Date post: | 25-Feb-2018 |
Category: |
Documents |
Upload: | hoanghuong |
View: | 218 times |
Download: | 4 times |
r
Minutes of meeting held in the chamber of Shri KamalbhaiTrivedi Advocate General State of Gujarat on dtd 382012 at1830 hrs and 21082012 at 1900 hrs regarding vetting of thereport prepared by Gujarat National law University on legalopinion for Bhadbhut Barrage Project
A meeting was held in the chairmanship of Advocate General Shri
Kamalbhai Trivedi on 382012 at 1830 hrs regarding vetting of the
report prepared by Gujarat National Law University (GNLU) on Legal
Opinion for Bhadbhut Barrage Project The following officials remained
present
(1) Dr Bimal N Patel Director GNLU
(2) Dr M S Patel Secretary (Kalpasar) Government of Gujarat
(3) Shri U S Chandorikar Chief Engineer amp Add Secretary (K-2)Kalpasar Department Government of Gujarat
(4) Shri A B Thakkar Superintending EngineerProject Implementation Unit-2 Vadodara
Chairman of the meeting welcomed all and requested to present the
agenda details of the meeting Secretary (Kalpasar) provided the details
of the study assigned to GNLU for legal opinion on the barrage project
It was explained that the proposed barrage will be constructed on
river Narmada near village Bhadbhut Looking to the experience in
case of Sardar Sarovar Project on river Narmada it was considered
to take legal opinion regarding possibility of inter state disputes if
any with reference to the provisions of Narmada Water Disputes
Tribunal Award In this regard Expert Advisory Group of Kalpasar
Project headed by Advisor to Honble Chief Minister decided to utilize the
services of Gujarat National Law University (GNLU) Gandhinagar
Accordingly memorandum of agreement was signed between GNLU and
Kalpasar Department GNLU has prepared the report on Legal Opinion
for Bhadbhut Barrage Project (Annexure-i) and as per agreement it is
also required to be vetted During the discussion Chairman of the1
meeting suggested to provide the details of the project along with its
objectives benefits and related activities for environmental impact
coastal regulation impact fisheries issues flood protection etc carried
out so far Accordingly second meeting was held on 21082012 at
1900 hrs During the discussions held in these two meetings the
following details were discussed with the Director GNLU and the
Kalpasar officials
(1) At the outset of the discussion it was explained that the state has
about 1600 km long sea coastal belt and all along coastline in the
estuarine portion of the rivers meeting sea tidal water entry
creates serious problem of salinity ingress Not only soil in this belt
looses its fertility the surface water and ground water quality is
deteriorated Considering seriousness of the problem in past
government had constituted High Level Committee headed by the
then Chief Secretary during 1975 The Committee suggested tidal
regulators bandharas spreading channels check-dams and other
minor works for prevention of salinity ingress On this suggestion
Government of Gujarat carried out some works from its budget
Also Central Government with due consideration to the problem
sanctioned Rs 200 crore grant during 12th Finance Commission for
salinity ingress prevention works including barrages These
structuresworks have shown good results in prevention of salinity
ingress Government has also carried out a study for evaluation of
positive impacts of these salinity ingress prevention works along
coastal line of Gujarat through Gandhi Labour Institute
Ahmedabad At some places over barrages bridges are also
constructed for road connectivity on both sides of the storages
(2) Narmada river is the largest west flowing river having total length of
1312 km and tail stretch of 161 km lying in Gujarat Before
construction of Sardar Sarovar Project in Gujarat and three major
projects Omkareshwar Maheshwar and Indira Sagar in Madhya
2
r
Pradesh there was continuous river water flow in the estuarine
portion of the river Now the river water is gradually reduced
whereas tidal water flow remained unchanged Hence water
requirement for domestic irrigation and industrial needs of
Bharuch- Dahej region cannot be met with at present At present
GIDC and other industries are pumping 58 MGD water from
Narmada river at Angareshwar (70 km in the upstream of the
proposed Bhadbhut Barrage Project) as the water in the river up to
Angreshwar is not usable even for industrial purpose and there is no
permanent water source available for water requirement of GIDC
and PCPIRexcept Narmada river GIDC has planned for Petroleum
Chemical and Petro-Chemical investment Region (PCPIR) in Dahej
Industrial Area GIDC has planned water requirement at 300 MGD
Per year from 2020 onwards from the proposed barrage for PCPIR
and GIDC estates as discussed with Chief Secretary on 30092011
Bhadbhut Barrage being ideally located is the most preferable water
resource for Dahej-PCPIR industrial arearegion
(3) Water Resources Department as well as GIDC separately envisaged
the barrage of Narmada River since one decade However it was
not materialized Finally Kalpasar Department Government of
Gujarat decided to take up the barrage project as a stand alone
project During the discussion on the need of the project it was
further explained that number of representations had been received
from local people and political leaders at Honble Chief minister
level Honble Minister level and other higher level for construction
of barrage on Narmada river to solve the problem of salinity ingress
and deteriorated quality of surface and ground water The notables
include representations of Hon MLAs of Jhagadia (2001) Jambusar
(2003) Surat and Hansot (2004) and Bharuch (2005) Hon MP of
Bharuch (2005) Shri Ahmed Patel Hon MP (Rajya Sabha) (2008)
Hon Central Minister of Water Resources GO (2010) GIDC (2008
onwards) etc3
It was also explained that Shri Pavankumar Bansal Hon Minister of
Water Resources Government of India vide his letter dated 4th
March 2010 addressed to Hon Chief Minister Gujarat had offered
all technical help for barrage across river Narmada and suggested to
take up a flood protection works in the flood affected area of
Bharuch District with an offer of financial assistance Hon MP Shri
Ahmed Patel vide his letter dated 28th October 2008 had
represented to Hon Minister of Water Resources Government of
India to construct protection wall along the length of the river on
the south bank to prevent the erosion salinity ingress prevention
work with causeway
(4) It was explained regarding initialization of the project that Kalpasar
Department worked out a plan to construct a tidal regulator
bandhara as a means of separating Narmada river water from tidal
water so as to check salinity ingress and ground water
deterioration Similarly GIDC concerned for meeting the domestic
and industrial water requirement of the various existing industries
and the upcoming PCPIR has been contemplating to construct a
barrage at Bhadbhut for dependence of fresh water supply from
Narmada river It was envisaged to construct a barrage In view of
the above Kalpasar Department decided to take up this project as a
stand alone vide Government order dated 22092009
(5) Project Benefits of the proposed barrage across river Narmada near
village Bhadbhut area
(a) The Bhadbhut Barrage will check the salinity ingress upstream
of Bhadbhut and Narmada river water will get stored at the
barrage The free catchment water at 90 dependability as
worked out by Ms SECON and CDO is 1000 mm3 The river
water reservoir is likely to extend up to 85 km on upstream
side of Barrage Domestic irrigation and industrial water users
may use this stored water of Narmada river This will result in4
increasing ground water recharge due to irrigation and storage
along 85 km stretch of the river and ultimately in the
improvement of the ground water quality and reduction of
salinity ingress
(b) About 400 sq km fertile land on left bank of Narmada river
coming in flood submergence will be permanently protected by
Flood Protection embankment on left bank of river Narmada
from Bhadbhut Barrage to Ankleshwar
This barrage will also be used in future for diverting Narmada
water to freshwater reservoir proposed in Gulf of Khambhat
through Narmada diversion canal
(c) A six-lane road on the Bhadbhut barrage will ease out the
traffic congestion between Surat (Hajira) - Bharuch - Dahej
with new coastal route ie Surat - Olpad - Hansot - Bhadbhut -
Dahej about 18 km shorter than the existing route ie Surat
(Hajira) - Ankleshwar - Bharuch - Dahej Ultimately it will
result in considerable saving of travel timecost
(6) Environment Impact
National Environmental Engineering Research Institute (NEERI)
Nagpur which is a constituent laboratory under Council of Scientific
and Industrial Research (CSIR) New Delhi has been entrusted with
the consultancy assignment for preparation of EIA studies
NEERI has prepared and submitted the report which was submitted
to Forest amp EnvironmelJt Department for EIA clearance The State
Level Appraisal Committee held the meeting on 05012012 It was
suggested to incorporate some additional points in the scope of the
study Accordingly NEERI has revised EIRA study report and the
same is (recently on 27072012) submitted to Forest amp
Environment Department for further consideration Next activity is
5
public hearing which will be held at collectorate level and based on
the discussion of public-hearing the EIA report will be finalized
However some of the points mentioned in the conclusions of the
present report are
a) The proposal for construction of Bhadbhut barrage on river
Narmada has emanated in response to peoples demand as
voiced through representations at various levels by public
figures from several social streams The planning of the
project has been carried out in respect of location and
engineering ~eatures on consideration of technical feasibility
and maximising benefits in terms of checking the problems of
salinity ingress and deterioration of ground water quality
storage of good quality river water for irrigation domestic and
industrial water supply flood protection of low lying area on
left bank of the river and road connectivity between left and
right banks
b) Fishermens concerns with respect to obstruction to their
movement as well as migration of Hilsa and other fisheries
species are to be aptly addressed by making provision of fish
passage and ship-lock type arrangement in the barrage Most
importantly the water stored at the barrage will provide a
congenial habitat for fresh water fishery which can be
intensified by stocking economically important fish species so
as to provide more productive employment to the fishermen
c) To sum up the Bhadbhut barrage project has no significant
environment repercussion and is in effect a long-term social
and environment promoting project
(7) Coastal Regulation Zone Impact
As per the CRZ Notification by MoEF dated 6th January 2011 water
area of tidal influenced water body from the mouth of water body at
6
the sea up to the influence of tide which is measured as 5 ppt (5000
mgI) during the driest season of the year is coverable under CRZ
IV wherein the activities disturbing the natural course of sea water
are prohibited Exceptions are however provided for measures to
prevent sand bars installation of tidal regulators laying of storm
water drains or for structures for protection of salinity ingress and
fresh water recharge based on examination carried out by any
agency specified by MoEF vide Office Memorandum dated 24th
February 2011 It is stipulated that all proposals relating to the
projects indicated as exceptions from the prohibited activities shall
be examined by any of the following institutions from technical
angle
(i) Central Water and Power Research Station Pune
(ii) IIT Chennai IIT Mumbai
(iii) Department of Erosion Directorate Ministry of Water Resources
(iv) ICMAM
(v) National Centre for Sustainable Coastal Management
(vi) NIT Suratkal
In this context the study of Bhadbhut barrage for CRZ clearance
proposal was assigned to Central Water and Power Research
Station Pune The proposal for CRZ clearance along with relevant
documents and CRZ map showing HTL and LTL with project layout
superimposed thereon as prepared by Space Application Center
(ISRO) Ahmedabad (the only authorized agency for preparing such
CRZ maps) was also sent to CWPRS Pune for their study The
report on Desk Studies for Salinity Ingress due to proposed
construction of Barrage across the river Narmada at Bhadbhut
Gujarat prepared by Central Water amp Power Research Station
Pune has been received by the Department The findings of the
report are as under
7
a) The analysis of the salinity as per the reports of NEERI
CSMCRI and data collected in Jan 2012 by the Kalpasar project
authorities indicates that the salinity values are well below 5
ppt near the proposed Bhadbhut barrage location during the
dry season at all stages of tides
b) With the construction of the proposed barrage the salinity
values in the us reaches are expected to become further less
and thus will add to the overall utility of the project
c) Due to the proposed barrage impounding of water will aid in
improving the ground water quality and also aid in lift irrigation
schemes
