+ All Categories
Home > Documents > MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition,...

MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition,...

Date post: 12-Mar-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
85
TECHNICAL REPORT HL-89-1 SUBMERSIBLE-TYPE TAINTER GATE FOR SPILLWAY MMARSEILLES LOCK AND DAM Hydraulic Model Investigation by " MCI ,GAN Deborah R. Cooper L. Hydraulics Laboratory 3EC I DEPARTMENT OF THE ARMY o Waterways Experiment Station, Corps of Engineers SPO Box 631, Vicksburg, Mississippi 39181-0631 MAP January 1989 Final Report Approved For Public Release. Distribution Unlimited DTIC CELcTE E HYDRAULICS Prepared for US Army Engineer District, Rock Island LABORATORY Rock Island, Illinois 61204-2004
Transcript
Page 1: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

TECHNICAL REPORT HL-89-1

SUBMERSIBLE-TYPE TAINTER GATE FOR SPILLWAYMMARSEILLES LOCK AND DAMHydraulic Model Investigation

by

" MCI ,GAN Deborah R. Cooper

L. Hydraulics Laboratory3EC

I DEPARTMENT OF THE ARMYo Waterways Experiment Station, Corps of EngineersSPO Box 631, Vicksburg, Mississippi 39181-0631

MAP

January 1989Final Report

Approved For Public Release. Distribution Unlimited

DTICCELcTE

EHYDRAULICS

Prepared for US Army Engineer District, Rock IslandLABORATORY Rock Island, Illinois 61204-2004

Page 2: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Destroy this report when no longer needed. Do not returnit to the oriqinator.

The findings in this report are not to be construed as an officialDepartment of the Army position unless so designated

by other authorized documents.

The contents of this report are not to be used for

advertising, publication, or promotional purposes.Citation of trade names does not constitute anofficial rndorsement or approval of the use of

such commercial products.

Page 3: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

UnclassifiedSECURITY CLASSIFICATION OF T S PAGE

Form ApprovedREPORT DOCUMENTATION PAGE 0MB N. 0704-0188

la REPORT SECURITY CLASSFCATON lb RESTRICTIVE MARKINGSUnclassified

2a SECURITY CLASSIFICATION AUTHORITY 3 DISTRIBUTION /AVAILABILITY OF REPORTApproved for public release; distribution

2b DECLASSIFICATION/DOWNGRADING SCHEDULE unlimited.

4 PERFORMING ORGANIZATION REPORT NUMBER(SI 5 MONITORING ORGANIZATION REPORT NUMBER(S)Technical Report HL-89-1

6a. NAME OF PERFORMING ORGANIZATION 6b OFFICE SYMBOL 7a. NAME OF MONITORING ORGANIZATIONUSAEES (If applicable)

Hydraulics Laboratory CEWES-HS-S

6c. ADDRESS (City, State, and ZIP Code) 7b. ADDRESS (City, State, and ZIP Code)PO Box 631

Vicksburg, MS 39181-0631

8a. NAME OF FUNDING/SPONSORING Sb OFFICE SYMBOL 9 PROCUREMENT INSTRUMENT IDENTIFICATION NUMBERORGANIZATION (If applicable)USAED, Rock Island CENCR-ED-DM

Sc. ADDRESS(Cit State, and ZIP Code) 10 SOURCE OF FUNDING NUMBERSP0 Box 20t4 PROGRAM PROJECT " TASK WORK UNITClock Tower Building ELEMENT NO NO NO. ACCESSION NO.Rock Island, IL 61204-2004

I1 TITLE (Include Security Clasification)Submersible-Type Tainter Gate for Spill'y, Marseilles Lock and Dam; Hydraulic ModelInvestigation

12 PERSONAL AUTHOR(S)Cooper, Deborah R.

13a. TYPE OF REPORT 13b. TIME COVERED 14. DATE OF REPORT (Yeer, Month, Oay) IS. PAGE COUNTFinal report FROM TO January 1989 85

16. SUPPLMENTARY NOTATIONAvailable from National Technical Information Service, 5285 Port Royal Road, Springfield,VA 22161.

17. COSATI CODES 18 SUBJECT TERMS (Continue on reverse if necessary ad identify by block number)FIELD GROUP SUB-GROUP 'Hydraulic forces, Submersible gates)

Spillway Vibrations.

19. ABSTRACT (Continue on reverse if necessary and identify by block number)

-A l:20-scale hydraulic model simulated a 120-ft-wide section of the spillway andstilling basin including one freely suspended 60-ft-wide by 16-ft-high submersible taintergate. The gate lifting mechanism consisted of a cable at each end of the gate attached toload cells. The magnitude and frequency of the forces acting on the cable supporting eachend of the gate were measured. Tests indicated that there was a likelihood of the cablesbeing subjected to exciting forces occurring at a random frequency with flow (a) over and(b) under the subject gate. The magnitude of these forces was about 1 percent of thetotal gate weight. Discharge characteristics and coefficients and stilling basin perfor-mance with various operating scenarios were determined. -,. -

20 DISTRIBUTION/AVAILABILITY OF ABSTRACT 21 ABSTRACT SECURITY CLASSIFICATIONML,NCLASSIFIED/IUNLIMITED 0 SAME AS RPT C DTIC USERS Unclassified

22a. NAME OF RESPONSIBLE INDIVIDUAL 22b TELEPHONE (Include Area Code) 22c. OFFICE SYMBOL

DD Form 1473, JUN 86 Previous editions are obsolete SECURITY CLASSIFICATION OF THIS PAGE

Unclassified

Page 4: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

IEC RjilY C .As .TcA"o, oN W''-5 Pe,?r;

SEC.AIhTy CLASS$FICATION OF T- S C

Page 5: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

PrFFACE

The model investigation reported herein was authorized bv the Head-

quarters, US Army Corps of Engineers (USACE), on 25 January 1985 at the re-

quest of the US Army Engineer District, Rock Island (NCR). The studies were

conducted in the Hydraulics Laboratory of the US Army Engineer Waterways

Experiment Station (WES) during the period January to October 1985 under the

direction of Messrs. F. A. Herrmann, Jr., Chief of the Hydraulics Laboratory,

and J. L. Grace, Jr., and G. A. Pickering, past and present Chiefs of the Hy-

draulic Structures Division. Tests were conducted by Mrs. D. R. Cooper,

Mr. E. L. Jefferson, and Mrs. J. A. Flowers, Spillways and Channels Branch,

under the direct supervision of Mr. N. R. Oswalt, Chief of the Spillways and

Channels Branch. This report was prepared by Mrs. Cooper.

During the course of the investigation, Messrs. B. McCartney of USACE;

J. Ordonez, B. Snowden, and H. Stuart of the US Army Engineer Division, North

Central; and S. K. Nanda, D. Wehrley, D. McCully, and J. Schliekelman of NCR

visited WES to discuss test results and correlate these results with current

design studies.

