Method Statement 4a; Operational Interface Contents Part 1. Description of Site(s)/Service 1.1. Opening hours 1.2. Timetable of scheduled closures 1.3. Site(s) components 1.3.1 Processing plant a) Waste reception and handling b) Feed chute and shut-off door c) Waste feeder d) Incinerator grate system e) Combustion air distribution f) Bottom ash discharger g) Boiler and power generation h) Inconel i) Refractory j) Infrared camera k) Grate siftings handling system 1) Hydraulic power system m) Combustion air supply n) Forced draught fans o) Air heater p) Auxiliary burner q) Heat recovery r) Access doors, inspection holes s) Cleaning equipment t) Ash hoppers u) Safety valves v) Steam and water piping w) Boiler water treatment x) Power generation plant and auxiliaries y) Air condenser z) Condensate system aa) Air pollution control equipment bb) Ash handling cc) SCADA system dd) Electrical ee) Emissions monitoring ff) Instrumentation 1.3.2 Waste vehicle turnaround 5 ...6 6 11 11 12 14 14 15 17 17 19 24 24 24 24 25 25 26 26 26 27 27 27 28 28 31 31 32 40 40 44 45 46 .57 Method Statement 4a Operational Interface 1
Transcript
Page 1: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

Method Statement 4a; Operational Interface

Contents

Part 1. Description of Site(s)/Service

1.1. Opening hours

1.2. Timetable of scheduled closures

1.3. Site(s) components 1.3.1 Processing plant

a) Waste reception and handling b) Feed chute and shut-off door c) Waste feeder d) Incinerator grate system e) Combustion air distribution f) Bottom ash discharger g) Boiler and power generation h) Inconel i) Refractory j) Infrared camera k) Grate siftings handling system 1) Hydraulic power system m) Combustion air supply n) Forced draught fans o) Air heater p) Auxiliary burner q) Heat recovery r) Access doors, inspection holes s) Cleaning equipment t) Ash hoppers u) Safety valves v) Steam and water piping w) Boiler water treatment x) Power generation plant and auxiliaries y) Air condenser z) Condensate system aa) Air pollution control equipment bb) Ash handling cc) SCADA system dd) Electrical ee) Emissions monitoring ff) Instrumentation

1.3.2 Waste vehicle turnaround

5 ...6

6 11 11 12 14 14 15 17 17 19 24 24 24 24 25 25 26 26 26 27 27 27 28 28 31 31 32 40 40 44 45 46

.57

Method Statement 4a Operational Interface

1

Page 2: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r -] ry^ (•amt mk

1.3.3 Wori^ing with local authorities 59 1.3.4 Contract waste handling philosophy 59 1.3.5 Operation maintenance and inspection 61 1.3.6 General access items 61 1.3.7 Traffic management plan 63 1.3.8 Non-authorised vehicle procedures 63 1.3.9 Waste transport plan 64 1.3.10 Product outputs (monthly and annual) 66

1.4. Site security 66

1.5. Waste handling procedures 69

1.6. Incoming waste procedure 70

1.7. Spillages 72

1.8. Non-contract waste 74

Part 2. Information 75

2.1. Management information systems 75 2.1.1 Computerised data handling system 75 2.1.2 Recorded data list 76 2.1.3 Council access 78

2.2. Plans 81 2.2.1 Contingency plan updates 81 2.2.2 Complaints 81

Parts. Visitor Centre 83

3.1. Operation of the centre 83

3.2. Maintenance of the centre 85

Part 4. Waste transfer and haulage 86

4.1. Transfer and haulage 86

4.2. Site signage and notices 87 4.2.1 Proposed Plant/Site(s) Entry Signs 87 4.2.2 Traffic Signs 88 4.2.3 Off-Site Signage 89

Part 5. Management of products and residues from contract waste 90

5.1. Nature, classification and destination of residues and secondary products 90

5.2. Markets 92

5.3. National indicators 94

Page 3: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r^crtm #OXFORDSHIRE COUNTY COUNCIL

[ Your courK-.i! lax vvot-king fcr yau

5.4. Disposal 95

Method Statement 4a Operational Interface

3

Page 4: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

^ L1 H

Part 1. Description of Site(s)/Service

1.1. Opening hours

Subject to the Planning and Environmental Permit, the Facility will be available for the Acceptance of

Contract Waste between 07.00 and 20.00 Mondays to Fridays and 07.00 to 16.00 on Saturdays. The Facility

will not Accept Contract Waste on Sundays. The Facility will process Contract Waste 24 hours a day, 7 days

a week.

An Environmental Permit has now been awarded and the full details will be updated within the Method

Statement on receipt of the Permit.

1.2. Timetable of sciieduled closures

Scheduled closures of the Facility will amount to up to 5 days in every operational year where both boilers

will be down. There will be, in each operational year, a period of 14 days when one boiler is down with one

boiler operational. The maximum the steam turbine downtime will be approximately 6 days. Further

discussions with CNIM will be held to ensure that we minimise any downtime impact during the outage

periods. . Details of the maintenance plan are set out in MS-5 and details of the Annual Maintenance Plan in

Schedule 11. The Martin GMBH moving grate is designed to operate safely and efficiently over a twenty year

design life with minimum maintenance and before the first major re-build. The Facility has a design life of 30

years.

For a typical annual detailed maintenance plan please refer to Appendix MS4a-2f and Method Statement 5

(Planned Maintenance).Table MS4a-2 below indicates the expected service life of major Works components

and systems.

Page 5: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

W) '' m im ®SfeOXFORDSHlRE ^P*COUNTY COUNCIL

www.axfordslliregow-uk

[ Your counc il lax v/crk'ng for you

SERVICE LIFE BY EQUIPMENT ITEM 1

Sheet 1

FURNACE -

FLUE GAS

COOLING -

ANCILLARY

EQUIPMENT

Equspnrent descnption Waste reception and handling equipment

Weighbndge - Weighing station

Overhead cranes and grabs

Other handling equipment

Furnace Furnace (grate)

Combustion anallaries (ducting, fans, burners, etc.)

Heat recovery installations

Boilers

Ancillaries {pipework, cleaners, etc )

Steel franiework, walkways, stairs, platforms

Boiler Feed pumps

Ash Disposal

Conveyors and Loading Equipment

Ferrous sorting

Other

Miscellaneous equipment

Water treatment, demineralisation process

Water treatment, deaerator

Fuel oil storage & distnbution and fuel oil pump

Compressed asr

Special machinery - lifting gear

Effluent treatment

Measurement - Control - Regulation

HV eiectrical installations

Supply station and transformer

Standby Supply

CCTJ monitoring

1 he Contractor shall list the mandatory options in the same detail as per this Service Lit

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

Year

e table.

Ser/ice life

30

30

10

30

20

30

20

30

20

10

10

10

20

20

20

15

N.'A

20

10

30

30

30

10

Comments

Table MS4a-2: Service life of major components and systems

The above Table MS4a-2 demonstrates the level of detail that will go into the maintenance and renewal plan.

This aspect is further developed in Method Statement 5 Maintenance

1.3. Site(s) components

The Facility design will be sufficiently flexible to allow for the acceptance of a wide range of vehicles

throughout the Contract Period. Please refer to the Transport and Traffic Management Plan (Appendix

MS4a-2g) for details on compatibility of the proposed solution with collection and delivery systems of the

Authorised Users. The Transport and Traffic Management Plan will be further developed on receipt of further

Transport details from the Authority.

Method Statement 4a Operational Interface

5

Page 6: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

mil 1.3.1 Processing plant

A full list of key items is detailed in CNIM's Scope of Supply and Battery Limits Document, which is

presented in Appendix l\/IS4a-2h.

The CNIM scope of supply includes the following main components:

• Waste reception and handling equipment;

• Weighing station;

• Tipping hall equipment;

• Waste processing;

• Waste pit equipment;

• Combustion plant and boilers including Martin reverse acting grate system;

• Primary and Secondary air fan and drive;

• Air pre-heat, air ducts and expansion joints;

• Auxiliary fuel firing equipments;

• Bottom ash handling and storage system;

• FGR handling and storage system;

• Air pollution control (APC) equipment;

• Plume reduction system;

• Power generation plant;

• Auxiliary systems; and

• Visitor Centre.

Waste reception and handling

Collection vehicles arriving at the Facility will be weighed on a computerised Weighbridge. The computerised

system will record vehicle weights and issue waste transfer tickets indicating:

Date;

Description of Waste (including EWC code);

Gross, tare, and net weights;

Disposal contractor number;

Page 7: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

Registered Contractor Waste/Ad Hoc Waste carrier number;

Source/destination of waste/product/residue;

Time of arrival/departure;

Vehicle registration number; and

Driver name and reference number.

CCTV cameras will be positioned to view the front and rear of vehicles on each Weighbridge at the Site.

Audio visual communication will be provided between the Weighbridge and the central control room. The

weighbridge operator will also conduct visual assessments of the Contract Waste delivered to the Facility as

defined in Schedule 29 (the Waste Acceptance Protocol).

The waste will then be delivered to the fully enclosed tipping hall (see Figure MS4a-1 below), where it will be

tipped into the refuse bunker via one of nine unloading bays.

:J: 1 i

M. WMPIM^MBI I »" •.•-.'-••k-^n^jthtnifi'p

..—IJI^ i.M,|l

Figure MS4a-1: Tipping iiall schematic

Method Statement 4a Operational Interface

7

Page 8: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r;t^ift

Figure MS4a-1: Tipping hall schematic

The refuse bunker will be made of reinforced, waterproof concrete and will be sized to ensure three days of

waste storage without stacking and almost five days with stacking based on the total throughput of the

Facility. A design schematic of the waste bunker is presented in Figure MS4a-2 below.

Page 9: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

Waste PIT

J * of slnEOTrisI 2

Worts PJT »to-n («/ 1 5 ^ Warte pr depth jrei: KJSO

Kaits-SiajasjiziztJaAalJ

V'ta-n •: 1S.08

Figure MS4a-2: Waste bunker schematic

Each unloading bay will be provided with traffic lights, located so as to be visible by truck drivers reversing

into the bay, to control traffic flows from the central control room and avoid congestion.

The waste bunker will be served by two identical hydraulically powered orange peel grab cranes (see Figure

MS4a-3 below). The cranes are designed to mix, stack and cast waste in the pit, to ensure that the waste

loaded into the hopper has a constant calorific value, as far as possible. The grabs and cranes will be

designed to transfer the average daily waste delivery into the feed hoppers in a twelve hour period. The

capacity of the grab will be sized to allow less than thirty five grab loadings per hour during the twelve hour

period.

Method Statement 4a Operational Interface

9

Page 10: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r.cY9

Figure MS4a-3: Grab crane schematic

The cranes will be designed for semi-automatic and manual operation by two different operators from two

separate operator positions. In semi-automatic mode, the cranes will discharge the grabs automatically into

the pre-programmed feed hopper positions, once the grabs have been loaded by the operators. The cranes

and grabs will be capable of simultaneous operation in two directions in the horizontal plane while raising

and lowering the grabs in the vertical plane. Appropriate design features will be employed to minimise grab

swing. A load cell weighing system for each grab will enable the operator to record the weight of each grab

load before discharge into the feed chute. Only such wastes as are acceptable for processing shall be tipped

into the bunker (i.e. those deemed acceptable under the terms of the Waste Acceptance Protocol). Inevitably

some erratic components will be identified within the waste mass in the bunker and these will be removed

using the crane grab for shredding or rejection from Site.

A shredding system for bulky household waste will be provided in order to reduce such items to a suitable

size for input into the incinerator and reloading hopper. All bulky items than can be shredded will be

shredded. The shredder will be located to one side of the bunker at the North East side in a position

accessible to the crane grabs. The output from the shredder will be positioned above a loading chute to allow

the shredded waste to be deposited into the bunker. The feed hopper provides a wide sloping feed entry and

diverging chute section. For the design of the hoppers, particular attention has been paid to the following

operational issues:

• Minimisation of noise emissions from the hopper into the boiler house and the tipping hall;

• Avoidance of accumulations of waste around the feed hopper and on the feed hopper floor; and

10

Page 11: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r»^^B mmsmmim ^t^^COUm\ COUNCIL

[_ Youj- council tax v.'grbng fci'yc;

• Minimisation of dust and waste being blown from the hopper.

The dimensions of the hopper are greater than those of the grab when fully open, and are such that sufficient

clearance is always provided around the grab during feeding operations.

The edges at the top of the hopper will be approximately 1 m above the surrounding floor to form a solid

balustrade with free access on three sides for manual stoking if the hopper becomes obstructed. Stoking and

clearing of the hoppers will not disturb the furnace feeding operations.

To reduce noise generated by refuse falling into the hopper, an erosion proof rubber sheet will be fitted

inside the hopper.

The feed chute beyond the hopper will be configured to prevent plugging (within practical limits) when

handling waste. When the plant is operational, the feed chute will be kept fully loaded. The waste contained

in the feed chute acts as a seal to the furnace inlet, preventing cold air from entering and disrupting the

design furnace combustion conditions. The storage capacity of the chute will be designed to permit cyclic

charging operations by maintaining a seal between each charge of waste delivered into the chute.

Waste is fed from the bottom end of the feed chute, over a step at the furnace inlet and onto the grate by a

hydraulically powered reciprocating feeding unit. The step causes the waste to tumble onto the grate and

disseminates material which may have become slightly compacted during passage through the feed chute.

Feed chute and shut-off door

The chute covers the full width of the furnace grate and is made of mild steel plate, suitably stiffened and

adequately supported. The feed chute is slightly divergent from top to bottom to enable the waste to be more

easily decompressed.

The shut off door Is actuated by a hydraulic cylinder which will be located in a recess at the top of the feed

chute.

The gate is placed at the bottom of the hopper and will be designed to resist mechanical and thermal stress.

The hydraulic operation will be remotely controlled from the control room with an automatic interlock.

All the components of the actuating system will be located outside the feed chute

Waste feeder

The pusher will be robustly constructed from high quality steel with a cast chrome steel nosing. Surface

materials will be designed to cater for the impact of refuse falling from the feed hopper. The pusher is

supported at the rear on roller bearings and is moved back and forth by hydraulic cylinders. Parallel motion

of the pusher is maintained by specially designed guides. A moveable end fixture compensates for lateral

expansion of the pusher which may result from temperature fluctuations.

Method Statement 4a Operational Interface

11

Page 12: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r ,lit 3 -H

The nose of the pusher and the table will be fitted with cast steel bars. Riddling passing through the bars is

pneumatically conveyed to the ash discharger.

• The flow of refuse entering the incineration grate can be adjusted by modulating:

• The number of strokes per minute; and

• The length of the stroke.

An oil leakage collecting tank is provided below the cylinders.

Incinerator grate system

The Contractor has selected a Martin GMBH moving grate incorporating the following features:

• The moving grate bars are reverse acting to ensure good mixing, combustion and flame position

control;

• The grate bars are made from high-grade alloy material to close tolerances;

• The grate bars are shaped and have a special movement to reduce clinker formation

• Expansion devices are incorporated which correctly maintain grate bar openings.

These features, all of which can be adjusted for control, enable the Martin grate to give a consistent

performance with a wide range of waste types, and to have a long trouble free life. These features also

provide combustion control, which, in terms of quality and flame position, is essential for consistent boiler

performance.

The reverse action of the grate bars prevents refuse from tumbling down the grate without ignition. The grate

bars control the movement of refuse and constantly mix it. This ensures rapid drying of the incoming refuse,

as the raw refuse is mixed with the burning mass. Hence, the full grate becomes an effective drying area as

the refuse moves down the grate.

This movement has the effect of continuously rotating the mixing of the red hot burning mass so that it is

pushed back underneath the fresh fuel being fed onto the front end of the stoker grate. This constant turning

of the burning mass enables a homogeneous bed to be formed and promotes a volatile fire at the head of

the grate.

The grate action prevents the formation of excessive hot spots and excessive clinker build-up. It is also this

grate action, which provides the high quality of burn out from the Martin system.

The close control of flame location also enables the flame exit from the grate to be accurately placed into the

furnace combustion area. It is into this area that secondary over fire air is introduced. This and the shape of

the furnace wall, results in a turbulent action which prevents unburned gases and odours from escaping and

being carried through to the chimney. This feature also helps to further reduce any paper char carry over.

12

Page 13: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

^. ,.„,m^ \.»,, W .,„^^BF

ifeoXFORDSHlRE sfea'cOUNTY COUNCIL

Having controlled the main area of combustion, the bottom end of the grate provides an area for final burn

out and a margin for better burning of dense objects. The grate bar elements are made from machined high-

grade chrome steel alloy castings and are capable of withstanding high temperatures. Thus a precise

alignment of bars is achieved and the openings for combustion air accurately sized.

The gap between bars is limited to about 2 per cent of the total grate surface. A certain amount of siftings

and fine ash can fall through and the standard Martin collecting system for these fines is built in beneath the

grate, feeding them to the bottom ash discharge system.

As a result of the Martin system of combustion control, the amount of unburned fines which fall through the

grate is very small. The spacing between bars is accurately maintained by the use of expansion bars fitted to

the sides of the grate. This allows the spacing to be maintained under varying temperature conditions.

Another important feature of the Martin grate is the combustion air system. Combustion air is supplied by a

forced draught fan, which feeds into a multi-compartment plenum. The amount of air flowing into each

compartment can be adjusted to meet the precise combustion requirements.

The primary air flows into the burning waste layer through gaps approximately 2mm wide between the heads

of adjacent bars. These small air gaps form a very high resistance and ensure uniform air distribution over

the surface of each grate zone. As a result of these design features, "craters or cold spots do not occur in the

refuse bed, thus avoiding poor combustion and high dust content in the flue gases. This arrangement for

distribution and control enables maintenance of a constant pressure, which ensures even distribution over

the complete grate area.

A discharge mechanism, in the form of a roller, controls the rate of discharge and depth of the bed of burning

refuse on the grate, and can be adjusted and controlled for varying conditions. The incinerator grate is set at

an angle of 26° and consists of three run sections divided into steps.

The grate surface consists of high grade heat resisting chromium steel alloy grate bars and plates with very

narrow apertures between the bars to control the air distribution over the full area of the grate.

The side faces of the bars are machined to achieve even, uniform widths of air gaps between adjacent bars

and are arranged to prevent spreading of individual bars. At the side of the grate section, self-compensating

expansion blocks are included to prevent binding of the grate bars due to heat expansion.

This enables a constant air gap to be maintained and ensures that the openings for combustion air are

limited to approximately 2 per cent of the grate surface. The openings in the Martin grate bar design are set

at the front of the bar where combustion air spreads over the whole underside of the fire bed, regardless of

any dense objects.

