+ All Categories
Home > Documents > MCCT Capital Cost Methodology and Estimate Report

MCCT Capital Cost Methodology and Estimate Report

Date post: 07-Nov-2021
Category:
Upload: others
View: 8 times
Download: 0 times
Share this document with a friend
204
Prepared by Capital Cost Methodology and Estimate Report August 2014
Transcript
Page 1: MCCT Capital Cost Methodology and Estimate Report

Prepared by

Capital CostMethodology andEstimate Report

August 2014

Page 2: MCCT Capital Cost Methodology and Estimate Report
Page 3: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportAugust 2014

Prepared by:The San Diego Association of Governments (SANDAG)

Page 4: MCCT Capital Cost Methodology and Estimate Report

THIS PAGE INTENTIONALLY LEFT BLANK

Page 5: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportTable of Contents

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TiAugust 2014

Table of Contents

1.0 INTRODUCTION .............................................................................................................. 1-11.1 Purpose of the Report ...................................................................................... 1-11.2 Description of the Mid-Coast Corridor .............................................................. 1-21.3 Description of the Mid-Coast Corridor Transit Project....................................... 1-4

2.0 FEDERAL TRANSIT ADMINISTRATION STANDARD COST CATEGORIES ................................. 2-12.1 Capital Cost Categories ................................................................................... 2-12.2 SCC 10—Guideway and Track Elements......................................................... 2-1

2.2.1 Guideway ............................................................................................. 2-12.2.2 Track .................................................................................................... 2-3

2.3 SCC 20—Stations, Stops, Terminals, and Intermodal ...................................... 2-42.4 SCC 30—Support Facilities: Yards, Shops, and Administration Buildings ........ 2-62.5 SCC 40—Sitework and Special Conditions ...................................................... 2-62.6 SCC 50—Systems ........................................................................................... 2-82.7 SCC 60—Right-of-Way, Land, and Existing Improvements ............................ 2-102.8 SCC 70—Vehicles ......................................................................................... 2-102.9 SCC 80—Professional Services ..................................................................... 2-112.10 SCC 90—Unallocated Contingency ............................................................... 2-112.11 SCC 100—Finance Charges .......................................................................... 2-11

3.0 ESTIMATING METHODOLOGY .......................................................................................... 3-13.1 General Approach ............................................................................................ 3-23.2 Cost Estimating Assumptions........................................................................... 3-23.3 Estimating Procedures ..................................................................................... 3-33.4 Allocated Contingency ..................................................................................... 3-43.5 Organization and Management of Cost Data ................................................... 3-73.6 Cost Estimating Results Format ....................................................................... 3-73.7 Cash Flow and Escalation ................................................................................ 3-83.8 Annualized Cost Factors .................................................................................. 3-93.9 Unit Pricing .................................................................................................... 3-10

4.0 CAPITAL COST ESTIMATE ............................................................................................... 4-1

5.0 ESTIMATE LIMITATIONS .................................................................................................. 5-15.1 Standard Design Criteria .................................................................................. 5-15.2 Scope and Quantity Definition .......................................................................... 5-15.3 Commodity Pricing ........................................................................................... 5-15.4 Unforeseen Challenges.................................................................................... 5-1

6.0 REFERENCES ............................................................................................................ 6-1

List of Appendices

APPENDIX A CAPITAL COST ESTIMATE DETAILED REPORT ....................................... A-1

Page 6: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportTable of Contents

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 2014ii

List of Figures

Figure 1-1. Mid-Coast Corridor ........................................................................................... 1-3Figure 1-2. Refined Build Alternative .................................................................................. 1-5Figure 1-3. Conceptual Plan and Profile of Refined Build Alternative ................................. 1-7

List of Tables

Table 3-1. Approximate Level of Design for Each SCC ..................................................... 3-4Table 3-2. Allocated Contingency Percentages for the Final SEIS/SEIR Cost

Estimate (Refined Build Alternative) ................................................................ 3-6Table 3-3. Annualization Factors ...................................................................................... 3-9Table 3-4. Unit Prices ..................................................................................................... 3-22Table 4-1. Summary of the Capital Cost for the Refined Build Alternative ......................... 4-1Table 4-2. Mid-Coast Capital Cost Estimate – Refined Build Alternative ........................... 4-3

Page 7: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportTable of Contents

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TiiiAugust 2014

Abbreviations

The following acronyms, initialisms, and short forms are used in this report.

BMPs Best Management Practices

Caltrans California Department of Transportation

FTA Federal Transit Administration

I- Interstate

LOSSAN Los Angeles-San Diego-San Luis Obispo Rail Corridor Agency

LRT light rail transit

LRV light rail vehicle

MSE Mechanically stabilized earth

MTDB Metropolitan Transit Development Board

MTS Metropolitan Transit System

MVE LRT Extension Mission Valley East Light Rail Extension

OCS Overhead Catenary System

OTTC Old Town Transit Center

PE preliminary engineering

ROM Rough Order of Magnitude

SANDAG San Diego Association of Governments

SCC Standard Cost Category

SEIS/SEIR Supplemental Environmental Impact Statement and SubsequentEnvironmental Report

TPSS Traction Power Substation

SR State Route

UCSD University of California, San Diego

UTC University Towne Centre

VA Veterans Administration

YOE Year of Expenditure

Page 8: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportTable of Contents

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 2014iv

THIS PAGE INTENTIONALLY LEFT BLANK

Page 9: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-1August 2014

1.0 INTRODUCTIONThe Federal Transit Administration (FTA) and the San Diego Association of Governments(SANDAG) have prepared a Supplemental Environmental Impact Statement andSubsequent Environmental Impact Report (SEIS/SEIR) for the Mid-Coast Corridor TransitProject in San Diego, California. The SEIS/SEIR supplements the following environmentaldocuments: the Mid-Coast Corridor Alternatives Analysis/Draft Environmental ImpactStatement/Draft Environmental Impact Report (Metropolitan Transit Development Board[MTDB], 1995a); the Final Environmental Impact Report for the Mid-Coast Corridor(MTDB, 1995b); and the Mid-Coast Corridor Project Balboa Extension and Nobel DriveCoaster Station Final Environmental Impact Statement (MTDB, 2001). The FTA is servingas lead agency for the SEIS in accordance with the National Environmental Policy Act of1969, and SANDAG is serving as lead agency for the SEIR in accordance with theCalifornia Environmental Quality Act of 1970.

The Final SEIS/SEIR includes an analysis of the affected environment and potential impactson the social, economic, cultural, and natural environment that will result from constructingand operating the alternatives under consideration within the Mid-Coast Corridor. Thealternatives being considered and analyzed for potential impacts include a No-BuildAlternative and a Refined Build Alternative. The No-Build Alternative is the same asdescribed in the Mid-Coast Corridor Transit Project Draft Supplemental EnvironmentalImpact Statement/Subsequent Environmental Impact Report (SANDAG, 2013a).

The Refined Build Alternative is the Mid-Coast Corridor Transit Project, or project, approvedby the SANDAG Board of Directors for evaluation in the Final SEIS/SEIR on November 15,2013. The project consists of extending the existing San Diego Trolley (Trolley) Blue Linefrom the Santa Fe Depot north to the Old Town Transit Center (OTTC), via the existingTrolley tracks, and then north along new tracks to the University Towne Centre (UTC)Transit Center in University City, with nine new stations at Tecolote Road, Clairemont Drive,Balboa Avenue, Nobel Drive, Veterans Administration (VA) Medical Center, University ofCalifornia, San Diego (UCSD) West Campus, UCSD East Campus, Executive Drive, andthe UTC Transit Center.

The Refined Build Alternative generally reflects the Build Alternative with the VA MedicalCenter Station Option evaluated in the Draft SEIS/SEIR; however, it also includes someadditional refinements. Section 2.4 in Chapter 2.0 of the Final SEIS/SEIR provides adetailed description of the Refined Build Alternative. The process of developing therefinements is discussed in Section 2.3 of Chapter 2.0 of the Final SEIS/SEIR, as well as inthe Mid-Coast Corridor Transit Project Final Refined Build Alternative Report (SANDAG,2014e).

1.1 Purpose of the ReportThis report describes the methodology used to determine capital costs associated withthe Refined Build Alternative. It also presents the capital cost estimates developed forthe Refined Build Alternative.

Page 10: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-2

This report is organized into the following chapters:

· Introduction

· FTA Standard Cost Categories

· Estimating Methodology

· Capital Cost Estimate

· Estimate Limitations

· References

1.2 Description of the Mid-Coast CorridorThe Mid-Coast Corridor is the area centering on Interstate (I-) 5 and extending fromDowntown San Diego on the south to University of California, San Diego (UCSD) andUniversity City on the north (Figure 1-1). Located entirely within the City of San Diego,the corridor is bounded by the Pacific Ocean on the west and by I-805 and State Route(SR) 163 on the east. The Mid-Coast Corridor is topographically diverse, with terrainranging from coastal beaches and bays to inland areas containing steep hillsides andnarrow canyons.

The Mid-Coast Corridor is characterized by dense urban centers and an abundance ofregional activity centers and other major trip generators. Dense population andemployment centers currently anchor both the northern and southern ends of the Mid-Coast Corridor. The UCSD campus, the Westfield UTC shopping center, and regionalhospitals are clustered in the north part of the corridor and represent the second mostdense land uses in the county. At the south end of the corridor is the region’s onlyidentified Metropolitan Center—Downtown San Diego—with the region’s densest landuses and high-rise development.

Other major land uses within or immediately adjacent to the corridor (Figure 1-1) include:

· Regional hospitals: Scripps Green Hospital, Scripps Memorial Hospital La Jolla(Scripps Hospital), UCSD Thornton Hospital, VA Medical Center, UCSD MedicalCenter Hillcrest, and Scripps Mercy Hospital

· Major colleges and universities: UCSD, University of San Diego, San Diego MesaCollege, and San Diego City College

· Regional shopping centers: Westfield UTC, Fashion Valley, and Westfield HortonPlaza

· Major parks and visitor attractions: Mission Bay Park, San Diego Zoo, SeaWorldSan Diego, Old Town San Diego State Historic Park, Balboa Park, the GaslampQuarter, San Diego Convention Center, Petco Park, Rose Canyon Open SpacePark, and Marian Bear Memorial Park

· San Diego International Airport

Page 11: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-3August 2014

Figure 1-1. Mid-Coast Corridor

Source: SANDAG, 2012Note: The Trolley lines shown represent the 2010 Trolley operating plan.

Page 12: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-4

1.3 Description of the Mid-Coast Corridor Transit ProjectThe Refined Build Alternative, or project, is described in detail in Section 2.4 in Chapter2.0 of the Final SEIS/SEIR (SANDAG, 2014a). Plan drawings of the project are containedin Final SEIS/FEIR Plan Set (SANDAG, 2014b).

The project will extend the Trolley Blue Line from Santa Fe Depot in Downtown SanDiego to the UTC Transit Center in University City. The project will use the existingTrolley tracks for approximately 3.5 miles, from the Santa Fe Depot to north of the OTTCand south of the San Diego River. The Trolley Blue Line trains will share the existingtracks with the Trolley Green Line trains. The project also will include construction of10.9 miles of new double track that would extend from south of the San Diego River tothe terminus at the UTC Transit Center.

The new extension will follow the Los Angeles—San Diego—San Luis Obispo RailCorridor Agency (LOSSAN) tracks within existing Metropolitan Transit System and Cityof San Diego right-of-way from the Santa Fe Depot to north of the I-5/SR 52 interchange.The alignment will then leave the LOSSAN right-of-way and parallel the east side of theI-5 corridor traveling north partially within Caltrans right-of-way and partially on privateproperty. South of Nobel Drive, the alignment will transition to an aerial structure andcross over to the west side of I-5. From Nobel Drive, the alignment will continue north tothe UCSD West Campus, cross back over to the east side of I-5 and along the southside of Voigt Drive to Genesee Avenue, and continue south in the median of GeneseeAvenue to the UTC Transit Center.

The project includes 9 new stations (4 at grade and 5 elevated); 5 park-and-ride facilitieswith 1,070 parking spaces; 14 new and 2 upgraded traction power substations (TPSS);and 36 new low-floor light rail transit vehicles. No new maintenance facilities areneeded. New stations will be located at Tecolote Road, Clairemont Drive, BalboaAvenue, Nobel Drive, the VA Medical Center, UCSD West, UCSD East, Executive Drive,and the UTC Transit Center.

Figure 1-2 shows the project alignment and station locations under the Refined BuildAlternative, and Figure 1-3 shows the plan and profile along with locations of stationsand TPSSs.

With the extension of the Trolley Blue Line from Santa Fe Depot to UTC Transit Center,continuous service would be provided from the San Ysidro Transit Center at the U.S.–Mexico international border to University City. The service would be provided every 7.5minutes during peak and off-peak periods in 2030.

Page 13: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-5August 2014

Figure 1-2. Refined Build Alternative

Source: SANDAG, 2014

Page 14: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-6

THIS PAGE INTENTIONALLY LEFT BLANK

Page 15: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-7August 2014

Figure 1-3. Conceptual Plan and Profile of Refined Build Alternative

Source: SANDAG, 2013

Page 16: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-8

THIS PAGE INTENTIONALLY LEFT BLANK

Page 17: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T1-9August 2014

Figure 1-3. Conceptual Plan and Profile of Refined Build Alternative (continued)

Source: SANDAG, 2014

Page 18: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 1.0 – Introduction

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20141-10

THIS PAGE INTENTIONALLY LEFT BLANK

Page 19: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-1August 2014

2.0 FEDERAL TRANSIT ADMINISTRATION STANDARD COSTCATEGORIESThe methodology used for generating capital cost estimates will be consistent with theFederal Transit Administration (FTA) guidelines for estimating capital costs. The basisof the FTA guidance is the Standard Cost Categories (SCC), which enables all FTA-funded projects to develop budget baselines that summarize SCCs. This cost structurewill be used for developing capital cost detail and summary sheets, as described below.

2.1 Capital Cost CategoriesIn accordance with the latest version of the FTA’s SCC, the capital cost components ofthe Refined Build Alternative will be classified into the following cost categories:

10 Guideway and Track Elements20 Station, Stops, Terminals, and Intermodal30 Support Facilities: Yards, Shops, and Administration Buildings40 Sitework and Special Conditions50 Systems60 Right-of-Way, Land, and Existing Improvements70 Vehicles80 Professional Services90 Unallocated Contingency100 Finance Charges

The following sections provide brief descriptions of these cost categories and theirconstituent elements.

2.2 SCC 10—Guideway and Track ElementsGuideway and track elements are portions of the transit system that can be assigned costsat a fairly aggregate level with an acceptable level of accuracy. Most commonly, theseelements are linear and can be represented by typical cross sections. Guideway and trackelements are subdivided into a number of subcategories, as described below.

2.2.1 GuidewayThe guideway cost category is comprised of the following subcategories:

10.01 Guideway: At-grade exclusive right-of-way10.02 Guideway: At-grade semi-exclusive (allows cross-traffic) (not used)10.03 Guideway: At-grade in mixed traffic (not used)10.04 Guideway: Aerial structure10.05 Guideway: Built-up fill (not used)10.06 Guideway: Underground cut and cover

Page 20: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-2

10.07 Guideway: Underground tunnel (not used)10.08 Guideway: Retained cut or fill

These cost categories include all construction elements up to the point where trackconstruction typically begins at the top of subballast. The guideway cost estimates arebased on parametric unit cost information specifically developed for each constructiontype. In general, all of the parametric guideway cost estimates provide for the followingconstruction elements, as appropriate:

10.01 At-Grade Construction

· Excavation and embankment· Permanent Best Management Practices (BMPs)· Drainage systems for the guideway· Cross drainage for off-site flow· Open channels paralleling the tracks· Subgrade preparation and base for ballasted track construction· Fencing· Landscape and Irrigation

10. 04 Aerial Structures Construction· Permanent BMPs· Drainage systems for the aerial guideway· Structural excavation and backfill· Foundation support, including piling, drilled piers, etc.· Structural concrete· Steel reinforcement· Catenary poles foundations· Sound walls on bridges· Emergency walkways· Architectural treatment· Stray current monitoring (Bridge)· Hydromodification

10.06 Underground Structures (Cut and Cover) Construction

· Approach U-sections· Structural excavation and backfill (including U-sections)· Structural concrete· Steel reinforcement· Architectural treatment and anti-graffiti coating· Stray current monitoring

Page 21: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-3August 2014

· Water proofing· Water diversion· Permanent BMPs· Drainage systems for the guideway· Temporary Shoring

10.08 Retained Cut or Fill Construction

· Structural excavation and backfill· Guideway excavation and embankment· Pervious Backfill· MSE Wall· Tieback Wall· Structural concrete (retaining wall)· Steel reinforcement (retaining wall)· Concrete Barrier· Permanent BMPs· Drainage systems for the guideway· Subgrade preparation and base for ballasted track construction· Fencing and railings· Sound walls on retaining walls· Architectural treatment and anti-graffiti coating· Stray current monitoring· Landscape and Irrigation

Earthwork quantities are generated from a comparison of existing terrain conditions withproposed subgrade elevations. Sections are evaluated at 50-foot intervals, and showrequirements for guideway excavation and embankments, and structural excavation andbackfill. Retaining wall quantities are generated from the analysis of wall height,thickness, and footing requirements.

2.2.2 TrackThe track cost categories include the running rails, ties, ballast, direct fixation concreteplinth, embedded track, and special track components (turnouts, crossovers, etc.)associated with the type of track construction. The following is a list of the subcategoriesassociated with this cost category:

10.09 Track: Direct fixation10.10 Track: Embedded (not used)10.11 Track: Ballasted10.12 Track: Special (switches and turnouts)10.13 Track: Vibration and noise dampening

Page 22: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-4

The cost of constructing the supporting subgrade, subballast, or concrete supportingstructure normally will be included in the guideway cost categories. The standard railsection for ballasted and direct-fixation track is continuous welded 115RE rail for LRTand 136RE rail for Los Angeles–San Diego–San Luis Obispo Rail Corridor Agency(LOSSAN) tracks. For ballasted track, the unit cost includes rail, rail welding, railfasteners, and rail anchors. For direct fixation track, the concrete ties and ballast arereplaced with rail attached on a second-pour reinforced concrete plinth pad with a directfixation rail fastener. Special trackwork typically includes turnouts, single and doublecrossovers, wyes, pocket tracks, and bumping posts. The costs for special trackworkare applied on a per unit basis at specific locations. The track costs for the storage yardor maintenance shop facility are typically included in Cost Category 30, SupportFacilities. However, for the Mid-Coast Corridor Transit Project, the existing track storageand maintenance facilities are adequate and improvements to the MTS maintenanceyard are not required.

2.3 SCC 20—Stations, Stops, Terminals, and IntermodalStation costs represent the fixed facilities and amenities for transit stations. Thepassenger station cost estimates are based on historical costs of similar facilities. Thestation cost category is comprised of the following subcategories:

20.01 At-grade station20.02 Aerial station20.03 Underground station, stop, shelter, mall, terminal, and platform (not used)20.04 Other stations, landings, and terminals: intermodal, ferry, trolley, etc. (not

used)20.05 Joint development (not used)20.06 Automobile parking multi-story structure20.07 Elevators and escalators

20.01 At-Grade StationsAt-grade stations will have side platforms. Station costs will include the following:

· Station striping (thermoplastic and markers)· Bike locker· Informational kiosk· Screen wall (8 feet high with footing where applicable)· Station plumbing· Station water· Metal panel screen wall· Chain link fence· Excavation and embankment· Permanent BMPs· Drainage

Page 23: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-5August 2014

· Concrete footings, walls, and platform slab· Canopy(ies) including foundation and seating, covering a portion of the

platform· Track paving, architectural surface treatment of platform with pavers and

tactile warning strips· Station furnishings, ornamental fencing and signage· Lighting, electrical, telecommunication, and mechanical allowances· Artwork· Planting and Irrigation

20.02 Aerial StationsAerial stations will have side platforms. Station costs will include the following:

· Stainless steel and glass screen wall· Guard railing—stainless steel with glass panel· Station striping (thermoplastic and markers)· Bike locker· Informational kiosk· Station plumbing· Permanent BMPs· Drainage· Platform pre-cast concrete panels and pedestrian railing· Canopy(ies) covering a portion of the platform· Architectural surface treatment of platform with pavers and tactile warning

strips· Station furnishings and signage· Lighting, electrical, and mechanical allowances· Vertical circulation elements (i.e., stairs or structural elements to support

elevators and escalators. Equipment purchase and installation is includedunder item 20.07)

· Equipment rooms or operator welfare structures· Artwork· Planting and irrigation

20.06 Automobile Parking Multi-story Structure· Excavation and rough grading· Structural excavation and backfill· Foundation support, including piling, drilled piers, etc.· Concrete footings, columns, pier caps, decking and superstructure

Page 24: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-6

· Steel reinforcement· Pedestrian access and protection for parking structures· Lighting, electrical, and mechanical allowances

20.07 Elevators and EscalatorsSingle and double elevators are used for all aerial stations and at parkingstructures. Escalators are not used in this project.

At-grade pedestrian access to transit stations and surface parking lots associated withpassenger stations are accounted for under other cost categories described below.

2.4 SCC 30—Support Facilities: Yards, Shops, and Administration BuildingsThis cost category includes vehicle storage and maintenance buildings, trackwork for thestorage of rail vehicles, vehicle cleaning and painting facilities, office support areas,maintenance-of-way facilities, and general and major shop equipment. The following isa list of the subcategories under this cost category:

30.01 Administration building: office, sales, storage, and revenue counting30.02 Light maintenance facility30.03 Heavy maintenance facility30.04 Storage or maintenance-of-way building30.05 Yard and yard track

For this project, the existing light rail transit (LRT) maintenance and storage facility iscapable of handling a fleet size of 200 light rail vehicles. The present fleet size is 158vehicles. Thirty of these vehicles have completed their design life and are slated to besold, leaving MTS with a fleet of 128 vehicles. The Mid-Coast Coast Corridor TransitProject will add an additional 36 vehicles to that fleet. Therefore, no costs for expansionof the yard will be incurred in this category.

2.5 SCC 40—Sitework and Special ConditionsThe development of a functional transit system often requires that a number of ancillarymitigation requirements, which may or may not be directly related to the transit systemservice, be addressed. These sitework and special conditions often include utilityrelocation, surface parking facilities at stations, station access facilities, and temporaryconstruction improvements and facilities. The sitework and special conditions costcategory is subdivided into the following:

40.01 Demolition, clearing, and fine grading40.02 Site utilities and utility relocation40.03 Hazardous materials, contaminated soil removal/mitigation, and ground

water treatments40.04 Environmental mitigation (e.g., wetlands, historic/archaeological, and parks)40.05 Site structures, including retaining walls and sound walls

Page 25: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-7August 2014

40.06 Pedestrian/bike access and accommodation, including landscaping40.07 Automobile, bus, and van accessways, including roads and parking lots40.08 Temporary facilities and other indirect costs during construction

40.01 Demolition, Clearing, and EarthworkThis cost category includes the project-wide cost of demolition, including thosestructures outside of the track or road bed. This includes, but is not limited to,removal of existing track elements, loading docks and their canopies, and pavedsurfaces. The cost of removal of street elements, such as curb and sidewalk, isincluded in Cost Category 40.07. Cost for abandoning, demolishing, or removingutility features is included in Cost Category 40.02. The cost of abandoning,demolishing, or removing drainage features is included in the various categoriesthat include drainage cost. The cost for removal and relocation of trees, clearingand grubbing, and fine grading also are included in this cost category.

40.02 Utility RelocationThis cost category includes the project-wide cost of utility relocation, includingthose utilities outside of the track or road bed. Generally one of the largest costelements within this cost category is the relocation of existing utilities from withinthe guideway construction envelope. These relocations can include both publicand private utilities, subject to any agreements that may apply to franchisedutilities that exist within public rights-of-way. Preliminary wet utility relocationplans were prepared and used to develop cost estimates. Preparation ofrelocation plans involved site visits, review of probable utilities as shown on Cityof San Diego Geographical Information System database, as-builts, potholing ofcertain existing utilities, and field survey information.

Preliminary dry utility relocation costs were developed based on identification ofpotential conflict locations, site visit, review of as-built plans, and discussions withutility owners. Unit prices were developed either on a linear foot basis or on alump sum basis for each relocation. The relocation cost did not include anyadditional right-of-way that may be required.

The cost associated with relocation of existing LOSSAN tracks has beenincluded in Cost Category 10.

40.03 and 40.04 Hazardous Material and Environmental MitigationAny special hazardous material handling cost such as contaminated soil orground water handling would be included in this category. Sites of concern havebeen identified in the Mid-Coast Corridor Transit Project Hazardous MaterialsTechnical Report (SANDAG, 2014c). Mitigation costs for removal of suchmaterial are project reserves that may or may not be used. Further studies willbe required to determine the extent of required mitigation, if any. The cost ofmitigation for noise and vibration is included under Cost Category 10.

Similarly, environmental mitigation for wetland impacts would also be includedunder this category. Sites of concern have been identified in the Mid-Coast

Page 26: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-8

Corridor Transit Project Biological Resources Technical Report (SANDAG,2014d). This allowance includes funds for purchase of properties to be used aswetlands and for their maintenance until the establishment of the wetlands.

40.05 Site StructuresThis cost category typically includes structures, such as retaining walls, soundwalls, etc., that are outside of the guideway construction envelope. Thesestructures generally are located at stations but are located outside of the platformarea. Structures such as retaining walls for retained cut or fill along the at-gradesections of the guideway and bridges are included in Cost Category 10.

40.06 Pedestrian Access and LandscapingPedestrian access and landscaping information has not been developed fully at thisphase of the project; therefore, average unit costs based on historical experiencehas been used. Landscaping costs associated with parking facilities are included inthe composite costs developed for those particular items and are included in CostCategory 40.07.

40.07 Automobile Accessways and Parking LotsThis cost category includes new and reconstructed roadways, streets, at-gradesurface parking areas, sidewalks, curbs and gutters, and related roadwayfacilities, all associated with the construction of rail guideways. Roadway andparking area cost estimates will be based on unit costs applied to quantitiesdeveloped on location-specific data taken from the Final SEIS/SEIR Plan Set.

40.08 Temporary FacilitiesUnless otherwise specified, this cost category includes costs for mobilization,demobilization, construction vehicles, traffic control, temporary BMPs, security,small tools and equipment, project phasing, temporary construction associatedwith weather, or temporary site access and mitigation. For the current phase ofproject development, some of these costs typically would be included as apercentage allowance mark-up.

2.6 SCC 50—SystemsThis cost category includes the following cost elements:

50.01 Train control and signals50.02 Traffic signals and crossing protection50.03 Traction power supply: substations50.04 Traction power distribution50.05 Communications50.06 Fare collection system and equipment50.07 Central control

Page 27: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-9August 2014

50.01 Train Control and SignalsThis cost category includes the signaling and control systems required for safeand efficient operations of the transit system and chosen technology. It includesautomatic wayside signals and automatic train stop circuitry in the track and onvehicles.

This category also includes the cost of modification to the LOSSAN signalingsystem required as part of relocation of the LOSSAN tracks.

Miscellaneous updates to core systems that include items such as system-wide routemap changes at stations and on the existing fleet are also included in this costcategory.

50.02 Traffic Signals and Crossing ProtectionFor transit systems that are constructed to operate either within existing streets or withat-grade crossings at existing roadways, there is often a need to modify existing trafficsignals or gated crossings or construct new traffic signals or add additional crossingprotection, such as signs and quad gates. This cost category includes the signalingand control systems required for items such as vehicle and pedestrian signals, trafficsignal pre-emption, and protection at all guideway/highway at-grade crossings(flashing lights, bells, and signs).

50.03 Traction Power Supply: SubstationsThe traction power supply system provides the power for all train operations. Thiscost category consists primarily of the civil, structural, and architectural infrastructurealong with the mechanical and electrical equipment needed to construct tractionpower substations (TPSSs). This includes the ductbank and cabling from theTPSSs to the overhead catenary system (OCS) interface and the ductbank andcabling to the substation from the outside electrical utilities source.

50.04 Traction Power DistributionThe traction power distribution system is based on a direct current OCS. The OCSconsists primarily of support poles, OCS foundations for at-grade segments,brackets arms and hardware, feeder cables, contact wire, and a messenger wire.Signal and communication power needs also are included in the traction powercosts. Power supply or distribution requirements for buildings associated with thestorage and maintenance facilities, or power for passenger stations, are not includedin this cost category.

50.05 CommunicationsThe communications system provides the necessary subsystems to support thetotal operational requirements of the transit system and chosen technology. Thecommunications system costs provide for subsystems, such as two-way radios,the public address system, telephone systems, variable message signs,interfaces with the fare collection and ticket vending equipment, and equipment

Page 28: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-10

for the hearing impaired, as well as closed-circuit television. The subsystemsscope includes equipment static testing by the contractor.

50.06 Fare Collection System and EquipmentCosts for elements in this category are based upon a self-service, barrier-free,proof of payment fare collection system. Ticket vending machine costs shall bebased on a microprocessor controlled coin or bill accepting machine capable ofoptionally accepting credit, debit, and stored value cards. The unit cost for farecollection includes all equipment costs, installation costs, and testing costs. Thehardware includes provisions for fare vending facilities, including ticket validatorsand Compass Card readers.

50.07 Central ControlThis cost category includes all civil, structural, architectural, mechanical, electrical, andsystems costs required for the remote monitoring of train operations, track conditions,substations, and station support facilities. The need for an upgraded central controlfacility or expansion of existing facilities is dependent upon the operational analysisand assumptions to be determined for the given transit system and chosentechnology. Per discussions with MTS, the existing facility can handle the addition ofthe Mid-Coast Corridor Transit Project with minimal additional expansion. Costcategory 50.07 provides an allowance for such minor expenses.

2.7 SCC 60—Right-of-Way, Land, and Existing ImprovementsThis cost category covers all land acquisition and acquisition-related costs required toobtain various real property interests required for the construction, operation, andmaintenance of the proposed alignments. Costs include the acquisition of permanentfee, easement and temporary construction easements, relocation costs, businessdamages, professional services related to the acquisitions, and other miscellaneouscosts. Sub-categories include the following:

60.01 Purchase or lease of real estate60.02 Relocation of existing households and businesses

2.8 SCC 70—VehiclesThis cost category is generally subdivided into revenue (identified by transit mode) andnon-revenue vehicles (where non-revenue vehicles include maintenance-of-way vehiclesand agency trucks and automobiles). During this phase of project development, the unitcosts for vehicles typically will include costs for engineering, procurement, spare parts,etc. and is based on current quotes received by the Metropolitan Transit System (MTS)or other transit authorities with similar vehicles. This cost category is subdivided into thefollowing categories:

70.01 Light rail (including streetcar)70.02 Heavy rail (not used)70.03 Commuter rail (not used)

Page 29: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T2-11August 2014

70.04 Bus (not used)70.05 Other (not used)70.06 Non-revenue vehicles (not used)70.07 Spare parts

2.9 SCC 80—Professional ServicesThis cost category includes estimates and allowances for Project Development,Engineering, project and construction management, agency program management,project insurance, surveys and testing, and start-up costs. For Project Development andEngineering, estimates of anticipated costs were developed. For all other categories,allowances are computed by applying a percentage to the total construction costsestimated for each cost category (excluding right-of-way and vehicle costs). Insurancein this category includes the cost of professional liability and other non-constructionrelated insurances. Right-of-way and vehicle costs are typically calculated to include themanagement and administration costs associated with these activities and therefore areexcluded from the calculation of professional services. The following is a list of thepercentage multipliers being applied to the total construction costs to cover these items:

80.01 Project Development 12.9%80.02 Engineering 5.7%80.03 Project Management for Design and Construction 5.0%80.04 Construction Administration and Management 10.0%80.05 Insurance 1.0%80.06 Legal: Permits, Review Fees, Etc. 2.0%80.07 Surveys, Testing, Investigation, and Inspection 1.0%80.08 Start up 1.5%

Total Professional Services Costs 39.1%

2.10 SCC 90—Unallocated ContingencyAn unallocated contingency is intended to cover project risks that cannot reasonably beallocated to specific SCC codes, including change orders during construction (allocatedcontingencies are covered in each of the construction subcategories). It is intended tocover unknowns that cannot be anticipated, but nonetheless are prudent to include forplanning purposes. The unallocated contingency is calculated at 9.5 percent of theconstruction costs, right-of-way, vehicles, and professional services. This would be aproject reserve, a portion of which would be carried into construction to cover changeorders.

2.11 SCC 100—Finance ChargesFinance charges represent interest cost and upfront costs associated with a long-termbond issuance that will be repaid with TransNet revenues. The bond proceeds willprovide funding for the majority of the local share of project funding for Fiscal Year 2012to Fiscal Year 2020 to cover year-of-expenditure dollar costs.

Page 30: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 2.0 – Federal Transit Administration Standard Cost Categories

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20142-12

THIS PAGE INTENTIONALLY LEFT BLANK

Page 31: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-1August 2014

3.0 ESTIMATING METHODOLOGYThe estimating methodology for preparation of the capital cost estimate for the RefinedBuild Alternative for the Final Supplemental Environmental Impact Statement andSubsequent Environmental Impact Report (SEIS/SEIR) has been developed in generalconformance with the Federal Transit Administration (FTA) guidelines for estimatingcapital costs for New Starts projects. The FTA guidelines call for cost estimates to beprepared and reported using the latest version of FTA’s Standard Cost Category (SCC)worksheet. The most current version of the SCC workbook is Revision 15, dated August5, 2013. These cost categories form the basis of the format and structure that will beused for the capital cost detail and summary sheets.

Cost data generally were developed using the most recent and applicable San DiegoAssociation of Governments (SANDAG), California Department of Transportation(Caltrans), and other transit systems’ related bid results in California. Caltrans annuallypublishes a cost database for project bid results for all districts in California, with the SanDiego area located within District 11. For the purposes of the Final SEIS/SEIR estimate,similar items with similar quantities were queried from the Caltrans cost database, whichcompiles cost data from projects throughout the state of California. The average weightedunit price was rounded up to the nearest whole dollar and used in the Final SEIS/SEIRestimate. The unit prices from Caltrans cost data are bid prices that include insurance,markups, tax, profit, overhead, contractor contingencies, and in some cases, as applicableto the item reviewed, time related overhead is added to the unit prices. Depending on theparticulars of the contract document, cost data from SANDAG may or may not includeinsurance costs. Overall, insurance costs for items obtained from SANDAG historicalprices constitute a small percentage of overall project cost and will be well within thecontingency factors provide in the estimate. Cost sources such as the PB transit projectsdatabase, which includes the recent projects in Hawaii, Seattle, and the Bay Area RapidTransit will be footnoted and cited as to the bid date and escalated to 2013 dollars.

For items of work where historical data from these sources were not available or wereunreliable because of the age of such data, data from other transit agencies were used.Adjustments were made to these sources to account for differences between thepublished date of the historical cost data and the current base year of the cost estimates.Escalation factor adjustments were made to these unit price data based on theConstruction Cost Index value, as published in the Engineering News Record. The RSMeans Location Factor also may be considered in adjusting unit costs to reflectconstruction economic conditions within California. Rough Order of Magnitude (ROM)cost was developed for items of work where detailed quantity take off cannot beperformed. The ROM costs constitute an allowance for the particular item of work untilsuch time that the project is further defined. For example, depending on defined scope ofwork, elevators can have a wide fluctuation in actual unit cost. Hence, the dollar amountfor elevators would be an allowance until the specification of each elevator is determined.

Where items of work can be quantified at the current phase of the project, the unit costswill be verified using historical cost data. At the end of the preliminary engineering (PE)phase of the project, a “bottoms up” estimate will be used on most items of work. All unitcosts include the contractor’s direct construction costs, plus all taxes, general expenses,

Page 32: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-2

overhead, and profit. The unit costs for items of construction do not include items such asengineering, construction management, and owner’s administrative costs. These costswill be included as percentage add-ons to the cost estimate under Cost Categories 80 and90. Allowances for contingencies are added separately to each of the cost subcategories.

3.1 General ApproachIn general, the Final SEIS/SEIR Plan Set (SANDAG, 2014b) formed the basis for thequantity take offs and were used to identify the various infrastructure elements that wereused to prepare the capital cost estimates.

As more detailed plans become available during the later stages of project development,additional quantity take offs will be performed to verify and update the ROM unit costs. Theupdated unit costs may include items of work that did not originally appear in the ROM unitcosts.

3.2 Cost Estimating AssumptionsThe basic assumptions and criteria used in developing the cost data are as follows:

· Unit prices are expressed in 4th quarter 2013 dollars.

· No hazardous or contaminated material is present in the subgrade or is contained inbuildings estimated for demolition.

· Unit prices used in the estimate assumes the best price procured from theConstruction Management/General Contractor. Because the majority of unit priceswere obtained from Caltrans database, competitive bidding has been assumed.

· Year-of-expenditure costs were based on inflation factors developed in 2013 and arebased on the target revenue operation date of 2019.

· Unit prices assume that labor costs are based on an eight-hour work day duringnormal working hours using the current general prevailing wage requirementspublished by the State of California Department of Industrial Relations.

· Adequate, experienced craft labor is available.

· Normal productivity rates, as historically experienced, will be used.

· Compatible trade agreements exist in the region.

· No strike impacts will be experienced by the project.

· There are sufficient, experienced contractors available to perform the work.

· The materials required by the scope of work are readily available in sufficientquantities to meet construction schedule requirements.

· Normal San Diego area weather has been considered in the development of theconstruction schedule and costs.

· Existing state-of-the-art construction technology and equipment will be available.

Page 33: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-3August 2014

3.3 Estimating ProceduresTypically, the capital cost estimate is developed using a combination of the stochastic orhistorical and deterministic or “bottom-up” approaches. However, during the currentdevelopment phase of the Mid-Coast Corridor Transit Project where many engineeringdetails still remain to be developed, the historical unit price method is used almostexclusively. As the project continues further into the PE and final design phases, a mixof detailed bottom-up pricing and historical unit pricing will be used.

In the historical method, an order-of-magnitude or composite cost is determined, usuallyderived using data from similar projects. This cost is used directly or converted to somecomponent unit measure (such as dollar per vehicle, dollar per route feet, etc.) andapplied as a unit cost. This method is less detailed than the bottom-up approach and,for certain items, the resulting comparative cost estimates can be sufficiently accurate.As an example, the cost for transit vehicles is generally derived using data from recenttransit agency procurements using similar vehicle types and is based upon a totalprocurement price that is divided by the number of vehicles purchased. Other system-wide elements, such as traction power distribution, also may use historical unit costs.Historical bids for traction power distribution contracts, typically composed of a hundredor more construction elements and unit prices, are used to develop composite unit costson a dollar-per-route-foot basis.

Alternatively, where a large set of historical data is available, and where these unit pricesgenerally fall within a reasonable range, the mean or average of the historical unit pricescan provide acceptable cost estimates. For the case of the Mid-Coast Corridor TransitProject, heavy reliance has been placed on historical unit prices from Caltrans. Thisproject intends to use Caltrans Standard Specification and unit prices for common itemsof work that would be comparable to those that would be obtained by Caltrans.

In the bottom-up approach, major work element costs, as generally defined by typicalsections, are determined by totaling the costs of all component parts. Sufficientengineering data are required to reasonably define the scope of work and quantitiesrepresented by each typical section. Unit prices are developed and combined with theestimated quantities to determine the costs for each major category of work, such asguideway elements, stations, and system elements. The advantage of this approach isthe ability to adjust costs for minor changes to the scope, as well as the higherconfidence level inherent in a bottom-up estimate. The drawback is the level ofengineering and estimating effort required to produce a bottom-up estimate and theadditional time required to adjust the estimate for revisions.

The quantities were derived from conceptual engineering drawings. These drawingshave been developed to various levels of completion. To the extent that design hadadvanced, detailed quantities were developed for each item of work. Earthworkquantities were developed by cross sections cut at 50-foot intervals. Most of thestructural quantities were developed from Advanced Planning Studies and TypeSelection. Most other quantities were developed from conceptual engineering drawings.

Where design had not adequately advanced, unit prices were based on a more broadset of historical prices. Items where the design has not adequately progressed to enable

Page 34: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-4

detailed quantity take-off include features such as environmental mitigation andelevators

Table 3-1 shows the level of plan development for each SCC.

Table 3-1. Approximate Level of Design for Each SCC

Description

Level ofCompletion

(approximatepercentage)

10.01 Guideway: At-grade exclusive right-of-way 40%10.04 Guideway: Aerial structure 20%10.06 Guideway: Underground cut and cover 30%10.08 Guideway: Retained cut or fill 40%10.09 Track: Direct fixation 50%10.11 Track: Ballasted 50%10.12 Track: Special (switches and turnouts) 40%10.13 Track: Vibration and noise dampening 10%20.01 At-grade station, stop, shelter, mall, terminal, and platform 15%20.02 Aerial station, stop, shelter, mall, terminal, and platform 15%20.06 Automobile parking multi-story structure 10%20.07 Elevators and escalators 5%40.01 Demolition, clearing, and earthwork 40%40.02 Site utilities and utility relocation 35%40.03 Hazardous materials, contaminated soil removal/mitigation, and ground water treatments 0% (Allowance)40.04 Environmental mitigation (e.g., wetlands, historic/archaeological, and parks) 0% (Allowance)40.06 Pedestrian/bike access and accommodation, including landscaping 30%40.07 Automobile, bus, and van accessways, including roads and parking lots 30%40.08 Temporary facilities and other indirect costs during construction 10%50.01 Train control and signals 20%50.02 Traffic signals and crossing protection 30%50.03 Traction power supply: Substations 20%50.04 Traction power distribution: Catenary and third rail 20%50.05 Communications 20%50.06 Fare collection system and equipment 5%50.07 Central control 0% (Allowance)

Source: SANDAG, 2014

3.4 Allocated ContingencyAn allocated contingency is typically included in an estimate to address a lack of scopeand quantity definition during the in-progress design stages. This is now a required stepin the preparation of cost estimates in the SCC cost format. In the early stages, anallocated contingency may represent a significant portion of the estimate for anyparticular SCC. As the design progresses and more detailed quantity take-offs can bemade, the allowance is reduced. At 100 percent design completion, the allocated

Page 35: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-5August 2014

contingency, by definition, will be zero. Beyond 100% design, the lack of scope andquantity definition will be addressed by the unallocated contingency.

For the Final SEIS/SEIR estimate, quantity take-offs were possible for most of the itemsof work. However, there still remain items of work that lack adequate definition.Variability in quantities can occur within a single subcategory of the SCC worksheet. Toaccount for this, the methodology for assigning the allocated contingency has beenenhanced to consider the design development for items that are better defined at thisstage, with sound sources for the unit prices, at the same time addressing the lack ofscope definition and inability to measure exact quantities or procure unit prices for itemsthat are still conceptual.

For each item, a quantity contingency is assigned based on the level of confidence inestimating the quantity, as well as the scope definition for that item. For example, theallocated quantity contingency for Special Trackwork is zero percent, as this item issimple to quantify and there is a well-defined scope for this item.

Similarly, a unit cost contingency is assigned based on the level of confidence in thesources used for obtaining the unit prices for each item. Where unit prices could beobtained from the Caltrans cost database, a 10 percent unit cost contingency has beenused. The unit cost has also been compared to other similar projects within the PBTransit database, which validates the level of allocated contingency.

For each SCC subcategory, the allocated contingency is the sum of the contingency forquantities and contingency for unit costs. The weighted average of the contingency forall items in each SCC category is then assigned to the categories in the SCC form. Theamount of allocated contingency will depend upon the complexity of any particular SCC,as well as the stage of engineering completion, but will typically be in the 5 to 30 percentrange. The percentages shown in Table 3-2 are the weighted averages for eachcategory for the Refined Build Alternative.

The light rail transit (LRT) vehicle would be a Siemens low floor, S70 Ultra Short (S70US) light rail vehicle (LRV). The vehicles will be purchased in a fleet of 36, thus offeringeconomies to the overall procurement. The vehicle procurement includes both designand agency costs. The contingency costs are expressed as a percentage of vehiclecapital cost. Vehicle design/procurement and agency costs associated with the vehiclesare included in the unit cost. Since the vehicles are specified, the vehicle contingency isstated at 5 percent and will be added to account for unforeseen costs associated withvehicle fleet procurement.

A contingency factor is applied to the right-of-way costs so that sufficient funds areidentified to secure necessary right-of-way. The following two items are recommendedadditives to the base right-of-way estimate to arrive at a final cost figure:

· For the purchase or lease of real estate, total right-of-way contingency isrecommended at 57.12 percent, which would be applied to the estimated cost of theproject right-of-way. This contingency was developed based on potential damages.

Page 36: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-6

Table 3-2. Allocated Contingency Percentages for the Final SEIS/SEIR Cost Estimate(Refined Build Alternative)

Description

AllocatedContingencyPercentage

10.01 Guideway: At-grade exclusive right-of-way 23.7410.04 Guideway: Aerial structure 24.8610.06 Guideway: Underground cut and cover 23.6810.08 Guideway: Retained cut or fill 20.1810.09 Track: Direct fixation 20.0010.11 Track: Ballasted 20.9010.12 Track: Special (switches and turnouts) 12.5810.13 Track: Vibration and noise dampening 30.0020.01 At-grade station, stop, shelter, mall, terminal, and platform 16.4620.02 Aerial station, stop, shelter, mall, terminal, and platform 22.0220.06 Automobile parking multi-story structure 16.6920.07 Elevators and escalators 11.8240.01 Demolition, clearing, and earthwork 20.9340.02 Site utilities and utility relocation 25.0740.03 Hazardous materials, contaminated soil removal/mitigation, and ground water treatments 30.0040.04 Environmental mitigation (e.g., wetlands, historic/archaeological, and parks) 28.2940.06 Pedestrian/bike access and accommodation, including landscaping 26.4440.07 Automobile, bus, and van accessways, including roads and parking lots 21.7340.08 Temporary facilities and other indirect costs during construction 15.9350.01 Train control and signals 23.5050.02 Traffic signals and crossing protection 25.0050.03 Traction power supply: Substations 18.1150.04 Traction power distribution: Catenary and third rail 25.5350.05 Communications 29.9950.06 Fare collection system and equipment 30.0050.07 Central control 30.0050.08 Existing System Updates 27.7860.01 Purchase or lease of real estate 57.1260.02 Relocation of existing households and businesses 15.0070.01 Light rail vehicles 5.0070.07 Spare Parts 5.0080.01 Preliminary Engineering 20.0080.02 Final Design 20.0080.03 Project Management for Design and Construction 20.0080.04 Construction Administration and Management 20.0080.05 Professional Liability and other Non-Construction Insurance 20.0080.06 Legal, Permits, Review Fees by other agencies, cities etc. 20.0080.07 Surveys, Testing, Investigation, Inspection 20.0080.08 Start up 20.00

Source: SANDAG, 2014

Page 37: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-7August 2014

· For relocation of existing business and households, right-of-way contingency isrecommended at 15 percent. Contingency for damages would not apply to thisscenario.

With the exception of Project Development and Engineering, the cost of professionalservices was developed using standard percentages that are similar to other FTAprojects. For these two items, the cost of professional services were estimated basedon current and anticipated expenditures during these phases of the project.

3.5 Organization and Management of Cost DataThe organization of the capital cost estimates for the Final SEIS/SEIR will follow that ofFTA’s SCC. Within the SCC spreadsheet, a summary of the backup data has beenprovided for each category. Some items of work may appear under more than onecategory. A more detailed supporting calculation for each quantity or cost estimate alsohas been provided.

3.6 Cost Estimating Results FormatThe cost estimate for the Final SEIS/SEIR uses three levels of cost presentation toprovide cost information results in increasing levels of detail. The first level is the SCCform itself, where the cost and contingency for each category are presented. Thesecond level is provided within the SCC spreadsheet, where a detailed list of quantitiesfor each category has been provided. Each item listed has its own quantity, unit price,total cost, and contingency for both quantity and unit price. This second level, with thelist of quantities within the SCC spreadsheet, will enable the user to perform a quickreview and check of the data.

The third level is a more detailed calculation of the quantities provided in the backup datawhere each item listed in the SCC spreadsheet is broken down into its component parts,with the unit prices that was derived from different sources. This third and more detailedestimate enables the users to perform a thorough review of quantities with respect to theplan and profile drawings, typical cross sections, and other details developed for theFinal SEIS/SEIR.

These levels provide an efficient and logical flow of data from the most detailed level to thesummary level. The SCC workbook estimate is the summary level that provides a quickreview of cost per mile or per station. The list of quantities within the SCC workbookprovides an overview of the type of items that has been considered in the development ofthe estimates. In addition, the detailed estimate presents all the component parts fromwhich the estimate was developed. It is at this level that changes to the quantities areaccounted for. The detailed quantity backup also would provide an indication of thepercentage of contingency that should be assigned to the various items of work. The moredetailed estimate would be an indication of the level project definition. Where detailedquantity take-off has been performed and additional scope is not anticipated, the quantitycontingency factors can be reduced.

Page 38: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-8

3.7 Cash Flow and EscalationThe current FTA SCC workbook includes several worksheets that assist in thepreparation of a cash flow projection for the project, as well as the calculation of theyear-of-expenditure value of the total project cost. The cash flow reflects a reasonabledistribution of the incurred project costs for the various Standard Cost Categories inaccordance with the approved Master Project Schedule, dated December 31, 2013.

Once the cash flow projection is developed, the results are placed into the SCC inflationworksheet. Escalation factors for this worksheet are then calculated using the projectedinflation developed at the time of this report.

For each year of capital expenditure activity, the SCC Worksheet allows for a singleescalation rate that is used to convert costs for all items of work from base year dollarsto YOE dollars. However, the Mid-Coast Corridor Transit Project Construction CostEscalation Forecast 2014-2023 report (SANDAG, 2013b) had recommended separateescalation rates for each of SCCs 10—50 (construction activities), SCC 60 (right-of-way), SCC 70 (vehicles), and SCC 80 (professional services). Based on thisrecommendation, a composite escalation rate was calculated for use in the SCCWorksheet. The following steps were taken to develop the composite rate:

· Step 1 – Capital costs were developed in 2013 dollars and spread by year for eachSCC (excluding SCC 100, finance charges).

· Step 2 – Annual escalation rates for SCCs 10—50, SCC 60, SCC 70, and SCC 80from the Construction Cost Escalation Forecast report were applied to base yeardollar costs for those respective categories to convert the costs to YOE dollars.

· Step 3 – An annual escalation rate for SCC 90 (unallocated contingency) wasassumed to be the same as those for SCCs10-50.

· Step 4 – The annual costs (in YOE dollars) for SCCs 10—90 were then summed upto calculate the total annual Project escalated cost (excluding finance charges).

· Step 5 – A composite escalation rate was developed for each year, by dividing thetotal Project escalated cost calculated in Step 4 by the total Project base year dollarcost developed in Step 1.

· Step 6 – The process (Step 1 through 5) was repeated for each year in which capitalcosts are incurred.

As noted in the SCC Workbook, the development of capital cost for each year wasbased on SANDAG’s fiscal year (July 1 through June 30), rather than on calendar year.

The above methodology provided for a composite escalation rate for each year. Theresults where then compared with a constant escalation rate of 3.5% for every year.Whereas the project YOE cost without finance charges were estimated to be$1,687,721, the YOE cost based on a constant 3.5% escalation rate was estimated to be$1,673,801. This estimate is only slightly lower than the variable composite escalationrate developed by the above methodology. For estimating purposes, the variablecomposite escalation rate has been used.

Page 39: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-9August 2014

3.8 Annualized Cost FactorsThe evaluation of the cost effectiveness of the Refined Build Alternative requires that allevaluation measures (capital costs, operating and maintenance costs, non-federalfunding, and user benefits) be expressed in annual terms. Since capital costs areestimated as a total expenditure of constant (base year) dollars, an annual payment willbe computed that is equivalent to what is, in reality, a one-time expenditure of capitalfunds. For each capital cost item, the annualized equivalent will be computed byapplying the following annualization factor:

Annualization Factor = i x (1+ i)n where i = discount rate and (1+i)n – 1 n = economic life

The annualized cost of the line item is the total cost of that line item multiplied by itsannualization factor. The summation of all annualized line-item costs provides theoverall annualized cost for the alternative. Table 3-3 lists the various cost categoriesand their respective economic lifetime and annualization factors. These annualizationfactors have been determined based on a FTA-prescribed 2 percent discount rate.

Table 3-3. Annualization Factors

DescriptionLifetime(Years)

AnnualizationFactor

10.01 Guideway: At-grade exclusive right-of-way 125 0.02210.02 Guideway: At-grade semi-exclusive (allows cross-traffic) 30 0.04510.03 Guideway: At-grade in mixed traffic 20 0.06110.04 Guideway: Aerial structure 80 0.02510.05 Guideway: Built-up fill 80 0.02510.06 Guideway: Underground cut and cover 125 0.02210.07 Guideway: Underground tunnel 125 0.02210.08 Guideway: Retained cut or fill 125 0.02210.09 Track: Direct fixation 30 0.04510.10 Track: Embedded 20 0.06110.11 Track: Ballasted 35 0.04010.12 Track: Special (switches and turnouts) 30 0.04510.13 Track: Vibration and noise dampening 30 0.04520.01 At-grade station, stop, shelter, mall, terminal, and platform 70 0.02720.02 Aerial station, stop, shelter, mall, terminal, and platform 70 0.02720.03 Underground station, stop, shelter, mall, terminal, and platform 125 0.02220.04 Other stations, landings, terminals: Intermodal, ferry, trolley, etc. 70 0.02720.05 Joint development 70 0.02720.06 Automobile parking multi-story structure 50 0.03220.07 Elevators and escalators 30 0.045

Page 40: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-10

Table 3-3. Annualization Factors (continued)

DescriptionLifetime(Years)

AnnualizationFactor

30.01 Administration building: Office, sales, storage, and revenue counting 50 0.03230.02 Light maintenance facility 50 0.03230.03 Heavy maintenance facility 50 0.03230.04 Storage or maintenance-of-way building 50 0.03230.05 Yard and yard track 80 0.02540.01 Demolition, clearing, and earthwork 125 0.02240.02 Site utilities and utility relocation 125 0.02240.03 Hazardous materials, contaminated soil removal/mitigation, and ground

water treatments125 0.022

40.04 Environmental mitigation (e.g., wetlands, historic/archaeological, and parks) 125 0.02240.05 Site structures, including retaining walls and sound walls 80 0.02540.06 Pedestrian/bike access and accommodation, including landscaping 20 0.06140.07 Automobile, bus, and van accessways, including roads and parking lots 20 0.06140.08 Temporary facilities and other indirect costs during construction 100 0.02350.01 Train control and signals 30 0.04550.02 Traffic signals and crossing protection 30 0.04550.03 Traction power supply: Substations 50 0.03250.04 Traction power distribution: Catenary and third rail 30 0.04550.05 Communications 20 0.06150.06 Fare collection system and equipment 25 0.05150.07 Central control 30 0.04560.01 Purchase or lease of real estate 125 0.02260.02 Relocation of existing households and businesses 125 0.02270.01 Light rail 25 0.05170.02 Heavy rail 25 0.05170.03 Commuter rail 25 0.05170.04 Bus 12 0.09570.05 Other 12 0.09570.06 Non-revenue vehicles 12 0.09570.07 Spare parts 12 0.095

Source: FTA, 2014

3.9 Unit PricingIn general, historical unit prices were applied to obtain cost estimates for each line itemor component parts of a line item. All unit prices include the contractor’s constructioncosts, general expenses, overhead, taxes, and profit. As noted in Section 3.0, the unitprices presented in this report are gathered from a variety of sources: the Caltrans costdatabase, published Caltrans bid tabulations, the Parsons Brinckerhoff transit database,and other similar transit projects. Information gathered from Caltrans is annotated towhere cost factors, such as time related overhead and mobilization, were applied or notapplied in the unit prices. If the factors were not applied in the unit prices, then 13 percent

Page 41: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-11August 2014

was added into the unit price. For projects where mobilization was not a separate biditem, 10 percent was deducted from the item unit price. In addition, for unit prices thatwere taken from other regions in California, the RS Means location factor was used toadjust for the San Diego region cost allowance. Other transit projects unit price data thatwere used in this project estimate applied the same methodology of factoring prices intothe San Diego region by using location factors as published in RS Means. These unitprices were also adjusted based on the bid date and the anticipated project duration totheir respective midpoint of construction. A brief discussion of the key unit price for eachitem of work follows.

Above and Below Grade Parking StructureParking structures are proposed at the Nobel Drive Station. Unit prices for above-ground and below-ground parking were obtained from the PB transit database, whereseveral similar parking structures were constructed for other large transit projects. Unitprices were also compared with the RS Mean database and resulted within anacceptable range and allowance. Location factors from the RS Means for labor andmaterial are included in the unit price for the San Diego region. The resulting unit priceof $21,000 per stall for above-ground and $30,000 per stall for below-ground includeslabor and materials with a 15 to 20 percent allowance.

Aerial StructuresThe cost for aerial structures were developed from Advanced Planning Studies (APS)and Type Selection (TS) Memoranda. The foundation type, falsework requirements,straddle bents, construction access, consideration for area geology, fault rupture, andarchitectural treatments are factored into the structure costs. Bridge costs are reportedby their component parts such as steel and concrete.

For pedestrian bridges, where plans were not developed to the levels noted above, aunit price of $400 per square foot was used.

Architectural TreatmentArchitectural treatments would be applied to the exposed face of retaining walls,including MSE walls and aerial bridge columns. Based on a review of the retaining wallsand their locations, certain walls were identified for architectural treatment, and thesurface area of these walls was computed. In addition, it is assumed that approximately25 percent of the facial area of the U-section would receive architectural treatment. TheCaltrans unit price of $40 per square foot is the weighted average from one contract, butthe unit price could vary significantly depending on the complexity and repetitive natureof the architectural treatment. It is expected that the project will adopt approximatelythree architectural themes along the corridor and there will be significant repetitivenessin the type of wall treatment where the walls are visible to the public. Therefore, a unitprice of $14 per square foot has been used. For mechanically stabilized earth (MSE)retaining walls, the cost of standard architectural treatment of $4 per square foot used bythe manufacturer is readily available and is assumed to be used for the Mid-CoastCorridor Transit Project MSE walls.

Page 42: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-12

BallastBallast quantities are generated from typical sections along the at-grade segments of thealignment. Sections have been evaluated at 50-foot intervals. Unit price is developedfrom the PB transit database, primarily from the most recent LA Metro projects thatincluded ballast. A unit price of $53 per cubic yard has been used for construction ofLRT. This is typical of current ballast prices in Southern California.

For temporary relocation of the Los Angeles-San Diego-San Luis Obispo Rail CorridorAgency (LOSSAN) tracks, it was assumed that the neat quantities of ballast estimatedfrom typical sections would not be required and portions of the existing ballast can beutilized. For this temporary relocation, a unit price of $35 per cubic yard has been used.

Bar Reinforcing Steel for Earth Retaining StructuresThe steel reinforcement required for all items of work has been quantified using CaltransStandard Plans based on the design height of the retaining wall. This quantity of steelmay be revised as the design is further developed. The Caltrans cost database containsan extensive set of data on steel reinforcement. For bar reinforcing steel (retaining wall),the weighted average of $1.00 per pound has been used. Steel reinforcement forretaining walls, cut-and-cover, depressed sections, and other minor items of work havebeen estimated at the cost of bar reinforcing steel (retaining wall). Bar reinforcing for theopen channel uses an average weighted unit price of $1.00 per pound due to the natureof long longitudinal bar and minimal fabricated bar needed at that location.

Bumping PostA bumping post (permanent terminal direct fixation) would be required at the northerlyproject terminus, which is at the end of the Genesee viaduct to prevent any accidentalovershooting of the LRT vehicle from the aerial tracks. A project allowance of $20,855per item has been assigned to this item. A bumping post for at-grade track is alsorequired at the end of storage track located south of SR 52.

Cable RailingCable railing would be applied to the top of retaining walls for safety, where onlymaintenance crew will have access. Where pedestrian activity near the top of aretaining wall is expected or where aesthetics are important, handrails or ornamentalrailing will be used. Many Caltrans projects require cable railing, and the weightedaverage from the Caltrans cost database provides a good estimate for this item of work.A unit price of $25 per foot has been used.

Catenary Pole FoundationThe unit pricing for the at-grade catenary pole foundations were based on theapproximate foundation depth and the type of overhead catenary system (OCS)foundation pole. Pricing was obtained from the PB transit database which containspricing from various transit projects. An average unit price of $5,000 was used toaccount for the various types of poles and loadings. The cost of foundation assembly onaerial structures in included in the cost of miscellaneous metal for each of the aerialstructures.

Page 43: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-13August 2014

Catenary SystemCapital cost for the OCS is based on the conceptual scope of OCS items. The costincludes installation of poles, wires, insulators, jumpers, hangers, OCS supports,disconnect switches, and termination and down guys. These items were priced from thePB transit database, which includes pricing from similar transit projects. Minormodification to the catenary system also would be required along the existing line fromSanta Fe Depot to the San Diego River due to the increase in operations through thissegment.

Central ControlIn discussion with the Metropolitan Transit System (MTS), the existing central controlfacility has been designed to accommodate the Mid-Coast extension. However, anallowance of $1.0 million has been used in the current estimate to accommodate anyminor improvements to the existing central control facility. Additionally an allowance of$200,000 was allocated to upgrade the central control computer system.

Chain-Link Fence (Type CL-3 thru CL 7)Chain-link fence would be required throughout the at-grade portion of the alignment.The Caltrans cost database provides a good indication of the probable cost for this itemof work. The unit price varies from $16 per linear foot to $24 per linear foot in the costestimate.

Class 2 Aggregate BaseClass 2 aggregate base would be applied below the ballast for a depth of 6 inches andat various thicknesses for roadway structural sections. The Caltrans cost databaseprovides a reliable estimate for this item of work as many of Caltrans’ projects includeClass 2 aggregate base. The weighted average from the Caltrans cost database is $45per cubic yard.

Clearing and GrubbingClearing and grubbing of the site would include removal of all items from the project sitethat are not paid for elsewhere in the contract. Possible examples of such items wouldbe removal of vegetation, and abandonment of various existing facilities (with theexception of drainage, utilities, and trackwork facilities). Adequate project definition hasnot been developed at this time to quantify all work to be performed under this category.Therefore, an allowance for this work has been used. The amount used for thisallowance was rounded up from that listed in the Caltrans cost database. An allowanceof $4,022 per acre has been used.

Concrete BarrierSeveral types of concrete barrier would be required at various locations along the entirealignment. The Caltrans cost database provides a good indication of the probable costfor this item of work. The unit price from the database varying from $46 per linear foot to$100 per linear foot has been used.

Page 44: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-14

Concrete PlinthConcrete plinth would be required at all direct fixation track locations. The unit cost forthis item was developed by estimating the required size of the plinth and formworkrequired for each plinth. The PB transit database includes plinth concrete from severaltransit projects. A unit cost of $44.10 per cubic foot has been used.

CommunicationCommunication costs include closed-circuit television, the public address system,variable message signs, and Supervisory Control and Data Acquisition at each station.In addition, a fiber optic line would have to be run along the entire alignment. The PBtransit database has provided an average unit price for communications facilities at eachstation. The cost for communication equipment installed in various station locations isestimated to range from $420,000 to $480,000.

Demolish Pedestrian BridgeThe existing pedestrian bridges on Genesee Avenue at the Executive Drive Station andnear La Jolla Village would be demolished as part of the Refined Build Alternative. Theunit price for bridge demolition from the Caltrans cost database was increased to $27per square foot to account for demolition work in a busy business and commercial areas.

DrainageDrainage systems were designed for the at-grade and aerial guideway, at stations, andalong roadways impacted by the project. The scope of work includes modification tocross drainage systems carrying off-site storm flows and an on-site drainage systemconsisting of underdrains and ditches. Although the low point of tracks at the La JollaColony Drive overhead structure falls within the limits of the U-section, the flow line ofthe invert of the structure would be designed to allow for a minimum slope of 0.3 percentto convey the flow to a point outside of the structure. This design would avoid the needfor a pump system within the structure.

Construction of tracks at SR 52 would require construction of a box culvert along RoseCreek. The box culvert is estimated to be approximately 700 feet long by 26 feet wide.The cost of the box culvert was estimated from its component parts of structuralconcrete and bar reinforcing steel.

DuctbankDuctbanks are planned in the vicinity of each substation. The unit price for ductbankswas developed from the estimated amount of concrete required per linear foot ofductbank. The concrete for ductbanks need not be structural concrete, and a limitedamount of formwork would be required to construct the ductbank. A unit cost that variesfrom $112 to $161 per linear foot has been used based on the number and size ofconduits in the cross-section.

ElevatorsElevators will be required at all aerial stations. The estimate used for this item of work isa project allowance until such time that adequate project definition is developed. Prices

Page 45: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-15August 2014

for elevators vary widely depending on the size, number of stops, rise, enclosure, andother features. An allowance of $710,000 per single elevator to $810,000 per doubleelevators has been used for the elevators depending on the height and set configuration.

Environmental MitigationBased on the preliminary limits of environmental mitigation identified in the Mid-CoastCorridor Transit Project Biological Resources Technical Report (SANDAG 2014d),wetland creation and wetland restoration/enhancement are assigned an allowance of$200,000 per acre, with $2 million allocated for the purchase of land. Shading impactsare assigned an allowance of $150,000 with $500,000 for the purchase of land. Otherconstruction-related impacts are assigned an allowance of $150,000. Tree removal andreplacement are also included in this category, with tree removal estimated at $400 to$600 depending on the size of the tree, and tree replacement at $2,000 per tree.

Fare Collection System and EquipmentEach platform would be required to have a ticket vending machine and a Compass Cardvalidator. In addition, some of the aerial stations also may have ticket vending machinesand validators at ground level to encourage riders to purchase tickets prior to enteringthe fare paid zone on the platforms. The cost of the vending machines and ticketvalidators were developed from recent data from MTS. The ticket vending machine unitcost is $140,000 each and includes contractor testing and installation. The ticketvalidators are $20,000 each, which also includes contractor testing and installation. Thecost for the fare collection infrastructure (conduits, pull boxes, and fiber) is included ineach station in 20.01 and 20.02.

Hazardous MaterialsPreliminary sites of concern for hazardous materials have been identified in theMid-Coast Corridor Transit Project Hazardous Materials Technical Report (SANDAG,2014c). An allowance of $4,400,000 for mitigation was developed based on possiblelocations where mitigation could be required rather than a cost per mile.

Hot Mix Asphalt (Type A)The unit price for this item was developed from the Caltrans cost database. Theweighted average for the San Diego region for this item of work is about $90 per ton, butthere is wide fluctuation in prices. A unit price of $102 per ton has been used due tocommodity price fluctuation.

Landscape and IrrigationTransit station site work and street improvement work have discrete items forlandscaping and irrigation. The unit price for this item of work was developed from theCaltrans cost database. The weighted average unit price for the San Diego region forthis item of work is about $4.70 for landscape and $1.40 for irrigation.

MobilizationMobilization is preparatory work that must be performed or costs incurred before startingwork on the various items on the job site. Mobilization is factored at 8.5 percent of the

Page 46: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-16

total construction costs. This allowance is based on an average of mobilizationallowance from various transit projects around the state, as well as those in San Diego.

Mud SlabMud slab would be used at the open channel, cut-and-cover and depressed section andwould be constructed below the bottom of the structure. The intent of the mud slab is toprovide a firm and workable surface for construction of the structure above. The unitprice was taken from the PB Transit database and factored for the San Diego region. Aunit price of $327 per cubic yard has been used.

PartneringThe need and scope for partnering effort have not been determined at this time. A$300,000 allowance is used for possible partnering efforts during the construction phaseof the project.

Pervious Backfill (Retaining Wall)The unit cost for pervious backfill was used to develop the estimate for retaining walls.The unit price was obtained from the Caltrans cost database and a value of $49 percubic yard has been used.

Remove Existing Track and TurnoutThe cost of removing trackwork items were developed from the PB transit database andfactored to San Diego regional cost. .

Earth Retaining Structure—Mechanically Stabilized EarthMSE walls would be required along the Mid-Coast Corridor at locations identified on theMid-Coast Corridor Transit Project Final SEIS/SEIR Plan Set (SANDAG, 2014b). Theunit price for MSE walls was developed from the Caltrans cost database. A unit cost of$72 per square foot has been used, which includes the MSE panel, the structuralbackfill, the straps, the coping, and the leveling pad.

Right-of-WayRight-of-way costs are based on market data research and estimates provided by anappraiser, although an actual appraisal was not performed. At this time, these prices area conservative estimate. The cost includes acquisition of private property interests (feeand easement), relocation costs for businesses and residences displaced by the project,damages to properties, and other administrative costs involved in the acquisition.Residences would not be permanently displaced by the project.

Roadway/Guideway ExcavationRoadway and guideway excavation would be required throughout the at-grade portion ofthe guideway and at at-grade stations. Because of the proximity of the existing activerailroad and the potential impact to construction efficiencies, a premium has been placedon guideway excavation when compared to the Caltrans cost database.. A unit price of$18 per cubic yard has been used for this item of work.

Page 47: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-17August 2014

Roadway excavation will generally be performed in narrow strips, as required forroadway widening and reconstruction. The estimated construction price was increasedto account for constrained construction work areas. A unit price of $28 per cubic yardhas been used for this item of work.

Roadway Improvements and Parking LotsVarious street improvements would be required along the Mid-Coast Corridor given theproximity and impacts of the LRT tracks on existing streets. Street improvement planshave been prepared and used for estimation purposes. Detailed cost breakdowns foreach street have been prepared. In addition, several at-grade parking lots would berequired to serve the parking needs near transit stations. The detailed cost breakdownsfor each street improvement utilized unit prices developed from the Caltrans costdatabase for the San Diego region..

Roadway Improvements (Allowance for Mitigation)Because of the reduced headways from the Santa Fe Depot to the San Diego River andthe additional activation of the crossing gates, it is expected that some roadwayimprovements may be required on streets with at-grade crossings, as well as on streetsparallel to the tracks. These improvements are generally limited to modification tosignalized intersections and minor striping. The exception would be improvements tothe Pacific Highway/Rosecrans/Taylor Street intersection. The allowance noted here isto account for the potential additional improvements that the City of San Diego mayrequire as part of modification to traffic signalized south of Taylor Street. An allowanceof $200,000 has been allocated for minor roadway improvements.

Sound WallsSound walls would be required at two locations along the Mid-Coast Corridor wherenoise impacts would be caused by the project. These are located in the vicinity of the LaPaz Condominiums located east of I-5 and the Sheraton Hotel located west of I-5.These walls are assumed to be of similar design and would have a similar cost persquare foot. A unit price of $35 per square foot (i.e., not requiring footings) and $35 persquare foot (i.e., requiring footings) has been used, which was developed from theCaltrans cost database for the San Diego region.

