1
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 1 of 129
Minutes of the 555thmeeting ofthe State Level Expert Appraisal Committee held on 03/10/2019 at
Committee Room, Gujarat Pollution Control Board, Sector 10A,Gandhinagar.
The 555thmeeting of the State Level Expert Appraisal Committee (SEAC) was held on 03rd October
2019 at Committee Room, Gujarat Pollution Control Board, Sector 10A, Gandhinagar. Following
members attended the meeting:
1. Dr. Dinesh Misra, Chairman, SEAC
2. Shri S. C. Srivastav, Vice Chairman, SEAC
3. Shri V. N. Patel, Member, SEAC
4. Shri. R. J. Shah, Member, SEAC
The regular agenda of Appraisal, Reconsideration, and Refer Back Cases&ToRcases were taken up. The
Committee considered the applications made by project proponents, additional details submitted as
required by the SEAC/SEIAA and details furnished in the Form-1, PFR, EIA-EMP reports.
Proposal No. Name and Address of the Unit Remarks
03. SIA/GJ/IND2/37526/2018
M/s. Shivam India Plasto Pack
169/1/A2, Phase –1, Opposite
Telephone Exchange, GIDC Naroda,
Ahmedabad
EC – Reconsideration
Category of the unit: 5(f)
Project status: New
• Project proponent (PP) submitted online application vide no. SIA/GJ/IND2/37526/2018 dated 27/08/19 for
obtaining Environmental Clearance.
• SEIAA issued TOR to PP vide their letter dated 26/11/2018.
• Project proponent has submitted EIA Report prepared by B. S. Rana, Ahmedabadbased on the TOR issued
by SEIAA.
• The project falls underCategory B of project activity 5(f) asper the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 05/09/2019.
• During the meeting dated 05/09/2019, technical presentation made by the Project proponent.
2
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 2 of 129
• During the meeting, the project was appraised based on the information furnished in the EIA Report, and
details presented during the meeting.
• Committee noted that ToR on this proposal was issued considering it as new project as the existing products
does not require Environmental Clearance, however PP submitted earlier the project details considering it as
expansion project as per PFR, Form-1 & Format submitted to SEAC dated 21/05/2019 however query on
this project was raised in SEAC meeting dated 28/06/209 and in compliance of the query of point no. (3)
Revised product list by removing non-EC products PP submitted revised product profile by removing non –
EC products and SEAC recommended ToR vide letter dated 01/11/2019 to SEIAA considering it as new
project by eliminating non – EC product and SEIAA issued ToR to PP considering it as new project dated
26/11/2019.
• Further committee deliberated on EIA Report Preparation and noted that PP has tactfully eliminated Page
No. 41-44 in EIA report covering detail deliberation on “Land Requirement Details” in Chapter – 2 and asked
PP/Consultant to reply for the same however both of them could not reply satisfactorily for the same.
• After detailed discussion, it was decided to defer the proposal and consider the same in one of the upcoming
meeting of SEAC only after submission of the following documents.
1. Revised EIA Report to be Prepared as per ToR granted by SEIAA dated 26/11/2018.
2. Details with respect to justification for proposed expansion: (1) To address proportionate availability of
space for production plant. (2) To address proportionate availability of storage area for raw materials
finished goods, utilities considering fire-safety norms & PESO standards and goods carrier movement
within premises. (3) To address proportionate captive/common infrastructure available to
accommodate additional load due to proposed expansion. (4) Environment impact and its mitigation
measures for common/ captive infrastructure due to proposed production by bifurcation of Existing
Area 1620 Sq. mt. in two viz (1) 620 Sq. mt. (Existing), (2) 1000 sq.mt. (Expansion) as per the EIA
Report Submitted dated 03/09/2019.
• Project proponent made presentation for the above mentioned query dated 03.10.2019 for the above
mentioned points.
• PP presented replied as below:
1. Revised EIA Report to be Prepared as per ToR granted by SEIAA dated 26/11/2018.
2. PP submitted that total area available with them is 1620 Sq. mt.
• This is a revised proposal for manufacturing of Synthetic Organic Chemicals as tabulated below:
Sr.
no.
Name of the Products CAS no. / CI no. of
raw materials.
Quantity
MT/Month
End-use of the
products
1. Reactive Black 5(Mix) 12225-25-1 200 • Dyes are used for
3
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 3 of 129
2. Reactive Black WNN 17095-24-8 dyeing of cloths.
3. Reactive Black 39 205071
• Reactive Black 8 12225-26-2
• Reactive Black 31 12731-63-4
• Direct Black 22 6473-13-8
• Acid Black 210 99576-15-5
• Acid Black 194 61931-02-0
• Acid Black 234 157577-99-6
• Acid Black 113 3351-05-1
• Acid Black 10BX 1820-82-5
• Acid Black 193 12392-64-2
• Reactive Red 195 93050-79-4
• Reactive Red 250 125830-49-1
• Reactive Red 223 93051-43-5
• Reactive Red 111 88232-20-6
• Reactive Red 198 145017-98-7
• Reactive Red 120 61951-82-4
• Reactive Red CD 91-56-5
• Reactive Red 21 11099-79-9
• Reactive Red 222 93051-45-7
• Reactive Red 141 61931-52-0
• Reactive Red 3.1 23211-47-4
• Reactive Red 24.1 72829-25-5
• Reactive Red 31 12237-00-2
• Reactive Red 45 12226-22-1
• Reactive Red 218 113653-03-5
• Reactive Red 245 340977-00-6
• Direct Red 81 2610-11-9
• Reactive Yellow 145 93050-80-7
• Reactive Yellow 44 12270-91-6
• Reactive Yellow 84 61951-85-7
4
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 4 of 129
• Reactive Yellow 18 12226-48-1
• Reactive Yellow 15 12226-47-0
• Reactive Yellow XLR 5809-16-7
• Reactive Yellow HEXL Mixture of
59112-78-6
77907-38-1
93050-80-7
• Reactive Yellow HE4G 59112-78-6
• Reactive Yellow W3R 12220-12-1
• Reactive Yellow RR 93050-80-7
• Reactive Yellow 42 12226-63-0
• Reactive Yellow 57 61969-35-5
• Reactive Yellow 85 71872-81-6
• Reactive Yellow 86 61951-86-8
• Reactive Yellow 210 Mix dyes
• Reactive Yellow 160 129898-77-7
• Reactive Yellow 135 77907-38-1
• Reactive Yellow 186 84000-63-5
• Reactive Yellow 95 71838-98-7
• Reactive Orange 122 79809-27-1
• Reactive Orange 13 12225-85-3
• Reactive Orange 107 90597-79-8
• Reactive Orange 2R 79809-27-1
• Reactive Orange 16 12225-83-1
• Reactive Orange 35 12270-76-7
• Reactive Orange W3R Mix dyes
• Reactive Orange
R(DABA)
12220-12-1
• Reactive Orange 12 35642-64-9
• Reactive Orange 84 91261-29-9
• Reactive Blue 160 71872-76-9
5
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 5 of 129
• Reactive Blue 221 93051-41-3
• Reactive Blue 198 124448-55-1
• Reactive Blue
FNG(FNR)
Mix dyes
• Reactive Blue 220 128416-19-3
• Reactive Blue 39 -
• Reactive Blue 13(P2R) -
• Reactive Blue 49 12236-92-9
• Reactive Blue 203 147826-71-9
• Reactive Blue XLE(19) 2580-78-1
• Reactive Blue 250 93951-21-4
• Reactive Blue 21 12236-86-1
• Reactive Blue 222 93051-44-6
• Reactive Blue 194 93050-78-3
• Reactive Blue 171 77907-32-5
• Reactive Blue 203 147826-71-9
• Direct Blue 71 4399-55-7
• Reactive Scarlet W2R Mixed Dyes
• Reactive Brown 11 12225-68-2
• Acid Brown 355 60181-77-3
• Acid Brown 425 119509-49-8
• Acid Brown 75 8011-86-7
• Acid Brown 83(100) 13011-68-2
• Reactive Violet 46 -/17175
• Reactive Violet ME2RL Mixed Dyes
• Reactive Magenta MERL Mixed Dyes
• Salient features of the project including Water, Air and Hazardous waste management (Revised):
Sr.
no.
Particulars Details
A
6
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 6 of 129
A Total cost of Proposed Project
(Rs. in Crores):
Total: 1.5 Crores
Details of EMP
Brief Details of EMP
Bifurcation of EMP cost:
Component Capital Cost of EMP Recurring Cost of EMP
(per year)
Total Cost 31,00,000 6,45,000
Operation Phase
Sr. No. Pollution Control Measures Capital Cost
(Rs.)
Recurring
Cost per
annum
(Rs.)
1 Air Pollution Control 15,00,000 3,00,000
2 Water Pollution Control 10,00,000 2,00,000
3 Noise Pollution Control 1,00,000 25,000
4 Environment Monitoring and
Management
1,00,000 20,000
5 Rain Water Harvesting 2,00,000 50,000
6 Occupational Health 1,00,000 25,000
7 Green Belt 1,00,000 20,000
Total 31,00,000 6,45,000
Details of CER as per OM dated 01/05/2018
Unit will allow fund for CER Activity for 3 Year (2019-2021)
CER
Activity
Education 0.30 Lacs/Yr
Drinking Water Supply 0.70 Lacs/Yr
Green Belt Development 2.00 Lacs/Yr
7
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 7 of 129
Trees Plantation
Gardening Area Development
TOTAL 3 Lacs/Yr.
Cost in Lacs/Yr.
2019-2020 2020-2021 2021-2022
− 0.35 Lacs for drinking
water facility provided in
Limbadia, Raipur & Zak
village.
_Providing drinking water
facility (Water Jug) at road
side.
0.30 Lacs for Education at
Valad, Lalpur& Bhat_With
the help of local Trust (For
Education) & NGO
_Stationary provided at
Primary School at Raipur/
Limbadia&Village.
− 0.35 Lacs for drinking
water facility provided in
Valad, Lalpur& Bhat
village.
_Providing drinking water
facility at Valad, Lalpur&
Bhat Villages.
− 2.0 Lacs for trees
Plantation at Limbadia,
Raipur , Zak, Valad,
Lalpur&
BhatVillage(Along with
Road Side) with help of
local people.
Total: 2.35 Lacs Total: 0.30 Lacs Total: 0.35 Lacs
B Total Plot area ( sq. meter)
Total:1620 Sq. m.
Green belt area
( sq. meter)
Total:330 Sq. m.
C Employment generation Total:30
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc..)
GIDC Water supply
Status of permission from the concern authority. Allotment letter enclosed
8
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 8 of 129
ii Water consumption (KLD)
Proposed
(Additional)
KLD
Remarks
(A) Domestic 1.5 Fresh Water
(B) Gardening
Industrial
Process 15.0 Fresh Water
Washing 5.0
Boiler 5.0
Cooling 1.0
Others 1.0
Industrial Total 27.0
Grand Total
(A+B+C)
28.5 Fresh water
1) Total water requirement for the project: 28.5 KLD
2) Quantity to be recycled: 0.0 KLD
3) Total fresh water requirement: 28.5 KLD
iii Waste water generation (KLD)
Category Proposed
(Additional)
KLD
Remarks
(A) Domestic 1.4 -
Process - -
Washing 5.0 -
Boiler 1.0 -
Cooling 0.5 -
Others 0.5 -
Total Industrial
waste water
7.0 Treat in ETP
and spray dried
in premises.
iv Treatment facility within premises with � ETP: Primary treatment
9
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 9 of 129
capacity
[In-house ETP (Primary, Secondary,
Tertiary), MEE, Stripper, Spray Dryer, STP
etc.
� ETP Capacity : 28.5 KLD
� Spray Dryer: 2.0 KL/Hr.
Treatment scheme including segregation at
source.
1.4 KLD Domestic effluents shall be
disposed through septic tank & Soak pit.
The total waste water generations from
Industrial will be 7.0 KLD. The waste water
shall generate mainly boiler blow down,
cooling tower, scrubber and plant process
cleaning water. The effluent will be treated in
ETP and sent to spray dryer for evaporation
in premises.
Note: (In case of CETP discharge) :
Management of waste water keeping in view direction under section 18 (1) (b) of the
Water (Prevention and Control of Pollution) act, 1974 issued by CPCB regarding
compliance of CETP.
� Not applicable as there shall no discharge of any effluent to CETP
Brief note on adequacy of ZLD (In case of Zero Liquid Discharge):
� Spray dryer and primary treatment plant will be provided for ZLD. There is no
connection of CETP for discharge of effluent.
v Mode of Disposal & Final meeting point
Domestic: Domestic: Soak pit
Industrial: Industrial: ZLD
Total generated effluent will be treated in ETP and sent to self spray dryer.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. Name
of CF
� Not proposed.
Membership of Common facility (CF)
(For waste water treatment)
Not proposed.
vii Simplified water balance diagram with reuse / recycle of waste water
10
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 10 of 129
Intake
28.5
Domestic
1.5
Soak pit
1.4
Gardening
0.0
Industrial
27.0
Process
15.0
Washing
5.0
Boiler
5.0
Cooling
1.0
5.0 5.0 1.015.0
5.0 1.0
ETP
7.0
Spray dryer
in premises
Water Balance Diagram
Others
0.5
0.5 0.5
viii Reuse/Recycle details (KLD)
Total reuse 0.0 KLD
Source of waste
water for reuse
with quantity in
KLD (From where
it is coming)
Application
area with
quantity in
KLD (Where it
is used)
Characteristics of
waste water to be
reused (COD, BOD,
TDS etc.)
Remarks
regarding
feasibility
to reuse i.e.
- - -- -
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
SR.
no.
Source of
emission
With
Capacity
Stack
Height
(meter)
Type of Fuel Quantity
of Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air
Pollution
Control
Measures
(APCM)
1 Hot Air 13 m Solid Fuel 1.8 PM/ Cyclone
11
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 11 of 129
Generator (Agro
Waste/Import
ed Coal/
White Coal)
MT/day
Agro
waste
Or 2000
SCM/day
NG
SO2/
NOx
Separator
2 Boiler
1 Ton
13 m Solid Fuel
(Agro
Waste/Import
ed Coal/
White Coal)
0.5
MT/day
Agro
waste
Or 200
SCM/day
NG
PM/
SO2/
NOx
Cyclone
Separator
3 DG Set 5 m Diesel 10 Lit/Hr PM/
SO2/
NOx
Adequate
Stack
Height
-
ii Process gas emission details i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
-Sr.
no.
Source of
emission
Type of
emission
Stack/Vent
Height (meter)
Air Pollution Control
Measures
(APCM)
1 Spray Dryer
(2 KL/day)
PM/
SO2/
NOx
20 m Cyclone Separator + Wet
Scrubber + Secondary
scrubber
iii Fugitive emission details with its mitigation measures:
As below:
Proposed project is of manufacturing of S. O. Dyes . Followings measures will take for
existing & proposed project.
• Maintaining the house keeping regularly
• Transferring the liquid materials by pump
• To carry out regular leak detection and repair activities
Proper routine maintenance of equipment reduces the likelihood of leaks
12
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 12 of 129
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary Movement)
Rules 2016.
i
Sr.
No
.
Type/Name
of
Hazardous
waste
Source of
Generatio
n
Category
and
Schedule
as per HW
Rules.
Quantity Disposal Method
1. Discarded
Containers/
Bags
Packing 33.3 24.0
MT/Annu
m
Collection, storage,
Transportation, and sold
to the registered recycler
or reusing premises.
2. Evaporatio
n Residue
Spray
Dryer
-
12.0
MT/Annu
m
Collection,
Storage, Reusing
in Blending mixing
of dyes
3. ETP
Sludge
ETP 35.3 14.0
MT/Annu
m
Collection, storage,
transportation,
disposal at the
Approved TSDFsite
4. Used oil Machiner
y
5.1 0.02MT/A
nnum
Collection, storage,
Reuse withinpremises or
sold to the registered
recycler.
5. Iron sludge Process 26.1
432
MT/Annu
m
Collection, storage,
transportation,disposal at
cement factory co-
processing
6. Bleed
Liquor
Spray
Drying
(Scrubbin
g
- 125MT/An
num
Collection, storage,
transportation, Treated in
ETP
13
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 13 of 129
Process)
Quantity of discarded containers must be in MT/Annum.
ii Membership details of TSDF, CHWIF etc.
(For HW management)
We shall be a member of active
TSDF siteIike Eco Care
Infrastructure Pvt. Ltd.,Viramgam
or Saurashtra Enviro Project Pvt.
Ltd or any active TSDS site
before applying CTE/CTO
iii Details of Non-Hazardous waste & its disposal
(MSW and others)
Plastic waste will sell to
registered recycler.
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery, reuse of recovered Solvents etc.
(Details in Table Format)
� No use of solvent
ii VOC emission sources and its mitigation measures
� There is no any Solvent will use though we will provide closed transferring system of
raw materials during manufacturing to avoid any VOC.
H � Details regarding storage of Hazardous chemicals
Storage details Name of major
Hazardous chemicals
Remarks
Storage tanks
Sulphuric Acid 10 KL
Drum/Barrel storage HCl 30% Carboys
50 kg
Solid Materials
HDPE bags 50 kg
� Applicability of PESO :
� Not Applicable
• During SEAC meeting dated 03/10/2019, Committee asked for reply of query dated 05/09/19. PP informed
14
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 14 of 129
that they have existing plant of spray drying of dyes but now they are not running plant for spray drying of
dyes. Hence Committee insisted for surrendering/Revoke CCA of GPCB for existing plant for spray drying of
dyes and submits documents regarding spray drying of dyes not existence in plant. Committee deliberated
on area adequacy of proposed plant and APCM adequacy and treatability report for ZLD scheme for
proposed project, PP not satisfactorily addressed about it during meeting. Committee insisted for revised air
matrix and Hazardous waste matrix mentioning regarding spent sulphuric acid generation from proposed
project.
• After detailed discussion, it was decided to defer the proposal and consider the same in one of the
upcoming meeting of SEAC only after submission of the following documents,
1. Submit CCA revoke order of GPCB for existing plant of spray drying of dyes, blending and mixing of
dyes and plastic jars etc. as per the ToR granted and photographs regarding removal of existing
plant machinery from site. Also submit area adequacy for the proposed activity.
2. Adequacy and Treatability report by recognized schedule I auditor regarding proposed EMS for
effluent and air emission for proposed project.
3. Submit revised Hazardous Waste matrix with mentioning spent sulphuric acid generation and its
sound management.
04. SIA/GJ/IND2/37355/2018
M/s. Kinjal Chemicals (Unit II )
Plot No. 1605-1606, Phase No -II,
GIDCNaroda, Ahmedabad
EC – Reconsideration
Category of the unit : 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/37355/2018 dated 27/08/2019 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated
04/05/2019.
• Project proponent has submitted EIA Report prepared by M/s: B.S.Rana based on the TOR issued by
SEIAA.
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 17/09/2019.
• During the meeting dated 17/09/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report,and
details presented during the meeting.
15
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 15 of 129
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted
for the study area of 10 km radial distance from project site for the period November 2018 to January 2019.
Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, at Eight locations, including the
project site. Values conform to the prescribed standards for Ambient Air Quality. The incremental Ground
Level Concentration (GLC) has been computed using ISCST – 3 model. The resultant concentrations are
within the NAAQS. The modeling study proved that the air emissions from the proposed plant would not
affect the ambient air quality of the region in any significant manner. The ambient air quality around the
proposed project site will remain within the National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• This unit was established well before year 2006. They have valid CC&A for existing unit. Copy of CC&A, its
compliance report is submitted. PP ensured that there are no court cases pending and no public complaints
against the project.
• During SEAC meeting, committee noted that the proposal is for expansion of existing plant in GIDC. This
unit is having valid CC&A for existing unit. Copy of CC&A, its compliance report is submitted. One SCN
issued by GPCB and its compliance reply submitted by the unit. Committee asked about products which
mentioned in existing plant CCA of GPCB is not match with product profile of proposed project, PP agreed
that they have obtained CCA-amendment for change of product mix on dated 16/01/2019 which is differ
than existing product mentioned in application.Committee asked about compliance of Direction under
section 18(1)(B) of Water Act’74, PP informed that additional partly waste water will be sent to CMEE/spray
dryer of M/s Society for clean earth, Vatva. Committee disagree with proposal of sending waste water to
CMEE/spray dryer facility at Vatva which is critical polluted area(CPA).Committee asked about area
adequacy for proposed expansion, PP informed that at a time only two products instead of proposed all
products manufactured, Hence Committee asked for submit revised product profile considering area
adequacy of proposed product. Committee noted about process waste generation quantity and Iron sludge
generation quantity discrepancy with respect to ToR issued by SEIAA. Committee deliberated on waste
water management, APCM, HW management, baseline data, EMP, CER etc.
• After deliberation, SEAC unanimously decided to consider the proposal after submission of the following
details.
1. Submit revised EIA report with mentioning revised product profile, Hazardous Waste Management
and Waste water disposal management. Ensure that there is no increase in production quantity and
16
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 16 of 129
pollution potential accordingly.
2. Submit membership certificate of CMEE/ spray dryer facility other than located at GIDC Vatva area
for additional waste water of proposed expansion project.
3. Submit revised Hazardous Waste matrix considering process waste and iron sludge generation.
• Project proponent made presentation for the above mentioned query on dated 03.10.2019 for the above
mentioned points.
• PP submitted revised product profile as below with subsequent change in salient features of proposed
project,
Sr.
no.
Name of the Products CAS no. /
CI no.
Quantity
MT/Month
End-use of the
products
Existing Proposed Total
1. Meta Amino Phenol 591-27-5 22.2 102.8 125 Dyes
Manufacturing 2. Aniline 2:5 Di sulfonic
Acid (ADSA)
98-44-2
3. Aniline 2:4 Di sulfonic
Acid (ADSA)
137-51-9
-
4. 2-Pyridone 142-08-5
5. G – Salt 842-18-2
6. 1-Amino 7-Napthol 118-46-7
7. Ortho Amino Phenol
Sulfonamide
98-32-8
8. 1,6 Naphasultan 629-11-8
9. Amido G Salt 86-65-7
10. 4,4-Diamino Benzanilide 785-30-8
11. 4-Nap 99-57-0
12. DMAP
Dimethyl Amino Phenol
91-68-9
Total 22.8 102.8 125
• Salient features of the project including Water, Air and Hazardous waste management (Revised):
Sr. no. Particulars Details
A
17
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 17 of 129
A Total cost of Proposed Project
(Rs. in Crores):
5 Cr.
Details of EMP
Brief details of EMP
Component Capital Cost of EMP Recurring Cost of EMP
(Per Year)
Total Cost 31 Lac 6.45 Lac
Bifurcation of EMP Cost
Sr.
