Rev Prepared Sign Off Checked Sign Off Approved Sign Off Date of Issue Comments 1 F. Johnson I. Sargent E. Rollings 19/02/2015 2 F. Johnson I. Sargent E. Rollings 01/04/2015 Consultation response. Minor spelling and grammar changes. Removal of consultation table. Construction Method Statement: HDD Marine Works Page 1 of 26 MEY-1A-40-HSE-001-D- ConstructionMethodStatementHDD MeyGen Tidal Energy Project Phase 1 Construction Method Statement: HDD Marine Works This document contains proprietary information belonging to MeyGen Ltd. and/or affiliated companies and shall be used only for the purpose for which it was supplied. It shall not be copied, reproduced, disclosed or otherwise used, nor shall such information be furnished in whole or in part to third parties, except in accordance with the terms of any agreement under which it was supplied or with the prior consent of MeyGen Ltd. and shall be returned upon request. Project Title/ Location MeyGen Tidal Energy Project, Phase 1a. Inner Sound. Date: 01/04/2015
Transcript
Page 1: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Rev Prepared Sign Off Checked Sign Off Approved Sign Off Date of Issue Comments

1 F. Johnson

I. Sargent

E. Rollings

19/02/2015

2 F. Johnson

I. Sargent

E. Rollings

01/04/2015 Consultation response. Minor spelling and grammar changes. Removal of consultation table.

 

Construction Method Statement: HDD Marine Works Page 1 of 26

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

MeyGen Tidal Energy Project Phase 1

Construction Method Statement:

HDD Marine Works

This document contains proprietary information belonging to MeyGen Ltd. and/or affiliated companies and shall be used only for the purpose for which it was supplied. It shall not be copied, reproduced, disclosed or otherwise used, nor shall such information be furnished in whole or in part to third parties, except in accordance with the terms of any agreement under which it was supplied or with the prior consent of MeyGen Ltd. and shall be returned upon request.

Project Title/ Location MeyGen Tidal Energy Project, Phase 1a. Inner Sound.

Date: 01/04/2015

Page 2: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 2 of 26

 

Table of Contents

Executive Summary ................................................................................................................ 3

1 Introduction .................................................................................................................. 4

2 Scope of Construction method statement ................................................................... 5

3 Communication, Roles and Responsibilities ............................................................... 6

3.1 Responsibilities and Ownership ....................................................................................... 6

3.2 Organisation Chart and Reporting ................................................................................... 6

3.3 MeyGen - Ecological Clerk of Works ............................................................................... 8

3.4 Principal Contractor – James Fisher Marine Services ..................................................... 8

3.5 Contractors .................................................................................................................... 10

3.6 Communication .............................................................................................................. 11

3.7 Reporting ....................................................................................................................... 12

3.8 Training .......................................................................................................................... 13

4 Programme ................................................................................................................ 14

5 Construction Methods and Procedures ..................................................................... 15

5.1 HDD Works .................................................................................................................... 15

5.2 HDD Marine Works ........................................................................................................ 16

5.3 Environmental Mitigation ................................................................................................ 19

6 Emergency Preparedness and Response ................................................................. 22

7 Licences and Legal Requirements ............................................................................ 23

8 Linkages with Other Strategies and SHE Management Systems ............................. 23

9 CMS Review and Consultation .................................................................................. 23

10 List of Abbreviations .................................................................................................. 25

 

 

 

Page 3: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 3 of 26

 

EXECUTIVE SUMMARY

This Construction Method Statement (CMS) has been prepared by MeyGen Ltd. to set out the proposed method for discharging the Condition 9 of the Section 36 Consent for the Development.

The document details the construction methods proposed for the Development, how construction related mitigation detailed in the Environmental Management Plan is to be delivered, the construction procedures and good working practices for installing the Development, how this document integrates with the wider environmental management of the Development, and how communication will be maintained between the Principal Contractor and MeyGen Ltd. on this Development.

The CMS presented within this document is to satisfy Condition 9 and enable construction of the Development to progress, subject to the CMS being implemented.

The CMS will be submitted to the licensing authority and consulted on by SNH, SEPA, MCA, the Planning Authority, NLB, and any such other advisors as may be required at the discretion of the Scottish Ministers, and will be used, where appropriate, to inform the discharge of other Conditions within the Section 36 Consent which refer to it.

THIS DOCUMENT ONLY CONSIDERS HDD MARINE WORKS. FURTHER CONSTRUCTION WORKS WILL BE DOCUMENTED IN SEPARATE CMS SUBMITTED FOR CONSULTATION AND APPROVAL PRIOR TO THAT PHASE COMMENCING.

 

Page 4: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 4 of 26

 

1 INTRODUCTION

The MeyGen Tidal Energy Project Phase 1 (“the Development”) received consent under Section 36 of the Electricity Act 1989 from the Scottish Ministers on 9th October 2013 (“the S.36 Consent”). This Construction Method Statement (CMS) is prepared to enable Condition 9 of the S.36 Consent (“the Condition”) to be discharged. Condition 9 states:

The Company must, prior to the Commencement of the Development, submit to the Scottish Ministers a Construction Method Statement (“CMS”), in writing, endorsed by the Ecological Clerk of Works, as referred to in Condition 10 of this consent, to the Scottish Ministers for their approval, following consultation with SNH, the Scottish Environment Protection Agency, the Maritime and Coastguard Agency, the Planning Authority, Northern Lighthouse Board, and any such other advisors as may be required at the discretion of the Scottish Ministers. Unless otherwise agreed in writing by the Scottish Ministers, construction of the Development must proceed in accordance with the approved CMS. The CMS must include, but is not limited to, the following information: a) Commencement dates; b) Working methods including the scope, frequency and hours of operations; c) Duration and Phasing Information of key elements of construction, for

example– turbine structures, foundations, turbine locations, inter-array cabling and land fall cabling;

d) Details of the location of the turbines, grid export cable(s), method of installation (including techniques and equipment) and depth of cable laying and cable landing sites;

e) Details of mitigation measures to prevent adverse impacts to species and habitats during construction;

f) Details of how all contractors and sub-contractors will be made aware of environmental sensitivities, what requirements they are expected to adhere to and how chains of command will work;

g) Confirmation of reporting mechanisms used to provide Scottish Ministers and relevant consultees with regular updates on construction activity, including any environmental issues encountered and how these have been addressed;

h) Vessel specification, routing, including location of vessel ports; and i) Pollution prevention measures including contingency plans.