Special TrackworkThe cost of various special trackwork items were developed from bid results of the PBtransit database and quotes from vendors. Those bid prices were extrapolated to covervarious special trackwork that would be used for this project and were escalated by 15percent to obtain current dollar values. Various unit prices have been used, rangingfrom $133,046 for a No. 14 turnout on ballasted track to $1,119,716 for a No. 20crossing diamond on direct fixation.

Station—At GradeThe Refined Build Alternative alignment has four at-grade stations: the Tecolote Road,Clairemont Drive, Balboa Avenue, and VA Medical Center Stations. The cost of each at-grade station was broken down by the components and included the platform and

Page 48: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-18

furnishings, canopies, architectural treatments, lighting, signage, and landscaping ateach station.

Station—AerialThe project has five aerial stations: the Nobel Drive, UCSD West, UCSD East,Executive Drive, and UTC Transit Center Stations. The cost of each aerial station wasbroken down by the components and included the furnishings, canopies, architecturaltreatments, lighting, and signage at each station. The cost of pedestrian walkways,pedestrian bridges, ramps, elevators, and other station access facilities are included inother items of work, such as Section 40.06 and 40.07. Concrete panels will be locatedbetween the platform edges and would provide a continuous surface between theplatforms. The cost of the concrete panels for the aerial stations is included in the bridgecosts.

Stray Current MonitoringThe intent of stray current monitoring is to detect any leakage of current so problemareas are identified and subsequently corrected. It is not intended to provide protectionagainst stray current. As such, it is imperative that any flow of current in barreinforcement be accurately measured. Measurement of current in bar reinforcementwould require positive electrical connectivity between various bar reinforcement. Toarrive at a unit price for this item of work, assumptions were made regarding bar spacingalong retaining walls, depressed sections, and cut-and-cover sections. The bars werethen assumed to be tack welded in such a way that all bars would be connectedelectrically to a monitoring device. For long structures, such as retaining walls, it wasassumed that monitoring wells would be located at 500-foot spacing. The cut-and-coverand U-section structures were assumed to have one monitoring well. Using theseassumptions, a unit price was developed for this item of work. The average price forstray current protection for all structures is $2.00 per square foot of structure.

Structure Backfill (Retaining Wall)Structural backfill (retaining wall) has been used for retaining walls, cut and cover, anddepressed sections. It is assumed that the quantity of excavated material that isgenerated from the site can be screened and re-used as structural backfill and import ofstructural backfill material would not be required. A unit price of $52 per cubic yard hasbeen used for structural backfill at retaining walls, and $73 per cubic yard has been usedfor cut-and-cover structures and depressed sections.

Structural Concrete (Retaining Wall)The unit cost for structural concrete was used in developing the estimate for retainingwalls and U-sections. The unit price was obtained from the Caltrans cost database anda value of $470 per cubic yard has been used.

Structural Concrete BridgeThe cost for aerial structures was developed from the Advanced Planning Studies andType Selection Memorandums prepared for various bridges. The foundation type,falsework requirements, straddle bents, maintenance of traffic, and architectural

Page 49: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-19August 2014

treatments are factored into the structure costs. Unit prices for the bridge cost itemswere taken from the Caltrans cost database. Whenever possible District 11 (San Diegoarea) was used as a basis for the unit prices. When other districts’ unit prices wereused, a RS Means database location factor was applied to approximate cost to the SanDiego area to account for the regional labor and material differentials. To develop aunified price for all aerial structures, the various estimates for all bridges were evaluatedand an average unit price was developed. An average unit price of $850 per cubic yardfor structural concrete bridge was used. This item has a higher unit price than structuralconcrete (retaining wall), and it is used for the more difficult construction of structures,where falsework is over highways and/or will require work at night.

Structure ExcavationThe Caltrans cost database was used for this item of work. Structural excavation wasused to estimate the cost of structures, including retaining walls, bridges, open channel,cut-and-cover structure, and depressed sections. The unit price obtained from theCaltrans cost database has been rounded to $60 per cubic yard for this project.

SubstationsUp to 16 substations would be required from the Santa Fe Depot to the UTC TransitCenter. Of these, 4 would be located south of Taylor Street and 12 would be locatednorth of Taylor Street. Each substation is estimated to cost approximately $1.5 to $3.3million per substation. The cost was determined by estimating all the civil and electricalimprovements required for construction of each substation site.

Temporary Crash Cushion ModuleTemporary cushion modules would be required whenever construction activities occur inclose proximity to existing roadways at the ends of the temporary railing. The unit pricefrom the Caltrans cost database has been rounded up to $4,000 per array.

Temporary Pavement MarkingTemporary pavement marking would be required during reconstruction of existingroadways or whenever construction activities occur in close proximity to existingroadways. The Caltrans cost database provides a good indication of the probable costof this item of work. A unit price of $3.50 per square foot has been used. The unit priceincludes placement and removal of temporary pavement markings.

Temporary Railing (Type K)Temporary railing (Type K) would be required whenever construction activities occur inclose proximity to existing roadways. The Caltrans cost database provides a goodindication of the probable cost of this item of work. A unit price of $17 per linear foot hasbeen used.

Temporary ShoringTemporary shoring would be required for cut-and-cover and depressed sectionconstruction. The prices from the Caltrans cost database have a wide range for thisitem. Because of the complexity of cut-and-cover and depressed section construction

Page 50: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-20

adjacent to La Jolla Colony Drive and the open channel near SR 52, the maximum bidprice from the cost database was used. A unit price of $70 per square foot has beenassigned.

Temporary Traffic SignalTemporary traffic signals would be required at the Balboa Avenue/Morena Boulevardramp, at the La Jolla Colony Drive/I-5 ramps, and at multiple locations on GeneseeAvenue during construction. These locations will require multi-directional changes to theexisting traffic signals. A project allowance of $150,000 to $300,000 per intersection hasbeen assigned.

Temporary Traffic StripeTemporary striping would be required during reconstruction of existing roadways orwhenever construction activities occur in close proximity to existing roadways. Workwould be done in small segments, and some striping may have to remain in place formore than six months. The removal of the temporary traffic strip is included in the unitprice. Therefore, the unit price from the Caltrans cost database has been increased to$2.50 per linear foot for this item of work.

Track ConstructionTrack construction has been estimated by procurement of material and then by the workrequired to place the tracks. Each component of track structure is estimated separately.These include subballast, ballast, ties, rails, direct fixation fasteners, and finally,placement of the tracks. A separate rail estimate is provided for LRT (115RE rail) andLOSSAN tracks (136RE rail). Also, material prices for standard and high-strength railshave been provided. Track placement is estimated to cost between $85 to $150 pertrack foot. The low range is used for ballasted track and the high range is used for directfixation track.

Track Slab (Structure Concrete approach slab)Track slab would be required at the approach to the San Diego River Bridge to preventany differential track movement. A comparable item from the Caltrans cost database ofapproach slab was used to derive the unit cost for this item. A unit price of $850 percubic yard has been used.

Traffic SignalsBecause of the reduced headways from the Santa Fe Depot to the San Diego River andthe additional activation of the crossing gates, it is expected that some improvementsmay be required on streets adjacent to the existing grade crossings. The traffic signalsat streets parallel to the tracks would be preempted with each crossing gate activation.Modification to the traffic signals at these intersections is expected to cost between$75,000 and $275,000 per location.

Train Control and SignalsCapital costs for train control and signals were based on recent bids on recent SANDAGprojects to rehabilitate existing tracks. These prices were adjusted to account for the

Page 51: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-21August 2014

fact that along 10.9 miles of improvements, there is no current track or revenue service.The cost includes installation along the extension of the system and upgrades to existingfacilities from the Santa Fe Depot to the San Diego River. The cost for this item of workwas broken down into its component parts and separately tabulated.

UtilitiesThe wet utilities—sewer and water—were analyzed to identify impacts from the LRTtracks. The length of relocation, abandonment, and reconstruction of these utilities weredetermined based on the Final SEIS/SEIR Plan Set (SANDAG, 2014b). The cost forutilities also includes the earthwork, trench, sewer/water pipe, appurtenances, fittings,other materials, and rehabilitation of existing pavement.

Preliminary dry utility relocation costs were developed based on identification of potentialconflict locations, site visits, review of as-built plans, and discussions with utility owners.Unit prices were developed either on a linear foot basis, or on a lump sum basis for eachrelocation. The relocation cost did not include any additional right-of-way that may berequired. Relocation of franchise utilities includes relocation of some gas and electrictransmission lines, as well as highly sensitive telephone, cable, and fiber optics lines. Itis anticipated that fiber optics lines belonging to about nine companies could beimpacted by the project. The capital cost estimate for relocation of utilities assumes thatthe full cost of relocation would be borne by SANDAG.

Vehicle CostIn 2010, MTS procured 57 new vehicles at a cost of approximately $3.5 million pervehicle. This cost did not include sales tax, spare parts, and other minor improvements.For this project, a unit cost of $3.7 million was used. With the addition of professionalservices, taxes and other minor improvements, the cost of each vehicle is estimated atapproximately $4.1 million. This cost includes design, bonding, insurance, tools,training, manuals, construction management, testing, and project administration. Thisproject intends to place an order for the opening year for 36 vehicles.

WaterproofingWaterproofing would be required behind the walls of cut-and-cover structures anddepressed sections and select bridges. The Caltrans cost database and the PB transitdatabase each provided only one source for this item of work. A unit prices of $15 persquare foot was used for the bridges on the project and $14 per square foot was usedfor the cut-and-cover structure

Water DiversionDiversion of water around construction activities may be required during the constructionof the La Jolla Colony Drive overhead structure and the Rose Creek open channel.Although such diversion can be accommodated relatively inexpensively, water qualityregulations may require treatment of diverted water. The Caltrans cost databaseindicated that Temporary Active Treatment on its projects averaged about $92,000. Anallowance of $100,000 per depressed/cut-and-cover section has been assumed for thisproject.

Page 52: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-22

A summary of unit costs used to develop the capital cost estimate is shown in Table 3-4.Unit Prices . Detailed quantity take-off and complete unit prices for all items are shownin Appendix A.

Table 3-4. Unit Prices

Item Unit Cost SourceAbove-ground parking Space $21,000 6Aerial structures - Used component parts 1Architectural treatment SF $4 1Ballast CY $53 1Bar reinforcing steel LB $1.00 1Below-ground parking Space $30,000 6Bumping post (DF) EA $20,855 4Cable railing LF $25 1Catenary pole foundations EA $5,000 2/6Catenary System - Used component parts 6Central control LS $1,000,000 4Chain link fence (Type CL-6) LF Varies: $16 to $24 1Class 2 aggregate base CY $45 1Clearing and grubbing Ac $4,022 1Concrete barrier LF Varies: $46 to $100 1Concrete plinth CF $44.10 3/6Communication (Station) LS Varies 3Demolish pedestrian bridge SF $27 1Drainage system LS Varies 3Ductbank LF Varies: $112 to $161 3Elevators EA Varies: $710,00 to

$810,0004

Environmental mitigation LS $6,500,000 4Fare collection system and equipment EA Varies: $20,000 to

$140,0005

Hazardous materials LS $4,400,000 4Hot mix asphalt (Type A) Ton $102 1Landscaping and irrigation SF $6.10 2Mobilization LS 8.5% 4/6Mud slab CY $327 6Ornamental fence LF $72 1Partnering EA $300,0000 6Pervious Backfill (retaining wall) CY $49 1Remove & Salvage Exist Track &Turnout EA Varies: $12,948 to $23,304 6Roadway/Guideway excavation CY $28 / $18 1Right of Way LS Varies 3/4Roadway improvements LS Varies 3/4Roadway improvements (allowance for mitigation) LS $200,000 4/6

Page 53: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T3-23August 2014

Table 3-4. Unit Prices (continued)

Item Unit Cost SourceSound wall SF Varies: $25 to $35 1Special Trackwork EA Varies: $130,000

to1,120,0002/6

Station—at grade LS Varies 3Station—aerial LS Varies 3Stray current monitoring SF $2 6Structure backfill (retaining wall) CY $52 1Structural concrete (retaining wall) CY $470 1Structural concrete (bridge) CY $850 1Structure excavation (retaining wall) CY $60 1Substation (Traction power supply) LS Varies 3/6Temporary crash cushion module EA $4,000 1Temporary pavement marking SF $3.50 1Temporary railing (Type K) LF $17 1Temporary shoring SF $70 1Temporary traffic signal LS Varies: $150,000 to

$300,0004

Temporary traffic stripe LF $2.50 1Track slab CY $850 1Train Control and Signals LS Varies 6Utilities LS Varies 3/5Vehicle EA $4,090,922 5/6Water proofing SF Varies: $14 to $15 1Water Diversion LS $100,000 1

Sources of unit costs:1 – Caltrans cost database2 – Mission Valley East Light Rail Transit Extension Project bid data3 – See Quantities/Unit Cost Workbook4 – Allowance for item of work lacking adequate scope and/or definition5 – SANDAG/MTS6 – Parsons Brinckerhoff transit databaseDF = direct fixation; MSE = mechanically stabilized earth; C&C = cut-and-cover; SF = square foot;CY = cubic yard; RF = route foot; LB = Pound; EA = each; LF = linear foot; Ac = acre; LS = lump sum;TF = track foot

Page 54: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 3.0 – Estimating Methodology

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20143-24

THIS PAGE INTENTIONALLY LEFT BLANK

Page 55: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 4.0 – Capital Cost Estimate

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T4-1August 2014

4.0 CAPITAL COST ESTIMATETable 4-1 summarizes capital costs for the Refined Build Alternative. Table 4-2 showsthe detailed capital cost estimate for the Refined Build Alternative.

Table 4-1. Summary of the Capital Cost for the Refined Build Alternative

Refined Build Alternative$’000

10-50 Construction Subtotal $753,96860 ROW, Land, Existing Improvements $145,95370 Vehicles $169,74280 Professional Services $290,45390 Unallocated Contingency $129,211Subtotal: Base Year (2013) Dollars Total $1,489,326Subtotal: YOE Dollars Total $1,687,721100 Finance Charges-Base Year (2013) $349,269100 Finance Charges-YOE $424,394Base Year (2013) Dollars Total $1,838596YOE Dollars Total $2,112,115

Source: SANDAG, 2014

Page 56: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 4.0 – Capital Cost Estimate

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20144-2

THIS PAGE INTENTIONALLY LEFT BLANK

Page 57: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 4.0 – Capital Cost Estimate

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T4-3August 2014

Table 4-2. Mid-Coast Capital Cost Estimate – Refined Build AlternativeM A I N W O R K S H E E T – R E F I N E D B U I L D A L T E R N A T I V E (Rev.15, August, 2013)

Refined Build Alternative (Final SEIS/SEIR) (Using SANDAG Fiscal Year) Today's Date 1/16/14Mid-Coast Corridor Transit Project, San Diego, California Yr of Base Year $ 2013

Yr of Revenue Ops 2019

Quantity Base YearDollars w/oContingenc

y(X000)

Base YearDollars

AllocatedContingency

(X000)

Base YearDollarsTOTAL(X000)

Base YearDollars Unit Cost

(X000)

Base YearDollars

Percentageof

ConstructionCost

Base YearDollars

Percentageof

TotalProjectCost

YOE DollarsTotal

(X000)

10 GUIDEWAY & TRACK ELEMENTS (route miles) 10.93 270,884 61,189 332,073 $30,382 44% 18% 381,49810.01 Guideway: At-grade exclusive right-of-way 1.71 13,939 3,309 17,248 $10,087 19,81510.02 Guideway: At-grade semi-exclusive (allows cross-traffic) 0 010.03 Guideway: At-grade in mixed traffic 0 010.04 Guideway: Aerial structure 4.04 133,925 33,296 167,221 $41,391 192,11010.05 Guideway: Built-up fill 0 010.06 Guideway: Underground cut & cover 0.04 6,799 1,610 8,409 $210,225 9,66110.07 Guideway: Underground tunnel 0 010.08 Guideway: Retained cut or fill 5.14 55,208 11,140 66,348 $12,908 76,22310.09 Track: Direct fixation 27,768 5,554 33,321 38,28110.10 Track: Embedded 0 010.11 Track: Ballasted 22,206 4,641 26,847 30,84310.12 Track: Special (switches, turnouts) 9,599 1,208 10,807 12,41510.13 Track: Vibration and noise dampening 1,440 432 1,872 2,15120 STATIONS, STOPS, TERMINALS, INTERMODAL (number) 9 87,374 16,607 103,981 $11,553 14% 6% 122,18220.01 At-grade station, stop, shelter, mall, terminal, platform 4 12,539 2,064 14,603 $3,651 17,15920.02 Aerial station, stop, shelter, mall, terminal, platform 5 47,405 10,438 57,843 $11,569 67,96820.03 Underground station, stop, shelter, mall, terminal, platform 0 020.04 Other stations, landings, terminals: Intermodal, ferry, trolley, etc. 0 020.05 Joint development 0 020.06 Automobile parking multi-story structure 17,700 2,955 20,655 24,27020.07 Elevators, escalators 9,730 1,151 10,881 12,78530 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS 10.93 0 0 0 $0 0% 0% 030.01 Administration Building: Office, sales, storage, revenue counting 0 #DIV/0!30.02 Light Maintenance Facility 0 #DIV/0!30.03 Heavy Maintenance Facility 0 #DIV/0!30.04 Storage or Maintenance of Way Building 0 #DIV/0!30.05 Yard and Yard Track 0 #DIV/0!40 SITEWORK & SPECIAL CONDITIONS 10.93 155,511 32,383 187,894 $17,191 25% 10% 214,05840.01 Demolition, Clearing, Earthwork 1,402 294 1,696 1,93240.02 Site Utilities, Utility Relocation 37,105 9,300 46,405 52,86740.03 Haz. mat'l, contam'd soil removal/mitigation, ground water

treatments4,400 1,320 5,720 6,516

40.04 Environmental mitigation, e.g. wetlands, historic/archeologic, parks 9,888 2,797 12,685 14,45240.05 Site structures including retaining walls, sound walls 0 040.06 Pedestrian / bike access and accommodation, landscaping 3,885 1,027 4,912 5,59640.07 Automobile, bus, van accessways including roads, parking lots 32,773 7,122 39,895 45,45040.08 Temporary Facilities and other indirect costs during construction 66,058 10,523 76,581 87,24450 SYSTEMS 10.93 105,959 24,060 130,019 $11,896 17% 7% 151,84750.01 Train control and signals 31,686 7,505 39,192 45,77250.02 Traffic signals and crossing protection 6,145 1,536 7,681 8,97150.03 Traction power supply: substations 38,909 7,047 45,957 53,67250.04 Traction power distribution: catenary and third rail 17,732 4,526 22,258 25,99550.05 Communications 7,106 2,131 9,237 10,78850.06 Fare collection system and equipment 3,380 1,014 4,394 5,13250.07 Central Control 1,000 300 1,300 1,518Construction Subtotal (10 - 50) 10.93 619,727 134,240 753,968 $68,981 100% 41% 869,58460 ROW, LAND, EXISTING IMPROVEMENTS 10.93 93,429 52,524 145,953 $13,353 8% 155,15660.01 Purchase or lease of real estate 91,429 52,224 143,653 152,71160.02 Relocation of existing households and businesses 2,000 300 2,300 2,44570 VEHICLES (number) 36 161,659 8,083 169,742 $4,715 9% 195,70670.01 Light Rail 36 147,273 7,364 154,637 $4,295 178,29170.02 Heavy Rail 0 070.03 Commuter Rail 0 070.04 Bus 0 070.05 Other 0 070.06 Non-revenue vehicles 0 070.07 Spare parts 14,386 719 15,105 17,41580 PROFESSIONAL SERVICES (applies to Cats. 10-50) 10.93 242,044 48,409 290,453 $26,574 39% 16% 319,04580.01 Project Development 80,000 16,000 96,000 105,45080.02 Engineering 35,000 7,000 42,000 46,13480.03 Project Management for Design and Construction 30,986 6,197 37,184 40,84480.04 Construction Administration & Management 61,973 12,395 74,367 81,68880.05 Professional Liability and other Non-Construction Insurance 6,197 1,239 7,437 8,16980.06 Legal; Permits; Review Fees by other agencies, cities, etc. 12,395 2,479 14,873 16,33880.07 Surveys, Testing, Investigation, Inspection 6,197 1,239 7,437 8,16980.08 Start up 9,296 1,859 11,155 12,253Subtotal (10 - 80) 10.93 1,116,859 243,256 1,360,115 $124,439 74% 1,539,49190 UNALLOCATED CONTINGENCY 129,211 7% 148,231Subtotal (10 - 90) 10.93 1,489,326 $136,260 81% 1,687,721100 FINANCE CHARGES 349,269 19% 424,394Total Project Cost (10 - 100) 10.93 1,838,596 $168,216 100% 2,112,115Allocated Contingency as % of Base Yr Dollars w/o Contingency 21.78%Unallocated Contingency as % of Base Yr Dollars w/o Contingency 11.57%Total Contingency as % of Base Yr Dollars w/o Contingency 33.35%Unallocated Contingency as % of Subtotal (10 - 80) 9.50%YOE Construction Cost per Mile (X000) $79,559YOE Total Project Cost per Mile Not Including Vehicles (X000) $175,335YOE Total Project Cost per Mile (X000) $193,240

Page 58: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 4.0 – Capital Cost Estimate

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20144-4

THIS PAGE INTENTIONALLY LEFT BLANK

Page 59: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 5.0 – Estimate Limitations

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T5-1August 2014

5.0 ESTIMATE LIMITATIONSSignificant uncertainties exist during the early stages of design. Uncertainties inherent inthe estimate include project definition, quantities, establishment of design criteria, projectschedule, escalation rates, and unknown items of work that can only be defined as theproject progresses further into design. As the project is further defined and the capitalcost estimate is refined, the project contingencies can be reduced.

5.1 Standard Design CriteriaThe San Diego Association of Governments (SANDAG) Draft Light Rail Transit (LRT)Design Criteria (SANDAG, 2010b), which reflects the attributes of previously completedLRT projects, will be adopted for estimating the Refined Build Alternative. The NorthCounty Transit District and the Southern California Rail Road Authority design criteriawill be followed in estimating costs for the relocation of existing Los Angeles–SanDiego–San Luis Obispo Rail Corridor Agency tracks. Should the Mid-Coast CorridorTransit Project require upgrades to existing facilities, such as modifications to signaling,fare collection, vehicle configuration, and other systems, these costs will be included inthe overall cost of this project.

5.2 Scope and Quantity DefinitionThe confirmation of the project scope by the SANDAG Board of Directors, coupled withthe need to perform additional design to allow precise quantity take offs, will result inchanges to the cost of the project as the design evolves. Issues relating to bridge typeand station design can result in significant swings in estimated costs. Changes in thescope assumptions will be incorporated into the estimate as the engineering progresseswith each iteration documenting the changes made. Although the contingencies areintended to mitigate some of these impacts, cost risks still remain in this regard.

5.3 Commodity PricingOver the past several years, commodities, such as petroleum, concrete, and steel, haveexperienced extreme price fluctuations, both rising and falling based on constructiondemand. This fluctuation has placed an extra burden on grantees as they endeavor toestablish reliable estimates and budget baselines that will reflect contractor bids. TheU.S. economy is slowly recovering from the recession, but prices have remained soft.This may be short-term to the extent that many of these commodities may remainmercurial as the project prepares for construction in the future. Additionally, the SanDiego region has seen a depletion of its active quarries. Should additional quarries beapproved for development in the future, the cost of ballast and aggregates couldfluctuate as a result of variable transportation costs.

5.4 Unforeseen ChallengesPerhaps one of the largest sources of uncertainty is the difficulty associated withanticipating problems that only are uncovered during the later stages of projectdevelopment. Areas that appear to be most susceptible are right-of-way acquisitions,utility relocations, hazardous materials, soil conditions, and bid/market risks.

Page 60: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 5.0 – Estimate Limitations

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20145-2

Over the past several years, many projects have seen substantial variations in bidscompared to engineer estimates. More recently, most project engineer estimates arehigher than contractor bids. Generally, this is the result of extreme competition by morecontractors bidding on fewer projects. To address appropriate project risk, the allocatedcontingency approximates the project risks and aides the estimate as the projectadvances to final design. In addition, prudent contingency levels allocated to theestimate are not designed to address extreme volatility in market conditions.

The estimating methods described in Section 3.0 represent professionally acceptedstandards for preparing capital cost estimates to a level of accuracy that is consistentwith the level of project definition. Accuracy is traditionally expressed as a +/-percentage range around the point estimate that has been produced. The percentagevariance factors are greatest during the early stage of project definition andprogressively decrease as project definition increases. For example, for typical transitprojects, the expected accuracy range of an estimate prepared from final designdocuments is approximately +10/-5 percent. For projects at a level of project definitionfrom 1 to 15 percent complete, the expected accuracy range is approximately +30/-25percent.

One of the primary techniques used to address the uncertainties inherent in theestimating process at this phase of project development is the application of appropriateallocated contingencies. The use and application of allocated contingencies also isdiscussed in Section 3.0. As a project progresses through subsequent phases, the levelof detail in the design will increase and the type, quantity, and location of systemelements can be better estimated. As this occurs, the accuracy of the cost estimates willimprove and the allocated contingency will decrease. Unallocated contingencies willremain the same up to the start of construction and then drawn down through theconstruction phase. In addition, the Federal Transit Administration’s mandated riskassessment process will address both allocated and unallocated contingences and setsminimum guidelines for agencies to follow.

Page 61: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 6.0 – References

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C T6-1August 2014

6.0 REFERENCESCalifornia Department of Transportation (Caltrans), 2013. Caltrans District 8 database,

accessed at: http://sv08data.dot.ca.gov/contractcost/

Metropolitan Transit Development Board (MTDB). 1995a. Mid-Coast CorridorAlternatives Analysis/Draft Environmental Impact Statement/Draft EnvironmentalImpact Report. February 1995.

Metropolitan Transit Development Board (MTDB). 1995b. Final Environmental ImpactReport for the Mid-Coast Corridor. December 1995.

Metropolitan Transit Development Board (MTDB). 2001. Mid-Coast Corridor ProjectBalboa Extension and Nobel Drive Coaster Station Final Environmental ImpactStatement. June 2001.

San Diego Association of Governments (SANDAG), 2010a. Mid-Coast Corridor TransitProject Construction Cost Escalation Forecast 2014-2023.

San Diego Association of Governments (SANDAG), 2010b. Draft Light Rail TransitDesign Criteria. January 2010.

San Diego Association of Governments (SANDAG), 2013a. Mid-Coast Corridor TransitProject Draft Supplemental Environmental Impact Statement/SubsequentEnvironmental Impact Report.

San Diego Association of Governments (SANDAG), 2013b, Mid-Coast Corridor TransitProject Construction Cost Escalation Forecast 2014-2023 Report

San Diego Association of Governments (SANDAG), 2014a. Mid-Coast Corridor TransitProject Final Supplemental Environmental Impact Statement/SubsequentEnvironmental Impact Report.

San Diego Association of Governments (SANDAG), 2014b. Mid-Coast Corridor TransitProject Final SEIS/SEIR Plan Set.

San Diego Association of Governments (SANDAG), 2014c. Mid-Coast Corridor TransitProject Hazardous Materials Technical Report.

San Diego Association of Governments (SANDAG), 2014d. Mid-Coast Corridor TransitProject Biological Resources Technical Report.

San Diego Association of Governments (SANDAG), 2014e. Mid-Coast Corridor TransitProject Final Refined Build Alternative Report.

Page 62: MCCT Capital Cost Methodology and Estimate Report

Capital Cost Methodology and Estimate ReportChapter 6.0 – References

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 20146-2

THIS PAGE INTENTIONALLY LEFT BLANK

Page 63: MCCT Capital Cost Methodology and Estimate Report

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 2014

Appendix ACapital Cost Estimate

Detailed Report

Page 64: MCCT Capital Cost Methodology and Estimate Report

M I D - C O A S T C O R R I D O R T R A N S I T P R O J E C TAugust 2014

THIS PAGE INTENTIONALLY LEFT BLANK

Page 65: MCCT Capital Cost Methodology and Estimate Report

Mid-coast Corridor Transit ProjectCapitol Cost Estimate - Item DetailSan Diego Association of Governments (SANDAG)San Diego, California

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Section 10 GUIDEWAY AND TRACK ELEMENTS

Sub Section 10.01 GUIDEWAY: AT-GRADE EXCLUSIVE RIGHT-OF-WAY

Group 10.01.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GUIDEWAY EXCAVATION Contingency

10.01.01 GUIDEWAY EXCAVATION 13,937.00 CY $18.00 $250,866 10.00% 5.00% 15.00% $37,630 $288,496

10.01.01.190101 GUIDEWAY EXCAVATION 8,470.00 CY $18.00 $152,460 10.00% 5.00% 15.00% $22,869 $175,329

10.01.01.190101 GUIDEWAY EXCAVATION 44.00 CY $18.00 $792 10.00% 5.00% 15.00% $119 $911

10.01.01.190101 GUIDEWAY EXCAVATION 15,260.00 CY $18.00 $274,680 10.00% 5.00% 15.00% $41,202 $315,882

Sum

Average

37,711.00 $678,798

10.00% 5.00% 15.00%

$101,820 $780,618Summary for Group: 10.01.01

Group 10.01.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PERMANENT BMP (AT-GRADE GUIDEWAY) Contingency

10.01.02 PERMANENT BMP (AT-GRADE GUIDEWAY) 1.00 LS $350,000.00 $350,000 0.00% 20.00% 20.00% $70,000 $420,000

Sum

Average

1.00 $350,000

0.00% 20.00% 20.00%

$70,000 $420,000Summary for Group: 10.01.02

Group 10.01.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GUIDEWAY DRAINAGE SYSTEMS Contingency

10.01.03.01 UNDERDRAIN (GUIDEWAY) 12,280.00 LF $30.00 $368,400 15.00% 15.00% 30.00% $110,520 $478,920

10.01.03.01 UNDERDRAIN (GUIDEWAY) 2,475.00 LF $30.00 $74,250 15.00% 15.00% 30.00% $22,275 $96,525

10.01.03.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 765.00 LF $27.00 $20,655 15.00% 15.00% 30.00% $6,197 $26,852

10.01.03.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 9,955.00 LF $27.00 $268,785 15.00% 15.00% 30.00% $80,636 $349,421

10.01.03.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 1,875.00 LF $27.00 $50,625 15.00% 15.00% 30.00% $15,188 $65,813

10.01.03.101 18" RCP STORM DRAIN 20.00 LF $120.00 $2,400 15.00% 15.00% 30.00% $720 $3,120

10.01.03.101 18" RCP STORM DRAIN 45.00 LF $120.00 $5,400 15.00% 15.00% 30.00% $1,620 $7,020

10.01.03.101 18" RCP STORM DRAIN 55.00 LF $120.00 $6,600 15.00% 15.00% 30.00% $1,980 $8,580

10.01.03.101 18" RCP STORM DRAIN 65.00 LF $120.00 $7,800 15.00% 15.00% 30.00% $2,340 $10,140

10.01.03.101 18" RCP STORM DRAIN 140.00 LF $120.00 $16,800 15.00% 15.00% 30.00% $5,040 $21,840

Monday, January 27, 2014 Page 1 of 140

Page 66: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.01.03.101 18" RCP STORM DRAIN 30.00 LF $120.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680

10.01.03.101 18" RCP STORM DRAIN 35.00 LF $120.00 $4,200 15.00% 15.00% 30.00% $1,260 $5,460

10.01.03.101 18" RCP STORM DRAIN 35.00 LF $120.00 $4,200 15.00% 15.00% 30.00% $1,260 $5,460

10.01.03.101 18" RCP STORM DRAIN 15.00 LF $120.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.01.03.102 24" RCP STORM DRAIN 35.00 LF $170.00 $5,950 15.00% 15.00% 30.00% $1,785 $7,735

10.01.03.102 24" RCP STORM DRAIN 30.00 LF $170.00 $5,100 10.00% 15.00% 25.00% $1,275 $6,375

10.01.03.102 24" RCP STORM DRAIN 85.00 LF $170.00 $14,450 15.00% 15.00% 30.00% $4,335 $18,785

10.01.03.102 24" RCP STORM DRAIN 360.00 LF $170.00 $61,200 15.00% 15.00% 30.00% $18,360 $79,560

10.01.03.102 24" RCP STORM DRAIN 90.00 LF $170.00 $15,300 15.00% 15.00% 30.00% $4,590 $19,890

10.01.03.103 30" RCP STORM DRAIN 30.00 LF $210.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

10.01.03.103 30" RCP STORM DRAIN 30.00 LF $210.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

10.01.03.104 36" RCP STORM DRAIN 45.00 LF $230.00 $10,350 15.00% 15.00% 30.00% $3,105 $13,455

10.01.03.104 36" RCP STORM DRAIN 30.00 LF $230.00 $6,900 15.00% 15.00% 30.00% $2,070 $8,970

10.01.03.104 36" RCP STORM DRAIN 70.00 LF $230.00 $16,100 15.00% 15.00% 30.00% $4,830 $20,930

10.01.03.104 36" RCP STORM DRAIN 35.00 LF $230.00 $8,050 15.00% 15.00% 30.00% $2,415 $10,465

10.01.03.105 42" RCP STORM DRAIN 30.00 LF $260.00 $7,800 15.00% 15.00% 30.00% $2,340 $10,140

10.01.03.106 48" RCP STORM DRAIN 35.00 LF $290.00 $10,150 15.00% 15.00% 30.00% $3,045 $13,195

10.01.03.106 48" RCP STORM DRAIN 30.00 LF $290.00 $8,700 15.00% 15.00% 30.00% $2,610 $11,310

10.01.03.106 48" RCP STORM DRAIN 60.00 LF $290.00 $17,400 15.00% 15.00% 30.00% $5,220 $22,620

10.01.03.106 48" RCP STORM DRAIN 30.00 LF $290.00 $8,700 15.00% 15.00% 30.00% $2,610 $11,310

10.01.03.106 48" RCP STORM DRAIN 10.00 LF $290.00 $2,900 15.00% 15.00% 30.00% $870 $3,770

10.01.03.115 12" PVC STORM DRAIN 20.00 LF $100.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

10.01.03.131 6' X 4' RCB STORM DRAIN 30.00 LF $1,027.00 $30,810 15.00% 15.00% 30.00% $9,243 $40,053

10.01.03.132 6' X 6' RCB STORM DRAIN 75.00 LF $1,270.00 $95,250 15.00% 15.00% 30.00% $28,575 $123,825

10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

Monday, January 27, 2014 Page 2 of 140

Page 67: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.01.03.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.01.03.204 TYPE B CURB INLET 1.00 EA $5,200.00 $5,200 10.00% 15.00% 25.00% $1,300 $6,500

10.01.03.204 10' MOD TYPE B-1 CURB INLET 1.00 EA $6,900.00 $6,900 15.00% 15.00% 30.00% $2,070 $8,970

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.01.03.206 TYPE G CATCH BASIN 1.00 EA $6,750.00 $6,750 10.00% 15.00% 25.00% $1,688 $8,438

10.01.03.206 MOD TYPE G CATCH BASIN 1.00 EA $6,750.00 $6,750 10.00% 15.00% 25.00% $1,688 $8,438

10.01.03.210 TYPE A STRAIGHT HEADWALL 1.00 EA $7,000.00 $7,000 10.00% 15.00% 25.00% $1,750 $8,750

10.01.03.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250

10.01.03.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250

10.01.03.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250

10.01.03.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250

10.01.03.214 CULVERT INLET (SPECIAL DETAIL) 1.00 EA $4,130.00 $4,130 0.00% 15.00% 15.00% $620 $4,750

Monday, January 27, 2014 Page 3 of 140

Page 68: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.01.03.214 CULVERT INLET (SPECIAL DETAIL) 1.00 EA $4,130.00 $4,130 0.00% 15.00% 15.00% $620 $4,750

10.01.03.216 CURTAIN WALL 1.00 EA $10,650.00 $10,650 15.00% 15.00% 30.00% $3,195 $13,845

10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.01.03.502 PIPE COLLAR 2.00 EA $1,800.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680

10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.01.03.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.01.03.503 PIPE TO CHANNEL TRANSITION 1.00 EA $6,230.00 $6,230 15.00% 15.00% 30.00% $1,869 $8,099

10.01.03.512 CULVERT EXTENSION JOINT, SDRSD D-81 (CY OF CONC) 0.65 CY $400.00 $260 15.00% 15.00% 30.00% $78 $338

10.01.03.700 ABN EXIST 18" ACP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878

10.01.03.700 ABN EXIST 8" PVC STORM DRAIN 3.00 EA $675.00 $2,025 15.00% 15.00% 30.00% $608 $2,633

10.01.03.701 ABN EXIST CATCH BASIN 1.00 EA $1,240.00 $1,240 15.00% 15.00% 30.00% $372 $1,612

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236

10.01.03.702 REMOVE EXIST DROP INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST CURB INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379

10.01.03.702 REMOVE EXIST ENDWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 3.00 EA $860.00 $2,580 15.00% 15.00% 30.00% $774 $3,354

10.01.03.702 REMOVE EXIST ENDWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST CURB INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

Monday, January 27, 2014 Page 4 of 140

Page 69: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST ENDWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST ENDWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236

10.01.03.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.01.03.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236

Sum

Average

29,028.65 $1,470,165

12.76% 15.00% 27.76%

$422,737 $1,892,902Summary for Group: 10.01.03

Group 10.01.03.800

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LA JOLLA RCB Contingency

10.01.03.800.192025 STRUCTURE EXCAVATION (CULVERT) 780.00 CY $60.00 $46,800 15.00% 10.00% 25.00% $11,700 $58,500

10.01.03.800.193004 STRUCTURAL BACKFILL (CULVERT) 448.00 CY $73.00 $32,704 15.00% 10.00% 25.00% $8,176 $40,880

10.01.03.800.510090 STRUCTURAL CONCRETE (CULVERT) 245.00 CY $620.00 $151,900 15.00% 10.00% 25.00% $37,975 $189,875

10.01.03.800.518002 3" MUD SLAB (CULVERT) 18.00 CY $327.00 $5,886 15.00% 10.00% 25.00% $1,472 $7,358

10.01.03.800.518002 WATER DIVERSION 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000

10.01.03.800.520107 BAR REINFORCING STEEL (CULVERT) 49,100.00 LB $1.00 $49,100 15.00% 10.00% 25.00% $12,275 $61,375

10.01.03.800.520122 STRAY CURRENT PROTECTION (CULVERT) 1,827.00 SF $2.00 $3,654 15.00% 10.00% 25.00% $914 $4,568

10.01.03.800.838521 CABLE RAILING 56.00 LF $25.00 $1,400 10.00% 10.00% 20.00% $280 $1,680

Sum

Average

52,475.00 $391,444

14.38% 10.00% 24.38%

$97,791 $489,235Summary for Group: 10.01.03.800

Group 10.01.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROSE CREEK OPEN CHANNEL Contingency

10.01.04.1000095 CONCRETE (RIPRAP BASIN - OPEN CHANNEL) 200.00 CY $544.00 $108,800 15.00% 10.00% 25.00% $27,200 $136,000

10.01.04.192025 STRUCTURE EXCAVATION (OPEN CHANNEL) 16,034.00 CY $60.00 $962,040 15.00% 10.00% 25.00% $240,510 $1,202,550

10.01.04.193004 STRUCTURAL BACKFILL (OPEN CHANNEL) 8,041.00 CY $73.00 $586,993 15.00% 10.00% 25.00% $146,748 $733,741

10.01.04.480600 TEMPORARY SHORING (OPEN CHANNEL) 22,190.00 SF $70.00 $1,553,300 15.00% 10.00% 25.00% $388,325 $1,941,625

10.01.04.490604 30" CIDH CONCRETE PILING 1,714.00 LF $370.00 $634,180 15.00% 10.00% 25.00% $158,545 $792,725

10.01.04.510090 STRUCTURAL CONCRETE (OPEN CHANNEL) 6,052.00 CY $620.00 $3,752,240 15.00% 10.00% 25.00% $938,060 $4,690,300

10.01.04.518002 WATER DIVERSION 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000

Monday, January 27, 2014 Page 5 of 140

Page 70: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.01.04.518002 3" MUD SLAB (OPEN CHANNEL) 229.00 CY $327.00 $74,883 15.00% 10.00% 25.00% $18,721 $93,604

10.01.04.520107 BAR REINFORCING STEEL (OPEN CHANNEL) 1,206,000.00 LB $1.00 $1,206,000 15.00% 10.00% 25.00% $301,500 $1,507,500

10.01.04.520122 STRAY CURRENT PROTECTION (OPEN CHANNEL) 21,745.00 SF $2.00 $43,490 15.00% 10.00% 25.00% $10,873 $54,363

10.01.04.838521 CABLE RAILING 1,373.00 LF $25.00 $34,325 10.00% 10.00% 20.00% $6,865 $41,190

Sum

Average

1,283,579.00 $9,056,251

14.55% 10.00% 24.55%

$2,262,347 $11,318,598Summary for Group: 10.01.04

Group 10.01.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBBALLAST Contingency

10.01.08 SUBBALLAST (LOSSAN) 3,576.00 CY $45.00 $160,920 10.00% 5.00% 15.00% $24,138 $185,058

10.01.08 SUBBALLAST 20,050.00 CY $45.00 $902,250 10.00% 5.00% 15.00% $135,338 $1,037,588

10.01.08 SUBBALLAST (SHOOFLY) 3,322.00 CY $45.00 $149,490 10.00% 5.00% 15.00% $22,424 $171,914

Sum

Average

26,948.00 $1,212,660

10.00% 5.00% 15.00%

$181,899 $1,394,559Summary for Group: 10.01.08

Group 10.01.11

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CHAIN LINK FENCE Contingency

10.01.11.01 CHAIN LINK FENCE (CL-6) 7,316.70 LF $19.00 $139,017 10.00% 10.00% 20.00% $27,803 $166,821

10.01.11.01 CHAIN LINK FENCE (CL-6) 13,486.50 LF $19.00 $256,244 10.00% 10.00% 20.00% $51,249 $307,492

10.01.11.01 CHAIN LINK FENCE (CL-6) 10,897.80 LF $19.00 $207,058 10.00% 10.00% 20.00% $41,412 $248,470

10.01.11.02 6 FT CL GATE 2.00 EA $2,225.00 $4,450 10.00% 10.00% 20.00% $890 $5,340

10.01.11.02 6 FT CL GATE 1.00 EA $2,225.00 $2,225 10.00% 10.00% 20.00% $445 $2,670

10.01.11.02 6 FT CL GATE 4.00 EA $2,225.00 $8,900 10.00% 10.00% 20.00% $1,780 $10,680

Sum

Average

31,708.00 $617,894

10.00% 10.00% 20.00%

$123,579 $741,473Summary for Group: 10.01.11

Group 10.01.14

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GUIDEWAY EMBANKMENT Contingency

10.01.14.193001 GUIDEWAY EMBANKMENT SEGMENT 1 25,424.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

10.01.14.193001 GUIDEWAY EMBANKMENT SEGMENT 3 11,218.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

10.01.14.193001 GUIDEWAY EMBANKMENT SEGMENT 2 25,439.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

Sum

Average

62,081.00 $0

15.00% 10.00% 25.00%

$0 $0Summary for Group: 10.01.14

Group 10.08.29

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SOUND/SCREEN WALL Contingency

Monday, January 27, 2014 Page 6 of 140

Page 71: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.29.580.86 SOUND WALL (WALL 580R-F) 6,480.00 SF $25.00 $162,000 20.00% 10.00% 30.00% $48,600 $210,600

Sum

Average

6,480.00 $162,000

20.00% 10.00% 30.00%

$48,600 $210,600Summary for Group: 10.08.29

Sum

Average

1,530,011.65 $13,939,212

12.75% 13.52% 26.27%

$3,308,772 $17,247,984Summary for Sub Section: 10.01

Sub Section 10.04 GUIDEWAY: AERIAL STRUCTURE

Group 10.04.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PERMANENT BMP (AERIAL STRUCTURE) Contingency

10.04.01 PERMANENT BMP (AERIAL STRUCTURE) 1.00 LS $1,450,000.00 $1,450,000 0.00% 20.00% 20.00% $290,000 $1,740,000

Sum

Average

1.00 $1,450,000

0.00% 20.00% 20.00%

$290,000 $1,740,000Summary for Group: 10.04.01

Group 10.04.03.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SAN DIEGO RIVER BRIDGE Contingency

10.04.03.01.15XXXX REMOVE AND REPLACE CONCRETE BERM 100.00 CY $198.00 $19,800 15.00% 10.00% 25.00% $4,950 $24,750

10.04.03.01.192003 STRUCTURE EXCAVATION (BRIDGE) 100.00 CY $60.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500

10.04.03.01.193003 STRUCTURAL BACKFILL (BRIDGE) 50.00 CY $73.00 $3,650 15.00% 10.00% 25.00% $913 $4,563

10.04.03.01.199XXX GROUND IMPROVEMENT 7.00 EA $380,000.00 $2,660,000 0.00% 10.00% 10.00% $266,000 $2,926,000

10.04.03.01.490607 48" CIDH CONCRETE PILING 360.00 LF $701.00 $252,360 15.00% 20.00% 35.00% $88,326 $340,686

10.04.03.01.490620 108"CIDH CONCRETE PILING 720.00 LF $1,967.00 $1,416,240 15.00% 20.00% 35.00% $495,684 $1,911,924

10.04.03.01.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 98,100.00 LB $1.85 $181,485 15.00% 20.00% 35.00% $63,520 $245,005

10.04.03.01.510053 STRUCTURAL CONCRETE (BRIDGE) 1,930.00 CY $850.00 $1,640,500 15.00% 20.00% 35.00% $574,175 $2,214,675

10.04.03.01.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 15.00 CY $850.00 $12,750 15.00% 10.00% 25.00% $3,188 $15,938

10.04.03.01.511035 ARCHITECT TREATMENT 360.00 SF $14.00 $5,040 15.00% 10.00% 25.00% $1,260 $6,300

10.04.03.01.518051 PTFE SPHERICAL BEARING 3.00 EA $6,191.00 $18,573 0.00% 10.00% 10.00% $1,857 $20,430

10.04.03.01.519093 JOINT SEAL ASSEMBLY (MR=3") 30.00 LF $211.00 $6,330 0.00% 10.00% 10.00% $633 $6,963

10.04.03.01.519095 JOINT SEAL ASSEMBLY (MR=4") 30.00 LF $265.00 $7,950 0.00% 10.00% 10.00% $795 $8,745

10.04.03.01.519099 JOINT SEAL ASSEMBLY (MR=6") 30.00 LF $737.00 $22,110 0.00% 10.00% 10.00% $2,211 $24,321

10.04.03.01.520102 BAR REINFORCING STEEL (BRIDGE) 774,000.00 LB $1.00 $774,000 15.00% 20.00% 35.00% $270,900 $1,044,900

10.04.03.01.520122 STRAY CURRENT PROTECTION (BRIDGE) 27,498.00 SF $2.00 $54,996 15.00% 10.00% 25.00% $13,749 $68,745

10.04.03.01.7351XX MINOR CONCRETE (CURB) 1,803.00 LF $28.00 $50,484 15.00% 10.00% 25.00% $12,621 $63,105

10.04.03.01.750501 MISCELANEOUS METAL (BRIDGE) 3,600.00 LB $4.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000

Monday, January 27, 2014 Page 7 of 140

Page 72: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.04.03.01.750505 BRIDGE DECK DRAINAGE SYSTEM 5,000.00 LB $5.00 $25,000 15.00% 10.00% 25.00% $6,250 $31,250

10.04.03.01.833000 METAL RAILING (PIPE) 1,803.00 LF $125.00 $225,375 15.00% 10.00% 25.00% $56,344 $281,719

10.04.03.01.XXXXXX CONSTRUCT TEMPORARY ACCESS TRESTLE 65.00 LF $2,250.00 $146,250 15.00% 20.00% 35.00% $51,188 $197,438

Sum

Average

915,604.00 $7,543,293

11.43% 12.86% 24.29%

$1,919,662 $9,462,955Summary for Group: 10.04.03.01

Group 10.04.03.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TECOLOTE CREEK BRIDGE Contingency

10.04.03.02.153220 REMOVE CONCRETE (CHANNEL) 25.00 CY $67.00 $1,675 15.00% 10.00% 25.00% $419 $2,094

10.04.03.02.192003 STRUCTURE EXCAVATION (BRIDGE) 70.00 CY $60.00 $4,200 15.00% 10.00% 25.00% $1,050 $5,250

10.04.03.02.193003 STRUCTURAL BACKFILL (BRIDGE) 45.00 CY $73.00 $3,285 15.00% 10.00% 25.00% $821 $4,106

10.04.03.02.490604 30" CIDH CONCRETE PILING 880.00 LF $370.00 $325,600 15.00% 10.00% 25.00% $81,400 $407,000

10.04.03.02.510053 STRUCTURAL CONCRETE (BRIDGE) 258.00 CY $850.00 $219,300 15.00% 10.00% 25.00% $54,825 $274,125

10.04.03.02.520120 BAR REINFORCING STEEL (BRIDGE) 88,711.00 LB $1.00 $88,711 15.00% 10.00% 25.00% $22,178 $110,889

10.04.03.02.520122 STRAY CURRENT PROTECTION (BRIDGE) 2,249.00 SF $2.00 $4,498 15.00% 10.00% 25.00% $1,125 $5,623

10.04.03.02.540104 WATERPROOFING AND COVER 2,220.00 SF $15.00 $33,300 15.00% 10.00% 25.00% $8,325 $41,625

10.04.03.02.833000 METAL RAILING (PIPE) 185.00 LF $125.00 $23,125 15.00% 10.00% 25.00% $5,781 $28,906

Sum

Average

94,643.00 $703,694

15.00% 10.00% 25.00%

$175,924 $879,618Summary for Group: 10.04.03.02

Group 10.04.03.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROSE CREEK SOUTH BRIDGE Contingency

10.04.03.03.153220 REMOVE CONCRETE (CHANNEL) 26.00 CY $67.00 $1,742 15.00% 10.00% 25.00% $436 $2,178

10.04.03.03.192003 STRUCTURE EXCAVATION (BRIDGE) 85.00 CY $60.00 $5,100 15.00% 10.00% 25.00% $1,275 $6,375

10.04.03.03.193003 STRUCTURAL BACKFILL (BRIDGE) 45.00 CY $73.00 $3,285 15.00% 10.00% 25.00% $821 $4,106

10.04.03.03.490605 36" CIDH CONCRETE PILING 300.00 LF $507.00 $152,100 15.00% 10.00% 25.00% $38,025 $190,125

10.04.03.03.490608 54" CIDH CONCRETE PILING 80.00 LF $880.00 $70,400 15.00% 10.00% 25.00% $17,600 $88,000

10.04.03.03.490611 72" CIDH CONCRETE PILING 150.00 LF $1,113.00 $166,950 15.00% 10.00% 25.00% $41,738 $208,688

10.04.03.03.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 20,000.00 LB $1.85 $37,000 15.00% 10.00% 25.00% $9,250 $46,250

10.04.03.03.510053 STRUCTURAL CONCRETE (BRIDGE) 725.00 CY $850.00 $616,250 15.00% 10.00% 25.00% $154,063 $770,313

10.04.03.03.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 30.00 CY $850.00 $25,500 15.00% 10.00% 25.00% $6,375 $31,875

10.04.03.03.519100 JOINT SEAL (MR=2") 63.00 LF $145.00 $9,135 0.00% 10.00% 10.00% $914 $10,049

10.04.03.03.520102 BAR REINFORCING STEEL (BRIDGE) 255,000.00 LB $1.00 $255,000 15.00% 10.00% 25.00% $63,750 $318,750

Monday, January 27, 2014 Page 8 of 140

Page 73: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.04.03.03.520122 STRAY CURRENT PROTECTION (BRIDGE) 9,250.00 SF $2.00 $18,500 15.00% 10.00% 25.00% $4,625 $23,125

10.04.03.03.720XXX ROCK SLOPE PROTECTION 70.00 CY $593.00 $41,510 15.00% 10.00% 25.00% $10,378 $51,888

10.04.03.03.7351XX MINOR CONCRETE (CURB) 592.00 LF $28.00 $16,576 15.00% 10.00% 25.00% $4,144 $20,720

10.04.03.03.750505 BRIDGE DECK DRAINAGE SYSTEM 1,200.00 LB $5.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500

10.04.03.03.83300 METAL RAILING (PIPE) 592.00 LF $125.00 $74,000 15.00% 10.00% 25.00% $18,500 $92,500

Sum

Average

288,208.00 $1,499,048

14.06% 10.00% 24.06%

$373,392 $1,872,440Summary for Group: 10.04.03.03

Group 10.04.03.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROSE CREEK NORTH BRIDGE Contingency

10.04.03.04.192003 STRUCTURE EXCAVATION (BRIDGE) 147.00 CY $60.00 $8,820 20.00% 15.00% 35.00% $3,087 $11,907

10.04.03.04.193003 STRUCTURAL BACKFILL (BRIDGE) 91.00 CY $73.00 $6,643 20.00% 15.00% 35.00% $2,325 $8,968

10.04.03.04.490604 30" CIDH CONCRETE PILING 240.00 LF $370.00 $88,800 20.00% 15.00% 35.00% $31,080 $119,880

10.04.03.04.490609 60" CIDH CONCRETE PILING 180.00 LF $935.00 $168,300 20.00% 15.00% 35.00% $58,905 $227,205

10.04.03.04.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 22,300.00 LB $1.85 $41,255 20.00% 15.00% 35.00% $14,439 $55,694

10.04.03.04.510053 STRUCTURAL CONCRETE (BRIDGE) 749.00 CY $850.00 $636,650 20.00% 15.00% 35.00% $222,828 $859,478

10.04.03.04.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 30.00 CY $850.00 $25,500 20.00% 15.00% 35.00% $8,925 $34,425

10.04.03.04.519100 JOINT SEAL (MR=2") 63.00 LF $145.00 $9,135 20.00% 15.00% 35.00% $3,197 $12,332

10.04.03.04.520102 BAR REINFORCING STEEL (BRIDGE) 252,000.00 LB $1.00 $252,000 20.00% 15.00% 35.00% $88,200 $340,200

10.04.03.04.520122 STRAY CURRENT PROTECTION (BRIDGE) 10,563.00 SF $2.00 $21,126 20.00% 15.00% 35.00% $7,394 $28,520

10.04.03.04.720XXX ROCK SLOPE PROTECTION 70.00 CY $593.00 $41,510 20.00% 15.00% 35.00% $14,529 $56,039

10.04.03.04.7351XX MINOR CONCRETE (CURB) 716.00 LF $28.00 $20,048 20.00% 15.00% 35.00% $7,017 $27,065

10.04.03.04.750041 ISOLATION CASING 2,700.00 LB $3.00 $8,100 20.00% 15.00% 35.00% $2,835 $10,935

10.04.03.04.750505 BRIDGE DECK DRAINAGE SYSTEM 2,630.00 LB $5.00 $13,150 20.00% 15.00% 35.00% $4,603 $17,753

10.04.03.04.833000 METAL RAILING (PIPE) 716.00 LF $125.00 $89,500 20.00% 15.00% 35.00% $31,325 $120,825

Sum

Average

293,195.00 $1,430,537

20.00% 15.00% 35.00%

$500,688 $1,931,225Summary for Group: 10.04.03.04

Group 10.04.03.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROSE CANYON LRT OH BRIDGE Contingency

10.04.03.05.192003 STRUCTURE EXCAVATION (BRIDGE) 433.00 CY $60.00 $25,980 15.00% 10.00% 25.00% $6,495 $32,475

10.04.03.05.193003 STRUCTURAL BACKFILL (BRIDGE) 488.00 CY $73.00 $35,624 15.00% 10.00% 25.00% $8,906 $44,530

10.04.03.05.490605 36" CIDH CONCRETE PILING 600.00 LF $507.00 $304,200 15.00% 10.00% 25.00% $76,050 $380,250

Monday, January 27, 2014 Page 9 of 140

Page 74: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.04.03.05.490620 108" CIDH CONCRETE PILING 1,275.00 LF $1,967.00 $2,507,925 15.00% 10.00% 25.00% $626,981 $3,134,906

10.04.03.05.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 250,000.00 LB $1.85 $462,500 15.00% 10.00% 25.00% $115,625 $578,125

10.04.03.05.510053 STRUCTURAL CONCRETE (BRIDGE) 6,400.00 CY $850.00 $5,440,000 15.00% 10.00% 25.00% $1,360,000 $6,800,000

10.04.03.05.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 30.00 CY $850.00 $25,500 15.00% 10.00% 25.00% $6,375 $31,875

10.04.03.05.518051 PTFE SPHERICAL BEARING 12.00 EA $6,191.00 $74,292 0.00% 10.00% 10.00% $7,429 $81,721

10.04.03.05.519092 JOINT SEAL ASSEMBLY (MR=2.5") 31.00 LF $189.00 $5,859 0.00% 10.00% 10.00% $586 $6,445

10.04.03.05.519094 JOINT SEAL ASSEMBLY (MR=3.5") 31.00 LF $227.00 $7,037 0.00% 10.00% 10.00% $704 $7,741

10.04.03.05.519095 JOINT SEAL ASSEMBLY (MR=4") 31.00 LF $265.00 $8,215 0.00% 10.00% 10.00% $822 $9,037

10.04.03.05.519099 JOINT SEAL ASSEMBLY (MR=6") 31.00 LF $737.00 $22,847 0.00% 10.00% 10.00% $2,285 $25,132

10.04.03.05.519105 JOINT SEAL ASSEMBLY (MR=7") 62.00 LF $1,218.00 $75,516 0.00% 10.00% 10.00% $7,552 $83,068

10.04.03.05.520102 BAR REINFORCING STEEL (BRIDGE) 2,074,000.00 LB $1.00 $2,074,000 15.00% 10.00% 25.00% $518,500 $2,592,500

10.04.03.05.520122 STRAY CURRENT PROTECTION (BRIDGE) 63,438.00 SF $2.00 $126,876 15.00% 10.00% 25.00% $31,719 $158,595

10.04.03.05.7351XX MINOR CONCRETE (CURB) 4,328.00 LF $28.00 $121,184 15.00% 10.00% 25.00% $30,296 $151,480

10.04.03.05.750501 MISCELANEOUS METAL (BRIDGE) 10,000.00 LB $4.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

10.04.03.05.750505 BRIDGE DECK DRAINAGE SYSTEM 7,500.00 LB $5.00 $37,500 15.00% 10.00% 25.00% $9,375 $46,875

10.04.03.05.833000 METAL RAILING (PIPE) 4,328.00 LF $125.00 $541,000 15.00% 10.00% 25.00% $135,250 $676,250

Sum

Average

2,423,018.00 $11,936,055

10.26% 10.00% 20.26%

$2,954,949 $14,891,004Summary for Group: 10.04.03.05

Group 10.04.03.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NOBEL VIADUCT Contingency

10.04.03.06.192003 STRUCTURE EXCAVATION (BRIDGE) 1,670.00 CY $60.00 $100,200 15.00% 10.00% 25.00% $25,050 $125,250

10.04.03.06.480600 TEMPORARY SHORING 12,300.00 SF $70.00 $861,000 15.00% 10.00% 25.00% $215,250 $1,076,250

10.04.03.06.490605 36" CIDH CONCRETE PILING 750.00 LF $507.00 $380,250 15.00% 10.00% 25.00% $95,063 $475,313

10.04.03.06.490611 72" CIDH CONCRETE PILING 440.00 LF $1,113.00 $489,720 20.00% 10.00% 30.00% $146,916 $636,636

10.04.03.06.490618 96" CIDH CONCRETE PILING 570.00 LF $1,344.00 $766,080 15.00% 10.00% 25.00% $191,520 $957,600

10.04.03.06.490620 108" CIDH CONCRETE PILING 220.00 LF $1,967.00 $432,740 15.00% 10.00% 25.00% $108,185 $540,925

10.04.03.06.490622 120" CIDH CONCRETE PILING 1,025.00 LF $2,310.00 $2,367,750 15.00% 10.00% 25.00% $591,938 $2,959,688

10.04.03.06.4906xx 144" CIDH CONCRETE PILING 110.00 LF $3,170.00 $348,700 15.00% 10.00% 25.00% $87,175 $435,875

10.04.03.06.4906xx 132" CIDH CONCRETE PILING 80.00 LF $2,923.00 $233,840 15.00% 10.00% 25.00% $58,460 $292,300

10.04.03.06.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 615,040.00 LB $1.85 $1,137,824 15.00% 10.00% 25.00% $284,456 $1,422,280

Monday, January 27, 2014 Page 10 of 140

Page 75: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.04.03.06.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 434.00 CY $440.00 $190,960 15.00% 10.00% 25.00% $47,740 $238,700

10.04.03.06.510051 STRUCTURAL BACKFILL (BRIDGE) 1,240.00 CY $73.00 $90,520 15.00% 10.00% 25.00% $22,630 $113,150

10.04.03.06.510053 STRUCTURAL CONCRETE (BRIDGE) 15,050.00 CY $850.00 $12,792,500 15.00% 10.00% 25.00% $3,198,125 $15,990,625

10.04.03.06.511035 ARCHITECT TREATMENT 1,500.00 SF $14.00 $21,000 15.00% 10.00% 25.00% $5,250 $26,250

10.04.03.06.518002 SOUND WALL 3,000.00 SF $25.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

10.04.03.06.518051 PTFE SPHERICAL BEARING 36.00 EA $6,191.00 $222,876 0.00% 10.00% 10.00% $22,288 $245,164

10.04.03.06.519092 JOINT SEAL ASSEMBLY (MR=2.5") 32.00 LF $189.00 $6,048 0.00% 10.00% 10.00% $605 $6,653

10.04.03.06.519093 JOINT SEAL ASSEMBLY (MR=3") 32.00 LF $211.00 $6,752 0.00% 10.00% 10.00% $675 $7,427

10.04.03.06.519099 JOINT SEAL ASSEMBLY (MR=6") 64.00 LF $737.00 $47,168 0.00% 10.00% 10.00% $4,717 $51,885

10.04.03.06.519105 JOINT SEAL ASSEMBLY (MR=7") 64.00 LF $1,218.00 $77,952 0.00% 10.00% 10.00% $7,795 $85,747

10.04.03.06.519109 JOINT SEAL ASSEMBLY (MR=6.5") 96.00 LF $1,085.00 $104,160 0.00% 10.00% 10.00% $10,416 $114,576

10.04.03.06.519XX JOINT SEAL ASSEMBLY (MR=8") 32.00 LF $1,650.00 $52,800 0.00% 10.00% 10.00% $5,280 $58,080

10.04.03.06.519xxx JOINT SEAL ASSEMBLY (MR=7.5") 32.00 LF $1,451.00 $46,432 0.00% 10.00% 10.00% $4,643 $51,075

10.04.03.06.520102 BAR REINFORCING STEEL (BRIDGE) 6,085,900.00 LB $1.00 $6,085,900 15.00% 10.00% 25.00% $1,521,475 $7,607,375

10.04.03.06.520122 STRAY CURRENT PROTECTION (BRIDGE) 155,061.00 SF $2.00 $310,122 15.00% 10.00% 25.00% $77,531 $387,653

10.04.03.06.7351xx MINOR CONCRETE (CURB) 9,321.00 LF $28.00 $260,988 15.00% 10.00% 25.00% $65,247 $326,235

10.04.03.06.750041 ISOLATION CASING 53,000.00 LB $3.00 $159,000 15.00% 10.00% 25.00% $39,750 $198,750

10.04.03.06.750501 MISCELANEOUS METAL (BRIDGE) 3,000.00 LB $4.00 $12,000 15.00% 10.00% 25.00% $3,000 $15,000

10.04.03.06.750505 BRIDGE DECK DRAINAGE SYSTEM 18,650.00 LB $5.00 $93,250 15.00% 10.00% 25.00% $23,313 $116,563

10.04.03.06.833000 METAL RAILING (PIPE) 9,321.00 LF $125.00 $1,165,125 15.00% 10.00% 25.00% $291,281 $1,456,406

Sum

Average

6,988,070.00 $28,938,657

11.17% 10.00% 21.17%

$7,174,522 $36,113,179Summary for Group: 10.04.03.06

Group 10.04.03.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UCSD VIADUCT Contingency

10.04.03.07.192003 STRUCTURE EXCAVATION (BRIDGE) 692.00 CY $60.00 $41,520 15.00% 10.00% 25.00% $10,380 $51,900

10.04.03.07.193003 STRUCTURAL BACKFILL (BRIDGE) 461.00 CY $73.00 $33,653 15.00% 10.00% 25.00% $8,413 $42,066

10.04.03.07.490603 24" CIDH CONCRETE PILING 12,098.00 LF $306.00 $3,701,988 15.00% 10.00% 25.00% $925,497 $4,627,485

10.04.03.07.490620 108" CIDH CONCRETE PILING 1,183.00 LF $1,967.00 $2,326,961 15.00% 10.00% 25.00% $581,740 $2,908,701

10.04.03.07.4906xx 132" CIDH CONCRETE PILING 662.00 LF $2,923.00 $1,935,026 15.00% 10.00% 25.00% $483,757 $2,418,783

10.04.03.07.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 1,187,110.00 LB $1.85 $2,196,154 15.00% 10.00% 25.00% $549,038 $2,745,192

Monday, January 27, 2014 Page 11 of 140

Page 76: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.04.03.07.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 1,405.00 CY $440.00 $618,200 15.00% 10.00% 25.00% $154,550 $772,750

10.04.03.07.510053 STRUCTURAL CONCRETE (BRIDGE) 20,729.00 CY $850.00 $17,619,650 15.00% 10.00% 25.00% $4,404,913 $22,024,563

10.04.03.07.511035 ARCHITECT TREATMENT 2,066.00 SF $14.00 $28,924 15.00% 10.00% 25.00% $7,231 $36,155

10.04.03.07.518051 PTFE SPHERICAL BEARING 68.00 EA $6,191.00 $420,988 0.00% 10.00% 10.00% $42,099 $463,087

10.04.03.07.519097 JOINT SEAL ASSEMBLY (MR=5") 531.00 LF $638.00 $338,778 0.00% 10.00% 10.00% $33,878 $372,656

10.04.03.07.520102 BAR REINFORCING STEEL (BRIDGE) 6,798,000.00 LB $1.00 $6,798,000 15.00% 10.00% 25.00% $1,699,500 $8,497,500

10.04.03.07.520122 STRAY CURRENT PROTECTION (BRIDGE) 203,000.00 SF $2.00 $406,000 15.00% 10.00% 25.00% $101,500 $507,500

10.04.03.07.7351xx MINOR CONCRETE (CURB) 38,111.00 LF $28.00 $1,067,108 15.00% 10.00% 25.00% $266,777 $1,333,885

10.04.03.07.750041 ISOLATION CASING 42,500.00 LB $3.00 $127,500 15.00% 10.00% 25.00% $31,875 $159,375

10.04.03.07.750501 MISCELANEOUS METAL (BRIDGE) 5,360.00 LB $4.00 $21,440 15.00% 10.00% 25.00% $5,360 $26,800

10.04.03.07.750505 BRIDGE DECK DRAINAGE SYSTEM 33,600.00 LB $5.00 $168,000 15.00% 10.00% 25.00% $42,000 $210,000

10.04.03.07.833000 METAL RAILING (PIPE) 12,976.00 LF $125.00 $1,622,000 15.00% 10.00% 25.00% $405,500 $2,027,500

Sum

Average

8,360,552.00 $39,471,890

13.33% 10.00% 23.33%

$9,754,007 $49,225,897Summary for Group: 10.04.03.07

Group 10.04.03.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE VIADUCT Contingency

10.04.03.08.192003 STRUCTURE EXCAVATION (BRIDGE) 356.00 CY $60.00 $21,360 15.00% 10.00% 25.00% $5,340 $26,700

10.04.03.08.193003 STRUCTURAL BACKFILL (BRIDGE) 176.00 CY $73.00 $12,848 15.00% 10.00% 25.00% $3,212 $16,060

10.04.03.08.490618 96" CIDH CONCRETE PILING 882.00 LF $1,344.00 $1,185,408 15.00% 10.00% 25.00% $296,352 $1,481,760

10.04.03.08.490620 108" CIDH CONCRETE PILING 1,323.00 LF $1,967.00 $2,602,341 15.00% 10.00% 25.00% $650,585 $3,252,926

10.04.03.08.490622 120" CIDH CONCRETE PILING 147.00 LF $2,310.00 $339,570 15.00% 10.00% 25.00% $84,893 $424,463

10.04.03.08.4906xx 132" CIDH CONCRETE PILING 243.00 LF $2,923.00 $710,289 15.00% 10.00% 25.00% $177,572 $887,861

10.04.03.08.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 982,000.00 LB $1.85 $1,816,700 15.00% 10.00% 25.00% $454,175 $2,270,875

10.04.03.08.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 38.00 CY $440.00 $16,720 15.00% 10.00% 25.00% $4,180 $20,900

10.04.03.08.510053 STRUCTURAL CONCRETE (BRIDGE) 20,000.00 CY $850.00 $17,000,000 15.00% 10.00% 25.00% $4,250,000 $21,250,000

10.04.03.08.511035 ARCHITECT TREATMENT 40,400.00 SF $14.00 $565,600 15.00% 10.00% 25.00% $141,400 $707,000

10.04.03.08.518051 PTFE SPHERICAL BEARING 52.00 EA $6,191.00 $321,932 0.00% 10.00% 10.00% $32,193 $354,125

10.04.03.08.519097 JOINT SEAL ASSEMBLY (MR=5") 438.00 LF $638.00 $279,444 0.00% 10.00% 10.00% $27,944 $307,388

10.04.03.08.520102 BAR REINFORCING STEEL (BRIDGE) 6,800,000.00 LB $1.00 $6,800,000 15.00% 10.00% 25.00% $1,700,000 $8,500,000

10.04.03.08.520122 STRAY CURRENT PROTECTION (BRIDGE) 177,672.00 SF $2.00 $355,344 15.00% 10.00% 25.00% $88,836 $444,180

Monday, January 27, 2014 Page 12 of 140

Page 77: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.04.03.08.7351xx MINOR CONCRETE (CURB) 32,850.00 LF $28.00 $919,800 15.00% 10.00% 25.00% $229,950 $1,149,750