Special thanks to Mrs. M. C. Gay, Information Technology Laboratory,

WES, who edited this report; Mr. R. T. Blackwell, Engineering and Construction

Services Division, WES, who constructed the gate; and Mr. J. L. Grace, Jr.,

who provided technical guidance during this study.

COL Dwayne G. Lee, EN, is the Commander and Director of WES.

Dr. Robert W. Whalin is the Technical Director.

D:IC TQ'.

ElJusti fit A4on1

ByD'striP-Ition/_ __

Avail;ility Codes

Avi. and/or

Dist Spocial

Page 6: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

CONTENTS

Page

PREFACE................................................................... I

CONVERSION FACTORS, NON-SI TO SI (METRIC) UNITS OF MEASUREMENT ............ 3

PART I: INTRODUCTION................................................... 5

The Prototype....................................................... 5Purpose and Scope of the Model Study............................... 6

PART It: THE MODEL AND TEST PROCEDURE.................... .............. 7

Description..................... .................................... 7Appurtenances and Instrumentation ................................... 7Scale Relations................................................... 9Test Procedure .........o.............. ................................. 9Presentation of Data.,....... ........ ..... o............ ......... 10

PART III: TESTS AND RESULTS.................... ............... ......... 11

Discharge Characteristics............................... ........... 11Stilling Basin Performance ......o.......................o..............15Gate Cable Loads and Vibrations................... ................. 16

PART IV: CONCLUSIONS.......................................... ... ..... 21

TABLES 1-7

PHOTOS 1-5

PLATES 1-44

2

Page 7: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

CONVERSION FACTORS, NON-SI TO SI (METRIC)

UNITS OF MEASUREMENT

Non-SI units of measurement used in this report can be converted to SI

(metric) units as follows:

Multiply By To Obtain

cubic feet 0.02831685 cubic metres

feet 0.3048 metres

inches 25.4 millimetres

miles (US statute) 1.609344 kilometres

pounds (force) 4.448222 newtons

pounds (mass) 0.45359 kilograms

3

Page 8: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

LAKEWISCONSIN ICHIGA

MICHIGAN

IOWA CHIICAGO

MARS:EILLES

JO LIE TOTTAWA

PROJECTL OCA TION

ILLINOISURIVER 1INAIAAPOLIS

ILLINOIS INDIANAjMissISSIPPIMISSOURI KENTUCKY

VICINITY MAP

SCALE50 0 50 100 MILES

\ \ NORTH CHANNEL

7 HEAD RACE

HEAD RACE DAMS

ILLINISTATE ARK MA SERLLELCAEA

SCALE WALKWAY

200T 0E 200W 40YF

Fiur 1.6 Viintyan octin a

PRTCIO4IR

Page 9: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

? UBMERSIBLE-TYPE TAINTER GATE FOR SPILLWAY

MARSEILLES LOCK AND DAM

Hydraulic Model Investigation

PART I: INTRODUCTION

The Prototype

1. Marseilles Dam is located at the upstream end of the Marseilles

Canal at river mile 247.0 on the Illinois River, near the city of Marseilles,

IL, approximately 6 miles* southeast of the city of Ottawa and 65 miles south-

west of Chicago, IL (Figure 1). The lock is located at the mouth of the

Marseilles Canal 2.4 miles downstream of the dam at river mile 244.6. The

lock and dam are connected by Bells Island.

2. The main dam is a gated structure founded on shale spanning the

Illinois River at the upstream end of the Marseilles Canal (Figure I). At the

time this model investigation was performed, the main dam consisted of a

552-ft-wide section containing eight counterweighted nonsubmersible 60-ft-wide

tainter gates and a 46.5-ft-wide section containing a 30-ft-wide Ice chute and

a 16.5-ft-wide ice chute valve room (Plate 1). The normal head on the main

dam is about 13 ft and the upper pool is maintained at el 483.17.** The

spillway tainter gates are 16 ft high with a radius of 25 ft (Plate 2). Con-

nected by two counterweighted side arms, each gate revolves about two trun-

nions located in adjacent piers at the origin of the gate radius.

3. To bring the dam up to current design standards, and provide a safe

and reliable operation, the US Army Engineer District, Rock Island, proposed

to replace the counterweighted, nonsubmersible tainter gates of the main dam

with new submersible tainter gates (Plate 3). All eight of the prototype sub-

mersible taintEr gates have been installed at Marseilles Dam. The new gates

are designed to pass water under the gate as at present (Photo 1), or over the

gate with a maximum 8 ft of gate submergence (Photo 2). During high flows,

* A table of factors for converting non-SI to SI (metric) units of measure-

ment is presented on page 3.

•* All elevations (el) cited herein are In feet referred to the National Geo-

detic Vertical Datum (NGVD).

5

Page 10: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

the vates may be raised completely out of the water.

4. The submergence feature of the gates will permit skimming ice and

debris over the top of the gate with a much smaller water discharge than would

he reauired to draw the material under a nonsubmersible type gate. Year-round

operation requires passage of quantities of ice and, to a lesser extent,

debris through the dam when flow in the river is insufficient to permit rais-

ing gates clear of the water surface without a serious loss of pool levels.

Flow sufficient to skim floating material over the top of a submerged gate

should produce less violent downstream effects.

Purpose and Scope of the Model Study

5. Because US Army Corps of Engineers submersible gates on the Ohio

River have historically experienced severe vibrations,* this model study was

conducted to determine the magnitude and frequency of the hvdraulic forces

acting on the lifting cables while the gatp is submerged. In addition, veri-

fication of anticipated stilling basin performance for all probable operating

conditions was of interest. Discharge characteristics and coefficients with

various operating scenarios were determined from the model.

* US Army Engineer District, Louisville. 1985 (Jun). "Submergible Gate Use

Within the Corps: Case Histories," Louisville, KY.

6

Page 11: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

PART I: THE MODEL AND TEST PROCEDURE

Description

6. Th i:20-scale model (Figure 2) reproduced a 120-ft-wide section of

the spiliwiv and stilling basin including one freely suspended 60-ft-wide by

16-ft-high submersible tainter gate, two 8-ft-wide piers, and two 22-ft-wide

:y 16-ft-high portions of the tainter gate on either side of the piers. The

model tainter gate (Figure 3) was constructed of brass and simulated a proto-

type weighing 160,000 lb (dry weight). The upstream and downstream skInplates

and trunnion arms were reproduced to scale. Originally the rubber side seals

were omitted, simulating a 4-in. gap between the gate and the piers. This

provision was made to avoid friction between the gate and piers and was part

of the type I and 2 designs. Howev-r, this provision proved to be too sig-

nificant a deviation from the prototype and was responsible for most of the

vibration reported herein. To reduce friction forces to a minimum, the gate

trunnions were mounted in roller bearings in the adjacent piers. The gate-to-

sill clearance simulated was I in. The piers and ice deflector shields

(Plate 3) were constructed of transparent plastic; the portion of the model

representing the spillway sill and apron was fabricated of sheet metal. The

two adjacent gates were simulated schematically and reproduced only the shape

and size of a nonsubmersible-type tainter gate. The gate lifting mechanism

consisted of a cable at each end of the gate attached to load cells suspended

by a pulley system (Figure 2). Each model cable was sized to reproduce the

elastic properties of four prototype cables proposed for each end of the gate.

