+ All Categories
Home > Documents > Ministry of Defence Report of the Audit General 2015 - OAG

Ministry of Defence Report of the Audit General 2015 - OAG

Date post: 07-Feb-2022
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
20
THE REPUBLIC OF UGANDA REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE MINISTRY OF DEFENCE FOR THE YEAR ENDED 30 TH JUNE 2015 OFFICE OF THE AUDITOR GENERAL UGANDA
Transcript
Page 1: Ministry of Defence Report of the Audit General 2015 - OAG

THE REPUBLIC OF UGANDA

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF

THE MINISTRY OF DEFENCE

FOR THE YEAR ENDED 30TH JUNE 2015

OFFICE OF THE AUDITOR GENERAL

UGANDA

Page 2: Ministry of Defence Report of the Audit General 2015 - OAG

ii

TABLE OF CONTENTS

LIST OF ACROYNMS ...................................................................................................... iii

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE MINISTRY

OF DEFENCE FOR THE YEAR ENDED 30TH JUNE, 2015 ..................................................... iv

1.0 INTRODUCTION .................................................................................................. 1

2.0 BACKGROUND INFORMATION .............................................................................. 1

3.0 ENTITY FINANCING ............................................................................................ 1

4.0 OBJECTIVES OF THE MINISTRY ........................................................................... 1

5.0 AUDIT SCOPE ..................................................................................................... 2

6.0 AUDIT PROCEDURES PERFORMED ....................................................................... 2

7.0 CATEGORIZATION AND SUMMARY OF FINDINGS .................................................. 3

7.1 Categorization of findings .................................................................................... 3

7.2 Summary of findings ........................................................................................... 4

8.0 DETAILED FINDINGS ........................................................................................... 4

8.1 Non- produced assets .......................................................................................... 4

8.2 Irregular payment of Compensation ...................................................................... 4

8.3 Anomalies in the Procurement Procedures ............................................................. 5

8.4 Un-reconciled UMEME Payments ........................................................................... 7

8.5 Breach of Contract for Construction Works ............................................................ 7

8.6 Land Compensation at Kabamba Barracks ............................................................ 8

8.7 Rental Arrears ..................................................................................................... 9

8.8 Audit Inspection .................................................................................................. 9

Page 3: Ministry of Defence Report of the Audit General 2015 - OAG

iii

LIST OF ACROYNMS

MOD Ministry of Defence

ICT Information Communication Technology

MoFPED Ministry of Finance Planning and Economic Development

UGX Uganda Shillings

BoU Bank of Uganda

LC Letter of Credit

NSSF National Social Security Fund

TAI Treasury Accounting Instruction

VAT Value Added Tax

ULC Uganda Land Commission

CHEC China Harbors and Engineering Corporation

TRRP Tororo Roads and Railways Polytechnic

PFMA Public Finance Management Act, 2015

PS/ST Permanent Secretary/Secretary to the Treasury

SOFAAD School of Field Artillery and Air Defence

Page 4: Ministry of Defence Report of the Audit General 2015 - OAG

iv

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF

THE MINISTRY OF DEFENCE

FOR THE YEAR ENDED 30TH JUNE, 2015

THE RT. HON. SPEAKER OF PARLIAMENT

I have audited the financial statements of Ministry of Defence for the year ended 30th June

2015. These financial statements comprise of the statement of financial position, the

statement of financial performance, and cash flow statement together with other

accompanying statements, notes and accounting policies.

Management Responsibility

Under Article 164 of the Constitution of the Republic of Uganda, 1995 (as amended) and

Section 45 of the Public Finance Management Act, 2015, the Accounting Officer is

accountable to Parliament for the funds and resources of the Ministry. The Accounting

Officer is also responsible for the preparation of financial statements in accordance with the

requirements of the Public Finance Management Act 2015, and the Financial Reporting

Guide, 2008, and for such internal control as management determines is necessary to

enable the preparation of financial statements that are free from material misstatement,

whether due to fraud or error.

