+ All Categories
Home > Documents > Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software...

Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software...

Date post: 22-Dec-2015
Category:
View: 215 times
Download: 1 times
Share this document with a friend
Popular Tags:
35
Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation describes work being done by TeraQuest Metrics
Transcript
Page 1: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measuring Dollar Savings from Software Process Improvement

with COCOMO II

Betsy Clark

Software Metrics Inc.October 25, 2001

Acknowledgment: This presentation describes work being done by TeraQuest Metrics

Page 2: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Outline

• Background• Measuring the Impact of Software Process

Improvement (SPI)• Some Initial Results

Page 3: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Customer Background

• Large financial institution • Actively involved in software process improvement

(SPI)– Software-CMM– System Test

• Began summer of 2000 at CMM Level 1• Incrementally adding Key Process Areas• Two pilot organizations

– Planning Level 2 assessment end of this year

Page 4: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Background (continued)

• Strong emphasis on measuring impact of SPI, especially hard dollar savings

• CIO: “If process improvement saves us money, I should be able to go down the street to my competitor’s bank and get a loan to fund our process improvement initiative.”

Page 5: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Outline

• Background• Measuring the Impact of Software Process

Improvement (SPI)• Some Initial Results• Conclusions

Page 6: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

“Maturity levels are meaningless if they cannot be explained in terms of business objectives”

John D. VuBoeing

Level 5 Organization

Page 7: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Business Objectives

• Reduce the cost of software activities• Reduce delivery time• Improve product quality• Increase customer satisfaction

– customers are internal to the bank (e.g., wholesale and retail mortgage, investment division)

Page 8: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measurement Objectives

• Measure impact of SPI in terms of these business objectives

• Impacts of SPI will be measured by comparing a set of baseline projects to pilot projects

Page 9: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measuring Hard Savings

• CFO’s initial understanding - – “If we have savings from SPI, we can reduce IT budget in

the future.”– First point of discussion - need to measure work load– Led to concept of unit savings, holding IT organization

accountable for those savings

• Brought IT manager into the discussion -– “But events occur outside of my control that can affect unit

costs. For example, I can lose my top staff.”

Page 10: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measuring Hard Savings

• The IT manager was talking about variability due to factors outside of SPI.

• That variability is addressed by parametric cost models.

• Approach - measure COCOMO II cost drivers for baseline projects and for SPI projects. Use them to adjust unit costs.– Backout all influences on unit costs except SPI

Page 11: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measuring Hard Savings (cont)

• Savings due to SPI– Difference in adjusted unit costs between baseline and SPI

projects

Page 12: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Setting Expectations

• SPI is a staged, long term initiative– implemented on pilot projects first, then on a wider scale

• Initially, we will estimate savings based on pilot results– few data points, wide variation

• As SPI is implemented on a wider scale, we will have more data points, clearer trends

• Moving from CMM Level 1 to Level 2 lays the foundation for unit cost savings– a few studies do show cost savings from Level 1 to 2

• major effect is in better estimation and planning• reduction in rework due to stable requirements

Page 13: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measures

1) estimation accuracy: effort

2) estimation accuracy: schedule

3) productivity

4) unit costs

5) project delivery rate (cycle time)

6) system test effectiveness

7) delivered defect density

8) customer satisfaction

9) requirements volatility

Page 14: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Approach

• Attempted to “mine” existing data sources (e.g., time tracking, financial, problem reporting systems)– not successful, sporadic and inconsistently used

• Selected a representative set of completed projects from the two pilot organizations

• Goal was 10-15 projects per pilot organization– 13 projects from one– 11 from the other

• Constructed a survey, met with project managers to collect data

• Followed-up with each manager to verify data

Page 15: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measures

1) estimation accuracy: effort

2) estimation accuracy: schedule

3) productivity

4) unit costs

5) project delivery rate (cycle time)