Appurtenances and Instrumentation

7. Water used in the operation of the model was supplied by pumps, and

discharges were measured with venturi meters. The tailwater in the downstream

end of the model was controlled by an adjustable tailgate. Steel rails set to

grade provided reference planes. Water-surface elevations were obtained with

point gages. Velocities were measured with a pitot tube. Load cells and an

oscillograph recorder (Figure 4) were used to measure and record the magnitude

and frequency of the total forces acting on each end of the gate. Chart speed

used during testing was I ips.

7

Page 12: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Figure 2. 1:2O-scale model

I- ~ Br~-'~ 'delgate

Page 13: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Figure 4. Oscillograph recorder

Scale Relations

8. The accepted equations of hydraulic similitude, based upon the

Froude relations, were used to express the mathematical relations between the

dimensions and hydraulic quantities of the model and the prototype. General

relations for transference of model data to prototype equivalents are pre-

sented in the following tabulation:

Dimension Ratio Scale Relation

Length L r= L 1:20

Area A = L2 1:400r r

Velocity V = L 11 2 1:4.472r r

Time T = L1 /2 1:4.472r r

Discharge Q = L 5 /2 1:1,788.85r r

Weight W = L 1:8,000r r

Force F = L 3 1:8,000r r

Test Procedure

9. Tests were conducted in the model to observe the conditions with

9

Page 14: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

flow over and under the gate and to determine the magnitude and frequency of

the hydraulic forces acting on the lifting cables with various gate openings

and submergences of the gate. To measure the forces on the gate, the pool

elevation was held constant while the position of the gate and the tailwater

were varied.

10. All tests were conducted with the upper pool level maintained at a

constant elevation of 483.17. Prior to the start of a test, the force-

measuring equipment was checked to ensure that it was working properly, the

moving parts of the test gate were examined, and the water levels of the upper

pool and the lower pool below the gate were properly adjusted. The force-

measuring device, having previously been zeroed, was then placed in operation

(raising or lowering the test gate). The force on the hoisting cables was

measured by raising the crest of the gate in 1-ft increments to a desired ele-

vation and holding it there for a measurement. All force data presented in

the tables in this report were measured in this manner.

Presentation of Data

11. In the presentation of test results, the data are not provided in

the chronological order in which the tests were conducted. Instead, as each

element of the gate and the gate lifting mechanism is considered, all tests

conducted thereon are discussed. All model data are presented in terms of

prototype equivalents. All tests are discussed in Part III.

10

Page 15: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

PART III: TESTS AND RESULTS

12. Tests were conducted with two different spillway crest designs for

the submersible-gated spillway. These designs, furnished by the sponsor, dif-

fered only in the shape of spillway crest upstream from the gate. The type 1

(original) design (Plate 4) had a curved shape with an 8-ft radius, and the

type 2 design had a 2.5-ft-broad horizontal sill preceded by a IV on 1.2H

sloping face (Plate 4). Tests were conducted to determine discharge charac-

teristics, stilling basin performance, loads on the gate lifting cables, and

vibration tendencies of the gate with each of these crest shapes. Tests were

also conducted to determine the effects on the cable loads and vibration ten-

dencies of decreasing the clearance between the gate and pier and increasing

the gate-to-sill clearance.

Discharge Characteristics

Flow conditions

13. Tests to determine the discharge characteristics of the spillway

with the two spillway crest designs were conducted for each of the following

flow conditions:

a. Free uncontrolled flow. Gate fully open; upper pool unaffected

by the tailwater.

b. Submerged uncontrolled flow. Gate fully open; upper pool con-

trolled by the submergence effect of the tailwater.

c. Free uncontrolled flow (over the gate). Gate in submergedposition with flow over gate; upper pool unaffected by thetailwater. Gate essentially behaves as a weir fixed at several

elevations.

d. Submerged uncontrolled flow (over the gate). Gate in submergedposition with flow over the gate; upper pool controlled by thesubmergence effect of the tailwater. Gate essentially behavesas a weir fixed at several elevations.

e. Free controlled flow. Gate partially open; upper pool unaf-

fected by the tailwater; controlled by the particular gate

opening with flow under the gate.

f. Submerged controlled flow. Gate partially open; upper poolcontrolled by both the submergence effect of the tailwater andthe gate opening with flow under the gate.

These flow regimes are shown in Plate 5. Symbols used in this plate are

defined in paragraph 18.

11

Page 16: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Description of tests

14. Free uncontrolled flow characteristics were determined by introduc-

ing various constant discharges into the model and observing the corresponding

upper pool elevation. Sufficient time was allowed for stabilization of the

upstream flow conditions. Upper pool elevations were measured at a point

180 ft upstream from the spillway. Tailwater elevations were measured at a

point 300 ft downstream of the end sill.

15. A similar procedure was followed for gate openings ranging from

2 to 8 ft to determine the discharge characteristics of free controlled flow.

16. Submerged flow characteristics for both controlled and uncontrolled

flows were determined by introducing several constant discharges into the

model and varying the tailwater for each discharge from an elevation at which

no interference with spillway flow was evident to an elevation at which the

flow was practically 100 percent submerged. The elevation of the upper pool

for each tailwater elevation was recorded.

Presentation and analysis of data

17. Basic data obtained with flow over the spillway are presented in

plots of upper pool elevation versus tailwater elevation for each of the

spillway crest designs. These data for the type 1 (original) design spillway

crest and type 2 design spillway crest are shown in Plates 6-10 and 11-15,

respectively. Free flow data with flow over the gate are shown in Plates 16

and 17 for the two spillway crest shapes. Data showing the effect of tail-

water elevation on discharge with flow over the gate are shown in Plates 18

and 19 for the two spillway crest shapes. It should be noted that with flow

over the gate, there was also some flow through the gaps between the end of

the gate and the piers and through the clearance between the gate and spillway

crest. Because the modeled gate-to-pier clearances of the type 2 and 3 design

structures differed by 3-1/2 in. (less than 3/16 in. in the model), there was

very little difference in the flow characteristics of each design.

