Date post: | 25-May-2018 |
Category: |
Documents |
Upload: | nguyenxuyen |
View: | 216 times |
Download: | 0 times |
Mind Over Model: Optimization of Gate Closure for the South
Hartford Conveyance and Storage Tunnel
Lawrence Soucie1*, Dominique Brocard1, Kate Mignone1, Andrew Perham2
1AECOM, Chelmsford, Massachusetts2Metropolitan District, Hartford, Connecticut
ABSTRACT
Hydraulic modeling is frequently used for planning and design of deep tunnel conveyance and
storage systems. However, care must be taken to check that the model results are reasonable and
that the end result is the best possible design. This paper illustrates some examples of how
human “thinking” can and should be used when reviewing model results. These principles are
illustrated using the design of the South Hartford Conveyance and Storage Tunnel (SHCST) in
Hartford, CT. This project includes a South Tunnel and a North Tunnel. The South Tunnel is
under construction while the North Tunnel is currently still in the planning phase. However, the
South Tunnel must work as part of an integrated system with the North Tunnel, and therefore the
analyses described in this paper included both tunnels. During wet weather, CSO / SSO flows
will be diverted into the tunnel when the capacity of the collection system is exceeded.
Hydraulic modeling was used to design and optimize the control logic for the gates that regulate
flows into the tunnel. Hand calculations of the initial model results indicated discrepancies
which were resolved by decreasing the length of the tunnel segments and time step used in the
model. The model was subsequently applied to determine the optimal gate closure based on 54
year continuous simulations. Hydraulic modelers often try to make the model completely self-
contained, so that the gates in the model automatically open and close based on calculated
parameters in the model, such as the hydraulic grade line (HGL). Analysis of the model results
showed that extreme storms in the period of record that caused the tunnel to fill would have been
predicted by modern weather forecasting days in advance. As a result, human “Predictive
Control” could be used to further optimize the operation of the tunnel by closing the CSO gates
earlier than the pre-programmed set-points used in the hydraulic model. Another aspect of the
tunnel design that involved imposing “human thinking” over raw model results was sediment
calculations. Sediment modeling was performed to estimate the distribution and quantity of
sediment in the tunnel over time. There is a lot of uncertainty in sediment modeling, and
therefore the results were checked in multiple ways, including using two different sediment
models. Through careful thinking about the model results and how the tunnel will actually be
operated, an optimal tunnel size and operating strategy was developed for the SHCST.
KEYWORDS: Hydraulic Modeling, Tunnel storage, CSO control, SSO control, tunnel
conveyance and storage
675Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
INTRODUCTION
Background
The South Hartford Conveyance and Storage Tunnel project (SHCST) is part of the Hartford, CT
Metropolitan District’s (MDC) program to comply with state and federally mandated clean water
regulations. Hartford is the capital of Connecticut, with a population of approximately 125,000
persons. The Connecticut River, which flows from north to south from near the Canadian border
into Long Island Sound, forms the city’s eastern boundary (Figure 1).
Figure 1. Location Plan
Figure 2 shows the conceptual layout of the tunnel system used for Preliminary Design. There is
a South Tunnel and a North Tunnel. The South Tunnel is under construction while the North
Tunnel is currently still in a planning phase. However, the South Tunnel must work as part of an
integrated system with the North Tunnel, and therefore the analyses described in this paper
included both tunnels.
During wet weather, CSO / SSO will be diverted into the tunnel when the capacity of the
collection system is exceeded. Diversion structures will be constructed at each CSO and SSO to
intercept overflows and divert them to near-surface consolidation sewers. These, in turn, will
discharge to vortex drop shafts which will convey the flow in a controlled manner to the deep
rock tunnel. Once flow reaches the downstream tunnel pump station, it will be pumped to the
Hartford Water Pollution Control Facility (HWPCF).
Mignone et.al. (2016) summarize the functional design of the SHCST. The main components of
the tunnel system include:
· 5.49 meter (18-foot) diameter, deep rock tunnel with 0.1% slope, 6,645 meter (21,800
feet) length for South Tunnel (final design) and 9,327 meter (30,600 feet) length for
North Tunnel (planning phase)
Hartford, CT Hartford,
676Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
· Consolidation conduits (0.61 to 1.68 meter (24 to 66 inches) in diameter, over 2,134
meters (7,000 feet) long
· Vortex drop shafts, seven in South Tunnel and eight in North Tunnel
· 2.19 cms (50 mgd) tunnel dewatering pump station
· Odor control at all potential air release points
Final design has been completed for the South Tunnel, and portions have been bid and are under
construction. The layout of the North Tunnel will likely be revised in later design phases.
Figure 2. Conceptual Layout of South Hartford CSO Storage Tunnel
Overflow Control Design Criteria
Design criteria for each overflow varies depending on either the characteristics of the overflow
(CSO or SSO) or the receiving water to which the overflow discharges (more or less sensitive).
Overflow control objectives are one of the key design criteria for the tunnel, and specific
performance measures were defined. These performance measures were assessed through the
677Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
use of collection system models and a long term model simulation based on a 54-year long
precipitation record between 1958 and 2011. Further information on the collection system
modeling approach is provided below.
SSOs are required to be eliminated. The performance measure for SSO control is that no
overflow can occur based on simulation of the 54-year period of record. There are two levels of
control for CSOs. A design storm with an 18-year return frequency was selected for CSOs
tributary to sensitive receiving waters because it would result in no more than two gate closures
during the 54-year period of record. The performance measure for the remaining CSOs, referred
to as 1-year CSOs, is that less than one overflow per year on average (i.e., less than 54 overflows
in the 54-year period of record) can occur. These performance measures are summarized in
Table 1, while the characteristics of the 1-year and 18-year design storms are summarized in
Table 2.