Auditor’s Responsibility

My responsibility as required by Article 163 of the Constitution of the Republic of Uganda,

1995 (as amended) and Sections 13 and 19 of the National Audit Act, 2008 is to audit and

express an opinion on these statements based on my audit. I conducted the audit in

accordance with International Standards on Auditing. Those standards require that I comply

with the ethical requirements and plan and perform the audit to obtain reasonable

assurance whether the financial statements are free from material misstatement.

An audit involves performing audit procedures to obtain evidence about the amounts and

disclosures in the financial statements as well as evidence supporting compliance with

relevant laws and regulations. The procedures selected depend on the Auditor’s judgment

including the assessment of risks of material misstatement of financial statements whether

due to fraud or error. In making those risk assessments, the Auditor considers internal

control relevant to the entity’s preparation and fair presentation of financial statements in

order to design audit procedures that are appropriate in the circumstances but not for

Page 5: Ministry of Defence Report of the Audit General 2015 - OAG

v

purposes of expressing an opinion on the effectiveness of the entity’s internal control. An

audit also includes evaluating the appropriateness of accounting policies used and the

reasonableness of accounting estimates made by management as well as evaluating the

overall presentation of the financial statements. I believe that the audit evidence I have

obtained is sufficient and appropriate to provide a basis for my audit opinion.

Part “A” of this report sets out my opinion on the financial statements. Part “B” which forms

an integral part of this report presents in detail all the significant audit findings made during

the audit which have been brought to the attention of management and form part of my

Annual Report to Parliament.

PART “A”

Opinion

In my opinion, the financial statements of Ministry of Defence for the year ended 30th June

2015 are prepared, in all material respects, in accordance with Section 51(1) of the Public

Finance Management Act, 2015, and the Financial Reporting Guide, 2008.

John F.S. Muwanga

AUDITOR GENERAL

KAMPALA

12th November, 2015

Page 6: Ministry of Defence Report of the Audit General 2015 - OAG

0

REPORT OF THE AUDITOR GENERAL AND SUPPLEMENTARY INFORMATION

Page 7: Ministry of Defence Report of the Audit General 2015 - OAG

1

PART “B”

DETAILED REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF

MINISTRY OF DEFENCE FOR THE FINANCIAL YEAR ENDED 30TH JUNE 2015

This section outlines in detail the audit scope, audit findings, my recommendations and

management responses in respect thereof.

1.0 INTRODUCTION

Article 163 (3) of the Constitution of the Republic of Uganda, 1995 (as amended)

requires me to audit and report on the public accounts of Uganda and all public offices

including the courts, the central and local government administrations, universities, and

public institutions of the like nature and any public corporation or other bodies or

organizations established by an Act of Parliament. Accordingly, I carried out the audit of

the Ministry to enable me report to Parliament.

2.0 BACKGROUND INFORMATION

Ministry of Defence headquarters are located at Mbuya Hill, Nakawa Division, Kampala

District. The mandate of the Ministry of Defence is derived from the Constitution of the

Republic of Uganda, where Article 208 establishes the Uganda Peoples Defence Forces

(UPDF) and Article 209 spells out the functions of the UPDF.

3.0 ENTITY FINANCING

Ministry of Defence is financed from Central Government and locally generated

revenues. During the year, the Ministry received releases worth UGX.1,026,138,023,817

from Central Government and a total of UGX.213,770,000 was received as Non-Tax

Revenue against the budget amount of UGX.440,000,000. The NTR increased because

the Ministry boarded off assets during the year. The total expenditure for the Ministry

was UGX.1,026,311,643,817.

4.0 OBJECTIVES OF THE MINISTRY

The Ministry of Defence has the following objectives:-

To ensure the Defence of the country and constitution of Uganda that encapsulates

Peoples’ Sovereignty through popular will.

Page 8: Ministry of Defence Report of the Audit General 2015 - OAG

2

To assist with peace keeping security

To contribute to regional stability

To provide support to civilian authorities.

