Facility Planning and Development Mendota Unified School District 2012 - 2022 Long Range Facilities Master Plan
Transcript
Page 1: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

Facility Planning and Development

Mendota

Unified School District

2012 - 2022 Long Range Facilities Master Plan

Page 2: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota
Page 3: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 3

Board of Trustees:Jose Zavala, PresidentAraceli Perez, Vice PresidentLupe Flores, ClerkJesus Zavala, MemberIsmael Herrera, MemberDiana Toscano, MemberIsabel Maldonado, Member

Superintendent:Michael Crass

Mendota Unified School District115 McCabe Street | Mendota, Ca 93640559.655.4942 | www.musdaztecs.com

Page 4: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota
Page 5: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 5

Table of Contents >> Superintendent’s Statement 7

Executive Summary 9• Introduction•Master Plan Process• Background• Implementation and Review•History

Educational Objectives and Goals 13

Planning Process 24

Facilities Master Plan 28• Completed Projects• Planning Assumptions Summary• Summary of Facility Recommendations

•Short Term•Long Term

• Project Phasing•Cost Analysis• Timeline

Appendix (separate document)A. Demographic StudyB. State Funding EligibilityC. Educational SpecificationsD. Condition Assessment – McCabe ESE. Condition Assessment – Washington ES

Page 6: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota
Page 7: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 7

I am delighted to announce the completion of our 2012 Facilities Master Plan.This plan, when implemented over the next decade, will guide the MendotaUnified School District’s facilities into the next 20 years with modernized,expanded, and new facilities to allow our great teaching staff to continue thework of educating our students across the District.

Through fiscally prudent decisions over the last 20 years, our District has beengreat stewards of the Communities funds and have been able to build both anew High School and a new Junior High School, however, there is still much toaccomplish to bring our facilities into alignment with our educational vision ofproviding the best learning environment for the students of Mendota. Inaddition, our District is poised to continue its growth as the housing marketbegins to return again in the next few years – our Demographic study suggeststhat we need to prepare to educate an additional 1000 students by the year2022. Further, once the River Ranch Development begins in approximately2022, we may expect an additional 1000 students bringing our Districts totalenrollment to approximately 5,000 students. I believe that it is important tocontinue what we started in the District to make all of our facilities among thevery best in the State for our students in Mendota – they deserve the best.

The Master Plan lays out some remarkable and much needed facilitiesimprovements over the next 20 years. Some of the highlights of this wellthought out plan are as follows:

• Secure land and construct a third elementary school to eliminate theovercrowding at Washington elementary School and to prepare for the pendinggrowth of our community over the next 10 years.

• Modernize both McCabe and Washington Elementary Schools to bring theminto the 21st century learning environment standards.

• Convert all Elementary schools to Pre-K - 6

• Add a new building at the high school to accommodate an additional 300students

• Begin discussions with the City of Mendota on a possible joint use AquaticsCenter and Performing Arts Center at the high school.

• Plan for our fourth elementary school between 2022 and 2030 as well asfurther expansions of both the high school and the junior high school.

• Optimize the energy efficiency of the school facilities through sustainabledesign methods and install solar power generation systems to reduce theoperational costs of the Districts facilities.

• Maintain the cutting edge technology in the classrooms through a technologyrefresh fund

We are fortunate in the Mendota Unified School District to have a forwardthinking Board of Education that have the incredible foresight to invest in thelearning environments of their students which clearly demonstrates theircommitment to their students and community. It also shows their fullunderstanding that excellent facilities can greatly assist the teaching staff toincrease the academic achievement of their students.

I believe that it is critically important that the District embrace theserecommended improvements and rally our Community to continue their greatsupport of the District through the implementation of this Master Plan that willallow school facilities to meet modern educational standards of the 21st century.

Sincerely,Mike CrassSuperintendent of Schools

Superintendent’s Statement >>

District Wide Facilities Master Plan

Page 8: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota
Page 9: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9

The Mendota Unified School District is committed to maintain educationalfacilities at a level that enables our teachers to meet the needs of 21stcentury learners. Facilities affect teaching and learning, student and staffhealth, day-to-day building operations, and the long-rage fiscal health ofthe entire educational organization. Thus the purpose of this document isto provide a master plan to meet the challenges of effective facilitiesmanagement. It is simply too big of a job to be addressed haphazardly.

The needs of the community and students drive planning for educationalprograms and support services. In turn, the demands of educationalprograms and support services drive facility planning. In recognition of thisrelationship, the development of this master plan began with assessment ofcommunity needs followed by analysis of the District’s ability to meet thoseneeds. The findings from this process of analysis led to recommendations

contained in the facilities plan found here. The proposed solutions arerealistic and resourceful.

The District is striving to deliver programs and services addressing theevolving needs of all segments of the community and recognizes the impactfacilities have on the teaching and learning process and on workingconditions. In an effort to accommodate the academic needs of thecommunity, the District continues to pursue funding strategies for schoolconstruction and modernization. The purpose of the Master Plan is todisseminate to decision makers and the community the result of planningefforts of the District.