d) From the proposed project an overall improvement in quality
and quantity of water in the region is likely to take place over a
period of time
e) The road link between Hansot and Dahej would not only reduce
the traffic on other existing highways but also reduce the
travel time and cost on fuel
In view of the conclusions of the report by CWPRS contextual to the
provisions regarding salinity of 5 ppt during the driest season of the
year and also exception to the measures for checking tidal salinity
ingress in CRZ notification 2011 the proposed barrage does not in
any way violate the provision of the said notification However as
per the guidelines for permissible activities contained in the CRZ
Notification 2011 issued by the Ministry of Environment amp Forest
GOl the applicationproposal is already submitted to the Gujarat
State Coastal Regulation Zone Management Authority (SCRZMA) for
obtaining CRZ clearance along with the prescribed documents and
necessary fee
(8) Fisheries Impact
8
81 The Bhadbhut barrage will have some challenges concerning
preservation protection and management of fisheries which
were studied so as to formulate strategies for maximizing the
positive aspects and minimizingmitigating the negative
aspects The study has been carried out based on relevant
secondary data consultation with professionals and interviews
with fishermen soliciting their views on various aspects of
fisheries The total number of fishermens families in 21 villages
is 2520 with a population of 12638 The fishermen are partly
employed and inadequately equipped with fishing
infrastmctures The fishing activities are mostly localized along
the frontal stretch of the estuary The boat-bound fishery is
limited to a small number of fishermen having access to
mechanizednon-mechanized boats Fishing activities are
mostly conventional type
Fish production in Bharuch district comprises inland and marine
fish Of the total marine fish production accounts for 18
which is confined to the villages of Gulf shore The inland fish
production includes estuarine fish catch in which Hilsa fish
holds a significant share and estuarine fish production has
shown a declining trend in the last ten years (25 of 1990-
91)
82 Hilsa basically a marine fish species is anadromous in nature
and ascends the rivers for spawning during monsoon Hilsa
supports a substantial fishery in the Narmada estuary and
several fishermen families are dependent on this fishery during
the monsoon for duration of 50-60 days Velocities of flow and
volumes of discharge at the mouth of the estuary are the
driving factors of migration The depletion of Hilsa fishery in the
Narmada estuary is attributable to reduction in flood flows
incidental to the construction of many irrigation projects in the
9
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
meeting suggested to provide the details of the project along with its
objectives benefits and related activities for environmental impact
coastal regulation impact fisheries issues flood protection etc carried
out so far Accordingly second meeting was held on 21082012 at
1900 hrs During the discussions held in these two meetings the
following details were discussed with the Director GNLU and the
Kalpasar officials
(1) At the outset of the discussion it was explained that the state has
about 1600 km long sea coastal belt and all along coastline in the
estuarine portion of the rivers meeting sea tidal water entry
creates serious problem of salinity ingress Not only soil in this belt
looses its fertility the surface water and ground water quality is
deteriorated Considering seriousness of the problem in past
government had constituted High Level Committee headed by the
then Chief Secretary during 1975 The Committee suggested tidal
regulators bandharas spreading channels check-dams and other
minor works for prevention of salinity ingress On this suggestion
Government of Gujarat carried out some works from its budget
Also Central Government with due consideration to the problem
sanctioned Rs 200 crore grant during 12th Finance Commission for
salinity ingress prevention works including barrages These
structuresworks have shown good results in prevention of salinity
ingress Government has also carried out a study for evaluation of
positive impacts of these salinity ingress prevention works along
coastal line of Gujarat through Gandhi Labour Institute
Ahmedabad At some places over barrages bridges are also
constructed for road connectivity on both sides of the storages
(2) Narmada river is the largest west flowing river having total length of
1312 km and tail stretch of 161 km lying in Gujarat Before
construction of Sardar Sarovar Project in Gujarat and three major
projects Omkareshwar Maheshwar and Indira Sagar in Madhya
2
r
Pradesh there was continuous river water flow in the estuarine
portion of the river Now the river water is gradually reduced
whereas tidal water flow remained unchanged Hence water
requirement for domestic irrigation and industrial needs of
Bharuch- Dahej region cannot be met with at present At present
GIDC and other industries are pumping 58 MGD water from
Narmada river at Angareshwar (70 km in the upstream of the
proposed Bhadbhut Barrage Project) as the water in the river up to
Angreshwar is not usable even for industrial purpose and there is no
permanent water source available for water requirement of GIDC
and PCPIRexcept Narmada river GIDC has planned for Petroleum
Chemical and Petro-Chemical investment Region (PCPIR) in Dahej
Industrial Area GIDC has planned water requirement at 300 MGD
Per year from 2020 onwards from the proposed barrage for PCPIR
and GIDC estates as discussed with Chief Secretary on 30092011
Bhadbhut Barrage being ideally located is the most preferable water
resource for Dahej-PCPIR industrial arearegion
(3) Water Resources Department as well as GIDC separately envisaged
the barrage of Narmada River since one decade However it was
not materialized Finally Kalpasar Department Government of
Gujarat decided to take up the barrage project as a stand alone
project During the discussion on the need of the project it was
further explained that number of representations had been received
from local people and political leaders at Honble Chief minister
level Honble Minister level and other higher level for construction
of barrage on Narmada river to solve the problem of salinity ingress
and deteriorated quality of surface and ground water The notables
include representations of Hon MLAs of Jhagadia (2001) Jambusar
(2003) Surat and Hansot (2004) and Bharuch (2005) Hon MP of
Bharuch (2005) Shri Ahmed Patel Hon MP (Rajya Sabha) (2008)
Hon Central Minister of Water Resources GO (2010) GIDC (2008
onwards) etc3
It was also explained that Shri Pavankumar Bansal Hon Minister of
Water Resources Government of India vide his letter dated 4th
March 2010 addressed to Hon Chief Minister Gujarat had offered
all technical help for barrage across river Narmada and suggested to
take up a flood protection works in the flood affected area of
Bharuch District with an offer of financial assistance Hon MP Shri
Ahmed Patel vide his letter dated 28th October 2008 had
represented to Hon Minister of Water Resources Government of
India to construct protection wall along the length of the river on
the south bank to prevent the erosion salinity ingress prevention
work with causeway
(4) It was explained regarding initialization of the project that Kalpasar
Department worked out a plan to construct a tidal regulator
bandhara as a means of separating Narmada river water from tidal
water so as to check salinity ingress and ground water
deterioration Similarly GIDC concerned for meeting the domestic
and industrial water requirement of the various existing industries
and the upcoming PCPIR has been contemplating to construct a
barrage at Bhadbhut for dependence of fresh water supply from
Narmada river It was envisaged to construct a barrage In view of
the above Kalpasar Department decided to take up this project as a
stand alone vide Government order dated 22092009
(5) Project Benefits of the proposed barrage across river Narmada near
village Bhadbhut area
(a) The Bhadbhut Barrage will check the salinity ingress upstream
of Bhadbhut and Narmada river water will get stored at the
barrage The free catchment water at 90 dependability as
worked out by Ms SECON and CDO is 1000 mm3 The river
water reservoir is likely to extend up to 85 km on upstream
side of Barrage Domestic irrigation and industrial water users
may use this stored water of Narmada river This will result in4
increasing ground water recharge due to irrigation and storage
along 85 km stretch of the river and ultimately in the
improvement of the ground water quality and reduction of
salinity ingress
(b) About 400 sq km fertile land on left bank of Narmada river
coming in flood submergence will be permanently protected by
Flood Protection embankment on left bank of river Narmada
from Bhadbhut Barrage to Ankleshwar
This barrage will also be used in future for diverting Narmada
water to freshwater reservoir proposed in Gulf of Khambhat
through Narmada diversion canal
(c) A six-lane road on the Bhadbhut barrage will ease out the
traffic congestion between Surat (Hajira) - Bharuch - Dahej
with new coastal route ie Surat - Olpad - Hansot - Bhadbhut -
Dahej about 18 km shorter than the existing route ie Surat
(Hajira) - Ankleshwar - Bharuch - Dahej Ultimately it will
result in considerable saving of travel timecost
(6) Environment Impact
National Environmental Engineering Research Institute (NEERI)
Nagpur which is a constituent laboratory under Council of Scientific
and Industrial Research (CSIR) New Delhi has been entrusted with
the consultancy assignment for preparation of EIA studies
NEERI has prepared and submitted the report which was submitted
to Forest amp EnvironmelJt Department for EIA clearance The State
Level Appraisal Committee held the meeting on 05012012 It was
suggested to incorporate some additional points in the scope of the
study Accordingly NEERI has revised EIRA study report and the
same is (recently on 27072012) submitted to Forest amp
Environment Department for further consideration Next activity is
5
public hearing which will be held at collectorate level and based on
the discussion of public-hearing the EIA report will be finalized
However some of the points mentioned in the conclusions of the
present report are
a) The proposal for construction of Bhadbhut barrage on river
Narmada has emanated in response to peoples demand as
voiced through representations at various levels by public
figures from several social streams The planning of the
project has been carried out in respect of location and
engineering ~eatures on consideration of technical feasibility
and maximising benefits in terms of checking the problems of
salinity ingress and deterioration of ground water quality
storage of good quality river water for irrigation domestic and
industrial water supply flood protection of low lying area on
left bank of the river and road connectivity between left and
right banks
b) Fishermens concerns with respect to obstruction to their
movement as well as migration of Hilsa and other fisheries
species are to be aptly addressed by making provision of fish
passage and ship-lock type arrangement in the barrage Most
importantly the water stored at the barrage will provide a
congenial habitat for fresh water fishery which can be
intensified by stocking economically important fish species so
as to provide more productive employment to the fishermen
c) To sum up the Bhadbhut barrage project has no significant
environment repercussion and is in effect a long-term social
and environment promoting project
(7) Coastal Regulation Zone Impact
As per the CRZ Notification by MoEF dated 6th January 2011 water
area of tidal influenced water body from the mouth of water body at
6
the sea up to the influence of tide which is measured as 5 ppt (5000
mgI) during the driest season of the year is coverable under CRZ
IV wherein the activities disturbing the natural course of sea water
are prohibited Exceptions are however provided for measures to
prevent sand bars installation of tidal regulators laying of storm
water drains or for structures for protection of salinity ingress and
fresh water recharge based on examination carried out by any
agency specified by MoEF vide Office Memorandum dated 24th
February 2011 It is stipulated that all proposals relating to the
projects indicated as exceptions from the prohibited activities shall
be examined by any of the following institutions from technical
angle
(i) Central Water and Power Research Station Pune
(ii) IIT Chennai IIT Mumbai
(iii) Department of Erosion Directorate Ministry of Water Resources
(iv) ICMAM
(v) National Centre for Sustainable Coastal Management
(vi) NIT Suratkal
In this context the study of Bhadbhut barrage for CRZ clearance
proposal was assigned to Central Water and Power Research
Station Pune The proposal for CRZ clearance along with relevant
documents and CRZ map showing HTL and LTL with project layout
superimposed thereon as prepared by Space Application Center
(ISRO) Ahmedabad (the only authorized agency for preparing such
CRZ maps) was also sent to CWPRS Pune for their study The