5.0 AUDIT SCOPE

The audit was carried out in accordance with International Standards on Auditing and

accordingly included a review of the accounting records and agreed procedures as was

considered necessary. In conducting my reviews, special attention was paid to establish

whether:-

a. The financial statements have been prepared in accordance with consistently

applied Accounting Policies and fairly present the revenues and expenditures for

the period and of the financial position as at the end of the period.

b. All Ministry funds were utilized with due attention to economy and efficiency and

only for the purposes for which the funds were provided.

c. Goods and services financed have been procured in accordance with the

Government of Uganda procurement regulations.

d. To evaluate and obtain a sufficient understanding of the internal control

structure of the Ministry, access control risk and identify reportable conditions,

including material internal control weaknesses.

e. Ministry of Defence management was in compliance with the Government of

Uganda financial regulations.

f. All necessary supporting documents, records and accounts have been kept in

respect of all Ministry activities, and are in agreement with the financial

statements presented.

6.0 AUDIT PROCEDURES PERFORMED

The following audit procedures were undertaken:-

a. Revenue

Obtained all schedules of all revenues collected and reconciled the amounts to the

Ministry of Defence’s cashbooks and bank statements.

Page 9: Ministry of Defence Report of the Audit General 2015 - OAG

3

b. Expenditure

The Ministry of Defence payments vouchers were examined for proper

authorization, eligibility and budgetary provision, accountability and support

documentation. It was established that all Ministry of Defence funds were utilized

for the intended purposes.

c. Internal Control System

Reviewed the internal control system and its operations to establish whether sound

controls were applied throughout the period audited.

d. Procurement

Reviewed the procurement of goods and services under the Ministry during the

period under review and reconciled with the approved procurement plan.

e. Fixed Assets Management

Reviewed the use and management of the assets of the Ministry during the period

audited.

f. Ministry of Defence’s Financial Statements

Examined, on a test basis, evidence supporting the amounts and disclosures in the

financial statements; assessed the accounting principles used and significant

estimates made by management; as well as evaluating the overall financial

statement presentation.

7.0 CATEGORIZATION AND SUMMARY OF FINDINGS

7.1 Categorization of findings

The following system of profiling of the audit findings has been adopted to better

prioritise the implementation of audit recommendations:

N

o

Category Description

1 High significance Has a significant/material impact, has a high likelihood of

reoccurrence, and in the opinion of the Auditor General, it

requires urgent remedial action. It is a matter of high risk or

high stakeholder interest.

2 Moderate significance Has a moderate impact, has a likelihood of reoccurrence,

and in the opinion of the Auditor General, it requires

remedial action. It is a matter of medium risk or moderate

stakeholder interest.

3 Low significance Has a low impact, has a remote likelihood of reoccurrence,

Page 10: Ministry of Defence Report of the Audit General 2015 - OAG

4

and in the opinion of the Auditor General, may not require

much attention, though its remediation may add value to the

entity. It is a matter of low risk or low stakeholder interest.

7.2 Summary of findings

No Finding Significance

8.1 Non- produced assets High

8.2 Payment of Compensation- UGX.1,000,000,000 High

8.3 Faulting Procurement Procedures High

8.4 Un-reconciled UMEME Payments High

8.5 Breach of Contract by M/S KG Adubango High

8.6 Land Compensation at Kabamba Barracks High

8.7 Rental Arrears - UGX.2.01bn. High

8.8 Audit Inspection Moderate

8.0 DETAILED FINDINGS

8.1 Non- produced assets

During the year the Ministry’s total expenditure on land acquired amounted to

UGX.1,119,388,145. However, it was noted that the government policy of capitalising

the acquired land from the financial year 2011/2012 did not give guidance on what to

include as cost of land acquired. As such, this amount could not be verified due to lack

of guidelines on treatment of land costs in the financial statements. There is a risk of

misstatement on the amount captured.

I advised the Accounting Officer to engage the Accountant General and ensure that

guidelines are provided to spell out clearly what should be capitalised as land acquired.