10.04.03.08.750041 ISOLATION CASING 27,500.00 LB $3.00 $82,500 15.00% 10.00% 25.00% $20,625 $103,125

10.04.03.08.750501 MISCELANEOUS METAL (BRIDGE) 4,700.00 LB $4.00 $18,800 15.00% 10.00% 25.00% $4,700 $23,500

10.04.03.08.750505 BRIDGE DECK DRAINAGE SYSTEM 28,900.00 LB $5.00 $144,500 15.00% 10.00% 25.00% $36,125 $180,625

10.04.03.08.833000 METAL RAILING (PIPE) 11,442.00 LF $125.00 $1,430,250 15.00% 10.00% 25.00% $357,563 $1,787,813

Sum

Average

8,129,119.00 $34,623,406

13.42% 10.00% 23.42%

$8,565,645 $43,189,051Summary for Group: 10.04.03.08

Group 10.04.03.09

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BALBOA AVE UP Contingency

10.04.03.09.192003 STRUCTURE EXCAVATION (BRIDGE) 468.00 CY $60.00 $28,080 15.00% 10.00% 25.00% $7,020 $35,100

10.04.03.09.193003 STRUCTURAL BACKFILL (BRIDGE) 311.00 CY $73.00 $22,703 15.00% 10.00% 25.00% $5,676 $28,379

10.04.03.09.490603 24" CIDH CONCRETE PILING 2,520.00 LF $306.00 $771,120 15.00% 10.00% 25.00% $192,780 $963,900

10.04.03.09.490611 72" CIDH CONCRETE PILING 120.00 LF $1,113.00 $133,560 15.00% 10.00% 25.00% $33,390 $166,950

10.04.03.09.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 34,940.00 LB $1.85 $64,639 15.00% 10.00% 25.00% $16,160 $80,799

10.04.03.09.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 227.00 CY $440.00 $99,880 15.00% 10.00% 25.00% $24,970 $124,850

10.04.03.09.510053 STRUCTURAL CONCRETE (BRIDGE) 834.00 CY $850.00 $708,900 15.00% 10.00% 25.00% $177,225 $886,125

10.04.03.09.519094 JOINT SEAL ASSEMBLY (MR=3.5") 85.00 LF $227.00 $19,295 0.00% 10.00% 10.00% $1,930 $21,225

10.04.03.09.520102 BAR REINFORCING STEEL (BRIDGE) 298,000.00 LB $1.00 $298,000 15.00% 10.00% 25.00% $74,500 $372,500

10.04.03.09.520122 STRAY CURRENT PROTECTION (BRIDGE) 9,295.00 SF $2.00 $18,590 15.00% 10.00% 25.00% $4,648 $23,238

10.04.03.09.540104 WATERPROOFING AND COVER 6,875.00 SF $15.00 $103,125 15.00% 10.00% 25.00% $25,781 $128,906

10.04.03.09.7351XX MINOR CONCRETE (CURB) 440.00 LF $28.00 $12,320 15.00% 10.00% 25.00% $3,080 $15,400

10.04.03.09.750505 BRIDGE DECK DRAINAGE SYSTEM 2,300.00 LB $5.00 $11,500 15.00% 10.00% 25.00% $2,875 $14,375

10.04.03.09.833020 CHAIN LINK RAILING 440.00 LF $150.00 $66,000 15.00% 10.00% 25.00% $16,500 $82,500

10.04.03.09.833088 METAL RAILING (PIPE) 220.00 LF $125.00 $27,500 15.00% 10.00% 25.00% $6,875 $34,375

Sum

Average

357,075.00 $2,385,212

14.00% 10.00% 24.00%

$593,409 $2,978,621Summary for Group: 10.04.03.09

Group 10.04.03.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CHARMANT SOUTH BRIDGE Contingency

10.04.03.10.192003 STRUCTURE EXCAVATION (BRIDGE) 320.00 CY $60.00 $19,200 15.00% 10.00% 25.00% $4,800 $24,000

10.04.03.10.193003 STRUCTURAL BACKFILL (BRIDGE) 270.00 CY $73.00 $19,710 15.00% 10.00% 25.00% $4,928 $24,638

10.04.03.10.490605 36" CIDH CONCRETE PILING 590.00 LF $507.00 $299,130 15.00% 10.00% 25.00% $74,783 $373,913

Monday, January 27, 2014 Page 13 of 140

Page 78: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.04.03.10.490618 96" CIDH CONCRETE PILING 80.00 LF $1,344.00 $107,520 15.00% 10.00% 25.00% $26,880 $134,400

10.04.03.10.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 31,500.00 LB $1.85 $58,275 15.00% 10.00% 25.00% $14,569 $72,844

10.04.03.10.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 105.00 CY $440.00 $46,200 15.00% 10.00% 25.00% $11,550 $57,750

10.04.03.10.510053 STRUCTURAL CONCRETE (BRIDGE) 780.00 CY $850.00 $663,000 15.00% 10.00% 25.00% $165,750 $828,750

10.04.03.10.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 15.00 CY $850.00 $12,750 15.00% 10.00% 25.00% $3,188 $15,938

10.04.03.10.511035 ARCHITECT TREATMENT 65.00 SF $14.00 $910 15.00% 10.00% 25.00% $228 $1,138

10.04.03.10.519100 JOINT SEAL ASSEMBLY (MR=2") 62.00 LF $145.00 $8,990 0.00% 10.00% 10.00% $899 $9,889

10.04.03.10.520102 BAR REINFORCING STEEL (BRIDGE) 276,520.00 LB $1.00 $276,520 15.00% 10.00% 25.00% $69,130 $345,650

10.04.03.10.520122 STRAY CURRENT PROTECTION (BRIDGE) 8,695.00 SF $2.00 $17,390 15.00% 10.00% 25.00% $4,348 $21,738

10.04.03.10.7351xx MINOR CONCRETE (CURB) 664.00 LF $28.00 $18,592 15.00% 10.00% 25.00% $4,648 $23,240

10.04.03.10.750505 BRIDGE DECK DRAINAGE SYSTEM 1,113.00 LB $5.00 $5,565 15.00% 10.00% 25.00% $1,391 $6,956

10.04.03.10.833000 METAL RAILING (PIPE) 632.00 LF $125.00 $79,000 15.00% 10.00% 25.00% $19,750 $98,750

Sum

Average

321,411.00 $1,632,752

14.00% 10.00% 24.00%

$406,840 $2,039,592Summary for Group: 10.04.03.10

Group 10.04.03.11

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CHARMANT NORTH BRIDGE Contingency

10.04.03.11.192003 STRUCTURE EXCAVATION (BRIDGE) 286.00 CY $60.00 $17,160 15.00% 10.00% 25.00% $4,290 $21,450

10.04.03.11.193003 STRUCTURAL BACKFILL (BRIDGE) 127.00 CY $73.00 $9,271 15.00% 10.00% 25.00% $2,318 $11,589

10.04.03.11.490605 36" CIDH CONCRETE PILING 600.00 LF $507.00 $304,200 15.00% 10.00% 25.00% $76,050 $380,250

10.04.03.11.490618 96" CIDH CONCRETE PILING 160.00 LF $1,344.00 $215,040 15.00% 10.00% 25.00% $53,760 $268,800

10.04.03.11.500001 PRESTRESSING CAST-IN-PLACE CONCRETE 40,320.00 LB $1.85 $74,592 15.00% 10.00% 25.00% $18,648 $93,240

10.04.03.11.510051 STRUCTURAL CONCRETE (BRIDGE FOOTING) 72.00 CY $440.00 $31,680 15.00% 10.00% 25.00% $7,920 $39,600

10.04.03.11.510053 STRUCTURAL CONCRETE (BRIDGE) 1,012.00 CY $850.00 $860,200 15.00% 10.00% 25.00% $215,050 $1,075,250

10.04.03.11.511035 ARCHITECT TREATMENT 100.00 SF $14.00 $1,400 15.00% 10.00% 25.00% $350 $1,750

10.04.03.11.519092 JOINT SEAL ASSEMBLY (MR=2.5") 32.00 LF $189.00 $6,048 0.00% 10.00% 10.00% $605 $6,653

10.04.03.11.519093 JOINT SEAL ASSEMBLY (MR=3") 32.00 LF $211.00 $6,752 0.00% 10.00% 10.00% $675 $7,427

10.04.03.11.520102 BAR REINFORCING STEEL (BRIDGE) 392,300.00 LB $1.00 $392,300 15.00% 10.00% 25.00% $98,075 $490,375

10.04.03.11.520122 STRAY CURRENT PROTECTION (BRIDGE) 13,047.00 SF $2.00 $26,094 15.00% 10.00% 25.00% $6,524 $32,618

10.04.03.11.7351xx MINOR CONCRETE (CURB) 879.00 LF $28.00 $24,612 15.00% 10.00% 25.00% $6,153 $30,765

10.04.03.11.750505 BRIDGE DECK DRAINAGE SYSTEM 1,650.00 LB $5.00 $8,250 15.00% 10.00% 25.00% $2,063 $10,313

Monday, January 27, 2014 Page 14 of 140

Page 79: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.04.03.11.833000 METAL RAILING (PIPE) 879.00 LF $125.00 $109,875 15.00% 10.00% 25.00% $27,469 $137,344

Sum

Average

451,496.00 $2,087,474

13.00% 10.00% 23.00%

$519,949 $2,607,423Summary for Group: 10.04.03.11

Group 10.04.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

HYDROMODIFICATION Contingency

10.04.04.601 HYDROMODIFICAITON-UNDERGROUND STORAGE (NOBEL VIADUC 24,104.60 CF $2.45 $59,056 15.00% 15.00% 30.00% $17,717 $76,773

10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (LRT OH BRIDGE) 16,767.40 CF $2.45 $41,080 15.00% 15.00% 30.00% $12,324 $53,404

10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (ROSE CREEK SO 2,405.00 CF $2.45 $5,892 15.00% 15.00% 30.00% $1,768 $7,660

10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (ROSE CREEK NO 2,753.40 CF $2.45 $6,746 15.00% 15.00% 30.00% $2,024 $8,770

10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD VIADUCT) 18,730.40 CF $2.45 $45,889 15.00% 15.00% 30.00% $13,767 $59,656

10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (CHARMANT NO 3,738.80 CF $2.45 $9,160 15.00% 15.00% 30.00% $2,748 $11,908

10.04.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (CHARMANT SO 2,641.60 CF $2.45 $6,472 15.00% 15.00% 30.00% $1,942 $8,413

10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD VIADUCT) 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (NOBEL VIADUCT) 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (CHARMANT NORT 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (CHARMANT SOUT 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (LRT OH BRIDGE) 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (ROSE CREEK SOUT 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

10.04.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (ROSE CREEK NOR 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

Sum

Average

71,148.20 $223,296

15.00% 15.00% 30.00%

$66,989 $290,285Summary for Group: 10.04.04

Sum

Average

28,693,540.20 $133,925,313

13.29% 11.04% 24.32%

$33,295,975 $167,221,288Summary for Sub Section: 10.04

Sub Section 10.06 GUIDEWAY: UNDERGROUND CUT & COVER

Group 10.06.00

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LA JOLLA COLONY OH Contingency

10.06.00.01 FACTOR FOR STAGE CONSTRUCTION (10%) 1.00 LS $418,573.64 $418,574 15.00% 15.00% 30.00% $125,572 $544,146

10.06.00.02 PERMANENT BMP (UNDERGROUND C&C) 1.00 LS $200,000.00 $200,000 0.00% 20.00% 20.00% $40,000 $240,000

10.06.00.480600 TEMPORARY SHORING 22,500.00 SF $70.00 $1,575,000 15.00% 15.00% 30.00% $472,500 $2,047,500

10.06.00.511035 ARCHITECTURAL TREATMENT 5,000.00 SF $14.00 $70,000 15.00% 10.00% 25.00% $17,500 $87,500

10.06.00.520122 STRAY CURRENT PROTECTION 16,238.00 SF $2.00 $32,476 15.00% 10.00% 25.00% $8,119 $40,595

Monday, January 27, 2014 Page 15 of 140

Page 80: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.06.00.540101 ASPHALT MEMBRANE WATERPROOFING 26,091.00 SF $14.00 $365,274 15.00% 15.00% 30.00% $109,582 $474,856

10.06.00.598001 ANTI-GRAFFITI COATING 10,850.00 SF $1.20 $13,020 15.00% 10.00% 25.00% $3,255 $16,275

10.06.00.601 HYDROMODIFICATION-UNDERGROUND STORAGE (LA JOLLA COLO 12,020.00 CF $2.45 $29,449 15.00% 15.00% 30.00% $8,835 $38,284

10.06.00.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (LA JOLLA COLONY 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

10.06.01.192037 STRUCTURE EXCAVATION (U SECTION) 7,878.00 CY $60.00 $472,680 10.00% 10.00% 20.00% $94,536 $567,216

10.06.01.193013 STRUCTURAL BACKFILL (U SECTION) 443.00 CY $73.00 $32,339 10.00% 10.00% 20.00% $6,468 $38,807

10.06.01.510060 STRUCTURAL CONCRETE (U SECTION) 2,211.00 CY $470.00 $1,039,170 10.00% 10.00% 20.00% $207,834 $1,247,004

10.06.01.510080 STRUCTURAL CONCRETE (APPROACH SLAB) 30.00 CY $850.00 $25,500 15.00% 10.00% 25.00% $6,375 $31,875

10.06.01.520103 BAR REINFORCING STEEL (U SECTION) 302,472.00 LB $1.00 $302,472 10.00% 10.00% 20.00% $60,494 $362,966

10.06.01.833020 CHAIN LINK RAILING 495.00 LF $150.00 $74,250 15.00% 10.00% 25.00% $18,563 $92,813

10.06.02.192025 STRUCTURE EXCAVATION (CUT N COVER) 7,270.00 CY $60.00 $436,200 10.00% 10.00% 20.00% $87,240 $523,440

10.06.02.193004 STRUCTURAL BACKFILL (CUT AND COVER) 1,285.00 CY $73.00 $93,805 10.00% 10.00% 20.00% $18,761 $112,566

10.06.02.510090 STRUCTURAL CONCRETE (CUT N COVER) 2,100.00 CY $620.00 $1,302,000 10.00% 10.00% 20.00% $260,400 $1,562,400

10.06.02.520107 BAR REINFORCING STEEL (CUT AND COVER) 309,702.00 LB $1.00 $309,702 10.00% 10.00% 20.00% $61,940 $371,642

Sum

Average

726,588.00 $6,798,911

12.11% 11.84% 23.95%

$1,610,074 $8,408,985Summary for Group: 10.06.00

Sum

Average

726,588.00 $6,798,911

12.11% 11.84% 23.95%

$1,610,074 $8,408,985Summary for Sub Section: 10.06

Sub Section 10.08 GUIDEWAY: RETAINED CUT OR FILL

Group 10.08.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

STRUCTURE EXCAVATION Contingency

10.08.01.211.20 STRUCTURE EXCAVATION 1,360.00 CY $60.00 $81,600 10.00% 10.00% 20.00% $16,320 $97,920

10.08.01.215.20 STRUCTURE EXCAVATION 6,665.00 CY $60.00 $399,900 10.00% 10.00% 20.00% $79,980 $479,880

10.08.01.271.20 STRUCTURE EXCAVATION 2,151.00 CY $60.00 $129,060 10.00% 10.00% 20.00% $25,812 $154,872

10.08.01.332.20 STRUCTURE EXCAVATION 12,645.00 CY $60.00 $758,700 10.00% 10.00% 20.00% $151,740 $910,440

10.08.01.376.20 STRUCTURE EXCAVATION 2,191.00 CY $60.00 $131,460 10.00% 10.00% 20.00% $26,292 $157,752

10.08.01.381.20 STRUCTURE EXCAVATION 373.00 CY $60.00 $22,380 10.00% 10.00% 20.00% $4,476 $26,856

10.08.01.388.20 STRUCTURE EXCAVATION 12,670.00 CY $60.00 $760,200 10.00% 10.00% 20.00% $152,040 $912,240

10.08.01.402.20 STRUCTURE EXCAVATION 5,802.00 CY $60.00 $348,120 10.00% 10.00% 20.00% $69,624 $417,744

10.08.01.416.20 STRUCTURE EXCAVATION 2,346.00 CY $60.00 $140,760 10.00% 10.00% 20.00% $28,152 $168,912

Monday, January 27, 2014 Page 16 of 140

Page 81: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.01.446.20 STRUCTURE EXCAVATION (MSE WALL) 2,972.00 CY $60.00 $178,320 10.00% 10.00% 20.00% $35,664 $213,984

10.08.01.449.20 STRUCTURE EXCAVATION (MSE WALL) 295.00 CY $60.00 $17,700 10.00% 10.00% 20.00% $3,540 $21,240

10.08.01.457.20 STRUCTURE EXCAVATION (MSE WALL) 1,029.00 CY $60.00 $61,740 10.00% 10.00% 20.00% $12,348 $74,088

10.08.01.465.20 STRUCTURE EXCAVATION 9,520.00 CY $60.00 $571,200 10.00% 10.00% 20.00% $114,240 $685,440

10.08.01.472.20 STRUCTURE EXCAVATION (MSE WALL) 2,721.00 CY $60.00 $163,260 10.00% 10.00% 20.00% $32,652 $195,912

10.08.01.475.20 STRUCTURE EXCAVATION (MSE WALL) 267.00 CY $60.00 $16,020 10.00% 10.00% 20.00% $3,204 $19,224

10.08.01.485.20 STRUCTURE EXCAVATION 1,712.00 CY $60.00 $102,720 10.00% 10.00% 20.00% $20,544 $123,264

10.08.01.498L.20 STRUCTURE EXCAVATION 3,980.00 CY $60.00 $238,800 10.00% 10.00% 20.00% $47,760 $286,560

10.08.01.498R.20 STRUCTURE EXCAVATION 6,812.00 CY $60.00 $408,720 10.00% 10.00% 20.00% $81,744 $490,464

10.08.01.500.20 STRUCTURE EXCAVATION (MSE WALL) 5,186.00 CY $60.00 $311,160 10.00% 10.00% 20.00% $62,232 $373,392

10.08.01.507.20 STRUCTURE EXCAVATION 686.00 CY $60.00 $41,160 10.00% 10.00% 20.00% $8,232 $49,392

10.08.01.510.20 STRUCTURE EXCAVATION 211.00 CY $60.00 $12,660 10.00% 10.00% 20.00% $2,532 $15,192

10.08.01.512.20 STRUCTURE EXCAVATION 169.00 CY $60.00 $10,140 10.00% 10.00% 20.00% $2,028 $12,168

10.08.01.516.20 STRUCTURE EXCAVATION 644.00 CY $60.00 $38,640 10.00% 10.00% 20.00% $7,728 $46,368

10.08.01.524.20 STRUCTURE EXCAVATION (MSE WALL) 8,629.00 CY $60.00 $517,740 10.00% 10.00% 20.00% $103,548 $621,288

10.08.01.526.20 STRUCTURE EXCAVATION 2,987.00 CY $60.00 $179,220 10.00% 10.00% 20.00% $35,844 $215,064

10.08.01.547.20 STRUCTURE EXCAVATION 86.00 CY $60.00 $5,160 10.00% 10.00% 20.00% $1,032 $6,192

10.08.01.550.20 STRUCTURE EXCAVATION (MSE WALL) 2,833.00 CY $60.00 $169,980 10.00% 10.00% 20.00% $33,996 $203,976

10.08.01.560.20 STRUCTURE EXCAVATION 2,204.00 CY $60.00 $132,240 10.00% 10.00% 20.00% $26,448 $158,688

10.08.01.580.20 STRUCTURE EXCAVATION 13,690.00 CY $60.00 $821,400 10.00% 10.00% 20.00% $164,280 $985,680

10.08.01.592.20 STRUCTURE EXCAVATION 722.00 CY $60.00 $43,320 10.00% 10.00% 20.00% $8,664 $51,984

10.08.01.598L.20 STRUCTURE EXCAVATION 247.00 CY $60.00 $14,820 10.00% 10.00% 20.00% $2,964 $17,784

10.08.01.598R.20 STRUCTURE EXCAVATION 554.00 CY $60.00 $33,240 10.00% 10.00% 20.00% $6,648 $39,888

10.08.01.648.20 STRUCTURE EXCAVATION 3,739.00 CY $60.00 $224,340 10.00% 10.00% 20.00% $44,868 $269,208

Sum

Average

118,098.00 $7,085,880

10.00% 10.00% 20.00%

$1,417,176 $8,503,056Summary for Group: 10.08.01

Group 10.08.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

STRUCTURAL BACKFILL Contingency

10.08.07.00 STRUCTURAL BACKFILL (MSE WALL) 2,100.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

10.08.07.211.10 STRUCTURAL BACKFILL 1,111.00 CY $52.00 $57,772 10.00% 10.00% 20.00% $11,554 $69,326

Monday, January 27, 2014 Page 17 of 140

Page 82: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.07.215.10 STRUCTURAL BACKFILL 5,359.00 CY $52.00 $278,668 10.00% 10.00% 20.00% $55,734 $334,402

10.08.07.271.10 STRUCTURAL BACKFILL 1,504.00 CY $52.00 $78,208 10.00% 10.00% 20.00% $15,642 $93,850

10.08.07.332.10 STRUCTURAL BACKFILL 9,666.00 CY $52.00 $502,632 10.00% 10.00% 20.00% $100,526 $603,158

10.08.07.376.10 STRUCTURAL BACKFILL 1,559.00 CY $52.00 $81,068 10.00% 10.00% 20.00% $16,214 $97,282

10.08.07.381.10 STRUCTURAL BACKFILL 238.00 CY $52.00 $12,376 10.00% 10.00% 20.00% $2,475 $14,851

10.08.07.388.10 STRUCTURAL BACKFILL 9,094.00 CY $52.00 $472,888 10.00% 10.00% 20.00% $94,578 $567,466

10.08.07.402.10 STRUCTURAL BACKFILL 3,752.00 CY $52.00 $195,104 10.00% 10.00% 20.00% $39,021 $234,125

10.08.07.416.10 STRUCTURAL BACKFILL 1,653.00 CY $52.00 $85,956 10.00% 10.00% 20.00% $17,191 $103,147

10.08.07.446.10 STRUCTURAL BACKFILL (MSE WALL) 5,174.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

10.08.07.449.10 STRUCTURAL BACKFILL (MSE WALL) 872.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

10.08.07.457.10 STRUCTURAL BACKFILL (MSE WALL) 2,322.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

10.08.07.465.10 STRUCTURAL BACKFILL 7,219.00 CY $52.00 $375,388 10.00% 10.00% 20.00% $75,078 $450,466

10.08.07.472.10 STRUCTURAL BACKFILL (MSE WALL) 10,045.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

10.08.07.475.10 STRUCTURAL BACKFILL (MSE WALL) 777.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

10.08.07.485.10 STRUCTURAL BACKFILL 1,211.00 CY $52.00 $62,972 10.00% 10.00% 20.00% $12,594 $75,566

10.08.07.498L.10 STRUCTURAL BACKFILL 3,035.00 CY $52.00 $157,820 10.00% 10.00% 20.00% $31,564 $189,384

10.08.07.498R.10 STRUCTURAL BACKFILL 5,011.00 CY $52.00 $260,572 10.00% 10.00% 20.00% $52,114 $312,686

10.08.07.500.10 STRUCTURAL BACKFILL (MSE WALL) 13,366.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

10.08.07.507.10 STRUCTURAL BACKFILL 418.00 CY $52.00 $21,736 10.00% 10.00% 20.00% $4,347 $26,083

10.08.07.510.10 STRUCTURAL BACKFILL 152.00 CY $52.00 $7,904 10.00% 10.00% 20.00% $1,581 $9,485

10.08.07.512.10 STRUCTURAL BACKFILL 116.00 CY $52.00 $6,032 10.00% 10.00% 20.00% $1,206 $7,238

10.08.07.516.10 STRUCTURAL BACKFILL 382.00 CY $52.00 $19,864 10.00% 10.00% 20.00% $3,973 $23,837

10.08.07.524.10 STRUCTURAL BACKFILL (MSE WALL) 12,558.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

10.08.07.526.10 STRUCTURAL BACKFILL 2,114.00 CY $52.00 $109,928 10.00% 10.00% 20.00% $21,986 $131,914

10.08.07.547.10 STRUCTURAL BACKFILL 66.00 CY $52.00 $3,432 10.00% 10.00% 20.00% $686 $4,118

10.08.07.550.10 STRUCTURAL BACKFILL (MSE WALL) 3,909.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

10.08.07.560.10 STRUCTURAL BACKFILL 1,559.00 CY $52.00 $81,068 10.00% 10.00% 20.00% $16,214 $97,282

10.08.07.580.10 STRUCTURAL BACKFILL 18,454.00 CY $52.00 $959,608 10.00% 10.00% 20.00% $191,922 $1,151,530

10.08.07.592.10 STRUCTURAL BACKFILL 792.00 CY $52.00 $41,184 10.00% 10.00% 20.00% $8,237 $49,421

Monday, January 27, 2014 Page 18 of 140

Page 83: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.07.598L.10 STRUCTURAL BACKFILL 224.00 CY $52.00 $11,648 10.00% 10.00% 20.00% $2,330 $13,978

10.08.07.598R.10 STRUCTURAL BACKFILL 668.00 CY $52.00 $34,736 10.00% 10.00% 20.00% $6,947 $41,683

10.08.07.648.10 STRUCTURAL BACKFILL 5,448.00 CY $52.00 $283,296 10.00% 10.00% 20.00% $56,659 $339,955

Sum

Average

131,928.00 $4,201,860

10.00% 10.00% 20.00%

$840,372 $5,042,232Summary for Group: 10.08.07

Group 10.08.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PERVIOUS BACKFILL Contingency

10.08.08.211.30 PERVIOUS BACKFILL 69.00 CY $49.00 $3,381 10.00% 10.00% 20.00% $676 $4,057

10.08.08.215.30 PERVIOUS BACKFILL 408.00 CY $49.00 $19,992 10.00% 10.00% 20.00% $3,998 $23,990

10.08.08.271.30 PERVIOUS BACKFILL 159.00 CY $49.00 $7,791 10.00% 10.00% 20.00% $1,558 $9,349

10.08.08.332.30 PERVIOUS BACKFILL 746.00 CY $49.00 $36,554 10.00% 10.00% 20.00% $7,311 $43,865

10.08.08.376.30 PERVIOUS BACKFILL 190.00 CY $49.00 $9,310 10.00% 10.00% 20.00% $1,862 $11,172

10.08.08.381.30 PERVIOUS BACKFILL 33.00 CY $49.00 $1,617 10.00% 10.00% 20.00% $323 $1,940

10.08.08.388.30 PERVIOUS BACKFILL 512.00 CY $49.00 $25,088 10.00% 10.00% 20.00% $5,018 $30,106

10.08.08.402.30 PERVIOUS BACKFILL 413.00 CY $49.00 $20,237 10.00% 10.00% 20.00% $4,047 $24,284

10.08.08.416.30 PERVIOUS BACKFILL 101.00 CY $49.00 $4,949 10.00% 10.00% 20.00% $990 $5,939

10.08.08.465.30 PERVIOUS BACKFILL 311.00 CY $49.00 $15,239 10.00% 10.00% 20.00% $3,048 $18,287

10.08.08.485.30 PERVIOUS BACKFILL 71.00 CY $49.00 $3,479 10.00% 10.00% 20.00% $696 $4,175

10.08.08.498L.30 PERVIOUS BACKFILL 281.00 CY $49.00 $13,769 10.00% 10.00% 20.00% $2,754 $16,523

10.08.08.498R.30 PERVIOUS BACKFILL 530.00 CY $49.00 $25,970 10.00% 10.00% 20.00% $5,194 $31,164

10.08.08.507.30 PERVIOUS BACKFILL 35.00 CY $49.00 $1,715 10.00% 10.00% 20.00% $343 $2,058

10.08.08.510.30 PERVIOUS BACKFILL 12.00 CY $49.00 $588 10.00% 10.00% 20.00% $118 $706

10.08.08.512.30 PERVIOUS BACKFILL 10.00 CY $49.00 $490 10.00% 10.00% 20.00% $98 $588

10.08.08.516.30 PERVIOUS BACKFILL 33.00 CY $49.00 $1,617 10.00% 10.00% 20.00% $323 $1,940

10.08.08.526.30 PERVIOUS BACKFILL 198.00 CY $49.00 $9,702 10.00% 10.00% 20.00% $1,940 $11,642

10.08.08.547.30 PERVIOUS BACKFILL 11.00 CY $49.00 $539 10.00% 10.00% 20.00% $108 $647

10.08.08.560.30 PERVIOUS BACKFILL 123.00 CY $49.00 $6,027 10.00% 10.00% 20.00% $1,205 $7,232

10.08.08.580.30 PERVIOUS BACKFILL 1,584.00 CY $49.00 $77,616 10.00% 10.00% 20.00% $15,523 $93,139

10.08.08.592.30 PERVIOUS BACKFILL 90.00 CY $49.00 $4,410 10.00% 10.00% 20.00% $882 $5,292

10.08.08.598L.30 PERVIOUS BACKFILL 25.00 CY $49.00 $1,225 10.00% 10.00% 20.00% $245 $1,470

Monday, January 27, 2014 Page 19 of 140

Page 84: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.08.598R.30 PERVIOUS BACKFILL 70.00 CY $49.00 $3,430 10.00% 10.00% 20.00% $686 $4,116

10.08.08.648.30 PERVIOUS BACKFILL 472.00 CY $49.00 $23,128 10.00% 10.00% 20.00% $4,626 $27,754

Sum

Average

6,487.00 $317,863

10.00% 10.00% 20.00%

$63,573 $381,436Summary for Group: 10.08.08

Group 10.08.09

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

STRUCTURAL CONCRETE Contingency

10.08.09.211.40 STRUCTURAL CONCRETE (RETAINING WALL) 306.00 CY $470.00 $143,820 10.00% 10.00% 20.00% $28,764 $172,584

10.08.09.215.40 STRUCTURAL CONCRETE (RETAINING WALL) 1,564.00 CY $470.00 $735,080 10.00% 10.00% 20.00% $147,016 $882,096

10.08.09.271.40 STRUCTURAL CONCRETE (RETAINING WALL) 773.00 CY $470.00 $363,310 10.00% 10.00% 20.00% $72,662 $435,972

10.08.09.332.40 STRUCTURAL CONCRETE (RETAINING WALL) 3,165.00 CY $470.00 $1,487,550 10.00% 10.00% 20.00% $297,510 $1,785,060

10.08.09.376.40 STRUCTURAL CONCRETE (RETAINING WALL) 708.00 CY $470.00 $332,760 10.00% 10.00% 20.00% $66,552 $399,312

10.08.09.381.40 STRUCTURAL CONCRETE (RETAINING WALL) 188.00 CY $470.00 $88,360 10.00% 10.00% 20.00% $17,672 $106,032

10.08.09.388.40 STRUCTURAL CONCRETE (RETAINING WALL) 3,613.00 CY $470.00 $1,698,110 10.00% 10.00% 20.00% $339,622 $2,037,732

10.08.09.402.40 STRUCTURAL CONCRETE (RETAINING WALL) 2,278.00 CY $470.00 $1,070,660 10.00% 10.00% 20.00% $214,132 $1,284,792

10.08.09.416.40 STRUCTURAL CONCRETE (RETAINING WALL) 759.00 CY $470.00 $356,730 10.00% 10.00% 20.00% $71,346 $428,076

10.08.09.465.40 STRUCTURAL CONCRETE (RETAINING WALL) 2,529.00 CY $470.00 $1,188,630 10.00% 10.00% 20.00% $237,726 $1,426,356

10.08.09.485.40 STRUCTURAL CONCRETE (RETAINING WALL) 525.00 CY $470.00 $246,750 10.00% 10.00% 20.00% $49,350 $296,100

10.08.09.498L.40 STRUCTURAL CONCRETE (RETAINING WALL) 1,106.00 CY $470.00 $519,820 10.00% 10.00% 20.00% $103,964 $623,784

10.08.09.498R.40 STRUCTURAL CONCRETE (RETAINING WALL) 2,359.00 CY $470.00 $1,108,730 10.00% 10.00% 20.00% $221,746 $1,330,476

10.08.09.507.40 STRUCTURAL CONCRETE (RETAINING WALL) 182.00 CY $470.00 $85,540 10.00% 10.00% 20.00% $17,108 $102,648

10.08.09.510.40 STRUCTURAL CONCRETE (RETAINING WALL) 62.00 CY $470.00 $29,140 10.00% 10.00% 20.00% $5,828 $34,968

10.08.09.512.40 STRUCTURAL CONCRETE (RETAINING WALL) 49.00 CY $470.00 $23,030 10.00% 10.00% 20.00% $4,606 $27,636

10.08.09.516.40 STRUCTURAL CONCRETE (RETAINING WALL) 167.00 CY $470.00 $78,490 10.00% 10.00% 20.00% $15,698 $94,188

10.08.09.526.40 STRUCTURAL CONCRETE (RETAINING WALL) 809.00 CY $470.00 $380,230 10.00% 10.00% 20.00% $76,046 $456,276

10.08.09.547.40 STRUCTURAL CONCRETE (RETAINING WALL) 56.00 CY $470.00 $26,320 10.00% 10.00% 20.00% $5,264 $31,584

10.08.09.560.40 STRUCTURAL CONCRETE (RETAINING WALL) 684.00 CY $470.00 $321,480 10.00% 10.00% 20.00% $64,296 $385,776

10.08.09.580.40 STRUCTURAL CONCRETE (RETAINING WALL) 7,152.00 CY $470.00 $3,361,440 10.00% 10.00% 20.00% $672,288 $4,033,728

10.08.09.582.40 STRUCTURAL CONCRETE (RETAINING WALL) 350.00 CY $470.00 $164,500 10.00% 10.00% 20.00% $32,900 $197,400

10.08.09.598L.40 STRUCTURAL CONCRETE (RETAINING WALL) 106.00 CY $470.00 $49,820 10.00% 10.00% 20.00% $9,964 $59,784

10.08.09.598R.40 STRUCTURAL CONCRETE (RETAINING WALL) 254.00 CY $470.00 $119,380 10.00% 10.00% 20.00% $23,876 $143,256

Monday, January 27, 2014 Page 20 of 140

Page 85: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.09.648.40 STRUCTURAL CONCRETE (RETAINING WALL) 2,172.00 CY $470.00 $1,020,840 10.00% 10.00% 20.00% $204,168 $1,225,008

Sum

Average

31,916.00 $15,000,520

10.00% 10.00% 20.00%

$3,000,104 $18,000,624Summary for Group: 10.08.09

Group 10.08.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BAR REINFORCING STEEL (RETAINING WALL) Contingency

10.08.10.211.60 BAR REINFORCING STEEL 38,614.00 LB $1.00 $38,614 10.00% 10.00% 20.00% $7,723 $46,337

10.08.10.215.60 BAR REINFORCING STEEL 186,260.00 LB $1.00 $186,260 10.00% 10.00% 20.00% $37,252 $223,512

10.08.10.271.60 BAR REINFORCING STEEL 93,098.00 LB $1.00 $93,098 10.00% 10.00% 20.00% $18,620 $111,718

10.08.10.332.60 BAR REINFORCING STEEL 508,332.00 LB $1.00 $508,332 10.00% 10.00% 20.00% $101,666 $609,998

10.08.10.376.60 BAR REINFORCING STEEL 84,988.00 LB $1.00 $84,988 10.00% 10.00% 20.00% $16,998 $101,986

10.08.10.381.60 BAR REINFORCING STEEL 24,349.00 LB $1.00 $24,349 10.00% 10.00% 20.00% $4,870 $29,219

10.08.10.388.60 BAR REINFORCING STEEL 400,965.00 LB $1.00 $400,965 10.00% 10.00% 20.00% $80,193 $481,158

10.08.10.402.60 BAR REINFORCING STEEL 463,226.00 LB $1.00 $463,226 10.00% 10.00% 20.00% $92,645 $555,871

10.08.10.416.60 BAR REINFORCING STEEL 62,851.00 LB $1.00 $62,851 10.00% 10.00% 20.00% $12,570 $75,421

10.08.10.465.60 BAR REINFORCING STEEL 210,009.00 LB $1.00 $210,009 10.00% 10.00% 20.00% $42,002 $252,011

10.08.10.485.60 BAR REINFORCING STEEL 42,113.00 LB $1.00 $42,113 10.00% 10.00% 20.00% $8,423 $50,536

10.08.10.498L.60 BAR REINFORCING STEEL 216,106.00 LB $1.00 $216,106 10.00% 10.00% 20.00% $43,221 $259,327

10.08.10.498R.60 BAR REINFORCING STEEL 414,163.00 LB $1.00 $414,163 10.00% 10.00% 20.00% $82,833 $496,996

10.08.10.507.60 BAR REINFORCING STEEL 16,773.00 LB $1.00 $16,773 10.00% 10.00% 20.00% $3,355 $20,128

10.08.10.510.60 BAR REINFORCING STEEL 5,858.00 LB $1.00 $5,858 10.00% 10.00% 20.00% $1,172 $7,030

10.08.10.512.60 BAR REINFORCING STEEL 4,679.00 LB $1.00 $4,679 10.00% 10.00% 20.00% $936 $5,615

10.08.10.516.60 BAR REINFORCING STEEL 15,731.00 LB $1.00 $15,731 10.00% 10.00% 20.00% $3,146 $18,877

10.08.10.526.60 BAR REINFORCING STEEL 94,255.00 LB $1.00 $94,255 10.00% 10.00% 20.00% $18,851 $113,106

10.08.10.547.60 BAR REINFORCING STEEL 5,026.00 LB $1.00 $5,026 10.00% 10.00% 20.00% $1,005 $6,031

10.08.10.560.60 BAR REINFORCING STEEL 91,479.00 LB $1.00 $91,479 10.00% 10.00% 20.00% $18,296 $109,775

10.08.10.580.60 BAR REINFORCING STEEL 781,440.00 LB $1.00 $781,440 10.00% 10.00% 20.00% $156,288 $937,728

10.08.10.592.60 BAR REINFORCING STEEL 53,908.00 LB $1.00 $53,908 10.00% 10.00% 20.00% $10,782 $64,690

10.08.10.598L.60 BAR REINFORCING STEEL 13,490.00 LB $1.00 $13,490 10.00% 10.00% 20.00% $2,698 $16,188

10.08.10.598R.60 BAR REINFORCING STEEL 47,505.00 LB $1.00 $47,505 10.00% 10.00% 20.00% $9,501 $57,006

10.08.10.648.60 BAR REINFORCING STEEL 237,135.00 LB $1.00 $237,135 10.00% 10.00% 20.00% $47,427 $284,562

Monday, January 27, 2014 Page 21 of 140

Page 86: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

4,112,353.00 $4,112,353

10.00% 10.00% 20.00%

$822,471 $4,934,824Summary for Group: 10.08.10

Group 10.08.11

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MSE WALL Contingency

10.08.11.00 EARTH RETAINING STRUCTURE (MSE WALL-TEMP SHOOFLY) 9,060.00 SF $82.00 $742,920 10.00% 10.00% 20.00% $148,584 $891,504

10.08.11.446.91 EARTH RETAINING STRUCTURE (MSE WALL) 16,439.00 SF $72.00 $1,183,608 10.00% 10.00% 20.00% $236,722 $1,420,330

10.08.11.449.91 EARTH RETAINING STRUCTURE (MSE WALL) 2,598.00 SF $72.00 $187,056 10.00% 10.00% 20.00% $37,411 $224,467

10.08.11.457.91 EARTH RETAINING STRUCTURE (MSE WALL) 6,490.00 SF $72.00 $467,280 10.00% 10.00% 20.00% $93,456 $560,736

10.08.11.472.91 EARTH RETAINING STRUCTURE (MSE WALL) 16,060.00 SF $72.00 $1,156,320 10.00% 10.00% 20.00% $231,264 $1,387,584

10.08.11.475.91 EARTH RETAINING STRUCTURE (MSE WALL) 2,801.00 SF $72.00 $201,672 10.00% 10.00% 20.00% $40,334 $242,006

10.08.11.500.91 EARTH RETAINING STRUCTURE (MSE WALL) 28,658.00 SF $72.00 $2,063,376 10.00% 10.00% 20.00% $412,675 $2,476,051

10.08.11.524.91 EARTH RETAINING STRUCTURE (MSE WALL) 30,752.00 SF $72.00 $2,214,144 10.00% 10.00% 20.00% $442,829 $2,656,973

10.08.11.550.91 EARTH RETAINING STRUCTURE (MSE WALL) 5,649.00 SF $72.00 $406,728 10.00% 10.00% 20.00% $81,346 $488,074

Sum

Average

118,507.00 $8,623,104

10.00% 10.00% 20.00%

$1,724,621 $10,347,725Summary for Group: 10.08.11

Group 10.08.13

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PERMANENT BMP (RETAINED CUT/FILL) Contingency

10.08.13 PERMANENT BMP (RETAINED CUT/FILL) 1.00 LS $1,550,000.00 $1,550,000 0.00% 20.00% 20.00% $310,000 $1,860,000

Sum

Average

1.00 $1,550,000

0.00% 20.00% 20.00%

$310,000 $1,860,000Summary for Group: 10.08.13

Group 10.08.17

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MINOR CONCRETE (RETAINING WALL) Contingency

10.08.17.446.70 MINOR CONCRETE (COPING) 117.00 CY $365.00 $42,705 10.00% 10.00% 20.00% $8,541 $51,246

10.08.17.449.70 MINOR CONCRETE (COPING) 17.00 CY $365.00 $6,205 10.00% 10.00% 20.00% $1,241 $7,446

10.08.17.457.70 MINOR CONCRETE (COPING) 34.00 CY $365.00 $12,410 10.00% 10.00% 20.00% $2,482 $14,892

10.08.17.472.70 MINOR CONCRETE (COPING) 57.00 CY $365.00 $20,805 10.00% 10.00% 20.00% $4,161 $24,966

10.08.17.475.70 MINOR CONCRETE (COPING) 20.00 CY $365.00 $7,300 10.00% 10.00% 20.00% $1,460 $8,760

10.08.17.500.70 MINOR CONCRETE (COPING) 137.00 CY $365.00 $50,005 10.00% 10.00% 20.00% $10,001 $60,006

10.08.17.509.70 MINOR CONCRETE (GUTTER) 7.00 CY $365.00 $2,555 10.00% 10.00% 20.00% $511 $3,066

10.08.17.509.70 MINOR CONCRETE (SLOPE PAVING) 22.00 CY $365.00 $8,030 10.00% 10.00% 20.00% $1,606 $9,636

10.08.17.514.70 MINOR CONCRETE (SLOPE PAVING) 24.00 CY $365.00 $8,760 10.00% 10.00% 20.00% $1,752 $10,512

10.08.17.514.70 MINOR CONCRETE (GUTTER) 10.00 CY $365.00 $3,650 10.00% 10.00% 20.00% $730 $4,380

Monday, January 27, 2014 Page 22 of 140

Page 87: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.17.524.70 MINOR CONCRETE (COPING) 162.00 CY $365.00 $59,130 10.00% 10.00% 20.00% $11,826 $70,956

10.08.17.550.70 MINOR CONCRETE (COPING) 23.00 CY $365.00 $8,395 10.00% 10.00% 20.00% $1,679 $10,074

Sum

Average

630.00 $229,950

10.00% 10.00% 20.00%

$45,990 $275,940Summary for Group: 10.08.17

Group 10.08.18

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CABLE RAILING Contingency

10.08.18.00 TEMPORARY RAILING - SHOOFLY 906.00 LF $25.00 $22,650 20.00% 10.00% 30.00% $6,795 $29,445

10.08.18.211.70 CABLE RAILING 359.00 LF $25.00 $8,975 10.00% 10.00% 20.00% $1,795 $10,770

10.08.18.215.70 CABLE RAILING 1,439.00 LF $25.00 $35,975 10.00% 10.00% 20.00% $7,195 $43,170

10.08.18.271.70 CABLE RAILING 822.00 LF $25.00 $20,550 10.00% 10.00% 20.00% $4,110 $24,660

10.08.18.332.70 CABLE RAILING 2,613.00 LF $25.00 $65,325 10.00% 10.00% 20.00% $13,065 $78,390

10.08.18.376.70 CABLE RAILING 193.00 LF $25.00 $4,825 10.00% 10.00% 20.00% $965 $5,790

10.08.18.381.70 CABLE RAILING 261.00 LF $25.00 $6,525 10.00% 10.00% 20.00% $1,305 $7,830

10.08.18.388.70 CABLE RAILING 1,242.00 LF $25.00 $31,050 10.00% 10.00% 20.00% $6,210 $37,260

10.08.18.402.70 CABLE RAILING 1,023.00 LF $25.00 $25,575 10.00% 10.00% 20.00% $5,115 $30,690

10.08.18.416.70 CABLE RAILING 450.00 LF $25.00 $11,250 10.00% 10.00% 20.00% $2,250 $13,500

10.08.18.446.70 CABLE RAILING 1,652.00 LF $25.00 $41,300 10.00% 10.00% 20.00% $8,260 $49,560

10.08.18.449.70 CABLE RAILING 233.00 LF $25.00 $5,825 10.00% 10.00% 20.00% $1,165 $6,990

10.08.18.457.70 CABLE RAILING 484.00 LF $25.00 $12,100 10.00% 10.00% 20.00% $2,420 $14,520

10.08.18.465.70 CABLE RAILING 1,416.00 LF $25.00 $35,400 10.00% 10.00% 20.00% $7,080 $42,480

10.08.18.472.70 CABLE RAILING 806.00 LF $25.00 $20,150 10.00% 10.00% 20.00% $4,030 $24,180

10.08.18.475.70 CABLE RAILING 276.00 LF $25.00 $6,900 10.00% 10.00% 20.00% $1,380 $8,280

10.08.18.485.70 CABLE RAILING 319.00 LF $25.00 $7,975 10.00% 10.00% 20.00% $1,595 $9,570

10.08.18.498L.70 CABLE RAILING 513.00 LF $25.00 $12,825 10.00% 10.00% 20.00% $2,565 $15,390

10.08.18.498R.70 CABLE RAILING 1,240.00 LF $25.00 $31,000 10.00% 10.00% 20.00% $6,200 $37,200

10.08.18.500.70 CABLE RAILING 1,925.00 LF $25.00 $48,125 10.00% 10.00% 20.00% $9,625 $57,750

10.08.18.507.70 CABLE RAILING 144.00 LF $25.00 $3,600 10.00% 10.00% 20.00% $720 $4,320

10.08.18.510.70 CABLE RAILING 40.00 LF $25.00 $1,000 10.00% 10.00% 20.00% $200 $1,200

10.08.18.512.70 CABLE RAILING 32.00 LF $25.00 $800 10.00% 10.00% 20.00% $160 $960

10.08.18.516.70 CABLE RAILING 128.00 LF $25.00 $3,200 10.00% 10.00% 20.00% $640 $3,840

Monday, January 27, 2014 Page 23 of 140

Page 88: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.18.524.70 CABLE RAILING 2,283.00 LF $25.00 $57,075 10.00% 10.00% 20.00% $11,415 $68,490

10.08.18.526.70 CABLE RAILING 749.00 LF $25.00 $18,725 10.00% 10.00% 20.00% $3,745 $22,470

10.08.18.547.70 CABLE RAILING 53.00 LF $25.00 $1,325 10.00% 10.00% 20.00% $265 $1,590

10.08.18.550.70 CABLE RAILING 323.00 LF $25.00 $8,075 10.00% 10.00% 20.00% $1,615 $9,690

10.08.18.560.70 CABLE RAILING 781.00 LF $25.00 $19,525 10.00% 10.00% 20.00% $3,905 $23,430

10.08.18.580.70 CABLE RAILING 852.00 LF $25.00 $21,300 10.00% 10.00% 20.00% $4,260 $25,560

10.08.18.592.70 CABLE RAILING 243.00 LF $25.00 $6,075 10.00% 10.00% 20.00% $1,215 $7,290

10.08.18.598L.70 CABLE RAILING 128.00 LF $25.00 $3,200 10.00% 10.00% 20.00% $640 $3,840

10.08.18.598R.70 CABLE RAILING 128.00 LF $25.00 $3,200 10.00% 10.00% 20.00% $640 $3,840

Sum

Average

24,056.00 $601,400

10.30% 10.00% 20.30%

$122,545 $723,945Summary for Group: 10.08.18

Group 10.08.19

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ARCHITECTURAL TREATMENT Contingency

10.08.19.211.50 ARCHITECTURAL TREATMENT 1,077.00 SF $14.00 $15,078 10.00% 10.00% 20.00% $3,016 $18,094

10.08.19.215.50 ARCHITECTURAL TREATMENT 4,317.00 SF $14.00 $60,438 10.00% 10.00% 20.00% $12,088 $72,526

10.08.19.271.50 ARCHITECTURAL TREATMENT 2,466.00 SF $14.00 $34,524 10.00% 10.00% 20.00% $6,905 $41,429

10.08.19.332.50 ARCHITECTURAL TREATMENT 7,839.00 SF $14.00 $109,746 10.00% 10.00% 20.00% $21,949 $131,695

10.08.19.376.50 ARCHITECTURAL TREATMENT 1,824.00 SF $14.00 $25,536 10.00% 10.00% 20.00% $5,107 $30,643

10.08.19.381.50 ARCHITECTURAL TREATMENT 783.00 SF $14.00 $10,962 10.00% 10.00% 20.00% $2,192 $13,154

10.08.19.388.50 ARCHITECTURAL TREATMENT 3,727.00 SF $14.00 $52,178 10.00% 10.00% 20.00% $10,436 $62,614

10.08.19.402.50 ARCHITECTURAL TREATMENT 15,975.00 SF $14.00 $223,650 10.00% 10.00% 20.00% $44,730 $268,380

10.08.19.416.50 ARCHITECTURAL TREATMENT 1,350.00 SF $14.00 $18,900 10.00% 10.00% 20.00% $3,780 $22,680

10.08.19.446.50 ARCHITECTURAL TREATMENT (MSE WALL) 16,439.00 SF $4.00 $65,756 10.00% 10.00% 20.00% $13,151 $78,907

10.08.19.449.50 ARCHITECTURAL TREATMENT (MSE WALL) 2,598.00 SF $4.00 $10,392 10.00% 10.00% 20.00% $2,078 $12,470

10.08.19.457.50 ARCHITECTURAL TREATMENT (MSE WALL) 6,490.00 SF $4.00 $25,960 10.00% 10.00% 20.00% $5,192 $31,152

10.08.19.465.50 ARCHITECTURAL TREATMENT 5,232.00 SF $14.00 $73,248 10.00% 10.00% 20.00% $14,650 $87,898

10.08.19.472.50 ARCHITECTURAL TREATMENT (MSE WALL) 16,060.00 SF $4.00 $64,240 10.00% 10.00% 20.00% $12,848 $77,088

10.08.19.475.50 ARCHITECTURAL TREATMENT (MSE WALL) 2,801.00 SF $4.00 $11,204 10.00% 10.00% 20.00% $2,241 $13,445

10.08.19.485.50 ARCHITECTURAL TREATMENT 956.00 SF $14.00 $13,384 10.00% 10.00% 20.00% $2,677 $16,061

10.08.19.498L.50 ARCHITECTURAL TREATMENT 1,538.00 SF $14.00 $21,532 10.00% 10.00% 20.00% $4,306 $25,838

Monday, January 27, 2014 Page 24 of 140

Page 89: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.19.498R.50 ARCHITECTURAL TREATMENT 3,719.00 SF $14.00 $52,066 10.00% 10.00% 20.00% $10,413 $62,479

10.08.19.500.50 ARCHITECTURAL TREATMENT (MSE WALL) 28,658.00 SF $4.00 $114,632 10.00% 10.00% 20.00% $22,926 $137,558

10.08.19.507.50 ARCHITECTURAL TREATMENT 1,171.00 SF $14.00 $16,394 10.00% 10.00% 20.00% $3,279 $19,673

10.08.19.510.50 ARCHITECTURAL TREATMENT 353.00 SF $14.00 $4,942 10.00% 10.00% 20.00% $988 $5,930

10.08.19.512.50 ARCHITECTURAL TREATMENT 290.00 SF $14.00 $4,060 10.00% 10.00% 20.00% $812 $4,872

10.08.19.516.50 ARCHITECTURAL TREATMENT 1,036.00 SF $14.00 $14,504 10.00% 10.00% 20.00% $2,901 $17,405

10.08.19.524.50 ARCHITECTURAL TREATMENT (MSE WALL) 30,752.00 SF $4.00 $123,008 10.00% 10.00% 20.00% $24,602 $147,610

10.08.19.526.50 ARCHITECTURAL TREATMENT 7,965.00 LB $14.00 $111,510 10.00% 10.00% 20.00% $22,302 $133,812

10.08.19.547.50 ARCHITECTURAL TREATMENT 159.00 SF $14.00 $2,226 10.00% 10.00% 20.00% $445 $2,671

10.08.19.550.50 ARCHITECTURAL TREATMENT (MSE WALL) 5,649.00 SF $4.00 $22,596 10.00% 10.00% 20.00% $4,519 $27,115

10.08.19.560.50 ARCHITECTURAL TREATMENT 2,344.00 SF $14.00 $32,816 10.00% 10.00% 20.00% $6,563 $39,379

10.08.19.580.50 ARCHITECTURAL TREATMENT 46,862.00 SF $14.00 $656,068 10.00% 10.00% 20.00% $131,214 $787,282

10.08.19.592.50 ARCHITECTURAL TREATMENT 3,281.00 SF $14.00 $45,934 10.00% 10.00% 20.00% $9,187 $55,121

10.08.19.598L.50 ARCHITECTURAL TREATMENT 1,114.00 SF $14.00 $15,596 10.00% 10.00% 20.00% $3,119 $18,715

10.08.19.598R.50 ARCHITECTURAL TREATMENT 2,341.00 SF $14.00 $32,774 10.00% 10.00% 20.00% $6,555 $39,329

10.08.19.648.50 ARCHITECTURAL TREATMENT 14,586.00 SF $14.00 $204,204 10.00% 10.00% 20.00% $40,841 $245,045

Sum

Average

241,752.00 $2,290,058

10.00% 10.00% 20.00%

$458,012 $2,748,070Summary for Group: 10.08.19

Group 10.08.21

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GUIDEWAY EXCAVATION Contingency

10.08.21.190101 GUIDEWAY EXCAVATION 21,718.00 CY $18.00 $390,924 10.00% 5.00% 15.00% $58,639 $449,563

10.08.21.190101 GUIDEWAY EXCAVATION 19,564.00 CY $18.00 $352,152 10.00% 5.00% 15.00% $52,823 $404,975

10.08.21.190101 GUIDEWAY EXCAVATION 19,250.00 CY $18.00 $346,500 10.00% 5.00% 15.00% $51,975 $398,475

10.08.21.190101 GUIDEWAY EXCAVATION 3,798.45 CY $18.00 $68,372 10.00% 5.00% 15.00% $10,256 $78,628

Sum

Average

64,330.45 $1,157,948

10.00% 5.00% 15.00%

$173,692 $1,331,640Summary for Group: 10.08.21

Group 10.08.26

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CHAIN LINK FENCE Contingency

10.08.26 CHAIN LINK FENCE (CL-7) 820.00 LF $24.00 $19,680 10.00% 10.00% 20.00% $3,936 $23,616

10.08.26.465.87 CHAIN LINK FENCE (CL-6) 101.00 LF $19.00 $1,919 10.00% 10.00% 20.00% $384 $2,303

10.08.26.547.87 CHAIN LINK FENCE (CL-6) 53.00 LF $19.00 $1,007 10.00% 10.00% 20.00% $201 $1,208

Monday, January 27, 2014 Page 25 of 140

Page 90: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.26.550.87 CHAIN LINK FENCE (CL-6) 323.00 LF $19.00 $6,137 10.00% 10.00% 20.00% $1,227 $7,364

10.08.26.567.87 CHAIN LINK FENCE (CL-6) 1,314.00 LF $19.00 $24,966 10.00% 10.00% 20.00% $4,993 $29,959

Sum

Average

2,611.00 $53,709

10.00% 10.00% 20.00%

$10,742 $64,451Summary for Group: 10.08.26

Group 10.08.29

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SOUND/SCREEN WALL Contingency

10.08.29.648.71 BLOCK WALL (8' HIGH) (WALL 648R-F) 4,935.00 SF $25.00 $123,375 10.00% 10.00% 20.00% $24,675 $148,050

Sum

Average

4,935.00 $123,375

10.00% 10.00% 20.00%

$24,675 $148,050Summary for Group: 10.08.29

Group 10.08.30

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CONCRETE BARRIER Contingency

10.08.30.465.73 CONCRETE BARRIER 328.00 LF $53.00 $17,384 10.00% 10.00% 20.00% $3,477 $20,861

Sum

Average

328.00 $17,384

10.00% 10.00% 20.00%

$3,477 $20,861Summary for Group: 10.08.30

Group 10.08.31

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TIEBACK WALLS Contingency

10.08.31.509.12 STRUCTURAL BACKFILL (TIEBACK WALL) 44.00 CY $73.00 $3,212 10.00% 10.00% 20.00% $642 $3,854

10.08.31.509.22 STRUCTURE EXCAVATION (TIEBACK WALL) 499.00 CY $60.00 $29,940 10.00% 10.00% 20.00% $5,988 $35,928

10.08.31.509.42 STRUCTURAL CONCRETE (TIEBACK WALL) 147.00 CY $620.00 $91,140 10.00% 10.00% 20.00% $18,228 $109,368

10.08.31.509.52 ARCHITECTURAL TREATMENT (TIEBACK WALL) 4,759.00 SF $14.00 $66,626 10.00% 10.00% 20.00% $13,325 $79,951

10.08.31.509.62 BAR REINFORCING STEEL (TIEBACK WALL) 57,301.00 LB $1.00 $57,301 10.00% 10.00% 20.00% $11,460 $68,761

10.08.31.509.70 CABLE RAILING 208.00 LF $25.00 $5,200 10.00% 10.00% 20.00% $1,040 $6,240

10.08.31.509.80 TIEBACK ANCHORS 119.00 EA $2,160.00 $257,040 10.00% 10.00% 20.00% $51,408 $308,448

10.08.31.509.81 SHOTCRETE 169.00 CY $623.00 $105,287 10.00% 10.00% 20.00% $21,057 $126,344

10.08.31.514.12 STRUCTURAL BACKFILL (TIEBACK WALL) 64.00 CY $73.00 $4,672 10.00% 10.00% 20.00% $934 $5,606

10.08.31.514.22 STRUCTURE EXCAVATION (TIEBACK WALL) 493.00 CY $60.00 $29,580 10.00% 10.00% 20.00% $5,916 $35,496

10.08.31.514.42 STRUCTURAL CONCRETE (TIEBACK WALL) 145.00 CY $620.00 $89,900 10.00% 10.00% 20.00% $17,980 $107,880

10.08.31.514.52 ARCHITECTURAL TREATMENT (TIEBACK WALL) 4,697.00 SF $14.00 $65,758 10.00% 10.00% 20.00% $13,152 $78,910

10.08.31.514.62 BAR REINFORCING STEEL (TIEBACK WALL) 57,638.00 LB $1.00 $57,638 10.00% 10.00% 20.00% $11,528 $69,166

10.08.31.514.70 CABLE RAILING 304.00 LF $25.00 $7,600 10.00% 10.00% 20.00% $1,520 $9,120

10.08.31.514.80 TIEBACK ANCHORS 134.00 EA $2,160.00 $289,440 10.00% 10.00% 20.00% $57,888 $347,328

10.08.31.514.81 SHOTCRETE 160.00 CY $623.00 $99,680 10.00% 10.00% 20.00% $19,936 $119,616

Monday, January 27, 2014 Page 26 of 140

Page 91: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.31.567.12 STRUCTURAL BACKFILL (TIEBACK WALL) 182.00 CY $73.00 $13,286 10.00% 10.00% 20.00% $2,657 $15,943

10.08.31.567.22 STRUCTURE EXCAVATION (TIEBACK WALL) 1,273.00 CY $60.00 $76,380 10.00% 10.00% 20.00% $15,276 $91,656

10.08.31.567.40 STRUCTURAL CONCRETE BACKFILL (TIEBACK WALL) 510.00 CY $470.00 $239,700 10.00% 10.00% 20.00% $47,940 $287,640

10.08.31.567.42 STRUCTURAL CONCRETE (TIEBACK WALL) 995.00 CY $620.00 $616,900 10.00% 10.00% 20.00% $123,380 $740,280

10.08.31.567.43 LEAN CONCRETE BACKFILL 1,273.00 CY $172.00 $218,956 10.00% 10.00% 20.00% $43,791 $262,747

10.08.31.567.52 ARCHITECTURAL TREATMENT (TIEBACK WALL) 26,858.00 SF $14.00 $376,012 10.00% 10.00% 20.00% $75,202 $451,214

10.08.31.567.62 BAR REINFORCING STEEL (TIEBACK WALL) 174,079.00 LB $1.00 $174,079 10.00% 10.00% 20.00% $34,816 $208,895

10.08.31.567.70 CABLE RAILING 1,314.00 LF $25.00 $32,850 10.00% 10.00% 20.00% $6,570 $39,420

10.08.31.567.80 TIEBACK ANCHORS 450.00 EA $2,160.00 $972,000 10.00% 10.00% 20.00% $194,400 $1,166,400

10.08.31.567.82 STEEL SOLDIER PILE (HP 14X73) 8,651.00 LF $80.00 $692,080 10.00% 10.00% 20.00% $138,416 $830,496

10.08.31.567.83 48" DRILLED HOLE 3,830.00 LF $100.00 $383,000 10.00% 10.00% 20.00% $76,600 $459,600

10.08.31.567.84 TIMBER LAGGING 121.00MFBM $1,194.00 $144,474 10.00% 10.00% 20.00% $28,895 $173,369

10.08.31.567.85 CLEAN AND PAINT SOLDIER PILE 1.00 LS $6,083.00 $6,083 10.00% 10.00% 20.00% $1,217 $7,300

Sum

Average

346,418.00 $5,205,814

10.00% 10.00% 20.00%

$1,041,163 $6,246,977Summary for Group: 10.08.31

Group 10.08.32

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

RETAINING WALL 648R-F REINFORCED DESIGN (DIFF.) Contingency

10.08.32.648.460210 GROUND ANCHOR 99.00 EA $11,490.00 $1,137,510 10.00% 10.00% 20.00% $227,502 $1,365,012

10.08.32.648.490605 36" CIDH CONCRETE PILING 2,156.00 LF $507.00 $1,093,092 10.00% 10.00% 20.00% $218,618 $1,311,710

10.08.32.648.510060 STRUCTURAL CONCRETE (RETAINING WALL) -403.00 CY $470.00 ($189,410) 10.00% 10.00% 20.00% ($37,882) ($227,292)

10.08.32.648.520103 BAR REINFORCING STEEL -43,661.00 LB $1.00 ($43,661) 10.00% 10.00% 20.00% ($8,732) ($52,393)

10.08.32.648.520122 STRAY CURRENT PROTECTION -802.00 SF $2.00 ($1,604) 10.00% 10.00% 20.00% ($321) ($1,925)

Sum

Average

-42,611.00 $1,995,927

10.00% 10.00% 20.00%

$399,185 $2,395,112Summary for Group: 10.08.32

Group 10.08.33

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GUIDEWAY DRAINAGE SYSTEMS Contingency

10.08.33.01 UNDERDRAIN (GUIDEWAY) 1,225.00 LF $30.00 $36,750 15.00% 15.00% 30.00% $11,025 $47,775

10.08.33.01 UNDERDRAIN (GUIDEWAY) 11,775.00 LF $30.00 $353,250 15.00% 15.00% 30.00% $105,975 $459,225

10.08.33.01 UNDERDRAIN (GUIDEWAY) 6,315.00 LF $30.00 $189,450 15.00% 15.00% 30.00% $56,835 $246,285

10.08.33.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 4,660.00 LF $27.00 $125,820 15.00% 15.00% 30.00% $37,746 $163,566

10.08.33.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 8,455.00 LF $27.00 $228,285 15.00% 15.00% 30.00% $68,486 $296,771

Monday, January 27, 2014 Page 27 of 140

Page 92: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.33.02 DRAINAGE DITCH, SDRSD D-75 (GUIDEWAY) 4,320.00 LF $27.00 $116,640 15.00% 15.00% 30.00% $34,992 $151,632

10.08.33.101 18" RCP STORM DRAIN 95.00 LF $120.00 $11,400 15.00% 15.00% 30.00% $3,420 $14,820

10.08.33.101 18" RCP STORM DRAIN 10.00 LF $120.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

10.08.33.101 18" RCP STORM DRAIN 70.00 LF $120.00 $8,400 15.00% 15.00% 30.00% $2,520 $10,920

10.08.33.101 18" RCP STORM DRAIN 60.00 LF $120.00 $7,200 15.00% 15.00% 30.00% $2,160 $9,360

10.08.33.102 24" RCP STORM DRAIN 35.00 LF $170.00 $5,950 15.00% 15.00% 30.00% $1,785 $7,735

10.08.33.102 24" RCP STORM DRAIN 120.00 LF $170.00 $20,400 15.00% 15.00% 30.00% $6,120 $26,520

10.08.33.102 24" RCP STORM DRAIN 20.00 LF $170.00 $3,400 15.00% 15.00% 30.00% $1,020 $4,420

10.08.33.102 24" RCP STORM DRAIN 10.00 LF $170.00 $1,700 15.00% 15.00% 30.00% $510 $2,210

10.08.33.103 30" RCP STORM DRAIN 35.00 LF $210.00 $7,350 15.00% 15.00% 30.00% $2,205 $9,555

10.08.33.103 30" RCP STORM DRAIN (JACKED) 25.00 LF $1,050.00 $26,250 15.00% 20.00% 35.00% $9,188 $35,438

10.08.33.103 30" RCP STORM DRAIN 21.00 LF $210.00 $4,410 15.00% 15.00% 30.00% $1,323 $5,733

10.08.33.103 30" RCP STORM DRAIN 30.00 LF $210.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

10.08.33.103 30" RCP STORM DRAIN 40.00 LF $210.00 $8,400 15.00% 15.00% 30.00% $2,520 $10,920

10.08.33.104 36" RCP STORM DRAIN 85.00 LF $230.00 $19,550 15.00% 15.00% 30.00% $5,865 $25,415

10.08.33.104 36" RCP STORM DRAIN 220.00 LF $230.00 $50,600 15.00% 15.00% 30.00% $15,180 $65,780

10.08.33.104 36" RCP STORM DRAIN 40.00 LF $230.00 $9,200 15.00% 15.00% 30.00% $2,760 $11,960

10.08.33.104 36" RCP STORM DRAIN 35.00 LF $230.00 $8,050 15.00% 15.00% 30.00% $2,415 $10,465

10.08.33.104 36" RCP STORM DRAIN 80.00 LF $230.00 $18,400 15.00% 15.00% 30.00% $5,520 $23,920

10.08.33.104 36" RCP STORM DRAIN 100.00 LF $230.00 $23,000 15.00% 15.00% 30.00% $6,900 $29,900

10.08.33.106 48" RCP STORM DRAIN 100.00 LF $290.00 $29,000 15.00% 15.00% 30.00% $8,700 $37,700

10.08.33.107 54" RCP STORM DRAIN 60.00 LF $470.00 $28,200 15.00% 15.00% 30.00% $8,460 $36,660

10.08.33.107 54" RCP STORM DRAIN 100.00 LF $470.00 $47,000 15.00% 15.00% 30.00% $14,100 $61,100

10.08.33.115 12" PVC STORM DRAIN 40.00 LF $100.00 $4,000 15.00% 15.00% 30.00% $1,200 $5,200

10.08.33.115 12" PVC STORM DRAIN 45.00 LF $100.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

10.08.33.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.08.33.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.08.33.201 TYPE A-4 SD CLEANOUT 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.08.33.204 4' MOD TYPE B CURB INLET 1.00 EA $5,200.00 $5,200 10.00% 15.00% 25.00% $1,300 $6,500

Monday, January 27, 2014 Page 28 of 140

Page 93: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.08.33.205 MOD TYPE F CATCH BASIN 1.00 EA $5,530.00 $5,530 10.00% 15.00% 25.00% $1,383 $6,913

10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.08.33.205 TYPE F CATCH BASIN 1.00 EA $5,120.00 $5,120 10.00% 15.00% 25.00% $1,280 $6,400

10.08.33.205 TYPE F CATCH BASIN 1.00 EA $6,120.00 $6,120 10.00% 15.00% 25.00% $1,530 $7,650

10.08.33.210 EXTEND HEADWALL 1.00 EA $2,800.00 $2,800 15.00% 15.00% 30.00% $840 $3,640

10.08.33.210 MOD HEADWALL WITH WINGWALLS 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.08.33.210 TYPE A STRAIGHT HEADWALL 1.00 EA $7,000.00 $7,000 10.00% 15.00% 25.00% $1,750 $8,750

10.08.33.210 MOD HEADWALL WITH WINGWALLS 1.00 EA $4,500.00 $4,500 10.00% 15.00% 25.00% $1,125 $5,625

10.08.33.210 TYPE A STRAIGHT HEADWALL 1.00 EA $7,000.00 $7,000 10.00% 15.00% 25.00% $1,750 $8,750

10.08.33.211 MOD TYPE A STRAIGHT HEADWALL 1.00 EA $5,500.00 $5,500 10.00% 15.00% 25.00% $1,375 $6,875

10.08.33.213 JUNCTION STRUCTURE (SPECIAL DETAIL) 1.00 EA $15,000.00 $15,000 0.00% 15.00% 15.00% $2,250 $17,250

10.08.33.215 WALL DRAIN 1.00 EA $2,000.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

10.08.33.215 WALL DRAIN 1.00 EA $2,000.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

10.08.33.501 CONCRETE LUG, SDRSD SDD-113 1.00 EA $1,100.00 $1,100 15.00% 15.00% 30.00% $330 $1,430

10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.08.33.502 PIPE COLLAR 2.00 EA $1,800.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680

10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.08.33.502 PIPE COLLAR 3.00 EA $1,800.00 $5,400 15.00% 15.00% 30.00% $1,620 $7,020

Monday, January 27, 2014 Page 29 of 140

Page 94: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.33.502 PIPE COLLAR 1.00 EA $1,800.00 $1,800 15.00% 15.00% 30.00% $540 $2,340

10.08.33.502 PIPE COLLAR 2.00 EA $1,800.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680

10.08.33.503 PIPE TO CHANNEL TRANSITION 1.00 EA $6,230.00 $6,230 15.00% 15.00% 30.00% $1,869 $8,099

10.08.33.505 MOD TYPE 2 RIP RAP ENERGY DISSIPATION 1.00 EA $1,840.00 $1,840 10.00% 15.00% 25.00% $460 $2,300

10.08.33.514 INLET APRON 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

10.08.33.700 ABN EXIST 36" RCP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878

10.08.33.700 ABN EXIST 24" CMP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878

10.08.33.700 ABN EXIST 36" CMP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878

10.08.33.700 ABN EXIST 24" RCP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878

10.08.33.700 ABN EXIST 30" RCP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878

10.08.33.700 ABN EXIST 24" ACP STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878

10.08.33.701 ABN EXIST CATCH BASIN 1.00 EA $1,240.00 $1,240 15.00% 15.00% 30.00% $372 $1,612

10.08.33.701 ABN EXIST CATCH BASIN 1.00 EA $1,240.00 $1,240 15.00% 15.00% 30.00% $372 $1,612

10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236

10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236

10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236

10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.08.33.702 REMOVE EXIST CURB INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379

