    Risk Managementfor

    Mega Air Separation Projects

    David R EdmondsonVice President, Engineering

    Air Products

    November 2004

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    2/19

    2

    Risk Management

    Why Risk management is important

    Air Products experience

    ORYX Approach

    Options for the future

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    3/19

    3

    Risk Management

    Why is Risk Management so Important? Oxygen is an integral part of the GTL process

    Significant proportion of overall project costs

    Oxygen is on the critical path for GTL projects

    Need to manage any perceived technology risk

    Important to manage the project financial risk

    Maintains site safety performance

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    4/19

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    5/195

    Basic Air Separation Process

    AirFilter

    Compression Train

    SteamTurbine

    BoosterAir Compressor

    (BAC)

    Air Pre-treatment Cold Box Storage

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    6/191

    Air Products Rotterdam - 3250 TPD O2

    Supplying Shell PER + Project Owned and operated by

    AP since 1997

    Execution Strategy

    Side by Side HP/LP

    columns

    Site built cold box

    Site assembledcompression system

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    7/192

    Air Products Trinidad - 3000 TPD O2

    Supplying MethanexMethanol Project Owned and operated by AP

    since 2003

    Execution Strategy

    Stacked HP/LP columns

    Site built cold box

    Site constructed double

    ended steam turbinedriving compression

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    8/198

    Risk Management - Construction Strategy

    Site built machinery & Cold Box Effective for single train plants

    Issues for multiple trains

    Increased site activities challenge

    safety performance

    Suitability/availability of local

    contractors for extended period

    Managing site through periods of

    extreme weather

    Significant logistics and material

    handling

    Plot area increased to allow for

    construction access

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    9/199

    Risk Management

    ORYX Construction StrategyPre-fabrication/packaging of specialist skills areas

    Focus on Cold Box & compression train Built in Quality

    Improved control over quality & cleanliness

    Improves construction sequencing

    Reduces schedule risk

    Reduces site manning

    Fewer specialist skills on site

    Reduced plot requirements

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    10/191

    ORYX Cold Box Strategy

    ORYX plant for 7000 TPD in two trainsbeing loaded in UK

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    11/19

    1

    ORYX Cold Box Strategy

    Cleaned assembled and tested in controlledenvironment

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    12/19

    1

    ORYX Cold Box Strategy

    Utilises construction principles used for yearsin many smaller Air Separation Units

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    13/19

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    14/19

    1

    ORYX Machinery Train Solution

    Complete

    train run and

    shop tested

    Simpler

    foundations Reduced site

    construction

    and start-up

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    15/19

    15

    Does Size Matter?

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    16/19

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    17/19

    17

    Does Size Matter?

    Single vs. Multiple trains Impact of increased equipment size needs to be

    fully understood:

    Equipment sourcing Reliability & operability

    Consider impact of steam balance on oxygenrequirements at different points of facil ity

    operating map Optimum plant size and unit cost of oxygen

    dependent on owner design and operatingphilosophy

    Advantages to project risk profile by usingexisting demonstrated Air Separation Unitcomponents and proven construction strategy

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    18/19

    18

    Risk Management

    Further reducing unit cost of Oxygen Need to incorporate innovation in process cycle

    and plant concepts

    Need to accept increased compression train size

    Need to accept change in equipment configuration

    Need to consider optimisation of each key area of

    the Air Separation Unit rather being focused on

    discrete trains

  • 8/12/2019 MEGA AIR SEPARATION RISK MANAGEMENT.pdf

    19/19

    19

    Summary Points

    Managing project risk includes: Client/supplier investment

    Employee/supplier safety

    Project risk profile reduced by using demonstratedequipment and project concepts

    Air Products have a broad experience of site built andpackaged approach

    ORYX project demonstrates packaged approach:

    Product competitiveness

    Greater schedule certainty

    Reduced safety risks in difficult construction locations

    Could go further on packaging other plant areas

    Further cost benefits can be realised by goodco-operation in the project development phase


Recommended