18. The following flow conditions and equations were used to satisfy

the calibration data:

a. Free uncontrolled flow:

3/2Q = CLH , where C is a function of H

b. Submerged uncontrolled flow:

3/2Q = C1 LH where C 1 is a function of h/H

12

Page 17: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

c. Free uncontrolled flow (over the gate):

3/2Q = C L H , where C is a function of Hccc C C

d. Submerged uncontrolled flow (over the gate):

3/2Q C L H , where C is a function of h /HQ 1 Cclc cI cC

e. Free controlled flow:

Q = C LG 2gH , where C is a function of H and Gg o - - g g g o

f. Submerged controlled flow:

Q = C Lh 2gAH , where C is a function of h/0gs gs o

Symbols used in these equations are defined as follows:

Q = total discharge, cfs

L = net length of spillway crest, ft

H = gross head on spillway crest, ft

h = depth of tailwater above spillway crest, ft

L = net length of gate crest, ftc

H = gross head on gate crest, ftc

h = depth of tailwater above gate crest, ftc

G = gate opening, ft

g = acceleration due to gravity, ft/sec2

H = gross head on gate (H - 1/2G ), ftg0

6H = differential between gross head on spillway crest and depth of

tailwater referenced to spillway crest (H - h), ft

Effect of spillway crest

shape on discharge characteristics

19. Discharge coefficients for free uncontrolled flows over the spill-

way weir with various gross heads on the weir are shown for the two spillway

crest designs investigated in Plates 20 and 21. These data have a reasonable

degree of scatter and indicate that the shape of the spillway approach face

had very little effect upon the discharge characteristics of free uncontrolled

flows.

20. The effect of tailwater submergence for uncontrolled flow over the

spillway weir was determined by plotting the percent of submergence (h/H) ver-

sus a percent reduction in the free flow coefficient (CI/C) as shown in

13

Page 18: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Plates 22 and 23 for the two weir shapes. As those plots indicate, the C I/C

value approaches unity at an h/H value of about 0.6; thus free flow condi-

tions exist with values smaller than this. The data indicate that the shape

of the weir crest had little effect on the submerged uncontrolled flow

characteristics.

21. Discharge coefficients for free uncontrolled flow over the gate

with various heads on the gate crest are shown in Plates 24 and 25 for the two

spillway weir shapes. As expected, the spillway weir shape had no effect on

these discharge coefficients.

22. The effect of tailwater submergence for uncontrolled flow over the

gate is shown by the coefficients in Plates 26 and 27. Again, the spillway

weir shape had no effect on these coefficients.

23. Relations between the free controlled flow discharge coefficient

and gross head on the gate for various gate openings and the two spillway

crest designs are presented in Plates 28 and 29. These data indicate that the

shape of the spillway face and crest has little effect upon the discharge

characteristics of this type of flow. Discharge-head relations are presented

for free flow in Plates 30 and 31.

24. Submerged controlled flow discharge coefficients versus the ratio

of tailwater depth above the crest to gate opening for each spillway crest

design are shown in Plates 32 and 33. A comparison of these two plates indi-

cates that the shape of the spillway face and crest has no effect on the dis-

charge characteristics of submerged controlled flow within the limits

investigated.

25. It was concluded from the data obtained with the gate raised out of

the flow, with the gate submerged so that flow passed over the gate, and with

the gate raised to allow flow underneath, that the spillway weir shapes tested

had very little effect on discharge characteristics of the Marseilles Dam.

The data were used to construct plots of discharge versus tailwater elevation

for the normal upper pool elevation of 483.17 with flow underneath various

gate openings. These plots are shown in Plates 34 and 35. The same type of

plot with flow over the gates is shown in Plates 18 and 19.

Flow regimes

26. An analysis of the data was made to define the limits of each flow

regime and corresponding discharge equation. The results of efforts to dis-

tinguish between free and submerged uncontrolled flows over the spillway,

14

Page 19: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

shown in Plate 36, illustrate that in general, free uncontrolled flow becomes

submerged uncontrolled flow for tailwater submergences equal to or greater

than 60 percent.

27. The difference between free uncontrolled and submerged uncontrolled

flows with flow over the gate can be determined from Plate 37.

28. Plate 38 indicates that free and submerged controlled flows can be

distinguished by the degree of submergence.

29. To define the limits of free controlled and free uncontrolled

flows, tests were made with several gate openings and free flow tailwater con-

ditions in which the head on the weir and the discharge were decreased until

the nappe separated from the gate. Observations indicated that free con-

trolled flow became free uncontrolled flow when the ratio of H/G was equal0

to or less than 1.2.

30. Similar investigations for submerged flows indicated that submerged

controlled flows became submerged uncontrolled flows when the ratio of h/G0

was equal to or less than 1.0 for ratios of (H - h)/G less than 0.30

(Plate 39). In distinguishing between those flow regimes, it is to be noted

that for conditions of h/G less than 1.0, the flow may be either submerged0

uncontrolled, free uncontrolled, or free controlled, depending upon the value

of (H - h)/G . If (H - h)/G is less than 0.3, the flow is submerged un-0 0

controlled. If (H - h)/G is greater than 0.3 but less than 0.6, the flow0

is free uncontrolled. If (H - h)/G is greater than 0.6, the flow is free0

controlled.

Stilling Basin Performance

Type I spillway crest

31. Initial tests were concerned with the hydraulic performance of the

original (type 1) spillway crest (Plate 4) with gate openings of 2, 4, 5, 7,

and 9 ft and an upper pool elevation of 483.17. For each of these conditions

and tailwater depths ranging from minimum to maximum, the stilling basin ac-

tion was observed, the type of jump recorded, and velocities measured at a

point 1 ft above the exit channel bottom 27 ft downstream of the end sill.

Data on stilling basin performance below the original spillway (type 1) are

given in Plate 40.

15

Page 20: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Type 2 spillway crest

32. The hydraulic performance of the type 2 spillway crest (Plate 4)

was invebtigated with the same gate openings and upper pool elevation as for

type 1. Velocities were measured for each of these conditions and tailwater

depths ranging from minimum to maximum and the resulting jump recorded. Data

on stilling basin performance below the type 2 spillway are given in Plate 41.

The spillway crest shape had very little effect on stilling basin action and

velocities downstream from the structure.

33. As requested by the Rock Island District, the depth of flow enter-

ing the stilling basin dI and the tailwater depth d2 were measured at

minimum tailwater conditions for various gate openings. The depth of flow

entering the stilling basin dI and the depth of tailwater d2 were measured

as indicated in Figure 5. The d depth was measured 10 ft downstream of the

spillway crest above the toe of the spillway. The d2 depth was measured

46 ft downstream of the spillway crest center line, 1 ft upstream of the

stepped end sill. These values are tabulated in Table I for gate openings of

2, 4, 5, and 7 ft and 2, 5, 7, and 8 ft of submergence.

Gate Cable Loads and Vibrations

Original (type 1) design structure

34. The original designs for the spillway and submersible tainter gate

were described in paragraph 6; general dimensions are shown in Plate 3.

35. Initial tests were conducted to assure that the natural frequency

of the model cables was not in the range of the natural frequency of the ex-

citing forces measured in the model. The prototype cable natural frequency

was estimated by the R ck Island District to be 4.5 Hz.

36. Forces induced in the gate lifting cables by flow (a) under and

(b) over the subject gate were measured with a normal upper pool (el 483.17)

in combination with various tailwater elevations. The test procedure is de-

scribed in paragraph 10. A profile sketch and definitions of terms are pre-

sented in Plate 42. A sample oscillograph record and sample calculation are

presented in Plate 43. Test results are tabulated in Tables 2 and 3.