10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.08.33.702 REMOVE HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236

10.08.33.702 REMOVE EXIST CURB INLET 1.00 EA $1,830.00 $1,830 15.00% 15.00% 30.00% $549 $2,379

10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.08.33.702 REMOVE EXIST HEADWALL 1.00 EA $860.00 $860 15.00% 15.00% 30.00% $258 $1,118

10.08.33.702 REMOVE EXIST HEADWALL 2.00 EA $860.00 $1,720 15.00% 15.00% 30.00% $516 $2,236

10.08.33.703 ABANDON EXIST 12" PVC STORM DRAIN 1.00 EA $675.00 $675 15.00% 15.00% 30.00% $203 $878

Monday, January 27, 2014 Page 30 of 140

Page 95: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.33.703 REMOVE EXIST 36" RCP STORM DRAIN 15.00 LF $80.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

10.08.33.703 6' MOD TYPE B CURB INLET 1.00 EA $5,200.00 $5,200 15.00% 15.00% 30.00% $1,560 $6,760

Sum

Average

38,313.00 $1,615,500

13.62% 15.05% 28.67%

$477,539 $2,093,039Summary for Group: 10.08.33

Group 10.08.34

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GUIDEWAY EMBANKMENT Contingency

10.08.34.193001 GUIDEWAY EMBANKMENT SEGMENT 3 27,038.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

10.08.34.193001 GUIDEWAY EMBANKMENT SEGMENT 1 14,440.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

10.08.34.193001 GUIDEWAY EMBANKMENT SEGMENT 2 43,540.00 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

10.08.34.193001 GUIDEWAY EMBANKMENT (LOSSAN) 12,495.58 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

Sum

Average

97,513.58 $0

15.00% 10.00% 25.00%

$0 $0Summary for Group: 10.08.34

Group 10.08.35

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ANTI-GRAFFITI COATING Contingency

10.08.35.211.598001 ANTI-GRAFFITI COATING 3,118.00 SF $1.20 $3,742 10.00% 10.00% 20.00% $748 $4,490

10.08.35.215.598001 ANTI-GRAFFITI COATING 16,047.00 SF $1.20 $19,256 10.00% 10.00% 20.00% $3,851 $23,108

10.08.35.271.598001 ANTI-GRAFFITI COATING 8,196.00 SF $1.20 $9,835 10.00% 10.00% 20.00% $1,967 $11,802

10.08.35.332.598001 ANTI-GRAFFITI COATING 32,540.00 SF $1.20 $39,048 10.00% 10.00% 20.00% $7,810 $46,858

10.08.35.376.598001 ANTI-GRAFFITI COATING 7,266.00 SF $1.20 $8,719 10.00% 10.00% 20.00% $1,744 $10,463

10.08.35.381.598001 ANTI-GRAFFITI COATING 1,813.00 SF $1.20 $2,176 10.00% 10.00% 20.00% $435 $2,611

10.08.35.388.598001 ANTI-GRAFFITI COATING 1,813.00 SF $1.20 $2,176 10.00% 10.00% 20.00% $435 $2,611

10.08.35.402.598001 ANTI-GRAFFITI COATING 15,975.00 SF $1.20 $19,170 10.00% 10.00% 20.00% $3,834 $23,004

10.08.35.416.598001 ANTI-GRAFFITI COATING 4,876.00 SF $1.20 $5,851 10.00% 10.00% 20.00% $1,170 $7,021

10.08.35.446.598001 ANTI-GRAFFITI COATING 16,439.00 SF $1.20 $19,727 10.00% 10.00% 20.00% $3,945 $23,672

10.08.35.449.598001 ANTI-GRAFFITI COATING 2,598.00 SF $1.20 $3,118 10.00% 10.00% 20.00% $624 $3,741

10.08.35.457.598001 ANTI-GRAFFITI COATING 6,490.00 SF $1.20 $7,788 10.00% 10.00% 20.00% $1,558 $9,346

10.08.35.465.598001 ANTI-GRAFFITI COATING 16,624.00 SF $1.20 $19,949 10.00% 10.00% 20.00% $3,990 $23,939

10.08.35.472.598001 ANTI-GRAFFITI COATING 16,060.00 SF $1.20 $19,272 10.00% 10.00% 20.00% $3,854 $23,126

10.08.35.475.598001 ANTI-GRAFFITI COATING 2,801.00 SF $1.20 $3,361 10.00% 10.00% 20.00% $672 $4,033

10.08.35.485.598001 ANTI-GRAFFITI COATING 3,430.00 SF $1.20 $4,116 10.00% 10.00% 20.00% $823 $4,939

10.08.35.498L.598001 ANTI-GRAFFITI COATING 9,392.00 SF $1.20 $11,270 10.00% 10.00% 20.00% $2,254 $13,524

Monday, January 27, 2014 Page 31 of 140

Page 96: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.35.498R.598001 ANTI-GRAFFITI COATING 18,636.00 SF $1.20 $22,363 10.00% 10.00% 20.00% $4,473 $26,836

10.08.35.500.598001 ANTI-GRAFFITI COATING 28,658.00 SF $1.20 $34,390 10.00% 10.00% 20.00% $6,878 $41,268

10.08.35.507.598001 ANTI-GRAFFITI COATING 1,171.00 SF $1.20 $1,405 10.00% 10.00% 20.00% $281 $1,686

10.08.35.509.598001 ANTI-GRAFFITI COATING 4,759.00 SF $1.20 $5,711 10.00% 10.00% 20.00% $1,142 $6,853

10.08.35.510.598001 ANTI-GRAFFITI COATING 353.00 SF $1.20 $424 10.00% 10.00% 20.00% $85 $508

10.08.35.512.598001 ANTI-GRAFFITI COATING 290.00 SF $1.20 $348 10.00% 10.00% 20.00% $70 $418

10.08.35.514.598001 ANTI-GRAFFITI COATING 4,697.00 SF $1.20 $5,636 10.00% 10.00% 20.00% $1,127 $6,764

10.08.35.516.598001 ANTI-GRAFFITI COATING 1,036.00 SF $1.20 $1,243 10.00% 10.00% 20.00% $249 $1,492

10.08.35.524.598001 ANTI-GRAFFITI COATING 30,752.00 SF $1.20 $36,902 10.00% 10.00% 20.00% $7,380 $44,283

10.08.35.526.598001 ANTI-GRAFFITI COATING 7,965.00 SF $1.20 $9,558 10.00% 10.00% 20.00% $1,912 $11,470

10.08.35.547.598001 ANTI-GRAFFITI COATING 425.00 SF $1.20 $510 10.00% 10.00% 20.00% $102 $612

10.08.35.550.598001 ANTI-GRAFFITI COATING 5,649.00 SF $1.20 $6,779 10.00% 10.00% 20.00% $1,356 $8,135

10.08.35.560.598001 ANTI-GRAFFITI COATING 7,040.00 SF $1.20 $8,448 10.00% 10.00% 20.00% $1,690 $10,138

10.08.35.567.598001 ANTI-GRAFFITI COATING 26,858.00 SF $1.20 $32,230 10.00% 10.00% 20.00% $6,446 $38,676

10.08.35.580.598001 ANTI-GRAFFITI COATING 46,862.00 SF $1.20 $56,234 10.00% 10.00% 20.00% $11,247 $67,481

10.08.35.592.598001 ANTI-GRAFFITI COATING 7,040.00 SF $1.20 $8,448 10.00% 10.00% 20.00% $1,690 $10,138

10.08.35.598L.598001 ANTI-GRAFFITI COATING 1,114.00 SF $1.20 $1,337 10.00% 10.00% 20.00% $267 $1,604

10.08.35.598R.598001 ANTI-GRAFFITI COATING 2,341.00 SF $1.20 $2,809 10.00% 10.00% 20.00% $562 $3,371

10.08.35.648.598001 ANTI-GRAFFITI COATING 14,586.00 SF $1.20 $17,503 10.00% 10.00% 20.00% $3,501 $21,004

10.08.35.999.598001 ANTI-GRAFFITI COATING 10,989.00 SF $1.20 $13,187 10.00% 10.00% 20.00% $2,637 $15,824

Sum

Average

386,699.00 $464,039

10.00% 10.00% 20.00%

$92,808 $556,847Summary for Group: 10.08.35

Group 10.08.36

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

STRAY CURRENT PROTECTION Contingency

10.08.36.211.520122 STRAY CURRENT PROTECTION 3,118.00 SF $2.00 $6,236 10.00% 10.00% 20.00% $1,247 $7,483

10.08.36.215.520122 STRAY CURRENT PROTECTION 16,047.00 SF $2.00 $32,094 10.00% 10.00% 20.00% $6,419 $38,513

10.08.36.271.520122 STRAY CURRENT PROTECTION 8,196.00 SF $2.00 $16,392 10.00% 10.00% 20.00% $3,278 $19,670

10.08.36.332.520122 STRAY CURRENT PROTECTION 32,540.00 SF $2.00 $65,080 10.00% 10.00% 20.00% $13,016 $78,096

10.08.36.376.520122 STRAY CURRENT PROTECTION 7,266.00 SF $2.00 $14,532 10.00% 10.00% 20.00% $2,906 $17,438

10.08.36.381.520122 STRAY CURRENT PROTECTION 1,813.00 SF $2.00 $3,626 10.00% 10.00% 20.00% $725 $4,351

Monday, January 27, 2014 Page 32 of 140

Page 97: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.08.36.388.520122 STRAY CURRENT PROTECTION 19,718.00 SF $2.00 $39,436 10.00% 10.00% 20.00% $7,887 $47,323

10.08.36.402.520122 STRAY CURRENT PROTECTION 15,975.00 SF $2.00 $31,950 10.00% 10.00% 20.00% $6,390 $38,340

10.08.36.416.520122 STRAY CURRENT PROTECTION 4,876.00 SF $2.00 $9,752 10.00% 10.00% 20.00% $1,950 $11,702

10.08.36.465.520122 STRAY CURRENT PROTECTION 16,624.00 SF $2.00 $33,248 10.00% 10.00% 20.00% $6,650 $39,898

10.08.36.485.520122 STRAY CURRENT PROTECTION 3,430.00 SF $2.00 $6,860 10.00% 10.00% 20.00% $1,372 $8,232

10.08.36.498L.520122 STRAY CURRENT PROTECTION 9,392.00 SF $2.00 $18,784 10.00% 10.00% 20.00% $3,757 $22,541

10.08.36.498R.520122 STRAY CURRENT PROTECTION 18,636.00 SF $2.00 $37,272 10.00% 10.00% 20.00% $7,454 $44,726

10.08.36.498R.520122 STRAY CURRENT PROTECTION (SOLDIER PILE WALL) 26,858.00 SF $2.00 $53,716 10.00% 10.00% 20.00% $10,743 $64,459

10.08.36.507.520122 STRAY CURRENT PROTECTION 1,171.00 SF $2.00 $2,342 10.00% 10.00% 20.00% $468 $2,810

10.08.36.509.520122 STRAY CURRENT PROTECTION (TIEBACK) 4,759.00 SF $2.00 $9,518 10.00% 10.00% 20.00% $1,904 $11,422

10.08.36.510.520122 STRAY CURRENT PROTECTION 353.00 SF $2.00 $706 10.00% 10.00% 20.00% $141 $847

10.08.36.512.520122 STRAY CURRENT PROTECTION 290.00 SF $2.00 $580 10.00% 10.00% 20.00% $116 $696

10.08.36.514.520122 STRAY CURRENT PROTECTION (TIEBACK) 4,697.00 SF $2.00 $9,394 10.00% 10.00% 20.00% $1,879 $11,273

10.08.36.516.520122 STRAY CURRENT PROTECTION 1,036.00 SF $2.00 $2,072 10.00% 10.00% 20.00% $414 $2,486

10.08.36.526.520122 STRAY CURRENT PROTECTION 7,965.00 SF $2.00 $15,930 10.00% 10.00% 20.00% $3,186 $19,116

10.08.36.547.520122 STRAY CURRENT PROTECTION 425.00 SF $2.00 $850 10.00% 10.00% 20.00% $170 $1,020

10.08.36.560.520122 STRAY CURRENT PROTECTION 7,040.00 SF $2.00 $14,080 10.00% 10.00% 20.00% $2,816 $16,896

10.08.36.580.520122 STRAY CURRENT PROTECTION 46,862.00 SF $2.00 $93,724 10.00% 10.00% 20.00% $18,745 $112,469

10.08.36.592.520122 STRAY CURRENT PROTECTION 3,281.00 SF $2.00 $6,562 10.00% 10.00% 20.00% $1,312 $7,874

10.08.36.598L.520122 STRAY CURRENT PROTECTION 1,114.00 SF $2.00 $2,228 10.00% 10.00% 20.00% $446 $2,674

10.08.36.598R.520122 STRAY CURRENT PROTECTION 2,341.00 SF $2.00 $4,682 10.00% 10.00% 20.00% $936 $5,618

10.08.36.648.520122 STRAY CURRENT PROTECTION 14,586.00 SF $2.00 $29,172 10.00% 10.00% 20.00% $5,834 $35,006

Sum

Average

280,409.00 $560,818

10.00% 10.00% 20.00%

$112,164 $672,982Summary for Group: 10.08.36

Sum

Average

5,964,674.03 $55,207,502

10.82% 11.06% 21.88%

$11,140,307 $66,347,809Summary for Sub Section: 10.08

Sub Section 10.09 Track: Direct fixation

Group 10.09.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

DF TRACK CONSTRUCTION Contingency

10.09.01 DF FASTENERS (FURNISH AND INSTALL) 4,263.00 EA $50.00 $213,150 5.00% 15.00% 20.00% $42,630 $255,780

Monday, January 27, 2014 Page 33 of 140

Page 98: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.09.01 DF FASTENERS (FURNISH AND INSTALL) 19,536.00 EA $50.00 $976,800 5.00% 15.00% 20.00% $195,360 $1,172,160

10.09.01 DF FASTENERS (FURNISH AND INSTALL) 2,055.00 EA $50.00 $102,750 5.00% 15.00% 20.00% $20,550 $123,300

10.09.01 DF FASTENERS (FURNISH AND INSTALL) 10,618.00 EA $50.00 $530,900 5.00% 15.00% 20.00% $106,180 $637,080

10.09.01.01 115RE DF HIGH STRENGTH RAIL (INSTALL) 21,386.12 TF $150.00 $3,207,918 5.00% 15.00% 20.00% $641,584 $3,849,502

10.09.01.01 115RE DF HIGH STRENGTH RAIL (INSTALL) 15,408.00 TF $150.00 $2,311,200 5.00% 15.00% 20.00% $462,240 $2,773,440

10.09.01.01 115RE DF HIGH STRENGTH RAIL (INSTALL) 5,250.58 TF $150.00 $787,587 5.00% 15.00% 20.00% $157,517 $945,104

10.09.01.01 115RE DF HIGH STRENGTH RAIL (INSTALL) 2,568.00 TF $150.00 $385,200 5.00% 15.00% 20.00% $77,040 $462,240

10.09.01.02 115RE DF HIGH STRENGTH RAIL (FURNISH) 98.40TON $1,550.00 $152,520 5.00% 15.00% 20.00% $30,504 $183,024

10.09.01.02 115RE DF HIGH STRENGTH RAIL (FURNISH) 590.60TON $1,550.00 $915,430 5.00% 15.00% 20.00% $183,086 $1,098,516

10.09.01.02 115RE DF HIGH STRENGTH RAIL (FURNISH) 201.30TON $1,550.00 $312,015 5.00% 15.00% 20.00% $62,403 $374,418

10.09.01.02 115RE DF HIGH STRENGTH RAIL (FURNISH) 819.80TON $1,550.00 $1,270,690 5.00% 15.00% 20.00% $254,138 $1,524,828

10.09.01.03 115RE DF STANDARD STRENGTH RAIL (INSTALL) 1,268.00 TF $135.00 $171,180 5.00% 15.00% 20.00% $34,236 $205,416

10.09.01.04 115RE DF STANDARD STRENGTH RAIL (FURNISH) 48.60TON $1,350.00 $65,610 5.00% 15.00% 20.00% $13,122 $78,732

Sum

Average

84,111.40 $11,402,950

5.00% 15.00% 20.00%

$2,280,590 $13,683,540Summary for Group: 10.09.01

Group 10.09.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CONCRETE PLINTH Contingency

10.09.02 CONCRETE PLINTH 28,801.00 CF $44.10 $1,270,124 5.00% 15.00% 20.00% $254,025 $1,524,149

10.09.02 CONCRETE PLINTH 11,562.00 CF $44.10 $509,884 5.00% 15.00% 20.00% $101,977 $611,861

10.09.02 CONCRETE PLINTH 5,573.00 CF $44.10 $245,769 5.00% 15.00% 20.00% $49,154 $294,923

10.09.02 CONCRETE PLINTH 52,992.00 CF $44.10 $2,336,947 5.00% 15.00% 20.00% $467,389 $2,804,337

Sum

Average

98,928.00 $4,362,725

5.00% 15.00% 20.00%

$872,545 $5,235,270Summary for Group: 10.09.02

Group 10.09.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SLAB TRACK Contingency

10.09.03.01 SLAB TRACK (CONCRETE) 1,134.00 CY $850.00 $963,900 5.00% 15.00% 20.00% $192,780 $1,156,680

10.09.03.02 CLASS 2 AGGREGATE BASE 600.00 CY $45.00 $27,000 5.00% 15.00% 20.00% $5,400 $32,400

Sum

Average

1,734.00 $990,900

5.00% 15.00% 20.00%

$198,180 $1,189,080Summary for Group: 10.09.03

Group 10.09.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

WALKWAY AT DF TRACK Contingency

10.09.04.01 WALKWAY AT DF TRACK 2,568.00 LF $240.00 $616,320 5.00% 15.00% 20.00% $123,264 $739,584

Monday, January 27, 2014 Page 34 of 140

Page 99: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

10.09.04.02 WALKWAY AT DF TRACK 6,518.00 LF $240.00 $1,564,320 5.00% 15.00% 20.00% $312,864 $1,877,184

10.09.04.03 WALKWAY AT DF TRACK 15,408.00 LF $240.00 $3,697,920 5.00% 15.00% 20.00% $739,584 $4,437,504

10.09.04.04 WALKWAY AT DF TRACK 21,386.00 LF $240.00 $5,132,640 5.00% 15.00% 20.00% $1,026,528 $6,159,168

Sum

Average

45,880.00 $11,011,200

5.00% 15.00% 20.00%

$2,202,240 $13,213,440Summary for Group: 10.09.04

Sum

Average

230,653.40 $27,767,775

5.00% 15.00% 20.00%

$5,553,555 $33,321,330Summary for Sub Section: 10.09

Sub Section 10.11 Track:Ballasted

Group 10.11.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BALLASTED TRACK CONSTRUCTION (DOUBLE TRACK) Contingency

10.11.01.01 115RE BALLASTED HIGH STRENGTH RAIL (INSTALL) 6,567.56 TF $85.00 $558,243 5.00% 10.00% 15.00% $83,736 $641,979

10.11.01.01 136RE BALLASTED STANDARD STRENGTH RAIL (FURNISH) LOSSAN 559.00TON $1,950.00 $1,090,050 5.00% 10.00% 15.00% $163,508 $1,253,558

10.11.01.01 115RE BALLASTED HIGH STRENGTH RAIL (INSTALL) 5,134.00 TF $85.00 $436,390 5.00% 20.00% 25.00% $109,098 $545,488

10.11.01.01 115RE BALLASTED HIGH STRENGTH RAIL (INSTALL) 2,588.31 TF $85.00 $220,006 5.00% 20.00% 25.00% $55,002 $275,008

10.11.01.01A 136RE BALLASTED STANDARD STRENGTH RAIL (INSTALL) LOSSAN 12,335.50 TF $100.00 $1,233,550 5.00% 10.00% 15.00% $185,033 $1,418,583

10.11.01.02 115RE BALLASTED HIGH STRENGTH RAIL (FURNISH) 251.80TON $1,550.00 $390,290 5.00% 10.00% 15.00% $58,544 $448,834

10.11.01.02 115RE BALLASTED HIGH STRENGTH RAIL (FURNISH) 99.20TON $1,550.00 $153,760 5.00% 10.00% 15.00% $23,064 $176,824

10.11.01.02 115RE BALLASTED HIGH STRENGTH RAIL (FURNISH) 196.80TON $1,550.00 $305,040 5.00% 10.00% 15.00% $45,756 $350,796

10.11.01.03 115RE BALLASTED STANDARD STRENGTH RAIL (INSTALL) 25,356.00 TF $85.00 $2,155,260 5.00% 20.00% 25.00% $538,815 $2,694,075

10.11.01.03 115RE BALLASTED STANDARD STRENGTH RAIL (INSTALL) 28,085.10 TF $85.00 $2,387,234 5.00% 20.00% 25.00% $596,808 $2,984,042

10.11.01.03A 136RE BALLASTED STANDARD STRENGTH RAIL (INSTALL) SHOOFLY 7,640.00 TF $100.00 $764,000 5.00% 10.00% 15.00% $114,600 $878,600

10.11.01.04 115RE BALLASTED STANDARD STRENGTH RAIL (FURNISH) 1,076.60TON $1,350.00 $1,453,410 5.00% 10.00% 15.00% $218,012 $1,671,422

10.11.01.04 115RE BALLASTED STANDARD STRENGTH RAIL (FURNISH) 972.00TON $1,350.00 $1,312,200 5.00% 10.00% 15.00% $196,830 $1,509,030

10.11.01.04A 136RE BALLASTED STANDARD STRENGTH RAIL (FURNISH) SHOOFLY 346.30TON $1,950.00 $675,285 5.00% 10.00% 15.00% $101,293 $776,578

10.11.01.10 CONCRETE TIES 2,628.00 EA $100.00 $262,800 15.00% 10.00% 25.00% $65,700 $328,500

10.11.01.10 CONCRETE TIES 13,490.00 EA $100.00 $1,349,000 15.00% 10.00% 25.00% $337,250 $1,686,250

10.11.01.10 CONCRETE TIES 11,712.00 EA $100.00 $1,171,200 5.00% 10.00% 15.00% $175,680 $1,346,880

10.11.01.10A CONCRETE TIES (SHOOFLY) 3,820.00 EA $130.00 $496,600 15.00% 10.00% 25.00% $124,150 $620,750

10.11.01.12 CONCRETE TIES (LOSSAN) 6,168.00 EA $130.00 $801,840 15.00% 10.00% 25.00% $200,460 $1,002,300

Sum

Average

129,026.17 $17,216,157

7.11% 12.11% 19.21%

$3,393,337 $20,609,494Summary for Group: 10.11.01

Monday, January 27, 2014 Page 35 of 140

Page 100: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Group 10.11.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BALLAST Contingency

10.11.02 BALLAST 71,559.00 CY $53.00 $3,792,627 15.00% 10.00% 25.00% $948,157 $4,740,784

10.11.02 BALLAST (LOSSAN) 11,181.00 CY $53.00 $592,593 15.00% 10.00% 25.00% $148,148 $740,741

10.11.02A BALLAST (SHOOFLY) 7,672.00 CY $35.00 $268,520 15.00% 10.00% 25.00% $67,130 $335,650

Sum

Average

90,412.00 $4,653,740

15.00% 10.00% 25.00%

$1,163,435 $5,817,175Summary for Group: 10.11.02

Group 10.11.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BALLAST CURB Contingency

10.11.08 BALLAST CURB 101.93 LF $42.00 $4,281 15.00% 10.00% 25.00% $1,070 $5,351

10.11.08 BALLAST CURB 6,175.64 LF $42.00 $259,377 15.00% 10.00% 25.00% $64,844 $324,221

10.11.08 BALLAST CURB 1,218.39 LF $42.00 $51,172 15.00% 10.00% 25.00% $12,793 $63,965

10.11.08.01 GUIDEWAY EXCAVATION 116.01 CY $18.00 $2,088 15.00% 10.00% 25.00% $522 $2,610

10.11.08.01 GUIDEWAY EXCAVATION 1,069.34 CY $18.00 $19,248 15.00% 10.00% 25.00% $4,812 $24,060

10.11.08.01 GUIDEWAY EXCAVATION 9.97 CY $18.00 $179 15.00% 10.00% 25.00% $45 $224

10.11.08.02 BACKFILL (BALLAST CURB) 982.80 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

10.11.08.02 BACKFILL (BALLAST CURB) 172.69 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

10.11.08.02 BACKFILL (BALLAST CURB) 11.35 CY $0.00 $0 15.00% 10.00% 25.00% $0 $0

Sum

Average

9,858.12 $336,346

15.00% 10.00% 25.00%

$84,087 $420,433Summary for Group: 10.11.08

Sum

Average

229,296.29 $22,206,244

10.16% 11.29% 21.45%

$4,640,858 $26,847,102Summary for Sub Section: 10.11

Sub Section 10.12 TRACK: SPECIAL (SWITCHES, TURNOUT)

Group 10.12.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NO. 10 SINGLE CROSSOVER (BALLASTED) Contingency

10.12.01 NO. 10 SINGLE CROSSOVER WITH RBM (BALLASTED) 1.00 EA $243,661.00 $243,661 0.00% 12.50% 12.50% $30,458 $274,119

Sum

Average

1.00 $243,661

0.00% 12.50% 12.50%

$30,458 $274,119Summary for Group: 10.12.01

Group 10.12.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NO. 10 DOUBLE CROSSOVER (DF) Contingency

10.12.03 NO. 10 DOUBLE CROSSOVER W/RBM FROGS (DF) 4.00 EA $711,589.00 $2,846,356 0.00% 12.50% 12.50% $355,795 $3,202,151

Sum

Average

4.00 $2,846,356

0.00% 12.50% 12.50%

$355,795 $3,202,151Summary for Group: 10.12.03

Monday, January 27, 2014 Page 36 of 140

Page 101: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Group 10.12.03A

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NO. 10 SINGLE CROSSOVER WITH SPRING FROGS (BALLASTED) Contingency

10.12.03A NO. 10 SINGLE CROSSOVER WITH SPRING FROGS (BALLASTED) 1.00 EA $314,401.00 $314,401 0.00% 12.50% 12.50% $39,300 $353,701

10.12.03A NO. 10 SINGLE CROSSOVER WITH SPRING FROGS (BALLASTED) - SP 1.00 EA $314,401.00 $314,401 0.00% 12.50% 12.50% $39,300 $353,701

Sum

Average

2.00 $628,802

0.00% 12.50% 12.50%

$78,600 $707,402Summary for Group: 10.12.03A

Group 10.12.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BUMPING POST Contingency

10.12.04.02 HYDRAULIC BUMPING POST 3.00 EA $20,855.00 $62,565 12.50% 12.50% 25.00% $15,641 $78,206

Sum

Average

3.00 $62,565

12.50% 12.50% 25.00%

$15,641 $78,206Summary for Group: 10.12.04

Group 10.12.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NO. 10 TURNOUT (BALLASTED) Contingency

10.12.05 NO. 10 TURNOUT WITH RBM (BALLASTED) - SPARE PARTS 1.00 EA $158,394.00 $158,394 0.00% 12.50% 12.50% $19,799 $178,193

10.12.05 NO. 10 TURNOUT WITH RBM (BALLASTED) 1.00 EA $158,394.00 $158,394 0.00% 12.50% 12.50% $19,799 $178,193

Sum

Average

2.00 $316,788

0.00% 12.50% 12.50%

$39,599 $356,387Summary for Group: 10.12.05

Group 10.12.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CROSSING DIAMOND 11DEG-26'-58" Contingency

10.12.06 CROSSING DIAMOND 11DEG-26'-58" - SPARE PARTS 1.00 EA $671,866.00 $671,866 0.00% 12.50% 12.50% $83,983 $755,849

10.12.06 NO. 20 CROSSING DIAMOND (DF/SLAB TRACK) - SPARE PARTS 1.00 EA $1,119,716.00 $1,119,716 0.00% 12.50% 12.50% $139,965 $1,259,681

10.12.06 NO. 20 CROSSING DIAMOND (DF/SLAB TRACK) 1.00 EA $1,119,716.00 $1,119,716 0.00% 12.50% 12.50% $139,965 $1,259,681

Sum

Average

3.00 $2,911,298

0.00% 12.50% 12.50%

$363,912 $3,275,210Summary for Group: 10.12.06

Group 10.12.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NO. 20 TURNOUT (DF/SLAB TRACK) Contingency

10.12.07 NO. 20 TURNOUT WITH RBM FROGS (DF/SLAB TRACK) 2.00 EA $147,051.00 $294,102 0.00% 12.50% 12.50% $36,763 $330,865

10.12.07 NO. 20 TURNOUT (DF/SLAB TRACK) - SPARE PARTS 1.00 EA $147,051.00 $147,051 0.00% 12.50% 12.50% $18,381 $165,432

Sum

Average

3.00 $441,153

0.00% 12.50% 12.50%

$55,144 $496,297Summary for Group: 10.12.07

Group 10.12.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NO. 10 DOUBLE CROSSOVER (BALLASTED) Contingency

10.12.10 NO. 10 DOUBLE CROSSOVER (BALLASTED) 3.00 EA $671,866.00 $2,015,598 0.00% 12.50% 12.50% $251,950 $2,267,548

Monday, January 27, 2014 Page 37 of 140

Page 102: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

3.00 $2,015,598

0.00% 12.50% 12.50%

$251,950 $2,267,548Summary for Group: 10.12.10

Group 10.12.11

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NO. 14 TURNOUT (BALLASTED) Contingency

10.12.11 NO. 14 TURNOUT (BALLASTED) 1.00 EA $133,046.00 $133,046 0.00% 12.50% 12.50% $16,631 $149,677

Sum

Average

1.00 $133,046

0.00% 12.50% 12.50%

$16,631 $149,677Summary for Group: 10.12.11

Sum

Average

22.00 $9,599,267

0.89% 12.50% 13.39%

$1,207,729 $10,806,996Summary for Sub Section: 10.12

Sub Section 10.13 VIBRATION MITIGATION

Group 10.13.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

VIBRATION MITIGATION (FLOATING SLAB TRACK) Contingency

10.13.01 FLOATING SLAB TRACK 720.00 TF $2,000.00 $1,440,000 0.00% 30.00% 30.00% $432,000 $1,872,000

Sum

Average

720.00 $1,440,000

0.00% 30.00% 30.00%

$432,000 $1,872,000Summary for Group: 10.13.01

Sum

Average

720.00 $1,440,000

0.00% 30.00% 30.00%

$432,000 $1,872,000Summary for Sub Section: 10.13

Sum

Average

37,375,505.57 $270,884,223

11.39% 11.63% 23.02%

$61,189,270 $332,073,493Summary for Section 10

Section 20 STATIONS, STOPS, TERMINALS, INTERMODAL

Sub Section 20.01 AT-GRADE STATION, STOP, SHELTER, MALL, TERMINAL, PLATFORM

Group 20.01.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PERMANENT BMP (AT-GRADE STATION) Contingency

20.01.01 PERMANENT BMP (AT-GRADE STATION) 1.00 LS $700,000.00 $700,000 0.00% 20.00% 20.00% $140,000 $840,000

Sum

Average

1.00 $700,000

0.00% 20.00% 20.00%

$140,000 $840,000Summary for Group: 20.01.01

Group 20.01.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TECOLOTE STATION Contingency

20.01.02.02370.27 STATION STRIPING (THERMO PLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253

20.01.02.09000.01 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600

20.01.02.09000.02 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000

20.01.02.09000.03 ARCHITECTURAL CONCRETE FINISH (ANCILLARY SPACE) 500.00 SF $20.00 $10,000 15.00% 10.00% 25.00% $2,500 $12,500

20.01.02.09000.05 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313

Monday, January 27, 2014 Page 38 of 140

Page 103: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.01.02.09000.07 INFORMATIONAL KIOSK 2.00 EA $7,973.00 $15,946 0.00% 10.00% 10.00% $1,595 $17,541

20.01.02.100 STATION ELECTRICAL (SITE TO WITHIN 5' OF ENTRY) 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000

20.01.02.1000 BLOCK WALL (8' High w/footing) 3,840.00 SF $35.00 $134,400 0.00% 10.00% 10.00% $13,440 $147,840

20.01.02.10100.01M SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

20.01.02.10500.05 LARGE SHELTER (INCL. FOUNDATION & SEATING) 6.00 EA $207,000.00 $1,242,000 0.00% 10.00% 10.00% $124,200 $1,366,200

20.01.02.12000.02M STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

20.01.02.15300.01A STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000

20.01.02.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

20.01.02.2000 METAL PANEL SCREEN WALL (8' X 6') 192.00 SF $32.00 $6,144 15.00% 10.00% 25.00% $1,536 $7,680

20.01.02.2820.01 CHAIN LINK FENCE (CL-4) 484.00 LF $16.00 $7,744 15.00% 10.00% 25.00% $1,936 $9,680

20.01.02.300 PLATFORM CONCRETE 400.00 CY $750.00 $300,000 15.00% 10.00% 25.00% $75,000 $375,000

20.01.02.400 GUIDEWAY EXCAVATION 800.00 CY $18.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000

20.01.02.500 CLASS 2 AGGREGATE BASE 400.00 CY $45.00 $18,000 15.00% 10.00% 25.00% $4,500 $22,500

20.01.02.600 STATION LIGHTING 32.00 EA $5,000.00 $160,000 0.00% 10.00% 10.00% $16,000 $176,000

20.01.02.601 THREE-BAY TELECOMMUNICATION CABINET 1.00 EA $140,000.00 $140,000 15.00% 15.00% 30.00% $42,000 $182,000

20.01.02.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545

20.01.02.604 TRACKWAY PAVING AT PLATFORM 1,954.00 SF $36.00 $70,344 15.00% 10.00% 25.00% $17,586 $87,930

Sum

Average

31,825.00 $2,882,666

10.91% 10.23% 21.14%

$450,415 $3,333,081Summary for Group: 20.01.02

Group 20.01.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CLAIREMONT STATION Contingency

20.01.03.02370.27 STATION STRIPING (THERMO PLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253

20.01.03.09000.01 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600

20.01.03.09000.02 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000

20.01.03.09000.03 ARCHITECTURAL CONCRETE FINISH (ANCILLARY SPACE) 500.00 SF $20.00 $10,000 15.00% 10.00% 25.00% $2,500 $12,500

20.01.03.09000.05 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313

20.01.03.09000.07 INFORMATIONAL KIOSK 2.00 EA $7,973.00 $15,946 0.00% 10.00% 10.00% $1,595 $17,541

20.01.03.100 STATION ELECTRICAL (SITE TO WITHIN 5' OF ENTRY) 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000

20.01.03.1000 BLOCK WALL (8' High w/footing) 2,880.00 SF $35.00 $100,800 0.00% 10.00% 10.00% $10,080 $110,880

20.01.03.10100.01M SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

Monday, January 27, 2014 Page 39 of 140

Page 104: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.01.03.10500.05 LARGE SHELTER (INCL. FOUNDATION & SEATING) 6.00 EA $207,000.00 $1,242,000 0.00% 10.00% 10.00% $124,200 $1,366,200

20.01.03.12000.02M STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

20.01.03.15300.01A STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000

20.01.03.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

20.01.03.2000 METAL PANEL SCREEN WALL (8' X 6') 192.00 SF $32.00 $6,144 15.00% 10.00% 25.00% $1,536 $7,680

20.01.03.2820.01 CHAIN LINK FENCE (CL-4) 484.00 LF $16.00 $7,744 15.00% 10.00% 25.00% $1,936 $9,680

20.01.03.300 PLATFORM CONCRETE 400.00 CY $750.00 $300,000 15.00% 10.00% 25.00% $75,000 $375,000

20.01.03.400 GUIDEWAY EXCAVATION 800.00 CY $18.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000

20.01.03.500 CLASS 2 AGGREGATE BASE 400.00 CY $45.00 $18,000 15.00% 10.00% 25.00% $4,500 $22,500

20.01.03.600 STATION LIGHTING 32.00 EA $5,000.00 $160,000 0.00% 10.00% 10.00% $16,000 $176,000

20.01.03.601 THREE-BAY TELECOMMUNICATION CABINET 1.00 EA $140,000.00 $140,000 15.00% 15.00% 30.00% $42,000 $182,000

20.01.03.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545

20.01.03.604 TRACKWAY PAVING AT PLATFORM 2,225.00 SF $36.00 $80,100 15.00% 10.00% 25.00% $20,025 $100,125

Sum

Average

31,136.00 $2,858,822

10.91% 10.23% 21.14%

$449,494 $3,308,316Summary for Group: 20.01.03

Group 20.01.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BALBOA STATION Contingency

20.01.04.02370.27 STATION STRIPING (THERMO PLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253

20.01.04.09000.01 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600

20.01.04.09000.02 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000

20.01.04.09000.03 ARCHITECTURAL CONCRETE FINISH (ANCILLARY SPACE) 500.00 SF $20.00 $10,000 15.00% 10.00% 25.00% $2,500 $12,500

20.01.04.09000.05 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313

20.01.04.09000.07 INFORMATIONAL KIOSK 2.00 EA $7,973.00 $15,946 0.00% 10.00% 10.00% $1,595 $17,541

20.01.04.100 STATION ELECTRICAL (SITE TO WITHIN 5' OF ENTRY) 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000

20.01.04.1000 BLOCK WALL (8' High) 2,880.00 SF $25.00 $72,000 0.00% 10.00% 10.00% $7,200 $79,200

20.01.04.10100.01M SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

20.01.04.10500.05 LARGE SHELTER (INCL. FOUNDATION & SEATING) 6.00 EA $207,000.00 $1,242,000 0.00% 10.00% 10.00% $124,200 $1,366,200

20.01.04.12000.02M STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

20.01.04.15300.01A STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000

20.01.04.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

Monday, January 27, 2014 Page 40 of 140

Page 105: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.01.04.2000 METAL PANEL SCREEN WALL (8' X 6') 192.00 SF $32.00 $6,144 15.00% 10.00% 25.00% $1,536 $7,680

20.01.04.2820.01 CHAIN LINK FENCE (CL-4) 484.00 LF $16.00 $7,744 15.00% 10.00% 25.00% $1,936 $9,680

20.01.04.300 PLATFORM CONCRETE 400.00 CY $750.00 $300,000 15.00% 10.00% 25.00% $75,000 $375,000

20.01.04.400 GUIDEWAY EXCAVATION 800.00 CY $18.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000

20.01.04.500 CLASS 2 AGGREGATE BASE 400.00 CY $45.00 $18,000 15.00% 10.00% 25.00% $4,500 $22,500

20.01.04.600 STATION LIGHTING 32.00 EA $5,000.00 $160,000 0.00% 10.00% 10.00% $16,000 $176,000

20.01.04.601 THREE-BAY TELECOMMUNICATION CABINET 1.00 EA $140,000.00 $140,000 15.00% 15.00% 30.00% $42,000 $182,000

20.01.04.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545

20.01.04.604 TRACKWAY PAVING AT PLATFORM 1,954.00 SF $36.00 $70,344 15.00% 10.00% 25.00% $17,586 $87,930

Sum

Average

30,865.00 $2,820,266

10.91% 10.23% 21.14%

$444,175 $3,264,441Summary for Group: 20.01.04

Group 20.01.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

VA MEDICAL CENTER STATION Contingency

20.01.05.02370.27 STATION STRIPING (THERMO PLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253

20.01.05.09000.01 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 9,200.00 SF $20.00 $184,000 0.00% 10.00% 10.00% $18,400 $202,400

20.01.05.09000.02 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000

20.01.05.09000.03 ARCHITECTURAL CONCRETE FINISH (ANCILLARY SPACE) 5,000.00 SF $20.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000

20.01.05.09000.05 BIKE LOCKER 10.00 EA $2,450.00 $24,500 15.00% 10.00% 25.00% $6,125 $30,625

20.01.05.09000.07 INFORMATIONAL KIOSK 2.00 EA $7,973.00 $15,946 0.00% 10.00% 10.00% $1,595 $17,541

20.01.05.100 STATION ELECTRICAL (SITE TO WITHIN 5' OF ENTRY) 1.00 LS $100,000.00 $100,000 15.00% 10.00% 25.00% $25,000 $125,000

20.01.05.10100.01M SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

20.01.05.10500.05 LARGE SHELTER (INCL. FOUNDATION & SEATING) 6.00 EA $207,000.00 $1,242,000 0.00% 10.00% 10.00% $124,200 $1,366,200

20.01.05.12000.02M STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

20.01.05.15300.01A STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000

20.01.05.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

20.01.05.2000 METAL PANEL SCREEN WALL (8' HIGH STAINLESS STEEL PICKET FEN 2,400.00 SF $45.00 $108,000 15.00% 10.00% 25.00% $27,000 $135,000

20.01.05.300 PLATFORM CONCRETE 400.00 CY $750.00 $300,000 15.00% 10.00% 25.00% $75,000 $375,000

20.01.05.400 GUIDEWAY EXCAVATION 800.00 CY $18.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000

20.01.05.500 CLASS 2 AGGREGATE BASE 400.00 CY $45.00 $18,000 15.00% 10.00% 25.00% $4,500 $22,500

20.01.05.600 STATION LIGHTING 32.00 EA $5,000.00 $160,000 0.00% 10.00% 10.00% $16,000 $176,000

Monday, January 27, 2014 Page 41 of 140

Page 106: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.01.05.601 THREE-BAY TELECOMMUNICATION CABINET 1.00 EA $140,000.00 $140,000 15.00% 15.00% 30.00% $42,000 $182,000

20.01.05.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545

20.01.05.604 TRACKWAY PAVING AT PLATFORM 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900

Sum

Average

39,480.00 $3,159,804

11.25% 10.25% 21.50%

$544,659 $3,704,463Summary for Group: 20.01.05

Group 20.01.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ART FEATURES (AT GRADE) Contingency

20.01.10 ART FEATURES (1% AT GRADE) 1.00 LS $117,215.58 $117,216 15.00% 15.00% 30.00% $35,165 $152,380

Sum

Average

1.00 $117,216

15.00% 15.00% 30.00%

$35,165 $152,380Summary for Group: 20.01.10

Sum

Average

133,308.00 $12,538,774

10.91% 10.40% 21.31%

$2,063,907 $14,602,680Summary for Sub Section: 20.01

Sub Section 20.02 AERIAL STATION, STOP, SHELTER, MALL, TERMINAL, PLATFORM

Group 20.02.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PERMANENT BMP (AERIAL STATION) Contingency

20.02.01 PERMANENT BMP (AERIAL STATION) 1.00 LS $550,000.00 $550,000 0.00% 20.00% 20.00% $110,000 $660,000

Sum

Average

1.00 $550,000

0.00% 20.00% 20.00%

$110,000 $660,000Summary for Group: 20.02.01

Group 20.02.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UCSD EAST STATION Contingency

20.02.02.02 STAINLESS STEEL & GLASS SCREEN WALL (8' X 6') 3,072.00 SF $60.00 $184,320 15.00% 10.00% 25.00% $46,080 $230,400

20.02.02.03 GUARD RAILING - STAINLESS STEEL W/GLASS PANEL 52.00 LF $60.00 $3,120 15.00% 10.00% 25.00% $780 $3,900

20.02.02.04 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600

20.02.02.05 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000

20.02.02.06 ARCHITECTURAL CONCRETE PAVERS (ANCILLARY SPACES) 22,871.00 SF $20.00 $457,420 15.00% 15.00% 30.00% $137,226 $594,646

20.02.02.06 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES) 2,831.00 SF $15.00 $42,465 15.00% 10.00% 25.00% $10,616 $53,081

20.02.02.08 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

20.02.02.09 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253

20.02.02.10 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200

20.02.02.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) (UCSD EAST STATION) 385,813.00 LB $2.15 $829,498 15.00% 10.00% 25.00% $207,374 $1,036,872

20.02.02.11 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

20.02.02.12 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313

Monday, January 27, 2014 Page 42 of 140

Page 107: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.02.02.14 INFORMATIONAL KIOSK 3.00 EA $7,973.00 $23,919 0.00% 10.00% 10.00% $2,392 $26,311

20.02.02.19 STAIR RAILING (STAINLESS STEEL W/GLASS PANEL) 1,077.00 LF $360.00 $387,720 15.00% 10.00% 25.00% $96,930 $484,650

20.02.02.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

20.02.02.25 LANDSCAPING 35,535.00 SF $4.70 $167,015 15.00% 10.00% 25.00% $41,754 $208,768

20.02.02.26 IRRIGATION 35,535.00 SF $1.40 $49,749 15.00% 10.00% 25.00% $12,437 $62,186

20.02.02.28 STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000

20.02.02.490605 36'' CIDH CONCRETE PILING 3,404.00 LF $507.00 $1,725,828 15.00% 15.00% 30.00% $517,748 $2,243,576

20.02.02.50 CIP CONCRETE ELEVATED WALKWAYS 16.37 CY $1,275.00 $20,872 15.00% 10.00% 25.00% $5,218 $26,090

20.02.02.52 STAIR (METAL PAN W/ CONCRETE FILL) 3,059.00 SF $25.00 $76,475 15.00% 10.00% 25.00% $19,119 $95,594

20.02.02.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 640.00 CY $440.00 $281,600 15.00% 10.00% 25.00% $70,400 $352,000

20.02.02.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 134,400.00 LB $1.00 $134,400 15.00% 10.00% 25.00% $33,600 $168,000

20.02.02.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250

20.02.02.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125

20.02.02.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000

20.02.02.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 15.00% 30.00% $114,000 $494,000

20.02.02.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 2.00 EA $1,109.00 $2,218 15.00% 10.00% 25.00% $555 $2,773

20.02.02.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900

20.02.02.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500

Sum

Average

661,188.37 $8,512,890

12.50% 10.50% 23.00%

$1,861,597 $10,374,487Summary for Group: 20.02.02

Group 20.02.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UCSD WEST STATION Contingency

20.02.03.02 STAINLESS STEEL & GLASS SCREEN WALL (8' X 6') 2,736.00 SF $60.00 $164,160 15.00% 10.00% 25.00% $41,040 $205,200

20.02.03.03 GUARD RAILING - STAINLESS STEEL W/GLASS PANEL 209.00 LF $60.00 $12,540 15.00% 10.00% 25.00% $3,135 $15,675

20.02.03.03 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 10,800.00 SF $20.00 $216,000 0.00% 10.00% 10.00% $21,600 $237,600

20.02.03.05 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000

20.02.03.06 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES/ANCILLARY SPA 15,291.00 SF $15.00 $229,365 15.00% 10.00% 25.00% $57,341 $286,706

20.02.03.08 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

20.02.03.09 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253

20.02.03.10 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200

Monday, January 27, 2014 Page 43 of 140

Page 108: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.02.03.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) (UCSD WEST STATION) 188,097.50 LB $2.15 $404,410 15.00% 10.00% 25.00% $101,102 $505,512

20.02.03.11 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

20.02.03.12 BIKE LOCKER 5.00 EA $2,450.00 $12,250 15.00% 10.00% 25.00% $3,063 $15,313

20.02.03.14 INFORMATIONAL KIOSK 1.00 EA $7,973.00 $7,973 0.00% 10.00% 10.00% $797 $8,770

20.02.03.20 STAIR RAILING (STAINLESS STEEL W/GLASS PANEL) 3,330.00 SF $360.00 $1,198,800 15.00% 10.00% 25.00% $299,700 $1,498,500

20.02.03.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

20.02.03.26 LANDSCAPING 34,800.00 SF $4.70 $163,560 15.00% 10.00% 25.00% $40,890 $204,450

20.02.03.27 IRRIGATION 34,800.00 SF $1.40 $48,720 15.00% 10.00% 25.00% $12,180 $60,900

20.02.03.29 STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000

20.02.03.490605 36'' CIDH CONCRETE PILING 3,957.00 LF $507.00 $2,006,199 15.00% 15.00% 30.00% $601,860 $2,608,059

20.02.03.50 CIP CONCRETE ELEVATED WALKWAYS 26.10 CY $1,275.00 $33,278 15.00% 10.00% 25.00% $8,319 $41,597

20.02.03.51 STRUCTURAL STEEL ELEVATED WALKWAY SUPPORT (F&I) 120,865.00 LB $2.95 $356,552 15.00% 10.00% 25.00% $89,138 $445,690

20.02.03.52 STAIR (METAL PAN W/ CONCRETE FILL) 3,573.00 SF $25.00 $89,325 15.00% 10.00% 25.00% $22,331 $111,656

20.02.03.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 549.63 CY $440.00 $241,837 15.00% 10.00% 25.00% $60,459 $302,297

20.02.03.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 115,422.22 LB $1.00 $115,422 15.00% 10.00% 25.00% $28,856 $144,278

20.02.03.56 STRUCTURAL STEEL GATEWAY (F&I) 199,525.00 LB $2.75 $548,694 15.00% 10.00% 25.00% $137,173 $685,867

20.02.03.57 METAL ROOF (F&I, GATEWAY) 3,000.00 SF $10.00 $30,000 15.00% 10.00% 25.00% $7,500 $37,500

20.02.03.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250

20.02.03.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125

20.02.03.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000

20.02.03.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 10.00% 25.00% $95,000 $475,000

20.02.03.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 2.00 EA $1,109.00 $2,218 15.00% 10.00% 25.00% $555 $2,773

20.02.03.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900

20.02.03.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500

Sum

Average

759,062.45 $9,779,324

12.66% 10.16% 22.81%

$2,152,745 $11,932,069Summary for Group: 20.02.03

Group 20.02.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NOBEL STATION Contingency

20.02.04.01 STAINLESS STEEL & GLASS SCREEN WALL (8' X 6') 5,760.00 SF $95.00 $547,200 15.00% 10.00% 25.00% $136,800 $684,000

20.02.04.02 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 9,200.00 SF $20.00 $184,000 0.00% 10.00% 10.00% $18,400 $202,400

Monday, January 27, 2014 Page 44 of 140

Page 109: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.02.04.03 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000

20.02.04.04 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES/ANCILLARY SPA 9,102.00 SF $15.00 $136,530 15.00% 10.00% 25.00% $34,133 $170,663

20.02.04.06 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

20.02.04.07 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253

20.02.04.08 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200

20.02.04.10 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

20.02.04.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) (NOBEL STATION) 213,930.00 LB $2.15 $459,950 15.00% 10.00% 25.00% $114,987 $574,937

20.02.04.11 BIKE LOCKER 10.00 EA $2,450.00 $24,500 15.00% 10.00% 25.00% $6,125 $30,625

20.02.04.13 INFORMATIONAL KIOSK 4.00 EA $7,973.00 $31,892 0.00% 10.00% 10.00% $3,189 $35,081

20.02.04.20 STAIR RAILING (STAINLESS STEEL W/GLASS PANELS) 2,484.00 SF $60.00 $149,040 15.00% 10.00% 25.00% $37,260 $186,300

20.02.04.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

20.02.04.32 STATION PLUMBING 9,200.00 SF $20.00 $184,000 15.00% 10.00% 25.00% $46,000 $230,000

20.02.04.490605 36'' CIDH CONCRETE PILING 3,612.00 LF $507.00 $1,831,284 15.00% 15.00% 30.00% $549,385 $2,380,669

20.02.04.50 CIP CONCRETE ELEVATED WALKWAYS 91.24 CY $1,275.00 $116,331 15.00% 10.00% 25.00% $29,083 $145,414

20.02.04.52 STAIR (METAL PAN W/ CONCRETE FILL) 3,750.00 SF $25.00 $93,750 15.00% 10.00% 25.00% $23,438 $117,188

20.02.04.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 900.74 CY $440.00 $396,326 15.00% 10.00% 25.00% $99,081 $495,407

20.02.04.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 189,155.56 LB $1.00 $189,156 15.00% 10.00% 25.00% $47,289 $236,444

20.02.04.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250

20.02.04.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125

20.02.04.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000

20.02.04.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 10.00% 25.00% $95,000 $475,000

20.02.04.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 3.00 EA $1,109.00 $3,327 15.00% 10.00% 25.00% $832 $4,159

20.02.04.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900

20.02.04.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500

Sum

Average

458,475.54 $8,029,307

12.12% 10.19% 22.31%

$1,707,707 $9,737,014Summary for Group: 20.02.04

Group 20.02.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

EXECUTIVE STATION Contingency

20.02.05.01 STAINLESS STEEL PICKET FENCE SCREEN WALL (8' X 6') 3,328.00 SF $95.00 $316,160 15.00% 10.00% 25.00% $79,040 $395,200

20.02.05.02 STAINLESS STEEL & GLASS SCREEN WALL (8' X 6') 2,592.00 SF $60.00 $155,520 15.00% 10.00% 25.00% $38,880 $194,400

Monday, January 27, 2014 Page 45 of 140

Page 110: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.02.05.03 STAINLESS STEEL & GLASS SCREEN WALL (8' X 3') - PED BRIDGE 2,688.00 SF $112.00 $301,056 15.00% 10.00% 25.00% $75,264 $376,320

20.02.05.04 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 9,200.00 SF $20.00 $184,000 0.00% 10.00% 10.00% $18,400 $202,400

20.02.05.05 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000

20.02.05.06 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES/ANCILLARY SPA 11,317.00 SF $15.00 $169,755 15.00% 10.00% 25.00% $42,439 $212,194

20.02.05.08 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

20.02.05.09 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253

20.02.05.10 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200

20.02.05.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) 468,116.40 LB $2.15 $1,006,450 15.00% 10.00% 25.00% $251,613 $1,258,063

20.02.05.11 SMALL CANOPY (7' X 20') - STAINLESS STEEL 1.00 EA $45,000.00 $45,000 0.00% 10.00% 10.00% $4,500 $49,500

20.02.05.12 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

20.02.05.13 BIKE LOCKER 6.00 EA $2,450.00 $14,700 15.00% 10.00% 25.00% $3,675 $18,375

20.02.05.15 INFORMATIONAL KIOSK 4.00 EA $7,973.00 $31,892 0.00% 10.00% 10.00% $3,189 $35,081

20.02.05.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

20.02.05.22 STAIR RAILING (STAINLESS STEEL W/GLASS PANELS) 1,028.00 LF $360.00 $370,080 15.00% 10.00% 25.00% $92,520 $462,600

20.02.05.29 LANDSCAPING 3,500.00 SF $4.70 $16,450 15.00% 10.00% 25.00% $4,113 $20,563

20.02.05.30 IRRIGATION 3,500.00 SF $1.40 $4,900 15.00% 10.00% 25.00% $1,225 $6,125

20.02.05.32 STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000

20.02.05.490605 36'' CIDH CONCRETE PILING 4,785.00 LF $507.00 $2,425,995 15.00% 15.00% 30.00% $727,799 $3,153,794

20.02.05.50 CIP CONCRETE ELEVATED WALKWAYS 149.98 CY $1,275.00 $191,225 15.00% 10.00% 25.00% $47,806 $239,031

20.02.05.52 STAIR (METAL PAN W/ CONCRETE FILL) 1,896.00 SF $25.00 $47,400 15.00% 10.00% 25.00% $11,850 $59,250

20.02.05.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 1,034.52 CY $440.00 $455,189 15.00% 10.00% 25.00% $113,797 $568,986

20.02.05.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 217,248.89 LB $1.00 $217,249 15.00% 10.00% 25.00% $54,312 $271,561

20.02.05.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250

20.02.05.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125

20.02.05.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000

20.02.05.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 10.00% 25.00% $95,000 $475,000

20.02.05.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 4.00 EA $1,109.00 $4,436 15.00% 10.00% 25.00% $1,109 $5,545

20.02.05.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900

20.02.05.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500

Monday, January 27, 2014 Page 46 of 140

Page 111: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

752,471.79 $9,855,478

12.10% 10.16% 22.26%

$2,187,236 $12,042,714Summary for Group: 20.02.05

Group 20.02.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UTC STATION Contingency

20.02.06.01 PICKET FENCE SCREEN WALL (8' X 6') 3,328.00 SF $32.00 $106,496 15.00% 10.00% 25.00% $26,624 $133,120

20.02.06.02 GLASS SCREEN WALL (8' X 6') 2,592.00 SF $112.00 $290,304 15.00% 10.00% 25.00% $72,576 $362,880

20.02.06.03 GLASS SCREEN WALL (8' X 3') - PED BRIDGE 3,552.00 SF $112.00 $397,824 15.00% 10.00% 25.00% $99,456 $497,280

20.02.06.04 ARCHITECTURAL CONCRETE FINISH (PLATFORM) 9,200.00 SF $20.00 $184,000 0.00% 10.00% 10.00% $18,400 $202,400

20.02.06.05 TACTILE WARNING STRIP 1,600.00 SF $50.00 $80,000 0.00% 10.00% 10.00% $8,000 $88,000

20.02.06.06 ARCHITECTURAL CONCRETE FINISH (PED BRIDGES/ANCILLARY SPA 10,490.00 SF $15.00 $157,350 15.00% 10.00% 25.00% $39,338 $196,688

20.02.06.08 SIGNAGE 1.00 LS $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

20.02.06.09 STATION STRIPING (THERMOPLASTIC & MARKERS) 1.00 LS $5,002.00 $5,002 15.00% 10.00% 25.00% $1,251 $6,253

20.02.06.10 LARGE CANOPY (15' X 54') - GLAZED 6.00 EA $352,000.00 $2,112,000 0.00% 10.00% 10.00% $211,200 $2,323,200

20.02.06.100 STRUCTURAL STEEL (F&I, ELEVATOR SHAFT) 554,519.00 LB $2.15 $1,192,216 15.00% 10.00% 25.00% $298,054 $1,490,270

20.02.06.11 SMALL CANOPY (7' X 20') - STAINLESS STEEL 2.00 EA $45,000.00 $90,000 0.00% 10.00% 10.00% $9,000 $99,000

20.02.06.12 STATION FURNISHINGS 1.00 LS $75,000.00 $75,000 15.00% 10.00% 25.00% $18,750 $93,750

20.02.06.15 INFORMATIONAL KIOSK 4.00 EA $7,973.00 $31,892 0.00% 10.00% 10.00% $3,189 $35,081

20.02.06.200 STATION WATER 1.00 LS $40,000.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

20.02.06.22 STAIR RAILING (STAINLESS STEEL W/GLASS) 1,085.00 LF $360.00 $390,600 15.00% 10.00% 25.00% $97,650 $488,250

20.02.06.29 LANDSCAPING 3,500.00 SF $4.70 $16,450 15.00% 10.00% 25.00% $4,113 $20,563

20.02.06.30 IRRIGATION 3,500.00 SF $1.40 $4,900 15.00% 10.00% 25.00% $1,225 $6,125

20.02.06.31 OPERATOR SHELTER 100.00 SF $33.00 $3,300 15.00% 10.00% 25.00% $825 $4,125

20.02.06.34 STATION PLUMBING 10,800.00 SF $20.00 $216,000 15.00% 10.00% 25.00% $54,000 $270,000

20.02.06.490605 36'' CIDH CONCRETE PILING 4,850.00 LF $507.00 $2,458,950 15.00% 15.00% 30.00% $737,685 $3,196,635

20.02.06.50 CIP CONCRETE ELEVATED WALKWAYS 121.33 CY $1,275.00 $154,696 15.00% 15.00% 30.00% $46,409 $201,104

20.02.06.52 STAIR (METAL PAN W/ CONCRETE FILL) 3,340.00 SF $25.00 $83,500 15.00% 10.00% 25.00% $20,875 $104,375

20.02.06.54 STRUCTURAL CONCRETE (STAIR/WALKWAY FOOTINGS) 1,156.15 CY $440.00 $508,706 15.00% 10.00% 25.00% $127,177 $635,883

20.02.06.55 BAR REINFORCING STEEL (STAIR/WALKWAY FOOTINGS) 242,791.11 LB $1.00 $242,791 15.00% 10.00% 25.00% $60,698 $303,489

20.02.06.59 CAULKING 1.00 LS $5,000.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250

20.02.06.60 FIRESTOPS 1.00 LS $2,500.00 $2,500 15.00% 10.00% 25.00% $625 $3,125

Monday, January 27, 2014 Page 47 of 140

Page 112: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.02.06.600 STATION LIGHTING 40.00 EA $5,000.00 $200,000 0.00% 10.00% 10.00% $20,000 $220,000

20.02.06.602 STATION ANCILLARY SPACES 800.00 SF $475.00 $380,000 15.00% 10.00% 25.00% $95,000 $475,000

20.02.06.603 PUBLIC TELEPHONE (HOUSING AND INFRASTRUCTURE) 2.00 EA $1,109.00 $2,218 15.00% 10.00% 25.00% $555 $2,773

20.02.06.604 TRACKWAY PAVING (AT PLATFORM) 8,820.00 SF $36.00 $317,520 15.00% 10.00% 25.00% $79,380 $396,900

20.02.06.61 AERIAL STATION STRUCTURAL 1.00 LS $450,000.00 $450,000 15.00% 10.00% 25.00% $112,500 $562,500

Sum

Average

866,205.59 $10,214,215

12.10% 10.32% 22.42%

$2,279,552 $12,493,767Summary for Group: 20.02.06

Group 20.02.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ART FEATURES (AERIAL) Contingency

20.02.10 ART FEATURES (1% AERIAL) 1.00 LS $463,912.14 $463,912 15.00% 15.00% 30.00% $139,174 $603,086

Sum

Average

1.00 $463,912

15.00% 15.00% 30.00%

$139,174 $603,086Summary for Group: 20.02.10

Sum

Average

3,497,405.74 $47,405,126

12.24% 10.36% 22.60%

$10,438,011 $57,843,137Summary for Sub Section: 20.02

Sub Section 20.06 AUTOMOBILE PARKING MULTI-STORY STRUCTURE

Group 20.06.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PARKING STRUCTURE (NOBEL STATION) Contingency

20.06.01.01 PARKING STRUCTURE, ABOVE GROUND (NOBEL STATION) 700.00STALL $21,000.00 $14,700,000 5.00% 10.00% 15.00% $2,205,000 $16,905,000

20.06.01.02 PARKING STRUCTURE, BELOW GROUND (NOBEL STATION) 100.00STALL $30,000.00 $3,000,000 5.00% 20.00% 25.00% $750,000 $3,750,000

Sum

Average

800.00 $17,700,000

5.00% 15.00% 20.00%

$2,955,000 $20,655,000Summary for Group: 20.06.01

Sum

Average

800.00 $17,700,000

5.00% 15.00% 20.00%

$2,955,000 $20,655,000Summary for Sub Section: 20.06

Sub Section 20.07 ELEVATORS, ESCALATORS

Group 20.07.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SINGLE ELEVATORS Contingency

20.07.01.05 SINGLE ELEVATOR (EXECUTIVE STATION) 2.00 EA $710,000.00 $1,420,000 0.00% 15.00% 15.00% $213,000 $1,633,000

20.07.01.06 SINGLE ELEVATOR (UTC STATION) 3.00 EA $710,000.00 $2,130,000 0.00% 15.00% 15.00% $319,500 $2,449,500

Sum

Average

5.00 $3,550,000

0.00% 15.00% 15.00%

$532,500 $4,082,500Summary for Group: 20.07.01

Group 20.07.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

DOUBLE ELEVATORS Contingency

20.07.02.02 DOUBLE ELEVATOR (UCSD EAST STATION) 2.00 EA $810,000.00 $1,620,000 0.00% 10.00% 10.00% $162,000 $1,782,000

Monday, January 27, 2014 Page 48 of 140

Page 113: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

20.07.02.03 DOUBLE ELEVATOR (UCSD WEST STATION) 1.00 EA $810,000.00 $810,000 0.00% 10.00% 10.00% $81,000 $891,000

20.07.02.04 SINGLE ELEVATOR (NOBEL STATION) 3.00 EA $710,000.00 $2,130,000 0.00% 10.00% 10.00% $213,000 $2,343,000

20.07.02.05 DOUBLE ELEVATOR (EXECUTIVE STATION) 1.00 EA $810,000.00 $810,000 0.00% 10.00% 10.00% $81,000 $891,000

20.07.02.06 DOUBLE ELEVATOR (UTC STATION) 1.00 EA $810,000.00 $810,000 0.00% 10.00% 10.00% $81,000 $891,000

Sum

Average

8.00 $6,180,000

0.00% 10.00% 10.00%

$618,000 $6,798,000Summary for Group: 20.07.02

Sum

Average

13.00 $9,730,000

0.00% 11.43% 11.43%

$1,150,500 $10,880,500Summary for Sub Section: 20.07

Sum

Average

3,631,526.74 $87,373,900

11.37% 10.44% 21.81%

$16,607,417 $103,981,317Summary for Section 20

Section 40 SITEWORK AND SPECIAL CONDITIONS

Sub Section 40.01 DEMOLITION, CLEARING, EARTHWORK

Group 40.01.01A

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

DEMOLISH PEDESTRIAN BRIDGE (750+50) Contingency

40.01.01A DEMOLISH PEDESTRIAN BRIDGE (750+50) 7,332.00 SF $27.00 $197,964 10.00% 10.00% 20.00% $39,593 $237,557

Sum

Average

7,332.00 $197,964

10.00% 10.00% 20.00%

$39,593 $237,557Summary for Group: 40.01.01A

Group 40.01.01B

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

DEMOLISH PEDESTRIAN BRIDGE (760+50) Contingency

40.01.01B DEMOLISH PEDESTRIAN BRIDGE (760+50) 9,490.00 SF $27.00 $256,230 10.00% 10.00% 20.00% $51,246 $307,476

Sum

Average

9,490.00 $256,230

10.00% 10.00% 20.00%

$51,246 $307,476Summary for Group: 40.01.01B

Group 40.01.02A

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

REMOVE EXISTING CANOPY AND LOADING DOCK Contingency

40.01.02A REMOVE EXISTING CANOPY AND LOADING DOCK 2,304.00 SF $70.00 $161,280 10.00% 10.00% 20.00% $32,256 $193,536

Sum

Average

2,304.00 $161,280

10.00% 10.00% 20.00%

$32,256 $193,536Summary for Group: 40.01.02A

Group 40.01.02B

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

REMOVE & SALVAGE EXISTING TRACK (TYPE 136RE) Contingency

40.01.02B REMOVE & SALVAGE EXISTING TRACK (TYPE 136RE) 1,486.00 LF $27.00 $40,122 10.00% 15.00% 25.00% $10,031 $50,153

Sum

Average

1,486.00 $40,122

10.00% 15.00% 25.00%

$10,031 $50,153Summary for Group: 40.01.02B

Group 40.01.02C

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

REMOVE & SALVAGE EXISTING TURNOUT Contingency

Monday, January 27, 2014 Page 49 of 140

Page 114: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.01.02C REMOVE & SALVAGE EXISTING TURNOUT (NO 15) 1.00 EA $12,948.00 $12,948 0.00% 15.00% 15.00% $1,942 $14,890

40.01.02C REMOVE & SALVAGE EXISTING TURNOUT (NO 20) 1.00 EA $23,304.00 $23,304 0.00% 15.00% 15.00% $3,496 $26,800

Sum

Average

2.00 $36,252

0.00% 15.00% 15.00%

$5,438 $41,690Summary for Group: 40.01.02C

Group 40.01.02D

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

REMOVE & SALVAGE EXISTING SPUR AND TURNOUT Contingency

40.01.02D REMOVE & SALVAGE EXISTING TURNOUT (NO 15) 1.00 EA $12,948.00 $12,948 0.00% 15.00% 15.00% $1,942 $14,890

Sum

Average

1.00 $12,948

0.00% 15.00% 15.00%

$1,942 $14,890Summary for Group: 40.01.02D

Group 40.01.02E

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SALVAGE EXISTING TURNOUT Contingency

40.01.02E SALVAGE EXISTING TURNOUT 1.00 EA $11,771.00 $11,771 10.00% 15.00% 25.00% $2,943 $14,714

Sum

Average

1.00 $11,771

10.00% 15.00% 25.00%

$2,943 $14,714Summary for Group: 40.01.02E

Group 40.01.02F

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

REMOVE & SALVAGE OH SIGNAL SYSTEM Contingency

40.01.02F REMOVE & SALVAGE OH SIGNAL SYSTEM 1.00 EA $50,000.00 $50,000 0.00% 15.00% 15.00% $7,500 $57,500

Sum

Average

1.00 $50,000

0.00% 15.00% 15.00%

$7,500 $57,500Summary for Group: 40.01.02F

Group 40.01.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PARTIAL BRIDGE REMOVAL Contingency

40.01.03.157560 BRIDGE REMOVAL (PARTIAL, SAN DIEGO RIVER) 1.00 LS $25,000.00 $25,000 10.00% 10.00% 20.00% $5,000 $30,000

Sum

Average

1.00 $25,000

10.00% 10.00% 20.00%

$5,000 $30,000Summary for Group: 40.01.03

Group 40.01.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CLEARING AND GRUBBING (GUIDEWAY) Contingency

40.01.04 CLEARING AND GRUBBING 10.21 AC $4,022.00 $41,065 10.00% 15.00% 25.00% $10,266 $51,331

40.01.04 CLEARING AND GRUBBING 38.52 AC $4,022.00 $154,927 10.00% 15.00% 25.00% $38,732 $193,659

40.01.04 CLEARING AND GRUBBING 18.50 AC $4,022.00 $74,407 10.00% 15.00% 25.00% $18,602 $93,009

40.01.04 CLEARING AND GRUBBING 0.69 AC $4,022.00 $2,771 10.00% 15.00% 25.00% $693 $3,464

Sum

Average

67.92 $273,170

10.00% 15.00% 25.00%

$68,293 $341,463Summary for Group: 40.01.04

Group 40.01.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PERMANENT BMP (DEMOLITION, CLEARING, EARTHWORK) Contingency

Monday, January 27, 2014 Page 50 of 140

Page 115: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.01.05 PERMANENT BMP (DEMOLITION, CLEARING, EARTHWORK) 1.00 LS $50,000.00 $50,000 0.00% 20.00% 20.00% $10,000 $60,000