report on Desk Studies for Salinity Ingress due to proposed
construction of Barrage across the river Narmada at Bhadbhut
Gujarat prepared by Central Water amp Power Research Station
Pune has been received by the Department The findings of the
report are as under
7
a) The analysis of the salinity as per the reports of NEERI
CSMCRI and data collected in Jan 2012 by the Kalpasar project
authorities indicates that the salinity values are well below 5
ppt near the proposed Bhadbhut barrage location during the
dry season at all stages of tides
b) With the construction of the proposed barrage the salinity
values in the us reaches are expected to become further less
and thus will add to the overall utility of the project
c) Due to the proposed barrage impounding of water will aid in
improving the ground water quality and also aid in lift irrigation
schemes
d) From the proposed project an overall improvement in quality
and quantity of water in the region is likely to take place over a
period of time
e) The road link between Hansot and Dahej would not only reduce
the traffic on other existing highways but also reduce the
travel time and cost on fuel
In view of the conclusions of the report by CWPRS contextual to the
provisions regarding salinity of 5 ppt during the driest season of the
year and also exception to the measures for checking tidal salinity
ingress in CRZ notification 2011 the proposed barrage does not in
any way violate the provision of the said notification However as
per the guidelines for permissible activities contained in the CRZ
Notification 2011 issued by the Ministry of Environment amp Forest
GOl the applicationproposal is already submitted to the Gujarat
State Coastal Regulation Zone Management Authority (SCRZMA) for
obtaining CRZ clearance along with the prescribed documents and
necessary fee
(8) Fisheries Impact
8
81 The Bhadbhut barrage will have some challenges concerning
preservation protection and management of fisheries which
were studied so as to formulate strategies for maximizing the
positive aspects and minimizingmitigating the negative
aspects The study has been carried out based on relevant
secondary data consultation with professionals and interviews
with fishermen soliciting their views on various aspects of
fisheries The total number of fishermens families in 21 villages
is 2520 with a population of 12638 The fishermen are partly
employed and inadequately equipped with fishing
infrastmctures The fishing activities are mostly localized along
the frontal stretch of the estuary The boat-bound fishery is
limited to a small number of fishermen having access to
mechanizednon-mechanized boats Fishing activities are
mostly conventional type
Fish production in Bharuch district comprises inland and marine
fish Of the total marine fish production accounts for 18
which is confined to the villages of Gulf shore The inland fish
production includes estuarine fish catch in which Hilsa fish
holds a significant share and estuarine fish production has
shown a declining trend in the last ten years (25 of 1990-
91)
82 Hilsa basically a marine fish species is anadromous in nature
and ascends the rivers for spawning during monsoon Hilsa
supports a substantial fishery in the Narmada estuary and
several fishermen families are dependent on this fishery during
the monsoon for duration of 50-60 days Velocities of flow and
volumes of discharge at the mouth of the estuary are the
driving factors of migration The depletion of Hilsa fishery in the
Narmada estuary is attributable to reduction in flood flows
incidental to the construction of many irrigation projects in the
9
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
r
Pradesh there was continuous river water flow in the estuarine
portion of the river Now the river water is gradually reduced
whereas tidal water flow remained unchanged Hence water
requirement for domestic irrigation and industrial needs of
Bharuch- Dahej region cannot be met with at present At present
GIDC and other industries are pumping 58 MGD water from
Narmada river at Angareshwar (70 km in the upstream of the
proposed Bhadbhut Barrage Project) as the water in the river up to
Angreshwar is not usable even for industrial purpose and there is no
permanent water source available for water requirement of GIDC
and PCPIRexcept Narmada river GIDC has planned for Petroleum
Chemical and Petro-Chemical investment Region (PCPIR) in Dahej
Industrial Area GIDC has planned water requirement at 300 MGD
Per year from 2020 onwards from the proposed barrage for PCPIR
and GIDC estates as discussed with Chief Secretary on 30092011
Bhadbhut Barrage being ideally located is the most preferable water
resource for Dahej-PCPIR industrial arearegion
(3) Water Resources Department as well as GIDC separately envisaged
the barrage of Narmada River since one decade However it was
not materialized Finally Kalpasar Department Government of
Gujarat decided to take up the barrage project as a stand alone
project During the discussion on the need of the project it was
further explained that number of representations had been received
from local people and political leaders at Honble Chief minister
level Honble Minister level and other higher level for construction
of barrage on Narmada river to solve the problem of salinity ingress
and deteriorated quality of surface and ground water The notables
include representations of Hon MLAs of Jhagadia (2001) Jambusar
(2003) Surat and Hansot (2004) and Bharuch (2005) Hon MP of
Bharuch (2005) Shri Ahmed Patel Hon MP (Rajya Sabha) (2008)
Hon Central Minister of Water Resources GO (2010) GIDC (2008
onwards) etc3
It was also explained that Shri Pavankumar Bansal Hon Minister of
Water Resources Government of India vide his letter dated 4th
March 2010 addressed to Hon Chief Minister Gujarat had offered
all technical help for barrage across river Narmada and suggested to
take up a flood protection works in the flood affected area of
Bharuch District with an offer of financial assistance Hon MP Shri
Ahmed Patel vide his letter dated 28th October 2008 had
represented to Hon Minister of Water Resources Government of
India to construct protection wall along the length of the river on
the south bank to prevent the erosion salinity ingress prevention
work with causeway
(4) It was explained regarding initialization of the project that Kalpasar
Department worked out a plan to construct a tidal regulator
bandhara as a means of separating Narmada river water from tidal
water so as to check salinity ingress and ground water
deterioration Similarly GIDC concerned for meeting the domestic
and industrial water requirement of the various existing industries
and the upcoming PCPIR has been contemplating to construct a
barrage at Bhadbhut for dependence of fresh water supply from
Narmada river It was envisaged to construct a barrage In view of
the above Kalpasar Department decided to take up this project as a
stand alone vide Government order dated 22092009
(5) Project Benefits of the proposed barrage across river Narmada near
village Bhadbhut area
(a) The Bhadbhut Barrage will check the salinity ingress upstream
of Bhadbhut and Narmada river water will get stored at the
barrage The free catchment water at 90 dependability as
worked out by Ms SECON and CDO is 1000 mm3 The river
water reservoir is likely to extend up to 85 km on upstream
side of Barrage Domestic irrigation and industrial water users
may use this stored water of Narmada river This will result in4
increasing ground water recharge due to irrigation and storage
along 85 km stretch of the river and ultimately in the
improvement of the ground water quality and reduction of
salinity ingress
(b) About 400 sq km fertile land on left bank of Narmada river
coming in flood submergence will be permanently protected by
Flood Protection embankment on left bank of river Narmada
from Bhadbhut Barrage to Ankleshwar
This barrage will also be used in future for diverting Narmada
water to freshwater reservoir proposed in Gulf of Khambhat
through Narmada diversion canal
(c) A six-lane road on the Bhadbhut barrage will ease out the
traffic congestion between Surat (Hajira) - Bharuch - Dahej
with new coastal route ie Surat - Olpad - Hansot - Bhadbhut -
Dahej about 18 km shorter than the existing route ie Surat
(Hajira) - Ankleshwar - Bharuch - Dahej Ultimately it will
result in considerable saving of travel timecost
(6) Environment Impact
National Environmental Engineering Research Institute (NEERI)
Nagpur which is a constituent laboratory under Council of Scientific
and Industrial Research (CSIR) New Delhi has been entrusted with
the consultancy assignment for preparation of EIA studies
NEERI has prepared and submitted the report which was submitted
to Forest amp EnvironmelJt Department for EIA clearance The State
Level Appraisal Committee held the meeting on 05012012 It was
suggested to incorporate some additional points in the scope of the
study Accordingly NEERI has revised EIRA study report and the
same is (recently on 27072012) submitted to Forest amp
Environment Department for further consideration Next activity is
5
public hearing which will be held at collectorate level and based on
the discussion of public-hearing the EIA report will be finalized
However some of the points mentioned in the conclusions of the
present report are
a) The proposal for construction of Bhadbhut barrage on river
Narmada has emanated in response to peoples demand as
voiced through representations at various levels by public
figures from several social streams The planning of the
project has been carried out in respect of location and
engineering ~eatures on consideration of technical feasibility
and maximising benefits in terms of checking the problems of
salinity ingress and deterioration of ground water quality
storage of good quality river water for irrigation domestic and
industrial water supply flood protection of low lying area on
left bank of the river and road connectivity between left and
right banks
b) Fishermens concerns with respect to obstruction to their
movement as well as migration of Hilsa and other fisheries
species are to be aptly addressed by making provision of fish
passage and ship-lock type arrangement in the barrage Most
importantly the water stored at the barrage will provide a
congenial habitat for fresh water fishery which can be
intensified by stocking economically important fish species so
as to provide more productive employment to the fishermen
c) To sum up the Bhadbhut barrage project has no significant
environment repercussion and is in effect a long-term social
and environment promoting project
(7) Coastal Regulation Zone Impact
As per the CRZ Notification by MoEF dated 6th January 2011 water
area of tidal influenced water body from the mouth of water body at
6
the sea up to the influence of tide which is measured as 5 ppt (5000
mgI) during the driest season of the year is coverable under CRZ
IV wherein the activities disturbing the natural course of sea water
are prohibited Exceptions are however provided for measures to
prevent sand bars installation of tidal regulators laying of storm
water drains or for structures for protection of salinity ingress and
fresh water recharge based on examination carried out by any
agency specified by MoEF vide Office Memorandum dated 24th
February 2011 It is stipulated that all proposals relating to the
projects indicated as exceptions from the prohibited activities shall
be examined by any of the following institutions from technical
angle
(i) Central Water and Power Research Station Pune
(ii) IIT Chennai IIT Mumbai
(iii) Department of Erosion Directorate Ministry of Water Resources
(iv) ICMAM
(v) National Centre for Sustainable Coastal Management
(vi) NIT Suratkal
In this context the study of Bhadbhut barrage for CRZ clearance
proposal was assigned to Central Water and Power Research
Station Pune The proposal for CRZ clearance along with relevant
documents and CRZ map showing HTL and LTL with project layout
superimposed thereon as prepared by Space Application Center
(ISRO) Ahmedabad (the only authorized agency for preparing such
CRZ maps) was also sent to CWPRS Pune for their study The
report on Desk Studies for Salinity Ingress due to proposed
construction of Barrage across the river Narmada at Bhadbhut
Gujarat prepared by Central Water amp Power Research Station
Pune has been received by the Department The findings of the
report are as under
7
a) The analysis of the salinity as per the reports of NEERI
CSMCRI and data collected in Jan 2012 by the Kalpasar project
authorities indicates that the salinity values are well below 5
ppt near the proposed Bhadbhut barrage location during the
dry season at all stages of tides
b) With the construction of the proposed barrage the salinity
values in the us reaches are expected to become further less
and thus will add to the overall utility of the project
c) Due to the proposed barrage impounding of water will aid in
improving the ground water quality and also aid in lift irrigation
schemes
d) From the proposed project an overall improvement in quality
and quantity of water in the region is likely to take place over a
period of time
e) The road link between Hansot and Dahej would not only reduce
the traffic on other existing highways but also reduce the