8.2 Payment of Compensation of UGX.1,000,000,000

It was observed that a sum of UGX.1,000,000,000 was paid to an individual as part

payment on a claim of UGX.2,958,668,733 for the compensation of 683 cattle and 119

goats which were handed over to 4th Division for safe custody during the insurgency

period in 1986. Reviews of the available documents indicate that;

The Ministry of Defence requested for the original documents from the Solicitor

General’s Office to effect the payment, instead payment was effected using photo-

copied documents on account that the original documents got misplaced.

Page 11: Ministry of Defence Report of the Audit General 2015 - OAG

5

It was not possible to confirm whether this claim had not been paid before since it is

now 28 years since the purported supply of the animals.

Available information indicates that the claimant was a quarter master of the Army

Division at the time of handing over the animals which implies conflict of interest.

It also appears that these animals were for various people but instead the

compensation was made to one individual

There is a risk of duplication of compensation payments.

In response, the Accounting Officer explained that this payment was based on the

advice from the Ministry of Justice and Constitutional Affairs and the Solicitor General

who guided that the claim be paid by Ministry of Defence since it was a contractual

arrangement between MOD and the claimant. However, I was not availed with any

evidence to that effect.

I advised Accounting Officer to ensure thorough scrutiny of documents prior to

settlement of the final claim.

8.3 Anomalies in the Procurement Procedures

During the audit, the Ministry carried out a number of procurements however, in certain

instances the procurement procedures were faulted as summarized in the table below;

Contract number and

Amount

Description of the

contract

Issues raised

1 MOD/SUPLS/2013-

14/00250 Amount

UGX.288,139,008

Industrial materials

for the renovation of

Mubende barracks

Items were delivered before

accepting the bid. The letter of bid

acceptance from the Accounting

Officer was dated 4/08/2014 and

was acknowledged by the supplier

on 8/8/2014 after the items had

been delivered on 18th July, 26th

July, 1st August, and 7th August

2014

2 MD/SUPLS/2013-14/00030

Amount UGX.1,323,240,000

Supply different types

of tyres to the

Ministry depot at

By the time the Call off order was

issued on 18/11/2014 tyres worth

UGX.1,323,240,000 had been

delivered to lower Mbuya.

Page 12: Ministry of Defence Report of the Audit General 2015 - OAG

6

Magamaga Deliveries worth UGX.56,448,847

were made using photocopies.

3 USD.842,599.60 equivalent

to UGX.2,467,974,228.4

Supply of assorted

clothing

By the time of signing the contract

on 3/11/2014, items worth USD

948,681 equivalent to

UGX.2,778,686,648 had already

been delivered.

Date of delivery Amount (US$)

1/5/2014 200,709

8/3/2014 18,410

- 570,317

1/6/2014 169,000

1/7/2014 190,153

Total 948,681

The letter of bid acceptance which

was signed on 24th July 2014 and

the Call off Order issued on 29th

January 2015 were both signed

after the delivery of the different

items.

4 Contract sum of

UGX.2,122,858,703

M/S Kent Uniforms

Ltd to supply

30,000 pairs of Digital

BDU and Assorted

Cap Budges for

UPDF.

Items worth USD.252,000

equivalent to UGX.690,480,000

had already been supplied to the

Ministry on 11th April 2014, and

yet the contracts committee sat

on 22/4/2014 to approve the

contract to supply uniforms.

All the items supplied before the

award of the contract did not

have a Call of Order which is an

indicator that the procurements

were not authorized by the

Accounting Officer.

I explained to the Accounting Officer that undertaking procurements in noncompliance

with the PPDA laws could mean that value for money may not have been achieved from

on the procurements.

The Accounting Officer attributed these anomalies to the unique nature of the Ministry

and promised in future to work within the provision of PPDA Act. I await the Accounting

officer’s action on the matter.