Executive Summary >>

Introduction

Executive Summary >>

Page 10: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects10

DEC/JAN2011/2012

2012MASTER

PLAN

FOUNDATION

INTEGRATION OF CURRICULUM & FACILITIES

OTHER KEY PROCESSES

ConditionAssessments

Step No. 2

InformationGatheringStep No. 1

EducationalSpecifications

Joint UseDiscussions

Purchase of new site(s)

Maintenance &OperationsStandards

Executive Summary >>

Master Plan Process>>

Page 11: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 11

District staff worked closely with the City of Mendota and consultants in thedevelopment of the Facilities Master Plan. The following reports werecompleted and used as resources in the creation of this Master Plan:

• Information Gathering and Facilities Conditions Assessments

• MUSD Educational Specifications and Sustainable Standards

• Demographic Study

• State Funding Eligibility Update

• Joint Use Discussions with the City of Mendota

• Site Selection Process

The Master Plan is intended to guide the development of the District’sFacilities for the next 10 to 20 years. During that time, a continuation ofdemographic changes can be expected. These changes could be of suchmagnitude as to prompt revision of this plan. It is, therefore, important thatthe District continue its planning efforts and be proactive to the changingneeds of students and other constituents. The flexibility of this plan can beexpected to make the District more efficient and effective.

The District will continue to seek input from its staff and community to helpensure this plan adequately meets the needs of the District and its studentsin the coming years.

Executive Summary >>

Background Implementation and Review

Executive Summary >>

Page 12: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects12

Executive Summary>>

HistoryMendota is a city with dynamic growth located in Fresno County, California,United States. The population was 11,014 at the 2010 census. The State Routes180 and 33 run through the agricultural city. Mendota is located 8.5 miles (14km) south-southwest of Firebaugh, at an elevation of 174 feet (53 m).

(Source: http://en.wikipedia.org/wiki/Mendota,_California )

Mendota Unified School District is a small rural district in the heart of theCentral Valley. The District was formed on April 4, 1893. School enrollment wasapproximately twenty-five students. No transportation was provided by theschool district until 1920. First an automobile was used, and then two buseswere purchased in 1937.

The district unified in 1987, and one hundred years after the founding of theMendota School District, Mendota High School was built to retain young peoplein Mendota to complete their k-12 educational program locally.

In 2012 with total population of 2,860 students, there are 2 elementary schools,1 junior high school, 1 high school and 1 alternative/independent study facility.

Executive Summary >>

Page 13: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 13

• Design facilities that address and support educational program needs.• Create superior teaching and high performance, indoor and outdoor

learning environments that support the intellectual success of everystudent and enhance the quality of student life.

• Develop facilities that balance functionality with safety and securitywith designs that respect the surrounding community.

• Design campuses with clear way-finding and provide safe pedestrianand vehicular access-ways.

• Design facilities that address evolving educational program needs.• Instill community pride.

• Design for flexible use of spaces with the future in mind.• Integrate technology of today and plan ahead for the technology of

the future.• Build technology into learning spaces including classrooms, Library/

Media Centers, and other common areas.• See District facilities as long term investments. Utilize life cycle

planning and decision making strategies.

• Commit to responsible use of resources in construction as well asoperations.

• Promote sensible use of renewable and alternative energy. Embracesustainable technologies.

• Implement guidelines from CHPS (Collaborative for High PerformanceSchools) and/or LEED (Leadership in Energy and EnvironmentalDesign)for schools as criteria for projects.

•Lower maintenance and operating costs by specifying materials andproducts that meet the District's performance, durability,maintainability, and sustainability goals.

• Utilize site specific building design and orientation to focus on energyefficiencies that will drive appropriate building and mechanicalsystems selections

• Exhibit responsibility toward the environment and use of limitedDistrict financial resources through implementation of energyefficient, sustainable design practices

Educational Objectives and Goals >>

Provide Quality Learning Environments

Have a Long Term Vision

Build & Maintain Sustainable Campuses

Educational Objectives and Goals >>

Page 14: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects14

Educational Objectives and Goals >>

WHY improve existing school facilities?

• Student Achievement• Provide Safe and Healthy Learning Environment• Provide 21st Century Learning Environment

• Protect Existing Assets• School Assets• Property Value

• Comply with legal requirements

Educational Objectives and Goals >>

Page 15: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 15

Educational Objectives and Goals >>

WHAT will it be like? The 21st Century Classroom

• Safe

• Healthy

• Flexible

• Technology Enhanced

• Home of I-Kids

• Student-Centric

Educational Objectives and Goals >>

Page 16: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects16

• Wireless Internet Access

• Projection: Digital Screen built into the wall

• Smart board

• Tablet PC

• Computing system

• DVD/CD/Cable TV

• Holographic Display System

• Printer

Educational Objectives and Goals >>

WHAT will it be like? Today’s Classroom Technology

Educational Objectives and Goals >>

Page 17: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 17

Educational Objectives and Goals >>

Page 18: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects18

Learning Environment >>Each learning studio supports a wide range of learning modes.Windows create reading nooks and computer corners bring technologydirectly into the classroom. Each studio is open through transparent,but acoustically isolated walls to the shared project commons spaces.Windows and indirect natural light from the project commons bring inabundant and natural light.