The CMS must, so far as is reasonably practicable, be consistent with the Environmental Management Plan, the Project Environmental Monitoring Programme, the Vessel Management Plan and the Navigational Safety Plan.

Reason: To ensure the appropriate construction management of the Development, taking into account mitigation measures to protect the environment and other users of the marine area.

This document sets out the proposed CMS that MeyGen Ltd, intends to undertake, to allow the Condition to be discharged.

Page 5: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 5 of 26

 

2 SCOPE OF CONSTRUCTION METHOD STATEMENT

Phase 1a of the Development is a 6MW, 4 tidal turbines initial phase to be installed and operatives under the restriction placed on the Development by Condition 2 of the S.36 Consent.

This document is the CMS for the marine works associated with the Horizontal Directional Drilling (HDD) Works for Phase 1a only (“HDD Marine Works”).

Given the Phase 1a programme for construction works associated with Phase 1a it has been agreed with the licensing authority that the CMS and other related consent documents for the installation of the Phase 1a infrastructure (4 x Tidal Turbine Generators (TTG), 4 x Gravity-base Turbine Support Structures (TSS) and Turbine Subsea Cables (TSC) can be submitted at a later date “the Construction Works”. MeyGen Ltd. will produce and update relevant documents for these construction works; these will be submitted and get approval prior to commencement of these works.

The CMS forms part of a suite of documents related to the consent conditions that MeyGen Ltd. seek to discharge:

Environmental Management Plan (EMP) (S.36 Consent, Condition 11) including Marine Pollution Contingency Plan (Marine Licence, Condition 3.2.13), Reporting Protocol for the Discovery of Marine Archaeology (S.36 Consent, Condition 16);

Vessel Management Plan (VMP) (S.36 Consent, Condition 14); and

Navigation Safety Plan (NSP) (S.36 Consent, Condition 17).

The CMS is in accordance with the construction methods assessed in the Environmental Statement (ES) and Supplementary Environmental Information Statement (SEIS) and includes details of how the construction related mitigation steps documented in the EMP are to be delivered. The EMP commits MeyGen Ltd. to safeguarding the environment through the identification, avoidance and mitigation of the potential negative environmental impacts associated with the development, construction and operation of the tidal array. The CMP will be an integral element of the EMP.

The CMS contains the following sections:

Roles and Responsibilities;

Programme;

Construction Methods and Procedures (including mitigation);

Emergency Preparedness and Response;

Licences and Legal Requirements;

Linkages with Other Conditions;

Linkages with Other Strategies and SHE Management Systems;

Page 6: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 6 of 26

 

CMS Review and Consultation; and

Technical Appendices Containing Detailed Construction Methodologies.

3 COMMUNICATION, ROLES AND RESPONSIBILITIES

This section details the project team roles, responsibilities and lines of communication during the construction and operation of the Development.

3.1 Responsibilities and Ownership

The Principal Contractor (PC) will have the ultimate responsibility for ensuring the implementation of the CMS.

The Ecological Clerk of Works (ECoW) will provide quality assurance and approval of any version of the CMS.

Any updates to the CMS by the PC will require the ECoW to check compliance with current legislation, consent conditions and related documents. Updated CMS will then be submitted to Scottish Ministers for approval.

3.2 Organisation Chart and Reporting

The organisational chart for the HDD Marine Works is below in . This includes how communication as part of the CMS will be conducted in normal working procedures and in the case of emergencies.

The organisation chart presents the key interfaces, lines of communication and responsibilities with regards to the flow of requirements and provision of mitigating actions across the HDD Marine Works.

Details are provided in the Table 1 below for contacts relevant to the delivery of this plan. These details may change and the CMS will be updated when necessary.

Name Role Organisation Telephone Mobile

Ian Sargent Project Manager

James Fisher Marine Services

01565 658812 +447584 293680

Stan Groundwater

Marine Coordinator

James Fisher Marine Services

01565658824 +44 7747 843712

Tony Blackshaw HSE Advisor James Fisher Marine Services

01565 658817 +447824 150124

Ed Rollings ECoW MeyGen Ltd +441316599662 +447825 414402

Fraser Johnson Marine Package Manager

MeyGen Ltd +441316599672 +447787 518373

Table 1 Contact Details

Page 7: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 7 of 26

 

 

Figure 1 Project Organogram

Page 8: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Constru

3.3 M

3.4 P

3.4.1

uction Metho

MeyGen - E

Review and

Review / co

Review / c

where nece

Inspect th

implementa

Audit PC p

Ensure co

legislation

10).

Review env

Report com

regulatory a

Notify the li

Notify the li

Provide Tra

3.2.2.1)

Notify the li

Ensuring a

Condition 1

Principal Co

Project Ma

Facilitate d

Oversee th

project.

Review and

VMP and N

Monitor th

overview of

Ensure tha

Implementa

project mee

Review an

where nece

Ensure tha

od Stateme

cological C

d approve a

omment on

comment on

essary with

he site

ation/operat

rocedures,

ompliance

and require

vironmental

mpliance a

authorities.

icensing au

icensing au

ansport Au

icensing au

any protecte

10)

ontractor –

nager

isseminatio

he implemen

d approve a

NSP.

e environm

f incidents,

at environm

ation of the

etings.

d approve

essary with

at all enviro

ent: HDD Ma

Clerk of Wo

all consent r

content of S

n Risk Asse

respect to e

/ vessel

tion of all en

inspections

with appr

ements and

l incidents /

nd incident

thority of ve

thority of th

dit Sheets

thority of de

ed species

– James Fis

on of specifi

ntation and

all consent

mental perf

inspections

mental con

Works and

Risk Asse

respect to e

onmental in

arine Works

orks

related docu

Site Inducti

essments a

environmen

on a

nvironmenta

s, investigat

rove conse

d address a

/ near misse

ts to the l

essel details

he commenc

for works

eposits by M

s licenses a

sher Marine

c environm

review of e

related doc

formance o

s and audits

nsiderations

d to include

essments a

environmen

cidents are

s

uments (S3

ons and To

and Method

ntal impacts

regular b

al mitigation

tion and rep

ent related

any shortfall

es and PC i

icensing au

s (ML Cond

cement dat

to the licen

MHWS (ML

are in plac

e Services

ental requir

environmen

cuments, in

of the pro

s.