No
System Approximate
recurring
cost per
annum
(in Lacs)
Approximate
capital cost
(Rs. In Lacs)
Basis for cost estimates
1 Air pollution
control
3.0 15.0 The capital cost would
include cost of providing
adequate height of the
stack, ladder and platform,
Air Pollution Control
Systems and recurring cost
would include cost of
monitoring of air
environment.
2 Water
pollution
control
2.0 10.0 Capital cost would include
cost of ETP. In capital cost
civil work, mechanical work,
Electrical work and piping
work is included. Recurring
cost is for ETP Operation &
Spray Drying Cost for
evaporation
3 Noise 0.25 1.0 The recurring cost would
18
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 18 of 129
pollution
monitoring
include cost of noise
monitoring.
4 Environment
Monitoring
and
Management
& Laboratory
0.20 1.0 The recurring cost would be
incurred on hiring of
consultants and payment of
various statutory fees to
regulatory agencies.
5 Green Belt
& Rain water
harvesting
0.20 1.0 Development of Greenbelt
including Gardening and
Plantation.
6 Occupational
health (OHC) 0.25 1.0
Occupational health check
up of Employees and
workers
7 Rain Water
Harvesting 0.50 2.0
Capital cost would include
cost of rain water
harvesting system.
Total 6.40 31.0
Details of CER as per OM dated 01/05/2018
Sr. No. Activities Social Benefits Expenses (Rs. Lacs)
1. Greenbelt
(Naroda GIDC,
Muthiya Village)
• Greenery for
ecological balance
• Enrich local
biodiversity
• Control Air and
Noise pollution,
windbreak
• Helpful to control
soil erosion
• Plan for plantations
2
19
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 19 of 129
2. Water Utilize
(Muthiya Village)
• Drinking & sanitation
facilities in schools of
nearby villages
1
Total 3
Cost in Lacs/Yr
2019-2020 2020-2021 2021-2022
− 1.0 Lacs for drinking
water facility provided .
_Providing drinking water
facility (Water Jug) at road
side.
− 0.50 Lacs for Education at
Muthiya village
_With the help of local Trust
(For Education) & NGO
_Stationary provided at
Primary School at Muthiya
Village.
− 0.5 Lacs for drinking
water facility provided in
Muthiya village.
− 1.0 Lacs for trees
Plantation (Along with
Road Side) with help of
local people.
Total: 2.0 Lacs Total: 0.5 Lacs Total: 0.5 Lacs
B Total Plot area ( sq. meter)
Existing: 900.Sq. m.
Proposed: 00 Sq. m.
Total: 900 Sq. m.
Green belt area
( sq. meter)
Existing: 00.Sq. m.
Proposed: 44 Sq. m.
Total: 44 Sq. m.
C Employment generation
Existing: 19
Proposed: 0
Total:19
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC, Naroda
Status of permission from the concern authority. NA
20
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 20 of 129
Ii
Water consumption (KLD)
Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(C) Domestic 0.6 1 1.6 1.6 fresh
(D) Gardening - 0.4 0.4 0.4 fresh
Industrial
Process 2.4 47.6 50.0
12 fresh +38 recycled
treated w/w
Washing 1.0 3.0 4.0 4.0 fresh
Boiler 0.5 4.5 5.0 5.0 fresh
Cooling -- 5.0 5.0 5.0 fresh
Scrubber 0.1 1.9 2.0 2.0 fresh
Industrial Total 4.0 62.0 66.0
28 fresh + 38
recycled treated w/w
Grand Total
(A+B+C) 4.6 64.4 68.0
30 fresh + 38
recycled treated w/w
1) Total water requirement for the project: 68.0 KLD
2) Quantity to be recycle: 38 KLD
3) Total fresh water requirement: 30 KLD
Iii
Waste water generation (KLD)
Category Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(B) Domestic 0.5 0.8 1.3
Discharge to
soak pit
Industrial
21
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 21 of 129
Process 1.8 45.3 47.1 -
Washing 1 3 4 -
Boiler 0.1 0.8 0.9 -
Cooling - 1 1 -
Scrubber 0.1 0.9 1 -
Total Industrial
Waste Water 3 51 54
-
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP
etc.
� ETP (Primary) + Tertiary (RO)
Treatment scheme including segregation at source.
Domestic: Soak pit
Industrial: ETP (Primary) + Tertiary (RO)
Note: (In case of CETP discharge) :
Management of waste water keeping in view direction under section 18 (1)
(b) of the Water (Prevention and Control of Pollution) act, 1974 issued by
CPCB regarding compliance of CETP.
� As unit will be provided tertiary treatment the discharge quality and quantity to
the CETP, Naroda. And hence the unit will be comply Management of waste
water keeping in view direction under section 18 (1) (b) of the Water
(Prevention and Control of Pollution) act, 1974 issued by CPCB regarding
compliance of CETP.
Brief note on adequacy of ZLD (In case of Zero Liquid Discharge):
� 3 KLD sent to the CETP, NEPL as per existing consent.
Remaining RO permeate 38 KLD reuse in the Process and RO Rejected 13 KLD
sent to the common spray drying facility of Society for Clean and Green
Environment Naroda.
V Mode of Disposal & Final meeting point
22
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 22 of 129
Domestic:
Soak Pit
Industrial:
CETP, Naroda: 3.0 KLD RO permeate
Common Spray Drying Facility: 13.0 KLD
Recycled in process: 38.0 KLD
Vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE
etc. Name of CF
CETP, Naroda: 3.0 KLD RO permeate
Common Spray Drying Facility: 13.0 KLD
(Society for Clean & Green Environment, Naroda & NEPL Naroda.)
Membership of Common facility (CF)
(For waste water treatment)
Not Required membership as unit will be achieved ZLD.
vii Simplified water balance diagram with reuse / recycle of waste water
viii Reuse/Recycle details (KLD)
23
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 23 of 129
Total reuse:38 KLD
Source of waste
water for reuse
with quantity in
KLD
Application area with
quantity in KLD
Remarks regarding
feasibility to reuse
i.e. w/w
characteristics (COD,
BOD, TDS etc.)
Diluted steam of
ETP
Manufacturing process 38
KLD
PH: 7.2
COD:500 mg/l
BOD:50 mg/l
TDS: 2500 mg/l
SS: 5 mg/l
Oil & Grease: 1.0 mg/l
Not be any effluent Recycle/Reuse.
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
KVA etc.
SR
.
no
.
Source of
emission
With Capacity
Stack
Height
(meter)
Type of
Fuel
Quantity
of Fuel
Type of
emissions
i.e. Air
Pollutants
Air
Pollution
Control
Measures
(APCM)
1.
IBR Boiler
(600 kg/hr.)
(Nos-1)
12 Natural
Gas
( 600
SCM /
Day)
Particulate
Matter,
SO2,
NOx
Adequate
Stack
Height
2.
HAG
(500 kg / hrs.)
(Nos- 1)
12
Natural
Gas
( 150
SCM /
Day)
Particulate
Matter,
SO2, NOx
Adequate
Stack
Height
3. TFH
(4lac kcal) 12
Natural
Gas
( 100
SCM /
Particulate
Matter,
Adequate
Stack
24
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 24 of 129
(Nos 3) Day) SO2, NOx Height
4.
TFF
(2lac kcal)
(No.1)
12
Natural
Gas
( 100
SCM /
Day)
Particulate
Matter,
SO2,NOx
Adequate
Stack
Height
5.
DG Set
(125 KV Stand
by) (Nos- 1)
12 LDO
(6
Litre/hr)
Particulate
Matter,
SO2, NOx
Adequate
Stack
Height
ii Process gas emission details i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx
etc.)
Sr.
no. Source of emission
Type of
emissio
n
Stack/Vent
Height (meter)
Air Pollution
Control
Measures
(APCM)
1. Dumping vessel
Product;
6 MAPSA, Aniline 2:5 Di
sulfonic Acid, Aniline 2:4
Di sulfonic Acid, G-salt,
4,4-Diamino Benzanilide, 4
NAP
SO2
&SO3
12 Alkali
Scrubber
2 Vent attached to the
Reaction Vessel
6 MAPSA, Aniline 2:5 Di
sulfonic Acid, Aniline 2:4
Di sulfonic Acid, G-salt,
4,4-Diamino Benzanilide, 4
NAP
SO2
SO3
HCl
12 Water & Alkali
Scrubber
3 Vent attached to the
Reaction Vessel-ONCBSA
product
NO2 12 Alkali
Scrubber
25
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 25 of 129
4 SFD
(Drying Process)
Particulat
e Matter - Duct Collector
iii Fugitive emission details with its mitigation measures:
As below:
Proposed project is of manufacturing of S. O. Chemicals. Followings measures will
take for existing & proposed project.
• Maintaining the house keeping regularly
• Transferring the liquid materials by pump
• To carry out regular leak detection and repair activities
Proper routine maintenance of equipment reduces the likelihood of leaks.
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
i S
r
.
n
o
.
Type/
Name of
Hazardo
us waste
Source of
generatio
n
Categor
y and
Schedul
e as per
HW
Rules.
Quantity
(MT/Annum)
Disposal Method
Exist
ing
Prop
osed
After
Propo
sed
1
.
ETP
Waste
ETP
35.3
0.24
0
8.760 9.00 Collection,
Storage,
Transportation,
Disposal at
Authorized TSDF
site.
2 Process
Waste
Manufact
uring
process
of MAP
26.1 48 917.0 965.0 Collection,
Storage,
Transportation,
Disposal to the
cement factory for
co-processing.
3 Used oil Machiner 5.1 0.02 0.5 0.52 Collection,
26
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 26 of 129
y Storage,
Transportation,
Disposal by selling
to Registered
recycler.
4 Discarde
d
Containe
r
Raw
material
33.1
4.2
.
5.0
9.2
Collection,
Storage,
Transportation &
Disposal by selling
to Authorized
Decontaminator.
5 Bleed
Scrubbin
g Liquor
Scrubbin
g System
- 36 324 360 Collection,
Storage,
Transportation &
Treat in to ETP
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Enclosed in
EIA
Annexure X
iii Details of Non-Hazardous waste & its disposal(MSW and others) -
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery, reuse of recovered
Solvents etc. (Details in Table Format)
� There is no any solvent recovery but distillation will be carried out for
product purification.
ii VOC emission sources and its mitigation measures
Unit will provide closed transferring system of raw materials during manufacturing
to avoid any leakages.
H � Details regarding storage of Hazardous chemicals
27
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 27 of 129
Name of Raw
Materi
al
Storage
Facility /
Packing
Storage /
Packing
Capacity
(KL)
Storage
condition
Sulfuric Acid Tank/Drum 20 NTP
Oleum Tank 10 NTP
HCl Tank/Drum 10/38 NTP
Caustic Lye Tank 40 NTP
� Applicability of PESO :
� Not Applicable
• During SEAC meeting dated 03/10/2019, committee asked about revised product profile as per existing
CCA. PP informed that they have submitted revised product profile as per existing plant CCA-amendment
order. PP informed that they have considered worst case scenario for meta amino phenol. PP submitted
membership certificate of CMEE/common spray dryer for area other than CPA as per NGT order dated
10/07/19. Committee deliberated on process waste generation and iron sludge generation and its disposal.
Committee asked about change in production capacity and pollution load, technical expert of PP informed
that there is no increase in production capacity and pollution load and submitted revised product profile and
revised EIA report.
• After detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of
Environmental Clearance.
05. SIA/GJ/IND2/39334/2018
M/s. Paragon Poly Resins LLP
Survey No.: 782, Jakhwada, Ta -
Viramgam, Dist -Ahmedabad
EC – Reconsideration
Category of the unit : 5(f)
Project status: New
• PP has submitted online application vide no. SIA/GJ/IND2/39334/2018 dated 28/08/2019 for obtaining
Environmental Clearance.
28
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 28 of 129
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated
31/12/2018.
• Project proponent has submitted EIA Report prepared by M/s: T.R.Associates based on the TOR issued by
SEIAA.
• Public Hearing was conducted by Gujarat Pollution Control Board on 07/07/2019 at project site of
M/s:Paragon Poly Resins LLP located at Survey No.: 782, Jakhwada, Ta -Viramgam, Dist -Ahmedabad.
• This is a new unit proposes manufacturing of synthetic organic chemicals as tabulated below:
Sr.
No.
Name of the
Products CAS no. /CI no.
Quantity
MT/Month
End-use of products
1 Alkyd Resin
68333620 2000 Paints, Pigment paste, Ink,
Varnish, etc.
2 Polyamide Resin 63428842 1500 Ink, Pigment paste, etc.
3 Polyester Resin
Not available 2000 Lamination sheet, Mold,
roof, general purpose, etc.
4 Acrylic Resin
028262-63-7 2500 Paints, Emulsion,
Thickener, etc.
5 Rosin Ester 8050315 500 Paints, varnish, Ink, etc.
6 Epoxy Resin
25068386 1500 Lamination sheet, Varnish,
Pigment paste, etc.
7
Phenol
Formaldehyde
Resin
9003354
25 Lamination sheet, roof,
mold, etc.
8
Melamine
Formaldehyde
Resin
9003081
25 Lamination sheet, roof,
paints, varnish, etc.
9
Urea
Formaldehyde
Resin
27967299
25 Lamination sheet, roof,
paints, varnish, etc.
10 Ketonic Resin 25054062 5 Lamination adhesive, etc.
29
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 29 of 129
Total 10080 --
• The project falls under Category B of project activity 5(f) asper the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 17/09/2019.
• During the meeting dated 17/09/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted
for the study area of 10 km radial distance from project site for the period October 2018 to December 2018.
Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, CO and VOC at Eight
locations, including the project site. Values conform to the prescribed standards for Ambient Air Quality. The
incremental Ground Level Concentration (GLC) has been computed using AERMOD model. The resultant
concentrations are within the NAAQS. The modeling study proved that the air emissions from the proposed
plant would not affect the ambient air quality of the region in any significant manner. The ambient air quality
around the proposed project site will remain within the National Ambient Air Quality Standards (NAAQS).
The pH of the ground water samples varying from 8.03 to 8.44 which is within acceptable limit. Other
parameters are found to be well within permissible limits. However, Flouride is found higher than permissible
limit in all sampling locations. The soils of project site and Karakthal village have pH more than 8.5 indicating
that the soils are highly alkaline in nature. pH values of remaining soil samples ranging from 7.66 to 8.36
revealing moderately alkaline soils.
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• This is a green field project in Viramgam area and is out of notified area.
• During SEAC meeting, Committee asked about CGWA permission for ground water source, PP informed
that they have applied for CGWA permission and still not obtained CGWA permission. Committee
deliberated on issues raised during public hearing of proposed project, Technical expert of project proponent
informed that they have submitted reply of written instruction received during public hearing. Committee
asked about status of ToR compliance as asked in written during public hearing of proposed project, PP
informed about compliance of ToR issued to proposed project. Committee disagree with specific ToR like
proposed project CER activity is not need based CER, adequacy of ETP and Evaporator for waste water
treatment solvent wise LDAR etc., technical expert of PP could not satisfied ToR compliance during
meeting.
30
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 30 of 129
• After deliberation, SEAC unanimously decided to consider the proposal after submission of the following
details.
1. Status of permission from CGWA for withdrawal of Ground water.
2. Technical justification regarding adequacy of in-house evaporator with stoichiometric mass balance
and reduction in pollutant.
3. Treatability report for ETP with stage wise reduction of pollutant.
4. Submit revised need based CER activity in nearby affected villages of proposed project.
5. Submit solvent wise LDAR programme with details regarding solvent generation, solvent recovery and
solvent losses at each stage in plant.
6. Ensure that all the ToR Points are complied in letter and spirit.
• Project proponent made presentation for the above mentioned query dated 03.10.2019 for the above
mentioned points.
• PP presented replied as below:
1. Status of permission from CGWA for withdrawal of Ground water.
2. Technical justification regarding adequacy of in-house evaporator with stoichiometric mass balance
and reduction in pollutant.
3. Treatability report for ETP with stage wise reduction of pollutant.
4. Submit revised need based CER activity in nearby affected villages of proposed project.
5. Submit solvent wise LDAR programme with details regarding solvent generation, solvent recovery and
solvent losses at each stage in plant.
6. Ensure that all the ToR Points are complied in letter and spirit.
• Salient features of the project including Water, Air and Hazardous waste management (Revised):
Sr.
no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
9.5 Crores
Details of EMP Capital cost : 97 Lakh
Recurring cost : 60
Lakh/Annum
Details of CER as per OM dated 01/05/2018 19 Lakh Rs.
B Total Plot area ( sq. meter) 16532 m²
Green belt area 5546 m²
31
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 31 of 129
( sq. meter)
C Employment generation Total 70
60 Local
10 Permanent
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
Borewell
Status of permission from the concern authority.
CGWA application in process
& it is in verification stage
ii Water consumption (KLD)
Category
Quantity
KLD
Remarks
(E) Domestic 4.5 Fresh
(F) Gardening 5.5 Fresh
(G) Industrial
Industrial Activity
Process 0 --
Washing 1.2 Reuse
Cooling 13 Reuse
Industrial Total 14.2 (14.2
Reuse)
Reuse
Total (A + B + C) 10 Total fresh Water Requirement
1) Total water requirement for the project: 24.2 KLD
2) Quantity to be recycled: 14.2 KLD
3) Total fresh water requirement: 10.0 KLD
iii Waste water generation (KLD)
Category Waste water
KLD
Remarks
(C) Domestic 3.8 To soak pit
32
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 32 of 129
Industrial Activity
Process 13.6
To ETP
Washing 1.1
Boiler 0
Cooling 1.3
Total Industrial
waste water
16.0
Total [A + B] 19.8
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
Name of the Units Capacity No. of Units
Collection cum Neutralization Tank 20 KL 2
Chemical Oxidation Tank 20 KL 1
Nutsche Filter / Settling Tank 20 KL 1
Holding Tank 20 kL 1
Evaporator 1.5
KL/Hr.
1
Treatment scheme including segregation at source.
o Industrial wastewater will be generated from process, cooling tower (blow-down) & washing.
o Wastewater generated from washing and process will be collected in collection cum neutralization
tank. Then wastewater will be given Chemical Oxidation treatment.
o After completion of Chemical Oxidation Treatment, wastewater will be taken to Nutch Filter/Settling
Tank for chemical sludge separation.
o Treated wastewater and cooling tower blow down will be collected in holding tank. After that it will be
sent to Evaporator followed by Condenser. Condensate water will be reused for industrial process.
o ETP sludge along with evaporation residue from Evaporator will be disposed off at TSDF site. Thus,
unit will maintain ZERO LIQUID DISCHARGE.
Note: (In case of CETP discharge) :
Management of waste water keeping in view direction under section 18 (1) (b) of the Water
(Prevention and Control of Pollution) act, 1974 issued by CPCB regarding compliance of CETP.
� NOT APPLICABLE
33
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 33 of 129
Brief note on adequacy of ZLD (In case of Zero Liquid Discharge):Industrial wastewater will be
generated from process, cooling tower (blow-down) & washing activities. Wastewater will be generated
from washing and process will be collected in collection cum neutralization tank. Then wastewater will
be given Chemical Oxidation treatment. After completion of Chemical Oxidation Treatment, wastewater
will be taken to Nutch Filter/Settling Tank for chemical sludge separation. Treated wastewater and
cooling tower blow down will be collected in holding tank. After that it will be sent to Evaporator followed
by Condenser. Condensate water will be reused for industrial process. ETP sludge along with
evaporation residue from Evaporator will be disposed off at TSDF site. Thus, unit will maintain ZERO
LIQUID DISCHARGE.
v Mode of Disposal & Final meeting point
Domestic:
Soak Pit via Septic Tank
Industrial:
To ETP, Reused in industrial activities, so the unit will maintain ZERO
Discharge
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. , Name of CF
Not Applicable
vii Simplified water balance diagram with reuse / recycle of waste water
34
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 34 of 129
viii Reuse/Recycle details (KLD)
Total reuse 14.2 KLD
Source of waste
water for reuse
with quantity in
KLD
Application area with
quantity in KLD
Remarks regarding
feasibility to reuse i.e.
w/w characteristics
(COD, BOD, TDS etc.)
From ETP 14.2 KLD Various Industrial
Activities 14.2 KLD
-
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Thermic Fluid Heater : 8 Lac Kcal./Hr. X 2 nos.,
Thermic Fluid Heater (1 No. stand-by): 6 Lac Kcal./Hr. &
35
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 35 of 129
DG set (1 No. stand-by): 250 HP
Sr.
no.
Source of
emission
With
Capacity
Stack
Height
(meter)
Type of
Fuel
Quantity
of Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air
Pollution
Control
Measures
(APCM)
1
Thermic
Fluid
Heater -
1 (8
Lakh
Kcal/Hr.)
30 m Bio-Coal &
Coal
5.0
MT/day &
3.5
MT/day.
SPM, SO2,
NOx
Multi
Cyclone
Separator
followed by
Bag - Filter
2
Thermic
Fluid
Heater –
2 (8
Lakh
Kcal/Hr.)
3
Thermic
Fluid
Heater –
3 (stand-
by)
(6 Lakh
Kcal/Hr.)
4
D. G.
Set
(1 X 250
HP)
5 HSD 43.33
liters/hr.
SPM, SO2,
NOx
Adequate
stack
height
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOxetc.)
There will be no process gas emission from manufacturing process
iii Fugitive emission details with its mitigation measures.
36
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 36 of 129
As below:
There are chances of fugitive emissions due to manufacturing activities and storage & handling of raw
materials. Also, during operation stage, leakages through valves, pumps, emission from open drums
containing chemicals, storage tanks, etc. are the major sources of fugitive emissions. Following
measures are adopted to prevent and control fugitive emissions:
• All the raw materials are stored in isolated storage area and containers are kept tightly closed.
• Entire manufacturing activity is carried out in closed reactors / vessels and regular checking and
maintenance of the same will be carried out to avoid any leakages.
• All the motors of pumps for the handling of hazardous chemicals are flame proof and provided
with suitable mechanical seal with stand-by arrangement.
• The control of all parameters on a continuous basis is done by adequate control valves, pressure
release valves and safety valves etc.