Educational Objectives and Goals >>

The Learning Studio: The Classroom Redefined

Educational Objectives and Goals >>

Page 19: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 19

Educational Objectives and Goals >>

Page 20: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects20

Physical Environment >>The neighborhood setting of the school requiresthoughtful integration of the outdoor environment.Early in the planning process, we identify specificintelligence types, including bodily kinesthetic andnaturalist. The design incorporates the entire site withinthe learning environment, integrating indoor andoutdoor spaces, instead of separating them.

Educational Objectives and Goals >>

Bringing the classroom outside

Educational Objectives and Goals >>

Page 21: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 21

Physical Environment >>Through extensive daylighting and transparency, the outdoorenvironment is often accessible and visually stimulating forstudents. Outdoor spaces with tables are used as classrooms,and garden areas can provide hands-on learningopportunities.

Educational Objectives and Goals >>

Educational Objectives and Goals >>

Natural Connections

Page 22: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects22

1. Safety

2. Educational Resources

3. Academic Focus

4. Intrinsic Motivation

5. Teacher Effectiveness

6. Comfort /Facility Standards

7. Peer Behavior

8. Learning Space

9. Parent Involvement

Educational Objectives and Goals >>

What factors affect student achievement?

Educational Objectives and Goals >>

*highlighted factors are affected by the built environment

Page 23: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 23

Educational Objectives and Goals >>

Page 24: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects24

Planning Process >>

Master Plan Methodology New Construction

A facilities master plan allows a school district to assess its facilities needsand prioritize its goals for addressing those needs. Therefore, thisFacilities Master Plan is a document that should constantly be reviewed,re-evaluated, and, if necessary, revised.

In collaboration between the Board of Trustees, District Administrationand consultants the following District-wide goals were established:

• Ensure that all classrooms are safe

• Bring all classrooms into 21st Century Learning Environments

• Maintain Flexibility (Financial, Facilites etc.)

• Allow Options for Increasing Capacity to accommodate futuregrowth in the community

• Establish/Maintain Parity throughout the District

• Reduce the Number of Portable Classrooms

• Increase Outdoor Learning Opportunities

• Reduce Transportation Costs

• Maximize Joint Use Opportunities with the City and otherAgencies

• Green our Schools: reduce operational costs

BCA has also prepared the District-Wide Educational Specifications aspart of the Master Planning Process. These Educational Specifications(required by the California Department of Education) will serve as abasis of design for the District’s third and fourth elementary school.This document describes essential relationships, size andprogrammatic requirements for educational and administrativefacilities and the application of these specifications will help ensurethat new facilities are equipped to meet District Educational Goals andObjectives. The following District Facility Standards have beenestablished to guide the design of the new elementary school.

Planning Process >>

Page 25: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 25

Planning Process >>

Summary of District Facility Standards for New Elementary Schools

• Pre-K - 6:- 800 Student Capacity (32 classrooms)- Design utilities and support spaces for future expansion to 1,000 Student Capacity (40 classrooms)-Average of 10-15 acre Site

• 1-Story Construction

• Efficiently planned site including:- 48-80 parking stalls per site (1.5 – 2 per CR)- Bus Drop-off Lane- Student Drop-off Lane- Kindergarten Drop-off Lane- Full Kindergarten Playground- 1.25 Acre, grade 1-6, asphalt playground-1.3 – 1.5 Acre Turf playground or Adjacent Park

• All classroom sizes to meet Title 5 California Department of Education Guidelines

• Technology integration in the classrooms

• High Performance Schools (Sustainability) for all new construction

• Outdoor Learning Environments

• Optimize the Sites Open Space

• Way Finding: Clear defined school entrance and Administration Office.

• Noise and Access Control: Buildings used as buffers.

• Campus Security: Reduce points of entry onto the campus to keep students safe and accounted.

• Layout to make instructional sense (i.e. avoid losing instructional time due to travel time).

• Provide a school that makes our parents and students feel welcome and comfortable.

Planning Process >>

Page 26: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects26

Planning Process >>

Master Plan Methodology Modernization and Addition ProjectsThrough detailed Conditions Assessments prepared to date for the District(as part of the master planning process), we have established “modernizationpriorities”, that will guide the Mendota Unified School District throughproper “scoping” of both McCabe Elementary and Washington ElementarySchools modernizations to the estimated construction costs. The followingpriorities were presented to the Board in the February 13, 2012 BoardMeeting:

Priority 1: Code, health, safety

Priority 2: InfrastructureBuilding shell integritySite utilities

Priority 3: ClassroomsClassroom renovationsNew construction for education program spacesAthletic programsTechnology

Priority 4: Miscellaneous modernizationsSupport facilitiesOutdoor spacesGeneral facility improvements

Planning Process >>

Page 27: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 27

In the McCabe and Washington Elementary School Modernizations, we are focused on how we can accomplish the following:

• Increase Student Achievement through the creation of Safe and Healthy Learning Environments (i.e. 21st century learning environments, sustainable design, etc).