Method Statement 4a Operational Interface

13

Page 14: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r*^iB Combustion air distribution

The Martin combustion air system regulates and controls combustion air under stable air pressure

conditions. Constant under fire air pressure is maintained automatically at the grate inlet by controlling the

inlet tilting blades of the combustion air fan.

Combustion air is distributed from the fan through ductwork and the air heater, into the separate air zone

compartments/hoppers fitted to the underside of the grate. All compartments have individual orifices covered

by dampers. All dampers will be remote controlled and actuated by motorised actuators. Each damper may

be individually regulated, if necessary, for particular fire-bed conditions.

Bottom ash discharger

The Martin bottom ash discharger unit is a device especially developed for quenching and handling the

bottom ash. It has the following advantages:

• It is of extremely robust construction and designed for arduous duty and continuous operation;

• It is compact and takes up little floor space;

• It is a small water trough, but this is more than adequate for residue quenching and conditioning so that

conveyors can then easily handle the residue;

• It has powerful reciprocating rams, hydraulically operated with variable speed control to push out the

residue at the desired rate;

• It has no chains or flights, therefore jamming problems are virtually eliminated and wearing problems

are avoided;

• It provides a gas seal to the incinerator and prevents ingress of air and egress of dust and fumes;

• It has few mechanical components, therefore system reliability is dependable and surveillance and

maintenance requirements are minimal

• It is driven through one or several hydraulic cylinders.

Water consumption is controlled at the optimum requirement for quenching and conditioning, so that when

the residue is finally discharged, its water content is only about fifteen to twenty per cent of the dry residue

weight depending on residue quality.

The ash discharger is composed of two main parts, a structural steel body and a mechanical ram. It is

robustly constructed in steel plate, heavily ribbed to form a watertight trough, with surfaces exposed to the

residue being covered with steel lining plates. The trough is filled with recycled process water, and the water

level is automatically maintained with a suitable level control device. This equipment is located so that

maintenance operations can be carried out externally without difficulty.

14

Page 15: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

¥^>Mt The ash discharger receives the bottom ash, inerts (metal, etc.), and the heavy dust and ash particles that

fall out of the gas flow during its passage through the boiler.

Boiler and power generation

Main concept of the CNIM horizontai boiler

The boiler is of the natural circulation horizontal type, one drum bottom supported, with passes and water

walls integral with the furnace as presented in Figure MS4a-9 below.

CNIM ENViRONNEMENT

Drum ,.,-jr

I Waste

"«!?*:•: " • -_' ~ — I '"•— ' ' "1

Feed hopper '

\

Superheated steam

Expansion duct

Feeder

Underf i re a i r ^-J- Bottom ash

Figure MS4a-9: Boiler principle

• First pass: radiant combustion chamber, empty vertical pass

• Second pass: vertical pass, with six evaporator panels

• Third pass: horizontal pass, with convective superheaters

• Fourth pass: vertical pass, with economiser bundles;

• Fifth pass: vertical pass, with economiser bundles; and

External economiser located down stream from the boiler.

Method Statement 4a Operational Interface

15

Page 16: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

P T L I I K

An external low pressure economiser will be installed on the flue gas path above the economiser to reduce

flues gas temperature to 140°C, which is the optimum temperature for the dry flue gas treatment process.

This design will also ensure a high efficiency of the thermal cycle and obviously better electrical production.

Water walls

All evaporating tube panel elements have the same profile.

Since all enclosure walls are at a uniform temperature, all expansion is uniform, and there is no possibility of

gas leaks causing damage to insulation or resulting in corrosion attack on the outer metal sheeting.

Drum

The drum is of a transverse arrangement. It will be of fusion welded construction. X-ray tested, stress

relieved and fabricated from steel plate according to the requirements of the relevant standards.

Steam drum internals include:

• Internal feed water pipe and supports;

• Continuous blow-down and chemical feed pipes and supports; and

• Separators and devices to limit solids carry over to the superheater.

Sufficient nozzles for each of the following are provided:

• Safety valves;

• Feed water;

• Continuous blow-down;

• Vents and sampling valves;

• Water columns and level transmitter; and

• Drains and miscellaneous.

Superheater

Made of convective bundles to increase the lifetime.

Evaporator

The natural circulation evaporator bank is installed in the corresponding pass and before the superheater to

protect it from high flue gas temperature.

16

Page 17: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r."^ii» ^OXFORDSHIRE ^ C O U N T Y COUNCIL

r council tax v.-ciijng fci' yo

Economiser

The economiser is located in the last pass, and is provided to preheat the feed water prior to entering the

boiler steam drum.

The economiser consists of several banks of plain tubes supported by water-cooled tubes or bars according

to flue gas temperature. The economiser is completely drainable and ventable, and is enclosed in a steel

welded casing.

Inconel

Inconel is used in specific areas with high potential risk of corrosion and/or high refractory maintenance. This

includes the following areas:

• Furnace roof, front, and side walls of the furnace above the refractory;

• Roof of the second pass; and

• Part of the final superheater (SHT).

Extended use of Inconel in the furnace (instead of refractory) is restricted by the regulatory condition of T=

800°C/2 sec. The proposed design has been determined based on the assumption that the condition

T=850°C/2 sec must be met while incinerating waste at a NCV of 9700kJ/kg. This assumption is consistent

with basic design data, and with CNIM's obligation to design a plant in compliance with environmental

regulations. Any additional extension of the Inconel plated area will change the gas temperature profile into

the furnace, and will not ensure the above condition will be met without auxiliary fuel firing. The mean height

of Inconel on the side walls in the upper part of the furnace is one metre. Details or inconel location are set.

R,efractory

Two kinds of refractory are used:

• Refractory on casing - in these areas refractory bricks, SIC bricks, Insulating concrete or refractory

concrete will be used; and

• Refractory on tubes - in these areas CNIM patented refractory bricks with high SIC contents will be

used as set in MS4a-10 below.

Method Statement 4a Operational Interface

17

Page 18: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r.T% Boiler system - Protection against corrosion

n-iB«eA»s

CNIW-BS'%SIC T — ^ ~ l —

\

1 -R?ifrei?li3iiY krh^t.,

4SIC brStb

4<lnmjlDHrtg caneM^A

Figure MS4a-10: Boiler system - Protection against corrosion

Based on the anticipated throughput and net calorific value (NCV) of the waste (also called lower calorific

value (LCV) or lower heating value (LHV)), the Facility will comprise a three-run grate and vertical boiler

arrangement. The grate/boiler will be from a CNIM/Martin standard range of equipment providing optimised

energy recovery and a reduced NOx level in the gaseous emissions.

18

Page 19: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump
Page 20: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

fi^^ The IR camera is integrated into the roof of the first boiler pass. The camera makes near real time recordings

of the fuel's surface temperature distribution on the combustion grate. A sophisticated image analysis

program, using arithmetic techniques specially developed for Martin, generates control signals using the

recorded values. Disruptive gas and particle radiation is effectively eliminated by the arithmetic techniques.

Infrared camera

Grate run

Grate run

Figure MS4a-5: Infrared camera schematic

20

Page 21: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

KO'^m ^OXFORDSHIRE ^ ' C O U N T Y COUNCIL

•r council t^j< wci-v.ing fc i ' yc^u

Figure Ms4a-6: Image processing schematic

Retract system

A retract system for withdrawing and introducing the camera and lens makes the system inherently safe. An

alarm chain (cooling water flow/temperature and compressed air flow as well as condition inside the camera)

monitors the operation and automatically retracts the infrared camera and lens in the event of any danger.

The infrared image

A fibre optic cable connects the infrared camera to the image analysis computer, on which software

developed by Martin is installed. The software performs in-depth analysis of the image information and

generates control signals by means of mathematical/statistical operations.

The signals are then integrated into the Martin combustion control system.

Method Statement 4a Operational Interface

21

Page 22: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

mr) '""m ^ f fell W

c SetPointi Contro) systanu Actuating v«rtabl« Contnittod vsrtabl** / actual valu*

131 oaOT.'Saw

Figure MS4a-7: Schematic representation of the IWARTIN combustion control system with IR camera

The basic control loops of the classical Martin combustion control system (see Figure MS4a-7 above) remain

the same with infrared camera control. The additional control loops are listed below.

Control loop - temperature compensation between the grate runs

Varying degrees of temperature difference may occur between the individual grates due to variability of the

fuel. These differences affect the gas and bottom ash burnout, flow profile in the first boiler pass, O2

stoichiometry, and combustion uniformity.

Determination of the temperature differences between the individual runs makes it possible to distribute

under fire air in a much more demand-oriented manner.

Control loop - compensation of characteristic temperature imbalances by the feeder

Characteristic temperature imbalances may be caused on the grate by changes in the feeding sequence due

to varying fuel qualities and by mechanical changes (e.g. differing strol<e lengths of individual rams). For this

reason, the strolce of an individual feed ram is adjusted in such a way that, on average, the amount of fuel

fed over a longer period is brought into line with that fed by the other rams. This significantly reduces

temperature imbalances on the grate. Figure MS4a-12 below shows the influence of the adjustment in strol<e

on the uniformity of the temperature distribution over the grate.

22

Page 23: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

[^OXFORDSHIRE P'COUNTY COUNCIL

r countii tiiK vvci'jjng fcryg:

Weekly comparison of the deviation of the position of main combustion one from th avarage value

^ TO

S E

15,0%

10,0%

5,0%

0,0%

- c -5,0% o

O 01

TO -Q

S O -10,0%

-15,0%

7,7%

5,5% 5,2%

11,1%

s-4.;%

^ j 2

1,7% •1,5% il.2%

o,a%i.o% I.I'XD.E

^-1.B% §-1,9% 1-1,9%

S 2

-5,7%

-7,9%

BBl-vm • B 2 - v m nB3-vm

Figure MS4a-12: Influence of stroke adjustment using IR camera

Control loop - adjustment of under fire air

The under fire air temperature can be used as a control variable to influence the position of the main

combustion zone, i.e. the fuel bed length. When the heating value is low, ignition is delayed and the fuel bed

becomes longer. In order to maintain the main combustion zone in its ideal position, the under fire air

temperature is increased to shorten the distance between the point at which fuel is fed and the area at which

the highest temperatures prevail (the main combustion zone). Accordingly, when the heating value is high,

the under fire air temperature is reduced to prevent early ignition and unnecessary fluctuations in heat

release.

Control loop - overfeed control

If excessive amounts of fuel are fed and the fuel fails to ignite quickly enough, there is a risk of excess fuel

build-up on the fuel bed.

To prevent overfeeding at low heating values, the degree of cover may be determined from the image

information. Freshly fed waste is introduced to the main combustion zone based on the temperature and

position information obtained. It is then possible to slow the feeding process and provide the fuel with

enough time to dry and ignite should there be a risk of overfeeding.

The infrared image also provides operating staff in the control room with visual information on the status of

the combustion process.

Method Statement 4a Operational Interface

23

Page 24: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

fl^^t Grate siftings handling system

This system comprises a series of mild steel hoppers, each with a butterfly type outlet valve connected to an

inclined duct terminating above the ash discharger.

The hoppers are situated beneath the grate section with one situated under the waste feeder device.

Siftings are collected in the hoppers and cleared at intervals of two to four discharges per hour. The siftings

are conveyed pneumatically, using combustion air as a pressure medium, and delivered to the ash

discharger.

The butterfly type valves are operated pneumatically and are designed to prevent leakage of combustion air

when in the shut position. Facilities will be provided in the hopper compartments to enable access and

inspection to be carried out. The hopper outside surface will be lagged to ensure the maximum surface

temperature does not exceed 60°C when the ambient is 25°C.

Hydraulic power system

The moving grate steps, feed chute shut-off door, refuse feeder, discharge roller and bottom ash discharger

are driven hydraulically through electro-hydraulic controls to obtain the required individual speed variations.

One complete pumping station is provided to serve the hydraulic drives for the grate.

Combustion air supply

The combustion air is drawn from above the waste pit, so that the odours and airborne dust are drawn from

the tipping hall and the boiler house into the incineration line. The air intake over the pit is fitted with a grid.

Air velocity through the grid is kept low (4m/s) in order to minimise clogging by paper, plastic sheets and

other debris.

For each line, a duct is run from the air intake down to the forced draught fans. The forced draught fans

discharge into two ducts:

• The main duct routing air through the air heater to the plenum under the Martin grate

• The second duct routing air directly to a row of air nozzles on the front wall and on the rear wall.

Forced draught fans

For the incineration line, two combustion fans (one for under fire and one for over fire air) will be provided.

The fans are a centrifugal type with an impeller overhung on the shaft. They are abrasion resistant, with self-

cleaning blades.

A vortex, operated by a pneumatic actuator, is created in the inlet vein to achieve flow rate control. Drive is

provided by a direct flexible coupling.

24

Page 25: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

fil'll' Air heater

One air steam heater will be provided to heat the combustion air up to the required temperature, which is

dependent upon the calorific value of the waste.

The heater will be designed and constructed to accommodate thermal expansion of the tube bundle and the

casing.

The heater will be insulated with mineral wool to ensure that the external temperature does not exceed 70°C.

An inspection door is provided.

Auxiliary burner

The combustion chamber/boiler is provided with an auxiliary burner, whose purpose is as follows:

• Igniting the refuse at the start-up of the plant following shut down period

• Ensuring compliance with the EC Directive on flue gas emissions. This requires that whenever the

temperature falls below 850°C, a standby burner must operate automatically to maintain the

temperature so long as there is refuse on the grate.

This burner is also used to raise the temperature in the combustion chamber prior to starting up from cold

and during shutting down of the plant.

The total capacity of the burner will be rated at around 60 per cent of the boiler design load (approximately

40MW). The burners will be oil fired.

The burner will be supplied complete with electric ignition, flame safeguard equipment, and a valve train,

which contains control valves, instrumentation, isolation valves and a local control panel. The system will be

pre-piped and pre-wired to the maximum extent possible to minimise the amount of field installation required.

Diesel oil pulverisation will be performed by compressed air.

The flame detection system for the burners is a flame detector with a self-checking feature. The flame

intensity is converted to an electrical signal, which is used to indicate flame status and initiate the appropriate

response.

The equipment includes a local control panel as well as a dedicated safety PLC installed in the PLC room.

The local control panel is capable of starting and stopping the burner sequencing through the PLC. The local

control panel functions as a termination panel for the burner and valve train electrical devices and

instruments.

Diesel oil will be stored in a bunded tanl<. Transferring of the diesel oil at the set pressure to start-up burners

and other users will be achieved by means of two (2 x 100%) AC motor-driven pumps.

Method Statement 4a Operational Interface

25

Page 26: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r."\ Heat recovery

The heat released from the combustion of waste is recovered in a CNIM water tube boiler, which is integral

with the grate. The boiler and associated equipment are suitable for waste incineration plant service

(reference installations are currently operating), and will meet the steam requirements of the turbine

generator as well as all other steam requirements of the plant.

The 'heat recovery boilers' include the following main components:

• Boiler pressure parts;

• Low pressure external economiser part;

• Protection against erosion / corrosion;

• Surface cleaning;

• Dusty gas ducts/ash hoppers;

• Slowdown system;

• Boiler feed water system; and

• Miscellaneous equipment.

Access doors, inspection holes

Access doors and inspection holes provide access to the convective passes and enable the furnace to be

inspected.

Cleaning equipment

Satisfactory cleanliness of the convective heat transfer surfaces is ensured by a combination of rapping

devices and online water sprays as follows;

2 nd vertical pass-online water sprays on vertical pass; each cleaning module will clean the boiler walls, the

roof of the radiant chamber and evaporator banl<. For this purpose, waster will be sprayed with special

nozzle lances onto the heating surfaces;

Horizontal pass: surface cleaning is performed by means of a mechanical rapping system; and

4'* and 5* vertical passes : to ensure satisfactory cleanliness of the economiser tubes, an in-operation

vibrating cleaning system will be provided for the economiser.

26

Page 27: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

¥^ ,.^ w Mm ^OXFORDSHIRE

^ ^ C O U N T Y COUNCIL

[ Your counc il tdx wGi-Vjng for you

Ash hoppers

In order to collect fly ash under the gas circuits, the boiler will be equipped with fabricated steel fly ash

collection hoppers at the bottom of each pass. The hoppers in the high temperature section of the boiler are

refractory-lined/water cooled, while hoppers in the low temperature section of the boiler are of casing type

with external thermal insulation only.

Safety valves

The boiler is fitted with:

• One main safety valve fitted on the drum and sized to release a minimum of 75 per cent of the boiler

steam rate

• One safety valve fitted on the superheater at its outlet and sized for releasing a minimum of 25 per cent

of the boiler steam rate.

This safety valve is set to open before the main safety valves fitted on the drum, to ensure a permanent flow

through the superheater.

Steam and water piping

Feed water is heated up in the economiser in counter-current flow to the flue gas to a temperature somewhat

lower than the evaporation temperature.

From the boiler drum the water flows down through the unheated downcomers and supplier tubes to the

lower headers of the evaporator system and thereafter is partly evaporated in the heated evaporator tubes

(walls and bundles). The resulting water/steam mixture flows over the riser tubes back to the drum, where

the water steam mixture is separated.

The saturated steam from the drum is heated up in the pre-superheater bundles in counter-current flow and

in the final superheater bundles in co-current flow.

The live steam temperature is kept constant by a spray type attemperator located between the first and

second superheater bundles. The attemperator is equipped with variable, orifice type spray valves.

All boiler heating surfaces, except platen type superheaters, can be completely drained and vented.

The system includes one drain and blow-down flash tank. The tank includes a system for emptying of the

drain to the recycled water pit.

Different connecting pipes between the blow-down sampling points on the boiler and the flash tank are also

supplied.

The temperature at the flash tank outlet can be adjusted, depending on the mean blow-down flow recorded,

in order to have a temperature of about 60°C, i.e. sufficient to send this water to the recirculation or disposal

Method Statement 4a Operational Interface

27

Page 28: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

fliHH system or use it in the slag discharger. The exact demands regarding temperature will be decided during

development of detailed engineering.

The high pressure, low pressure, steam and feed water pipeworl< will be designed and manufactured in

accordance with the relevant National Standards or equivalent.

All steam and feed water pipework will be adequately supported with provision for accommodating any

expansion encountered by the inclusion of suitable spring supports and expansion joints.

All steam and feed water pipework operating at a high temperature will be insulated.

Flanged joints in the steam and feed water systems will be kept to the minimum. Turbine isolation (for

maintenance purposes) at the exhaust will be through a blind flange. A bypass valve (sized to approximately

10 per cent of steam flow) will be provided to allow for functional checking at reduced load prior to returning

to normal operation.

Boiler water treatment

Demineralisation plant

Boiler feed water is produced by one dual common demineralisation plant. The treated water will be used to

fill up the boilers and water network and then for topping up of the same. Each plant will be automatically

controlled by the levels in the demineralised water tank.

