+ All Categories
Home > Documents > Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro –...

Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro –...

Date post: 24-Sep-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
11
BC Hydro – Metro North Transmission Study – Anmore Community Information Open House Welcome Metro North Transmission Study – Anmore Community Information Open House – June 23, 2016 Thank you for attending this Community Information Open House about the Metro North Transmission Study. We’re here to provide you with updated information on a conceptual design of the power line upgrade along the existing right-of-way in Anmore, and other considerations as we do further study and technical work on this alternative. About the Metro North Transmission Study We need an additional transmission line between Coquitlam and Vancouver to address the growing demand for electricity resulting from the region’s increasing population. We’re working to ensure the line is in place as early as 2020¹ to improve the region’s transmission network by increasing electrical transmission capacity and strengthening reliability. Our current transmission system is approaching its limit and without these improvements the network faces reduced service reliability. Under certain conditions, this could mean outages for the equivalent of about 30,000 homes and businesses, and service interruption for the equivalent of about 90,000 homes and businesses. Engaging with communities Since July 2013, we’ve had more than 60 meetings with local and regional governments, transportation authorities, community groups, property owners, and others to discuss the need for transmission improvements and the alternatives being studied. At the same time, engagement has also been ongoing with First Nations. Information about previous engagement can be found at bchydro.com/mnt . 1 Required in service date is influenced by load forecast, which is monitored annually.
Transcript
Page 1: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

WelcomeMetro North Transmission Study – Anmore Community Information Open House – June 23, 2016Thank you for attending this Community

Information Open House about the Metro North

Transmission Study.

We’re here to provide you with updated

information on a conceptual design of the power

line upgrade along the existing right-of-way in

Anmore, and other considerations as we do further

study and technical work on this alternative.

About the Metro North Transmission Study

We need an additional transmission line between

Coquitlam and Vancouver to address the growing

demand for electricity resulting from the region’s

increasing population.

We’re working to ensure the line is in place as early

as 2020¹ to improve the region’s transmission

network by increasing electrical transmission

capacity and strengthening reliability.

Our current transmission system is approaching

its limit and without these improvements the

network faces reduced service reliability. Under

certain conditions, this could mean outages

for the equivalent of about 30,000 homes

and businesses, and service interruption for

the equivalent of about 90,000 homes and

businesses.

Engaging with communitiesSince July 2013, we’ve had more than 60

meetings with local and regional governments,

transportation authorities, community groups,

property owners, and others to discuss the

need for transmission improvements and the

alternatives being studied. At the same time,

engagement has also been ongoing with

First Nations. Information about previous

engagement can be found at

bchydro.com/mnt.

1 Required in service date is influenced by load forecast, which is monitored annually.

Page 2: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

Further study and technical work underway We’ve been studying three alternatives as part of the Metro

North Transmission Study and have identified Alternative 2

(see map) for further study, technical work and consultation.

Alternative 2 affects fewer residents and property owners,

has lower seismic and construction risks, and offers the best

value in terms of capacity for investment, compared to the

other alternatives studied.

The transmission improvement will consist of a combination

of overhead transmission lines and underground

transmission cables, running from the Meridian Substation

in Coquitlam to the Mount Pleasant Substation in Vancouver.

Generally, we’ll be able to use our existing rights-of-way.

While further technical work and study is needed, the

improvement could include:

0 Replacement of existing overhead lines in Anmore and

Port Moody, resulting in fewer, taller poles than currently

exist in these areas.

0 An overhead crossing of Burrard Inlet, within the current

right-of-way.

0 A new underground route through Burnaby and

Vancouver.

Page 3: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

Further study and technical work underway We are exploring options for:Positioning the line as it leaves the Meridian Substation

0 Technical challenge: Crossing an existing 500

kilovolt (kV) power line given the constraints of

the existing right-of-way.

Positioning the line south of Sasamat Lake

0 Technical challenge: Routing the line through an

area that includes a FortisBC gas pipeline, seven

existing transmission lines of varying voltages

and structure types, and a regional park, given

the constraints of the existing rights-of-way.