• All the flange joints of the pipe lines are covered with flange guards.
• The spillages / leakages of specific chemical will be collected and used or drained to effluent
treatment plant.
• Precautionary measures are taken while handling various hazardous chemicals.
• There will be provisions of adequate ventilation systems in process plant and hazardous
chemical storage area.
• A regular preventive maintenance will be planned to replace or rectify all gaskets, joints etc.
• Transporters will be instructed to cover the trucks by tarpaulin sheets.
• TREM card will be provided to the driver during the transportation of Hazardous raw
materials/products.
• Sufficient information and training regarding characteristics and immediate actions in case of any
spillage or accident during transportation of hazardous chemical will be provided to the driver.
• The unit will develop green belt area within the factory premises to control the fugitive emissions
from spreading into surrounding environment.
• Moreover, unit will carry out regular work place monitoring.
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Trans boundary Movement) Rules 2016.
i
Sr. Type/Name Specific Category Quantity Management of
37
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 37 of 129
no. of
Hazardous
waste
Source of
generation
(Name of
the
Activity,
Product
etc.)
and
Schedule
as per
HW
Rules.
(MT/Annum) HW
1 Used oil Plant and
Machineries 5.1
1.5
MT/Annu
m
Collection,
storage and Use
within premises
as a lubricant/
sell to registered
recycler
2
Discarded
Plastic
bags/Barrels
Raw
Material
Storage
Area
33.1
1260
MT/Annu
m
Collection,
storage and
decontamination
or Reuse within
premises/ sell to
approved scrap
vendor
3 ETP Sludge ETP 35.3
48.0
MT/Annu
m
Collection,
storage and
Disposal at
TSDF Site
4 Evaporation
Residue ETP 35.3
36.0
MT/Annu
m
Collection,
storage and
Disposal at
TSDF Site
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Unit will become member of
TSDF after obtaining
Environmental Clearance
iii Details of Non-Hazardous waste & its disposal None
38
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 38 of 129
(MSW and others)
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents etc. (details in
table format)
� All solvents used in process will be used as dilution purpose.
� Solvents will be directly pumped into reactors/day tanks from the storage tanks and drums
without involving any manual handling.
� VOC detection sensors will be provided with alarm system. Flame proof wiring and flame proof
electrical accessories shall be provided to avoid any mishap.
ii VOC emission sources and its mitigation measures
� Pump with double mechanical seals will be provided to control VOC emission
� Regular work place area monitoring will be carried out to find out concentration level in ambient air.
� Provision will be made for breather valve cum flame arrester to the solvent storage tank
� Routine & periodic inspection to check leakage and Preventive maintenance as well SOP will be
followed for maintenance.
H � Details regarding storage of Hazardous chemicals
Storage details Name of major Hazardous
chemicals
Remarks
Storage tanks
1. Toluene/Xylene/MTO/
C-9/Slop oil
-
Drum/Barrel storage
Ethylene diamine,
Methacrylate, Acrylates,
Rosin, Cyclohexanone
-
� Applicability of PESO : will be obtained from PESO Department after getting EC.
• During SEAC meeting committee asked about reply of previous meeting query, technical expert of PP
informed that they have applied for CGWA permission for ground water source in respective authority.
Committee asked about stage wise reduction in pollutants in ETP and adequacy of in-house evaporator,
technical expert of PP informed that COD, BOD and TDS reduction in stage wise ETP units and in
evaporator. Committee disagree with adequacy of in-house evaporator and stage wise reduction of pollutant
I ETP and insisted for third party NABL accredited academic institute treatability and adequacy report for
ETP and in-house evaporator. Committee deliberated on CER and LDAR programmed details which was
39
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 39 of 129
not presented precisely by technical expert of PP.Committee insisted for submit LDAR programme for
solvent with mentioning about solvent losses at each stage like storage, pipeline, pumps, reactors etc. and
need based CER
After deliberation, SEAC unanimously decided to consider the proposal only after submission of the
following details.
1. Submit revised need based CER activity in nearby affected villages of proposed project.
2. Submit solvent wise LDAR programme with details regarding solvent generation, solvent recovery and
solvent losses at each stage like storage, pipeline, pumps, valves, reactor etc. in plant area in place of
conventional note regarding LDAR programme.
3. Adequacy and Treatability report by recognized schedule I auditor regarding proposed ETP units and
in-house evaporator. Stage wise reduction in pollutants like COD, BOD, TDS etc. shall be
incorporated.
4. Ensure that all the ToR Points are complied in letter and spirit.
06. SIA/GJ/IND2/38454/2018
M/s. Ven Petrochem And Pharma India
Pvt. Ltd.
Nos.2903,05,07,09,10,& 2704 to 2708,
GIDC, Sarigam, Ta- Umbergaon, Dist -
Valsad.
EC – Reconsideration
Category of the unit : 5(f)
Project status: Expansion
• Project proponent (PP) submitted online application vide no. SIA/GJ/IND2/38454/2018dated 31/07/2019 for
obtaining Environmental Clearance.
• SEIAA issued TOR to PP vide their letter dated 10/01/2019.
• Project proponent has submitted EIA Report prepared by Anand Environmental Consultants Pvt Ltd,
Ahmedabadbased on the TOR issued by SEIAA.
• This is an expansion project for manufacturing of synthetic organic chemical as tabulated below.
Sr.
no.
Name of the Products CAS no. /
CI no.
Quantity MT/Month End-use of the products
Existing Proposed Total
1 Acebrophylline
179118-73-1 0.0
1.0 1.0 Anti-mucolytic
(for cough)
2 Ambroxol Hydrochloride 23828-92-4 0.0 6.6 6.6 Anti-mucolytic
40
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 40 of 129
(for cough)
3 Bromhexine Base
3572-43-8 0.0 1.0 1.0 For manufacture of
Bromohexine Hydrochloride
4 Bromhexine Hydrochloride 611-75-6 3.0 3.0 6.0 Anti-mucolytic
(for cough)
5 Timolol Maleate 26921-17-5 0.0 1.2 1.2 Anti – Glaucoma
(for eye drops)
6 2-Amino-N-Methyl-N-
Cyclohexyl
Benzenemethanamine
57365-08-9 0.0 1.2 1.2 For manufacture of
Bromohexine Hydrochloride
Total 3.0 14.0 17
• The project falls underCategory B of project activity 5(f) asper the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 19/08/2019.
• During the meeting dated 19/08/2019, technical presentation made by the Project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report and
details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect for the study area of 10 km radial distance from project
site for the period January 2019 to March 2019. Ambient Air Quality monitoring was carried out for PM10,
PM2.5, SO2, NOx, HCl, HBr, & VOC as Benzene, Toluene & Xylene at eight locations, including the project
site. Values conform to the prescribed standards for Ambient Air Quality. The incremental Ground Level
Concentration (GLC) has been computed using AERMOD. The resultant concentrations are within the
NAAQS. The modelling study proved that the air emissions from the proposed plant would not affect the
ambient air quality of the region in any significant manner. The ambient air quality around the proposed
project site will remain within the National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• During SEAC meeting on 19/08/2019, committee noted that the proposal is for expansion. This unit has valid
CC&A for existing unit. Copy of CC&A, its compliance report is submitted. PP ensured that there are no
court cases pending and no public complaints against the project. Source of water is GIDC. PP mentioned
that entire effluent generated after expansion from process, washing & scrubber will be incinerated in in-
house incinerator or will be sent to co-processing in cement industries. PP mentioned that effluent generated
41
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 41 of 129
from boiler blow down & cooling tower blow down will be recycled back in the same process. Unit will
maintain complete ZLD. PP has proposed one boiler & one incinerator. Fuel used will be PNG. Committee
noted that PP has not addressed LDAR (Solvent Recovery) product wise and committee asked PP to submit
revised LDAR product wise. Committee also noted that PP has not addressed Hazardous Waste as per
HWR – 2016 and was asked the submit the revised table eliminating the by-product and incorporating the
same in Hazardous Waste Matrix. Committee also noted that PP has not satisfactorily address the likely
impacts of project and its mitigation measures along with technical details pertaining to best available
technologies (BAT) for the proposed project considering the expansion of existing products.
• After detailed discussion, it was decided to consider the proposal only after submission of the following
documents:
1. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for
use in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor
prevention of losses of solvents to the best minimum extent. Address all the solvents product wise
separately.
2. Technical Justification for direct recycle/reuse of utility effluent along with its treatability & feasibility.
3. Technical details of the plant/s along with details on best available technologies (BAT), proposed
technology and reasons for selecting the same.
4. Anticipated environmental impacts due to the proposed project/production may be evaluated for
significance and based on corresponding likely impacts VECs (Valued Environmental Components)
may be identified. Baseline studies may be conducted within the study area for all the
concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to
identify mitigation measures.
5. Revised Hazardous Waste Matrix addressing the by-product in Hazardous Waste as per HWR –
2016.
• Project proponent made presentation for the above mentioned query dated 03.10.2019 for the above
mentioned points.
• PP presented replied as below:
1. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for
use in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor
prevention of losses of solvents to the best minimum extent. Address all the solvents product wise
separately.
2. Technical Justification for direct recycle/reuse of utility effluent along with its treatability & feasibility.
3. Technical details of the plant/s along with details on best available technologies (BAT), proposed
42
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 42 of 129
technology and reasons for selecting the same.
4. Anticipated environmental impacts due to the proposed project/production may be evaluated for
significance and based on corresponding likely impacts VECs (Valued Environmental Components)
may be identified. Baseline studies may be conducted within the study area for all the
concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to
identify mitigation measures.
5. Revised Hazardous Waste Matrix addressing the by-product in Hazardous Waste as per HWR –
2016.
• Revised product profile as above submitted along with Salient features of the project including Water, Air
and Hazardous waste management (Revised):
Sr.
no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Existing: INR 4.50 Crores
Proposed : 20 Crores
Total : INR 24.50 Crores
Details of EMP
Sr. No.Area of
Expenditure
Capital
Cost
(Rs.)
Recurring
Cost /Annum
(Rs.)
Remarks
1. Air Pollution
Control
30,00,000 10,00,000 Capital cost would include air pollution
control devices and the recurring cost
would include operation and maintenance
of pollution control devices and stack
monitoring.
2. Water Pollution
Control
40,00,000 20,00,000 Capital cost would include cost of septic
tank and recurring cost would include
maintenance charges of incinerator,
manpower salary etc.
3. Noise Pollution
Control
2,00,000 1,00,000 Capital cost would include providing
adequate sound enclosures and recurring
cost would include monitoring of noise
level.
43
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 43 of 129
4. Solid Waste
Pollution
Control
20,00,000 2,00,000 Capital cost would include expense for
providing storage area for hazardous
waste and recurring cost would be for
solid/ hazardous waste packing and for the
membership of TSDF site.
5. Green Belt 2,50,000 1,00,000 Capital cost would include development of
green belt and recurring cost would include
maintenance charges.
6. Rain Water
Harvesting
2,50,000 1,00,000 Capital cost would include development of
Rain water harvesting and recurring cost
would include maintenance charges.
7. Occupational
Health & Safety
3,00,000 1,00,000 Capital cost would include expense for
providing stock/storage of personnel
protective equipments and safety systems
etc. and recurring cost would include
maintenance charges.
Total 100,00,000 36,00,000 --
Details of CER as per OM dated 01/05/2018
Activities Budgetary cost
(Rs.)*
Implementation
schedule
� Awareness Program about the Government schemes
with the help of wall painting, IEC material, LED
presentation.
1,00,000 2020- 2021
� To establish R.O water system with the budget amount
of CER in villages. 2,00,000 2021- 2022
� Help village panchayats for existing deepen ponds to
increase the capacity of water consumption 5,00,000 2022- 2023
� To promote modern low cost techniques in farming
amongst the farmers 2,00,000 2023- 2024
� To organize medical camp for the villagers weekly or
monthly. 4,00,000 2024- 2025
� Construction of Public Toilets in urban areas / RCC
roads in rural areas within villages. 4,00,000 2025- 2026
44
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 44 of 129
� To provide solar panels to those households who does
not have electricity at their home with CER budget or
through government subsidy.
2,00,000 2026-2027
Total 20,00,000 2020 - 2026
B Total Plot area
( sq. meter)
Existing: 9690 Sq. m.
Proposed: 2300 Sq. m. (from 9690 sqm)
Total: 9690 Sq. m.
Green belt area
( sq. meter)
Existing: 970.67. Sq. m.
Proposed: 240 Sq. m.
Total: 1210.67 Sq.m. i.e. 1211 Sq. m
C Employment generation Existing: 83
Proposed: 62
Total: 145
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
G.I.D.C
Status of permission from the concern authority. Permission obtained from GIDC.
ii Water consumption (KLD)
Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(H) Domestic 4 4 8 --
(I) Gardening
1 1 2 --
(J) Industrial
Process 2.0 3.4 5.4 --
Washing 1.1 0.9 2.0 --
Boiler 12 12 24 --
Cooling 6 2 8 --
Others 0.1 0.2 0.3 --
Industrial Total 21.2 18.5 39.7 --
Grand Total (A+B+C) 26.2 23.5 49.7 --
45
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 45 of 129
1) Total water requirement for the project: 49.7 KLD
2) Quantity to be recycled: 12 KLD
3) Total fresh water requirement: 37.7 KLD
(Total water requirement = Fresh water + Recycled water)
(49.7 = 37.7 + 12)
iii Waste water generation (KLD)
Category Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(D) Domestic 2.4 2.4 4.8 --
(E) Industrial
Process 1.55 1.75 3.30 Incineration within premises.
Washing 1.1 0.9 2.0 Incineration within premises.
Boiler 4.5 3.5 8 Will be recycled.
Cooling 3.0 1.0 4 Will be recycled.
Others 0.1 0.2 0.3 Incineration within premises.
Total Industrial
waste water 10.25 7.35 17.6
--
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc.
� Existing : Capacity of Incinerator – 250 kg/hour , 2.75 KLD incinerated within premises, 7.5
KLD recycled back
� Proposed: Capacity of Incinerator –500 kg/hour, 2.85 KLD will be incinerated within premises,
4.5 KLD will be recycled back after treatment.
� i.e., after expansion total 5.6 KL/day will be incinerated within premises and 12 KL/day will be
recycled.
Treatment scheme including segregation at source. (Give Characteristics of each stream i.e.
COD, BOD, TDS etc.)
� 4.8 KL / day domestic waste water generated will be disposed into septic tank /soak pit system.
� 17.6 KL/day industrial waste water generated out of which 5.60 KL / day (3.30 KLDfrom
Process + 2.0 KLD from Washing + 0.3 KLD from Scrubber) will be incinerated in an incinerator
within premises AND 12 KL / day (8 KLD from boiler + 4 KLD from cooling) will be recycled.
46
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 46 of 129
Note: (In case of CETP discharge) :
Management of waste water keeping in view direction under section 18 (1) (b) of the Water
(Prevention and Control of Pollution) act, 1974 issued by CPCB regarding compliance of
CETP.
� NOT APPLICABLE.
Brief note on adequacy of ZLD (In case of Zero Liquid Discharge):
� Unit maintains ZLD by incinerating industrial waste water in an incinerator within premises
and the same practice will be continued after expansion.
V Mode of Disposal & Final meeting point
Domestic: 4.8 KL / day (existing + proposed) domestic waste water generated will be disposed
into septic tank /soak pit system.
Industrial:
5.60 KL / day (3.30 KLD from Process + 2.0 KLD from Washing + 0.3 KLD from
Scrubber) (existing + proposed) will be incinerated in an incinerator within premises,
12 KL / day (8 KLD from boiler + 4 KLD from cooling) (existing + proposed) will be
recycled back.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE, CHWIF etc.
Name of Common facility (CF)(For waste water treatment)
� Not Applicable
Membership of Common facility (CF)
(For waste water treatment)
� NOT APPLICABLE
vii Simplified water balance diagram with reuse / recycle of waste water
47
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 47 of 129
vii Reuse/Recycle details (KLD)
[Source of reuse & application area]
Total reuse 12 KLD
Source of waste
water for reuse with
quantity in KLD
(From where it is
coming)
Application area
with quantity in
KLD (Where it is
used)
Characteristics of
waste water to be
reused (COD, BOD,
TDS etc.)
Remarks regarding
feasibility to reuse i.e.
Boiler condensate
and cooling water
purge will be the
source of waste water
generated which is
planned to be used.
Approximately 8
KLD of boiler
condensate and 4
KLD of cooling
purge water will
be reused back
into the boiler as
well as back for
cooling makeup
� pH : 7- 8.5
� Suspended Solids
: 150 – 200 mg/l
� TDS:1000– 1200
mg/l
� Oil & Grease: 5 -
10 mg/l
� COD : 80-100
mg/l
� BOD : 10-20 mg/l
It is completely feasible
to use for Boiler &
cooling
E Air
i Flue gas emission details
48
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 48 of 129
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Existing & Proposed
- Existing
Sr.
no.
Source of
emission
With Capacity
Stack
Height
(meter)
Type of
Fuel
Quantity of
Fuel
Type of
emissions i.e.
Air Pollutants
Air Pollution
Control
Measures
(APCM)
1 Boiler
1000 kg / hour
11 PNG 25 scm/hr PM
SO2
NOX
--
2 D.G. Set
(250 KVA)
5 Diesel 25 lit/hr PM
SO2
NOX
--
3. Incinerator
(250 kg/hr)
30** PNG
25 scm/hr PM
SO2
HCl
Dust Collector
followed by
scrubber
- Proposed
Sr.
no.
Source of
emission
With Capacity
Stack
Height
(meter)
Type of
Fuel
Quantity of
Fuel
Type of
emissions i.e.
Air Pollutants
Air Pollution
Control
Measures
(APCM)
1 Boiler
1000 kg / hour
12 PNG 25 scm/hr PM
SO2
NOX
--
2 D.G. Set
(250 KVA)
5 Diesel 25 lit/hr PM
SO2
NOX
--
3. Incinerator
(500 kg/hr)
30** PNG
50 scm/hr PM
SO2
HCl
Dust Collector
followed by
scrubber
** This will be a common stack for existing as well as proposed expanded incinerator
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
49
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 49 of 129
Existing & Proposed
-Existing
Sr.
no.
Specific Source of
emission
(Name of the
Product &
Process)
Type of
emission
Stack/Vent
Height (meter)
Air Pollution Control
Measures
(APCM)
1 Bromination
Vessels
(2 Nos).
(Bromohexine
Hydrochloride &
During bromination
reaction )
HBr
Br2
12 Two separate two Stage Alkali
Scrubber
- Proposed
Sr.
no.
Specific Source of
emission
(Name of the
Product &
Process)
Type of
emission
Stack/Vent
Height (meter)
Air Pollution Control
Measures
(APCM)
1 Bromination
Vessels
(2 Nos).
(Ambroxol
Hydrochloride/
Acebrophylline &
During Bromination
reaction,
Bromhexine base
& During
HBr
Br2
10 Two separate two Stage Alkali
Scrubber
50
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 50 of 129
Bromination
reaction)
iii Fugitive emission details with its mitigation measures.
� Concrete road is/will be developed within plot premises to avoid fugitive dust due to vehicle
movement.
� Manufacturing activity will be carried out in closed reactors / vessels and regular checking and
maintenance of the same will be carried out to avoid any leakage and relative fugitive emissions.
� All the raw materials will be stored in closed containers and in sealed bags and will be handled
through closed system to avoid the handling losses and relative fugitive emissions.
� Water sprinkling will be done to avoid dust emission.
F Hazardous waste
(As per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016.
Existing & Proposed
I Sr.
no.
Type/Name
of
Hazardous
waste
Specific
Source of
generation
(Name of the
Activity,
Product etc.)
Catego
ry and
Sched
ule as
per HW
Rules.
Quantity
(MT/Annum)
Management of HW
Existin
g
Propose
d
Tota
l
1 ETP Sludge
From Wet
Scrubbers 35.3
14.4 28.8 43.2 Collection, Storage,
Transportation and
Disposal at approved
TSDF.
From treatment
of water to be
recycled
-- 24 24
Total 14.4 52.8 67.2
2. Distillation
Residue
From
manufacturing
process
28.1 0.36 35.64 36 Collection, Storage,
Transportation and
disposed to cement
industries / RSPL –
Panoli for co -
processing.
3. Used Spent
Oil
From lubrication
or D.G. Set
5.1 0.08 11.92 12 Collection, Storage,
Transportation and
51
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 51 of 129
Disposal by selling to
registered
reprocessors.
4. Empty
barrels /
containers /
liners
contaminate
d with
hazardous
chemicals /
wastes
From raw
materials
33.1 2.7 27.3 30
Collection, Storage,
Decontamination,
Transportation and
Disposal by selling to
authorized recycler.
5. Spent
Carbon
From
manufacturing
process of
Acebrophylline,
Ambroxol
hydrochloride,
Bromhexine
Base,
Bromhexine
Hydrochloride,
Timolol
Maleate,2-
Amino-n-
methyl-n-
cyclohexyl
benzenemethan
amine
28.3 1.2 13.2 14.4 Collection, Storage,
Transportation and
Disposed to cement
industries / RSPL -
Panoli.
6. Incineration
Ash
From
Incinerator
37.2 35 51.4 86.4 Collection, Storage,
Transportation and
Disposal at approved
TSDF site.
52
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 52 of 129
7. Date
expired –off
specification
process
Expired
Products
28.4 0.005 0.115 0.12 Collection, Storage,
Incineration within
unit.
8. Sodium
Bromide
Solution**
From
manufacturing
process
- 128.4 1118.4 124
7
Collection, Storage,
and sold to
authorized end users
registered under
Rule -9 and users
having PCB
Approvals.
9. Dimethyl
Hydantoin**
From
manufacturing
process
- 6 13.2 19.2 Collection, Storage,
and sold to
authorized end users
registered under
Rule -9 and users
having PCB
Approvals.
10. Bleed
Liquor
From Scrubbing - 1.2 2.4 3.6 Collection, Storage,
Incineration within
premises.
**- By-Products
ii Membership details of TSDF, CHWIF
etc.