37. During tests an undular jump or "rooster tail" developed immedi-

ately downstream of the gate with several combinations of gate openings and

tailwater elevations with a normal upper pool (el 483.17) (Photo 3).

16

" ' I l lI

Page 21: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

i

cooa03

CL

w -

00

cc,-

17.

Page 22: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Vibrations of the gate with flow under the gate were recorded with these con-

ditions. The model test results indicated that the original (type 1) design

structure will likely permit the gate cables to be subjected to loads occur-

ring at a random frequency during normal operations with flow under small gate

opening3 due to the contact of the gate with flow (Photo 4). The magnitude of

these vibrations, however, is very small (less than 3 percent) compared to the

gate's weight. With flow over the type 1 design structure, the likelihood of

forces acting on the cables at a periodic frequency was indicated for essen-

tially all submergences and expected headwaters and tailwaters, as shown in

Table 3. The frequency of the induced forces (1.6-3.4 Hz) is considered un-

acceptably close to the natural frequency of the prototype lifting cables

(4.5 Hz). Because of the proximity of the frequency of the flow-induced loads

on the cables to the natural frequency of the prototype cables, the type 1

design structure (Plate 3) was considered unstable.

Type 2 design structure

38. The type 2 design structure consisted of the type 2 spillway crest

and the type I gate.

39. Forces induced in the gate lifting cables by flow (a) under and

(b) over the gate were measured with a normal upper pool (el 483.17) in com-

bination with various tailwater elevations. Test results are tabulated in

Tables 4 and 5.

40. The tests indicated that the type 2 design structure will likely

permit the gate cables to be subjected to loads occurring at a random fre-

quency during normal operations with flow under small gate openings due to

contact of the gate with flow. The magnitude of these vibrations, however, is

very small (less than 2 percent) compared to the gate's weight. With flow

over the type 2 design structure (Photo 5), the likelihood of forces acting on

the cables at a periodic frequency was indicated for gate submergences of up

to and including 6 ft. There was some reduction in the frequency and magni-

tude of the periodic vibrations with the type 2 design structure. Loads began

to occur at a random frequency for gate submergences of 7 and 8 ft (fully sub-

merged). The incidence of the reported vibration is primarily attributable to

the large gap at the sides of the gate as evident in comparing the results

from tests of the type 2 design with those of the type 3 design. The side

seal gap was decreased to eliminate the vibrations with flow over the gate.

18

Page 23: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Type 3 design structure

41. The type 3 design structure incorporated the type 2 design spillway

crest and the type 2 design gate (extension of the gate end shields to de-

crease the gate-to-pier clearance from 4 in. to 1/2 in., while maintaining a

gate-to-sill clearance of 1 in.).

42. Forces induced in the gate lifting cables by flow (a) under and

(b) over the gate were measured with a normal upper pool (el 483.17). The

results are tabulated in Tables 6 and 7.

43. The tests indicated that the type 3 design structure will likely

permit the gate cables to be subjected to loads occurring at a random fre-

quency during normal operations with flow under small gate openings due to

contact of the gate with flow. The magnitude of these vibrations, however,

was very small (about I percent) compared to the gate's weight. With flow

over the type 3 design structure, the forces acting on the cables occurred at

a random frequency for submergences of 2, 5, 6, and 7 ft. The gate cables

were not subjected to any vibrations for most gate submergences.

44. Because of the likelihood of the occurrence of random vibrations

during normal operations of the gate with flow (a) under or (b) over the gate,

the US Army Engineer Waterways Experiment Station (WES) suggested a brace to

physically hold or "lock" the gate into position. A friction shoe (Plate 44)

that could be installed on each side of the gate between the gate and pier was

designed by the Rock Island District and was tested in the model. Although

tests with the friction shoe indicated essentially no occurrence of vibra-

tions, there is some doubt that these results are anything but qualitative be-

cause the friction in the model supplied by the friction shoe cannot be di-

rectly scaled to simulate prototype friction. The value of a friction shoe is

that it provides a factor of safety in the event that vibrations do occur.

Therefore, the type 3 design structure with a friction shoe installed on each

side of the gate was recommended for prototype construction. The Rock Island

District, however, opted not to include the friction shoe in the construction

contract for the submersible tainter gates with the following rationale. The

total amplitude, A , of the highest load fluctuation measured in the modelPwas 1,500 lb. Only one-half of that load fluctuation would have to be over-

come by friction to negate the exciting forces and prevent vibration

(Plate 43). One-half of that, or 375 lb, would have to be overcome by fric-

tion on each side of the gate. A conservatively low estimate of the prototype

19

Page 24: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

trunnion friction on each side of the prototype gate is 600 lb. The side seal

friction at each side of the prototype is estimated at 3,000 ib, giving a sig-

nificant factor of safety. In addition, the load fluctuations in the model

all acted at random frequencies rather than at periodic frequencies; thus, the

deflection in the cables will not build resonantly. The first of the proto-

type gates v3s put in operation in January 1987, and the last (eighth) gate

was put in operation in March 1988. All of the prototype submersible tainter

gates are operating vibration free.

Type 4 and 5 design structures

45. The type 4 design structure incorporated the type 2 design spillway

crest shape and the type 2 design gate (extension of the gate end shields to

decrease the gate-to-pier clearance from 4 in. to 1/2 in., while maintaining a

gate-to-sill clearance of 1/2 in.). The type 5 design structure differed from

the type 4 design structure only in the gate-to-sill clearance. The gate-to-

sill clearance of the type 5 design structure was 3 in. Cursory tests were

conducted on these two designs to examine the relationship between gate-to-

sill clearance and the tendency for periodic or larger load fluctuations in

the gate cables. Because the 1/2-in. gate-to-sill clearance was so small (in

the model less than 1/32 in.), tests to determine the effect on the occurrence

of vibrations are not considered valid. There was an increase, however, in

the occurrence, magnitude, and frequency of the load fluctuations when the

gate-to-sill clearance was increased to 3 in. (with the type 5 design struc-

ture). Therefore, it was concluded that the increased gate-to-sill clearance

increased the tendency for larger periodic vibrations based on these tests.

Further study, however, is required to examine specific factors that affect

vibrations of submersible tainter gates.

46. The tendency and frequency of vibrations increased at the smaller

gate submergences (1-3 ft) and lower tailwater elevations (el 470-472). The

smaller gate submergences produced unstable conditions because of the almost

equal amounts of flow under and over the gate. As the tailwater increased,

the flow under the gate (between the gate and sill) decreased and the magni-

tude and frequency of vibrations decreased.

