40.07.03.201 ROADWAY EXCAVATION 3,324.00 CY $28.00 $93,072 10.00% 10.00% 20.00% $18,614 $111,686
40.07.03.204 ROADWAY EMBANKMENT 32,285.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
40.07.03.301 CURB 2,474.00 LF $20.00 $49,480 10.00% 10.00% 20.00% $9,896 $59,376
Monday, January 27, 2014 Page 69 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.03.302 CURB AND GUTTER 3,387.00 LF $30.00 $101,610 10.00% 10.00% 20.00% $20,322 $121,932
40.07.03.303 CROSS GUTTERS 40.00 LF $135.00 $5,400 10.00% 10.00% 20.00% $1,080 $6,480
40.07.03.304 HOT MIX ASPHALT (TYPE A) 3,218.00TON $102.00 $328,236 10.00% 10.00% 20.00% $65,647 $393,883
40.07.03.305 PORTLAND CEMENT CONCRETE PAVEMENT 722.00 CY $603.00 $435,366 10.00% 10.00% 20.00% $87,073 $522,439
40.07.03.306 MINOR CONCRETE (ADA RAMPS) 52.00 CY $765.00 $39,780 10.00% 10.00% 20.00% $7,956 $47,736
40.07.03.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 1,685.00 SF $22.00 $37,070 10.00% 10.00% 20.00% $7,414 $44,484
40.07.03.308 METAL BEAM GUARD RAILING (WOOD POST) 1,167.00 LF $32.00 $37,344 10.00% 10.00% 20.00% $7,469 $44,813
40.07.03.310 CONCRETE SIDEWALKS 25,082.00 SF $12.00 $300,984 10.00% 10.00% 20.00% $60,197 $361,181
40.07.03.311 CONCRETE STAIRS 77.00 CY $525.00 $40,425 10.00% 10.00% 20.00% $8,085 $48,510
40.07.03.312 CLASS 2 AGGREGATE BASE 2,978.00 CY $45.00 $134,010 10.00% 10.00% 20.00% $26,802 $160,812
40.07.03.313 CLASS 2 AGGREGATE BASE 2,692.00 CY $45.00 $121,140 10.00% 10.00% 20.00% $24,228 $145,368
40.07.03.315 FILTER FABRIC 4,850.00 SY $0.80 $3,880 10.00% 10.00% 20.00% $776 $4,656
40.07.03.402 STRUCTURE EXCAVATION (RETAINING WALL) 1,432.00 CY $60.00 $85,920 10.00% 10.00% 20.00% $17,184 $103,104
40.07.03.403 STRUCTURAL BACKFILL 3,238.00 CY $52.00 $168,376 10.00% 10.00% 20.00% $33,675 $202,051
40.07.03.405 STRUCTURAL CONCRETE (RETAINING WALL) 912.00 CY $470.00 $428,640 10.00% 10.00% 20.00% $85,728 $514,368
40.07.03.406 BAR REINFORCING STEEL (RETAINING WALL) 104,040.00 LB $1.00 $104,040 10.00% 10.00% 20.00% $20,808 $124,848
40.07.03.407 ARCHITECTURAL TREATMENT (RETAINING WALL) 10,989.00 SF $14.00 $153,846 10.00% 10.00% 20.00% $30,769 $184,615
40.07.03.408 CABLE RAILING 718.00 LF $25.00 $17,950 10.00% 10.00% 20.00% $3,590 $21,540
40.07.03.901 METAL RAILING (PIPE) 1,327.00 LF $125.00 $165,875 15.00% 10.00% 25.00% $41,469 $207,344
40.07.03.902 STRIPING 3,456.00 LF $2.00 $6,912 10.00% 10.00% 20.00% $1,382 $8,294
40.07.03.904 SIGNAGE 2.00 EA $278.00 $556 15.00% 10.00% 25.00% $139 $695
40.07.03.905 FOUNDATIONS (MONUMENT SIGNS) 10.00 CY $441.00 $4,410 10.00% 10.00% 20.00% $882 $5,292
40.07.03.906 FENCING 1,060.00 LF $117.00 $124,020 10.00% 10.00% 20.00% $24,804 $148,824
40.07.03.909 LANDSCAPING 43,507.00 SF $4.70 $204,483 15.00% 10.00% 25.00% $51,121 $255,604
40.07.03.911 IRRIGATION 43,507.00 SF $1.40 $60,910 10.00% 10.00% 20.00% $12,182 $73,092
40.07.03.913 BUS SHELTERS 6.00 EA $36,800.00 $220,800 10.00% 10.00% 20.00% $44,160 $264,960
Sum
Average
298,240.95 $3,490,422
10.50% 10.00% 20.50%
$716,630 $4,207,052Summary for Group: 40.07.03
Group 40.07.03.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BALBOA STATION DRAINAGE IMPROVEMENTS Contingency
Monday, January 27, 2014 Page 70 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.03.03.101 18" RCP STORM DRAIN 529.00 LF $120.00 $63,480 15.00% 10.00% 25.00% $15,870 $79,350
40.07.03.03.102 24" RCP STORM DRAIN 42.00 LF $170.00 $7,140 15.00% 10.00% 25.00% $1,785 $8,925
40.07.03.03.104 36" RCP STORM DRAIN 52.00 LF $230.00 $11,960 15.00% 10.00% 25.00% $2,990 $14,950
40.07.03.03.110 3" NON-PERFORATED PVC 56.00 LF $14.00 $784 15.00% 10.00% 25.00% $196 $980
40.07.03.03.112 4" NON-PERFORATED PVC 663.00 LF $20.00 $13,260 15.00% 10.00% 25.00% $3,315 $16,575
40.07.03.03.113 6" NON-PERFORATED PVC 43.00 LF $65.00 $2,795 15.00% 10.00% 25.00% $699 $3,494
40.07.03.03.122 4" PERFORATED PVC 776.00 LF $20.00 $15,520 15.00% 10.00% 25.00% $3,880 $19,400
40.07.03.03.201 WASH WATER CLEANOUT 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625
40.07.03.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 3.00 EA $4,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
40.07.03.03.203 15' TYPE A CURB INLET, SDRSD SDD-115 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500
40.07.03.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 3.00 EA $5,200.00 $15,600 15.00% 10.00% 25.00% $3,900 $19,500
40.07.03.03.204 10' TYPE B-1 CURB INLET, SDRSD SDD-116 2.00 EA $6,900.00 $13,800 15.00% 10.00% 25.00% $3,450 $17,250
40.07.03.03.207 TYPE I CATCH BASIN, SDRSD D-29 3.00 EA $6,450.00 $19,350 10.00% 10.00% 20.00% $3,870 $23,220
40.07.03.03.507 3" GRATE INLET 2.00 EA $20.00 $40 15.00% 10.00% 25.00% $10 $50
40.07.03.03.508 4" UNDERDRAIN CLEANOUT 31.00 EA $60.00 $1,860 15.00% 10.00% 25.00% $465 $2,325
40.07.03.03.509 12" STEEL CASING 43.00 LF $150.00 $6,450 15.00% 10.00% 25.00% $1,613 $8,063
40.07.03.03.510 TRENCH DRAIN 701.00 LF $35.00 $24,535 15.00% 10.00% 25.00% $6,134 $30,669
40.07.03.03.515 6" TRENCH DRAIN CLEANOUT 1.00 EA $80.00 $80 15.00% 10.00% 25.00% $20 $100
40.07.03.03.601 HYDROMODIFICATION UNDERGROUND STORAGE 15,300.00 CF $2.45 $37,485 15.00% 10.00% 25.00% $9,371 $46,856
40.07.03.03.603 HYDROMODIFICATION OUTLET STRUCTURE - UNDERGROUND STO 1.00 EA $7,000.00 $7,000 15.00% 10.00% 25.00% $1,750 $8,750
40.07.03.03.610 BIORETENTION PLANTER SOIL 1,114.00 CY $35.00 $38,990 15.00% 10.00% 25.00% $9,748 $48,738
40.07.03.03.611 BIORETENTION 3/4" CRUSHED ROCK 186.00 CY $50.00 $9,300 15.00% 10.00% 25.00% $2,325 $11,625
40.07.03.03.612 BIORETENTION 1-1/2" CRUSHED ROCK 371.00 CY $30.00 $11,130 15.00% 10.00% 25.00% $2,783 $13,913
40.07.03.03.613 BIORETENTION LINER 20,050.00 SF $0.80 $16,040 15.00% 10.00% 25.00% $4,010 $20,050
Sum
Average
39,974.00 $342,199
14.58% 10.00% 24.58%
$83,907 $426,106Summary for Group: 40.07.03.03
Group 40.07.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NOBEL STATION SITEWORK Contingency
40.07.04.101 CLEARING AND GRUBBING 0.13 AC $4,022.00 $523 10.00% 10.00% 20.00% $105 $627
40.07.04.104 ASPHALT PAVEMENT DEMOLITION 8,660.00 SY $14.00 $121,240 10.00% 10.00% 20.00% $24,248 $145,488
Monday, January 27, 2014 Page 71 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.04.105 ASPHALT PAVEMENT REMOVAL 994.00TON $34.00 $33,796 10.00% 10.00% 20.00% $6,759 $40,555
40.07.04.302 CURB AND GUTTER 392.00 CY $365.00 $143,080 10.00% 10.00% 20.00% $28,616 $171,696
40.07.04.306 MINOR CONCRETE (ADA RAMPS) 18.00 CY $765.00 $13,770 10.00% 10.00% 20.00% $2,754 $16,524
40.07.04.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 180.00 SF $22.00 $3,960 15.00% 15.00% 30.00% $1,188 $5,148
40.07.04.310 CONCRETE SIDEWALKS 17,130.00 SF $12.00 $205,560 15.00% 15.00% 30.00% $61,668 $267,228
40.07.04.312 CLASS 2 AGGREGATE BASE 320.00 CY $45.00 $14,400 10.00% 10.00% 20.00% $2,880 $17,280
40.07.04.501 LIGHTING AREA 196,890.00 SF $1.50 $295,335 15.00% 15.00% 30.00% $88,601 $383,936
40.07.04.902 STRIPING 11,130.00 LF $2.00 $22,260 10.00% 10.00% 20.00% $4,452 $26,712
40.07.04.904 SIGNAGE 2.00 EA $278.00 $556 15.00% 10.00% 25.00% $139 $695
40.07.04.905 FOUNDATIONS (MONUMENT SIGNS) 6.00 CY $441.00 $2,646 10.00% 10.00% 20.00% $529 $3,175
40.07.04.909 LANDSCAPING 22,990.00 SF $4.70 $108,053 15.00% 10.00% 25.00% $27,013 $135,066
40.07.04.911 IRRIGATION 22,990.00 SF $1.40 $32,186 10.00% 10.00% 20.00% $6,437 $38,623
40.07.04.920 ONSITE VEHICULAR CIRCULATION SIGNAGE 8.00 EA $750.00 $6,000 10.00% 10.00% 20.00% $1,200 $7,200
Sum
Average
281,710.13 $1,003,365
11.67% 11.00% 22.67%
$256,589 $1,259,954Summary for Group: 40.07.04
Group 40.07.04.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NOBEL STATION DRAINAGE IMPROVEMENTS Contingency
40.07.04.03.101 18" RCP STORM DRAIN 73.00 LF $120.00 $8,760 15.00% 10.00% 25.00% $2,190 $10,950
40.07.04.03.102 24" RCP STORM DRAIN 350.00 LF $170.00 $59,500 15.00% 10.00% 25.00% $14,875 $74,375
40.07.04.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 6.00 EA $4,500.00 $27,000 10.00% 10.00% 20.00% $5,400 $32,400
40.07.04.03.601 HYDROMODIFICATION UNDERGROUND STORAGE 22,580.00 CF $2.45 $55,321 15.00% 10.00% 25.00% $13,830 $69,151
40.07.04.03.603 HYDROMODIFICATION OUTLET STRUCTURE - UNDERGROUND STO 2.00 EA $7,000.00 $14,000 15.00% 10.00% 25.00% $3,500 $17,500
40.07.04.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 2.00 EA $675.00 $1,350 15.00% 10.00% 25.00% $338 $1,688
Sum
Average
23,013.00 $165,931
14.17% 10.00% 24.17%
$40,133 $206,064Summary for Group: 40.07.04.03
Group 40.07.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
VA MEDICAL CENTER STATION SITEWORK Contingency
40.07.05.101 CLEARING AND GRUBBING 0.11 AC $4,022.00 $442 10.00% 10.00% 20.00% $88 $531
40.07.05.102 CONCRETE PAVEMENT DEMOLITION 440.00 SY $14.00 $6,160 10.00% 10.00% 20.00% $1,232 $7,392
40.07.05.103 CONCRETE PAVEMENT REMOVAL 153.00TON $23.00 $3,519 10.00% 10.00% 20.00% $704 $4,223
40.07.05.106 MILL AND OVERLAY (VA STATION) 127,374.00 SF $1.90 $242,011 10.00% 10.00% 20.00% $48,402 $290,413
Monday, January 27, 2014 Page 72 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.05.108 DEMOLISH EXIST FENCE 88.00 LF $2.20 $194 15.00% 15.00% 30.00% $58 $252
40.07.05.201 ROADWAY EXCAVATION 674.00 CY $28.00 $18,872 10.00% 10.00% 20.00% $3,774 $22,646
40.07.05.304 HOT MIX ASPHALT (TYPE A) 29.18TON $102.00 $2,976 10.00% 10.00% 20.00% $595 $3,572
40.07.05.306 MINOR CONCRETE (ADA RAMPS) 3.00 CY $765.00 $2,295 10.00% 10.00% 20.00% $459 $2,754
40.07.05.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 24.00 SF $22.00 $528 15.00% 15.00% 30.00% $158 $686
40.07.05.310 CONCRETE SIDEWALKS 3,955.00 SF $12.00 $47,460 15.00% 15.00% 30.00% $14,238 $61,698
40.07.05.316 CLASS 2 AGGREGATE BASE 15.00 CY $45.00 $675 10.00% 10.00% 20.00% $135 $810
40.07.05.317 AGGREGATE SUBBASE 15.00 CY $35.00 $525 10.00% 10.00% 20.00% $105 $630
40.07.05.318 CLASS 2 AGGREGATE BASE 49.00 CY $45.00 $2,205 10.00% 10.00% 20.00% $441 $2,646
40.07.05.401 RETAINING WALLS 320.00 SF $80.00 $25,600 15.00% 15.00% 30.00% $7,680 $33,280
40.07.05.901 METAL RAILING (PIPE) 320.00 LF $125.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000
40.07.05.902 STRIPING 150.00 LF $2.00 $300 10.00% 10.00% 20.00% $60 $360
Sum
Average
133,609.29 $393,762
11.56% 11.25% 22.81%
$88,131 $481,893Summary for Group: 40.07.05
Group 40.07.05.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
VA MEDICAL CENTER STATION DRAINAGE IMPROVEMENTS Contingency
40.07.05.03.101 18" RCP STORM DRAIN 125.00 LF $120.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
40.07.05.03.113 6" NON-PERFORATED PVC 26.00 LF $65.00 $1,690 15.00% 10.00% 25.00% $423 $2,113
40.07.05.03.201 WASH WATER CLEANOUT 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625
40.07.05.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500
40.07.05.03.207 TYPE I CATCH BASIN, SDRSD D-29 1.00 EA $6,450.00 $6,450 10.00% 10.00% 20.00% $1,290 $7,740
40.07.05.03.210 WING TYPE HEADWALL, SDRSD D-34 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
40.07.05.03.212 OCP INLET, CT STD 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625
40.07.05.03.213 JUNCTION STRUCTION (CT STD) 1.00 EA $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750
40.07.05.03.510 TRENCH DRAIN 703.00 LF $35.00 $24,605 15.00% 10.00% 25.00% $6,151 $30,756
40.07.05.03.515 6" TRENCH DRAIN CLEANOUT 1.00 EA $80.00 $80 15.00% 10.00% 25.00% $20 $100
40.07.05.03.610 BIORETENTION PLANTER SOIL 159.00 CY $35.00 $5,565 15.00% 10.00% 25.00% $1,391 $6,956
40.07.05.03.611 BIORETENTION 3/4" CRUSHED ROCK 26.00 CY $50.00 $1,300 15.00% 10.00% 25.00% $325 $1,625
40.07.05.03.612 BIORETENTION 1-1/2" CRUSHED ROCK 53.00 CY $30.00 $1,590 15.00% 10.00% 25.00% $398 $1,988
40.07.05.03.613 BIORETENTION LINER 2,859.00 SF $0.80 $2,287 15.00% 10.00% 25.00% $572 $2,859
Monday, January 27, 2014 Page 73 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
3,959.00 $96,767
14.29% 10.00% 24.29%
$23,419 $120,187Summary for Group: 40.07.05.03
Group 40.07.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UCSD WEST STATION SITEWORK Contingency
40.07.06.101 CLEARING AND GRUBBING 0.77 AC $4,022.00 $3,097 10.00% 10.00% 20.00% $619 $3,716
40.07.06.201 ROADWAY EXCAVATION 3.00 CY $28.00 $84 10.00% 10.00% 20.00% $17 $101
40.07.06.204 ROADWAY EMBANKMENT 10,562.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
40.07.06.305 PORTLAND CEMENT CONCRETE PAVEMENT 196.00 CY $603.00 $118,188 10.00% 10.00% 20.00% $23,638 $141,826
40.07.06.312 CLASS 2 AGGREGATE BASE 294.00 CY $45.00 $13,230 10.00% 10.00% 20.00% $2,646 $15,876
40.07.06.403 STRUCTURAL BACKFILL 1,700.00 CY $52.00 $88,400 10.00% 10.00% 20.00% $17,680 $106,080
40.07.06.405 STRUCTURAL CONCRETE (RETAINING WALL) 877.00 CY $470.00 $412,190 10.00% 10.00% 20.00% $82,438 $494,628
40.07.06.406 BAR REINFORCING STEEL (RETAINING WALL) 135,650.00 LB $1.00 $135,650 10.00% 10.00% 20.00% $27,130 $162,780
40.07.06.407 ARCHITECTURAL TREATMENT 2,688.00 SF $14.00 $37,632 10.00% 10.00% 20.00% $7,526 $45,158
40.07.06.901 METAL RAILING (PIPE) 487.00 LF $125.00 $60,875 15.00% 10.00% 25.00% $15,219 $76,094
Sum
Average
152,457.77 $869,346
10.50% 10.00% 20.50%
$176,913 $1,046,259Summary for Group: 40.07.06
Group 40.07.06.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UCSD WEST STATION DRAINAGE IMPROVEMENTS Contingency
40.07.06.03.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD WEST ST 5,096.00 CF $2.45 $12,485 15.00% 15.00% 30.00% $3,746 $16,231
40.07.06.03.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD WEST STATI 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
Sum
Average
5,097.00 $19,485
15.00% 15.00% 30.00%
$5,846 $25,331Summary for Group: 40.07.06.03
Group 40.07.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UCSD EAST STATION SITEWORK Contingency
40.07.07.101 CLEARING AND GRUBBING 0.37 AC $4,022.00 $1,488 10.00% 10.00% 20.00% $298 $1,786
40.07.07.106 MILL AND OVERLAY (UCSD EAST STATION) 43,518.00 SF $1.90 $82,684 10.00% 10.00% 20.00% $16,537 $99,221
40.07.07.201 ROADWAY EXCAVATION 194.00 CY $28.00 $5,432 10.00% 10.00% 20.00% $1,086 $6,518
40.07.07.202 HAUL AND DISPOSE 50.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
40.07.07.302 CURB AND GUTTER 850.00 LF $30.00 $25,500 10.00% 10.00% 20.00% $5,100 $30,600
40.07.07.304 HOT MIX ASPHALT (TYPE A) 254.00TON $102.00 $25,908 10.00% 10.00% 20.00% $5,182 $31,090
40.07.07.310 CONCRETE SIDEWALKS 600.00 SF $12.00 $7,200 10.00% 10.00% 20.00% $1,440 $8,640
40.07.07.312 CLASS 2 AGGREGATE BASE 200.00 CY $45.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
Monday, January 27, 2014 Page 74 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.07.902 STRIPING 3,400.00 LF $2.00 $6,800 10.00% 10.00% 20.00% $1,360 $8,160
Sum
Average
49,066.37 $164,012
10.00% 10.00% 20.00%
$32,802 $196,815Summary for Group: 40.07.07
Group 40.07.07.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UCSD EAST STATION DRAINAGE IMPROVEMENTS Contingency
40.07.07.03.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD EAST STA 1,315.60 CF $2.45 $3,223 15.00% 15.00% 30.00% $967 $4,190
40.07.07.03.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD EAST STATI 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
Sum
Average
1,316.60 $10,223
15.00% 15.00% 30.00%
$3,067 $13,290Summary for Group: 40.07.07.03
Group 40.07.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
EXECUTIVE STATION SITEWORK Contingency
40.07.08.101 CLEARING AND GRUBBING 0.01 AC $4,022.00 $40 10.00% 10.00% 20.00% $8 $48
40.07.08.304 HOT MIX ASPHALT (TYPE A) 22.00TON $102.00 $2,244 10.00% 10.00% 20.00% $449 $2,693
40.07.08.312 CLASS 2 AGGREGATE BASE 13.00 CY $45.00 $585 10.00% 10.00% 20.00% $117 $702
40.07.08.313 AGGREGATE SUBBASE 13.00 CY $35.00 $455 10.00% 10.00% 20.00% $91 $546
40.07.08.909 LANDSCAPING 3,500.00 SF $4.70 $16,450 15.00% 10.00% 25.00% $4,113 $20,563
40.07.08.911 IRRIGATION 3,500.00 SF $1.40 $4,900 10.00% 10.00% 20.00% $980 $5,880
Sum
Average
7,048.01 $24,674
10.83% 10.00% 20.83%
$5,757 $30,432Summary for Group: 40.07.08
Group 40.07.09
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UTC STATION SITEWORK Contingency
40.07.09.101 CLEARING AND GRUBBING 0.01 AC $4,022.00 $40 10.00% 10.00% 20.00% $8 $48
40.07.09.304 HOT MIX ASPHALT (TYPE A) 22.00TON $102.00 $2,244 10.00% 10.00% 20.00% $449 $2,693
40.07.09.312 CLASS 2 AGGREGATE BASE 13.00 CY $45.00 $585 10.00% 10.00% 20.00% $117 $702
40.07.09.313 AGGREGATE SUBBASE 13.00 CY $35.00 $455 10.00% 10.00% 20.00% $91 $546
40.07.09.909 LANDSCAPING 3,500.00 SF $4.70 $16,450 15.00% 15.00% 30.00% $4,935 $21,385
40.07.09.911 IRRIGATION 3,500.00 SF $1.40 $4,900 15.00% 15.00% 30.00% $1,470 $6,370
Sum
Average
7,048.01 $24,674
11.67% 11.67% 23.33%
$7,070 $31,744Summary for Group: 40.07.09
Group 40.07.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MORENA/CLAIREMONT STREET IMPROVEMENTS Contingency
40.07.10.106 MILL AND OVERLAY (MORENA/CLAIREMONT) 84,699.00 SF $1.90 $160,928 10.00% 10.00% 20.00% $32,186 $193,114
Monday, January 27, 2014 Page 75 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.10.141101 REMOVE YELLOW PAINTED TRAFFIC STRIPE (HAZARDOUS WASTE) 1,500.00 LF $1.00 $1,500 15.00% 10.00% 25.00% $375 $1,875
40.07.10.150608 REMOVE CHAIN LINK FENCE 233.00 LF $2.75 $641 10.00% 10.00% 20.00% $128 $769
40.07.10.150662 REMOVE METAL BEAM GUARD RAILING 213.00 LF $13.00 $2,769 10.00% 10.00% 20.00% $554 $3,323
40.07.10.150711 REMOVE PAINTED TRAFFIC STRIPE 4,930.00 LF $1.00 $4,930 15.00% 10.00% 25.00% $1,233 $6,163
40.07.10.150715 REMOVE THERMOPLASTIC PAVEMENT MARKING 561.00 SF $1.10 $617 15.00% 10.00% 25.00% $154 $771
40.07.10.150722 REMOVE PAVEMENT MARKER 114.00 EA $1.10 $125 15.00% 10.00% 25.00% $31 $157
40.07.10.150838 REMOVE RETAINING WALL (PORTION) (LF) 135.00 LF $54.00 $7,290 10.00% 10.00% 20.00% $1,458 $8,748
40.07.10.153139 REMOVE CONCRETE (SIDEWALK) 1,039.00 LF $12.00 $12,468 10.00% 10.00% 20.00% $2,494 $14,962
40.07.10.153142 REMOVE CONCRETE ISLAND (PORTIONS) (CY) 44.00 CY $175.00 $7,700 10.00% 10.00% 20.00% $1,540 $9,240
40.07.10.153211 REMOVE CONCRETE (SIDEWALK AND DRIVEWAY) 7.00 CY $175.00 $1,225 10.00% 10.00% 20.00% $245 $1,470
40.07.10.153215 REMOVE CONCRETE (CURB AND GUTTER) 3,771.00 LF $3.75 $14,141 10.00% 10.00% 20.00% $2,828 $16,970
40.07.10.190101 ROADWAY EXCAVATION 700.00 CY $28.00 $19,600 10.00% 10.00% 20.00% $3,920 $23,520
40.07.10.192037 STRUCTURE EXCAVATION (RETAINING WALL) 375.00 CY $60.00 $22,500 10.00% 10.00% 20.00% $4,500 $27,000
40.07.10.270003 CEMENT TREATED BASE 316.00 CY $57.00 $18,012 10.00% 10.00% 20.00% $3,602 $21,614
40.07.10.390132 HOT MIX ASPHALT (TYPE A) 547.00TON $102.00 $55,794 10.00% 10.00% 20.00% $11,159 $66,953
40.07.10.510060 STRUCTURAL CONCRETE (RETAINING WALL) 400.00 CY $470.00 $188,000 10.00% 10.00% 20.00% $37,600 $225,600
40.07.10.520103 BAR REINFORCING STEEL (RETAINING WALL) 32,000.00 LB $1.00 $32,000 10.00% 10.00% 20.00% $6,400 $38,400
40.07.10.730070 DETECTABLE WARNING SURFACE 72.00 SF $45.00 $3,240 10.00% 10.00% 20.00% $648 $3,888
40.07.10.731504 MINOR CONCRETE (CURB AND GUTTER) 194.00 CY $365.00 $70,810 10.00% 10.00% 20.00% $14,162 $84,972
40.07.10.731519 MINOR CONCRETE (STAMPED CONCRETE) 7,970.00 SF $19.00 $151,430 10.00% 10.00% 20.00% $30,286 $181,716
40.07.10.731521 MINOR CONCRETE (SIDEWALK) 113.00 CY $347.00 $39,211 10.00% 10.00% 20.00% $7,842 $47,053
40.07.10.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 9.00 CY $765.00 $6,885 10.00% 10.00% 20.00% $1,377 $8,262
40.07.10.800360 CHAIN LINK FENCE (CL-6) 145.00 LF $19.00 $2,755 10.00% 10.00% 20.00% $551 $3,306
40.07.10.832001 METAL BEAM GUARD RAILING (WOOD POST) 425.00 LF $32.00 $13,600 10.00% 10.00% 20.00% $2,720 $16,320
40.07.10.833088 TUBULAR HANDRAILING 266.00 LF $220.00 $58,520 10.00% 10.00% 20.00% $11,704 $70,224
40.07.10.839581 END ANCHOR ASSEMBLY (TYPE SFT) 1.00 EA $819.00 $819 10.00% 10.00% 20.00% $164 $983
40.07.10.839603 CRASH CUSHION (ADIEM) 1.00 EA $30,300.00 $30,300 0.00% 10.00% 10.00% $3,030 $33,330
40.07.10.839703 CONCRETE BARRIER (TYPE 60C) 392.00 LF $88.00 $34,496 10.00% 10.00% 20.00% $6,899 $41,395
40.07.10.840515 THERMOPLASTIC PAVEMENT MARKING 71.00 SF $5.00 $355 10.00% 10.00% 20.00% $71 $426
Monday, January 27, 2014 Page 76 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.10.840515 THERMOPLASTIC PAVEMENT MARKING 584.00 SF $5.00 $2,920 10.00% 10.00% 20.00% $584 $3,504
40.07.10.840656 PAINT TRAFFIC STRIPE (2-COAT) 1,800.00 LF $2.00 $3,600 10.00% 10.00% 20.00% $720 $4,320
40.07.10.850111 PAVEMENT MARKER (RETROREFLECTIVE) 3.00 EA $3.00 $9 10.00% 10.00% 20.00% $2 $11
40.07.10.850111 PAVEMENT MARKER (RETROREFLECTIVE) 91.00 EA $3.00 $273 10.00% 10.00% 20.00% $55 $328
40.07.10.900 STREET LIGHT 2.00 EA $2,000.00 $4,000 10.00% 10.00% 20.00% $800 $4,800
Sum
Average
143,723.00 $973,464
10.29% 10.00% 20.29%
$192,021 $1,165,485Summary for Group: 40.07.10
Group 40.07.10.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MORENA/CLAIREMONT DRAINAGE SYSTEMS Contingency
40.07.10.03.101 18" RCP STORM DRAIN 242.00 LF $120.00 $29,040 15.00% 10.00% 25.00% $7,260 $36,300
40.07.10.03.102 24" RCP STORM DRAIN 151.00 LF $170.00 $25,670 15.00% 10.00% 25.00% $6,418 $32,088
40.07.10.03.103 30" RCP STORM DRAIN 655.00 LF $210.00 $137,550 15.00% 10.00% 25.00% $34,388 $171,938
40.07.10.03.104 36" RCP STORM DRAIN 99.00 LF $230.00 $22,770 15.00% 10.00% 25.00% $5,693 $28,463
40.07.10.03.112 4" NON-PERFORATED PVC 55.00 LF $20.00 $1,100 15.00% 10.00% 25.00% $275 $1,375
40.07.10.03.113 6" NON-PERFORATED PVC 38.00 LF $65.00 $2,470 15.00% 10.00% 25.00% $618 $3,088
40.07.10.03.201 WASH WATER CLEANOUT 2.00 EA $4,500.00 $9,000 15.00% 10.00% 25.00% $2,250 $11,250
40.07.10.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 1.00 EA $4,500.00 $4,500 10.00% 10.00% 20.00% $900 $5,400
40.07.10.03.203 15' TYPE A CURB INLET, SDRSD SDD-115 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500
40.07.10.03.203 5' TYPE A CURB INLET, SDRSD SDD-115 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500
40.07.10.03.203 12' TYPE A CURB INLET, SDRSD SDD-115 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500
40.07.10.03.204 MOD 10' TYPE B-1 CURB INLET, SDRSD SDD-116 2.00 EA $6,900.00 $13,800 10.00% 10.00% 20.00% $2,760 $16,560
40.07.10.03.204 15' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500
40.07.10.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 2.00 EA $5,200.00 $10,400 15.00% 10.00% 25.00% $2,600 $13,000