(For HW management)
BEAIL,RSPL,VWEMCL
iii Details of Non-Hazardous waste & its
disposal(MSW and others)
--
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery, reuse of recovered Solvents etc. (Details
in Table Format)
Name of Name of Input Output Loss Recovery Loss
53
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 53 of 129
Products Solvent (Kg/Month) (Kg/Month) (Kg/Month) (%) (%)
Bromhexine
Hydrochloride
Mono chlorobenzene
(Stage – 1) 18000 17640 360 98 2
Methanol
(Stage- 2) 18720 17800 920 95 5
Toluene
(Stage 2) 41280 39620 1660
96 4 (Stage 3) 34800 33490 1310
Total 76080 73110 2970
Industrial
spirit
(Stage 2) 12000 11520 480
96 4 (Stage 3) 39200 37630 1570
Total 51200 49150 2050
2-amino-n-
methyl-n-
cyclohexyl
benzenemeth
anamine
Mono chlorobenzene
(Stage 1) 7200 7056 144 98 2
Methanol
(Stage 2) 7488 7120 368 95 5
Toluene (Stage 2) 16512 15860 652 96 4
Bromhexine
base
Mono chlorobenzene
(Stage 1) 3150 3087 63 98 2
Methanol
(Stage 2) 3276 3115 161 95 5
Industrial
spirit
(Stage 2) 2100 2016 84
96 4 (Stage 3) 936 900 36
Total 3036 2916 120
Toluene
(Stage 2) 7224 6902 322
96 4 (Stage 3) 5740 5542.3 197.7
Total 12964 12444.3 519.7
Ambroxol
Hydrochloride
Methanol
(Stage -1) 56160 53400 2760 95 5
Toluene (Stage 1) 41280 39600 1680
96 4 (Stage 2) 10320 9900 420
54
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 54 of 129
(Stage 4) 51600 49560 2040
Total 103200 99060 4140
Industrial spirit
(Stage 3) 11700 11220 480 96 4
N-butanol (Stage 4) 15840 15240 600 96 4
Acebrophylline
Methanol (Stage 1) 6180 5870 310 95 5
Toluene
(Stage 1) 4540 4360 180
96 4
(Stage 2) 1135 1089 46
(Stage 4) 5676 5450 226
(Stage 5) 5830 5560 270
Total 17181 16459 722
Industrial spirit
(Stage 3) 1287 1235 52 96 4
Acetone
(Stage 4) 370 352 18
95 5 (Stage 5) 600 570 30
Total 970 922 48
N-butanol
(Stage 4) 1740 1670 70
96 4 (Stage 5) 3100 2980 120
Total 4840 4650 190
Timolol
maleate
Tert-butanol
(Stage 1 & 2) 5520 5280 240 96 4
Acetone
(Stage 3 & 4) 7680 7220 460 94 6
Toluene
(Stage 1 & 2) 6912 6528 384
95 5 (Stage 3 & 4) 5760 5520 240
Total 12672 12048 624
Recovered solvents will be reused in process.
ii VOC emission sources and its mitigation measures
� Closed loop systems, double mechanical seal pumps will be provided to reduce VOC emission
as much as possible.
55
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 55 of 129
H � Details regarding storage of Hazardous chemicals
Storage details Name of major Hazardous chemicals Remarks
Storage tanks Hydrochloric acid --
Drum/Barrel storage
Acetic acid, Acetone, Benzaldehyde,
Benzoic acid, Hydrazine hydrate,
Industrial spirit, Liquor ammonia,
Maleic acid, Methanol, Mono
chlorobenzene, N-butanol, N-
methylcyclohexylamine, Ortho nitro
benzaldehyde, Ortho nitro toluene,
Sodium hydride, Sodium
hydrosulphite, Soidum borohydride,
Tert-butanol, Theophylline, Toluene,
Trans-4-amino cyclohexanol
--
� Applicability of PESO: Available for existing and will be obtained for proposed project.
• During SEAC meeting dated 03/10/2019, Committee deliberated on query point regarding adequate LDAR
for solvents and BAT for proposed project, Technical expert of PP informed about each solvent
storage,handling, solvent recovery and solvent losses details. They informed that for control of solvent
losses, solvent will be transferred from barrels to reactor under vacuum and canister containing carbon
granules attached with vent of solvent barrels for control of VOC in atmosphere. PP informed that BAT for
convert nitro compound into amino compound by using hydrazine hydrate instead of conventional method.
And for manufacturing of Ambroxol Hydrochloride and Acebrophyline they will use an Aldehyde due to which
there will be no by-products as part of BAT in place of using esters. Committee asked about Technical
Justification for direct recycle/reuse of utility effluent along with its treatability & feasibility, technical expert of
PP informed that GIDC water supply is river water hence TDS value is only 300 mg/l as feed for boiler and
cooling tower. PP informed that they will reuse boiler blow down and cooling blow down after treatment like
for settling and filter method to treat for reuse. PP informed about the anticipated environmental impacts due
to the proposed project have been evaluated by carrying out the baseline status for the ambient air at 8
different locations for PM10, PM2.5, SO2, NOx, HCl, VOCs and HBr and informed results of ambient air
baseline data and mitigation measures for air pollution control. .Committee deliberated on Hazardous waste
details and technical expert of PP informed that previously mentioning by products is mentioned as
Hazardous waste and process wastewater will be incinerated in own incinerator instead of sending it to
56
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 56 of 129
cement industries for co-processing.
• After detailed discussion, it was decided to recommend the project to SEIAA, Gujarat for grant of
Environmental Clearance.
07. SIA/GJ/IND2/37351/2018
M/s. TransworldFurtichemPvt Ltd
Plot No. 353 to 367, Sector-4, KSEZ,
Gandhidham, Dist - Kutchh.
Appraisal
Category of the unit : 5(a)
Project status: New
• PP has submitted online application vide no SIA/GJ/IND2/37351/2018 dated 03/09/2019 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated
16/10/2018.
• Project proponent has submitted EIA Report prepared by M/s: EQMS India Pvt. Ltd. based on the TOR
issued by SEIAA
• This is a new unit proposes manufacturing of chemical fertilizer as tabulated below:
Sr.
No.
Name of the
Products
CAS no. /CI no. Quantity
MT/Month
End-use of products
1 SSP 8011 -76-55 6000 Used as fertilizer
2 GSSP 10031-30-8 6000
(Under CTE)
Used as fertilizer
• The project falls under Category B of project activity 5(a) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 03/10/2019.
• Salient features of the project are as under:
Sr.
no.
Particulars Details
A
A Total cost of Proposed Project
(Rs. in Crores):
5.0 Crores
Details of EMP 0.50 Crores
57
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 57 of 129
Details of CER as per OM dated 01/05/2018 10 Lacks
B Total Plot area ( sq. meter)
9600 Sq. m.
Green belt area
( sq. meter)
670 Sq. m.
C Employment generation
60 regular and 100
contractual persons
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply
etc...)
Water requirement will be
made available through
Gujarat water supply (NBCC)
Status of permission from the concern authority.
available
ii
Fresh Water consumption (KLD)
Category QuantityKLD Remarks
(K) Domestic 4.0
(L) Gardening 4.0
(M) Industrial
Process 40.4
Washing -
Boiler -
Cooling -
Others -
Industrial Total 40.4
Total (A + B + C) 48.4
1) Total water requirement for the project 60.4 KLD
2) Quantity to be recycled: 12 KLD
3) Total fresh water requirement: 48.4 KLD
(Total water requirement = Fresh water + Recycled water)
58
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 58 of 129
iii Waste water generation (KLD)
Category Waste waterKLD Remarks
(F) Domestic 3 Disposed in
septic
tank/soakpit
(G) Industrial
Process 12
Washing -
Boiler -
Cooling -
Others -
Total Industrial
waste water
12 Recycle back
in process
Total [A + B] 15
-
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc.
� Domestic waste shall be disposed in septic tank/ soakpit
� Process waste shall be reused in process for acid dilution.
Treatment scheme including segregation at source.
� NA
Note: (In case of CETP discharge) :Not Applicable
Management of waste water keeping in view direction under section 18 (1) (b)
of the Water (Prevention and Control of Pollution) act, 1974 issued by CPCB
regarding compliance of CETP.
�
Brief note on adequacy of ZLD (In case of Zero Liquid Discharge):
� About 15 KLD waste water shall be generated from the proposed unit. Out of
the total waste generated about 12 KLD shall be Process (Industrial) waste
and 3 KLD shall be domestic waste. Process waste shall be reused in
process for acid dilution, and domestic waste shall be disposed in Septic tank
and soak pit. The Effluent generation from the proposed unit will be Nil as the
59
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 59 of 129
unit will operate on a principal of “Zero Liquid Discharge” and no waste water
shall be discharge outside the plant premises.
v Mode of Disposal & Final meeting point
The unit will operate on a principal of “Zero Liquid Discharge” and no waste water
shall be disposed/discharge outside the plant premises.
Domestic:
3 KLD domestic waste shall be disposed in Septic Tank /soak pit
Industrial:
2 KLD shall be Process (Industrial) waste shall be reused in
process for acid dilution
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE
etc. Name of CF
� Not Applicable
Membership of Common facility (CF):
(For waste water treatment): NA
vii Simplified water balance diagram with reuse / recycle of waste water
60
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 60 of 129
viii Reuse/Recycle details (KLD)
Total reuseMM.KLD
Source of waste
water for reuse
with quantity in
KLD (From
where it is
coming)
Application
area with
quantity in
KLD (Where it
is used)
Characteristics of
waste water to be
reused (COD, BOD,
TDS etc.)
Remarks
regarding
feasibility
to reuse i.e.
Process Effluent 12 NA Reused for
acid dilution
61
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 61 of 129
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
KVA etc. NA
-
Sr.
no.
Source
of
emission
With
Capacity
Stack
Height
(meter)
Type
of
Fuel
Quantity
of Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air
Pollution
Control
Measures
(APCM)
ii Process gas emission details i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx
etc.)
Sr.
no.
Specific
Source of
emission
(Name of
the
Product &
Process)
Type of
emission
Stack/Vent
Height
(meter)
Air Pollution
Control
Measures
(APCM)
1 SSP Stack PM and
Fluoride
50
Cyclone
Separators,
Ventury
Scrubbers
2
Rock
drying
Section
Stack
PM
emission
30
Cyclone
Separators,
62
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 62 of 129
Granulation
Section
Stack
PM
emission
40
Cyclone
Separators,
-
iii Fugitive emission details with its mitigation measures:
As below:
There is no source of fugitive emission as such except during transportation of rock
phosphate and handling of SSP. The rock phosphate is proposed to be transported
under cover truck only. The SSP process happens under shed and powder is in
moist conditions. As such all products remains confine to shed area only even if
become air borne. All precaution and provision are made for arresting the dust
particle during crushing of rock and handling of SSP which will include covered
conveyer system with dust collection system at transfer points and Water spraying
for dust suppression on heavy vehicles movement areas/ roads.
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
i
Sr.
no.
Type/Name
of
Hazardous
waste
Specific
Source of
generation
(Name of
the
Activity,
Product
etc.)
Category
and
Schedule
as per HW
Rules.
Quantity
(MT/Annum)
Management
of HW
1 Discarded
Container/
barrels
From tores/
Drum yard 33.3 0.06 MTPA
Sale to
authorized
recycler
2 Spent/Used
Oil
From D.G.
set 5.1 720 Lit/year
Sale to
authorized
recyclers
3 H2SiF6 From 34.2 56 MTPA Reused
63
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 63 of 129
scrubber
All solid waste and hazardous waste shall be disposed as per norm.
ii Membership details of TSDF, CHWIF etc.
(For HW management)
NA
iii Details of Non-Hazardous waste & its disposal
(MSW and others)
Commercial waste like empty
cement bags, Iron scrap etc.
will be sold to scrap buyers
after the construction phase.
Domestic waste like used
paper, label, cartoons will be
disposed to the scrap buyers.
Organic waste from canteen
will be disposed as per the
local Panchayath / Municipal
disposal mechanism.
G Solvent management, VOC emissions etc.
NA
i Types of solvents, Details of Solvent recovery, % recovery, reuse of recovered
Solvents etc. (Details in Table Format)
� No Applicable
ii VOC emission sources and its mitigation measures
� Not Applicable
H � Details regarding storage of Hazardous chemicals
Storage details Name of major
Hazardous chemicals
Remarks
Storage tanks
Sulphuric Acid Brick lined
MS Tank
(1000 KLD)
Drum/Barrel storage
� Applicability of PESO : NA
• During the meeting dated 03/10/2019, technical presentation made during the meeting by project proponent.
Technical expert of PP informed that this is existing unit for non-EC applicable product NPK fertilizer and
64
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 64 of 129
proposed new SSP product which is EC applicable. Committee asked about Existing plant CCA status, PP
informed that they have valid CCA for existing plant. Committee insisted for apply ToR-amendment as
expansion project instead of ToR obtained as new project.
• After detailed discussion, it was decided to defer the proposal and consider the same in one of the
upcoming meeting of SEAC only after satisfactory submission of the following documents,
1. Submit ToR – Amendmentapplication as expansion project with mentioning details of existing
product NPK fertilizer and subsequent change in water, air and hazardous waste details.
08. SIA/GJ/MIS/21743/2016 M/s. Dr. H.K. Patnaik (Cairn Energy)
Bhogat, Dist - DevbhoomiDwarka. Ec-Reconsideration
• PP remained absent in the EC – Appraisal presentation held on 03/10/2019.
• The project proponent remained absent during the two consecutive meetings of SEAC i.e. 04/09/2019 &
03/10/2019.
• It was unanimously decided to delist the proposal from the list of applications pending with the SEAC and to
close the file of the project.
09. SIA/GJ/IND2/29282/2018
M/s. Jay Ganesh Industries
Plot No. 824/2, Sejal Glass Road,
GIDC Industrial Estate - Jhagadia,
Bharuch
Reconsideration of EC-
Refer Back Case
Category of the unit: 5(f)
Project status: Expansion
• M/s: Jay Ganesh Industries, applied for Environmental clearance and the SEAC recommended the
project for grant of environmental clearance vide this office letter no. EIA-10-2018/IND2/2605 dated
09/08/2019 for conditions as mentioned therein:
• The case was referred back by the SEIAA, Gujarat vide SEIAA minutes of 264th meeting dated
22/08/2019 with the following point:
1. To verify the details of treatability and feasibility study report submitted.
• Project proponent submitted reply vide their letter dated 22/09/2019 showing Characteristics of effluent
for the above mentioned points.
• PP has submitted as under:
1. PP has submitted characteristic of effluent with segregation of stream and stage wise
reduction of effluent in ETP.
65
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 65 of 129
• The case was reconsidered in the SEAC meeting dated 03/10/2019.
• During the SEAC meeting dated 03/10/2019, the said reply was considered by the Committee.
Committee asked clarification regarding drastic reduction in TDS, COD and BOD value in ETP units,
technical expert of PP has informed that BOD and COD value after secondary treatment will be reduced
from 1020 mg/l and 2700 mg/l to 80 mg/l and 250 mg/l respectively. Committee disagree with drastic
reduction of BOD and COD value in secondary treatment plant. Hence, Committee asked for adequacy
and treatability report by recognized schedule I auditor for proposed ETP units.
After deliberation, SEAC unanimously decided to consider the proposal after satisfactory submission of
the following details.
1. Adequacy and Treatability report by recognized schedule I auditor regarding proposed ETP units. Stage
wise reduction in pollutants like COD, BOD etc. shall be incorporated.
10. SIA/GJ/MIS/35539/2018
M/s. Care BMW Incinerator
Sr. No 1186,Block No .3013/8, 3014/A,
3014 /B, Chhatral GlDC- Kalol, Dist -
Gandhinagar
Reconsideration of EC-
Refer Back Case
Category of the unit: 7(d)
Project status: New
• M/s: Care BMW Incineratorapplied for Environmental clearance and the SEAC recommended the
project for grant of environmental clearance vide this office letter no. EIA-10-2018/IND2/2792 dated
04/09/2019 for conditions as mentioned therein:
• The case was referred back by the SEIAA, Gujarat vide SEIAA minutes of 271th meeting dated
19/09/2019 with the following point:
1. To verify the distance of proposed site from the nearest human habitation and compliance of
the same in respect of guidelines published by GPCB.
• Project proponent submitted presentation for compliance of above query showing distance of proposed
site from the nearest human habitation and compliance of the same in respect of guidelines published by
GPCB.
• PP has submitted as under:
1. PP has submitted distance of proposed site from the nearest human habitation and
compliance of the same in respect of guidelines published by GPCB.
• The case was reconsidered in the SEAC meeting dated 03/10/2019.
66
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 66 of 129
• During the SEAC meeting dated 03/10/2019, the said reply was considered by the Committee.
Committee asked distance of proposed project from nearby habitat area, technical expert of PP informed
that this CBWTF facility is involved in Common Bio medical waste treatment facility since 2002 at Santej,
Gandhinagar. Generation of waste and nos. of beds is increasing in existing HCUs, year by year. So as
considering future scenario, there is a need of expansion in biomedical waste treatment and disposal
facility. Expansion in present facility at Santej, Gandhinagar is not possible due to space constraint and
surrounding setup. Hence, management has decided to shift this facility at Survey No.-1186 Block
3013/B, 3014/A, 3014/B, Chhatral G.I.D.C, Taluka: Kalol, Dist: Gandhinagar which is located within
notified industrial area.According to the CPCB’s “Revised Guidelines for Common Bio-medical Waste
Treatment Facilities” published in December 21, 2016, it states under “Sr. No. 6 – Location Criteria as A
CBWTF shall preferably be developed in a notified industrial area without any requirement of buffer zone
(or)”. Proposed CBWTF is located within Chhatral GIDC which is notified as industrial area since 1993.
Due to Govt. notified area it does not attracts general sitting criteria and buffer zone requirement. Further
Project site is surrounded by other 25 nos. of plot and various other industries such as Shreeji paper
product, Uma Fabrics, DN Tubes Pvt. Ltd., Mornis Industries Wheelers, etc. The companies DN Tubes
Pvt. Ltd. and Mornis Industries Wheelers are located between project site and nearest human habitation.
PP submitted authenticated satellite map showing distance of proposed site from human habitation is
approx 200 meter.
• Committee asked about air quality modeling due to proposed project, technical expert of PP informed
that Air pollution control device will be designed to control PM, NOx, HCl, Hg, Total Dioxin and Furan
emissions up to 50 mg/Nm3, 400 mg/Nm3,50 mg/Nm3, 0.05 mg/Nm3 and ≤ 0.1 ng TEQ/Nm3
respectively, as per prescribe norms.
• Maximum incremental Ground Level Concentration (GLC) due to proposed project observed is 0.38
µg/m3 at 1.1 km in SW direction, in case of the steady state condition (80% calm), GLC observed is
0.31at 0.55 km in SW direction i.e. within Industrial area. Increase in Ground Level Concentration due to
proposed project will be only 0.3 µg/m3 in comparison to ambient concentration of PM i.e. around 90.0
µg/m3 is negligible. Moreover, as stated above nearest human habitation is located at 0.2 km in NW
direction, which is in cross wind direction. Hence, there will not be significant impact of air emission.
• Site specific meteorology data shows calm condition of 37%.
• Modeling has been carried out considering Incinerator’s stack height at 30 m, metrological data collected
during study period and other parameters i.e. exit gas velocity, exit gas temperature, stack diameter etc.,
which predicts maximum GLC as below,
67
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 67 of 129
Maximum Ground Level Concentration from Proposed Source
Pollutant Co-ordinates Latitude &
Longitude
Average Maximum Ground
Level Concentration (µg/m3
)
Distance
(km) Direction
X Y
PM10
-500 -500 23°17'18.95"N
72°26'34.62"E
0.31 0.55 SW
NOX 1.47
HCl -500 0 23°16'47.36"N
72°25'50.06"E 2.17 0.5 W
• From the above table it can be concluded that even in the steady state condition (80% calm), GLC falls
in industrial area.
After detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of
Environmental Clearance,
1. CBWTF shall install adequate APCM for control of parameter like Total Dioxins and furans for
proposed biomedical waste incinerator and shall construct boundary wall of adequate height
for control of fugitive emission from proposed CBWTF site.
2. Unit shall discontinue existing CBWTF running at Santej after getting EC and CTE of the
Board for proposed CBWTF site.
3. CBWTF shall install Continuous emission Monitoring system (CEMS) as per CPCB guideline
with stack attached to proposed incinerator.
4. Unit shall develop dense green belt of adequate width along periphery of the project
boundary.
11. Offline application
M/s. Dholu Earth Industries
Sr. No.92./2, Kalitalavadi, Bhuj, Dist -
Kutch
Reconsideration of EC-
Referback
Category of the unit: 2(b)
Project status: New
• M/s: Dholu Earth Industries, applied for Environmental clearance and the SEAC recommended the
project for grant of environmental clearance vide this office letter no. EIA-10-2017/IND2/2787 dated
04/09/2019 for conditions as mentioned therein:
• The case was referred back by the SEIAA, Gujarat vide SEIAA minutes of 271th meeting dated
19/09/2019 with the following point:
68
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 68 of 129
1. To verify the details of disposal of hazardous waste especially spent sulphuric acid and its
viability.
• Project proponent submitted reply vide their letter dated 28/09/2019 showing revised proposal for the
management of spent sulphuric acid as the above mentioned points,
• PP has submitted as under:
1. PP has submitted revised proposal with mentioning regarding spent sulphuric acid treated in
ETP and manufacturing gypsum instead of previously showing spent sulphuric acid disposal
to end -users.
• The case was reconsidered in the SEAC meeting dated 03/10/2019.
• During the SEAC meeting dated 03/10/2019, the said reply was considered by the Committee.
Committee asked clarification regarding change of mode of disposal of spent sulphuric acid disposal.
Technical expert of PP informed that previously they have proposal of sending spent sulphuric acid to
end users like IFFCO but IFFCO is not ready for accept spent sulphuric acid of the unit. Hence PP
submitted revised proposal with sending spent sulphuric acid in ETP for wastewater treatment and
Gypsum mentioned as Hazardous Waste. Committee asked clarification regarding gypsum is Hazardous
Waste or not and justification regarding adequacy of ETP and treated waste water disposal, technical
expert of PP could not explain satisfactorily regarding it.
After deliberation, SEAC unanimously decided to consider the proposal after satisfactory submission of
the following details.
1. Submit MoEF&CC accredited laboratory report regarding gypsum characteristic with recommendation
regarding gypsum is Hazardous Waste or Non-Hazardous waste.
2. Sound management of concentrated acidic effluent stream.
12 SIA/GJ/IND2/38556/2019
M/s. AnjuLifescience
Plot No. C/261, GIDC Industrial Estate,
Saykha, Ta -Vagra, Dist -Bharuch
Screening & Scoping
Project / Activity No.: 5(f)
Project status: New
• This office has received an application vide their online proposal no. SIA/GJ/IND2/38556/2019 dated
29/08/2019 regarding grant of Terms of Reference [ToR] for preparation of EIA/EMP report.