• Protect Existing Assets to keep them from losing value over time through deterioration.

• Comply with Legal and Safety Requirements such as ADA, Building Code,Hazardous Materials.

• Life Cycle Cost analysis to assess the cost of modernization vs. newconstruction thereby allowing the District to make informed decisions bothnow and in the future on the costs of their facilities projects today andtomorrow.

Planning Process >>

Master Plan Methodology Modernization and Addition Projects

Planning Process >>

Page 28: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects28

Facilities Master Plan >>

Projects completed 1989-2010

Major improvements to all school campuses were accomplished in the past 20years. The District completed the following facilities new construction andmodernization projects:

1989 McCabe Elementary School: Modernization of Administration building,Multi-Purpose building, 6 classrooms buildings (700, 800, 900, 1000, 1100and 1300)

1989 Washington Elementary School: Modernization of all permanent buildings

1991 Construction of New High School campus, the first high school in the townof Mendota. This modern facility consists of Administration/MediaCenter, 26 teaching spaces, Multi-purpose building, Gymnasium and aStadium. New vocational center is currently in construction.

2006 Construction of New Junior High School campus. The campus facilitiesinclude: Administration/Media Center, 28 teaching spaces and Multi-purpose building.

2006 McCabe Elementary School: Modernization of Multi-Purpose building, 6classrooms buildings (500, 600, 700, 1000, 1100 and 1300)

2008 Modernization of the High School

2010 McCabe Elementary School: the exteriors of all buildings were painted andthe roof of the cafeteria was replaced

Technology Upgrades All elementary school classrooms are equipped withSmartboard technology, Laptops for students and Laptop chargingstations.

Facilities Master Plan >>

33

180

18033

33

J1

180

JH HS

McC

AB

E

WASHINGTON

Page 29: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 29

1,072 Students

Facilities Master Plan >>

Planning Assumptions (Provided by Davis Demographics)

Facilities Master Plan >>

Page 30: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects30

TOTAL (incl. Pre-School)

ENROLLMENT(2012)

CAPACITY(2012)

McCabe ES (Grades 3-6) 853 850

Washington ES (Grades K-2) 860 400

OVERCROWDED(2012)

3

460

Washington ES (Pre-School) 45 25 15

MendotaJunior High 419 720

MendotaJunior High 737 780

2,914 2,775 478

Facilities Master Plan >>

33

180

18033

33

J1

180

JH HS

McC

AB

E

WASHINGTON

Facilities Master Plan >>

Permanent Capacity of Existing School Campuses

Page 31: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 31

Facilities Master Plan >>

Short Term Projections •2,869 Current 2012 enrollment (includes 463 current overcrowding at Washington)

• 1,072 Additional Students expected by 2022 (per Davis Demographics)

• 3,941 Expected enrollment by 2022 (current district enrollment + expected growth per Davis Demographics)

Total Expected Short Term Increase: 1,535 students (1,072 additional students + 463 current overcrowding)

ES (K-6) 921 additional students (60% of total students)

JH (7-8) 154 additional students (10% of total students)

HS (9-12) 460 additional students (30% of total students)

Long Term Projections • 2,869 Current 2012 enrollment (includes 463 current overcrowding at Washington)

• 1,072 Additional Students expected by 2022 (per Davis Demographics)

• 940 additional students expected with the build out of River Ranch Development – not expected to begin until after 2022(per Davis Demographics)

• 4,881 Expected enrollment beyond 2022 (current overcrowding + short term student increase + River Ranch Development student increase)

Total Possible Long Term Increase: 2,475 students (1,535 students from short term increase + 940 students expected with the build outof River Ranch Development – not expected to begin until after 2022)

ES (K-6) 1,485 additional students (60% of total students)

JH (7-8) 247 additional students (10% of total students)

HS (9-12) 743 additional students (30% of total students)

Facilities Master Plan >>

Planning Assumptions Summary

Page 32: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects32

Facilities Master Plan >>

Summary of Projects

SHORT TERM

LONG TERM

High School Modernization and Addition Project- Complete Fall 2017-2018

Modernize McCabe-Complete Fall 2015

New Elementary Construction Project-Complete Fall 2014

SHORT TERM PROJECTS

STEP 1

STEP 2

Modernize Washington-Complete Fall 2016

STEP 3

STEP 4

LONG TERM PROJECTS (River Ranch Development)

STEP 5 Future New Elementary School and Junior High & High School Modernization and Addition Projects - 2022-2032

Facilities Master Plan >>

Page 33: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 33

Facilities Master Plan >>

Short Term Master Plan Projects 2012-2022The primary short term goal is to provide sufficient number of permanentclassrooms and eliminate current overcrowding at WashingtonElementary School. With the construction of a new (third ) elementaryschool additional 800 seats will be provided. Parity is critical betweenelementary schools for all districts, to implement this all three elementaryschools will accommodate grades Pre-K - 6.