travel time and cost on fuel
In view of the conclusions of the report by CWPRS contextual to the
provisions regarding salinity of 5 ppt during the driest season of the
year and also exception to the measures for checking tidal salinity
ingress in CRZ notification 2011 the proposed barrage does not in
any way violate the provision of the said notification However as
per the guidelines for permissible activities contained in the CRZ
Notification 2011 issued by the Ministry of Environment amp Forest
GOl the applicationproposal is already submitted to the Gujarat
State Coastal Regulation Zone Management Authority (SCRZMA) for
obtaining CRZ clearance along with the prescribed documents and
necessary fee
(8) Fisheries Impact
8
81 The Bhadbhut barrage will have some challenges concerning
preservation protection and management of fisheries which
were studied so as to formulate strategies for maximizing the
positive aspects and minimizingmitigating the negative
aspects The study has been carried out based on relevant
secondary data consultation with professionals and interviews
with fishermen soliciting their views on various aspects of
fisheries The total number of fishermens families in 21 villages
is 2520 with a population of 12638 The fishermen are partly
employed and inadequately equipped with fishing
infrastmctures The fishing activities are mostly localized along
the frontal stretch of the estuary The boat-bound fishery is
limited to a small number of fishermen having access to
mechanizednon-mechanized boats Fishing activities are
mostly conventional type
Fish production in Bharuch district comprises inland and marine
fish Of the total marine fish production accounts for 18
which is confined to the villages of Gulf shore The inland fish
production includes estuarine fish catch in which Hilsa fish
holds a significant share and estuarine fish production has
shown a declining trend in the last ten years (25 of 1990-
91)
82 Hilsa basically a marine fish species is anadromous in nature
and ascends the rivers for spawning during monsoon Hilsa
supports a substantial fishery in the Narmada estuary and
several fishermen families are dependent on this fishery during
the monsoon for duration of 50-60 days Velocities of flow and
volumes of discharge at the mouth of the estuary are the
driving factors of migration The depletion of Hilsa fishery in the
Narmada estuary is attributable to reduction in flood flows
incidental to the construction of many irrigation projects in the
9
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
It was also explained that Shri Pavankumar Bansal Hon Minister of
Water Resources Government of India vide his letter dated 4th
March 2010 addressed to Hon Chief Minister Gujarat had offered
all technical help for barrage across river Narmada and suggested to
take up a flood protection works in the flood affected area of
Bharuch District with an offer of financial assistance Hon MP Shri
Ahmed Patel vide his letter dated 28th October 2008 had
represented to Hon Minister of Water Resources Government of
India to construct protection wall along the length of the river on
the south bank to prevent the erosion salinity ingress prevention
work with causeway
(4) It was explained regarding initialization of the project that Kalpasar
Department worked out a plan to construct a tidal regulator
bandhara as a means of separating Narmada river water from tidal
water so as to check salinity ingress and ground water
deterioration Similarly GIDC concerned for meeting the domestic
and industrial water requirement of the various existing industries
and the upcoming PCPIR has been contemplating to construct a
barrage at Bhadbhut for dependence of fresh water supply from
Narmada river It was envisaged to construct a barrage In view of
the above Kalpasar Department decided to take up this project as a
stand alone vide Government order dated 22092009
(5) Project Benefits of the proposed barrage across river Narmada near
village Bhadbhut area
(a) The Bhadbhut Barrage will check the salinity ingress upstream
of Bhadbhut and Narmada river water will get stored at the
barrage The free catchment water at 90 dependability as
worked out by Ms SECON and CDO is 1000 mm3 The river
water reservoir is likely to extend up to 85 km on upstream
side of Barrage Domestic irrigation and industrial water users
may use this stored water of Narmada river This will result in4
increasing ground water recharge due to irrigation and storage
along 85 km stretch of the river and ultimately in the
improvement of the ground water quality and reduction of
salinity ingress
(b) About 400 sq km fertile land on left bank of Narmada river
coming in flood submergence will be permanently protected by
Flood Protection embankment on left bank of river Narmada
from Bhadbhut Barrage to Ankleshwar
This barrage will also be used in future for diverting Narmada
water to freshwater reservoir proposed in Gulf of Khambhat
through Narmada diversion canal
(c) A six-lane road on the Bhadbhut barrage will ease out the
traffic congestion between Surat (Hajira) - Bharuch - Dahej
with new coastal route ie Surat - Olpad - Hansot - Bhadbhut -
Dahej about 18 km shorter than the existing route ie Surat
(Hajira) - Ankleshwar - Bharuch - Dahej Ultimately it will
result in considerable saving of travel timecost
(6) Environment Impact
National Environmental Engineering Research Institute (NEERI)
Nagpur which is a constituent laboratory under Council of Scientific
and Industrial Research (CSIR) New Delhi has been entrusted with
the consultancy assignment for preparation of EIA studies
NEERI has prepared and submitted the report which was submitted
to Forest amp EnvironmelJt Department for EIA clearance The State
Level Appraisal Committee held the meeting on 05012012 It was
suggested to incorporate some additional points in the scope of the
study Accordingly NEERI has revised EIRA study report and the
same is (recently on 27072012) submitted to Forest amp
Environment Department for further consideration Next activity is
5
public hearing which will be held at collectorate level and based on
the discussion of public-hearing the EIA report will be finalized
However some of the points mentioned in the conclusions of the
present report are
a) The proposal for construction of Bhadbhut barrage on river
Narmada has emanated in response to peoples demand as
voiced through representations at various levels by public
figures from several social streams The planning of the
project has been carried out in respect of location and
engineering ~eatures on consideration of technical feasibility
and maximising benefits in terms of checking the problems of
salinity ingress and deterioration of ground water quality
storage of good quality river water for irrigation domestic and
industrial water supply flood protection of low lying area on
left bank of the river and road connectivity between left and
right banks
b) Fishermens concerns with respect to obstruction to their
movement as well as migration of Hilsa and other fisheries
species are to be aptly addressed by making provision of fish
passage and ship-lock type arrangement in the barrage Most
importantly the water stored at the barrage will provide a
congenial habitat for fresh water fishery which can be
intensified by stocking economically important fish species so
as to provide more productive employment to the fishermen
c) To sum up the Bhadbhut barrage project has no significant
environment repercussion and is in effect a long-term social
and environment promoting project
(7) Coastal Regulation Zone Impact
As per the CRZ Notification by MoEF dated 6th January 2011 water
area of tidal influenced water body from the mouth of water body at
6
the sea up to the influence of tide which is measured as 5 ppt (5000
mgI) during the driest season of the year is coverable under CRZ
IV wherein the activities disturbing the natural course of sea water
are prohibited Exceptions are however provided for measures to
prevent sand bars installation of tidal regulators laying of storm
water drains or for structures for protection of salinity ingress and
fresh water recharge based on examination carried out by any
agency specified by MoEF vide Office Memorandum dated 24th
February 2011 It is stipulated that all proposals relating to the
projects indicated as exceptions from the prohibited activities shall
be examined by any of the following institutions from technical
angle
(i) Central Water and Power Research Station Pune
(ii) IIT Chennai IIT Mumbai
(iii) Department of Erosion Directorate Ministry of Water Resources
(iv) ICMAM
(v) National Centre for Sustainable Coastal Management
(vi) NIT Suratkal
In this context the study of Bhadbhut barrage for CRZ clearance
proposal was assigned to Central Water and Power Research
Station Pune The proposal for CRZ clearance along with relevant
documents and CRZ map showing HTL and LTL with project layout
superimposed thereon as prepared by Space Application Center
(ISRO) Ahmedabad (the only authorized agency for preparing such
CRZ maps) was also sent to CWPRS Pune for their study The
report on Desk Studies for Salinity Ingress due to proposed
construction of Barrage across the river Narmada at Bhadbhut
Gujarat prepared by Central Water amp Power Research Station
Pune has been received by the Department The findings of the
report are as under
7
a) The analysis of the salinity as per the reports of NEERI
CSMCRI and data collected in Jan 2012 by the Kalpasar project
authorities indicates that the salinity values are well below 5
ppt near the proposed Bhadbhut barrage location during the
dry season at all stages of tides
b) With the construction of the proposed barrage the salinity
values in the us reaches are expected to become further less
and thus will add to the overall utility of the project
c) Due to the proposed barrage impounding of water will aid in
improving the ground water quality and also aid in lift irrigation
schemes
d) From the proposed project an overall improvement in quality
and quantity of water in the region is likely to take place over a
period of time
e) The road link between Hansot and Dahej would not only reduce
the traffic on other existing highways but also reduce the
travel time and cost on fuel
In view of the conclusions of the report by CWPRS contextual to the
provisions regarding salinity of 5 ppt during the driest season of the
year and also exception to the measures for checking tidal salinity
ingress in CRZ notification 2011 the proposed barrage does not in
any way violate the provision of the said notification However as
per the guidelines for permissible activities contained in the CRZ
Notification 2011 issued by the Ministry of Environment amp Forest
GOl the applicationproposal is already submitted to the Gujarat
State Coastal Regulation Zone Management Authority (SCRZMA) for
obtaining CRZ clearance along with the prescribed documents and
necessary fee
(8) Fisheries Impact
8
81 The Bhadbhut barrage will have some challenges concerning
preservation protection and management of fisheries which
were studied so as to formulate strategies for maximizing the
positive aspects and minimizingmitigating the negative
aspects The study has been carried out based on relevant
secondary data consultation with professionals and interviews
with fishermen soliciting their views on various aspects of
fisheries The total number of fishermens families in 21 villages
is 2520 with a population of 12638 The fishermen are partly
employed and inadequately equipped with fishing
infrastmctures The fishing activities are mostly localized along
the frontal stretch of the estuary The boat-bound fishery is
limited to a small number of fishermen having access to
mechanizednon-mechanized boats Fishing activities are
mostly conventional type
Fish production in Bharuch district comprises inland and marine
fish Of the total marine fish production accounts for 18
which is confined to the villages of Gulf shore The inland fish
production includes estuarine fish catch in which Hilsa fish
holds a significant share and estuarine fish production has
shown a declining trend in the last ten years (25 of 1990-
91)
82 Hilsa basically a marine fish species is anadromous in nature
and ascends the rivers for spawning during monsoon Hilsa
supports a substantial fishery in the Narmada estuary and
several fishermen families are dependent on this fishery during
the monsoon for duration of 50-60 days Velocities of flow and
volumes of discharge at the mouth of the estuary are the
driving factors of migration The depletion of Hilsa fishery in the
Narmada estuary is attributable to reduction in flood flows
incidental to the construction of many irrigation projects in the
9
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
increasing ground water recharge due to irrigation and storage
along 85 km stretch of the river and ultimately in the
improvement of the ground water quality and reduction of
salinity ingress
(b) About 400 sq km fertile land on left bank of Narmada river
coming in flood submergence will be permanently protected by
Flood Protection embankment on left bank of river Narmada
from Bhadbhut Barrage to Ankleshwar
This barrage will also be used in future for diverting Narmada