Crossing Burrard Inlet

0 Technical challenge: Consolidating the additional

line with existing infrastructure that currently

crosses Burrard Inlet.

Positioning the cable around Burnaby Mountain

0 Technical challenge: Routing the underground

cable around the north side of Burnaby

Mountain so that it is seismically secure. Along

Barnet Highway, placing the cable in the

roadway reduces the seismic risk.

South of Sasamat Lake

Existing Burrard Inlet crossing,

looking south

An area of slope instability along Barnet Highway,

west of the velodrome

We’ll also work with local governments to

determine the routing of the underground cable

through Burnaby to the Horne Payne Substation,

and from there through Vancouver to the Mount

Pleasant Substation.

Page 4: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

Anmore In developing the design of the overhead

portion of the line for Alternative 2, we have

been mindful of these guiding principles:

0 Stay within the existing right-of-way

0 Minimize the number of poles

0 Use existing monopoles as the basis for

design

0 Preserve and/or enhance existing vegetation

where possible to screen views of towers

and disturbed areas

0 Minimize access roads and laydown areas

0 Re-vegetate affected areas

Alternative 2 would involve adding an additional

230 kV transmission line originating at the

Meridian Substation in Coquitlam and extending

through Anmore, using our right-of-way that

has been in place since the 1960s.

Although additional technical work is required,

the current preliminary design in the residential

area of Anmore includes:

0 Consolidating the proposed additional line

with an existing line by replacing six wooden

H-frame structures totaling 13 poles, with

three taller steel monopoles, resulting in a

reduction of 10 poles.

0 Three existing monopoles, supporting two

230 kV lines, would remain in place with an

added grounding wire.

We would also do a landscape and visual

impact assessment, and work with landowners

to discuss options to reduce impacts.

Existing structures (monopole and wooden H-frame) in Anmore

Preliminary rendering showing a new steel monopole replacing a

wooden H-frame in Anmore (tower design and placement subject

to change). With Alternative 2, there would be 17 fewer poles than

existing in the Anmore area.

Alternative 2 overview

Page 5: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

Port Moody/Burrard Inlet Crossing Through Port Moody, the alignment would generally be within our existing

right-of-way in and adjacent to Belcarra Regional Park and Admiralty Point.

Within the existing right-of-way, we are looking to consolidate existing lines

onto fewer, taller poles. The location of these poles will be the subject of

further study.

Three options were looked at for crossing Burrard Inlet. The option identified

for further study:

0 Uses our existing right-of-way, eliminating the need for a third

transmission line crossing of the inlet.

0 Uses our existing property on the south side of Burrard Inlet to transition

the line from overhead transmission line to an underground transmission

cable.

0 Considers input from First Nations, Burnaby, Port Moody, Metro

Vancouver, and the Federal government.

Burnaby/Vancouver (Mount Pleasant Substation)Alternative 2 would require an additional transmission cable to run underground in Burnaby and Vancouver to the Mount

Pleasant Substation in Vancouver. The exact alignment would be determined through technical work and discussions

with stakeholders, including the City of Burnaby and the City of Vancouver.

The additional transmission line will be built underground in Burnaby and Vancouver because we don’t have an overhead

right-of-way. Along Barnet Highway, placing the cable in the roadway reduces the seismic risk.

Alternative 2 overview

Existing Burrard Inlet crossing,

looking north

Existing Burrard Inlet crossing,

looking south

Page 6: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

Underground cable versus overhead line Some of you have asked “Why can’t you build the transmission line underground in Anmore”?

Our right-of-way doesn’t include the rights to place the lines underground; however, we did take a look and here’s what we learned:

0 It is difficult to excavate a trench in uneven,

rocky terrain along the entire existing right-

of-way, especially at the west end where the

topography is very steep. Extensive blasting

would be required for new cable and casing.

0 The crossing of the creek at the west end of the

right-of-way (west of Fern Drive) would require

horizontal directional drilling.