Demineraiised water tank

Demineralised water is stored in a water tank that:

• Acts as a buffer tank to ensure that demineralised water is continuously available

• Stores demineralised water during any planned shut-down and/or emptying operations.

Demineralised water storage capacity is equivalent to the volume of one boiler.

Boiler water conditioning

A combined unit suitable for both phosphate and oxygen scavenger dosing will be fitted. A dosing pump will

inject the oxygen scavenger at the feed water pump suction. A dosing pump will inject the phosphate in the

drum.

Power generation plant and auxiliaries

The power generation plant and auxiliaries include the following main components:

• Steam turbine and auxiliary equipment;

• Power generator;

28

Page 29: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r » ^ ^ eSaOXFORDSHlRE «3*COUNTY COUNCIL

[ Yourcouricil tdx WGfkinj fcf you

• Air condenser;

• Condensed steam heater(s);

• Boiler feed water system

• Miscellaneous equipment.

Stearn turbine and auxiliary equipment

The total steam quantity generated by the heat recovery boiler is used in a common condensing/bled turbine

to generate electricity. The steam turbine will be used in full condensing mode.

The condensing steam turbo generator is designed for continuous operation twenty four hours per day and

365 days per year. After subtraction of the power required for internal use, the electrical net production will

be discharged to the grid system via a step-up transformer.

The selected condensing steam turbo generator will be able to operate in island mode at full steam flow with

steam dumped to the condensers at an ambient temperature of up to 30°C.

Upon loss of the main export connection while the turbine generator is running, the turbine output shall

automatically reduce in a stable manner to Island Mode without tripping.

Turbine

The turbine is designed to accept the total steam flow produced by the incineration train under any

anticipated ambient conditions.

It will accept the full boiler operating range including operation with all possible combinations of lines in

conjunction with acceptable Waste within the stoker capability diagram (Figure MS4a-4).

A gland steam exhauster system consisting of a condenser and fan exhauster recovers heat and condensate

to the feedwater system, while non-condensable gases are exhausted to atmosphere outside the building.

Upstream steam pressure is regulated through the turbine by the governor-controlled steam admission

valves. The governor valves operate sequentially to provide maximum efficiency corresponding to the design

rating of the boiler at rated capacity. The governor programmable microprocessor control unit controls the

turbine speed, accepts an external control signal generated from the boiler outlet steam pressure, and

provides all the control functions required to maintain safe operation of the turbine. The control unit shall be

fully interfaced with the SCADA and the boiler control system.

The turbine is protected with a mechanical overspeed trip device and an electronic overspeed unit using

speed sensors.

The subsequent loss of oil pressure causes the stop valves to rapidly close and the governing valves to

close.

Method Statement 4a Operational Interface

29

Page 30: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r;iiii The turbine will be equipped with a steam take off valve.

Gearbox

A double helical, horizontally offset, parallel shaft, speed reducing gearbox is provided in between the turbine

and the generator.

The gearbox is fitted with the necessary equipment for turbine operation and safety including but not limited

to:

• AC motor and manual engagement;

• Oil pressure switch interlock;

• Bearing temperature indicators and transmitters; and

• Bearing vibration sensors.

Lubricating oil system

A common remote mounted lube oil system is provided for lubricating the turbine, gearbox, generator main,

and subsidiary bearings.

A separate system will supply oil for the high pressure hydraulic operation and servo control of the control

and emergency shut off valves.

The main oil pump will be either AC electric motor driven, or driven directly from the low speed gearwheel of

the gearbox, and will supply oil to the complete assembly for both lubrication and power control purposes. An

AC starting and standby pump is provided to start in the event of failure of the main pump. An AC UPS

supplied rundown/cooling pump is provided for safe stoppage in case of failure of the main pump.

The emergency AC UPS driven pump, which operates on low pressure in the event of both the main pumps

being unavailable for maintaining bearing lubrication, shall maintain effective cooling for a sufficient length of

time, while the unit coasts to a halt and is mechanically or hand driven.

Lubrication oil passes through one of two 100 per cent heat exchangers and a duplex filter for removing

particles. A lube oil centrifuge is provided for lube oil conditioning together with fan extraction vented to the

outside. The oil tank is fitted with a visible level indicator and high and low level switches.

Generator

The generator will be supplied with an appropriate excitation cabinet containing:

• Auto excitation controller for voltage control, power factor;

• Neutral point cabinet with current transformers, earth resistor with a homopolar detection core and

connection terminals; and

30

Page 31: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•p;^iiii s i * OXFORDSHIRE S 3'COUNTY COUNCIL

ur courn ii t .x vvcr!'.!ng Fcr you

• Monitoring panel containing the following: line voltage meter, excitation ammeter, watt meter, phase

meter, frequency meter, duplex voltage meter, duplex frequency meter, a synchroscope, emergency

stop switch, power factor control, voltage and current excitation control, automatic or manual control,

control for turbine speed, generator voltage and generator power factor.

Air condenser

An air condenser is provided. The air condenser is designed to condense the total amount of exhaust steam

produced.

The proposed solution refers to an anti-freezing steam condenser arranged in a direct roof A-frame type, air

cooled and mounted on a steel structure. The steam condenser is designed to condense all of the steam

from the turbine and/or from the bypass of the turbine.

The proposed air cooled solution allows for maximum flexibility against variations in thermal load and/or

ambient conditions.

Condensate system

Condensed steam will be collected and stored in a single condensate tank arranged at ground level. The

condensate tank is sized to ensure a storage capacity corresponding to more than seven minutes of

operation at full load.

The condensate tank is cylindrical in shape and arranged horizontally. It will be made of carbon steel plates.

Two 100 per cent condensate pumps are provided to transfer condensate to the de-aerator via condensate

heater(s). Pumps are centrifugal, single-stage type driven by an AC constant speed electric motor.

Condensed steam heaters are used to improve the Rankine cycle efficiency by heating the steam from the

condenser using extraction steam from the turbine. The condensed steam is returned to the main condensed

steam tank.

Condensate is returned to the de-aerator for suitable heating and degassing. The de-aerator tank is sized to

ensure a storage capacity corresponding to more than twenty minutes of pump feeding at full load without

condensate return.

The boiler is fed with water from the de-aerator by multistage, centrifugal, horizontal feed water pumps.

Free thermal expansion takes place in a downward direction.

The design of the boiler makes it particularly suitable for waste incineration. In order to prevent fouling,

erosion and corrosion problems, the design was governed by the following main criteria:

• Proper design of the combustion chamber (shape, dimensions) to improve gas velocity and

temperature profiles;

Method Statement 4a Operational Interface

31

Page 32: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

I 1P'V„„ 1 mr

• Low gas velocity in the combustion chamber to reduce ash carry over;

• Protection of water walls in the flame zone designed to achieve good heat transfer without excessive

inner face temperature;

• Wide spacing of tubes in convection tube banks;

• On-line cleaning well adapted to the design; and

• Easy access for inspection and maintenance of all pressure parts On-line surface cleaning by a

combination of soot blowing, rapping and vibrating.

Air pollution control equipment

The proposed air pollution control equipment will allow the plant to operate at any load within the limits set in

the stoker capability diagram (Figure MS4a-4), with emissions levels in compliance with the European

Directive 2000/76/EC dated December 4/2000.

The proposed technology is a combination of the four following processes:

• Selective non-catalytic reduction (SNCR) process into the furnace for treatment of NOx;

• Neutralisation of acid gases by injection of hydrated lime in a dry process;

• Dioxin reduction by injection of activated carbon; and

• Dust removal through a bag filter.

The flue gas treatment will be implemented by LAB (part of the CNIM group).

The removal of NOx from the flue gases is performed by selective non-catalytic reduction (SNCR) with

urea/ammonia which is added in the furnace.

4N0 + 2CO(NH2)2 + 0 2 ^ 4N2 + 2CO2 + 4H2O

2NO2 + 2CO(NH2)2 + 0 2 ^ 3N2 + 2CO2 + 4H2O

The removal of acidic compounds from the flue gases is performed by chemical reaction with lime which is

added and turbulently mixed by way of the reacting duct with its associated residue recycling system.

The main reactions performed in the dry reactor and on the consecutive entrained suspension path are:

Ca(0H)2 + SO2 ^ CaSOa + H2O

Ca(0H)2 + SO3 => CaS04 + H2O

Ca(0H)2 + 2HCI => CaClz + 2H2O

Ca(0H)2 + 2HF ^ CaFz + 2H2O

32

Page 33: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r.^ift Ca(0H)2 + CO2 => CaCOs + H2O

Depending on their acid value, the acid polluted gas components react according to the following priority:

SO3 > HF > HCI > SO2 > CO2

The separation of CO2 as an extremely weak acid plays a minor part as part of the given reaction conditions

and holding times of the process. Moreover, low quantities of CO2 eventually separated in the form of CaCOa

will be expelled from their combination at the latest as part of the re-circulation of the absorbents through the

stronger acids available in the flue gas.

Concurrently to the described chemical transformation reactions of the acid pollutant gas components with

hydrated lime, volatile heavy metals (i.e. mercury) and toxic organic components (i.e. PCDD/F) will also be

separated efficiently. In this case, the retention of the specified pollutants takes place through adsorption on

the carbon-containing surfaces of the activated carbon.

Process description

The proposed in-furnace SNCR and dry process consists of the following consecutive steps through which

the pollutant carrying flue gases pass:

• Urea is injected upstream in the furnace where NOx reduction takes place;

• The dry reacting duct for the intensive and turbulent mixing of pollutant-carrying flue gases, fresh lime

absorbent, activated carbon, and recycled residues from the fabric filter;

• The high performance fabric filter for separation of all particle-type pollutants contained in the flue gas

flow downstream of the reacting duct, mainly composed of entrained fly ash, reaction salts formed from

absorbents and pollutants and residually available active absorbent portions;

• The heavy duty recycle system to return most of the fabric filter residues to the suspension reactor, with

buffer silo and mechanical conveyors; and

• The induced draft fan (IDF) including silencer for compensation of the upstream plant pressure drops,

conveying the flue gas flow throughout the plant and controlling the furnace under-pressure

simultaneously.

The flue gas generated during the thermal treatment of the residues runs through a waste heat boiler and is

fed to the flue gas treatment plant via a coupled flue gas duct.

There, the hot flue gases are carried via a flue gas duct to the reaction duct, where they are contacted under

highly turbulent conditions with fresh lime, activated carbon, re-circulated and re-activated residues from the

bag filter. Such contacts under highly reactive conditions serve to optimise the removal of pollutants and to

form dust-like products.

Method Statement 4a Operational Interface

33

Page 34: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

The dust-carrying flue gas is then introduced into the bag filter where it is discharged from all particle-type

contaminants composed of entrained dust, reaction salts and remaining active reagents. A portion of the

dust removed on the fabric filter is returned to the dry reactor after its reactivation.

The conveying of flue gas through the plant components, including the under-pressure control in the furnace,

is controlled by the induced draught fans.

Consumables required are limited to hydrated lime for neutralising the acid gases, activated carbon to

separate volatile heavy metals and toxic organic compounds, and urea for the NOx reduction.

Dry urea NO^ reduction system (see Figure MS4a-11 beiow)

The system described below is a dry SNCR system using dry urea as reagent. This system is simpler though

more efficient than a wet system using aqueous urea or ammonia. It is particularly well suited to medium

sized streams.

Each furnace has its own air booster with a further booster available on standby for the plant. The

installations for all streams are independent and redundant of each other. If one is shut down, there must be

no effect on the operation of the other.

The selection of air conveying system and booster is done manually. The standby booster has the same

capability as the operational boosters.

The whole installation is controlled from an electrical control and power distribution cabinet, the location of

which is to be agreed, with local boxes for each line.

The urea injection metering and injection level selection valve shall be controlled from the plant's central

control room. The selection of distribution level is generated in the electrical cabinet.

The final choice of injection levels and positions will be made during commissioning and fine tuning on Site.

Only two levels and two injection points per level will be retained. It must therefore be possible to configure

the installation easily during the adjustment phase.

34

Page 35: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•p;c\iii jfiEaiOXFORDSHlRE <BfS3 COUNTY COUNCIL

ii'council tdx '.•••gryjng Feryou _

ENIM

BOILER

BUFFER TANK \

STREAM 2 " | - T

DOSIMG SCREW

ROTARY VALVE

w

— ^ 4 - *

-X-SCAVENGING AIR CIRCUIT

IT

LEVEL SELECTOR

BOOSTERS

SCHEMATIC FOR DRY UREA INJECTION

Figure MS4a-11: Dry urea injection schematic

Reaction duct

The reaction duct is used to optimise the mass transfer between the flue gases and the dry absorbents. It is

designed in the form of an area of intensive mass transfer. The reactor actively participates in:

• High-performing separation of the pollutants contained in the flue gas under the actual operating

conditions of the combustion plant;

• Reduction of the generated pollutant peaks by optimal reaction with absorbents;

• Increase of the operational flexibility; and

• Considerable minimisation of the quantity of residues generated.

High turbulence is produced by the turbulent flow created by means of a carefully calculated flue gas speed.

Its active zone is produced by adding reactivated recycled material coming from the fabric filter, fresh and

powdery hydrated lime and activated carbon.

Fabric filler

The bag filter is used for the major separation of particle pollutants from the flue gas. These pollutants mainly

consist of entrained dust, dried reaction salts and used up absorbents.

Method Statement 4a Operational Interface

35

Page 36: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

rvi^t The bag filter is a high-performing filter with compressed air de-dusting composed of a chambered housing

with vertically arranged cylindrical bags, the bag bottom, the raw gas inlet duct, the pure gas discharge duct

and the dust collection hoppers.

The design of the different chambers comprises a welded gas-proof steel structure with reinforced steel

profiles. The welded-in bag bottom separates the raw gas room from the pure gas room. The pyramidal dust

collection hoppers are positioned below the raw gas room.

The dust-carrying flue gas is introduced into the bag filter housing through the raw gas duct. The housing is a

chambered design allowing for the separation, inspection and maintenance of parts of the unit involved in the

flue gas process during plant operation, thanks to the shut-off valves between the raw gas and pure gas

room.

The raw gas related interlock is ensured through shut-off valves between the raw gas duct, the filter chamber

and the pure gas related interlock through disk-type or shut-off valves.

Filter bags are arranged inside the filter chambers. The flow runs through the filter bags from outside to

inside. During the passage through the filter bags, the majority of the dust proportion of the flue gases is

retained and deposited as a filter cake on the surface of the bags. Filter baskets inside the bags prevent the

filter bag from collapsing.

The filtered flue gas is directed inside the filter bags and from there to the pure gas chambers and pure gas

duct. The filter medium perfectly matches the application in terms of the flue gas parameters and dust

properties, so as to ensure high operational safety with extended shutdown times.

The main characteristics of the fabric filter are as follows:

• Six independent cells;

• On line air pulse cleaning of bags;

• PTFE membrane bags, with 316L carbon steel baskets;

• Four independent hoppers with high level detection, isolating gate valves, temperature measurement

and connection to the inert gas station;

• Complete by-pass system;

• Preheating system with booster fan and electrical battery;

• Precoating system using main lime injection circuit. Lime is injected during start-up of the line to protect

the bags, as soon as the flue gas flow is sufficient to carry the lime to the filter; and

• Downstream dust measurement.

In order to limit increased pressure drop caused by the filter, the filter bags are controlled using differential

pressure-control or de-dusted at regular intervals through compressed air pulses. This can be done

36

Page 37: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•fvl^li, electronically or fully automatically through the short opening of a diaphragm valve, in order to direct the

compressed air from the compressed air tank via the nozzles to the relevant filter bag rows. Other relevant

process signals, such as flue gas volume flow, current inlet and outlet pollutant concentrations can be

considered during the cleaning sequence.

Compressed air pulses from the nozzles are sent inside the filter bags thus generating a pressure wave

passing throughout the bag and leading to the short expansion of the filter bag. This phenomenon causes

the filter cake to be detached and to fall into the dust collection hoppers, directly arranged under the filter

chamber.

From there, the residues are extracted via the feeder screws and transported to the residue silo or re­

circulation system.

Recycling of fabric filter residues

The dust like material separated within the fabric filter among reaction salts still contains a certain portion of

unreacted lime. In order to make best use of that, most of the dust coming from the fabric filter is recycled to

the reaction duct.

For this purpose, a mechanical, fully proven self-controlled recirculation system developed by LAB is

implemented. The residues are first collected from the dust collection hoppers by means of feeder screws.

The extracted residues are fed into the recirculation buffer silo and all material that cannot be accepted is

transported to the residue silo automatically.

To make optimum use of the recycled material it is reactivated prior to re-injection to the reaction duct. For

this purpose the buffer silo is designed to allow the correct maturation time for reactivation of the residues.

After being injected to the reactor, the recycled material is dragged by the flue gas flow to the fabric filter, to

be returned to the reacting duct.

Storage capacity will be 100 m^ for each line.

This type of recirculation design allows for automatic expulsion of the part of residues from the system

corresponding to the sum of fresh absorbents and flue ash taken in, without implementing sophisticated and

failure-causing control and measurement systems and intermediate tanks. This system further eliminates

overloads of the reactor/bag filter unit as well as unnecessarily high consumption of absorbents.

Dependable insulation, trace heating and the heavy duty design matching the properties of bulk material

ensure the consistent operation of this simple, self-controlled and reliable re-circulation system.

Method Statement 4a Operational Interface

37

Page 38: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

Fv YMm Dry injection of hydrated lime and activated carbon

Hydrated lime and activated carbon are taken from their respective silos by mechanical extraction devices.

They are transported to the feeding point of a common pneumatic conveying pipe by means of speed-

controlled feed screws.

A radial fan produces the required volume flow and ensures the pneumatic conveying of the absorbent-air

mixture to the flue gas duct upstream of the dry LAB-Loop reactor. There it is intensively mixed with the flue

gases and entrained under continuous reaction with the flue gas pollutants.

Unused portions are recycled to the flue gas flow by way of the recycling and reactivation loop as described

above.

Induced draft fan and silencer

The induced draft fan is used to compensate for plant pressure drops, conveyance of flue gas through the

upstream plant components, and depression control in the combustion room.

This is a radial speed-controlled fan with bilateral intake and single-flow design. Flue gas enters the welded

sheet steel housing via the flue gas ducts on the intake sides, where it is accelerated through the rotor and

fed to the discharge end. The rotor is equipped with profile blades and is electro-dynamically balanced out in

two levels.

The coupling to upstream or downstream flue gas ducts is provided using compensators. The rotor is located

on a shaft with lubricated dust-proof roller bearings and is driven by two three-phase frequency converter

controlled motors by means of elastic coupling.

The whole unit is located on a common vibration-free frame, housing both the booster fan and the drives.

