7/21/17 10:34 AM Page 1 of 3 MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -7/18/17-8/1/17 WORK HOURS: 7:00 AM - 7:00 PM FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected] FULL CONSTRUCTION BUILD OUT ZONE LOCATION STATUS 1 95 and 101 State Street 95 State Interior fit out is underway along with interior demolition work/cleanup and floor leveling. Window delivery and installation has begun. Exterior façade work is underway. Sidewalk work inside fenced area anticipated to begin in coming weeks. 2 Hotel The following activities are ongoing: Above ground storm piping, spray on fireproofing, mechanical, electrical and plumbing (MEP), exterior framing/backup wall, interior framing lay out, and interior framing. Support steel for Union Chandler will be removed on Saturday July 29th & Saturday Aug 5th if needed. A police detail is anticipated. During this work a portion of Main Street will be closed to traffic. Access to Red Rose will be maintained. 3 Casino The following activities are ongoing: Above ground storm piping, exterior framing/backup wall, MEPs, roofing, interior framing/sheet rock, fire protection, dryfall paint, painting in telecommunications rooms, and escalator truss installation. 4 Da Vinci Park No work anticipated 5 Dave's Furniture No work anticipated 6 Armory No work anticipated 7 Plaza No work anticipated 8 Church No work anticipated 9 Entertainment The following activities are ongoing: spray on fireproofing, exterior framing/backup wall, roofing, and scaffold erection. 10 Parking Garage The following activities are ongoing: Above ground MEP installation, waterproofing and caulking, painting and line striping, installation of storefront, and elevator construction.. 11 Support Area No work anticipated 12 MGM Way Receiving deliveries and staging of material/equipment.
Transcript
Page 1: MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -7/18/17-8/1/17 ... · 7/21/17 10:34 AM Page 3 of 3 Springfield Water & Sewer No work anticipated MISCELLANEOUS ACTIVITY LOCATION WORK TO BE

7/21/1710:34AM Page1of3

MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -7/18/17-8/1/17

WORK HOURS: 7:00 AM - 7:00 PM

FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected]

FULL CONSTRUCTION BUILD OUT

ZONE LOCATION STATUS

1 95 and 101 State Street 95 State Interior fit out is underway along with interior demolition work/cleanup and floor leveling. Window delivery and installation has begun. Exterior façade work is underway. Sidewalk work inside fenced area anticipated to begin in coming weeks.

2 Hotel

The following activities are ongoing: Above ground storm piping, spray on fireproofing, mechanical, electrical and plumbing (MEP), exterior framing/backup wall, interior framing lay out, and interior framing.

Support steel for Union Chandler will be removed on Saturday July 29th & Saturday Aug 5th if needed. A police detail is anticipated. During this work a portion of Main Street will be closed to traffic. Access to Red Rose will be maintained.

3 Casino The following activities are ongoing: Above ground storm piping, exterior framing/backup wall, MEPs, roofing, interior framing/sheet rock, fire protection, dryfall paint, painting in telecommunications rooms, and escalator truss installation.

4 Da Vinci Park No work anticipated

5 Dave's Furniture No work anticipated

6 Armory No work anticipated

7 Plaza No work anticipated

8 Church No work anticipated

9 Entertainment The following activities are ongoing: spray on fireproofing, exterior framing/backup wall, roofing, and scaffold erection.

10 Parking Garage The following activities are ongoing: Above ground MEP installation, waterproofing and caulking, painting and line striping, installation of storefront, and elevator construction..

11 Support Area No work anticipated

12 MGM Way Receiving deliveries and staging of material/equipment.

Page 2: MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -7/18/17-8/1/17 ... · 7/21/17 10:34 AM Page 3 of 3 Springfield Water & Sewer No work anticipated MISCELLANEOUS ACTIVITY LOCATION WORK TO BE

7/21/1710:34AM Page2of3

STREET WORK

State Street Saturday Aug 12th, the city will be holding its Jazz & Roots Festival. On this day no work will occur on State or Main Street.

Main Street

Reflectorized drums will intermittently be placed in the south bound lane to shift traffic from 6am-6pm Monday through Friday to allow for the unloading of certain materials onto the construction site. The barrels will be moved out of the road at the end of each day to allow parking during non-working hours. Two way traffic will be maintained at all times and two police details will be present. This traffic shift is currently underway.

Support steel for the Union Chandler building will be removed on Saturday July 29th and, if needed, Aug 5th. A police detail is anticipated. During this work Main Street will be closed from State Street to Union Street. Vehicles will utilize Maple Street as a detour route. Access to local businesses will be maintained and signage will be in place to notify/direct patrons/drivers. Anticipated work hours are 6:00 AM until 6:00 PM.

Beginning on Monday July 24th, utility work will take place in the sidewalk and parking stalls on the east side of Main Street from Red Rose to Union Street. The sidewalk will be closed to pedestrian traffic at this time. This work is anticipated to take all week. The work area will be protected with barriers, construction barrels, and fencing at all times.

Saturday Aug 12th the city will be holding its Jazz & Roots Festival. On this day no work will occur on State or Main Street.