40.07.10.03.208 9' TYPE J MEDIAN CURB INLET, SDRSD SDD-118 6.00 EA $6,900.00 $41,400 15.00% 10.00% 25.00% $10,350 $51,750
40.07.10.03.504 PIPE TO RCB CONNECTION 4.00 EA $9,993.00 $39,972 15.00% 10.00% 25.00% $9,993 $49,965
40.07.10.03.510 TRENCH DRAIN 651.00 LF $35.00 $22,785 15.00% 10.00% 25.00% $5,696 $28,481
40.07.10.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 4.00 EA $675.00 $2,700 15.00% 10.00% 25.00% $675 $3,375
40.07.10.03.701 ABANDON DRAINAGE STRUCTURE 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546
40.07.10.03.702 REMOVE EXIST DRAINAGE STRUCTURE 3.00 EA $1,829.00 $5,487 15.00% 10.00% 25.00% $1,372 $6,859
Monday, January 27, 2014 Page 77 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
1,920.00 $397,881
14.50% 10.00% 24.50%
$98,555 $496,436Summary for Group: 40.07.10.03
Group 40.07.11
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE STREET IMPROVEMENTS Contingency
40.07.11.100 CHAIN LINK FENCE (CL-6) 1,510.00 LF $19.00 $28,690 10.00% 10.00% 20.00% $5,738 $34,428
40.07.11.103 AWNING (LA JOLLA COUNTRY DAY SCHOOL) 1,970.00 SF $38.00 $74,860 10.00% 10.00% 20.00% $14,972 $89,832
40.07.11.106 MILL AND OVERLAY (GENESEE) 546,940.00 SF $1.90 $1,039,186 10.00% 10.00% 20.00% $207,837 $1,247,023
40.07.11.141101 REMOVE YELLOW PAINTED TRAFFIC STRIPE (HAZARDOUS WASTE) 14,027.00 LF $1.00 $14,027 15.00% 10.00% 25.00% $3,507 $17,534
40.07.11.150609A REMOVE FENCE (MASONARY BLOCK) 249.00 LF $30.00 $7,470 10.00% 10.00% 20.00% $1,494 $8,964
40.07.11.150711 REMOVE PAINTED TRAFFIC STRIPE 33,575.00 LF $1.00 $33,575 15.00% 10.00% 25.00% $8,394 $41,969
40.07.11.150715 REMOVE THERMOPLASTIC PAVEMENT MARKING 4,218.00 SF $1.10 $4,640 15.00% 10.00% 25.00% $1,160 $5,800
40.07.11.150722 REMOVE PAVEMENT MARKER 1,177.00 EA $1.10 $1,295 15.00% 10.00% 25.00% $324 $1,618
40.07.11.150742 REMOVE ROADSIDE SIGN 50.00 EA $500.00 $25,000 10.00% 10.00% 20.00% $5,000 $30,000
40.07.11.150838 REMOVE SOUNDWALL 351.00 LF $54.00 $18,954 10.00% 10.00% 20.00% $3,791 $22,745
40.07.11.153139 REMOVE CONCRETE (SIDEWALK) 9,158.00 LF $12.00 $109,896 10.00% 10.00% 20.00% $21,979 $131,875
40.07.11.153142 REMOVE CONCRETE ISLAND (PORTIONS) (CY) 666.00 CY $175.00 $116,550 10.00% 10.00% 20.00% $23,310 $139,860
40.07.11.153211 REMOVE CONCRETE (SIDEWALK AND DRIVEWAY) 51.00 CY $175.00 $8,925 10.00% 10.00% 20.00% $1,785 $10,710
40.07.11.153215 REMOVE CONCRETE (CURB AND GUTTER) 20,334.00 LF $3.75 $76,253 10.00% 10.00% 20.00% $15,251 $91,503
40.07.11.190101 ROADWAY EXCAVATION 19,339.00 CY $28.00 $541,492 10.00% 10.00% 20.00% $108,298 $649,790
40.07.11.192037 STRUCTURE EXCAVATION (RETAINING WALL) 1,481.00 CY $60.00 $88,860 10.00% 10.00% 20.00% $17,772 $106,632
40.07.11.260203 CLASS 2 AGGREGATE BASE 47.00 CY $45.00 $2,115 10.00% 10.00% 20.00% $423 $2,538
40.07.11.270003 CEMENT TREATED BASE 6,361.00 CY $57.00 $362,577 10.00% 10.00% 20.00% $72,515 $435,092
40.07.11.390132 HOT MIX ASPHALT (TYPE A) 3,817.00TON $102.00 $389,334 10.00% 10.00% 20.00% $77,867 $467,201
40.07.11.401050 JOINTED PLAIN CONCRETE PAVEMENT 47.00 CY $447.00 $21,009 10.00% 10.00% 20.00% $4,202 $25,211
40.07.11.475010 RETAINING WALL (MASONRY WALL) 13,438.00 SF $70.00 $940,660 15.00% 15.00% 30.00% $282,198 $1,222,858
40.07.11.510062A STRUCTURAL CONCRETE (GRAVITY RETAINING WALL) 187.00 CY $650.00 $121,550 10.00% 10.00% 20.00% $24,310 $145,860
40.07.11.518002 SOUND WALL (W/FOOTING) 4,551.00 SF $35.00 $159,285 10.00% 10.00% 20.00% $31,857 $191,142
40.07.11.566011 ROADSIDE SIGN - ONE POST 50.00 EA $750.00 $37,500 10.00% 10.00% 20.00% $7,500 $45,000
40.07.11.582003A FENCE (MASONRY BLOCK) 2,000.00 SF $35.00 $70,000 10.00% 10.00% 20.00% $14,000 $84,000
40.07.11.730070 DETECTABLE WARNING SURFACE 396.00 SF $45.00 $17,820 10.00% 10.00% 20.00% $3,564 $21,384
Monday, January 27, 2014 Page 78 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.11.731504 MINOR CONCRETE (CURB AND GUTTER) 530.00 CY $365.00 $193,450 10.00% 10.00% 20.00% $38,690 $232,140
40.07.11.731516 MINOR CONCRETE (DRIVEWAY) 76.00 CY $475.00 $36,100 10.00% 10.00% 20.00% $7,220 $43,320
40.07.11.731519 MINOR CONCRETE (STAMPED CONCRETE) 957.00 CY $347.00 $332,079 10.00% 10.00% 20.00% $66,416 $398,495
40.07.11.731521 MINOR CONCRETE (SIDEWALK) 626.00 CY $347.00 $217,222 10.00% 10.00% 20.00% $43,444 $260,666
40.07.11.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 40.00 CY $765.00 $30,600 10.00% 10.00% 20.00% $6,120 $36,720
40.07.11.833088 TUBULAR HANDRAILING 790.00 LF $220.00 $173,800 10.00% 10.00% 20.00% $34,760 $208,560
40.07.11.839607A CRASH CUSHION (TAU II) 16.00 EA $15,000.00 $240,000 0.00% 10.00% 10.00% $24,000 $264,000
40.07.11.839701 CONCRETE BARRIER (TYPE 60) 8,700.00 LF $46.00 $400,200 10.00% 10.00% 20.00% $80,040 $480,240
40.07.11.840515 THERMOPLASTIC PAVEMENT MARKING 6,901.00 SF $5.00 $34,505 10.00% 10.00% 20.00% $6,901 $41,406
40.07.11.840656 PAINT TRAFFIC STRIPE (2-COAT) 54,100.00 LF $2.00 $108,200 10.00% 10.00% 20.00% $21,640 $129,840
40.07.11.850111 PAVEMENT MARKER (RETROREFLECTIVE) 1,072.00 EA $3.00 $3,216 10.00% 10.00% 20.00% $643 $3,859
40.07.11.900 STREET LIGHT 28.00 EA $2,000.00 $56,000 10.00% 10.00% 20.00% $11,200 $67,200
40.07.11.901 REMOVE STREET LIGHT 10.00 EA $1,500.00 $15,000 10.00% 10.00% 20.00% $3,000 $18,000
40.07.11.902 LIGHT FIXTURES UNDER AERIAL STRUCTURE 20.00 EA $2,000.00 $40,000 10.00% 10.00% 20.00% $8,000 $48,000
Sum
Average
759,856.00 $6,191,894
10.38% 10.13% 20.50%
$1,311,122 $7,503,016Summary for Group: 40.07.11
Group 40.07.11.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE AVE DRAINAGE IMPROVEMENTS Contingency
40.07.11.03.101 18" RCP STORM DRAIN 2,368.00 LF $120.00 $284,160 15.00% 10.00% 25.00% $71,040 $355,200
40.07.11.03.102 24" RCP STORM DRAIN 77.00 LF $170.00 $13,090 15.00% 10.00% 25.00% $3,273 $16,363
40.07.11.03.103 30" RCP STORM DRAIN 6.00 LF $210.00 $1,260 15.00% 10.00% 25.00% $315 $1,575
40.07.11.03.104 36" RCP STORM DRAIN 57.00 LF $230.00 $13,110 15.00% 10.00% 25.00% $3,278 $16,388
40.07.11.03.105 42" RCP STORM DRAIN 734.00 LF $260.00 $190,840 15.00% 10.00% 25.00% $47,710 $238,550
40.07.11.03.116 10" NON-PERFORATED PVC 10.00 LF $104.00 $1,040 15.00% 10.00% 25.00% $260 $1,300
40.07.11.03.201 TYPE A-6 SD CLEANOUT, SDRSD D-9 3.00 EA $5,500.00 $16,500 15.00% 10.00% 25.00% $4,125 $20,625
40.07.11.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 17.00 EA $4,500.00 $76,500 15.00% 10.00% 25.00% $19,125 $95,625
40.07.11.03.201 TYPE A-8 SD CLEANOUT, SDRSD D-9 1.00 EA $6,000.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500
40.07.11.03.204 10' TYPE B CURB INLET, SDRSD SDD-116 3.00 EA $6,900.00 $20,700 15.00% 10.00% 25.00% $5,175 $25,875
40.07.11.03.204 21' TYPE B-1 CURB INLET, SDRSD SDD-116 3.00 EA $8,100.00 $24,300 15.00% 10.00% 25.00% $6,075 $30,375
40.07.11.03.204 15' TYPE B CURB INLET, SDRSD SDD-116 6.00 EA $7,600.00 $45,600 15.00% 10.00% 25.00% $11,400 $57,000
Monday, January 27, 2014 Page 79 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.11.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 2.00 EA $5,200.00 $10,400 15.00% 10.00% 25.00% $2,600 $13,000
40.07.11.03.204 21' TYPE B-2 CURB INLET, SDRSD SDD-116 1.00 EA $8,100.00 $8,100 15.00% 10.00% 25.00% $2,025 $10,125
40.07.11.03.204 10' TYPE B-2 CURB INLET, SDRSD SDD-116 3.00 EA $6,900.00 $20,700 15.00% 10.00% 25.00% $5,175 $25,875
40.07.11.03.204 7' TYPE B-2 CURB INLET, SDD-116 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500
40.07.11.03.207 TYPE I CATCH BASIN, SDRSD D-29 11.00 EA $6,450.00 $70,950 15.00% 10.00% 25.00% $17,738 $88,688
40.07.11.03.208 9' TYPE J MEDIAN CURB INLET, SDRSD SDD-118 2.00 EA $6,900.00 $13,800 15.00% 10.00% 25.00% $3,450 $17,250
40.07.11.03.209 TYPE A CURB OUTLET, SDRSD D-25 3.00 EA $2,500.00 $7,500 15.00% 10.00% 25.00% $1,875 $9,375
40.07.11.03.500 ADJUST MH TO FG 2.00 EA $1,100.00 $2,200 15.00% 10.00% 25.00% $550 $2,750
40.07.11.03.501 CONCRETE LUG, SDRSD SD-113 5.00 EA $1,100.00 $5,500 15.00% 10.00% 25.00% $1,375 $6,875
40.07.11.03.502 PIPE COLLAR 12.00 EA $1,800.00 $21,600 15.00% 10.00% 25.00% $5,400 $27,000
40.07.11.03.600 HYDROMODIFICATION SURFACE STORAGE 24,000.00 CF $2.00 $48,000 15.00% 10.00% 25.00% $12,000 $60,000
40.07.11.03.602 HYDROMODIFICATION OUTLET STRUCTURE - SURFACE STORAGE 12.00 EA $5,000.00 $60,000 15.00% 10.00% 25.00% $15,000 $75,000
40.07.11.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 8.00 EA $675.00 $5,400 15.00% 10.00% 25.00% $1,350 $6,750
40.07.11.03.701 ABANDON DRAINAGE STRUCTURE 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546
40.07.11.03.702 REMOVE EXIST DRAINAGE STRUCTURE 14.00 EA $1,829.00 $25,606 15.00% 10.00% 25.00% $6,402 $32,008
40.07.11.03.704 REMOVE EXIST CURB OUTLET 4.00 EA $590.00 $2,360 15.00% 10.00% 25.00% $590 $2,950
Sum
Average
27,366.00 $1,001,653
15.00% 10.00% 25.00%
$250,413 $1,252,066Summary for Group: 40.07.11.03
Group 40.07.12
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PACIFIC HWY/ TAYLOR/ ROSECRANS STREET IMPROVEMENTS Contingency
40.07.12.10.08 PERVIOUS BACKFILL 62.00 CY $36.00 $2,232 10.00% 10.00% 20.00% $446 $2,678
40.07.12.10.10 STRUCTURAL BACKFILL 298.00 CY $52.00 $15,496 10.00% 10.00% 20.00% $3,099 $18,595
40.07.12.10.20 STRUCTURE EXCAVATION 378.00 CY $60.00 $22,680 10.00% 10.00% 20.00% $4,536 $27,216
40.07.12.10.40 STRUCTURAL CONCRETE (RETAINING WALL) 443.00 CY $470.00 $208,210 10.00% 10.00% 20.00% $41,642 $249,852
40.07.12.10.50 ARCHITECTURAL TREATMENT 3,996.00 SF $14.00 $55,944 10.00% 10.00% 20.00% $11,189 $67,133
40.07.12.10.60 BAR REINFORCING STEEL 58,631.00 LB $1.00 $58,631 10.00% 10.00% 20.00% $11,726 $70,357
40.07.12.10.70 CABLE RAILING 666.00 LF $25.00 $16,650 10.00% 10.00% 20.00% $3,330 $19,980
40.07.12.101 CHAIN LINK FENCE (CL-3) 890.00 LF $16.00 $14,240 10.00% 10.00% 20.00% $2,848 $17,088
40.07.12.106 MILL AND OVERLAY (PACIFIC HWY/ROSECRANS) 75,208.00 SF $1.90 $142,895 10.00% 10.00% 20.00% $28,579 $171,474
40.07.12.109 6" PORTLAND CEMENT CONCRETE (DECORATIVE CONCRETE) 25.90 CY $625.00 $16,188 10.00% 10.00% 20.00% $3,238 $19,425
Monday, January 27, 2014 Page 80 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.12.150710 REMOVE TRAFFIC STRIPE 5,800.00 LF $1.00 $5,800 15.00% 10.00% 25.00% $1,450 $7,250
40.07.12.150713 REMOVE PAVEMENT MARKING 1,300.00 SF $1.10 $1,430 15.00% 10.00% 25.00% $358 $1,788
40.07.12.150742 ROADSIDE SIGN - ONE POST 12.00 EA $750.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
40.07.12.150742 REMOVE ROADSIDE SIGN 12.00 EA $500.00 $6,000 10.00% 10.00% 20.00% $1,200 $7,200
40.07.12.150770 SAWCUT ASPHALT PAVEMENT 237.00 LF $2.00 $474 10.00% 10.00% 20.00% $95 $569
40.07.12.150770 SAWCUT ASPHALT PAVEMENT 963.00 LF $2.00 $1,926 10.00% 10.00% 20.00% $385 $2,311
40.07.12.150838 REMOVE RETAINING WALL 300.00 LF $54.00 $16,200 10.00% 10.00% 20.00% $3,240 $19,440
40.07.12.150838 REMOVE RETAINING WALL 910.00 LF $54.00 $49,140 10.00% 10.00% 20.00% $9,828 $58,968
40.07.12.153241 REMOVE CONCRETE (SIDEWALK) 3,963.00 SF $3.00 $11,889 10.00% 10.00% 20.00% $2,378 $14,267
40.07.12.153241 REMOVE CONCRETE (SIDEWALK) 1,500.00 SF $3.00 $4,500 10.00% 10.00% 20.00% $900 $5,400
40.07.12.190101 ROADWAY EXCAVATION 750.00 CY $28.00 $21,000 10.00% 10.00% 20.00% $4,200 $25,200
40.07.12.190101 ROADWAY EXCAVATION 181.00 CY $28.00 $5,068 10.00% 10.00% 20.00% $1,014 $6,082
40.07.12.270011 CEMENT TREATED BASE 116.00 CY $57.00 $6,612 10.00% 10.00% 20.00% $1,322 $7,934
40.07.12.270011 CEMENT TREATED BASE 445.00 CY $57.00 $25,365 10.00% 10.00% 20.00% $5,073 $30,438
40.07.12.390132 HOT MIX ASPHALT (TYPE A) 53.00TON $102.00 $5,406 10.00% 10.00% 20.00% $1,081 $6,487
40.07.12.390132 HOT MIX ASPHALT (TYPE A) 255.00TON $102.00 $26,010 10.00% 10.00% 20.00% $5,202 $31,212
40.07.12.731504.1 MINOR CONCRETE (CURB AND GUTTER) (TYPE B) 380.00 LF $34.00 $12,920 10.00% 10.00% 20.00% $2,584 $15,504
40.07.12.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 219.00 LF $36.00 $7,884 10.00% 10.00% 20.00% $1,577 $9,461
40.07.12.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 784.00 LF $36.00 $28,224 10.00% 10.00% 20.00% $5,645 $33,869
40.07.12.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 72.00 CY $635.00 $45,720 10.00% 10.00% 20.00% $9,144 $54,864
40.07.12.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 26.00 CY $635.00 $16,510 10.00% 10.00% 20.00% $3,302 $19,812
40.07.12.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.12.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.12.840515 THERMOPLASTIC PAVEMENT MARKING 1,279.00 SF $5.00 $6,395 10.00% 10.00% 20.00% $1,279 $7,674
40.07.12.840656 PAINT TRAFFIC STRIPE (2-COAT) 6,060.00 LF $2.00 $12,120 10.00% 10.00% 20.00% $2,424 $14,544
40.07.12.850101 PAVEMENT MARKER (NON-REFLECTIVE) 120.00 EA $2.00 $240 15.00% 10.00% 25.00% $60 $300
40.07.12.850111 PAVEMENT MARKER (RETROREFLECTIVE) 121.00 EA $3.00 $363 10.00% 10.00% 20.00% $73 $436
40.07.12.850111 PAVEMENT MARKER (RETROREFLECTIVE) 121.00 EA $3.00 $363 10.00% 10.00% 20.00% $73 $436
40.07.12.900 STREET LIGHT 2.00 EA $2,000.00 $4,000 10.00% 10.00% 20.00% $800 $4,800
Monday, January 27, 2014 Page 81 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.12.901 REMOVE STREET LIGHT 2.00 EA $1,500.00 $3,000 10.00% 10.00% 20.00% $600 $3,600
Sum
Average
166,594.90 $897,435
10.38% 10.00% 20.38%
$179,860 $1,077,295Summary for Group: 40.07.12
Group 40.07.13
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
WASHINGTON/ FRONTAGE STREET IMPROVEMENTS Contingency
40.07.13.150713 REMOVE PAVEMENT MARKING 164.00 SF $1.10 $180 15.00% 10.00% 25.00% $45 $226
40.07.13.150742 REMOVE ROADSIDE SIGN 3.00 EA $500.00 $1,500 10.00% 10.00% 20.00% $300 $1,800
40.07.13.566011 ROADSIDE SIGN - ONE POST 3.00 EA $750.00 $2,250 10.00% 10.00% 20.00% $450 $2,700
40.07.13.840515 THERMOPLASTIC PAVEMENT MARKING 164.00 SF $5.00 $820 10.00% 10.00% 20.00% $164 $984
40.07.13.850111 PAVEMENT MARKER (RETROREFLECTIVE) 17.00 EA $3.00 $51 10.00% 10.00% 20.00% $10 $61
Sum
Average
351.00 $4,801
11.00% 10.00% 21.00%
$969 $5,771Summary for Group: 40.07.13
Group 40.07.14
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SASSAFRAS/ KETTNER STREET IMPROVEMENTS Contingency
40.07.14.150713 REMOVE PAVEMENT MARKING 30.00 SF $1.10 $33 15.00% 10.00% 25.00% $8 $41
40.07.14.150742 REMOVE ROADSIDE SIGN 2.00 EA $500.00 $1,000 10.00% 10.00% 20.00% $200 $1,200
40.07.14.566011 ROADSIDE SIGN - ONE POST 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800
40.07.14.840515 THERMOPLASTIC PAVEMENT MARKING 30.00 SF $5.00 $150 10.00% 10.00% 20.00% $30 $180
40.07.14.850111 PAVEMENT MARKER (RETROREFLECTIVE) 7.00 EA $3.00 $21 10.00% 10.00% 20.00% $4 $25
Sum
Average
71.00 $2,704
11.00% 10.00% 21.00%
$542 $3,246Summary for Group: 40.07.14
Group 40.07.15
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CEDAR/ KETTNER STREET IMPROVEMENTS Contingency
40.07.15.150713 REMOVE PAVEMENT MARKING 60.00 SF $1.10 $66 15.00% 10.00% 25.00% $17 $83
40.07.15.150742 REMOVE ROADSIDE SIGN 6.00 EA $500.00 $3,000 10.00% 10.00% 20.00% $600 $3,600
40.07.15.566011 ROADSIDE SIGN - ONE POST 6.00 EA $750.00 $4,500 10.00% 10.00% 20.00% $900 $5,400
40.07.15.840515 THERMOPLASTIC PAVEMENT MARKING 60.00 SF $5.00 $300 10.00% 10.00% 20.00% $60 $360
Sum
Average
132.00 $7,866
11.25% 10.00% 21.25%
$1,577 $9,443Summary for Group: 40.07.15
Group 40.07.16
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PACIFIC HWY/CEDAR STREET IMPROVEMENTS Contingency
40.07.16.150713 REMOVE PAVEMENT MARKING 70.00 SF $1.10 $77 15.00% 10.00% 25.00% $19 $96
Monday, January 27, 2014 Page 82 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.16.150742 REMOVE ROADSIDE SIGN 3.00 EA $500.00 $1,500 10.00% 10.00% 20.00% $300 $1,800
40.07.16.150770 SAWCUT ASPHALT PAVEMENT 3,120.00 LF $2.00 $6,240 10.00% 10.00% 20.00% $1,248 $7,488
40.07.16.270011 CEMENT TREATED BASE 115.00 CY $57.00 $6,555 10.00% 10.00% 20.00% $1,311 $7,866
40.07.16.390132 HOT MIX ASPHALT (TYPE A) 66.00TON $102.00 $6,732 10.00% 10.00% 20.00% $1,346 $8,078
40.07.16.566011 ROADSIDE SIGN - ONE POST 3.00 EA $750.00 $2,250 10.00% 10.00% 20.00% $450 $2,700
40.07.16.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 800.00 LF $36.00 $28,800 10.00% 10.00% 20.00% $5,760 $34,560
40.07.16.840515 THERMOPLASTIC PAVEMENT MARKING 115.00 SF $5.00 $575 10.00% 10.00% 20.00% $115 $690
40.07.16.850111 PAVEMENT MARKER (RETROREFLECTIVE) 90.00 EA $3.00 $270 10.00% 10.00% 20.00% $54 $324
Sum
Average
4,382.00 $52,999
10.56% 10.00% 20.56%
$10,604 $63,603Summary for Group: 40.07.16
Group 40.07.17
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MORENA/BALBOA STREET IMPROVEMENTS Contingency
40.07.17.106 MILL AND OVERLAY (MORENA/BALBOA) 122,414.00 SF $1.90 $232,587 10.00% 10.00% 20.00% $46,517 $279,104
40.07.17.107 ASPHALT PAVEMENT REMOVAL 258,300.00 SF $1.60 $413,280 10.00% 10.00% 20.00% $82,656 $495,936
40.07.17.150710 REMOVE TRAFFIC STRIPE 13,250.00 LF $1.00 $13,250 15.00% 10.00% 25.00% $3,313 $16,563
40.07.17.150713 REMOVE PAVEMENT MARKING 20.00 SF $1.10 $22 15.00% 10.00% 25.00% $6 $28
40.07.17.190101 ROADWAY EXCAVATION 3,062.00 CY $28.00 $85,736 10.00% 10.00% 20.00% $17,147 $102,883
40.07.17.192037 STRUCTURE EXCAVATION (RETAINING WALL) 556.00 CY $60.00 $33,360 10.00% 10.00% 20.00% $6,672 $40,032
40.07.17.193013 STRUCTURAL BACKFILL 730.00 CY $52.00 $37,960 10.00% 10.00% 20.00% $7,592 $45,552
40.07.17.260203 CLASS 2 AGGREGATE BASE 1,060.00 CY $45.00 $47,700 10.00% 10.00% 20.00% $9,540 $57,240
40.07.17.390132 HOT MIX ASPHALT (TYPE A) 1,340.00TON $102.00 $136,680 10.00% 10.00% 20.00% $27,336 $164,016
40.07.17.401050 JOINTED PLAIN CONCRETE PAVEMENT 120.00 CY $447.00 $53,640 10.00% 10.00% 20.00% $10,728 $64,368
40.07.17.510060 STRUCTURAL CONCRETE (RETAINING WALL) 273.00 CY $470.00 $128,310 10.00% 10.00% 20.00% $25,662 $153,972
40.07.17.520103 BAR REINFORCING STEEL (RETAINING WALL) 39,240.00 LB $1.00 $39,240 10.00% 10.00% 20.00% $7,848 $47,088
40.07.17.730020 MINOR CONCRETE (CURB) 8.00 CY $500.00 $4,000 10.00% 10.00% 20.00% $800 $4,800
40.07.17.730070 DETECTABLE WARNING SURFACE 192.00 SF $45.00 $8,640 10.00% 10.00% 20.00% $1,728 $10,368
40.07.17.731504 MINOR CONCRETE (CURB AND GUTTER) 222.00 CY $365.00 $81,030 10.00% 10.00% 20.00% $16,206 $97,236
40.07.17.731521 MINOR CONCRETE (SIDEWALK) 325.00 CY $347.00 $112,775 10.00% 10.00% 20.00% $22,555 $135,330
40.07.17.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 13.00 CY $765.00 $9,945 10.00% 10.00% 20.00% $1,989 $11,934
40.07.17.839521 CABLE RAILING 425.00 LF $25.00 $10,625 10.00% 10.00% 20.00% $2,125 $12,750
Monday, January 27, 2014 Page 83 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.17.839603 CRASH ATTENUATOR 1.00 EA $55,205.00 $55,205 0.00% 10.00% 10.00% $5,521 $60,726
40.07.17.840515 THERMOPLASTIC PAVEMENT MARKING 2,680.00 SF $5.00 $13,400 10.00% 10.00% 20.00% $2,680 $16,080
40.07.17.840656 PAINT TRAFFIC STRIPE (2 COAT) 13,250.00 LF $2.00 $26,500 10.00% 10.00% 20.00% $5,300 $31,800
40.07.17.850111 PAVEMENT MARKER (RETROREFLECTIVE) 336.00 EA $3.00 $1,008 10.00% 10.00% 20.00% $202 $1,210
40.07.17.866011 ROADSIDE SIGN - ONE POST 70.00 EA $750.00 $52,500 10.00% 10.00% 20.00% $10,500 $63,000
40.07.17.900 STREET LIGHT 10.00 EA $2,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
40.07.17.901 REMOVE STREET LIGHT 9.00 EA $1,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
Sum
Average
457,906.00 $1,630,893
10.00% 10.00% 20.00%
$321,322 $1,952,214Summary for Group: 40.07.17
Group 40.07.17.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MORENA/BALBOA STREET IMPROVEMENTS DRAINAGE SYSTEMS Contingency
40.07.17.03.101 18" RCP STORM DRAIN 714.00 LF $120.00 $85,680 15.00% 10.00% 25.00% $21,420 $107,100
40.07.17.03.122 4" PERFORATED PVE 340.00 LF $20.00 $6,800 15.00% 10.00% 25.00% $1,700 $8,500
40.07.17.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
40.07.17.03.204 15' TYPE B-1 CURB INLET, SDRSD SDD-116 2.00 EA $7,600.00 $15,200 15.00% 10.00% 25.00% $3,800 $19,000
40.07.17.03.204 10' TYPE B-1 CURB INLET, SDRSD SDD-116 2.00 EA $6,900.00 $13,800 15.00% 10.00% 25.00% $3,450 $17,250
40.07.17.03.204 21' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $8,100.00 $8,100 15.00% 10.00% 25.00% $2,025 $10,125
40.07.17.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 2.00 EA $5,200.00 $10,400 15.00% 10.00% 25.00% $2,600 $13,000
40.07.17.03.207 TYPE I CATCH BASIN, SDRSD D-29 1.00 EA $6,450.00 $6,450 10.00% 10.00% 20.00% $1,290 $7,740
40.07.17.03.208 9' TYPE J MEDIAN CURB INLET, SDRSD SDD-118 3.00 EA $6,900.00 $20,700 15.00% 10.00% 25.00% $5,175 $25,875
40.07.17.03.210 WING TYPE HEADWALL, SDRSD D34 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
40.07.17.03.211 4.5' TYPE OS INLET, CT STD D72 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625
40.07.17.03.501 CONCRETE LUG, SDRSD SDD-113 1.00 EA $1,100.00 $1,100 15.00% 10.00% 25.00% $275 $1,375
40.07.17.03.505 1/4 TON RIPRAP ENERGY DISSIPATOR TYPE 2, SDRSD SDD-104 2.00 EA $2,500.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250
40.07.17.03.508 4" UNDERDRAIN CLEANOUT 5.00 EA $60.00 $300 15.00% 10.00% 25.00% $75 $375
Sum
Average
1,078.00 $196,030
13.93% 10.00% 23.93%
$47,785 $243,815Summary for Group: 40.07.17.03
Group 40.07.18
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
W MORENA/TECOLOTE STREET IMPROVEMENTS Contingency
40.07.18.102 6' PICKET FENCE 700.00 LF $72.00 $50,400 10.00% 10.00% 20.00% $10,080 $60,480
40.07.18.106 MILL AND OVERLAY (WMORENA/TECOLOTE) 49,272.00 SF $1.90 $93,617 10.00% 10.00% 20.00% $18,723 $112,340
Monday, January 27, 2014 Page 84 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.18.141101 REMOVE YELLOW PAINTED TRAFFIC STRIPE (HAZARDOUS WASTE) 20.00 LF $1.00 $20 15.00% 10.00% 25.00% $5 $25
40.07.18.150608 REMOVE CHAIN LINK FENCE 175.00 LF $2.75 $481 10.00% 10.00% 20.00% $96 $578
40.07.18.150662 REMOVE METAL BEAM GUARD RAILING 48.00 LF $13.00 $624 10.00% 10.00% 20.00% $125 $749
40.07.18.150710 REMOVE TRAFFIC STRIPE 38.00 LF $1.00 $38 15.00% 10.00% 25.00% $10 $48
40.07.18.150715 REMOVE THERMOPLASTIC PAVEMENT MARKING 433.00 SF $1.10 $476 15.00% 10.00% 25.00% $119 $595
40.07.18.150722 REMOVE PAVEMENT MARKER 6.00 EA $1.10 $7 15.00% 10.00% 25.00% $2 $8
40.07.18.153139 REMOVE CONCRETE (SIDEWALK) 119.00 LF $12.00 $1,428 10.00% 10.00% 20.00% $286 $1,714
40.07.18.153142 REMOVE CONCRETE ISLAND (PORTIONS) (CY) 9.00 CY $175.00 $1,575 10.00% 10.00% 20.00% $315 $1,890