To minimise the noise emissions from the equipment of the flue gas treatment plant, an absorptive silencer is

connected to the booster fan, which reduces noise levels at the inlet of the chimney.

Peripheral equipment

Lime storage

Hydrated lime (Ca(0H)2) is supplied as dry powdered absorbent using silo trucks and stored in one bulk

material silos. The silo will have a storage capacity of 210 m . When the minimum level in a lime silo is

reached, operational staff order the required quantity of lime from the supplier.

Lime is fed pneumatically from the silo truck into the buffer silo. To do so, the extraction coupling of the silo

truck is coupled to the pneumatic filling pipe of the buffer silo using a flexible hose and lime is fed into the silo

by means of the truck compressor dedicated to this purpose.

38

Page 39: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

ijOXFORDSHlRE S COUNTY COUNCIL

wwwaxfufdsSiiregovuk

[Yourcount 11 taxwcti'^ing fcryou

The feeding operation is complete after the full emptying of the silo truck or once the maximum filling level is

reached in the silo. The exhaust air generated during the feeding operation is de-dusted by means of a silo

top filter and released to atmosphere.

From the silo, the hydrated lime is discharged for injection in the reaction ducts as described above.

Storage of activated carbon

For the adsorption of the volatile heavy metals (i.e. mercury, Hg) and organic components (i.e. PCDD/F) to

separate, powdery activated carbon (PAC) is added to the flue gas together with lime.

The absorbent is supplied by silo trucks as dry powder and stored in a bulk material silo with a storage

capacity of 80 m . When the minimum level in the silo is reached, operational staff shall order the required

quantity from the supplier.

The PAC is fed pneumatically from the silo truck into the bulk material silo. To do so, the extraction coupling

of the silo truck is coupled to the pneumatic filling pipe of the buffer silo using a flexible hose and lime is fed

into the PAC silo by means of the truck compressor dedicated to this purpose.

The feeding operation is complete after the full emptying of the silo truck or once the maximum filling level is

reached in the silo. The exhaust air generated during the feeding operation is de-dusted by means of a silo

top filter and released to atmosphere.

The absorbent silo is equipped with a continuous filling level monitor, a maximum filling level sensor, an

overflow sensor, an overpressure and depression safety valve, mechanical extraction equipment and a silo

top filter.

Conveying and storage of residues

The residues generated in the flue gas treatment plant are a mixture of fly ash, dried reaction salts, used up

and fresh absorbents. They are deposited in the dust collection hoppers of the bag filter.

Residues from the fabric filter are conveyed to the buffer silos using mechanical equipment, e.g. screw

conveyors, chain conveyor and a final bucket elevator.

In order to avoid operational difficulties due to deposits/bonding, equipment for conveying dust between

extraction from the flue gas plant components and the intake of the residue silo is insulated and equipped

with electrical trace heating.

The residue silo is designed as a cylindrical bulk material silo with a flat end and is used for the intermediate

storage of generated resid

operation at design point.

storage of generated residues. The silo will have a storage capacity of 230 m^ equivalent to five days

Method Statement 4a Operational Interface

39

Page 40: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

m-^m Ash handling

Bottom ash

Each incineration line will be equipped with its own ash conveying system. Bottom ash from Martin ash

dischargers will be conveyed to the ash pit by means of vibrating conveyors and a belt conveyor.

Bottom ash is collected from the two ash dischargers by means of a common vibrating conveyor equipped

with a screen for sorting the coarse fraction. The vibrating screen will be designed to allow for a backup ash

removal option in case of failure of the main conveying system. In such a case the total stream of ash will be

temporarily diverted to contingency storage bins located adjacent to the central access road through the

plant building. Storage will be based on the use of standard roll-on roll-off containers having an individual

storage capacity of 12 tonnes. Once filled the containers will be transported to the ash storage area where

the contents may be tipped for further processing or stored for transport off site (as appropriate depending

on the nature of the failure requiring ash diversion).

The passing fraction of bottom ash is then conveyed directly to the ash storage by a belt conveyor.

A magnetic separator will facilitate the separation of ferrous and there will be non-ferrous separator from the

bottom ashes.

Storage capacity will be designed for three days storage capacity without operator maintenance and five

days with manual stacking.

Fly ash

Fly ashes will be collected from boiler and economiser hoppers and conveyed to the bottom ash discharger.

SCADA system

The Facility will incorporate a Supervisory Control And Data Acquisition (SCADA) system for the combustion

of Waste in an efficient and clean manner. The installation will be designed to operate continuously twenty

four hours a day, all year round except for planned outages. Monitoring systems and processes will be fully

integrated into the automated control systems to ensure that data are collected and used to adjust operating

parameters as required to maintain optimum plant performance.

The proposed main control and supervision system will consist of a distributed digital control system (DCS)

organised on several levels:

Level Zero; Process level {see Figure Ms4a-11)

This level ensures logical and analogical signals conditioning, i.e. inputs and outputs from and towards local

instrumentation and cabinets.

40

Page 41: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

i n r^ ^ f , ii 1 1, w

iftgiOXFORDSHlRE WtA'COUNTY COUNCIL

r council tax v/crhng fcr you

U N E 1 ; FURNACE - BOILER • FGT LINE 2 : FURNACE - BOiLER - FGT

IB

Ulll 1

Profhus DP Ring

2 : FURNACE-aOiLER-FGT COMMOfj UTlLIT:ESaP(WER ' , " ' : [ jHI

4 A I :• -,.a Uf ^ V^E ? CC. ^cricfae Speed Driver Fre-quercy coiveier.

D'sfc'ibutan

Figure MS4a-11: SCADA DCS level 0

Level One: Control level {see Figure IVlS4a-12)

This level will ensure:

• Data processing (including logical sequences, closed control loops, mathematic functions) related to the

main process;

• Data exchanges with local PLCs by communication on serial bus; and

• Alarms processing.

Level one will be composed of:

• Part one:

• Two redundant controller units for each line.

• Two redundant controllers unit for the utilities and common parts.

• Part two: Specific sub-systems

• Various other PLCs are associated with complex equipment which represent independent functional

systems. This mainly concerns the turbo-generator, water treatment, cranes and crusher.

I EraEdin SBT? m mis • o?nc«L FIBER RING I

SWETvlJ] ftC

MlHipil ,.MllNi|g PLCi>«K«GEfOli

Hfl;SE:aA.Nil62

Figure MS4a-12: SCADA DCS level 1

Level two: Supervision levels (see Figure MS4a-13)

This level provides:

Method Statement 4a Operational Interface

41

Page 42: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r.1^1, • The operator interface;

• The data storage and display; and

• Alarm processing functions.

This level will be composed of:

• Three operator stations (PC type) fitted with two 20inch monitors, keyboard and pointing device;

• One engineer station (PC type) can be used in operator station fitted with a 17inch monitor, keyboard

and pointing device;

• One black and white printer for alarms and data-logging;

• Two colour printers for trends, mimic views and reports printing; and

• One diagnostic station (laptop PC).

Level two will enable the supervision of the whole plant and provide detailed information about main

processes. It will also provide grouped information for remote and secondary equipment as well as data

storage on a short term (weekly) and a medium term (monthly) basis. Long term storage is assumed to be

recorded on an optical disk or equivalent (via the streamer).

^ ^ ^ ^ ^ ^ ^ B ^ ^ ^ B ^ ^ ^ B rOR ECHANGE ^ ^ ^ B

OPERATO* s DSACROSTIC

GPSCIodt

I / ^

^ ^ O'ERATSII B mt. ^ B

. ^ ^ J I - I / U ENGlNEEaiNS I I p -^S^ H / • • 5TAT10H iB'^OMHI!

•/ iSEDt iNDANT

SERVERS i-y-7 AlARMSOATA

LOGGIlie

! •

i

LEVEL 0

LEVEL 1

LEVEL 2

E T i l C M n SRT? too MD,'5 CJTICAL TIBER RIHG

Figure MS4a-13: SCADA DCS level 2

Level three; Administrative and technical management level (see Figure MS4a-14)

Level three provides the following functions:

• Data analysis;

• Recording of long term data;

• Data display on screen (tables, trends);

• Report printing;

42

Page 43: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

K'^'^m t^ijOXFORDSHlRE <KB'C0UNTY COUNCIL

our couric ti tax vvcrj-jng far yoi

• Remote consulting of the operating values.

This level will comprise:

• One atmospheric emissions monitoring station

• One weighing station for recording of waste throughput data;

• One streamer for long term data storage;

• One server data collection station;

• One "CCTV" system with one PC for digital cameras.

The open structure of level three will allow the eventual addition of other stations for plant commissioning,

operating or maintenance to be supplied and configured by the operator as PMMS System.

SERVO 0 A « COtilCT STATION AMD DATA REPORT

STATKm

S-tJClEM • STATION H

MaaJaaa

EMIS&OH MONITOfilHG

FCJTEIi C-3C3

-S: CfT'tS

LEVELS

Figure MS4a-14: SCADA DCS level 3

Data exchange

Throughout the different levels of the DCS, data will be exchanged by means of several buses:

• Field bus for communication between levels zero and one;

• Main redundant bus for communication between levels one and two Ethernet bus for communication

between levels two and three.

Operator station

The operator station will supply the following functions:

• Users passwords on several levels;

• Screen views summary;

• Mimic views including logical controls (on/off, working mode selection) and analogical controls (set-

points adjustments, valves controls);

• Trends;

Method Statement 4a Operational Interface

43

Page 44: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

rviii-• Alarm reporting views;

• Controllers views;

• Logical sequences status view

• DCS status views (CPU, inputs/outputs cards, communication cards, power supplies).

Engineer station

The configuration (or engineer) station will carry out the following functions:

• Users passwords management;

• Database realisation;

• Screen views summary realisation;

• Mimic views configuration;

• Input/output and communication cards configuration;

• Trends and reports configuration;

• Alarms configuration (groups, labels, emergency levels);

• Controllers and logical sequence programming

• Fixed set-points, delays, thresholds, controller's parameters adjustments.

Server station

The server station is used for remote consultation of operating data. This station will include a PC with a

modem and software which extracts relevant data and displays the information on a dedicated website. This

will enable the remote interrogation and monitoring of the Facility by CNIM during the 5 year Supervisory

Contract and subsequently by the Contractor's management team.

Electrical

The plant will be connected into the grid at 33kV. The turbo-generator generates electricity at 11 kV and is

connected to the 33kV power distribution system through an 11kV/33kV step-up transformer.

The plant auxiliaries are supplied from the 33kV distribution system through step-down MV/LV transformers

with neutral three-phase 50Hz alternating current.

Should the main export / import connection become unavailable together with the turbo generator set while

in normal operation, a standby diesel generator will start automatically to restore power supply to priority

circuits allowing for the plant to shut down safely.

44

Page 45: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r»iiift The diesel generator is not sized to start or operate the plant and shall under no circumstances be used to

export electricity or to provide electricity while the main line or the turbo generator is being used.

Emissions monitoring

Atmospheric emissions monitoring statiori

This computer station will be supplied in order to perform data storage and calculations concerning

emissions and performance of the plant.

This dedicated equipment will consist of the following:

• One station (PC type) fitted with 15inch monitor, l<eyboard and pointing device;

• One printer for reports

• One long term data storage device.

As emission values and associated parameters (Namely: two seconds temperature, oxygen, and

combustion) are necessary for control of the process, primary correction calculations are made directly by

the main control system (DCS).

Auxiliary calculations (averages on diverse time bases, peak values) are made by the auxiliary station.

All the information from the combustion and the flue gas cleaning system will then be made available from

the auxiliary station which allows on-screen monitoring and reports to be printed.

This system will issue all reports requested by the regulating bodies with regards to pollutant emissions. All

the data will be expressed in the standard format and then published in daily, weekly and monthly reports.

Emissions measurements

The following will be continuously monitored and recorded:

• Total dust;

• HCI (hydrogen chloride);

• CO (carbon monoxide);

• Hydrogen Fluoride

• SO2 (sulphur dioxide);

• NOx (Ntrogen oxides, NO and N02 expressed as N02);

• NH3 (ammonia)

• VOC (Volatile organic compounds expressed as TOC - total organic carbon).

Method Statement 4a Operational Interface

45

Page 46: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r;^ift other elements will be monitored on a periodic basis.

Associated parameters:

• Oxygen (O2);

• Water vapour (H2O);

• Carbon dioxide (CO2);

• Pressure;

• Temperature

• Volume flow.

According to the selected equipment, parameters will be measured either directly or by calculation/evaluation

based on other direct measurements. Pressure measurement is not necessary because it has a negligible

influence on the accuracy of results.

The system will allow data logging of the flue gas treatment system status (operation/fault condition

information) as well as data logging and recording of some parameters issued from the incinerator/boiler

units, which are representative of the status of the process such as:

• Incinerator on/off;

• Combustion temperature (or two seconds temperature);

• Oxygen content after incineration;

• Steam flow;

• Auxiliary burner(s) on/off

• Power generation.

Instrumentation

Important note: unless otherwise stated, all the signals are 4/20 mA.

The main features of the proposed control equipment are as follows:

• Pressure and differential pressure:

• Transmitter: SMART type

• Power supply: 10/36 Vcc two wires

• Accuracy class: +/- 0.25%

• Flow:

46

Page 47: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r;"^iB kOXFORDSHlRE ^'COUNTY COUNCIL

[ Your council tax v/orVjng Fcryou

• Venturi nozzle with differential pressure transmitter for air and flue gas;

» Orifice plates with differential pressure transmitter for water and steam;

• Flow meter adapted to the fluid to be measured (e.g. electromagnetic flow meter)

• If an extractive type dust content analyser is used, the flue gas flow measurement will be issued

from this apparatus (using a pitot tube).

• Temperature:

• Primary element:

« T < 400 °C: resistance probe PT 100 type

• T > 400 °C: thermocouple K type

• Sensor and thermowell material:

• T < 1000 °C: stainless steel 316 L

• T > 1000 °C: refractory stainless steel (NS 30 or equivalent)

• Thermowells manufacture:

• Water and steam circuits: drilled thermowells

e Air and flue gas circuits: welded thermowells

• Power supply: 10/36 Vcc two wires

• Accuracy class: +/-1 %

• Level:

• Gauge pressure measurement for tanks under atmospheric pressure;

• Differential pressure measurement for pressurised tanks;

» Capacity probe, hydrostatic pressure sensor, ultrasonic transmitter or micro-waves (Radar)

measurements according to the fluid to be measured; and

• Power supply: 10/36VCG or 220Vca.

• Flue gas analysers:

• Combustion O2 analyser:

• Type: zirconium probe

• Power supply: 230Vca, 50Hz

Method Statement 4a Operational interface

47

Page 48: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r^^'^m • Dust content analyser:

• Type: light diffusion

• Power supply: 230Vca, 50Hz

• Multi-gas content analysers set for measurements at emission:

• Power supply: 230Vca, 50Hz

• Accuracy class: 3 per cent of the full scale

» This set will allow the measurement of the required components on the following principles:

• HCI, CO, SO2: wet or dry gas extractive or in-situ infrared spectroscopy;

• NOx and NH3: wet or dry gas extractive or in-situ infrared spectroscopy or ultraviolet spectroscopy;

» Water content ( percentage of H2O) will be determined as follows:

• IR spectroscopy measurement in case of a wet gas extraction type multi-gas analyser or in situ type

multi-gas analyser.

• The calculation is based on the measurement of wet O2 by a dedicated zirconium cell probe-type

analyser compared with dry O2 (dry gas extraction type multi-gas analyser).

For total flexibility a third analyser on standby is provided.

The Facility will have an overall capacity of 300,000 tonnes per annum and is based on two combustion

streams, each treating 19.2 tonnes of waste per hour, i.e. the total waste throughput will be approximately

38.4 tonnes per hour.

The Contractor has allowed a potential storage capacity of three to five days (depending on the level of

stacking in the waste bunker) of delivered waste at the Facility to ensure that the Facility can remain

operational over extended periods such as weekends and Bank Holidays.

Redundancy levels of key components included in the basis of design are summarised in Table MS4a-5

below.

48

Page 49: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

rwAi

System / component

WASTE RECEPTION, STORAGE & HANDLING (Common)

Weighing bridge way-in

Weighing bridge way-out

Gantry crane

COMBUSTION AIR SYSTEM (Per line)

Primary air fan

Secondary air fan

Air heater

GRATE (Per line)

Bottom ash discharger

BOILER

TURBINE/GENERATOR (Common)

CONDENSING PLANT

Water circulating pumps

Air condenser

BOILER FEEDWATER (Common)

Design basis

1 X 100%

1 X 100%

2x100%

1 x115%

1 x115%

1 X 400110%

1x130%

1x110%

2x100%

1 X 100%

Operating basis at Design Point

1x100%

1 x100%

1 x100%

1 x100%

1 x100%

1 x100%

1x100%

1x100%

1x100%

1 x100%

Method Statement 4a Operational Interface

49

Page 50: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

KMt Deaerator

Feed water pumps

WATER SUPPLY AND USAGE

BOTTOM ASH HANDLING AND STORAGE

Bottom ash vibrating conveyors (common)

Bottom ash conveying lines to bottom ash processing plant (Common)

AIR POLLUTION CONTROL (Per line)

REAGENTS HANDLING AND STORAGE (common)

Lime storage silo

Lime dosing and injeciion system

Activated Carbon silo

AC dosing and injection system

FLY ASH HANDLING AND STORAGE

Fly ash handling systemto discharger AFC (Per line)

conveying system to silos (Common)

APC residue silo (Common)

FLUE GAS HANDLING

(Per line)

ID fan and drive

CHIPvlNEY

CONTROL & INSTRUMENTATION

O2iHCUS02/N0x/C0A/'0C/NH3/HF analyser (Common)

Dust control (Common)

ELECTRICAL

Transfol 1000/690 V

Transfot 1000/415 V

1 X 100%

3x120%

1>:13D%

1x130%

1 X 110%

3-1 5 X 1550%

1x110%

1.5x150%1 x150 .-c

cpnro

1 x>150%

1 x>150%

1 x110%

1X 120%

1.5x100%

1x100%

4-2x100%

4-2x100%

1x100% 1 2 X 100'%

1x1 C0%

1 X100%

1 X 100%

1 x100%

^ 1 x 1 0 0 %

1 X 100%

1 X 100%

1 X 100%

1 X 100%

1 X 100%

1x100%

1x100%

1 x100%

1 X 100%

50

Page 51: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r^\% CIVIL WORKS AND BUILDINGS

FIRE PROTECTION AND DETECTION

BALANCE OF PLANT

Air corsipressors

Demineralization trains (Duplex)

Treated water transfer pumps

Diesel generator

Fuel storage capacity

Fuel pymped circulation capacity

2x100%

2.x > 100%

2x120%

1x 1C0%

Capacity 11 be the larger of: required to

start up from cold one incineration

stream or 120% of the content of the

largest gas oil road delivery tanker

2 X 200%

1x100%

1 X 1CG%

1x100%

1 X 100%

1x100%

1 X 200%

Table MS4a-5: Component redundancy levels

The Sub-Contractor will guarantee/expected equipment availability as follows:

• For the overall processing plant (boiler, furnace, flue gas treatment):

• Minimum annual availability: refer to Table MS4a-6 - Works Performance Schedule;

• Manual cleaning of the boiler: once a year only.