Sum

Average

1.00 $50,000

0.00% 20.00% 20.00%

$10,000 $60,000Summary for Group: 40.01.05

Group 40.01.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

DEMOLISH TEMPORARY WALL Contingency

40.01.06 DEMOLITION OF TEMPORARY WALL (SHOOFLY) 906.00 LF $40.00 $36,240 10.00% 15.00% 25.00% $9,060 $45,300

Sum

Average

906.00 $36,240

10.00% 15.00% 25.00%

$9,060 $45,300Summary for Group: 40.01.06

Group 40.01.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

REMOVE EXIST RAMP AND STAIRS Contingency

40.01.07 REMOVE EXIST RAMP AND STAIRS 715.00 SF $70.00 $50,050 10.00% 10.00% 20.00% $10,010 $60,060

Sum

Average

715.00 $50,050

10.00% 10.00% 20.00%

$10,010 $60,060Summary for Group: 40.01.07

Group 40.01.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

REMOVE EXIST OPEN CHANNEL Contingency

40.01.08 REMOVE EXIST OPEN CHANNEL 36,555.00 SF $5.50 $201,053 5.00% 15.00% 20.00% $40,211 $241,263

Sum

Average

36,555.00 $201,053

5.00% 15.00% 20.00%

$40,211 $241,263Summary for Group: 40.01.08

Sum

Average

58,862.92 $1,402,080

6.94% 13.89% 20.83%

$293,521 $1,695,601Summary for Sub Section: 40.01

Sub Section 40.02 SITE UTILITIES, UTILITY RELOCATION

Group 40.02.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

WET UTILITY RELOCATION Contingency

40.02.01.1101 CONNECT TO Exist 30" RCSC WATER 1.00 EA $9,344.00 $9,344 15.00% 10.00% 25.00% $2,336 $11,680

40.02.01.1102 CONNECT TO Exist 24" SCRW WATER 2.00 EA $8,721.00 $17,442 15.00% 10.00% 25.00% $4,361 $21,803

40.02.01.1102 CONNECT TO Exist 24" SCRW WATER 2.00 EA $8,721.00 $17,442 15.00% 10.00% 25.00% $4,361 $21,803

40.02.01.1103 CONNECT TO Exist 20" ACP WATER 1.00 EA $4,361.00 $4,361 15.00% 10.00% 25.00% $1,090 $5,451

40.02.01.1104 CONNECT TO Exist 16" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1104 CONNECT TO Exist 16" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1105 CONNECT TO Exist 12" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1105 CONNECT TO Exist 12" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1105 CONNECT TO Exist 12" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1106 CONNECT TO Exist 10" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

Monday, January 27, 2014 Page 51 of 140

Page 116: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.1106 CONNECT TO Exist 10" ACP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1107 CONNECT TO Exist 8" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1107 CONNECT TO Exist 8" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1108 CONNECT TO Exist 6" ACP WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1110 CONNECT TO Exist 16" PVC RECLAIMED WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1111 CONNECT TO Exist 12" PVC WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1112 CONNECT TO Exist 8" PVC WATER 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1113 CONNECT TO Exist 16" CIP WATER 3.00 EA $3,474.00 $10,422 15.00% 10.00% 25.00% $2,606 $13,028

40.02.01.1114 CONNECT TO Exist 12" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1114 CONNECT TO Exist 12" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1114 CONNECT TO Exist 12" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1114 CONNECT TO Exist 12" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1115 CONNECT TO Exist 10" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1116 CONNECT TO Exist 8" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1116 CONNECT TO Exist 8" CIP WATER 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1117 CONNECT TO Exist 6" FH LEAD 2.00 EA $3,474.00 $6,948 15.00% 10.00% 25.00% $1,737 $8,685

40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1117 CONNECT TO Exist 6" FH LEAD 1.00 EA $3,474.00 $3,474 15.00% 10.00% 25.00% $869 $4,343

40.02.01.1118 CONNECT TO Exist 8" WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584

40.02.01.1119 CONNECT TO Exist 6" WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584

40.02.01.1120 CONNECT TO Exist 4" WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584

40.02.01.1121 CONNECT TO Exist 2" WATER SERVICE 2.00 EA $2,867.00 $5,734 15.00% 10.00% 25.00% $1,434 $7,168

40.02.01.1122 CONNECT TO Exist 1 1/4" COPPER WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584

40.02.01.1123 CONNECT TO Exist 1" COPPER WATER SERVICE 4.00 EA $2,867.00 $11,468 15.00% 10.00% 25.00% $2,867 $14,335

40.02.01.1123 CONNECT TO Exist 1" COPPER WATER SERVICE 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584

Monday, January 27, 2014 Page 52 of 140

Page 117: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.1124 CONNECT TO Exist xx" WATER LATERAL 1.00 EA $2,867.00 $2,867 15.00% 10.00% 25.00% $717 $3,584

40.02.01.1125 CONNECT TO Exist 36" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.1126 CONNECT TO Exist 24" WSP CASING WITH WELDED JOINT 1.00 EA $935.00 $935 15.00% 10.00% 25.00% $234 $1,169

40.02.01.1127 CONNECT TO Exist 22" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.1128 CONNECT TO Exist 18" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.1129 CONNECT TO Exist 16" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.1130 CONNECT TO Exist 14" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.1131 CONNECT 26" HDPE WATER TO 20" PVC WATER 2.00 EA $7,475.00 $14,950 15.00% 10.00% 25.00% $3,738 $18,688

40.02.01.1202 24" 22.5^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690

40.02.01.1202 24" 22.5^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690

40.02.01.1203 20" 45^ BEND 6.00 EA $3,738.00 $22,428 15.00% 10.00% 25.00% $5,607 $28,035

40.02.01.1204 20" 22.5^ BEND 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673

40.02.01.1205 16" 45^ BEND 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673

40.02.01.1205 16" 45^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690

40.02.01.1205 16" 45^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690

40.02.01.1205 16" 45^ BEND 4.00 EA $3,738.00 $14,952 15.00% 10.00% 25.00% $3,738 $18,690

40.02.01.1206 12" 90^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1207 12" 45^ BEND 4.00 EA $1,247.00 $4,988 15.00% 10.00% 25.00% $1,247 $6,235

40.02.01.1207 12" 45^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1207 12" 45^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1207 12" 45^ BEND 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118

40.02.01.1208 12" 11.25^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1209 10" 45^ BEND 4.00 EA $1,247.00 $4,988 15.00% 10.00% 25.00% $1,247 $6,235

40.02.01.1209 10" 45^ BEND 4.00 EA $1,247.00 $4,988 15.00% 10.00% 25.00% $1,247 $6,235

40.02.01.1210 10" 11.25^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1211 8" 45^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1211 8" 45^ BEND 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118

40.02.01.1212 8" 11.25^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1213 6" 45^ BEND 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

Monday, January 27, 2014 Page 53 of 140

Page 118: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.1214 20" X 30" TEE 1.00 EA $4,361.00 $4,361 15.00% 10.00% 25.00% $1,090 $5,451

40.02.01.1216 20" X 12" TEE 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673

40.02.01.1217 20" X x" TEE 2.00 EA $3,738.00 $7,476 15.00% 10.00% 25.00% $1,869 $9,345

40.02.01.1218 16" X 12" TEE 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673

40.02.01.1219 16" X 6" TEE 1.00 EA $3,738.00 $3,738 15.00% 10.00% 25.00% $935 $4,673

40.02.01.1220 12" X 12" TEE 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1221 12" X 6" TEE 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1222 10" X 8" TEE 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118

40.02.01.1223 10" X 6" TEE 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1223 10" X 6" TEE 8.00 EA $1,247.00 $9,976 15.00% 10.00% 25.00% $2,494 $12,470

40.02.01.1224 10" X 4" TEE 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1301 36" WSP CASING 24.00 LF $779.00 $18,696 15.00% 10.00% 25.00% $4,674 $23,370

40.02.01.1302 28" WSP CASING - JACK CONSTRUCTION 120.00 LF $1,496.00 $179,520 15.00% 10.00% 25.00% $44,880 $224,400

40.02.01.1303 24" WSP CASING 44.00 LF $413.00 $18,172 15.00% 10.00% 25.00% $4,543 $22,715

40.02.01.1304 22" WSP CASING 30.00 LF $413.00 $12,390 15.00% 10.00% 25.00% $3,098 $15,488

40.02.01.1304 22" WSP CASING 48.00 LF $413.00 $19,824 15.00% 10.00% 25.00% $4,956 $24,780

40.02.01.1305 20" WSP CASING 49.00 LF $339.00 $16,611 15.00% 10.00% 25.00% $4,153 $20,764

40.02.01.1306 18" WSP CASING 37.00 LF $305.00 $11,285 15.00% 10.00% 25.00% $2,821 $14,106

40.02.01.1307 16" WSP CASING 38.00 LF $200.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500

40.02.01.1308 14" WSP CASING 50.00 LF $182.00 $9,100 15.00% 10.00% 25.00% $2,275 $11,375

40.02.01.1402 24" SCRW WATER 66.00 LF $812.00 $53,592 15.00% 10.00% 25.00% $13,398 $66,990

40.02.01.1402 24" SCRW WATER 130.00 LF $812.00 $105,560 15.00% 10.00% 25.00% $26,390 $131,950

40.02.01.1403 26" HDPE WATER - TRENCHLESS CONSTRUCTION 120.00 LF $498.00 $59,760 15.00% 10.00% 25.00% $14,940 $74,700

40.02.01.1404 20" PVC WATER 458.00 LF $207.00 $94,806 15.00% 10.00% 25.00% $23,702 $118,508

40.02.01.1405 16" PVC RECLAIMED WATER 41.00 LF $166.00 $6,806 15.00% 10.00% 25.00% $1,702 $8,508

40.02.01.1406 16" PVC WATER 54.00 LF $166.00 $8,964 15.00% 10.00% 25.00% $2,241 $11,205

40.02.01.1406 16" PVC WATER 54.00 LF $166.00 $8,964 15.00% 10.00% 25.00% $2,241 $11,205

40.02.01.1406 16" PVC WATER 1,645.00 LF $166.00 $273,070 15.00% 10.00% 25.00% $68,268 $341,338

40.02.01.1407 12" PVC WATER 166.00 LF $129.00 $21,414 15.00% 10.00% 25.00% $5,354 $26,768

Monday, January 27, 2014 Page 54 of 140

Page 119: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.1407 12" PVC WATER 185.00 LF $129.00 $23,865 15.00% 10.00% 25.00% $5,966 $29,831

40.02.01.1407 12" PVC WATER 24.00 LF $129.00 $3,096 15.00% 10.00% 25.00% $774 $3,870

40.02.01.1407 12" PVC WATER 43.00 LF $129.00 $5,547 15.00% 10.00% 25.00% $1,387 $6,934

40.02.01.1407 12" PVC WATER 30.00 LF $129.00 $3,870 15.00% 10.00% 25.00% $968 $4,838

40.02.01.1408 10" PVC WATER 157.00 LF $104.00 $16,328 15.00% 10.00% 25.00% $4,082 $20,410

40.02.01.1408 10" PVC WATER 56.00 LF $104.00 $5,824 15.00% 10.00% 25.00% $1,456 $7,280

40.02.01.1408 10" PVC WATER 1,561.00 LF $104.00 $162,344 15.00% 10.00% 25.00% $40,586 $202,930

40.02.01.1409 8" PVC WATER 83.00 LF $94.00 $7,802 15.00% 10.00% 25.00% $1,951 $9,753

40.02.01.1409 8" PVC WATER 49.00 LF $94.00 $4,606 15.00% 10.00% 25.00% $1,152 $5,758

40.02.01.1409 8" PVC WATER 57.00 LF $94.00 $5,358 15.00% 10.00% 25.00% $1,340 $6,698

40.02.01.1410 6" PVC WATER 10.00 LF $94.00 $940 15.00% 10.00% 25.00% $235 $1,175

40.02.01.1411 6" DIP FH HEAD 8.00 LF $351.00 $2,808 15.00% 10.00% 25.00% $702 $3,510

40.02.01.1411 6" DIP FH HEAD 10.00 LF $351.00 $3,510 15.00% 10.00% 25.00% $878 $4,388

40.02.01.1411 6" DIP FH HEAD 79.00 LF $351.00 $27,729 15.00% 10.00% 25.00% $6,932 $34,661

40.02.01.1411 6" DIP FH HEAD 62.00 LF $351.00 $21,762 15.00% 10.00% 25.00% $5,441 $27,203

40.02.01.1411 6" DIP FH HEAD 13.00 LF $351.00 $4,563 15.00% 10.00% 25.00% $1,141 $5,704

40.02.01.1411 6" DIP FH HEAD 7.00 LF $351.00 $2,457 15.00% 10.00% 25.00% $614 $3,071

40.02.01.1411 6" DIP FH HEAD 6.00 LF $351.00 $2,106 15.00% 10.00% 25.00% $527 $2,633

40.02.01.1411 6" DIP FH HEAD 202.00 LF $351.00 $70,902 15.00% 10.00% 25.00% $17,726 $88,628

40.02.01.1412 8" PVC WATER SERVICE 40.00 LF $351.00 $14,040 15.00% 10.00% 25.00% $3,510 $17,550

40.02.01.1413 4" PVC WATER SERVICE 10.00 LF $351.00 $3,510 15.00% 10.00% 25.00% $878 $4,388

40.02.01.1414 2" PVC WATER SERVICE 8.00 LF $189.00 $1,512 15.00% 10.00% 25.00% $378 $1,890

40.02.01.1415 1" COPPER WATER SERVICE 106.00 LF $187.00 $19,822 15.00% 10.00% 25.00% $4,956 $24,778

40.02.01.1416 XX" WATER SERVICE 21.00 EA $351.00 $7,371 15.00% 10.00% 25.00% $1,843 $9,214

40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531

40.02.01.1417 FIRE HYDRANT 4.00 EA $8,425.00 $33,700 15.00% 10.00% 25.00% $8,425 $42,125

40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531

40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531

40.02.01.1417 FIRE HYDRANT 2.00 EA $8,425.00 $16,850 15.00% 10.00% 25.00% $4,213 $21,063

Monday, January 27, 2014 Page 55 of 140

Page 120: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531

40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531

40.02.01.1417 FIRE HYDRANT 1.00 EA $8,425.00 $8,425 15.00% 10.00% 25.00% $2,106 $10,531

40.02.01.1418 1 1/4" CORPORATION STOP 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.1419 1" CORPORATION STOP 4.00 EA $1,670.00 $6,680 15.00% 10.00% 25.00% $1,670 $8,350

40.02.01.1419 1" CORPORATION STOP 1.00 EA $1,670.00 $1,670 15.00% 10.00% 25.00% $418 $2,088

40.02.01.1420 8" ABOVE GROUND METER INSTALLATION WITH BYPASS PER SDRS 1.00 EA $8,645.00 $8,645 15.00% 10.00% 25.00% $2,161 $10,806

40.02.01.1421 2" POLYMERE Conc METER BOX AND APPURTENANCES PER SDRSD 1.00 EA $1,200.00 $1,200 15.00% 10.00% 25.00% $300 $1,500

40.02.01.1422 1" POLYMERE Conc METER BOX AND APPURTENANCES PER SDRSD 2.00 EA $1,200.00 $2,400 15.00% 10.00% 25.00% $600 $3,000

40.02.01.1424 Abn Exist 24" SCRW WATER 63.00 LF $19.00 $1,197 15.00% 10.00% 25.00% $299 $1,496

40.02.01.1424 Abn Exist 24" SCRW WATER 126.00 LF $19.00 $2,394 15.00% 10.00% 25.00% $599 $2,993

40.02.01.1425 Abn Exist 20" WATER 619.00 LF $19.00 $11,761 15.00% 10.00% 25.00% $2,940 $14,701

40.02.01.1426 Abn Exist 16" ACP WATER 47.00 LF $19.00 $893 15.00% 10.00% 25.00% $223 $1,116

40.02.01.1426 Abn Exist 16" ACP WATER 1,622.00 LF $19.00 $30,818 15.00% 10.00% 25.00% $7,705 $38,523

40.02.01.1427 Abn Exist 10" ACP WATER 147.00 LF $19.00 $2,793 15.00% 10.00% 25.00% $698 $3,491

40.02.01.1427 Abn Exist 10" ACP WATER 1,538.00 LF $19.00 $29,222 15.00% 10.00% 25.00% $7,306 $36,528

40.02.01.1428 Abn Exist 8" ACP WATER 83.00 LF $19.00 $1,577 15.00% 10.00% 25.00% $394 $1,971

40.02.01.1428 Abn Exist 8" ACP WATER 15.00 LF $19.00 $285 15.00% 10.00% 25.00% $71 $356

40.02.01.1429 Abn Exist 16" PVC RECLAIMED WATER 34.00 LF $19.00 $646 15.00% 10.00% 25.00% $162 $808

40.02.01.1430 Abn Exist 12" PVC WATER 18.00 LF $19.00 $342 15.00% 10.00% 25.00% $86 $428

40.02.01.1431 Abn Exist 12" CIP WATER 183.00 LF $19.00 $3,477 15.00% 10.00% 25.00% $869 $4,346

40.02.01.1431 Abn Exist 12" CIP WATER 176.00 LF $19.00 $3,344 15.00% 10.00% 25.00% $836 $4,180

40.02.01.1432 Abn Exist 6" FH LEAD 17.00 LF $19.00 $323 15.00% 10.00% 25.00% $81 $404

40.02.01.1432 Abn Exist 6" FH LEAD 206.00 LF $19.00 $3,914 15.00% 10.00% 25.00% $979 $4,893

40.02.01.1432 Abn Exist 6" FH LEAD 52.00 LF $19.00 $988 15.00% 10.00% 25.00% $247 $1,235

40.02.01.1432 Abn Exist 6" FH LEAD 55.00 LF $19.00 $1,045 15.00% 10.00% 25.00% $261 $1,306

40.02.01.1432 Abn Exist 6" FH LEAD 14.00 LF $19.00 $266 15.00% 10.00% 25.00% $67 $333

40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24

40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24

Monday, January 27, 2014 Page 56 of 140

Page 121: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24

40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24

40.02.01.1433 REMOVE Exist FIRE HYDRANT 2.00 LF $19.00 $38 15.00% 10.00% 25.00% $10 $48

40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24

40.02.01.1433 REMOVE Exist FIRE HYDRANT 1.00 LF $19.00 $19 15.00% 10.00% 25.00% $5 $24

40.02.01.1433 REMOVE Exist FIRE HYDRANT 4.00 LF $19.00 $76 15.00% 10.00% 25.00% $19 $95

40.02.01.1434 Abn Exist MH 2.00 LF $1,237.00 $2,474 15.00% 10.00% 25.00% $619 $3,093

40.02.01.1435 Abn Exist 8" WATER SERVICE 48.00 LF $19.00 $912 15.00% 10.00% 25.00% $228 $1,140

40.02.01.1436 Abn Exist 6" WATER SERVICE 15.00 LF $19.00 $285 15.00% 10.00% 25.00% $71 $356

40.02.01.1437 Abn Exist 1 1/4" COPPER WATER SERVICE 20.00 LF $19.00 $380 15.00% 10.00% 25.00% $95 $475

40.02.01.1438 Abn Exist 1" COPPER WATER SERVICE 75.00 LF $19.00 $1,425 15.00% 10.00% 25.00% $356 $1,781

40.02.01.1438 Abn Exist 1" COPPER WATER SERVICE 14.00 LF $19.00 $266 15.00% 10.00% 25.00% $67 $333

40.02.01.1439 Abn Exist XX" WATER SERVICE 12.00 LF $19.00 $228 15.00% 10.00% 25.00% $57 $285

40.02.01.1501 20" BUTTERFLY VALVE 2.00 LF $12,583.00 $25,166 15.00% 10.00% 25.00% $6,292 $31,458

40.02.01.1502 16" BUTTERFLY VALVE 1.00 EA $347.00 $347 15.00% 10.00% 25.00% $87 $434

40.02.01.1503 12" GATE VALVE 2.00 EA $2,866.00 $5,732 15.00% 10.00% 25.00% $1,433 $7,165

40.02.01.1503 12" GATE VALVE 1.00 EA $2,866.00 $2,866 15.00% 10.00% 25.00% $717 $3,583

40.02.01.1504 10" GATE VALVE 2.00 EA $2,368.00 $4,736 15.00% 10.00% 25.00% $1,184 $5,920

40.02.01.1505 8" GATE VALVE 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.1505 8" GATE VALVE 2.00 EA $1,870.00 $3,740 15.00% 10.00% 25.00% $935 $4,675

40.02.01.1506 6" GATE VALVE 6.00 EA $1,558.00 $9,348 15.00% 10.00% 25.00% $2,337 $11,685

40.02.01.1506 6" GATE VALVE 1.00 EA $1,558.00 $1,558 15.00% 10.00% 25.00% $390 $1,948

40.02.01.1506 6" GATE VALVE 1.00 EA $1,558.00 $1,558 15.00% 10.00% 25.00% $390 $1,948

40.02.01.1506 6" GATE VALVE 2.00 EA $1,558.00 $3,116 15.00% 10.00% 25.00% $779 $3,895

40.02.01.1506 6" GATE VALVE 1.00 EA $1,558.00 $1,558 15.00% 10.00% 25.00% $390 $1,948

40.02.01.1507 XX" GATE VALVE 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.1601 8" WATER SERVICE TEMPORARY LOWERING 1.00 EA $6,229.00 $6,229 15.00% 10.00% 25.00% $1,557 $7,786

40.02.01.1602 6" WATER SERVICE TEMPORARY LOWERING 1.00 EA $6,229.00 $6,229 15.00% 10.00% 25.00% $1,557 $7,786

40.02.01.1603 CONC PROTECTION FOR Exist PIPE 3.00 CY $249.00 $747 15.00% 10.00% 25.00% $187 $934

Monday, January 27, 2014 Page 57 of 140

Page 122: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.1604 COVER BERM GRADING 1.00 LS $6,229.00 $6,229 15.00% 10.00% 25.00% $1,557 $7,786

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 3.00 EA $998.00 $2,994 15.00% 10.00% 25.00% $749 $3,743

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 9.00 EA $998.00 $8,982 15.00% 10.00% 25.00% $2,246 $11,228

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 6.00 EA $998.00 $5,988 15.00% 10.00% 25.00% $1,497 $7,485

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 1.00 EA $998.00 $998 15.00% 10.00% 25.00% $250 $1,248

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 1.00 EA $998.00 $998 15.00% 10.00% 25.00% $250 $1,248

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 4.00 EA $998.00 $3,992 15.00% 10.00% 25.00% $998 $4,990

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 15.00 EA $998.00 $14,970 15.00% 10.00% 25.00% $3,743 $18,713

40.02.01.1605 THRUST BLOCK PER CSD Std DRAWING WT-01 1.00 EA $998.00 $998 15.00% 10.00% 25.00% $250 $1,248

40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 2.00 EA $1,370.00 $2,740 15.00% 10.00% 25.00% $685 $3,425

40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 1.00 EA $1,370.00 $1,370 15.00% 10.00% 25.00% $343 $1,713

40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 1.00 EA $1,370.00 $1,370 15.00% 10.00% 25.00% $343 $1,713

40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 5.00 EA $1,370.00 $6,850 15.00% 10.00% 25.00% $1,713 $8,563

40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 2.00 EA $1,370.00 $2,740 15.00% 10.00% 25.00% $685 $3,425

40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 2.00 EA $1,370.00 $2,740 15.00% 10.00% 25.00% $685 $3,425

40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 1.00 EA $1,370.00 $1,370 15.00% 10.00% 25.00% $343 $1,713

40.02.01.1606 ANCHOR BLOCK PER CSD Std DRAWING WT-01 2.00 EA $1,370.00 $2,740 15.00% 10.00% 25.00% $685 $3,425

40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1607 END SEAL 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118

40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

Monday, January 27, 2014 Page 58 of 140

Page 123: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.1607 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.1608 PRESSURE CONTROL STATION FACILITY 1.00 LS $59,000.00 $59,000 15.00% 10.00% 25.00% $14,750 $73,750

40.02.01.2101 CONNECT Exist Conc CASING WITH Conc COLLAR 1.00 CY $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.2102 CONNECT TO Exist 16" CIP Swr WITH ECCENTRIC REDUCER 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2104 CONNECT TO Exist MH PER CSD Std SM-04 1.00 EA $1,172.00 $1,172 15.00% 10.00% 25.00% $293 $1,465

40.02.01.2104 CONNECT TO Exist MH PER CSD Std SM-04 1.00 EA $1,172.00 $1,172 15.00% 10.00% 25.00% $293 $1,465

40.02.01.2104 CONNECT TO Exist MH PER CSD Std SM-04 1.00 EA $1,172.00 $1,172 15.00% 10.00% 25.00% $293 $1,465

40.02.01.2105 CONNECT TO Exist 48" WSP CASING WITH WELDED JOINT 1.00 EA $998.00 $998 15.00% 10.00% 25.00% $250 $1,248

40.02.01.2106 CONNECT TO Exist 42" WSP CASING WITH WELDED JOINT 1.00 EA $935.00 $935 15.00% 10.00% 25.00% $234 $1,169

40.02.01.2107 CONNECT TO Exist 24" WSP CASING WITH WELDED JOINT 1.00 EA $935.00 $935 15.00% 10.00% 25.00% $234 $1,169

40.02.01.2108 CONNECT TO Exist 18" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.2108 CONNECT TO Exist 18" WSP CASING WITH WELDED JOINT 1.00 EA $1,870.00 $1,870 15.00% 10.00% 25.00% $468 $2,338

40.02.01.2201 74" WSP CASING 45.00 LF $2,742.00 $123,390 15.00% 10.00% 25.00% $30,848 $154,238

40.02.01.2202 48" WSP CASING 72.00 LF $1,389.00 $100,008 15.00% 10.00% 25.00% $25,002 $125,010

40.02.01.2203 42" WSP CASING 70.00 LF $1,370.00 $95,900 15.00% 10.00% 25.00% $23,975 $119,875

40.02.01.2204 28" WSP CASING 34.00 LF $690.00 $23,460 15.00% 10.00% 25.00% $5,865 $29,325

40.02.01.2205 24" WSP CASING 45.00 LF $413.00 $18,585 15.00% 10.00% 25.00% $4,646 $23,231

40.02.01.2206 18" WSP CASING 72.00 LF $305.00 $21,960 15.00% 10.00% 25.00% $5,490 $27,450

40.02.01.2206 18" WSP CASING 58.00 LF $305.00 $17,690 15.00% 10.00% 25.00% $4,423 $22,113

40.02.01.2207 60" CLASS 145-20 STEEL Swr 588.00 LF $2,180.00 $1,281,840 15.00% 10.00% 25.00% $320,460 $1,602,300

40.02.01.2208 45" PLASTIC LINED RCP Swr 57.00 LF $873.00 $49,761 15.00% 10.00% 25.00% $12,440 $62,201

40.02.01.2209 42" PLASTIC LINED RCP Swr 69.00 LF $738.00 $50,922 15.00% 10.00% 25.00% $12,731 $63,653

40.02.01.2209 42" PLASTIC LINED RCP Swr 875.00 LF $738.00 $645,750 15.00% 10.00% 25.00% $161,438 $807,188

40.02.01.2210 21" ESVC Swr 752.00 LF $142.00 $106,784 15.00% 10.00% 25.00% $26,696 $133,480

40.02.01.2212 30" VCP Swr 70.00 LF $162.00 $11,340 15.00% 10.00% 25.00% $2,835 $14,175

40.02.01.2213 15" VCP Swr 34.00 LF $142.00 $4,828 15.00% 10.00% 25.00% $1,207 $6,035

40.02.01.2214 8" VCP Swr 45.00 LF $77.00 $3,465 15.00% 10.00% 25.00% $866 $4,331

40.02.01.2215 27" PVC Swr 92.00 LF $142.00 $13,064 15.00% 10.00% 25.00% $3,266 $16,330

40.02.01.2216 24" PVC Swr 33.00 LF $142.00 $4,686 15.00% 10.00% 25.00% $1,172 $5,858

Monday, January 27, 2014 Page 59 of 140

Page 124: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.2217 12" PVC Swr 36.00 LF $116.00 $4,176 15.00% 10.00% 25.00% $1,044 $5,220

40.02.01.2217 12" PVC Swr 129.00 LF $116.00 $14,964 15.00% 10.00% 25.00% $3,741 $18,705

40.02.01.2218 10" PVC Swr 100.00 LF $116.00 $11,600 15.00% 10.00% 25.00% $2,900 $14,500

40.02.01.2219 8" CIP Swr 58.00 LF $187.00 $10,846 15.00% 10.00% 25.00% $2,712 $13,558

40.02.01.2301 TEMPORARY 42" RCP Swr 86.00 LF $498.00 $42,828 15.00% 10.00% 25.00% $10,707 $53,535

40.02.01.2302 TEMPORARY 30" PVC Swr 100.00 LF $142.00 $14,200 15.00% 10.00% 25.00% $3,550 $17,750

40.02.01.2303 TEMPORARY 27" PVC Swr 118.00 LF $180.00 $21,240 15.00% 10.00% 25.00% $5,310 $26,550

40.02.01.2304 TEMPORARY 24" PVC Swr 42.00 LF $180.00 $7,560 15.00% 10.00% 25.00% $1,890 $9,450

40.02.01.2305 SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000

40.02.01.2305 SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000

40.02.01.2306 SEWER MH 1.00 EA $4,400.00 $4,400 15.00% 10.00% 25.00% $1,100 $5,500

40.02.01.2306 SEWER MH 3.00 EA $4,400.00 $13,200 15.00% 10.00% 25.00% $3,300 $16,500

40.02.01.2306 SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000

40.02.01.2306 SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000

40.02.01.2306 SEWER MH 3.00 EA $4,400.00 $13,200 15.00% 10.00% 25.00% $3,300 $16,500

40.02.01.2306 SEWER MH 3.00 EA $4,400.00 $13,200 15.00% 10.00% 25.00% $3,300 $16,500

40.02.01.2307 TEMPORARY SEWER MH 3.00 EA $4,400.00 $13,200 15.00% 10.00% 25.00% $3,300 $16,500

40.02.01.2307 TEMPORARY SEWER MH 4.00 EA $4,400.00 $17,600 15.00% 10.00% 25.00% $4,400 $22,000

40.02.01.2307 TEMPORARY SEWER MH 2.00 EA $4,400.00 $8,800 15.00% 10.00% 25.00% $2,200 $11,000

40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2401 END SEAL 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2402 45" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2403 30" PLUG 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118

40.02.01.2404 27" PLUG 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118

40.02.01.2405 24" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

Monday, January 27, 2014 Page 60 of 140

Page 125: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.2405 24" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2406 21" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2407 12" PLUG 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118

40.02.01.2407 12" PLUG 2.00 EA $1,247.00 $2,494 15.00% 10.00% 25.00% $624 $3,118

40.02.01.2408 8" PLUG 1.00 EA $1,247.00 $1,247 15.00% 10.00% 25.00% $312 $1,559

40.02.01.2409 CONC ENCASEMENT 150.00 CY $249.00 $37,350 15.00% 10.00% 25.00% $9,338 $46,688

40.02.01.2901 REMOVE Exist MH 1.00 EA $1,978.00 $1,978 15.00% 10.00% 25.00% $495 $2,473

40.02.01.2901 REMOVE Exist MH 2.00 EA $1,978.00 $3,956 15.00% 10.00% 25.00% $989 $4,945

40.02.01.2902 Abn Exist MH 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546

40.02.01.2902 Abn Exist MH 2.00 EA $1,237.00 $2,474 15.00% 10.00% 25.00% $619 $3,093

40.02.01.2902 Abn Exist MH 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546

40.02.01.2902 Abn Exist MH 2.00 EA $1,237.00 $2,474 15.00% 10.00% 25.00% $619 $3,093

40.02.01.2902 Abn Exist MH 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546

40.02.01.2902 Abn Exist MH 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546

40.02.01.2903 Abn TEMOPORARY MH 4.00 EA $1,978.00 $7,912 15.00% 10.00% 25.00% $1,978 $9,890

40.02.01.2903 Abn TEMOPORARY MH 3.00 EA $1,978.00 $5,934 15.00% 10.00% 25.00% $1,484 $7,418

40.02.01.2903 Abn TEMOPORARY MH 3.00 EA $1,978.00 $5,934 15.00% 10.00% 25.00% $1,484 $7,418

40.02.01.2904 Abn Exist 60" CLASS 145-20 STEEL Swr 627.00 LF $153.00 $95,931 15.00% 10.00% 25.00% $23,983 $119,914

40.02.01.2905 Abn Exist 42" PLASTIC LINED RCP Swr 72.00 LF $102.00 $7,344 15.00% 10.00% 25.00% $1,836 $9,180

40.02.01.2905 Abn Exist 42" PLASTIC LINED RCP Swr 875.00 LF $102.00 $89,250 15.00% 10.00% 25.00% $22,313 $111,563

40.02.01.2906 Abn Exist 21" ESVC Swr 754.00 LF $63.00 $47,502 15.00% 10.00% 25.00% $11,876 $59,378

40.02.01.2907 Abn Exist 21" VCP Conc ENCASED Swr 92.00 LF $63.00 $5,796 15.00% 10.00% 25.00% $1,449 $7,245

40.02.01.2908 Abn Exist 12" VCP Swr 117.00 LF $17.00 $1,989 15.00% 10.00% 25.00% $497 $2,486

40.02.01.2908 Abn Exist 12" VCP Swr 25.00 LF $17.00 $425 15.00% 10.00% 25.00% $106 $531

40.02.01.2909 Abn Exist 10" VCP Swr 63.00 LF $17.00 $1,071 15.00% 10.00% 25.00% $268 $1,339

40.02.01.2910 Abn Exist 8" VCP Swr 80.00 LF $17.00 $1,360 15.00% 10.00% 25.00% $340 $1,700

40.02.01.2910 Abn Exist 8" VCP Swr 50.00 LF $17.00 $850 15.00% 10.00% 25.00% $213 $1,063

40.02.01.2911 Abn Exist 24" PVC Swr 66.00 LF $17.00 $1,122 15.00% 10.00% 25.00% $281 $1,403

40.02.01.2912 Abn Exist 8" LATERAL 31.00 LF $17.00 $527 15.00% 10.00% 25.00% $132 $659

Monday, January 27, 2014 Page 61 of 140

Page 126: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.02.01.2913 Abn Exist 6" LATERAL 26.00 LF $17.00 $442 15.00% 10.00% 25.00% $111 $553

40.02.01.2913 Abn Exist 6" LATERAL 24.00 LF $17.00 $408 15.00% 10.00% 25.00% $102 $510

40.02.01.2913 Abn Exist 6" LATERAL 25.00 LF $17.00 $425 15.00% 10.00% 25.00% $106 $531

40.02.01.2915 Abn TEMPORARY 42" RCP Swr 86.00 LF $63.00 $5,418 15.00% 10.00% 25.00% $1,355 $6,773

40.02.01.2916 Abn TEMPORARY 30" PVC Swr 100.00 LF $63.00 $6,300 15.00% 10.00% 25.00% $1,575 $7,875

40.02.01.2917 Abn TEMPORARY 27" PVC Swr 118.00 LF $63.00 $7,434 15.00% 10.00% 25.00% $1,859 $9,293

40.02.01.2918 Abn TEMPORARY 24" PVC Swr 44.00 LF $63.00 $2,772 15.00% 10.00% 25.00% $693 $3,465

40.02.01.2919 ADJUST MH BARREL SECTION 1.00 EA $1,100.00 $1,100 15.00% 10.00% 25.00% $275 $1,375

40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358

40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358

40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358

40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358

40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358

40.02.01.2920 TEMPORARY SYSTEM BYPASS 1.00 EA $18,686.00 $18,686 15.00% 10.00% 25.00% $4,672 $23,358

40.02.01.2921 RELOCATE Exist 8" LATERAL 33.00 LF $21.00 $693 15.00% 10.00% 25.00% $173 $866

40.02.01.2922 RELOCATE Exist 6" LATERAL 26.00 LF $21.00 $546 15.00% 10.00% 25.00% $137 $683

40.02.01.2922 RELOCATE Exist 6" LATERAL 27.00 LF $21.00 $567 15.00% 10.00% 25.00% $142 $709

40.02.01.2922 RELOCATE Exist 6" LATERAL 26.00 LF $21.00 $546 15.00% 10.00% 25.00% $137 $683

Sum

Average

18,791.00 $5,562,691

15.00% 10.00% 25.00%

$1,390,673 $6,953,364Summary for Group: 40.02.01

Group 40.02.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

DRY UTILITY RELOCATION Contingency

40.02.02 DRY UTILITY RELOCATION 1.00 LS $31,300,000.00 $31,300,000 5.00% 20.00% 25.00% $7,825,000 $39,125,000

40.02.02A TEMPORARY RELOCATION OF PCT F/O 2,850.00 LF $85.00 $242,250 25.00% 10.00% 35.00% $84,788 $327,038

Sum

Average

2,851.00 $31,542,250

15.00% 15.00% 30.00%

$7,909,788 $39,452,038Summary for Group: 40.02.02

Sum

Average

21,642.00 $37,104,941

15.00% 10.03% 25.03%

$9,300,460 $46,405,401Summary for Sub Section: 40.02

Sub Section 40.03 HAZ MAT/CONTAMINATED SOIL REMOVAL/MITIGATION, GROUND WATER TREATMENTS

Group 40.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

HAZARDOUS MATERIAL REMOVAL/MITIGATION Contingency

Monday, January 27, 2014 Page 62 of 140

Page 127: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.03 HAZARDOUS MATERIAL REMOVAL/MITIGATION 1.00 LS $4,400,000.00 $4,400,000 0.00% 30.00% 30.00% $1,320,000 $5,720,000

Sum

Average

1.00 $4,400,000

0.00% 30.00% 30.00%

$1,320,000 $5,720,000Summary for Group: 40.03

Sum

Average

1.00 $4,400,000

0.00% 30.00% 30.00%

$1,320,000 $5,720,000Summary for Sub Section: 40.03

Sub Section 40.04 ENVIRONMENTAL MITIGATION/WETLAND RESTORATION

Group 40.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ENVIRONMENTAL MITIGATION/WETLAND RESTORATION Contingency

40.04.01 ENVIRONMENTAL MITIGATION/WETLAND RESTORATION 1.00 LS $6,500,000.00 $6,500,000 0.00% 30.00% 30.00% $1,950,000 $8,450,000

40.04.02.01 TREE REMOVAL (<6") 188.00 EA $400.00 $75,200 15.00% 10.00% 25.00% $18,800 $94,000

40.04.02.01 TREE REMOVAL (>6") 78.00 EA $600.00 $46,800 15.00% 10.00% 25.00% $11,700 $58,500

40.04.02.01 TREE REMOVAL (>6") 155.00 EA $600.00 $93,000 15.00% 10.00% 25.00% $23,250 $116,250

40.04.02.01 TREE REMOVAL (<6") 71.00 EA $400.00 $28,400 15.00% 10.00% 25.00% $7,100 $35,500

40.04.02.01 TREE REMOVAL (<6") 7.00 EA $400.00 $2,800 15.00% 10.00% 25.00% $700 $3,500

40.04.02.01 TREE REMOVAL (<6") 36.00 EA $400.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000

40.04.02.01 TREE REMOVAL (>6") 21.00 EA $600.00 $12,600 15.00% 10.00% 25.00% $3,150 $15,750

40.04.02.01 TREE REMOVAL (>6") 325.00 EA $600.00 $195,000 15.00% 10.00% 25.00% $48,750 $243,750

40.04.02.02 TREE REPLACEMENT 227.00 EA $2,000.00 $454,000 15.00% 10.00% 25.00% $113,500 $567,500

40.04.02.02 TREE REPLACEMENT 657.00 EA $2,000.00 $1,314,000 15.00% 10.00% 25.00% $328,500 $1,642,500

40.04.02.02 TREE REPLACEMENT 346.00 EA $2,000.00 $692,000 15.00% 10.00% 25.00% $173,000 $865,000

40.04.02.02 TREE REPLACEMENT 230.00 EA $2,000.00 $460,000 15.00% 10.00% 25.00% $115,000 $575,000

Sum

Average

2,342.00 $9,888,200

13.85% 11.54% 25.38%

$2,797,050 $12,685,250Summary for Group: 40.04

Sum

Average

2,342.00 $9,888,200

13.85% 11.54% 25.38%

$2,797,050 $12,685,250Summary for Sub Section: 40.04

Sub Section 40.06 PEDESTRIAN/BIKE ACCESS AND ACCOMODATIONS

Group 40.06.00

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROSE CANYON BIKE PATH (DETOUR) Contingency

40.06.00.190101 ROADWAY EXCAVATION 52.00 CY $28.00 $1,456 15.00% 15.00% 30.00% $437 $1,893

40.06.00.260203 CLASS 2 AGGREGATE BASE 691.00 CY $45.00 $31,095 15.00% 10.00% 25.00% $7,774 $38,869

40.06.00.390132 HOT MIX ASPHALT (TYPE A) 677.00TON $102.00 $69,054 15.00% 15.00% 30.00% $20,716 $89,770

Monday, January 27, 2014 Page 63 of 140

Page 128: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.06.00.566011 ROADSIDE SIGN - ONE POST 2.00 EA $750.00 $1,500 15.00% 15.00% 30.00% $450 $1,950

40.06.00.800360 CHAIN LINK FENCE (CL-6) 9,331.00 LF $19.00 $177,289 15.00% 15.00% 30.00% $53,187 $230,476

Sum

Average

10,753.00 $280,394

15.00% 14.00% 29.00%

$82,563 $362,957Summary for Group: 40.06.00

Group 40.06.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROSE CANYON BIKE PATH (BK1) Contingency

40.06.01.01 ASPHALT PAVEMENT REMOVAL 26,823.00 SF $1.60 $42,917 15.00% 15.00% 30.00% $12,875 $55,792

40.06.01.01 DEMOLISH EXISTING RETAINING WALL 730.00 LF $40.00 $29,200 15.00% 15.00% 30.00% $8,760 $37,960

40.06.01.160101 CLEARING AND GRUBBING 0.51 AC $4,022.00 $2,051 10.00% 15.00% 25.00% $513 $2,564

40.06.01.190101 ROADWAY EXCAVATION 5,310.00 CY $28.00 $148,680 15.00% 15.00% 30.00% $44,604 $193,284

40.06.01.260203 CLASS 2 AGGREGATE BASE 283.00 CY $45.00 $12,735 15.00% 10.00% 25.00% $3,184 $15,919

40.06.01.390132 HOT MIX ASPHALT (TYPE A) 369.00TON $102.00 $37,638 15.00% 15.00% 30.00% $11,291 $48,929

40.06.01.566011 ROADSIDE SIGN - ONE POST 2.00 EA $750.00 $1,500 15.00% 15.00% 30.00% $450 $1,950

Sum

Average

33,517.51 $274,721

14.29% 14.29% 28.57%

$81,677 $356,398Summary for Group: 40.06.01

Group 40.06.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROSE CANYON BIKE PATH (BK2) Contingency

40.06.02.01 ASPHALT PAVEMENT REMOVAL 38,398.00 SF $1.60 $61,437 15.00% 15.00% 30.00% $18,431 $79,868

40.06.02.160101 CLEARING AND GRUBBING 1.32 AC $4,022.00 $5,309 10.00% 15.00% 25.00% $1,327 $6,636

40.06.02.190101 ROADWAY EXCAVATION 975.00 CY $28.00 $27,300 15.00% 15.00% 30.00% $8,190 $35,490

40.06.02.260203 CLASS 2 AGGREGATE BASE 592.00 CY $45.00 $26,640 15.00% 10.00% 25.00% $6,660 $33,300

40.06.02.390132 HOT MIX ASPHALT (TYPE A) 773.00TON $102.00 $78,846 15.00% 15.00% 30.00% $23,654 $102,500

40.06.02.566011 ROADSIDE SIGN - ONE POST 2.00 EA $750.00 $1,500 15.00% 15.00% 30.00% $450 $1,950

Sum

Average

40,741.32 $201,032

14.17% 14.17% 28.33%

$58,712 $259,744Summary for Group: 40.06.02

Group 40.06.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GRAVITY RETAINING WALL Contingency

40.06.03.2 STRUCTURE EXCAVATION 1,318.00 CY $60.00 $79,080 15.00% 15.00% 30.00% $23,724 $102,804

40.06.03.3 STRUCTURAL BACKFILL (GRAVITY WALL) 466.00 CY $52.00 $24,232 15.00% 15.00% 30.00% $7,270 $31,502

40.06.03.510062A STRUCTURAL CONCRETE (GRAVITY RETAINING WALL) 522.00 CY $650.00 $339,300 15.00% 15.00% 30.00% $101,790 $441,090

Sum

Average

2,306.00 $442,612

15.00% 15.00% 30.00%

$132,784 $575,396Summary for Group: 40.06.03

Monday, January 27, 2014 Page 64 of 140

Page 129: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Group 40.06.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PEDESTRIAN BRIDGES Contingency

40.06.04.01 VOIGT PED OC 2,520.00 SF $400.00 $1,008,000 15.00% 10.00% 25.00% $252,000 $1,260,000

40.06.04.02 EXECUTIVE PED OC 1,835.00 SF $400.00 $734,000 15.00% 10.00% 25.00% $183,500 $917,500

40.06.04.03 UTC PED OC 2,360.00 SF $400.00 $944,000 15.00% 10.00% 25.00% $236,000 $1,180,000

Sum

Average

6,715.00 $2,686,000

15.00% 10.00% 25.00%

$671,500 $3,357,500Summary for Group: 40.06.04

Sum

Average

94,032.83 $3,884,759

14.58% 13.75% 28.33%

$1,027,236 $4,911,995Summary for Sub Section: 40.06

Sub Section 40.07 AUTOMOBILE, BUS, VAN ACCESS WAYS INCLUDING ROADS, PARKING LOTS

Group 40.07.00

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.00.00 ALLOWANCE FOR ROADWAY IMPROVEMENTS (CEDAR,SASSAFRAS, 1.00 LS $200,000.00 $200,000 0.00% 30.00% 30.00% $60,000 $260,000

40.07.00.00 ALLOWANCE FOR ROADWAY IMPROVEMENTS (VOIGT DRIVE) 1.00 LS $1,300,000.00 $1,300,000 0.00% 30.00% 30.00% $390,000 $1,690,000

Sum

Average

2.00 $1,500,000

0.00% 30.00% 30.00%

$450,000 $1,950,000Summary for Group: 40.07.00

Group 40.07.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TECOLOTE STATION SITEWORK Contingency

40.07.01.101 CLEARING AND GRUBBING 1.50 AC $4,022.00 $6,033 10.00% 10.00% 20.00% $1,207 $7,240

40.07.01.102 CONCRETE PAVEMENT DEMOLITION 3,126.00 SY $14.00 $43,764 10.00% 10.00% 20.00% $8,753 $52,517

40.07.01.103 CONCRETE PAVEMENT REMOVAL 1,090.00TON $23.00 $25,070 10.00% 10.00% 20.00% $5,014 $30,084

40.07.01.104 ASPHALT PAVEMENT DEMOLITION 5,846.00 SY $14.00 $81,844 10.00% 10.00% 20.00% $16,369 $98,213

40.07.01.105 ASPHALT PAVEMENT REMOVAL 1,907.00TON $34.00 $64,838 10.00% 10.00% 20.00% $12,968 $77,806

40.07.01.106 BUILDING FOOTING REMOVAL 8,250.00 SF $0.40 $3,300 10.00% 10.00% 20.00% $660 $3,960

40.07.01.106 MILL AND OVERLAY (TECOLOTE STATION) 42,400.00 SF $1.90 $80,560 10.00% 10.00% 20.00% $16,112 $96,672

40.07.01.107 BUILDING REMOVAL 8,250.00 SF $2.40 $19,800 10.00% 10.00% 20.00% $3,960 $23,760

40.07.01.201 ROADWAY EXCAVATION 3,295.00 CY $28.00 $92,260 10.00% 10.00% 20.00% $18,452 $110,712

40.07.01.204 ROADWAY EMBANKMENT 7,368.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

40.07.01.302 CURB AND GUTTER 429.00 CY $365.00 $156,585 10.00% 10.00% 20.00% $31,317 $187,902

40.07.01.304 HOT MIX ASPHALT (TYPE A) 3,830.00TON $102.00 $390,660 10.00% 10.00% 20.00% $78,132 $468,792

40.07.01.306 MINOR CONCRETE (ADA RAMPS) 87.00 CY $765.00 $66,555 10.00% 10.00% 20.00% $13,311 $79,866

40.07.01.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 108.00 SF $22.00 $2,376 15.00% 15.00% 30.00% $713 $3,089

Monday, January 27, 2014 Page 65 of 140

Page 130: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.01.309 DECORATIVE CONCRETE PAVEMENT 1,370.00 SF $20.00 $27,400 10.00% 10.00% 20.00% $5,480 $32,880

40.07.01.310 CONCRETE SIDEWALKS 11,306.00 SF $12.00 $135,672 10.00% 10.00% 20.00% $27,134 $162,806

40.07.01.311 CONCRETE STAIRS 25.00 CY $525.00 $13,125 10.00% 10.00% 20.00% $2,625 $15,750

40.07.01.312 CLASS 2 AGGREGATE BASE 2,040.00 CY $45.00 $91,800 15.00% 10.00% 25.00% $22,950 $114,750

40.07.01.313 CLASS 2 AGGREGATE BASE 2,182.00 CY $45.00 $98,190 10.00% 10.00% 20.00% $19,638 $117,828

40.07.01.314 DRIVEWAY 360.00 SF $20.00 $7,200 10.00% 10.00% 20.00% $1,440 $8,640

40.07.01.401 RETAINING WALLS 3,160.00 SF $80.00 $252,800 15.00% 15.00% 30.00% $75,840 $328,640

40.07.01.501 LIGHTING AREA 150,630.00 SF $1.50 $225,945 15.00% 15.00% 30.00% $67,784 $293,729

40.07.01.901 METAL RAILING (PIPE) 1,171.00 LF $125.00 $146,375 15.00% 10.00% 25.00% $36,594 $182,969

40.07.01.902 STRIPING 4,866.00 LF $2.00 $9,732 10.00% 10.00% 20.00% $1,946 $11,678

40.07.01.903 PAVEMENT MARKERS 3,954.00 SF $3.00 $11,862 10.00% 10.00% 20.00% $2,372 $14,234

40.07.01.904 SIGNAGE 4.00 EA $278.00 $1,112 15.00% 10.00% 25.00% $278 $1,390

40.07.01.905 FOUNDATIONS (MONUMENT SIGNS) 12.00 CY $441.00 $5,292 10.00% 10.00% 20.00% $1,058 $6,350

40.07.01.906 FENCING 566.00 LF $117.00 $66,222 10.00% 10.00% 20.00% $13,244 $79,466

40.07.01.907 GATES 1.00 EA $1,850.00 $1,850 10.00% 10.00% 20.00% $370 $2,220

40.07.01.909 LANDSCAPING 32,842.00 SF $4.70 $154,357 15.00% 10.00% 25.00% $38,589 $192,947

40.07.01.911 IRRIGATION 32,842.00 SF $1.40 $45,979 10.00% 10.00% 20.00% $9,196 $55,175

40.07.01.913 BUS SHELTERS 2.00 EA $36,800.00 $73,600 10.00% 10.00% 20.00% $14,720 $88,320

40.07.01.914 WHEEL STOPS 253.00 EA $86.00 $21,758 10.00% 10.00% 20.00% $4,352 $26,110

40.07.01.920 ONSITE VEHICULAR CIRCULATION SIGNAGE 6.00 EA $750.00 $4,500 10.00% 10.00% 20.00% $900 $5,400

Sum

Average

333,579.50 $2,428,416

11.03% 10.44% 21.47%

$553,478 $2,981,894Summary for Group: 40.07.01

Group 40.07.01.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TECOLOTE STATION DRAINAGE IMPROVEMENTS Contingency

40.07.01.03.101 18" RCP STORM DRAIN 102.00 LF $120.00 $12,240 15.00% 10.00% 25.00% $3,060 $15,300

40.07.01.03.101 18" RCP STORM DRAIN 78.00 LF $120.00 $9,360 15.00% 10.00% 25.00% $2,340 $11,700

40.07.01.03.102 24" RCP STORM DRAIN 690.00 LF $170.00 $117,300 15.00% 10.00% 25.00% $29,325 $146,625

40.07.01.03.103 30" RCP STORM DRAIN 243.00 LF $210.00 $51,030 15.00% 10.00% 25.00% $12,758 $63,788

40.07.01.03.104 36" RCP STORM DRAIN 248.00 LF $230.00 $57,040 15.00% 10.00% 25.00% $14,260 $71,300

40.07.01.03.105 42" RCP STORM DRAIN 239.00 LF $260.00 $62,140 15.00% 10.00% 25.00% $15,535 $77,675

Monday, January 27, 2014 Page 66 of 140

Page 131: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.01.03.112 4" NON-PERFORATED PVC 220.00 LF $20.00 $4,400 15.00% 10.00% 25.00% $1,100 $5,500

40.07.01.03.121 3" PERFORATED PVC 240.00 LF $14.00 $3,360 15.00% 10.00% 25.00% $840 $4,200

40.07.01.03.122 4" PERFORATED PVC 1,078.00 LF $20.00 $21,560 15.00% 10.00% 25.00% $5,390 $26,950

40.07.01.03.201 WASH WATER CLEANOUT 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625

40.07.01.03.201 TYPE A-8 SD CLEANOUT, SDRSD D-9 2.00 EA $6,000.00 $12,000 10.00% 10.00% 20.00% $2,400 $14,400

40.07.01.03.201 TYPE A-5 SD CLEANOUT, SDRSD D-9 3.00 EA $4,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

40.07.01.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

40.07.01.03.204 10' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $6,900.00 $6,900 15.00% 10.00% 25.00% $1,725 $8,625

40.07.01.03.204 21' TYPE B-1 CURB INLET, SDRSD SDD-116 3.00 EA $8,100.00 $24,300 15.00% 10.00% 25.00% $6,075 $30,375

40.07.01.03.204 15' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500

40.07.01.03.207 TYPE I CATCH BASIN, SDRSD D-29 6.00 EA $6,450.00 $38,700 10.00% 10.00% 20.00% $7,740 $46,440

40.07.01.03.501 CONCRETE LUG, SDRSD SDD-113 1.00 EA $1,100.00 $1,100 15.00% 10.00% 25.00% $275 $1,375

40.07.01.03.503 PIPE TO CHANNEL CONNECTION 1.00 EA $6,230.00 $6,230 15.00% 10.00% 25.00% $1,558 $7,788

40.07.01.03.506 3" UNDERDRAIN CLEANOUT 2.00 EA $46.00 $92 15.00% 10.00% 25.00% $23 $115

40.07.01.03.508 4" UNDERDRAIN CLEANOUT 23.00 EA $60.00 $1,380 15.00% 10.00% 25.00% $345 $1,725

40.07.01.03.510 TRENCH DRAIN 751.00 LF $35.00 $26,285 15.00% 10.00% 25.00% $6,571 $32,856

40.07.01.03.515 6" TRENCH DRAIN CLEANOUT 1.00 EA $80.00 $80 15.00% 10.00% 25.00% $20 $100

40.07.01.03.610 BIORETENTION PLANTER SOIL 889.00 CY $35.00 $31,115 15.00% 10.00% 25.00% $7,779 $38,894

40.07.01.03.611 BIORETENTION 3/4" CRUSHED ROCK 148.00 CY $50.00 $7,400 15.00% 10.00% 25.00% $1,850 $9,250

40.07.01.03.612 BIORETENTION 1-1/2" CRUSHED ROCK 296.00 CY $30.00 $8,880 15.00% 10.00% 25.00% $2,220 $11,100

40.07.01.03.613 BIORETENTION LINER 16,000.00 SF $0.80 $12,800 15.00% 10.00% 25.00% $3,200 $16,000

40.07.01.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 6.00 EA $675.00 $4,050 15.00% 10.00% 25.00% $1,013 $5,063

Sum

Average

21,275.00 $554,342

14.29% 10.00% 24.29%

$134,926 $689,268Summary for Group: 40.07.01.03

Group 40.07.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CLAIREMONT STATION SITEWORK Contingency

40.07.02.101 CLEARING AND GRUBBING 0.55 AC $4,022.00 $2,212 10.00% 10.00% 20.00% $442 $2,655

40.07.02.102 CONCRETE PAVEMENT DEMOLITION 1,429.00 SY $14.00 $20,006 10.00% 10.00% 20.00% $4,001 $24,007

40.07.02.103 CONCRETE PAVEMENT REMOVAL 498.00TON $23.00 $11,454 10.00% 10.00% 20.00% $2,291 $13,745

40.07.02.104 ASPHALT PAVEMENT DEMOLITION 11,851.00 SY $14.00 $165,914 10.00% 10.00% 20.00% $33,183 $199,097

Monday, January 27, 2014 Page 67 of 140

Page 132: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.02.105 ASPHALT PAVEMENT REMOVAL 3,866.00TON $34.00 $131,444 10.00% 10.00% 20.00% $26,289 $157,733

40.07.02.106 BUILDING FOOTING REMOVAL 37,485.00 SF $0.40 $14,994 10.00% 10.00% 20.00% $2,999 $17,993

40.07.02.201 ROADWAY EXCAVATION 2,248.00 CY $28.00 $62,944 10.00% 10.00% 20.00% $12,589 $75,533

40.07.02.204 ROADWAY EMBANKMENT 6,918.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

40.07.02.302 CURB AND GUTTER 272.00 CY $365.00 $99,280 10.00% 10.00% 20.00% $19,856 $119,136

40.07.02.304 HOT MIX ASPHALT (TYPE A) 2,190.00TON $102.00 $223,380 10.00% 10.00% 20.00% $44,676 $268,056

40.07.02.305 PORTLAND CEMENT CONCRETE PAVEMENT 310.00 CY $603.00 $186,930 10.00% 10.00% 20.00% $37,386 $224,316

40.07.02.306 MINOR CONCRETE (ADA RAMPS) 22.00 CY $765.00 $16,830 10.00% 10.00% 20.00% $3,366 $20,196

40.07.02.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 144.00 SF $22.00 $3,168 15.00% 15.00% 30.00% $950 $4,118

40.07.02.309 DECORATIVE CONCRETE PAVEMENT 13,200.00 SF $20.00 $264,000 10.00% 10.00% 20.00% $52,800 $316,800

40.07.02.310 CONCRETE SIDEWALKS 28,110.00 SF $12.00 $337,320 10.00% 10.00% 20.00% $67,464 $404,784

40.07.02.311 CONCRETE STAIRS 30.00 CY $525.00 $15,750 10.00% 10.00% 20.00% $3,150 $18,900

40.07.02.312 CLASS 2 AGGREGATE BASE 2,200.00 CY $45.00 $99,000 10.00% 10.00% 20.00% $19,800 $118,800

40.07.02.313 CLASS 2 AGGREGATE BASE 210.00 CY $45.00 $9,450 10.00% 10.00% 20.00% $1,890 $11,340

40.07.02.401 RETAINING WALLS 2,900.00 SF $80.00 $232,000 15.00% 15.00% 30.00% $69,600 $301,600

40.07.02.501 LIGHTING AREA 145,080.00 SF $1.50 $217,620 15.00% 15.00% 30.00% $65,286 $282,906

40.07.02.901 METAL RAILING (PIPE) 655.00 LF $125.00 $81,875 15.00% 10.00% 25.00% $20,469 $102,344

40.07.02.902 STRIPING 2,200.00 LF $2.00 $4,400 10.00% 10.00% 20.00% $880 $5,280

40.07.02.903 PAVEMENT MARKERS 4,212.00 SF $3.00 $12,636 10.00% 10.00% 20.00% $2,527 $15,163

40.07.02.904 SIGNAGE 6.00 EA $278.00 $1,668 15.00% 10.00% 25.00% $417 $2,085

40.07.02.905 FOUNDATIONS (MONUMENT SIGNS) 18.00 CY $441.00 $7,938 10.00% 10.00% 20.00% $1,588 $9,526

40.07.02.906 FENCING 350.00 LF $117.00 $40,950 10.00% 10.00% 20.00% $8,190 $49,140

40.07.02.907 GATES 1.00 EA $1,850.00 $1,850 10.00% 10.00% 20.00% $370 $2,220

40.07.02.909 LANDSCAPING 34,490.00 SF $4.70 $162,103 15.00% 10.00% 25.00% $40,526 $202,629

40.07.02.911 IRRIGATION 34,490.00 SF $1.40 $48,286 10.00% 10.00% 20.00% $9,657 $57,943

40.07.02.913 BUS SHELTERS 4.00 EA $36,800.00 $147,200 10.00% 10.00% 20.00% $29,440 $176,640

40.07.02.914 WHEEL STOPS 156.00 EA $86.00 $13,416 10.00% 10.00% 20.00% $2,683 $16,099

40.07.02.920 ONSITE VEHICULAR CIRCULATION SIGNAGE 15.00 EA $750.00 $11,250 10.00% 10.00% 20.00% $2,250 $13,500

Monday, January 27, 2014 Page 68 of 140

Page 133: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

335,560.55 $2,647,268

10.94% 10.47% 21.41%

$587,015 $3,234,283Summary for Group: 40.07.02

Group 40.07.02.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CLAIREMONT STATION DRAINAGE IMPROVEMENTS Contingency

40.07.02.03.101 18" RCP STORM DRAIN 210.00 LF $120.00 $25,200 15.00% 10.00% 25.00% $6,300 $31,500

40.07.02.03.102 24" RCP STORM DRAIN 39.00 LF $170.00 $6,630 15.00% 10.00% 25.00% $1,658 $8,288

40.07.02.03.112 4" NON-PERFORATED PVC 680.00 LF $20.00 $13,600 15.00% 10.00% 25.00% $3,400 $17,000

40.07.02.03.121 3" PERFORATED PVC 23.00 LF $14.00 $322 15.00% 10.00% 25.00% $81 $403

40.07.02.03.122 4" PERFORATED PVC 574.00 LF $20.00 $11,480 15.00% 10.00% 25.00% $2,870 $14,350

40.07.02.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

40.07.02.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500

40.07.02.03.204 10' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $6,900.00 $6,900 15.00% 10.00% 25.00% $1,725 $8,625

40.07.02.03.207 TYPE I CATCH BASIN, SDRSD D-29 2.00 EA $6,450.00 $12,900 10.00% 10.00% 20.00% $2,580 $15,480

40.07.02.03.501 CONCRETE LUG, SDRSD SDD-113 1.00 EA $1,100.00 $1,100 15.00% 10.00% 25.00% $275 $1,375

40.07.02.03.508 4" UNDERDRAIN CLEANOUT 45.00 EA $60.00 $2,700 15.00% 10.00% 25.00% $675 $3,375

40.07.02.03.510 TRENCH DRAIN 16.00 LF $35.00 $560 15.00% 10.00% 25.00% $140 $700

40.07.02.03.610 BIORETENTION PLANTER SOIL 342.00 CY $35.00 $11,970 15.00% 10.00% 25.00% $2,993 $14,963

40.07.02.03.611 BIORETENTION 3/4" CRUSHED ROCK 57.00 CY $50.00 $2,850 15.00% 10.00% 25.00% $713 $3,563

40.07.02.03.612 BIORETENTION 1-1/2" CRUSHED ROCK 114.00 CY $30.00 $3,420 15.00% 10.00% 25.00% $855 $4,275

40.07.02.03.613 BIORETENTION LINER 6,160.00 SF $0.80 $4,928 15.00% 10.00% 25.00% $1,232 $6,160

40.07.02.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 4.00 EA $675.00 $2,700 15.00% 10.00% 25.00% $675 $3,375

40.07.02.03.701 ABANDON DRAINAGE STRUCTURE 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546

40.07.02.03.702 REMOVE EXIST DRAINAGE STRUCTURE 4.00 EA $1,829.00 $7,316 15.00% 10.00% 25.00% $1,829 $9,145

Sum

Average

8,276.00 $130,013

14.47% 10.00% 24.47%

$31,408 $161,421Summary for Group: 40.07.02.03

Group 40.07.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BALBOA STATION SITEWORK Contingency

40.07.03.101 CLEARING AND GRUBBING 3.95 AC $4,022.00 $15,887 10.00% 10.00% 20.00% $3,177 $19,064

40.07.03.201 ROADWAY EXCAVATION 3,324.00 CY $28.00 $93,072 10.00% 10.00% 20.00% $18,614 $111,686

40.07.03.204 ROADWAY EMBANKMENT 32,285.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

40.07.03.301 CURB 2,474.00 LF $20.00 $49,480 10.00% 10.00% 20.00% $9,896 $59,376

Monday, January 27, 2014 Page 69 of 140

Page 134: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.03.302 CURB AND GUTTER 3,387.00 LF $30.00 $101,610 10.00% 10.00% 20.00% $20,322 $121,932

40.07.03.303 CROSS GUTTERS 40.00 LF $135.00 $5,400 10.00% 10.00% 20.00% $1,080 $6,480

40.07.03.304 HOT MIX ASPHALT (TYPE A) 3,218.00TON $102.00 $328,236 10.00% 10.00% 20.00% $65,647 $393,883

40.07.03.305 PORTLAND CEMENT CONCRETE PAVEMENT 722.00 CY $603.00 $435,366 10.00% 10.00% 20.00% $87,073 $522,439

40.07.03.306 MINOR CONCRETE (ADA RAMPS) 52.00 CY $765.00 $39,780 10.00% 10.00% 20.00% $7,956 $47,736

40.07.03.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 1,685.00 SF $22.00 $37,070 10.00% 10.00% 20.00% $7,414 $44,484

40.07.03.308 METAL BEAM GUARD RAILING (WOOD POST) 1,167.00 LF $32.00 $37,344 10.00% 10.00% 20.00% $7,469 $44,813

40.07.03.310 CONCRETE SIDEWALKS 25,082.00 SF $12.00 $300,984 10.00% 10.00% 20.00% $60,197 $361,181

40.07.03.311 CONCRETE STAIRS 77.00 CY $525.00 $40,425 10.00% 10.00% 20.00% $8,085 $48,510

40.07.03.312 CLASS 2 AGGREGATE BASE 2,978.00 CY $45.00 $134,010 10.00% 10.00% 20.00% $26,802 $160,812

40.07.03.313 CLASS 2 AGGREGATE BASE 2,692.00 CY $45.00 $121,140 10.00% 10.00% 20.00% $24,228 $145,368

40.07.03.315 FILTER FABRIC 4,850.00 SY $0.80 $3,880 10.00% 10.00% 20.00% $776 $4,656

40.07.03.402 STRUCTURE EXCAVATION (RETAINING WALL) 1,432.00 CY $60.00 $85,920 10.00% 10.00% 20.00% $17,184 $103,104

40.07.03.403 STRUCTURAL BACKFILL 3,238.00 CY $52.00 $168,376 10.00% 10.00% 20.00% $33,675 $202,051

40.07.03.405 STRUCTURAL CONCRETE (RETAINING WALL) 912.00 CY $470.00 $428,640 10.00% 10.00% 20.00% $85,728 $514,368

40.07.03.406 BAR REINFORCING STEEL (RETAINING WALL) 104,040.00 LB $1.00 $104,040 10.00% 10.00% 20.00% $20,808 $124,848

40.07.03.407 ARCHITECTURAL TREATMENT (RETAINING WALL) 10,989.00 SF $14.00 $153,846 10.00% 10.00% 20.00% $30,769 $184,615

40.07.03.408 CABLE RAILING 718.00 LF $25.00 $17,950 10.00% 10.00% 20.00% $3,590 $21,540

40.07.03.901 METAL RAILING (PIPE) 1,327.00 LF $125.00 $165,875 15.00% 10.00% 25.00% $41,469 $207,344

40.07.03.902 STRIPING 3,456.00 LF $2.00 $6,912 10.00% 10.00% 20.00% $1,382 $8,294

40.07.03.904 SIGNAGE 2.00 EA $278.00 $556 15.00% 10.00% 25.00% $139 $695

40.07.03.905 FOUNDATIONS (MONUMENT SIGNS) 10.00 CY $441.00 $4,410 10.00% 10.00% 20.00% $882 $5,292

40.07.03.906 FENCING 1,060.00 LF $117.00 $124,020 10.00% 10.00% 20.00% $24,804 $148,824

40.07.03.909 LANDSCAPING 43,507.00 SF $4.70 $204,483 15.00% 10.00% 25.00% $51,121 $255,604

40.07.03.911 IRRIGATION 43,507.00 SF $1.40 $60,910 10.00% 10.00% 20.00% $12,182 $73,092

40.07.03.913 BUS SHELTERS 6.00 EA $36,800.00 $220,800 10.00% 10.00% 20.00% $44,160 $264,960

Sum

Average

298,240.95 $3,490,422

10.50% 10.00% 20.50%

$716,630 $4,207,052Summary for Group: 40.07.03

Group 40.07.03.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BALBOA STATION DRAINAGE IMPROVEMENTS Contingency

Monday, January 27, 2014 Page 70 of 140

Page 135: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.03.03.101 18" RCP STORM DRAIN 529.00 LF $120.00 $63,480 15.00% 10.00% 25.00% $15,870 $79,350

40.07.03.03.102 24" RCP STORM DRAIN 42.00 LF $170.00 $7,140 15.00% 10.00% 25.00% $1,785 $8,925

40.07.03.03.104 36" RCP STORM DRAIN 52.00 LF $230.00 $11,960 15.00% 10.00% 25.00% $2,990 $14,950

40.07.03.03.110 3" NON-PERFORATED PVC 56.00 LF $14.00 $784 15.00% 10.00% 25.00% $196 $980

40.07.03.03.112 4" NON-PERFORATED PVC 663.00 LF $20.00 $13,260 15.00% 10.00% 25.00% $3,315 $16,575

40.07.03.03.113 6" NON-PERFORATED PVC 43.00 LF $65.00 $2,795 15.00% 10.00% 25.00% $699 $3,494

40.07.03.03.122 4" PERFORATED PVC 776.00 LF $20.00 $15,520 15.00% 10.00% 25.00% $3,880 $19,400

40.07.03.03.201 WASH WATER CLEANOUT 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625

40.07.03.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 3.00 EA $4,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

40.07.03.03.203 15' TYPE A CURB INLET, SDRSD SDD-115 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500

40.07.03.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 3.00 EA $5,200.00 $15,600 15.00% 10.00% 25.00% $3,900 $19,500

40.07.03.03.204 10' TYPE B-1 CURB INLET, SDRSD SDD-116 2.00 EA $6,900.00 $13,800 15.00% 10.00% 25.00% $3,450 $17,250

40.07.03.03.207 TYPE I CATCH BASIN, SDRSD D-29 3.00 EA $6,450.00 $19,350 10.00% 10.00% 20.00% $3,870 $23,220

40.07.03.03.507 3" GRATE INLET 2.00 EA $20.00 $40 15.00% 10.00% 25.00% $10 $50

40.07.03.03.508 4" UNDERDRAIN CLEANOUT 31.00 EA $60.00 $1,860 15.00% 10.00% 25.00% $465 $2,325

40.07.03.03.509 12" STEEL CASING 43.00 LF $150.00 $6,450 15.00% 10.00% 25.00% $1,613 $8,063

40.07.03.03.510 TRENCH DRAIN 701.00 LF $35.00 $24,535 15.00% 10.00% 25.00% $6,134 $30,669

40.07.03.03.515 6" TRENCH DRAIN CLEANOUT 1.00 EA $80.00 $80 15.00% 10.00% 25.00% $20 $100

40.07.03.03.601 HYDROMODIFICATION UNDERGROUND STORAGE 15,300.00 CF $2.45 $37,485 15.00% 10.00% 25.00% $9,371 $46,856

40.07.03.03.603 HYDROMODIFICATION OUTLET STRUCTURE - UNDERGROUND STO 1.00 EA $7,000.00 $7,000 15.00% 10.00% 25.00% $1,750 $8,750