40.07.18.153212A REMOVE CONCRETE (SIDEWALK AND BARRIER) 15.00 CY $100.00 $1,500 15.00% 10.00% 25.00% $375 $1,875
40.07.18.153215 REMOVE CONCRETE (CURB AND GUTTER) 1,231.00 LF $3.75 $4,616 10.00% 10.00% 20.00% $923 $5,540
40.07.18.190101 ROADWAY EXCAVATION 639.00 CY $28.00 $17,892 10.00% 10.00% 20.00% $3,578 $21,470
40.07.18.260203 CLASS 2 AGGREGATE BASE 135.00 CY $45.00 $6,075 10.00% 10.00% 20.00% $1,215 $7,290
40.07.18.390132 HOT MIX ASPHALT (TYPE A) 95.00TON $102.00 $9,690 10.00% 10.00% 20.00% $1,938 $11,628
40.07.18.401050 JOINTED PLAIN CONCRETE PAVEMENT 135.00 CY $447.00 $60,345 10.00% 10.00% 20.00% $12,069 $72,414
40.07.18.478010 RETAINING WALL (MASONRY WALL) 1,350.00 SF $70.00 $94,500 15.00% 15.00% 30.00% $28,350 $122,850
40.07.18.730020 MINOR CONCRETE (CURB) 17.00 CY $500.00 $8,500 10.00% 10.00% 20.00% $1,700 $10,200
40.07.18.730070 DETECTABLE WARNING SURFACE 60.00 SF $45.00 $2,700 10.00% 10.00% 20.00% $540 $3,240
40.07.18.731502 MINOR CONCRETE (MISCELLANEOUS CONSTRUCTION) 34.00 CY $937.00 $31,858 10.00% 10.00% 20.00% $6,372 $38,230
40.07.18.731504 MINOR CONCRETE (CURB AND GUTTER) 52.00 CY $365.00 $18,980 10.00% 10.00% 20.00% $3,796 $22,776
40.07.18.731519 MINOR CONCRETE (STAMPED CONCRETE) 861.00 SF $19.00 $16,359 10.00% 10.00% 20.00% $3,272 $19,631
40.07.18.731521 MINOR CONCRETE (SIDEWALK) 106.00 CY $347.00 $36,782 10.00% 10.00% 20.00% $7,356 $44,138
40.07.18.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 6.00 CY $765.00 $4,590 10.00% 10.00% 20.00% $918 $5,508
40.07.18.800360 CHAIN LINK FENCE (CL-6) 690.00 LF $19.00 $13,110 10.00% 10.00% 20.00% $2,622 $15,732
40.07.18.833088 TUBULAR HANDRAILING 270.00 LF $220.00 $59,400 10.00% 10.00% 20.00% $11,880 $71,280
40.07.18.833140 CONCRETE BARRIER (TYPE 26) 62.00 LF $100.00 $6,200 10.00% 10.00% 20.00% $1,240 $7,440
40.07.18.840515 THERMOPLASTIC PAVEMENT MARKING 433.00 SF $5.00 $2,165 10.00% 10.00% 20.00% $433 $2,598
Sum
Average
57,011.00 $543,928
11.07% 10.18% 21.25%
$118,338 $662,266Summary for Group: 40.07.18
Group 40.07.18.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
W MORENA/TECOLOTE STREET IMPROVEMENTS DRAINAGE SYSTEMS Contingency
Monday, January 27, 2014 Page 85 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.18.03.101 18" RCP STORM DRAIN 58.00 LF $120.00 $6,960 15.00% 10.00% 25.00% $1,740 $8,700
40.07.18.03.208 5' TYPE J MEDIAN CURB INLET, SDRSD SDD-118 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500
Sum
Average
59.00 $12,160
15.00% 10.00% 25.00%
$3,040 $15,200Summary for Group: 40.07.18.03
Group 40.07.19
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CAMPUS POINT STREET IMPROVEMENTS Contingency
40.07.19.106 MILL AND OVERLAY (CAMPUS POINT) 58,200.00 SF $1.90 $110,580 10.00% 10.00% 20.00% $22,116 $132,696
40.07.19.150742 REMOVE ROADSIDE SIGN 12.00 EA $500.00 $6,000 10.00% 10.00% 20.00% $1,200 $7,200
40.07.19.150770 SAWCUT ASPHALT PAVEMENT 580.00 LF $2.00 $1,160 10.00% 10.00% 20.00% $232 $1,392
40.07.19.153241 REMOVE CONCRETE (SIDEWALK) 1,716.00 SF $3.00 $5,148 10.00% 10.00% 20.00% $1,030 $6,178
40.07.19.190101 ROADWAY EXCAVATION 633.00 CY $28.00 $17,724 10.00% 10.00% 20.00% $3,545 $21,269
40.07.19.260203 CLASS 2 AGGREGATE BASE 222.00 CY $45.00 $9,990 10.00% 10.00% 20.00% $1,998 $11,988
40.07.19.390132 HOT MIX ASPHALT (TYPE A) 193.00TON $102.00 $19,686 10.00% 10.00% 20.00% $3,937 $23,623
40.07.19.566011 ROADSIDE SIGN - ONE POST 12.00 EA $750.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
40.07.19.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 792.00 LF $36.00 $28,512 10.00% 10.00% 20.00% $5,702 $34,214
40.07.19.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 16.00 CY $635.00 $10,160 10.00% 10.00% 20.00% $2,032 $12,192
40.07.19.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.19.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.19.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.19.839603 CRASH ATTENUATOR 2.00 EA $55,205.00 $110,410 0.00% 10.00% 10.00% $11,041 $121,451
40.07.19.839701 CONCRETE BARRIER 125.00 LF $53.00 $6,625 10.00% 10.00% 20.00% $1,325 $7,950
40.07.19.900 STREET LIGHT 10.00 EA $2,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
40.07.19.901 REMOVE STREET LIGHT 10.00 EA $1,500.00 $15,000 10.00% 10.00% 20.00% $3,000 $18,000
Sum
Average
62,544.00 $386,060
9.41% 10.00% 19.41%
$66,171 $452,231Summary for Group: 40.07.19
Group 40.07.20
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LYMAN/SIXTH LANE STREET IMPROVEMENTS Contingency
40.07.20.106 MILL AND OVERLAY (LYMAN/SIXTH) 6,278.00 SF $1.90 $11,928 10.00% 10.00% 20.00% $2,386 $14,314
40.07.20.150710 REMOVE TRAFFIC STRIPE 2,400.00 LF $1.00 $2,400 15.00% 10.00% 25.00% $600 $3,000
40.07.20.150713 REMOVE PAVEMENT MARKING 90.00 SF $1.10 $99 15.00% 10.00% 25.00% $25 $124
40.07.20.150742 REMOVE ROADSIDE SIGN 5.00 EA $500.00 $2,500 10.00% 10.00% 20.00% $500 $3,000
Monday, January 27, 2014 Page 86 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.20.150770 SAWCUT ASPHALT PAVEMENT 591.00 LF $2.00 $1,182 10.00% 10.00% 20.00% $236 $1,418
40.07.20.153241 REMOVE CONCRETE (SIDEWALK) 5,146.00 SF $3.00 $15,438 10.00% 10.00% 20.00% $3,088 $18,526
40.07.20.190101 ROADWAY EXCAVATION 1,268.00 CY $28.00 $35,504 10.00% 10.00% 20.00% $7,101 $42,605
40.07.20.260203 CLASS 2 AGGREGATE BASE 475.00 CY $45.00 $21,375 10.00% 10.00% 20.00% $4,275 $25,650
40.07.20.390132 HOT MIX ASPHALT (TYPE A) 446.00TON $102.00 $45,492 10.00% 10.00% 20.00% $9,098 $54,590
40.07.20.566011 ROADSIDE SIGN - ONE POST 10.00 EA $750.00 $7,500 10.00% 10.00% 20.00% $1,500 $9,000
40.07.20.731504.1 MINOR CONCRETE (CURB AND GUTTER) (TYPE B) 71.00 LF $34.00 $2,414 10.00% 10.00% 20.00% $483 $2,897
40.07.20.731504.3 MINOR CONCRETE (CURB AND GUTTER) (TYPE H) 1,471.00 LF $38.00 $55,898 10.00% 10.00% 20.00% $11,180 $67,078
40.07.20.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 163.00 CY $635.00 $103,505 10.00% 10.00% 20.00% $20,701 $124,206
40.07.20.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 14.00 CY $765.00 $10,710 10.00% 10.00% 20.00% $2,142 $12,852
40.07.20.840515 THERMOPLASTIC PAVEMENT MARKING 478.00 SF $5.00 $2,390 10.00% 15.00% 25.00% $598 $2,988
40.07.20.840656 PAINT TRAFFIC STRIPE (2-COAT) 2,400.00 LF $2.00 $4,800 15.00% 15.00% 30.00% $1,440 $6,240
40.07.20.900 STREET LIGHT 7.00 EA $2,000.00 $14,000 10.00% 10.00% 20.00% $2,800 $16,800
40.07.20.901 REMOVE STREET LIGHT 5.00 EA $1,500.00 $7,500 10.00% 10.00% 20.00% $1,500 $9,000
Sum
Average
21,318.00 $344,635
10.83% 10.56% 21.39%
$69,651 $414,287Summary for Group: 40.07.20
Group 40.07.20.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LYMAN/SIXTH LANE IMPROVEMENTS DRAINAGE SYSTEMS Contingency
40.07.20.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD WEST STR 3,481.40 CF $2.45 $8,529 15.00% 15.00% 30.00% $2,559 $11,088
40.07.20.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD WEST STRE 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
Sum
Average
3,482.40 $15,529
15.00% 15.00% 30.00%
$4,659 $20,188Summary for Group: 40.07.20.04
Group 40.07.21
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
VOIGT STREET IMPROVEMENTS Contingency
40.07.21.100 CHAIN LINK FENCE (CL-6) 252.00 LF $19.00 $4,788 10.00% 10.00% 20.00% $958 $5,746
40.07.21.106 MILL AND OVERLAY (VOIGT) 142,560.00 SF $1.90 $270,864 10.00% 10.00% 20.00% $54,173 $325,037
40.07.21.110 9" PORTLAND CEMENT CONCRETE 61.00 CY $603.00 $36,783 10.00% 10.00% 20.00% $7,357 $44,140
40.07.21.150710 REMOVE TRAFFIC STRIPE 8,700.00 LF $1.00 $8,700 15.00% 10.00% 25.00% $2,175 $10,875
40.07.21.150713 REMOVE PAVEMENT MARKING 75.00 SF $1.10 $83 15.00% 10.00% 25.00% $21 $103
40.07.21.150742 REMOVE ROADSIDE SIGN 5.00 EA $500.00 $2,500 10.00% 10.00% 20.00% $500 $3,000
40.07.21.150770 SAWCUT ASPHALT PAVEMENT 1,134.00 LF $2.00 $2,268 10.00% 10.00% 20.00% $454 $2,722
Monday, January 27, 2014 Page 87 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.21.153241 REMOVE CONCRETE (SIDEWALK) 14,871.00 SF $3.00 $44,613 10.00% 10.00% 20.00% $8,923 $53,536
40.07.21.190101 ROADWAY EXCAVATION 1,584.00 CY $28.00 $44,352 10.00% 10.00% 20.00% $8,870 $53,222
40.07.21.260203 CLASS 2 AGGREGATE BASE 191.00 CY $45.00 $8,595 10.00% 10.00% 20.00% $1,719 $10,314
40.07.21.270011 CEMENT TREATED BASE 94.00 CY $57.00 $5,358 10.00% 10.00% 20.00% $1,072 $6,430
40.07.21.390132 HOT MIX ASPHALT (TYPE A) 189.00TON $102.00 $19,278 10.00% 10.00% 20.00% $3,856 $23,134
40.07.21.566011 ROADSIDE SIGN - ONE POST 5.00 EA $750.00 $3,750 10.00% 10.00% 20.00% $750 $4,500
40.07.21.731504.1 MINOR CONCRETE (CURB AND GUTTER) (TYPE B) 100.00 LF $34.00 $3,400 10.00% 10.00% 20.00% $680 $4,080
40.07.21.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 1,280.00 LF $36.00 $46,080 10.00% 10.00% 20.00% $9,216 $55,296
40.07.21.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 121.00 CY $635.00 $76,835 10.00% 10.00% 20.00% $15,367 $92,202
40.07.21.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.21.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.21.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.21.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.21.839701 CONCRETE BARRIER 89.00 LF $53.00 $4,717 10.00% 10.00% 20.00% $943 $5,660
40.07.21.840515 THERMOPLASTIC PAVEMENT MARKING 183.00 SF $5.00 $915 10.00% 15.00% 25.00% $229 $1,144
40.07.21.840656 PAINT TRAFFIC STRIPE (2-COAT) 1,683.00 LF $2.00 $3,366 15.00% 15.00% 30.00% $1,010 $4,376
40.07.21.850111 PAVEMENT MARKER (RETROREFLECTIVE) 19.00 EA $3.00 $57 15.00% 15.00% 30.00% $17 $74
40.07.21.900 STREET LIGHT 7.00 EA $2,000.00 $14,000 10.00% 10.00% 20.00% $2,800 $16,800
40.07.21.901 REMOVE STREET LIGHT 6.00 EA $1,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
Sum
Average
173,237.00 $631,722
10.77% 10.58% 21.35%
$127,171 $758,893Summary for Group: 40.07.21
Group 40.07.21.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
VOIGT STREET IMPROVEMENTS DRAINAGE SYSTEMS Contingency
40.07.21.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD EAST STR 2,246.40 CF $2.45 $5,504 15.00% 15.00% 30.00% $1,651 $7,155
40.07.21.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD EAST STREE 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
Sum
Average
2,247.40 $12,504
15.00% 15.00% 30.00%
$3,751 $16,255Summary for Group: 40.07.21.04
Group 40.07.22
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
I-5 STREET IMPROVEMENTS Contingency
40.07.22.108 DEMO METAL BEAM GUARD RAIL (WOOD POST) 1,200.00 LF $10.00 $12,000 10.00% 10.00% 20.00% $2,400 $14,400
40.07.22.150710 REMOVE TRAFFIC STRIPE 37,300.00 LF $1.00 $37,300 15.00% 10.00% 25.00% $9,325 $46,625
Monday, January 27, 2014 Page 88 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.22.150713 REMOVE PAVEMENT MARKING 20.00 SF $1.10 $22 15.00% 10.00% 25.00% $6 $28
40.07.22.208 DEMO CONCRETE BARRIER 1,202.00 LF $10.00 $12,020 10.00% 10.00% 20.00% $2,404 $14,424
40.07.22.832003 METAL BEAM GUARD RAILING (WOOD POST) 5,557.00 LF $32.00 $177,824 10.00% 10.00% 20.00% $35,565 $213,389
40.07.22.839701 CONCRETE BARRIER 1,202.00 LF $53.00 $63,706 10.00% 10.00% 20.00% $12,741 $76,447
40.07.22.840501 THERMOPLASTIC TRAFFIC STRIPE 37,300.00 LF $2.75 $102,575 15.00% 10.00% 25.00% $25,644 $128,219
40.07.22.840515 THERMOPLASTIC PAVEMENT MARKING 20.00 SF $5.00 $100 10.00% 15.00% 25.00% $25 $125
40.07.22.850101 PAVEMENT MARKER (NON-REFLECTIVE) 3,108.00 EA $2.00 $6,216 15.00% 10.00% 25.00% $1,554 $7,770
40.07.22.850111 PAVEMENT MARKER (RETROREFLECTIVE) 781.00 EA $3.00 $2,343 15.00% 15.00% 30.00% $703 $3,046
Sum
Average
87,690.00 $414,106
12.50% 11.00% 23.50%
$90,366 $504,472Summary for Group: 40.07.22
Group 40.07.23
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LA JOLLA COLONY STREET IMPROVEMENTS Contingency
40.07.23.106 MILL AND OVERLAY (LA JOLLA COLONY) 30,000.00 SF $1.90 $57,000 10.00% 10.00% 20.00% $11,400 $68,400
40.07.23.108 DEMO METAL BEAM GUARD RAIL (WOOD POST) 99.00 LF $10.00 $990 10.00% 10.00% 20.00% $198 $1,188
40.07.23.150710 REMOVE TRAFFIC STRIPE 6,100.00 LF $1.00 $6,100 15.00% 10.00% 25.00% $1,525 $7,625
40.07.23.150713 REMOVE PAVEMENT MARKING 30.00 SF $1.10 $33 15.00% 10.00% 25.00% $8 $41
40.07.23.150742 REMOVE ROADSIDE SIGN 8.00 EA $500.00 $4,000 15.00% 15.00% 30.00% $1,200 $5,200
40.07.23.150770 SAWCUT ASPHALT PAVEMENT 49.00 LF $2.00 $98 10.00% 10.00% 20.00% $20 $118
40.07.23.153241 REMOVE CONCRETE (SIDEWALK) 167.00 SF $3.00 $501 10.00% 10.00% 20.00% $100 $601
40.07.23.190101 ROADWAY EXCAVATION 130.00 CY $28.00 $3,640 10.00% 10.00% 20.00% $728 $4,368
40.07.23.270011 CEMENT TREATED BASE 145.00 CY $57.00 $8,265 10.00% 10.00% 20.00% $1,653 $9,918
40.07.23.390132 HOT MIX ASPHALT (TYPE A) 213.00TON $102.00 $21,726 10.00% 10.00% 20.00% $4,345 $26,071
40.07.23.566011 ROADSIDE SIGN - ONE POST 8.00 EA $750.00 $6,000 15.00% 15.00% 30.00% $1,800 $7,800
40.07.23.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 200.00 LF $36.00 $7,200 10.00% 10.00% 20.00% $1,440 $8,640
40.07.23.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 1.00 CY $635.00 $635 10.00% 10.00% 20.00% $127 $762
40.07.23.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426
40.07.23.832003 METAL BEAM GUARD RAILING (WOOD POST) 525.00 LF $32.00 $16,800 10.00% 10.00% 20.00% $3,360 $20,160
40.07.23.839603 CRASH ATTENUATOR 2.00 EA $55,205.00 $110,410 0.00% 10.00% 10.00% $11,041 $121,451
40.07.23.839701 CONCRETE BARRIER 303.00 LF $53.00 $16,059 10.00% 10.00% 20.00% $3,212 $19,271
40.07.23.840515 THERMOPLASTIC PAVEMENT MARKING 129.00 SF $5.00 $645 10.00% 15.00% 25.00% $161 $806
Monday, January 27, 2014 Page 89 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.23.840656 PAINT TRAFFIC STRIPE (2-COAT) 9,966.00 LF $2.00 $19,932 15.00% 15.00% 30.00% $5,980 $25,912
40.07.23.850111 PAVEMENT MARKER (RETROREFLECTIVE) 128.00 EA $3.00 $384 15.00% 15.00% 30.00% $115 $499
40.07.23.900 STREET LIGHT 2.00 EA $2,000.00 $4,000 15.00% 15.00% 30.00% $1,200 $5,200
40.07.23.901 REMOVE STREET LIGHT 2.00 EA $1,500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
Sum
Average
48,214.00 $292,773
11.36% 11.59% 22.95%
$51,584 $344,357Summary for Group: 40.07.23
Group 40.07.24
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PERMANENT BMP (ROADS/PARKING LOTS) Contingency
40.07.24 PERMANENT BMP (ROADS/PARKING LOTS) 1.00 LS $2,000,000.00 $2,000,000 0.00% 20.00% 20.00% $400,000 $2,400,000
Sum
Average
1.00 $2,000,000
0.00% 20.00% 20.00%
$400,000 $2,400,000Summary for Group: 40.07.24
Group 40.07.25
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PARKING RECONSTRUCTION Contingency
40.07.25.101 MILL AND OVERLAY (LA JOLLA VILLAGE SQUARE) 212,340.00 SF $1.90 $403,446 10.00% 10.00% 20.00% $80,689 $484,135
40.07.25.102 MILL AND OVERLAY (SOUTH OF GILMAN) 27,078.00 SF $1.90 $51,448 10.00% 10.00% 20.00% $10,290 $61,738
40.07.25.103 MILL AND OVERLAY (NORTH OF GILMAN) 33,727.00 SF $1.90 $64,081 10.00% 10.00% 20.00% $12,816 $76,898
40.07.25.104 MILL AND OVERLAY (CALTRANS D11) 16,800.00 SF $1.90 $31,920 10.00% 10.00% 20.00% $6,384 $38,304
40.07.25.105 MILL AND OVERLAY (NEAR LOVELOCK) 8,400.00 SF $1.90 $15,960 10.00% 10.00% 20.00% $3,192 $19,152
40.07.25.106 MILL AND OVERLAY (CITY OF SD MAINT YARD) 58,750.00 SF $1.90 $111,625 10.00% 10.00% 20.00% $22,325 $133,950
40.07.25.107 MILL AND OVERLAY (ALONG ROSE CREEK CHANNEL) 3,012.00 SF $1.90 $5,723 10.00% 10.00% 20.00% $1,145 $6,867
40.07.25.108 MILL AND OVERLAY (NORTH OF MORENA/ARIANE) 39,098.00 SF $1.90 $74,286 10.00% 10.00% 20.00% $14,857 $89,143
40.07.25.109 MILL AND OVERLAY (WHOLE FOODS MARKET) 44,716.00 SF $1.90 $84,960 10.00% 10.00% 20.00% $16,992 $101,952
40.07.25.110 MILL AND OVERLAY (S. OF VOIGT DR PARKING) 52,329.00 SF $1.90 $99,425 10.00% 10.00% 20.00% $19,885 $119,310
40.07.25.111 MILL AND OVERLAY (CAMPUS POINT/VOIGT PARKING) 105,261.00 SF $1.90 $199,996 10.00% 10.00% 20.00% $39,999 $239,995
Sum
Average
601,511.00 $1,142,871
10.00% 10.00% 20.00%
$228,574 $1,371,445Summary for Group: 40.07.25
Group 40.07.26
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
FRIARS ROAD STREET IMPROVEMENTS Contingency
40.07.26.104 REMOVE ASPHALT CONCRETE DIKE 877.00 LF $1.75 $1,535 10.00% 10.00% 20.00% $307 $1,842
40.07.26.105 ASPHALT CONCRETE DIKE 877.00 LF $20.00 $17,540 10.00% 10.00% 20.00% $3,508 $21,048
40.07.26.106 MILL AND OVERLAY (FRIARS) 38,400.00 SF $1.90 $72,960 10.00% 10.00% 20.00% $14,592 $87,552
40.07.26.108 DEMO METAL BEAM GUARD RAIL (WOOD POST) 250.00 LF $10.00 $2,500 10.00% 10.00% 20.00% $500 $3,000
Monday, January 27, 2014 Page 90 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.26.150710 REMOVE TRAFFIC STRIPE 14,400.00 LF $1.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000
40.07.26.150770 SAWCUT ASPHALT PAVEMENT 800.00 LF $2.00 $1,600 10.00% 10.00% 20.00% $320 $1,920
40.07.26.832003 METAL BEAM GUARD RAILING (WOOD POST) 265.00 LF $32.00 $8,480 10.00% 10.00% 20.00% $1,696 $10,176
40.07.26.839603 CRASH ATTENUATOR 2.00 EA $55,205.00 $110,410 0.00% 10.00% 10.00% $11,041 $121,451
40.07.26.840656 PAINT TRAFFIC STRIPE (2-COAT) 14,400.00 LF $2.00 $28,800 15.00% 15.00% 30.00% $8,640 $37,440
40.07.26.840656 PAINT TRAFFIC STRIPE (2-COAT) 14,400.00 LF $2.00 $28,800 10.00% 10.00% 20.00% $5,760 $34,560
40.07.26.850111 PAVEMENT MARKER (RETROREFLECTIVE) 301.00 EA $3.00 $903 10.00% 10.00% 20.00% $181 $1,084
Sum
Average
84,972.00 $287,928
10.00% 10.45% 20.45%
$50,145 $338,072Summary for Group: 40.07.26
Group 40.07.27
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NOBEL DRIVE STREET IMPROVEMENTS Contingency
40.07.27.106 MILL AND OVERLAY (NOBEL) 30,400.00 SF $1.90 $57,760 10.00% 10.00% 20.00% $11,552 $69,312
40.07.27.150710 REMOVE TRAFFIC STRIPE 3,600.00 LF $1.00 $3,600 15.00% 10.00% 25.00% $900 $4,500
40.07.27.150713 REMOVE PAVEMENT MARKING 60.00 SF $1.10 $66 15.00% 10.00% 25.00% $17 $83
40.07.27.153241 REMOVE CONCRETE (SIDEWALK) 450.00 SF $3.00 $1,350 10.00% 10.00% 20.00% $270 $1,620
40.07.27.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 31.00 CY $635.00 $19,685 10.00% 10.00% 20.00% $3,937 $23,622
40.07.27.840515 THERMOPLASTIC PAVEMENT MARKING 60.00 SF $5.00 $300 10.00% 15.00% 25.00% $75 $375
40.07.27.840656 PAINT TRAFFIC STRIPE (2-COAT) 3,600.00 LF $2.00 $7,200 15.00% 15.00% 30.00% $2,160 $9,360
40.07.27.850111 PAVEMENT MARKER (RETROREFLECTIVE) 76.00 EA $3.00 $228 15.00% 15.00% 30.00% $68 $296
Sum
Average
38,277.00 $90,189
12.50% 11.88% 24.38%
$18,979 $109,168Summary for Group: 40.07.27
Group 40.07.28
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LA JOLLA VILLAGE DRIVE STREET IMPROVEMENTS Contingency
40.07.28.150710 REMOVE TRAFFIC STRIPE 1,000.00 LF $1.00 $1,000 15.00% 10.00% 25.00% $250 $1,250
40.07.28.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 31.00 CY $635.00 $19,685 10.00% 10.00% 20.00% $3,937 $23,622
Sum
Average
1,031.00 $20,685
12.50% 10.00% 22.50%
$4,187 $24,872Summary for Group: 40.07.28
Group 40.07.29
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MORENA STREET IMPROVEMENTS Contingency
40.07.29.104 REMOVE ASPHALT CONCRETE DIKE 2,800.00 LF $1.75 $4,900 10.00% 10.00% 20.00% $980 $5,880
40.07.29.105 ASPHALT CONCRETE DIKE 2,800.00 LF $20.00 $56,000 10.00% 10.00% 20.00% $11,200 $67,200
40.07.29.106 MILL AND OVERLAY (MORENA BLVD) 520,331.00 SF $1.90 $988,629 10.00% 10.00% 20.00% $197,726 $1,186,355
Monday, January 27, 2014 Page 91 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.29.108 DEMO METAL BEAM GUARD RAIL (WOOD POST) 2,800.00 LF $10.00 $28,000 10.00% 10.00% 20.00% $5,600 $33,600
40.07.29.150710 REMOVE TRAFFIC STRIPE 10,200.00 LF $1.00 $10,200 15.00% 10.00% 25.00% $2,550 $12,750
40.07.29.150713 REMOVE PAVEMENT MARKING 60.00 SF $1.10 $66 15.00% 10.00% 25.00% $17 $83
40.07.29.150742 REMOVE ROADSIDE SIGN 10.00 EA $500.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000
40.07.29.150770 SAWCUT ASPHALT PAVEMENT 204.00 LF $2.00 $408 10.00% 10.00% 20.00% $82 $490
40.07.29.153241 REMOVE CONCRETE (SIDEWALK) 4,000.00 SF $3.00 $12,000 10.00% 10.00% 20.00% $2,400 $14,400
40.07.29.270011 CEMENT TREATED BASE 8.00 CY $57.00 $456 10.00% 10.00% 20.00% $91 $547
40.07.29.390132 HOT MIX ASPHALT (TYPE A) 4.00TON $102.00 $408 10.00% 10.00% 20.00% $82 $490
40.07.29.566011 ROADSIDE SIGN - ONE POST 10.00 EA $750.00 $7,500 10.00% 10.00% 20.00% $1,500 $9,000
40.07.29.731504.1 MINOR CONCRETE (CURB AND GUTTER) (TYPE B) 350.00 LF $34.00 $11,900 10.00% 10.00% 20.00% $2,380 $14,280
40.07.29.731504.3 MINOR CONCRETE (CURB AND GUTTER) (TYPE H) 204.00 LF $38.00 $7,752 10.00% 10.00% 20.00% $1,550 $9,302
40.07.29.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 54.00 CY $635.00 $34,290 10.00% 10.00% 20.00% $6,858 $41,148
40.07.29.832003 METAL BEAM GUARD RAILING (WOOD POST) 2,848.00 LF $32.00 $91,136 10.00% 10.00% 20.00% $18,227 $109,363
40.07.29.840656 PAINT TRAFFIC STRIPE (2-COAT) 10,200.00 LF $2.00 $20,400 15.00% 15.00% 30.00% $6,120 $26,520
40.07.29.850111 PAVEMENT MARKER (RETROREFLECTIVE) 214.00 EA $3.00 $642 10.00% 10.00% 20.00% $128 $770
40.07.29.900 STREET LIGHT 22.00 EA $2,000.00 $44,000 10.00% 10.00% 20.00% $8,800 $52,800
40.07.29.901 REMOVE STREET LIGHT 6.00 EA $1,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800
Sum
Average
557,125.00 $1,332,687
10.75% 10.25% 21.00%
$269,091 $1,601,778Summary for Group: 40.07.29
Group 40.07.30
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROSE CANYON BUSINESS PARK-PARKING LOT Contingency
40.07.30.104 REMOVE ASPHALT CONCRETE DIKE 735.00 LF $1.75 $1,286 10.00% 10.00% 20.00% $257 $1,544
40.07.30.105 ASPHALT CONCRETE DIKE 735.00 LF $20.00 $14,700 10.00% 10.00% 20.00% $2,940 $17,640
40.07.30.150770 SAWCUT ASPHALT PAVEMENT 735.00 LF $2.00 $1,470 10.00% 10.00% 20.00% $294 $1,764
40.07.30.270011 CEMENT TREATED BASE 27.00 CY $57.00 $1,539 10.00% 10.00% 20.00% $308 $1,847
40.07.30.390132 HOT MIX ASPHALT (TYPE A) 16.00TON $102.00 $1,632 10.00% 10.00% 20.00% $326 $1,958
Sum
Average
2,248.00 $20,627
10.00% 10.00% 20.00%
$4,125 $24,753Summary for Group: 40.07.30
Group 40.07.31
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GILMAN DR STREET IMPROVEMENTS Contingency
40.07.31.150710 REMOVE TRAFFIC STRIPE 600.00 LF $1.00 $600 15.00% 10.00% 25.00% $150 $750
Monday, January 27, 2014 Page 92 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.07.31.840656 PAINT TRAFFIC STRIPE (2-COAT) 600.00 LF $2.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
Sum
Average
1,200.00 $1,800
15.00% 12.50% 27.50%
$510 $2,310Summary for Group: 40.07.31
Sum
Average
5,006,780.88 $32,772,723
11.61% 10.41% 22.02%