Page 13: Ministry of Defence Report of the Audit General 2015 - OAG

7

8.4 Un-reconciled UMEME Payments

In my report to Parliament for the year ended 30th June 2014, I recommended that

before any further payments are made to UMEME the Ministry should reconcile with

Ministry of Finance, Planning and Economic Development and establish how much

money was paid from Escrow Account to settle the Ministry electricity debt.

The Accounting Officer explained that the Ministry had communicated to PS/ST about

the outstanding debt and promised to offset the amount paid from the Escrow account

prior to making any payment. However, the Ministry with the approval of Ministry of

Finance, Planning and Economic Development paid a sum of UGX.40bn from the

classified vote to UMEME to offset the outstanding bills.

I noted that that after effecting payment no follow up has ever been made with the

money paid from the escrow account. Besides, I was not availed with the reconciled

outstanding amounts at the year end.

Management noted the matter and promised to follow it up. I advised the Accounting

Officer that reconciliation for payment from the Escrow account should be undertaken in

liaison with the MoFPED to establish the outstanding amounts.

8.5 Breach of Contract for Construction Works

The Ministry signed a contract with a local company on 14th June 2013 for the

construction of a maintenance workshop at Moi Brigade headquarters, Nakasongola at a

contract price of UGX.1,507,894.518. The contract was an admeasurement contract

where interim payments are made based on certified works and was expected to be

completed by 30th June 2014.

A review of the available documents revealed the following anomalies;

Cumulative amount of UGX.533,493,648 representing 35% had been paid, however,

the corresponding certificates for the works done were not availed for audit.

For the year under review UGX.167,823,272 was paid to the firm as part payment

for the construction works without a record of certified work.

Page 14: Ministry of Defence Report of the Audit General 2015 - OAG

8

An inspection carried out on 24th September 2015 revealed that the project had not

been completed and was behind schedule by one year and 3 months. The contractor

has been onsite for more than two years and this may result into unnecessary

extension costs.

Management attributed the delays to complete the project to inadequate funding.

I advised the Accounting Officer to enhance supervision of this contractor and have the

works certified and completed.

8.6 Land Compensation at Kabamba Barracks

A total of UGX.65,000,000 was paid on 23rd October 2014 as part payment on a claim of

UGX.3,135,792,749. Documents available indicate that Ministry of Defence signed a

Memorandum of Understanding on 25th September 2014 to compensate interests and all

developments of the owner of the land taken over by the Ministry. The following issues

were noted;

The land in question is government land (Kabamba Barracks) which was erroneously

leased out to an individual by Mubende District Land Board. By the time the lease

was offered, Ministry of Defence had already occupied the land. It is not clear why

the District leased out land which was already occupied.

The lease agreement between the District Land Board and the Land Lord was not

availed to enable me review the terms under which they acquired the land.

The specific conditions for government leases do not permit the lessee to change the

land use without the consent of the lessor. It appears the land use was changed

without the consent of Mubende District Land Board.

The signed Memorandum stated that compensation was to cover the interest and

development on the land but the Landlord never took possession of the land and

therefore no development was made. There is a risk that government is

compensating for development that never existed.

The method used to arrive at the amount of UGX.3,135,792,749 to be compensated

was not clearly defined and the Ministry did not raise any objection.

Page 15: Ministry of Defence Report of the Audit General 2015 - OAG

9

In response the Accounting Officer stated that the Land Lord had acquired the land

before MOD took possession. The Chief Government Valuer valued the land and it is on

this basis that the Ministry is settling the obligation.

I advised the Accounting Officer to seek advice from the Solicitor General on matters of

acquiring leased land prior to effecting further payments.

8.7 Rental Arrears of UGX.2.01 Billion

In 1988, Government took a decision that all land including houses overlooking Entebbe

Air base be taken over by Ministry of Defence and that owners be compensated. By

March 1989, all properties taken over by the Air force in Entebbe had been paid for by

Government. However, National Housing and Construction Company (NHCC) after 17

years has now come up with a claim of UGX.2.01 billion in respect of rent arrears for the

purported company property. I was not availed a tenancy agreement to determine the

value. Besides, there was no supporting document for the ownership of the property but

the Ministry of Finance, Planning and Economic Development has committed to avail the

funds.