water to freshwater reservoir proposed in Gulf of Khambhat
through Narmada diversion canal
(c) A six-lane road on the Bhadbhut barrage will ease out the
traffic congestion between Surat (Hajira) - Bharuch - Dahej
with new coastal route ie Surat - Olpad - Hansot - Bhadbhut -
Dahej about 18 km shorter than the existing route ie Surat
(Hajira) - Ankleshwar - Bharuch - Dahej Ultimately it will
result in considerable saving of travel timecost
(6) Environment Impact
National Environmental Engineering Research Institute (NEERI)
Nagpur which is a constituent laboratory under Council of Scientific
and Industrial Research (CSIR) New Delhi has been entrusted with
the consultancy assignment for preparation of EIA studies
NEERI has prepared and submitted the report which was submitted
to Forest amp EnvironmelJt Department for EIA clearance The State
Level Appraisal Committee held the meeting on 05012012 It was
suggested to incorporate some additional points in the scope of the
study Accordingly NEERI has revised EIRA study report and the
same is (recently on 27072012) submitted to Forest amp
Environment Department for further consideration Next activity is
5
public hearing which will be held at collectorate level and based on
the discussion of public-hearing the EIA report will be finalized
However some of the points mentioned in the conclusions of the
present report are
a) The proposal for construction of Bhadbhut barrage on river
Narmada has emanated in response to peoples demand as
voiced through representations at various levels by public
figures from several social streams The planning of the
project has been carried out in respect of location and
engineering ~eatures on consideration of technical feasibility
and maximising benefits in terms of checking the problems of
salinity ingress and deterioration of ground water quality
storage of good quality river water for irrigation domestic and
industrial water supply flood protection of low lying area on
left bank of the river and road connectivity between left and
right banks
b) Fishermens concerns with respect to obstruction to their
movement as well as migration of Hilsa and other fisheries
species are to be aptly addressed by making provision of fish
passage and ship-lock type arrangement in the barrage Most
importantly the water stored at the barrage will provide a
congenial habitat for fresh water fishery which can be
intensified by stocking economically important fish species so
as to provide more productive employment to the fishermen
c) To sum up the Bhadbhut barrage project has no significant
environment repercussion and is in effect a long-term social
and environment promoting project
(7) Coastal Regulation Zone Impact
As per the CRZ Notification by MoEF dated 6th January 2011 water
area of tidal influenced water body from the mouth of water body at
6
the sea up to the influence of tide which is measured as 5 ppt (5000
mgI) during the driest season of the year is coverable under CRZ
IV wherein the activities disturbing the natural course of sea water
are prohibited Exceptions are however provided for measures to
prevent sand bars installation of tidal regulators laying of storm
water drains or for structures for protection of salinity ingress and
fresh water recharge based on examination carried out by any
agency specified by MoEF vide Office Memorandum dated 24th
February 2011 It is stipulated that all proposals relating to the
projects indicated as exceptions from the prohibited activities shall
be examined by any of the following institutions from technical
angle
(i) Central Water and Power Research Station Pune
(ii) IIT Chennai IIT Mumbai
(iii) Department of Erosion Directorate Ministry of Water Resources
(iv) ICMAM
(v) National Centre for Sustainable Coastal Management
(vi) NIT Suratkal
In this context the study of Bhadbhut barrage for CRZ clearance
proposal was assigned to Central Water and Power Research
Station Pune The proposal for CRZ clearance along with relevant
documents and CRZ map showing HTL and LTL with project layout
superimposed thereon as prepared by Space Application Center
(ISRO) Ahmedabad (the only authorized agency for preparing such
CRZ maps) was also sent to CWPRS Pune for their study The
report on Desk Studies for Salinity Ingress due to proposed
construction of Barrage across the river Narmada at Bhadbhut
Gujarat prepared by Central Water amp Power Research Station
Pune has been received by the Department The findings of the
report are as under
7
a) The analysis of the salinity as per the reports of NEERI
CSMCRI and data collected in Jan 2012 by the Kalpasar project
authorities indicates that the salinity values are well below 5
ppt near the proposed Bhadbhut barrage location during the
dry season at all stages of tides
b) With the construction of the proposed barrage the salinity
values in the us reaches are expected to become further less
and thus will add to the overall utility of the project
c) Due to the proposed barrage impounding of water will aid in
improving the ground water quality and also aid in lift irrigation
schemes
d) From the proposed project an overall improvement in quality
and quantity of water in the region is likely to take place over a
period of time
e) The road link between Hansot and Dahej would not only reduce
the traffic on other existing highways but also reduce the
travel time and cost on fuel
In view of the conclusions of the report by CWPRS contextual to the
provisions regarding salinity of 5 ppt during the driest season of the
year and also exception to the measures for checking tidal salinity
ingress in CRZ notification 2011 the proposed barrage does not in
any way violate the provision of the said notification However as
per the guidelines for permissible activities contained in the CRZ
Notification 2011 issued by the Ministry of Environment amp Forest
GOl the applicationproposal is already submitted to the Gujarat
State Coastal Regulation Zone Management Authority (SCRZMA) for
obtaining CRZ clearance along with the prescribed documents and
necessary fee
(8) Fisheries Impact
8
81 The Bhadbhut barrage will have some challenges concerning
preservation protection and management of fisheries which
were studied so as to formulate strategies for maximizing the
positive aspects and minimizingmitigating the negative
aspects The study has been carried out based on relevant
secondary data consultation with professionals and interviews
with fishermen soliciting their views on various aspects of
fisheries The total number of fishermens families in 21 villages
is 2520 with a population of 12638 The fishermen are partly
employed and inadequately equipped with fishing
infrastmctures The fishing activities are mostly localized along
the frontal stretch of the estuary The boat-bound fishery is
limited to a small number of fishermen having access to
mechanizednon-mechanized boats Fishing activities are
mostly conventional type
Fish production in Bharuch district comprises inland and marine
fish Of the total marine fish production accounts for 18
which is confined to the villages of Gulf shore The inland fish
production includes estuarine fish catch in which Hilsa fish
holds a significant share and estuarine fish production has
shown a declining trend in the last ten years (25 of 1990-
91)
82 Hilsa basically a marine fish species is anadromous in nature
and ascends the rivers for spawning during monsoon Hilsa
supports a substantial fishery in the Narmada estuary and
several fishermen families are dependent on this fishery during
the monsoon for duration of 50-60 days Velocities of flow and
volumes of discharge at the mouth of the estuary are the
driving factors of migration The depletion of Hilsa fishery in the
Narmada estuary is attributable to reduction in flood flows
incidental to the construction of many irrigation projects in the
9
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
public hearing which will be held at collectorate level and based on
the discussion of public-hearing the EIA report will be finalized
However some of the points mentioned in the conclusions of the
present report are
a) The proposal for construction of Bhadbhut barrage on river
Narmada has emanated in response to peoples demand as
voiced through representations at various levels by public
figures from several social streams The planning of the
project has been carried out in respect of location and
engineering ~eatures on consideration of technical feasibility
and maximising benefits in terms of checking the problems of
salinity ingress and deterioration of ground water quality
storage of good quality river water for irrigation domestic and
industrial water supply flood protection of low lying area on
left bank of the river and road connectivity between left and
right banks
b) Fishermens concerns with respect to obstruction to their
movement as well as migration of Hilsa and other fisheries
species are to be aptly addressed by making provision of fish
passage and ship-lock type arrangement in the barrage Most
importantly the water stored at the barrage will provide a
congenial habitat for fresh water fishery which can be
intensified by stocking economically important fish species so
as to provide more productive employment to the fishermen
c) To sum up the Bhadbhut barrage project has no significant
environment repercussion and is in effect a long-term social
and environment promoting project
(7) Coastal Regulation Zone Impact
As per the CRZ Notification by MoEF dated 6th January 2011 water
area of tidal influenced water body from the mouth of water body at
6
the sea up to the influence of tide which is measured as 5 ppt (5000
mgI) during the driest season of the year is coverable under CRZ
IV wherein the activities disturbing the natural course of sea water
are prohibited Exceptions are however provided for measures to
prevent sand bars installation of tidal regulators laying of storm
water drains or for structures for protection of salinity ingress and
fresh water recharge based on examination carried out by any
agency specified by MoEF vide Office Memorandum dated 24th
February 2011 It is stipulated that all proposals relating to the
projects indicated as exceptions from the prohibited activities shall
be examined by any of the following institutions from technical
angle
(i) Central Water and Power Research Station Pune
(ii) IIT Chennai IIT Mumbai
(iii) Department of Erosion Directorate Ministry of Water Resources
(iv) ICMAM
(v) National Centre for Sustainable Coastal Management
(vi) NIT Suratkal
In this context the study of Bhadbhut barrage for CRZ clearance
proposal was assigned to Central Water and Power Research
Station Pune The proposal for CRZ clearance along with relevant
documents and CRZ map showing HTL and LTL with project layout
superimposed thereon as prepared by Space Application Center
(ISRO) Ahmedabad (the only authorized agency for preparing such
CRZ maps) was also sent to CWPRS Pune for their study The
report on Desk Studies for Salinity Ingress due to proposed
construction of Barrage across the river Narmada at Bhadbhut
Gujarat prepared by Central Water amp Power Research Station
Pune has been received by the Department The findings of the
report are as under
7
a) The analysis of the salinity as per the reports of NEERI
CSMCRI and data collected in Jan 2012 by the Kalpasar project
authorities indicates that the salinity values are well below 5
ppt near the proposed Bhadbhut barrage location during the
dry season at all stages of tides
b) With the construction of the proposed barrage the salinity
values in the us reaches are expected to become further less
and thus will add to the overall utility of the project
c) Due to the proposed barrage impounding of water will aid in
improving the ground water quality and also aid in lift irrigation
schemes
d) From the proposed project an overall improvement in quality
and quantity of water in the region is likely to take place over a
period of time
e) The road link between Hansot and Dahej would not only reduce
the traffic on other existing highways but also reduce the
travel time and cost on fuel
In view of the conclusions of the report by CWPRS contextual to the
provisions regarding salinity of 5 ppt during the driest season of the
year and also exception to the measures for checking tidal salinity
ingress in CRZ notification 2011 the proposed barrage does not in
any way violate the provision of the said notification However as
per the guidelines for permissible activities contained in the CRZ
Notification 2011 issued by the Ministry of Environment amp Forest
GOl the applicationproposal is already submitted to the Gujarat
State Coastal Regulation Zone Management Authority (SCRZMA) for
obtaining CRZ clearance along with the prescribed documents and
necessary fee
(8) Fisheries Impact
8
81 The Bhadbhut barrage will have some challenges concerning
preservation protection and management of fisheries which
were studied so as to formulate strategies for maximizing the
positive aspects and minimizingmitigating the negative
aspects The study has been carried out based on relevant
secondary data consultation with professionals and interviews
with fishermen soliciting their views on various aspects of
