Mega – CokersCommissioning Experience
01-Oct-13 1Raj Sharma
October 2013New Delhi, India
Raj SharmaCoker Consultant
Safety First Awareness – key for successful startups
01-Oct-13 2Raj Sharma
Emerging Cokers due to heavier Crude Blends- Old Cokers at Digboi, Gauhati, Bongaigaon and
Barauni- New Cokers at Jamnagar (Reliance), Essar Oil,
IOC-Panipat, Vadodara, Bina and Bhatinda.- Proposed /Under construction Cokers at IOC-
Paradeep, MRPL-Mangalore, Cochin and Chennai.- 2 Cokers at Reliance Jamnagar are having 8 coke
drums each with capacity of 162000 and 175000 BPD.
01-Oct-13 3Raj Sharma
Mega cokers in India are 9MMTPA + capacity 8 Coke drums with single fractionator Commissioning was done phase wise based on
construction progress. This earned extra revenue due to early startup of 4 drums.
Part commissioning was a safety challenge as many common lines like CBD/pump drains/OWS/Fire water /DCS/Alarm system/Gas detector system/Utilities were common
01-Oct-13 4Raj Sharma
Steps at early stage to achieve stage wise start up if required. Mega cokers have lot of flexibility
4 drums clubbed with independent Blow down system. So plant is 4+4 drums operability.
Next each pair of coke drums with heater made an independent block. So total 4 blocks
Gas plant was common with suitable turn down capability. All trays were designed for this load.
01-Oct-13 5Raj Sharma
Exhaustive positive isolation (Blind list) with proper Tags and administrative control.
Additional isolation valves were provided to achieve positive isolation. Also these isolation valves at construction interphase were chain locked additionally and position logged every shift.
All utilities were also provided with additional isolation valves with blinds including Flare header.
01-Oct-13 6Raj Sharma
01-Oct-13 7
1. Whole area was hard-barricaded2. Security person manned the gates with cards 3. Block 1 Area declared safety permit area4. Construction area (block 4)was barricaded by
GI sheet /Fire blankets up to coke drum platforms
5. Live lines in non operating area were painted red & tagged. Valves were positive blinded and chain locked
6. Visible lights provided blockwise at each deck
Early Startup/seggregation
Raj Sharma
Escape routes
Existing escape routes reviewed in the new barricaded scenario and new escape route marked wherever applicable considering wind directions
Minimum two gates considered for entry / exit
Additional wind socks will be provided in prominent locations for easy identification of wind directions
Assembly points
Additional assembly points provided at suitable locations for both construction and operation personnel
Mock drills will be conducted to ensure rapid & orderly evacuation of people , in case of emergency
Escape route /Assembly points
01-Oct-13 8Raj Sharma
01-Oct-13 9
UNDER GROUND SYSTEM
Raj Sharma
76
46
45
44
43
17
42
41
79 42
47
50
53
56
59
6261
58
55
52
49
48
51
4140 43
77 15 14
78
13
63
60
57
54
82
78
75
44
7475733
72
71
80 81
838485
89
76
77
70
21
3
4
5
6
12
117
9 29
21
2030 31
23
32
25
2434 35 36
26 27 38
64
372726
36
35
34
222120
33
2523
19
3231302928
17
68
88
37
39494847
65 66
67 40
16
18
38
3979
86
46
28
R01 R02 R03 R04 R05 R06R07 R08
C01FRACT
F 03F 02F 01
F 04
OSBL
OSBL
OSBL
01-Oct-13 10
Storm Water System
Raj Sharma
R01 R02 R03 R04 R05 R06R07 R08
C01FRACT
C03
C02/03
MC-372-C01COMP.