Table 1. Tunnel Overflow Performance Measures
SSOs CSOs Tributary to Sensitive
Receiving Waters (18-year
return frequency)
1-Year CSOs
No overflows allowed Two overflows per 54-year
period of record
Less than 54 overflows in the
54-year period of record
Table 2. Design Storm Characteristics for Initial Tunnel Sizing
Storm Event
Date Total Depth of
Rainfall DuringStorm (cm)
Peak 1-hr
intensity(cm/hr)
Storm
Duration(hrs)
1-Year Storm October 7, 1951 6.1 1.83 22
18-Year Storm May 24, 1989 12.4 4.01 16
Objective
As noted above, the tunnel is designed to store the overflow, convey it to the HWPCF, and then
treat it when there is available capacity. The tunnel is designed to provide a specified level of
service. This requires that gates be installed that are set to close at specified set-points to limit
flow into the tunnel from the CSO that discharge to non-critical areas, thereby reserving capacity
for the SSOs and CSOs in sensitive areas.
Hydraulic modeling is an important tool in planning, design, and optimization of tunnel systems.
However, care must be taken to carefully check the results and not blindly accept the model
678Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
predictions. The first part of this paper describes the various modeling tools and how they were applied. The second part of the paper discusses modeling of the gates and the initial model results, how the results were checked, and how the model was modified based on the checking. Once it was confirmed that the model produced reasonable results, the model was applied to determine the optimal gate closure based on 54 year continuous simulations. The hydraulic model can be completely self-contained, so that the gates in the model automatically open and close based on calculated parameters in the model, such as the hydraulic grade line (HGL) at a particular point in the tunnel. However, analysis of the model results showed that extreme storms in the 54-year period of record that caused the tunnel to fill would have been predicted by modern weather forecasting days in advance. The third part of this paper discusses how human “Predictive Control” could be used to further optimize the operation of the tunnel by closing the CSO gates earlier than the pre-programmed set-points based the hydraulic model. Another component of the tunnel design that involved imposing “human thinking” over raw model results was sediment calculations. Sediment modeling was performed to estimate the distribution and quantity of sediment in the tunnel over time. There is a lot of uncertainty in sediment modeling, and therefore the results were checked in multiple ways. The fourth part of this paper discusses the sediment modeling, including how the results were checked, and the final results.
HYDRAULIC MODELING TOOLS
Various hydraulic models were used to support the design of the tunnel system, and these are briefly described below.
System-Wide Hydraulic Model
A system-wide hydraulic model of the collection system, using the Stormwater Management Model (SWMM), was used to generate SSO and CSO inflow hydrographs for the 54-year period of record. The period of record flows represent predicted flow over existing or proposed
SSO/CSO control points, typically weirs or high pipe outlets. These overflow control points represent the interface point between the system-wide hydraulic model of the collection system and the tunnel system model.
Tunnel System Hydraulic Model
A detailed model of the combined South and North Tunnel system was developed using the Personal Computer Storm Water Management Model (PCSWMM) modeling software. PCSWMM is distributed by Computational Hydraulic Inc. (CHI) and is a graphical user interface for the USEPA SWMM model. This model included both the deep rock tunnel and the consolidation conduits. A schematic of the model was shown in Figure 2. This model was used to develop gate controls and adjust tunnel diameters to meet the overflow performance measures in Table 1.
679Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
An analysis of sediment deposition was conducted to estimate the quantity and distribution of
sediment build-up in the tunnel system. These analyses were conducted using the InfoWorks CS
collection system modeling software, which is distributed by Innovyze. The SWMM model of
the tunnel system was imported into InfoWorks CS, which was subsequently configured to
simulate sediment.
HYDRAULIC MODELING OF GATES
The tunnel system is designed to intercept, store, and convey SSO and CSO to the HWPCF,
where it will be treated when there is available capacity. As was noted in Table 1, there are three
types of discharges: SSOs, CSOs in sensitive areas, and CSOs in non-sensitive areas. This
requires that gates be installed at the inlets to the tunnel that are set to close at specified set-
points to limit flow into the tunnel from the CSO areas, thereby reserving capacity for the SSOs.
A typical gate chamber is shown in Figure 3. Each gate chamber will be constructed in close
proximity to an associated drop shaft and will limit CSO and SSO into the tunnel system based
on measured water level in the tunnel. Flow in excess of tunnel system capacity will be
excluded from the tunnel system using an electric motor-actuated slide gate. This slide gate
closure will cause flow to back up in the associated consolidation conduit and overflow to
receiving waters. Since slide gate closure is critical for protecting the tunnel system, redundant
electric motor-actuated slide gates will be provided.
Figure 3. Typical Gate Chamber
Sediment Deposition Model
680Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
The initial sizing of the tunnel and design of the gate control system utilized the design storms
summarized in Table 2. The tunnel sizing and gate control system were subsequently refined
based on the 54-year continuous simulations. The tunnel configuration used for the current
analysis was a diameter of 18 feet for the South Tunnel and a diameter of 17 feet for the North
Tunnel with a 0.1% slope for both tunnels.
The basic procedure followed for the initial design of the gate control system was:
1. Run the model for the 1-year design storm and note the maximum predicted HGL at the
downstream pump station connection to the HWPCF.
2. Set the 1-year CSO gates to close at the HGL determined in Step 1. This process allows
the 1-year storm to be captured by the tunnel. CSO volumes greater than the 1-year
storm elevation will be diverted to the existing CSO discharge. This process reserves
tunnel capacity for the SSOs and CSOs in sensitive areas.