In response, the Accounting Officer explained that Ministry of Defence occupies twenty

five (25) housing units at Bulime in Entebbe Municipal Council which belongs to National

Housing and Construction Corporation Ltd and the Ministry was paying up to 2005.

I explained to the Accounting Officer the risk of paying rental arrears for the property

that were taken over long ago and compensation effected and advised her to cross

check the records before committing more funds.

8.8 Audit Inspection

I carried out an inspection on various Ministry of Defence properties and observed the

following:

8.1.1 Un-registered land on 6th Street Industrial Area

The Ministry of Defence was allocated land on 6th Street Industrial area by Custodian

Board which the Ministry has occupied since 1986. This land is currently occupied by the

Production Unit of the UPDF. A review of the Ministry of Land Inventory revealed that

this land was not recorded in the assets register and the land is not valued and titled. If

Page 16: Ministry of Defence Report of the Audit General 2015 - OAG

10

this land is not transferred and titled to Ministry of Defence, the land will be reallocated

to another developer.

The Accounting Officer explained that this land is in the custody of Uganda Land

Commission and the Ministry has written to ULC for a formal allocation and have it

caveated for exclusive use by the Ministry of Defence.

I await the Accounting Officer’s action.

8.8.2 Accreditation of Tororo Roads and Railways Polytechnic Institute

The Ministry took a decision to establish Tororo road & railway polytechnic to train and

develop human resource, to build, operate and maintain the standard gauge Railway

system.

I noted that there was no policy framework and accreditation by National Council of

High Education (NCHE) and how this school will relate with the Ministry of Works and

Transport and the contractor of the Standard Gauge Railway. There is a risk that the

graduates of this polytechnic may be rejected by the Ministry of Works and Transport

and the Contractor of the Standard Gauge Railway if there is no binding legal frame

work.

The Accounting Officer explained that a Memorandum of Understanding was concluded

in 2013 between China Harbors and Engineering Corporation (CHEC) and Ministry of

Defence to formalize the agreement. A Cabinet Memo is soon being forwarded to secure

an executive mandate for the formal establishment of Tororo Roads and Railways

Polytechnic (TRRP). Besides, legal technocrats in both MOD and Ministry of Works and

Transport are harmonizing a frame work of staff to the Standard Gauge Railways project

and mutual development of TRRP. The process is still ongoing.

I await the outcome of the engagement process.

8.8.3 Delayed Works at SOFAAD Training School

The Ministry took a decision to transfer SOFAAD training school from Butiaba to Olilim in

2012 and a contract for the construction of priority works was awarded to a local

company at a contract sum of UGX.5,981,499,609. Audit inspection carried out last year

Page 17: Ministry of Defence Report of the Audit General 2015 - OAG

11

indicated that some equipment had been mobilized and were on site to commence the

construction works. However, an inspection carried out in September, 2015 indicated

that the contractor has abandoned the site. There is a risk that the contractor may sue

government of breaching the contract thus paying litigation costs and the agreed costs

are likely to escalate.

In response the accounting Officer stated that the funds for the school were re-allocated

to Kaweweta Training School because of the large numbers of the recruits. Funding for

the school will be availed in the financial year 2016/2017 and the contractor will be able

to resume the project since the execution period in the contract has been extended.

I await the actions of the Accounting Officer.

8.8.4 Delayed Operationalization of Water Bottling Plant at Kakiri

It was noted that the water bottling plant at Kakiri was still not in operation by the time

of inspection in October 2015 despite the Ministry paying a sum of UGX.560,756,632 to

set up this project. I explained to the Accounting Officer that there is a risk of not

achieving the objectives of the projects.

The Accounting Officer stated that the project was complete and was only waiting for

final certification from Uganda National Bureau of Standards (UNBS).