Availability.as set out in MSI-3c technical Specification Section 4.7 and Appendix C, which is still under

discussion with the EPC Contractor, is calculated as follows either as:

• [8760 - (planned stoppages in hours) - (unforeseen stoppages in hours)]/8760

• Planned and unforeseen stoppages apply to either stream.

» Planned stoppages will be less than 360 hours per year in accordance with the Technical

Specification as set out in MS1-3c.

• Or as set out in FichtnerTechnical Specification section 4.7 and Appendix C.

For the turbo generator:

• Minimum annual level of availability, refer to table MS4a-6 Works Performance Schedule;

• Manual cleaning of the whole condenser: as far as necessary.

For the flue gas treatment system:

Method Statement 4a Operational Interface

51

Page 52: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r^i. 1 ™^B

• Performance to be in accordance with WID.

• The Works shall therefore be designed and arranged to allow the processing of collected Waste in

accordance with the provisions of the Works performance. Expected performance levels and

guaranteed levels as set below:

Expected performance levels and guaranteed levels as listed below:

Performance Indicator

Flue gas temperature maintained

for at least 2 seconds in the

presence of at least 6% oxygen

(by volume dry) after final

introduction of secondary air, for

all Waste within the firing diagram

determined at design by CFD

modelling and during Performance

Tests, by tracer gas or other

technique used by the Contractor

and approved by the EA

Flue Gas treatment plant:

Unless otherwise stated, the

Guaranteed Performance Level

below shall be achieved with each

boiler firing at 100 MCR on Design

Waste

Maximum emissions

concentrations of pollutants as

specified under the WID under the

full range of firing conditions

shown within the firing diagram

and under the full range of raw

gas pollutant concentrations

Units

°C

Guaranteed Levels

850

WID limit

52

Page 53: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

Performance Indicator

Noise levels

Maximum noise at 1 m from the

equipment (excluding TG set,

steam bypass value of TF set,

safety valves)

Maximum noise at 1 m from TG

set

Units

DB(A)

DB(A)

Guaranteed Levels

85

95

Table MS4a-6 - Plant Guarantees

Performance Indicator

Boiler grate- values are for each

stream unless otherwise stated

1) continuous throughput at a net

calorific value at design of 9.7

MJ/kg (rolling average 3-4 hour

period)

2) heat release from the

combustion of waste at Design

Point (waste NOV 9.7 MJ/kg)

Corresponding reference

conditions for the heat release

guarantee:

Steam temperature at superheater

outlet

Units

t/hr

MWth

°C

Plant expected performance level

19.2

51.8

400

Method Statement 4a Operational Interface

53

Page 54: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r.iiiB Performance Indicator

Steam pressure at superheater

Steam flow at superheater outletl

Feedwater temperature at

economiser inlet

Primary air preheat temperature

Secondary air temperature

External air preheat temperature

Maximum heat release with grate

processing at the guaranteed

continuous throughput waste with

NCVof 14MJ/kg

Net power output measured at the

generator terminals at Design

Point

Maximum unburnt matter in

combined bottom ash and Boiler

ash as loss on ignition expressed

as Total Organic Carbon

excluding elemental carbon)

Maximum consumption of

hydrated lime per stream at

design point

Units

Bar-a

t/hr

°C

°C

°C

°C

MWth

MWe

%W/W

Kg/h

Plant expected performance level

61

64.2

130

150

40

15

51.8

17.6

3.0

224

^ Since the heat release from the waste cannot be accurately measured the steam flow from the superheater to the turbine is the parameter which represents the achievement of the heat release expected performance

54

Page 55: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•f;r\ift #OXFORDSHIRE COUNTY COUNCIL www oxfordsliifCPav.uk

[ Your coiincil tax vvorl-jngfcr you

Performance Indicator

Maximum consumption of

activated carbon per stream at

design point

Maximum concentration of Urea

per stream at design point

Maximum APC residue production

per stream

Minimum annual availabilities

(including unscheduled and

scheduled shutdown)

Overall plant

Turbogenerator

Units

Kg/h

Kg/h

Kg/h

%

%

Plant expected performance level

6.9

53

625

91.3 (First year only)

96

Table MS4a-6 - Plant Expected Performance Levels

Each of the two combustion lines will be sized to have a throughput of 19.2 tonnes per hour for waste having

a LCV of9,700.

WID compliance methodology

The results of the computation below are given under condition of confidentiality and are CNIM property.

The following paragraphs explain the method used at the Facility, to verify that the minimum temperature of

850°C is reached for a duration of two seconds in order to comply with the requirements of the WID. This

determines the necessity for starting up the auxiliary burner if the temperature is not reached. This is a

practical modelling fit for digital permanent control of boiler running. The correlation coefficients (see below)

are calculated from theoretical modelling.

Notations

• H 2s mean height reached by the gases two seconds after the last row of secondary air (m) (calculated)

• H roof geometric height between the last row of secondary air and the position of the continuous

measurement: T roof (m)

• O 2 humid oxygen level in the gases at the boiler output (percentage measured continuously)

Method Statement 4a Operational Interface

55

Page 56: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r^i i ib • Q steam stoam flow at boiler output (kg/h) (measured continuously)

• T adiab gas combustion adiabatic temperature (°C, calculated)

• T roof gas temperature at furnace roof (°C measured continuously, using three temperature transmitters)

Temperature measurement location

The most reliable temperature measurements for the flue gas are achieved by use of temperature probes

located on the roof of the combustion chamber.

For the Oxfordshire project, the Contractor has specified the use of three thermocouples with the rejection of

one measurement (in case this measure is too far from the average value measured by the two other

thermocouples). This average value is T roof

Temperature Tjs calculation formula

The formula is broken down into three stages:

Calculation of the adiabatic temperature

This depends mainly on excess combustion air and therefore the O2 in the gases.

T adiab = f(02) = a. O2 + b

The coefficients are calculated according to combustion conditions of the Oxfordshire boiler.

Determining the heigfrt corresponding to two seconds

Based on the chart of temperatures in the furnace for various operating configurations, characterised by the

load and excess air, the calculation obtains the value of the height corresponding to two seconds.

The height corresponding to two seconds is thus determined as a function of the excess combustion air (O2)

and the output of the boiler (steam flow).

H2S = 0 - 0 2 + d . O2. Q steam + 6 . Q steam + f

The various coefficients (c, d, e, f) are determined on the basis of the H2s values obtained from the chart of

temperatures in the combustion chamber.

Determining temperature T;,^

It is impossible to measure this value continuously for the various operating conditions. Therefore a method

of calculation has been adopted which comprises determining the value through linear interpolation between

the calculated adiabatic temperature (at secondary air nozzle level) and the average of three measurements

of roof temperature.

T2S - T adiab ~ ^2sl^ roof- ( T adiab ~ T roof)

56

Page 57: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

fir^Ki, Calibrating T roof

The continuous measurement of Troof is tainted with errors due to fouling of the thermowell and the effects of

radiation toward the cold walls. To avoid these errors, this measurement must first be calibrated using a

measurement carried out for different thermal loads, at the same level, by a specialised organisation using a

calibrated suction probe. The continuous measurement is then corrected using a formula determined during

this calibration phase.

The plant DCS can thus calculate continuously the temperature reached by gases two seconds after the last

injection of secondary air.

A process flow and energy balance diagram is provided in Figure MS4a-15 below.

EfW Plant Energy and Mass Balance s Export 600 kWh

Internal consumption

90 kWh

1 tonne of msw NCV 9.7 MJ/kQ

•4? 5 200 Nm' riut gas at aolltr txit

3 tonnes steam

HCI«700to1 200mgWm' S02= 150mg/Nm' Dust» 3 000 mg/Nm' Heavy metals » 40 to SO mg/Nm' DIoxins «1 to 5 ng/Nm'

HCI < 8 mg/Nm' SOjOOmg/Nm' Dust < 5 mg?Nm' Htavy metals < 0,5 mg/Nm' Dioxins < 0.08 ng/Nm' j CO < 30 ng/NmS

20 kg Scrap iron

220 kg Bottonn

ash 16 kg fty ash

STEEL I N D U S T R Y ) ( ROAD CONSTRUCTION J ^ • T ? ^

4 - 25 Kg residues depending on the process

,iiluiL£liiR

FIGURE MS4a-15 - Estimated Process flow and energy balance diagram

1.3.2 Waste vehicle turnaround

Waste will be delivered by RCVs and bulk articulated vehicles into the main reception hall. All vehicles

delivering waste will reverse into the building through roller shutter doors before depositing the waste into a

concrete storage bunker protected by kerbing. The tipping of waste into the bunker within an enclosed

Method Statement 4a Operational Interface

57

Page 58: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r^CY^t building ensures that potential nuisance which may be caused by windblown litter, odours and vermin is

minimised.

The required vehicle turnaround time for Authorised Vehicles will be 20 minutes except for HGVs which will

be 25 minutes.

To achieve the twenty minute turnaround time the Contractor will adopt the following operational strategy:

• Authorised Vehicles delivering Contract Waste will be given preference over other users of the Facility

in delivering Waste;

• Computerised data recording system for Weighbridge operations;

• Adequate traffic control, well maintained roads and hard landscape;

• Tipping hall designed for simultaneous safe tipping of Waste from up to nine vehicles;

• Assistance from well trained Facility staff for unloading Contract Waste;

• Clear, visible and legible signage to safely direct Authorised Users around the Site

• Provision of a separate Weighbridge for vehicles exiting the Site so as to minimise the on-Site queuing.

• Active bunker management to maximise tipping capacity;

• A manned loading shovel will be available during delivery periods to clean up spillages and clear tipping

bays;

• Preference shall be given to vehicles weighing out as opposed to those weighing in;

• Contract Waste HGV deliveries shall be scheduled with reference to the RCV delivery schedule; and

• Non-Contract Waste deliveries shall be scheduled outside peak RCV deliveries.

The proposed traffic management system (Section 1.3.7 of this Method Statement) together with the

provision of dedicated Weighbridges will facilitate the shortest possible turnaround times for vehicles

delivering Contract Waste.

The Contractor confirms that its design of the Facility will achieve the required vehicle turnaround time of

twenty minutes.

Critical points in ensuring vehicle turn around times are the capacity of the Weighbridges and the tipping bay

to accommodate the overall daily load to the Facility. A Weighbridge each is provided for the weighing of

incoming and outgoing vehicles. The tipping hall has nine tipping bays and is designed for simultaneous

Waste tipping in all nine bays.

In order to prevent queuing and achieve the required turn around time, it is considered that each RCV

delivering Waste to the Facility should be able to occupy, on an average, the Weighbridge for two minutes

58

Page 59: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

ri"^iB and a tipping bay for five minutes. Since the availability of the critical elements (Weighbridge and tipping bay)

is more than that is actually required, no queuing of vehicles is anticipated. This will ensure achievement of

an average vehicle turn around time of twenty minutes.

Vehicle turnaround times will be recorded using the electronic Weighbridge system which will register the

time that each Authorised Vehicle weighs in to Site and the time that each vehicle weighs out having

deposited its load.

Vehicle access to the Ef/V/IBA facility

Vehicle access to the Site will be from the public road, the B430 to the west via a new junction and access

road. This access road will be provided with a new gatehouse and Weighbridge that will control all access to

and from the Site.

1.3.3 Working with local authorities

The Contractor will invite Waste Collection Authority (WCA) representatives to participate in meetings of the

Project Liaison Group as specified in Schedule 6 (Liaison Procedure). Such meetings will routinely take

place on a quarterly basis, although additional meetings can be convened at any time. This will be the

primary mechanism for establishing and maintaining a productive working relationship with the WCAs. A

progress report will be tabled for every quarter. Regular Site tours will be offered to the officers and the

elected members of the WCA.

1.3.4 Contract waste handling philosophy

The Facility will comply with local, national and European regulations and guidelines as well as the Waste

objectives of the Authority.

Waste reception will initially take place at the entry Weighbridge, after which all Waste delivery vehicles will

be directed to the reception hall, where Waste loads will be deposited into the Waste storage bunker. The

Facility will have a storage capacity of between 3 and 5 working days (depending on the level of stacking

employed in the waste bunker) to ensure continuous operation during weekends and bank holiday periods.

All Waste reception and handling areas will be provided with adequate traffic control and safety barrier

systems, lighting, fire sprinkler system, drainage, effluent treatment, ventilation and dust suppression

equipment as minimum requirements.

The Contractor will ensure that all Waste processing, treatment and product storage will take place within

confined spaces with appropriate environmental controls provided. A key element of these controls will be

the provision of an extraction system drawing air from above the Waste storage bunker into the combustion

process in order to minimise the potential dispersal of dust and odour around the reception hall.

Method Statement 4a Operational Interface

59

Page 60: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r^crw. Contract Waste handling will predominantly use automated processes with grab cranes, conveyors, moving

grates and hoppers. In conjunction with the environmental controls described above, this will ensure that the

potential for operational staff to come into direct contact with Waste is kept to a minimum at all times.

Process residues in the form of ash will be collected and stored in purpose built hoppers to ensure that fine

particulates are suitably contained at all times.

The Waste in the bunker will be managed by a duty and standby crane and grab system operated by a crane

operator accommodated in the control room located at high level with a direct view over the bunker area.

The cranes will normally be operated semi-automatically but may also be operated manually if required. A

separate loading hopper and shredder will be provided to take bulky household Waste and reduce it to a

suitable size for input onto the grate.

For the evacuation of APC residues, the Contractor will use mechanical equipment, e.g. screw conveyors,

chain conveyors and a final bucket elevator, to deliver the bulk material into the silo for APC residues. The

whole process is sealed to minimise any risk of spillages on Site.

In order to avoid operational difficulties due to deposit accumulation, equipment for conveying dust between

extraction from the flue gas plant components and the intake of the residue silo is insulated and equipped

with electrical trace heating.

Bottom ash storage:

Process residues in the form of ash from the bottom of the grate will be collected and stored in purpose built

bunkers to ensure that fine particulates are suitably contained at all times.

Metals from bottom ash will be recovered for recycling and the Contractor proposes to recycle the remaining

bottom ash as secondary aggregate.

The Facility bottom ash storage will minimise conveyor runs and spillage, helping to avoid windblown

nuisance and cleaning.

Air pollution control residue storage:

Air Pollution Control residues (APC), which are hazardous in nature, will be loaded into purpose designed,

sealed aluminium vacuum tankers, driven by appropriately trained drivers. Once all the paperwork has been

checked at the Hazardous Waste disposal Facility at Bishops Cleeve, the tanker will discharge its load in a

sealed system, to one of the four silos available at Bishops Cleve and subsequently treated prior to disposal.

Boiler ash storage

Boiler ash will be collected from boiler and economiser hoppers and conveyed with the bottom ash.

60

Page 61: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r:, l i s C OXFORDSHIRE t'COUNTY COUNCIL

r council Idx wcrking for you

Fly ash

Fly ash will be captured along with the APC residues.

1.3.5 Operation maintenance and inspection

There will be ten tipping bays into the waste bunker as shown in the Site layout drawings in Appendix

MS1-4a. This will provide sufficient discharge points to prevent undue delays to Waste collection and

transfer vehicles, taking into account peak time delivery patterns.

All Waste reception and handling areas will have adequate traffic control and safety barrier systems,

including traffic lights and LED displays, registration and recording systems and identification systems.

Individual vehicles will be instructed to use particular bays, giving the Facility a high degree of accountability

and making it easier to audit.

On entry to the Facility, all incoming deliveries will be inspected either visually and or via remote CCTV by

the Weighbridge staff. Visual inspections of the Waste will be carried out by the crane operators at the

tipping hall.

The Facility design will be sufficiently flexible to allow for the acceptance of a wide range of vehicles

throughout the Contract Period.

1.3.6 General access items

Public transport

A scheduled bus service operates along the B430 within the vicinity of the Site. The nearest bus stop to the

Site is located to the north of the Site access.

A travel plan will be developed by the Contractor to encourage the use of public transport and discourage car

use for the construction period and later during normal operation of the Facility.

Pedestrian access

The main pedestrian access to the Facility will be from the bus stop along a ramped footpath designed to

wheelchair standards of gradient with non-slip surfaces.

Vehicle circulation within the site

Vehicles leaving the public highway to access the EfW Facility will proceed to the gatehouse and

Weighbridge located adjacent to the southern boundary of the Site via a redesigned junction and newly

formed access road. From the gatehouse entry vehicles will proceed to the roundabout.as set out in

drawings 0385 08 02 02 / 65 G 004 in Appendix MS1-2f).

Method Statement 4a Operational Interface

61

Page 62: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r»n^^B Waste vehicles will proceed from the roundabout via a two-way road along the southern boundary of the IBA

Facility. They will then travel around the eastern end of the Facility to enter the tipping hall at its southeast

entrance, and continue through the hall before returning to the Weighbridge via the roundabout prior the

leaving the Site. This movement arrangement allows the natural safe reversing of right hand drive vehicles

depositing Waste into the bunker.

Vehicles for the loading and transporting of incinerator bottom ash (IBA) off Site will proceed from the

roundabout, travel around the southern and eastern end of the Facility and enter the IBA Facility at its east

entrance. They will then continue through the plant before returning to the Weighbridge via the roundabout

prior the leaving the Site.

Vehicles for the residue silos the flue gas treatment area and plant maintenance will proceed from the

roundabout along the two-way road around the southern and eastern side of the Facility. They will continue

around a single lane road to the east of the air-cooled condensers turn south around the northern tp of the

EfW to enter the building at the north west entry. Loading and unloading will take place inside the building.

The vehicles will then leave the Facility and proceed south, picking up the two lane road to the south of the

ACC and proceeding around the southern boundary of the IBA Facility to the roundabout and then to the

Weighbridge.

Vehicle parking

A safe parking area will be provided for staff and visitors in front of the offices. Parking provision at the Site

has been devised in line with car parking standards and guidelines operating in Oxfordshire. This parking is

accessed by the two-way road off the roundabout to the west of the EfW.

The parking area is designed with discrete circulation away from the lorry circulating routes. There will be fifty

two car parking spaces at the Site, four of which will be larger spaces specifically designated for blue badge

holders. A lay-by will be provided for visitors' coaches or minibus standing.