$7,122,203 $39,894,926Summary for Sub Section: 40.07
Sub Section 40.08 TEMPORARY FACILITIES AND OTHER INDIRECT COSTS DURING CONSTRUCTION
Group 40.08.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PARTNERING SESSIONS Contingency
40.08.01 PARTNERING SESSIONS 1.00 LS $300,000.00 $300,000 0.00% 0.00% 0.00% $0 $300,000
Sum
Average
1.00 $300,000
0.00% 0.00% 0.00%
$0 $300,000Summary for Group: 40.08.01
Group 40.08.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MOBILIZATION (8.5%) Contingency
40.08.02 MOBILIZATION (8.5%) 1.00 LS $47,061,899.61 $47,061,900 0.00% 10.00% 10.00% $4,706,190 $51,768,090
Sum
Average
1.00 $47,061,900
0.00% 10.00% 10.00%
$4,706,190 $51,768,090Summary for Group: 40.08.02
Group 40.08.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CLAIREMONT DR Contingency
40.08.10.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875
40.08.10.120161 TEMPORARY TRAFFIC STRIPE 1,800.00 LF $2.50 $4,500 20.00% 10.00% 30.00% $1,350 $5,850
40.08.10.129000 TEMPORARY RAILING (TYPE K) 600.00 LF $17.00 $10,200 20.00% 10.00% 30.00% $3,060 $13,260
40.08.10.129110 TEMPORARY CRASH CUSHION 2.00 EA $4,000.00 $8,000 20.00% 10.00% 30.00% $2,400 $10,400
40.08.10.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250
40.08.10.992 SHORT-TERM TRAFFIC CONTROL 10.00DAY $605.00 $6,050 20.00% 20.00% 40.00% $2,420 $8,470
40.08.10.993 FLAGGER 10.00DAY $750.00 $7,500 15.00% 15.00% 30.00% $2,250 $9,750
Sum
Average
2,438.00 $40,250
18.57% 12.14% 30.71%
$12,605 $52,855Summary for Group: 40.08.10
Group 40.08.11
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE AVE Contingency
40.08.11.120090 CONSTRUCTION AREA SIGNS 30.00 EA $250.00 $7,500 15.00% 10.00% 25.00% $1,875 $9,375
40.08.11.120161 TEMPORARY TRAFFIC STRIPE 113,200.00 LF $2.50 $283,000 20.00% 10.00% 30.00% $84,900 $367,900
40.08.11.128650 PORTABLE CHANGEABLE MESSAGE SIGN 6.00 EA $5,000.00 $30,000 10.00% 10.00% 20.00% $6,000 $36,000
40.08.11.129000 TEMPORARY RAILING (TYPE K) 22,900.00 LF $17.00 $389,300 20.00% 10.00% 30.00% $116,790 $506,090
Monday, January 27, 2014 Page 93 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.08.11.129110 TEMPORARY CRASH CUSHION 28.00 EA $4,000.00 $112,000 20.00% 10.00% 30.00% $33,600 $145,600
40.08.11.158210 RESET TEMPORARY RAILING (TYPE K) 6,500.00 LF $4.00 $26,000 15.00% 10.00% 25.00% $6,500 $32,500
40.08.11.991 TRAFFIC HANDING SIGNS 100.00 EA $250.00 $25,000 20.00% 10.00% 30.00% $7,500 $32,500
40.08.11.992 SHORT-TERM TRAFFIC CONTROL 1,750.00DAY $605.00 $1,058,750 20.00% 20.00% 40.00% $423,500 $1,482,250
40.08.11.993 FLAGGER 1,750.00DAY $750.00 $1,312,500 15.00% 15.00% 30.00% $393,750 $1,706,250
40.08.11120150 TEMPORARY PAVEMENT MARKING 1,880.00 SF $3.50 $6,580 20.00% 10.00% 30.00% $1,974 $8,554
Sum
Average
148,144.00 $3,250,630
17.50% 11.50% 29.00%
$1,076,389 $4,327,019Summary for Group: 40.08.11
Group 40.08.12
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PAC HWY/TAYLOR/ROSECRANS Contingency
40.08.12.120090 CONSTRUCTION AREA SIGNS 10.00 EA $250.00 $2,500 15.00% 10.00% 25.00% $625 $3,125
40.08.12.120150 TEMPORARY PAVEMENT MARKING 1,300.00 SF $3.50 $4,550 20.00% 10.00% 30.00% $1,365 $5,915
40.08.12.120161 TEMPORARY TRAFFIC STRIPE 5,800.00 LF $2.50 $14,500 20.00% 10.00% 30.00% $4,350 $18,850
40.08.12.128650 PORTABLE CHANGEABLE MESSAGE SIGN 2.00 EA $5,000.00 $10,000 10.00% 10.00% 20.00% $2,000 $12,000
40.08.12.129000 TEMPORARY RAILING (TYPE K) 1,500.00 LF $17.00 $25,500 20.00% 10.00% 30.00% $7,650 $33,150
40.08.12.129110 TEMPORARY CRASH CUSHION 2.00 EA $4,000.00 $8,000 20.00% 10.00% 30.00% $2,400 $10,400
40.08.12.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500
40.08.12.992 SHORT-TERM TRAFFIC CONTROL 30.00DAY $605.00 $18,150 20.00% 20.00% 40.00% $7,260 $25,410
40.08.12.993 FLAGGER 30.00DAY $750.00 $22,500 15.00% 15.00% 30.00% $6,750 $29,250
Sum
Average
8,694.00 $110,700
17.78% 11.67% 29.44%
$33,900 $144,600Summary for Group: 40.08.12
Group 40.08.17
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BALBOA AVE Contingency
40.08.17.120090 CONSTRUCTION AREA SIGNS 24.00 EA $250.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500
40.08.17.120150 TEMPORARY PAVEMENT MARKING 160.00 SF $3.50 $560 20.00% 10.00% 30.00% $168 $728
40.08.17.120161 TEMPORARY TRAFFIC STRIPE 25,200.00 LF $2.50 $63,000 20.00% 10.00% 30.00% $18,900 $81,900
40.08.17.128650 PORTABLE CHANGEABLE MESSAGE SIGN 4.00 EA $5,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
40.08.17.129000 TEMPORARY RAILING (TYPE K) 5,400.00 LF $17.00 $91,800 20.00% 10.00% 30.00% $27,540 $119,340
40.08.17.129110 TEMPORARY CRASH CUSHION 6.00 EA $4,000.00 $24,000 20.00% 10.00% 30.00% $7,200 $31,200
40.08.17.991 TRAFFIC HANDING SIGNS 50.00 EA $250.00 $12,500 20.00% 10.00% 30.00% $3,750 $16,250
40.08.17.992 SHORT-TERM TRAFFIC CONTROL 310.00DAY $605.00 $187,550 20.00% 20.00% 40.00% $75,020 $262,570
Monday, January 27, 2014 Page 94 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.08.17.993 FLAGGER 310.00DAY $750.00 $232,500 15.00% 15.00% 30.00% $69,750 $302,250
Sum
Average
31,464.00 $637,910
17.78% 11.67% 29.44%
$207,828 $845,738Summary for Group: 40.08.17
Group 40.08.18
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TECOLOTE RD Contingency
40.08.18.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500
40.08.18.992 SHORT-TERM TRAFFIC CONTROL 10.00DAY $605.00 $6,050 20.00% 20.00% 40.00% $2,420 $8,470
40.08.18.993 FLAGGER 10.00DAY $750.00 $7,500 15.00% 15.00% 30.00% $2,250 $9,750
Sum
Average
40.00 $18,550
18.33% 15.00% 33.33%
$6,170 $24,720Summary for Group: 40.08.18
Group 40.08.19
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
VOIGT DR/CAMPUS PT DR Contingency
40.08.19.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875
40.08.19.120161 TEMPORARY TRAFFIC STRIPE 11,700.00 LF $2.50 $29,250 20.00% 10.00% 30.00% $8,775 $38,025
40.08.19.128650 PORTABLE CHANGEABLE MESSAGE SIGN 2.00 EA $5,000.00 $10,000 10.00% 10.00% 20.00% $2,000 $12,000
40.08.19.129000 TEMPORARY RAILING (TYPE K) 4,500.00 LF $17.00 $76,500 20.00% 10.00% 30.00% $22,950 $99,450
40.08.19.129110 TEMPORARY CRASH CUSHION 7.00 EA $4,000.00 $28,000 20.00% 10.00% 30.00% $8,400 $36,400
40.08.19.158210 RESET TEMPORARY RAILING (TYPE K) 3,000.00 LF $4.00 $12,000 15.00% 10.00% 25.00% $3,000 $15,000
40.08.19.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250
40.08.19.992 SHORT-TERM TRAFFIC CONTROL 140.00DAY $605.00 $84,700 20.00% 20.00% 40.00% $33,880 $118,580
40.08.19.993 FLAGGER 100.00DAY $750.00 $75,000 15.00% 15.00% 30.00% $22,500 $97,500
40.08.19120150 TEMPORARY PAVEMENT MARKING 150.00 SF $3.50 $525 20.00% 10.00% 30.00% $158 $683
Sum
Average
19,615.00 $319,975
17.50% 11.50% 29.00%
$102,788 $422,763Summary for Group: 40.08.19
Group 40.08.20
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SIXTH LANE/LYMAN AVE Contingency
40.08.20.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875
40.08.20.120150 TEMPORARY PAVEMENT MARKING 90.00 SF $3.50 $315 20.00% 10.00% 30.00% $95 $410
40.08.20.120161 TEMPORARY TRAFFIC STRIPE 2,400.00 LF $2.50 $6,000 20.00% 10.00% 30.00% $1,800 $7,800
40.08.20.128650 PORTABLE CHANGEABLE MESSAGE SIGN 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000
40.08.20.129000 TEMPORARY RAILING (TYPE K) 2,700.00 LF $17.00 $45,900 20.00% 10.00% 30.00% $13,770 $59,670
40.08.20.129110 TEMPORARY CRASH CUSHION 3.00 EA $4,000.00 $12,000 20.00% 10.00% 30.00% $3,600 $15,600
Monday, January 27, 2014 Page 95 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.08.20.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250
40.08.20.992 SHORT-TERM TRAFFIC CONTROL 120.00DAY $605.00 $72,600 20.00% 20.00% 40.00% $29,040 $101,640
40.08.20.993 FLAGGER 80.00DAY $750.00 $60,000 15.00% 15.00% 30.00% $18,000 $78,000
Sum
Average
5,410.00 $205,815
17.78% 11.67% 29.44%
$68,430 $274,245Summary for Group: 40.08.20
Group 40.08.22
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
I-5 AND I-5 RAMPS Contingency
40.08.22.120090 CONSTRUCTION AREA SIGNS 18.00 EA $250.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625
40.08.22.120150 TEMPORARY PAVEMENT MARKING 20.00 SF $3.50 $70 20.00% 10.00% 30.00% $21 $91
40.08.22.120161 TEMPORARY TRAFFIC STRIPE 37,300.00 LF $2.50 $93,250 20.00% 10.00% 30.00% $27,975 $121,225
40.08.22.128650 PORTABLE CHANGEABLE MESSAGE SIGN 6.00 EA $5,000.00 $30,000 10.00% 10.00% 20.00% $6,000 $36,000
40.08.22.129000 TEMPORARY RAILING (TYPE K) 13,900.00 LF $17.00 $236,300 20.00% 10.00% 30.00% $70,890 $307,190
40.08.22.129110 TEMPORARY CRASH CUSHION 11.00 EA $4,000.00 $44,000 20.00% 10.00% 30.00% $13,200 $57,200
40.08.22.991 TRAFFIC HANDING SIGNS 80.00 EA $250.00 $20,000 20.00% 10.00% 30.00% $6,000 $26,000
40.08.22.992 SHORT-TERM TRAFFIC CONTROL 350.00DAY $605.00 $211,750 20.00% 20.00% 40.00% $84,700 $296,450
40.08.22.993 FLAGGER 30.00DAY $750.00 $22,500 15.00% 15.00% 30.00% $6,750 $29,250
Sum
Average
51,715.00 $662,370
17.78% 11.67% 29.44%
$216,661 $879,031Summary for Group: 40.08.22
Group 40.08.23
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LA JOLLA COLONY DR Contingency
40.08.23.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875
40.08.23.120150 TEMPORARY PAVEMENT MARKING 534.00 SF $3.50 $1,869 20.00% 10.00% 30.00% $561 $2,430
40.08.23.120161 TEMPORARY TRAFFIC STRIPE 12,900.00 LF $2.50 $32,250 20.00% 10.00% 30.00% $9,675 $41,925
40.08.23.128650 PORTABLE CHANGEABLE MESSAGE SIGN 3.00 EA $5,000.00 $15,000 10.00% 10.00% 20.00% $3,000 $18,000
40.08.23.129000 TEMPORARY RAILING (TYPE K) 2,600.00 LF $17.00 $44,200 20.00% 10.00% 30.00% $13,260 $57,460
40.08.23.129110 TEMPORARY CRASH CUSHION 2.00 EA $4,000.00 $8,000 20.00% 10.00% 30.00% $2,400 $10,400
40.08.23.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500
40.08.23.992 SHORT-TERM TRAFFIC CONTROL 200.00DAY $605.00 $121,000 20.00% 20.00% 40.00% $48,400 $169,400
40.08.23.993 FLAGGER 200.00DAY $750.00 $150,000 15.00% 15.00% 30.00% $45,000 $195,000
Sum
Average
16,465.00 $378,819
17.78% 11.67% 29.44%
$124,171 $502,990Summary for Group: 40.08.23
Monday, January 27, 2014 Page 96 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Group 40.08.26
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
FRIARS RD Contingency
40.08.26.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875
40.08.26.120150 TEMPORARY PAVEMENT MARKING 150.00 SF $3.50 $525 20.00% 10.00% 30.00% $158 $683
40.08.26.120161 TEMPORARY TRAFFIC STRIPE 16,800.00 LF $2.50 $42,000 20.00% 10.00% 30.00% $12,600 $54,600
40.08.26.128650 PORTABLE CHANGEABLE MESSAGE SIGN 4.00 EA $5,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
40.08.26.129000 TEMPORARY RAILING (TYPE K) 1,500.00 LF $17.00 $25,500 20.00% 10.00% 30.00% $7,650 $33,150
40.08.26.129110 TEMPORARY CRASH CUSHION 4.00 EA $4,000.00 $16,000 20.00% 10.00% 30.00% $4,800 $20,800
40.08.26.158210 RESET TEMPORARY RAILING (TYPE K) 1,500.00 LF $4.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500
40.08.26.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500
40.08.26.992 SHORT-TERM TRAFFIC CONTROL 280.00DAY $605.00 $169,400 20.00% 20.00% 40.00% $67,760 $237,160
40.08.26.993 FLAGGER 280.00DAY $750.00 $210,000 15.00% 15.00% 30.00% $63,000 $273,000
Sum
Average
20,544.00 $495,925
17.50% 11.50% 29.00%
$163,343 $659,268Summary for Group: 40.08.26
Group 40.08.27
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NOBEL DR Contingency
40.08.27.120090 CONSTRUCTION AREA SIGNS 4.00 EA $250.00 $1,000 15.00% 10.00% 25.00% $250 $1,250
40.08.27.120150 TEMPORARY PAVEMENT MARKING 60.00 SF $3.50 $210 20.00% 10.00% 30.00% $63 $273
40.08.27.120161 TEMPORARY TRAFFIC STRIPE 3,600.00 LF $2.50 $9,000 20.00% 10.00% 30.00% $2,700 $11,700
40.08.27.128650 PORTABLE CHANGEABLE MESSAGE SIGN 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000
40.08.27.129000 TEMPORARY RAILING (TYPE K) 1,000.00 LF $17.00 $17,000 20.00% 10.00% 30.00% $5,100 $22,100
40.08.27.129110 TEMPORARY CRASH CUSHION 3.00 EA $4,000.00 $12,000 20.00% 10.00% 30.00% $3,600 $15,600
40.08.27.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500
40.08.27.992 SHORT-TERM TRAFFIC CONTROL 60.00DAY $605.00 $36,300 20.00% 20.00% 40.00% $14,520 $50,820
40.08.27.993 FLAGGER 60.00DAY $750.00 $45,000 15.00% 15.00% 30.00% $13,500 $58,500
Sum
Average
4,808.00 $130,510
17.78% 11.67% 29.44%
$42,233 $172,743Summary for Group: 40.08.27
Group 40.08.28
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LA JOLLA VILLAGE DR Contingency
40.08.28.120161 TEMPORARY TRAFFIC STRIPE 1,000.00 LF $2.50 $2,500 20.00% 10.00% 30.00% $750 $3,250
40.08.28.129000 TEMPORARY RAILING (TYPE K) 1,000.00 LF $17.00 $17,000 20.00% 10.00% 30.00% $5,100 $22,100
Monday, January 27, 2014 Page 97 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
40.08.28.129110 TEMPORARY CRASH CUSHION 4.00 EA $4,000.00 $16,000 20.00% 10.00% 30.00% $4,800 $20,800
40.08.28.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250
40.08.28.992 SHORT-TERM TRAFFIC CONTROL 20.00DAY $605.00 $12,100 20.00% 20.00% 40.00% $4,840 $16,940
40.08.28.993 FLAGGER 20.00DAY $750.00 $15,000 15.00% 15.00% 30.00% $4,500 $19,500
Sum
Average
2,054.00 $65,100
19.17% 12.50% 31.67%
$20,740 $85,840Summary for Group: 40.08.28
Group 40.08.29
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MORENA BLVD Contingency
40.08.29.120090 CONSTRUCTION AREA SIGNS 10.00 EA $250.00 $2,500 15.00% 10.00% 25.00% $625 $3,125
40.08.29.120150 TEMPORARY PAVEMENT MARKING 320.00 SF $3.50 $1,120 20.00% 10.00% 30.00% $336 $1,456
40.08.29.120161 TEMPORARY TRAFFIC STRIPE 10,200.00 LF $2.50 $25,500 20.00% 10.00% 30.00% $7,650 $33,150
40.08.29.128650 PORTABLE CHANGEABLE MESSAGE SIGN 4.00 EA $5,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
40.08.29.129000 TEMPORARY RAILING (TYPE K) 8,600.00 LF $17.00 $146,200 20.00% 10.00% 30.00% $43,860 $190,060
40.08.29.129110 TEMPORARY CRASH CUSHION 3.00 EA $4,000.00 $12,000 20.00% 10.00% 30.00% $3,600 $15,600
40.08.29.991 TRAFFIC HANDING SIGNS 30.00 EA $250.00 $7,500 20.00% 10.00% 30.00% $2,250 $9,750
40.08.29.992 SHORT-TERM TRAFFIC CONTROL 300.00DAY $605.00 $181,500 20.00% 20.00% 40.00% $72,600 $254,100
40.08.29.993 FLAGGER 200.00DAY $750.00 $150,000 15.00% 15.00% 30.00% $45,000 $195,000
Sum
Average
19,667.00 $546,320
17.78% 11.67% 29.44%
$179,921 $726,241Summary for Group: 40.08.29
Group 40.08.31
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GILMAN DR Contingency
40.08.31.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875
40.08.31.120161 TEMPORARY TRAFFIC STRIPE 1,200.00 LF $2.50 $3,000 20.00% 10.00% 30.00% $900 $3,900
40.08.31.128650 PORTABLE CHANGEABLE MESSAGE SIGN 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000
40.08.31.129000 TEMPORARY RAILING (TYPE K) 1,100.00 LF $17.00 $18,700 20.00% 10.00% 30.00% $5,610 $24,310
40.08.31.129110 TEMPORARY CRASH CUSHION 1.00 EA $4,000.00 $4,000 20.00% 10.00% 30.00% $1,200 $5,200
40.08.31.158210 RESET TEMPORARY RAILING (TYPE K) 1,100.00 LF $4.00 $4,400 15.00% 10.00% 25.00% $1,100 $5,500
40.08.31.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250
40.08.31.992 SHORT-TERM TRAFFIC CONTROL 40.00DAY $605.00 $24,200 20.00% 20.00% 40.00% $9,680 $33,880
40.08.31.993 FLAGGER 40.00DAY $750.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
Monday, January 27, 2014 Page 98 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
3,498.00 $93,300
17.22% 11.67% 28.89%
$29,615 $122,915Summary for Group: 40.08.31
Group 40.08.32
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROSE CANYON BIKE PATH Contingency
40.08.32.120090 CONSTRUCTION AREA SIGNS 5.00 EA $250.00 $1,250 15.00% 10.00% 25.00% $313 $1,563
40.08.32.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500
Sum
Average
25.00 $6,250
17.50% 10.00% 27.50%
$1,813 $8,063Summary for Group: 40.08.32
Group 40.08.33
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
OCEAN BEACH BIKE PATH Contingency
40.08.33.120150 TEMPORARY PAVEMENT MARKING 50.00 SF $3.50 $175 20.00% 10.00% 30.00% $53 $228
40.08.33.128650 PORTABLE CHANGEABLE MESSAGE SIGN 2.00 EA $5,000.00 $10,000 10.00% 10.00% 20.00% $2,000 $12,000
40.08.33.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250
40.08.33.994 SPECIAL HEIGHT LIMITATION WARNING TREATMENT FOR BIKE 2.00 EA $10,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
Sum
Average
64.00 $32,675
16.25% 11.25% 27.50%
$8,803 $41,478Summary for Group: 40.08.33
Group 40.08.34
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
OTHER BIKE LANE CLOSURES Contingency
40.08.34.128650 PORTABLE CHANGEABLE MESSAGE SIGN 10.00 EA $5,000.00 $50,000 10.00% 10.00% 20.00% $10,000 $60,000
40.08.34.991 TRAFFIC HANDING SIGNS 40.00 EA $250.00 $10,000 20.00% 10.00% 30.00% $3,000 $13,000
Sum
Average
50.00 $60,000
15.00% 10.00% 25.00%
$13,000 $73,000Summary for Group: 40.08.34
Group 40.08.35
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
UTILITY RELOCATIONS Contingency
40.08.35.992 SHORT-TERM TRAFFIC CONTROL 250.00DAY $605.00 $151,250 20.00% 20.00% 40.00% $60,500 $211,750
40.08.35.993 FLAGGER 250.00DAY $750.00 $187,500 15.00% 15.00% 30.00% $56,250 $243,750
Sum
Average
500.00 $338,750
17.50% 17.50% 35.00%
$116,750 $455,500Summary for Group: 40.08.35
Group 40.08.36
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
ROADWAYS S. OF OLD TOWN Contingency
40.08.36.992 SHORT-TERM TRAFFIC CONTROL 10.00DAY $605.00 $6,050 20.00% 20.00% 40.00% $2,420 $8,470
40.08.36.993 FLAGGER 10.00DAY $750.00 $7,500 15.00% 15.00% 30.00% $2,250 $9,750
Sum
Average
20.00 $13,550
17.50% 17.50% 35.00%
$4,670 $18,220Summary for Group: 40.08.36
Monday, January 27, 2014 Page 99 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Group 40.08.40
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TEMPORARY BMP (2%) Contingency
40.08.40 TEMPORARY BMP (2%) 1.00 LS $11,288,709.10 $11,288,709 0.00% 30.00% 30.00% $3,386,613 $14,675,322
Sum
Average
1.00 $11,288,709
0.00% 30.00% 30.00%
$3,386,613 $14,675,322Summary for Group: 40.08.40
Sum
Average
335,218.00 $66,058,008
17.29% 11.92% 29.21%
$10,522,630 $76,580,638Summary for Sub Section: 40.08
Sum
Average
5,518,879.63 $155,510,710
13.18% 10.63% 23.81%
$32,383,100 $187,893,811Summary for Section 40
Section 50 SYSTEMS
Sub Section 50.01 TRAIN CONTROL AND SIGNALS
Group 50.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TRAIN CONTROL AND SIGNALS Contingency
50.01.00 TEMPORARY RELOCATION OF SIGNAL (SHOOFLY) 1.00 LS $1,300,000.00 $1,300,000 0.00% 10.00% 10.00% $130,000 $1,430,000
50.01.01 ASH STREET 1.00 LS $260,000.00 $260,000 15.00% 10.00% 25.00% $65,000 $325,000
50.01.02 BEECH STREET 1.00 LS $260,000.00 $260,000 15.00% 10.00% 25.00% $65,000 $325,000
50.01.03 CEDAR STREET - ABS SIGNAL O045 1.00 LS $303,000.00 $303,000 15.00% 10.00% 25.00% $75,750 $378,750
50.01.05 ABS SIGNALS O086, O087, O088, O089 1.00 LS $456,000.00 $456,000 15.00% 10.00% 25.00% $114,000 $570,000
50.01.06 PALM STREET - ABS SIGNALS O121, O123 1.00 LS $328,000.00 $328,000 15.00% 10.00% 25.00% $82,000 $410,000
50.01.07 INTERLOCKING - O6 1.00 LS $1,151,000.00 $1,151,000 15.00% 10.00% 25.00% $287,750 $1,438,750
50.01.08 SASSAFRAS STREET - ABS SIGNALS O161, O162 1.00 LS $466,000.00 $466,000 15.00% 10.00% 25.00% $116,500 $582,500
50.01.09 ABS SIGNALS O191, O192, O193 1.00 LS $447,000.00 $447,000 15.00% 10.00% 25.00% $111,750 $558,750
50.01.10 WASHINGTON STREET 1.00 LS $366,000.00 $366,000 15.00% 10.00% 25.00% $91,500 $457,500
50.01.11 NOELL STREET - ABS SIGNALS O224, O225, O226 1.00 LS $476,000.00 $476,000 15.00% 10.00% 25.00% $119,000 $595,000
50.01.12 ABS SIGNALS O257, O258, O259 1.00 LS $447,000.00 $447,000 15.00% 10.00% 25.00% $111,750 $558,750
50.01.13 ABS SIGNAL O296, O297 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
50.01.14 INTERLOCKING O14 1.00 LS $650,000.00 $650,000 15.00% 10.00% 25.00% $162,500 $812,500
50.01.15 INTERLOCKING 018 1.00 LS $650,000.00 $650,000 15.00% 10.00% 25.00% $162,500 $812,500
50.01.16 TAYLOR STREET 1.00 LS $366,000.00 $366,000 15.00% 10.00% 25.00% $91,500 $457,500
50.01.17 ABS SIGNAL M391 CHANGES 1.00 LS $53,000.00 $53,000 15.00% 10.00% 25.00% $13,250 $66,250
50.01.18 ABS SIGNAL M404, M405 1.00 LS $428,000.00 $428,000 15.00% 10.00% 25.00% $107,000 $535,000
Monday, January 27, 2014 Page 100 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.01.19 INTERLOCKING O22 1.00 LS $1,286,000.00 $1,286,000 15.00% 10.00% 25.00% $321,500 $1,607,500
50.01.20 ABS SIGNALS O402, O403, O 404, O405 1.00 LS $456,000.00 $456,000 15.00% 10.00% 25.00% $114,000 $570,000
50.01.21 INTERLOCKING O26 1.00 LS $1,058,000.00 $1,058,000 15.00% 10.00% 25.00% $264,500 $1,322,500
50.01.22 ABS SIGNALS O452, O454 1.00 LS $402,000.00 $402,000 15.00% 10.00% 25.00% $100,500 $502,500
50.01.23 ABS SIGNALS O524, O525, O526, O527 1.00 LS $417,000.00 $417,000 15.00% 10.00% 25.00% $104,250 $521,250
50.01.24 ABS SIGNALS O585, O587 1.00 LS $402,000.00 $402,000 15.00% 10.00% 25.00% $100,500 $502,500
50.01.25 INTERLOCKING O34 1.00 LS $1,118,000.00 $1,118,000 15.00% 10.00% 25.00% $279,500 $1,397,500
50.01.26 ABS SIGNALS O663, O664, O665, O666 1.00 LS $417,000.00 $417,000 15.00% 10.00% 25.00% $104,250 $521,250
50.01.27 ABS SIGNALS 0707, 0709 1.00 LS $402,000.00 $402,000 15.00% 10.00% 25.00% $100,500 $502,500
50.01.28 INTERLOCKING O38 1.00 LS $1,058,000.00 $1,058,000 15.00% 10.00% 25.00% $264,500 $1,322,500
50.01.29 ABS SIGNALS O791, O792, O793, O794 1.00 LS $417,000.00 $417,000 15.00% 10.00% 25.00% $104,250 $521,250
50.01.30 ABS SIGNALS O861, O862, O863, O864 1.00 LS $417,000.00 $417,000 15.00% 10.00% 25.00% $104,250 $521,250
50.01.31 INTERLOCKING O46 1.00 LS $1,058,000.00 $1,058,000 15.00% 10.00% 25.00% $264,500 $1,322,500
50.01.32 ABS SIGNAL O1035, O1036, O1037 1.00 LS $414,000.00 $414,000 15.00% 10.00% 25.00% $103,500 $517,500
50.01.33 ABS SIGNALS O1121, O1122 1.00 LS $402,000.00 $402,000 15.00% 10.00% 25.00% $100,500 $502,500
50.01.34 ABS SIGNALS O1132 1.00 LS $429,000.00 $429,000 15.00% 10.00% 25.00% $107,250 $536,250
50.01.35 ABS SIGNALS O1171, O1173 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
50.01.36 INTERLOCKING O54 1.00 LS $1,211,000.00 $1,211,000 15.00% 10.00% 25.00% $302,750 $1,513,750
50.01.37 ABS SIGNALS O1221, O1223 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
50.01.38 ABS SIGNALS O1232, O1234 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
50.01.39 ABS SIGNALS O1246, O1247 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
50.01.40 ABS SIGNALS O1257, O1259 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