form an

environme

nd Method

ntal impacts

e reported t

P

MEY-1A-4Construct

36 Condition

oolbox Talks

d Statemen

s and contro

basis to

n measures

porting.

d documen

ls with the

nvestigation

uthority and

dition 3.1.3)

e (ML Cond

nsing autho

Condition 3

ce for the D

rements to t

ntal procedu

cluding, but

oject throug

integral pa

ntal reviews

Statement

s and mitiga

to the ECoW

Page 8 of 26

40-HSE-00tionMethodS

n 10).

s.

nts (RAMS)

ols.

ensure e

s.

nts, enviro

PC (S36 C

ns

d other ne

dition 3.2.1.

ority (ML C

3.2.2.2)

Developme

the project

ures throug

t exhaustive

gh maintain

art of Des

ws as part of

ts (RAMS)

ation.

W and Me

 

6

1-D-StatementH

as and

effective

nmental

Condition

ecessary

4)

Condition

ent (S36

team.

hout the

e, CMS,

ning an

ign and

f regular

as and

yGen in

HDD

Page 9: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

3.4.2

Key role

ruction Meth

accordance(where req

Review enregulatory b

Ensure thaenvironmen

Implement relations an

Produce w

ECoW.

Ensure co

confirm th

undertake

HSE Adviso

es and resp

Verify comp

Prepare, im

with the Pr

Fisher Mar

Advise the

Review Ris

with respec

Approve To

effective en

and commu

Provide su

matters tha

Audit contr

have under

Ensure suit

monitoring

Inspect an

implementa

Ensure com

Provide ins

be address

hod Statem

e detailed uired) as so

nvironmentabodies on a

at arrangemntal issues

and maintand complain

eekly and m

ontractors

hat they a

n suitable

or

ponsibilities

pliance with

mplement, r

roject Mana

ine Service

project team

sk Assessm

ct to environ

oolbox Talk

nvironmenta

unicate ass

upport to th

at may arise

ractors to c

rtaken suita

table consid

(particularly

nd audit th

ation / opera

mpliance wi

spection rep

sed

ment: HDD M

reporting reoon as poss

al matters a regular ba

ents for liaiis appropria

ain a projecnts.

monthly rep

are appro

are suitab

environme

of the HSE

h relevant le

review and

agement Te

s procedure

m on enviro

ments and M

nmental imp

ks and Site

al managem

ociated less

he Marine

e.

onfirm that

able environ

deration is

y with respe

he site /

ation of any

th environm

ports to the

Marine Work

equirementsible.

with the asis and as

ison with Pate and mai

ct communic

ports and su

oved, oper

bly qualifie

ental trainin

E Advisor in

egislation.

update co

eam) in acc

es and curr

onmental re

Method State

pacts and m

e / Vessel I

ment, spec

sons learnt

Coordinato

they are s

nmental train

given to th

ect to highe

vessels on

y environme

mental requi

project ma

ks

ts and the

ECoW anper project

roject respeintained.

cations stra

ubmit to Me

rates a Sa

ed in the

ng to cove

clude, but a

nsent relate

cordance w

ent legislati

elated decis

ements (RA

mitigation.

Inductions a

cific works a

.

or and wor

suitably qua

ning to cove

e period an

er risk areas

n a regula

ental mitigat

irements an

anagement

MEY-1A-4Constructio

respective

nd MeyGerequiremen

ective regul

ategy to ma

eyGen Pac

afety Mana

ir line of

r tasks to b

are not limite

ed docume

with consen

on.

ion making

AMS) as an

and ensure

and Site / V

kforce on

alified in the

er tasks to b

nd frequenc

s).

ar basis to

tion measur

nd address

detailing an

0-HSE-001onMethodS

Page 9 of

e regulatory

en and resnts.

latory bodie

nage projec

kage Mana

agement S

work and

be underta

ed to the fo

ents (in con

nt condition

nd where ne

e content p

Vessel sen

any enviro

eir line of w

be undertak

cy of enviro

o ensure e

res.

any shortfa

ny issues th

-D-StatementHD

f 26

y bodies

spective

es on all

ct public

ager and

System,

d have

aken.

ollowing:

njunction

, James

ecessary

romotes

nsitivities

onmental

work and

ken.

nmental

effective

alls.

hat must

DD

Page 10: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

3.4.3

3.5 C

3.5.1

ruction Meth

Undertake

the root/dire

Monitor ha

aspects an

environmen

Marine Coo

Responsibl

site HSE du

Ensure tha

Undertake

communica

Monitor and

Production

stakeholde

Responsibl

notices.

Liaise with

Implement

related doc

Coordinatin

personnel m

Emergency

Produce da

Manager a

Keep Trans

part of the w

Keep audit

deposited b

Contractors

Vessel Mas

Overriding navigation

Dedicated w

The person

Adhere to

hod Statem

investigatio

ect cause a

azardous ob

nd impacts

ntal impacts

ordinator

le for all co

uring constr

t all contrac

Toolbox T

ate associat

d dissemina

of marine

r list.

le for colla

port author

/ operate e

cuments at t

ng, ensurin

movements

y response

aily reports

nd ECoW.

sport Audit

works

t reports st

below MHW

s

ster

authority of the vesse

watch-keep

ns present o

IMO Interna

ment: HDD M

ons into en

and present

bservations

s and initia

s and reduc

onstruction

ruction oper

ctors have r

Talks to pr

ted lessons

ate weather

safety ale

ating, comm

rities.

environmen

the site / ve

ng complian

s offshore.

coordinatio

s and subm

Sheets for

tating the n

WS under th

and respoel and matt

per on board

on board mu

ational Reg

Marine Work

nvironmenta

t the finding

s and incide

ate actions

ce risk in a t

operations

rations.

received an

romote effe

s learnt.

r information

erts includin

municating

tal mitigatio

essel.

nce for an

n.