Cycle parking

In order to encourage staff to cycle to work in line with the travel plan initiatives, a covered cycle storage for

fifteen bicycles will be provided for cyclists adjacent to the administrative building as set out in Drawing No.

0385 08 02 02 / 65 G 004 in Appendix MS1-2f.

Pedestrian access to the building

All pedestrian areas will be clearly signposted and traffic control measures will be implemented to ensure

safety. Access to the entrance of the main Facility, the Visitor Centre and the EfW offices has a gentle

ramped footpath, designed to wheelchair standards of gradient with non-slip surfaces. It is designed to have

contrasting coloured bands and textures to aid perception for people with visual impairments. The spaces

62

Page 63: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•rii^ti. mm ^ ^ COUNTY COUNCIL

www Oxfordshire gov,uk

specifically designated for blue badge holders are located nearest to the entrances to the offices and main

Facility.

Routes

Routes to the entrances will be signposted with signs meeting the recommendations of the Sign Design

Guide (as per the Sign Design Society guide to inclusive signage and complying with the Disabilities

Discrimination Act). The main entrances to the plant and the offices will be highlighted using colour and

luminance contrast and an appropriate level of lighting.

A Transport and Traffic Management Plan for the Facility is provided in Appendix MS4a-2g it includes the

tonnage of Waste that is expected to be transported on the roads within and outside the Site boundary.

Access to car parks is separated from the access for Waste delivery and haulage vehicles and therefore will

not interfere with the proposed Waste delivery arrangements and vehicle turnaround times. The exit from the

car park to the main roundabout at the entrance will have a give way sign and speed limit of 10 mph will be

implemented at the roundabout.

Please refer to the detailed Transport and Traffic Management Plan in Appendix MS4a-2g for traffic control

proposals including safety barrier systems.

1.3.7 Traffic management plan

A detailed assessment of traffic to and from the Facility during the construction and operation phase was

undertaken and taken into consideration in preparing a transport and traffic management plan for the Site.

Please refer to the detailed Transport and Traffic Management Plan provided in Appendix MS4a-2g for more

details.

1.3.8 Non-authorised vehicle procedures

it is expected that the Contract Waste will be delivered to the Facility in Authorised Vehicles in accordance

with Schedule 26 (Non Authorised Vehicle Procedure), previously agreed by the Authority and whose details

are passed in the Contractor's data base. In the rare event of delivery of Contract Waste in a non Authorised

Vehicle, the vehicle will be directed to park at a designated location by the Site staff. The vehicle registration

number, the WCA authority from where the Contract Waste is generated and the Waste Carrier's licence will

be recorded. The Authority's Representative(s) will be contacted immediately to confirm acceptance of

Contract Waste brought to the Facility in the non Authorised Vehicle. Subject to approval from the Authority's

Representative, the non Authorised Vehicle will be directed to the Weighbridge and the Contract Waste will

be accepted as detailed in Section 1.8 of Method Statement 4a.

Method Statement 4a Operational Interface

63

Page 64: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

"^•E

Where the Authority does not authorise the Waste brought to the Facility in a non Authorised Vehicle as

Contract Waste, The Contractor reserves the right to send back the non Authorised Vehicle without

accepting the Waste.

Non Authorised Vehicles shall not be subject to the twenty minutes guaranteed turnaround time.

Audit Trail for Non-Authorised Vehicles

The proposed data recording procedures (section 1.3.11 of Method Statement 4a) will allow separate audit

trail of Contract Waste delivered in Non Authorised Vehicles.

1.3.9 Waste transport plan

A Transport and Traffic Management Plan indicating tonnage and vehicle type for movement of Waste and

materials to and from the Facility and from the Facility to the final destination is prepared and attached

(Appendix MS4a-2g).

1.3.10 Waste weighing and data management

A fully computerised Weighbridge system will be employed comprising two units (one to record vehicles

entering the Site, one to record those leaving the Site) to record the arrival and departure of all vehicles

carrying Waste into or away from Site.

The Weighbridges, incorporating a computerised data handling system, will be used to record the details of

all vehicles delivering Waste to the Facility, removing process outputs (residues and products) from the

Facility and other waste transfer operations. All vehicles will be inspected, monitored, weighed and

electronically recorded to capture (as a minimum) the following information:

• Transaction date;

• Description of Waste (including EWC code);

• Gross, tare and net weights;

• Disposal contractor number;

• Collection round reference number

• Fleet number

• Registered Contract Waste carrier number;

• Source/destination of Waste/product/residue;

• Time of arrival/departure;

• Vehicle registration number; and

64

Page 65: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

f i l ^ l . :!?% OXFORDSHIRE ' i ' - ^ COUNTY COUNCIL

[_ Your council tax v.'c;ijng far you _

• Driver name and reference number.

Weighbridge tickets will be issued to each vehicle transporting Contract Waste to or from the Facility and

copies of such tickets will be retained for a period of seven years. The computerised data handling system is

explained in section 1.6 of the Method Statement 4a.

Calibration

All Weighbridges will be maintained in accordance with the manufacturers' recommendations and in line with

Trading Standards statutory requirements. Weighbridge maintenance will be incorporated into the overall

maintenance plan to ensure that the appropriate inspection and calibration frequencies are adhered to.

The Weighbridge loadcells and electronics will be factory tested and approved prior to installation. Final

calibration will be carried out on Site by a manufacturer. The Contractor will enter into a contract for a

calibration service performed under the UK Weighing Federation Code of Practice for the Calibration of Non-

Automatic Weighing Machines (NAWIS) and the Institute of Measurement and Control Code of Practice for

Industrial Weighing Equipment. All test weights used for calibration will be UK Accreditation Service (UKAS)

calibrated, providing direct traceability to the National Physical Laboratory.

The system will contain all the data necessary for the Authority to comply with statutory reporting

requirements such as Waste Data Flow. The Contractor will email all the necessary data to the Authority on

a monthly basis. For day to day contract management the Contractor will accept the use of emails,

supported by faxed copies of documents where necessary.

The system will provide an auditable trail for each load of Contract Waste through every stage of the

process, from receipt to final processing or disposal.

Waste records kept will be suitable for the Environmental Permit and Environment Agency authorisation.

The Contractor will keep any additional Waste records that might reasonably be requested by the

Environment Agency or by the Authority

When Waste is delivered by a Waste Collection Authority, its contractors or other Authorised Users, their

vehicles will only be accepted if they have been pre-registered by the Authority or the Contractor. Vehicles

will be recognised through Automatic Number Plate Recognition (ANPR) systems.

CCTV provision

Colour CCTV facilities will be provided at each Weighbridge. The facilities will be operational during the

opening hours of the Facility. Recordings will be retained and stored for a minimum of ninety days and will be

made available to the Authority's Representative upon request.

Method Statement 4a Operational Interface

65

Page 66: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

ri^^i. Contingency arrangements for waste weighing and data management

In the event of Weighbridge failure a manual system of data recording will be implemented. The manual

system will only be required in the event of complete failure of both weighbridges. As a minimum, the manual

system will record:

• Date;

• Description of Waste (including EWC code);

• Gross, tare and net weights;

• Disposal contractor number;

• Collection round reference number

• Fleet number

• Registered Contract Waste carrier number;

• Source/destination of waste/product/residue;

• Time of arrival/departure;

• Vehicle registration number; and

• Driver name and reference number.

The manual recording system will be fully auditable and will remain in operation until such time as the

automated Weighbridge system comes back on line.

If the gross and net weights are not available, all the other information will be recorded and a comparison will

be made with the average net weight of the previous four weeks for that collection.

1.3.11 Product outputs (monthly and annual)

For product outputs please refer to MS 2 Section 1.3 and MS 4A-Part 6 Management of Products and

Residues.

1.4. Site security

The Contractor will ensure provision of the necessary fencing and security arrangements to maintain the

safety and security of the public. Site staff, visitors and company assets. Site specific fencing and security

arrangements will be determined by risk assessment.

Perimeter security:

• A boundary fence will provide perimeter security which will be a 2.4 m galvanised palisade fence.

66

Page 67: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

F^R^i, i»>;«w3:<tH; ^ ^ COUNTY COUNCIL

www oxfotdsliire gov.Lift

rcouncil tax v.'CFJing fcryou

• The main entrance gate will be an electrically driven sliding gate. It will be open during normal working

hours and be closed at all other times. The gate may be opened via swipe card, remotely over an

intercom connection to the control room or locally via manual override situated on the Facility side. The

gate will open automatically when exiting the Site.

• A pedestrian gate will be adjacent to the main entrance gate. It will be fitted with an automatic closing

mechanism and remain closed at all times when not in use for access. It will open by means of a swipe

card, over an intercom with the control room or locally via manual override situated on the Facility side.

The gate will be opened by push button when exiting the Site.

• Supervised CCTV will monitor the entrance gate, pedestrian gate and the whole boundary either from

the Gatehouse during normal operating hours of from the Control Room during night time hours.

Security for external areas:

• High level CCTV cameras will be strategically positioned, mounted on buildings on masts. Cameras will

be fitted with infrared lights for night time coverage, to reduce light pollution. All external CCTV cameras

will have an automatic sweep and manual override option. Cameras will be linked to and controlled

from monitors in the Weighbridge offices and main control room for night time coverage should a night

time watchman not be employed.

• External lighting will be kept to the minimum level required to allow safe working and pedestrian/vehicle

movement.

• Deterrent security lighting may be installed, together with movement-activated lighting around non-

operational pedestrian doors.

• External gates will have a default open position on power failure. There will be an emergency override

button in the control room.

Internal security:

• Restricted areas will have their own locking and security system with access restricted to specified

personnel and controlled via a swipe card system

• Reception area:

• In and out quick-close vehicle doors will be operated in conjunction with the Weighbridge systems;

their default position will be closed.

• The pedestrian door will be opened using a live swipe card, with exit via a push bar.

» CCTV coverage will monitor the area, controlled from the main control room.

• EfW plant

Method Statement 4a Operational Interface

67

Page 68: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r r ni. • CCTV coverage will monitor the area, controlled from the main control room, including any night

time coverage should a night watchman not be employed.

• Vehicle doors will have a default closed position, which can be overridden by a swipe card, to allow

forklifts etc to move bacl<wards and forwards

• Pedestrian doors will be opened from the outside using a live swipe card, with exit via a push bar

• The main control room will be a secure room located within the EfW plant:

• The pedestrian door will be operated by a live swipe card. The door will be linked to a coded entry

alarm

• A direct line to the police will be located in the control room.

Visitor centre/ office

• Main entrance and rear entrance doors will be opened by means of a live swipe card, or following

intercom communication with the office or the main control room who will manually open the door

remotely. Exit will be by push button activation.

• Fire escape doors will have a push bar opening.

• All doors will be alarmed.

Entry, exit and movement controls:

In addition to the door controls mentioned earlier:

• Visitors will be required to sign in and out at the office during normal working hours. Out of working

hours, visitors' credentials will be verified via the main gate telecommunications link, before they

proceed to the main control room to sign in

• Movement around the Site outside of clearly designated pedestrian and vehicle routes will be controlled

and limited to those individuals who have completed the Site safety induction course

• Contractor (maintenance) vehicles will sign in at the Weighbridge kiosk before proceeding to their

location for work.

The Contractor will also ensure provision of sufficient lighting levels to facilitate safe completion of all

operations and activities (internal and external) required at the Facility.

External lighting units will be positioned and installed in order to create the optimum spread of lighting in

accordance with CIBSE guidance, while optimising the number of units needed to meet those requirements.

Each unit will have integrated baffle diffuser controls to minimise light pollution, both laterally beyond the Site

boundary and vertically.

68

Page 69: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r^niK Arrangements for dealing with vandalism

Routine checks will be carried out on the integrity of the Site security infrastructure, including daily checks of

the infrastructure at the EfW building and a weekly check of the perimeter fencing. Any vandalism events will

be fully documented within the Site diary and presented in the Monthly Service Report along with the details

of any actions taken to repair damage. Any damage to Site security infrastructure identified during routine

inspections will be made good within forty eight hours.

Procedure for notifying the council of breaches in site security

All breaches in Site security will be reported to the Authority within two working days of the incident being

recorded. Security breaches will also be formally recorded and submitted to the Authority as part of the

Monthly Service Report process.

1.5. Waste handling procedures

All Wastes will be handled and stored in accordance with:

• The prevailing regulatory requirements regarding Waste management and health and safety;

• Technical specifications and operating requirements of the EfW process developed by CNIM

• Site specific operating procedures to be developed and maintained by the Contractor throughout the

duration of the Contract.

• Details of Waste handling and storage at each stage of the process are provided in Section 1.3.1 of this

method statement.

The Contractor will operate and maintain the Facility for the storage and handling of Waste on Site such that

there are no releases to water or land during normal operation and that emissions to air and the risk of

accidental release to water and land are minimised. All Waste handling and storage arrangements at the

Facility will be in compliance with conditions of the PPC Permit. The overall Waste handling and storage

arrangements that will be provided for the Facility are summarised in the Table MS4a-7.

Description of Waste

Reject loads

Oversize or

unacceptable Waste

Manner of Storage

Segregated area. Loose and liquid

loads in containers.

Segregated area. Loose and liquid

loads in containers.

Storage Conditions

Impermeable hard standing within

Waste reception hall.

Impermeable hard standing within

Waste reception hall.

Method Statement 4a Operational Interface

69

Page 70: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

^V1^. w L. 1 -'V H P

Bottom ash

APC residues

Waste for incineration

Waste oil

Metals for recycling

Other Wastes

Dedicated bottom ash bunker within

building.

Dedicated APC silo vented through

self cleaning fabric filter.

Dedicated Waste storage bunker.

Drums

Dedicated section of ash storage

area.

Drums or bins.

Concrete hard standing with

contained drainage.

Inside building in dedicated area with

contained drainage.

Inside Waste reception area

Drums to be clearly marked, held on

contained concrete hard standing.

Concrete hard standing with

controlled drainage.

Concrete hard standing with

controlled drainage.

Table MS4a-7: Waste handling & storage arrangements

The bottom ash storage/transport containers will be sealed to prevent emissions of dust and leachate while

being transported off-Site.

1.6. Incoming waste procedure

The particular software to be used for this contract will be Gatehouse, which is a computer based system,

linked to the Weighbridges at each Site.

Within the Gatehouse system details that will be held include:

• Name and address of each WCA delivering Waste to the Site,

• Name and address of each haulier/recyclate processor collecting Waste from the Site,

• Full Waste Transfer Note details for each customer/delivery,

• Waste Carriers' Licence details,

• Vehicles used by each customer,

• Every category of Waste delivered and recyclate/product removed from the Site.

Every time a delivery or collection is made at a Site the weight of the full and empty vehicle will be recorded

and a Weighbridge ticket produced. The ticket will contain a reference number, date and time of each

transaction, vehicle registration number, name and address of the account against which the transaction is to

be recorded, the gross, tare weight of the vehicle, the net weight of the material delivered or collected, the

70

Page 71: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

Fj^lli S«OXFORDSHlRE m S COUNTY COUNCIL

r council tax v.-ort-ing fcr you

Waste Carrier's licence number and the Waste transfer note reference. That ticket is also stored

electronically and both the paper and electronic versions have the same unique reference number, thus

ensuring traceability at all times.

If for any reason there is an error found on the ticket, an incorrect Waste category for example, the original

ticket cannot be deleted. A new ticket has to be issued.

The Gatehouse system can be interrogated at any time and is capable of producing a wide range of reports

based on the data stored. It is proposed that the precise form of reports for this Contract be jointly agreed.

The Contractor will email copies of the reports to Oxfordshire County Council (monthly) and this will include

details of Contract Waste received from each WCA, and commercial premises and the tonnage of Non

Contract Waste.

Smouldering loads

Where Waste delivered to the Facility contains a smouldering load presenting a risk of fire, the load will be

quarantined and the Site foreman and Site manager will be informed about the load immediately. They will

implement Site emergency procedures specific to explosion and fire. Specific emergency procedures will be

developed and implemented by the Contractor. All Facility staff will receive detailed health and safety training

as part of their induction and all Site operatives will be given full training on Site specific health and safety

issues. The Contractor's health and safety and emergency procedures are available at each Site as well as

in the company's intranet system where all employees have full access. The Waste will be discharged from

the vehicle in a designated area if safe to do so.

Fire suppression equipment will be located at the entrance to the plant. Once on Site, each load will be

inspected visually to check for smouldering loads, roadworthiness, and non-conforming materials. Inside the

treatment plant, there will be a fire ring main and fire suppression equipment.

A copy of the list of generic unit emergency plans as available on the Contractor's intranet is attached

(Appendix MS4a-2j). A copy of the Contractor's Site emergency and safety plan guidance is also attached

for Authority's review (Appendix MS4a-2k). A Site specific emergency and safety plan will be developed

when the detailed layout of the plant and associated process are fully understood. This will ensure that Risk

Assessments are as comprehensive as possible.

Hazardous waste

The Contractor's procedure for accepting Waste mitigates the risk of Hazardous Waste being tipped at Site

in accordance with the Contractor's Standard Operating Procedures as Appendix MS4a-2l.

All employees employed in the reception, handling or transfer of Waste at the transfer stations will receive

training in the form of toolbox talks and on Site demonstration of how to look for and deal with Hazardous

Method Statement 4a Operational Interface

71

Page 72: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r;c^ift Waste in loads delivered to a transfer station. This training will be followed up by regular assessments of

performance, and additional training will be provided where necessary.

If any deposited Waste is identified to contain Excluded Waste it shall be managed in accordance with

Schedule 29 (Waste Acceptance Protocol). If particularly Hazardous Waste of sufficient high risk is

encountered, such as asbestos or radio active Waste, the unit emergency procedures will be implemented.

Quarantine procedure

A designated area will be provided for the storage of quarantined materials prior to their removal from Site

for disposal or other treatment as deemed appropriate.

The quarantine area will incorporate dedicated containers for those materials that require specific handling,

storage or disposal, for example Hazardous Wastes. The disposal route of such materials will be fully

documented to ensure that compliance with all relevant prevailing legislation is maintained.