50.01.41 ABS SIGNALS O1268, O1270 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
50.01.42 INTERLOCKING O58 1.00 LS $1,151,000.00 $1,151,000 15.00% 10.00% 25.00% $287,750 $1,438,750
50.01.43 ABS SIGNALS O1319, O1321 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
50.01.44 INTERLOCKING O62 1.00 LS $1,151,000.00 $1,151,000 15.00% 10.00% 25.00% $287,750 $1,438,750
50.01.45 ABS SIGNALS O1371, O1372, O1374 1.00 LS $447,000.00 $447,000 15.00% 10.00% 25.00% $111,750 $558,750
50.01.46 ABS SIGNALS O1395, O1396, O1397 1.00 LS $447,000.00 $447,000 15.00% 10.00% 25.00% $111,750 $558,750
50.01.47 ABS SIGNALS O1411, O1413 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
Monday, January 27, 2014 Page 101 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.01.48 INTERLOCKING O66 1.00 LS $1,001,000.00 $1,001,000 15.00% 10.00% 25.00% $250,250 $1,251,250
50.01.49 INTERLOCKING O66 REMOTE 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500
50.01.50 ABS SIGNALS O1454, O1455, O1456, O1457 1.00 LS $456,000.00 $456,000 15.00% 10.00% 25.00% $114,000 $570,000
50.01.51 CONTINGENCY FOR INTERLOCKING O8 1.00 LS $1,035,000.00 $1,035,000 0.00% 0.00% 0.00% $0 $1,035,000
Sum
Average
51.00 $29,839,000
14.41% 9.80% 24.22%
$7,006,000 $36,845,000Summary for Group: 50.01
Group 50.01.100
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TRAIN CONTROL AND SIGNALS (INFRASTRUCTURE) Contingency
50.01.100.01 PLATFORM (SIGNAL HOUSE AT RETAINING WALL) 1.00 LS $189,000.00 $189,000 15.00% 10.00% 25.00% $47,250 $236,250
50.01.100.02 PLATFORM (HOUSE AT BRIDGE) 1.00 LS $244,800.00 $244,800 15.00% 10.00% 25.00% $61,200 $306,000
50.01.100.03 PLATFORM (SIGNAL AT BRIDGE) 1.00 LS $63,000.00 $63,000 15.00% 10.00% 25.00% $15,750 $78,750
Sum
Average
3.00 $496,800
15.00% 10.00% 25.00%
$124,200 $621,000Summary for Group: 50.01.100
Sum
Average
54.00 $30,335,800
14.44% 9.81% 24.26%
$7,130,200 $37,466,000Summary for Sub Section: 50.01
Sub Section 50.02 TRAFFIC SIGNALS AND CROSSING PROTECTION
Group 50.02.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CEDAR/KETTNER TRAFFIC SIGNAL Contingency
50.02.01.2 SIGNAL MODIFICATION 1.00 LS $195,000.00 $195,000 0.00% 25.00% 25.00% $48,750 $243,750
Sum
Average
1.00 $195,000
0.00% 25.00% 25.00%
$48,750 $243,750Summary for Group: 50.02.01
Group 50.02.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CEDAR/PACIFIC HWY TRAFFIC SIGNAL Contingency
50.02.02.2 SIGNAL MODIFICATION 1.00 LS $75,000.00 $75,000 0.00% 25.00% 25.00% $18,750 $93,750
Sum
Average
1.00 $75,000
0.00% 25.00% 25.00%
$18,750 $93,750Summary for Group: 50.02.02
Group 50.02.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SASSAFRAS/PACIFIC HWY TRAFFIC SIGNALS Contingency
50.02.03.2 SIGNAL MODIFICATION 1.00 LS $75,000.00 $75,000 0.00% 25.00% 25.00% $18,750 $93,750
Sum
Average
1.00 $75,000
0.00% 25.00% 25.00%
$18,750 $93,750Summary for Group: 50.02.03
Group 50.02.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PACIFIC HWY/TAYLOR TRAFFIC SIGNAL Contingency
50.02.04.2 SIGNAL MODIFICATION 1.00 LS $220,000.00 $220,000 0.00% 25.00% 25.00% $55,000 $275,000
Monday, January 27, 2014 Page 102 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
1.00 $220,000
0.00% 25.00% 25.00%
$55,000 $275,000Summary for Group: 50.02.04
Group 50.02.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
W. MORENA/VEGA TRAFFIC SIGNAL Contingency
50.02.05.2 SIGNAL MODIFICATION 1.00 LS $85,000.00 $85,000 0.00% 25.00% 25.00% $21,250 $106,250
Sum
Average
1.00 $85,000
0.00% 25.00% 25.00%
$21,250 $106,250Summary for Group: 50.02.05
Group 50.02.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MORENA/INGULF TRAFFIC SIGNAL Contingency
50.02.06.2 SIGNAL MODIFICATION 1.00 LS $105,000.00 $105,000 0.00% 25.00% 25.00% $26,250 $131,250
Sum
Average
1.00 $105,000
0.00% 25.00% 25.00%
$26,250 $131,250Summary for Group: 50.02.06
Group 50.02.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MORENA/GESNER TRAFFIC SIGNAL Contingency
50.02.07.2 SIGNAL MODIFICATION 1.00 LS $115,000.00 $115,000 0.00% 25.00% 25.00% $28,750 $143,750
Sum
Average
1.00 $115,000
0.00% 25.00% 25.00%
$28,750 $143,750Summary for Group: 50.02.07
Group 50.02.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
MORENA/BALBOA TRAFFIC SIGNAL Contingency
50.02.08.1 NEW TRAFFIC SIGNAL 1.00 LS $225,000.00 $225,000 0.00% 25.00% 25.00% $56,250 $281,250
50.02.08.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $150,000.00 $150,000 0.00% 25.00% 25.00% $37,500 $187,500
Sum
Average
2.00 $375,000
0.00% 25.00% 25.00%
$93,750 $468,750Summary for Group: 50.02.08
Group 50.02.09
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
BALBOA STATION BUS ACCESS TRAFFIC SIGNAL Contingency
50.02.09.1 NEW TRAFFIC SIGNAL 1.00 LS $195,000.00 $195,000 0.00% 25.00% 25.00% $48,750 $243,750
Sum
Average
1.00 $195,000
0.00% 25.00% 25.00%
$48,750 $243,750Summary for Group: 50.02.09
Group 50.02.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
NOBEL/I-5 TRAFFIC SIGNAL Contingency
50.02.10.2 SIGNAL MODIFICATION 1.00 LS $115,000.00 $115,000 0.00% 25.00% 25.00% $28,750 $143,750
50.02.10.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $150,000.00 $150,000 0.00% 25.00% 25.00% $37,500 $187,500
Sum
Average
2.00 $265,000
0.00% 25.00% 25.00%
$66,250 $331,250Summary for Group: 50.02.10
Monday, January 27, 2014 Page 103 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Group 50.02.11
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LA JOLLA COLONY/I-5 TRAFFIC SIGNAL Contingency
50.02.11.2 SIGNAL MODIFICATION 1.00 LS $140,000.00 $140,000 0.00% 25.00% 25.00% $35,000 $175,000
50.02.11.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000
Sum
Average
2.00 $440,000
0.00% 25.00% 25.00%
$110,000 $550,000Summary for Group: 50.02.11
Group 50.02.12
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
VOIGT/CAMPUS POINT TRAFFIC SIGNAL Contingency
50.02.12.2 SIGNAL MODIFICAITON 1.00 LS $155,000.00 $155,000 0.00% 25.00% 25.00% $38,750 $193,750
50.02.12.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000
Sum
Average
2.00 $455,000
0.00% 25.00% 25.00%
$113,750 $568,750Summary for Group: 50.02.12
Group 50.02.13
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE/CAMPUS POINT TRAFFIC SIGNAL Contingency
50.02.13.2 SIGNAL MODIFICATION 1.00 LS $60,000.00 $60,000 0.00% 25.00% 25.00% $15,000 $75,000
Sum
Average
1.00 $60,000
0.00% 25.00% 25.00%
$15,000 $75,000Summary for Group: 50.02.13
Group 50.02.14
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE/REGENTS TRAFFIC SIGNAL Contingency
50.02.14.2 SIGNAL MODIFICATION 1.00 LS $165,000.00 $165,000 0.00% 25.00% 25.00% $41,250 $206,250
50.02.14.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $150,000.00 $150,000 0.00% 25.00% 25.00% $37,500 $187,500
Sum
Average
2.00 $315,000
0.00% 25.00% 25.00%
$78,750 $393,750Summary for Group: 50.02.14
Group 50.02.15
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE/EASTGATE MALL TRAFFIC SIGNAL Contingency
50.02.15.2 SIGNAL MODIFICATION 1.00 LS $265,000.00 $265,000 0.00% 25.00% 25.00% $66,250 $331,250
50.02.15.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000
Sum
Average
2.00 $565,000
0.00% 25.00% 25.00%
$141,250 $706,250Summary for Group: 50.02.15
Group 50.02.16
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE/EXECUTIVE DR TRAFFIC SIGNAL Contingency
50.02.16.2 SIGNAL MODIFICATION 1.00 LS $265,000.00 $265,000 0.00% 25.00% 25.00% $66,250 $331,250
50.02.16.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000
Monday, January 27, 2014 Page 104 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
2.00 $565,000
0.00% 25.00% 25.00%
$141,250 $706,250Summary for Group: 50.02.16
Group 50.02.17
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE/EXECUTIVE SQ TRAFFIC SIGNAL Contingency
50.02.17.2 SIGNAL MODIFICATION 1.00 LS $265,000.00 $265,000 0.00% 25.00% 25.00% $66,250 $331,250
50.02.17.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000
Sum
Average
2.00 $565,000
0.00% 25.00% 25.00%
$141,250 $706,250Summary for Group: 50.02.17
Group 50.02.18
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE/LA JOLLA VILLAGE TRAFFIC SIGNAL Contingency
50.02.18.2 SIGNAL MODIFICATION 1.00 LS $370,000.00 $370,000 0.00% 25.00% 25.00% $92,500 $462,500
50.02.18.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000
Sum
Average
2.00 $670,000
0.00% 25.00% 25.00%
$167,500 $837,500Summary for Group: 50.02.18
Group 50.02.19
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE/ESPLANADE TRAFFIC SIGNAL Contingency
50.02.19.2 SIGNAL MODIFICATION 1.00 LS $275,000.00 $275,000 0.00% 25.00% 25.00% $68,750 $343,750
50.02.19.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000
Sum
Average
2.00 $575,000
0.00% 25.00% 25.00%
$143,750 $718,750Summary for Group: 50.02.19
Group 50.02.20
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
GENESEE/NOBEL TRAFFIC SIGNAL Contingency
50.02.20.2 SIGNAL MODIFICATION 1.00 LS $80,000.00 $80,000 0.00% 25.00% 25.00% $20,000 $100,000
50.02.20.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $150,000.00 $150,000 0.00% 25.00% 25.00% $37,500 $187,500
Sum
Average
2.00 $230,000
0.00% 25.00% 25.00%
$57,500 $287,500Summary for Group: 50.02.20
Sum
Average
31.00 $6,145,000
0.00% 25.00% 25.00%
$1,536,250 $7,681,250Summary for Sub Section: 50.02
Sub Section 50.03 TRACTION POWER SUBSTATIONS
Group 50.03.012
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATIONS 1 & 2 Contingency
50.03.012.01 CLEARING AND GRUBBING 0.13 AC $4,022.00 $523 10.00% 15.00% 25.00% $131 $654
50.03.012.02 REMOVE EXIST TPSS 1.00 EA $14,758.00 $14,758 0.00% 15.00% 15.00% $2,214 $16,972
50.03.012.04 REMOVE EXIST CL FENCE 48.00 LF $2.20 $106 15.00% 15.00% 30.00% $32 $137
Monday, January 27, 2014 Page 105 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.012.05 REMOVE EXIST GATE 1.00 EA $42.00 $42 15.00% 15.00% 30.00% $13 $55
50.03.012.08 REMOVE EXIST POLE FOUNDATION 2.00 EA $913.00 $1,826 15.00% 15.00% 30.00% $548 $2,374
50.03.012.09 ROADWAY EXCAVATION 475.00 CY $28.00 $13,300 10.00% 15.00% 25.00% $3,325 $16,625
50.03.012.10 HAUL AND DISPOSE 545.00 CY $0.00 $0 15.00% 15.00% 30.00% $0 $0
50.03.012.100 UPGRADE POWER TO SUBSTATION 1.00 LS $200,000.00 $200,000 0.00% 30.00% 30.00% $60,000 $260,000
50.03.012.13 CONCRETE PAD 48.00 CY $571.00 $27,408 15.00% 15.00% 30.00% $8,222 $35,630
50.03.012.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 15.00% 15.00% 30.00% $723 $3,133
50.03.012.16 HOT MIX ASPHALT (TYPE A) 2.00TON $102.00 $204 10.00% 10.00% 20.00% $41 $245
50.03.012.18 TPSS STAIRS AND LANDING 165.00 SF $24.00 $3,960 10.00% 15.00% 25.00% $990 $4,950
50.03.012.19 CLASS 2 AGGREGATE BASE 22.00 CY $45.00 $990 10.00% 10.00% 20.00% $198 $1,188
50.03.012.23 10' CL FENCE W/BARBED WIRE 66.00 LF $43.00 $2,838 15.00% 15.00% 30.00% $851 $3,689
50.03.012.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 15.00% 15.00% 30.00% $1,175 $5,090
50.03.012.27 CRUSHED ROCK 63.00 CY $45.00 $2,835 15.00% 15.00% 30.00% $851 $3,686
50.03.012.50 TPSS (1500kW) 2.00 EA $800,000.00 $1,600,000 0.00% 15.00% 15.00% $240,000 $1,840,000
50.03.012.54 #4/0 BARE COPPER WIRE 1,200.00 LF $1.80 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.03.012.55 COPPER GROUND RODS 28.00 EA $250.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100
50.03.012.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 2.00 EA $20,000.00 $40,000 10.00% 15.00% 25.00% $10,000 $50,000
50.03.012.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 2.00 EA $20,000.00 $40,000 15.00% 15.00% 30.00% $12,000 $52,000
50.03.012.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 2.00 EA $13,500.00 $27,000 15.00% 15.00% 30.00% $8,100 $35,100
50.03.012.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 2.00 EA $20,000.00 $40,000 15.00% 15.00% 30.00% $12,000 $52,000
50.03.012.62 POSITIVE DC FEEDER - 1/C 500 kcmil 6,300.00 LF $31.00 $195,300 10.00% 15.00% 25.00% $48,825 $244,125
50.03.012.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 2,100.00 LF $31.00 $65,100 10.00% 15.00% 25.00% $16,275 $81,375
50.03.012.65 POSITIVE DUCTBANK (6 - 4" PVC) 5,970.00 LF $161.00 $961,170 10.00% 15.00% 25.00% $240,293 $1,201,463
50.03.012.66 NEGATIVE DUCTBANK (4 - 4" PVC) 1,200.00 LF $161.00 $193,200 10.00% 15.00% 25.00% $48,300 $241,500
50.03.012.71 GENERAL SERVICE LIGHTING 5,663.00 SF $20.00 $113,260 15.00% 15.00% 30.00% $33,978 $147,238
Sum
Average
26,321.13 $3,559,304
11.61% 15.18% 26.79%
$751,831 $4,311,135Summary for Group: 50.03.012
Group 50.03.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 3 Contingency
50.03.03.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 15.00% 25.00% $70 $352
Monday, January 27, 2014 Page 106 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.03.02 REMOVE EXIST TPSS 1.00 EA $14,758.00 $14,758 0.00% 15.00% 15.00% $2,214 $16,972
50.03.03.04 REMOVE EXIST CL FENCE 76.00 LF $2.20 $167 15.00% 15.00% 30.00% $50 $217
50.03.03.05 REMOVE EXIST GATE 1.00 EA $42.00 $42 15.00% 15.00% 30.00% $13 $55
50.03.03.08 REMOVE EXIST POLE FOUNDATION 2.00 EA $913.00 $1,826 15.00% 15.00% 30.00% $548 $2,374
50.03.03.100 UPGRADE POWER TO SUBSTATION 1.00 LS $200,000.00 $200,000 0.00% 30.00% 30.00% $60,000 $260,000
50.03.03.11 ROADWAY EMBANKMENT 742.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.03.13 CONCRETE PAD 24.00 CY $571.00 $13,704 15.00% 15.00% 30.00% $4,111 $17,815
50.03.03.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 15.00% 15.00% 30.00% $723 $3,133
50.03.03.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.03.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 15.00% 25.00% $492 $2,460
50.03.03.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.03.23 10' CL FENCE W/BARBED WIRE 152.00 LF $43.00 $6,536 15.00% 15.00% 30.00% $1,961 $8,497
50.03.03.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 15.00% 15.00% 30.00% $1,175 $5,090
50.03.03.27 CRUSHED ROCK 37.00 CY $45.00 $1,665 15.00% 15.00% 30.00% $500 $2,165
50.03.03.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 15.00% 15.00% $120,000 $920,000
50.03.03.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.03.03.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 15.00% 15.00% 30.00% $1,050 $4,550
50.03.03.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 15.00% 25.00% $5,000 $25,000
50.03.03.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.03.03.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 15.00% 15.00% 30.00% $4,050 $17,550
50.03.03.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.03.03.62 POSITIVE DC FEEDER - 1/C 500 kcmil 1,236.00 LF $31.00 $38,316 10.00% 15.00% 25.00% $9,579 $47,895
50.03.03.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,050.00 LF $31.00 $32,550 10.00% 15.00% 25.00% $8,138 $40,688
50.03.03.65 POSITIVE DUCTBANK (6 - 4" PVC) 1,086.00 LF $161.00 $174,846 10.00% 15.00% 25.00% $43,712 $218,558
50.03.03.66 NEGATIVE DUCTBANK (4 - 4" PVC) 600.00 LF $161.00 $96,600 10.00% 15.00% 25.00% $24,150 $120,750
50.03.03.71 GENERAL SERVICE LIGHTING 2,614.00 SF $20.00 $52,280 15.00% 15.00% 30.00% $15,684 $67,964
Sum
Average
10,746.07 $1,520,542
11.48% 15.00% 26.48%
$315,661 $1,836,203Summary for Group: 50.03.03
Group 50.03.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 4 Contingency
Monday, January 27, 2014 Page 107 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.04.09 ROADWAY EXCAVATION 176.00 CY $28.00 $4,928 10.00% 15.00% 25.00% $1,232 $6,160
50.03.04.10 HAUL AND DISPOSE 202.00 CY $0.00 $0 15.00% 15.00% 30.00% $0 $0
50.03.04.100 UPGRADE POWER TO SUBSTATION 1.00 LS $200,000.00 $200,000 0.00% 30.00% 30.00% $60,000 $260,000
50.03.04.13 CONCRETE PAD 24.00 CY $571.00 $13,704 15.00% 15.00% 30.00% $4,111 $17,815
50.03.04.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 15.00% 15.00% 30.00% $723 $3,133
50.03.04.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.04.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 15.00% 25.00% $492 $2,460
50.03.04.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.04.23 10' CL FENCE W/BARBED WIRE 208.00 LF $43.00 $8,944 15.00% 15.00% 30.00% $2,683 $11,627
50.03.04.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 15.00% 15.00% 30.00% $1,175 $5,090
50.03.04.27 CRUSHED ROCK 39.00 CY $45.00 $1,755 15.00% 15.00% 30.00% $527 $2,282
50.03.04.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 15.00% 15.00% $120,000 $920,000
50.03.04.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.03.04.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 15.00% 15.00% 30.00% $1,050 $4,550
50.03.04.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 15.00% 25.00% $5,000 $25,000
50.03.04.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.03.04.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 15.00% 15.00% 30.00% $4,050 $17,550
50.03.04.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.03.04.62 POSITIVE DC FEEDER - 1/C 500 kcmil 1,680.00 LF $31.00 $52,080 10.00% 15.00% 25.00% $13,020 $65,100
50.03.04.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,050.00 LF $31.00 $32,550 10.00% 15.00% 25.00% $8,138 $40,688
50.03.04.65 POSITIVE DUCTBANK (6 - 4" PVC) 1,530.00 LF $161.00 $246,330 10.00% 15.00% 25.00% $61,583 $307,913
50.03.04.66 NEGATIVE DUCTBANK (4 - 4" PVC) 600.00 LF $161.00 $96,600 10.00% 15.00% 25.00% $24,150 $120,750
50.03.04.71 GENERAL SERVICE LIGHTING 2,614.00 SF $20.00 $52,280 15.00% 15.00% 30.00% $15,684 $67,964
Sum
Average
11,248.00 $1,596,141
11.74% 15.22% 26.96%
$336,060 $1,932,201Summary for Group: 50.03.04
Group 50.03.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 5 Contingency
50.03.05.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338
50.03.05.09 ROADWAY EXCAVATION 42.00 CY $28.00 $1,176 10.00% 10.00% 20.00% $235 $1,411
50.03.05.10 HAUL AND DISPOSE 12.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
Monday, January 27, 2014 Page 108 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.05.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
50.03.05.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.05.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.05.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.05.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.05.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.05.23 10' CL FENCE W/BARBED WIRE 208.00 LF $43.00 $8,944 10.00% 10.00% 20.00% $1,789 $10,733
50.03.05.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.05.27 CRUSHED ROCK 39.00 CY $45.00 $1,755 10.00% 10.00% 20.00% $351 $2,106
50.03.05.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.05.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.05.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.05.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.05.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.05.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.05.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.05.62 POSITIVE DC FEEDER - 1/C 500 kcmil 8,430.00 LF $31.00 $261,330 10.00% 10.00% 20.00% $52,266 $313,596
50.03.05.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 960.00 LF $31.00 $29,760 10.00% 10.00% 20.00% $5,952 $35,712
50.03.05.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 4,220.00 LF $8.50 $35,870 10.00% 10.00% 20.00% $7,174 $43,044
50.03.05.65 POSITIVE DUCTBANK (6 - 4" PVC) 4,775.00 LF $161.00 $768,775 10.00% 10.00% 20.00% $153,755 $922,530
50.03.05.66 NEGATIVE DUCTBANK (4 - 4" PVC) 620.00 LF $161.00 $99,820 10.00% 10.00% 20.00% $19,964 $119,784
50.03.05.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 4,210.00 LF $112.00 $471,520 10.00% 10.00% 20.00% $94,304 $565,824
50.03.05.71 GENERAL SERVICE LIGHTING 14,810.00 SF $20.00 $296,200 15.00% 15.00% 30.00% $88,860 $385,060
Sum
Average
41,475.07 $3,176,106
9.42% 10.58% 20.00%
$584,841 $3,760,947Summary for Group: 50.03.05
Group 50.03.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 6 Contingency
50.03.06.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338
50.03.06.09 ROADWAY EXCAVATION 35.00 CY $28.00 $980 10.00% 10.00% 20.00% $196 $1,176
50.03.06.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
Monday, January 27, 2014 Page 109 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.06.11 ROADWAY EMBANKMENT 23.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.06.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.06.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.06.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 2.00 EA $5,000.00 $10,000 10.00% 10.00% 20.00% $2,000 $12,000
50.03.06.16 HOT MIX ASPHALT (TYPE A) 9.00TON $102.00 $918 10.00% 10.00% 20.00% $184 $1,102
50.03.06.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.06.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.06.25 10' PICKET FENCE W/BARBED WIRE 194.00 LF $100.00 $19,400 10.00% 10.00% 20.00% $3,880 $23,280
50.03.06.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.06.27 CRUSHED ROCK 33.00 CY $45.00 $1,485 10.00% 10.00% 20.00% $297 $1,782
50.03.06.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.06.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.06.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.06.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.06.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.06.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.06.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.06.62 POSITIVE DC FEEDER - 1/C 500 kcmil 3,360.00 LF $31.00 $104,160 10.00% 10.00% 20.00% $20,832 $124,992
50.03.06.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,050.00 LF $31.00 $32,550 10.00% 10.00% 20.00% $6,510 $39,060
50.03.06.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 7,495.00 LF $8.50 $63,708 10.00% 10.00% 20.00% $12,742 $76,449
50.03.06.65 POSITIVE DUCTBANK (6 - 4" PVC) 1,590.00 LF $161.00 $255,990 10.00% 10.00% 20.00% $51,198 $307,188
50.03.06.66 NEGATIVE DUCTBANK (4 - 4" PVC) 600.00 LF $161.00 $96,600 10.00% 10.00% 20.00% $19,320 $115,920
50.03.06.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 7,485.00 LF $112.00 $838,320 10.00% 10.00% 20.00% $167,664 $1,005,984
50.03.06.71 GENERAL SERVICE LIGHTING 2,614.00 SF $20.00 $52,280 15.00% 15.00% 30.00% $15,684 $67,964
Sum
Average
27,638.07 $2,677,244
9.44% 10.56% 20.00%
$460,677 $3,137,921Summary for Group: 50.03.06
Group 50.03.078
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATIONS 7 & 8 Contingency