6) system test effectiveness

7) delivered defect density

8) customer satisfaction

9) requirements volatility

Page 16: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Planned Labor Hours

Per

cen

t d

iffe

ren

ce b

etw

een

act

ual

an

d e

sti

mat

ed

0

Overruns

Underruns

Calculation:(Actual labor hours - estimated) / estimated

Estimation Accuracy - Effort

Page 17: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Planned duration

Per

cen

t D

iffe

ren

ce b

etw

een

act

ual

an

d e

sti

mat

ed

0

Overruns

Underruns

Calculation:(Actual calendar months - estimated) / estimated

Estimation Accuracy - Schedule

Page 18: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measures of Interest

• Median - very stable across organizations• standard deviation• Goals with SPI:

– median should approach zero– standard deviation should be smaller

Page 19: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measures

1) estimation accuracy: effort

2) estimation accuracy: schedule

3) productivity

4) unit costs

5) project delivery rate (cycle time)

6) system test effectiveness

7) delivered defect density

8) customer satisfaction

9) requirements volatility

Page 20: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Productivity and Unit Costs

• High variability• Median is stable across divisions

Page 21: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Initial Results

• Used COCOMO II parameters to adjust size• Led to a reduction in the standard deviation• Helped explain:

– why lower productivity projects had difficulty– why higher productivity projects had an easier time

• Projects with very high productivity seemed to do everything right– capable staff, low turnover, managing requirements…– these are good things that should improve with SPI– don’t want to penalize organization for improvement in these other

(non-SPI) areas– management controllables vs noncontrollables

Page 22: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measures

• 1) estimation accuracy: effort• 2) estimation accuracy: schedule• 3) productivity• 4) unit costs• 5) project delivery rate (cycle time)• 6) system test effectiveness• 7) delivered defect density• 8) customer satisfaction• 9) requirements volatility

Page 23: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Project Delivery Rate

• Calculation:– Function points / calendar months

• Goal: Increasing

Page 24: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Function Points

Fu

nct

ion

po

ints

pe

r ca

len

da

r m

on

ths

Project Delivery Rate

Page 25: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measures

1) estimation accuracy: effort

2) estimation accuracy: schedule

3) productivity

4) unit costs

5) project delivery rate (cycle time)

6) system test effectiveness

7) delivered defect density

8) customer satisfaction

9) requirements volatility

Page 26: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

System Test Effectiveness

• Calculation:– (Defects Found in System Test / Total Defects)– where – Total Defects = (Defects Found in System Test +

Delivered Defects found in first 30 days)– Example:– Defects found in System Test = 45– Defects found in first 30 days of operations = 5– Test Effectiveness = 90%

• Goal: 100%• Result: Wide variation in effectiveness

Page 27: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measures

1) estimation accuracy: effort

2) estimation accuracy: schedule

3) productivity

4) unit costs

5) project delivery rate (cycle time)

6) system test effectiveness

7) delivered defect density

8) customer satisfaction

9) requirements volatility

Page 28: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Delivered Defect Density

• Calculation:– Defects found in first 30 days of operations / function points

• Goal: 0

Page 29: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Function Points

Def

ects

per

fu

nct

ion

po

ints

0

COTS

Custom

Delivered Defect Density

Page 30: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

(Very Preliminary) Finding of Interest• In contrast to custom development, defect density for

COTS projects appears unrelated to size

Page 31: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Measures

1) estimation accuracy: effort

2) estimation accuracy: schedule

3) productivity

4) unit costs

5) project delivery rate (cycle time)

6) system test effectiveness

7) delivered defect density

8) customer satisfaction

9) requirements volatility

Page 32: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Customer Satisfaction, Rqts Volatility

• Data do not exist• Strategy was altered to request the manager’s

estimate

Page 33: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Message to Executive Level

• Measurement – can be a powerful foundation for understanding and

managing IT– is a cultural change and not a scoreboard– will improve as process maturity improves

Page 34: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

Response from Executive Level (CIO and direct reports)• Intense interest in the measures and in

benchmarking• Basis for excellent discussions about need for

visibility into – requirements management– quality– customer satisfaction

• Collection of the nine measures has been made part of executive compensation– Moving forward to put supporting processes, tools and

training in place

Page 35: Measuring Dollar Savings from Software Process Improvement with COCOMO II Betsy Clark Software Metrics Inc. October 25, 2001 Acknowledgment: This presentation.

To be continued...


Recommended