+ All Categories
Home > Documents > Mine Tour – Project Overview October 2,...

Mine Tour – Project Overview October 2,...

Date post: 27-May-2018
Category:
Upload: ngodieu
View: 216 times
Download: 0 times
Share this document with a friend
43
© 2008 Katanga Mining Limited Trading symbol: KAT.TO October 2, 2008 Mine Tour – Project Overview
Transcript

© 2008 Katanga Mining Limited Trading symbol: KAT.TO

October 2, 2008Mine Tour – Project Overview

22

This management presentation contains “forward-looking statements”, within the meaning of the United States Private Securities Litigation Reform Act of 1995 and similar Canadian legislation, concerning the business, operations and financial performance and condition of Katanga. Forward-looking statements include, but are not limited to, statements with respect to anticipated developments in Katanga’s operations in future periods; planned exploration activities; the adequacy of Katanga’s financial resources and other events or conditions that may occur in the future; estimated production and synergies; the ability of Katanga to become a significant low cost copper/cobalt company; the ability of Katanga to continue to create value for its shareholders; the ability of Katanga to meet expected financing requirements; the future price of copper and cobalt; the estimation of mineral reserves and resources; the realization of mineral reserve estimates; the timing and amount of estimated future production; costs of production; capital expenditures; permitting time lines and permitting, mining or processing issues; currency exchange rate fluctuations; government regulation of mining operations; information concerning the interpretation of drill results; success of exploration activities; environmental risks; unanticipated reclamation expenses; title disputes or claims; and limitations on insurance coverage. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “plans”, “expects” or “does not expect”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates” or “does not anticipate”, or “believes”, or variations of such words and phrases or state that certain actions, events or results “may”, “could”, “would”, “might”, “will” or “will be taken”, “occur” or “be achieved”. Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Katanga to be materially different from those expressed or implied by such forward-looking statements, including but not limited to risks related to: unexpected events during construction, expansion and start-up; variations in ore grade, tonnes mined; delay or failure to receive board or government approvals; timing and availability of external financing on acceptable terms; risks related to international operations; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of copper and cobalt; possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; political unrest and insurrection; acts of terrorism; accidents, labour disputes and other risks of the mining industry; delays in the completion of development or construction activities, as well as those factors discussed in or referred to in the current annual Management’s Discussion and Analysis and current Annual Information Form of Katanga filed with the securities regulatory authorities in Canada and available at www.sedar.com. Although management of Katanga has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Katanga does not undertakes to update any forward-looking statements that are incorporated herein, except in accordance with applicable securities laws.

Cautionary and Forward-Looking Statements

3

10 Years Invested in the DRC

Council of Ministers and Presidential

approval of JV

Kamoto JV Agreement

entered into after 12 months of negotiation

New Mining Code published

Findings of DRC mining contract review received

Democratic Presidential

elections

Katanga milestones DRC milestones

First contact made with DRC

to explore opportunities

Kinross Forrest Limited JV

formed

JV assumes site mgmt; initial

financing & path to Phase I

Phase I completed and

first copper produced

1997 Oct 2001 Jul 2002 Feb 2004 Jul/Aug 2005 Jul 2006 Nov 2006 Dec 2007 Jan 2008 Feb 2008 Jul 2008

Merger with Nikanor

completed

MoU signed between

Gécamines and KFL Limited &

GEC

44

From Mine to Metal

Underground Mining

Cobalt metal

Milling

Flotation

Open Pit Mining

Copper cathode

5

Company Highlights

Major single-site operation in the DRC

Producing refined copper cathode and cobalt metal

Commercial production achieved in 2Q 2008; generating operating cash flow

239Mt M&I resource @ 4.45% Cu and 0.44% Co

Target >300ktpa Cu and >30ktpa Co production in 2011

Mine life 40+ years

75-25 joint venture with Gécamines (state-owned mining company)

6

0% 1% 2% 3% 4% 5% 6%

KatangaTenke

Mount IsaTaimyr Peninsula

AntaminaOlympic Dam

OK TediCollahuasiGrasberg

EscondidaEl Teniente

Codelco NorteLos Pelambres

Bingham CanyonLos Bronces

AlumbreraBatu HijauToquepala

Morenci

Ore Grade - % M&I Contained Copper0 500 1,000 1,500

EscondidaGrasberg

Codelco NorteMount IsaAntaminaKatanga

CollahuasiEl Teniente

Bingham CanyonMorenci

Los PelambresTaimyr Peninsula

Batu HijauAlumbrera

Olympic DamOK Tedi

Los BroncesToquepala

Tenke

Copper Equivalent Production (Kt)

Leading Global Mines by Production1

…Ranked by Grade2,3

1. Based on 2007 production, except Katanga, Tenke and Taimyr Peninsula (2011 forecasts: 300 Kt Cu and 30 Kt Co, 115kt Cu and 8Kt Co, 2006 figures respectively). Price assumptions used to convert production to copper equivalent: Cu $1.60/lb, Co $10.00/lb, Zn $0.75/lb, Ag $11.00/Oz, Au $700/Oz, Mo $12.00/lb.