mit to the P

all materia

nature and

e authority

nsibility to ters related

d the vesse

ust adhere

gulations for

ks

al incidents

s, recomme

ents trends

as require

timely and e

s Marine Co

d understoo

ective envi

n and forec

ng issuing N

and respo

on measure

d recording

PC Project

ls listed in t

quantity o

of the licen

make decto HSE.

el, or nomina

to the Vess

r the Preve

MEY-1A-4Constructio

or near m

endations a

s in relation

ed to minim

effective ma

oordination

od the Site /

ironmental

asts

Notice to M

nding to st

es as appro

g all vesse

Manager,

the licence

of all substa

ce.

cisions with

ate suitable

sel Master’s

ntion of Co

0-HSE-001onMethodS

Page 10 o

isses to de

and lessons

n to enviro

mise the p

anner.

including

/ Vessel ind

manageme

Mariners to

statutory na

oved in the

el moveme

MeyGen P

to be depo

ances and

h respect

e qualified d

s instruction

ollisions at S

-D-StatementHD

of 26

etermine

learnt.

nmental

potential

vessel /

duction.

ent and

agreed

avigation

consent

nts and

Package

osited as

objects

to safe

eputy.

s.

Sea and

DD

Page 11: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

3.5.2

3.6 C

EnvironVessel

MeetingSafety, Securityand ProDaily siRisk AsStatemeToolboxenvironmitigatioSite / V

3.6.1

The PCcommuenviron

The ECan openVessel on thosadditionof the w

ruction Meth

UK Merchqualified cr

Ensure tha

All Other S

To understa

To conductthe ProjectProject Ma

To report asoon as po

Communica

nmental issin Table 2.

g/briefing Health, Envy and Qualiogress Meete team brie

ssessment/Ment briefingx Talks inclumental pracon measureessel Induc

SHESQ an

C shall convnicate, dismental arra

CoW and ren invitation shall nominse contractnal meetingworks.

hod Statem

ant Shippirew and per

t all contrac

taff

and and im

t their work t and to ranager.

all environmossible.

ation

ues will be

vironment, ty (SHESQ

eting efs Method s uding ctices and es ction

Tab

d Progress

vene weeklyscuss and angements,

epresentativto attend t

nate a persotors behalfs at interva

ment: HDD M

ng legislatrsonnel on b

ctors have r

plement pro

with a viewaise any en

ental incide

e formally c

Freq

) Wee

DailyEach

Befominiper wOn fsite is un

ble 2 Comm

Meeting

y Site / Vesconsult anprocedures

ves from Mehese weekon to attendf. SHESQals dictated

Marine Work

tion includiboard.

received an

ocedures re

w to eliminatnvironmenta

ents to the M

communicat

quency ekly

y h job task

ore mobilisamum of oneweek first attendaBEFORE a

ndertaken

munication

ssel meetingny changes and overa

eyGen and ly Site / Ve

d these meeQ and Prog

by the requ

ks

ng ensurin

d understoo

elevant to th

ting/reducinal concerns

Marine Coo

ted through

ation, or a e

ance at any work

and Meeti

gs with all ce in conditall environm

other intereessel meetinetings with tgress Meetuirements o

MEY-1A-4Constructio

ng appropr

od the vess

heir role as

ng the enviros with Mar

rdinator and

h the arran

AttendeesSee parag

All work pAll membeparty All Site / V

All personVessel

ngs

contractors ions, work

mental perfo

ested Thirdngs. Each cthe approprings shall f the contra

0-HSE-001onMethodS

Page 11 o

riately train

sel induction

laid out.

ronmental imrine Coordi

d Vessel M

ngements o

s graph below

parties ers of the w

Vessel pers

ns attending

on Site / Vking practicormance.

d Parties shcontractor oriate authoribe augme

act or at key

-D-StatementHD

of 26

ned and

n.

mpact of nator or

aster as

on Site /

w

working

onnel

g Site /

Vessel to ces and

hall have on Site / ity to act nted by y stages

DD

Page 12: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

Minutescopies s

3.6.2

Extraormay arorganisany ide

3.6.3

Daily sicontrac

3.6.4

These involvedand rev

3.6.5

Inductioawarenenvironunderst

3.6.6

Site / VSafety place toas newof envir

3.7 R

The PC

ruction Meth

s of all sucsupplied to

Extraordina

rdinary meerise during sed by the Hntified issue

Daily site te

te team mectors. Any e

Risk Asses

briefings wd in the tasviewed.

Site / Vesse

ons, conducess for persmental prtanding.

Site / Vesse

Vessel noticand Enviroo highlight asletters andronmental m

Reporting

C will comm

Details of aDetails andDetails of aincidents; Any other pTransport A

Audit repor

below MHW

hod Statem

h meetingseach contra

ary meeting

etings wouldthe projec

HSE Advisoes.

eam meetin

eetings will nvironment

ssment / Me

will take placsk. Environm

el induction

cted beforesonnel regaotection a

el notice bo

ce boards wonmental issawareness d posters wmatters.

unicate the

audits and ind statistics foany pending

pertinent enAudit Sheet

rts for the

WS.

ment: HDD M

s shall be pactor on Sit

s

d be held in t such as or with the a

ngs

take place al concern

ethod Statem

ce before emental requ

ns

e anyone coarding Site /rrangemen

oards

will contain rsues. The of environm

will also be p

following to

nspections;or environm

g and actual

nvironmentas; and

nature and

Marine Work

produced ante / Vessel,

order to deenvironmenaim of ensu

at the Onsshall be ad

ment briefin

each constuirements a

ommences / Vessel rults. The i

relevant SitSite / Vessmental hazaposted on n

o the ECoW

mental incidl enforceme

al issues ide

d quantity o

ks

nd held on the CDM C

eal with spental incidenuring a time

hore / Offshdressed at

ngs

ruction tasknd mitigatio

work on thes, emergenductions

te / Vessel sel will alsoards. Other notice board

W and contra

ents and neent action in

entified;

of all subst

MEY-1A-4Constructio

file for recCo-ordinator

ecial environnts. These ely respons

hore site bethis meeting

k and attenon measure

he project aency respon

include a

informationo have appr

communicds to comm

actors on S

ear misses; n respect of

tances and

0-HSE-001onMethodS

Page 12 o

cord purposr and ECoW

nmental issmeetings s

se and reso

etween the g.