40.07.03.03.610 BIORETENTION PLANTER SOIL 1,114.00 CY $35.00 $38,990 15.00% 10.00% 25.00% $9,748 $48,738

40.07.03.03.611 BIORETENTION 3/4" CRUSHED ROCK 186.00 CY $50.00 $9,300 15.00% 10.00% 25.00% $2,325 $11,625

40.07.03.03.612 BIORETENTION 1-1/2" CRUSHED ROCK 371.00 CY $30.00 $11,130 15.00% 10.00% 25.00% $2,783 $13,913

40.07.03.03.613 BIORETENTION LINER 20,050.00 SF $0.80 $16,040 15.00% 10.00% 25.00% $4,010 $20,050

Sum

Average

39,974.00 $342,199

14.58% 10.00% 24.58%

$83,907 $426,106Summary for Group: 40.07.03.03

Group 40.07.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NOBEL STATION SITEWORK Contingency

40.07.04.101 CLEARING AND GRUBBING 0.13 AC $4,022.00 $523 10.00% 10.00% 20.00% $105 $627

40.07.04.104 ASPHALT PAVEMENT DEMOLITION 8,660.00 SY $14.00 $121,240 10.00% 10.00% 20.00% $24,248 $145,488

Monday, January 27, 2014 Page 71 of 140

Page 136: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.04.105 ASPHALT PAVEMENT REMOVAL 994.00TON $34.00 $33,796 10.00% 10.00% 20.00% $6,759 $40,555

40.07.04.302 CURB AND GUTTER 392.00 CY $365.00 $143,080 10.00% 10.00% 20.00% $28,616 $171,696

40.07.04.306 MINOR CONCRETE (ADA RAMPS) 18.00 CY $765.00 $13,770 10.00% 10.00% 20.00% $2,754 $16,524

40.07.04.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 180.00 SF $22.00 $3,960 15.00% 15.00% 30.00% $1,188 $5,148

40.07.04.310 CONCRETE SIDEWALKS 17,130.00 SF $12.00 $205,560 15.00% 15.00% 30.00% $61,668 $267,228

40.07.04.312 CLASS 2 AGGREGATE BASE 320.00 CY $45.00 $14,400 10.00% 10.00% 20.00% $2,880 $17,280

40.07.04.501 LIGHTING AREA 196,890.00 SF $1.50 $295,335 15.00% 15.00% 30.00% $88,601 $383,936

40.07.04.902 STRIPING 11,130.00 LF $2.00 $22,260 10.00% 10.00% 20.00% $4,452 $26,712

40.07.04.904 SIGNAGE 2.00 EA $278.00 $556 15.00% 10.00% 25.00% $139 $695

40.07.04.905 FOUNDATIONS (MONUMENT SIGNS) 6.00 CY $441.00 $2,646 10.00% 10.00% 20.00% $529 $3,175

40.07.04.909 LANDSCAPING 22,990.00 SF $4.70 $108,053 15.00% 10.00% 25.00% $27,013 $135,066

40.07.04.911 IRRIGATION 22,990.00 SF $1.40 $32,186 10.00% 10.00% 20.00% $6,437 $38,623

40.07.04.920 ONSITE VEHICULAR CIRCULATION SIGNAGE 8.00 EA $750.00 $6,000 10.00% 10.00% 20.00% $1,200 $7,200

Sum

Average

281,710.13 $1,003,365

11.67% 11.00% 22.67%

$256,589 $1,259,954Summary for Group: 40.07.04

Group 40.07.04.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NOBEL STATION DRAINAGE IMPROVEMENTS Contingency

40.07.04.03.101 18" RCP STORM DRAIN 73.00 LF $120.00 $8,760 15.00% 10.00% 25.00% $2,190 $10,950

40.07.04.03.102 24" RCP STORM DRAIN 350.00 LF $170.00 $59,500 15.00% 10.00% 25.00% $14,875 $74,375

40.07.04.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 6.00 EA $4,500.00 $27,000 10.00% 10.00% 20.00% $5,400 $32,400

40.07.04.03.601 HYDROMODIFICATION UNDERGROUND STORAGE 22,580.00 CF $2.45 $55,321 15.00% 10.00% 25.00% $13,830 $69,151

40.07.04.03.603 HYDROMODIFICATION OUTLET STRUCTURE - UNDERGROUND STO 2.00 EA $7,000.00 $14,000 15.00% 10.00% 25.00% $3,500 $17,500

40.07.04.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 2.00 EA $675.00 $1,350 15.00% 10.00% 25.00% $338 $1,688

Sum

Average

23,013.00 $165,931

14.17% 10.00% 24.17%

$40,133 $206,064Summary for Group: 40.07.04.03

Group 40.07.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

VA MEDICAL CENTER STATION SITEWORK Contingency

40.07.05.101 CLEARING AND GRUBBING 0.11 AC $4,022.00 $442 10.00% 10.00% 20.00% $88 $531

40.07.05.102 CONCRETE PAVEMENT DEMOLITION 440.00 SY $14.00 $6,160 10.00% 10.00% 20.00% $1,232 $7,392

40.07.05.103 CONCRETE PAVEMENT REMOVAL 153.00TON $23.00 $3,519 10.00% 10.00% 20.00% $704 $4,223

40.07.05.106 MILL AND OVERLAY (VA STATION) 127,374.00 SF $1.90 $242,011 10.00% 10.00% 20.00% $48,402 $290,413

Monday, January 27, 2014 Page 72 of 140

Page 137: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.05.108 DEMOLISH EXIST FENCE 88.00 LF $2.20 $194 15.00% 15.00% 30.00% $58 $252

40.07.05.201 ROADWAY EXCAVATION 674.00 CY $28.00 $18,872 10.00% 10.00% 20.00% $3,774 $22,646

40.07.05.304 HOT MIX ASPHALT (TYPE A) 29.18TON $102.00 $2,976 10.00% 10.00% 20.00% $595 $3,572

40.07.05.306 MINOR CONCRETE (ADA RAMPS) 3.00 CY $765.00 $2,295 10.00% 10.00% 20.00% $459 $2,754

40.07.05.307 SIDEWALK RAMPS WITH TACTILE WARNING STRIP 24.00 SF $22.00 $528 15.00% 15.00% 30.00% $158 $686

40.07.05.310 CONCRETE SIDEWALKS 3,955.00 SF $12.00 $47,460 15.00% 15.00% 30.00% $14,238 $61,698

40.07.05.316 CLASS 2 AGGREGATE BASE 15.00 CY $45.00 $675 10.00% 10.00% 20.00% $135 $810

40.07.05.317 AGGREGATE SUBBASE 15.00 CY $35.00 $525 10.00% 10.00% 20.00% $105 $630

40.07.05.318 CLASS 2 AGGREGATE BASE 49.00 CY $45.00 $2,205 10.00% 10.00% 20.00% $441 $2,646

40.07.05.401 RETAINING WALLS 320.00 SF $80.00 $25,600 15.00% 15.00% 30.00% $7,680 $33,280

40.07.05.901 METAL RAILING (PIPE) 320.00 LF $125.00 $40,000 15.00% 10.00% 25.00% $10,000 $50,000

40.07.05.902 STRIPING 150.00 LF $2.00 $300 10.00% 10.00% 20.00% $60 $360

Sum

Average

133,609.29 $393,762

11.56% 11.25% 22.81%

$88,131 $481,893Summary for Group: 40.07.05

Group 40.07.05.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

VA MEDICAL CENTER STATION DRAINAGE IMPROVEMENTS Contingency

40.07.05.03.101 18" RCP STORM DRAIN 125.00 LF $120.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

40.07.05.03.113 6" NON-PERFORATED PVC 26.00 LF $65.00 $1,690 15.00% 10.00% 25.00% $423 $2,113

40.07.05.03.201 WASH WATER CLEANOUT 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625

40.07.05.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500

40.07.05.03.207 TYPE I CATCH BASIN, SDRSD D-29 1.00 EA $6,450.00 $6,450 10.00% 10.00% 20.00% $1,290 $7,740

40.07.05.03.210 WING TYPE HEADWALL, SDRSD D-34 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

40.07.05.03.212 OCP INLET, CT STD 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625

40.07.05.03.213 JUNCTION STRUCTION (CT STD) 1.00 EA $15,000.00 $15,000 15.00% 10.00% 25.00% $3,750 $18,750

40.07.05.03.510 TRENCH DRAIN 703.00 LF $35.00 $24,605 15.00% 10.00% 25.00% $6,151 $30,756

40.07.05.03.515 6" TRENCH DRAIN CLEANOUT 1.00 EA $80.00 $80 15.00% 10.00% 25.00% $20 $100

40.07.05.03.610 BIORETENTION PLANTER SOIL 159.00 CY $35.00 $5,565 15.00% 10.00% 25.00% $1,391 $6,956

40.07.05.03.611 BIORETENTION 3/4" CRUSHED ROCK 26.00 CY $50.00 $1,300 15.00% 10.00% 25.00% $325 $1,625

40.07.05.03.612 BIORETENTION 1-1/2" CRUSHED ROCK 53.00 CY $30.00 $1,590 15.00% 10.00% 25.00% $398 $1,988

40.07.05.03.613 BIORETENTION LINER 2,859.00 SF $0.80 $2,287 15.00% 10.00% 25.00% $572 $2,859

Monday, January 27, 2014 Page 73 of 140

Page 138: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

3,959.00 $96,767

14.29% 10.00% 24.29%

$23,419 $120,187Summary for Group: 40.07.05.03

Group 40.07.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UCSD WEST STATION SITEWORK Contingency

40.07.06.101 CLEARING AND GRUBBING 0.77 AC $4,022.00 $3,097 10.00% 10.00% 20.00% $619 $3,716

40.07.06.201 ROADWAY EXCAVATION 3.00 CY $28.00 $84 10.00% 10.00% 20.00% $17 $101

40.07.06.204 ROADWAY EMBANKMENT 10,562.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

40.07.06.305 PORTLAND CEMENT CONCRETE PAVEMENT 196.00 CY $603.00 $118,188 10.00% 10.00% 20.00% $23,638 $141,826

40.07.06.312 CLASS 2 AGGREGATE BASE 294.00 CY $45.00 $13,230 10.00% 10.00% 20.00% $2,646 $15,876

40.07.06.403 STRUCTURAL BACKFILL 1,700.00 CY $52.00 $88,400 10.00% 10.00% 20.00% $17,680 $106,080

40.07.06.405 STRUCTURAL CONCRETE (RETAINING WALL) 877.00 CY $470.00 $412,190 10.00% 10.00% 20.00% $82,438 $494,628

40.07.06.406 BAR REINFORCING STEEL (RETAINING WALL) 135,650.00 LB $1.00 $135,650 10.00% 10.00% 20.00% $27,130 $162,780

40.07.06.407 ARCHITECTURAL TREATMENT 2,688.00 SF $14.00 $37,632 10.00% 10.00% 20.00% $7,526 $45,158

40.07.06.901 METAL RAILING (PIPE) 487.00 LF $125.00 $60,875 15.00% 10.00% 25.00% $15,219 $76,094

Sum

Average

152,457.77 $869,346

10.50% 10.00% 20.50%

$176,913 $1,046,259Summary for Group: 40.07.06

Group 40.07.06.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UCSD WEST STATION DRAINAGE IMPROVEMENTS Contingency

40.07.06.03.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD WEST ST 5,096.00 CF $2.45 $12,485 15.00% 15.00% 30.00% $3,746 $16,231

40.07.06.03.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD WEST STATI 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

Sum

Average

5,097.00 $19,485

15.00% 15.00% 30.00%

$5,846 $25,331Summary for Group: 40.07.06.03

Group 40.07.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UCSD EAST STATION SITEWORK Contingency

40.07.07.101 CLEARING AND GRUBBING 0.37 AC $4,022.00 $1,488 10.00% 10.00% 20.00% $298 $1,786

40.07.07.106 MILL AND OVERLAY (UCSD EAST STATION) 43,518.00 SF $1.90 $82,684 10.00% 10.00% 20.00% $16,537 $99,221

40.07.07.201 ROADWAY EXCAVATION 194.00 CY $28.00 $5,432 10.00% 10.00% 20.00% $1,086 $6,518

40.07.07.202 HAUL AND DISPOSE 50.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

40.07.07.302 CURB AND GUTTER 850.00 LF $30.00 $25,500 10.00% 10.00% 20.00% $5,100 $30,600

40.07.07.304 HOT MIX ASPHALT (TYPE A) 254.00TON $102.00 $25,908 10.00% 10.00% 20.00% $5,182 $31,090

40.07.07.310 CONCRETE SIDEWALKS 600.00 SF $12.00 $7,200 10.00% 10.00% 20.00% $1,440 $8,640

40.07.07.312 CLASS 2 AGGREGATE BASE 200.00 CY $45.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

Monday, January 27, 2014 Page 74 of 140

Page 139: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.07.902 STRIPING 3,400.00 LF $2.00 $6,800 10.00% 10.00% 20.00% $1,360 $8,160

Sum

Average

49,066.37 $164,012

10.00% 10.00% 20.00%

$32,802 $196,815Summary for Group: 40.07.07

Group 40.07.07.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UCSD EAST STATION DRAINAGE IMPROVEMENTS Contingency

40.07.07.03.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD EAST STA 1,315.60 CF $2.45 $3,223 15.00% 15.00% 30.00% $967 $4,190

40.07.07.03.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD EAST STATI 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

Sum

Average

1,316.60 $10,223

15.00% 15.00% 30.00%

$3,067 $13,290Summary for Group: 40.07.07.03

Group 40.07.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

EXECUTIVE STATION SITEWORK Contingency

40.07.08.101 CLEARING AND GRUBBING 0.01 AC $4,022.00 $40 10.00% 10.00% 20.00% $8 $48

40.07.08.304 HOT MIX ASPHALT (TYPE A) 22.00TON $102.00 $2,244 10.00% 10.00% 20.00% $449 $2,693

40.07.08.312 CLASS 2 AGGREGATE BASE 13.00 CY $45.00 $585 10.00% 10.00% 20.00% $117 $702

40.07.08.313 AGGREGATE SUBBASE 13.00 CY $35.00 $455 10.00% 10.00% 20.00% $91 $546

40.07.08.909 LANDSCAPING 3,500.00 SF $4.70 $16,450 15.00% 10.00% 25.00% $4,113 $20,563

40.07.08.911 IRRIGATION 3,500.00 SF $1.40 $4,900 10.00% 10.00% 20.00% $980 $5,880

Sum

Average

7,048.01 $24,674

10.83% 10.00% 20.83%

$5,757 $30,432Summary for Group: 40.07.08

Group 40.07.09

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UTC STATION SITEWORK Contingency

40.07.09.101 CLEARING AND GRUBBING 0.01 AC $4,022.00 $40 10.00% 10.00% 20.00% $8 $48

40.07.09.304 HOT MIX ASPHALT (TYPE A) 22.00TON $102.00 $2,244 10.00% 10.00% 20.00% $449 $2,693

40.07.09.312 CLASS 2 AGGREGATE BASE 13.00 CY $45.00 $585 10.00% 10.00% 20.00% $117 $702

40.07.09.313 AGGREGATE SUBBASE 13.00 CY $35.00 $455 10.00% 10.00% 20.00% $91 $546

40.07.09.909 LANDSCAPING 3,500.00 SF $4.70 $16,450 15.00% 15.00% 30.00% $4,935 $21,385

40.07.09.911 IRRIGATION 3,500.00 SF $1.40 $4,900 15.00% 15.00% 30.00% $1,470 $6,370

Sum

Average

7,048.01 $24,674

11.67% 11.67% 23.33%

$7,070 $31,744Summary for Group: 40.07.09

Group 40.07.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MORENA/CLAIREMONT STREET IMPROVEMENTS Contingency

40.07.10.106 MILL AND OVERLAY (MORENA/CLAIREMONT) 84,699.00 SF $1.90 $160,928 10.00% 10.00% 20.00% $32,186 $193,114

Monday, January 27, 2014 Page 75 of 140

Page 140: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.10.141101 REMOVE YELLOW PAINTED TRAFFIC STRIPE (HAZARDOUS WASTE) 1,500.00 LF $1.00 $1,500 15.00% 10.00% 25.00% $375 $1,875

40.07.10.150608 REMOVE CHAIN LINK FENCE 233.00 LF $2.75 $641 10.00% 10.00% 20.00% $128 $769

40.07.10.150662 REMOVE METAL BEAM GUARD RAILING 213.00 LF $13.00 $2,769 10.00% 10.00% 20.00% $554 $3,323

40.07.10.150711 REMOVE PAINTED TRAFFIC STRIPE 4,930.00 LF $1.00 $4,930 15.00% 10.00% 25.00% $1,233 $6,163

40.07.10.150715 REMOVE THERMOPLASTIC PAVEMENT MARKING 561.00 SF $1.10 $617 15.00% 10.00% 25.00% $154 $771

40.07.10.150722 REMOVE PAVEMENT MARKER 114.00 EA $1.10 $125 15.00% 10.00% 25.00% $31 $157

40.07.10.150838 REMOVE RETAINING WALL (PORTION) (LF) 135.00 LF $54.00 $7,290 10.00% 10.00% 20.00% $1,458 $8,748

40.07.10.153139 REMOVE CONCRETE (SIDEWALK) 1,039.00 LF $12.00 $12,468 10.00% 10.00% 20.00% $2,494 $14,962

40.07.10.153142 REMOVE CONCRETE ISLAND (PORTIONS) (CY) 44.00 CY $175.00 $7,700 10.00% 10.00% 20.00% $1,540 $9,240

40.07.10.153211 REMOVE CONCRETE (SIDEWALK AND DRIVEWAY) 7.00 CY $175.00 $1,225 10.00% 10.00% 20.00% $245 $1,470

40.07.10.153215 REMOVE CONCRETE (CURB AND GUTTER) 3,771.00 LF $3.75 $14,141 10.00% 10.00% 20.00% $2,828 $16,970

40.07.10.190101 ROADWAY EXCAVATION 700.00 CY $28.00 $19,600 10.00% 10.00% 20.00% $3,920 $23,520

40.07.10.192037 STRUCTURE EXCAVATION (RETAINING WALL) 375.00 CY $60.00 $22,500 10.00% 10.00% 20.00% $4,500 $27,000

40.07.10.270003 CEMENT TREATED BASE 316.00 CY $57.00 $18,012 10.00% 10.00% 20.00% $3,602 $21,614

40.07.10.390132 HOT MIX ASPHALT (TYPE A) 547.00TON $102.00 $55,794 10.00% 10.00% 20.00% $11,159 $66,953

40.07.10.510060 STRUCTURAL CONCRETE (RETAINING WALL) 400.00 CY $470.00 $188,000 10.00% 10.00% 20.00% $37,600 $225,600

40.07.10.520103 BAR REINFORCING STEEL (RETAINING WALL) 32,000.00 LB $1.00 $32,000 10.00% 10.00% 20.00% $6,400 $38,400

40.07.10.730070 DETECTABLE WARNING SURFACE 72.00 SF $45.00 $3,240 10.00% 10.00% 20.00% $648 $3,888

40.07.10.731504 MINOR CONCRETE (CURB AND GUTTER) 194.00 CY $365.00 $70,810 10.00% 10.00% 20.00% $14,162 $84,972

40.07.10.731519 MINOR CONCRETE (STAMPED CONCRETE) 7,970.00 SF $19.00 $151,430 10.00% 10.00% 20.00% $30,286 $181,716

40.07.10.731521 MINOR CONCRETE (SIDEWALK) 113.00 CY $347.00 $39,211 10.00% 10.00% 20.00% $7,842 $47,053

40.07.10.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 9.00 CY $765.00 $6,885 10.00% 10.00% 20.00% $1,377 $8,262

40.07.10.800360 CHAIN LINK FENCE (CL-6) 145.00 LF $19.00 $2,755 10.00% 10.00% 20.00% $551 $3,306

40.07.10.832001 METAL BEAM GUARD RAILING (WOOD POST) 425.00 LF $32.00 $13,600 10.00% 10.00% 20.00% $2,720 $16,320

40.07.10.833088 TUBULAR HANDRAILING 266.00 LF $220.00 $58,520 10.00% 10.00% 20.00% $11,704 $70,224

40.07.10.839581 END ANCHOR ASSEMBLY (TYPE SFT) 1.00 EA $819.00 $819 10.00% 10.00% 20.00% $164 $983

40.07.10.839603 CRASH CUSHION (ADIEM) 1.00 EA $30,300.00 $30,300 0.00% 10.00% 10.00% $3,030 $33,330

40.07.10.839703 CONCRETE BARRIER (TYPE 60C) 392.00 LF $88.00 $34,496 10.00% 10.00% 20.00% $6,899 $41,395

40.07.10.840515 THERMOPLASTIC PAVEMENT MARKING 71.00 SF $5.00 $355 10.00% 10.00% 20.00% $71 $426

Monday, January 27, 2014 Page 76 of 140

Page 141: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.10.840515 THERMOPLASTIC PAVEMENT MARKING 584.00 SF $5.00 $2,920 10.00% 10.00% 20.00% $584 $3,504

40.07.10.840656 PAINT TRAFFIC STRIPE (2-COAT) 1,800.00 LF $2.00 $3,600 10.00% 10.00% 20.00% $720 $4,320

40.07.10.850111 PAVEMENT MARKER (RETROREFLECTIVE) 3.00 EA $3.00 $9 10.00% 10.00% 20.00% $2 $11

40.07.10.850111 PAVEMENT MARKER (RETROREFLECTIVE) 91.00 EA $3.00 $273 10.00% 10.00% 20.00% $55 $328

40.07.10.900 STREET LIGHT 2.00 EA $2,000.00 $4,000 10.00% 10.00% 20.00% $800 $4,800

Sum

Average

143,723.00 $973,464

10.29% 10.00% 20.29%

$192,021 $1,165,485Summary for Group: 40.07.10

Group 40.07.10.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MORENA/CLAIREMONT DRAINAGE SYSTEMS Contingency

40.07.10.03.101 18" RCP STORM DRAIN 242.00 LF $120.00 $29,040 15.00% 10.00% 25.00% $7,260 $36,300

40.07.10.03.102 24" RCP STORM DRAIN 151.00 LF $170.00 $25,670 15.00% 10.00% 25.00% $6,418 $32,088

40.07.10.03.103 30" RCP STORM DRAIN 655.00 LF $210.00 $137,550 15.00% 10.00% 25.00% $34,388 $171,938

40.07.10.03.104 36" RCP STORM DRAIN 99.00 LF $230.00 $22,770 15.00% 10.00% 25.00% $5,693 $28,463

40.07.10.03.112 4" NON-PERFORATED PVC 55.00 LF $20.00 $1,100 15.00% 10.00% 25.00% $275 $1,375

40.07.10.03.113 6" NON-PERFORATED PVC 38.00 LF $65.00 $2,470 15.00% 10.00% 25.00% $618 $3,088

40.07.10.03.201 WASH WATER CLEANOUT 2.00 EA $4,500.00 $9,000 15.00% 10.00% 25.00% $2,250 $11,250

40.07.10.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 1.00 EA $4,500.00 $4,500 10.00% 10.00% 20.00% $900 $5,400

40.07.10.03.203 15' TYPE A CURB INLET, SDRSD SDD-115 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500

40.07.10.03.203 5' TYPE A CURB INLET, SDRSD SDD-115 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500

40.07.10.03.203 12' TYPE A CURB INLET, SDRSD SDD-115 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500

40.07.10.03.204 MOD 10' TYPE B-1 CURB INLET, SDRSD SDD-116 2.00 EA $6,900.00 $13,800 10.00% 10.00% 20.00% $2,760 $16,560

40.07.10.03.204 15' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $7,600.00 $7,600 15.00% 10.00% 25.00% $1,900 $9,500

40.07.10.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 2.00 EA $5,200.00 $10,400 15.00% 10.00% 25.00% $2,600 $13,000

40.07.10.03.208 9' TYPE J MEDIAN CURB INLET, SDRSD SDD-118 6.00 EA $6,900.00 $41,400 15.00% 10.00% 25.00% $10,350 $51,750

40.07.10.03.504 PIPE TO RCB CONNECTION 4.00 EA $9,993.00 $39,972 15.00% 10.00% 25.00% $9,993 $49,965

40.07.10.03.510 TRENCH DRAIN 651.00 LF $35.00 $22,785 15.00% 10.00% 25.00% $5,696 $28,481

40.07.10.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 4.00 EA $675.00 $2,700 15.00% 10.00% 25.00% $675 $3,375

40.07.10.03.701 ABANDON DRAINAGE STRUCTURE 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546

40.07.10.03.702 REMOVE EXIST DRAINAGE STRUCTURE 3.00 EA $1,829.00 $5,487 15.00% 10.00% 25.00% $1,372 $6,859

Monday, January 27, 2014 Page 77 of 140

Page 142: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

1,920.00 $397,881

14.50% 10.00% 24.50%

$98,555 $496,436Summary for Group: 40.07.10.03

Group 40.07.11

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE STREET IMPROVEMENTS Contingency

40.07.11.100 CHAIN LINK FENCE (CL-6) 1,510.00 LF $19.00 $28,690 10.00% 10.00% 20.00% $5,738 $34,428

40.07.11.103 AWNING (LA JOLLA COUNTRY DAY SCHOOL) 1,970.00 SF $38.00 $74,860 10.00% 10.00% 20.00% $14,972 $89,832

40.07.11.106 MILL AND OVERLAY (GENESEE) 546,940.00 SF $1.90 $1,039,186 10.00% 10.00% 20.00% $207,837 $1,247,023

40.07.11.141101 REMOVE YELLOW PAINTED TRAFFIC STRIPE (HAZARDOUS WASTE) 14,027.00 LF $1.00 $14,027 15.00% 10.00% 25.00% $3,507 $17,534

40.07.11.150609A REMOVE FENCE (MASONARY BLOCK) 249.00 LF $30.00 $7,470 10.00% 10.00% 20.00% $1,494 $8,964

40.07.11.150711 REMOVE PAINTED TRAFFIC STRIPE 33,575.00 LF $1.00 $33,575 15.00% 10.00% 25.00% $8,394 $41,969

40.07.11.150715 REMOVE THERMOPLASTIC PAVEMENT MARKING 4,218.00 SF $1.10 $4,640 15.00% 10.00% 25.00% $1,160 $5,800

40.07.11.150722 REMOVE PAVEMENT MARKER 1,177.00 EA $1.10 $1,295 15.00% 10.00% 25.00% $324 $1,618

40.07.11.150742 REMOVE ROADSIDE SIGN 50.00 EA $500.00 $25,000 10.00% 10.00% 20.00% $5,000 $30,000

40.07.11.150838 REMOVE SOUNDWALL 351.00 LF $54.00 $18,954 10.00% 10.00% 20.00% $3,791 $22,745

40.07.11.153139 REMOVE CONCRETE (SIDEWALK) 9,158.00 LF $12.00 $109,896 10.00% 10.00% 20.00% $21,979 $131,875

40.07.11.153142 REMOVE CONCRETE ISLAND (PORTIONS) (CY) 666.00 CY $175.00 $116,550 10.00% 10.00% 20.00% $23,310 $139,860

40.07.11.153211 REMOVE CONCRETE (SIDEWALK AND DRIVEWAY) 51.00 CY $175.00 $8,925 10.00% 10.00% 20.00% $1,785 $10,710

40.07.11.153215 REMOVE CONCRETE (CURB AND GUTTER) 20,334.00 LF $3.75 $76,253 10.00% 10.00% 20.00% $15,251 $91,503

40.07.11.190101 ROADWAY EXCAVATION 19,339.00 CY $28.00 $541,492 10.00% 10.00% 20.00% $108,298 $649,790

40.07.11.192037 STRUCTURE EXCAVATION (RETAINING WALL) 1,481.00 CY $60.00 $88,860 10.00% 10.00% 20.00% $17,772 $106,632

40.07.11.260203 CLASS 2 AGGREGATE BASE 47.00 CY $45.00 $2,115 10.00% 10.00% 20.00% $423 $2,538

40.07.11.270003 CEMENT TREATED BASE 6,361.00 CY $57.00 $362,577 10.00% 10.00% 20.00% $72,515 $435,092

40.07.11.390132 HOT MIX ASPHALT (TYPE A) 3,817.00TON $102.00 $389,334 10.00% 10.00% 20.00% $77,867 $467,201

40.07.11.401050 JOINTED PLAIN CONCRETE PAVEMENT 47.00 CY $447.00 $21,009 10.00% 10.00% 20.00% $4,202 $25,211

40.07.11.475010 RETAINING WALL (MASONRY WALL) 13,438.00 SF $70.00 $940,660 15.00% 15.00% 30.00% $282,198 $1,222,858

40.07.11.510062A STRUCTURAL CONCRETE (GRAVITY RETAINING WALL) 187.00 CY $650.00 $121,550 10.00% 10.00% 20.00% $24,310 $145,860

40.07.11.518002 SOUND WALL (W/FOOTING) 4,551.00 SF $35.00 $159,285 10.00% 10.00% 20.00% $31,857 $191,142

40.07.11.566011 ROADSIDE SIGN - ONE POST 50.00 EA $750.00 $37,500 10.00% 10.00% 20.00% $7,500 $45,000

40.07.11.582003A FENCE (MASONRY BLOCK) 2,000.00 SF $35.00 $70,000 10.00% 10.00% 20.00% $14,000 $84,000

40.07.11.730070 DETECTABLE WARNING SURFACE 396.00 SF $45.00 $17,820 10.00% 10.00% 20.00% $3,564 $21,384

Monday, January 27, 2014 Page 78 of 140

Page 143: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.11.731504 MINOR CONCRETE (CURB AND GUTTER) 530.00 CY $365.00 $193,450 10.00% 10.00% 20.00% $38,690 $232,140

40.07.11.731516 MINOR CONCRETE (DRIVEWAY) 76.00 CY $475.00 $36,100 10.00% 10.00% 20.00% $7,220 $43,320

40.07.11.731519 MINOR CONCRETE (STAMPED CONCRETE) 957.00 CY $347.00 $332,079 10.00% 10.00% 20.00% $66,416 $398,495

40.07.11.731521 MINOR CONCRETE (SIDEWALK) 626.00 CY $347.00 $217,222 10.00% 10.00% 20.00% $43,444 $260,666

40.07.11.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 40.00 CY $765.00 $30,600 10.00% 10.00% 20.00% $6,120 $36,720

40.07.11.833088 TUBULAR HANDRAILING 790.00 LF $220.00 $173,800 10.00% 10.00% 20.00% $34,760 $208,560

40.07.11.839607A CRASH CUSHION (TAU II) 16.00 EA $15,000.00 $240,000 0.00% 10.00% 10.00% $24,000 $264,000

40.07.11.839701 CONCRETE BARRIER (TYPE 60) 8,700.00 LF $46.00 $400,200 10.00% 10.00% 20.00% $80,040 $480,240

40.07.11.840515 THERMOPLASTIC PAVEMENT MARKING 6,901.00 SF $5.00 $34,505 10.00% 10.00% 20.00% $6,901 $41,406

40.07.11.840656 PAINT TRAFFIC STRIPE (2-COAT) 54,100.00 LF $2.00 $108,200 10.00% 10.00% 20.00% $21,640 $129,840

40.07.11.850111 PAVEMENT MARKER (RETROREFLECTIVE) 1,072.00 EA $3.00 $3,216 10.00% 10.00% 20.00% $643 $3,859

40.07.11.900 STREET LIGHT 28.00 EA $2,000.00 $56,000 10.00% 10.00% 20.00% $11,200 $67,200

40.07.11.901 REMOVE STREET LIGHT 10.00 EA $1,500.00 $15,000 10.00% 10.00% 20.00% $3,000 $18,000

40.07.11.902 LIGHT FIXTURES UNDER AERIAL STRUCTURE 20.00 EA $2,000.00 $40,000 10.00% 10.00% 20.00% $8,000 $48,000

Sum

Average

759,856.00 $6,191,894

10.38% 10.13% 20.50%

$1,311,122 $7,503,016Summary for Group: 40.07.11

Group 40.07.11.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE AVE DRAINAGE IMPROVEMENTS Contingency

40.07.11.03.101 18" RCP STORM DRAIN 2,368.00 LF $120.00 $284,160 15.00% 10.00% 25.00% $71,040 $355,200

40.07.11.03.102 24" RCP STORM DRAIN 77.00 LF $170.00 $13,090 15.00% 10.00% 25.00% $3,273 $16,363

40.07.11.03.103 30" RCP STORM DRAIN 6.00 LF $210.00 $1,260 15.00% 10.00% 25.00% $315 $1,575

40.07.11.03.104 36" RCP STORM DRAIN 57.00 LF $230.00 $13,110 15.00% 10.00% 25.00% $3,278 $16,388

40.07.11.03.105 42" RCP STORM DRAIN 734.00 LF $260.00 $190,840 15.00% 10.00% 25.00% $47,710 $238,550

40.07.11.03.116 10" NON-PERFORATED PVC 10.00 LF $104.00 $1,040 15.00% 10.00% 25.00% $260 $1,300

40.07.11.03.201 TYPE A-6 SD CLEANOUT, SDRSD D-9 3.00 EA $5,500.00 $16,500 15.00% 10.00% 25.00% $4,125 $20,625

40.07.11.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 17.00 EA $4,500.00 $76,500 15.00% 10.00% 25.00% $19,125 $95,625

40.07.11.03.201 TYPE A-8 SD CLEANOUT, SDRSD D-9 1.00 EA $6,000.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500

40.07.11.03.204 10' TYPE B CURB INLET, SDRSD SDD-116 3.00 EA $6,900.00 $20,700 15.00% 10.00% 25.00% $5,175 $25,875

40.07.11.03.204 21' TYPE B-1 CURB INLET, SDRSD SDD-116 3.00 EA $8,100.00 $24,300 15.00% 10.00% 25.00% $6,075 $30,375

40.07.11.03.204 15' TYPE B CURB INLET, SDRSD SDD-116 6.00 EA $7,600.00 $45,600 15.00% 10.00% 25.00% $11,400 $57,000

Monday, January 27, 2014 Page 79 of 140

Page 144: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.11.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 2.00 EA $5,200.00 $10,400 15.00% 10.00% 25.00% $2,600 $13,000

40.07.11.03.204 21' TYPE B-2 CURB INLET, SDRSD SDD-116 1.00 EA $8,100.00 $8,100 15.00% 10.00% 25.00% $2,025 $10,125

40.07.11.03.204 10' TYPE B-2 CURB INLET, SDRSD SDD-116 3.00 EA $6,900.00 $20,700 15.00% 10.00% 25.00% $5,175 $25,875

40.07.11.03.204 7' TYPE B-2 CURB INLET, SDD-116 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500

40.07.11.03.207 TYPE I CATCH BASIN, SDRSD D-29 11.00 EA $6,450.00 $70,950 15.00% 10.00% 25.00% $17,738 $88,688

40.07.11.03.208 9' TYPE J MEDIAN CURB INLET, SDRSD SDD-118 2.00 EA $6,900.00 $13,800 15.00% 10.00% 25.00% $3,450 $17,250

40.07.11.03.209 TYPE A CURB OUTLET, SDRSD D-25 3.00 EA $2,500.00 $7,500 15.00% 10.00% 25.00% $1,875 $9,375

40.07.11.03.500 ADJUST MH TO FG 2.00 EA $1,100.00 $2,200 15.00% 10.00% 25.00% $550 $2,750

40.07.11.03.501 CONCRETE LUG, SDRSD SD-113 5.00 EA $1,100.00 $5,500 15.00% 10.00% 25.00% $1,375 $6,875

40.07.11.03.502 PIPE COLLAR 12.00 EA $1,800.00 $21,600 15.00% 10.00% 25.00% $5,400 $27,000

40.07.11.03.600 HYDROMODIFICATION SURFACE STORAGE 24,000.00 CF $2.00 $48,000 15.00% 10.00% 25.00% $12,000 $60,000

40.07.11.03.602 HYDROMODIFICATION OUTLET STRUCTURE - SURFACE STORAGE 12.00 EA $5,000.00 $60,000 15.00% 10.00% 25.00% $15,000 $75,000

40.07.11.03.700 ABANDON EXIST PIPE (CAP AND PLUG) 8.00 EA $675.00 $5,400 15.00% 10.00% 25.00% $1,350 $6,750

40.07.11.03.701 ABANDON DRAINAGE STRUCTURE 1.00 EA $1,237.00 $1,237 15.00% 10.00% 25.00% $309 $1,546

40.07.11.03.702 REMOVE EXIST DRAINAGE STRUCTURE 14.00 EA $1,829.00 $25,606 15.00% 10.00% 25.00% $6,402 $32,008

40.07.11.03.704 REMOVE EXIST CURB OUTLET 4.00 EA $590.00 $2,360 15.00% 10.00% 25.00% $590 $2,950

Sum

Average

27,366.00 $1,001,653

15.00% 10.00% 25.00%

$250,413 $1,252,066Summary for Group: 40.07.11.03

Group 40.07.12

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PACIFIC HWY/ TAYLOR/ ROSECRANS STREET IMPROVEMENTS Contingency

40.07.12.10.08 PERVIOUS BACKFILL 62.00 CY $36.00 $2,232 10.00% 10.00% 20.00% $446 $2,678

40.07.12.10.10 STRUCTURAL BACKFILL 298.00 CY $52.00 $15,496 10.00% 10.00% 20.00% $3,099 $18,595

40.07.12.10.20 STRUCTURE EXCAVATION 378.00 CY $60.00 $22,680 10.00% 10.00% 20.00% $4,536 $27,216

40.07.12.10.40 STRUCTURAL CONCRETE (RETAINING WALL) 443.00 CY $470.00 $208,210 10.00% 10.00% 20.00% $41,642 $249,852

40.07.12.10.50 ARCHITECTURAL TREATMENT 3,996.00 SF $14.00 $55,944 10.00% 10.00% 20.00% $11,189 $67,133

40.07.12.10.60 BAR REINFORCING STEEL 58,631.00 LB $1.00 $58,631 10.00% 10.00% 20.00% $11,726 $70,357

40.07.12.10.70 CABLE RAILING 666.00 LF $25.00 $16,650 10.00% 10.00% 20.00% $3,330 $19,980

40.07.12.101 CHAIN LINK FENCE (CL-3) 890.00 LF $16.00 $14,240 10.00% 10.00% 20.00% $2,848 $17,088

40.07.12.106 MILL AND OVERLAY (PACIFIC HWY/ROSECRANS) 75,208.00 SF $1.90 $142,895 10.00% 10.00% 20.00% $28,579 $171,474

40.07.12.109 6" PORTLAND CEMENT CONCRETE (DECORATIVE CONCRETE) 25.90 CY $625.00 $16,188 10.00% 10.00% 20.00% $3,238 $19,425

Monday, January 27, 2014 Page 80 of 140

Page 145: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.12.150710 REMOVE TRAFFIC STRIPE 5,800.00 LF $1.00 $5,800 15.00% 10.00% 25.00% $1,450 $7,250

40.07.12.150713 REMOVE PAVEMENT MARKING 1,300.00 SF $1.10 $1,430 15.00% 10.00% 25.00% $358 $1,788

40.07.12.150742 ROADSIDE SIGN - ONE POST 12.00 EA $750.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

40.07.12.150742 REMOVE ROADSIDE SIGN 12.00 EA $500.00 $6,000 10.00% 10.00% 20.00% $1,200 $7,200

40.07.12.150770 SAWCUT ASPHALT PAVEMENT 237.00 LF $2.00 $474 10.00% 10.00% 20.00% $95 $569

40.07.12.150770 SAWCUT ASPHALT PAVEMENT 963.00 LF $2.00 $1,926 10.00% 10.00% 20.00% $385 $2,311

40.07.12.150838 REMOVE RETAINING WALL 300.00 LF $54.00 $16,200 10.00% 10.00% 20.00% $3,240 $19,440

40.07.12.150838 REMOVE RETAINING WALL 910.00 LF $54.00 $49,140 10.00% 10.00% 20.00% $9,828 $58,968

40.07.12.153241 REMOVE CONCRETE (SIDEWALK) 3,963.00 SF $3.00 $11,889 10.00% 10.00% 20.00% $2,378 $14,267

40.07.12.153241 REMOVE CONCRETE (SIDEWALK) 1,500.00 SF $3.00 $4,500 10.00% 10.00% 20.00% $900 $5,400

40.07.12.190101 ROADWAY EXCAVATION 750.00 CY $28.00 $21,000 10.00% 10.00% 20.00% $4,200 $25,200

40.07.12.190101 ROADWAY EXCAVATION 181.00 CY $28.00 $5,068 10.00% 10.00% 20.00% $1,014 $6,082

40.07.12.270011 CEMENT TREATED BASE 116.00 CY $57.00 $6,612 10.00% 10.00% 20.00% $1,322 $7,934

40.07.12.270011 CEMENT TREATED BASE 445.00 CY $57.00 $25,365 10.00% 10.00% 20.00% $5,073 $30,438

40.07.12.390132 HOT MIX ASPHALT (TYPE A) 53.00TON $102.00 $5,406 10.00% 10.00% 20.00% $1,081 $6,487

40.07.12.390132 HOT MIX ASPHALT (TYPE A) 255.00TON $102.00 $26,010 10.00% 10.00% 20.00% $5,202 $31,212

40.07.12.731504.1 MINOR CONCRETE (CURB AND GUTTER) (TYPE B) 380.00 LF $34.00 $12,920 10.00% 10.00% 20.00% $2,584 $15,504

40.07.12.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 219.00 LF $36.00 $7,884 10.00% 10.00% 20.00% $1,577 $9,461

40.07.12.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 784.00 LF $36.00 $28,224 10.00% 10.00% 20.00% $5,645 $33,869

40.07.12.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 72.00 CY $635.00 $45,720 10.00% 10.00% 20.00% $9,144 $54,864

40.07.12.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 26.00 CY $635.00 $16,510 10.00% 10.00% 20.00% $3,302 $19,812

40.07.12.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.12.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.12.840515 THERMOPLASTIC PAVEMENT MARKING 1,279.00 SF $5.00 $6,395 10.00% 10.00% 20.00% $1,279 $7,674

40.07.12.840656 PAINT TRAFFIC STRIPE (2-COAT) 6,060.00 LF $2.00 $12,120 10.00% 10.00% 20.00% $2,424 $14,544

40.07.12.850101 PAVEMENT MARKER (NON-REFLECTIVE) 120.00 EA $2.00 $240 15.00% 10.00% 25.00% $60 $300

40.07.12.850111 PAVEMENT MARKER (RETROREFLECTIVE) 121.00 EA $3.00 $363 10.00% 10.00% 20.00% $73 $436

40.07.12.850111 PAVEMENT MARKER (RETROREFLECTIVE) 121.00 EA $3.00 $363 10.00% 10.00% 20.00% $73 $436

40.07.12.900 STREET LIGHT 2.00 EA $2,000.00 $4,000 10.00% 10.00% 20.00% $800 $4,800

Monday, January 27, 2014 Page 81 of 140

Page 146: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.12.901 REMOVE STREET LIGHT 2.00 EA $1,500.00 $3,000 10.00% 10.00% 20.00% $600 $3,600

Sum

Average

166,594.90 $897,435

10.38% 10.00% 20.38%

$179,860 $1,077,295Summary for Group: 40.07.12

Group 40.07.13

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

WASHINGTON/ FRONTAGE STREET IMPROVEMENTS Contingency

40.07.13.150713 REMOVE PAVEMENT MARKING 164.00 SF $1.10 $180 15.00% 10.00% 25.00% $45 $226

40.07.13.150742 REMOVE ROADSIDE SIGN 3.00 EA $500.00 $1,500 10.00% 10.00% 20.00% $300 $1,800

40.07.13.566011 ROADSIDE SIGN - ONE POST 3.00 EA $750.00 $2,250 10.00% 10.00% 20.00% $450 $2,700

40.07.13.840515 THERMOPLASTIC PAVEMENT MARKING 164.00 SF $5.00 $820 10.00% 10.00% 20.00% $164 $984

40.07.13.850111 PAVEMENT MARKER (RETROREFLECTIVE) 17.00 EA $3.00 $51 10.00% 10.00% 20.00% $10 $61

Sum

Average

351.00 $4,801

11.00% 10.00% 21.00%

$969 $5,771Summary for Group: 40.07.13

Group 40.07.14

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SASSAFRAS/ KETTNER STREET IMPROVEMENTS Contingency

40.07.14.150713 REMOVE PAVEMENT MARKING 30.00 SF $1.10 $33 15.00% 10.00% 25.00% $8 $41

40.07.14.150742 REMOVE ROADSIDE SIGN 2.00 EA $500.00 $1,000 10.00% 10.00% 20.00% $200 $1,200

40.07.14.566011 ROADSIDE SIGN - ONE POST 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800

40.07.14.840515 THERMOPLASTIC PAVEMENT MARKING 30.00 SF $5.00 $150 10.00% 10.00% 20.00% $30 $180

40.07.14.850111 PAVEMENT MARKER (RETROREFLECTIVE) 7.00 EA $3.00 $21 10.00% 10.00% 20.00% $4 $25

Sum

Average

71.00 $2,704

11.00% 10.00% 21.00%

$542 $3,246Summary for Group: 40.07.14

Group 40.07.15

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CEDAR/ KETTNER STREET IMPROVEMENTS Contingency

40.07.15.150713 REMOVE PAVEMENT MARKING 60.00 SF $1.10 $66 15.00% 10.00% 25.00% $17 $83

40.07.15.150742 REMOVE ROADSIDE SIGN 6.00 EA $500.00 $3,000 10.00% 10.00% 20.00% $600 $3,600

40.07.15.566011 ROADSIDE SIGN - ONE POST 6.00 EA $750.00 $4,500 10.00% 10.00% 20.00% $900 $5,400

40.07.15.840515 THERMOPLASTIC PAVEMENT MARKING 60.00 SF $5.00 $300 10.00% 10.00% 20.00% $60 $360

Sum

Average

132.00 $7,866

11.25% 10.00% 21.25%

$1,577 $9,443Summary for Group: 40.07.15

Group 40.07.16

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PACIFIC HWY/CEDAR STREET IMPROVEMENTS Contingency

40.07.16.150713 REMOVE PAVEMENT MARKING 70.00 SF $1.10 $77 15.00% 10.00% 25.00% $19 $96

Monday, January 27, 2014 Page 82 of 140

Page 147: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.16.150742 REMOVE ROADSIDE SIGN 3.00 EA $500.00 $1,500 10.00% 10.00% 20.00% $300 $1,800

40.07.16.150770 SAWCUT ASPHALT PAVEMENT 3,120.00 LF $2.00 $6,240 10.00% 10.00% 20.00% $1,248 $7,488

40.07.16.270011 CEMENT TREATED BASE 115.00 CY $57.00 $6,555 10.00% 10.00% 20.00% $1,311 $7,866

40.07.16.390132 HOT MIX ASPHALT (TYPE A) 66.00TON $102.00 $6,732 10.00% 10.00% 20.00% $1,346 $8,078

40.07.16.566011 ROADSIDE SIGN - ONE POST 3.00 EA $750.00 $2,250 10.00% 10.00% 20.00% $450 $2,700

40.07.16.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 800.00 LF $36.00 $28,800 10.00% 10.00% 20.00% $5,760 $34,560

40.07.16.840515 THERMOPLASTIC PAVEMENT MARKING 115.00 SF $5.00 $575 10.00% 10.00% 20.00% $115 $690

40.07.16.850111 PAVEMENT MARKER (RETROREFLECTIVE) 90.00 EA $3.00 $270 10.00% 10.00% 20.00% $54 $324

Sum

Average

4,382.00 $52,999

10.56% 10.00% 20.56%

$10,604 $63,603Summary for Group: 40.07.16

Group 40.07.17

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MORENA/BALBOA STREET IMPROVEMENTS Contingency

40.07.17.106 MILL AND OVERLAY (MORENA/BALBOA) 122,414.00 SF $1.90 $232,587 10.00% 10.00% 20.00% $46,517 $279,104

40.07.17.107 ASPHALT PAVEMENT REMOVAL 258,300.00 SF $1.60 $413,280 10.00% 10.00% 20.00% $82,656 $495,936

40.07.17.150710 REMOVE TRAFFIC STRIPE 13,250.00 LF $1.00 $13,250 15.00% 10.00% 25.00% $3,313 $16,563

40.07.17.150713 REMOVE PAVEMENT MARKING 20.00 SF $1.10 $22 15.00% 10.00% 25.00% $6 $28

40.07.17.190101 ROADWAY EXCAVATION 3,062.00 CY $28.00 $85,736 10.00% 10.00% 20.00% $17,147 $102,883

40.07.17.192037 STRUCTURE EXCAVATION (RETAINING WALL) 556.00 CY $60.00 $33,360 10.00% 10.00% 20.00% $6,672 $40,032

40.07.17.193013 STRUCTURAL BACKFILL 730.00 CY $52.00 $37,960 10.00% 10.00% 20.00% $7,592 $45,552

40.07.17.260203 CLASS 2 AGGREGATE BASE 1,060.00 CY $45.00 $47,700 10.00% 10.00% 20.00% $9,540 $57,240

40.07.17.390132 HOT MIX ASPHALT (TYPE A) 1,340.00TON $102.00 $136,680 10.00% 10.00% 20.00% $27,336 $164,016

40.07.17.401050 JOINTED PLAIN CONCRETE PAVEMENT 120.00 CY $447.00 $53,640 10.00% 10.00% 20.00% $10,728 $64,368

40.07.17.510060 STRUCTURAL CONCRETE (RETAINING WALL) 273.00 CY $470.00 $128,310 10.00% 10.00% 20.00% $25,662 $153,972

40.07.17.520103 BAR REINFORCING STEEL (RETAINING WALL) 39,240.00 LB $1.00 $39,240 10.00% 10.00% 20.00% $7,848 $47,088

40.07.17.730020 MINOR CONCRETE (CURB) 8.00 CY $500.00 $4,000 10.00% 10.00% 20.00% $800 $4,800

40.07.17.730070 DETECTABLE WARNING SURFACE 192.00 SF $45.00 $8,640 10.00% 10.00% 20.00% $1,728 $10,368

40.07.17.731504 MINOR CONCRETE (CURB AND GUTTER) 222.00 CY $365.00 $81,030 10.00% 10.00% 20.00% $16,206 $97,236

40.07.17.731521 MINOR CONCRETE (SIDEWALK) 325.00 CY $347.00 $112,775 10.00% 10.00% 20.00% $22,555 $135,330

40.07.17.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 13.00 CY $765.00 $9,945 10.00% 10.00% 20.00% $1,989 $11,934

40.07.17.839521 CABLE RAILING 425.00 LF $25.00 $10,625 10.00% 10.00% 20.00% $2,125 $12,750

Monday, January 27, 2014 Page 83 of 140

Page 148: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.17.839603 CRASH ATTENUATOR 1.00 EA $55,205.00 $55,205 0.00% 10.00% 10.00% $5,521 $60,726

40.07.17.840515 THERMOPLASTIC PAVEMENT MARKING 2,680.00 SF $5.00 $13,400 10.00% 10.00% 20.00% $2,680 $16,080

40.07.17.840656 PAINT TRAFFIC STRIPE (2 COAT) 13,250.00 LF $2.00 $26,500 10.00% 10.00% 20.00% $5,300 $31,800

40.07.17.850111 PAVEMENT MARKER (RETROREFLECTIVE) 336.00 EA $3.00 $1,008 10.00% 10.00% 20.00% $202 $1,210

40.07.17.866011 ROADSIDE SIGN - ONE POST 70.00 EA $750.00 $52,500 10.00% 10.00% 20.00% $10,500 $63,000

40.07.17.900 STREET LIGHT 10.00 EA $2,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

40.07.17.901 REMOVE STREET LIGHT 9.00 EA $1,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

Sum

Average

457,906.00 $1,630,893

10.00% 10.00% 20.00%

$321,322 $1,952,214Summary for Group: 40.07.17

Group 40.07.17.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MORENA/BALBOA STREET IMPROVEMENTS DRAINAGE SYSTEMS Contingency

40.07.17.03.101 18" RCP STORM DRAIN 714.00 LF $120.00 $85,680 15.00% 10.00% 25.00% $21,420 $107,100

40.07.17.03.122 4" PERFORATED PVE 340.00 LF $20.00 $6,800 15.00% 10.00% 25.00% $1,700 $8,500

40.07.17.03.201 TYPE A-4 SD CLEANOUT, SDRSD D-9 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

40.07.17.03.204 15' TYPE B-1 CURB INLET, SDRSD SDD-116 2.00 EA $7,600.00 $15,200 15.00% 10.00% 25.00% $3,800 $19,000

40.07.17.03.204 10' TYPE B-1 CURB INLET, SDRSD SDD-116 2.00 EA $6,900.00 $13,800 15.00% 10.00% 25.00% $3,450 $17,250

40.07.17.03.204 21' TYPE B-1 CURB INLET, SDRSD SDD-116 1.00 EA $8,100.00 $8,100 15.00% 10.00% 25.00% $2,025 $10,125

40.07.17.03.204 5' TYPE B CURB INLET, SDRSD SDD-116 2.00 EA $5,200.00 $10,400 15.00% 10.00% 25.00% $2,600 $13,000

40.07.17.03.207 TYPE I CATCH BASIN, SDRSD D-29 1.00 EA $6,450.00 $6,450 10.00% 10.00% 20.00% $1,290 $7,740

40.07.17.03.208 9' TYPE J MEDIAN CURB INLET, SDRSD SDD-118 3.00 EA $6,900.00 $20,700 15.00% 10.00% 25.00% $5,175 $25,875

40.07.17.03.210 WING TYPE HEADWALL, SDRSD D34 2.00 EA $4,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

40.07.17.03.211 4.5' TYPE OS INLET, CT STD D72 1.00 EA $4,500.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625

40.07.17.03.501 CONCRETE LUG, SDRSD SDD-113 1.00 EA $1,100.00 $1,100 15.00% 10.00% 25.00% $275 $1,375

40.07.17.03.505 1/4 TON RIPRAP ENERGY DISSIPATOR TYPE 2, SDRSD SDD-104 2.00 EA $2,500.00 $5,000 15.00% 10.00% 25.00% $1,250 $6,250

40.07.17.03.508 4" UNDERDRAIN CLEANOUT 5.00 EA $60.00 $300 15.00% 10.00% 25.00% $75 $375

Sum

Average

1,078.00 $196,030

13.93% 10.00% 23.93%

$47,785 $243,815Summary for Group: 40.07.17.03

Group 40.07.18

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

W MORENA/TECOLOTE STREET IMPROVEMENTS Contingency

40.07.18.102 6' PICKET FENCE 700.00 LF $72.00 $50,400 10.00% 10.00% 20.00% $10,080 $60,480

40.07.18.106 MILL AND OVERLAY (WMORENA/TECOLOTE) 49,272.00 SF $1.90 $93,617 10.00% 10.00% 20.00% $18,723 $112,340

Monday, January 27, 2014 Page 84 of 140

Page 149: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.18.141101 REMOVE YELLOW PAINTED TRAFFIC STRIPE (HAZARDOUS WASTE) 20.00 LF $1.00 $20 15.00% 10.00% 25.00% $5 $25

40.07.18.150608 REMOVE CHAIN LINK FENCE 175.00 LF $2.75 $481 10.00% 10.00% 20.00% $96 $578

40.07.18.150662 REMOVE METAL BEAM GUARD RAILING 48.00 LF $13.00 $624 10.00% 10.00% 20.00% $125 $749

40.07.18.150710 REMOVE TRAFFIC STRIPE 38.00 LF $1.00 $38 15.00% 10.00% 25.00% $10 $48

40.07.18.150715 REMOVE THERMOPLASTIC PAVEMENT MARKING 433.00 SF $1.10 $476 15.00% 10.00% 25.00% $119 $595

40.07.18.150722 REMOVE PAVEMENT MARKER 6.00 EA $1.10 $7 15.00% 10.00% 25.00% $2 $8

40.07.18.153139 REMOVE CONCRETE (SIDEWALK) 119.00 LF $12.00 $1,428 10.00% 10.00% 20.00% $286 $1,714

40.07.18.153142 REMOVE CONCRETE ISLAND (PORTIONS) (CY) 9.00 CY $175.00 $1,575 10.00% 10.00% 20.00% $315 $1,890

40.07.18.153212A REMOVE CONCRETE (SIDEWALK AND BARRIER) 15.00 CY $100.00 $1,500 15.00% 10.00% 25.00% $375 $1,875

40.07.18.153215 REMOVE CONCRETE (CURB AND GUTTER) 1,231.00 LF $3.75 $4,616 10.00% 10.00% 20.00% $923 $5,540

40.07.18.190101 ROADWAY EXCAVATION 639.00 CY $28.00 $17,892 10.00% 10.00% 20.00% $3,578 $21,470

40.07.18.260203 CLASS 2 AGGREGATE BASE 135.00 CY $45.00 $6,075 10.00% 10.00% 20.00% $1,215 $7,290

40.07.18.390132 HOT MIX ASPHALT (TYPE A) 95.00TON $102.00 $9,690 10.00% 10.00% 20.00% $1,938 $11,628

40.07.18.401050 JOINTED PLAIN CONCRETE PAVEMENT 135.00 CY $447.00 $60,345 10.00% 10.00% 20.00% $12,069 $72,414

40.07.18.478010 RETAINING WALL (MASONRY WALL) 1,350.00 SF $70.00 $94,500 15.00% 15.00% 30.00% $28,350 $122,850

40.07.18.730020 MINOR CONCRETE (CURB) 17.00 CY $500.00 $8,500 10.00% 10.00% 20.00% $1,700 $10,200

40.07.18.730070 DETECTABLE WARNING SURFACE 60.00 SF $45.00 $2,700 10.00% 10.00% 20.00% $540 $3,240

40.07.18.731502 MINOR CONCRETE (MISCELLANEOUS CONSTRUCTION) 34.00 CY $937.00 $31,858 10.00% 10.00% 20.00% $6,372 $38,230

40.07.18.731504 MINOR CONCRETE (CURB AND GUTTER) 52.00 CY $365.00 $18,980 10.00% 10.00% 20.00% $3,796 $22,776

40.07.18.731519 MINOR CONCRETE (STAMPED CONCRETE) 861.00 SF $19.00 $16,359 10.00% 10.00% 20.00% $3,272 $19,631

40.07.18.731521 MINOR CONCRETE (SIDEWALK) 106.00 CY $347.00 $36,782 10.00% 10.00% 20.00% $7,356 $44,138

40.07.18.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 6.00 CY $765.00 $4,590 10.00% 10.00% 20.00% $918 $5,508

40.07.18.800360 CHAIN LINK FENCE (CL-6) 690.00 LF $19.00 $13,110 10.00% 10.00% 20.00% $2,622 $15,732

40.07.18.833088 TUBULAR HANDRAILING 270.00 LF $220.00 $59,400 10.00% 10.00% 20.00% $11,880 $71,280

40.07.18.833140 CONCRETE BARRIER (TYPE 26) 62.00 LF $100.00 $6,200 10.00% 10.00% 20.00% $1,240 $7,440

40.07.18.840515 THERMOPLASTIC PAVEMENT MARKING 433.00 SF $5.00 $2,165 10.00% 10.00% 20.00% $433 $2,598

Sum

Average

57,011.00 $543,928

11.07% 10.18% 21.25%

$118,338 $662,266Summary for Group: 40.07.18

Group 40.07.18.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

W MORENA/TECOLOTE STREET IMPROVEMENTS DRAINAGE SYSTEMS Contingency

Monday, January 27, 2014 Page 85 of 140

Page 150: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.18.03.101 18" RCP STORM DRAIN 58.00 LF $120.00 $6,960 15.00% 10.00% 25.00% $1,740 $8,700

40.07.18.03.208 5' TYPE J MEDIAN CURB INLET, SDRSD SDD-118 1.00 EA $5,200.00 $5,200 15.00% 10.00% 25.00% $1,300 $6,500

Sum

Average

59.00 $12,160

15.00% 10.00% 25.00%

$3,040 $15,200Summary for Group: 40.07.18.03

Group 40.07.19

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CAMPUS POINT STREET IMPROVEMENTS Contingency

40.07.19.106 MILL AND OVERLAY (CAMPUS POINT) 58,200.00 SF $1.90 $110,580 10.00% 10.00% 20.00% $22,116 $132,696

40.07.19.150742 REMOVE ROADSIDE SIGN 12.00 EA $500.00 $6,000 10.00% 10.00% 20.00% $1,200 $7,200

40.07.19.150770 SAWCUT ASPHALT PAVEMENT 580.00 LF $2.00 $1,160 10.00% 10.00% 20.00% $232 $1,392

40.07.19.153241 REMOVE CONCRETE (SIDEWALK) 1,716.00 SF $3.00 $5,148 10.00% 10.00% 20.00% $1,030 $6,178

40.07.19.190101 ROADWAY EXCAVATION 633.00 CY $28.00 $17,724 10.00% 10.00% 20.00% $3,545 $21,269

40.07.19.260203 CLASS 2 AGGREGATE BASE 222.00 CY $45.00 $9,990 10.00% 10.00% 20.00% $1,998 $11,988

40.07.19.390132 HOT MIX ASPHALT (TYPE A) 193.00TON $102.00 $19,686 10.00% 10.00% 20.00% $3,937 $23,623

40.07.19.566011 ROADSIDE SIGN - ONE POST 12.00 EA $750.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

40.07.19.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 792.00 LF $36.00 $28,512 10.00% 10.00% 20.00% $5,702 $34,214

40.07.19.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 16.00 CY $635.00 $10,160 10.00% 10.00% 20.00% $2,032 $12,192

40.07.19.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.19.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.19.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.19.839603 CRASH ATTENUATOR 2.00 EA $55,205.00 $110,410 0.00% 10.00% 10.00% $11,041 $121,451

40.07.19.839701 CONCRETE BARRIER 125.00 LF $53.00 $6,625 10.00% 10.00% 20.00% $1,325 $7,950

40.07.19.900 STREET LIGHT 10.00 EA $2,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

40.07.19.901 REMOVE STREET LIGHT 10.00 EA $1,500.00 $15,000 10.00% 10.00% 20.00% $3,000 $18,000

Sum

Average

62,544.00 $386,060

9.41% 10.00% 19.41%

$66,171 $452,231Summary for Group: 40.07.19

Group 40.07.20

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LYMAN/SIXTH LANE STREET IMPROVEMENTS Contingency

40.07.20.106 MILL AND OVERLAY (LYMAN/SIXTH) 6,278.00 SF $1.90 $11,928 10.00% 10.00% 20.00% $2,386 $14,314

40.07.20.150710 REMOVE TRAFFIC STRIPE 2,400.00 LF $1.00 $2,400 15.00% 10.00% 25.00% $600 $3,000

40.07.20.150713 REMOVE PAVEMENT MARKING 90.00 SF $1.10 $99 15.00% 10.00% 25.00% $25 $124

40.07.20.150742 REMOVE ROADSIDE SIGN 5.00 EA $500.00 $2,500 10.00% 10.00% 20.00% $500 $3,000

Monday, January 27, 2014 Page 86 of 140

Page 151: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.20.150770 SAWCUT ASPHALT PAVEMENT 591.00 LF $2.00 $1,182 10.00% 10.00% 20.00% $236 $1,418

40.07.20.153241 REMOVE CONCRETE (SIDEWALK) 5,146.00 SF $3.00 $15,438 10.00% 10.00% 20.00% $3,088 $18,526

40.07.20.190101 ROADWAY EXCAVATION 1,268.00 CY $28.00 $35,504 10.00% 10.00% 20.00% $7,101 $42,605

40.07.20.260203 CLASS 2 AGGREGATE BASE 475.00 CY $45.00 $21,375 10.00% 10.00% 20.00% $4,275 $25,650

40.07.20.390132 HOT MIX ASPHALT (TYPE A) 446.00TON $102.00 $45,492 10.00% 10.00% 20.00% $9,098 $54,590

40.07.20.566011 ROADSIDE SIGN - ONE POST 10.00 EA $750.00 $7,500 10.00% 10.00% 20.00% $1,500 $9,000

40.07.20.731504.1 MINOR CONCRETE (CURB AND GUTTER) (TYPE B) 71.00 LF $34.00 $2,414 10.00% 10.00% 20.00% $483 $2,897

40.07.20.731504.3 MINOR CONCRETE (CURB AND GUTTER) (TYPE H) 1,471.00 LF $38.00 $55,898 10.00% 10.00% 20.00% $11,180 $67,078

40.07.20.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 163.00 CY $635.00 $103,505 10.00% 10.00% 20.00% $20,701 $124,206

40.07.20.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 14.00 CY $765.00 $10,710 10.00% 10.00% 20.00% $2,142 $12,852

40.07.20.840515 THERMOPLASTIC PAVEMENT MARKING 478.00 SF $5.00 $2,390 10.00% 15.00% 25.00% $598 $2,988

40.07.20.840656 PAINT TRAFFIC STRIPE (2-COAT) 2,400.00 LF $2.00 $4,800 15.00% 15.00% 30.00% $1,440 $6,240

40.07.20.900 STREET LIGHT 7.00 EA $2,000.00 $14,000 10.00% 10.00% 20.00% $2,800 $16,800

40.07.20.901 REMOVE STREET LIGHT 5.00 EA $1,500.00 $7,500 10.00% 10.00% 20.00% $1,500 $9,000

Sum

Average

21,318.00 $344,635

10.83% 10.56% 21.39%

$69,651 $414,287Summary for Group: 40.07.20

Group 40.07.20.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LYMAN/SIXTH LANE IMPROVEMENTS DRAINAGE SYSTEMS Contingency

40.07.20.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD WEST STR 3,481.40 CF $2.45 $8,529 15.00% 15.00% 30.00% $2,559 $11,088

40.07.20.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD WEST STRE 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

Sum

Average

3,482.40 $15,529

15.00% 15.00% 30.00%

$4,659 $20,188Summary for Group: 40.07.20.04

Group 40.07.21

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

VOIGT STREET IMPROVEMENTS Contingency

40.07.21.100 CHAIN LINK FENCE (CL-6) 252.00 LF $19.00 $4,788 10.00% 10.00% 20.00% $958 $5,746

40.07.21.106 MILL AND OVERLAY (VOIGT) 142,560.00 SF $1.90 $270,864 10.00% 10.00% 20.00% $54,173 $325,037

40.07.21.110 9" PORTLAND CEMENT CONCRETE 61.00 CY $603.00 $36,783 10.00% 10.00% 20.00% $7,357 $44,140

40.07.21.150710 REMOVE TRAFFIC STRIPE 8,700.00 LF $1.00 $8,700 15.00% 10.00% 25.00% $2,175 $10,875

40.07.21.150713 REMOVE PAVEMENT MARKING 75.00 SF $1.10 $83 15.00% 10.00% 25.00% $21 $103

40.07.21.150742 REMOVE ROADSIDE SIGN 5.00 EA $500.00 $2,500 10.00% 10.00% 20.00% $500 $3,000

40.07.21.150770 SAWCUT ASPHALT PAVEMENT 1,134.00 LF $2.00 $2,268 10.00% 10.00% 20.00% $454 $2,722

Monday, January 27, 2014 Page 87 of 140

Page 152: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.21.153241 REMOVE CONCRETE (SIDEWALK) 14,871.00 SF $3.00 $44,613 10.00% 10.00% 20.00% $8,923 $53,536

40.07.21.190101 ROADWAY EXCAVATION 1,584.00 CY $28.00 $44,352 10.00% 10.00% 20.00% $8,870 $53,222

40.07.21.260203 CLASS 2 AGGREGATE BASE 191.00 CY $45.00 $8,595 10.00% 10.00% 20.00% $1,719 $10,314

40.07.21.270011 CEMENT TREATED BASE 94.00 CY $57.00 $5,358 10.00% 10.00% 20.00% $1,072 $6,430

40.07.21.390132 HOT MIX ASPHALT (TYPE A) 189.00TON $102.00 $19,278 10.00% 10.00% 20.00% $3,856 $23,134

40.07.21.566011 ROADSIDE SIGN - ONE POST 5.00 EA $750.00 $3,750 10.00% 10.00% 20.00% $750 $4,500

40.07.21.731504.1 MINOR CONCRETE (CURB AND GUTTER) (TYPE B) 100.00 LF $34.00 $3,400 10.00% 10.00% 20.00% $680 $4,080

40.07.21.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 1,280.00 LF $36.00 $46,080 10.00% 10.00% 20.00% $9,216 $55,296

40.07.21.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 121.00 CY $635.00 $76,835 10.00% 10.00% 20.00% $15,367 $92,202

40.07.21.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.21.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.21.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.21.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.21.839701 CONCRETE BARRIER 89.00 LF $53.00 $4,717 10.00% 10.00% 20.00% $943 $5,660

40.07.21.840515 THERMOPLASTIC PAVEMENT MARKING 183.00 SF $5.00 $915 10.00% 15.00% 25.00% $229 $1,144

40.07.21.840656 PAINT TRAFFIC STRIPE (2-COAT) 1,683.00 LF $2.00 $3,366 15.00% 15.00% 30.00% $1,010 $4,376

40.07.21.850111 PAVEMENT MARKER (RETROREFLECTIVE) 19.00 EA $3.00 $57 15.00% 15.00% 30.00% $17 $74

40.07.21.900 STREET LIGHT 7.00 EA $2,000.00 $14,000 10.00% 10.00% 20.00% $2,800 $16,800

40.07.21.901 REMOVE STREET LIGHT 6.00 EA $1,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

Sum

Average

173,237.00 $631,722

10.77% 10.58% 21.35%

$127,171 $758,893Summary for Group: 40.07.21

Group 40.07.21.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

VOIGT STREET IMPROVEMENTS DRAINAGE SYSTEMS Contingency

40.07.21.04.601 HYDROMODIFICATION-UNDERGROUND STORAGE (UCSD EAST STR 2,246.40 CF $2.45 $5,504 15.00% 15.00% 30.00% $1,651 $7,155

40.07.21.04.603 HYDROMODIFICATION-OUTLET STRUCTURE-UG (UCSD EAST STREE 1.00 EA $7,000.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

Sum

Average

2,247.40 $12,504

15.00% 15.00% 30.00%

$3,751 $16,255Summary for Group: 40.07.21.04

Group 40.07.22

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

I-5 STREET IMPROVEMENTS Contingency

40.07.22.108 DEMO METAL BEAM GUARD RAIL (WOOD POST) 1,200.00 LF $10.00 $12,000 10.00% 10.00% 20.00% $2,400 $14,400

40.07.22.150710 REMOVE TRAFFIC STRIPE 37,300.00 LF $1.00 $37,300 15.00% 10.00% 25.00% $9,325 $46,625

Monday, January 27, 2014 Page 88 of 140

Page 153: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.22.150713 REMOVE PAVEMENT MARKING 20.00 SF $1.10 $22 15.00% 10.00% 25.00% $6 $28