3. Run the model for the 18-year design storm and note the maximum predicted HGL at the
downstream pump station connection to the HWPCF.
4. Set the gate elevations for the CSOs in sensitive areas to close at the 18-year design storm
elevation determined in Step 3. This process reserves capacity for the SSOs, which can
continue to enter the tunnel after the 1-year and 18-year CSO gates have closed.
One of the limitations of model simulations is that they may be affected by numerical
instability. To assess the impact of potential numerical instability, the model was run with 3-
second, 1-second, and 0.5 second time steps. Table 3 shows the initial model simulation
results. The continuity error is calculated internally and is the sum of the inflows divided by
the sum of the outfalls. A negative continuity error indicates more water exited the system
than entered. A low continuity error means the model has converged to a stable solution.
The continuity error for the 18-year design storm model run with the 3-second time step
model run was higher than the 1-second or 0.5 second model runs, which indicates the model
results for the 3-second run may be inaccurate.
The maximum amount of water stored in the tunnel was calculated based on the volume into
the tunnel minus the volume out. This is illustrated in Figure 4 for the 1-year design storm.
The cumulative volume into the tunnel is the sum of all the inlets and the cumulative volume
out is the volume pumped at the connection to the HWPCF. The amount of water stored is
equal to the difference, which is 244,605 m3 (64.61 MG) for the 1-year storm. Similar
calculations were made to determine the stored volume for the model runs summarized in
Table 3.
681Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
Table 3. Sensitivity of Volume Stored in Tunnel to Time Step Used in Model for Initial
Assessment
Figure 4. Example of Calculation of Volume Stored in Tunnel for 1-year Design Storm
In general, the predicted volumes stored in the tunnel are within about 500 m3 (0.14 MG) for all
three time step simulations, suggesting that the simulated volumes are not sensitive to the time
step used in the simulations. However, the difference in peak elevation is 0.69 meters (2.3 feet)
between the 1 second and 0.5 second time step model runs, which may indicate the simulated
peak elevations are sensitive to the time step.
Peak HGL
(m)
Continuity
Error (%)
Peak
HGL (m)
Continuity
Error (%)
Maximum Volume
Stored in Tunnel (m3)
Inclined Cylinder1
Volume Check (m3)
Percent
Difference (%)
3 -38.44 -0.26 -33.35 -6.24 361,986 337,644 6.7
1 -38.45 -0.24 -33.26 0.29 361,948 338,780 6.4
0.5 -38.51 0.35 -33.95 1.40 361,456 329,164 8.9
1 Hand calculations using inclined cylinder volume formula were used to check model results
Time
Step
(sec)
1-Year Design Storm 18-year Design Storm Tunnel Volume Comparison for 18-year Design Storm
682Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
Since the tunnel is essentially a large, inclined cylinder, the results from the mass balance
volume calculations should be reasonably close to hand calculations performed with the inclined
cylinder formula. The peak elevations predicted by the model were used to compute the volume
in a partially filled inclined cylinder, which was then used to assess the accuracy of the model
results. This is illustrated in Figure 5. These results are summarized in Table 3 and indicate that
the volumes predicted by the inclined cylinder calculations are about 6 to 9 % lower than the
volume calculations based on cumulative volume in minus cumulative volume out. This is
considered too great a difference and indicates the predicted peak HGL may be too low.
Additional investigations were performed to determine the reason for this outcome.
In most collection system models, the HGL versus flow rate (which causes CSOs) is the most
significant relationship. For a tunnel system, what matters most is the HGL versus volume
correlation. Collection system models need to be configured correctly to simulate the important
phenomena. The initial model configuration has model nodes only at the inlet connections and at
the downstream pump station. This results in relatively long pipe lengths ranging from 331
meters (1,086 feet) to 2,361 meters (7,746 feet). To further investigate the level of discretization
used in the model, the pipe lengths were subdivided into 76 meter (250 feet) segments and the
analysis was repeated. The results are summarized in Table 4.
Table 4. Sensitivity of Volume Stored in Tunnel to Time Step Used in Refined1 Model
Assessment
The continuity errors decrease as the time step is reduced, which is expected. These results
indicate the 0.5 second time step produces the most accurate result.
In general, the predicted HGL for the 18-year storm are 1.7 to 2.3 meters (5.7 to 7.7 feet) higher
for the refined model than the comparable elevation in the initial configuration. As a result, the
inclined cylinder volume calculations are higher and are within 1.3 % of the volumes calculated
based on the cumulative volume in minus cumulative volume out calculations. These results
suggest that the refined model is more accurate than the initial model configuration with the long
tunnel segments. Further refinement may increase the accuracy further. However, this model
was to be run for numerous 54-year continuous simulations, with each run taking approximately
45 hours. Since the maximum volume stored calculations are within 1.3% of the inclined
cylinder volume calculations, the level of accuracy was considered adequate to support the
Peak HGL
(m)
Continuity
Error (%)
Peak
HGL (m)
Continuity
Error (%)
Maximum Volume
Stored in Tunnel (m3)
Inclined Cylinder2
Volume Check (m3)
Percent
Difference (%)
3 -38.21 -1.81 -31.62 -1.07 356,573 351,766 1.3
1 -38.19 -0.63 -31.56 -0.26 356,686 351,985 1.3
0.5 -38.19 -0.55 -31.61 -0.22 356,535 351,803 1.3
1 Model refined by splitting the tunnel links into 76 meter (250 feet) segments
2 Hand calculations using inclined cylinder volume formula were used to check model results
Time
Step
(sec)
1-Year Design Storm 18-year Design Storm Tunnel Volume Comparison for 18-year Design Storm
683Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
application of the model. All additional analyses were performed using the refined version of the
model with a 0.5 second time step.