50.03.078.01 CLEARING AND GRUBBING 0.14 AC $4,022.00 $563 10.00% 10.00% 20.00% $113 $676
50.03.078.04 REMOVE EXIST CL FENCE 331.00 LF $2.20 $728 10.00% 10.00% 20.00% $146 $874
Monday, January 27, 2014 Page 110 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.078.06 REMOVE EXIST STORM DRAIN 107.00 LF $37.00 $3,959 10.00% 10.00% 20.00% $792 $4,751
50.03.078.09 ROADWAY EXCAVATION 476.00 CY $28.00 $13,328 10.00% 10.00% 20.00% $2,666 $15,994
50.03.078.10 HAUL AND DISPOSE 514.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.078.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
50.03.078.12 RETAINING WALL (TYPE H) 1,401.00 SF $117.00 $163,917 10.00% 10.00% 20.00% $32,783 $196,700
50.03.078.13 CONCRETE PAD 48.00 CY $571.00 $27,408 10.00% 10.00% 20.00% $5,482 $32,890
50.03.078.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.078.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000
50.03.078.16 HOT MIX ASPHALT (TYPE A) 2.00TON $102.00 $204 10.00% 10.00% 20.00% $41 $245
50.03.078.18 TPSS STAIRS AND LANDING 165.00 SF $24.00 $3,960 10.00% 10.00% 20.00% $792 $4,752
50.03.078.19 CLASS 2 AGGREGATE BASE 22.00 CY $45.00 $990 10.00% 10.00% 20.00% $198 $1,188
50.03.078.22 6' CL FENCE W/BARBED WIRE 180.00 LF $43.00 $7,740 10.00% 10.00% 20.00% $1,548 $9,288
50.03.078.25 10' PICKET FENCE W/BARBED WIRE 122.00 LF $100.00 $12,200 10.00% 10.00% 20.00% $2,440 $14,640
50.03.078.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.078.27 CRUSHED ROCK 71.00 CY $45.00 $3,195 10.00% 10.00% 20.00% $639 $3,834
50.03.078.50 TPSS (1500kW) 2.00 EA $800,000.00 $1,600,000 0.00% 10.00% 10.00% $160,000 $1,760,000
50.03.078.54 #4/0 BARE COPPER WIRE 1,200.00 LF $1.80 $2,160 10.00% 10.00% 20.00% $432 $2,592
50.03.078.55 COPPER GROUND RODS 28.00 EA $250.00 $7,000 10.00% 10.00% 20.00% $1,400 $8,400
50.03.078.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 2.00 EA $20,000.00 $40,000 10.00% 10.00% 20.00% $8,000 $48,000
50.03.078.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 2.00 EA $20,000.00 $40,000 10.00% 10.00% 20.00% $8,000 $48,000
50.03.078.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 2.00 EA $13,500.00 $27,000 10.00% 10.00% 20.00% $5,400 $32,400
50.03.078.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 2.00 EA $20,000.00 $40,000 10.00% 10.00% 20.00% $8,000 $48,000
50.03.078.62 POSITIVE DC FEEDER - 1/C 500 kcmil 14,130.00 LF $31.00 $438,030 10.00% 10.00% 20.00% $87,606 $525,636
50.03.078.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 2,520.00 LF $31.00 $78,120 10.00% 10.00% 20.00% $15,624 $93,744
50.03.078.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 8,955.00 LF $8.50 $76,118 10.00% 10.00% 20.00% $15,224 $91,341
50.03.078.65 POSITIVE DUCTBANK (6 - 4" PVC) 6,765.00 LF $161.00 $1,089,165 10.00% 10.00% 20.00% $217,833 $1,306,998
50.03.078.66 NEGATIVE DUCTBANK (4 - 4" PVC) 2,000.00 LF $161.00 $322,000 10.00% 10.00% 20.00% $64,400 $386,400
50.03.078.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 8,935.00 LF $112.00 $1,000,720 10.00% 10.00% 20.00% $200,144 $1,200,864
50.03.078.71 GENERAL SERVICE LIGHTING 5,663.00 SF $20.00 $113,260 15.00% 15.00% 30.00% $33,978 $147,238
Monday, January 27, 2014 Page 111 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
56,058.14 $5,423,090
9.52% 10.48% 20.00%
$935,944 $6,359,034Summary for Group: 50.03.078
Group 50.03.09
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 9 Contingency
50.03.09.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338
50.03.09.09 ROADWAY EXCAVATION 124.00 CY $28.00 $3,472 10.00% 10.00% 20.00% $694 $4,166
50.03.09.10 HAUL AND DISPOSE 143.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.09.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
50.03.09.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.09.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.09.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.09.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.09.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.09.23 10' CL FENCE W/BARBED WIRE 198.00 LF $43.00 $8,514 10.00% 10.00% 20.00% $1,703 $10,217
50.03.09.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.09.27 CRUSHED ROCK 35.00 CY $45.00 $1,575 10.00% 10.00% 20.00% $315 $1,890
50.03.09.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.09.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.09.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.09.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.09.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.09.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.09.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.09.62 POSITIVE DC FEEDER - 1/C 500 kcmil 4,560.00 LF $31.00 $141,360 10.00% 10.00% 20.00% $28,272 $169,632
50.03.09.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 900.00 LF $31.00 $27,900 10.00% 10.00% 20.00% $5,580 $33,480
50.03.09.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 5,720.00 LF $8.50 $48,620 10.00% 10.00% 20.00% $9,724 $58,344
50.03.09.65 POSITIVE DUCTBANK (6 - 4" PVC) 4,560.00 LF $161.00 $734,160 10.00% 10.00% 20.00% $146,832 $880,992
50.03.09.66 NEGATIVE DUCTBANK (4 - 4" PVC) 400.00 LF $161.00 $64,400 10.00% 10.00% 20.00% $12,880 $77,280
50.03.09.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 5,710.00 LF $112.00 $639,520 10.00% 10.00% 20.00% $127,904 $767,424
50.03.09.71 GENERAL SERVICE LIGHTING 3,049.00 SF $20.00 $60,980 15.00% 15.00% 30.00% $18,294 $79,274
Monday, January 27, 2014 Page 112 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
28,548.07 $2,931,457
9.42% 10.58% 20.00%
$512,389 $3,443,846Summary for Group: 50.03.09
Group 50.03.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 10 Contingency
50.03.10.01 CLEARING AND GRUBBING 0.08 AC $4,022.00 $322 10.00% 10.00% 20.00% $64 $386
50.03.10.04 REMOVE EXIST CL FENCE 5.00 LF $2.20 $11 10.00% 10.00% 20.00% $2 $13
50.03.10.09 ROADWAY EXCAVATION 59.00 CY $28.00 $1,652 10.00% 10.00% 20.00% $330 $1,982
50.03.10.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
50.03.10.11 ROADWAY EMBANKMENT 300.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.10.12 RETAINING WALL (TYPE H) 261.00 SF $117.00 $30,537 10.00% 10.00% 20.00% $6,107 $36,644
50.03.10.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.10.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.10.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000
50.03.10.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.10.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.10.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.10.23 10' CL FENCE W/BARBED WIRE 223.00 LF $43.00 $9,589 10.00% 10.00% 20.00% $1,918 $11,507
50.03.10.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.10.27 CRUSHED ROCK 46.00 CY $45.00 $2,070 10.00% 10.00% 20.00% $414 $2,484
50.03.10.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.10.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.10.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.10.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.10.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.10.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.10.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.10.62 POSITIVE DC FEEDER - 1/C 500 kcmil 1,920.00 LF $31.00 $59,520 10.00% 10.00% 20.00% $11,904 $71,424
50.03.10.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 900.00 LF $31.00 $27,900 10.00% 10.00% 20.00% $5,580 $33,480
50.03.10.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 9,520.00 LF $8.50 $80,920 10.00% 10.00% 20.00% $16,184 $97,104
50.03.10.65 POSITIVE DUCTBANK (6 - 4" PVC) 810.00 LF $161.00 $130,410 10.00% 10.00% 20.00% $26,082 $156,492
Monday, January 27, 2014 Page 113 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.10.66 NEGATIVE DUCTBANK (4 - 4" PVC) 400.00 LF $161.00 $64,400 10.00% 10.00% 20.00% $12,880 $77,280
50.03.10.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 9,510.00 LF $112.00 $1,065,120 10.00% 10.00% 20.00% $213,024 $1,278,144
50.03.10.71 GENERAL SERVICE LIGHTING 7,405.00 SF $20.00 $148,100 15.00% 15.00% 30.00% $44,430 $192,530
Sum
Average
34,509.08 $2,826,225
9.48% 10.52% 20.00%
$500,055 $3,326,280Summary for Group: 50.03.10
Group 50.03.11
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 11 Contingency
50.03.11.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338
50.03.11.09 ROADWAY EXCAVATION 906.00 CY $28.00 $25,368 10.00% 10.00% 20.00% $5,074 $30,442
50.03.11.10 HAUL AND DISPOSE 1,041.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.11.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
50.03.11.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.11.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.11.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.11.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.11.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.11.23 10' CL FENCE W/BARBED WIRE 208.00 LF $43.00 $8,944 10.00% 10.00% 20.00% $1,789 $10,733
50.03.11.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.11.27 CRUSHED ROCK 39.00 CY $45.00 $1,755 10.00% 10.00% 20.00% $351 $2,106
50.03.11.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.11.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.11.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.11.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.11.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.11.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.11.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.11.62 POSITIVE DC FEEDER - 1/C 500 kcmil 4,380.00 LF $31.00 $135,780 10.00% 10.00% 20.00% $27,156 $162,936
50.03.11.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 900.00 LF $31.00 $27,900 10.00% 10.00% 20.00% $5,580 $33,480
50.03.11.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 6,246.00 LF $8.50 $53,091 10.00% 10.00% 20.00% $10,618 $63,709
50.03.11.65 POSITIVE DUCTBANK (6 - 4" PVC) 1,170.00 LF $161.00 $188,370 10.00% 10.00% 20.00% $37,674 $226,044
Monday, January 27, 2014 Page 114 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.11.66 NEGATIVE DUCTBANK (4 - 4" PVC) 400.00 LF $161.00 $64,400 10.00% 10.00% 20.00% $12,880 $77,280
50.03.11.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 6,256.00 LF $112.00 $700,672 10.00% 10.00% 20.00% $140,134 $840,806
50.03.11.71 GENERAL SERVICE LIGHTING 4,356.00 SF $20.00 $87,120 15.00% 15.00% 30.00% $26,136 $113,256
Sum
Average
29,051.07 $2,494,356
9.42% 10.58% 20.00%
$427,583 $2,921,939Summary for Group: 50.03.11
Group 50.03.12
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 12 Contingency
50.03.12.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338
50.03.12.04 REMOVE EXIST CL FENCE 75.00 LF $2.20 $165 10.00% 10.00% 20.00% $33 $198
50.03.12.09 ROADWAY EXCAVATION 41.00 CY $28.00 $1,148 10.00% 10.00% 20.00% $230 $1,378
50.03.12.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
50.03.12.11 ROADWAY EMBANKMENT 9.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.12.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.12.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.12.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.12.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.12.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.12.23 10' CL FENCE W/BARBED WIRE 211.00 LF $43.00 $9,073 10.00% 10.00% 20.00% $1,815 $10,888
50.03.12.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.12.27 CRUSHED ROCK 38.00 CY $45.00 $1,710 10.00% 10.00% 20.00% $342 $2,052
50.03.12.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.12.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.12.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.12.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.12.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.12.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.12.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.12.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720
50.03.12.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800
50.03.12.62 POSITIVE DC FEEDER - 1/C 500 kcmil 2,322.00 LF $31.00 $71,982 10.00% 10.00% 20.00% $14,396 $86,378
Monday, January 27, 2014 Page 115 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.12.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 996.00 LF $31.00 $30,876 10.00% 10.00% 20.00% $6,175 $37,051
50.03.12.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 3,720.00 LF $8.50 $31,620 10.00% 10.00% 20.00% $6,324 $37,944
50.03.12.65 POSITIVE DUCTBANK (6 - 4" PVC) 450.00 LF $161.00 $72,450 10.00% 10.00% 20.00% $14,490 $86,940
50.03.12.66 NEGATIVE DUCTBANK (4 - 4" PVC) 480.00 LF $161.00 $77,280 10.00% 10.00% 20.00% $15,456 $92,736
50.03.12.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 501.00 LF $165.00 $82,665 10.00% 10.00% 20.00% $16,533 $99,198
50.03.12.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 364.00 LF $213.00 $77,532 10.00% 10.00% 20.00% $15,506 $93,038
50.03.12.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 3,710.00 LF $112.00 $415,520 10.00% 10.00% 20.00% $83,104 $498,624
50.03.12.71 GENERAL SERVICE LIGHTING 5,227.00 SF $20.00 $104,540 15.00% 15.00% 30.00% $31,362 $135,902
Sum
Average
21,296.07 $2,179,617
9.52% 10.48% 20.00%
$366,377 $2,545,994Summary for Group: 50.03.12
Group 50.03.13
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 13 Contingency
50.03.13.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338
50.03.13.04 REMOVE EXIST CL FENCE 70.00 LF $2.20 $154 10.00% 10.00% 20.00% $31 $185
50.03.13.09 ROADWAY EXCAVATION 99.00 CY $28.00 $2,772 10.00% 10.00% 20.00% $554 $3,326
50.03.13.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
50.03.13.11 ROADWAY EMBANKMENT 236.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.13.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.13.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.13.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.13.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.13.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.13.25 10' PICKET FENCE W/BARBED WIRE 200.00 LF $100.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.13.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.13.27 CRUSHED ROCK 34.00 CY $45.00 $1,530 10.00% 10.00% 20.00% $306 $1,836
50.03.13.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.13.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.13.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.13.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.13.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
Monday, January 27, 2014 Page 116 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.13.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.13.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.13.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720
50.03.13.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800
50.03.13.62 POSITIVE DC FEEDER - 1/C 500 kcmil 3,660.00 LF $31.00 $113,460 10.00% 10.00% 20.00% $22,692 $136,152
50.03.13.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,320.00 LF $31.00 $40,920 10.00% 10.00% 20.00% $8,184 $49,104
50.03.13.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 5,190.00 LF $8.50 $44,115 10.00% 10.00% 20.00% $8,823 $52,938
50.03.13.65 POSITIVE DUCTBANK (6 - 4" PVC) 780.00 LF $161.00 $125,580 10.00% 10.00% 20.00% $25,116 $150,696
50.03.13.66 NEGATIVE DUCTBANK (4 - 4" PVC) 540.00 LF $161.00 $86,940 10.00% 10.00% 20.00% $17,388 $104,328
50.03.13.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 1,050.00 LF $165.00 $173,250 10.00% 10.00% 20.00% $34,650 $207,900
50.03.13.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 520.00 LF $213.00 $110,760 10.00% 10.00% 20.00% $22,152 $132,912
50.03.13.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 5,200.00 LF $112.00 $582,400 10.00% 10.00% 20.00% $116,480 $698,880
50.03.13.71 GENERAL SERVICE LIGHTING 9,148.00 SF $20.00 $182,960 15.00% 15.00% 30.00% $54,888 $237,848
Sum
Average
31,199.07 $2,687,897
9.52% 10.48% 20.00%
$475,875 $3,163,772Summary for Group: 50.03.13
Group 50.03.14
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 14 Contingency
50.03.14.01 CLEARING AND GRUBBING 0.09 AC $4,022.00 $362 10.00% 10.00% 20.00% $72 $434
50.03.14.07 REMOVE EXIST TREE 4.00 EA $200.00 $800 20.00% 10.00% 30.00% $240 $1,040
50.03.14.08 REMOVE EXIST POLE FOUNDATION 1.00 EA $913.00 $913 15.00% 15.00% 30.00% $274 $1,187
50.03.14.09 ROADWAY EXCAVATION 138.00 CY $28.00 $3,864 10.00% 10.00% 20.00% $773 $4,637
50.03.14.10 HAUL AND DISPOSE 158.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.14.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
50.03.14.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.14.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.14.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.14.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.14.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.14.25 10' PICKET FENCE W/BARBED WIRE 229.00 LF $100.00 $22,900 10.00% 10.00% 20.00% $4,580 $27,480
50.03.14.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
Monday, January 27, 2014 Page 117 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.14.27 CRUSHED ROCK 45.00 CY $45.00 $2,025 10.00% 10.00% 20.00% $405 $2,430
50.03.14.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.14.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.14.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.14.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.14.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.14.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.14.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.14.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720
50.03.14.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800
50.03.14.62 POSITIVE DC FEEDER - 1/C 500 kcmil 3,660.00 LF $31.00 $113,460 10.00% 10.00% 20.00% $22,692 $136,152
50.03.14.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,080.00 LF $31.00 $33,480 10.00% 10.00% 20.00% $6,696 $40,176
50.03.14.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 5,265.00 LF $8.50 $44,753 10.00% 10.00% 20.00% $8,951 $53,703
50.03.14.65 POSITIVE DUCTBANK (6 - 4" PVC) 510.00 LF $161.00 $82,110 10.00% 10.00% 20.00% $16,422 $98,532
50.03.14.66 NEGATIVE DUCTBANK (4 - 4" PVC) 340.00 LF $161.00 $54,740 10.00% 10.00% 20.00% $10,948 $65,688
50.03.14.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 702.00 LF $165.00 $115,830 10.00% 10.00% 20.00% $23,166 $138,996
50.03.14.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 360.00 LF $213.00 $76,680 10.00% 10.00% 20.00% $15,336 $92,016
50.03.14.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 5,255.00 LF $112.00 $588,560 10.00% 10.00% 20.00% $117,712 $706,272
50.03.14.71 GENERAL SERVICE LIGHTING 20,038.00 SF $20.00 $400,760 15.00% 15.00% 30.00% $120,228 $520,988
Sum
Average
40,937.09 $2,744,010
10.00% 10.63% 20.63%
$509,049 $3,253,060Summary for Group: 50.03.14
Group 50.03.15
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 15 Contingency
50.03.15.01 CLEARING AND GRUBBING 0.13 AC $4,022.00 $523 10.00% 10.00% 20.00% $105 $627
50.03.15.02 REMOVE EXIST DRAINAGE DITCH 85.00 LF $20.00 $1,700 10.00% 10.00% 20.00% $340 $2,040
50.03.15.04 REMOVE EXIST CL FENCE 10.00 LF $2.20 $22 10.00% 10.00% 20.00% $4 $26
50.03.15.05 REMOVE EXIST GATE 1.00 EA $42.00 $42 10.00% 10.00% 20.00% $8 $50
50.03.15.07 REMOVE EXIST TREE 6.00 EA $200.00 $1,200 20.00% 10.00% 30.00% $360 $1,560
50.03.15.09 ROADWAY EXCAVATION 191.00 CY $28.00 $5,348 10.00% 10.00% 20.00% $1,070 $6,418
50.03.15.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
Monday, January 27, 2014 Page 118 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.15.11 ROADWAY EMBANKMENT 732.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.15.12 RETAINING WALL (TYPE H) 2,623.00 SF $117.00 $306,891 10.00% 10.00% 20.00% $61,378 $368,269
50.03.15.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.15.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.15.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000
50.03.15.16 HOT MIX ASPHALT (TYPE A) 107.00TON $102.00 $10,914 10.00% 10.00% 20.00% $2,183 $13,097
50.03.15.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.15.19 CLASS 2 AGGREGATE BASE 63.00 CY $45.00 $2,835 10.00% 10.00% 20.00% $567 $3,402
50.03.15.20 RELOCATE EXIST GATE 1.00 EA $80.00 $80 10.00% 10.00% 20.00% $16 $96
50.03.15.22 6' CL FENCE W/BARBED WIRE 157.00 LF $43.00 $6,751 10.00% 10.00% 20.00% $1,350 $8,101
50.03.15.23 10' CL FENCE W/BARBED WIRE 103.00 LF $43.00 $4,429 10.00% 10.00% 20.00% $886 $5,315
50.03.15.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.15.27 CRUSHED ROCK 47.00 CY $45.00 $2,115 10.00% 10.00% 20.00% $423 $2,538
50.03.15.30 CONCRETE LINED DRAINAGE DITCH 70.00 LF $27.00 $1,890 10.00% 10.00% 20.00% $378 $2,268
50.03.15.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.15.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.15.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.15.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.15.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.15.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.15.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.15.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720
50.03.15.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800
50.03.15.62 POSITIVE DC FEEDER - 1/C 500 kcmil 7,512.00 LF $31.00 $232,872 10.00% 10.00% 20.00% $46,574 $279,446
50.03.15.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 2,640.00 LF $31.00 $81,840 10.00% 10.00% 20.00% $16,368 $98,208
50.03.15.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 3,763.00 LF $8.50 $31,986 10.00% 10.00% 20.00% $6,397 $38,383
50.03.15.65 POSITIVE DUCTBANK (6 - 4" PVC) 3,306.00 LF $161.00 $532,266 10.00% 10.00% 20.00% $106,453 $638,719
50.03.15.66 NEGATIVE DUCTBANK (4 - 4" PVC) 1,400.00 LF $161.00 $225,400 10.00% 10.00% 20.00% $45,080 $270,480
50.03.15.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 228.00 LF $165.00 $37,620 10.00% 10.00% 20.00% $7,524 $45,144
Monday, January 27, 2014 Page 119 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.15.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 340.00 LF $213.00 $72,420 10.00% 10.00% 20.00% $14,484 $86,904