371-V11372-V20
C02
372C04
372-S06B
372-S06A
C15
V16
V10
372-S14
372-S12
372-S08
V07
372-S07
V14
V30V33
371-01
371-05
V06
S07C05371-V23
371-S08
C22
V31
CO-6
MH-3
MH-4
CO-5
CO-6
MH-6
MH-5
CO-8MH-7
HV-107
H631 H591 H632H592
MH-8MH-50MH-51MH-52MH-53MH-54
CO-33
CO-03
MH-56
MH-01
MH-60
CO-01CO-12
MH-02
MH-62MH-61
MH-63
MH-64
MH-65
MH-66
MH-67
MH-68
MH-69 CO-107
CO-104
MH-72
MH-71
CO-11
MH-85MH-84MH-83
MH-82
MH-81
MH-55
CO-10
FO1 FO2 FO3FO4
H621
H619H618H616
H615HV101H609 H607
H610H608H606H611
H612H613H614
H617H620
H676
H593 H594H595
H582
H583
HV104
H562H561
H560H563H566
H672H671H670
H570 H569H587
CO-7
HV108HV105
HV106
HV150HV151
HV152
H573
HV153
ME-
371-
S01A
-JH155
H154
H153
H156
H37
H152
H158 H157H151
H38
H100
H99
H84
H11
H75 HV-63
HV-69
H74
HV-64H12H13H14
H32
H15
H31H16
H17
H58H57H160
H18H23H21
H169
HV-65
H22
H30
HV-66
H26
H56
HV-67H165
H164
HV-68
H19
H49
H59
H60H61H62
H8H72
H71
H70H48H69
H35
H36H33
H65H66H67H68
H16
H34
H80
H73
H84
H85
H83
H159H82
H81
H76
H77
H78 H79
H39
H03
H93 H10
H91
H89
H95H94H07H02
H92H90
HV62H98
HV61
HV02
HV60
V12
C06
V11
S06
S10
S05
COKE PIT
H96 H 01 H5
HV56
HV85H826
HV84HV83
H800
H813
H822H814
H811
H825H824H808H823
H809 H810
H820
H815 H816
H817 H818
H819
HV54
H572
H574H576
H575
H577
H53 H28
H29 H51
H52
H802
H807
H804
H821
H801
H803
HV-82
HV-81
H805H806
H812
H601
H597 H602
H603H598
H604H599
H605H600
H678
H677H590
H581
H630
H586
H588H633
H589H673
H567
H564
H565
H622H623H624H625
H674
H675
H24 H64
H47
HV153
OSBL
OSBL
H27H46
H25
H41
H44
H42H43
H44
HV-72
HV-71
H40
H50
H55
H54
H154
H88
H04H628H627H626
H02
H584
371-A06
HV55
H585H580
H578
H579
FO5
01-Oct-13 11
Underground isolation: OWS
Raj Sharma
R01 R02 R03 R04 R05 R06R07 R08
C01FRACT
C03
C02/03
MC-372-C01COMP.
371-V11372-V20
C02
372C04
372-S06B
372-S06A
C15
V16
V10
372-S14
372-S12
372-S08
V07
372-S07
V14
V30V33
371-01
371-05
V06
S07C05
371-V23
371-S08
C22
V31
FO1 FO2 FO3FO4
ME-37
1-S01
A-J
V12
C06
V11
S06
S10
S05
COKE PIT
CO-116 CO-106
CO-120
CO-122
CO-111 CO-108
CO-103
CO-105
CO-102
CO-20 CO-21
CO-25
CO-22
CO-18
CO-140
CO-141
CO-143
CO-142
CO-144
CO-17
CO-15
CO-16
H644
H645
H636
H635
H634
H637
H641
H640 H639
H654
H653
H652
H642H643
H636
H655H659
H127H128
H137
H125H123
H130
H440
H138
H136
H124
H120
H134
H132H131
H135H135
H752
H756H754
H757
H753 H755
H129H126
H658
H121
H122H647
H641
H650
H651
H646
H649
H760
H758 H750 H751
CO-125
FO5
01-Oct-13 12
Underground CBD isoleted
Raj Sharma
01-Oct-13 13
ABOVE GROUND SYSTEM
Raj Sharma
R01 R02 R03 R04 R05 R06R07 R08
C01FRACTIONATOR
C02/03
372-C01
HP FLARE KO DRUM
C02
COKE CUTTING WATER TANK
SLUDGE TANK
HEATER FO3
FRES
H FE
ED
HEAT
ER
COKE PIT MT-371-02
Blowdown Tower
U/G SLO
P TANKB.D.HEATER
B.D. SETTLING
DRUM
STRIPPER
COMPRESSOR
STRIPPER REBOILER
ABSORBER/STRIPPER
SP. ABSORBER
LEAN/RICH SP OIL H E
DEBUT REBOILER
DEBUT REBOILER
DEBUTANISER
LLP FLARE KO DRUM
AMINE SUMP TANK
UNSAT FG KO DRUM
AMINE ABSORBER
AMINE KO DRUM
FG KO DRUM
SLOP OIL HEATER
HCN COOLER
LCN COOLER
N/S O/H RECEIVER
NAPHTHA SPLITTER N.S. REBOILER
WASH WATER DRUM
AMMONIUM POLY S DRUM
V30V33
U/G SLOP TANKS
MP STEAM GEN.
LP STEAM GEN.
LP STEAM GEN.
Blowdown Tower
B.D. HEATER
B.D SETTLING DRUM
B.D CIR. OIL
COO
LER
372-P16 A/B
372-P05 A/B
372-P06 A/B
372-P04 A/B
372-P02 A/B/C
372-P03 A/B
372-P01A/B
371-P10A/B
371-P16A/B
371-P09A/B
371-P18 A/B
HCN PUMP
371-P13A-D
371-
P15A
/B/C 371-P11 A/B
371-P12 A/B
371-P14 A/B
CHAR
GE
PUM
P
371-P17A/B
APHAPHAPHAPH
COKE CUTTING PUMP
371-P03A/B/C
371-
P04A
/B
371-
P05A
/B
P22
A/B/
C
P24
A/B
P23
A/B
COKE PIT MT-371-01
MP-371-P08 A/B/E MP-371-P08 C/D
372-A01
372-A03
371-A04
371-A03
371-A05 371-A02371-A01
LLP
FLAR
E CO
OLE
RHP
FLA
RE
COO
LER
SPONGE COOLER
LEAN
OIL
CO
OLE
RNA
PH
O/H
CO
ND.