fisheries The total number of fishermens families in 21 villages
is 2520 with a population of 12638 The fishermen are partly
employed and inadequately equipped with fishing
infrastmctures The fishing activities are mostly localized along
the frontal stretch of the estuary The boat-bound fishery is
limited to a small number of fishermen having access to
mechanizednon-mechanized boats Fishing activities are
mostly conventional type
Fish production in Bharuch district comprises inland and marine
fish Of the total marine fish production accounts for 18
which is confined to the villages of Gulf shore The inland fish
production includes estuarine fish catch in which Hilsa fish
holds a significant share and estuarine fish production has
shown a declining trend in the last ten years (25 of 1990-
91)
82 Hilsa basically a marine fish species is anadromous in nature
and ascends the rivers for spawning during monsoon Hilsa
supports a substantial fishery in the Narmada estuary and
several fishermen families are dependent on this fishery during
the monsoon for duration of 50-60 days Velocities of flow and
volumes of discharge at the mouth of the estuary are the
driving factors of migration The depletion of Hilsa fishery in the
Narmada estuary is attributable to reduction in flood flows
incidental to the construction of many irrigation projects in the
9
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
the sea up to the influence of tide which is measured as 5 ppt (5000
mgI) during the driest season of the year is coverable under CRZ
IV wherein the activities disturbing the natural course of sea water
are prohibited Exceptions are however provided for measures to
prevent sand bars installation of tidal regulators laying of storm
water drains or for structures for protection of salinity ingress and
fresh water recharge based on examination carried out by any
agency specified by MoEF vide Office Memorandum dated 24th
February 2011 It is stipulated that all proposals relating to the
projects indicated as exceptions from the prohibited activities shall
be examined by any of the following institutions from technical
angle
(i) Central Water and Power Research Station Pune
(ii) IIT Chennai IIT Mumbai
(iii) Department of Erosion Directorate Ministry of Water Resources
(iv) ICMAM
(v) National Centre for Sustainable Coastal Management
(vi) NIT Suratkal
In this context the study of Bhadbhut barrage for CRZ clearance
proposal was assigned to Central Water and Power Research
Station Pune The proposal for CRZ clearance along with relevant
documents and CRZ map showing HTL and LTL with project layout
superimposed thereon as prepared by Space Application Center
(ISRO) Ahmedabad (the only authorized agency for preparing such
CRZ maps) was also sent to CWPRS Pune for their study The
report on Desk Studies for Salinity Ingress due to proposed
construction of Barrage across the river Narmada at Bhadbhut
Gujarat prepared by Central Water amp Power Research Station
Pune has been received by the Department The findings of the
report are as under
7
a) The analysis of the salinity as per the reports of NEERI
CSMCRI and data collected in Jan 2012 by the Kalpasar project
authorities indicates that the salinity values are well below 5
ppt near the proposed Bhadbhut barrage location during the
dry season at all stages of tides
b) With the construction of the proposed barrage the salinity
values in the us reaches are expected to become further less
and thus will add to the overall utility of the project
c) Due to the proposed barrage impounding of water will aid in
improving the ground water quality and also aid in lift irrigation
schemes
d) From the proposed project an overall improvement in quality
and quantity of water in the region is likely to take place over a
period of time
e) The road link between Hansot and Dahej would not only reduce
the traffic on other existing highways but also reduce the
travel time and cost on fuel
In view of the conclusions of the report by CWPRS contextual to the
provisions regarding salinity of 5 ppt during the driest season of the
year and also exception to the measures for checking tidal salinity
ingress in CRZ notification 2011 the proposed barrage does not in
any way violate the provision of the said notification However as
per the guidelines for permissible activities contained in the CRZ
Notification 2011 issued by the Ministry of Environment amp Forest
GOl the applicationproposal is already submitted to the Gujarat
State Coastal Regulation Zone Management Authority (SCRZMA) for
obtaining CRZ clearance along with the prescribed documents and
necessary fee
(8) Fisheries Impact
8
81 The Bhadbhut barrage will have some challenges concerning
preservation protection and management of fisheries which
were studied so as to formulate strategies for maximizing the
positive aspects and minimizingmitigating the negative
aspects The study has been carried out based on relevant
secondary data consultation with professionals and interviews
with fishermen soliciting their views on various aspects of
fisheries The total number of fishermens families in 21 villages
is 2520 with a population of 12638 The fishermen are partly
employed and inadequately equipped with fishing
infrastmctures The fishing activities are mostly localized along
the frontal stretch of the estuary The boat-bound fishery is
limited to a small number of fishermen having access to
mechanizednon-mechanized boats Fishing activities are
mostly conventional type
Fish production in Bharuch district comprises inland and marine
fish Of the total marine fish production accounts for 18
which is confined to the villages of Gulf shore The inland fish
production includes estuarine fish catch in which Hilsa fish
holds a significant share and estuarine fish production has
shown a declining trend in the last ten years (25 of 1990-
91)
82 Hilsa basically a marine fish species is anadromous in nature
and ascends the rivers for spawning during monsoon Hilsa
supports a substantial fishery in the Narmada estuary and
several fishermen families are dependent on this fishery during
the monsoon for duration of 50-60 days Velocities of flow and
volumes of discharge at the mouth of the estuary are the
driving factors of migration The depletion of Hilsa fishery in the
Narmada estuary is attributable to reduction in flood flows
incidental to the construction of many irrigation projects in the
9
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
a) The analysis of the salinity as per the reports of NEERI
CSMCRI and data collected in Jan 2012 by the Kalpasar project
authorities indicates that the salinity values are well below 5
ppt near the proposed Bhadbhut barrage location during the
dry season at all stages of tides
b) With the construction of the proposed barrage the salinity
values in the us reaches are expected to become further less
and thus will add to the overall utility of the project
c) Due to the proposed barrage impounding of water will aid in
improving the ground water quality and also aid in lift irrigation
schemes
d) From the proposed project an overall improvement in quality
and quantity of water in the region is likely to take place over a
period of time
e) The road link between Hansot and Dahej would not only reduce
the traffic on other existing highways but also reduce the
travel time and cost on fuel
In view of the conclusions of the report by CWPRS contextual to the
provisions regarding salinity of 5 ppt during the driest season of the
year and also exception to the measures for checking tidal salinity
ingress in CRZ notification 2011 the proposed barrage does not in
any way violate the provision of the said notification However as
per the guidelines for permissible activities contained in the CRZ
Notification 2011 issued by the Ministry of Environment amp Forest
GOl the applicationproposal is already submitted to the Gujarat
State Coastal Regulation Zone Management Authority (SCRZMA) for
obtaining CRZ clearance along with the prescribed documents and
necessary fee
(8) Fisheries Impact
8
81 The Bhadbhut barrage will have some challenges concerning
preservation protection and management of fisheries which
were studied so as to formulate strategies for maximizing the
positive aspects and minimizingmitigating the negative
aspects The study has been carried out based on relevant
secondary data consultation with professionals and interviews
with fishermen soliciting their views on various aspects of
fisheries The total number of fishermens families in 21 villages
is 2520 with a population of 12638 The fishermen are partly
employed and inadequately equipped with fishing
infrastmctures The fishing activities are mostly localized along
the frontal stretch of the estuary The boat-bound fishery is
limited to a small number of fishermen having access to
mechanizednon-mechanized boats Fishing activities are
mostly conventional type
Fish production in Bharuch district comprises inland and marine
fish Of the total marine fish production accounts for 18
which is confined to the villages of Gulf shore The inland fish
production includes estuarine fish catch in which Hilsa fish
holds a significant share and estuarine fish production has
shown a declining trend in the last ten years (25 of 1990-
91)
82 Hilsa basically a marine fish species is anadromous in nature
and ascends the rivers for spawning during monsoon Hilsa
supports a substantial fishery in the Narmada estuary and
several fishermen families are dependent on this fishery during
the monsoon for duration of 50-60 days Velocities of flow and
volumes of discharge at the mouth of the estuary are the
driving factors of migration The depletion of Hilsa fishery in the
Narmada estuary is attributable to reduction in flood flows
incidental to the construction of many irrigation projects in the
9
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
81 The Bhadbhut barrage will have some challenges concerning
preservation protection and management of fisheries which
were studied so as to formulate strategies for maximizing the
positive aspects and minimizingmitigating the negative
aspects The study has been carried out based on relevant
secondary data consultation with professionals and interviews
with fishermen soliciting their views on various aspects of
fisheries The total number of fishermens families in 21 villages
is 2520 with a population of 12638 The fishermen are partly
employed and inadequately equipped with fishing
infrastmctures The fishing activities are mostly localized along
the frontal stretch of the estuary The boat-bound fishery is
limited to a small number of fishermen having access to
mechanizednon-mechanized boats Fishing activities are
mostly conventional type
Fish production in Bharuch district comprises inland and marine
fish Of the total marine fish production accounts for 18
which is confined to the villages of Gulf shore The inland fish
production includes estuarine fish catch in which Hilsa fish
holds a significant share and estuarine fish production has
shown a declining trend in the last ten years (25 of 1990-
91)
82 Hilsa basically a marine fish species is anadromous in nature
and ascends the rivers for spawning during monsoon Hilsa
supports a substantial fishery in the Narmada estuary and
several fishermen families are dependent on this fishery during
the monsoon for duration of 50-60 days Velocities of flow and
volumes of discharge at the mouth of the estuary are the
driving factors of migration The depletion of Hilsa fishery in the
Narmada estuary is attributable to reduction in flood flows
incidental to the construction of many irrigation projects in the
9
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
upstream stretch of the river The success of establishing Hilsa
fish species in the fresh water of Ukai reservoir has been a
breakthrough that can open up the opportunity for permanent
fresh water habitation of the new Hilsa breed in the Bhadbhut
barrage reservoir The size of the new strain of Hilsa fish
adopted to fresh water environment is reported to be small
compared to the marine forms
83 The fishermens views were assessed through interviews with
the office bearers of 23 Fishermen Co-operative Societies The
office bearers of 21 Societies did not show any notable
apprehensionsconcerns presumably as the fishermen are
residing near the sea coast or carrying out fishery activities in
non-estuary inland water bodies or are partly engaged in
fishery activities which they carry out occasionally in the
Narmada estuary Several societies are inactive and defunct
The two societies which are strongly worked up belong to
Bharuch and Bhadbhut representing 2526 and 2302 fishermen
respectively Their views are abstracted as notional
apprehensions and genuine concerns
The fishermens views on the reduction in the Hilsa fish
migration and Hilsa fish catch due to reduction in flood flows to
be caused by the barrage is a notional apprehension The
understanding that the barrage would be a barrier to the
movement of the fishermen and also to the migration of the
Hilsa and other fishery species is a genuine concern Also the
understanding that with the construction of the barrage the
fishermen might be losing for ever whatever fishing advantage