Union Street

Utility work is underway and will continue throughout the summer at the intersections of Union, Howard West, and Bliss Street with East Columbus Ave. During this work, Union Street will be closed to through traffic from Main Street to East Columbus Avenue. Access to Pride Gas Station, the Colvest Building, and 55 State Street will be maintained at all times. Signage will be in place to direct patrons to business’ on Main Street via State Street and to provide updates and direction for drivers in the area.

East Columbus Ave will be open to through traffic throughout the project. At times, lanes will need to be reduced to accommodate utility crossings at the intersections. Police details will be present throughout the summer to help traffic flow as efficiently as possible.

East Columbus Avenue Work is underway to repair/replace portions of water main piping. A police detail is anticipated.

Bliss Street Work is underway to repair/replace portions of water main piping. A police detail is anticipated.

Howard Street Turn Around No work anticipated

Howard Street Work is underway to repair/replace portions of water main piping. A police detail is anticipated.

UTILITY ACTIVITY

UTILITY PROVIDER WORK TO BE PERFORMED

Eversource No work anticipated

Verizon No work anticipated

Comcast No work anticipated

Columbia Gas No work anticipated

Page 3: MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -7/18/17-8/1/17 ... · 7/21/17 10:34 AM Page 3 of 3 Springfield Water & Sewer No work anticipated MISCELLANEOUS ACTIVITY LOCATION WORK TO BE

7/21/1710:34AM Page3of3

Springfield Water & Sewer No work anticipated

MISCELLANEOUS ACTIVITY

LOCATION WORK TO BE PERFORMED

York Street Lot Construction material staging is underway.

Zorzi Lot Established as parking for craft labor foreman and superintendents.

Offsite Parking Lots Craft labor parking has been established at the Mass Mutual Center parking garage and 1870 E. Columbus Ave.

Page 4: MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -7/18/17-8/1/17 ... · 7/21/17 10:34 AM Page 3 of 3 Springfield Water & Sewer No work anticipated MISCELLANEOUS ACTIVITY LOCATION WORK TO BE

MAIN STREET

EAST COLUMBUS AVENUE

HOW

ARD

TURN

ARO

UND

195/101 STATE

2HOTEL

3CASINO

12MGM WAY

7PLAZA

6ARMORY

8CHURCH

5DAVE’S

FURNITURE

4DA VINCI

PARK

9ENTERTAINMENT

10PARKING GARAGE

11SUPPORT

AREA

BLIS

S ST

REET

HOW

ARD

STRE

ET

STAT

E ST

REET

UNIO

N ST

REET

BEGINNING IN MID JUNE AND CONTINUING THROUGHOUT THE SUMMER, UTILITY WORK WILL BE TAKING PLACE AT THE INTERSECTIONS OF UNION, HOWARD WEST, AND BLISS STREET WITH EAST COLUMBUS AVE. DURING THIS WORK, UNION STREET WILL BE CLOSED TO THROUGH TRAFFIC FROM MAIN STREET TO EAST COLUMBUS AVENUE. ACCESS TO PRIDE GAS STATION, THE COLVEST BUILDING, AND 55 STATE STREET WILL BE MAINTAINED AT ALL TIMES. SIGNAGE WILL BE IN PLACE TO DIRECT PATRONS TO BUSINESSES ON MAIN STREET VIA STATE STREET AND TO PROVIDE UPDATES AND DIRECTION FOR DRIVERS IN THE AREA.

EAST COLUMBUS AVE WILL BE OPEN TO THROUGH TRAFFIC THROUGHOUT THE PROJECT. AT TIMES, LANES WILL NEED TO BE REDUCED TO ACCOMMODATE UTILITY CROSSINGS AT THE INTERSECTIONS. POLICE DETAILS WILL BE PRESENT THROUGHOUT THE SUMMER TO HELP TRAFFIC FLOW AS EFFICIENTLY AS POSSIBLE.

SUPPORT STEEL FOR THE UNION CHANDLER BUILDING WILL BE REMOVED ON SATURDAY JULY 29TH AND, IF NEEDED, AUG 5TH. A POLICE DETAIL IS ANTICIPATED. DURING THIS WORK MAIN STREET WILL BE CLOSED FROM STATE STREET TO UNION STREET. VEHICLES WILL UTILIZE MAPLE STREET AS A DETOUR ROUTE. ACCESS TO LOCAL BUSINESSES WILL BE MAINTAINED AND SIGNAGE WILL BE IN PLACE TO NOTIFY/DIRECT PATRONS/DRIVERS. ANTICIPATED WORK HOURS ARE 6:00 AM UNTIL 6:00 PM.

BEGINNING ON MONDAY JULY 24TH, UTILITY WORK WILL TAKE PLACE IN THE SIDEWALK AND PARKING STALLS ON THE EAST SIDE OF MAIN STREET FROM RED ROSE TO UNION STREET. THE SIDEWALK WILL BE CLOSED TO PEDESTRIAN TRAFFIC AT THIS TIME. THIS WORK IS ANTICIPATED TO TAKE ALL WEEK. THE WORK AREA WILL BE PROTECTED WITH BARRIERS, CONSTRUCTION BARRELS, AND FENCING AT ALL TIMES.