This discussion demonstrates why it is important carefully review model results. The initial
model configuration used very long tunnel segments, which appears to have resulted in water
level predictions that were lower than would be predicted based on hand calculations using an
inclined cylinder formula. Since the water levels predicted by the model were critical for the
design of the gate control strategy, it was important that the model results were reasonable.
Subdividing the tunnel segments into 76 meter (250 foot) segments and using a time step of 0.5
seconds resulted in model predications that were consistent with inclined cylinder hand
calculations, and were therefore believed to be more accurate. Tunnel segments of 152 meters
(500 feet) and 30.5 meters (100 feet) were also investigated, but the 76 meter (250 foot)
segments produced the best results.
Figure 5. Example of Inclined Cylinder Volume Calculation for Depth of 4.57 meter
(15 feet) in 5.49 meter (18-feet) Diameter Tunnel
-50.0
-48.0
-46.0
-44.0
-42.0
-40.0
-38.0
-36.0
-34.0
-32.0
-30.0
0 1,000 2,000 3,000 4,000 5,000 6,000 7,000
Ele
vati
on
(m)
Length (m)
Crown Water Surface Invert
Volume = 44,153 m3 (11.66 MG)
Depth = 4.57 m (15 feet) above invert
684Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
The refined model described above was used to design the gate control strategy. Three control
system strategies were initially considered:
· Passive control
· Direct measurement control
· Predictive control
The passive control strategy would involve the use of fixed weirs at the inlets to the tunnel and at
an emergency overflow at the downstream end. This option was eliminated because of the need
to provide different levels of service at the various inlets. It was also determined that installation
of a passive emergency overflow at the downstream end of the tunnel system was infeasible.
This alternative was not considered further. Both direct measurement and predictive control are
discussed below.
Direct Measurement Control
Direct measurement control, as used for the SHCST system, involves measuring water levels at
the downstream pump station, and then controlling the upstream gates based on the set points to
achieve the desired level of control. The gate control set points were initially determined based
on the 1-year and 18-year design storms as described above. The model was then run for the
54-year period of record (POR) which included the period from 1958 to 2011. Since the 1-year
design storm was used to set the 1-year gate closure level, it was anticipated that there would be
on the order of 54 activations during the period of record simulation. However, the POR
simulation indicated that there were 76 1-year gate activations. When the 1-year gate control
elevation was raised in an attempt to reduce the number of 1-year gate activations, the number
of 18-year gate activations increased since there was less storage available in the tunnel for the
18-year CSOs. A detailed evaluation of the 1-year design storm was conducted to determine
why using it to set the 1-year gate levels resulted in more than the expected number of 1-year
overflows during the POR simulation.
Figure 6 shows the predicted cumulative volume pumped at the pump station and the
corresponding water level at the pump station for the 1-year design storm. At the time of the
peak water level elevation of -38.19 m (-125.3 feet), the pumps had extracted 53,508 m3 (14.1
MG). The model was configured to shut the 1-year gates at an elevation of -38.19 m (-125.3
feet) and the model was run for the 18-year storm. As shown in Figure 7, the simulated HGL
reached the 1-year gate closure level at hour 17 compared to hour 40 for the 1-year design storm.
Because of the shorter pump run time, the pumps had only extracted 20,001 m3 (5.3 MG) from
the tunnel. This is about 33,334 m3 (8.8 MG) less than the 53,508 m3 (14.1 MG) for the 1-year
design storm at the peak HGL. The reason for this difference is the shape of the 1-year design
storm hydrograph. The 1-year storm begins with low rainfall rates, during which time the pumps
are able to keep up with the incoming flows. As a result, the pumps are able to remove more
water during the 1-year design storm than during the 18-year design storm. These results show
that the 1-year design storm is not a suitable surrogate event for determining the elevation at
which to close the 1-year CSO gates. It was determined from these model simulation results that
GATE CONTROL STRATEGY
685Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
Figure 6. Water Levels at Pump Station and Cumulative Volume Pumped for 1-Year
Storm
an iterative approach using the 54-year POR would be necessary to size the tunnel and establish
the 1-year and 18-year gate closure levels.
Multiple 54-year POR simulations were run with various 1-year CSO gate closure elevations
in order to determine the 1-year gate closure elevation that would result in 53 overflows during
the period of record. The 1-year gate closure elevation determined from this iterative POR
approach was higher than the 1-year gate closure level determined from the 1-year design
storm due to the shape of the 1-year design storm. The higher 1-year gate control level
resulted in less storage being available for the 18-year CSOs. As the POR analysis progressed,
it became apparent that it wasn’t feasible to meet performance goals for the 18-year CSOs with
a direct measurement control approach without increasing the size of the tunnel. Accordingly,
evaluations of a simple predictive control approach were conducted.
686Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
Figure 7. Water Levels at Pump Station and Cumulative Volume Pumped for 18-Year
Storm
Predictive Control
Traditional predictive control strategies use weather forecasting along with rainfall-overflow
volume relationships derived from hydrologic/hydraulic models, plus level monitoring, to
assess available tunnel volume. Instead of a more complex, traditional predictive control
system, a simple predictive control system was developed and modeled in order to meet the
specified overflow performance measures. Essentially, the operators would watch the
weather forecast. When very large and readily predictable storm events were forecasted (i.e.,
predicted total rainfall depth greater than a threshold value), operators would indicate this to
the control system. This could be as simple as clicking a selection on the appropriate
Supervisory Control and Data Acquisition (SCADA) screen. With this entry, the slide gates
associated with the 1-year CSOs would close at a lower downstream tunnel water level than
normal, preserving tunnel volume for the 18-year CSOs associated with sensitive receiving
waters and the SSOs. This would not impact the key performance measure for the 1-year
CSOs of less than one overflow per year on average because the gates would have closed
during these large storms even if based solely on downstream tunnel level. Although this
control approach would not increase the number of overflows from the 1-year CSOs in the
687Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
54-year period of record, it would increase the overflow volume from the 1-year CSOs
during large events when the 1-year CSO gates would close sooner than the pre-programmed
set points. But, by closing at a lower than normal downstream tunnel water level, overflow
performance measures for the 18-year CSOs associated with sensitive receiving waters
would be met in all but the very largest storm events in the 54-year period of record. In
addition, performance measures for the SSOs would be met for all storms in the 54-year
period of record.