LCG
O P
/A
COO
LER
LCG
O
COO
LER
HCG
O
COO
LER
B/D CONDENSER B.D CONDENSERB/D CIR.
OIL COOLER
STRUCTURE-B
COMP SUC. K.O DRUM
STRIPPER REBOILER
ABSORBER INTER COOLER
372-P18 A/B
372-A05
371-A08
371-A07
LEAN AMINE COOLER
372-P11 A/B/C
MP STEAM GEN.
LP STEAM GEN.
LP STEAM B/D DRUM MP STEAM B/D DRUM
KERO DRUM
FLARE SYS. SEAL POT
ANTIFOAM PACK DE-EMUL.
PACK
FD FAN
ID FAN
FD FAN
ID FAN
FD FAN
ID FAN
FD FAN
ID FAN
HEATER FO2
HEATER FO1
HEATER FO4
371-
P55A
/B
371-
P54A
/B
371-
P53A
/B
Z371-P21A/B
P36 A/B/C
371-P02 A/B/C
CRUSHER-I CRUSHER-II
PG KOD
UTILITY BOOSTER PUMP
DELTA VALVE WS PUMP
372-A02
FRESH FEED HEATER
SITE OFFICE
WORK SHOP
CONTRACTOR OFFICE
DINI
NG
HALL
FOUR DRUM START UP
UNSAT FG AA FEED COOLER
QUENCH WATER PUMP
STRUCTURE-A
371-A06
N.S. REBOILER
SUBSTATION
Z300 - 30
PIB - 57
371-V17 A/B/C
Z371-V28
CT - 03
Fresh feed Heater
Z371 F 05
MAPS PACKAGE POLY FLOW PACKAGE
V24 A/B/C
Z371-F07
FLUSHING OIL TANK
NEUTRALIZING AMINE PACKAGE
FILMING AMINE PACKAGE
CCD ICCD II
LEGEND
NORTH
EWSOUTH
E-14S 06A
E-17S 05A
E-16S 06
E-15S 05
E-18S 10
OPERATIONAL AREA
HOT WORK PERMIT AREACONSTRUCTION AREA
Above Ground System
01-Oct-13 14Raj Sharma
R01 R02 R03 R04 R05 R06R07 R08
C01FRACTIONATOR
C02/03
372-C01
HP FLARE KO DRUM
C02
COKE CUTTING WATER TANK
SLUDGE TANK
HEATER FO3
FRES
H FE
ED
HEAT
ER
COKE PIT MT-371-02
Blowdown Tower
U/G SLO
P TANKB.D.HEATER
B.D. SETTLING
DRUM
STRIPPER
COMPRESSOR
STRIPPER REBOILER
ABSORBER/STRIPPER
SP. ABSORBER
LEAN/RICH SP OIL H E
DEBUT REBOILER
DEBUT REBOILER
DEBUTANISER
LLP FLARE KO DRUM
AMINE SUMP TANK
UNSAT FG KO DRUM
AMINE ABSORBER
AMINE KO DRUM
FG KO DRUM
SLOP OIL HEATER
HCN COOLER
LCN COOLER
N/S O/H RECEIVER
NAPHTHA SPLITTER N.S. REBOILER
WASH WATER DRUM
AMMONIUM POLY S DRUM
V30V33
U/G SLOP TANKS
MP STEAM GEN.
LP STEAM GEN.
LP STEAM GEN.
Blowdown Tower
B.D. HEATER
B.D SETTLING DRUM
B.D CIR. OIL
COO
LER
372-P16 A/B
372-P05 A/B
372-P06 A/B
372-P04 A/B
372-P02 A/B/C
372-P03 A/B
372-P01A/B
371-P10A/B
371-P16A/B
371-P09A/B
371-P18 A/B
HCN PUMP
371-P13A-D
371-
P15A
/B/C 371-P11 A/B
371-P12 A/B
371-P14 A/B
CHAR
GE
PUM
P
371-P17A/B
APHAPHAPHAPH
COKE CUTTING PUMP
371-P03A/B/C
371-
P04A
/B
371-
P05A
/B
P22
A/B/
C
P24
A/B
P23
A/B
COKE PIT MT-371-01
MP-371-P08 A/B/E MP-371-P08 C/D
372-A01
372-A03
371-A04
371-A03
371-A05 371-A02371-A01
LLP
FLAR
E CO
OLE
RHP
FLA
RE
COO
LER
SPONGE COOLER
LEAN
OIL
CO
OLE
RNA
PH
O/H
CO
ND.