Secondary short term goal is to maintain all of the school facilities at thehigh standards expected by the community. Modernizations of McCabeand Washington Elementary Schools will facilitate improvements to thesafety, energy efficiency , and maintenance of the school sites.

Third short term goal is to create a learning environment where every

student will have access to personal computing devices and other tools towork collaboratively and creatively with their peers throughout the schoolday. Both, McCabe and Washington, school sites to receive electrical andcomputer network systems upgrades needed to install robust wirelessnetworks that will allow all students to have appropriate access to web-based resources throughout the school campus.

The new elementary school to receive “smart walls” and casework thatfacilitates the technology used in a 21st century classroom environment.Modernizations of McCabe and Washington Elementary schools to includecabinetry replacement to mirror the efficient and functional classroomcabinetry in the new elementary school.

Facilities Master Plan >>

*numbers represent student capacity at each campus

Page 34: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects34

• 1-Story Construction

• Efficiently planned site including:- 48-80 parking stalls per site (1.5 – 2

per CR)- Bus Drop-off Lane- Student Drop-off Lane- Kindergarten Drop-off Lane- Full Kindergarten Playground- 1.25 Acre, grade 1-6, asphalt

playground- 1.3 – 1.5 Acre Turf playground or

Adjacent Park

• All classroom sizes to meet Title 5 California Department of Education Guidelines

• Technology integration in the classrooms

• High Performance Schools (Sustainability) for all new construction

• Outdoor Learning Environment

• Optimize the Sites Open Space

• Noise and Access Control: Buildings used as buffers.

• Campus Security: Reduce points of entry onto the campus to keep students safe and accounted.

• Layout to make instructional sense (i.e. avoid losing instructional time due to travel time).

• Provide a school that makes our parents and students feel welcome andComfortable.

• Design for installation of a 260kW solar power system

THIRD NEW ELEMENTARY SHORT TERM MASTER PLAN

Grade Level

Student Capacity

Ability to Surge

Total Campus Site

Athletic Fields

Total Building Area

Classrooms

Portable Classrooms

Average Classroom Size

Parking Spaces

Pre-K - 6

800

1000

10-15 acres

3 acres

60,000 sf

32

0

960 S.F.

48-80

“ B u i l d i n g S c h o l a r s , L e a d e r s a n d C h a m p i o n s ”

KEY FEATURES

Facilities Master Plan >>

* hypothetical site and school layout

PROJECTED CONDITIONS

Page 35: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 35

McCABE ELEMENTARY MODERNIZATION SHORT TERM MASTER PLAN

250 S. Derrick Blvd.Mendota, CA 93640Tel: (559) 655-4262 Before:

After:

1. NEW OUTDOOR LUNCHSHELTER

2. REMOVE (E) PORTABLES

“ B u i l d i n g S c h o l a r s , L e a d e r s a n d C h a m p i o n s ”

Date of original construction: 1940’sDate of last modernization: 2006

Enrollment 2011/12: 853Campus site: 30 acreTotal Building Area: 59,000 sfClassrooms: 40Portable Classrooms: 8Average Classroom Size: 960 sfParking Spaces: 62 (incl. 9 ADA)

Existing Grade Level: 3-6Proposed Grade Level: Pre-K - 6

Existing Capacity (Permanent): 840Existing Capacity (Portables): 192Proposed Capacity : 800-1000 3. INSTALL SOLAR PANELS

3

2

1

Facilities Master Plan >>

PRIORITY 1- Code, Health, Safety• An automatic, addressable fire alarm system from

a single manufacturer should be installed• Hazardous materials inspection by certified firm

prior to finalizing modernization scope of work• An allowance for Seismic Upgrades to be included

in modernization scope• New energy efficient heating and ventilating

systems

PRIORITY 2- Envelope, Site Utilities• Repair/Replace roofing• Replace doors• New energy efficient lighting systems (lights,

sensors and automatic controls)

PRIORITY 3- Classrooms• New floor, wall and ceiling finishes• New casework and furniture to allow for

differentiated instruction• Telephone/Intercom System- update the

telephone system to a new voice over the IP telephone system

• Public Address System- new system to be installed• Clock System- the system should be extended to

include all of the campus• Computer Network System- sufficient wireless

access to each classroom and teaching space• Television Distribution System- install new IP

based television broad cast system• Intrusion Detection System- install new unified

and updated intrusion alarm system with new door contacts and motion sensors

PRIORITY 4- Miscellaneous• Play areas to be resurfaced; new playground

equipment• Energy Efficiency audit• Solar Energy Generating system in parking lots

SCOPE OF WORK

Page 36: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects36

WASHINGTON ELEMENTARY MODERNIZATION SHORT TERM MASTER PLAN

1599 Fifth StreetMendota, CA 93640Tel: (559) 655-4365 Before:

After:

“ B u i l d i n g S c h o l a r s , L e a d e r s a n d C h a m p i o n s ”