I advised the Accounting Officer to follow up on the certification and have the project

operationalized.

8.8.5 Non-functioning Water Project

A local company was awarded a contract to extract and distribute water to the barracks

at Mburamaizi from River Kiruruma in the financial year 2008/2009 and was supposed to

complete the project in the financial year 2009/2010 at a contract sum of

UGX.492,676,973. The cumulative payments to-date totaled to UGX.326,948,553.

During inspections in October 2014, it was observed that the pipes burst four years after

commissioning and as such the water project is not in operation. The bursting of pipes

could be an indicator of use of inferior materials and inadequate project management.

Page 18: Ministry of Defence Report of the Audit General 2015 - OAG

12

The Ministry also carried out a project to install a reservoir and other accessories at a

cost of UGX.100,000,000. However, instead the barracks is now obtaining water from

Katete supplied by National Water and Sewerage Corporation. The owner of the land on

which the project is operating has not been compensated for the land occupied by the

pump station. The option of accessing water from the National Water and Sewerage

Corporation plant at Katete could be an indicator that the Sumadhura Project has failed.

The Accounting Officer explained that the water from National Water and Sewerage

Corporation was an alternative source in case the MOD pump failed.

I advised the Accounting Officer to replace the pipes for the water that burst before

clearing the balance on the contract.

8.8.6 Army units on private property

During the audit inspection, I observed that out of 307 Brigade Commander Units, ten

(10) detaches were settled on private premises that lacked tenancy agreements and

thus I could not determine the amount payable to these private owners as rent.

Litigation costs may arise due to illegal occupation.

Management stated that the Chief Government Valuer (CGV) is currently ascertaining

the rent payable to the identified land owners.

I advised the Accounting Officer to review occupation of private properties in the entire

army to avoid unnecessary litigation costs. In the meantime, the CGVs report is awaited.

8.8.7 Procurement of plot in Hima Town Council

The Ministry purchased a plot of land in Hima Town Council at a cost of UGX.2,800,000

from an individual in the year 2004. The ownership of this plot appears to not have been

regularized. This is the second time this matter has been brought to the attention of

management and no appropriate action has been taken so far. This land has not been

put to use for the last eleven years.

Management is aware of this plot and the Military Land Board has engaged Kasese

District Land Board to have the title issued.

Page 19: Ministry of Defence Report of the Audit General 2015 - OAG

13

I await the Accounting Officer’s action on the matter.

8.8.8 State of Hima Barracks 305 Brigade Headquarters

The structures at the brigade headquarters are worrying. All buildings had developed

cracks yet they appeared to be freshly renovated. These included the administration

block, hospital and barracks quarters. Substandard works could not be ruled out.

Management attributed the problem to the location of the barracks near a limestone

quarry for Hima cement factory. The company extracts the limestone by blasting which

are causing shrinkage cracks to the buildings. These cracks are being repaired as part of

the routine maintenance of buildings.

I urged the Accounting Officer to consider undertaking a technical audit of the buildings

with a view to getting a lasting solution.

8.8.9 Termination of Bwera Water Supply Contract

Records from Engineers’ Brigade indicated that a local company was awarded a contract

at a sum of UGX.680,749,070 for construction of water supply to Rusese Barracks from

river Lubrirha. By the time of audit inspection, a total of UGX.202,250,000 had been paid

to the contractor leaving a balance of UGX.478,499,100. Physical inspection revealed

that the contractor had stopped the works because the contract had been terminated.

There was no contract file at the time of inspection to enable me review the

procurement and determine the reason for termination of this contract. There is a risk of

the Ministry incurring litigation costs in case the termination of the contract was

unlawful.

Management explained that consultations with Directorate of Water Development have

since been concluded and measures are underway to review the contract and allow

works to proceed.

I await the Accounting Officer’s action on the matter.

Page 20: Ministry of Defence Report of the Audit General 2015 - OAG

14

APPENDIX 1

FINANCIAL STATEMENTS


Recommended