0 The cable would require terminal stations and

manholes (12 metres long x 3 metres wide

x 3 metres deep) within the right-of-way,

potentially on private land.

For these reasons, it’s technically challenging to build an underground cable within the existing right-of-way, so we looked at what is involved with building it underground in local streets, and here’s what we learned:

0 The cable length would be about 4 kilometres

to replace 3 kilometres of overhead line.

0 We would need to build a large termination

station just east of Legget Drive to transition

from an overhead line to an underground cable.

0 We would also have to build a second large

termination station so the cable can transition

to an overhead line and travel along this

right-of-way to cross Burrard Inlet.

0 Three existing lines would remain in the

right-of-way.

The difference in cost*? 0 Overhead (3 kilometres):

Approximately $9 million*

0 Underground (4 kilometres): Approximately $35 million*

It would cost approximately 3.5 to 4 times

more to build an underground cable. It would

be difficult for us to justify the significant cost

increase to underground the line when there

is sufficient space in an existing-right-of-way

for an overhead line.

* Given the early stage of this study, costing is based on a conceptual level estimate only (+100/-35%).

-40 0

40

80

12

0

16

0

20

0

24

0

28

0

32

0

36

0

40

0

44

0

48

0

52

0

56

0

60

0

64

0

68

0

72

0

76

0

80

0

84

0

88

0

92

0

96

0

10

00

10

40

10

80

11

20

11

60

12

00

12

40

12

80

13

20

13

60

14

00

14

40

14

80

15

20

15

60

16

00

16

40

16

80

17

20

17

60

18

00

18

40

18

80

19

20

19

60

20

00

20

40

20

80

21

20

21

60

22

00

22

40

22

80

23

20

23

60

24

00

24

40

24

80

150

160

170

180

190

200

210

220

230

240

250

260

270

280

290

300

310

320

330

340

350

360

370

380

390

400

410

420

430

440

450

460

470

480

490

500

510

150

160

170

180

190

200

210

220

230

240

250

260

270

280

290

300

310

320

330

340

350

360

370

380

390

400

410

420

430

440

450

460

470

480

490

500

510

PI

-55

.19

°

PI

0.1

PI

-0.4

PI

0.5

PI

-0.1

PI

-0.0

PI

-0.9

PI

7.9

PI

-0.2

PI

-0.0

PI

-0.4

PI

-7.7

02

-06

02

-06

03

-01

03

-01

02

-07

02

-07

03

-03

03

-03

03

-02

03

-02

02

-01

02

-01

02

-03

02

-03

02

-02

02

-02

02

-04

02

-04

02

-05

02

-05

01

-07

01

-07

01

-08

01

-08

303

121

218

145

380

456

204

170

120

278

81

2L49MDN CIRCUIT

260

260

260

26

0

220

22

0

260

26

0

280

280

320

32

0 320

34

0

340 320

380

30

0

280

220

420

180

180

22

0

200

18

0

180

200

240

24

0

220

180 180

180 200

20

0

180 180

18

0 1

80

20

0

200

200

240

240

220 220

180 220

02-0603-01 02-0703-03 03-02

02-01

02-03

02-02

02-0402-05

01-0701-08

2L49MDN CIRCUIT

2L54||2L61 CIRCUITS

REV

DATE

ACPT

DSGN

RDWG NO

CHK

DFTG

CHK

DFTG

INDEP

INSP

DISTR

NO

T T

O B

E R

EP

RO

DU

CE

D W

ITH

OU

T P

ER

MIS

SIO

N

NOT TO BE REPRODUCED WITHOUT PERMISSION

SIZE

REVISIONS

REMARKS DATE REV ACPTNOREF# TITLE REF# TITLEDRAWING NUMBER DRAWING NUMBER

REFERENCE DRAWINGS REFERENCE DRAWINGS

DESIGNED DFTGCHK

DFTG

CHK

INDEPINSP

FORILLUSTRATION

ONLY

CONTOUR LINES SHOWN AT 10 m INTERVALS

EXISTING CONDUCTORS

EXISTING STRUCTURE (BROWN FOR 2L49MDN)

RIGHT-OF-WAY BOUNDARY (+/-1.0m ACCURACY)

PROPERTY LINE (+/-1.0m ACCURACY)

CLEARANCE LINES SHOWN AT 8.1 m ABOVE GROUND

FIL

E M

ET

RO

_N

OR

TH

_R

B_

2L

49

MD

N.x

yz

LIN

E "

Ex

isti

ng

2L

04

9M

DN

" P

LO

TT

ED

20

16

-06

-16

NOTES:

1) ALL DIMENSIONS ARE IN METRES UNLESS OTHERWISE NOTED.