Date of original construction: 1952Date of last modernization: 1989

Enrollment 2011/2012: 905Campus site: 6.43 acreTotal Building Area: 25,470 sfClassrooms: 17Portable Classrooms: 23Average Classroom Size: 960 sfParking Spaces: 30 (incl. 3 ADA)

Existing Grade Level: Pre-K - 2Proposed Grade Level: Pre-K - 6

Existing Capacity (Permanent): 424Existing Capacity (Portables): 575Proposed Capacity: 400-600

PRIORITY 1- Code, Health, Safety• An automatic, addressable fire alarm system from

a single manufacturer should be installed• Hazardous materials inspection by certified firm

prior to finalizing modernization scope of work• An allowance for Seismic Upgrades to be included

in modernization scope• New energy efficient heating and ventilating

systems

PRIORITY 2- Envelope, Site Utilities• Repair/Replace roofing• Replace doors• New energy efficient lighting systems (lights,

sensors and automatic controls)

PRIORITY 3- Classrooms• New floor, wall and ceiling finishes• New casework and furniture to allow for

differentiated instruction• Telephone/Intercom System- update the

telephone system to a new voice over the IP telephone system

• Public Address System- new system to be installed• Clock System- the system should be extended to

include all of the campus• Computer Network System- sufficient wireless

access to each classroom and teaching space• Television Distribution System- install new IP

based television broad cast system• Intrusion Detection System- install new unified

and updated intrusion alarm system with new door contacts and motion sensors

PRIORITY 4- Miscellaneous• Play areas to be resurfaced; new playground

equipment• Energy Efficiency audit• Solar Energy Generating system in parking lots

SCOPE OF WORK

Facilities Master Plan >>

2. REMOVE (E) PORTABLES

3. INSTALL SOLAR PANELS

2 3

1. NEW OUTDOOR LUNCHSHELTER

1

Page 37: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 37

SHORT TERM

• No improvements needed• Install Solar Panels

MENDOTA JUNIOR HIGH SHORT TERM MASTER PLAN

Grade Level

Enrollment (2011-2012)

Original Construction Date

Date of Last Modernization

Total Campus Site

Athletic Fields

Open Space

Total Building Area

Classrooms

Portable Classrooms

Average Classroom Size

Parking Spaces

7-8

419

2006

N/A

28 acres

7 acres

2 acres

56,502 sf

28

0

900 S.F.

71/ 4 ADA

1258 Belmont Ave.Mendota, CA 93640Tel: (559) 655-4301

SCOPE OF WORK

1

“ B u i l d i n g S c h o l a r s , L e a d e r s a n d C h a m p i o n s ”

EXISTING CONDITIONS (2011-2012)

Facilities Master Plan >>

Before:

After: 1. INSTALL SOLAR PANELS

1

Page 38: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects38

MENDOTA HIGH SCHOOL SHORT TERM MASTER PLAN

Grade Level

Enrollment (2011-2012)

Original Construction Date

Date of Last Modernization

Total Campus Site

Athletic Fields

Total Building Area

Classrooms

Portable Classrooms

Average Classroom Size

Parking Spaces

9-12

737

1991

2008

45.9 acres

23.7 acres

36,823 sf

26

7

930 S.F.

270 / 11ADA

1282 Belmont Ave.Mendota, CA 93640Tel: (559) 655-1993

SCOPE OF WORKBefore:

After:

“ B u i l d i n g S c h o l a r s , L e a d e r s a n d C h a m p i o n s ”

• Add (10) classroom wing• Install Solar Panels

EXISTING CONDITIONS (2011-2012)

Facilities Master Plan >>

• All classroom sizes to meet Title 5 California Department of Education Guidelines

• Technology integration in the classrooms

• High Performance Schools (Sustainability) for all new construction

• Outdoor Learning Environment• Optimize the Sites Open Space• Noise and Access Control: Buildings

used as buffers.

KEY FEATURES

1. NEW (10) CLASSROOM WING

2. INSTALL SOLAR PANELS

1

2

Page 39: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 39

Facilities Master Plan >>

Long Term Master Plan Projects: 2022-2032

2

33

33

DER

RIC

K A

VE

W BELMONT AVE

DER

RIC

K A

VE

180

180

33

J1

400-600

800-1000

800-1000

800-1000

1,400800

Dependent upon the build out of the River RanchDevelopment the student population will increase by 940students.

• Plan for our fourth elementary school between 2022 and2032 as well as further expansions of both the high schooland the junior high school.

• Optimize the energy efficiency of the school facilitiesthrough sustainable design methods and install solarpower generation systems to reduce the operational costsof the Districts facilities.

• Maintain the cutting edge technology in the classroomsthrough a technology refresh fund .