50.03.15.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 3,753.00 LF $112.00 $420,336 10.00% 10.00% 20.00% $84,067 $504,403
50.03.15.71 GENERAL SERVICE LIGHTING 3,049.00 SF $20.00 $60,980 15.00% 15.00% 30.00% $18,294 $79,274
Sum
Average
33,328.13 $3,247,636
9.87% 10.38% 20.26%
$575,745 $3,823,382Summary for Group: 50.03.15
Group 50.03.16
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SUBSTATION 16 Contingency
50.03.16.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338
50.03.16.07 REMOVE EXIST TREE 3.00 EA $200.00 $600 20.00% 10.00% 30.00% $180 $780
50.03.16.09 ROADWAY EXCAVATION 1,212.00 CY $28.00 $33,936 10.00% 10.00% 20.00% $6,787 $40,723
50.03.16.10 HAUL AND DISPOSE 1,394.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0
50.03.16.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000
50.03.16.12 RETAINING WALL (TYPE H) 1,767.00 SF $117.00 $206,739 10.00% 10.00% 20.00% $41,348 $248,087
50.03.16.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445
50.03.16.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892
50.03.16.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000
50.03.16.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122
50.03.16.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362
50.03.16.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594
50.03.16.25 10' PICKET FENCE W/BARBED WIRE 198.00 LF $100.00 $19,800 10.00% 10.00% 20.00% $3,960 $23,760
50.03.16.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698
50.03.16.27 CRUSHED ROCK 35.00 CY $45.00 $1,575 10.00% 10.00% 20.00% $315 $1,890
50.03.16.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000
50.03.16.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296
50.03.16.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200
50.03.16.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.16.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.16.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200
50.03.16.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000
50.03.16.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720
Monday, January 27, 2014 Page 120 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.03.16.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800
50.03.16.62 POSITIVE DC FEEDER - 1/C 500 kcmil 1,518.00 LF $31.00 $47,058 10.00% 10.00% 20.00% $9,412 $56,470
50.03.16.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,050.00 LF $31.00 $32,550 10.00% 10.00% 20.00% $6,510 $39,060
50.03.16.65 POSITIVE DUCTBANK (6 - 4" PVC) 390.00 LF $161.00 $62,790 10.00% 10.00% 20.00% $12,558 $75,348
50.03.16.66 NEGATIVE DUCTBANK (4 - 4" PVC) 320.00 LF $161.00 $51,520 10.00% 10.00% 20.00% $10,304 $61,824
50.03.16.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 264.00 LF $165.00 $43,560 10.00% 10.00% 20.00% $8,712 $52,272
50.03.16.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 360.00 LF $213.00 $76,680 10.00% 10.00% 20.00% $15,336 $92,016
50.03.16.71 GENERAL SERVICE LIGHTING 3,049.00 SF $20.00 $60,980 15.00% 15.00% 30.00% $18,294 $79,274
Sum
Average
14,713.07 $1,845,844
9.84% 10.48% 20.32%
$295,327 $2,141,170Summary for Group: 50.03.16
Sum
Average
407,068.13 $38,909,467
9.99% 11.40% 21.39%
$7,047,415 $45,956,882Summary for Sub Section: 50.03
Sub Section 50.04 TRACTION POWER DISTRIBUTION
Group 50.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
TRACTION POWER DISTRIBUTION Contingency
50.04.01 TAPERED TUBULAR POLE ASSEMBLY - STANDARD POLE (13" DIA. 2 269.00 EA $2,296.00 $617,624 10.00% 15.00% 25.00% $154,406 $772,030
50.04.02 TAPERED TUBULAR POLE ASSEMBLY - HEADSPAN/2 TRACK POLE (1 1.00 EA $4,029.00 $4,029 10.00% 15.00% 25.00% $1,007 $5,036
50.04.03 TAPERED TUBULAR POLE ASSEMBLY - FEEDER POLE (15" DIA. 26' L 26.00 EA $5,778.00 $150,228 10.00% 15.00% 25.00% $37,557 $187,785
50.04.04 TAPERED TUBULAR POLE ASSEMBLY - COUTERWEIGHT POLE (15" D 70.00 EA $6,325.00 $442,750 10.00% 15.00% 25.00% $110,688 $553,438
50.04.05 TAPERED TUBULAR POLE ASSEMBLY - FIXED END/MIDPOINT/OVER 115.00 EA $3,730.00 $428,950 10.00% 15.00% 25.00% $107,238 $536,188
50.04.06 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - STANDA 132.00 EA $5,000.00 $660,000 10.00% 15.00% 25.00% $165,000 $825,000
50.04.07 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - HEADSP 1.00 EA $5,000.00 $5,000 10.00% 15.00% 25.00% $1,250 $6,250
50.04.08 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - FEEDER 15.00 EA $5,000.00 $75,000 10.00% 15.00% 25.00% $18,750 $93,750
50.04.09 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - COUNTE 42.00 EA $5,000.00 $210,000 10.00% 15.00% 25.00% $52,500 $262,500
50.04.10 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - FIXED E 73.00 EA $5,000.00 $365,000 10.00% 15.00% 25.00% $91,250 $456,250
50.04.11 CANTILEVER ASSEMBLY - LIGHT & MEDIUM LOAD 831.00 EA $2,627.00 $2,183,037 10.00% 15.00% 25.00% $545,759 $2,728,796
50.04.12 CANTILEVER ASSEMBLY - HEAVY LOAD 171.00 EA $3,152.00 $538,992 10.00% 15.00% 25.00% $134,748 $673,740
50.04.14 HEADSPAN ASSEMBLY 4.00 EA $6,304.00 $25,216 10.00% 15.00% 25.00% $6,304 $31,520
50.04.15 PULL OFF ASSEMBLY (NOT USED) 1.00 EA $3,152.00 $3,152 10.00% 15.00% 25.00% $788 $3,940
50.04.16 DOWN GUY ASSEMBLY 128.00 EA $3,152.00 $403,456 10.00% 15.00% 25.00% $100,864 $504,320
Monday, January 27, 2014 Page 121 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.04.17 DOWN GUY FOUNDATION ASSEMBLY 77.00 EA $5,000.00 $385,000 10.00% 15.00% 25.00% $96,250 $481,250
50.04.18 FIXED TERMINATION ASSEMBLY 17.00 EA $3,677.00 $62,509 10.00% 15.00% 25.00% $15,627 $78,136
50.04.19 COUNTERWEIGHT ASSEMBLY 21.00 EA $10,506.00 $220,626 10.00% 15.00% 25.00% $55,157 $275,783
50.04.20 CONTACT BRIDGE ASSEMBLY 36.00 EA $315.00 $11,340 10.00% 15.00% 25.00% $2,835 $14,175
50.04.21 SECTION INSULATOR ASSEMBLY 80.00 EA $6,304.00 $504,320 10.00% 15.00% 25.00% $126,080 $630,400
50.04.22 MANUAL DISCONNECT SWITCH ASSEMBLY 74.00 EA $9,455.00 $699,670 10.00% 15.00% 25.00% $174,918 $874,588
50.04.23 FEEDER TAP ASSEMBLY 46.00 EA $1,051.00 $48,346 10.00% 15.00% 25.00% $12,087 $60,433
50.04.24 LIGHTNING ARRESTER ASSEMBLY 46.00 EA $2,101.00 $96,646 10.00% 15.00% 25.00% $24,162 $120,808
50.04.25 MIDPOINT ASSEMBLY 18.00 EA $2,627.00 $47,286 10.00% 15.00% 25.00% $11,822 $59,108
50.04.26 POLE GROUNDING 481.00 EA $525.00 $252,525 10.00% 15.00% 25.00% $63,131 $315,656
50.04.27 FULL FEED JUMPER ASSEMBLY 73.00 EA $315.00 $22,995 10.00% 15.00% 25.00% $5,749 $28,744
50.04.28 UNDER BRIDGE SUPPORT ASSEMBLY 6.00 EA $840.00 $5,040 10.00% 15.00% 25.00% $1,260 $6,300
50.04.29 IN-SPAN JUMPER 337.00 EA $263.00 $88,631 10.00% 15.00% 25.00% $22,158 $110,789
50.04.30 HANGER SET 1,092.00 EA $1,051.00 $1,147,692 10.00% 15.00% 25.00% $286,923 $1,434,615
50.04.31 DOUBLE MW FIXED TERMINATION ASSEMBLY 44.00 EA $3,152.00 $138,688 10.00% 15.00% 25.00% $34,672 $173,360
50.04.32 DOUBLE MW COUNTERWEIGHT ASSEMBLY 52.00 EA $15,759.00 $819,468 10.00% 15.00% 25.00% $204,867 $1,024,335
50.04.33 MESSENGER WIRE 190,349.00 LF $19.00 $3,616,631 10.00% 15.00% 25.00% $904,158 $4,520,789
50.04.34 CONTACT WIRE 141,315.00 LF $11.00 $1,554,465 10.00% 15.00% 25.00% $388,616 $1,943,081
50.04.35 REMOVE EXISTING OCS STRUCTURE 2.00 EA $2,101.00 $4,202 10.00% 15.00% 25.00% $1,051 $5,253
50.04.37 EQUALIZING JUMPER 23.00 EA $210.00 $4,830 10.00% 15.00% 25.00% $1,208 $6,038
50.04.38 EXISTING GL OCS TRANSITION/MODIFICATION 1.00 LS $21,012.00 $21,012 10.00% 15.00% 25.00% $5,253 $26,265
50.04.50.01 BRIDGE SOFFIT MANHOLE 1.00 LS $72,000.00 $72,000 15.00% 15.00% 30.00% $21,600 $93,600
50.04.50.02 REMOVAL OF LOST DECK 1.00 LS $36,000.00 $36,000 15.00% 15.00% 30.00% $10,800 $46,800
50.04.50.03.01 PARALLEL FEEDER - 3-500 KCMIL CABLES (UCSD WEST ZONE) 8,280.00 LF $93.00 $770,040 15.00% 15.00% 30.00% $231,012 $1,001,052
50.04.50.03.02 INTERMEDIATE RISER, 1-500 KCMIL CABLE (UCSD WEST ZONE) 1,350.00 LF $31.00 $41,850 15.00% 15.00% 30.00% $12,555 $54,405
50.04.50.03.03 SPLICE KITS - INSULATED (UCSD WEST ZONE) 30.00 EA $100.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.04.50.03.04 LONGITUDINAL CABLE TRAY (UCSD WEST ZONE) 2,580.00 LF $50.00 $129,000 15.00% 15.00% 30.00% $38,700 $167,700
50.04.50.03.05 LATERAL CABLE TRAY (UCSD WEST ZONE) 255.00 LF $50.00 $12,750 15.00% 15.00% 30.00% $3,825 $16,575
50.04.50.04.01 PARALLEL FEEDER - 3-500 KCMIL CABLES (UCSD EAST ZONE) 7,014.00 LF $93.00 $652,302 15.00% 15.00% 30.00% $195,691 $847,993
Monday, January 27, 2014 Page 122 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.04.50.04.02 INTERMEDIATE RISER, 1-500 KCMIL CABLE (UCSD EAST ZONE) 990.00 LF $31.00 $30,690 15.00% 15.00% 30.00% $9,207 $39,897
50.04.50.04.03 SPLICE KITS - INSULATED (UCSD EAST ZONE) 22.00 EA $100.00 $2,200 15.00% 15.00% 30.00% $660 $2,860
50.04.50.04.04 LONGITUDINAL CABLE TRAY (UCSD EAST ZONE) 2,158.00 LF $50.00 $107,900 15.00% 15.00% 30.00% $32,370 $140,270
50.04.50.04.05 LATERAL CABLE TRAY (UCSD EAST ZONE) 195.00 LF $50.00 $9,750 15.00% 15.00% 30.00% $2,925 $12,675
Sum
Average
358,945.00 $17,731,838
11.25% 15.00% 26.25%
$4,526,334 $22,258,172Summary for Group: 50.04
Sum
Average
358,945.00 $17,731,838
11.25% 15.00% 26.25%
$4,526,334 $22,258,172Summary for Sub Section: 50.04
Sub Section 50.05 COMMUNICATIONS
Group 50.05.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (TECOLOTE STATION) Contingency
50.05.01.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780
50.05.01.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
50.05.01.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000
50.05.01.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.05.01.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.01.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
50.05.01.106 SMOKE DETECTORS - TC&C ROOM 1.00 EA $200.00 $200 0.00% 15.00% 15.00% $30 $230
50.05.01.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272
50.05.01.108 2" CONDUIT FROM MICRODUCTBANK TO TC&C ROOM 100.00 LF $29.50 $2,950 15.00% 15.00% 30.00% $885 $3,835
50.05.01.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056
50.05.01.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.05.01.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.05.01.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012
50.05.01.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.05.01.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.01.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
50.05.01.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050
50.05.01.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000
50.05.01.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475
Monday, January 27, 2014 Page 123 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.01.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520
50.05.01.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170
50.05.01.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501
50.05.01.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500
50.05.01.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.01.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101
50.05.01.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
50.05.01.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910
50.05.01.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068
50.05.01.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080
50.05.01.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
50.05.01.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195
50.05.01.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940
Sum
Average
7,610.00 $421,759
14.53% 15.00% 29.53%
$126,498 $548,257Summary for Group: 50.05.01
Group 50.05.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (CLAIREMONT STATION) Contingency
50.05.02.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780
50.05.02.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
50.05.02.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000
50.05.02.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.05.02.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.02.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
50.05.02.106 SMOKE DETECTORS - TC&C ROOM 1.00 EA $200.00 $200 0.00% 15.00% 15.00% $30 $230
50.05.02.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272
50.05.02.108 2" CONDUIT FROM MICRODUCTBANK TO TC&C ROOM 100.00 LF $29.50 $2,950 15.00% 15.00% 30.00% $885 $3,835
50.05.02.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056
50.05.02.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.05.02.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.05.02.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012
Monday, January 27, 2014 Page 124 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.02.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.05.02.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.02.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
50.05.02.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050
50.05.02.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000
50.05.02.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475
50.05.02.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520
50.05.02.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170
50.05.02.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501
50.05.02.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500
50.05.02.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.02.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101
50.05.02.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
50.05.02.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910
50.05.02.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068
50.05.02.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080
50.05.02.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
50.05.02.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195
50.05.02.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940
Sum
Average
7,610.00 $421,759
14.53% 15.00% 29.53%
$126,498 $548,257Summary for Group: 50.05.02
Group 50.05.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (BALBOA STATION) Contingency
50.05.03.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780
50.05.03.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
50.05.03.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000
50.05.03.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.05.03.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.03.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
50.05.03.106 SMOKE DETECTORS - TC&C ROOM 1.00 EA $200.00 $200 0.00% 15.00% 15.00% $30 $230
Monday, January 27, 2014 Page 125 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.03.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272
50.05.03.108 2" CONDUIT FROM MICRODUCTBANK TO TC&C ROOM 100.00 LF $29.50 $2,950 15.00% 15.00% 30.00% $885 $3,835
50.05.03.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056
50.05.03.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.05.03.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.05.03.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012
50.05.03.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.05.03.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.03.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
50.05.03.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050
50.05.03.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000
50.05.03.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475
50.05.03.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520
50.05.03.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170
50.05.03.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501
50.05.03.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500
50.05.03.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.03.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101
50.05.03.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
50.05.03.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910
50.05.03.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068
50.05.03.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080
50.05.03.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
50.05.03.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195
50.05.03.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940
Sum
Average
7,610.00 $421,759
14.53% 15.00% 29.53%
$126,498 $548,257Summary for Group: 50.05.03
Group 50.05.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (NOBEL STATION) Contingency
50.05.04.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780
Monday, January 27, 2014 Page 126 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.04.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
50.05.04.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000
50.05.04.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.05.04.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.04.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.04.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
50.05.04.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920
50.05.04.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272
50.05.04.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670
50.05.04.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056
50.05.04.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.05.04.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.05.04.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012
50.05.04.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702
50.05.04.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.05.04.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.04.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
50.05.04.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050
50.05.04.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000
50.05.04.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475
50.05.04.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520
50.05.04.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170
50.05.04.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501
50.05.04.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500
50.05.04.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.04.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101
50.05.04.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
50.05.04.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910
50.05.04.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068
Monday, January 27, 2014 Page 127 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.04.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080
50.05.04.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
50.05.04.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195
50.05.04.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940
50.05.04.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
Sum
Average
7,736.00 $472,149
14.57% 15.00% 29.57%
$141,525 $613,674Summary for Group: 50.05.04
Group 50.05.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (VA MEDICAL CENTER STATION) Contingency
50.05.05.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780
50.05.05.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
50.05.05.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000
50.05.05.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.05.05.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.05.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
50.05.05.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920
50.05.05.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272
50.05.05.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670
50.05.05.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056
50.05.05.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.05.05.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.05.05.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012
50.05.05.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702
50.05.05.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.05.05.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.05.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
50.05.05.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050
50.05.05.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000
50.05.05.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475
50.05.05.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520
Monday, January 27, 2014 Page 128 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.05.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170
50.05.05.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501
50.05.05.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500
50.05.05.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.05.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101
50.05.05.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
50.05.05.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910
50.05.05.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068
50.05.05.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080
50.05.05.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
50.05.05.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195
50.05.05.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940
50.05.05.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
Sum
Average
7,718.00 $465,849
14.56% 15.00% 29.56%
$139,635 $605,484Summary for Group: 50.05.05
Group 50.05.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (UCSD WEST STATION) Contingency
50.05.06.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780
50.05.06.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
50.05.06.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000
50.05.06.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.05.06.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.06.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
50.05.06.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920
50.05.06.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272
50.05.06.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670
50.05.06.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056
50.05.06.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.05.06.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.05.06.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012