LCG
O P
/A
COO
LER
LCG
O
COO
LER
HCG
O
COO
LER
B/D CONDENSER B.D CONDENSERB/D CIR.
OIL COOLER
STRUCTURE-B
COMP SUC. K.O DRUM
STRIPPER REBOILER
ABSORBER INTER COOLER
372-P18 A/B
372-A05
371-A08
371-A07
LEAN AMINE COOLER
372-P11 A/B/C
MP STEAM GEN.
LP STEAM GEN.
LP STEAM B/D DRUM MP STEAM B/D DRUM
KERO DRUM
FLARE SYS. SEAL POT
ANTIFOAM PACK DE-EMUL.
PACK
FD FAN
ID FAN
FD FAN
ID FAN
FD FAN
ID FAN
FD FAN
ID FAN
HEATER FO2
HEATER FO1
HEATER FO4
371-
P55A
/B
371-
P54A
/B
371-
P53A
/B
Z371-P21A/B
P36 A/B/C
371-P02 A/B/C
CRUSHER-I CRUSHER-II
PG KOD
UTILITY BOOSTER PUMP
DELTA VALVE WS PUMP
372-A02
FRESH FEED HEATER
SITE OFFICE
WORK SHOP
CONTRACTOR OFFICE
DINI
NG
HALL
FOUR DRUM START UP
UNSAT FG AA FEED COOLER
QUENCH WATER PUMP
STRUCTURE-A
371-A06
N.S. REBOILER
SUBSTATION
Z300 - 30
PIB - 57
371-V17 A/B/C
Z371-V28
CT - 03
Fresh feed Heater
Z371 F 05
MAPS PACKAGE POLY FLOW PACKAGE
V24 A/B/C
Z371-F07
FLUSHING OIL TANK
NEUTRALIZING AMINE PACKAGE
FILMING AMINE PACKAGE
CCD ICCD II
LEGEND
NORTH
EWSOUTH
E-14S 06A
E-17S 05A
E-16S 06
E-15S 05
E-18S 10
OPERATIONAL AREA
HOT WORK PERMIT AREACONSTRUCTION AREA
Above Ground System
01-Oct-13 15Raj Sharma
R07 R08
B.D. HEATER
B.D SETTLING DRUM
B.D CIR. OIL COOLER
APH
P22 A
/B/C
P24 A
/B
P23 A
/B
371-A05
B/D CONDENSER
FD FAN
ID FAN
HEATER FO4
P36 A
/B/C
371-A06
Fresh feed Heater
Z371 F 05
V24 A/B/C
CCD II
C01FRACTIONATOR
FLARE SYS. SEAL POT
From V-06
HARD BARRICATED AREA
GATE WITH SECURITY GUARD
SP 3
Blowdown Tower
U/S of These valves will be
blinded & inspected in every shift
01-Oct-13 16Raj Sharma
DCS graphics were also divided in Blockwise along with DS alarms grouping.
Since 4 drums startup was envisaged, underground piping was designed for such isolation facility.
Physical barricading was engineered between 4 live coke drums and rest, both at coke drum structure(at all levels) and at grade plot.
01-Oct-13 17Raj Sharma
Safety interlocks were designed blockwise to avoid interference. Specific inputs from outside (load shedding)were identified.
Construction priority was given for systems in 4 drums, 2 drums and then last 2 drums
4 Drums started= 23rd January 2009 Next 2 drums started= 16th May 2009 Last 2 drums started = 23rd July 2009 Extra Revenue earned= millions of Dollars
01-Oct-13 18Raj Sharma
Zero LTI- safety first during construction/Pre-comm/startup
Zero fire – Fire free startup Zero flaring during startup –save money Zero/Minimum Recycle –Maximize thruput Zero /Minimum slops(generation-Reprocess) Zero sludge –Reprocess all Zero steam leak- Steam traps/flanges tightness
01-Oct-13 19Raj Sharma
Start up Outline
• Methodology & Sequence –Define ,Microplan
• Focus - Project basis, P&IDs, Hazops, Manpower (Team
coker),Training
• Expedite - Engineering
• Ensure -- Procurement in time
• Quality Assurance -Construction, Systemwise priority ,
Milestones, Critical Paths, ‘S’ Curve
• Essential- Proving – Precommissioning , RFSU
• Safety – PSSR, DCS, Startup
• Maximize –Revenue by operational excellence01-Oct-13z 20Raj Sharma
BuildingTeamCoker.Process/Operation/Maintenance. Organogram
EPCO Team concept. (Engg/Project/Construction/O&M. Focus on Safety/Quality/schedule/operability
Integration within and Other Refinery units/Upstream/downstream/Utilities Teams
Define clear responsibility to each team member. Set defined targets for everyone.