*numbers represent student capacity at each campus

Facilities Master Plan >>

Page 40: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects40

• Add (10) classroom wing

MENDOTA JUNIOR HIGH LONG TERM MASTER PLAN

Grade Level

Enrollment (2011-2012)

Original Construction Date

Date of Last Modernization

Total Campus Site

Athletic Fields

Open Space

Total Building Area

Classrooms

Portable Classrooms

Average Classroom Size

Parking Spaces

7-8

419

2006

N/A

28 acres

7 acres

2 acres

56,502 sf

28

0

900 S.F.

71/ 4 ADA

1258 Belmont Ave.Mendota, CA 93640Tel: (559) 655-4301

SCOPE OF WORKBefore:

After:

1

“ B u i l d i n g S c h o l a r s , L e a d e r s a n d C h a m p i o n s ”

EXISTING CONDITIONS (2011-2012)

• All classroom sizes to meet Title 5 California Department of Education Guidelines

• Technology integration in the classrooms

• High Performance Schools (Sustainability) for all new construction

• Outdoor Learning Environment

• Optimize the Sites Open Space

• Noise and Access Control: Buildings used as buffers.

KEY FEATURES

Facilities Master Plan >>

Page 41: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 41

MENDOTA HIGH SCHOOL LONG TERM MASTER PLAN

Grade Level

Enrollment (2011-2012)

Original Construction Date

Date of Last Modernization

Total Campus Site

Athletic Fields

Total Building Area

Classrooms

Portable Classrooms

Average Classroom Size

Parking Spaces

9-12

737

1991

2008

45.9 acres

23.7 acres

36,823 sf

26

7

930 S.F.

270 / 11ADA

1282 Belmont Ave.Mendota, CA 93640Tel: (559) 655-1993

SCOPE OF WORKBefore:

After:

“ B u i l d i n g S c h o l a r s , L e a d e r s a n d C h a m p i o n s ”

• Add (10) classroom wing• Joint use Performing Arts Center• Joint use Aquatic center

EXISTING CONDITIONS (2011-2012)

• All classroom sizes to meet Title 5 California Department of Education Guidelines

• Technology integration in the classrooms

• High Performance Schools (Sustainability) for all new construction

• Outdoor Learning Environment

• Optimize the Sites Open Space

• Noise and Access Control: Buildings used as buffers.

KEY FEATURES

Facilities Master Plan >>

1. NEW (10) CLASSROOM WING

12

2. JOINT USE PERFORMINGART CENTER

3. JOINT USE AQUATICCENTER

3

Page 42: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects42

• 1-Story Construction

• Efficiently planned site including:- 48-80 parking stalls per site (1.5 – 2

per CR)- Bus Drop-off Lane- Student Drop-off Lane- Kindergarten Drop-off Lane- Full Kindergarten Playground- 1.25 Acre, grade 1-6, asphalt

playground- 1.3 – 1.5 Acre Turf playground or

Adjacent Park

• All classroom sizes to meet Title 5 California Department of Education Guidelines

• Technology integration in the classrooms

• High Performance Schools (Sustainability) for all new construction

• Outdoor Learning Environment

• Optimize the Sites Open Space

• Noise and Access Control: Buildings used as buffers.

• Campus Security: Reduce points of entry onto the campus to keep students safe and accounted.

• Layout to make instructional sense (i.e. avoid losing instructional time due to travel time).

• Provide a school that makes our parents and students feel welcome andComfortable.

• Design for installation of a 260kW solar power system

FOURTH NEW ELEMENTARY LONG TERM MASTER PLAN

Grade Level

Student Capacity

Ability to Surge

Total Campus Site

Athletic Fields

Total Building Area

Classrooms

Portable Classrooms

Average Classroom Size

Parking Spaces

Pre-K - 6

800

1000

10-15 acres

3 acres

60,000 sf

32

0

960 S.F.

48-80

“ B u i l d i n g S c h o l a r s , L e a d e r s a n d C h a m p i o n s ”

KEY FEATURES

Facilities Master Plan >>

* hypothetical site and school layout

PROJECTED CONDITIONS

Page 43: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota
Page 44: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects44

Step 3: Move all 850 (grades 3-6) students from McCabe to the New school

Step 2: Build New K-6 Elementary School with capacity 800-1000 students and accommodations for 2 pre-school classrooms

Step 1: Secure new site for new school (site shown is tentative)

Facilities Master Plan >>

Phase 1- Short Term (Complete Fall 2014)

Facilities Master Plan >>

Page 45: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 45

Step 1: Modernize McCabe and convert to Pre-K - 6

Step 2a: Move 400 students (grades 3-6) from the New ES back to their permanent home at McCabe

Step 2b: Move 450 students (grades K-2) from Washington to their permanent home at McCabe

Step 2c: Move 450 students (grades K-2) from Washington to their permanent home at the New ES

Facilities Master Plan >>

Phase 2- Short Term (Complete Fall 2015)

Facilities Master Plan >>

Page 46: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects46

Step 2: Distribute students among three Elementary Schools

1. New Elementary School: estimated enrollment 970 students

2. McCabe Elementary: estimated enrollment 800 students

3. Washington Elementary: estimated enrollment 400 students

Step 1: Modernize Washington Elementary and convert to Pre-k - 6

Facilities Master Plan >>

Phase 3- Short Term (Complete Fall 2016)

Facilities Master Plan >>

Page 47: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 47

Step 1: Build new (10) classroom wing at High School forpredicted surge in student population

Facilities Master Plan >>

Phase 4- Short Term ( Complete 2017-2018)

Facilities Master Plan >>

Page 48: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects48

Step 1: Build fourth New K-6 Elementary School to accommodate growth from the River Ranch Development.Expected growth: 564 students

Step 2: Expansion of Junior High to accommodate possible growth from the River Ranch Development. Expected growth: 93 students.