• Project proponent (PP) has submitted Form-1, PFR and relevant details/information.
• This is a new unit proposes for Synthetic Organic Chemicals manufacturing plant as tabulated below:
Sr. Name of the Products CAS no. /CI Quantity End-use of products
69
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 69 of 129
No. no. MT/Month
1 Tenofovir disoproxil fumarate & [its
itntermediate (diethyl (tosyloxy) methyl
phosphonate)]
202138-50-9
(31618-90-
3)
10 Anti-HIV medicine
2 Para hydroxyl phenyl acetonitrile 150810-68-7 70 Pharma Intermediate
3 N-Sulfomyl-3-chloropropionamide
hydrochloride[IF]
106649-95-0 Pharma Intermediate
4 Sulphonamide of Glimepiride 93479-97-1 20 Anti Diabetic
5 Adapalene 76824-35-6 Skin allergic
6 Tapentadol Hydrochloride 845273-93-0 Analgesic
7 Bromo OTBN 114772-54-2 Intermediate for
Losartan
8 Rusvastatin Calcium 7554-65-6 High cholesterol
9 1-3 dichloro Acetone 182815-44-7 Pharma Intermediate
10 Gunylthiourea 93479-97-1 Pharma Intermediate
11 Rabeprazole Sodium 5579-84-0 Pharma
12 Carvediol 106685-40-9 Hypertension
13 Clopidogrel Bisulfate 175591-09-0 Heart attacks
14 Tranexamic Acid 2114-02-5 Antifibrinolytic
15 Sildenafil Citrate 171599-83-0 Hypertension
16 Pregabaline 169590-42-5 Anti diabetes
17 Chlorohexidine Base 120202-66-6 Pharma Intermediate
18 Miconazole Nitrate 59-30-3 Antifungal
19 Ecanazole Nitrate 189005-44-5 Antifungal
20 Desloratadine 148553-50-8 Antihistamine
21 Loratidine 79794-75-5 Antihistamine
22 Gabapentine 60142-96-3 Anti-convulsant
23 Albendazole 54965-21-8 Moderate infestation
24 Citrezine Hydrochloride 83881-52-1 Anti allergic
25 Lasamide 2736-23-4 Anti Diuretic
26 Pioglitazone Hydrochloride 112529-15-4 High blood sugar
27 Mesalamine 89-57-6 Anti-inflammatory
70
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 70 of 129
28 Febuxostat 144060-53-7 Anti hyperuricemia
29 Itopride Hydrochloride 122892-31-3 Anti Diabetes
30 Amodafinil 68693-11-8 Obstruct. sleep apnea
31 Quetipine Fumrate 111974-72-2 Anti-psychotic
32 Aripiperazole 129722-12-9 Antipsychotic
33 Amlodipine Besylate 111470-99-6 Anti hypertensation
34 Nebivilol Hydrochloride 152520-56-4 Cardioselective
35 Sevelamer Hydrochloride 106-27-4 Hyper phosphataemia
36 Sevelamer Carbonate 103-45-7 Hyper phosphataemia
37 Poly Allaylamine Hydrochloride 122-70-3 250 Pharma Intermediate
38 Phthalimido Amlodipine 88150-62-3 5 Pharma Intermediate
39 Sulfamide 7803-58-9 20 Antibiotics
40 Furfuryl Amine 617-89-0 40 Synthesis
of Barmastine
41 Methyl Acetate 79-20-9 100 Pharma Intermediate
42 Doxophiline Hydrochloride -- 20 Treatment of asthma
43 Ethyl (2-Nitro-4-Aminophenyl)
Carbamate
150812-24-1 Synthesis of
Retigabine
44 Milnacipran 92623-85-3 Serotonin-non repine
phrine reuptake -
inhibiter
45 Levomilnacipran 96847-55-1 Antidepressants
46 Ataluren 775304-57-9 Duchenne Muscular
Dystrophy
47 Pranlukast 103177-37-3 Antagonist
48 Suvorexant 1030377-33-
3
Sedative/ Hypnotics
49 Apixaban 503612-47-3 Anticoagulant
50 Luliconazole 187164-19-8 Antifungal
51 Venlafaxine 93413-69-5 Antidepressant
52 Tetra Butyl Ammonium Bromide 1643-19-2 Phase Transfer
Catalyst
53 Meta Bromo Anisole 2398-37-0 Pharma Intermediate
71
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 71 of 129
54 N-Methyl Piperazine 109-01-3 Intermediate for
antibiotics
55 4- Methoxy Phenyl Acetone 122-84-9 Pharma Intermediate
56 3-Hydroxy Acetophenone 121-71-1 Anti-tuberculosis
agents
57 Albendazole 54965-21-8 Pharma Intermediate
58 Febendazole 43210-67-9 Pharma Intermediate
59 Oxfendazole 53716-50-0 Anthelminthic
60 Ricobendazole 54029-12-8 Anthelminthic
61 Oxyclozanide 2277-92-1 Anthelminthic
62 4-Hydroxy Cumerine 1076-38-6 5 Pharma Intermediate
63 Trimethyl ortho benzoate 707-07-3 Pharma Intermediate
64 2,4-thiazolidinedione 2295-31-0 Pharma Intermediate
65 1-Phenyl Piperazine 92-54-6 Pharma Intermediate
66 1-(2-Chloro Phenyl)piperazine 39512-50-0 Pharma Intermediate
67 2-Piperidone(2-PD) 675-20-7 Pharma Intermediate
68 Dimethyl Formamide Dimethyl Acetal 4637-24-5 Pharma Intermediate
69 1-methyl-4-piperidone 1445-73-4 Pharma Intermediate
70 1-(2,3-dichloro phenyl) piperazine HCl 119532-26-2 Pharma Intermediate
71 1-(3-chlorophenyl) piperazine HCl 65369-76-8 Pharma Intermediate
72 1-Methyl-3-Phenyl Piperazine 5271-27-2 Pharma Intermediate
73 4-chloro butyraldehyde dimethyl acetal 29882-07-3 Pharma Intermediate
TOTAL 540
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 03/10/2019.
• Salient features of the project including Water, Air and Hazardous waste management :
Sr.
no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
4.0 Crores
B Total Plot area( sq. meter) 4000 Sq. m.
Green belt area 1200 Sq. m.
72
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 72 of 129
( sq. meter)
C Employment generation 30
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply
etc...)
GIDC Water Supply
Status of permission from the concern authority. Permission will be taken after
getting ToR
ii Water consumption (KLD)
Category
Quantity
KLD
Remarks
(N) Domestic 5.0
(O) Gardening 3.0
(P) Industrial
Process 75.0
Washing 2.0
Boiler 20.0
Cooling 15.0
Others 2.0
Industrial Total 112
Total (A + B + C) 120
4) Total water requirement for the project: 120 KLD
5) Quantity to be recycled: 0.0 KLD
6) Total fresh water requirement: 120 KLD
iii Waste water generation (KLD)
Category Waste water
KLD
Remarks
(H) Domestic 4.0
(I) Industrial
Process 60.0
Washing 2.0
Boiler 2.0
73
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 73 of 129
Cooling 1.0
Others 2.6
Total Industrial
waste water
67.6
Total [A + B] 71.6
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
In-house ETP consisting of Primary & Secondary Treatment facility @ 60 KL/Day &
In-house ETP consisting of Primary Treatment facility @ 5 KL/Day
v Mode of Disposal & Final meeting point
Domestic: Domestic waste water (4.0 KL/Day) will be sent to Septic Tank & Soak
Pit.
Industrial: Out of 65 KL/Day Industrial effluent, 5 KL/Day High COD wastewater
will be sent to Common MEE of M/s. BEIL, Dahej after primary
treatment in ETP & 60 KL/Day Low COD will be sent to CETP of
Saykha after primary & secondary treatment in ETP for further
treatment & disposal.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. ,
Name of CF
Common MEE Facility of M/s. BEIL, Dahej & CETP of Saykha
Membership of Common facility (CF)
(For waste water treatment)
Common MEE Facility of M/s. BEIL, Dahej & CETP of Saykha
vii Simplified water balance diagram with reuse / recycle of waste water
All figures are in KL/ Day.
74
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 74 of 129
viii Reuse/Recycle details (KLD)
Total reuse: 0.0 KLD
Source of waste water
for reuse with
quantity in KLD
Application area
with quantity in
KLD
Remarks regarding feasibility to
reuse i.e. w/w characteristics
(COD, BOD, TDS etc.)
No Reuse/Recycle
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA
etc.
Sr.
no.
Source of
emission
Stack
Height
Type of
Fuel
Quantity
of Fuel
Type of
emissions
Air Pollution
Control Measures
75
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 75 of 129
With
Capacity
(meter) MT/Day i.e. Air
Pollutants
(APCM)
1
Boiler
(Capacity:
1 TPH)
30 Briquettes
of Bio-
Coal/ Coal
5 MT/Day
/ 4
MT/Day
SPM
SO2
NOx
Multi-cyclone
Separator with Bag
Filter
2
Boiler
(Capacity:
2.0 TPH)
30 Briquettes
of Bio-
Coal/ Coal
10
MT/Day
/ 8
MT/Day
SPM
SO2
NOx
Multi-cyclone
separator with bag
filter
3
Thermic
fluid
heater
(Capacity:
4 Lakh
Kcal/ Hr)
30 Briquettes
of Bio-
Coal/ Coal
4 MT/Day
/ 3
MT/Day
SPM
SO2
NOx
Multi-cyclone
separator with bag
filter
4
Thermic
fluid
heater
(Capacity:
6 Lakh
Kcal/ Hr)
30 Briquettes
of Bio-
Coal
6 MT/Day SPM
SO2
NOx
Multi-cyclone
separator with bag
filter
5
D. G. Set
(250 KVA)
11 HSD 400
Lit/Day
SPM
SO2
NOx
Adequate Stack
Height
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Sr.
no.
Specific Source of
emission
(Name of the
Product &
Process)
Type of
emission
Stack/Vent
Height
(meter)
Air Pollution Control
Measures
(APCM)
1
Process Vent
(Chlorination)
(Product Name:
Cl2
HCl
11 Two Stage Water + Alkali
scrubber
76
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 76 of 129
Rosuvastatin
Calcium)
2
Process Vent
(Sulphonation)
(Product Name:
Cetrizine
Dihydrochloride)
SO2 11 Two Stage Caustic scrubber
3
Process Vent
(Amination)
(Product Name:
Glimepride)
NH3
11 Two Stage Acid scrubber
4
Process Vent
(Bromination)
(Product Name:
Bromo OTBN)
HBr 11 Two Stage Water + Alkali
scrubber
iii Fugitive emission details with its mitigation measures.
As below:
• Enclosed Processed
• Minimum joints/flanges
• Auto handling for charging Raw Materials
• Pumps with double mechanical seals
• Proper Ventilation
• PPEs
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary Movement)
Rules 2016.
i -
Sr.
no.
Type/
Name of
Hazardous
waste
Specific
Source of
generation
(Name of the
Activity,
Product etc.)
Category
and
Schedule
as per HW
Rules.
Quantit
y
(MT/
Annum)
Management of HW
77
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 77 of 129
1 Discarded
HDPE
Drums/Bag
s
Raw Material
and Storage
Sch-I/
33.1
12 Collection, Storage,
Transportation and
sell to Register Re-
processors after
decontamination.
2 Used /
Spent Oil
Equipment &
Machinery
Sch-I/
5.1
120 Lit/
Year
Collection, Storage,
Transportation and
sell to registered
recycler.
3 ETP
Sludge
ETP Sch-I/
35.3
80 Collection, Storage,
Transportation and
sent to common TSDF
of M/s. SEPPL.
4 Distillation
Residue
Distillation Sch-I/
20.3
200 Collection, Storage,
Transportation and
sent for co-processing
in cement industries or
sent to common
incineration of M/s.
SEPPL.
5 Spent
Carbon
Process
(Furosemide,
Benzbromarone
, Pregabaline)
Sch-I/
28.2
24 Collection, Storage,
Transportation and
sent for co-processing
in cement industries or
sent to common
incineration of M/s.
SEPPL
6 Spent
Catalyst
Process
(Atorvastatin)
Sch-I/
28.3
60 Collection, Storage,
Transportation and
sent to registered
regenerator.
7 Inorganic
Solid
Process
(Rabeprazole
Sch-I/
28.1
240 Collection, Storage,
Transportation and
78
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 78 of 129
Waste Sodium) sent to common TSDF
of M/s. SEPPL.
8 Organic
Waste
Process
(Rosuvastatin
Calcium)
Sch-I/
28.1
60 Collection, Storage,
Transportation and
sent for co-processing
in cement industries or
sent to common
incineration of M/s.
SEPPL
9 Sodium
Chloride
Process
(Tenofovir
disoproxil
fumarate +
Amrodafinil)
Sch-I/
28.1
538 Collection, Storage,
and sent to ETP.
10 Hydrochlori
c Acid (30
%)
Scrubber (312
MT + Process
(IF)(996 MT)
Sch-II/
B15
1308 Collection, Storage
and Reuse within
premises (For
manufacturing of
Polyallyamine
Hydrochloride (5000
TPA).
11 Potassium
Chloride
Process
(Benzarone)
Sch-I/
28.1
425
Collection, Storage,
Transportation and
sold to end user
having permission
under rule-9.
12 Dil.
Sulphuric
Acid (80%)
Process
(Loratidine)
Sch-II/
B15
1550
13 Sodium
Bromide
(23%)
Process
(Albendazole)
Sch-II/
B36
564
14 Ammonium
Chloride
(30%)
Scrubber (115
TPA) + Process
(Lasamide)
(416 TPA)
Sch-II/
B15
528
79
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 79 of 129
15 Sodium
Sulphite
(25%)
Scrubber Sch-II/
B36
60
16 Di
Potassium
Phosphate
Process
(Guanyl
Thiourea)
Sch-I/
28.1
420
17 Sodium
Hydroxide
Process
(Tenofovir
disoproxil
fumarate)
Sch-I/
28.1
1500
Collection, Storage
and Reuse within
premises (For
manufacturing of
Mesalmine (1704
TPA), Citrizine HCl
(724 TPA)).
18 Spent
Solvent
Process
(Zolpidic Acid,
Colistimethate
Sodium)
Sch-I/
28.6
9600 Collection, Storage,
in-house Distillation
and Reuse within
plant premises.
19 Off
Specificatio
n Products
From mfg.
Process
(Batch failure)
Sch-I/
28.4
10
Collection, Storage,
Transportation and
sent for co-processing
in cement industries or
Disposal at common
incineration site.
20 HBr (28%) Scrubber Sch-II/
B15
120 Collection, Storage,
Transportation and
sold to end user
having permission
under rule-9.
21 NaBr
(23%)
Scrubber +
Process
Sch-II/
B15
180
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Membership of TSDF/ CHWIF will
be obtained.
iii Details of Non-Hazardous waste & its disposal
(MSW and others)
No such wastes generate.
G Solvent management, VOC emissions etc.
80
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 80 of 129
• All the solvents shall be directly distilled from product mixes and; if required shall be
purified in packed column with the help of reflux and therefore there is no generation
of any distillation residue from the solvent distillation.
• The solvent distillation system shall be designed so as to achieve minimum 94.0 %
recovery of solvent.
• Pure solvent, crude solvent and distilled (recovered) solvent shall be stored only in
storage tanks and we shall not be using drums at any stage in the Solvent
Management System.
• Wherever required, the solvents shall be directly pumped into day tanks from the
storage tanks and shall be charged into the reactors without involving any manual
handling.
• All the pumps shall be mechanical seal type to avoid any leakage of solvent.
• All necessary fire fighting systems shall be provided with alarm system. Flame proof
wiring and flame proof electrical accessories shall be provided to avoid any mishap.
• All the storage tank and day tank shall be connected to a vent system through cooling
water and chilled brine condensers to prevent loss of solvents in the atmosphere.
• All the distillation column vents will be also connected to cooling water/chilled brine
condensers for maximum possible recovery of the solvents.
• All the vents will be connected to a common carbon Adsorber for removing traces of
solvent from vent gases.
• Residue generated from the distillation will be incinerated in-house or sent to BEIL
incinerator site.
• Coolant to be used
Primary Condensers Cooling Water
Secondary Condensers Chilled Brine up to -50C
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
LIST OF SOLVENTS ALONGWITH TOTAL RECOVERY
Name of Solvent
Total
Input
(Kg)
Qty. of
Recovered
Solvent
(Kg)
Qty. of
Losses
(Kg)
%
Recovery
%
Losses
Acetone 855 8150 407 95.24 4.76
81
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 81 of 129
7
Butanol 117
0
1117 53
95.47 4.53
Dichloromethane 950
2
9075 427
95.50 4.5
Dimethylformamide 723 698 25 96.54 3.46
Ethanol 650 620 30 95.38 4.62
Hexane 528 505 23 95.64 4.36
Iso Propyl Alcohol 625
0
5997 253
95.95 4.05
Methanol 227
32
21766 966
95.75 4.25
Toluene 977
7
9295 482
95.07 4.93
Xylene 666
0
6432 228
96.58 3.42
ii VOC emission sources and its mitigation measures
• Enclosed Processed
• Minimum joints/flanges
• Adequate Condenser
• Brine will be utilised as chilling agent
• Pumps with double mechanical seals
• Proper Ventilation
• PPEs
• During the meeting dated 03/10/2019, technical presentation made by the Project proponent.
• Committee noted that this proposal is new bulk drug unit in GIDC Saykha. Source of Water is GIDC.
Committee asked justification regarding capital project cost of proposed project with respect to size of
production plant, technical expert of PP could not explain satisfactorily. PP mentioned that effluent
generated from plant will be segregated in High COD and Low COD stream. High COD stream will be sent
to CMEE, Dahej while Low COD stream will be sent to CETP Saykha for further treatment and disposal.PP
informed that bio coal or coal will be used as fuel for boiler and MCS and bag filter as APCM will be provided
82
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 82 of 129
with it. PP has addressed Hazardous Waste as per HWR – 2016.
• Considering the above project details, after detailed discussion, the terms of reference (ToR) were
prescribed as below and as per the standard TOR for the Synthetic Organic Chemical projects
recommended by SEAC vide letter no. EIA-10-GEN-21/1480 dated 14/09/2017 and approved by SEIAA
in its 12th meeting dated 16/09/2017 for the EIA study to be done covering 10 Km radial distance from
the project boundary.
1. Compliance of MoEF&CC’s OM dated 01/05/2018 regarding “Corporate Environment Responsibility”
(CER). Fund allocation for Corporate Environment Responsibility (CER) shall be made as per
MoEFCC’s O.M. No. 22-65/2017-IA.III dated 01/05/2018 for various activities therein. The details of
fund allocation and activities for CER shall be incorporated in EIA/EMP report.
2. Submit CA certificate for proposed capital project with mentioning land, plant machinery, utility,
building shed etc. cost and justification regarding proposed project cost with respect to size of bulk
drug unit.
3. Membership certificate of CETP Saykha with valid CCA order of CETP saykha.
4. Adequate safety measures for hydrogenation process
5. Explore the use of renewable energy to the maximum extent possible. Details of provisions to make
the project energy-efficient through energy efficient devices and adoption of modes of alternative eco-
friendly sources of energy like solar water heater, solar lighting etc. Measures proposed for energy
conservation.
6. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for use
in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor prevention
of losses of solvents to the best minimum extent.
7. Technical details of in-house solvent stripper for stripping solvent from process with stoichiometric
mass balance and solvent recovery.
8. Safety precautions including flame proof electric fittings to be taken to avoid fire hazard during
unloading, storage, transportation, handling and processing of Solvents etc.
9. Membership certificate of Common facility (Common Spray dryer, Common MEE, Common
Incinerator etc.) with booking quantity in KLD along with other details/information like Spare capacity
of Common Facility (CF), quality of waste water by member industry and assurance by CF that there
is no adverse impact on Environment and Human Health due to treatment of waste water received
from your industrial effluent.
10. PP shall furnish status of all the applicable Rules, Acts, Regulation, Clearances in a tabular form.
• The TOR prescribed as above and as per the standard TOR approved by SEIAA and the model ToRs
83
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 83 of 129
available in the MoEF&CC’s sector specific EIA Manual for ‘Synthetic Organic Chemical Industry’ shall be
considered as generic TORs for preparation of the EIA report in addition to all the relevant information as
per the generic structure of EIA given in Appendix III in the EIA Notification, 2006.
• Further Project Proponent may be advised to submit final EIA Report with EC application within 100 days
from the date of issuance of this ToR to expedite processing of Environment Clearance application.
• The project proponent shall have to apply for Environmental clearance through online portal
http://environmentclearance.nic.in/along with final EIA report.
13 SIA/GJ/IND2/40919/2019
M/s. Perivinc Pharmaceuticals Pvt. Ltd.
Plot No.: 257, GIDC Estate, Hansalpur,
Viramgam, Ahmedabad
ToR - Reconsideration
Category of the unit: 5(f)
Project status: Expansion
• This office has received an application vide their online proposal no. SIA/GJ/IND2/40919/2019 dated
29/08/2019 made by project proponent (PP) regarding grant of Terms of Reference [ToR] for preparation of
EIA/EMP report.
• Project proponent (PP) has submitted Form-1, PFR and relevant details/information.
• This is an existing unit for chemical manufacturing and now proposes for expansion in manufacturing of new
synthetic organic chemicals tabulated as below:
Sr.
No.
Name of the
Products CAS.NO
Existing Proposed Total after
Expansion Uses
MT/Month MT/Month MT/Month
1 Herbal Extract
(Vinea Alkaloids) - 0.5 -0.5 0.0 -
2 Trihexy Phenidyl-
HCl 52-49-3 0.0 0.70 0.70
Pharmaceutical
formulation
3 Procyclidine-HCl 1508-76-5 0.0 0.40 0.40
4 Pantoprazole
Sodium 164579-32-2 0.0 2.8 2.8
5 Levosulpride 23672-07-3 0.0 1.834 1.834
84
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 84 of 129
6 Bromhexine-HCl 611-75-6 0.0 1.5 1.5
Total 0.5 7.234 7.234
Unit will stop manufacturing of existing product after obtaining EC, CTE and CTO for proposed
products.