Monday, January 27, 2014 Page 129 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.06.113 UNIVERSITY SECURITY BLUE LIGHT STATION 4.00 EA $3,500.00 $14,000 15.00% 15.00% 30.00% $4,200 $18,200
50.05.06.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702
50.05.06.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.05.06.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.06.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
50.05.06.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050
50.05.06.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000
50.05.06.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475
50.05.06.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520
50.05.06.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170
50.05.06.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501
50.05.06.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500
50.05.06.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.06.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101
50.05.06.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
50.05.06.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910
50.05.06.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068
50.05.06.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080
50.05.06.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
50.05.06.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195
50.05.06.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940
50.05.06.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
Sum
Average
7,722.00 $479,849
14.57% 15.00% 29.57%
$143,835 $623,684Summary for Group: 50.05.06
Group 50.05.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (UCSD EAST STATION) Contingency
50.05.07.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780
50.05.07.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
50.05.07.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000
50.05.07.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
Monday, January 27, 2014 Page 130 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.07.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.07.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
50.05.07.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920
50.05.07.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272
50.05.07.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670
50.05.07.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056
50.05.07.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.05.07.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.05.07.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012
50.05.07.113 UNIVERSITY SECURITY BLUE LIGHT STATION 4.00 EA $3,500.00 $14,000 15.00% 15.00% 30.00% $4,200 $18,200
50.05.07.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702
50.05.07.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.05.07.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.07.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
50.05.07.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050
50.05.07.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000
50.05.07.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475
50.05.07.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520
50.05.07.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170
50.05.07.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501
50.05.07.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500
50.05.07.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.07.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101
50.05.07.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
50.05.07.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910
50.05.07.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068
50.05.07.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080
50.05.07.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
50.05.07.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195
Monday, January 27, 2014 Page 131 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.07.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940
50.05.07.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
Sum
Average
7,722.00 $479,849
14.57% 15.00% 29.57%
$143,835 $623,684Summary for Group: 50.05.07
Group 50.05.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (EXECUTIVE STATION) Contingency
50.05.08.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780
50.05.08.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
50.05.08.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000
50.05.08.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.05.08.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.08.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
50.05.08.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920
50.05.08.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272
50.05.08.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670
50.05.08.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056
50.05.08.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.05.08.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.05.08.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012
50.05.08.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702
50.05.08.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.05.08.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.08.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
50.05.08.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050
50.05.08.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000
50.05.08.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475
50.05.08.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520
50.05.08.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170
50.05.08.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501
50.05.08.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500
Monday, January 27, 2014 Page 132 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.08.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.08.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101
50.05.08.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
50.05.08.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910
50.05.08.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068
50.05.08.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080
50.05.08.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
50.05.08.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195
50.05.08.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940
50.05.08.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
Sum
Average
7,718.00 $465,849
14.56% 15.00% 29.56%
$139,635 $605,484Summary for Group: 50.05.08
Group 50.05.09
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (UTC STATION) Contingency
50.05.09.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780
50.05.09.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
50.05.09.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000
50.05.09.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000
50.05.09.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190
50.05.09.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600
50.05.09.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920
50.05.09.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272
50.05.09.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670
50.05.09.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056
50.05.09.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404
50.05.09.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808
50.05.09.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012
50.05.09.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702
50.05.09.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900
50.05.09.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
Monday, January 27, 2014 Page 133 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.09.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
50.05.09.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050
50.05.09.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000
50.05.09.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475
50.05.09.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520
50.05.09.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170
50.05.09.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501
50.05.09.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500
50.05.09.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.09.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101
50.05.09.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850
50.05.09.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910
50.05.09.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068
50.05.09.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080
50.05.09.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560
50.05.09.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195
50.05.09.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940
50.05.09.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000
Sum
Average
7,718.00 $465,849
14.56% 15.00% 29.56%
$139,635 $605,484Summary for Group: 50.05.09
Group 50.05.10
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
COMMUNICATIONS (SUBSTATIONS) Contingency
50.05.10.00.01 MICRO DUCTBANK 43,300.00 LF $4.30 $186,190 15.00% 15.00% 30.00% $55,857 $242,047
50.05.10.00.02 MICRO DUCTBANK - REDUNDANT PATH 43,300.00 LF $4.30 $186,190 15.00% 15.00% 30.00% $55,857 $242,047
50.05.10.00.03 2" CONDUIT (AERIAL STRUCTURE) 21,450.00 LF $25.00 $536,250 15.00% 15.00% 30.00% $160,875 $697,125
50.05.10.00.04 2" CONDUIT (AERIAL STRUCTURE) - REDUNDANT PATH 21,450.00 LF $29.50 $632,775 15.00% 15.00% 30.00% $189,833 $822,608
50.05.10.00.05 144 STRAND BACKBONE SINGLE MODE FIBER 64,750.00 LF $6.50 $420,875 15.00% 15.00% 30.00% $126,263 $547,138
50.05.10.00.06 144 STRAND BACKBONE SINGLE MODE FIBER - REDUNDANT PATH 64,750.00 LF $8.15 $527,713 15.00% 15.00% 30.00% $158,314 $686,026
50.05.10.012.07 2" CONDUIT 500.00 LF $29.50 $14,750 15.00% 15.00% 30.00% $4,425 $19,175
50.05.10.012.08 12 STRAND SINGLE MODE FIBER 500.00 LF $5.00 $2,500 15.00% 15.00% 30.00% $750 $3,250
Monday, January 27, 2014 Page 134 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.10.03.07 2" CONDUIT 940.00 LF $29.50 $27,730 15.00% 15.00% 30.00% $8,319 $36,049
50.05.10.03.08 12 STRAND SINGLE MODE FIBER 940.00 LF $5.00 $4,700 15.00% 15.00% 30.00% $1,410 $6,110
50.05.10.04.07 2" CONDUIT 1,880.00 LF $29.50 $55,460 15.00% 15.00% 30.00% $16,638 $72,098
50.05.10.04.08 12 STRAND SINGLE MODE FIBER 1,880.00 LF $5.00 $9,400 15.00% 15.00% 30.00% $2,820 $12,220
50.05.10.05.07 2" CONDUIT 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670
50.05.10.05.08 12 STRAND SINGLE MODE FIBER 4,090.00 LF $5.00 $20,450 15.00% 15.00% 30.00% $6,135 $26,585
50.05.10.05.09 MICRO DUCTBANK 3,890.00 LF $4.30 $16,727 15.00% 15.00% 30.00% $5,018 $21,745
50.05.10.06.07 2" CONDUIT 210.00 LF $29.50 $6,195 15.00% 15.00% 30.00% $1,859 $8,054
50.05.10.06.08 12 STRAND SINGLE MODE FIBER 210.00 LF $5.00 $1,050 15.00% 15.00% 30.00% $315 $1,365
50.05.10.078.07 2" CONDUIT 50.00 LF $29.50 $1,475 15.00% 15.00% 30.00% $443 $1,918
50.05.10.078.08 12 STRAND SINGLE MODE FIBER 50.00 LF $5.00 $250 15.00% 15.00% 30.00% $75 $325
50.05.10.09.07 2" CONDUIT 50.00 LF $29.50 $1,475 15.00% 15.00% 30.00% $443 $1,918
50.05.10.09.08 12 STRAND SINGLE MODE FIBER 2,750.00 LF $5.00 $13,750 15.00% 15.00% 30.00% $4,125 $17,875
50.05.10.09.09 MICRO DUCTBANK 2,700.00 LF $4.30 $11,610 15.00% 15.00% 30.00% $3,483 $15,093
50.05.10.10.07 2" CONDUIT 50.00 LF $29.50 $1,475 15.00% 15.00% 30.00% $443 $1,918
50.05.10.10.08 12 STRAND SINGLE MODE FIBER 8,370.00 LF $5.00 $41,850 15.00% 15.00% 30.00% $12,555 $54,405
50.05.10.10.09 MICRO DUCTBANK 8,320.00 LF $4.30 $35,776 15.00% 15.00% 30.00% $10,733 $46,509
50.05.10.11.07 2" CONDUIT 2,000.00 LF $29.50 $59,000 15.00% 15.00% 30.00% $17,700 $76,700
50.05.10.11.08 12 STRAND SINGLE MODE FIBER 7,000.00 LF $5.00 $35,000 15.00% 15.00% 30.00% $10,500 $45,500
50.05.10.11.09 MICRO DUCTBANK 5,000.00 LF $4.30 $21,500 15.00% 15.00% 30.00% $6,450 $27,950
50.05.10.12.07 2" CONDUIT 970.00 LF $29.50 $28,615 15.00% 15.00% 30.00% $8,585 $37,200
50.05.10.12.08 12 STRAND SINGLE MODE FIBER 970.00 LF $5.00 $4,850 15.00% 15.00% 30.00% $1,455 $6,305
50.05.10.13.07 2" CONDUIT 480.00 LF $29.50 $14,160 15.00% 15.00% 30.00% $4,248 $18,408
50.05.10.13.08 12 STRAND SINGLE MODE FIBER 480.00 LF $5.00 $2,400 15.00% 15.00% 30.00% $720 $3,120
50.05.10.14.07 2" CONDUIT 720.00 LF $29.50 $21,240 15.00% 15.00% 30.00% $6,372 $27,612
50.05.10.14.08 12 STRAND SINGLE MODE FIBER 720.00 LF $5.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680
50.05.10.15.07 2" CONDUIT 1,000.00 LF $29.50 $29,500 15.00% 15.00% 30.00% $8,850 $38,350
50.05.10.15.08 12 STRAND SINGLE MODE FIBER 1,000.00 LF $5.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500
50.05.10.16.07 2" CONDUIT 690.00 LF $29.50 $20,355 15.00% 15.00% 30.00% $6,107 $26,462
Monday, January 27, 2014 Page 135 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
50.05.10.16.08 12 STRAND SINGLE MODE FIBER 690.00 LF $5.00 $3,450 15.00% 15.00% 30.00% $1,035 $4,485
Sum
Average
318,300.00 $3,011,186
15.00% 15.00% 30.00%
$903,356 $3,914,541Summary for Group: 50.05.10
Sum
Average
387,464.00 $7,105,857
14.60% 15.00% 29.60%
$2,130,947 $9,236,803Summary for Sub Section: 50.05
Sub Section 50.06 FARE COLLECTION SYSTEM AND EQUIPMENT
Group 50.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
FARE COLLECTION SYSTEM AND EQUIPMENT Contingency
50.06.01 TICKET VENDING MACHINES (TVM) 20.00 EA $140,000.00 $2,800,000 15.00% 15.00% 30.00% $840,000 $3,640,000
50.06.02 PAID CARD INTERFACE DEVICES (PCID) 29.00 EA $20,000.00 $580,000 15.00% 15.00% 30.00% $174,000 $754,000
Sum
Average
49.00 $3,380,000
15.00% 15.00% 30.00%
$1,014,000 $4,394,000Summary for Group: 50.06
Sum
Average
49.00 $3,380,000
15.00% 15.00% 30.00%
$1,014,000 $4,394,000Summary for Sub Section: 50.06
Sub Section 50.07 CENTRAL CONTROL
Group 50.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CENTRAL CONTROL Contingency
50.07 CENTRAL CONTROL 1.00 LS $1,000,000.00 $1,000,000 15.00% 15.00% 30.00% $300,000 $1,300,000
Sum
Average
1.00 $1,000,000
15.00% 15.00% 30.00%
$300,000 $1,300,000Summary for Group: 50.07
Sum
Average
1.00 $1,000,000
15.00% 15.00% 30.00%
$300,000 $1,300,000Summary for Sub Section: 50.07
Sub Section 50.08 EXISTING SYSTEM UPDATES (SYSTEM WIDE)
Group 50.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
EXISTING SYSTEM UPDATES (SYSTEM WIDE) Contingency
50.08.01 UPDATES TO COMPUTER SYSTEM AT CENTRAL CONTROL FOR CMS 1.00 LS $200,000.00 $200,000 0.00% 15.00% 15.00% $30,000 $230,000
50.08.02 UPDATES TO MAPS AT EXISTING STATIONS/FACILITIES 1.00 LS $121,500.00 $121,500 15.00% 15.00% 30.00% $36,450 $157,950
50.08.03 UPDATES TO MAPS IN EXISTING FLEET 1.00 LS $1,029,120.00 $1,029,120 15.00% 15.00% 30.00% $308,736 $1,337,856
Sum
Average
3.00 $1,350,620
10.00% 15.00% 25.00%
$375,186 $1,725,806Summary for Group: 50.08
Sum
Average
3.00 $1,350,620
10.00% 15.00% 25.00%
$375,186 $1,725,806Summary for Sub Section: 50.08
Monday, January 27, 2014 Page 136 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
1,153,615.13 $105,958,581
11.77% 13.38% 25.15%
$24,060,331 $130,018,913Summary for Section 50
Section 60 ROW, LAND, EXISTING IMPROVEMENTS
Sub Section 60.01 PURCHASE OR LEASE REAL ESTATE
Group 60.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PURCHASE OR LEASE REAL ESTATE Contingency
60.01 PURCHASE OR LEASE REAL ESTATE 1.00 LS $71,432,073.00 $71,432,073 0.00% 73.11% 73.11% $52,224,425 $123,656,498
Sum
Average
1.00 $71,432,073
0.00% 73.11% 73.11%
$52,224,425 $123,656,498Summary for Group: 60.01
Sum
Average
1.00 $71,432,073
0.00% 73.11% 73.11%
$52,224,425 $123,656,498Summary for Sub Section: 60.01
Sub Section 60.02 RELOCATION OF EXISTIN HOUSEHOLDS AND BUSINESSES
Group 60.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
RELOCATION OF EXISTIN HOUSEHOLDS AND BUSINESSES Contingency
60.02 RELOCATION OF EXISTIN HOUSEHOLDS AND BUSINESSES 1.00 LS $2,000,000.00 $2,000,000 0.00% 15.00% 15.00% $300,000 $2,300,000
Sum
Average
1.00 $2,000,000
0.00% 15.00% 15.00%
$300,000 $2,300,000Summary for Group: 60.02
Sum
Average
1.00 $2,000,000
0.00% 15.00% 15.00%
$300,000 $2,300,000Summary for Sub Section: 60.02
Sub Section 60.03 PRIOR ACQUISITION
Group 60.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PRIOR ACQUISITION Contingency
60.03 PRIOR ACQUISITION 1.00 LS $19,996,580.00 $19,996,580 0.00% 0.00% 0.00% $0 $19,996,580
Sum
Average
1.00 $19,996,580
0.00% 0.00% 0.00%
$0 $19,996,580Summary for Group: 60.03
Sum
Average
1.00 $19,996,580
0.00% 0.00% 0.00%
$0 $19,996,580Summary for Sub Section: 60.03
Sum
Average
3.00 $93,428,653
0.00% 29.37% 29.37%
$52,524,425 $145,953,078Summary for Section 60
Section 70 VEHICLES
Sub Section 70.01 LIGHT RAIL
Group 70.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LIGHT RAIL Contingency
70.01 LIGHT RAIL 36.00 EA $4,090,922.00 $147,273,192 0.00% 5.00% 5.00% $7,363,660 $154,636,852
Monday, January 27, 2014 Page 137 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
36.00 $147,273,192
0.00% 5.00% 5.00%
$7,363,660 $154,636,852Summary for Group: 70.01
Sum
Average
36.00 $147,273,192
0.00% 5.00% 5.00%
$7,363,660 $154,636,852Summary for Sub Section: 70.01
Sub Section 70.07 SPARE PARTS
Group 70.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SPARE PARTS Contingency
70.07 SPARE PARTS 1.00 LS $14,385,600.00 $14,385,600 0.00% 5.00% 5.00% $719,280 $15,104,880
Sum
Average
1.00 $14,385,600
0.00% 5.00% 5.00%
$719,280 $15,104,880Summary for Group: 70.07
Sum
Average
1.00 $14,385,600
0.00% 5.00% 5.00%
$719,280 $15,104,880Summary for Sub Section: 70.07
Sum
Average
37.00 $161,658,792
0.00% 5.00% 5.00%
$8,082,940 $169,741,732Summary for Section 70
Section 80 PROFESSIONAL SERVICES
Sub Section 80.01 PRELIMINARY ENGINEERING
Group 80.01
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PRELIMINARY ENGINEERING Contingency
80.01 PRELIMINARY ENGINEERING 1.00 LS $80,000,000.00 $80,000,000 0.00% 20.00% 20.00% $16,000,000 $96,000,000
Sum
Average
1.00 $80,000,000
0.00% 20.00% 20.00%
$16,000,000 $96,000,000Summary for Group: 80.01
Sum
Average
1.00 $80,000,000
0.00% 20.00% 20.00%
$16,000,000 $96,000,000Summary for Sub Section: 80.01
Sub Section 80.02 FINAL DESIGN
Group 80.02
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
FINAL DESIGN Contingency
80.02 FINAL DESIGN 1.00 LS $35,000,000.00 $35,000,000 0.00% 20.00% 20.00% $7,000,000 $42,000,000
Sum
Average
1.00 $35,000,000
0.00% 20.00% 20.00%
$7,000,000 $42,000,000Summary for Group: 80.02
Sum
Average
1.00 $35,000,000
0.00% 20.00% 20.00%
$7,000,000 $42,000,000Summary for Sub Section: 80.02
Sub Section 80.03 PROJECT MANAGEMENT FOR DESIGN & CONSTRUCTION
Group 80.03
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PROJECT MANAGEMENT FOR DESIGN & CONSTRUCTION Contingency
Monday, January 27, 2014 Page 138 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
80.03 PROJECT MANAGEMENT FOR DESIGN & CONSTRUCTION (5%) 1.00 LS $30,986,370.75 $30,986,371 0.00% 20.00% 20.00% $6,197,274 $37,183,645
Sum
Average
1.00 $30,986,371
0.00% 20.00% 20.00%
$6,197,274 $37,183,645Summary for Group: 80.03
Sum
Average
1.00 $30,986,371
0.00% 20.00% 20.00%
$6,197,274 $37,183,645Summary for Sub Section: 80.03
Sub Section 80.04 CONSTRUCTION ADMINISTRATION AND MANAGEMENT (10%)
Group 80.04
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
CONSTRUCTION ADMINISTRATION AND MANAGEMENT Contingency
80.04 CONSTRUCTION ADMINISTRATION AND MANAGEMENT (10%) 1.00 LS $61,972,741.49 $61,972,741 0.00% 20.00% 20.00% $12,394,548 $74,367,290
Sum
Average
1.00 $61,972,741
0.00% 20.00% 20.00%
$12,394,548 $74,367,290Summary for Group: 80.04
Sum
Average
1.00 $61,972,741
0.00% 20.00% 20.00%
$12,394,548 $74,367,290Summary for Sub Section: 80.04
Sub Section 80.05 PROFESSIONAL LIABILITY & OTHER NON-CONSTRUCTION INSURANCE
Group 80.05
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
PROFESSIONAL LIABILITY & OTHER NON-CONSTRUCTION INSURANCE Contingency
80.05 PROFESSIONAL LIABILITY & OTHER NON-CONSTRUCTION INSURAN 1.00 LS $6,197,274.15 $6,197,274 0.00% 20.00% 20.00% $1,239,455 $7,436,729
Sum
Average
1.00 $6,197,274
0.00% 20.00% 20.00%
$1,239,455 $7,436,729Summary for Group: 80.05
Sum
Average
1.00 $6,197,274
0.00% 20.00% 20.00%
$1,239,455 $7,436,729Summary for Sub Section: 80.05
Sub Section 80.06 LEGAL, PERMITS, REVIEW FEES BY OTHER AGENCIES, CITIES, ETC
Group 80.06
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
LEGAL, PERMITS, REVIEW FEES BY OTHER AGENCIES, CITIES, ETC Contingency
80.06 LEGAL, PERMITS, REVIEW FEES BY OTHER AGENCIES, CITIES, ETC (2 1.00 LS $12,394,548.30 $12,394,548 0.00% 20.00% 20.00% $2,478,910 $14,873,458
Sum
Average
1.00 $12,394,548
0.00% 20.00% 20.00%
$2,478,910 $14,873,458Summary for Group: 80.06
Sum
Average
1.00 $12,394,548
0.00% 20.00% 20.00%
$2,478,910 $14,873,458Summary for Sub Section: 80.06
Sub Section 80.07 SURVEYS, TESTING, INVESTIGATION, INSPECTION
Group 80.07
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
SURVEYS, TESTING, INVESTIGATION, INSPECTION Contingency
80.07 SURVEYS, TESTING, INVESTIGATION, INSPECTION (1%) 1.00 LS $6,197,274.15 $6,197,274 0.00% 20.00% 20.00% $1,239,455 $7,436,729
Monday, January 27, 2014 Page 139 of 140
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
Contingency
Sum
Average
1.00 $6,197,274
0.00% 20.00% 20.00%
$1,239,455 $7,436,729Summary for Group: 80.07
Sum
Average
1.00 $6,197,274
0.00% 20.00% 20.00%
$1,239,455 $7,436,729Summary for Sub Section: 80.07
Sub Section 80.08 STARTUP
Group 80.08
SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)
STARTUP Contingency
80.08 STARTUP (1.5%) 1.00 LS $9,295,911.22 $9,295,911 0.00% 20.00% 20.00% $1,859,182 $11,155,093
Sum
Average
1.00 $9,295,911
0.00% 20.00% 20.00%
$1,859,182 $11,155,093Summary for Group: 80.08
Sum
Average
1.00 $9,295,911
0.00% 20.00% 20.00%
$1,859,182 $11,155,093Summary for Sub Section: 80.08
Sum
Average
8.00 $242,044,120
0.00% 20.00% 20.00%
$48,408,824 $290,452,944Summary for Section 80
47,679,575.07 $1,116,858,980 $243,256,307 $1,360,115,287Grand Total
Monday, January 27, 2014 Page 140 of 140