2. Katanga figure includes all deposits.3. Based on reported Measured and Indicated resource copper grades. Source: CIBC World Markets

World-Scale Producer

Katanga

Katanga

7

Strengthened Management Team

Kim FreemanSenior Vice President, Project Development

Jean-Louis LabelleDirector, Senior Project Manager

John RossDirector, Metallurgy

Brian BarberConstruction Manager

Steve Jones CFO

Adrian De FreitasDirector, Operations &Acting GM, Operations

8

20 km

3. KOV open pit

mine

1. Luilu Met. Plant /

Planned SX-EW refinery

Mine to Refinery on One Site

A. Dikuluwe open pit (O/P) B. Mashamba West (O/P) C. Mashamba East (O/P)D. Musonie-T-17 (O/P) E. Kananga (O/P) F. Tilwezembe (O/P)G. Kolwezi Concentrator

Approximately 5 km

A B C

F

D

E

G

1

2 3

4

2. Kamoto Concentrator

4. Kamotounderground

mine

9

Reserves & Resources

10

High-Grade Reserves & Resources

Reported under Canadian NI 43-101 standards of disclosure for mineral projects. Sources: Katanga June 2006 Feasibility Study & NI 43-101 and press release dated 22/02/07; Nikanor November 2007 Revised Independent Technical Report.

400

0.38

740

0.43

CoCuProven and Probable Mineral Reserves

310

0.48

107,000Ore Tonnes (’000s)

66,000Ore Tonnes (’000s)

3.3Contained Metal Grade %

3,500Contained Metal Tonnes (000s)

3.5Contained Metal Grade %

2,300Contained Metal Tonnes (000s)

Measured and Indicated Mineral Resources

172,000Ore Tonnes (000s)

4.8Contained Metal Grade %

8,200Contained Metal Tonnes (000s)

Inferred Mineral Resources

Updated Reserves & Resources Statement to be published as part of expansion feasibility study

11

Reserve and Resource Estimate by Mine

0.38%3.34%107,782Total Inferred Mineral Resources

Inferred Mineral Resources

0.65%1.59%13,100Tilwezembe0.74%1.44%4,000Kananga West0.32%3.56%71,200KOV

0.40%5.33%126,900KOV

Resource Estimate by Mine

0.73%0.58%0.15%

0.43%

0.48%0.87%0.45%

0.48%0.48%0.54%0.48%

Cobalt Grade %

5.28%

4.13%

3.85%Copper Grade %Ore Tonnes (000s)Proven and Probable Mineral Reserves

4.79%172,848

3.54%66,297

2.58%2.14%

2.28%3.61%

2.79%3.81%

11,826Kamoto

45,507Kamoto

5,336Mashamba East2,320Musonoie-T17

1,501T1719,289Mashamba East

Total Proven & Probable Mineral Reserves

21,227Kamoto5,985T17

18,736Mashamba East

Total Indicated Mineral Resources

Mineral reserves are separate from mineral resources.Reported under Canadian NI 43-101 standards of disclosure for mineral projects. Sources: Katanga June 2006 Feasibility Study & NI 43-101 and press release dated 22/02/07; Nikanor November 2007 Revised Independent Technical Report.

Updated Reserves & Resources Statement to be published as part of expansion feasibility study

12

Geology

13

Kamoto Underground

2007 Reserve Extraction Plan

14

KOV and Kamoto East Pits

0 1000 2000

1400

1000

Kamoto pit Kov pit

S N

Cut 3Cut 7

Geotechnical units, Cut 3 and Cut 7

LEGEND:

RGSCMNSDSOREBDYRSCRATL

14

15

Olivera Orebody

Virgule Orebody

Kamoto East Orebody

Final Phase 1

TopoPhase 2

KOV Ore Body / Pit Cross Section

16

Project Overview

1717

Kamoto Phase II Rehabilitation

KTC:– 3rd cascade mill– 58 flotation cells

Luilu:– New roaster– Doubling leaching & electro-winning

capacityWork completed to date:– 12 of 14 leach & CCD tanks– 18 of 54 electro-winning cells– 58 of 58 float cells

Piling of roaster line 2 starting in August

Production capacity of 70,000 tpa Cu and 3,000 tpa CoCompletion scheduled for end 2008