01-Oct-13 21Raj Sharma
Select Process Licensor earlyAssist Project group Process Package/Layout/PFD/P&ID/Hazops
Assist Engineering group EPC/Engineering/Equipment Data sheet/PDS
Model/ISOs review /Spools/Fabrication
Assist procurement group Equipment PR/Procurement/Vendor packages
01-Oct-13 22Raj Sharma
Assist Construction group
System-sub system- owners
Priority/Schedule/Equipment preservation, Erection/QA, QC Alignment/Hydrotest loops/PMI
Mechanical completion/Check Lists/Internals/Gaskets/Flushing/Cleaning/
Steam blow/RFC
01-Oct-13 23Raj Sharma
Operation preparedness.Operating-manuals/SOP,SMP/Training manual/Safety manualCommunication/safety permit/shift /Licensor/manpower /op-shelters
DCS-system Graphics, Alarm priority, Inter-connectivity
Operator Training/on site/Simulator/validation/learning from incidents
System proving including vendor packages and instrumentation, safety interlocks
01-Oct-13 24Raj Sharma
PSSR-Include all systems like electrical sub station, PIB, safety systems like fire/gas detectors
Hydrocarbon-In/Refractory dryout/Circulation RFSU Commissioning/Feed Cut In/Product–out Stabilization/Test Run
01-Oct-13 25Raj Sharma
Major startup Pitfalls PMI – misses Heater coke up,Heater tube failure/BMS
failures/Burner extinguish Coke drum foam over- Level problems/Delays
in Cycle, Fractionator upsets/level losses/Feed failures
01-Oct-13 26Raj Sharma
Identify right block- measures Flange leakages/opening-measures Wrong operation of coke drum-measures,
valves-interlock/Isolators Power failure-Tarry drum Utilities failure – Control fractionator temp Pump seal failures- seal selection, plan Pump failures due to strainer chock up-hot
circulation-more time Compressor failures
01-Oct-13 27Raj Sharma
Expansion loops fouling with other piping-measures taken
Water hammers –steam headers Steam traps malfunctions-heater coke up Heater pass flow failures. Heater trips Coke drum cave in- shot coke problems Cutting tool jamming- experience manpower
01-Oct-13 28Raj Sharma
Coke drum hot spot/Blow over Fire at Blow down tower/air coolers Fire–MOC-PMI misses Down stream units upsets- product storage-air
cooler sudden expansion Gas/H2S leakages Sampling errors Bad line breaks Coke drum cycle delays
01-Oct-13 29Raj Sharma
Check valves in wrong direction Fire at coke drums- Safety valve blows Products going off specs. LPG, Naphtha Coke cutting Hose failures-Hose quality Instrument ferrules leakages- Hydrotest
problems HPV/LPD vibration cracks- gusset support-
engg standards
01-Oct-13 30Raj Sharma
COKER COMPLEX
01-Oct-13 31
WE WILL MAKE IT HAPPEN …Raj Sharma
•Commissioned 5 Cokers in the world,Including IOCL, KNPC & Reliance Jamnagar.
•Enhanced capacity by 140% - 175000bpd • Reduced Coke drum cycle to 12 hrs
•Contact : [email protected]•Mobile: +91 8130577115•Landline : +91 124 2219558• 11,Birch Court, Nirvana Country, Gurgaon (122018)
01-Oct-13 Raj Sharma 33
INDIA - DELAYED COKERS AT GLANCE
Sl No DISCRIPTION LICENSOR LOCATION CAPACITY BPDYEAR OF START COKE DRUMS Unheading System Completion
(A) INDIAN COKERS
1 Reliance Industries Limited -- Coker 1 FWUSA Jamnagar Gujrat 161000 1999 8 DELTA 1999
2 Reliance Industries Limited -- Coker 2 FWUSA Jamnagar Gujrat 175000 2009 8 DELTA 2009
3 Essar Oil Limited ABB LUMMUS Jamnagar Gujrat 60000 6 DELTA 2010
4 IOC Baroda ABB LUMMUS Baroda Gujrat 71204 2010 4 ZIMMERMAN JENSON 2010