20

Page 25: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

PART IV: CONCLUSIONS

47. Results of tests to determine discharge characteristics of the

Marseilles Dam with two spillway crest designs Indicated six possible flow

conditions, which can be satisfied by the following equations:

a. Free uncontrolled flow (over the spillway):

Q = CLH3 /2 , where C is a function of H as shown in

Plates 20 and 21.

b. Submerged uncontrolled flow (over the spillway):

3/2Q = C1LH , where C I is a function of h/H as shown inPlates 22 and 23.

c. Free uncontrolled flow (over the gate):

3/2Q = C L H , where C is a function of H as shown in

Plates 24 and 25.

d. Submerged uncontrolled flow (over the gate):

3/2Q = C L H , where C is a function of h /H as shown

in Plates 26 and 27.

e. Free controlled flow:

Q=CLG Vg , where C is a function of H and C as

shown in Plates 28 and 29.

f. Submerged controlled flow:

Q = C Lh V2gAH , where C is a function of h/G as showngs gs 0

in Plates 32 and 33.

The spillway crest shape had little or no effect on the discharge characteris-

tics of the structure.

48. Stilling basin performance tests and velocities measured downstream

from the basin Indicated that the spillway crest shape had little effect on

basin performance.

49. Testing of the type 3 design structure (a 2.5-ft-broad horizontal

sill preceded by a IV on 1.2H sloping face and a gate with 1/2-in. gate-to-

pier clearance) indicated the gate cables to be subject to load fluctuations

occurring at a random frequency during normal operations with flow under small

21

Page 26: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

gate openings due to contact between the gate and the water surface. The

r gnitude of these vibrations, however, was only about I percent of the gate's

total weight. Based on the gate's performance in the prototype, mathemati-

cally speaking, the prototype cables would not detect these load fluctuations

because these vibrating forces are less than the combination of the prototype

trunnion and side seal friction. The forces acting on the cables occurred at

a random frequency for gate submergences of 2, 5, 6, and 7 ft with flow over

the gate. There were no periodic vibrations.

50. Because of the likelihood of the occurrence of random vibrations

during normal operations of the gate with flow (a) under or (b) over the gate,

a friction shoe between the gate and pier was tested in the model. Although

tests with the friction shoe indicated essentially no occurrence of random or

periodic vibrations, there is some doubt that these results are anything but

qualitative because the friction in the model supplied by the friction shoe

cannot be directly scaled to simulate prototype friction. The value of the

friction shoe tests is the indication that such a "dogging" device can be

designed and is useful in eliminating vibrations that my occur. The shoe

introduces a factor of safety for dampening out the random vibrations of the

Marseilles gate cables. Therefore, the type 3 design structure with friction

shoe was recommended by WES for prototype construction. The Rock Island Dis-

trict elected not to use the friction shoe, which could have been used if vi-

bration was noted in the prototype. However, the magnitude of the exciting

forces was small compared to the total cable loid and the trunnion and side

seal friction. The District reports that the eight new Marseilles Dam proto-

type submersible tainter gates are in operation without any noticeable

vibration.

51. Tests indicated that at smaller gate submergences and lower

tailwater elevations, vibrations were more likely to occur at a periodic fre-

quency. Further, a direct relationship was established between increased

gate-to-sill clearance and an increase in magnitude and frequency of gate

vibrations. As the gate-to-sill clearance increased, the tendency for

increased and more periodic vibrations also increased.

22

Page 27: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 1

d1 and d2 Values

Type 2 Spillway Crest

Pool El 483.17, Tailwater El 470.00

G 0Qd 1 d 2

ft* cfs ft ft

2 2,700 6.9 8.2

4 4,100 7.1 9.4

5 5,000 7.8 10.0

7 6,320 10.3 10.7

-2 500 7.5 7.7

-5 1,800 8.2 8.6

-7 3,200 8.4 9.7

-8 3,850 9.2 10.6

* Negative values represent the amount of gate submergence.

Page 28: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 2

Gate Cable Loads and Vibrations

Type I (Original) Design Structure

Flow Under Gate

G F2 3 F4 F5 F5G TW 3 4 max min f Apft EL lb lb lb lb lb Hz lb

1 470 0 115,300 153,200 37,900 36,400 RANDOM 1,5001 473 5,200 110,100 164,800 54,700 54,100 RANDOM 6001 474 7,400 107,900 161,900 54,000 54,000 RANDOM 0

2 470 0 115,300 156,100 40,800 39,300 RANDOM 1,5002 472 800 114,500 166,200 51,700 51,100 RANDOM 6002 474 5,200 110,100 164,800 54,700 54,100 RANDOM 6002 475 7,400 107,900 141,500 33,600 33,000 RANDOM 600

4 470 0 115,300 156,200 40,900 39,400 RANDOM 1,5004 472 0 115,300 164,800 49,500 48,000 RANDOM 1,5004 474 800 114,500 163,300 48,800 47,300 RANDOM 1,5004 476 5,200 110,100 156,200 46,100 44,600 RANDOM 1,500

5 470 0 115,300 162,000 46,700 43,700 RANDOM 3,0005 474 0 115,300 161,800 46,500 45,000 RANDOM 1,5005 478 7,400 107,900 161,500 53,600 52,700 RANDOM 900

5 480 10,100 105,200 157,700 52,500 51,600 RANDOM 900

6 470 0 115,300 163,300 48,000 45,400 RANDOM 2,6006 474 0 115,300 161,800 46,500 45,000 RANDOM 1,5006 476 800 114,500 163,300 48,800 47,900 RANDOM 900

6 480 9,100 106,200 161,800 55,600 55,600 0 0

7 470 0 115,300 163,800 48,500 47,700 RANDOM 800

7 473 0 115,300 162,100 46,800 46,000 RANDOM 8007 476 2,900 112,400 162,000 49,600 48,800 RANDOM 8007 479 5,200 110,100 164,700 54,600 53,700 RANDOM 9007 481 9,100 106,200 161,600 55,400 53,900 RANDOM 1,500

8 470 0 115,300 163,300 48,000 46,500 RANDOM 1,500

8 473 0 115,300 166,300 51,000 51,000 0 08 479 2,900 112,400 158,900 46,500 46,500 0 0

8 482 9,100 106,200 141,300 35,100 35,100 0 0

9 470 0 115,300 164,900 49,600 46,600 RANDOM 3,0009 472 0 115,300 163,300 48,000 46,500 RANDOM 1,5009 480 2,900 112,400 163,300 50,900 50,900 0 09 483 9,100 106,200 144,300 38,100 38,100 0 0

(Continued)

Note: See Plates 42 and 43 for definitions of symbols. Dry weight of gateF = 115,300 lb.