2) TERRAIN DATA BASED ON LIDAR DATA CAPTURED ON NOV 2, 2011 (L_00202)

MERIDIAN - HORNE PAYNE 230 kV T/L

METRO NORTH PROJECT (MNT)

EXISTING 2L49MDN CIRCUIT

PLAN AND PROFILE

SHEET 1 OF 1

2016 JUN AD

A ISSUED FOR ILLUSTRATION ONLY 2016-JUN JZ

J. ZABALA

MNT-OH-SK-00009

Vert. Scale

Horiz. Scale

10.0 m

40.0 m

N

Profile of the right-of-way through Anmore

Page 7: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

Health and safety We are committed to ensuring the safety of our communities and our workers.

Safety considerationsAs with the existing transmission lines and poles in the

right-of-way, our infrastructure is designed to withstand large

seismic and weather events, as per industry standards. Our

wires and poles are inspected yearly to ensure that they

remain safe.

The line would be designed to withstand a large seismic event,

and weather events including:

0 155 km/h winds

0 25 mm of ice accumulation around each wire

What are the EMF guidelines?

The World Health Organization endorses the guideline established by The

International Committee on Non-Ionizing Radiation Protection (ICNIRP). In its

guideline update in 2010, ICNIRP recommends a residential magnetic field

exposure limit of 2,000 milligauss (mG) and an electric field exposure limit of

5 kilovolts per meter (kV/m).

We follow the ICNIRP guidelines when we build our infrastructure.

The relationship between EMF and health remains a subject of ongoing

research. We will continue to monitor scientific research, as well as policy and

regulatory developments.

Distance (metres)

0

500

1000

1500

2000

2500

40 4030 3020 10 0 10 20

Proposed

MF

mea

sure

men

t in

mill

igau

ss (m

G)

Existing

Residential magnetic field exposure limit

Page 8: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

Electric and magnetic fields Magnetic field levels The proposed work will replace the wooden H-frames with fewer, but

taller, steel monopoles that will support two 230 kilovolt lines, instead of

one, and a grounding wire. The existing monopoles that support two 230

kilovolt lines will remain in place with an added grounding wire.

For the new monopoles, we are arranging the order of the lines to

minimize magnetic field levels resulting in lower magnetic field levels at the

northern right-of-way edge.

These estimates are based on an estimated average electricity load

when the line reaches its maximum rating (or the maximum amount of

current the line is designed to carry) in about 30 years. The World Health

Organization endorses a residential magnetic field exposure limit of 2000

milligauss (mG).

Electric field levelsOn the northern right-of-way edge, the electric field level would decrease

by 25% to less than 0.5 kV/m.

On the southern right-of-way edge, the electric field level does not change

and remains less than 0.3 kV/m.

If you would like to learn more about electric and magnetic fields, please

review the resources listed on our EMF profile, or visit our website at

bchydro.com/emf.

Source: EMF in your Environment, U.S. Protection Agency, 1992.All measurements were taken 6 inches from the sources.

T YPICAL MAGNETIC F IELD LEVELS IN THE HOME

Hairdryer: 300 mG

Vacuum: 300 mG

Washing Machine: 20 mG

Dishwasher: 20 mG

Power Saw:200 mG

Portable Heater: 100 mG

Page 9: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

Environment and archaeology processFor a project of this size, BC Hydro will conduct a number of environmental and archaeological studies.