Step 3: Expansion of High School to accommodate possible growth from the River Ranch Development.Expected growth: 283 students

Facilities Master Plan >>

Phase 5- Long Term (Complete Fall 2022-2025)

Facilities Master Plan >>

Page 49: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 49

High School Modernization and Addition Project-Complete Fall 2017-2018

Future New Elementary School

Modernize McCabe-Complete Fall 2015

New Elementary Construction Project-Complete Fall 2014

SHORT TERM PROJECTS:

1

2

Modernize Washington-Complete Fall 2016

3

4

5

Junior High Expansion 5

High School Expansion5

LONG TERM PROJECTS – RIVER RANCH:

Total District Enrollment (2022): 4,000

Total District Enrollment (2032): 5,000

Facilities Master Plan >>

Put Classrooms where they’re Needed

Facilities Master Plan >>

Page 50: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects50

GOAL 2: Modernize McCabe & Washington

GOAL 1: Build New Elementary School

MODERNIZATION TOTAL BUDGET: $18,800,000

PRIORITY 1- Code, Health, Safety

PRIORITY 2- Envelope, Site Utilities

PRIORITY 3- Classrooms

MODERNIZATION- Total Estimated CostMcCABE 12,500,000WASHINGTON 6,300,000

$18,800,000

*ALL ESTIMATES ARE IN 2012 DOLLARS AND INCLUDE:

GCOH&P (GENERAL CONTRACTOR) 15%CONSTRUCTION CONTINGENCY 5%SOFT COST BUDGET (NEW CONSTRUCTION) 20%SOFT COST BUDGET (MODERNIZATION) 25%

DOES NOT INCLUDE CONSTRUCTION COST ESCALATION

Recommendations >> Short Term Master Plan Projects

NEW CONSTRUCTION TOTAL BUDGET: $25,000,000

GOAL 3: Modernization and Addition of the Mendota High School

ADDITION (10 classrooms) TOTAL BUDGET: $4,500,000

Addition of 10 classrooms (12,000 sf)Estimated Cost $ 4,500,000

Total Estimated Cost $ 4,500,000

Recommendations >>

Page 51: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 51

GOAL 2: Modernization and Addition Mendota Junior High and High School

GOAL 1: Build New (fourth) Elementary School

NEW CONSTRUCTION TOTAL BUDGET: TBD

Junior High Modernization and Addition of 10 classrooms (12,000 sfNew Construction)Estimated Cost TBD

High School Modernization Addition of 10 classrooms (12,000 sf New Construction)Estimated Cost TBD

Total Estimated Cost TBD

Recommendations >> Long Term Master Plan Projects

Recommendations>>

GOAL 3: Joint-Use Projects (cost shared with the City of Mendota)

Aquatic CenterEstimated Cost TBD

PACEstimated Cost TBD

Total Estimated Cost TBD

Page 52: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects52

Go Bond $ 19M

District Funds $ 10M

State Funding (New Construction) $ 19M

State Funding (Modernization ES) $ 2M

State Funding (Modernization HS) $ 0.5M

State Funding (HPI) $ 0.5M

State Funding (Service Site) $ 2M

Developer Fees

Short Term (excluding River Ranch Development) $ 7.4M

Total estimated available funds to 2022: $ 60.4M

TOTAL ESTIMATED AVAILABLE FUNDS TO 2022

Recommendations >>

Recommendations >>Short Term Master Plan Projects

Page 53: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 53

Recommendations >>Summary of Short Term Master Plan Projects

NEW ELEMENTARY SCHOOL• School Site TBD $ 25.0M

MODERNIZATION PROJECTS• McCabe ES $ 12.5M• Washington ES $ 6.3M

ADDITION• Mendota HS $ 4.5M

TECHNOLOGY REFRESH • District Wide $ 0.75M

DEFERRED MAINTENANCE • District Wide $ 0.75M

CONSTRUCTION COST ESCALATION (3%/year)

• District Wide $ 3.2M

TOTAL: $ 53.0MAVAILABLE FUNDS: $ 60.4MDIFFERENCE $ 7.4M (back to District reserves)

Recommendations>>

Page 54: Mendota Unified School District - Home | BCA Architectsbcaarchitects.com/wp-content/uploads/2016/07/Mendota...MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects 9 The Mendota

MUSD Facilities Master Plan >> 2012–2022 >> BCA Architects54

Recommendations >>Master Plan Project Timeline

Recommendations >>


Recommended