that they presently avail and thereby compromising their
livelihood is a genuine concern These apprehensions and
concerns are addressed through an effective Fishery
Management Policy (draft)
10
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
r
84 Draft fishery management policy for the post-construction
phase is focused on maximizing fishery production and fetching
good economic returns There is also a possibility of
transplanting Hilsa fish species in the barrage reservoir just as
it could be done in Vallabh Sagar Reservoir at Ukai in Southern
Gujarat
By making provision of fish passage and navigation lock in the
design of the barrage unobstructed movement of fishery
species and fishermen across the barrage will be ensured
Moreover the barrage gates will be kept open during the
monsoon months to release the flood which having
concentrated flow and hence increased flow velocity will flush
out the sediments at the estuary mouth and the present
sediment-related obstruction to migration of marine Hilsa fish
will get eliminated and the large flood volume will have
increased inducement for Hilsa fish migration after barrage
construction
85 The Commissionerate of Fishery Government of Gujarat has
reviewed the Fishery Report related to Bhadbhut Barrage
Project and concurred with the findings including the provisions
of Fish passage and Navigation lock in the design of barrage as
mitigating measures against likely obstruction to migration of
fishery species (saline water Hilsa fish and fresh water prawn)
and general river fishing activities Further to the above it has
been suggested for establishment of a series of small scale
Hatcheries for Hilsa fresh water Prawn Indian Major Carp and
other native species to produce seeds and to ranch in estuarine
region as a part of sustainable enhancement of fish species as a
means of intensifying fresh water fishery production The Hilsa
fish the fresh water fish and the fresh water prawn hatcheries
are to be established and managed by the State Fisheries
11
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
r
Department Preservation of Fisheries Rights of fishermen in
the barrage influenced water body will be ensured The
hatcheries need to maintain a good breed stock bank using the
available natural resources Such propositions are acceptable
within the ambit of Bhadbhut barrage project and Kalpasar
Department will provide budgetory Support for their mitigation
measures
(9) Water demand
91 The project will store approximately 400 to 500 MM3 fresh
water in length of about 85 km which will meet domestic
irrigation amp industrial water requirements Central Design
OrganizationSECON has worked out water availability from
free catchment (down-stream of SSP) at 50 dependability as
3307 MM3 Moreover Narmada river being perennial
continuous flow of river water will also be available Hence the
fresh water reservoir of Bhadbhut can be stored twicethrice in
a year with this water and sufficient water will be available for
domestic irrigation and industrial uses
GIDC and other industries at present are pumping 58 MGD
water from Narmada river at Angareshwar (70km from
Bhadbhut) as there is no permanent water source available for
water requirement of PCPIR except Narmada river and
presently the Narmada river water up to Angareshwar is not
usable even for industrial purposes
92 GIDC has worked out planned water requirement for PCPIR
with different development scenario of PCPIR as discussed with
Chief Secretary on 30092011 The Chief Engineer GIDC has
informed Kalpasar Department regarding water requirement
around 500 MGD by year 2020 with demand of 300 MGD to be
met from Bhadbhut barrage Thus there is a huge water12
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
requirement for PCPIR and other industrial zones
93 The barrage construction is planned to commence in the year
2012-13 and is envisaged to be completed by 2016-17
Government has already approved to take up this project on
PPP (BOT) The draft tender paper for PPP as per the guideline
of Planning Commission is under preparation at Kalpasar
Department The revenue generation for PPP is mainly from
transportation amp industrial water supply components Hence
for assessing projected industrial water income water rate of
Rs 1464 per 1000 lit (2012-13) for industrial use with an
increment of 10 every year has been mentioned in the
government resolution issued by Water Resources Department
By calculating revenue for industrial water for 20 year period
the water rate will reach up to RS145 in year 2037-38 This
issue was discussed with Advisor to Honble Chief Minister
(Chairman EAG) Shri P P Vora Member EAG and Shri A K
Doda National Level Consultant (Ex-Executive Director IDBI)
and it was decided that industrial water rate should be
increased 10 every year till the rate reaches up to Rs 40 and
thereafter as per RBI price indices (1981-82 to 2010-11) for all
commodities percentage change of 478 say 5 should be
used for calculation of industrial water rate During the
discussion it was however felt that the projection of water
requirement by GIDC is seemingly on higher side GIDC
industrial water demand is directly related to various industries
coming up in PCPIR and an element of uncertainty in industrial
development cannot be ruled out There is a need factor in this
eventuality for revenue earning by PPP(BOT) agency Taking a
rational view 25 variation is middotconsidered in average industrial
water demand of 200 MCMannum (to be earmarked to PPP
agency for the concession period of 20 years) which may
13
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
range between 150 MCMannum (lower side) and 250
MCMannum (higher side) If the actual water demand goes
down below 150 MCMannum in a particular year the
govern I ent will be required to compensate PPP agency for
50 of the decrease in the quantity of water demand below
150 MCMannum at the water rate of that particular year In
case the actual water demand is increased above 250
MCMannum the PPP(BOT) agency has to pass on the revenue
earned on 50 of the increase in the quantity of water demand
above 250 MCM to the Government For lower side this
arrangement should continue till PPPagency secures IRR 14
However for higher side the PPPagency will continue to pass
on the amount as indicated to the Government Water is of
prime importance for any industrial development PCPIR Dahej
is already in development phase and all its industries require
water Bhadbhut barrage will be the most assured Narmada
water resource and also preferable Hence the projection of
water demand and revenue generation as worked out is
feasible
(10) Flood protection for left bank
The Bhadbhut project envisages construction of a 1663 m long
barrage across river Narmada about 27 km downstream of Bharuch
city and about 25 km upstream from the sea The right bank of the
river is steep with an average level of EI 9 m whereas the left bank
is relatively flat and at a lower level of EI 55 to 6 m The FRL of
Bhadbhut barrage is EL 75m so that in future water can be
diverted to Kalpasar reservoir through Narmada Diversion Canal
Hence FRL 75m is mandatory If water is to be stored up to EL
75m permanently then huge private land on left bank will come
under permanent submergence requiring acquisition of large land
area Therefore left bank embankment is essential to safeguard the14
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
r
area against submergence Mis SECON has worked out that
minimum private land will come under submergence if the left bank
embankment is provided nearly parallel to the river bank at 16 km
river width (existing bridges are 13 km to 14 km wide only) The
river reach upstream of the barrage up to Golden bridge(of about
27 km) is required to be protected against frequent flooding of low
lying left bank area as well as consequent rise in water levels due to
construction of the barrage The protection work is proposed to be
in the form of RCCretaining wall or embankment
(11) LegaI aspests
Gujarat National Law University (GNLU) Gandhinagar has
prepared the report on Legal Opinion for Bhadbhut Barrage
Project The brief points covered in the report are as under
10 Whether the Kalpasar Department can construct the Bhadbhut
Barrage on River Narmada Is there any violation of Narmada
Water Disputes Tribunal award If yes then give the
reference of Narmada Water Disputes Tribunal award by
which the Kalpasar Department cannot construct Bhadbhut
Barrage Project
11 Various provisions of the Narmada Water Disputes
Tribunal (NWDT) Award enable the Department to
construct the Barrage By building the Barrage the
Department will not be violating the Award
12 First the NWDT for such type of projects in view of their
aims and objectives has expressed desirability for the
best utilization of water which would otherwise go waste1
13 Second the NWDT has given free hand to the State in
terms of using Spill-over or non-storable spill water2
14 Based on the analysis of the above provision of the
NWDT it is concluded that the Tribunal Award does not
15
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
prohibit the construction of Barrage and Department will
not be violating the award either inletter or in spirit
1 Clause 111 (5) reads it is desirable that water which would go wastewithout even generating power at the last river-bed power-house shouldbe allowed to he utilized hy the party States to the extent they can2 Clause 1V (5) reads the party States whose reservoirs are spillingand the spill water cannot be stored elsewhere may utilize such RowsfrOIll the said reservoirs as they like and such utilization hy the partyStates ~ill not count to bullbullards allotment of supplies to them but use ofsuch raquotIter will not establish any prescriptive rights
20 Whether KaJpasar Department of Government of Gujarat can
utilize free catchment water at Bhadbhut Barrage without
consulting other basin states ie Maharashtra and Madhya
Pradesh
The Department can utilize free catchment water at the
Barrage because the catchment water at the Barrage will
neither create a situation of flooding in other states nor these
states can positively claim on this water3 The Department
can make such changes in the pattern of consumption of
water and in the areas to be benefitted within or outside the
Narmada basin in its territory as it may consider necessary
30 Whether Kalpasar Department of the Government of Gujarat
can utilize water released from River Bed4 Power House of
Sardar Sarovar Project without violation of Narmada Water
Disputes Tribunal award
According to clause IX (vii) Gujarat may let down water from
the Sardar Sarovar for its downstream use by making specific
indent for it and such release shall reckon against its share
Such releases for downstream use shall be made through the
turbines and the power so generated shared between Madhya
Pradesh Maharashtra and Gujarat in the prescribed ratio16
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
r
Water letdown into the river from Sardar Sarovar except at
the specific indent of Gujarat shall not reckon against the
share of Gujarat Thus the Award does not provide any
restriction on the utilisation of water released from River Bed
Power House of Sardar Sarovar Project by Gujarat
3 Water in the catchment area is considered catchment water Catchment isthe most significant factor for determining the amount or likelihood offlooding Since Gujarat is lower riparian state the question of flooding inother basin states does not arise Several factors shall be kept into accounthowever First topography influences the speed with which the runoff waterwill reach a river Since the topography (ie land territory) surroundingBhadhhut is exclusively in the jurisdiction of Gujarat stale the question doesnot arise4 River hed is the channel bottom of a river the physical confine of normalwater flow
40 Whether Government of Gujarat Kalpasar Department can
utilize spillway surplus water of Sardar Sarovar Project
without violation of Narmada Water Disputes Tribunal award
As per clause IV(S)5 the Tribunal Award categorically
authorizes Gujarat to use the spillway6surplus water7and such
usage will not violate the Award in any way According to the
Order Gujarat is directed that whenever water starts going
waste to sea without generating power or based on the
information received from upstream gauging stations it
anticipates that water would so go waste it shall inform the
Authority and designated representatives of all the concerned
states Gujarat shall also inform them when such flows cease
During the period such flows Gujarat whose reservoirs (SSP)
are spilling and the spill water cannot be stored elsewhere
may utilize such flow from the said reservoirs as they like and
such utilization of the party States will not count towards
allotment of supplies to them but use of such water will not
establish any prescriptive rightss
17
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
5 ClauseIV (5)