18

Expansion Feasibility Study

Scheduled for completion during October 2008

Mineral resource evaluations to be updated to comply with NI 43-101

Project capital and operating costs to be updated

Assessment of the environmental issues related to the combined operations

sufficient to complete a revised EIS/EMPP

1919

KOV Open Pit

Oxide:Sulphide ratio at KOV calculated to be 57:43

Equipment arriving on site and commissioning ongoing

Fleet and workshop to be fully operational 4Q 2008

20

1275

Lining a Decant Pond

Silt Dam

Pumping starts fourth quarter 2008

KOV Dewatering Plan

21

Greenfield SX/EW

Roaster

High voltage yard

Acid plant

Cobalt area

Leach tanks & CCD circuitSX/EW module 3

Fire water pond

SX/EW module 1

SX/EW module 2

Existing Luilu RefineryHigher grade refined metal produced

Increased Cu & Co recoveries

Phased modular approach

1 Module ~ 80ktpa Cu

2222

Key Project Milestones*

*Based on scoping study. Feasibility study will finalize schedule.1. Current estimate of capex schedule for Kamoto project. Phases III & IV are being reviewed as part of the Expansion Feasibility Study

Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1

2008 2009 2010Task 2011

Kamoto phase II 1

Kamoto phase III 1

Kamoto phase IV 1

Expansion Feasibility Study

Module 1 SX/EW Construction

Mining of KOV Begins

Acid Plant Commissioning

New Cobalt Plant Commissioning

Module 2 SX/EW Construction

Capex $152 m

Est. Capex $124 m

Est. Capex $64 m

2323

Phased Production Growth

0

50

100

150

200

250

300

350

2008 2009 2010 2011

Tonn

es C

oppe

r ('0

00s) Copper - new refinery

Copper - refurbished plant

New feasibility study and mine plan available during Oct 2008 will redefine the production profile

0

5

10

15

20

25

30

35

2008 2009 2010 2011

Tonn

es C

obal

t ('0

00s) Cobalt - new refinery

Cobalt - refurbished plant

2424

2008 Expected Quarterly Production

9,800

7,450

6,150

4,115

0

2,000

4,000

6,000

8,000

10,000

12,000

1QA 2QA 3QE 4QE

Tonn

es C

oppe

r

Payable Copper in ConcentrateCopper Cathode

1,125

875

585

135

0

200

400

600

800

1,000

1,200

1QA 2QA 3QE 4QE

Tonn

es C

obal

t

Payable Cobalt in ConcentrateCobalt Metal

2Q copper production on forecast, but 2H 2008 forecast lowered

2008 expected payable production of 27,500t copper & 2,700t cobalt

Previous forecast 33,500t payable copper & 2,900t payable cobalt

Cobalt Residue Belt Filter

2525

2008 Expected Production

KTC Copper Concentrate (tonnes) – feed to Luilu 106,000

Copper cathode (pounds) 54 million

Cobalt metal (pounds) 2.4 million

KZC Cobalt Concentrate (tonnes) 54,000

Payable copper (pounds) 6.3 million

Payable cobalt (pounds) 3.5 million

Total Payable copper (pounds) 60.3 million

Total Payable cobalt (pounds) 5.9 million

26

Financial Position at June 30, 2008

2009+ GlencoreMarket pricing90% payable on leaving site

2009 onwards capex spend to be determined by expansion feasibility study

100% Offtake agreements in place

2008 LN Metals

Capital expenditure

US$150m Glencore convertible loan

US$125m in corporate debentures

Low debt level

US$352m at June 30, 2008

Net cash position

First draw planned in 1H 2009

Facility currently under discussion:up to $550 million

Future needs offset by:Current operating cash flowMetal prices remaining strong

Financial scope to be determined following completion of expansion feasibility study

Financing initiative

27

Mining Lease & Contract Review

Memorandum of Understanding with Gécamines signed, July 31

Merging DCP and KCC Joint Ventures

Mining licence to be held directly by KCC

Addressing requirements of DRC resulting from Mining Contract Review

Provisions of July 31 MoU, together with provisions of Feb 7 agreement, will be integrated into the merged JV document

28

External Challenges: Infrastructure

RailImports – rail already used for importing suppliesExports – current route to DurbanMaputo and Dar-es-Salaam operational but not practicalRoute to Lobito: shorter with only one border crossing; upgrade expected to be completed by 2009.