nded by alles will be in

are utilised nse procedu test to

n relating toropriate sig

cations medmunicate aw

ite / Vessel

f any enviro

objects de

-D-StatementHD

of 26

ses, with W.

ues that shall be lution to

PC and

directly structed

to raise ures and

confirm

o Health, gnage in dia, such wareness

:

nmental

eposited

DD

Page 13: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

The PC

3.7.1

The Ma

The EC

3.8 T

The puknowled

In ordefollowin

ruction Meth

C will provide

Daily logs aWeekly proMonthly repenvironmenstatistics, trany of the c

External Co

arine Coord

Documentifor the DevEmergencycommunicaEmergency

CoW is resp

NotificationReporting m

o Det

o Det

o Detenv

o Any

o Tra

o Auddep

Meeting wiand Receiving, third parties

raining

urpose of dge to succ

r to ensure ng environm

hod Statem

e these in:

and reports ogress repoports (additntal commraining delivconsents re

ommunicati

inator is res

ng, issuing,velopment; ay Responseation and ry Response

onsible for:

n to the licenmonthly to t

ails of audit

ails and sta

ails of anyvironmental

y other perti

nsport Audi

dit reports posited belo

th the licen

documentis.

environmencessfully imp

that the enmental trainin

ment: HDD M

when consrts tionally, conitments anvered, envirelated docum

on

sponsible fo

, communicand e Co-operareporting p

e Co-operati

nsing authothe licensing

ts and inspe

atistics for e

y pending incidents;

nent enviro

it Sheets; a

for the naw MHWS.

sing author

ng and res

ntal trainingplement the

nvironmentang Table 3

Marine Work

struction act

nfirming thend mitigatioronmental inments)

or:

cating and r

tion Procedprotocols foion Plan (N

ority detailedg authority

ections;

environment

and actual

onmental iss

nd

ature and q

rity and stat

sponding to

g is to ene environme

al mitigationin will be re

ks

tivities are t

e status of ton measurenitiatives un

responding

dures are ior such an SP).

d in the cononce works

tal incidents

enforceme

sues identif

quantity of

tutory agen

any enviro

nsure that ental require

n measuresequired.

MEY-1A-4Constructio

aking place

the project,es, monthlndertaken, a

to statutory

n place forevent can

sent condits have comm

s and near m

ent action

ied;

all substa

cies and th

onmental co

all site peements of th

s are implem

0-HSE-001onMethodS

Page 13 o

e on site / ve

, implemently and cumamendmen

y navigation

r such evenn be found

ion; menced wit

misses;

in respect

ances and

he local com

ommunicati

ersonnel hahe project.

mented on

-D-StatementHD

of 26

essels;

tation of mulative ts to the

n notices

nts. The d in the

th:

of any

objects

mmunity;

ion from

ave the

site, the

DD

Page 14: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 14 of 26

 

Any person working on the site/vessel will be competent and trained sufficiently to undertake their work in a safe and efficient manner. Each Contractor will ensure that their personnel maintain the necessary level of competence for their work & will maintain the training records on site & make them available for review and audit.

Training Target Persons Induction (which will include environmental aspects such as environmental sensitivities and controls, pollution prevention, waste management, emergency preparedness and response and  include shipboard operations under STCW requirements)

All persons attending Site / Vessel (Site / Vessel personnel, contractors on Site / Vessel, and visitors)

Environmental Toolbox Talks Toolbox talks will be carried out at a minimum of one per week appropriate to the construction works being carried out on Site / Vessel at that time. All persons carrying out work on site (site personnel, contractors on site) shall attend.

Environmental Bulletins / Legislation Briefings / Best Practice Briefings

All persons carrying out work on Site / Vessel (Site / Vessel personnel, contractors on Site / Vessel) shall attend.

Job specific training e.g. IOSH Working with Environmental

Responsibilities / IOSH Managing Environmental Responsibilities.

Use of Pollution Prevention Equipment. Site Waste Management.

As identified for personnel with environmental responsibilities

Project specific information, including relevant elements of: the EMP, CMS, NSP, VMP Consent Conditions

Briefed out and available for reference to all Site / Vessel staff.

Table 3 Training

Any person working on the Site / Vessel will be competent and trained sufficiently to undertake their work in a safe and efficient manner. Each Contractor will ensure that their personnel maintain the necessary level of competence for their work & will maintain the training records on site & make them available for review and audit. Records of training will be maintained and made available for inspection. 

4 PROGRAMME

The high level programme for the HDD Marine Works in shown in Figure 2. The Programme is subject to change and will be regularly updated during the course of the Development.

Page 15: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 15 of 26

 

 

Figure 2 HDD Marine Works Programme

5 CONSTRUCTION METHODS AND PROCEDURES

5.1 HDD Works

4 x HDD Bores are to be drilled from the onshore Ness of Quoys Power Conversion Centre to target exit locations on the seabed (Figure 3). The HDD bores are drilled using at 16’ (406mm) drill bit. As the drilling is undertaken, the exact location of the drill head is monitored as it proceeds along its path and provide real-time information as to its location and depth. This will be achieved using a Real-Time Constant Rate Gyroscope based guidance system which is impervious to magnetic interference.

During the drilling process, drilling fluid (bentonite mud) is pumped down the inside of the drill string where it cools the guidance system and drilling motor. The drilling fluid then flows out of the drill bit via nozzles and flushes drilled cuttings back to surface as it flows up the annulus. The drilling fluid also lubricates and supports the borehole. Before the drill is punched out onto the seabed the drill string will be pulled from the bore and re-run performing a ‘wiper trip’ to condition the drilling mud and remove cuttings from the bore. When the drill punches out onto the seabed drilling muds will immediately stop cycling; a small amount of bentonite and cuttings will be released into the marine environment (bentonite will flocculate on contact with salt water).

As described in the EMP (Marine Pollution Contingency Plan) a small amount of bentonite drilling mud and cuttings will be released into the marine environment. As stated in Marine Licence Condition 3.1.9 any drill cuttings associated with the use of water-based drilling muds situated within the outer boundary of the works need not be removed from the seabed.