5 BPCL/Oman Petroleim-Joint venture ABB LUMMUS Bina M.P 60000 2010 4 ZIMMERMAN JENSON 2010
6 HPCL/Mittal ABB LUMMUS Bhatinda Punjab 60000 2012 4 ZIMMERMAN JENSON 2012
7 IOC Barauni - 2 Units EIL Baurani Bihar 30000 1984 2 MANUAL TROLLY 1985
8 IOC Bongaigaon EIL Bongaigaon Assam 30000 1981 2 MANUAL TROLLY 1980
9 IOC Bongaigaon EIL Bongaigaon Assam 30000 1990 2 MANUAL TROLLY 1990
10 IOC Assam EIL Assam 30000 1990 2 MANUAL TROLLY 1990
11 Oil India Limited OLD Assam Digboi 5000 1942 2 MANUAL TROLLY 1945
12 IOC Gauhati EIL Gahauti Assam 25000 1977 2 MANUAL TROLLY 1967
13 IOC Panipat ABB LUMMUS Panipat Haryana 60000 2005 4 HAAN & CLAY 2008
14 MRPL Manglore ABB LUMMUS Manglore Karnataka 60000 4 ZIMMERMAN JENSON 2014
15 BPCL Cochin ABB LUMMUS Cochin Kerala 60000 4 ZIMMERMAN JENSON 2015
16 IOC Paradeep Orissa FWUK Paradeep Orissa 74000 4 DELTA 2014
17 Chennai Petroleum ABB LUMMUS Chennai Tamilnadu 40000 2 2015
18 IOC Mathura Projected Uttar Pradesh
19 IOC- Haldia Projected Bengal
Blowdown 1
Blowdown 2
01-Oct-13 Raj Sharma 35
PRE-START-UP SAFETY REVIEW CHECKLIST
DATE Annexure1
PLANT
EQUIPMENT / SYSTEM
SR NO DESCRIPTION Supporting Documents STATUSYES/NO REMARKS
1.0 SAFETY AND HEALTH
1.1 “General” Safety
1.1.1 Has adequate and appropriate PPE (Personal Protective Equipment)been specified and provided in control room, field, SFE / FE porta cabin? PSCL
1.1.5 Are points of isolation clearly marked/labelled and readily accessible? PSCL
1.1.6 Have bump/trip hazards been identified and all sharp edges removed? PSCL
1.1.7 Has proper guarding, handrails/barriers, been provided to prevent falls? PSCL
1.1.8 Are Safety Showers and Eye Wash facilities provided, adequate & operational? PSCL
1.1.9 Has sufficient lighting been provided so that operation, servicing, maintenance and repair of the facility can be carried out safely? PSCL
1.1.10 Are display systems for providing operational instructions, safety warnings and emergency information provided and positioned so that they are clearly visible and easily read? PSCL
01-Oct-13 Raj Sharma 36
01-Oct-13 Raj Sharma 37
R01 R02 R03 R04 R05 R06R07 R08
C01FRACTIONATOR
C02/03
372-C01
HP FLARE KO DRUM
C02
COKE CUTTING WATER TANK
SLUDGE TANK
HEATER FO3
FRES
H FE
ED
HEAT
ER
COKE PIT MT-371-02
Blowdown Tower
U/G SLO
P TANKB.D.HEATER
B.D. SETTLING
DRUM
STRIPPER
COMPRESSOR
STRIPPER REBOILER
ABSORBER/STRIPPER
SP. ABSORBER
LEAN/RICH SP OIL H E
DEBUT REBOILER
DEBUT REBOILER
DEBUTANISER
LLP FLARE KO DRUM
AMINE SUMP TANK
UNSAT FG KO DRUM
AMINE ABSORBER
AMINE KO DRUM
FG KO DRUM
SLOP OIL HEATER
HCN COOLER
LCN COOLER
N/S O/H RECEIVER
NAPHTHA SPLITTER N.S. REBOILER
WASH WATER DRUM
AMMONIUM POLY S DRUM
V30V33
U/G SLOP TANKS
MP STEAM GEN.
LP STEAM GEN.
LP STEAM GEN.
Blowdown Tower
B.D. HEATER
B.D SETTLING DRUM
B.D CIR. OIL
COO
LER
372-P16 A/B
372-P05 A/B
372-P06 A/B
372-P04 A/B
372-P02 A/B/C
372-P03 A/B
372-P01A/B
371-P10A/B
371-P16A/B
371-P09A/B
371-P18 A/B
HCN PUMP
371-P13A-D
371-
P15A
/B/C 371-P11 A/B
371-P12 A/B
371-P14 A/B
CHAR
GE
PUM
P
371-P17A/B
APHAPHAPHAPH
COKE CUTTING PUMP
371-P03A/B/C
371-
P04A
/B
371-
P05A
/B
P22
A/B/
C
P24
A/B
P23
A/B
COKE PIT MT-371-01
MP-371-P08 A/B/E MP-371-P08 C/D
372-A01
372-A03
371-A04
371-A03
371-A05 371-A02371-A01
LLP
FLAR
E CO
OLE
RHP
FLA
RE
COO
LER
SPONGE COOLER
LEAN
OIL
CO
OLE
RNA
PH
O/H
CO
ND.
LCG
O P
/A
COO
LER
LCG
O
COO
LER
HCG
O
COO
LER
B/D CONDENSER B.D CONDENSERB/D CIR.