RoadExports – direct route from Kolwezi to DurbanImports – over 600 loads transported for Phase I – transit as short as 7 days from JohannesburgLubumbashi to Kolwezi road – upgrade being financed by World Bank

29

External Challenges: Power

Short term

Unaffected by recent load shedding on 220kV network

Our installations are fed from 120kV substation

SNEL guaranteed 65MW by June 2008 – sufficient power until end 2009

Long term

Private sector refurbishment of Inga II will add 850 MW by 2011

Plans to secure financing to refurbish Koni and Mwadingusha

Working closely with SNEL on future needs – 2011 requirement approx. 250MW

30

Corporate Social Responsibility

313131

Benefits

Now employing some 3,700 DRC nationals

Local payroll now exceeding US$3.5m per month

Supporting up to 15,000 jobs in the regional economy

Benefits to the DRC to date: US$900m1

Returns over 20 years from 2011: US$7.0bn2

Substantial Benefits to DRC

Policy

Open & active engagement with local stakeholdersWork in partnership to create sustainable livelihoodsLong-term improvements to living standardsGuided by international standards

Education/Training &Enterprise

Health

Agriculture

Infrastructure

Programs

1. Benefits to the DRC to date figure is up to June 30, 2008 and includes capital expenditure2. Returns to DRC figure based on $1.50/lb Cu and $10.00/lb Co & excludes capital expenditure

3232

Agriculture

Mukweji Farm – crops & livestock introduced; self sustaining by end 2008Women’s agricultural projectNursery established for site rehabilitation

Implementing Community Projects

30kms of road rehabilitation / paving Kolwezi plus Luilu to airport roadLocal road improvement employing ex-artisanal minersWater & electricity supply reinstatedDitch & drain clearance

Infrastructure

3333

Implementing Community Projects

Supporting creation of independent SMEsDay care centre for orphansRefurbishing Kolwezi schools & build new Tilwezembe school

Education / Training & Enterprise

Mwangeji Hospital refurbishment –water supply & sanitationChild vaccination programMalaria prevention program

Health

© 2008 Katanga Mining Limited Trading symbol: KAT.TO

Mine Tour – Achievements and Looking Ahead

35

Achievements to Date

36

From Rehabilitation…

Joint Venture took over site July 2006 – US$175m Phase I investment program

37

…to Production

Production restarted Dec 2007 …on Schedule …on Budget

38

Merger – January 2008

Economies and efficiencies of scale

Significant capital and operating synergies

Strong balance sheet and cash flow generation

Reunite adjacent assets

Potential to be Africa’s largest Cu producer and world’s largest Co producer

39

Conclusions and Looking Ahead

40

Goals for 2H 2008

Continue to strengthen management team

Complete Kamoto Phase II construction

Continue production ramp up of copper cathode and cobalt metal

Start mining at KOV

Complete feasibility study near end of 3Q 2008

Consolidate Joint Ventures & complete contract review process

Potential for LSE listing in 2009

Generate earnings and positive cash flow from operations

41

0% 1% 2% 3% 4% 5% 6%

KatangaTenke

Mount IsaTaimyr Peninsula

AntaminaOlympic Dam

OK TediCollahuasiGrasberg

EscondidaEl Teniente

Codelco NorteLos Pelambres

Bingham CanyonLos Bronces

AlumbreraBatu HijauToquepala

Morenci

Ore Grade - % M&I Contained Copper0 500 1,000 1,500

EscondidaGrasberg

Codelco NorteMount IsaAntaminaKatanga

CollahuasiEl Teniente

Bingham CanyonMorenci

Los PelambresTaimyr Peninsula

Batu HijauAlumbrera

Olympic DamOK Tedi

Los BroncesToquepala

Tenke

Copper Equivalent Production (Kt)

Leading Global Mines by Production1

…Ranked by Grade2,3

1. Based on 2007 production, except Katanga, Tenke and Taimyr Peninsula (2011 forecasts: 300 Kt Cu and 30 Kt Co, 115kt Cu and 8Kt Co, 2006 figures respectively). Price assumptions used to convert production to copper equivalent: Cu $1.60/lb, Co $10.00/lb, Zn $0.75/lb, Ag $11.00/Oz, Au $700/Oz, Mo $12.00/lb.

2. Katanga figure includes all deposits.3. Based on reported Measured and Indicated resource copper grades. Source: CIBC World Markets

World-Scale Producer

Katanga

Katanga

42

Overview

Targeting over 300,000 tonnes Cu and over 30,000 tonnes Co by 2011

Potential to be Africa’s largest Cu producer & world’s largest Co producer

Now generating operational cash flow

Genuine commitment tosustainable development

Globally significant integratedsingle-site operation

Proven management teamand track record

Large-scale, low-cost andlong-life producer

43

Q & A

Tel: +44 20 7440 5800Fax: +44 20 7440 5801

Contact Details

Email: [email protected]: www.katangamining.com


Recommended