Page 16: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

5.2 H

Construshall no

The foll

5.2.1

ruction Meth

HDD Marine

uction methot be limited

Identifying

Cut the ‘bu

ConnectingHDD liner;

Fit a seal to

owing sequ

Pre-mobilis

No less thalicensing aless than 2

The PC wil

hod Statem

Fig

e Works

hods and pd to) the follo

the exit po

llnose’ from

g and discoand

o the end of

uence outlin

sation

an one monuthority, in 4 hours bef

l confirm:

ment: HDD M

gure 3 HDD

rocedures fowing:

int of the 4

m the HDD li

onnecting e

f the HDD li

nes the HDD

nth prior to writing, the

fore comme

Marine Work

D Marine W

for the HD

x HDD bore

iner;

equipment t

iner to prev

D Marine W

commencee date of cencement (M

ks

orks Locat

D Marine W

es on the se

to the drill s

vent debris e

Works proces

ement of wcommencemML 3.2.1.4)

MEY-1A-4Constructio

tion

Works will

eabed;

string to cle

entering.

ss.

works the ECment and co

HDD site lo

0-HSE-001onMethodS

Page 16 o

be set out

ean and pr

CoW will nonfirm this

ocation

-D-StatementHD

of 26

for (but

rove the

otify the date no

DD

Page 17: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

5.2.2

5.2.3

The HDspecificto ensu

ruction Meth

1. the ves

2. vessel m

3. vessel

4. vessel o

to be usedauthority, in3.1.3)

Notice to Mthe works,

Weather foconditions.

Mobilisation

All commun

Inventoriesthe vessel.

Vessel envthe EMP (R

Vessel will (MEY-1A-4

Vessel and

DD Marine cation). There the vess

hod Statem

sel,

master,

IMO numbe

owner and

d on the won writing, no

Mariners wilan example

orecasts will

n

nications an

s for all tool

vironmental RHK-1A-40-

leave selec40-HSE-003

d Moorings

Works will e vessel willsel hold stat

ment: HDD M

er, and

operator

orks to the o less than

ll be issuede is provided

l be reviewe

nd meetings

ls, materials

mitigation m-HSE-D-001

cted port an3-D-VesselM

utilise a sin be anchorion during t

Marine Work

ECoW, so72 hours p

d a minimumd in Append

ed at regula

s will be hel

s and liquid

measures w1-Environm

nd transit toManagemen

ngle 26m Mred within athe subsea

ks

that the Eprior to com

m of 2 weedix A of the

ar intervals

ld as per Se

ds will be c

will be checkentalManag

o site on thntPlanHDD)

Multi-cat vea 4 point tem

dive work.

MEY-1A-4Constructio

ECoW can nmmencemen

eks prior to NSP.

to ensure t

ection 3.6.

completed b

ked to ensugementPlan

e route des)

ssel (see tmporary mo

0-HSE-001onMethodS

Page 17 o

notify the lnt of the wo

commence

the appropr

before load

ure complianHDD).

scribed in t

he VMP foooring arran

-D-StatementHD

of 26

icensing orks (ML

ement of

riate site

ing onto

nce with

he VMP

r vessel ngement

DD

Page 18: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

Details Navigat

5.2.4

The divassembtaken.

A helme'rockfall

This dicontinu

5.2.5

The HDthe HDD

a)

ruction Meth

of the navigtionSafetyP

HDD Bore

ve is requirebly at the se

et camera wl' that may c

ve will be e.

HDD Bore

DD bore lineD bore liner

Cut off thepolyethylenvessel deck

hod Statem

Fig

gation safetPlanHDD).

1 Dive 1

ed to confireabed on a

will be usedcompromise

undertake

1 Dive 2a, 2

er will be pr has been

e cable ducne pipe, usk for safe d

ment: HDD M

gure 4 HDD

ty measure

rm the drilletight line so

to enable de cable duc

n at the f

2b and 2c

pushed throinstalled a d

ct bull noseing a pneuisposal.

Marine Work

D Marine W

e are contain

ed exit locao that a GP

drilling persct installation

first availab

ough the HDdive is requ

e. This invoumatic saw.

ks

orks Locat

ned in the N

tion. A marPS reading

sonnel to iden operation

ble slack ti

DD bore frouired to perf

olves sawin. The bull n

MEY-1A-4Constructio

tion

NSP (MEY-

rker buoy isof the buoy

entify any ps.

de before

om onshoreorm the foll

ng through nose will be

0-HSE-001onMethodS

Page 18 o

-1A-40-HSE

s tied to they on surface

potential iss

drilling op

e to offshorowing tasks

a 315mm e recovered

-D-StatementHD

of 26

E-002-D-

e drilling e can be

ues with

erations

re. Once s:

SDR-11 d to the

DD

Page 19: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

b)

c)

These davailab

5.2.6

5.2.7

For HDmooringMarine

The moSubmar

5.2.8

Should pushedwill be u

5.3 E

The EMMarine These a

ruction Meth

The drillingsite, trailingBrush, (5mrope.

The drillingdraw rope, behind the

The divers to temporaphase of th

dives shall ility of a sui

Demobilisa

The vesselcorrectly m

Check tools

Return to p

At port, waccordanceManageme

HDD Bores

DD Bores 2g and demoWorks for H

ooring sprerine Cable.

Contingenc

the drilling away by thundertaken

Environmen

MP describeWorks. Th

are summa

hod Statem

g team will g a draw ro

mm larger th

g team will pbrushing amandrel fro

will then bory seal off t

he installatio

be undertaktable period

ation from B

l will disconarked and l

s, materials

port via the r

waste matere with the went Plan inc

s 2, 3, 4

, 3, 4, the obilising fromHDD Bore 4

ead will rem

cy Diving

g operation he drilling ain accorda

ntal Mitigat

es the mitigese have brised below

ment: HDD M

then pumpope. The dhan ID), and

pull the bruand provingom the seab

olt a Viking the end of ton

ken in accod of calm we

ore 1

nnect from lit (see NSP

s and liquids

route descr

rials and liwaste manaluded in the

procedure m the moor4 the vessel

main in po

create loosassembly, dnce with the

tion

gation meabeen taken

w.