Page 29: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 2 (Concluded)

o F2 F3 F4 F5 F5G TW F F max min f Ap

ft EL lb lb lb lb lb Hz lb

10 470 0 115,300 163,300 48,000 46,500 RANDOM 1,500

10 472 0 115,300 167,800 52,500 51,000 RANDOM 1,500

10 478 0 115,300 166,300 51,000 51,000 0 0

10 483 7,400 107,900 147,300 39,400 39,400 0 0

Page 30: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 3

Gate Cable Loads and Vibrations

Type 1 (Original) Design Structure

Flow Over Gate

GateSubmer- F F F F5 F5gence TW 2 3 4 max min f

ft EL lb lb lb lb lb Hz lb

1 470 2,900 112,400 132,900 20,500 19,100 3.4 1,4001 471 5,200 110,100 127,000 16,900 15,500 3.4 1,400

2 470 5,200 110,100 141,600 31,500 30,100 3.1 1,4002 472 9,100 106,200 132,900 26,700 23,800 2.7 2,9002 473 10,100 105,200 130,000 24,800 22,800 2.7 2,0002 475 11,300 104,000 128,500 24,500 22,500 2.2 2,000

3 470 7,400 107,900 144,600 36,700 33,700 2.9 3,0003 472 10,100 105,200 138,700 33,500 29,500 2.5 4,0003 474 11,300 104,000 145,800 41,800 38,800 2.5 3,0003 476 12,450 102,850 131,400 28,550 24,550 2.5 4,000

4 470 9,100 106,200 141,700 35,500 31,500 2.5 4,0004 472 10,700 104,600 143,100 38,500 34,500 2.5 4,0004 474 11,850 103,450 138,700 35,250 32,250 2.2 3,0004 476 13,000 102,300 124,200 21,900 18,900 2.2 3,000

5 470 10,100 105,200 147,100 41,900 38,100 2.2 3,8005 472 11,300 104,000 145,900 41,900 38,300 2.2 3,6005 475 13,000 102,300 134,300 32,000 28,500 1.8 3,5005 478 14,800 100,500 113,800 13,300 9,900 1.8 3,400

6 470 10,700 104,600 144,400 39,800 32,600 1.6 7,2006 472 11,850 103,450 132,800 29,350 25,850 2.0 3,5006 476 14,200 101,100 110,800 9,700 8,100 RANDOM 1,600

7 470 11,300 104,000 154,600 50,600 47,100 2.0 3,5007 472 12,450 102,850 165,000 62,150 56,250 2.0 5,9007 476 14,800 100,500 117,600 17,100 11,200 I.P 5,9007 477 15,300 100,000 109,500 9,500 8,100 1.8 1,400

8 470 11,850 103,450 122,700 19,250 16,250 RANDOM 3,0008 473 13,600 101,700 122,700 21,000 15,100 RANDOM 5,9008 478 15,300 100,000 58,300 -41,700 -41,700 0 08 483 15,300 100,000 49,700 -50,300 -50,300 0 0

Note: See Plates 42 and 43 for definitions of symbols. Dry weight of gateF I = 115,300 lb.

Page 31: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 4

Gate Cable Loads and Vibrations

Type 2 Design Structure

Flow Under Gate

G F 2 F3 F4 F F5Ao TW 2 3 4 max min f Ap

ft EL lb lb lb lb lb Hz lb

1 470 0 115,300 140,100 24,800 24,000 RANDOM 8001 473 5,200 110,100 147,400 37,300 37,300 0 01 474 7,400 107,900 135,700 27,800 27,800 0 0

2 470 0 115,300 158,900 43,600 42,800 RANDOM 8002 472 800 114,500 148,800 34,300 34,300 0 02 474 5,200 110,100 148,800 38,700 38,700 0 02 475 7,400 107,900 141,600 33,700 33,700 0 0

4 470 0 115,300 134,300 19,000 17,500 RANDOM 1,5004 472 0 115,300 141,600 26,300 24,800 RANDOM 1,5004 474 800 114,500 140,100 25,600 24,100 RANDOM 1,5004 476 5,200 110,100 137,200 27,100 25,600 RANDOM 1,500

5 470 0 115,300 134,300 19,000 17,500 RANDOM 1,5005 474 0 115,300 141,600 26,300 24,800 RANDOM 1,5005 478 7,400 107,900 137,200 29,300 27,800 RANDOM 1,5005 480 10,100 105,200 119,600 14,400 12,200 RANDOM 2,200

6 470 0 115,300 141,700 26,400 25,700 RANDOM 7006 474 0 115,300 141,600 26,300 25,600 RANDOM 7006 476 800 114,500 137,300 22,800 22,100 RANDOM 7006 480 9,100 106,200 129,700 23,500 21,300 RANDOM 2,200

7 470 0 115,300 135,800 20,500 19,700 RANDOM 8007 473 0 115,300 134,300 19,000 18,200 RANDOM 8007 476 2,900 112,400 134,000 21,600 20,800 RANDOM 8007 479 5,200 110,100 128,300 18,200 17,400 RANDOM 8007 481 9,100 106,200 116,800 10,600 9,800 RANDOM 800

8 470 0 115,300 127,000 11,700 10,200 RANDOM 1,5008 473 0 115,300 124,000 8,700 8,000 RANDOM 7008 479 2,900 112,400 124,000 11,600 10,900 RANDOM 7008 482 9,100 106,200 105,000 -1,200 -1,200 0 0

9 470 0 115,300 128,500 13,200 11,800 RANDOM 1,4009 472 0 115,300 124,100 8,800 7,400 RANDOM 1,4009 480 2,900 112,400 127,000 14,600 13,200 RANDOM 1,4009 483 9,100 106,200 115,100 8,900 8,900 0 0

(Continued)

Note: See Plates 42 and 43 for definitions of symbols. Dry weight of gateF l = 115,300 lb.

, I

Page 32: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 4 (Concluded)

G F2 F3 F 5 F5o TW 2 3 4 max min f Ap

ft EL lb lb lb lb lb Hz lb

10 470 0 115,300 127,200 11,900 10,400 RANDOM 1,50010 472 0 115,300 128,500 13,200 13,200 0 010 478 0 115,300 127,000 11,700 11,700 0 010 483 7,400 107,900 113,900 6,000 6,000 0 0

Page 33: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 5

Gate Cable Loads and Vibrations

Type 2 Design Structure

Flow Over Gate

GateSubmer- F F F F5 Fmgence TW 2 3 4 max mi f p

ft EL lb lb lb lb lb _z lb

1 470 2,900 112,400 134,300 21,900 20,500 3.4 1,4001 471 5,200 110,100 128,500 18,400 17,000 3.4 1,400

2 470 5,200 110,100 140,200 30,100 28,700 3.1 1,4002 472 9,100 106,200 138,700 32,500 29,600 2.7 2,9002 473 10,100 105,200 138,600 33,400 30,500 2.5 2,9002 475 11,300 104,000 128,400 24,400 23,000 2.0 1,400

3 470 7,400 107,900 139,100 31,200 29,000 2.9 2,2003 472 10,100 105,200 138,400 33,200 31,000 2.5 2,2003 474 11,300 104,000 138,400 34,400 33,000 2.3 1,4003 476 12,450 102,850 125,250 22,400 20,200 2.3 2,200