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 19/09/2019.
• During the meeting dated 19/09/2019, technical presentation made by the Project proponent.
• Committee noted that the name of the Project is “SELF REGISTRATION” and asked PP to clarify about the
same. PP mentioned that they have made an error while applying the application and they will submit the
required documents for the name change/correction of the same.
• Committee noted that this proposal is for expansion. Unit is located at GIDC, Hansalpur. Unit has valid
CC&A. Unit has submitted Compliance of CC&A. PP ensured that there is no court case and public
complaint against this unit. Source of water is GIDC. PP mentioned that they will surrender existing products
hence all the effluent coming out from existing plant will be NIL. PP mentioned that effluent generated after
expansion from process, washing, cooling tower blow down & boiler blow down will be treated in in-house
primary ETP and treated effluent will be sent to Common Spray Drying Facility developed by M/s. Chhatral
Environmental Management System Pvt. Ltd for final treatment and disposal. Committee noted that PP has
not satisfactorily addressed water balance diagram and water consumption and generation table. PP has
proposed one standby D.G. Sets. Fuel used will be HSD. Committee noted that PP has not addressed
process stack considering the mass balance of product profile and have not incorporated any APCM for the
same. Committee also noted that PP has not addressed Bleed Liquor in Hazardous Waste which will be
coming out of process stack.
• After detailed discussion, it was decided to consider the proposal only after satisfactory submission of the
following details.
1. Revised Water Balance Diagram Considering Expansion scenario and addressing the Water
Consumption & Generation Table Considering the Same.
2. Addressing the Process Stack Considering the Expansion in Product Profile along with its APCM.
3. Revised Hazardous Waste Matrix Considering Bleed Liquor from APCM of Process Stack and Sound
Management of the Same.
4. Authenticated Documents for change of name of Project from “Self Registration” to “Perivinc
Pharmaceuticals Pvt Ltd”.
85
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 85 of 129
• Project proponent made presentation for the above mentioned query on dated 03.10.2019 for the above
mentioned points.
• PP presented replied as below:
1. Revised Water Balance Diagram Considering Expansion scenario and addressing the Water
Consumption & Generation Table Considering the Same submitted.
2. Addressing the Process Stack Considerig the Expansion in Product Profile along with its APCM
submitted.
3. Revised Hazardous Waste Matrix Considering Bleed Liquor from APCM of Process Stack and Sound
Management of the Same submitted.
4. Authenticated Documents for change of name of Project from “Self Registration” to “Perivinc
Pharmaceuticals Pvt Ltd” submitted.
• Salient features of the project including Water, Air and Hazardous waste management (Revised):
Sr.
no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Proposed: Approx Rs. 1.4 Crores
B Total Plot area (sq. meter)
2248.5 Sq.m
Green belt area
( sq. meter)
744 Sq. m
C Employment generation
Proposed: 25 people
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC water supply
Status of permission from the concern authority. Required permission obtained
ii Water consumption (KLD)
Sr.
No
.
Source
Existing
Water
Consumptio
n as per CTO
Change/
Reduction/
Addition in Water
Consumption
Quantity of
water
Consumption
for Proposed
Total Quantity of
Water
Consumption
after Proposed
86
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 86 of 129
due to Proposed
API
Products
API products Expansion
1. Domestic 3 .0 Nil 0 3 .0
2. Gardenin
g - -- 2.5 2.5
3. Industrial
A.
Process 14.0 -13.4* 0.6 0.6
B. Boiler 5.0 -3.0* 2.0 2.0
C.
Washin
g
3.0 -1.0 * 2.0 2.0
D. Cooling 0.0 +2.0 2.0 2.0
E. APCM 0.0 +0.2 0.2 0.2
Total
Industrial 22.0 -15.2 6.8 6.8
Total
(Domestic +
Industrial)
25.0 -- -- 12.3
Unit will stop manufacturing of existing product after obtaining EC, CTE, CTO for proposed
products. Therefore,
* After the proposed expansion, there will be
1. reduction of water consumption in process from 14.0 KLD to 0.6 KLD (reduction of 13.4
KLD)
2. reduction of water consumption in boiler from 5.0 KLD to 2.0 KLD (reduction of 3.0 KLD)
3.reduction of water consumption in washing from 3.0 KLD to 2.0 KLD (reduction of 1.0 KLD)
Total water requirement for the project: 12.3 KLD
Quantity to be recycled: 0 KLD
Total fresh water requirement: 12.3 KLD
87
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 87 of 129
iii Waste water generation (KLD)
Sr.
No.
Source
Existing
Waste
Water
Generation
as per CTO
Change/
Reduction/A
ddition in
Waste Water
Generation
due to
Proposed
API
Products
Quantity of
Waste
Water
Generation
for
Proposed
API
products
Total Quantity
of Waste Water
Generation after
Proposed
Expansion
1. Domestic 2.5 Nil 0 2.5
2. Gardening - - - -
3. Industrial
A. Process 3.0 - 1.7* 1.3 1.3
B. Boiler 0.5 -0.2 * 0.3 0.3
C. Washing 3.0 -1.0 * 2.0 2.0
D. Cooling 0.0 + 0.3 0.3 0.3
E. APCM 0.0 + 0.2 0.2 0.2
Total Industrial 6.5 -2.4 4.1 4.1
Total
(Domestic + Industrial) 9.0 - - 6.6
* After the proposed expansion, there will be
1.reduction of Wastewater generation in process from 3.0 KLD to 1.3 KLD (reduction of 1.7
KLD)
2.reduction of Wastewater generation in boiler from 0.5 KLD to 0.3 KLD (reduction of 0.2 KLD)
3.reduction of Wastewater generation in washing from 3.0 KLD to 2.0 KLD (reduction of 1.0
KLD)
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
88
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 88 of 129
ETP: 10 KLD, Stripper: 0.5 KL/hr
v Mode of Disposal & Final meeting point
Domestic:
2.5 KLD Septic Tank/soak pit system
Industrial:
4.1 KLD Treated effluent will be sent to Common
Spray Drying Facility developed by M/s. Chhatral
Environmental Management System Pvt. Ltd.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. , Name
of CF
Unit has already obtained membership for disposal of treated effluent at Common Spray
Drying Facility developed by M/s. Chhatral Environmental Management System Pvt. Ltd.
Membership of Common facility (CF)
(For waste water treatment)
Obtained
vii Simplified water balance diagram with reuse / recycle of waste water
89
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 89 of 129
viii Reuse/Recycle details (KLD)
Total reuse: Nil
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Sr
.
N
o.
Stack
Attached
to
Type of Fuel &
Rate of Consumption Stack
Heigh
t (m)
APC
M
Parameter &
Permissible
Limit
Existing Proposed
after
expansion
1
Steam
Boiler
(1 No.)
Wood –
200
Kg/day
Agro waste
Briquettes –
800 Kg/day
32 Bag
Filter
PM < 150
mg/Nm3
SO2< 100 ppm
NOx< 50 ppm
Proposed
*0.7 KLD generated
from manufacturing
process
90
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 90 of 129
Sr.
No
.
Stack
Attached to
Type of Fuel
&
Rate of
Consumption
Stack
Height
(m)
APCM
Parameter &
Permissible
Limit
2
D.G Set -
1 Cap.
250 KVA
HSD: 10
lit/hr 12
Acousti
c
Enclos
ure
PM < 150
mg/Nm3
SO2< 100
ppm
NOx< 50 ppm
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Existing: There is no process emission from the production of existing product.
Proposed:
Sr.
No.
Stack Attached
To
Stack
Height (m)
Air
Pollution
Control
System
Parameter Emission
1. Reaction
Vessel 15 m
Water
Scrubber HCl <20mg/Nm3
2.
Solvent Storage
Area & Process
Area
(Common)
8 meter
Packed
Carbon
Column
VOC --
ii
i
Fugitive emission details with its mitigation measures.
As below:
� Regular sprinkling of water is carried out & green belt is provided within premises to prevent
fugitive emissions due to vehicular movement. Regular maintenance of vehicles.
� Management to ensure proper handling of the spillages during transfer, charging operation
and provision of a Dust Collection System for collection of the air borne material wherever
applicable.
� Preventive maintenance of flange connections and glands of pumps.
91
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 91 of 129
� Management will also ensure proper usage of the Personnel Protective Equipment by the
workers.
� Closed handling system shall be provided for chemicals.
� Reflux condenser to be provided over the reactor.
� The raw materials shall be taken from storage tanks to reactor through closed pipeline.
Storage tanks shall be vented through trap receiver
� Fugitive emissions in the work zone environment, product raw material storage area will be
monitored regularly.
-
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules
2016.
i
Sr.
No.
Type of
Waste Source
Categor
y
Existing
Hazardous
waste
Generation
Change/
Reduction
/ Addition
in
Quantity
of Haz.
Waste
Generatio
n
due to
Proposed
API
Products
Quantity of
Haz. Waste
Generation
for Proposed
API products
Total
Quantity
after
Proposed
Expansion
Mode
of Disposal
1. Used Oil
Plant
Machineri
es
5.1 0.5
MT/YEAR Nil
0.5
MT/YEAR
0.5
MT/year
Collection,
Storage ,
Transportat
ion , Reuse
and/or
Disposal
by selling
92
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 92 of 129
to
Registered
Re-refiners
2.
Empty Barrels
Glass Bottle
Liners,
Containers
Storage of
Raw
Materials
and
Products
33.1 2.28
MT/YEAR
+ 3.72
MT/Year
6.0
MT/Year
6.0
MT/Year
Collection,
Storage,
Decontami
nation,
transportati
on,
disposal by
selling to
authorized
recycler.
3.
Process
Wastes,
Residues &
Wastes
Manufactu
ring of
existing
product
21.1 29.5
MT/Year
- 29.5
MT/Year Nil Nil ---
4. Spent Solvent
From
Manufactu
ring
process
26.4 540
MT/Year
+ 195.84
MT/Year
735.84
MT/Year
735.84
MT/Year
Collection
and
Distillation
in-
house/reco
very &
reused
5. Distillation
residue
Solvent
Recovery
26.3 Nil 6.0
MT/Year
6.0
MT/Year
6.0
MT/Year
Collection,
Storage,
Transportat
ion,
Disposal
by co-
processing
or
93
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 93 of 129
Incineratio
n
6.
Chemical
Sludge from
wastewater
treatment
From
Effluent
Treatment
Plant
35.3 9.36
MT/Year
- 4.36
MT/Year
5.0
MT/ Year
5.0
MT/ Year
Collection,
Storage,
transportati
on and
disposal at
any
registered
TSDF site.
7.
Spent Acid
(HCl)
Scrubber
From
APCM Sch.II Nil Nil 70 MT/Year 70 MT/Year
Collection,
Storage, &
disposal by
sending to
ETP for
treatment
and finally
at common
Spray
drying
facility ,
Chhatral
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Will be obtained before
going for production
ii
i
Details of Non-Hazardous waste & its disposal
(MSW and others)
--
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
Name of
Product
Reacti
on
Stage
Name of
Solvent
Input Recovery %
Recovery
Machiner
y End
Use Kg/
Mont
Kg/
Month Used
94
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 94 of 129
h
Trihexy
Phenidyl-HCl
I & II Methanol 2870 2660 92.68% Separate
distillation
Col. With
Reactor
Re
used
in
next
batch
II Toluene& THF 3500 1645 94.00%
Procyclidine-
HCL
I & II Methanol 2050 1900 92.68%
II Toluene& THF 2500 2350 94.00%
Pantoprazole
Sodium
I Methanol 8800 8160 92.73%
II Acetone 9600 8920 92.92%
III Acetone 1120
0 10560 94.29%
Levosulpride I
Ethylene
Glycol 3850 3696 96.00%
Methanol 1155
0 10850 93.94%
Bromhexine-
HCL I Methanol 5400 5040 93.33%
ii VOC emission sources and its mitigation measures
� Breather valves will be provided on solvent tanks.
� To eliminate chances of leakages from glands of pumps, mechanical seal will be provided at
all solvent pumps.
� Entire process will be carried out in the closed reactors with proper maintenance of pressure
and temperature.
� Periodic monitoring of work area will be carried out to check the VOC emission.
Solvent recovery system will be provided with chilled water condenser system
• During SEAC meeting dated 03/10/2019, Committee asked for revised product profile, technical expert of
PP informed that they have submitted revised proposal and product profile as expansion project with
subsequent details of water, air and Hazardous waste as expansion project.PP informed that they will stop
production of existing plant after getting EC and CTE of the Board for proposed expansion project.
Committee asked about existing plant CCA status, PP informed that they have valid CCA of the Board for
existing plant.
• Committee deliberated on revised water balance diagram, air matrix and Hazardous waste matrix
considering bleed liquor disposal and ETP sludge generation quantity. Committee deliberated on
wastewater management and its disposal and PP informed that after primary treatment, treated waste water
will be disposed into common spray dryer of M/s Chhatral Environment management system pvt. Ltd,
95
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 95 of 129
Chhatral. Committee asked about online status of unit showing name of unit as self registration, PP informed
that name change of self registration to M/s Perivinc Pharmaceuticals P. Ltd is not edited by them.
• Considering the above project details, after detailed discussion, the terms of reference (ToR) were
prescribed as below and as per the standard TOR for the Synthetic Organic Chemical projects
recommended by SEAC vide letter no. EIA-10-GEN-21/1480 dated 14/09/2017 and approved by SEIAA in
its 12th meeting dated 16/09/2017 for the EIA study to be done covering 10 Km radial distance from the
project boundary.
1. Unit shall discontinue production of existing product after getting CTE and EC for proposed
expansion.
2. Details with respect to justification for proposed expansion: (1) To address proportionate availability of
space for production plant. (2) To address proportionate availability of storage area for raw materials
finished goods, utilities considering fire-safety norms & PESO standards and goods carrier movement
within premises. (3) To address proportionate captive/common infrastructure available to
accommodate additional load due to proposed expansion. (4) Environment impact and its mitigation
measures for common/ captive infrastructure due to proposed production.
3. Compliance of MoEFCC’s OM dated 01/05/2018 regarding “Corporate Environment Responsibility”
(CER). Fund allocation for Corporate Environment Responsibility (CER) shall be made as per
MoEFCC’s O.M. No. 22-65/2017-IA.III dated 01/05/2018 for various activities therein. The details of
fund allocation and activities for CER shall be incorporated in EIA/EMP report.
4. Submit end use of each proposed bulk drug products instead of simply showing use in
pharmaceutical formulation units.
5. Explore the use of renewable energy to the maximum extent possible. Details of provisions to make
the project energy-efficient through energy efficient devices and adoption of modes of alternative eco-
friendly sources of energy like solar water heater, solar lighting etc. Measures proposed for energy
conservation.
6. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for use
in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor prevention
of losses of solvents to the best minimum extent.
7. Technical details of in-house stripper for stripping solvent from effluent with stoichiometric mass
balance and solvent recovery.
8. Safety precautions including flame proof electric fittings to be taken to avoid fire hazard during
unloading, storage, transportation, handling and processing of Solvents etc.
9. Membership certificate of Common facility (Common Spray dryer, Common MEE, Common
96
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 96 of 129
Incinerator etc.) with booking quantity in KLD along with other details/information like Spare capacity
of Common Facility (CF), quality of waste water by member industry and assurance by CF that there
is no adverse impact on Environment and Human Health due to treatment of waste water received
from your industrial effluent.
10. Submit status of compliance of Environmental norms of existing Common Infrastructure of M/s:
Chhatral Environment management system pvt. Ltd, Chhatral.
11. PP shall furnish status of all the applicable Rules, Acts, Regulation, Clearances in a tabular form.
• The TOR prescribed as above and as per the standard TOR approved by SEIAA and the model ToRs
available in the MoEF&CC’s sector specific EIA Manual for ‘Synthetic Organic Chemical Industry’ shall be
considered as generic TORs for preparation of the EIA report in addition to all the relevant information as
per the generic structure of EIA given in Appendix III in the EIA Notification, 2006.
• Further Project Proponent may be advised to submit final EIA Report with EC application within 100 days
from the date of issuance of this ToR to expedite processing of Environment Clearance application.
• The project proponent shall have to apply for Environmental clearance through online portal
http://environmentclearance.nic.in/along with final EIA report.
14 SIA/GJ/IND2/40968/2019
M/s. ParasPharmaChem
Plot No. C-235, GIDC Industrial Estate,
Saykha, Ta--Vagra, Dist -Bharuch
ToR – Reconsideration
Category of the unit: 5(f)
Project status: New
• This office has received an application vide their online proposal no. SIA/GJ/IND2/40968/2019 dated
29/08/2019 made by project proponent (PP) regarding grant of Terms of Reference [ToR] for preparation of
EIA/EMP report.
• Project proponent (PP) has submitted Form-1, PFR and relevant details/information.
• This is a new unit proposes for manufacturing of synthetic organic chemicals as tabulated as below:
Sr.
No
Product Name CAS No. Proposed
Quantity
(MT/Month)
End Use Of Product
1. 1,3 DICHLORO DIMETHYL 112-36-7 Pharma & Water Treatment
97
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 97 of 129
HYDANTOIN
750
2. 1,3 Dibromo-5,5- Dimethyl
Hydantion
77-48-5 Pharma Industries
3. 5,5 Dimethyl Hydantion 77-71-4 Pharma Industries
4. 2,2-Azobisisobutyronitrile 78-67-1 Pharma, Polymer,Paint
5. Benzoyl Peroxide 94-36-0 Paint & Polymer Industries
6. MEK Peroxide 1338-23-4 Paint & Polymer Industries
7. LABSA 27176-87-0 Use In Detergents Industries
8. Methyl Methacrylate (MMA) 80-62-6 Acrylic Resin, Paint & Plastic
Industries
9. Acrylic Emulsion 25067-01-0 Textile , Paper & Leather
Industries,
10. VAM Emulsion 108-05-4 Textile, Paint Industries
11. Sodium Hypochlorite 7681-52-9
350
Textile & Paper Bleaching
12 Calcium Chloride 7440-70-2 Paint & Dyes Industries
13 Benzalkonium Chloride (BKC-50) 8001-54-5 Clinical Products
14 Benzalkonium Chloride (BKC-80) 8001-54-5 Clinical Products
15 Amine Oxides 1643-20-5 Clinical Products
16 Pearl Essence 8039-79-0 Used in Paint and Plastic
Industries
17 Cobalt Octate 13586-82-8 Paint & FRP Plastic Industries
18 TRO Turky Red Oil 8002-33-3 Antifoaming Agent & Textile
Industries
19 Coco Diethanolamide 68603-42-9 Cosmetic & Toiletries
20 Solvent Based Paints ---- Use in Wooden,Metal,
Household & Industrial Use
TOTAL: 1100
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 19/09/2019.
• During the meeting dated 19/09/2019, technical presentation made by the Project proponent.
• Committee noted that this proposal is new in GIDC Saykha. Source of Water is GIDC. Committee noted that
PP has addressed product profile considering end-use of some products in pesticides industry and asked
98
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 98 of 129
PP to clarify the same, PP mentioned that they will submit revised product profile considering the same. PP
mentioned that effluent generated from process, washing will be treated in in-house ETP consisting of
Primary, Secondary & Tertiary treatment followed by RO, while effluent generated boiler blow down, cooling
tower blow down will be directly treated in RO. PP mentioned that RO – Permeate will be mixed with fresh
water and reused/recycled back while RO – Reject will be fed to Single Stage Evaporator, Condensate from
Evaporator will be reused back in utility while residue/salt will be disposed at approved TSDF.Committee
noted that treatment characteristic proposed by PP is not satisfactory. PP has proposed two Steam Boiler&
one Thermic Fluid Heater. Fuel used will be Briquette of Bio-Coal/Coal. PP has addressed Hazardous
Waste as per HWR – 2016.
• After detailed discussion, it was decided to consider the proposal only after satisfactory submission of the
following documents:
1. Revised Product Profile eliminating the end-use of Products pertaining to Pesticides & Pesticides
Specific Intermediates (Address Water Balance Diagram, Consumption & Generation Details along
with Flue Gas Stack & Process Stack, Hazardous Waste Details).
2. Properly Addressing Characteristic of Waste Water Based on Treatment Technology with Technical
Justification for % Reduction of Load (pH, COD, BOD, SS).
3. Technical Justification for use of Single Stage Evaporator Instead of Multiple Effect Evaporator
Considering the Product Profile and Characteristic of Waste Water to be generated.
• Project proponent made presentation for the above mentioned query on dated 03.10.2019 for the above
mentioned points.
• PP presented replied as below:
1. Revised Product Profile eliminating the end-use of Products pertaining to Pesticides & Pesticides
Specific Intermediates (Address Water Balance Diagram, Consumption & Generation Details along
with Flue Gas Stack & Process Stack, Hazardous Waste Details) submitted.
2. Properly Addressing Characteristic of Waste Water Based on Treatment Technology with Technical
Justification for % Reduction of Load (pH, COD, BOD, SS).submitted
3. Technical Justification for use of Single Stage Evaporator Instead of Multiple Effect Evaporator
Considering the Product Profile and Characteristic of Waste Water to be generated submitted
• Revised product profile with mentioning end use of product submitted as above and Salient features of the
project including Water, Air and Hazardous waste management (Revised):
Sr.
no.
Particulars Details
99
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 99 of 129
A
A Total cost of Proposed Project
(Rs. in Crores):
9.50 Crores
B Total Plot area ( sq. meter) 8304.338 Sq. m.
Green belt area ( sq. meter) 2689.11 Sq. m.
C Employment generation 80
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply, etc...)
GIDC Water Supply
Status of permission from the concern authority. Unit has obtained the permission
letter from GIDC.
Ref No:GIDC/EE(W/D)/BRH/585
ii Water consumption (KLD)
Category
Quantity
KLD
Remarks
(Q) Domestic 3.0
(R) Gardening 10.0
(S) Industrial
Process 37.0
Washing 30.0
Boiler 9.5
Cooling 8.5
Scrubber 2.0
Industrial Total 87.0
Total (A + B + C) 100.0
1) Total water requirement for the project: 100 KLD
2) Quantity to be recycled: 1.7 KLD
3) Total fresh water requirement: 98.3 KLD
iii Waste water generation (KLD)
Category Waste water
KLD
Remarks
(J) Domestic 2.0
100
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 100 of 129
(K) Industrial
Process 40.0 Stream-I: Low COD &
TDS: 69 KLD
Washing 29.0
Boiler 1.0 Stream-II:Utilites: 2 KLD
Cooling 1.0
Scrubber 2.795 Reuse and sell end users
having permission under
rule-9
Total Industrial waste
water
73.795
Total [A + B + C] 75.795
-
Iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc.