Marine Work

a foam pigivers will u

d a 230mm

ush and mag it. A seconbed.

Johnson Athe HDD bo

ordance witheather, calm

the moorinP for further

s are all on

ribed in the

iquids will agement plae EMP)

will be repring spread l will be dem

osition to a

se material divers may e Waste Ma

asures and from the m

ks

g down thenclip the foMandrel, (

ndrel back nd draw rop

Aquagrip coore liner and

h the progam seas and

ng spread, r details),

board and

VMP.

be taken an. (James

peated with that is left

mobilised an

id the insta

at the seabe required

anagement

methodolomitigation de

MEY-1A-4Constructio

e cable ductoam pig an10% less th

through thepe will be t

nnector to td left in situ

mme (Figurgood visibi

ensure that

accounted f

onshore anFisher Mari

the vesselin-situ. On nd return to

allation wor

abed exit pod to assist iPlan (see E

gies to be escribed in

0-HSE-001onMethodS

Page 19 o

ct from the d attach a hat ID), to t

e cable ductrailed into t

the cable du ready for

re 2), subjeility.

t the moori

for on inven

nd disposeine Service

l mobilisingcompletion

o port.

rks of the

oint that cain its removEMP)

used for ththe ES an

-D-StatementHD

of 26

onshore 267mm he draw

ct on the the duct

uct stub the next

ct to the

ings are

ntories.

ed of in s Waste

g to site, of HDD

Turbine

annot be val. This

he HDD nd SEIS.

DD

Page 20: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

5.3.1

Navigat

Navigatprocedu

Marine

Mitigatiounder th

Pollutio

Mitigatiospills anrequirem

Invasive

A short Scotlanlisted in

Waste M

Waste mrequirem

5.3.2

Navigat

Navigatprocedu

Marine

ruction Meth

Vessels

tion Safety 

tion safety nures of and

Mammals 

on measurehe procedu

Training of of marine mProvision otherefore toMaintenancany interacrecord manundertakingcurious aboengaged in

on Preventio

on measurend objects oments of the

e Non-Nativ

non-nativend for each vn the manag

Manageme

managemements of the

Moorings

tion Safety 

tion safety nures of and

Mammals 

hod Statem

notices, wato meet the

es detailed res of and t

all on site /mammals anof advice to o be avoidece of a daily

ction will be ny approachg HDD Marout any in wn marine wo

on 

es detailed overboard we Marine Po

ve Species

managemevessel arrivgement plan

nt 

nt will be coe Waste Ma

notices, wato meet the

ment: HDD M

rnings and e requireme

for the proteto meet the

/ on vessel pnd their legstaff detailid; and y marine manoted. It is

hes by mariine Works.

water constrorks.

for the prevwill be condollution Con

Manageme

ent report wval on site an in the EM

onducted unanagement

rnings and e requireme

Marine Work

demarcatioents of the N

ected of marequiremen

personnel rislative protng the type

ammal log bs important tne mamma Marine ma

ruction work

vention of mucted unde

ntingency P

ent

will be providand used in P.

nder the proPlan in the

demarcatioents of the N

ks

ons will be cNSP. 

arine mammnts of the E

regarding thtection; s of activity

by the Princto make cle

als to the veammals are ks, regularly

marine polluter the procePlan in the E

ded by the PHDD Marin

ocedures ofe EMP. 

ons will be cNSP. 

MEY-1A-4Constructio

conducted u

mal species MP and VM

he importan

y potentially

cipal Contraear that suchssels and pintelligent a

y approachi

tion from oidures of an

EMP. 

Principal Cone Works, in

f and to mee

conducted u

0-HSE-001onMethodS

Page 20 o

under the

will be conMP. These i

ce and sen

disturbing,

actor, into wh a log is lik

personnel and naturalng vessels

l and chemnd to meet t

ontractor toncluding the

et the

under the

-D-StatementHD

of 26

ducted nclude:

sitivity

and

which kely to

ly

ical he

Marine e details

DD

Page 21: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

Mitigatiounder th

Pollutio

Mitigatiospills anrequirem

Archaeo

A reporthe accmonitorMarine

5.3.3

Navigat

Navigatprocedu

Marine

Mitigatiounder th

ruction Meth

on measurehe procedu

Training of of marine mProvision otherefore toMaintenancany interacrecord manundertakingcurious aboengaged in

on Preventio

on measurend objects oments of the

ology 

rting protococidental discring.  Full dArchaeolog

Dive Activit

tion Safety 

tion safety nures of and

Mammals 

on measurehe procedu

Training of of marine mProvision otherefore toMaintenancany interacrecord manundertaking

hod Statem

es detailed res of and t

all on site /mammals anof advice to o be avoidece of a daily

ction will be ny approachg HDD Marout any in wn marine wo

on 

es detailed overboard we Marine Po

ol for the dcovery of metails and gy are in the

ty

notices, wato meet the

es detailed res of and t

all on site /mammals anof advice to o be avoidece of a daily

ction will be ny approachg HDD Mar

ment: HDD M

for the proteto meet the

/ on vessel pnd their legstaff detailid; and y marine manoted. It is

hes by mariine Works.

water constrorks.

for the prevwill be condollution Con

iscovery of marine culturequiremen

e EMP. 

rnings and e requireme

for the proteto meet the

/ on vessel pnd their legstaff detailid; and y marine manoted. It is

hes by mariine Works.

Marine Work

ected of marequiremen

personnel rislative protng the type

ammal log bs important tne mamma Marine ma

ruction work

vention of mucted unde

ntingency P

marine arcural materiants of the

demarcatioents of the N

ected of marequiremen

personnel rislative protng the type

ammal log bs important tne mamma Marine ma

ks

arine mammnts of the E

regarding thtection; s of activity

by the Princto make cle

als to the veammals are ks, regularly

marine polluter the procePlan in the E

chaeology hal during deReporting P

ons will be cNSP. 

arine mammnts of the E

regarding thtection; s of activity

by the Princto make cle

als to the veammals are

MEY-1A-4Constructio

mal species MP and VM

he importan

y potentially

cipal Contraear that suchssels and pintelligent a

y approachi

tion from oidures of an

EMP.

has been prevelopmentProtocol fo

conducted u

mal species MP and VM

he importan

y potentially

cipal Contraear that suchssels and pintelligent a

0-HSE-001onMethodS

Page 21 o

will be conMP. These i

ce and sen

disturbing,

actor, into wh a log is lik

personnel and naturalng vessels

l and chemnd to meet t

roduced to t, maintenanr the Disco

under the

will be conMP. These i

ce and sen

disturbing,

actor, into wh a log is lik

personnel and natural

-D-StatementHD

of 26

ducted nclude:

sitivity

and

which kely to

ly

ical he

address nce and overy of

ducted nclude:

sitivity

and

which kely to

ly

DD

Page 22: MeyGen Tidal Energy Project Phase 1 Construction Method ...