1.7. Spillages

Control of pollution from leaks and spillages

In order to mitigate against the risk of surface water pollution occurring during development and operation of

the Site the following management measures will be included:

• A traffic management system will be put in place to reduce the potential conflicts between vehicles,

thereby reducing the risk of a collision and potential fuel release; the Contractor will incorporate a Site

routing systems for the vehicles i.e. a one way system, with traffic lights etc as appropriate

• A Site speed limit will be enforced to further reduce the likelihood and significance of collisions;

• Refuelling of vehicles will either be undertaken in a surfaced compound area from a fuel tank(s) bunded

in compliance with the Control of Pollution (Oil Storage) (England) Regulations 2001, and PPG2 or

undertaken off-Site to minimise the risk of uncontrolled release of polluting liquids/liquors;

• Maintenance of plant and machinery will be undertaken within the Site compound or off Site, as

appropriate, to minimise the risk of uncontrolled release of polluting liquids;

• Spill kits will be made available on Site to stop the migration of spillages should they occur;

• Soil movements and excavations will be undertaken using methods that minimise the generation of silt,

and all soils will be stored in accordance with the relevant guidance (PPG1, PPG5 and PPG6) to avoid

the migration of contaminated liquors. Where necessary, ditches will be cut to capture runoff from areas

generating clay and silt to allow settlement of fines (clay and silt fractions) prior to discharge;

• Foul water will be managed on Site will be managed in accordance with PPG4;

72

Page 73: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•f^C^'vv i jfT* OXFORDSHIRE •te?! COUNTY COUNCrL

f ccunciildx v/ci'^Jngfci-ya

• Disturbance of made ground will be minimised during construction works Contained drainage will be

used to control any process water spillage.

All Site vehicles will be maintained so as to prevent the escape of polluting substances. Filling of fuel and

other fluids will take place in designated areas to minimise the risk of leakages escaping. Spill kits will be

maintained in designated locations at the Facility. These will be located adjacent to areas assessed as

having the potential for uncontrolled release. If customers' contractors' or visitors' vehicles and plant is

observed to be leaking they will be notified and appropriate measures taken.

Control and monitoring of surface water discharge

All areas of sealed hardstanding, gullies, drainage channels, drains, and downpipes etc will be inspected

monthly to ensure they are free of blockages and are functioning correctly. Any malfunctioning drainage

system will be rectified in a timely fashion.

Monitoring of surface water quality will be arranged with the compliance chemist in the event of spillage or

leakage of potentially polluting liquids.

In the event of a spillage, the following steps are proposed:

Minor spills

• Cover with absorbent granules and leave to work for effect as per instructions on the container.

Major spill, leakage or run-off

• Evacuate the area if necessary.

• Inform supervisor or manager who will follow up on any first aid delivered or provision required.

• Contain with bunds, oil absorbent granules, sand or booms to prevent spill reaching drains and

watercourses.

• If spillage has potential to reach drains, drain outlets should be bunged.

• If there is a risk of fire contact the Fire Brigade.

• Inform area manager or Contracts office who will notify the EA and arrange for a specialist contractor to

clear up.

A Site specific UEP will be prepared by the Contractor and co-ordinated by the CDM co-ordinator. The CDM

letter of appointment is shown in Appendix MS5 -4d.

Method Statement 4a Operational Interface

73

Page 74: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

f.^ui. 1.8. Non-contract waste

The Contractor will develop the Site for a design capacity of 300,000 tonnes per annum. This will ensure,

without risk, sufficient capacity for Contract Waste over the entire Contract period.

The Facility is being designed with buffer capacity of around 140,000 tonnes per annum in order to deal with

local Commercial Waste and MSW from other Local Authorities. For the avoidance of doubt, priority will

always be given to Contract Waste.

It is predicted that around 100,000 tonnes per annum of locally generated Commercial Waste will be

accepted at the Site. The majority of this will be generated within the northern part of the county. Generally

this will be in Cherwell including Banbury and Bicester, parts of West Oxfordshire District and the northern

areas of Oxford City itself. The Contractor will develop further Services at the Facility to encourage Waste

carriers operating within the area to utilise the Site.

Preference will be given at the Facility for treatment of Contract Waste. Extensive, robust and independently

audited Management Information Systems (IMS) will track, save and provide separate audit trails for

Contract and Non-Contract Waste. All Waste deliveries to the Facility will be measured at entry and exit

Weighbridges. The electronic data management system as explained in Section 1.6 of this Method

Statement will enable separate audit trail of Contract Waste and Non-Contract Waste.

74

Page 75: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

Fiil^k (.OXFORDSHIRE rcOUNTY COUNCIL

www oxfurdsfiire gov.uk

r council tax'.vcr^jng fcryou

Part 2. Information

2.1. Management information systems

2.1.1 Computerised data handling system

The particular software to be used for this contract will be Gatehouse, which is a computer based system,

linked to the Weighbridges at the Site.

Within the Gatehouse system details that will be held include:

• Name and address of each WCA delivering Waste to the Site;

• Name and address of each haulier/recyclate processor collecting Waste from the Site;

• Full Waste transfer note details for each customer/delivery;

• Waste carrier's licence details;

• Vehicles used by each customer; and

• Every category of Waste delivered and recyclate/product removed from the Site.

Every time a delivery or collection is made at a Site the weight of the full and empty vehicle will be recorded

and a Weighbridge ticket produced. The ticket will contain a reference number, date and time of each

transaction, vehicle registration number, name and address of the account against which the transaction is to

be recorded, the gross, tare weight of the vehicle, the net weight of the material delivered or collected, The

waste carrier's licence number and the Waste transfer note reference. That ticket Is also stored electronically

and both the paper and electronic versions have the same unique reference number, thus ensuring

traceabillty at all times. If for any reason there is an error found on the ticket, an incorrect Waste category for

example, the original ticket cannot be deleted. A new ticket has to be Issued.

The data handling system will be directly linked to Weighbridges at the Facility to ensure that data are

automatically transferred without the need for manual Input (other than during periods of Weighbridge

breakdown).

The Gatehouse system can be interrogated at any time and is capable of producing a wide range of reports

based on the data stored. The system will be used to generate the reports specified in the draft Project

agreement. The precise form of reports for this contract shall be jointly agreed.

The Contractor will email copies of the reports to the Authority on a monthly basis as part of Monthly Service

Report and this will include details of Contract Waste received from each WCA, commercial premises and

the tonnage of Non Contract Waste. For day to day Contract management the Contractor proposes the use

of emails, supported by faxed copies of documents where necessary.

Method Statement 4a Operational Interface

75

Page 76: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

2.1.2 Recorded data list

The Contractor will maintain copies of all documents relevant to ensure successful audit trail of all aspects of

the Contract including project communications, meeting notes. Weighbridge tickets, monthly and annual

reports (specified in the draft Project agreement).

The electronic filing system will include the copies of the following as a minimum:

• Monthly Service Report;

• Annual Service Report;

• Best value performance plans (relevant to Contract Waste management);

• Minutes from the Project liaison group meetings;

• Relevant information and data regarding completion of Works and to monitor the Contract's

performance in line with the specification, payment mechanism and Performance Measurement

Framework.

• Service Delivery Plans;

• Data and information required for the purpose of determining the Unitary Charge in accordance with the

payment mechanism and invoicing requirements;

• Details of all Contract Waste and Non-Contract Waste accepted at the Contract Waste treatment

Facilities including:

» Total tonnage of Contract Waste and Non-Contract Waste;

• Number of separate deliveries;

• Quantity of Contract Waste and Non-Contract Waste stored on Sites at the beginning and end of the

relevant Contract Month;

• Quantity of Contract Waste and Non-Contract Waste treated;

• Sources and type of Contract Waste and Non-Contract Waste

• Number of Authorised Vehicles and tonnage or estimated tonnage of Contract Waste rejected prior

to discharge.

• Details of all Contract Waste, Non-Contract Waste and process residues removed from the Sites

including:

• Total tonnage broken down by type;

• Contract Waste

76

Page 77: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

• Input tonnage

• Recovered metals

• Bottom ash

• Fly ash

• Waste to landfill

• Non-Contract Waste

• Input tonnage

• Recovered metals

• Bottom ash

• Fly ash

• Waste to landfill

» Number of outgoing loads

• Destination

• Details of any breaches of Legislation, or Necessary Consents;

• A statement of the status of all Necessary Consents and any applications for new or amended

Necessary Consents;

• A resume of the reasons for any delay in the provision of the Service together with details of the actions

and timetable to be taken to mitigate delays;

• A summary statement of any changes requested by the Authority or by the Contractor and agreed by

the Authority in the case of material changes;

• Details of any outstanding information required by the Authority and/or the Contractor in connection with

the Contract;

• Details of each instance of the events and circumstances resulting in Non-Acceptance Deductions or

Mileage Deductions or Performance Deductions;

• Details of any complaints received from the public and/or the Authority, the response provided, lessons

learned and mitigating actions undertaken;

• Details of any health, safety or welfare related issues and lessons learned including any RIDDOR

reportable incidents;

Method Statement 4a Operational Interface

77

Page 78: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r'~i r m ^ MD

• Details of any fires and the reasons for the fires occurrence along with the Contract's proposals to

prevent future reoccurrence;

• Any relevant training initiatives undertaken or planned;

• Details of any deliveries of Contract Waste that have been rejected;

• Any other matter reasonably required by the Authority in relation to the Project;

• Results of any audits or inspections undertaken by any Relevant Authority; and

• Any security breaches.

2.1.3 Council access

The Contractor will seek to have a partnering approach with the Authority in delivering the services and will

provide the information and reports as specified in Clauses 24, 43, 91 and Part H of the Project Agreement.

Where the Authority wishes to have access to the data that has been used for the preparation of these

reports, the Contractor will endeavour to meet the Authority's requests provided access to commercially

sensitive data not directly relevant to the Contract is not requested.

The Gatehouse system to be implemented at the Site is capable of remote interrogation of data. The

Contractor will agree the data access requirements with the Authority.

The Contractor has undertaken a number of developments over the last year and is now able to offer these

added value Services to the Authority as part of a transparent and communicative approach. These

developments are outlined below and the Contractor will consult the Authority for input to the design of these

systems and the output requirements.

Contract monitoring software and the internet

Overview

The Contractor will use a Contract monitoring software for the operation and management of the Contract. A

new suite of software modules, named the Whitespace Power Suite, will be used for the operation of the

Contract.

The Whitespace Power Suite system is a package of software that includes the Whitespace HUB, which is

the Gatehouse Validation and Reporting Software, and the Whitespace Power Modeller which is the

Payment Mechanism Modelling System. The Power Suite has been designed to offer the flexibility and

adaptability to be applied for use in PPP and PFI contracts.

Through its own or a stand alone website the Contractor will provide important information to the public

including Contract data, emissions monitoring data, news feeds and information from partner Sites such as

Oxfordshire CC and the Oxford Waste Partnership.

78

Page 79: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•f.:^ift Whitespace Power Suite

Power modeller

The Whitespace Power HUB captures tonnage and other Weighbridge and input data from the Contractor's

ISYS Gatehouse software, analyses and checks the data for inconsistencies and provides a suite of

management reports.

The Power Modeller is an extension to this system which takes the data from the HUB together with any

other inputs from third parties, the local authority, issues management systems etc and models the algebra

of the payment mechanism. This will replace the complex spreadsheet models currently used on other

contracts to calculate the monthly Contract payments.

The Power Modeller also has the advantage of a full audit trail on all calculations and input variables,

something that is extremely important in the early days of the Contract when some calculations have to be

made under certain assumptions.

Issues management system

Viridor have built upon the experience gained from developing Issue Management Systems in both West

Sussex and Greater Manchester. When an issue arises, the Contract administrator is contacted and asked

to input into the system. At first the issues categorised by type. Site, time and logged as a new issue. Viridor

management then contact Waste management services staff to agree the category and actions. Open

discussion between the Contract managers from both parties then attempts to agree on the action taken and

if possible the issue is signed off without having to generate a Performance Deduction. If the action taken by

the Contractor is not satisfactory the system automatically works out the value of the Performance

Deduction, and its contribution towards set warning or termination levels of Performance Deductions. WMS

and Viridor staff are able to view issues on-line and a report of all relevant issues can be generated in Excel

or XML format.

This system logs the issues as reported by the authority and tracks them through the various stages of

resolution, agreement and sign off, applying the appropriate penalty deductions and performance points

along the way. Automatic notification of issues via email and a comprehensive set of reports allow

outstanding issues to be efficiently managed.

The Internet

The Contractor will create an Internet relationship with the people of Oxfordshire; either through its existing

website or as a stand alone website. The Contractor has allocated a budget for both options and the final

choice of Internet relationship will be decided through meetings with the Authority.

Method Statement 4a Operational Interface

79

Page 80: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

li^Hl. Option one

An additional section to the Contractor's corporate website will be created specifically for contracts in

Oxfordshire. This will sit within the same design template as the current website and will include the

following:

• A designed banner (to appear along the top of the website);

• Well researched and edited copy for up to ten additional content pages;

• Uploaded content and images;

• Buying and redirecting a specific domain name for the compost section which can be used for

consultation purposes (e.g. viridor-oxfordshire.co.uk); and

• An online enquiry form that will be directed to an email address/es at Viridor.

The Viridor website is built on a user-friendly content management system (CMS) so regular updates to

pages such as information on emission monitoring can be completed as required.

Option two

This will be a full stand alone website specifically for contracts in Oxfordshire. This will be built on its own

CMS to allow regular updates to pages to be completed as required. The website will be completely

independent from the corporate website, which will allow more flexibility with design and the ability to add

analytics software to track all statistics to and through the website. This will also include

• Researched and edited copy for up to ten content pages;

• Uploaded content and images;

• A specific domain name for the compost section which can be used for consultation purposes (e.g.

viridor-oxfordshire.co.uk); and

• An online enquiry form directed to an email address(es) at Viridor Waste.

The following additional features and functionality will be added:

• A specific news section for the Contracts;

• Searchable FAQs database with the option to submit questions; and

• RSS feeds - to allow visitors to be informed when updates are made to the website.

Viridor Extranet

The Contractor has developed a sophisticated extranet service which enables access to all company

information. The extranet enables access to specific information depending on the nature of employee

80

Page 81: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r^riift ti,OXFORDSHIRE SCOUNTY COUNCIL

[ Yaur council tdx v/cfking fcr you

responsibilities, interests and ideas for business improvement. This is primarily for technical, environmental

and managerial information and can be made available to the Authority as a long term contract partner.

However, the design is flexible and could contain Contract documentation including the performance

management framework as part of a suite of electronic filing which could include Monthly Service Reports,

best value performance plans, Service Delivery Plans and detailed Waste data.

2.2. Plans

The Monthly Service Report will be submitted within ten Business Days after the Contract Month end, and

will include the minimum information requirements in accordance with Schedule 8 (Authority Requirements).

Within fifteen Business Days of the end of each Contract Year, an Annual Service Report will be submitted to

the Authority. The Annual Service Report will detail the performance and delivery of the Services for the

previous Contract Year.

Requests from the Authority regarding information relating to the Service will be addressed within five

Business Days of receipt.

2.2.1 Contingency plan updates

Hosted at Viridor's Aintree House data centre, the Viridor Portal is covered by the Viridor business continuity

and disaster recovery procedures. The principle risks for continuation of data transfer from the Information

system have been identified as power failure at the Site or disconnection from the company network limiting

transfer of data. The management information system can be set up to automatically back up data to shared

network drives that can be accessed from anywhere in the network. Data can be access and transferred to

the Authority even In the event of the Facility being shut off from communication systems. Recent experience

shows this system effectively minimises disruption to the Service. It is considered that the risk of power

failure interrupting data capture and transfer is negated at the Facility in question as the plant will be

designed to include a back-up generator.

2.2.2 Complaints

The Contractor's complaints procedure (Appendix MS4a-3a) provides a framework for all employees to

understand what actions they must take in response to a complaint of any kind. The range of Services

offered under this are not as public facing as those provided by the WCAs, nonetheless there is the potential

for Site activities to give rise to complain.

The complaints procedure applies to all complaints, feedback and requests made by third parties regarding

the Contractor's operational activities or environmental performance. The procedure also provides a system

to ensure records are kept and corrective and preventative actions are implemented for all justified

complaints, feedback and requests.

Method Statement 4a Operational Interface

81

Page 82: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r. 1. Also, a local procedure will be in place for receiving and initially recording complaints, feedback or requests.

All employees will be aware of this local procedure and is particularly relevant in the event that a member of

the public makes a complaint in person.

All complaints received from the third parties are recorded on an incident report. The complaints are passed

to a nominated responsible person i.e. someone who is able to implement corrective and preventative action.

Where a complaint or query is likely to involve a statutory authority, the emergency services, an insurance

company, or the media, the external affairs manager will be informed. All complaints will be investigated and

reported to regional managers and discussed at Site meetings.

The Contractor has an open door policy and the Site will be available for visits by local interested parties at

all times during the Site opening hours, and at other times by prior arrangement, subject to health and safety

and operational priorities.

The arrangements referred to above are the standard procedures applied by the Contractor. A complaints

Procedure specific to this contract will be developed in consultation with the Authority. The procedure shall

meet the overall needs of the Authority and the public within those areas.

In any event, the complaints procedure will be activated within four hours of a complaint being received by

the Contractor. A record will be maintained of all complaints, the response provided, the mitigating actions

taken, and any lessons learned. Such details will be reported back to the Authority within the Monthly

Service Report.

82

Page 83: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

iffJiOXFORDSHIRE tgtS'cOUNTY COUNCIL

;r coijnc il tLix v.'cridng for ycu

Parts. Visitor Centre

3.1. Operation of tlie centre

Opening hours

The Contractor will provide a Visitor Centre within the Facility. The Visitor Centre will be made available for a

minimum of five days a week to include Saturdays, Sundays and Bank Holidays, but excluding Christmas

Day, Boxing Day and New Year's Day. The Centre will be open from 10.00 am until 17.00 pm on all working

days.

Staffing

A full-time equivalent post of communications and education officer will be recruited to manage the centre,

develop resources, monitor their effectiveness, collate feedback and produce performance reports. The job

description and person specification will be developed and agreed with the Authority prior to recruitment.

Displays and exhibitions

The Visitor Centre will:

• Have one primary entranceway arranged such that visitors can be regulated and monitored, and access

controlled.

• Be accessible for all in accordance with the Disability Discrimination (Premises) Regulations 2006.

• Be suitable to accommodate groups (including seating) of up to 40 persons, including school children

and people with disabilities,

• Contain an appropriate number of toilet facilities and at least one toilet facility that is suitable for use by

a disabled person,

• Contain a safe and secure viewing gallery over an operational part of the Site, and safe visitor

pathways around the Site,

• Include two seminar rooms equipped with audio-visual aids

• Be supplied with the furniture and fittings as are necessary to provide the above functions.

The Visitor Centre will have a heating system that is capable of maintaining the seminar rooms at or above

the minimum heated temperatures of 18°C when visitors are present. Adequate ventilation will be provided

for the Visitor Centre.

All water supplies fed from storage tanks (not designed for potable water provision) will be clearly labelled as

not drinking water and will not be located in areas where unsupervised visitors have access.

Method Statement 4a Operational Interface

83

Page 84: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•P.^^t, The Facility together with the Visitor Centre is designed with provision for up to 52 car parking spaces within

its boundaries and up to ten per cent of the parking spaces will be reserved for disabled parking. Coach/mini

bus parking facilities will also be available.

