VGM MStmt Ver2012(Jan) Page 1 METHOD STATEMENT FOR ELMICH GREEN WALL VERTICAL GREENING MODULE (VGM) PREPARED BY ELMICH PTE LTD
Transcript
Page 1: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 1

METHOD STATEMENT

FOR

ELMICH GREEN WALL

VERTICAL GREENING MODULE (VGM)

PREPARED BY ELMICH PTE LTD

Page 2: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 2

METHOD STATEMENT

ELMICH GREEN WALL VERTICAL GREENING MODULE (VGM)

1. VGM

1.1 Assemble VGM modules leaving removable top open

1.2 Yellow triangle on front and back panels should be at the top

1.3 Insert custom-fit planting media bag into module

1.4 Fill media bag with planting medium flush with top of module

1.5 Fold mouth of media bag to prevent spillage of media and attach VGM cover

Media Bag Planting Medium VGM top open Assembled VGM

Page 3: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 3

2. Pre-plant VGMs in Nursery Environment

2.1 Make slits in media bag and insert selected green wall plants,1 plant per aperture

2.2 If side planting is required, cut and remove centre disk of side panel

Make slit in Media Bag to insert plant

Centre disk removed

Centre disk of side panel Planted side panel

Page 4: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 4

2.3 Allow at least 12 weeks for plants to firmly establish in nursery environment

2.4 Orientate plants to growth from a wall by progressively tilting VGM modules from horizontal to vertical over the 12 weeks

3. Prepare Wall for VGM Installation

3.1 Prime RC wall and/or construct framework (including waterproofing, painting, welding, etc) according to project requirements

RC Wall Staging Framework

VGMs tilted to orientate plants

Page 5: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 5

3.2 Vertical beams of framework MUST correspond precisely with

VGM width for pilaster installation 3.3 Erect staging for work on high wall 4. Install Pilasters

4.1 Take vertical and horizontal wall measurements to determine position of first pilaster (anchor rails) according to project requirements

4.2 Drill holes at all securing points to required depth using drill bit

diameter corresponding with anchor used. Blow out dust and fragments

Beam does not correspond with VGM width

Setting Tool

Threaded Wedge Anchor

Stainless Steel Bolt

Stainless Steel Washer

Beam does not correspond with VGM width

Wedge, Washer & Bolt

Page 6: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 6

4.3 Pilaster positions MUST register with width of VGM and all pilaster mounting slots align

4.3 Use assembled VGM modules to assist in accurate alignment of pilasters

4.5 Secure pilaster with stainless steel Stud or Wedge anchors tighten with torque wrench for RC wall or secure with stainless steel nuts and bolts for a constructed framework accordingly

Assembled VGM modules assist in alignment of pilasters

Pilasters

VGM

Pilaster

Stainless Steel Bolt & Washer Stainless Steel Bolt & Nut

RC Wall Framework

Page 7: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 7

5. Irrigation and Fertigator System

5.1 Secure irrigation tubing to pilasters at specifically spaced holes provided along length of pilasters with cable ties

5.2 Insert arrow drippers into separate points either at rear or rear and front of each VGM to evenly distribute water supply

Cable-tie

Hole for securing tubing

Cable-tie

Hole for securing tubing

Distribute drippers evenly

Dripper to bottom half of VGM

Dripper to top half of VGM

Yellow triangle at top of VGM

Page 8: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 8

5.3 Install irrigation system, including controller, solenoid valve,

pressure regulator, filters and valves linked to fertiliser supply, to project requirements or as advised, to deliver irrigation and fertiliser at programmable intervals for controlled durations

5.4 A rain sensor (optional) may be installed to override

programmed water release when the green wall receives sufficient water from rain

Solenoid Valve

Controller

Rain Sensor

Over-pressure valve

Page 9: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 9

6. Mounting

6.1 Attach stainless steel mounting brackets to the 4 corners of

each VGM and cover each with its plastic cover

6.2 Secure mounting bracket to VGM with self-tapping screw to prevent bracket dislodgement before mounting

6.3 Anchor VGM to the pilasters beginning from the bottom row

Anchor VGM to Pilaster

Attach Self-tapping Screw here

Attach Self-tapping Screw here

Page 10: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 10

6.4 Insert anti-lift arm between tops of mounted VGMs and push, from front to back, until arm clasp locks into pilaster slots

6.5 Plug connectors of manifold/s into corresponding emitters along horizontal irrigation tubing as each VGM row is installed

6.6 Install subsequent rows until all VGM rows are installed

Emitters along tubing

Emitters along tubing

Arm clasp locked into pilaster slots

Insert Anti-lift Arm

Plug connectors into emitters

Plug connectors into emitters

Page 11: METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE (VGM) 1. VGM . 1.1 Assemble VGM modules leaving removable top open . 1.2 Yellow

VGM MStmt Ver2012(Jan) Page 11

7. Inspection & Maintenance 7.1 Follow a routine inspection and maintenance regime 7.2 Ensure smooth running of irrigation system

7.3 Weed away invasive unwanted growth

7.4 Prune as necessary

Install bottom row followed by subsequent rows above

Plug in connectors to emitters as each VGM row is installed