 

Constr

Pollutio

Mitigatiospills anrequirem

Archaeo

A reporthe accmonitorMarine

5.3.4

No altedives ar

6 EM

Pollutiobe adhe

Emergespecific

These p

ruction Meth

curious aboengaged in

on Preventio

on measurend objects oments of the

ology 

rting protococidental discring.  Full dArchaeolog

Alternatives

ernative mitre required.

MERGENC

on preventioered to at a

ency Respocally to the w

procedures

Man OverbGeneral MOFire & ExplPersonnel Serious InjuMedical AdRequest foEvacuationAdverse WEnvironmeClean up aSpill NotificSpill DocumImmediate Clean-up aSpill notificaSpill DocumLocation an

hod Statem

out any in wn marine wo

on 

es detailed overboard we Marine Po

ol for the dcovery of metails and gy are in the

s

tigation met.

CY PREPA

on measurell times on v

onse Proceworks being

include:

board OB Proceduosion Injury or Meury or Illnes

dvice r medical a

n of a sick oWeather Proc

ntal Responctions spec

cation mentation actions

actions ation

mentation nd Content

ment: HDD M

water constrorks.

for the prevwill be condollution Con

iscovery of marine culturequiremen

e EMP. 

thods are r

AREDNESS

s included vessels and

edures are g executed,

ure

edical Evacss

ssistance r injured pecedure nse Plan cific to haza

of a Spill K

Marine Work

ruction work

vention of mucted unde

ntingency P

marine arcural materiants of the

required for

S AND RE

in the EMPd working at

an intrinsithe ERCoP

cuation

erson from a

rdous mate

it

ks

ks, regularly

marine polluter the procePlan in the E

chaeology hal during deReporting P

r the HDD

SPONSE

P (Marine Pot quayside.

ic part of tP is detailed

a vessel

erials

MEY-1A-4Constructio

y approachi

tion from oidures of an

EMP.

has been prevelopmentProtocol fo

Marine Wo

ollution Con

the Scope d in the NSP

0-HSE-001onMethodS

Page 22 o

ng vessels

l and chemnd to meet t

roduced to t, maintenanr the Disco

orks if cont

ntingency P

of Works P.

-D-StatementHD

of 26

ical he

address nce and overy of

tingency

Plan) will

relating

DD

Page 23: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 23 of 26

 

Post incident reporting Training 

7 LICENCES AND LEGAL REQUIREMENTS

Licence / Consent Legislation Granted

Section 36 Consent Electricity Act 1989 09/10/2013

Marine Licence (licence number 04577/14/0)

Marine (Scotland) Act 2010 31/01/2014

Decommissioning Programme Energy Act 2005 xx

Table 4 Consent

8 LINKAGES WITH OTHER STRATEGIES AND SHE MANAGEMENT SYSTEMS

The NSP complies with the Principal Contractor’s Construction Phase Health and Safety Plan (under the Construction (Design and Management) Regulations 2007) and their Health, Safety and Environment Manual.

9 CMS REVIEW AND CONSULTATION

Under Condition 9 of the Section 36 the CMS will be reviewed and commented on by the licensing authority and SNH, SEPA, MCA, NLB, the planning authority and any other such advisors that may be required at the discretion of the Scottish Ministers. The CMS must be approved by the licensing authority.

The CMS will be submitted to the licensing authority for distribution to the stakeholders and for approval.

Any changes the CMS deemed necessary (working methods or procedures) must be reviewed and approved by the ECoW before it is submitted for approval to the licensing authority (Figure 5).

Version control will be conducted by the revision review block on the front page of the CMS.

Page 24: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 24 of 26

 

 

Figure 5 CMS Change Process

Page 25: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 25 of 26

 

10 LIST OF ABBREVIATIONS

Abbreviation

CDM Construction (Design and Management) Regulations 2007

CMS Construction Method Statement

COSHH Control of Substance Hazardous to Health

ECoW Ecological Clerk of Works

EIA Environmental Impact Assessment

EMP Environmental Management Plan

ERCoP Emergency Response Co-operation Plan

ERP Emergency Response Procedures

EPS European Protected Species

ES Environmental Statement

HDD Horizontal Directional Drilling

HSE Health, Safety and Environment

IOSH Institute of Occupational Safety and Health

JNCC Joint Nature Conservation Committee

NSP Navigation Safety Plan

MCA Maritime Coastguard Agency

MHWS Mean High Water Springs

ML Marine Licence under the Marine (Sotland) Act 2010

MLWS Mean Low Water Springs

MMO Marine Mammal Observer

PC Principal Contractor – James Fisher Marine Services

Page 26: MeyGen Tidal Energy Project Phase 1 Construction Method ...

Construction Method Statement: HDD Marine Works

MEY-1A-40-HSE-001-D-ConstructionMethodStatementHDD

Page 26 of 26

 

PEMP Project Environmental Monitoring Programme

RAMS Risk Assessments and Method Statements

SAC Special Area of Conservation

SCIMS Seal Corkscrew Injury Monitoring Scheme

SEIS Supplementary Environmental Information Statement

SEPA Scottish Environment Protection Agency

SHESQ Safety, Health, Environment, Security and Quality

SNCA Statutory Nature Conservation Agency

SNH Scottish Natural Heritage

SPA Special Protected Area

STCW International Convention on Standards of Training, Certification and Watchkeeping for Seafarers, 1978

S36 Section 36 of the Electricity Act 1989

TSC Turbine Submarine Cable

TSS Turbine Support Structure

TTG Tidal Turbine Generator

VMP Vessel Management Plan

 