OIL COOLER
STRUCTURE-B
COMP SUC. K.O DRUM
STRIPPER REBOILER
ABSORBER INTER COOLER
372-P18 A/B
372-A05
371-A08
371-A07
LEAN AMINE COOLER
372-P11 A/B/C
MP STEAM GEN.
LP STEAM GEN.
LP STEAM B/D DRUM MP STEAM B/D DRUM
KERO DRUM
FLARE SYS. SEAL POT
ANTIFOAM PACK DE-EMUL.
PACK
FD FAN
ID FAN
FD FAN
ID FAN
FD FAN
ID FAN
FD FAN
ID FAN
HEATER FO2
HEATER FO1
HEATER FO4
371-
P55A
/B
371-
P54A
/B
371-
P53A
/B
Z371-P21A/B
P36 A/B/C
371-P02 A/B/C
CRUSHER-I CRUSHER-II
PG KOD
UTILITY BOOSTER PUMP
DELTA VALVE WS PUMP
372-A02
FRESH FEED HEATER
SITE OFFICE
WORK SHOP
CONTRACTOR OFFICE
DINI
NG
HALL
FOUR DRUM START UP
UNSAT FG AA FEED COOLER
QUENCH WATER PUMP
STRUCTURE-A
371-A06
N.S. REBOILER
SUBSTATION
Z300 - 30
PIB - 57
371-V17 A/B/C
Z371-V28
CT - 03
Fresh feed Heater
Z371 F 05
MAPS PACKAGE POLY FLOW PACKAGE
V24 A/B/C
Z371-F07
FLUSHING OIL TANK
NEUTRALIZING AMINE PACKAGE
FILMING AMINE PACKAGE
CCD ICCD II
LEGEND
NORTH
EWSOUTH
E-14S 06A
E-17S 05A
E-16S 06
E-15S 05
E-18S 10
Early startup –entry control
Z371 under Operation
Z371 under Construction
Z372 under Operation
01-Oct-13 38
PHASE 1 AREA
PHASE 2 AREA
ENTRY GATE
BARRICADING WITH TIN SHEETS
SECURITY
Raj Sharma
R01 R02 R03 R04 R05 R06R07 R08
C01FRACTIONATOR
C02/03
372-C01
HP FLARE KO DRUM
C02
COKE CUTTING WATER TANK
SLUDGE TANK
HEATER FO3
FRES
H FE
ED
HEAT
ER
COKE PIT MT-371-02
Blowdown Tower
U/G SLO
P TANKB.D.HEATER
B.D. SETTLING
DRUM
STRIPPER
COMPRESSOR
STRIPPER REBOILER
ABSORBER/STRIPPER
SP. ABSORBER
LEAN/RICH SP OIL H E
DEBUT REBOILER
DEBUT REBOILER
DEBUTANISER
LLP FLARE KO DRUM
AMINE SUMP TANK
UNSAT FG KO DRUM
AMINE ABSORBER
AMINE KO DRUM
FG KO DRUM
SLOP OIL HEATER
HCN COOLER
LCN COOLER
N/S O/H RECEIVER
NAPHTHA SPLITTER N.S. REBOILER
WASH WATER DRUM
AMMONIUM POLY S DRUM
V30V33
U/G SLOP TANKS
MP STEAM GEN.
LP STEAM GEN.
LP STEAM GEN.
Blowdown Tower
B.D. HEATER
B.D SETTLING DRUM
B.D CIR. OIL
COO
LER
372-P16 A/B
372-P05 A/B
372-P06 A/B
372-P04 A/B
372-P02 A/B/C
372-P03 A/B
372-P01A/B
371-P10A/B
371-P16A/B
371-P09A/B
371-P18 A/B
HCN PUMP
371-P13A-D
371-
P15A
/B/C 371-P11 A/B
371-P12 A/B
371-P14 A/B
CHAR
GE
PUM
P
371-P17A/B
APHAPHAPHAPH
COKE CUTTING PUMP
371-P03A/B/C
371-
P04A
/B
371-
P05A
/B
P22
A/B/
C
P24
A/B
P23
A/B
COKE PIT MT-371-01
MP-371-P08 A/B/E MP-371-P08 C/D
372-A01
372-A03
371-A04
371-A03
371-A05 371-A02371-A01
LLP
FLAR
E CO
OLE
RHP
FLA
RE
COO
LER
SPONGE COOLER
LEAN
OIL
CO
OLE
RNA
PH
O/H
CO
ND.
LCG
O P
/A
COO
LER
LCG
O
COO
LER
HCG
O
COO
LER
B/D CONDENSER B.D CONDENSERB/D CIR.
OIL COOLER
STRUCTURE-B
COMP SUC. K.O DRUM
STRIPPER REBOILER
ABSORBER INTER COOLER
372-P18 A/B
372-A05
371-A08
371-A07
LEAN AMINE COOLER
372-P11 A/B/C
MP STEAM GEN.