To investigate the practicality of simple predictive control, the predictability of storms that
would cause closure of the 18-year gates was assessed. This assessment consisted of first
assuming tunnel diameters for the North and South tunnel segments. For the South tunnel
segment, a constant diameter of 5.49 m (18 feet) was used. For the North tunnel segment,
diameters of 4.88, 5.18, and 5.49 m (16, 17, and 18 feet) were assessed. For each tunnel
system size (16N, 18S; 17N, 18S; and 18N, 18S) the 1-year gate closure elevation required to
achieve less than 54 1-year CSO discharges in the 54-year POR was determined. Using this 1-
year gate closure elevation, the corresponding number of 18-year gate closures and the storms
that resulted in these closures were determined. An assessment was then conducted to
determine whether each storm that caused an 18-year gate closure could have been predicted.
In order to meet the performance criterion for number of 18-year gate closures in the 54 year
POR, the analysis had to result in fewer than three 18-year gate closure storms that could not
be predicted.
The results of this iterative assessment are presented in Table 5. In summary, it was determined
that both the North and South tunnel segments would have to be 5.49 m (18-feet) in diameter. It
was also determined that, for large, predictable storm events, the 1-year CSO gates should close
when the water level elevation at the pump station reaches -39.32 m (-129.00 feet.) and the 18-
year CSO gates should close when the water level elevation at the pump station reaches -34.29
m (-112.50 ft.). Finally, it was determined that the 1-year CSO gates should re-open when the
water level elevation reaches -45.69 m (-149.89 ft.). These results will need to be updated for
the new boundary conditions for the North Tunnel, as the North Tunnel design progresses.
Key observations from inspection of Table 5 are summarized below:
· With the 5.49 m (18 ft.) South Tunnel and 4.88 m (16 ft.) North Tunnel configuration, a
total of 15 18-year CSO gate closures were predicted. Of these, at least six were judged
to be “unpredictable storms”, for which the 18-year CSO gates would have closed even
if simple predictive control was used.
· With the 5.49 m (18 ft.) South Tunnel and 5.18 (17 ft.) North Tunnel configuration, a
total of 11 18-year CSO gate closures were predicted. Of these, at least four were judged
to be unpredictable storms for which the 18-year CSO gates would have closed. Thus,
the 5.49 m (18 ft.) South Tunnel and 5.18 (17 ft.) North Tunnel configuration also failed
to meet the performance requirement for 18-year CSO gate closures.
· With the 5.49 m (18 ft.) South Tunnel and 5.49 m (18 ft.) North Tunnel configuration,
seven 18-year CSO gate closures were predicted. Of these, only two were judged to be
688Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
associated with unpredictable storm events. Thus, the 5.49 m (18 ft.) South Tunnel and
5.49 m (18 ft.) North Tunnel configuration would meet the performance requirement for
the 18-year CSO gates.
· If simple predictive control was not used, the performance requirement for the 18-year
CSO gates would not be met, even with the 5.49 m (18 ft.) South Tunnel and 5.49 m (18
ft.) North Tunnel configuration.
Table 5. Results of Simple Predictive
ControlAnalysis
Tunnel
Diameters
1-year gate
Closure
Level1
Number of
18-year CSO
Gate
Closures
18-year CSO
gate Closure
Storms
Assessment of Storm
Predictability
No. of
Unpredictable
Storms
18S / 16N -125.0 15 Oct 24,1959
Sep 12,1960Oct 03, 1979Jun 05, 1982Aug 09, 1982Aug 11, 1985May 24, 1989Sep 16, 1999
June 17, 2001Aug 21, 2004July 27, 2005Oct 14, 2005Sep 06, 2008Aug 28, 2011Sep 08, 2011
No- Long Duration
Yes - HurricaneNo - TornadoYes – Flood
No-Summer Storm
No - ThunderstormYes - Big StormYes – HurricaneYes- Big Storm
No –Thunderstorm
No – ThunderstormYes -Tropical StormYes- Tropical Storm
Yes – Hurricane
Yes – Hurricane
6
18S / 17N -127.0 11 Oct 24, 1959
Sep 12,1960Oct 03, 1979Jun 06, 1982Aug 11, 1985May 24, 1989
Sep 16, 1999Aug 21, 2004Oct 14, 2005Sep 06, 2008Sep 08, 2011
No – Long Duration
Yes - HurricaneNo – TornadoYes - Flood
No - Thunderstorm
Yes - Big StormYes - Hurricane
No – Thunderstorm
Yes - Tropical StormYes -Tropical Storm
Yes – Hurricane
4
18S / 18N -129.0 7 Oct 24, 1959Sep 12, 1960Aug 11, 1985
May 24, 1989 Oct 15, 2005Sep 06, 2008Sep 08-, 2011
No – Long DurationYes – HurricaneNo - Thunderstorm
Yes - Big StormYes -Tropical StormYes - Tropical StormYes – Hurricane
2
Notes: 1. Level resulting in 53 closures of the 1-year CSO gates
689Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
Perspective on Predicted Tunnel System Performance
There is a certain degree of uncertainty in the predicted tunnel system performance presented
above. Factors that should be taken into account with respect to the 54-year period of record
results are:
· The 54-year period of record modeling results show long periods with no predicted gate
activations for CSOs associated with sensitive receiving waters. For example, for the
18S / 18N configuration, no activations of these gates are predicted for the 25-year period
from 1960 to 1985. Then, five activations are predicted in the next 25-year period. This
means that it will be important for project stakeholders to note that an assessment of the
system’s ability to meet overflow performance measures cannot be made until many
years of operation have passed.