40.07.22.208 DEMO CONCRETE BARRIER 1,202.00 LF $10.00 $12,020 10.00% 10.00% 20.00% $2,404 $14,424

40.07.22.832003 METAL BEAM GUARD RAILING (WOOD POST) 5,557.00 LF $32.00 $177,824 10.00% 10.00% 20.00% $35,565 $213,389

40.07.22.839701 CONCRETE BARRIER 1,202.00 LF $53.00 $63,706 10.00% 10.00% 20.00% $12,741 $76,447

40.07.22.840501 THERMOPLASTIC TRAFFIC STRIPE 37,300.00 LF $2.75 $102,575 15.00% 10.00% 25.00% $25,644 $128,219

40.07.22.840515 THERMOPLASTIC PAVEMENT MARKING 20.00 SF $5.00 $100 10.00% 15.00% 25.00% $25 $125

40.07.22.850101 PAVEMENT MARKER (NON-REFLECTIVE) 3,108.00 EA $2.00 $6,216 15.00% 10.00% 25.00% $1,554 $7,770

40.07.22.850111 PAVEMENT MARKER (RETROREFLECTIVE) 781.00 EA $3.00 $2,343 15.00% 15.00% 30.00% $703 $3,046

Sum

Average

87,690.00 $414,106

12.50% 11.00% 23.50%

$90,366 $504,472Summary for Group: 40.07.22

Group 40.07.23

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LA JOLLA COLONY STREET IMPROVEMENTS Contingency

40.07.23.106 MILL AND OVERLAY (LA JOLLA COLONY) 30,000.00 SF $1.90 $57,000 10.00% 10.00% 20.00% $11,400 $68,400

40.07.23.108 DEMO METAL BEAM GUARD RAIL (WOOD POST) 99.00 LF $10.00 $990 10.00% 10.00% 20.00% $198 $1,188

40.07.23.150710 REMOVE TRAFFIC STRIPE 6,100.00 LF $1.00 $6,100 15.00% 10.00% 25.00% $1,525 $7,625

40.07.23.150713 REMOVE PAVEMENT MARKING 30.00 SF $1.10 $33 15.00% 10.00% 25.00% $8 $41

40.07.23.150742 REMOVE ROADSIDE SIGN 8.00 EA $500.00 $4,000 15.00% 15.00% 30.00% $1,200 $5,200

40.07.23.150770 SAWCUT ASPHALT PAVEMENT 49.00 LF $2.00 $98 10.00% 10.00% 20.00% $20 $118

40.07.23.153241 REMOVE CONCRETE (SIDEWALK) 167.00 SF $3.00 $501 10.00% 10.00% 20.00% $100 $601

40.07.23.190101 ROADWAY EXCAVATION 130.00 CY $28.00 $3,640 10.00% 10.00% 20.00% $728 $4,368

40.07.23.270011 CEMENT TREATED BASE 145.00 CY $57.00 $8,265 10.00% 10.00% 20.00% $1,653 $9,918

40.07.23.390132 HOT MIX ASPHALT (TYPE A) 213.00TON $102.00 $21,726 10.00% 10.00% 20.00% $4,345 $26,071

40.07.23.566011 ROADSIDE SIGN - ONE POST 8.00 EA $750.00 $6,000 15.00% 15.00% 30.00% $1,800 $7,800

40.07.23.731504.2 MINOR CONCRETE (CURB AND GUTTER) (TYPE G) 200.00 LF $36.00 $7,200 10.00% 10.00% 20.00% $1,440 $8,640

40.07.23.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 1.00 CY $635.00 $635 10.00% 10.00% 20.00% $127 $762

40.07.23.731623 MINOR CONCRETE (CURB RAMP)(TYPE A) 7.00 CY $765.00 $5,355 10.00% 10.00% 20.00% $1,071 $6,426

40.07.23.832003 METAL BEAM GUARD RAILING (WOOD POST) 525.00 LF $32.00 $16,800 10.00% 10.00% 20.00% $3,360 $20,160

40.07.23.839603 CRASH ATTENUATOR 2.00 EA $55,205.00 $110,410 0.00% 10.00% 10.00% $11,041 $121,451

40.07.23.839701 CONCRETE BARRIER 303.00 LF $53.00 $16,059 10.00% 10.00% 20.00% $3,212 $19,271

40.07.23.840515 THERMOPLASTIC PAVEMENT MARKING 129.00 SF $5.00 $645 10.00% 15.00% 25.00% $161 $806

Monday, January 27, 2014 Page 89 of 140

Page 154: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.23.840656 PAINT TRAFFIC STRIPE (2-COAT) 9,966.00 LF $2.00 $19,932 15.00% 15.00% 30.00% $5,980 $25,912

40.07.23.850111 PAVEMENT MARKER (RETROREFLECTIVE) 128.00 EA $3.00 $384 15.00% 15.00% 30.00% $115 $499

40.07.23.900 STREET LIGHT 2.00 EA $2,000.00 $4,000 15.00% 15.00% 30.00% $1,200 $5,200

40.07.23.901 REMOVE STREET LIGHT 2.00 EA $1,500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

Sum

Average

48,214.00 $292,773

11.36% 11.59% 22.95%

$51,584 $344,357Summary for Group: 40.07.23

Group 40.07.24

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PERMANENT BMP (ROADS/PARKING LOTS) Contingency

40.07.24 PERMANENT BMP (ROADS/PARKING LOTS) 1.00 LS $2,000,000.00 $2,000,000 0.00% 20.00% 20.00% $400,000 $2,400,000

Sum

Average

1.00 $2,000,000

0.00% 20.00% 20.00%

$400,000 $2,400,000Summary for Group: 40.07.24

Group 40.07.25

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PARKING RECONSTRUCTION Contingency

40.07.25.101 MILL AND OVERLAY (LA JOLLA VILLAGE SQUARE) 212,340.00 SF $1.90 $403,446 10.00% 10.00% 20.00% $80,689 $484,135

40.07.25.102 MILL AND OVERLAY (SOUTH OF GILMAN) 27,078.00 SF $1.90 $51,448 10.00% 10.00% 20.00% $10,290 $61,738

40.07.25.103 MILL AND OVERLAY (NORTH OF GILMAN) 33,727.00 SF $1.90 $64,081 10.00% 10.00% 20.00% $12,816 $76,898

40.07.25.104 MILL AND OVERLAY (CALTRANS D11) 16,800.00 SF $1.90 $31,920 10.00% 10.00% 20.00% $6,384 $38,304

40.07.25.105 MILL AND OVERLAY (NEAR LOVELOCK) 8,400.00 SF $1.90 $15,960 10.00% 10.00% 20.00% $3,192 $19,152

40.07.25.106 MILL AND OVERLAY (CITY OF SD MAINT YARD) 58,750.00 SF $1.90 $111,625 10.00% 10.00% 20.00% $22,325 $133,950

40.07.25.107 MILL AND OVERLAY (ALONG ROSE CREEK CHANNEL) 3,012.00 SF $1.90 $5,723 10.00% 10.00% 20.00% $1,145 $6,867

40.07.25.108 MILL AND OVERLAY (NORTH OF MORENA/ARIANE) 39,098.00 SF $1.90 $74,286 10.00% 10.00% 20.00% $14,857 $89,143

40.07.25.109 MILL AND OVERLAY (WHOLE FOODS MARKET) 44,716.00 SF $1.90 $84,960 10.00% 10.00% 20.00% $16,992 $101,952

40.07.25.110 MILL AND OVERLAY (S. OF VOIGT DR PARKING) 52,329.00 SF $1.90 $99,425 10.00% 10.00% 20.00% $19,885 $119,310

40.07.25.111 MILL AND OVERLAY (CAMPUS POINT/VOIGT PARKING) 105,261.00 SF $1.90 $199,996 10.00% 10.00% 20.00% $39,999 $239,995

Sum

Average

601,511.00 $1,142,871

10.00% 10.00% 20.00%

$228,574 $1,371,445Summary for Group: 40.07.25

Group 40.07.26

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

FRIARS ROAD STREET IMPROVEMENTS Contingency

40.07.26.104 REMOVE ASPHALT CONCRETE DIKE 877.00 LF $1.75 $1,535 10.00% 10.00% 20.00% $307 $1,842

40.07.26.105 ASPHALT CONCRETE DIKE 877.00 LF $20.00 $17,540 10.00% 10.00% 20.00% $3,508 $21,048

40.07.26.106 MILL AND OVERLAY (FRIARS) 38,400.00 SF $1.90 $72,960 10.00% 10.00% 20.00% $14,592 $87,552

40.07.26.108 DEMO METAL BEAM GUARD RAIL (WOOD POST) 250.00 LF $10.00 $2,500 10.00% 10.00% 20.00% $500 $3,000

Monday, January 27, 2014 Page 90 of 140

Page 155: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.26.150710 REMOVE TRAFFIC STRIPE 14,400.00 LF $1.00 $14,400 15.00% 10.00% 25.00% $3,600 $18,000

40.07.26.150770 SAWCUT ASPHALT PAVEMENT 800.00 LF $2.00 $1,600 10.00% 10.00% 20.00% $320 $1,920

40.07.26.832003 METAL BEAM GUARD RAILING (WOOD POST) 265.00 LF $32.00 $8,480 10.00% 10.00% 20.00% $1,696 $10,176

40.07.26.839603 CRASH ATTENUATOR 2.00 EA $55,205.00 $110,410 0.00% 10.00% 10.00% $11,041 $121,451

40.07.26.840656 PAINT TRAFFIC STRIPE (2-COAT) 14,400.00 LF $2.00 $28,800 15.00% 15.00% 30.00% $8,640 $37,440

40.07.26.840656 PAINT TRAFFIC STRIPE (2-COAT) 14,400.00 LF $2.00 $28,800 10.00% 10.00% 20.00% $5,760 $34,560

40.07.26.850111 PAVEMENT MARKER (RETROREFLECTIVE) 301.00 EA $3.00 $903 10.00% 10.00% 20.00% $181 $1,084

Sum

Average

84,972.00 $287,928

10.00% 10.45% 20.45%

$50,145 $338,072Summary for Group: 40.07.26

Group 40.07.27

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NOBEL DRIVE STREET IMPROVEMENTS Contingency

40.07.27.106 MILL AND OVERLAY (NOBEL) 30,400.00 SF $1.90 $57,760 10.00% 10.00% 20.00% $11,552 $69,312

40.07.27.150710 REMOVE TRAFFIC STRIPE 3,600.00 LF $1.00 $3,600 15.00% 10.00% 25.00% $900 $4,500

40.07.27.150713 REMOVE PAVEMENT MARKING 60.00 SF $1.10 $66 15.00% 10.00% 25.00% $17 $83

40.07.27.153241 REMOVE CONCRETE (SIDEWALK) 450.00 SF $3.00 $1,350 10.00% 10.00% 20.00% $270 $1,620

40.07.27.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 31.00 CY $635.00 $19,685 10.00% 10.00% 20.00% $3,937 $23,622

40.07.27.840515 THERMOPLASTIC PAVEMENT MARKING 60.00 SF $5.00 $300 10.00% 15.00% 25.00% $75 $375

40.07.27.840656 PAINT TRAFFIC STRIPE (2-COAT) 3,600.00 LF $2.00 $7,200 15.00% 15.00% 30.00% $2,160 $9,360

40.07.27.850111 PAVEMENT MARKER (RETROREFLECTIVE) 76.00 EA $3.00 $228 15.00% 15.00% 30.00% $68 $296

Sum

Average

38,277.00 $90,189

12.50% 11.88% 24.38%

$18,979 $109,168Summary for Group: 40.07.27

Group 40.07.28

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LA JOLLA VILLAGE DRIVE STREET IMPROVEMENTS Contingency

40.07.28.150710 REMOVE TRAFFIC STRIPE 1,000.00 LF $1.00 $1,000 15.00% 10.00% 25.00% $250 $1,250

40.07.28.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 31.00 CY $635.00 $19,685 10.00% 10.00% 20.00% $3,937 $23,622

Sum

Average

1,031.00 $20,685

12.50% 10.00% 22.50%

$4,187 $24,872Summary for Group: 40.07.28

Group 40.07.29

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MORENA STREET IMPROVEMENTS Contingency

40.07.29.104 REMOVE ASPHALT CONCRETE DIKE 2,800.00 LF $1.75 $4,900 10.00% 10.00% 20.00% $980 $5,880

40.07.29.105 ASPHALT CONCRETE DIKE 2,800.00 LF $20.00 $56,000 10.00% 10.00% 20.00% $11,200 $67,200

40.07.29.106 MILL AND OVERLAY (MORENA BLVD) 520,331.00 SF $1.90 $988,629 10.00% 10.00% 20.00% $197,726 $1,186,355

Monday, January 27, 2014 Page 91 of 140

Page 156: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.29.108 DEMO METAL BEAM GUARD RAIL (WOOD POST) 2,800.00 LF $10.00 $28,000 10.00% 10.00% 20.00% $5,600 $33,600

40.07.29.150710 REMOVE TRAFFIC STRIPE 10,200.00 LF $1.00 $10,200 15.00% 10.00% 25.00% $2,550 $12,750

40.07.29.150713 REMOVE PAVEMENT MARKING 60.00 SF $1.10 $66 15.00% 10.00% 25.00% $17 $83

40.07.29.150742 REMOVE ROADSIDE SIGN 10.00 EA $500.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000

40.07.29.150770 SAWCUT ASPHALT PAVEMENT 204.00 LF $2.00 $408 10.00% 10.00% 20.00% $82 $490

40.07.29.153241 REMOVE CONCRETE (SIDEWALK) 4,000.00 SF $3.00 $12,000 10.00% 10.00% 20.00% $2,400 $14,400

40.07.29.270011 CEMENT TREATED BASE 8.00 CY $57.00 $456 10.00% 10.00% 20.00% $91 $547

40.07.29.390132 HOT MIX ASPHALT (TYPE A) 4.00TON $102.00 $408 10.00% 10.00% 20.00% $82 $490

40.07.29.566011 ROADSIDE SIGN - ONE POST 10.00 EA $750.00 $7,500 10.00% 10.00% 20.00% $1,500 $9,000

40.07.29.731504.1 MINOR CONCRETE (CURB AND GUTTER) (TYPE B) 350.00 LF $34.00 $11,900 10.00% 10.00% 20.00% $2,380 $14,280

40.07.29.731504.3 MINOR CONCRETE (CURB AND GUTTER) (TYPE H) 204.00 LF $38.00 $7,752 10.00% 10.00% 20.00% $1,550 $9,302

40.07.29.731521 MINOR CONCRETE (SIDEWALK & MEDIAN) 54.00 CY $635.00 $34,290 10.00% 10.00% 20.00% $6,858 $41,148

40.07.29.832003 METAL BEAM GUARD RAILING (WOOD POST) 2,848.00 LF $32.00 $91,136 10.00% 10.00% 20.00% $18,227 $109,363

40.07.29.840656 PAINT TRAFFIC STRIPE (2-COAT) 10,200.00 LF $2.00 $20,400 15.00% 15.00% 30.00% $6,120 $26,520

40.07.29.850111 PAVEMENT MARKER (RETROREFLECTIVE) 214.00 EA $3.00 $642 10.00% 10.00% 20.00% $128 $770

40.07.29.900 STREET LIGHT 22.00 EA $2,000.00 $44,000 10.00% 10.00% 20.00% $8,800 $52,800

40.07.29.901 REMOVE STREET LIGHT 6.00 EA $1,500.00 $9,000 10.00% 10.00% 20.00% $1,800 $10,800

Sum

Average

557,125.00 $1,332,687

10.75% 10.25% 21.00%

$269,091 $1,601,778Summary for Group: 40.07.29

Group 40.07.30

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROSE CANYON BUSINESS PARK-PARKING LOT Contingency

40.07.30.104 REMOVE ASPHALT CONCRETE DIKE 735.00 LF $1.75 $1,286 10.00% 10.00% 20.00% $257 $1,544

40.07.30.105 ASPHALT CONCRETE DIKE 735.00 LF $20.00 $14,700 10.00% 10.00% 20.00% $2,940 $17,640

40.07.30.150770 SAWCUT ASPHALT PAVEMENT 735.00 LF $2.00 $1,470 10.00% 10.00% 20.00% $294 $1,764

40.07.30.270011 CEMENT TREATED BASE 27.00 CY $57.00 $1,539 10.00% 10.00% 20.00% $308 $1,847

40.07.30.390132 HOT MIX ASPHALT (TYPE A) 16.00TON $102.00 $1,632 10.00% 10.00% 20.00% $326 $1,958

Sum

Average

2,248.00 $20,627

10.00% 10.00% 20.00%

$4,125 $24,753Summary for Group: 40.07.30

Group 40.07.31

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GILMAN DR STREET IMPROVEMENTS Contingency

40.07.31.150710 REMOVE TRAFFIC STRIPE 600.00 LF $1.00 $600 15.00% 10.00% 25.00% $150 $750

Monday, January 27, 2014 Page 92 of 140

Page 157: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.07.31.840656 PAINT TRAFFIC STRIPE (2-COAT) 600.00 LF $2.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

Sum

Average

1,200.00 $1,800

15.00% 12.50% 27.50%

$510 $2,310Summary for Group: 40.07.31

Sum

Average

5,006,780.88 $32,772,723

11.61% 10.41% 22.02%

$7,122,203 $39,894,926Summary for Sub Section: 40.07

Sub Section 40.08 TEMPORARY FACILITIES AND OTHER INDIRECT COSTS DURING CONSTRUCTION

Group 40.08.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PARTNERING SESSIONS Contingency

40.08.01 PARTNERING SESSIONS 1.00 LS $300,000.00 $300,000 0.00% 0.00% 0.00% $0 $300,000

Sum

Average

1.00 $300,000

0.00% 0.00% 0.00%

$0 $300,000Summary for Group: 40.08.01

Group 40.08.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MOBILIZATION (8.5%) Contingency

40.08.02 MOBILIZATION (8.5%) 1.00 LS $47,061,899.61 $47,061,900 0.00% 10.00% 10.00% $4,706,190 $51,768,090

Sum

Average

1.00 $47,061,900

0.00% 10.00% 10.00%

$4,706,190 $51,768,090Summary for Group: 40.08.02

Group 40.08.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CLAIREMONT DR Contingency

40.08.10.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875

40.08.10.120161 TEMPORARY TRAFFIC STRIPE 1,800.00 LF $2.50 $4,500 20.00% 10.00% 30.00% $1,350 $5,850

40.08.10.129000 TEMPORARY RAILING (TYPE K) 600.00 LF $17.00 $10,200 20.00% 10.00% 30.00% $3,060 $13,260

40.08.10.129110 TEMPORARY CRASH CUSHION 2.00 EA $4,000.00 $8,000 20.00% 10.00% 30.00% $2,400 $10,400

40.08.10.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250

40.08.10.992 SHORT-TERM TRAFFIC CONTROL 10.00DAY $605.00 $6,050 20.00% 20.00% 40.00% $2,420 $8,470

40.08.10.993 FLAGGER 10.00DAY $750.00 $7,500 15.00% 15.00% 30.00% $2,250 $9,750

Sum

Average

2,438.00 $40,250

18.57% 12.14% 30.71%

$12,605 $52,855Summary for Group: 40.08.10

Group 40.08.11

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE AVE Contingency

40.08.11.120090 CONSTRUCTION AREA SIGNS 30.00 EA $250.00 $7,500 15.00% 10.00% 25.00% $1,875 $9,375

40.08.11.120161 TEMPORARY TRAFFIC STRIPE 113,200.00 LF $2.50 $283,000 20.00% 10.00% 30.00% $84,900 $367,900

40.08.11.128650 PORTABLE CHANGEABLE MESSAGE SIGN 6.00 EA $5,000.00 $30,000 10.00% 10.00% 20.00% $6,000 $36,000

40.08.11.129000 TEMPORARY RAILING (TYPE K) 22,900.00 LF $17.00 $389,300 20.00% 10.00% 30.00% $116,790 $506,090

Monday, January 27, 2014 Page 93 of 140

Page 158: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.08.11.129110 TEMPORARY CRASH CUSHION 28.00 EA $4,000.00 $112,000 20.00% 10.00% 30.00% $33,600 $145,600

40.08.11.158210 RESET TEMPORARY RAILING (TYPE K) 6,500.00 LF $4.00 $26,000 15.00% 10.00% 25.00% $6,500 $32,500

40.08.11.991 TRAFFIC HANDING SIGNS 100.00 EA $250.00 $25,000 20.00% 10.00% 30.00% $7,500 $32,500

40.08.11.992 SHORT-TERM TRAFFIC CONTROL 1,750.00DAY $605.00 $1,058,750 20.00% 20.00% 40.00% $423,500 $1,482,250

40.08.11.993 FLAGGER 1,750.00DAY $750.00 $1,312,500 15.00% 15.00% 30.00% $393,750 $1,706,250

40.08.11120150 TEMPORARY PAVEMENT MARKING 1,880.00 SF $3.50 $6,580 20.00% 10.00% 30.00% $1,974 $8,554

Sum

Average

148,144.00 $3,250,630

17.50% 11.50% 29.00%

$1,076,389 $4,327,019Summary for Group: 40.08.11

Group 40.08.12

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PAC HWY/TAYLOR/ROSECRANS Contingency

40.08.12.120090 CONSTRUCTION AREA SIGNS 10.00 EA $250.00 $2,500 15.00% 10.00% 25.00% $625 $3,125

40.08.12.120150 TEMPORARY PAVEMENT MARKING 1,300.00 SF $3.50 $4,550 20.00% 10.00% 30.00% $1,365 $5,915

40.08.12.120161 TEMPORARY TRAFFIC STRIPE 5,800.00 LF $2.50 $14,500 20.00% 10.00% 30.00% $4,350 $18,850

40.08.12.128650 PORTABLE CHANGEABLE MESSAGE SIGN 2.00 EA $5,000.00 $10,000 10.00% 10.00% 20.00% $2,000 $12,000

40.08.12.129000 TEMPORARY RAILING (TYPE K) 1,500.00 LF $17.00 $25,500 20.00% 10.00% 30.00% $7,650 $33,150

40.08.12.129110 TEMPORARY CRASH CUSHION 2.00 EA $4,000.00 $8,000 20.00% 10.00% 30.00% $2,400 $10,400

40.08.12.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500

40.08.12.992 SHORT-TERM TRAFFIC CONTROL 30.00DAY $605.00 $18,150 20.00% 20.00% 40.00% $7,260 $25,410

40.08.12.993 FLAGGER 30.00DAY $750.00 $22,500 15.00% 15.00% 30.00% $6,750 $29,250

Sum

Average

8,694.00 $110,700

17.78% 11.67% 29.44%

$33,900 $144,600Summary for Group: 40.08.12

Group 40.08.17

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BALBOA AVE Contingency

40.08.17.120090 CONSTRUCTION AREA SIGNS 24.00 EA $250.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500

40.08.17.120150 TEMPORARY PAVEMENT MARKING 160.00 SF $3.50 $560 20.00% 10.00% 30.00% $168 $728

40.08.17.120161 TEMPORARY TRAFFIC STRIPE 25,200.00 LF $2.50 $63,000 20.00% 10.00% 30.00% $18,900 $81,900

40.08.17.128650 PORTABLE CHANGEABLE MESSAGE SIGN 4.00 EA $5,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

40.08.17.129000 TEMPORARY RAILING (TYPE K) 5,400.00 LF $17.00 $91,800 20.00% 10.00% 30.00% $27,540 $119,340

40.08.17.129110 TEMPORARY CRASH CUSHION 6.00 EA $4,000.00 $24,000 20.00% 10.00% 30.00% $7,200 $31,200

40.08.17.991 TRAFFIC HANDING SIGNS 50.00 EA $250.00 $12,500 20.00% 10.00% 30.00% $3,750 $16,250

40.08.17.992 SHORT-TERM TRAFFIC CONTROL 310.00DAY $605.00 $187,550 20.00% 20.00% 40.00% $75,020 $262,570

Monday, January 27, 2014 Page 94 of 140

Page 159: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.08.17.993 FLAGGER 310.00DAY $750.00 $232,500 15.00% 15.00% 30.00% $69,750 $302,250

Sum

Average

31,464.00 $637,910

17.78% 11.67% 29.44%

$207,828 $845,738Summary for Group: 40.08.17

Group 40.08.18

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TECOLOTE RD Contingency

40.08.18.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500

40.08.18.992 SHORT-TERM TRAFFIC CONTROL 10.00DAY $605.00 $6,050 20.00% 20.00% 40.00% $2,420 $8,470

40.08.18.993 FLAGGER 10.00DAY $750.00 $7,500 15.00% 15.00% 30.00% $2,250 $9,750

Sum

Average

40.00 $18,550

18.33% 15.00% 33.33%

$6,170 $24,720Summary for Group: 40.08.18

Group 40.08.19

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

VOIGT DR/CAMPUS PT DR Contingency

40.08.19.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875

40.08.19.120161 TEMPORARY TRAFFIC STRIPE 11,700.00 LF $2.50 $29,250 20.00% 10.00% 30.00% $8,775 $38,025

40.08.19.128650 PORTABLE CHANGEABLE MESSAGE SIGN 2.00 EA $5,000.00 $10,000 10.00% 10.00% 20.00% $2,000 $12,000

40.08.19.129000 TEMPORARY RAILING (TYPE K) 4,500.00 LF $17.00 $76,500 20.00% 10.00% 30.00% $22,950 $99,450

40.08.19.129110 TEMPORARY CRASH CUSHION 7.00 EA $4,000.00 $28,000 20.00% 10.00% 30.00% $8,400 $36,400

40.08.19.158210 RESET TEMPORARY RAILING (TYPE K) 3,000.00 LF $4.00 $12,000 15.00% 10.00% 25.00% $3,000 $15,000

40.08.19.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250

40.08.19.992 SHORT-TERM TRAFFIC CONTROL 140.00DAY $605.00 $84,700 20.00% 20.00% 40.00% $33,880 $118,580

40.08.19.993 FLAGGER 100.00DAY $750.00 $75,000 15.00% 15.00% 30.00% $22,500 $97,500

40.08.19120150 TEMPORARY PAVEMENT MARKING 150.00 SF $3.50 $525 20.00% 10.00% 30.00% $158 $683

Sum

Average

19,615.00 $319,975

17.50% 11.50% 29.00%

$102,788 $422,763Summary for Group: 40.08.19

Group 40.08.20

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SIXTH LANE/LYMAN AVE Contingency

40.08.20.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875

40.08.20.120150 TEMPORARY PAVEMENT MARKING 90.00 SF $3.50 $315 20.00% 10.00% 30.00% $95 $410

40.08.20.120161 TEMPORARY TRAFFIC STRIPE 2,400.00 LF $2.50 $6,000 20.00% 10.00% 30.00% $1,800 $7,800

40.08.20.128650 PORTABLE CHANGEABLE MESSAGE SIGN 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000

40.08.20.129000 TEMPORARY RAILING (TYPE K) 2,700.00 LF $17.00 $45,900 20.00% 10.00% 30.00% $13,770 $59,670

40.08.20.129110 TEMPORARY CRASH CUSHION 3.00 EA $4,000.00 $12,000 20.00% 10.00% 30.00% $3,600 $15,600

Monday, January 27, 2014 Page 95 of 140

Page 160: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.08.20.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250

40.08.20.992 SHORT-TERM TRAFFIC CONTROL 120.00DAY $605.00 $72,600 20.00% 20.00% 40.00% $29,040 $101,640

40.08.20.993 FLAGGER 80.00DAY $750.00 $60,000 15.00% 15.00% 30.00% $18,000 $78,000

Sum

Average

5,410.00 $205,815

17.78% 11.67% 29.44%

$68,430 $274,245Summary for Group: 40.08.20

Group 40.08.22

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

I-5 AND I-5 RAMPS Contingency

40.08.22.120090 CONSTRUCTION AREA SIGNS 18.00 EA $250.00 $4,500 15.00% 10.00% 25.00% $1,125 $5,625

40.08.22.120150 TEMPORARY PAVEMENT MARKING 20.00 SF $3.50 $70 20.00% 10.00% 30.00% $21 $91

40.08.22.120161 TEMPORARY TRAFFIC STRIPE 37,300.00 LF $2.50 $93,250 20.00% 10.00% 30.00% $27,975 $121,225

40.08.22.128650 PORTABLE CHANGEABLE MESSAGE SIGN 6.00 EA $5,000.00 $30,000 10.00% 10.00% 20.00% $6,000 $36,000

40.08.22.129000 TEMPORARY RAILING (TYPE K) 13,900.00 LF $17.00 $236,300 20.00% 10.00% 30.00% $70,890 $307,190

40.08.22.129110 TEMPORARY CRASH CUSHION 11.00 EA $4,000.00 $44,000 20.00% 10.00% 30.00% $13,200 $57,200

40.08.22.991 TRAFFIC HANDING SIGNS 80.00 EA $250.00 $20,000 20.00% 10.00% 30.00% $6,000 $26,000

40.08.22.992 SHORT-TERM TRAFFIC CONTROL 350.00DAY $605.00 $211,750 20.00% 20.00% 40.00% $84,700 $296,450

40.08.22.993 FLAGGER 30.00DAY $750.00 $22,500 15.00% 15.00% 30.00% $6,750 $29,250

Sum

Average

51,715.00 $662,370

17.78% 11.67% 29.44%

$216,661 $879,031Summary for Group: 40.08.22

Group 40.08.23

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LA JOLLA COLONY DR Contingency

40.08.23.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875

40.08.23.120150 TEMPORARY PAVEMENT MARKING 534.00 SF $3.50 $1,869 20.00% 10.00% 30.00% $561 $2,430

40.08.23.120161 TEMPORARY TRAFFIC STRIPE 12,900.00 LF $2.50 $32,250 20.00% 10.00% 30.00% $9,675 $41,925

40.08.23.128650 PORTABLE CHANGEABLE MESSAGE SIGN 3.00 EA $5,000.00 $15,000 10.00% 10.00% 20.00% $3,000 $18,000

40.08.23.129000 TEMPORARY RAILING (TYPE K) 2,600.00 LF $17.00 $44,200 20.00% 10.00% 30.00% $13,260 $57,460

40.08.23.129110 TEMPORARY CRASH CUSHION 2.00 EA $4,000.00 $8,000 20.00% 10.00% 30.00% $2,400 $10,400

40.08.23.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500

40.08.23.992 SHORT-TERM TRAFFIC CONTROL 200.00DAY $605.00 $121,000 20.00% 20.00% 40.00% $48,400 $169,400

40.08.23.993 FLAGGER 200.00DAY $750.00 $150,000 15.00% 15.00% 30.00% $45,000 $195,000

Sum

Average

16,465.00 $378,819

17.78% 11.67% 29.44%

$124,171 $502,990Summary for Group: 40.08.23

Monday, January 27, 2014 Page 96 of 140

Page 161: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Group 40.08.26

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

FRIARS RD Contingency

40.08.26.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875

40.08.26.120150 TEMPORARY PAVEMENT MARKING 150.00 SF $3.50 $525 20.00% 10.00% 30.00% $158 $683

40.08.26.120161 TEMPORARY TRAFFIC STRIPE 16,800.00 LF $2.50 $42,000 20.00% 10.00% 30.00% $12,600 $54,600

40.08.26.128650 PORTABLE CHANGEABLE MESSAGE SIGN 4.00 EA $5,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

40.08.26.129000 TEMPORARY RAILING (TYPE K) 1,500.00 LF $17.00 $25,500 20.00% 10.00% 30.00% $7,650 $33,150

40.08.26.129110 TEMPORARY CRASH CUSHION 4.00 EA $4,000.00 $16,000 20.00% 10.00% 30.00% $4,800 $20,800

40.08.26.158210 RESET TEMPORARY RAILING (TYPE K) 1,500.00 LF $4.00 $6,000 15.00% 10.00% 25.00% $1,500 $7,500

40.08.26.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500

40.08.26.992 SHORT-TERM TRAFFIC CONTROL 280.00DAY $605.00 $169,400 20.00% 20.00% 40.00% $67,760 $237,160

40.08.26.993 FLAGGER 280.00DAY $750.00 $210,000 15.00% 15.00% 30.00% $63,000 $273,000

Sum

Average

20,544.00 $495,925

17.50% 11.50% 29.00%

$163,343 $659,268Summary for Group: 40.08.26

Group 40.08.27

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NOBEL DR Contingency

40.08.27.120090 CONSTRUCTION AREA SIGNS 4.00 EA $250.00 $1,000 15.00% 10.00% 25.00% $250 $1,250

40.08.27.120150 TEMPORARY PAVEMENT MARKING 60.00 SF $3.50 $210 20.00% 10.00% 30.00% $63 $273

40.08.27.120161 TEMPORARY TRAFFIC STRIPE 3,600.00 LF $2.50 $9,000 20.00% 10.00% 30.00% $2,700 $11,700

40.08.27.128650 PORTABLE CHANGEABLE MESSAGE SIGN 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000

40.08.27.129000 TEMPORARY RAILING (TYPE K) 1,000.00 LF $17.00 $17,000 20.00% 10.00% 30.00% $5,100 $22,100

40.08.27.129110 TEMPORARY CRASH CUSHION 3.00 EA $4,000.00 $12,000 20.00% 10.00% 30.00% $3,600 $15,600

40.08.27.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500

40.08.27.992 SHORT-TERM TRAFFIC CONTROL 60.00DAY $605.00 $36,300 20.00% 20.00% 40.00% $14,520 $50,820

40.08.27.993 FLAGGER 60.00DAY $750.00 $45,000 15.00% 15.00% 30.00% $13,500 $58,500

Sum

Average

4,808.00 $130,510

17.78% 11.67% 29.44%

$42,233 $172,743Summary for Group: 40.08.27

Group 40.08.28

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LA JOLLA VILLAGE DR Contingency

40.08.28.120161 TEMPORARY TRAFFIC STRIPE 1,000.00 LF $2.50 $2,500 20.00% 10.00% 30.00% $750 $3,250

40.08.28.129000 TEMPORARY RAILING (TYPE K) 1,000.00 LF $17.00 $17,000 20.00% 10.00% 30.00% $5,100 $22,100

Monday, January 27, 2014 Page 97 of 140

Page 162: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

40.08.28.129110 TEMPORARY CRASH CUSHION 4.00 EA $4,000.00 $16,000 20.00% 10.00% 30.00% $4,800 $20,800

40.08.28.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250

40.08.28.992 SHORT-TERM TRAFFIC CONTROL 20.00DAY $605.00 $12,100 20.00% 20.00% 40.00% $4,840 $16,940

40.08.28.993 FLAGGER 20.00DAY $750.00 $15,000 15.00% 15.00% 30.00% $4,500 $19,500

Sum

Average

2,054.00 $65,100

19.17% 12.50% 31.67%

$20,740 $85,840Summary for Group: 40.08.28

Group 40.08.29

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MORENA BLVD Contingency

40.08.29.120090 CONSTRUCTION AREA SIGNS 10.00 EA $250.00 $2,500 15.00% 10.00% 25.00% $625 $3,125

40.08.29.120150 TEMPORARY PAVEMENT MARKING 320.00 SF $3.50 $1,120 20.00% 10.00% 30.00% $336 $1,456

40.08.29.120161 TEMPORARY TRAFFIC STRIPE 10,200.00 LF $2.50 $25,500 20.00% 10.00% 30.00% $7,650 $33,150

40.08.29.128650 PORTABLE CHANGEABLE MESSAGE SIGN 4.00 EA $5,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

40.08.29.129000 TEMPORARY RAILING (TYPE K) 8,600.00 LF $17.00 $146,200 20.00% 10.00% 30.00% $43,860 $190,060

40.08.29.129110 TEMPORARY CRASH CUSHION 3.00 EA $4,000.00 $12,000 20.00% 10.00% 30.00% $3,600 $15,600

40.08.29.991 TRAFFIC HANDING SIGNS 30.00 EA $250.00 $7,500 20.00% 10.00% 30.00% $2,250 $9,750

40.08.29.992 SHORT-TERM TRAFFIC CONTROL 300.00DAY $605.00 $181,500 20.00% 20.00% 40.00% $72,600 $254,100

40.08.29.993 FLAGGER 200.00DAY $750.00 $150,000 15.00% 15.00% 30.00% $45,000 $195,000

Sum

Average

19,667.00 $546,320

17.78% 11.67% 29.44%

$179,921 $726,241Summary for Group: 40.08.29

Group 40.08.31

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GILMAN DR Contingency

40.08.31.120090 CONSTRUCTION AREA SIGNS 6.00 EA $250.00 $1,500 15.00% 10.00% 25.00% $375 $1,875

40.08.31.120161 TEMPORARY TRAFFIC STRIPE 1,200.00 LF $2.50 $3,000 20.00% 10.00% 30.00% $900 $3,900

40.08.31.128650 PORTABLE CHANGEABLE MESSAGE SIGN 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000

40.08.31.129000 TEMPORARY RAILING (TYPE K) 1,100.00 LF $17.00 $18,700 20.00% 10.00% 30.00% $5,610 $24,310

40.08.31.129110 TEMPORARY CRASH CUSHION 1.00 EA $4,000.00 $4,000 20.00% 10.00% 30.00% $1,200 $5,200

40.08.31.158210 RESET TEMPORARY RAILING (TYPE K) 1,100.00 LF $4.00 $4,400 15.00% 10.00% 25.00% $1,100 $5,500

40.08.31.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250

40.08.31.992 SHORT-TERM TRAFFIC CONTROL 40.00DAY $605.00 $24,200 20.00% 20.00% 40.00% $9,680 $33,880

40.08.31.993 FLAGGER 40.00DAY $750.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

Monday, January 27, 2014 Page 98 of 140

Page 163: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

3,498.00 $93,300

17.22% 11.67% 28.89%

$29,615 $122,915Summary for Group: 40.08.31

Group 40.08.32

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROSE CANYON BIKE PATH Contingency

40.08.32.120090 CONSTRUCTION AREA SIGNS 5.00 EA $250.00 $1,250 15.00% 10.00% 25.00% $313 $1,563

40.08.32.991 TRAFFIC HANDING SIGNS 20.00 EA $250.00 $5,000 20.00% 10.00% 30.00% $1,500 $6,500

Sum

Average

25.00 $6,250

17.50% 10.00% 27.50%

$1,813 $8,063Summary for Group: 40.08.32

Group 40.08.33

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

OCEAN BEACH BIKE PATH Contingency

40.08.33.120150 TEMPORARY PAVEMENT MARKING 50.00 SF $3.50 $175 20.00% 10.00% 30.00% $53 $228

40.08.33.128650 PORTABLE CHANGEABLE MESSAGE SIGN 2.00 EA $5,000.00 $10,000 10.00% 10.00% 20.00% $2,000 $12,000

40.08.33.991 TRAFFIC HANDING SIGNS 10.00 EA $250.00 $2,500 20.00% 10.00% 30.00% $750 $3,250

40.08.33.994 SPECIAL HEIGHT LIMITATION WARNING TREATMENT FOR BIKE 2.00 EA $10,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

Sum

Average

64.00 $32,675

16.25% 11.25% 27.50%

$8,803 $41,478Summary for Group: 40.08.33

Group 40.08.34

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

OTHER BIKE LANE CLOSURES Contingency

40.08.34.128650 PORTABLE CHANGEABLE MESSAGE SIGN 10.00 EA $5,000.00 $50,000 10.00% 10.00% 20.00% $10,000 $60,000

40.08.34.991 TRAFFIC HANDING SIGNS 40.00 EA $250.00 $10,000 20.00% 10.00% 30.00% $3,000 $13,000

Sum

Average

50.00 $60,000

15.00% 10.00% 25.00%

$13,000 $73,000Summary for Group: 40.08.34

Group 40.08.35

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

UTILITY RELOCATIONS Contingency

40.08.35.992 SHORT-TERM TRAFFIC CONTROL 250.00DAY $605.00 $151,250 20.00% 20.00% 40.00% $60,500 $211,750

40.08.35.993 FLAGGER 250.00DAY $750.00 $187,500 15.00% 15.00% 30.00% $56,250 $243,750

Sum

Average

500.00 $338,750

17.50% 17.50% 35.00%

$116,750 $455,500Summary for Group: 40.08.35

Group 40.08.36

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

ROADWAYS S. OF OLD TOWN Contingency

40.08.36.992 SHORT-TERM TRAFFIC CONTROL 10.00DAY $605.00 $6,050 20.00% 20.00% 40.00% $2,420 $8,470

40.08.36.993 FLAGGER 10.00DAY $750.00 $7,500 15.00% 15.00% 30.00% $2,250 $9,750

Sum

Average

20.00 $13,550

17.50% 17.50% 35.00%

$4,670 $18,220Summary for Group: 40.08.36

Monday, January 27, 2014 Page 99 of 140

Page 164: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Group 40.08.40

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TEMPORARY BMP (2%) Contingency

40.08.40 TEMPORARY BMP (2%) 1.00 LS $11,288,709.10 $11,288,709 0.00% 30.00% 30.00% $3,386,613 $14,675,322

Sum

Average

1.00 $11,288,709

0.00% 30.00% 30.00%

$3,386,613 $14,675,322Summary for Group: 40.08.40

Sum

Average

335,218.00 $66,058,008

17.29% 11.92% 29.21%

$10,522,630 $76,580,638Summary for Sub Section: 40.08

Sum

Average

5,518,879.63 $155,510,710

13.18% 10.63% 23.81%

$32,383,100 $187,893,811Summary for Section 40

Section 50 SYSTEMS

Sub Section 50.01 TRAIN CONTROL AND SIGNALS

Group 50.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TRAIN CONTROL AND SIGNALS Contingency

50.01.00 TEMPORARY RELOCATION OF SIGNAL (SHOOFLY) 1.00 LS $1,300,000.00 $1,300,000 0.00% 10.00% 10.00% $130,000 $1,430,000

50.01.01 ASH STREET 1.00 LS $260,000.00 $260,000 15.00% 10.00% 25.00% $65,000 $325,000

50.01.02 BEECH STREET 1.00 LS $260,000.00 $260,000 15.00% 10.00% 25.00% $65,000 $325,000

50.01.03 CEDAR STREET - ABS SIGNAL O045 1.00 LS $303,000.00 $303,000 15.00% 10.00% 25.00% $75,750 $378,750

50.01.05 ABS SIGNALS O086, O087, O088, O089 1.00 LS $456,000.00 $456,000 15.00% 10.00% 25.00% $114,000 $570,000

50.01.06 PALM STREET - ABS SIGNALS O121, O123 1.00 LS $328,000.00 $328,000 15.00% 10.00% 25.00% $82,000 $410,000

50.01.07 INTERLOCKING - O6 1.00 LS $1,151,000.00 $1,151,000 15.00% 10.00% 25.00% $287,750 $1,438,750

50.01.08 SASSAFRAS STREET - ABS SIGNALS O161, O162 1.00 LS $466,000.00 $466,000 15.00% 10.00% 25.00% $116,500 $582,500

50.01.09 ABS SIGNALS O191, O192, O193 1.00 LS $447,000.00 $447,000 15.00% 10.00% 25.00% $111,750 $558,750

50.01.10 WASHINGTON STREET 1.00 LS $366,000.00 $366,000 15.00% 10.00% 25.00% $91,500 $457,500

50.01.11 NOELL STREET - ABS SIGNALS O224, O225, O226 1.00 LS $476,000.00 $476,000 15.00% 10.00% 25.00% $119,000 $595,000

50.01.12 ABS SIGNALS O257, O258, O259 1.00 LS $447,000.00 $447,000 15.00% 10.00% 25.00% $111,750 $558,750

50.01.13 ABS SIGNAL O296, O297 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

50.01.14 INTERLOCKING O14 1.00 LS $650,000.00 $650,000 15.00% 10.00% 25.00% $162,500 $812,500

50.01.15 INTERLOCKING 018 1.00 LS $650,000.00 $650,000 15.00% 10.00% 25.00% $162,500 $812,500

50.01.16 TAYLOR STREET 1.00 LS $366,000.00 $366,000 15.00% 10.00% 25.00% $91,500 $457,500

50.01.17 ABS SIGNAL M391 CHANGES 1.00 LS $53,000.00 $53,000 15.00% 10.00% 25.00% $13,250 $66,250

50.01.18 ABS SIGNAL M404, M405 1.00 LS $428,000.00 $428,000 15.00% 10.00% 25.00% $107,000 $535,000

Monday, January 27, 2014 Page 100 of 140

Page 165: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.01.19 INTERLOCKING O22 1.00 LS $1,286,000.00 $1,286,000 15.00% 10.00% 25.00% $321,500 $1,607,500

50.01.20 ABS SIGNALS O402, O403, O 404, O405 1.00 LS $456,000.00 $456,000 15.00% 10.00% 25.00% $114,000 $570,000

50.01.21 INTERLOCKING O26 1.00 LS $1,058,000.00 $1,058,000 15.00% 10.00% 25.00% $264,500 $1,322,500

50.01.22 ABS SIGNALS O452, O454 1.00 LS $402,000.00 $402,000 15.00% 10.00% 25.00% $100,500 $502,500

50.01.23 ABS SIGNALS O524, O525, O526, O527 1.00 LS $417,000.00 $417,000 15.00% 10.00% 25.00% $104,250 $521,250

50.01.24 ABS SIGNALS O585, O587 1.00 LS $402,000.00 $402,000 15.00% 10.00% 25.00% $100,500 $502,500

50.01.25 INTERLOCKING O34 1.00 LS $1,118,000.00 $1,118,000 15.00% 10.00% 25.00% $279,500 $1,397,500

50.01.26 ABS SIGNALS O663, O664, O665, O666 1.00 LS $417,000.00 $417,000 15.00% 10.00% 25.00% $104,250 $521,250

50.01.27 ABS SIGNALS 0707, 0709 1.00 LS $402,000.00 $402,000 15.00% 10.00% 25.00% $100,500 $502,500

50.01.28 INTERLOCKING O38 1.00 LS $1,058,000.00 $1,058,000 15.00% 10.00% 25.00% $264,500 $1,322,500

50.01.29 ABS SIGNALS O791, O792, O793, O794 1.00 LS $417,000.00 $417,000 15.00% 10.00% 25.00% $104,250 $521,250

50.01.30 ABS SIGNALS O861, O862, O863, O864 1.00 LS $417,000.00 $417,000 15.00% 10.00% 25.00% $104,250 $521,250

50.01.31 INTERLOCKING O46 1.00 LS $1,058,000.00 $1,058,000 15.00% 10.00% 25.00% $264,500 $1,322,500

50.01.32 ABS SIGNAL O1035, O1036, O1037 1.00 LS $414,000.00 $414,000 15.00% 10.00% 25.00% $103,500 $517,500

50.01.33 ABS SIGNALS O1121, O1122 1.00 LS $402,000.00 $402,000 15.00% 10.00% 25.00% $100,500 $502,500

50.01.34 ABS SIGNALS O1132 1.00 LS $429,000.00 $429,000 15.00% 10.00% 25.00% $107,250 $536,250

50.01.35 ABS SIGNALS O1171, O1173 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

50.01.36 INTERLOCKING O54 1.00 LS $1,211,000.00 $1,211,000 15.00% 10.00% 25.00% $302,750 $1,513,750

50.01.37 ABS SIGNALS O1221, O1223 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

50.01.38 ABS SIGNALS O1232, O1234 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

50.01.39 ABS SIGNALS O1246, O1247 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

50.01.40 ABS SIGNALS O1257, O1259 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

50.01.41 ABS SIGNALS O1268, O1270 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

50.01.42 INTERLOCKING O58 1.00 LS $1,151,000.00 $1,151,000 15.00% 10.00% 25.00% $287,750 $1,438,750

50.01.43 ABS SIGNALS O1319, O1321 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

50.01.44 INTERLOCKING O62 1.00 LS $1,151,000.00 $1,151,000 15.00% 10.00% 25.00% $287,750 $1,438,750

50.01.45 ABS SIGNALS O1371, O1372, O1374 1.00 LS $447,000.00 $447,000 15.00% 10.00% 25.00% $111,750 $558,750

50.01.46 ABS SIGNALS O1395, O1396, O1397 1.00 LS $447,000.00 $447,000 15.00% 10.00% 25.00% $111,750 $558,750

50.01.47 ABS SIGNALS O1411, O1413 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

Monday, January 27, 2014 Page 101 of 140

Page 166: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.01.48 INTERLOCKING O66 1.00 LS $1,001,000.00 $1,001,000 15.00% 10.00% 25.00% $250,250 $1,251,250

50.01.49 INTERLOCKING O66 REMOTE 1.00 LS $438,000.00 $438,000 15.00% 10.00% 25.00% $109,500 $547,500

50.01.50 ABS SIGNALS O1454, O1455, O1456, O1457 1.00 LS $456,000.00 $456,000 15.00% 10.00% 25.00% $114,000 $570,000

50.01.51 CONTINGENCY FOR INTERLOCKING O8 1.00 LS $1,035,000.00 $1,035,000 0.00% 0.00% 0.00% $0 $1,035,000

Sum

Average

51.00 $29,839,000

14.41% 9.80% 24.22%

$7,006,000 $36,845,000Summary for Group: 50.01

Group 50.01.100

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TRAIN CONTROL AND SIGNALS (INFRASTRUCTURE) Contingency

50.01.100.01 PLATFORM (SIGNAL HOUSE AT RETAINING WALL) 1.00 LS $189,000.00 $189,000 15.00% 10.00% 25.00% $47,250 $236,250

50.01.100.02 PLATFORM (HOUSE AT BRIDGE) 1.00 LS $244,800.00 $244,800 15.00% 10.00% 25.00% $61,200 $306,000

50.01.100.03 PLATFORM (SIGNAL AT BRIDGE) 1.00 LS $63,000.00 $63,000 15.00% 10.00% 25.00% $15,750 $78,750

Sum

Average

3.00 $496,800

15.00% 10.00% 25.00%

$124,200 $621,000Summary for Group: 50.01.100

Sum

Average

54.00 $30,335,800

14.44% 9.81% 24.26%

$7,130,200 $37,466,000Summary for Sub Section: 50.01

Sub Section 50.02 TRAFFIC SIGNALS AND CROSSING PROTECTION

Group 50.02.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CEDAR/KETTNER TRAFFIC SIGNAL Contingency

50.02.01.2 SIGNAL MODIFICATION 1.00 LS $195,000.00 $195,000 0.00% 25.00% 25.00% $48,750 $243,750

Sum

Average

1.00 $195,000

0.00% 25.00% 25.00%

$48,750 $243,750Summary for Group: 50.02.01

Group 50.02.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CEDAR/PACIFIC HWY TRAFFIC SIGNAL Contingency

50.02.02.2 SIGNAL MODIFICATION 1.00 LS $75,000.00 $75,000 0.00% 25.00% 25.00% $18,750 $93,750

Sum

Average

1.00 $75,000

0.00% 25.00% 25.00%

$18,750 $93,750Summary for Group: 50.02.02

Group 50.02.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SASSAFRAS/PACIFIC HWY TRAFFIC SIGNALS Contingency

50.02.03.2 SIGNAL MODIFICATION 1.00 LS $75,000.00 $75,000 0.00% 25.00% 25.00% $18,750 $93,750

Sum

Average

1.00 $75,000

0.00% 25.00% 25.00%

$18,750 $93,750Summary for Group: 50.02.03

Group 50.02.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PACIFIC HWY/TAYLOR TRAFFIC SIGNAL Contingency

50.02.04.2 SIGNAL MODIFICATION 1.00 LS $220,000.00 $220,000 0.00% 25.00% 25.00% $55,000 $275,000

Monday, January 27, 2014 Page 102 of 140

Page 167: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

1.00 $220,000

0.00% 25.00% 25.00%

$55,000 $275,000Summary for Group: 50.02.04

Group 50.02.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

W. MORENA/VEGA TRAFFIC SIGNAL Contingency

50.02.05.2 SIGNAL MODIFICATION 1.00 LS $85,000.00 $85,000 0.00% 25.00% 25.00% $21,250 $106,250

Sum

Average

1.00 $85,000

0.00% 25.00% 25.00%

$21,250 $106,250Summary for Group: 50.02.05

Group 50.02.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MORENA/INGULF TRAFFIC SIGNAL Contingency

50.02.06.2 SIGNAL MODIFICATION 1.00 LS $105,000.00 $105,000 0.00% 25.00% 25.00% $26,250 $131,250

Sum

Average

1.00 $105,000

0.00% 25.00% 25.00%

$26,250 $131,250Summary for Group: 50.02.06

Group 50.02.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MORENA/GESNER TRAFFIC SIGNAL Contingency

50.02.07.2 SIGNAL MODIFICATION 1.00 LS $115,000.00 $115,000 0.00% 25.00% 25.00% $28,750 $143,750

Sum

Average

1.00 $115,000

0.00% 25.00% 25.00%

$28,750 $143,750Summary for Group: 50.02.07

Group 50.02.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

MORENA/BALBOA TRAFFIC SIGNAL Contingency

50.02.08.1 NEW TRAFFIC SIGNAL 1.00 LS $225,000.00 $225,000 0.00% 25.00% 25.00% $56,250 $281,250

50.02.08.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $150,000.00 $150,000 0.00% 25.00% 25.00% $37,500 $187,500

Sum

Average

2.00 $375,000

0.00% 25.00% 25.00%

$93,750 $468,750Summary for Group: 50.02.08

Group 50.02.09

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

BALBOA STATION BUS ACCESS TRAFFIC SIGNAL Contingency

50.02.09.1 NEW TRAFFIC SIGNAL 1.00 LS $195,000.00 $195,000 0.00% 25.00% 25.00% $48,750 $243,750

Sum

Average

1.00 $195,000

0.00% 25.00% 25.00%

$48,750 $243,750Summary for Group: 50.02.09

Group 50.02.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

NOBEL/I-5 TRAFFIC SIGNAL Contingency

50.02.10.2 SIGNAL MODIFICATION 1.00 LS $115,000.00 $115,000 0.00% 25.00% 25.00% $28,750 $143,750

50.02.10.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $150,000.00 $150,000 0.00% 25.00% 25.00% $37,500 $187,500

Sum

Average

2.00 $265,000

0.00% 25.00% 25.00%

$66,250 $331,250Summary for Group: 50.02.10

Monday, January 27, 2014 Page 103 of 140

Page 168: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Group 50.02.11

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LA JOLLA COLONY/I-5 TRAFFIC SIGNAL Contingency

50.02.11.2 SIGNAL MODIFICATION 1.00 LS $140,000.00 $140,000 0.00% 25.00% 25.00% $35,000 $175,000

50.02.11.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000

Sum

Average

2.00 $440,000

0.00% 25.00% 25.00%

$110,000 $550,000Summary for Group: 50.02.11

Group 50.02.12

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

VOIGT/CAMPUS POINT TRAFFIC SIGNAL Contingency

50.02.12.2 SIGNAL MODIFICAITON 1.00 LS $155,000.00 $155,000 0.00% 25.00% 25.00% $38,750 $193,750

50.02.12.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000

Sum

Average

2.00 $455,000

0.00% 25.00% 25.00%

$113,750 $568,750Summary for Group: 50.02.12

Group 50.02.13

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE/CAMPUS POINT TRAFFIC SIGNAL Contingency

50.02.13.2 SIGNAL MODIFICATION 1.00 LS $60,000.00 $60,000 0.00% 25.00% 25.00% $15,000 $75,000

Sum

Average

1.00 $60,000

0.00% 25.00% 25.00%

$15,000 $75,000Summary for Group: 50.02.13

Group 50.02.14

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE/REGENTS TRAFFIC SIGNAL Contingency

50.02.14.2 SIGNAL MODIFICATION 1.00 LS $165,000.00 $165,000 0.00% 25.00% 25.00% $41,250 $206,250

50.02.14.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $150,000.00 $150,000 0.00% 25.00% 25.00% $37,500 $187,500

Sum

Average

2.00 $315,000

0.00% 25.00% 25.00%

$78,750 $393,750Summary for Group: 50.02.14

Group 50.02.15

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE/EASTGATE MALL TRAFFIC SIGNAL Contingency

50.02.15.2 SIGNAL MODIFICATION 1.00 LS $265,000.00 $265,000 0.00% 25.00% 25.00% $66,250 $331,250

50.02.15.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000

Sum

Average

2.00 $565,000

0.00% 25.00% 25.00%

$141,250 $706,250Summary for Group: 50.02.15

Group 50.02.16

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE/EXECUTIVE DR TRAFFIC SIGNAL Contingency

50.02.16.2 SIGNAL MODIFICATION 1.00 LS $265,000.00 $265,000 0.00% 25.00% 25.00% $66,250 $331,250

50.02.16.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000

Monday, January 27, 2014 Page 104 of 140

Page 169: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

2.00 $565,000

0.00% 25.00% 25.00%

$141,250 $706,250Summary for Group: 50.02.16

Group 50.02.17

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE/EXECUTIVE SQ TRAFFIC SIGNAL Contingency

50.02.17.2 SIGNAL MODIFICATION 1.00 LS $265,000.00 $265,000 0.00% 25.00% 25.00% $66,250 $331,250

50.02.17.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000

Sum

Average

2.00 $565,000

0.00% 25.00% 25.00%

$141,250 $706,250Summary for Group: 50.02.17

Group 50.02.18

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE/LA JOLLA VILLAGE TRAFFIC SIGNAL Contingency

50.02.18.2 SIGNAL MODIFICATION 1.00 LS $370,000.00 $370,000 0.00% 25.00% 25.00% $92,500 $462,500

50.02.18.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000

Sum

Average

2.00 $670,000

0.00% 25.00% 25.00%

$167,500 $837,500Summary for Group: 50.02.18

Group 50.02.19

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE/ESPLANADE TRAFFIC SIGNAL Contingency

50.02.19.2 SIGNAL MODIFICATION 1.00 LS $275,000.00 $275,000 0.00% 25.00% 25.00% $68,750 $343,750

50.02.19.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $300,000.00 $300,000 0.00% 25.00% 25.00% $75,000 $375,000

Sum

Average

2.00 $575,000

0.00% 25.00% 25.00%

$143,750 $718,750Summary for Group: 50.02.19

Group 50.02.20

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

GENESEE/NOBEL TRAFFIC SIGNAL Contingency

50.02.20.2 SIGNAL MODIFICATION 1.00 LS $80,000.00 $80,000 0.00% 25.00% 25.00% $20,000 $100,000

50.02.20.3 TEMP. SIGNAL MODIFICATION (DURING CONST) 1.00 LS $150,000.00 $150,000 0.00% 25.00% 25.00% $37,500 $187,500

Sum

Average

2.00 $230,000

0.00% 25.00% 25.00%

$57,500 $287,500Summary for Group: 50.02.20

Sum

Average

31.00 $6,145,000

0.00% 25.00% 25.00%

$1,536,250 $7,681,250Summary for Sub Section: 50.02

Sub Section 50.03 TRACTION POWER SUBSTATIONS

Group 50.03.012

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATIONS 1 & 2 Contingency

50.03.012.01 CLEARING AND GRUBBING 0.13 AC $4,022.00 $523 10.00% 15.00% 25.00% $131 $654

50.03.012.02 REMOVE EXIST TPSS 1.00 EA $14,758.00 $14,758 0.00% 15.00% 15.00% $2,214 $16,972

50.03.012.04 REMOVE EXIST CL FENCE 48.00 LF $2.20 $106 15.00% 15.00% 30.00% $32 $137

Monday, January 27, 2014 Page 105 of 140

Page 170: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.012.05 REMOVE EXIST GATE 1.00 EA $42.00 $42 15.00% 15.00% 30.00% $13 $55

50.03.012.08 REMOVE EXIST POLE FOUNDATION 2.00 EA $913.00 $1,826 15.00% 15.00% 30.00% $548 $2,374

50.03.012.09 ROADWAY EXCAVATION 475.00 CY $28.00 $13,300 10.00% 15.00% 25.00% $3,325 $16,625

50.03.012.10 HAUL AND DISPOSE 545.00 CY $0.00 $0 15.00% 15.00% 30.00% $0 $0

50.03.012.100 UPGRADE POWER TO SUBSTATION 1.00 LS $200,000.00 $200,000 0.00% 30.00% 30.00% $60,000 $260,000

50.03.012.13 CONCRETE PAD 48.00 CY $571.00 $27,408 15.00% 15.00% 30.00% $8,222 $35,630

50.03.012.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 15.00% 15.00% 30.00% $723 $3,133

50.03.012.16 HOT MIX ASPHALT (TYPE A) 2.00TON $102.00 $204 10.00% 10.00% 20.00% $41 $245

50.03.012.18 TPSS STAIRS AND LANDING 165.00 SF $24.00 $3,960 10.00% 15.00% 25.00% $990 $4,950

50.03.012.19 CLASS 2 AGGREGATE BASE 22.00 CY $45.00 $990 10.00% 10.00% 20.00% $198 $1,188

50.03.012.23 10' CL FENCE W/BARBED WIRE 66.00 LF $43.00 $2,838 15.00% 15.00% 30.00% $851 $3,689

50.03.012.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 15.00% 15.00% 30.00% $1,175 $5,090

50.03.012.27 CRUSHED ROCK 63.00 CY $45.00 $2,835 15.00% 15.00% 30.00% $851 $3,686

50.03.012.50 TPSS (1500kW) 2.00 EA $800,000.00 $1,600,000 0.00% 15.00% 15.00% $240,000 $1,840,000

50.03.012.54 #4/0 BARE COPPER WIRE 1,200.00 LF $1.80 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.03.012.55 COPPER GROUND RODS 28.00 EA $250.00 $7,000 15.00% 15.00% 30.00% $2,100 $9,100

50.03.012.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 2.00 EA $20,000.00 $40,000 10.00% 15.00% 25.00% $10,000 $50,000

50.03.012.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 2.00 EA $20,000.00 $40,000 15.00% 15.00% 30.00% $12,000 $52,000

50.03.012.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 2.00 EA $13,500.00 $27,000 15.00% 15.00% 30.00% $8,100 $35,100

50.03.012.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 2.00 EA $20,000.00 $40,000 15.00% 15.00% 30.00% $12,000 $52,000

50.03.012.62 POSITIVE DC FEEDER - 1/C 500 kcmil 6,300.00 LF $31.00 $195,300 10.00% 15.00% 25.00% $48,825 $244,125

50.03.012.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 2,100.00 LF $31.00 $65,100 10.00% 15.00% 25.00% $16,275 $81,375

50.03.012.65 POSITIVE DUCTBANK (6 - 4" PVC) 5,970.00 LF $161.00 $961,170 10.00% 15.00% 25.00% $240,293 $1,201,463

50.03.012.66 NEGATIVE DUCTBANK (4 - 4" PVC) 1,200.00 LF $161.00 $193,200 10.00% 15.00% 25.00% $48,300 $241,500

50.03.012.71 GENERAL SERVICE LIGHTING 5,663.00 SF $20.00 $113,260 15.00% 15.00% 30.00% $33,978 $147,238

Sum

Average

26,321.13 $3,559,304

11.61% 15.18% 26.79%

$751,831 $4,311,135Summary for Group: 50.03.012

Group 50.03.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 3 Contingency

50.03.03.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 15.00% 25.00% $70 $352

Monday, January 27, 2014 Page 106 of 140

Page 171: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.03.02 REMOVE EXIST TPSS 1.00 EA $14,758.00 $14,758 0.00% 15.00% 15.00% $2,214 $16,972

50.03.03.04 REMOVE EXIST CL FENCE 76.00 LF $2.20 $167 15.00% 15.00% 30.00% $50 $217

50.03.03.05 REMOVE EXIST GATE 1.00 EA $42.00 $42 15.00% 15.00% 30.00% $13 $55

50.03.03.08 REMOVE EXIST POLE FOUNDATION 2.00 EA $913.00 $1,826 15.00% 15.00% 30.00% $548 $2,374

50.03.03.100 UPGRADE POWER TO SUBSTATION 1.00 LS $200,000.00 $200,000 0.00% 30.00% 30.00% $60,000 $260,000

50.03.03.11 ROADWAY EMBANKMENT 742.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.03.13 CONCRETE PAD 24.00 CY $571.00 $13,704 15.00% 15.00% 30.00% $4,111 $17,815

50.03.03.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 15.00% 15.00% 30.00% $723 $3,133

50.03.03.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.03.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 15.00% 25.00% $492 $2,460

50.03.03.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.03.23 10' CL FENCE W/BARBED WIRE 152.00 LF $43.00 $6,536 15.00% 15.00% 30.00% $1,961 $8,497

50.03.03.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 15.00% 15.00% 30.00% $1,175 $5,090

50.03.03.27 CRUSHED ROCK 37.00 CY $45.00 $1,665 15.00% 15.00% 30.00% $500 $2,165

50.03.03.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 15.00% 15.00% $120,000 $920,000

50.03.03.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.03.03.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 15.00% 15.00% 30.00% $1,050 $4,550

50.03.03.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 15.00% 25.00% $5,000 $25,000

50.03.03.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.03.03.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 15.00% 15.00% 30.00% $4,050 $17,550

50.03.03.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.03.03.62 POSITIVE DC FEEDER - 1/C 500 kcmil 1,236.00 LF $31.00 $38,316 10.00% 15.00% 25.00% $9,579 $47,895

50.03.03.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,050.00 LF $31.00 $32,550 10.00% 15.00% 25.00% $8,138 $40,688

50.03.03.65 POSITIVE DUCTBANK (6 - 4" PVC) 1,086.00 LF $161.00 $174,846 10.00% 15.00% 25.00% $43,712 $218,558

50.03.03.66 NEGATIVE DUCTBANK (4 - 4" PVC) 600.00 LF $161.00 $96,600 10.00% 15.00% 25.00% $24,150 $120,750

50.03.03.71 GENERAL SERVICE LIGHTING 2,614.00 SF $20.00 $52,280 15.00% 15.00% 30.00% $15,684 $67,964

Sum

Average

10,746.07 $1,520,542

11.48% 15.00% 26.48%

$315,661 $1,836,203Summary for Group: 50.03.03

Group 50.03.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 4 Contingency

Monday, January 27, 2014 Page 107 of 140

Page 172: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.04.09 ROADWAY EXCAVATION 176.00 CY $28.00 $4,928 10.00% 15.00% 25.00% $1,232 $6,160

50.03.04.10 HAUL AND DISPOSE 202.00 CY $0.00 $0 15.00% 15.00% 30.00% $0 $0

50.03.04.100 UPGRADE POWER TO SUBSTATION 1.00 LS $200,000.00 $200,000 0.00% 30.00% 30.00% $60,000 $260,000

50.03.04.13 CONCRETE PAD 24.00 CY $571.00 $13,704 15.00% 15.00% 30.00% $4,111 $17,815

50.03.04.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 15.00% 15.00% 30.00% $723 $3,133

50.03.04.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.04.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 15.00% 25.00% $492 $2,460

50.03.04.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.04.23 10' CL FENCE W/BARBED WIRE 208.00 LF $43.00 $8,944 15.00% 15.00% 30.00% $2,683 $11,627

50.03.04.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 15.00% 15.00% 30.00% $1,175 $5,090

50.03.04.27 CRUSHED ROCK 39.00 CY $45.00 $1,755 15.00% 15.00% 30.00% $527 $2,282

50.03.04.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 15.00% 15.00% $120,000 $920,000

50.03.04.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.03.04.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 15.00% 15.00% 30.00% $1,050 $4,550

50.03.04.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 15.00% 25.00% $5,000 $25,000

50.03.04.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.03.04.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 15.00% 15.00% 30.00% $4,050 $17,550

50.03.04.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.03.04.62 POSITIVE DC FEEDER - 1/C 500 kcmil 1,680.00 LF $31.00 $52,080 10.00% 15.00% 25.00% $13,020 $65,100

50.03.04.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,050.00 LF $31.00 $32,550 10.00% 15.00% 25.00% $8,138 $40,688

50.03.04.65 POSITIVE DUCTBANK (6 - 4" PVC) 1,530.00 LF $161.00 $246,330 10.00% 15.00% 25.00% $61,583 $307,913

50.03.04.66 NEGATIVE DUCTBANK (4 - 4" PVC) 600.00 LF $161.00 $96,600 10.00% 15.00% 25.00% $24,150 $120,750

50.03.04.71 GENERAL SERVICE LIGHTING 2,614.00 SF $20.00 $52,280 15.00% 15.00% 30.00% $15,684 $67,964

Sum

Average

11,248.00 $1,596,141

11.74% 15.22% 26.96%

$336,060 $1,932,201Summary for Group: 50.03.04

Group 50.03.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 5 Contingency

50.03.05.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338

50.03.05.09 ROADWAY EXCAVATION 42.00 CY $28.00 $1,176 10.00% 10.00% 20.00% $235 $1,411

50.03.05.10 HAUL AND DISPOSE 12.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

Monday, January 27, 2014 Page 108 of 140

Page 173: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.05.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

50.03.05.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.05.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.05.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.05.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.05.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.05.23 10' CL FENCE W/BARBED WIRE 208.00 LF $43.00 $8,944 10.00% 10.00% 20.00% $1,789 $10,733

50.03.05.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.05.27 CRUSHED ROCK 39.00 CY $45.00 $1,755 10.00% 10.00% 20.00% $351 $2,106

50.03.05.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.05.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.05.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.05.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.05.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.05.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.05.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.05.62 POSITIVE DC FEEDER - 1/C 500 kcmil 8,430.00 LF $31.00 $261,330 10.00% 10.00% 20.00% $52,266 $313,596

50.03.05.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 960.00 LF $31.00 $29,760 10.00% 10.00% 20.00% $5,952 $35,712

50.03.05.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 4,220.00 LF $8.50 $35,870 10.00% 10.00% 20.00% $7,174 $43,044

50.03.05.65 POSITIVE DUCTBANK (6 - 4" PVC) 4,775.00 LF $161.00 $768,775 10.00% 10.00% 20.00% $153,755 $922,530

50.03.05.66 NEGATIVE DUCTBANK (4 - 4" PVC) 620.00 LF $161.00 $99,820 10.00% 10.00% 20.00% $19,964 $119,784

50.03.05.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 4,210.00 LF $112.00 $471,520 10.00% 10.00% 20.00% $94,304 $565,824

50.03.05.71 GENERAL SERVICE LIGHTING 14,810.00 SF $20.00 $296,200 15.00% 15.00% 30.00% $88,860 $385,060

Sum

Average

41,475.07 $3,176,106

9.42% 10.58% 20.00%

$584,841 $3,760,947Summary for Group: 50.03.05

Group 50.03.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 6 Contingency

50.03.06.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338

50.03.06.09 ROADWAY EXCAVATION 35.00 CY $28.00 $980 10.00% 10.00% 20.00% $196 $1,176

50.03.06.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

Monday, January 27, 2014 Page 109 of 140

Page 174: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.06.11 ROADWAY EMBANKMENT 23.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.06.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.06.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.06.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 2.00 EA $5,000.00 $10,000 10.00% 10.00% 20.00% $2,000 $12,000