� ETP (Primary,Secondary& Tertiary): 69 KLD
Treatment scheme including segregation at source.
� Total 75.795 KL/Day (73.795 KL/Day: Industrial + 2.0 KL/Day: Domestic) of effluent shall be
generated.
� Stream-I: 69 KL/day low COD & TDS stream (from process & Washing) will be treated in ETP
giving primary, secondary & Tertiary treatment then sent to CETP Saykha for further treatment.
� Stream-II: 2 KL/day utilities stream (from Boiler, cooling) will be send to RO And then RO
reject will be sent to ETP And RO permeate shall be reuse/recycle in boiler or cooling.
� 2.795 KL/Day Scrubbing water Will be reused or sold to end users having permission under
Rule-9.
Note: (In case of CETP discharge) :
Management of waste water keeping in view direction under section 18 (1) (b) of the Water
(Prevention and Control of Pollution) act, 1974 issued by CPCB regarding compliance of
CETP.
� Treated effluent in ETP giving primary, secondary & Tertiary treatment then sent to CETP
Saykha for further treatment.
� Reference no of CETP letter: GIDC/BRH/DEF(DRG)/326 dated 10/06/2019
101
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 101 of 129
v Mode of Disposal & Final meeting point
Domestic: Domestic waste water (2.0 KL/day) will be disposed by septic tank
or soak pit system
Industrial: � Stream-I: 69 KL/day low COD & TDS stream (from process &
Washing) will be treated in ETP giving primary, secondary &
Tertiary treatment then sent to CETP Saykha for further
treatment.
� Stream-II: 2 KL/day utilities stream (from Boiler, cooling) will be
send to RO And then RO reject(0.3 KL/day) will be sent to ETP
And RO permeate(1.7 KL/day) shall be reuse/recycle in boiler
or cooling.
� 2.795 KL/Day Scrubbing water Will be reused or sold to end
users having permission under Rule-9.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. Name of
CF
� CETP Saykha
� Reference no of CETP letter: GIDC/BRH/DEF(DRG)/326 dated 10/06/2019
vii Simplified water balance diagram with reuse / recycle of waste water
102
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 102 of 129
viii Reuse/Recycle details (KLD)
Total reuse: 1.7 KLD
Source of waste
water for reuse
with quantity in
KLD (From where
it is coming)
Application
area with
quantity in
KLD (Where it
is used)
Characteristics of
waste water to be
reused (COD, BOD,
TDS etc.)
Remarks
regarding
feasibility
to reuse i.e.
RO Permeate: 1.7
KLD
Boiler &
Cooling:1.7
COD: 50 mg/l
BOD: 25 mg/l
103
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 103 of 129
KLD TDS: 80 mg/l
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
-
Sr.
no.
Source of
emission
With
Capacity
Stack
Height
(meter)
Type of
Fuel
Quantity
of Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air Pollution
Control Measures
(APCM)
1
Boiler
(Capacity:
500
KG/PH)
18 Briquettes
of Bio-
Coal/ Coal
1 MT/Day
/ 0.8
MT/Day
SPM
SO2
NOx
Multi-cyclone
Separator with Bag
Filter
2
Boiler
(Capacity:
1 TPH)
18 Briquettes
of Bio-
Coal/ Coal
5 MT/Day
/ 4
MT/Day
SPM
SO2
NOx
Multi-cyclone
separator with bag
filter
3
Thermic
fluid heater
(Capacity:
1 Lakh
Kcal/ Hr)
18 Briquettes
of Bio-
Coal/ Coal
4 MT/Day
/ 3
MT/Day
SPM
SO2
NOx
Multi-cyclone
separator with bag
filter
4
D. G. Set
(125 KVA)
11 HSD 300
Lit/Day
SPM
SO2
NOx
Adequate Stack
Height
5
D. G. Set
(125 KVA)
11 HSD 300
Lit/Day
SPM
SO2
NOx
Adequate Stack
Height
104
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 104 of 129
-
ii Process gas emission details i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Sr.
no.
Specific Source of
emission
(Name of the
Product & Process)
Type of
emission
Stack/Vent
Height
(meter)
Air Pollution Control
Measures
(APCM)
1
Process Vent
(Chlorination)
(Product Name: AIBN,
DDH, DCDH)
Cl2
HCl
11 Two Stage Water + Caustic
Scrubber
2
Process Vent
(Sulphonation)
(Product Name: MMA
and LABSA)
SO2 11 Two Stage Caustic scrubber
3
Process Vent
(Ammoniation)
(Product Name: DMH)
NH3
11 Two Stage Acid scrubber
iii Fugitive emission details with its mitigation measures:
As below:
Following measures will be adopted to prevent and control fugitive emissions:
1. Airborne dust at all transfers operations/ points will be controlled either by spraying water or
providing enclosures.
2. Adequate ventilation will be provided.
3. Regular maintenance of valves, pumps, flanges, joints and other equipment will be done to
prevent leakages and thus minimizing the fugitive emissions.
4. Entire process will be carried out in the closed reactors with proper maintenance of pressure
and temperature.
5. Periodic monitoring of work area will be carried out to check the fugitive emission.
6. Stand by pumps will be provided on all scrubbers. Besides, scrubbers will be equipped with
on-line pH meter with hooter system for better operational control.
7. Close feeding system will be provided for centrifuges. Centrifuge and filtrate tank vents will
be connected to vent chillers.
105
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 105 of 129
8. Minimum number of flanges, joints and valves in pipelines.
9. Regular inspection of floating roof seals and proper preventive maintenance of roofs and
seals for tanks.
10. Fugitive emission over reactors, formulation areas, centrifuges, chemical loading,
transfer area will be collected through hoods and ducts by induced draft and controlled by
scrubber/ dust collector.
11. Dedicated scrubber will be provided are used for fugitive emissions to control.
12. For dust emissions bag filter will be provided.
13. Enclosures to chemical storage area, collection of emission from loading of raw
materials in particular solvents through hoods and ducts by induced draft, and control by
scrubber / dust collector to be ensured.
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules
2016.
i Sr.
no.
Type/Name of
Hazardous waste
Specific
Source of
generation
(Name of the
Activity,
Product etc.)
Category
&
Schedule
as per HW
Rules.
Quantity
(MT/
Annum)
Management of HW
1 Discarded
Drums/Bags
Raw
Material and
Storage
Sch-I/
33.1
45 Collection, Storage,
Transportation and sell
to Register Re-
processors after
decontamination.
2 Used / Spent Oil Equipment
& Machinery
Sch-I/
5.1
200 Lit/
Year
Collection, Storage,
Transportation and sell
to registered recycler.
3 ETP Sludge ETP Sch-I/
35.3
216 Collection, Storage,
Transportation and sent
to common TSDF of M/s.
BEIL.
106
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 106 of 129
4 Distillation
Residue
Distillation Sch-I/
20.3
100.68 Collection, Storage,
Transportation and sent
for co-processing in
cement industries or sent
to common incineration
site,BEIL Dahej.
5 Spent Catalyst Process
(Product
No:9,10)
Sch-I/
28.3
5 Collection, Storage,
Transportation and
sent to registered
regenerator under Rule-
9 permission.
6 HCl (10%) Scrubber SCH-
1/26.1
263 Collection, Storage &
210 MT/Month (2520
MT/year)will be reused
within premises in the
manufacturing of Calcium
Chloride.
7 NaOCl (12%) Scrubber SCH-
1/26.1
270 Collection, Storage &
convert to product and
than sell as main product.
8 Sodium Sulphite
(25%)
Scrubber Sch-II/
B36
316.8
Collection, Storage,
Transportation and sold
to end user having
permission under rule-9. 9 Spent Sulphuric
Acid (50%)
Process
(Product
No:7,8)
Sch-I/
26.3
2529
10 Ammonium
sulphate (15%)
Scrubber
Sch-II/
B15
1350
11 Ammonium
bisulphate (50%)
Process
(Product
No:8)
Sch-I/
26.3
1350
107
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 107 of 129
12 Spent Solvent Process
(Product
No;17)
Sch-I/
28.6
3045
Collection, Storage,
Distillation and Reuse
within premises.
13. Off Specification
Products
From mfg.
Process
(Batch
failure)
Sch-I/
28.4
20
Collection, Storage,
Transportation and sent
for co-processing in
cement industries or
Disposal at common
incineration site,BEIL
Dahej.
-
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Unit has membership of
CETP,Saykha
Ref. No: BEIL/ANK/2019
dated13/09/2019
iii Details of Non-Hazardous waste & its disposal
(MSW and others)
There will be no generation of
Non-Hazardous waste.
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery, reuse of recovered Solvents etc.
(Details in Table Format)
Only one solvent is Used in process. Other Solvent is to be used as reactant.
Solvent
Boiling
Point
(0C)
Vapor
Pressure
Inpu
t
(MT/
mon
th)
Outpu
t
(MT/m
onth)
Loss %
Recovery
%
Loss
Toluene 110.6°C
3.8 kPa
(@
25°C)
420 400 39 95.25 1.85
ii VOC emission sources and its mitigation measures
During operation stage, leakage through valves/pumps, leakage and emission from open
drum containing chemicals, open feeding, storage tanks, etc. will be major sources of fugitive
108
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 108 of 129
emissions and VOCs. Excess use of solvent/s may also results fugitive emission from the
process vessels.
• Solid raw material charging will be done through closed system.
• Entire process will be carried out in the closed reactors with proper maintenance of
pressure and temperature.
• Close feeding system will be provided for centrifuges. Centrifuge and filtrate tank vents
will be connected to vent chillers.
• Fugitive emission over reactors, formulation areas, centrifuges, chemical loading,
transfer area, will be collected through hoods and ducts by induced draft and controlled
by scrubber/dust collector.
• Emphasis will be given to solvent management/solvent loss prevention.
• Control by having proper scrubbing system.
• Condenser to trap VOC.
• Enclosures to chemical storage area, collection of emission from loading of raw
materials in particular solvents through hoods and ducts by induced draft, and control
by scrubber/dust collector to be ensured.
• Proper maintenance schedule will be adhered to avoid emissions through flange joints,
pump seals etc.
• Minimum number of flanges, joints and valves in pipelines.
• Proper gland packing will be maintained for pumps and valves and to the extent
possible pumps with mechanical seal.
• All the raw materials will be pneumatically transfer to the reactor.
• All rotating equipments like pumps will be installed with mechanical seals to arrest any
sort of emissions.
• A regular preventive maintenance schedule will be in place to replace or rectify all
gaskets and joints etc. as a part of ISO systems to ensure no fugitive emissions take
place.
• Periodic monitoring of work area will be carried out to check the fugitive emission.
• Solvent tank vents will be connected to vent chillers.
• Adequate ventilation will be provided.
• Airborne dust at all transfers operations/ points will be controlled either by spraying
water or providing enclosures.
109
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 109 of 129
• Breather valves will be provided on solvent tanks.
H � Details regarding storage of Hazardous chemicals
Storage details Name of major Hazardous chemicals Remarks
Storage tanks
Acetone cynohydrin, Benzoyl
Chloride,Hydrochloric Acid,Sulphuric
Acid , Methanol or Toluene
Drum/Barrel storage
Liquid Ammonia, Hydrazine Hydrate,
Hydrogen peroxide, Dibuthyl Phthalate,
Acetone,IPA, Diethylamine, 2-
Ethylhexanoic acid
Cylinder,Bottle or
Tonner
Bromine and Chlorine
� Applicability of PESO: If Applicable, company will take permission.
• During the meeting dated 03/10/2019, technical presentation made by the Project proponent. Committee
asked about query reply regarding product profile change and end use of product, technical expert of PP
informed that there is no change in product profile and only change is in end use of product mentioning other
than pesticide.
• Committee noted that this proposal is new unit in GIDC Saykha. Source of Water is GIDC. Committee asked
waste water management, PP informed that total industrial effluent process and washing will be treated in
primary,secondary and tertiary ETP units and treated effluent alongwith utility effluent will be further treated
in RO plant.RO permeate will be reused back in process while RO reject will be evaporated in single stage
evaporator. Committee asked for adequacy of in-house single stage evaporator and drastic reduction of
COD in ETP units, PP could not explain during meeting .Committee asked for submit third party NABL
accredited academic institute report regarding adequacy of ETP and RO and single stage evaporator. PP
mentioned that MCS and bag filter will be as APCM with boiler and thermopack separately. PPhas
addressed revised Hazardous waste generation and its disposal details.
• Considering the above project details, after detailed discussion, the terms of reference (ToR) were
prescribed as below and as per the standard TOR for the Synthetic Organic Chemical projects
recommended by SEAC vide letter no. EIA-10-GEN-21/1480 dated 14/09/2017 and approved by SEIAA
in its 12th meeting dated 16/09/2017 for the EIA study to be done covering 10 Km radial distance from
the project boundary.
1. Unit shall submit Notarized undertaking regarding end use of proposed products areother than
110
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 110 of 129
pesticide and its intermediate.
2. Compliance of MoEF&CC’s OM dated 01/05/2018 regarding “Corporate Environment Responsibility”
(CER). Fund allocation for Corporate Environment Responsibility (CER) shall be made as per
MoEFCC’s O.M. No. 22-65/2017-IA.III dated 01/05/2018 for various activities therein. The details of
fund allocation and activities for CER shall be incorporated in EIA/EMP report.
3. Submit third party NABL accredited recognized academic institute report regarding adequacy of ETP,
RO plant and single stage evaporator with stage wise reduction of pollutants like BOD, COD, TDS
etc.
4. Submit Membership certificate of CETP Saykha with valid CCA order of CETP saykha at a time of
appraisal.
5. Explore the use of renewable energy to the maximum extent possible. Details of provisions to make
the project energy-efficient through energy efficient devices and adoption of modes of alternative eco-
friendly sources of energy like solar water heater, solar lighting etc. Measures proposed for energy
conservation.
6. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for use
in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor prevention
of losses of solvents to the best minimum extent.
7. Safety precautions including flame proof electric fittings to be taken to avoid fire hazard during
unloading, storage, transportation, handling and processing of Solvents etc.
8. PP shall furnish status of all the applicable Rules, Acts, Regulation, Clearances in a tabular form.
• The TOR prescribed as above and as per the standard TOR approved by SEIAA and the model ToRs
available in the MoEF&CC’s sector specific EIA Manual for ‘Synthetic Organic Chemical Industry’ shall be
considered as generic TORs for preparation of the EIA report in addition to all the relevant information as
per the generic structure of EIA given in Appendix III in the EIA Notification, 2006.
• Further Project Proponent may be advised to submit final EIA Report with EC application within 100 days
from the date of issuance of this ToR to expedite processing of Environment Clearance application.
• The project proponent shall have to apply for Environmental clearance through online portal
http://environmentclearance.nic.in/along with final EIA report.
15. SIA/GJ/IND2/40220/2019
M/s. Industrial Chemical Work
Plot no. B-1/1+2+3, Phase – II, GIDC
Naroda, Ahmedabad
ToR – Reconsideration
Category of the unit: 5(f)
111
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 111 of 129
Project status: Expansion
• This office has received an application vide their online proposal no. SIA/GJ/IND2/40220/2019 dated
29/07/2019 made by project proponent (PP) regarding grant of Terms of Reference [ToR] for preparation of
EIA/EMP report.
• Project proponent (PP) has submitted Form-1, PFR and relevant details/information.
• This is an expansion unit proposes for manufacturing of synthetic organic chemicals tabulated as below:
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
SR.
NO PRODUCT NAME
CI Name/
CAS No.
Existing
MT/Month
Proposed
MT/Month
Total
Proposed
MT/Month
1 Para Amino Azo Benzene 4-sulfonic
Acid (PAAB4SA) 104-23-4 5.0 65.0 70
2 Ortho Anisidine para sulphonic Acid 98-42-0 1.0 NIL 1.0
3 4 Amino Di phenyl Amine 2 sulfonic
Acid 101-54-2 5.0 15.0 20.0
4 Para Nitro Toluene Ortho Sulfonic
Acid (PNTOSA) - NIL 70 70
5 Direct Dyes
- NIL 60 60
Direct Black 22
Direct Black 80
Direct Black 168
Direct Red 23
Direct Red 80
Direct Red 81
Direct Yellow 147
Direct Red 239
Direct Orange 39
Direct Red 153
Direct Red 152
Direct Red 154
TOTAL 11 210 221
112
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 112 of 129
• PP was called for presentation in the SEAC meeting dated 14/08/2019.
• During the meeting dated 14/08/2019, technical presentation made by the Project proponent.
• Committee noted that this proposal is for expansion. Unit is located at GIDC, Naroda. Unit has valid CC&A.
Unit has submitted Compliance of CC&A. PP ensured that there is no court case and public complaint
against this unit. Source of water is GIDC. Committee noted that expansion is @ 22 times than the current
capacity and told the project proponent/expert consultant to revise the proposal and come again for the
presentation considering existing capacity.
• After detailed discussion, it was decided to defer the proposal and call the project proponent with revised
proposal considering existing production capacity.
• PP submitted revised application with considering existing production capacity and its presentation for
meeting dated 03/10/2019.
• This case was reconsidered in meeting dated 03/10/2019.
• PP submitted revised product profile as above and salient features of water , air and Hazardous waste
management as below(Revised):
Sr.
no. Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Existing: 0.60Cr.
Proposed: 4.30Cr.
Total: 4.9Cr.
B Total Plot area
( sq. meter)
Existing:4581Sq. m.
Proposed: NIL
Green belt area
( sq. meter)
Existing: 200 Sq. m.
Proposed: 200 Sq. m.
Total: 400 Sq. m.
C Employment generation Existing: 10
Proposed: 17
Total: 27
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC Naroda
113
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 113 of 129
Status of permission from the concern authority
ii Water consumption (KLD)
Sr
No Category
Water Consumption In KLD
Existing Additional Total
1. Domestic Purpose 0.5 1.5 2.0
2.
INDUSTRIAL
Mfg. Process Water 11.0 14.0 25.0
Washing 9.0 NIL 9.0
Boiler 1.0 19.0 20.0
Cooling 1.0 4.0 5.0
Total water Consumption ( Domestic) 0.5 1.5 2.0
Total water Consumption (Industrial ) 22.0 37.0 59.0
1) Total water requirement for the project: 61.0 KLD
2) Quantity to be recycle: Nil
3) Total fresh water requirement: 61.0KLD
iii Waste water generation (KLD)
Sr
No Category
Waste Water Generation In KLD
Existing Additional Total
1. Domestic Purpose 0.5 1.5 2.0
2.
INDUSTRIAL
Mfg. Process 6.0 41.0 47.0
Washing 9.0 NIL 9.0
Boiler 1.0 2.0 3.0
Cooling 1.0 1.0 2.0
Total Waste water Generation
( Domestic) 0.5 1.5 2.0
Total Waste water generation
(Industrial ) 17.0 44.0 61.0
iv Treatment facility within premises with capacity [For existing and Proposed]
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
Existing Low Concentration Effluent Treatment Plant
114
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 114 of 129
Sr.
No. Name of Unit Capacity
1 Collection Tank 16.50 KL
2 Neutralization Tank 9.50 KL
3 Filter Press -
4 Primary Settling Tank 34.0 KL
5 Aeration Tank 32.0 KL
6 Secondary Settling Tank 15.0 KL
7 Filter Nutch -
8 Holding Tank 12.0 KL
9 Activated Carbon 5.0 KL
10 Sand Filter 2.0 KL
Proposed Dilute Stream Effluent Treatment Plant
Sr.
No. Name of Unit Capacity
1 Collection Tank 16.50 KL
2 Neutralization Tank 9.50 KL
3 Filter Press -
4 Activated Carbon 5.0 KL
5 Sand Filter 2.0 KL
High Concentration Effluent Treatment Plant
Sr.
No. Name of Unit Capacity
1 Collection cum Neutralization Tank 35 KL
2 Filter Press -
3 Holding Tank -2 Nos. 35 KL each
Treatment scheme including segregation at source.
• Existing Low Concentration Effluent Treatment Plant
555th meeting of SEAC
• Proposed Dilute Steam Effluent Treatment Plant
• High Concentration Effluent Treatment Plant
Note: (In case of CETP discharge) :
Management of waste water keeping in view direction under section 18 (1) (b) of the Water
(Prevention and Control of Pollution) act, 1974 issued by CPCB regarding compliance of
CETP.
• Total industrial 61.0 KLD Waste Water Generation from Manufacturing Process and Other
Ancillary Operation.
• Low Concentrated Waste Water Treated in Primary, secondary ETP Plant and then
Treated Water Final Discharge though 5 KLD CETP Naroda (NEPL).
• High Concentrated Effluent @ 56.00 KLD including washing stream will be discharge
through Common Facility @ 28.00 KLD and remaining 28.0 KLD Water in house Spray
dryer for the Evaporation.
Brief note on adequacy of ZLD (In case of Zero Liquid Discharge):
• Not applicable
Collection Tank
Neutralization Tank
Filter NutchHolding
Tank
Collection Tank Neutralization
Tank
meeting of SEAC-Gujarat, dated 03.10.2019
Page 115 of 129
Proposed Dilute Steam Effluent Treatment Plant
High Concentration Effluent Treatment Plant
Note: (In case of CETP discharge) :
ste water keeping in view direction under section 18 (1) (b) of the Water
(Prevention and Control of Pollution) act, 1974 issued by CPCB regarding compliance of
Total industrial 61.0 KLD Waste Water Generation from Manufacturing Process and Other
Low Concentrated Waste Water Treated in Primary, secondary ETP Plant and then
Treated Water Final Discharge though 5 KLD CETP Naroda (NEPL).
High Concentrated Effluent @ 56.00 KLD including washing stream will be discharge
on Facility @ 28.00 KLD and remaining 28.0 KLD Water in house Spray
dryer for the Evaporation.
Brief note on adequacy of ZLD (In case of Zero Liquid Discharge):
Filter PressPrimary Settling
Tank
Aeration Tank
Activated Carbon
Sand Filter Final
Collection Tank
Neutralization Tank
Activated Carbon
Sand Filter
115
ste water keeping in view direction under section 18 (1) (b) of the Water
(Prevention and Control of Pollution) act, 1974 issued by CPCB regarding compliance of
Total industrial 61.0 KLD Waste Water Generation from Manufacturing Process and Other
Low Concentrated Waste Water Treated in Primary, secondary ETP Plant and then
High Concentrated Effluent @ 56.00 KLD including washing stream will be discharge
on Facility @ 28.00 KLD and remaining 28.0 KLD Water in house Spray
Secondary Settling
Tank
Final Collection Tank
116
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 116 of 129
v Mode of Disposal & Final meeting point
Domestic: The generated sewage will be disposed through soak pit/septic tank.
