MJC Measure E Bond Program College Wide Forum January 11, 2008

Date post: 31-Dec-2015
Category:
Upload: nayda-mckinney
View: 24 times
Download: 0 times
Share this document with a friend
Description:
MJC Measure E Bond Program College Wide Forum January 11, 2008. Facilities Master Plan Status. May 2007, First Draft of Master Plan Issued for review June 2007, Board Accepted Increment I Plan and Revised Measure E MJC Budget November 2007, Second Draft of Master Plan issued for review - PowerPoint PPT Presentation
17
MJC Measure E Bond Program College Wide Forum January 11, 2008
Transcript

MJC Measure E Bond Program

College Wide ForumJanuary 11, 2008

Facilities Master Plan Status

• May 2007, First Draft of Master Plan Issued for review

• June 2007, Board Accepted Increment I Plan and Revised Measure E MJC Budget

• November 2007, Second Draft of Master Plan issued for review

• December- January 25, 2008- Review and Comment Period from College Community

• February 6, 2008- Final presentation to Board with College Comments

Facilities Master Plan Status

What is approved?

• Increment I Site Plans

• Increment I Project Budgets

What is currently in review?

• The remainder of Volume I of the Facilities Master Plan

• Volume 2 of the Facilities Master Plan

Board Approved Plan

• Modesto Junior College – Overall

Board Approved Plan- West

• Modesto Junior College – Overall

Board Approved Budgets

Board Approved Budgets• Agricultural Projects

$24,800,000• Parking Structure $12,000,000• Allied Health $25,822,000• West Side Site $ 5,037,370• Science Comm. Ctr./GVM $70,000,000• Student Services $16,000,000• Loop Road- West Campus $ 5,000,000• Infrastructure- West $ 5,000,000• Turlock Site $ 937,185• Softball Complex $ 786,300• High Tech Center- (Science East) $16,000,000• Interim Housing- Founders $ 1,000,000• Founders Hall Modernization

$12,000,000• Library/ LRC $ 6,145,145

East Campus Planning

• Modesto Junior College – Overall

East Campus Planning

• Modesto Junior College – Auditorium

East Campus Planning

• Modesto Junior College – Student Services

East Campus Planning

• Modesto Junior College – High Tech Center (existing Science Center East)

West Campus Planning

• Modesto Junior College – Overall

West Campus Planning

• Modesto Junior College – Science Quadrant

West Campus Planning

• Modesto Junior College – Softball

West Campus Planning

• Modesto Junior College – Ag Multi Use Pavilion

West Campus Planning

• Modesto Junior College – Ag Housing

Facilities Master Plan Next Steps

• Faculty and Staff Review of posted FMP, http://www.mjc.edu/news/Draft%20Master%20Plan%2012-07.pdf

• Review and revision of the Facilities Master Plan

• Written Response to all comments/ questions

• February 6, 2008- Final presentation to Board with College Comments

Question and Answer

January 11, 2008