Milwaukee’s Best Brew Stand
Ben CayaCarl Czajka
4th Update
Parts
(3) 6” Cast Iron Burner-$18ea• 55,000 BTU
(1) Propane Regulator - $28ea
(3) 15gal Kettle - $220ea• 1mm walls• Best Kettle Money Can Buy
Parts
(2) March Pumps - 815-PL - $150ea• 8 GPM• .04 HP• 110V
(4) 6” Pneumatic Castor - $19ea• 300lb capacity
(1)Heat Exchanger - $40• Aluminum shell• Inner Copper Spiral
PartsName Quantity Price Ea Total
Steel for Frame 1 Donate -
Burners 3 $18 $54.00
Regulators 1 $26 $26.00
Pumps 2 $150 $300.00
Castors 4 $19 $76.00
Kettles 3 $175 $525.00
Thermometers 3 $26 $78.00
Valves 3 $20 $60.00
Piping 1 $40 $40.00
Heat Exchanger 1 $40 $40.00
Total: $1,058.80
Frame – Shearing Material
Frame – Forming Angles
Frame – Sub Frame
Frame - Welded
Frame - Welded
Gantt Chart
WBS TasksTaskLead Start End
Duration (Days)
% Complete
Working Days
Days Compl
ete
Days Remaining
23 - Jan - 12 30 - Jan - 12 06 - Feb - 12 13 - Feb - 12 20 - Feb - 12 27 - Feb - 12 05 - Mar - 12 12 - Mar - 12 19 - Mar - 12 26 - Mar - 12 02 - Apr - 12
1 Initialize Project 1/23/12 2/15/12 3 100% 18 3 0
1.1 Partner Assign 1/23/12 1/24/12 2 100% 2 2 0
1.2 Choose Project 1/23/12 1/25/12 3 100% 3 3 0
2 VOC and Design Requirments 2/16/12 2/29/12 14 100% 10 14 0
2.1 HBT Design Pole 2/16/12 2/22/12 7 100% 5 7 0
2.2 Design Requirments 2/16/12 2/18/12 3 100% 2 3 0
2.3 Bi-Weekly Report #1 2/25/12 2/29/12 5 100% 3 5 0
2.4 Oral Presentation #1 2/25/12 2/29/12 5 100% 3 5 0
3 VOC and Design Requirments 2/16/12 2/29/12 14 100% 10 14 0
3.1 HBT Design Pole 2/16/12 2/22/12 7 100% 5 7 0
3.2 Design Requirments 2/16/12 2/18/12 3 100% 2 3 0
3.3 Bi-Weekly Report #2 2/25/12 2/29/12 5 100% 3 5 0
3.4 Oral Presentation #2 2/25/12 2/29/12 5 100% 3 5 0
4 Design Selection 3/01/12 3/14/12 14 77% 10 10 4
4.1 Select Design 3/01/12 3/04/12 4 100% 2 4 0
4.2 CAD Models 3/04/12 3/10/12 7 100% 5 7 0
4.3 FEA Analysis 3/10/12 3/14/12 5 0% 3 0 5
4.4 Bi-Weekly Report #3 3/12/12 3/14/12 3 100% 3 3 0
4.5 Oral Presentation #3 3/12/12 3/14/12 3 100% 3 3 0
5 Manufacturing Design 3/15/12 4/04/12 21 36% 15 7 14
5.1 Parts List 3/15/12 3/19/12 5 90% 3 4 1
5.2 Order Parts 3/19/12 3/21/12 3 30% 3 0 3
5.2.1 Steel for Frame 3/19/12 3/25/12 7 100% 5 7 0
5.2.2 Heating 3/19/12 3/25/12 7 0% 5 0 7
5.2.2.1 Burners 3/19/12 3/25/12 7 0% 5 0 7
5.2.2.2 Piping 3/19/12 3/25/12 7 0% 5 0 7
5.2.2.3 Pilot Lighting 3/19/12 3/25/12 7 0% 5 0 7
5.2.3 Pumps (2) 2/27/12 3/27/12 30 25% 22 7 23
5.2.4 Hoses for Pumps 3/19/12 3/25/12 7 0% 5 0 7
5.2.5 Valves 3/19/12 3/25/12 7 100% 5 7 0
5.2.6 Kettles 3/19/12 3/25/12 7 100% 5 7 0
5.2.7 Thermometers 3/19/12 3/25/12 7 100% 5 7 0
5.2.8 Heat Exhanger 3/19/12 3/25/12 7 0% 5 0 7
5.2.9 Castors 3/19/12 3/25/12 7 0% 5 0 7
5.3 Frame and Accessory Assembly 4/01/12 4/04/12 4 30% 3 1 3
5.4 Bi-Weekly Report #4 4/02/12 4/04/12 3 100% 3 3 0
5.5 Oral Presentation #4 4/02/12 4/04/12 3 100% 3 3 0