6 Spillway is defined as passage jrJr surplus water over or around a damwhen the reservoir itself is full Spillways are particularly important safetyfeatures for earth dams protecting the dam and its foundation from erosionThey may lead over the dam or a portion of it or along a channel around thedam or a conduit through it SourcewwwBritanicacom7 There are two types of pillway - controlled and uncontrolled SSP has acontrolled spillway consisting of mechanical structures and gates to regulatethe flow rate of water As the controlled pillway will always have the fidlheight of the dam to be used for water storage year-round only the floodwaters can be released as required by opening one or more gates On thecontrary in case of uncontrolled spillways surplus water will rise above thelip or crest and will be released rom Sarovar There is no mechanical controlover the discharge rates as the depth of reservoir water can only determinethe rate of discharge Since the storage volume in the Sarovar above thespillway can he used only for the temporary storage of flood water any claimor complaint that Gujarat can use such water for water supply does not arise8 The use of term prescriptive right in this award can be meant to suggestthat Gujarat has a right to use such waters when only the other hasin statesfail to or claim to use the water for the time defined hy the law Gujaratcannot claim thus every year to use the entire spillway water if the otherstates otherwise need to claim or use the water which would otherwise createa surplus water situation in the Sardar Sarovar
50 Whether the Kalpasar Department of the Government of
Gujarat can request in emergency for releasing water by
indenting through Narmada Department to the Narmada
Control authority
51 The Award lays down specification for the quantum and
pattern of regulated releases in normal circumstances
However Gujarat can request in emergency for releasing
water by indenting through Narmada Department to the
NCA
52 While the above interpretation holds true in the normal
circumstances Gujarat in case of emergency situation
indeed tan use allocated share from the surplus water in
the reservoir according to clause IX(ii) for irrigation and
other purposes
18
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
60 Whether Kalpasar Department of the Government of Gujarat
has to notify the Narmada River for construction of the
Bhadbhut Barrage or Department can use the present
notification
61 The Water Resources Department has notified Narmada
river vide government notification no INF 1161 dated 21
September 1963 for Navagam dam (now renamed as
SSP) This notification is applicable to the projects Karjan
Sukhi However this notification is not applicable for the
Bhadbhut Barrage Project
62 Tile NWRWS amp Kalpasar Department has to notify
Narmada river for construction of Bhadbhut Barrage
Project in a similar way as the notification issued earlier
for Navagam dam after taking approval from the
competent authority
70 Whether any permission with reference to coastal regulation
zone act rules is necessary in case of construction of the
Bhadbhut Barrage
71 Ministry of Environment and Forests of the Government
of India has issued revised CRZ notification Earlier
notification of 1991 was vague in the sense that it lacked
certain specifications This has now been revised in
January 2011 As per the Revised Notification the
Coastal Regulation Zones (CRZ) have been classified as
under
CRZ-I The areas that are ecologically sensitive and
geomorphological features which play a role in
maintaining the integrity of the coast which included
Mangrove area Corals Sand dunes Mud flats
Biologically active National park Marine park Reserve
forest Wild life habitats and other protected areas
19
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
CRZ-II The areas that have been developed up to or
close to the shore line
CRZ-III Areas that are relatively undisturbed and those
do not belong to either CRZ- I or CRZ- II which include
coastal zone in the rural area and also areas within
municipal limit or in other legally designated urban areas
which are not substantially built up
CRZ-IV
(A) The water area from the low tide line to the 12
nautical miles on the seaward side
(B) Shall include the water area of the tidal influence
water body from the mouth of the water body at
the sea up to the influence of tide which is
measured as five parts per thousand during the
driest season of the year
72 The Bhadbhut Barrage Project is planned to be located
about 22 km inside the estuary As per the classifications
of CRZ area explained in 71 the Barrage location does
not fall in the sea area Therefore the project falls under
CRZ-IV (B) category Further as per the 2011
Notification following structures are permitted in the CRZ
area Measure to prevent sand bars installation of tidal
regulators laying of storm water drains or for structures
for prevention of salinity ingress and fresh water
recharge The Bhadbhut Barrage is created for the
prevention of salinity ingress
The CRZ is applicable to the land area between high tide
level to 100 meters or width of the creek whichever is
less on the landward side along the tidal influenced
water bodies that are connected to the sea and the
distance up to which development along such tidal
20
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
influenced water bodies is to be regulated shall be
governed by the distance up to which the tidal effects are
experienced which shall be determined based on salinity
concentration of 5 parts per thousand (ppt) measured
during the driest period of the year
80 Whether Kalpasar Department can execute Bhadbhut Barrage
Project on Public Private Participation (PPP) mode and collect
revenue generated through water land transports and other
infrastructure created
The Kalpasar Department can finalise this issue in consultation with
the Finance Department Gujarat Infrastructure Development Board
and any other concerned Departments of Gujarat
90 Additional reasons in justification consideration and caution for the
construction and operation of the Bhadbhut Project
91 Reasons for Justification
a Fulfilment of the Overriding Public Interest Regime -
Prevention and control of salinity ingress Currently the
incoming tidal surge-bores up the Narmada river as far as
Shukaltirth and the spring tides of salty water inundates
thus exposed low-lying areas creating salt-marshes
Therefore it can be argued that the barrage will significantly
moderate this tidal surge and positively affect the extent of
inundation of salty-water As per estimation hundreds of
hectares of agricultural land gets salt ingress annually
creating socio-economic impacts on thousands of families
surviving on farming
b For restoration of quality of water The Barrage aims to
promote the objectives of the Water (prevention and Control
of Pollution) Act1974 as the project will restore the
wholesomeness of water Thus Gujarat Government
through this project reaffirms its commitment to the larger
21
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
population and fulfils the obligation Considering the Water
Policy the Barrage would prevent further deterioration of
water quality and will in fact restore the water quality
c Risk prevention for low-lying areas If the Barrage is not
created the low lying areas around the estuary will become
more at risk of increased flooding due to storm surges and
sea level rises by climate change The barrage will play a
significant role in flood defence and protection against sea
level rise compared to other measures
d Alternate Better Sustainable Employment for Thousands of
Families and the whole region The Project will generate
direct jobs in barrage construction operation and technology
export could follow in other states of India The Dahej SEZ
and neighboring regions will benefit from inward investment
due to the road link increased land and property values and
possibly new recreational opportunities The barrage would
also become a touristic spot followed by sight seeing
housing tourist and other developments around the area
e The Barrage will reverse the national trend which sees that
there has been significant degradation of coastal resources
due to poor planning of developmental activities and
overexploitation of natural resources
92 Reasons for Consideration
a No Ecological Imbalance or Harm The existing area where
the barrage is to be constructed is not ecologically rich and
rare environmental area for birds or for wildlife habitats
Of course the Hilsa fish is a migratory species which travel
between salt and fresh water to complete their breeding
cycle and they use the whole estuary system as a breeding
area nursery and food resource
b Effects on silt deposition sediment and salinity ingress As
the barrage will change the energy of the current flows in
22
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
r
the estuary it will impact on the sediment regime on silt
deposition and to a significant degree on salinity ingress
c The area under the proposed barrage is not a National or
International Protected Area The Bhadbhut estuary is
neither protected under any national or international
designations The adverse impact on the species and
habitats can be justified for imperative reasons of overriding
public interest namely reduction in salinity ingress and
irrigation of thousands of hectares of land At the end of all
studies such as environmental technical and financial
studies it can be argued that the alternative solutions are
not available either in the area or a wider field
d It is unlikely that the barrage itself will cause coastal erosion
and flood risk on its seaward side
e Overriding public need and interests regime has to be
articulated and costbenefit ratio in favor of public vis-a-vis
environmental damage shall be proven
f The barrage is promoted in terms of its benefits to socio-
economic sectors especially rural economies therefore all
the benefits need to be placed in context for informed
consideration
g Requirement of the Barrage at current juncture The barrage
would be a monumental and iconic structure so it shall be
built for the best reasons and the most appropriate moment
in time which has come now There is a clear need for the
barrage for checking of salinity ingression irrigation and
potable water needs energy greenhouse gas reduction
coastal defense industrial activities etc
h Compliance with Environmental Law Principles The Project
complies with the provisions of all environmental principles
such as the precautionary principles polluter pays principle
23
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
use of proper resource accounting trans boundary
responsibility and intergenerational equity
i Best Management Approaches The project will have best
ma agement approaches inter alia restricting reclamation
for essential activities prohibition of disposal of untreated
waste ensure sufficient fresh water discharge to maintain
estuarine characteristics ensure sufficient tidal exchange
zonate areas for aquaculture salt manufacture ports and
industries and tourism to avoid critical habitats and conflicts
in use avoid locating chemical plants with toxic discharge
near estuaries
J Others The Project- the goals of biodiversity conservation
and local peoples livelihood security is placed at the centre
stage of all decision making pertaining to the infrastructure
development or economic consideration of revenue
generation
93 Application of Precautionary Principles
a While the barrage will impact some habitats it will also bring
benefits to some habitats and some species as the
remaining inter-tidal area would become more biologically
rich
b Hilsa Fish The barrage will have an impact on the Hilsa fish
in particular Hence suitable provision for movement of fish
shall be planned in the barrage
c The Barrage aims to give coastal protection the top priority
as this is extremely important even for the fixing of the HTL
Any structure (hard measure) should be considered only if
soft measure is not possible The agency considering the
hard measure particular groins or breakwaters should be
made responsible for protecting the shoreline at least 500 m
on either side of the shoreline from erosion The agency
responsible for the construction should be made responsible
24
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar
r
for the monitoring of the shoreline for a minimum period of
one year so as to cover the seasonal variation in the wave
climate which dictates its dynamics Similarly within the
said distance if river is blocked by sand bar formation on its
up drift side due to the construction of barrier jetting into
the sea suitable control measures are to be incorporated in
the planning stage of the project The construction agency
shall be made responsible for a minimum period of one year
(12) Recognizing the project benefits and the details of activities
carried out so far by Kalpasar Department and legal issues
covered by GNLU in its report on legal opinion for the proposed
barrage project it was decided that Bhadbhut barrage project will
be within the purview of the applicable iegal and regulatory
framework and will have a long-term social and environment
impact and does not violate any provisions of prevailing
notifications and Narmada Disputes Tribunal Award
(Dr Bimal Patel)Director
Gujarat NationalLaw University
Gandhinagar
(Kamalbhai Trivedi)Advocate GeneralGovt of Gujarat
25
mUjoJ~(~ Patel)
Secretary (Kalpasar)Narmada Water
Resources WS amp KalpasarDepartment Govt ofGujarat Gandhinagar