The design of the Visitor Centre is shown below.

S«ixindFk)ar Plan

Giountl Fbof Ptian

\jiridor

ni i rd FkKjr pJan

First f^lajrPtaii

The Visitor Centre includes an education room to accommodate up to forty visitors and an exhibition area.

The exhibition area has been designed to provide a flexible space where the content and theme of the

materials and items on display can be changed to convey specific or seasonal messages to increase the

effectiveness of the education and awareness activities.

The centre will consist of current and comprehensive information displays on all aspects of the Waste

hierarchy - highlighting the role EfW plays in the recovery of energy in Oxfordshire.

Activities for children and young visitors will be developed to reflect their learning needs and linked to the

national curriculum. These may consist of interactive computer applications, activity sheets, etc.

84

Page 85: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r 9 k f ^ W ^OXFORDSHIRE

s^^VCOUNTY COUNCIL wwwaxfardshirepov.uk

[ YQUI" council tax ••voi'fejng for yuu

All educational resources will build upon current best practices that have demonstrated their value in

educating people. Where appropriate, national and regional campaigns and messages will be utilised to

maximise impact and campaign recognition.

Appropriate display equipment will be provided by the Contractor. This will include:

• A Smartboard;

• A projector and white screen;

• LCD screen(s) and DVD player; and

• Display boards.

3.2. Maintenance of the centre

The Contractor will ensure that the ceilings, walls, floors and windows of the Visitor Centre are kept

reasonably free of damage or deterioration (including grids and tiles where appropriate).

Testing of all electrical equipment will be carried out in accordance with statutory requirements.

The condition of all furniture and welfare facilities will be kept under review as part of the routine

maintenance checks carried out at the Facility.

Method Statement 4a Operational Interface

85

Page 86: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

p.:ii& Part 4. Waste transfer and haulage

4.1. Transfer and haulage

The following vehicle movements are expected during the operational phase of the Contract:

• WCA collection vehicles delivering Contract Waste to the Facility

• Bulk haulage vehicles delivering bulked Contract Waste from Waste transfer stations to the Facility;

• Transfer of metals recovered from bottom ash to off-Site metal re-processors;

• Transport of inert bottom ash from the Facility to the market which could be recycling or disposal

operations;

• Transport of hazardous APC residues from the Facility to the Grundon hazardous waste treatment and

disposal site in Bishops Cleeve, Cheltenham; and

• Deliveries of raw materials for use in the plant transports of products and rejected materials.

The process outputs that require further transport from the Facility are metals recovered from bottom ash,

remaining bottom ash and hazardous fly ash. All process outputs will be transported off Site in HGVs with an

average payload of 20 tonnes. For a five day per week transport arrangement, two, thirteen and three HGV

loads of recovered metals, bottom ash and fly ash, respectively will be transported daily to their proposed

destinations.

Bulk vehicles transporting process outputs will be loaded up evenly with the process outputs using a suitable

item of mobile plant (e.g. loading shovel). Once the vehicle is loaded. Waste will be secured and covered

prior to leaving Site. Any loose Waste at high level will be removed using a pole and hook. The vehicle driver

will be required to wear a safety harness if he/she needs to climb on top of the Waste container to free

trapped Waste. An annual 'season ticket' arrangement for Waste transfer notes will be made with the

receiving treatment and disposal facilities. Outgoing Waste loads will be weighed in at the receiving

disposal/treatment Facility and the weights booked into the computer system on return. Outgoing waste

loads will be weighed as they leave the Facility and again at any receiving facility thereafter if required.

In developing this transport plan, the Contractor has assumed the need for a further four vehicles on a daily

basis to cover for other process related delivery and transport.

Minimising impact on surrounding highways

Fully enclosed vehicles will be used for the transport of Waste and process outputs. All transfer vehicles will

be regularly serviced and maintained. The Contractor will seek to include fuel efficient, low emission vehicles

for the transport of Waste. Care will be taken to avoid peak hours where practically possible for Waste

transportation in order to minimise impact on the highways.

86

Page 87: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

f»-^ll^ All vehicles transporting Contract Waste and process residues will carry livery agreed with the Authority prior

to Contract commencement.

The Contractor will review any possibility of adopting a schedule of Contract Waste deliveries as this may

support any carbon management action plan to reduce carbon and thus the overall cost structure of the

project on an ongoing basis which will be a shared approach.

A detailed Transport and Traffic Management Plan for the Facility is provided in Appendix MS4a-2g.

4.2. Site signage and notices

Signage requirements for the Facility will be developed during the design and construction phase and will be

discussed and agreed with the Authority prior to Contract commencement.

The Contractor will review the use of small scale wind turbines and solar panels for any signage that requires

the use of electricity where it is practicable to generate the requirement at the local signage point of use.

4.2.1 Proposed Plant/Site(s) Entry Signs

Plant/Site entry signs:

• One or more signs indicating access and egress;

• Signage showing general layout of buildings/offices/Site (including Site Control Office) including:

• Welfare facilities;

• First aid point;

• Eye wash station;

• Fire exits;

• Location of fire extinguishers/blankets (including type i.e. foam, C02, powder);

• Fire assembly points;

• Location of emergency spill kits;

• Permit boundary;

• Site access routes for emergency services (marked clearly);

• Safe walking routes;

• Hard hat area;

• Hearing protection area;

• Information, traffic and warning signs;

Method Statement 4a Operational Interface

87

Page 88: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

K^^ • Car park;

• Weighbridge for incoming and outgoing vehicles;

• A sign board at the entrance displaying the following information as a minimum:

o Name and address of the Facility

o Environmental Permit number

o Nature of Waste management operations undertaken at the Site

o Opening hours

o Contact details for both the operator and the Environment Agency

o Emergency call out numbers

o Sign board at the Site entrance and car park requiring visitors to report to Site reception office

o Sign boards at the entrance and other relevant locations to inhibit unauthorised access to the

Site and facilities

o Sign board at the Site reception office displaying 'Site Reception' for easy identification by visitors

to the Site

• Site layout signage will be erected (as a minimum) at or near the following locations:

o Weighbridge

o Visitors car park

o Site reception office

o Waste acceptance / disposal locations

o Welfare facilities

• Warning signs for pedestrians at locations intended for vehicle manoeuvring and reversing

• Relevant health and safety warning signage near machinery and equipment (e.g. hot surfaces,

slippery surfaces; hazardous material storage areas; loud areas; hard hat areas etc).

4.2.2 Traffic Signs

Traffic signs necessary for ensuring safety of vehicles and pedestrians using the Sites will be erected and

maintained. Traffic signs installed at the Site will include the following where applicable:

• Signage showing access and egress

• Speed limit

88

Page 89: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r».i^» iOXFORDSHIRE ^ C O U N T Y COUNCIL

www Oxfordshire govuk

i' council tax v.'cr^jr^ Tci' yoi

• Give way

• One way (if applicable)

• Keep left etc.

4.2.3 Off-Site Signage

The Contractor will provide signage off-Site in consultation with the relevant bodies including the Authority

and Highways Agency. It will seek to provide signage indicating directions to the Waste Facility at the

following locations:

• Main road exits within five miles of the Site entrance

• Major roundabouts and junctions within five miles of the Site entrance

• Two hundred yards before reaching the Site entrance

• At the Site entrance.

Method Statement 4a Operational Interface

89

Page 90: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

p.^^ft Part 5. ivlanagement of products and residues from contract waste

5.1. Nature, classification and destination of residues and secondary products

The table below describes the principle residues and secondary products.

Source/

material

Bottom ash

Ferrous and

non ferrous

metals

Properties of Waste

Grate ash, grate riddlings.

This ash is relatively inert,

classified as non-

hazardous.

From bottom ash

Storage

location/

volume

stored

Bottom ash

storage

area.

Bottom ash

storage

area

Future

annual

quantity of

Waste

produced

(estimate)

75,000

tonnes

6,000 tonnes

Disposal route

and transport

method

A small fraction

(up to 15%) of

the bottom ash

will be

unsuitable for

processing and

will be

landfilled.

Transport

occurs by road

vehicles.

The metals are

separated from

the Waste and

recycled.

Transport

occurs by road

vehicles.

Frequency

Daily /

Weekly

Bi weekly /

Weekly

90

Page 91: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r] (^ ^ msmmm ^ ^ COUNTY COUNCIL

wwwoxfofdstiiregov.uk

[ Your couric 11 Idx vveriung for yo

Fly ash /

APCR

Bottom ash

leachate

Ash from dry flue gas

treatment, may contain

some unreacted lime

Water containing trace

contaminants from

bottom ash processing.

APCR silo.

Capacity of

203 m^

Leachate

lagoon

(800 m )

10,800

tonnes

2,000 tonnes

Recycled or

disposed of in a

licensed Site

for Hazardous

Waste.

Transport

occurs by road

vehicle.

Treated in

leachate

treatment plant.

Transport

occurs by road

vehicle.

Weekly

Weekly

Bottom ash

Bottom ash or IBA is an inert non hazardous by product suitable for processing into secondary aggregates

and is principally used as a road aggregate. The Contractor will establish a sub-contract with a specialist

reprocessor to deliver bottom ash recycling services.

Approximately 3,600 tonnes of boiler ash will be added to the bottom ash as part of the process and some of

this will form part of the production residues which will be unsuitable for sale as a consequence of their poor

quality. Approximately 10 per cent or 7,000 - 8,000 tonnes of IBA input will be inert Waste. This Waste will

be disposed of at Ardley landfill for as long as it is operational which could be to 2021. At the end of its

operational life this inert material will be disposed of via landfill.

Ferrous and non-ferrous metais

The Contractor expects that 4 per cent (6,000 tonnes) of the MSW Waste feedstock will be metal. This will

pass through the EfW Facility and will be a component part of the bottom ash. An overband magnet will

recover 2% of the metals on route to the bottom ash reception area leaving about 2 per cent embedded in

the ash which will either be incorporated into the secondary aggregate or where possible separated out and

recycled in the secondary metals market.

Metals recovered from the Facility will (subject to acceptance criteria) be processed through an off-site

facility such as EMR at Ridham in Kent. This outlet has the capacity to clean up the metals before sending

them to higher grade recovery/recycling facilities.

Method Statement 4a Operational Interface

91

Page 92: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

F.^1 Fly ash / APCR residues

Grundon Waste Management has developed a purpose built facility that treats ARC residue from a range of

incinerator plants. The Contractor will establish a Sub-Contractor agreements with Grundon Waste

Management for the treatment of approximately 10,800 tonnes of ARC residues (3.6 per cent of Waste

feedstock) and subsequent disposal to landfill.

5.2. Markets

Marketing plan

Introduction

The principle will be to maximise the recovery of recyclable materials from the Wastes handled under the

Contract with due regard to the potential for securing markets for those materials and the economic and

environmental costs of their recovery.

Where products are identified to be recovered from the Waste stream, due regard will be given to the quality

that can be achieved and the appropriate markets for these materials. Material quality will be a key factor in

determining the likely market for a material and where improvement in its quality will open up alternative and

more sustainable markets then the necessary process improvements will be evaluated to determine the

costs and practicality of doing so. The underlying principle will be for local markets to take precedence

subject to comparison of other factors including quality issues and economics.

Products

The following products and potential products will be produced the Facility:

• Ferrous and non-ferrous metals

• Bottom ash secondary aggregate

• Electricity

Markets

Ferrous and non-ferrous metals

The market for the metals recovered from the waste may be more restricted than for normal metals

recovered from a MRF for example. The nature of the source material and the ability to segregate will most

likely result in higher levels of contamination. This output would therefore require further processing and will

be sent to an external facility (such as EMR in Kent) with the capacity to clean up the metals before sending

them to higher grade recovery/recycling facilities.

92

Page 93: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

Bottom ash

The Facility has an incinerator bottom ash (IBA) reception storage and recycling facility designed to accept

the bottom ash output, which will be up to 75,000 tonnes each year. Depending upon the Waste composition

a proportion of bottom ash will be metals, perhaps as much as 4 per cent, which will be separated during ash

handling and stored separately prior to sale into the recovered metals market.

The adjacent landfill site (Ardley) will be used for the disposal of rejected bottom ash or bottom ash if outlets

for recycling them as secondary aggregates do not materialise. The landfill site is consented to accept inert

Waste such as bottom ash from incinerators subject to Waste acceptance criteria and standards stipulated in

the relevant consents.

The Contractor has entered into commercial negotiations with [Ballast Phoenix] for the provision of bottom

ash reprocessing services. The Contractor will supply bottom ash from the Facility to the ash storage area

where [Ballast Phoenix] will process the material and sell it as a road aggregate and for other

environmentally acceptable applications. The detailed Sub-Contractor Contract will be developed and agreed

after the Waste Contract has been signed. Approximately 10 per cent of bottom ash input becomes Waste

from the secondary aggregates process which equates to about 7 - 8,000 tonnes This material is inert and

suitable for landfill and will be landfilled at Ardley landfill Site. An alternative disposal site will be identified

prior to the closure of Ardley landfill.

A drat agreement has been received from Ballast Phoenix and is included in Appendix MS4a-5a. A guide to

the treatment process is also included in Appendix MS4a-5b.

Market risks

IBA

The Highways Agency, WRAP, the Quarry Products Association and a recently published Environment

Agency report all recognise processed IBA as a valuable resource. Work among stakeholders such as

WRAP, Defra, EA, the HA, and a number of other industry organisations is underway to develop a quality

protocol for the processing of IBA.

The Environmental Services Association's Ash Working Group, the BSI committee on aggregates from

secondary sources and the European Specification Group TC154-TG10, are working on the specifications

and use of IBA.

The Highways Agency's Specification for Highway Works is the most widely used infrastructure development

document of its kind in the UK. The ESA's Ash Working Group has been working closely with the Quarry

Products Association to negotiate IBA into a number of the Specification for Highway Works clauses. The

latest specification was published in November 2004 and provides for the use of IBA as a recognised

replacement for primary aggregate.

Method Statement 4a Operational Interface

93

Page 94: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump
Page 95: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

• r .^ ' i^ eiiOXFORDSHlRE g S COUNTY COUNCIL

[_YaL'i'council tdx v.'Gfi'jn^ fcryci

5.4. Disposal

Incinerator Bottom Ash (IBA)

Ardley landfill site would be used for the disposal of inert bottom ash reject which is estimated to be 15% of

bottom ash. Should outlets for recycling bottom ash as secondary aggregates not materialise then the landfill

will also be used. The landfill has void space in excess of 2.5 million m^ and planning permission to operate

until 2021 and is consented to accept inert waste such as bottom ash from incinerators subject to waste

acceptance criteria and standards stipulated in the relevant consents. A copy of the waste management

licence, WML BV7346IM and PPC permit for the Ardley landfill is attached (Appendix MS1-2I).

Prior to the closure of Ardley landfill the Contractor will make alternative arrangements to utilise one or more

of the disposal sites listed below.

Site

Ardley

Sutton

Courtenay

Dix Pit

Address Operator Environmental

Permit No.

Ardley Field Farm

Ardley

Oxfordshire

0X6 9PH

Viridor 86232

Appleford Sidings

Abington

Oxfordshire

0X14 4PW

OS reference

number SU 508 928

WRG 86157

Linch Hill

Stanton Harcourt

Oxfordshire

0X8 1BJ

OS reference

number SP 411 048

WRG 86399

Method Statement 4a Operational Interface

95

Page 96: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

r»::i^» Sands Farm Sand Pit Road

Calne

Wiltshire

SN11 8JQ

OS reference

number ST 998 711

Viridor 27308

Calvert Brackley Lane

Calvert Brickworks

Calvert

Buckinghamshire

MK18 2HF

OS reference

number SP 693 237

WRG 75026

The Contractor intends that IBA residues will be disposed of in Oxfordshire for the duration of the contract.

Air Pollution Control Residues (APCR)

The air pollution control (APC) residues from an EfW plant would be delivered to the Grundon's Wingmoor

Farm Waste Treatment Plant, with PPC permit number NP3831ST, in Bishop's Cleeve, from where the

treated residues would be delivered to the adjacent hazardous waste landfill site. This site operates under an

existing Planning Permission and waste permitting arrangements under WML BU36711Y and variations

GP3538MM and these are attached in Appendix MSI-2m. The site is operated by Grundon and The

Contractor has received consent to use the site for disposing APC residues from the Facility. Appendices

MS4a-5c and MS4a-5d include a Grundon letter of agreement and draft contract respectively. The address

of this facility is:

S Grundon (Waste) Limited

Wingmoor Landfill

Stoke Orchard Road

Bishops Cleeve

Cheltenham

GL52 4DG

96

Page 97: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

P w i l ^ l l jglaOXFORDSHlRE ma'cOUNTY COUNCIL

The Bishops Cleave landfill is consented to accept hazardous waste under Condition 2.1.2.1 (with the

exception of 16.91.09, 16.02.09, and 16.02.10). Incinerator Air Pollution Control residues (APCR), as in this

proposal, are accepted provided that material has a moisture content between 27% and 50% (Condition

2.1.2.3). Condition 2.1.5 also places a maximum annual waste input limit of 120ktpa. An agreement in

principle has been established to safeguard capacity for Viridor at this site for the APC residues arising from

the Facility.

The relevant consents for the Bishop's Cleeve landfill site is provided in Appendix MS1-2m.

In the event of a period of prolonged unavailability of the Grundon facility there are other facilities that are

licensed to accept APC residue although they are further away. At this stage it is not intended to enter into a

fixed agreement with an alternative disposal site as it should be possible to negotiate a disposal option as

and when required. There are two principle sites that would be considered. Details of the disposal sites for

APC residue are as follows:

Operator

Grundon Waste Management

Castle Environmental Ltd

Minosus Ltd

Address

Wingmoor Farm

Stoke Orchard Road

Bishops Cleeve

Gloucestershire

GL52 7DG

OS Reference

Number SO 931 279

Crompton Road

llkston

Derbyshire

DE7 4BG

OS Reference

Number SK 477 394

Jack Lane

Bostock

Environmental Permit No.

NP3831ST (Treatment plant)

BU3671IY/GP3538MM (Landfill site)

AP3337SJ

PP3535MG

Method Statement 4a Operational Interface

97

Page 98: Method Statement 4a; Operational Interface · PDF fileMethod Statement 4a; Operational Interface ... Waste transfer and haulage 86 ... Fuel oil storage & distnbution and fuel oil pump

•r;n\^ft Middlewich

Cheshire

CW10 9JQ

OS Reference

Number SJ 655 685

Ineos Chlor Randle Landfill

Astmoor

Runcorn

Cheshire

WA7 4QF

OS Grid Reference

SJ 53906 83358

BP3633LN