· Only one rain gage was available for the 54-year period of record rainfall data. Many
high-intensity summer storm events picked up by that single gage, and applied uniformly
over the study area, likely only impacted a limited portion of the study area.
Accordingly, high-intensity summer storm events may be less likely to cause the tunnel
system to fill than predicted.
· The system-wide hydraulic model does not take into account inflow restrictions. For
example, catch basin inlet grates have a limited capacity to admit high rates of runoff
during high intensity storm events. Thus, it is possible that peak flows entering the
tunnel may be less than modeled.
· The results are based on a historical period of record which will not re-occur in the
future. In particular, global climate change has been predicted to result in a larger
number of intense storms. Thus, some degree of conservatism is warranted in the design.
As indicated in the bulleted text above, in some cases, the inherent uncertainty in the analyses
performed leads to a conservative (over-designed) condition. This is considered appropriate
given the need to attain regulatory compliance with a costly built solution. It also indicates that
optimization of tunnel system controls, 1-year CSO gate closure elevations in particular, can
likely be improved over time based on actual operating experience.
The simple, predictive control approach described above is an example of not blindly accepting
pre-programmed gate control set points based on model output and then applying them for all
situations. Instead, operators inject “human” thought into the control system, and over-ride the
normal control gate set points based on modern weather forecasts. In so doing, they are able to
operate the tunnel system more efficiency than would otherwise be the case using only pre-
programmed set points.
690Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
SEDIMENT DEPOSITION INVESTIGATIONS
Another aspect of the tunnel design that involved imposing “human thinking” over raw model
results was sediment calculations. Sediment modeling was performed to estimate the
distribution and quantity of sediment in the tunnel over time. The SWMM model used for the
hydraulic analyses does not support sediment calculations. Therefore, the SWMM model was
imported into the InfoWorks CS modeling software. InfoWorks CS is a collection system
modeling software distributed by Innovyze which includes three sediment transport algorithims:
· KUL
· Ackers-White
· Velikanov
The KUL methodology did not contain sufficient information to apply it for the SHCST, and
therefore it was not used.
The Ackers-White sediment model is the default sediment model used in the InfoWorks CS
Software. This algorithm computes the maximum concentration of sediment that can be held
within the flow. This is defined as the “carrying capacity”. If the actual concentration is greater
than the carrying capacity, then deposition occurs, and if the actual concentration is less than the
carrying capacity, then bed erosion occurs. Erosion is assumed to occur instantaneously, while
the rate of deposition is a function of the settling velocity.
The Velikanov sediment model uses two total suspended solids (TSS) concentrations in the
water (Cmin and Cmax). If the flow concentration is below Cmin then erosion occurs to achieve
Cmin if possible. If the flow concentration is above Cmax then deposition occurs to achieve Cmax
if possible.
The sediment analysis was performed using both the Ackers-White and Velikanov algorithms,
and the variation in the results provides an indication of the uncertainty that is inherent in these
calculations.
Model Setup
A schematic of the InfoWorks CS model is shown in Figure 8. Sediment transport in the North
Tunnel System may impact the South Tunnel System, and therefore the two tunnels were
analyzed as part of an integrated system. The InfoWorks model was based on the refined version
of the SWMM model with 5.49 m (18 feet) diameter tunnel reaches subdivided into 76 m (250
ft.) segments. Flow inputs to the tunnel were extracted from the SWMM model and were added
at the corresponding location in the InfoWorks model. The pump station at the HWPCF was
configured the same as in the SWMM model.
The InfoWorks software allows two sediment fractions to be simulated, such as organic (volatile
fraction) and inorganic (grit). Table 6 provides a summary of the sediment characteristics used
in the modeling. Information from previous studies indicated the average TSS were 142 mg/L.
Based on typical composition of untreated domestic wastewater (Metcalf & Eddy, 1991), the
TSS concentration of 142 mg/l was divided into an organic fraction of 106 mg/l and an inorganic
691Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
Figure 8. Schematic of InfoWorks CS Sediment Model
Table 6. Summary of Sediment Characteristics for Settlement Modeling
Sediment
Fraction CSO SSO Particle Size
Specific
Gravity
Inorganic 36 mg/L None 0.75 mm 2.6
Organic 106 mg/L 130 mg/L 0.04 mm 1.4
fraction of 36 mg/l. For flows entering tunnel dropshafts with CSO flows, both fractions were
applied. However, for SSO inflows, only the organic fraction was used. An inorganic fraction
was included in the TSS from CSOs to reflect roadway constituents (i.e. sand and grit) that could
wash off and become part of the solids matrix in CSOs. Other parameters required for the
sediment modeling include the median particle size, and specific gravity of the inorganic (grit)
and organic (sanitary solids), and these were obtained from CIRIA (1996).
692Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
Sensitivity Testing
Experience has shown that sediment modeling can be sensitive to the time step used in the
model. One of the ways that the results of sediment models can be assessed is by computing the
mass balance. This involves extracting from the simulation results the mass of TSS entering the
tunnel, the mass leaving the system through the pump station, and the mass that accumulates
(deposits) in the tunnel. Multiple model runs for the year 2002 were performed using both the
Ackers-White and Velikanov sediment modeling algorithms with various time steps. The mass
in for the year 2002 were the same for all of the model runs and was equal to 237,324 kg for the
organic fraction, and 80,222 kg for the inorganic fraction (total 317,546 kg). The model results
for the mass out, accumulation, and mass balance are summarized in Table 7.
As can be seen from the results in Table 7, a much greater fraction of the TSS is accumulating in
the tunnel for the Ackers-White sediment model than for the Velikanov. The model results
indicate the total mass balance errors generally decrease as the time step decreases for the
Ackers-White model, and increase for the Velikanov model. Generally, a lower time step results
in an improved mass balance. It is not known why the opposite occurred for the Velikanov
model. In this respect, the sensitivity results were inconclusive. Both sediment models were
used for the full analysis to provide an estimate of the uncertainty inherent in these types of
analyses.
Table 7. Results of Sediment Sensitivity Analysis
Sediment Model Results
Model simulations were conducted over the most recent 10 years for which flow data were
available (2002 – 2011), and the results are summarized in Table 8. Long term simulations are
warranted for sedimentation modeling as accumulation occurs gradually and erosion tends to
occur during larger storms.
It can be noted from the results in Table 8 that the net accumulation based on the Ackers-White
sediment model for the second 5-year period (years 6 through 10) was approximately half of the
accumulation for the first 5-year period, suggesting that the rate of sediment accumulation may
decrease. In contrast to the Ackers-White sediment model, the rate of sediment accumulation
based on the Velikanov sediment model is roughly the same for the two 5-year periods.
Time
Sediment Step Organic Inorganic Total Organic Inorganic Total Organic Inorganic Total
Model (sec) SF1 (kg) SF2 (kg) (kg) SF1 (kg) SF2 (kg) (kg) SF1 (%) SF2 (%) (%)
Ackers-White 60 158,118 368 158,486 42,767 70,250 113,018 15.4 12.0 14.5
Ackers-White 30 168,109 197 168,305 45,219 84,187 129,406 10.1 (5.2) 6.2
Ackers-White 10 175,786 221 176,007 49,271 73,312 122,583 5.2 8.3 6.0
Ackers-White 0.5 177,541 216 177,757 50,279 71,099 121,378 4.0 11.1 5.8
Velikanov 60 220,881 68,155 289,036 8,352 21,558 29,911 3.4 (11.8) (0.4)
Velikanov 30 225,928 65,282 291,210 6,697 18,734 25,431 2.0 (4.7) 0.3
Velikanov 10 226,541 47,376 273,916 8,222 28,424 36,646 1.1 5.5 2.2
Velikanov 0.5 227,227 47,113 274,341 7,942 28,704 36,646 0.9 5.5 2.1
Mass Out Accumulation Mass Balance
693Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
Table 8: Predicted Sediment Accumulation and Volume
Year Component Sediment Model Results
Ackers-White Velikanov
End of
Year 5
Mass In (kg) 2,478,900 2,478,900
Accumulation (kg) 651,900 288,500
Percentage of Mass Inflow Predicted to
Accumulate 26% 12%
Bulk Density (kg/m3) 1,595 1,662
Total Volume of Sediment (m3) 409 174
Mass Balance (%) 5.8 2.0
End of
Year 10
Mass In (kg) 5,006,300 5,006,300
Accumulation (kg) 973,800 586,700
Net Accumulation (kg) 321,900 298,200
Percentage of Mass Inflow Predicted to
Accumulate 19% 12%
Bulk Density (kg/m3) 1,640 1,650
Total Volume of Sediment (m3) 594 356
Mass Balance (%) 5.4 2.0
Assuming a porosity of 30%, the bulk density of the sediment was calculated for the various
simulations, and results are presented in Table 8. In general, the bulk density is on the order of
1,600 kg/m3 (99.7 lb/ft3). The mass balance errors were about 5.5 % for the Ackers-White
sediment model and 2% for the Velikanov sediment model. A positive mass balance error
indicates that more TSS entered the tunnel than accounted for by the mass existing at the pump
station and the mass that accumulated in the tunnel. Thus, the actual accumulations in the tunnel
could be marginally higher. However, the mass balance errors are considered within acceptable
limits for this type of analysis.
Figures 9 and 10 shows the sediment depth distribution in the South tunnel after 5 and 10 years
for the Ackers-White and Velikanov models, respectively. The sediment depth for the North
Tunnel is similar. In general, higher sediment accumulations are predicted to occur at the
downstream end of the South Tunnel. This follows logically since water will back up at this
location and provide the greatest opportunity for sediments to deposit. The sediment modeling
also predicts that the depth of sediment is lower just downstream of the S-19 and S-21 Gate
connection (refer to Figure 8). This is believed to occur because the North Tunnel connects at
this location, and the additional flow from the North Tunnel reduces the sediment deposition.
The maximum depth of sediment after 10-years is predicted to be less than about 0.3 meters (one
foot) for both the Ackers-White and Velikanov sediment models.
694Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
Figure 9. Predicted Sediment Depth for Ackers-White Sediment Model
Figure 10. Predicted Sediment Depth for Velikanov Sediment Model
0
10
20
30
40
50
60
70
80
90
0 1,000 2,000 3,000 4,000 5,000 6,000
Sed
imen
tD
epth
(cm
)
Distance from Upstream End of Tunnel (meters)
End of 5 Year
End of 10 Year
MACPGate
Franklin @
Standish
CTS3 S-19 &
S-21
Douglas and
PrestonHanmer
Tredeau
Pump
StationNTS
and
New
Britain
South Tunnel
0
10
20
30
40
50
60
70
80
90
0 1,000 2,000 3,000 4,000 5,000 6,000
Sed
imen
tD
epth
(cm
)
Distance from Upstream End of Tunnel (meters)
End of 5 Year
End of 10 Year
MACPGate
Franklin @
Standish
CTS3 S-19 &
S-21
Douglas and
PrestonHanmer
Tredeau
Pump
StationNTS
and
New
Britain
South Tunnel
695Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
As these results show, there is a lot of uncertainty with modeling of the sediment. The sediment
models produce results, and the challenge then becomes how to gain confidence in the
predictions. Some of the tools that were employed for the SCHST sediment modeling include
time step sensitivity testing, comparing results from two different sediment modeling algorithms,
and mass balance analyses. Based on these analyses, the general magnitude of the potential
sediment deposition was assessed and is believed to be reasonable.
CONCLUSIONS AND RECOMMENDATIONS
Hydraulic modeling is an important component in the planning, design, and optimization of deep
tunnel systems such as the SHCST. However, the model predictions have to be checked, and
challenged, in order to gain confidence in the results. Some of the ways this was done for the
SHCST include:
Compare Model Results for Different Time Steps
Numerical models can be unstable. In general, the longer the time step, the faster the model runs
and the more susceptible the results are to numerical instability. The instabilities may be
difficult to detect in a 54-year simulation. Time step sensitivity testing was performed on shorter
runs which indicated a 0.5 second time step produced the most accurate result.
Recommendation: An assessment of the time step should be made during model development
to confirm the model has time step independence, which means the model results are not
significantly affected by the selection of the time step used in the model.
Compare Volume Stored with Hand Calculations
The maximum volume of water stored in the tunnel was computed based on a mass balance
analysis using flow volume into the tunnel minus flow volume exiting the tunnel. The peak
hydraulic grade predicted by the model was then used to compute the volume of water stored in
the tunnel using hand calculations based on an inclined cylinder formula. The initial results
indicated a significant discrepancy (6 to 9 %) for the initial model configurations which utilized
relatively long tunnel segments. The discrepancy was reduced to 1.3 % by subdividing the
tunnel reaches into smaller segments.
Recommendation: Model results should be checked against hand calculations whenever
possible.
Recommendation: When applying SWMM for large diameter, relatively flat pipes, such as a
tunnel, care should be taken to avoid excessively long segments. If necessary, long pipes should
be subdivided.
Compare Design Storm and Continuous Simulation Results
Initial sizing of the tunnel was performed using design storms selected from the historical period
of record. Gate control and tunnel sizing for a 1-year storm should have, in theory, resulted in
696Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
about 54 overflows over a 54-year period. This was not the case for the SHCST because the
shape of the 1-year design storm used for the SHCST was not typical. The storm started out
slow and stopped, which allowed pumps to dewater the tunnel. When the storm picked up again,
it was essentially a new storm with a smaller volume than a 1-year design storm.
Recommendation. Confirm design storm simulation results with continuous simulations
whenever possible.
Use Predictive Control to Further Optimize Tunnel Performance
The 54-year period of record simulations resulted in too many CSOs in sensitive areas, which are
only allowed to overflow on average once every 18-years or twice in the 54-year period of
record. Iterative model simulations indicated that it was not possible to meet the CSO control
objectives with a pre-programmed gate control system without increasing the size of the tunnel.
However, many of the storms that resulted in CSOs in sensitive areas could have been predicted
days in advance by modern weather forecasts. As a result, human “Predictive Control” could be
used to further optimize the operation of the tunnel by closing the CSO gates earlier than the pre-
programmed set-points based the hydraulic model.
Recommendation: Don’t rely solely on model results for design and operations. Look for
opportunities to inject human thought, such as the application of Predictive Control, into the
process.
Check Sediment Calculations Carefully
Sediment calculations are inherently uncertain. Some of the tools that were employed for the
SHCST sediment modeling to check the results included time step sensitivity testing, comparing
results from two different sediment modeling algorithms, and mass balance analyses. The time
step testing established that a 0.5 second time step was appropriate. The results from the
different sediment modeling algorithms established the range of variability in these types of
analyses and the mass balance analyses provided a measure of the accuracy. Based on these
analyses, the general magnitude of the potential sediment deposition was assessed and was
determined to be minimal.
Recommendation: When performing sediment calculations, use multiple sediment models,
conduct time step testing, and check the mass balance.
It is hoped that the conclusions and recommendations presented above will be valuable to others
facing the design of similar tunnel systems to control wet weather overflows. Each tunnel
design should be carefully considered in terms of the site-specific overflow performance targets
and design criteria.
REFERENCES
AECOM in association with Black and Veatch, February 2013. South Hartford Conveyance &
Storage Tunnel, Hartford Connecticut. Final Basis of Design Report.
697Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017
CIRIA, 1996, Report 141: Design of Sewers to Control Sediment Problems, Construction
Industry Research and Information Association, London.
Hartford MDC and CDM Smith, December 4, 2014. Long-Term Combined Sewer Overflow
Control Plan 2012 Update, The Metropolitan District, Hartford, Connecticut.
Metcalf & Eddy, Inc. 1991, Wastewater Engineering: Treatment, Disposal, and Reuse, Third
Edition, McGraw-Hill, Inc. New York.
Mignone, T. K, S. Craig, G. Heath, and J. Sullivan (2016), Functional Design for the South
Hartford CSO Storage Tunnel, Presented at Water Environment Federation Collection Systems
Specialty Conference, May 2, 2016.
698Copyright© 2017 by the Water Environment Federation
WEF Collection Systems Conference 2017