50.03.06.16 HOT MIX ASPHALT (TYPE A) 9.00TON $102.00 $918 10.00% 10.00% 20.00% $184 $1,102

50.03.06.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.06.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.06.25 10' PICKET FENCE W/BARBED WIRE 194.00 LF $100.00 $19,400 10.00% 10.00% 20.00% $3,880 $23,280

50.03.06.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.06.27 CRUSHED ROCK 33.00 CY $45.00 $1,485 10.00% 10.00% 20.00% $297 $1,782

50.03.06.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.06.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.06.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.06.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.06.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.06.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.06.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.06.62 POSITIVE DC FEEDER - 1/C 500 kcmil 3,360.00 LF $31.00 $104,160 10.00% 10.00% 20.00% $20,832 $124,992

50.03.06.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,050.00 LF $31.00 $32,550 10.00% 10.00% 20.00% $6,510 $39,060

50.03.06.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 7,495.00 LF $8.50 $63,708 10.00% 10.00% 20.00% $12,742 $76,449

50.03.06.65 POSITIVE DUCTBANK (6 - 4" PVC) 1,590.00 LF $161.00 $255,990 10.00% 10.00% 20.00% $51,198 $307,188

50.03.06.66 NEGATIVE DUCTBANK (4 - 4" PVC) 600.00 LF $161.00 $96,600 10.00% 10.00% 20.00% $19,320 $115,920

50.03.06.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 7,485.00 LF $112.00 $838,320 10.00% 10.00% 20.00% $167,664 $1,005,984

50.03.06.71 GENERAL SERVICE LIGHTING 2,614.00 SF $20.00 $52,280 15.00% 15.00% 30.00% $15,684 $67,964

Sum

Average

27,638.07 $2,677,244

9.44% 10.56% 20.00%

$460,677 $3,137,921Summary for Group: 50.03.06

Group 50.03.078

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATIONS 7 & 8 Contingency

50.03.078.01 CLEARING AND GRUBBING 0.14 AC $4,022.00 $563 10.00% 10.00% 20.00% $113 $676

50.03.078.04 REMOVE EXIST CL FENCE 331.00 LF $2.20 $728 10.00% 10.00% 20.00% $146 $874

Monday, January 27, 2014 Page 110 of 140

Page 175: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.078.06 REMOVE EXIST STORM DRAIN 107.00 LF $37.00 $3,959 10.00% 10.00% 20.00% $792 $4,751

50.03.078.09 ROADWAY EXCAVATION 476.00 CY $28.00 $13,328 10.00% 10.00% 20.00% $2,666 $15,994

50.03.078.10 HAUL AND DISPOSE 514.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.078.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

50.03.078.12 RETAINING WALL (TYPE H) 1,401.00 SF $117.00 $163,917 10.00% 10.00% 20.00% $32,783 $196,700

50.03.078.13 CONCRETE PAD 48.00 CY $571.00 $27,408 10.00% 10.00% 20.00% $5,482 $32,890

50.03.078.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.078.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000

50.03.078.16 HOT MIX ASPHALT (TYPE A) 2.00TON $102.00 $204 10.00% 10.00% 20.00% $41 $245

50.03.078.18 TPSS STAIRS AND LANDING 165.00 SF $24.00 $3,960 10.00% 10.00% 20.00% $792 $4,752

50.03.078.19 CLASS 2 AGGREGATE BASE 22.00 CY $45.00 $990 10.00% 10.00% 20.00% $198 $1,188

50.03.078.22 6' CL FENCE W/BARBED WIRE 180.00 LF $43.00 $7,740 10.00% 10.00% 20.00% $1,548 $9,288

50.03.078.25 10' PICKET FENCE W/BARBED WIRE 122.00 LF $100.00 $12,200 10.00% 10.00% 20.00% $2,440 $14,640

50.03.078.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.078.27 CRUSHED ROCK 71.00 CY $45.00 $3,195 10.00% 10.00% 20.00% $639 $3,834

50.03.078.50 TPSS (1500kW) 2.00 EA $800,000.00 $1,600,000 0.00% 10.00% 10.00% $160,000 $1,760,000

50.03.078.54 #4/0 BARE COPPER WIRE 1,200.00 LF $1.80 $2,160 10.00% 10.00% 20.00% $432 $2,592

50.03.078.55 COPPER GROUND RODS 28.00 EA $250.00 $7,000 10.00% 10.00% 20.00% $1,400 $8,400

50.03.078.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 2.00 EA $20,000.00 $40,000 10.00% 10.00% 20.00% $8,000 $48,000

50.03.078.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 2.00 EA $20,000.00 $40,000 10.00% 10.00% 20.00% $8,000 $48,000

50.03.078.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 2.00 EA $13,500.00 $27,000 10.00% 10.00% 20.00% $5,400 $32,400

50.03.078.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 2.00 EA $20,000.00 $40,000 10.00% 10.00% 20.00% $8,000 $48,000

50.03.078.62 POSITIVE DC FEEDER - 1/C 500 kcmil 14,130.00 LF $31.00 $438,030 10.00% 10.00% 20.00% $87,606 $525,636

50.03.078.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 2,520.00 LF $31.00 $78,120 10.00% 10.00% 20.00% $15,624 $93,744

50.03.078.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 8,955.00 LF $8.50 $76,118 10.00% 10.00% 20.00% $15,224 $91,341

50.03.078.65 POSITIVE DUCTBANK (6 - 4" PVC) 6,765.00 LF $161.00 $1,089,165 10.00% 10.00% 20.00% $217,833 $1,306,998

50.03.078.66 NEGATIVE DUCTBANK (4 - 4" PVC) 2,000.00 LF $161.00 $322,000 10.00% 10.00% 20.00% $64,400 $386,400

50.03.078.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 8,935.00 LF $112.00 $1,000,720 10.00% 10.00% 20.00% $200,144 $1,200,864

50.03.078.71 GENERAL SERVICE LIGHTING 5,663.00 SF $20.00 $113,260 15.00% 15.00% 30.00% $33,978 $147,238

Monday, January 27, 2014 Page 111 of 140

Page 176: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

56,058.14 $5,423,090

9.52% 10.48% 20.00%

$935,944 $6,359,034Summary for Group: 50.03.078

Group 50.03.09

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 9 Contingency

50.03.09.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338

50.03.09.09 ROADWAY EXCAVATION 124.00 CY $28.00 $3,472 10.00% 10.00% 20.00% $694 $4,166

50.03.09.10 HAUL AND DISPOSE 143.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.09.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

50.03.09.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.09.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.09.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.09.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.09.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.09.23 10' CL FENCE W/BARBED WIRE 198.00 LF $43.00 $8,514 10.00% 10.00% 20.00% $1,703 $10,217

50.03.09.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.09.27 CRUSHED ROCK 35.00 CY $45.00 $1,575 10.00% 10.00% 20.00% $315 $1,890

50.03.09.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.09.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.09.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.09.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.09.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.09.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.09.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.09.62 POSITIVE DC FEEDER - 1/C 500 kcmil 4,560.00 LF $31.00 $141,360 10.00% 10.00% 20.00% $28,272 $169,632

50.03.09.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 900.00 LF $31.00 $27,900 10.00% 10.00% 20.00% $5,580 $33,480

50.03.09.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 5,720.00 LF $8.50 $48,620 10.00% 10.00% 20.00% $9,724 $58,344

50.03.09.65 POSITIVE DUCTBANK (6 - 4" PVC) 4,560.00 LF $161.00 $734,160 10.00% 10.00% 20.00% $146,832 $880,992

50.03.09.66 NEGATIVE DUCTBANK (4 - 4" PVC) 400.00 LF $161.00 $64,400 10.00% 10.00% 20.00% $12,880 $77,280

50.03.09.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 5,710.00 LF $112.00 $639,520 10.00% 10.00% 20.00% $127,904 $767,424

50.03.09.71 GENERAL SERVICE LIGHTING 3,049.00 SF $20.00 $60,980 15.00% 15.00% 30.00% $18,294 $79,274

Monday, January 27, 2014 Page 112 of 140

Page 177: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

28,548.07 $2,931,457

9.42% 10.58% 20.00%

$512,389 $3,443,846Summary for Group: 50.03.09

Group 50.03.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 10 Contingency

50.03.10.01 CLEARING AND GRUBBING 0.08 AC $4,022.00 $322 10.00% 10.00% 20.00% $64 $386

50.03.10.04 REMOVE EXIST CL FENCE 5.00 LF $2.20 $11 10.00% 10.00% 20.00% $2 $13

50.03.10.09 ROADWAY EXCAVATION 59.00 CY $28.00 $1,652 10.00% 10.00% 20.00% $330 $1,982

50.03.10.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

50.03.10.11 ROADWAY EMBANKMENT 300.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.10.12 RETAINING WALL (TYPE H) 261.00 SF $117.00 $30,537 10.00% 10.00% 20.00% $6,107 $36,644

50.03.10.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.10.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.10.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000

50.03.10.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.10.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.10.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.10.23 10' CL FENCE W/BARBED WIRE 223.00 LF $43.00 $9,589 10.00% 10.00% 20.00% $1,918 $11,507

50.03.10.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.10.27 CRUSHED ROCK 46.00 CY $45.00 $2,070 10.00% 10.00% 20.00% $414 $2,484

50.03.10.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.10.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.10.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.10.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.10.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.10.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.10.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.10.62 POSITIVE DC FEEDER - 1/C 500 kcmil 1,920.00 LF $31.00 $59,520 10.00% 10.00% 20.00% $11,904 $71,424

50.03.10.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 900.00 LF $31.00 $27,900 10.00% 10.00% 20.00% $5,580 $33,480

50.03.10.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 9,520.00 LF $8.50 $80,920 10.00% 10.00% 20.00% $16,184 $97,104

50.03.10.65 POSITIVE DUCTBANK (6 - 4" PVC) 810.00 LF $161.00 $130,410 10.00% 10.00% 20.00% $26,082 $156,492

Monday, January 27, 2014 Page 113 of 140

Page 178: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.10.66 NEGATIVE DUCTBANK (4 - 4" PVC) 400.00 LF $161.00 $64,400 10.00% 10.00% 20.00% $12,880 $77,280

50.03.10.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 9,510.00 LF $112.00 $1,065,120 10.00% 10.00% 20.00% $213,024 $1,278,144

50.03.10.71 GENERAL SERVICE LIGHTING 7,405.00 SF $20.00 $148,100 15.00% 15.00% 30.00% $44,430 $192,530

Sum

Average

34,509.08 $2,826,225

9.48% 10.52% 20.00%

$500,055 $3,326,280Summary for Group: 50.03.10

Group 50.03.11

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 11 Contingency

50.03.11.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338

50.03.11.09 ROADWAY EXCAVATION 906.00 CY $28.00 $25,368 10.00% 10.00% 20.00% $5,074 $30,442

50.03.11.10 HAUL AND DISPOSE 1,041.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.11.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

50.03.11.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.11.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.11.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.11.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.11.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.11.23 10' CL FENCE W/BARBED WIRE 208.00 LF $43.00 $8,944 10.00% 10.00% 20.00% $1,789 $10,733

50.03.11.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.11.27 CRUSHED ROCK 39.00 CY $45.00 $1,755 10.00% 10.00% 20.00% $351 $2,106

50.03.11.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.11.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.11.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.11.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.11.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.11.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.11.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.11.62 POSITIVE DC FEEDER - 1/C 500 kcmil 4,380.00 LF $31.00 $135,780 10.00% 10.00% 20.00% $27,156 $162,936

50.03.11.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 900.00 LF $31.00 $27,900 10.00% 10.00% 20.00% $5,580 $33,480

50.03.11.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 6,246.00 LF $8.50 $53,091 10.00% 10.00% 20.00% $10,618 $63,709

50.03.11.65 POSITIVE DUCTBANK (6 - 4" PVC) 1,170.00 LF $161.00 $188,370 10.00% 10.00% 20.00% $37,674 $226,044

Monday, January 27, 2014 Page 114 of 140

Page 179: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.11.66 NEGATIVE DUCTBANK (4 - 4" PVC) 400.00 LF $161.00 $64,400 10.00% 10.00% 20.00% $12,880 $77,280

50.03.11.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 6,256.00 LF $112.00 $700,672 10.00% 10.00% 20.00% $140,134 $840,806

50.03.11.71 GENERAL SERVICE LIGHTING 4,356.00 SF $20.00 $87,120 15.00% 15.00% 30.00% $26,136 $113,256

Sum

Average

29,051.07 $2,494,356

9.42% 10.58% 20.00%

$427,583 $2,921,939Summary for Group: 50.03.11

Group 50.03.12

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 12 Contingency

50.03.12.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338

50.03.12.04 REMOVE EXIST CL FENCE 75.00 LF $2.20 $165 10.00% 10.00% 20.00% $33 $198

50.03.12.09 ROADWAY EXCAVATION 41.00 CY $28.00 $1,148 10.00% 10.00% 20.00% $230 $1,378

50.03.12.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

50.03.12.11 ROADWAY EMBANKMENT 9.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.12.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.12.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.12.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.12.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.12.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.12.23 10' CL FENCE W/BARBED WIRE 211.00 LF $43.00 $9,073 10.00% 10.00% 20.00% $1,815 $10,888

50.03.12.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.12.27 CRUSHED ROCK 38.00 CY $45.00 $1,710 10.00% 10.00% 20.00% $342 $2,052

50.03.12.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.12.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.12.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.12.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.12.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.12.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.12.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.12.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720

50.03.12.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800

50.03.12.62 POSITIVE DC FEEDER - 1/C 500 kcmil 2,322.00 LF $31.00 $71,982 10.00% 10.00% 20.00% $14,396 $86,378

Monday, January 27, 2014 Page 115 of 140

Page 180: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.12.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 996.00 LF $31.00 $30,876 10.00% 10.00% 20.00% $6,175 $37,051

50.03.12.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 3,720.00 LF $8.50 $31,620 10.00% 10.00% 20.00% $6,324 $37,944

50.03.12.65 POSITIVE DUCTBANK (6 - 4" PVC) 450.00 LF $161.00 $72,450 10.00% 10.00% 20.00% $14,490 $86,940

50.03.12.66 NEGATIVE DUCTBANK (4 - 4" PVC) 480.00 LF $161.00 $77,280 10.00% 10.00% 20.00% $15,456 $92,736

50.03.12.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 501.00 LF $165.00 $82,665 10.00% 10.00% 20.00% $16,533 $99,198

50.03.12.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 364.00 LF $213.00 $77,532 10.00% 10.00% 20.00% $15,506 $93,038

50.03.12.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 3,710.00 LF $112.00 $415,520 10.00% 10.00% 20.00% $83,104 $498,624

50.03.12.71 GENERAL SERVICE LIGHTING 5,227.00 SF $20.00 $104,540 15.00% 15.00% 30.00% $31,362 $135,902

Sum

Average

21,296.07 $2,179,617

9.52% 10.48% 20.00%

$366,377 $2,545,994Summary for Group: 50.03.12

Group 50.03.13

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 13 Contingency

50.03.13.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338

50.03.13.04 REMOVE EXIST CL FENCE 70.00 LF $2.20 $154 10.00% 10.00% 20.00% $31 $185

50.03.13.09 ROADWAY EXCAVATION 99.00 CY $28.00 $2,772 10.00% 10.00% 20.00% $554 $3,326

50.03.13.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

50.03.13.11 ROADWAY EMBANKMENT 236.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.13.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.13.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.13.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.13.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.13.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.13.25 10' PICKET FENCE W/BARBED WIRE 200.00 LF $100.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.13.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.13.27 CRUSHED ROCK 34.00 CY $45.00 $1,530 10.00% 10.00% 20.00% $306 $1,836

50.03.13.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.13.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.13.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.13.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.13.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

Monday, January 27, 2014 Page 116 of 140

Page 181: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.13.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.13.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.13.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720

50.03.13.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800

50.03.13.62 POSITIVE DC FEEDER - 1/C 500 kcmil 3,660.00 LF $31.00 $113,460 10.00% 10.00% 20.00% $22,692 $136,152

50.03.13.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,320.00 LF $31.00 $40,920 10.00% 10.00% 20.00% $8,184 $49,104

50.03.13.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 5,190.00 LF $8.50 $44,115 10.00% 10.00% 20.00% $8,823 $52,938

50.03.13.65 POSITIVE DUCTBANK (6 - 4" PVC) 780.00 LF $161.00 $125,580 10.00% 10.00% 20.00% $25,116 $150,696

50.03.13.66 NEGATIVE DUCTBANK (4 - 4" PVC) 540.00 LF $161.00 $86,940 10.00% 10.00% 20.00% $17,388 $104,328

50.03.13.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 1,050.00 LF $165.00 $173,250 10.00% 10.00% 20.00% $34,650 $207,900

50.03.13.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 520.00 LF $213.00 $110,760 10.00% 10.00% 20.00% $22,152 $132,912

50.03.13.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 5,200.00 LF $112.00 $582,400 10.00% 10.00% 20.00% $116,480 $698,880

50.03.13.71 GENERAL SERVICE LIGHTING 9,148.00 SF $20.00 $182,960 15.00% 15.00% 30.00% $54,888 $237,848

Sum

Average

31,199.07 $2,687,897

9.52% 10.48% 20.00%

$475,875 $3,163,772Summary for Group: 50.03.13

Group 50.03.14

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 14 Contingency

50.03.14.01 CLEARING AND GRUBBING 0.09 AC $4,022.00 $362 10.00% 10.00% 20.00% $72 $434

50.03.14.07 REMOVE EXIST TREE 4.00 EA $200.00 $800 20.00% 10.00% 30.00% $240 $1,040

50.03.14.08 REMOVE EXIST POLE FOUNDATION 1.00 EA $913.00 $913 15.00% 15.00% 30.00% $274 $1,187

50.03.14.09 ROADWAY EXCAVATION 138.00 CY $28.00 $3,864 10.00% 10.00% 20.00% $773 $4,637

50.03.14.10 HAUL AND DISPOSE 158.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.14.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

50.03.14.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.14.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.14.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.14.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.14.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.14.25 10' PICKET FENCE W/BARBED WIRE 229.00 LF $100.00 $22,900 10.00% 10.00% 20.00% $4,580 $27,480

50.03.14.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

Monday, January 27, 2014 Page 117 of 140

Page 182: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.14.27 CRUSHED ROCK 45.00 CY $45.00 $2,025 10.00% 10.00% 20.00% $405 $2,430

50.03.14.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.14.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.14.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.14.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.14.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.14.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.14.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.14.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720

50.03.14.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800

50.03.14.62 POSITIVE DC FEEDER - 1/C 500 kcmil 3,660.00 LF $31.00 $113,460 10.00% 10.00% 20.00% $22,692 $136,152

50.03.14.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,080.00 LF $31.00 $33,480 10.00% 10.00% 20.00% $6,696 $40,176

50.03.14.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 5,265.00 LF $8.50 $44,753 10.00% 10.00% 20.00% $8,951 $53,703

50.03.14.65 POSITIVE DUCTBANK (6 - 4" PVC) 510.00 LF $161.00 $82,110 10.00% 10.00% 20.00% $16,422 $98,532

50.03.14.66 NEGATIVE DUCTBANK (4 - 4" PVC) 340.00 LF $161.00 $54,740 10.00% 10.00% 20.00% $10,948 $65,688

50.03.14.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 702.00 LF $165.00 $115,830 10.00% 10.00% 20.00% $23,166 $138,996

50.03.14.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 360.00 LF $213.00 $76,680 10.00% 10.00% 20.00% $15,336 $92,016

50.03.14.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 5,255.00 LF $112.00 $588,560 10.00% 10.00% 20.00% $117,712 $706,272

50.03.14.71 GENERAL SERVICE LIGHTING 20,038.00 SF $20.00 $400,760 15.00% 15.00% 30.00% $120,228 $520,988

Sum

Average

40,937.09 $2,744,010

10.00% 10.63% 20.63%

$509,049 $3,253,060Summary for Group: 50.03.14

Group 50.03.15

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 15 Contingency

50.03.15.01 CLEARING AND GRUBBING 0.13 AC $4,022.00 $523 10.00% 10.00% 20.00% $105 $627

50.03.15.02 REMOVE EXIST DRAINAGE DITCH 85.00 LF $20.00 $1,700 10.00% 10.00% 20.00% $340 $2,040

50.03.15.04 REMOVE EXIST CL FENCE 10.00 LF $2.20 $22 10.00% 10.00% 20.00% $4 $26

50.03.15.05 REMOVE EXIST GATE 1.00 EA $42.00 $42 10.00% 10.00% 20.00% $8 $50

50.03.15.07 REMOVE EXIST TREE 6.00 EA $200.00 $1,200 20.00% 10.00% 30.00% $360 $1,560

50.03.15.09 ROADWAY EXCAVATION 191.00 CY $28.00 $5,348 10.00% 10.00% 20.00% $1,070 $6,418

50.03.15.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

Monday, January 27, 2014 Page 118 of 140

Page 183: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.15.11 ROADWAY EMBANKMENT 732.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.15.12 RETAINING WALL (TYPE H) 2,623.00 SF $117.00 $306,891 10.00% 10.00% 20.00% $61,378 $368,269

50.03.15.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.15.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.15.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000

50.03.15.16 HOT MIX ASPHALT (TYPE A) 107.00TON $102.00 $10,914 10.00% 10.00% 20.00% $2,183 $13,097

50.03.15.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.15.19 CLASS 2 AGGREGATE BASE 63.00 CY $45.00 $2,835 10.00% 10.00% 20.00% $567 $3,402

50.03.15.20 RELOCATE EXIST GATE 1.00 EA $80.00 $80 10.00% 10.00% 20.00% $16 $96

50.03.15.22 6' CL FENCE W/BARBED WIRE 157.00 LF $43.00 $6,751 10.00% 10.00% 20.00% $1,350 $8,101

50.03.15.23 10' CL FENCE W/BARBED WIRE 103.00 LF $43.00 $4,429 10.00% 10.00% 20.00% $886 $5,315

50.03.15.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.15.27 CRUSHED ROCK 47.00 CY $45.00 $2,115 10.00% 10.00% 20.00% $423 $2,538

50.03.15.30 CONCRETE LINED DRAINAGE DITCH 70.00 LF $27.00 $1,890 10.00% 10.00% 20.00% $378 $2,268

50.03.15.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.15.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.15.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.15.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.15.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.15.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.15.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.15.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720

50.03.15.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800

50.03.15.62 POSITIVE DC FEEDER - 1/C 500 kcmil 7,512.00 LF $31.00 $232,872 10.00% 10.00% 20.00% $46,574 $279,446

50.03.15.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 2,640.00 LF $31.00 $81,840 10.00% 10.00% 20.00% $16,368 $98,208

50.03.15.64 TRANSFER TRIP CABLE - 12 STRAND SINGLE MODE FIBER BETWEEN 3,763.00 LF $8.50 $31,986 10.00% 10.00% 20.00% $6,397 $38,383

50.03.15.65 POSITIVE DUCTBANK (6 - 4" PVC) 3,306.00 LF $161.00 $532,266 10.00% 10.00% 20.00% $106,453 $638,719

50.03.15.66 NEGATIVE DUCTBANK (4 - 4" PVC) 1,400.00 LF $161.00 $225,400 10.00% 10.00% 20.00% $45,080 $270,480

50.03.15.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 228.00 LF $165.00 $37,620 10.00% 10.00% 20.00% $7,524 $45,144

Monday, January 27, 2014 Page 119 of 140

Page 184: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.15.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 340.00 LF $213.00 $72,420 10.00% 10.00% 20.00% $14,484 $86,904

50.03.15.69 COMMUNICATIONS DUCTBANK (2 - 2" PVC) 3,753.00 LF $112.00 $420,336 10.00% 10.00% 20.00% $84,067 $504,403

50.03.15.71 GENERAL SERVICE LIGHTING 3,049.00 SF $20.00 $60,980 15.00% 15.00% 30.00% $18,294 $79,274

Sum

Average

33,328.13 $3,247,636

9.87% 10.38% 20.26%

$575,745 $3,823,382Summary for Group: 50.03.15

Group 50.03.16

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SUBSTATION 16 Contingency

50.03.16.01 CLEARING AND GRUBBING 0.07 AC $4,022.00 $282 10.00% 10.00% 20.00% $56 $338

50.03.16.07 REMOVE EXIST TREE 3.00 EA $200.00 $600 20.00% 10.00% 30.00% $180 $780

50.03.16.09 ROADWAY EXCAVATION 1,212.00 CY $28.00 $33,936 10.00% 10.00% 20.00% $6,787 $40,723

50.03.16.10 HAUL AND DISPOSE 1,394.00 CY $0.00 $0 10.00% 10.00% 20.00% $0 $0

50.03.16.101 POWER TO SUBSTATION 1.00 LS $300,000.00 $300,000 0.00% 20.00% 20.00% $60,000 $360,000

50.03.16.12 RETAINING WALL (TYPE H) 1,767.00 SF $117.00 $206,739 10.00% 10.00% 20.00% $41,348 $248,087

50.03.16.13 CONCRETE PAD 24.00 CY $571.00 $13,704 10.00% 10.00% 20.00% $2,741 $16,445

50.03.16.14 BAR REINFORCING STEEL 2,410.00 LB $1.00 $2,410 10.00% 10.00% 20.00% $482 $2,892

50.03.16.15 COMMERCIAL DRIVEWAY (WIDTH PER PLANS) 1.00 EA $5,000.00 $5,000 10.00% 10.00% 20.00% $1,000 $6,000

50.03.16.16 HOT MIX ASPHALT (TYPE A) 1.00TON $102.00 $102 10.00% 10.00% 20.00% $20 $122

50.03.16.18 TPSS STAIRS AND LANDING 82.00 SF $24.00 $1,968 10.00% 10.00% 20.00% $394 $2,362

50.03.16.19 CLASS 2 AGGREGATE BASE 11.00 CY $45.00 $495 10.00% 10.00% 20.00% $99 $594

50.03.16.25 10' PICKET FENCE W/BARBED WIRE 198.00 LF $100.00 $19,800 10.00% 10.00% 20.00% $3,960 $23,760

50.03.16.26 DOUBLE SWING GATE (WIDTH PER PLANS) 1.00 EA $3,915.00 $3,915 10.00% 10.00% 20.00% $783 $4,698

50.03.16.27 CRUSHED ROCK 35.00 CY $45.00 $1,575 10.00% 10.00% 20.00% $315 $1,890

50.03.16.50 TPSS (1500kW) 1.00 EA $800,000.00 $800,000 0.00% 10.00% 10.00% $80,000 $880,000

50.03.16.54 #4/0 BARE COPPER WIRE 600.00 LF $1.80 $1,080 10.00% 10.00% 20.00% $216 $1,296

50.03.16.55 COPPER GROUND RODS 14.00 EA $250.00 $3,500 10.00% 10.00% 20.00% $700 $4,200

50.03.16.56 POSITIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IRO 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.16.57 NEGATIVE MANHOLE 8'X8' PRECAST W/IRON RACKS & PULLING IR 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.16.58 COMMUNICATION PULL BOX 5'X4' PRECAST W/IRON RACKS & PUL 1.00 EA $13,500.00 $13,500 10.00% 10.00% 20.00% $2,700 $16,200

50.03.16.59 SDG&E 12kV SERVICE MANHOLE 8'X8' 1.00 EA $20,000.00 $20,000 10.00% 10.00% 20.00% $4,000 $24,000

50.03.16.60 3'L X 3'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 1.00 EA $600.00 $600 10.00% 10.00% 20.00% $120 $720

Monday, January 27, 2014 Page 120 of 140

Page 185: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.03.16.61 4'L X 4'W X 2'D FIBERGLASS PULLBOX (SURFACE MOUNTED) 2.00 EA $750.00 $1,500 10.00% 10.00% 20.00% $300 $1,800

50.03.16.62 POSITIVE DC FEEDER - 1/C 500 kcmil 1,518.00 LF $31.00 $47,058 10.00% 10.00% 20.00% $9,412 $56,470

50.03.16.63 NEGATIVE DC FEEDER - 1/C 500 kcmil 1,050.00 LF $31.00 $32,550 10.00% 10.00% 20.00% $6,510 $39,060

50.03.16.65 POSITIVE DUCTBANK (6 - 4" PVC) 390.00 LF $161.00 $62,790 10.00% 10.00% 20.00% $12,558 $75,348

50.03.16.66 NEGATIVE DUCTBANK (4 - 4" PVC) 320.00 LF $161.00 $51,520 10.00% 10.00% 20.00% $10,304 $61,824

50.03.16.67 EXPOSED - POSITIVE CONDUITS (3 - 4" GRS) 264.00 LF $165.00 $43,560 10.00% 10.00% 20.00% $8,712 $52,272

50.03.16.68 EXPOSED - NEGATIVE CONDUITS (4 - 4" GRS) 360.00 LF $213.00 $76,680 10.00% 10.00% 20.00% $15,336 $92,016

50.03.16.71 GENERAL SERVICE LIGHTING 3,049.00 SF $20.00 $60,980 15.00% 15.00% 30.00% $18,294 $79,274

Sum

Average

14,713.07 $1,845,844

9.84% 10.48% 20.32%

$295,327 $2,141,170Summary for Group: 50.03.16

Sum

Average

407,068.13 $38,909,467

9.99% 11.40% 21.39%

$7,047,415 $45,956,882Summary for Sub Section: 50.03

Sub Section 50.04 TRACTION POWER DISTRIBUTION

Group 50.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

TRACTION POWER DISTRIBUTION Contingency

50.04.01 TAPERED TUBULAR POLE ASSEMBLY - STANDARD POLE (13" DIA. 2 269.00 EA $2,296.00 $617,624 10.00% 15.00% 25.00% $154,406 $772,030

50.04.02 TAPERED TUBULAR POLE ASSEMBLY - HEADSPAN/2 TRACK POLE (1 1.00 EA $4,029.00 $4,029 10.00% 15.00% 25.00% $1,007 $5,036

50.04.03 TAPERED TUBULAR POLE ASSEMBLY - FEEDER POLE (15" DIA. 26' L 26.00 EA $5,778.00 $150,228 10.00% 15.00% 25.00% $37,557 $187,785

50.04.04 TAPERED TUBULAR POLE ASSEMBLY - COUTERWEIGHT POLE (15" D 70.00 EA $6,325.00 $442,750 10.00% 15.00% 25.00% $110,688 $553,438

50.04.05 TAPERED TUBULAR POLE ASSEMBLY - FIXED END/MIDPOINT/OVER 115.00 EA $3,730.00 $428,950 10.00% 15.00% 25.00% $107,238 $536,188

50.04.06 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - STANDA 132.00 EA $5,000.00 $660,000 10.00% 15.00% 25.00% $165,000 $825,000

50.04.07 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - HEADSP 1.00 EA $5,000.00 $5,000 10.00% 15.00% 25.00% $1,250 $6,250

50.04.08 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - FEEDER 15.00 EA $5,000.00 $75,000 10.00% 15.00% 25.00% $18,750 $93,750

50.04.09 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - COUNTE 42.00 EA $5,000.00 $210,000 10.00% 15.00% 25.00% $52,500 $262,500

50.04.10 OCS FOUNDATION ASSEMBLY (36" DIA.; AVG 12' DEPTH) - FIXED E 73.00 EA $5,000.00 $365,000 10.00% 15.00% 25.00% $91,250 $456,250

50.04.11 CANTILEVER ASSEMBLY - LIGHT & MEDIUM LOAD 831.00 EA $2,627.00 $2,183,037 10.00% 15.00% 25.00% $545,759 $2,728,796

50.04.12 CANTILEVER ASSEMBLY - HEAVY LOAD 171.00 EA $3,152.00 $538,992 10.00% 15.00% 25.00% $134,748 $673,740

50.04.14 HEADSPAN ASSEMBLY 4.00 EA $6,304.00 $25,216 10.00% 15.00% 25.00% $6,304 $31,520

50.04.15 PULL OFF ASSEMBLY (NOT USED) 1.00 EA $3,152.00 $3,152 10.00% 15.00% 25.00% $788 $3,940

50.04.16 DOWN GUY ASSEMBLY 128.00 EA $3,152.00 $403,456 10.00% 15.00% 25.00% $100,864 $504,320

Monday, January 27, 2014 Page 121 of 140

Page 186: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.04.17 DOWN GUY FOUNDATION ASSEMBLY 77.00 EA $5,000.00 $385,000 10.00% 15.00% 25.00% $96,250 $481,250

50.04.18 FIXED TERMINATION ASSEMBLY 17.00 EA $3,677.00 $62,509 10.00% 15.00% 25.00% $15,627 $78,136

50.04.19 COUNTERWEIGHT ASSEMBLY 21.00 EA $10,506.00 $220,626 10.00% 15.00% 25.00% $55,157 $275,783

50.04.20 CONTACT BRIDGE ASSEMBLY 36.00 EA $315.00 $11,340 10.00% 15.00% 25.00% $2,835 $14,175

50.04.21 SECTION INSULATOR ASSEMBLY 80.00 EA $6,304.00 $504,320 10.00% 15.00% 25.00% $126,080 $630,400

50.04.22 MANUAL DISCONNECT SWITCH ASSEMBLY 74.00 EA $9,455.00 $699,670 10.00% 15.00% 25.00% $174,918 $874,588

50.04.23 FEEDER TAP ASSEMBLY 46.00 EA $1,051.00 $48,346 10.00% 15.00% 25.00% $12,087 $60,433

50.04.24 LIGHTNING ARRESTER ASSEMBLY 46.00 EA $2,101.00 $96,646 10.00% 15.00% 25.00% $24,162 $120,808

50.04.25 MIDPOINT ASSEMBLY 18.00 EA $2,627.00 $47,286 10.00% 15.00% 25.00% $11,822 $59,108

50.04.26 POLE GROUNDING 481.00 EA $525.00 $252,525 10.00% 15.00% 25.00% $63,131 $315,656

50.04.27 FULL FEED JUMPER ASSEMBLY 73.00 EA $315.00 $22,995 10.00% 15.00% 25.00% $5,749 $28,744

50.04.28 UNDER BRIDGE SUPPORT ASSEMBLY 6.00 EA $840.00 $5,040 10.00% 15.00% 25.00% $1,260 $6,300

50.04.29 IN-SPAN JUMPER 337.00 EA $263.00 $88,631 10.00% 15.00% 25.00% $22,158 $110,789

50.04.30 HANGER SET 1,092.00 EA $1,051.00 $1,147,692 10.00% 15.00% 25.00% $286,923 $1,434,615

50.04.31 DOUBLE MW FIXED TERMINATION ASSEMBLY 44.00 EA $3,152.00 $138,688 10.00% 15.00% 25.00% $34,672 $173,360

50.04.32 DOUBLE MW COUNTERWEIGHT ASSEMBLY 52.00 EA $15,759.00 $819,468 10.00% 15.00% 25.00% $204,867 $1,024,335

50.04.33 MESSENGER WIRE 190,349.00 LF $19.00 $3,616,631 10.00% 15.00% 25.00% $904,158 $4,520,789

50.04.34 CONTACT WIRE 141,315.00 LF $11.00 $1,554,465 10.00% 15.00% 25.00% $388,616 $1,943,081

50.04.35 REMOVE EXISTING OCS STRUCTURE 2.00 EA $2,101.00 $4,202 10.00% 15.00% 25.00% $1,051 $5,253

50.04.37 EQUALIZING JUMPER 23.00 EA $210.00 $4,830 10.00% 15.00% 25.00% $1,208 $6,038

50.04.38 EXISTING GL OCS TRANSITION/MODIFICATION 1.00 LS $21,012.00 $21,012 10.00% 15.00% 25.00% $5,253 $26,265

50.04.50.01 BRIDGE SOFFIT MANHOLE 1.00 LS $72,000.00 $72,000 15.00% 15.00% 30.00% $21,600 $93,600

50.04.50.02 REMOVAL OF LOST DECK 1.00 LS $36,000.00 $36,000 15.00% 15.00% 30.00% $10,800 $46,800

50.04.50.03.01 PARALLEL FEEDER - 3-500 KCMIL CABLES (UCSD WEST ZONE) 8,280.00 LF $93.00 $770,040 15.00% 15.00% 30.00% $231,012 $1,001,052

50.04.50.03.02 INTERMEDIATE RISER, 1-500 KCMIL CABLE (UCSD WEST ZONE) 1,350.00 LF $31.00 $41,850 15.00% 15.00% 30.00% $12,555 $54,405

50.04.50.03.03 SPLICE KITS - INSULATED (UCSD WEST ZONE) 30.00 EA $100.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.04.50.03.04 LONGITUDINAL CABLE TRAY (UCSD WEST ZONE) 2,580.00 LF $50.00 $129,000 15.00% 15.00% 30.00% $38,700 $167,700

50.04.50.03.05 LATERAL CABLE TRAY (UCSD WEST ZONE) 255.00 LF $50.00 $12,750 15.00% 15.00% 30.00% $3,825 $16,575

50.04.50.04.01 PARALLEL FEEDER - 3-500 KCMIL CABLES (UCSD EAST ZONE) 7,014.00 LF $93.00 $652,302 15.00% 15.00% 30.00% $195,691 $847,993

Monday, January 27, 2014 Page 122 of 140

Page 187: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.04.50.04.02 INTERMEDIATE RISER, 1-500 KCMIL CABLE (UCSD EAST ZONE) 990.00 LF $31.00 $30,690 15.00% 15.00% 30.00% $9,207 $39,897

50.04.50.04.03 SPLICE KITS - INSULATED (UCSD EAST ZONE) 22.00 EA $100.00 $2,200 15.00% 15.00% 30.00% $660 $2,860

50.04.50.04.04 LONGITUDINAL CABLE TRAY (UCSD EAST ZONE) 2,158.00 LF $50.00 $107,900 15.00% 15.00% 30.00% $32,370 $140,270

50.04.50.04.05 LATERAL CABLE TRAY (UCSD EAST ZONE) 195.00 LF $50.00 $9,750 15.00% 15.00% 30.00% $2,925 $12,675

Sum

Average

358,945.00 $17,731,838

11.25% 15.00% 26.25%

$4,526,334 $22,258,172Summary for Group: 50.04

Sum

Average

358,945.00 $17,731,838

11.25% 15.00% 26.25%

$4,526,334 $22,258,172Summary for Sub Section: 50.04

Sub Section 50.05 COMMUNICATIONS

Group 50.05.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (TECOLOTE STATION) Contingency

50.05.01.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780

50.05.01.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

50.05.01.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000

50.05.01.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.05.01.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.01.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

50.05.01.106 SMOKE DETECTORS - TC&C ROOM 1.00 EA $200.00 $200 0.00% 15.00% 15.00% $30 $230

50.05.01.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272

50.05.01.108 2" CONDUIT FROM MICRODUCTBANK TO TC&C ROOM 100.00 LF $29.50 $2,950 15.00% 15.00% 30.00% $885 $3,835

50.05.01.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056

50.05.01.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.05.01.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.05.01.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012

50.05.01.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.05.01.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.01.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

50.05.01.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050

50.05.01.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000

50.05.01.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475

Monday, January 27, 2014 Page 123 of 140

Page 188: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.01.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520

50.05.01.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170

50.05.01.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501

50.05.01.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500

50.05.01.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.01.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101

50.05.01.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

50.05.01.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910

50.05.01.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068

50.05.01.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080

50.05.01.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

50.05.01.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195

50.05.01.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940

Sum

Average

7,610.00 $421,759

14.53% 15.00% 29.53%

$126,498 $548,257Summary for Group: 50.05.01

Group 50.05.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (CLAIREMONT STATION) Contingency

50.05.02.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780

50.05.02.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

50.05.02.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000

50.05.02.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.05.02.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.02.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

50.05.02.106 SMOKE DETECTORS - TC&C ROOM 1.00 EA $200.00 $200 0.00% 15.00% 15.00% $30 $230

50.05.02.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272

50.05.02.108 2" CONDUIT FROM MICRODUCTBANK TO TC&C ROOM 100.00 LF $29.50 $2,950 15.00% 15.00% 30.00% $885 $3,835

50.05.02.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056

50.05.02.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.05.02.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.05.02.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012

Monday, January 27, 2014 Page 124 of 140

Page 189: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.02.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.05.02.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.02.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

50.05.02.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050

50.05.02.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000

50.05.02.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475

50.05.02.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520

50.05.02.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170

50.05.02.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501

50.05.02.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500

50.05.02.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.02.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101

50.05.02.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

50.05.02.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910

50.05.02.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068

50.05.02.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080

50.05.02.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

50.05.02.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195

50.05.02.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940

Sum

Average

7,610.00 $421,759

14.53% 15.00% 29.53%

$126,498 $548,257Summary for Group: 50.05.02

Group 50.05.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (BALBOA STATION) Contingency

50.05.03.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780

50.05.03.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

50.05.03.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000

50.05.03.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.05.03.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.03.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

50.05.03.106 SMOKE DETECTORS - TC&C ROOM 1.00 EA $200.00 $200 0.00% 15.00% 15.00% $30 $230

Monday, January 27, 2014 Page 125 of 140

Page 190: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.03.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272

50.05.03.108 2" CONDUIT FROM MICRODUCTBANK TO TC&C ROOM 100.00 LF $29.50 $2,950 15.00% 15.00% 30.00% $885 $3,835

50.05.03.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056

50.05.03.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.05.03.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.05.03.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012

50.05.03.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.05.03.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.03.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

50.05.03.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050

50.05.03.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000

50.05.03.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475

50.05.03.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520

50.05.03.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170

50.05.03.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501

50.05.03.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500

50.05.03.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.03.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101

50.05.03.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

50.05.03.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910

50.05.03.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068

50.05.03.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080

50.05.03.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

50.05.03.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195

50.05.03.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940

Sum

Average

7,610.00 $421,759

14.53% 15.00% 29.53%

$126,498 $548,257Summary for Group: 50.05.03

Group 50.05.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (NOBEL STATION) Contingency

50.05.04.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780

Monday, January 27, 2014 Page 126 of 140

Page 191: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.04.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

50.05.04.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000

50.05.04.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.05.04.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.04.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.04.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

50.05.04.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920

50.05.04.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272

50.05.04.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670

50.05.04.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056

50.05.04.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.05.04.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.05.04.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012

50.05.04.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702

50.05.04.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.05.04.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.04.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

50.05.04.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050

50.05.04.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000

50.05.04.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475

50.05.04.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520

50.05.04.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170

50.05.04.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501

50.05.04.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500

50.05.04.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.04.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101

50.05.04.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

50.05.04.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910

50.05.04.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068

Monday, January 27, 2014 Page 127 of 140

Page 192: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.04.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080

50.05.04.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

50.05.04.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195

50.05.04.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940

50.05.04.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

Sum

Average

7,736.00 $472,149

14.57% 15.00% 29.57%

$141,525 $613,674Summary for Group: 50.05.04

Group 50.05.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (VA MEDICAL CENTER STATION) Contingency

50.05.05.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780

50.05.05.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

50.05.05.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000

50.05.05.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.05.05.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.05.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

50.05.05.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920

50.05.05.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272

50.05.05.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670

50.05.05.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056

50.05.05.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.05.05.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.05.05.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012

50.05.05.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702

50.05.05.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.05.05.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.05.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

50.05.05.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050

50.05.05.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000

50.05.05.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475

50.05.05.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520

Monday, January 27, 2014 Page 128 of 140

Page 193: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.05.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170

50.05.05.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501

50.05.05.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500

50.05.05.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.05.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101

50.05.05.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

50.05.05.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910

50.05.05.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068

50.05.05.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080

50.05.05.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

50.05.05.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195

50.05.05.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940

50.05.05.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

Sum

Average

7,718.00 $465,849

14.56% 15.00% 29.56%

$139,635 $605,484Summary for Group: 50.05.05

Group 50.05.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (UCSD WEST STATION) Contingency

50.05.06.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780

50.05.06.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

50.05.06.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000

50.05.06.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.05.06.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.06.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

50.05.06.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920

50.05.06.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272

50.05.06.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670

50.05.06.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056

50.05.06.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.05.06.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.05.06.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012

Monday, January 27, 2014 Page 129 of 140

Page 194: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.06.113 UNIVERSITY SECURITY BLUE LIGHT STATION 4.00 EA $3,500.00 $14,000 15.00% 15.00% 30.00% $4,200 $18,200

50.05.06.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702

50.05.06.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.05.06.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.06.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

50.05.06.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050

50.05.06.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000

50.05.06.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475

50.05.06.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520

50.05.06.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170

50.05.06.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501

50.05.06.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500

50.05.06.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.06.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101

50.05.06.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

50.05.06.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910

50.05.06.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068

50.05.06.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080

50.05.06.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

50.05.06.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195

50.05.06.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940

50.05.06.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

Sum

Average

7,722.00 $479,849

14.57% 15.00% 29.57%

$143,835 $623,684Summary for Group: 50.05.06

Group 50.05.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (UCSD EAST STATION) Contingency

50.05.07.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780

50.05.07.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

50.05.07.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000

50.05.07.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

Monday, January 27, 2014 Page 130 of 140

Page 195: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.07.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.07.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

50.05.07.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920

50.05.07.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272

50.05.07.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670

50.05.07.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056

50.05.07.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.05.07.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.05.07.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012

50.05.07.113 UNIVERSITY SECURITY BLUE LIGHT STATION 4.00 EA $3,500.00 $14,000 15.00% 15.00% 30.00% $4,200 $18,200

50.05.07.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702

50.05.07.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.05.07.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.07.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

50.05.07.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050

50.05.07.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000

50.05.07.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475

50.05.07.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520

50.05.07.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170

50.05.07.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501

50.05.07.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500

50.05.07.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.07.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101

50.05.07.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

50.05.07.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910

50.05.07.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068

50.05.07.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080

50.05.07.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

50.05.07.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195

Monday, January 27, 2014 Page 131 of 140

Page 196: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.07.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940

50.05.07.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

Sum

Average

7,722.00 $479,849

14.57% 15.00% 29.57%

$143,835 $623,684Summary for Group: 50.05.07

Group 50.05.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (EXECUTIVE STATION) Contingency

50.05.08.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780

50.05.08.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

50.05.08.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000

50.05.08.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.05.08.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.08.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

50.05.08.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920

50.05.08.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272

50.05.08.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670

50.05.08.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056

50.05.08.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.05.08.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.05.08.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012

50.05.08.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702

50.05.08.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.05.08.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.08.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

50.05.08.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050

50.05.08.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000

50.05.08.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475

50.05.08.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520

50.05.08.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170

50.05.08.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501

50.05.08.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500

Monday, January 27, 2014 Page 132 of 140

Page 197: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.08.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.08.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101

50.05.08.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

50.05.08.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910

50.05.08.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068

50.05.08.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080

50.05.08.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

50.05.08.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195

50.05.08.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940

50.05.08.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

Sum

Average

7,718.00 $465,849

14.56% 15.00% 29.56%

$139,635 $605,484Summary for Group: 50.05.08

Group 50.05.09

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (UTC STATION) Contingency

50.05.09.100 INTRUSION ALARMS FOR TICKET VENDING MACHINES 4.00 EA $150.00 $600 15.00% 15.00% 30.00% $180 $780

50.05.09.101 PLATFORM PTZ CAMERAS @ 75 FEET PER PLATFORM 10.00 EA $3,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

50.05.09.102 PARKING LOT PTZ CAMERAS 4.00 EA $2,500.00 $10,000 15.00% 15.00% 30.00% $3,000 $13,000

50.05.09.103 VARIABLE MESSAGE SIGNS (INC. SUPPORTS) 4.00 EA $5,000.00 $20,000 15.00% 15.00% 30.00% $6,000 $26,000

50.05.09.104 BIDIRECTIONAL SPEAKERS@ 40FEET PER PLATFORM 18.00 EA $350.00 $6,300 15.00% 15.00% 30.00% $1,890 $8,190

50.05.09.105 AMBIENT NOISE SENSORS 4.00 EA $500.00 $2,000 15.00% 15.00% 30.00% $600 $2,600

50.05.09.106 SMOKE DETECTORS - TC&C ROOM 4.00 EA $200.00 $800 0.00% 15.00% 15.00% $120 $920

50.05.09.107 4 -1" CONDUITS PER PLATFORM FROM DEVICES TO TC&C ROOM 2,880.00 LF $38.00 $109,440 15.00% 15.00% 30.00% $32,832 $142,272

50.05.09.108 2" CONDUIT TO TC&C ROOM 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670

50.05.09.109 CAT5E CABLE FOR CCTV CAMERAS 2,400.00 LF $1.30 $3,120 15.00% 15.00% 30.00% $936 $4,056

50.05.09.110 RS-485 CABLE FOR VMS 720.00 LF $1.50 $1,080 15.00% 15.00% 30.00% $324 $1,404

50.05.09.111 3# 10 AWG VMS POWER CABLE 720.00 LF $3.00 $2,160 15.00% 15.00% 30.00% $648 $2,808

50.05.09.112 2PR# 14 CABLE FOR SPEAKERS 720.00 LF $2.15 $1,548 15.00% 15.00% 30.00% $464 $2,012

50.05.09.114 EMERGENCY TELEPHONES 4.00 EA $2,635.00 $10,540 15.00% 15.00% 30.00% $3,162 $13,702

50.05.09.200 COMMUNICATION EQUIPMENT RACKS (24"X24"X72" H) 6.00 EA $500.00 $3,000 15.00% 15.00% 30.00% $900 $3,900

50.05.09.201 FIRE ALARM PANEL 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

Monday, January 27, 2014 Page 133 of 140

Page 198: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.09.202 INTRUSION CONTROL PANEL 1.00 EA $2,500.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

50.05.09.203 UPS UNIT 1.00 EA $28,500.00 $28,500 15.00% 15.00% 30.00% $8,550 $37,050

50.05.09.204 EXTERNAL BATTERIES 1.00 EA $120,000.00 $120,000 15.00% 15.00% 30.00% $36,000 $156,000

50.05.09.205 BY PASS SWITCH 1.00 EA $5,750.00 $5,750 15.00% 15.00% 30.00% $1,725 $7,475

50.05.09.206 FIBER DISTRIBUTION PANEL 1.00 EA $400.00 $400 15.00% 15.00% 30.00% $120 $520

50.05.09.207 FIBER SLACK ENCLOSURE 1.00 EA $900.00 $900 15.00% 15.00% 30.00% $270 $1,170

50.05.09.208 MAIN DISTRIBUTION FRAME 1.00 EA $12,693.00 $12,693 15.00% 15.00% 30.00% $3,808 $16,501

50.05.09.209 CISCO NETWORK SWITCH 1.00 EA $25,000.00 $25,000 15.00% 15.00% 30.00% $7,500 $32,500

50.05.09.210 VIDEO SURVEILLANCE ENCODING SERVER 1.00 EA $5,000.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.09.211 CCTV SWITCH 1.00 EA $4,693.00 $4,693 15.00% 15.00% 30.00% $1,408 $6,101

50.05.09.212 NETWORK VIDEO RECORDER 1.00 EA $4,500.00 $4,500 15.00% 15.00% 30.00% $1,350 $5,850

50.05.09.213 MEDIA CONVERTER 1.00 EA $700.00 $700 15.00% 15.00% 30.00% $210 $910

50.05.09.214 RTU CPU 1.00 EA $6,975.00 $6,975 15.00% 15.00% 30.00% $2,093 $9,068

50.05.09.216 STATION CONTROLLER 1.00 EA $1,600.00 $1,600 15.00% 15.00% 30.00% $480 $2,080

50.05.09.217 PA AMPLIFIER 2.00 EA $600.00 $1,200 15.00% 15.00% 30.00% $360 $1,560

50.05.09.218 MICROPHONE 1.00 EA $150.00 $150 15.00% 15.00% 30.00% $45 $195

50.05.09.219 RADIO REPEATER 1.00 EA $3,800.00 $3,800 15.00% 15.00% 30.00% $1,140 $4,940

50.05.09.220 EMERGENCY MANAGEMENT PANEL (EMP) 1.00 EA $30,000.00 $30,000 15.00% 15.00% 30.00% $9,000 $39,000

Sum

Average

7,718.00 $465,849

14.56% 15.00% 29.56%

$139,635 $605,484Summary for Group: 50.05.09

Group 50.05.10

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

COMMUNICATIONS (SUBSTATIONS) Contingency

50.05.10.00.01 MICRO DUCTBANK 43,300.00 LF $4.30 $186,190 15.00% 15.00% 30.00% $55,857 $242,047

50.05.10.00.02 MICRO DUCTBANK - REDUNDANT PATH 43,300.00 LF $4.30 $186,190 15.00% 15.00% 30.00% $55,857 $242,047

50.05.10.00.03 2" CONDUIT (AERIAL STRUCTURE) 21,450.00 LF $25.00 $536,250 15.00% 15.00% 30.00% $160,875 $697,125

50.05.10.00.04 2" CONDUIT (AERIAL STRUCTURE) - REDUNDANT PATH 21,450.00 LF $29.50 $632,775 15.00% 15.00% 30.00% $189,833 $822,608

50.05.10.00.05 144 STRAND BACKBONE SINGLE MODE FIBER 64,750.00 LF $6.50 $420,875 15.00% 15.00% 30.00% $126,263 $547,138

50.05.10.00.06 144 STRAND BACKBONE SINGLE MODE FIBER - REDUNDANT PATH 64,750.00 LF $8.15 $527,713 15.00% 15.00% 30.00% $158,314 $686,026

50.05.10.012.07 2" CONDUIT 500.00 LF $29.50 $14,750 15.00% 15.00% 30.00% $4,425 $19,175

50.05.10.012.08 12 STRAND SINGLE MODE FIBER 500.00 LF $5.00 $2,500 15.00% 15.00% 30.00% $750 $3,250

Monday, January 27, 2014 Page 134 of 140

Page 199: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.10.03.07 2" CONDUIT 940.00 LF $29.50 $27,730 15.00% 15.00% 30.00% $8,319 $36,049

50.05.10.03.08 12 STRAND SINGLE MODE FIBER 940.00 LF $5.00 $4,700 15.00% 15.00% 30.00% $1,410 $6,110

50.05.10.04.07 2" CONDUIT 1,880.00 LF $29.50 $55,460 15.00% 15.00% 30.00% $16,638 $72,098

50.05.10.04.08 12 STRAND SINGLE MODE FIBER 1,880.00 LF $5.00 $9,400 15.00% 15.00% 30.00% $2,820 $12,220

50.05.10.05.07 2" CONDUIT 200.00 LF $29.50 $5,900 15.00% 15.00% 30.00% $1,770 $7,670

50.05.10.05.08 12 STRAND SINGLE MODE FIBER 4,090.00 LF $5.00 $20,450 15.00% 15.00% 30.00% $6,135 $26,585

50.05.10.05.09 MICRO DUCTBANK 3,890.00 LF $4.30 $16,727 15.00% 15.00% 30.00% $5,018 $21,745

50.05.10.06.07 2" CONDUIT 210.00 LF $29.50 $6,195 15.00% 15.00% 30.00% $1,859 $8,054

50.05.10.06.08 12 STRAND SINGLE MODE FIBER 210.00 LF $5.00 $1,050 15.00% 15.00% 30.00% $315 $1,365

50.05.10.078.07 2" CONDUIT 50.00 LF $29.50 $1,475 15.00% 15.00% 30.00% $443 $1,918

50.05.10.078.08 12 STRAND SINGLE MODE FIBER 50.00 LF $5.00 $250 15.00% 15.00% 30.00% $75 $325

50.05.10.09.07 2" CONDUIT 50.00 LF $29.50 $1,475 15.00% 15.00% 30.00% $443 $1,918

50.05.10.09.08 12 STRAND SINGLE MODE FIBER 2,750.00 LF $5.00 $13,750 15.00% 15.00% 30.00% $4,125 $17,875

50.05.10.09.09 MICRO DUCTBANK 2,700.00 LF $4.30 $11,610 15.00% 15.00% 30.00% $3,483 $15,093

50.05.10.10.07 2" CONDUIT 50.00 LF $29.50 $1,475 15.00% 15.00% 30.00% $443 $1,918

50.05.10.10.08 12 STRAND SINGLE MODE FIBER 8,370.00 LF $5.00 $41,850 15.00% 15.00% 30.00% $12,555 $54,405

50.05.10.10.09 MICRO DUCTBANK 8,320.00 LF $4.30 $35,776 15.00% 15.00% 30.00% $10,733 $46,509

50.05.10.11.07 2" CONDUIT 2,000.00 LF $29.50 $59,000 15.00% 15.00% 30.00% $17,700 $76,700

50.05.10.11.08 12 STRAND SINGLE MODE FIBER 7,000.00 LF $5.00 $35,000 15.00% 15.00% 30.00% $10,500 $45,500

50.05.10.11.09 MICRO DUCTBANK 5,000.00 LF $4.30 $21,500 15.00% 15.00% 30.00% $6,450 $27,950

50.05.10.12.07 2" CONDUIT 970.00 LF $29.50 $28,615 15.00% 15.00% 30.00% $8,585 $37,200

50.05.10.12.08 12 STRAND SINGLE MODE FIBER 970.00 LF $5.00 $4,850 15.00% 15.00% 30.00% $1,455 $6,305

50.05.10.13.07 2" CONDUIT 480.00 LF $29.50 $14,160 15.00% 15.00% 30.00% $4,248 $18,408

50.05.10.13.08 12 STRAND SINGLE MODE FIBER 480.00 LF $5.00 $2,400 15.00% 15.00% 30.00% $720 $3,120

50.05.10.14.07 2" CONDUIT 720.00 LF $29.50 $21,240 15.00% 15.00% 30.00% $6,372 $27,612

50.05.10.14.08 12 STRAND SINGLE MODE FIBER 720.00 LF $5.00 $3,600 15.00% 15.00% 30.00% $1,080 $4,680

50.05.10.15.07 2" CONDUIT 1,000.00 LF $29.50 $29,500 15.00% 15.00% 30.00% $8,850 $38,350

50.05.10.15.08 12 STRAND SINGLE MODE FIBER 1,000.00 LF $5.00 $5,000 15.00% 15.00% 30.00% $1,500 $6,500

50.05.10.16.07 2" CONDUIT 690.00 LF $29.50 $20,355 15.00% 15.00% 30.00% $6,107 $26,462

Monday, January 27, 2014 Page 135 of 140

Page 200: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

50.05.10.16.08 12 STRAND SINGLE MODE FIBER 690.00 LF $5.00 $3,450 15.00% 15.00% 30.00% $1,035 $4,485

Sum

Average

318,300.00 $3,011,186

15.00% 15.00% 30.00%

$903,356 $3,914,541Summary for Group: 50.05.10

Sum

Average

387,464.00 $7,105,857

14.60% 15.00% 29.60%

$2,130,947 $9,236,803Summary for Sub Section: 50.05

Sub Section 50.06 FARE COLLECTION SYSTEM AND EQUIPMENT

Group 50.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

FARE COLLECTION SYSTEM AND EQUIPMENT Contingency

50.06.01 TICKET VENDING MACHINES (TVM) 20.00 EA $140,000.00 $2,800,000 15.00% 15.00% 30.00% $840,000 $3,640,000

50.06.02 PAID CARD INTERFACE DEVICES (PCID) 29.00 EA $20,000.00 $580,000 15.00% 15.00% 30.00% $174,000 $754,000

Sum

Average

49.00 $3,380,000

15.00% 15.00% 30.00%

$1,014,000 $4,394,000Summary for Group: 50.06

Sum

Average

49.00 $3,380,000

15.00% 15.00% 30.00%

$1,014,000 $4,394,000Summary for Sub Section: 50.06

Sub Section 50.07 CENTRAL CONTROL

Group 50.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CENTRAL CONTROL Contingency

50.07 CENTRAL CONTROL 1.00 LS $1,000,000.00 $1,000,000 15.00% 15.00% 30.00% $300,000 $1,300,000

Sum

Average

1.00 $1,000,000

15.00% 15.00% 30.00%

$300,000 $1,300,000Summary for Group: 50.07

Sum

Average

1.00 $1,000,000

15.00% 15.00% 30.00%

$300,000 $1,300,000Summary for Sub Section: 50.07

Sub Section 50.08 EXISTING SYSTEM UPDATES (SYSTEM WIDE)

Group 50.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

EXISTING SYSTEM UPDATES (SYSTEM WIDE) Contingency

50.08.01 UPDATES TO COMPUTER SYSTEM AT CENTRAL CONTROL FOR CMS 1.00 LS $200,000.00 $200,000 0.00% 15.00% 15.00% $30,000 $230,000

50.08.02 UPDATES TO MAPS AT EXISTING STATIONS/FACILITIES 1.00 LS $121,500.00 $121,500 15.00% 15.00% 30.00% $36,450 $157,950

50.08.03 UPDATES TO MAPS IN EXISTING FLEET 1.00 LS $1,029,120.00 $1,029,120 15.00% 15.00% 30.00% $308,736 $1,337,856

Sum

Average

3.00 $1,350,620

10.00% 15.00% 25.00%

$375,186 $1,725,806Summary for Group: 50.08

Sum

Average

3.00 $1,350,620

10.00% 15.00% 25.00%

$375,186 $1,725,806Summary for Sub Section: 50.08

Monday, January 27, 2014 Page 136 of 140

Page 201: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

1,153,615.13 $105,958,581

11.77% 13.38% 25.15%

$24,060,331 $130,018,913Summary for Section 50

Section 60 ROW, LAND, EXISTING IMPROVEMENTS

Sub Section 60.01 PURCHASE OR LEASE REAL ESTATE

Group 60.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PURCHASE OR LEASE REAL ESTATE Contingency

60.01 PURCHASE OR LEASE REAL ESTATE 1.00 LS $71,432,073.00 $71,432,073 0.00% 73.11% 73.11% $52,224,425 $123,656,498

Sum

Average

1.00 $71,432,073

0.00% 73.11% 73.11%

$52,224,425 $123,656,498Summary for Group: 60.01

Sum

Average

1.00 $71,432,073

0.00% 73.11% 73.11%

$52,224,425 $123,656,498Summary for Sub Section: 60.01

Sub Section 60.02 RELOCATION OF EXISTIN HOUSEHOLDS AND BUSINESSES

Group 60.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

RELOCATION OF EXISTIN HOUSEHOLDS AND BUSINESSES Contingency

60.02 RELOCATION OF EXISTIN HOUSEHOLDS AND BUSINESSES 1.00 LS $2,000,000.00 $2,000,000 0.00% 15.00% 15.00% $300,000 $2,300,000

Sum

Average

1.00 $2,000,000

0.00% 15.00% 15.00%

$300,000 $2,300,000Summary for Group: 60.02

Sum

Average

1.00 $2,000,000

0.00% 15.00% 15.00%

$300,000 $2,300,000Summary for Sub Section: 60.02

Sub Section 60.03 PRIOR ACQUISITION

Group 60.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PRIOR ACQUISITION Contingency

60.03 PRIOR ACQUISITION 1.00 LS $19,996,580.00 $19,996,580 0.00% 0.00% 0.00% $0 $19,996,580

Sum

Average

1.00 $19,996,580

0.00% 0.00% 0.00%

$0 $19,996,580Summary for Group: 60.03

Sum

Average

1.00 $19,996,580

0.00% 0.00% 0.00%

$0 $19,996,580Summary for Sub Section: 60.03

Sum

Average

3.00 $93,428,653

0.00% 29.37% 29.37%

$52,524,425 $145,953,078Summary for Section 60

Section 70 VEHICLES

Sub Section 70.01 LIGHT RAIL

Group 70.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LIGHT RAIL Contingency

70.01 LIGHT RAIL 36.00 EA $4,090,922.00 $147,273,192 0.00% 5.00% 5.00% $7,363,660 $154,636,852

Monday, January 27, 2014 Page 137 of 140

Page 202: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

36.00 $147,273,192

0.00% 5.00% 5.00%

$7,363,660 $154,636,852Summary for Group: 70.01

Sum

Average

36.00 $147,273,192

0.00% 5.00% 5.00%

$7,363,660 $154,636,852Summary for Sub Section: 70.01

Sub Section 70.07 SPARE PARTS

Group 70.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SPARE PARTS Contingency

70.07 SPARE PARTS 1.00 LS $14,385,600.00 $14,385,600 0.00% 5.00% 5.00% $719,280 $15,104,880

Sum

Average

1.00 $14,385,600

0.00% 5.00% 5.00%

$719,280 $15,104,880Summary for Group: 70.07

Sum

Average

1.00 $14,385,600

0.00% 5.00% 5.00%

$719,280 $15,104,880Summary for Sub Section: 70.07

Sum

Average

37.00 $161,658,792

0.00% 5.00% 5.00%

$8,082,940 $169,741,732Summary for Section 70

Section 80 PROFESSIONAL SERVICES

Sub Section 80.01 PRELIMINARY ENGINEERING

Group 80.01

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PRELIMINARY ENGINEERING Contingency

80.01 PRELIMINARY ENGINEERING 1.00 LS $80,000,000.00 $80,000,000 0.00% 20.00% 20.00% $16,000,000 $96,000,000

Sum

Average

1.00 $80,000,000

0.00% 20.00% 20.00%

$16,000,000 $96,000,000Summary for Group: 80.01

Sum

Average

1.00 $80,000,000

0.00% 20.00% 20.00%

$16,000,000 $96,000,000Summary for Sub Section: 80.01

Sub Section 80.02 FINAL DESIGN

Group 80.02

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

FINAL DESIGN Contingency

80.02 FINAL DESIGN 1.00 LS $35,000,000.00 $35,000,000 0.00% 20.00% 20.00% $7,000,000 $42,000,000

Sum

Average

1.00 $35,000,000

0.00% 20.00% 20.00%

$7,000,000 $42,000,000Summary for Group: 80.02

Sum

Average

1.00 $35,000,000

0.00% 20.00% 20.00%

$7,000,000 $42,000,000Summary for Sub Section: 80.02

Sub Section 80.03 PROJECT MANAGEMENT FOR DESIGN & CONSTRUCTION

Group 80.03

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PROJECT MANAGEMENT FOR DESIGN & CONSTRUCTION Contingency

Monday, January 27, 2014 Page 138 of 140

Page 203: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

80.03 PROJECT MANAGEMENT FOR DESIGN & CONSTRUCTION (5%) 1.00 LS $30,986,370.75 $30,986,371 0.00% 20.00% 20.00% $6,197,274 $37,183,645

Sum

Average

1.00 $30,986,371

0.00% 20.00% 20.00%

$6,197,274 $37,183,645Summary for Group: 80.03

Sum

Average

1.00 $30,986,371

0.00% 20.00% 20.00%

$6,197,274 $37,183,645Summary for Sub Section: 80.03

Sub Section 80.04 CONSTRUCTION ADMINISTRATION AND MANAGEMENT (10%)

Group 80.04

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

CONSTRUCTION ADMINISTRATION AND MANAGEMENT Contingency

80.04 CONSTRUCTION ADMINISTRATION AND MANAGEMENT (10%) 1.00 LS $61,972,741.49 $61,972,741 0.00% 20.00% 20.00% $12,394,548 $74,367,290

Sum

Average

1.00 $61,972,741

0.00% 20.00% 20.00%

$12,394,548 $74,367,290Summary for Group: 80.04

Sum

Average

1.00 $61,972,741

0.00% 20.00% 20.00%

$12,394,548 $74,367,290Summary for Sub Section: 80.04

Sub Section 80.05 PROFESSIONAL LIABILITY & OTHER NON-CONSTRUCTION INSURANCE

Group 80.05

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

PROFESSIONAL LIABILITY & OTHER NON-CONSTRUCTION INSURANCE Contingency

80.05 PROFESSIONAL LIABILITY & OTHER NON-CONSTRUCTION INSURAN 1.00 LS $6,197,274.15 $6,197,274 0.00% 20.00% 20.00% $1,239,455 $7,436,729

Sum

Average

1.00 $6,197,274

0.00% 20.00% 20.00%

$1,239,455 $7,436,729Summary for Group: 80.05

Sum

Average

1.00 $6,197,274

0.00% 20.00% 20.00%

$1,239,455 $7,436,729Summary for Sub Section: 80.05

Sub Section 80.06 LEGAL, PERMITS, REVIEW FEES BY OTHER AGENCIES, CITIES, ETC

Group 80.06

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

LEGAL, PERMITS, REVIEW FEES BY OTHER AGENCIES, CITIES, ETC Contingency

80.06 LEGAL, PERMITS, REVIEW FEES BY OTHER AGENCIES, CITIES, ETC (2 1.00 LS $12,394,548.30 $12,394,548 0.00% 20.00% 20.00% $2,478,910 $14,873,458

Sum

Average

1.00 $12,394,548

0.00% 20.00% 20.00%

$2,478,910 $14,873,458Summary for Group: 80.06

Sum

Average

1.00 $12,394,548

0.00% 20.00% 20.00%

$2,478,910 $14,873,458Summary for Sub Section: 80.06

Sub Section 80.07 SURVEYS, TESTING, INVESTIGATION, INSPECTION

Group 80.07

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

SURVEYS, TESTING, INVESTIGATION, INSPECTION Contingency

80.07 SURVEYS, TESTING, INVESTIGATION, INSPECTION (1%) 1.00 LS $6,197,274.15 $6,197,274 0.00% 20.00% 20.00% $1,239,455 $7,436,729

Monday, January 27, 2014 Page 139 of 140

Page 204: MCCT Capital Cost Methodology and Estimate Report

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

Contingency

Sum

Average

1.00 $6,197,274

0.00% 20.00% 20.00%

$1,239,455 $7,436,729Summary for Group: 80.07

Sum

Average

1.00 $6,197,274

0.00% 20.00% 20.00%

$1,239,455 $7,436,729Summary for Sub Section: 80.07

Sub Section 80.08 STARTUP

Group 80.08

SCC Item Code Item Name Quantity Unit Unit Price ($) Cost ($) Quantity (%) Unit Price (%) Total (%) Total ($) Total Cost ($)

STARTUP Contingency

80.08 STARTUP (1.5%) 1.00 LS $9,295,911.22 $9,295,911 0.00% 20.00% 20.00% $1,859,182 $11,155,093

Sum

Average

1.00 $9,295,911

0.00% 20.00% 20.00%

$1,859,182 $11,155,093Summary for Group: 80.08

Sum

Average

1.00 $9,295,911

0.00% 20.00% 20.00%

$1,859,182 $11,155,093Summary for Sub Section: 80.08

Sum

Average

8.00 $242,044,120

0.00% 20.00% 20.00%

$48,408,824 $290,452,944Summary for Section 80

47,679,575.07 $1,116,858,980 $243,256,307 $1,360,115,287Grand Total

Monday, January 27, 2014 Page 140 of 140


Recommended