Environmental and archaeological overview assessmentsIdentification: 2013 – 2016

Environmental and

Archaeological Overview

Assessments are conducted to

help inform the selection of a

leading alternative for further

study.

Environmental and archaeological assessments Definition: 2016 – 2017

Once a leading alternative is

confirmed, Environmental and

Archaeological Assessments are

conducted. These studies include

fieldwork and help inform the

design of the transmission line

and appropriate mitigation.

Construction environmental management Implementation: 2018 (earliest)

Environmental mitigation and

best management practices

are included in a Construction

Environmental Management

Plan (CEMP). The contractors

working on the project will have

to comply with the requirements

of the CEMP by producing

and implementing their own

Environmental Protection Plans

(EPPs).

Environmental protection plans

Operation: 2020 (earliest) BC Hydro will audit the

contractors work to ensure that

work is conducted in accordance

with the requirements of the

CEMP and EPPs.

Page 10: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

The Anmore environmentWe’re committed to planning new infrastructure in an environmentally responsible manner. Studies are underway to determine how best to avoid or mitigate environmental and archeological effects.

Wildlife 0 The proposed additional line would pass over

top of residential backyards. Vegetation is

mainly limited to planted trees, gardens, and

manicured lawns. Wildlife habitat suitability is

limited to species that can co-exist in suburban

areas, including birds, small mammals, and

some large mammals tolerant of human

interactions, such as coyote, deer, and black

bear.

0 Forested areas are located to the west of the

community associated with Belcarra Regional

Park and Port Moody, and to the east associated

with Crown land within Anmore. These forested

areas provide increased wildlife suitability for a

variety of species.

Fish habitat 0 The proposed additional line would cross

suspected fish-bearing Schoolhouse Creek, just

west of Fern Drive, and fish-bearing Mossom

Creek to the east of Leggett Drive. Mossom

Creek is known to support Chinook salmon,

Chum salmon, Coho salmon, Pink salmon, and

Cutthroat trout. A small tributary of Anmore

Creek runs to the east of Sunnyside Road.

Vegetation 0 Metro Vancouver Sensitive Ecosystem Inventory

(SEI) Young Forest polygons are located in Port

Moody and Anmore, including one polygon east

of Mossom Creek identified as mature forest.

0 There have been several invasive species

identified in Anmore and within 100 metres

of the right-of-way, including Scotch Broom,

Himalayan Blackberry, Japanese Knotweed, and

Orange Hawkweed.

Archaeology 0 The existing right-of-way through the Anmore

area has been assessed as an area of low

archaeological potential. Further archaeological

assessment would be conducted if necessary.

Pho

to b

y: S

ean

Wes

ton

Pho

to b

y: S

ean

Wes

ton

Pho

to b

y: S

ean

Wes

ton

Page 11: Metro North About the Metro North Transmission Study ... Hydro story boards.pdf · BC Hydro – Metro North Transmission Study – Anmore Community Information Open House . Anmore

BC Hydro – Metro North Transmission Study – Anmore Community Information Open House

Next steps We’ll continue discussions with First Nations, local and regional governments, stakeholders, and property owners throughout the summer. We anticipate arriving at a decision this fall regarding a preferred alternative.

Ultimately, this transmission upgrade will require a

Certificate of Public Convenience and Necessity (CPCN)

from the BC Utilities Commission (more information

can be found at bcuc.com). Subject to receiving that

certificate, we anticipate construction could start as

early as 2018 and be complete as early as 2020² to

meet growing demand for electricity and avoid impacts

to reliability.

More information will be available at

bchydro.com/mnt and we encourage you to email us

at [email protected] to provide

your feedback or to sign-up for updates.

2 Required in service date is influenced by load forecast, which is monitored annually.

Identification: 2013 – 2016

0 Initial studies

0 Additional studies

0 Confirm preferred alternative

Definition: 2016 – 2017

0 Preliminary design

0 BC Utilities Commission

review process initiated

Implementation: 2018 (earliest)

0 Final design

0 Procurement

0 Construction

0 Commissioning

Operation: 2020 (earliest)


Recommended