LP STEAM GEN.
LP STEAM B/D DRUM MP STEAM B/D DRUM
KERO DRUM
FLARE SYS. SEAL POT
ANTIFOAM PACK DE-EMUL.
PACK
FD FAN
ID FAN
FD FAN
ID FAN
FD FAN
ID FAN
FD FAN
ID FAN
HEATER FO2
HEATER FO1
HEATER FO4
371-
P55A
/B
371-
P54A
/B
371-
P53A
/B
Z371-P21A/B
P36 A/B/C
371-P02 A/B/C
CRUSHER-I CRUSHER-II
PG KOD
UTILITY BOOSTER PUMP
DELTA VALVE WS PUMP
372-A02
FRESH FEED HEATER
SITE OFFICE
WORK SHOP
CONTRACTOR OFFICE
DINI
NG
HALL
FOUR DRUM START UP
UNSAT FG AA FEED COOLER
QUENCH WATER PUMP
STRUCTURE-A
371-A06
N.S. REBOILER
SUBSTATION
Z300 - 30
PIB - 57
371-V17 A/B/C
Z371-V28
CT - 03
Fresh feed Heater
Z371 F 05
MAPS PACKAGE POLY FLOW PACKAGE
V24 A/B/C
Z371-F07
FLUSHING OIL TANK
NEUTRALIZING AMINE PACKAGE
FILMING AMINE PACKAGE
CCD ICCD II
LEGEND
NORTH
EWSOUTH
E-14S 06A
E-17S 05A
E-16S 06
E-15S 05
E-18S 10
Escape route & Assembly points (Contd)
Normal Wind direction – From West01-Oct-13 39
PHASE 1 AREA
PHASE 2 AREA
ESCAPE ROUTE
ASSEMBLY POINT
Raj Sharma
Sys System Description Oct'07No. PREREQUISITES 9 11 13 15 17 19 21 23 25 27 29 31
SYS REQD FROM CONST ON
RAW MATERIAL REDYNESS
FLUSHING BY
371-SO Office space 01.03.07 NA NA
371-SOA Porta cabin
371-SOB Site office space
371-SOC CCR ofice
371 C&T Communication & Transportation 01.03.07 NA NA
371 C&T-1 Telephone,Plant radio
371 C&T-2 PC network
371/372-ELE Electricity 15.10.07 NA NA
371/372-ELE-A Electric sub station charging SS charging
371/372-ELE-B Emergency power generator
371/372 LT Plant lighting system 15.10.07 NA NA Plant lighting charging
371-CS Storm water sewer(CS) 10.10.07 NA 2 Storm water sewer(CS)
371-OS Oily sewer(OS) 10.10.07 NA 3 Oily sewer(OS)
371-SH Closed drain(SH&SC) 10.10.07 NA 12 Closed drain(SH&SC)
371-CA Chemical drain 10.10.08 NA 2 Chem drain
371-CP Coke pit / maze 10.10.07 NA 2 Drain to maze
371-WF Fire water 10.10.07 NA 2 Fire water
371-WU Utility water 01.11.07 NA
371-WD Potable water/Drinking water 20.10.07 NA 2 Potable water
371-WC Cooling tower/ CT 3 10.12.07 NA
371-WP Process water 15.11.07 NA
371-BFW MP&LP BFW 20.01.08 NA
371-BFW HP BFW 20.02.08 NA
01-Oct-13 Raj Sharma 40
01-Oct-13 Raj Sharma 41
Overall Construction Progress - JERP COKER (Unit 371 / 372)
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
2007 2008
PlanFront AvlActualPlan 1
01-Oct-13 42Raj Sharma
01-Oct-13 Raj Sharma 43
Flanges not aligned
01-Oct-13 44Raj Sharma
Misaligned flanges will result in leakage
01-Oct-13 45Raj Sharma
Low Point Drains Need Valves
01-Oct-13 46Raj Sharma
Low Point Drains Need Valves
01-Oct-13 47Raj Sharma
Small bore pipe needs bracing for strength
01-Oct-13 48Raj Sharma
The Right Gasket can be identified by color coding
01-Oct-13 49Raj Sharma
The Right Gasket Will Fit Properly in The Right Flange
01-Oct-13 50Raj Sharma
Proper nuts and bolts can be verified with stamp
01-Oct-13 51Raj Sharma
01-Oct-13 52
Coke drum vapor inlet nozzle
No provision for installation of Heat shield
Raj Sharma
01-Oct-13 53Raj Sharma
01-Oct-13 54Raj Sharma
01-Oct-13 55
POSITIVE MATERIAL IDENTIFICATION
Raj Sharma
01-Oct-13 Raj Sharma 56
01-Oct-13 Raj Sharma 57
01-Oct-13 Raj Sharma 58