Industrial:
• Total industrial 61.0 KLD Waste Water Generation from Manufacturing Process and Other
Ancillary Operation.
• Low Concentrated Waste Water Treated in Primary, secondary ETP Plant and then
Treated Water Final Discharge though 5 KLD CETP Naroda (NEPL).
• High Concentrated Effluent @ 56.00 KLD including washing stream will be discharge
through Common Facility @ 28.00 KLD and remaining28.0 KLD Water in house Spray
dryer for the Evaporation.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE, CHWIF etc.
Name of Common facility
Sr No Method of Disposal Wastewater quantity in KLD
1. CETP Naroda 5.0
2. In House Spray Dryer 28.0
3 society for clean & green earth -Naroda 28.0
4 Common Spray Drier NEPL,
Membership of Common facility (CF)
• society for clean & green earth -Naroda
• NEPL
(For waste water treatment)
vii Simplified water balance diagram with reuse / recycle of waste water
Existing Water Balance Diagram
555th meeting of SEAC
Total Proposed Water Balance Diagram
meeting of SEAC-Gujarat, dated 03.10.2019
Page 117 of 129
Total Proposed Water Balance Diagram
117
555th meeting of SEAC
vii Reuse/Recycle details (KLD)
[Source of reuse & application area]
Total reuse NIL
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Existing & Proposed
Sr.
no Stack attached to
Stack
height
in meter
1 Small Industrial
Boiler 0.8 TPH
2 IBR Boiler (2 TPH)
meeting of SEAC-Gujarat, dated 03.10.2019
Page 118 of 129
[Source of reuse & application area]
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Stack
height
in meter
Fuel Consumption APCM
11 Fire Wood
(Removed) 10 MT/Month
Adequate
Stack
Height
15 Natural
Gas 1200 SCM/Day
Adequate
Stack
118
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
APCM Remark
Adequate
Stack
Height
Replace
with 2
TPH
Boiler
Adequate
Stack Proposed
119
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 119 of 129
Height
3
Hot Air Generator
for SFD (800 Kcal
/Hr)
11 Natural
Gas 200 SCM/Day
Adequate
Stack
Height
Existing
4
Hot Air Generator
for SFD (800 Kcal
/Hr) 2 nos
11 Natural
Gas 400 SCM/Day
Adequate
Stack
Height
Proposed
5 Hot Air Generator
(10 lac Kcal /Hr) 15 Coal 3 MT/Day
Multi
Cyclone
Separator
with Bag
Filter
Proposed
6 Hot Air Generator
(30 Lac Kcal /Hr) 21 Coal 7 MT/Day
Multi
Cyclone
Separator
with Bag
Filter
Proposed
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Existing & Proposed
-
Sr
no
Stack attached to Stack
height in
meter
APCM Type of
Emission
Remark
1 Sulphonation Vessel of
Vessel (OA4SA)
12 Two Stage
Alkali Scrubber
SO2 Existing
2 Sulphonation Vessel of
PNTOSA
SO2 Proposed
3 Spin Flash Dryer 11 - PM Existing
4 Tray Dryer 11 - PM Existing
5 Spray Dryer for Product
(1000 LPH)
15 Multi Cyclone
Separator With
Two Stage
PM Proposed
120
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 120 of 129
Water Scrubber
6 Spin Flash Dryer 11 - PM Proposed
7. Spray Dryer for Water
Evaporation (2500 LPH)
21 Multi Cyclone
Separator With
Two Stage
Water Scrubber
PM Proposed
iii Fugitive emission details with its mitigation measures.
� The entire manufacturing activities will be carried out in the closed reactors and regular
checking and maintenance of reactors will be carried out to avoid any leakages.
� The tank vents will be equipped with either a carbon filter or an oil trap to prevent water vapor
from entering the tank as it breathes.
� All the motors of pumps for the handling of hazardous chemicals will be flame proof and
provided with suitable mechanical seal with stand-by arrangement
� Control of all parameters on a continuous basis will be done by adequate control valves,
pressure release valves and safety valves etc.
� All the flange joints of the pipe lines will be covered with flange guards.
� All the raw materials will be stored in isolated storage area and containers tightly closed.
� There will also be provision of adequate ventilation system in process plant and hazardous
chemical storage area
F Hazardous waste
(as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules
2016.
Existing & Proposed
i
S
r
.
N
o
Types of
Hazardous
Waste
Sources Categ
ory
Existi
ng
MT/Ye
ar
Propo
se
MT/Ye
ar
Ultim
ate
MT/Y
ear
Disposal
1 ETP Sludge ETP
Plant 35.3 360 540 900
Collection, storage,
Transportation and
Dispose by sending to co-
processing OR Send to
121
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 121 of 129
Active TSDF Site
2 Used Oil
Plant
Machiner
y
5.1 0.1 0.4 0.5 Collection, storage, Reuse
within premises.
3
Empty
barrels/
Container/
Liners
contaminated
Material
Storage
and
Handling
33.1
2.0 18.0 20.0 Collection, storage,
Transportation and
Dispose by selling to
Registered Recycler 2.5 22.5 25.0
4
Process
Waste
(Residue)
4
ADAPSA 26.1 1.2 NIL NIL ---
5 SBS
Scrubbin
g media
4
ADAPSA
PNTOSA
26.1 NIL 150 150
Collection, Storage and
reuse within plant
premises in PAABSA
process against total
requirements of @ 1300
MT/Year
6
Process
Waste
(Gypsum)
-- 26.1 120 NIL NIL ---
7
Process
Waste
(Iron Sludge)
4
ADAPSA 26.1 36 175 211
Collection, Storage,
Transportation & Dispose
to Co processing or TSDF
8
Spent
Sulphuric
Acid (45% to
70%)
PNTOSA
OA4SA 26.2 62.0 1224 1286
Collection, Storage and
900 MT/Year Spent Acid
Reuse in PAAB4SA and
216 MT/Year Spent Acid
Reuse in 4-ADA2SA
manufacturing process
and remaining 170
MT/Year Spent Acid Send
to actual users having
122
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 122 of 129
permission under Rule 9
Note: There is no generation of process residue and Gypsum waste from process. The acidic
effluent will treat in ETP.
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Not Applicable
iii Details of Non-Hazardous waste & its disposal(MSW and
others)
No
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
� There is no any type of solvent required
ii VOC emission sources and its mitigation measures
• Sources of fugitive emissions include storage of chemicals, raw material handling and,
hazardous waste storage area
Measures :
• The fugitive emissions in terms of handling losses will get reduced by proper storage and
handling.
• Hazardous chemicals will be stored as per standard criteria. • Periodically monitoring will
be carried out as per the post project monitoring plan.
• All materials must be stored in suitable packing to prevent contamination of air.
• Enclosed system & efficient procedures for materials charging shall be ensured.
H � Details regarding storage of Hazardous chemicals
Storage details Name of major Hazardous
chemicals Capacity Nos.
Tank
Sr
No
Name of Raw
Material
Max
Storage
MT
Nos of
Storage Tank
Rema
rk
1 Sulphuric Acid 20 1 -
2 Spent Sulphuric
Acid
20 1 -
3 Oleum 23 % 10 1 1
123
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 123 of 129
4 Oleum 65 % 2 1 spare
tank
5 Formaldehyde 5 1
6 HCl 20 1
Drum / Barrel storage
Aniline Oil
Caustic Soda
Mix Cleave Acid
� Applicability of PESO: Not Applicable.
• During SEAC meeting dated 03/10/2019, Committee asked about reply of above query dated 14/8/19,
technical expert of PP informed that they have submitted revised proposal with curtail production and now
expansion of production is from 11 to 221 MT/Month of dyes intermediates and dyes. Committee asked
about area adequacy for proposed expansion, PP informed that proposed plot is having sufficient area for
accommodate proposed expansion. Committee asked about waste water management, technical expert of
PP informed that dilute stream from prosed expansion will be treated in primary and tertiary ETP units and
treated effluent will be sent to CETP of NEPL through tanker as per existing CCA. High COD effluent will be
partly evaporated in in-house spray dryer and rest of sent to common facility of M/s NEPL and M/s Society
for clean and green, Naroda after primary treatment.Natural gas will be used as fuel in boiler and hot air
generator. MCS with two stage scrubber will be provided with spray dryer. Committee deliberated on
Hazardous waste management and bleed liquor disposal details.
• Considering the above project details, after detailed discussion, the terms of reference (ToR) were
prescribed as below and as per the standard TOR for the Synthetic Organic Chemical projects
recommended by SEAC vide letter no. EIA-10-GEN-21/1480 dated 14/09/2017 and approved by SEIAA
in its 12th meeting dated 16/09/2017 for the EIA study to be done covering 10 Km radial distance from
the project boundary.
1. Unit shall submit third party NABL accredited recognized academic institute treatability report
regarding ETP units and adequacy of in-house spray dryer for effluent at a time of appraisal.
2. Details with respect to justification for proposed expansion: (1) To address proportionate availability of
space for production plant. (2) To address proportionate availability of storage area for raw materials
finished goods, utilities considering fire-safety norms & PESO standards and goods carrier movement
within premises. (3) To address proportionate captive/common infrastructure available to
accommodate additional load due to proposed expansion. (4) Environment impact and its mitigation
measures for common/ captive infrastructure due to proposed production.
124
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 124 of 129
3. Compliance of MoEFCC’s OM dated 01/05/2018 regarding “Corporate Environment Responsibility”
(CER). Fund allocation for Corporate Environment Responsibility (CER) shall be made as per
MoEFCC’s O.M. No. 22-65/2017-IA.III dated 01/05/2018 for various activities therein. The details of
fund allocation and activities for CER shall be incorporated in EIA/EMP report.
4. Segregation of waste water streams based on characteristics and its proper management keeping in
view direction under section 18 (1) (b) of the Water (Prevention and Control of Pollution) act, 1974
issued by CPCB regarding compliance of CETP. (COD, BOD, TDS etc. of each stream shall be
given)
5. Explore the use of renewable energy to the maximum extent possible. Details of provisions to make
the project energy-efficient through energy efficient devices and adoption of modes of alternative eco-
friendly sources of energy like solar water heater, solar lighting etc. Measures proposed for energy
conservation.
6. Adequacy of utilization of spent sulphuric acid back in process with material balance for various
products and management of balance quantity keeping Hazardous and Other Waste (Management
and Trans boundary Movement) Rules, 2016 in view.
7. Provision of spare tank as a safety precaution for Oleum storage and emergency transfer facility for
Oleum as per the prevailing Rules/ guidelines.
8. Membership certificate of Common facility (Common Spray dryer, Common MEE, Common
Incinerator etc.) with booking quantity in KLD along with other details/information like Spare capacity
of Common Facility (CF), quality of waste water by member industry and assurance by CF that there
is no adverse impact on Environment and Human Health due to treatment of waste water received
from your industrial effluent.
9. Submit status of compliance of Environmental norms of existing Common Infrastructure of M/s: NEPL
and M/s Society for clean and green earth, Naroda.
10. PP shall furnish status of all the applicable Rules, Acts, Regulation, Clearances in a tabular form.
• The TOR prescribed as above and as per the standard TOR approved by SEIAA and the model ToRs
available in the MoEF&CC’s sector specific EIA Manual for ‘Synthetic Organic Chemical Industry’ shall be
considered as generic TORs for preparation of the EIA report in addition to all the relevant information as
per the generic structure of EIA given in Appendix III in the EIA Notification, 2006.
• Further Project Proponent may be advised to submit final EIA Report with EC application within 100 days
from the date of issuance of this ToR to expedite processing of Environment Clearance application.
• The project proponent shall have to apply for Environmental clearance through online portal
125
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 125 of 129
http://environmentclearance.nic.in/along with final EIA report.
16 SIA/GJ/IND2/35821/2019
M/s. Harsh OrganoChem (I) Pvt Ltd
Plot No. C-74, GIDC Saykha, Vagra;
Bharuch
ToR – Reconsideration
• PP remained absent in the EC – Appraisal presentation held on 01/10/2019.
• After detailed discussion, Committee decided to defer the proposal and consider the same after
reply is submitted from Project Proponent in one of the upcoming meeting of SEAC.
17. SIA/GJ/MIS/34441/2019
M/s. Industrial Waste Management
Services
Plot no.399,400,401,402,403,404,405/2 &
406,Saragvala,Ta- Dholka,Dis- Ahmedabad
Reconsideration of
ToR- Refer Back Case
Category of the unit: 7(d)
Project status: New
• M/s: Industrial Waste Management Services, applied for Terms of Reference (ToR) and the SEAC
recommended the project for grant of Terms of Reference (ToR) vide this office letter no. EIA-10-
2018/IND2/1217/2565 dated 08/08/2019 for conditions as mentioned therein:
• The case was referred back by the SEIAA, Gujarat vide SEIAA letter no- SEIAA/GUJ/ToR/1227/2019
dated 23/08/2019 with the following point:
1. To check the validity of TOR accorded by MoEF&CC in past and extension application if any.
2. To verify the reason/s for delay in project considering the TOR accorded previously by
MoEF&CC.
3. To check the proposed location of site with respect to land use pattern nearby & the water
bodies if any.
4. To verify the source of incinerable waste & feasibility of development of preprocessing facility
of incinerable waste along with TSDF looking to past scenario.
5. To verify the expertise of handling of different types of hazardous waste specifically
incinerable for AFR.
6. To verify the Risk Assessment Report looking to the village location @ 800 meter.
7. To verify the ground water level for post monsoon season.
• Project proponent submitted reply vide their letter dated 26/09/2019 for the above mentioned points.
• PP has submitted as under:
126
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 126 of 129
1. The validity of TOR accorded by MoEF&CC in past and extension application details
submitted.
2. The reason/s for delay in project considering the TOR accorded previously by
MoEF&CC submitted.
3. The proposed location of site with respect to land use pattern nearby & the water
bodies if any details submitted.
4. The source of incinerable waste & feasibility of development of preprocessing facility
of incinerable waste along with TSDF looking to past scenario submitted.
5. The expertise of handling of different types of hazardous waste specifically incinerable
for AFR submitted.
6. The Risk Assessment Report looking to the village location @ 800 meter submitted.
7. The ground water level for post monsoon season will be carried out in October 2019.
• The case was reconsidered in the SEAC meeting dated 03/10/2019.
• During the SEAC meeting dated 03/10/2019, the said reply was considered by the Committee.
Committee asked clarification regarding validity of TOR accorded by MoEF&CC in past and extension
application details, technical expert of PP has informed that TOR had been accorded by MoEF&CC with
letter No. 10-11/2016-IA.III, 26th March, 2016 under Category 7 (d) “A” and valid up to 25th March, 2019
and extension of validity of ToR is not done by PP. Committee asked clarification regarding delay in
project considering the TOR accorded previously by MoEF&CC submitted, PP informed that due to
postpone of public hearing frequently for proposed project and hence delay in proposed project.
Committee asked about proposed location of site with respect to land use pattern nearby & the water
bodies, PP submitted goggle map of proposed site and nearby Bhogavo river distance. Committee
disagree with goggle image and asked them to submit adequate land use patter with classify regarding
proposed site land characteristic and is agriculture land or not. Committee asked about source of
Incinerable waste & feasibility of development of pre-processing facility of Incinerable waste along with
TSDF looking to past scenario, PP has informed general details regarding hazardous waste generation
in his presentation. Hence committee informed that you have to submit actual data of source of
Incinerable waste with feasibility report regarding pre-processing facility of Incinerable waste along with
TSDF looking to past scenario. Committee deliberated on the expertise of handling of different types of
hazardous waste specifically Incinerable for AFR, Risk Assessment Report looking to the village location
@ 800 meter and the ground water level for post monsoon season, PP has not submitted adequate
technical details regarding it.
127
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 127 of 129
After deliberation, SEAC unanimously decided to consider the proposal after satisfactory and adequate
technical details submission of the following points,
1. To check the proposed location of site with respect to land use pattern nearby & the water
bodies if any.
2. To verify the source of Incinerable waste & feasibility of development of pre-processing facility
of Incinerable waste along with TSDF looking to past scenario.
3. To verify the expertise of handling of different types of hazardous waste specifically
Incinerable for AFR.
4. To verify the Risk Assessment Report looking to the village location @ 800 meter.
5. To verify the ground water level for post monsoon season.
18 SIA/GJ/IND2/34072/2019
M/s. Ambica Industries
Plot No. 1305/4 and 1305/05, Phase-
IV, GIDC, Naroda, Ahmedabad
Reconsideration of ToR
- Refer back Case
Category of the unit: 5(f)
Project status: Expansion
• M/s: Ambica Industries applied for Terms of Reference (ToR) and the SEAC recommended the project
for grant of Terms of Reference (ToR) vide this office letter no. EIA-10-2018/IND2/1220 dated
08/08/2019 for conditions as mentioned therein:
• The case was referred back by the SEIAA, Gujarat vide SEIAA letter no- SEIAA/GUJ/ToR/1228/2019
dated 23/08/2019 with the following point:
1. To verify the applicability of GPCB circular dated 03/11/2018 and compliance of the same
along with revised details submitted by project proponent and ZLD option.
• Project proponent submitted presentation for compliance of above query showing applicability of GPCB
circular dated 03/11/2018 and compliance of the same along with revised details submitted by project
proponent and ZLD option for meeting dated 03/10/2019.
• The case was reconsidered in the SEAC meeting dated 03/10/2019.
• During the SEAC meeting dated 03/10/2019, committee asked for compliance of GPCB circular dated
03/11/2018 regarding dirty products. Technical expert of PP informed that Unit has valid Consent to
Operate (CTO) for existing products having total production capacity 10 MT/Month. 6- Acetyl
OAPSA falls in dirty product list. As per GPCB Circular 3rd November, 2018, 50 % additional capacity of
dirty product can be permitted to existing units. Therefore, they have applied for additional quantity of 2.5
128
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 128 of 129
MT/Month of 6 Acetyl OAPSA. Committee disagree with reply submitted by the unit and informed PP to
submit compliance of GPCB circular dated 03/11/2018 with each and every condition of circular dated
03/11/2018.
After deliberation, SEAC unanimously decided to consider the proposal after adequate reply of SEIAA
query and submission of the following details.
1. To verify the applicability of GPCB circular dated 03/11/2018 and compliance of the same
along with revised details submitted by project proponent and ZLD option.
19 SIA/GJ/IND2/35510/2018
M/s. Atlas Life Sciences
Plot No:C-1,360 & 361, GIDC Odhav,
Ahmedabad
Appraisal
• PP remained absent in the EC – Appraisal presentation held on 01/10/2019.
• After detailed discussion, Committee decided to defer the proposal and consider the same in one of
the upcoming meeting of SEAC.
20 SIA/GJ/IND2/32683/2019
M/s. Icon Pharmachem
Plot No. D‐2/CH/146, GIDC‐Dahej‐2,
.Vagra ,Bharuch
EC – Reconsideration
of Refer Back Case
Category of the unit: 5(f)
Project status: EC-Amendment
• M/s: Icon Pharmachem applied for amendment of Environment clearance and the SEAC recommended
the project for grant of amendment of Environment clearance vide this office letter no. EIA-10-
2018/IND2/1862 dated 11/06/2019 for conditions as mentioned therein:
• The case was referred back by the SEIAA, Gujarat vide SEIAA meeting 272th dated 20/09/2019 with the
following point:
1. To verify the compliance of existing unit through SPCB’s last inspection report.
• Project proponent submitted presentation for compliance of existing unit through SPCB’s last inspection
report for meeting dated 03/10/2019.
• The case was reconsidered in the SEAC meeting dated 03/10/2019.
• During the SEAC meeting dated 03/10/2019, committee asked for compliance of existing unit through
SPCB’s last inspection report, Technical expert of PP informed that GPCB visited this unit on 14/05/2019
and written instruction regarding unit have established 3KL Glass line reactor, Centrifuge & simple Nutch
Filter. In this regard unit shall have to submit product wise Plant capacity and Waste like spent Solvent of
129
555th meeting of SEAC-Gujarat, dated 03.10.2019
Page 129 of 129
Distillation Residue, spent carbon & Organic process waste are mentioned in Environment Clearance but
not presented in CTO fresh application. Technical expert of PP informed that they have installed plant
machinery for product namely 2-Chloroethylamine Hydrochloride,N,N Bis(2‐Chloroethyl)Amine
Hydrochloride,1‐Acetyl‐4‐(4’‐ Hydroxyphenyl) Piperazine and 1‐(3‐Chlorophenyl) Piperazine only which
is zero liquid discharge product and hence not installed ETP and MEE. Also from this proposed products
for which CTO applied in which distillation residue, spent carbon and organic process waste is not
generated. Also technical expert of PP informed that no legal action taken by GPCB with respect to
inspection report dated 14/05/2019. Committee observed that there is no adverse remarks in last
inspection report of GPCB on dated 14/05/2019
• After detailed deliberation, SEAC unanimously decided to recommend grant of EC-Amendment
order as earlier submitted vide letter no-.EIA-10-2018/IND2/1862 dated 11/06/2019 for conditions
as mentioned therein.
Subject: Recommendation to return 151 proposals to respective Project Proponents regarding.
• The 151 proposals were considered in the SEAC meeting dated 01.08.2019 and accordingly
recommendation letters to de-list such proposals were sent to SEIAA, Gujarat.
• The project location of said 151 proposals fall under Critically Polluted Areas (CPAs) and Severely Polluted
Areas (SPAs) identified by the CPCB.
• Committee noted that these proposals attracts the General Condition (GC) of the Environment Impact
Assessment Notification, 2006.
• Committee felt that these proposals shall be returned to the respective Project Proponents.
• During SEAC meeting dated 03.10.2019, committee unanimously decided to recommend to return all 151
aforementioned proposals to the respective project proponent.
Meeting ended with thanks to the Chair.
Minutes approved by:
1. Dr. Dinesh Misra, Chairman, SEAC
2. Shri S. C. Srivastav, Vice Chairman, SEAC
3. Shri. R. J. Shah, Member, SEAC
4. Shri V. N. Patel, Member, SEAC