4 470 9,100 106,200 138,700 32,500 29,600 2.7 2,9004 472 10,700 104,600 138,300 33,700 32,300 2.5 1,4004 474 11,850 103,450 132,800 29,350 27,950 2.4 1,4004 476 13,000 102,300 125,600 23,300 20,400 2.4 2,900

5 470 10,100 105,200 143,000 37,800 36,400 2.0 1,4005 472 11,300 104,000 146,000 42,000 40,600 1.9 1,4005 475 13,000 102,300 127,300 25,000 23,600 1.7 1,4005 478 14,800 100,500 124,100 23,600 22,200 1.6 1,400

6 470 10,700 104,600 151,600 47,000 45,600 2.0 1,4006 472 11,850 103,450 156,200 52,750 51,350 2.0 1,4006 476 14,200 101,100 148,700 47,600 46,900 RANDOM 700

7 470 11,300 104,000 158,000 54,000 52,600 RANDOM 1,4007 472 12,450 102,850 163,300 60,450 59,050 RANDOM 1,4007 476 14,800 100,500 140,200 39,700 38,300 RANDOM 1,4007 477 15,300 100,000 132,000 32,000 30,600 RANDOM 1,400

8 470 11,850 103,850 127,400 23,550 20,650 RANDOM 2,9008 473 13,600 101,700 119,300 17,600 16,200 RANDOM 1,4008 478 15,300 100,000 114,200 14,200 14,200 0 08 483 15,300 100,000 103,500 3,500 3,500 0 0

Note: See Plates 42 and 43 for definitions of symbols. Dry weight of gateF = 115,300 lb.

1

Page 34: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 6

Gate Cable Loads and Vibrations

Type 3 Design Structure

Flow Under Gate

G TW 2 F3 F4 5 5 pft EL lb lb lb lb lb Hz lb

1 470 0 115,300 132,700 17,400 16,600 RANDOM 8001 473 5,200 110,100 129,800 19,700 19,700 0 01 474 7,400 107,900 129,800 21,900 21,900 0 0

2 470 0 115,300 128,400 13,100 12,300 RANDOM 8002 472 800 114,500 131,300 16,800 16,800 0 02 474 5,200 110,100 125,500 15,400 15,400 0 02 475 7,400 107,900 124,000 16,100 16,100 0 0

4 470 0 115,300 115,300 0 -1,500 RANDOM 1,5004 472 0 115,300 118,200 2,900 1,400 RANDOM 1,5004 474 800 114,500 125,500 11,000 9,500 RANDOM 1,5004 476 5,200 110,100 129,000 18,900 17,400 RANDOM 1,500

5 470 0 115,300 123,900 8,600 7,100 RANDOM 1,5005 474 0 115,300 125,400 10,100 8,600 RANDOM 1,5005 478 7,400 107,900 126,700 18,800 17,300 RANDOM 1,5005 480 10,100 105,200 115,300 10,100 10,100 0 0

6 470 0 115,300 125,600 10,300 9,500 RANDOM 8006 474 0 115,300 128,400 13,100 12,300 RANDOM 8006 476 800 114,500 127,000 12,500 11,700 RANDOM 8006 480 9,100 106,200 113,600 7,400 7,400 0 0

7 470 0 115,300 131,200 15,900 15,100 RANDOM 8007 473 0 115,300 131,200 15,900 15,100 RANDOM 8007 476 2,900 112,400 131,200 18,800 17,300 RANDOM 1,5007 479 5,200 110,100 131,300 21,200 19,700 RANDOM 1,5007 481 9,100 106,200 131,300 25,100 24,300 RANDOM 800

8 470 0 115,300 131,300 16,000 14,500 RANDOM 1,5008 473 0 115,300 136,400 21,100 19,600 RANDOM 1,5008 479 2,900 112,400 133,200 20,800 20,000 RANDOM 8008 482 9,100 106,200 131,300 25,100 25,100 0 0

9 470 0 115,300 132,000 16,700 15,200 RANDOM 1,5009 472 0 115,300 131,500 16,200 14,700 RANDOM 1,5009 480 2,900 112,400 133,400 21,000 20,200 RANDOM 8009 483 9,100 107,900 103,500 -4,400 -4,400 0 0

(Continued)

Note: See Plates 42 and 43 for definitions of symbols. Dry weight of gateFI = 115,300 lb.

" ' ' i l l I ll1

Page 35: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 6 (Concluded)

G F2 F3 F4 5 F5ft EL lb lb lb lb lb Hz lb

10 470 0 115,300 132,100 16,800 15,300 RANDOM 1,500

10 472 0 115,300 131,400 16,100 15,300 RANDOM 800

10 478 0 115,300 126,000 10,700 10,700 0 0

10 483 7,400 107,900 123,000 15,100 15,100 0 0

Page 36: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Table 7

Gate Cable Loads and Vibrations

Type 3 Design Structure

Flow Over Gate

GateSubmer- F F F F5 F Agence TW 2 3 4 max mn f p

ft EL lb lb lb lb lb Hz lb

1 470 2,900 112,400 137,100 24,700 24,700 0 01 471 5,200 110,100 132,800 22,700 22,700 0 0

2 470 5,200 110,100 128,400 18,300 17,500 RANDOM 8002 472 9,100 106,200 131,300 25,100 25,100 0 02 473 10,100 105,200 128,400 23,200 23,200 0 02 475 11,300 104,000 115,200 11,200 11,200 0 0

3 470 7,400 107,900 123,900 16,000 16,000 0 03 472 10,100 105,200 121,000 15,800 15,800 0 03 474 11,300 104,000 113,700 9,700 9,700 0 03 476 12,450 102,850 112,850 10,000 10,000 0 0

4 470 9,100 106,200 156,100 49,900 49,900 0 04 472 10,700 104,600 148,800 44,200 44,200 0 04 474 11,850 103,450 144,400 40,950 40,950 0 04 476 13,000 102,300 138,500 36,200 36,200 0 0

5 470 10,100 105,200 141,500 36,300 36,300 0 05 472 11,300 104,000 132,700 28,700 27,200 RANDOM 1,5005 475 13,000 102,300 122,500 20,200 20,200 0 05 478 14,800 100,500 120,000 19,500 19,500 0 0

6 470 10,700 104,600 126,900 22,300 21,500 RANDOM 8006 472 11,850 103,450 118,100 14,650 14,650 0 06 476 14,200 101,100 107,900 6,800 6,800 0 0

7 470 11,300 104,000 116,100 12,100 12,900 RANDOM 8007 472 12,450 102,850 118,250 15,400 15,400 0 07 476 14,800 100,500 83,000 -17,500 -17,500 0 07 477 15,300 100,000 78,700 -21,300 -21,300 0 0

8 470 11,850 103,450 150,400 46,950 46,950 0 08 473 13,600 101,700 138,600 36,900 36,900 0 08 478 15,300 100,000 131,000 31,000 31,000 0 08 483 15,300 100,000 61,300 -38,700 -38,700 0 0

Note: See Plates 42 and 43 for definitions of symbols. Dry weight of gateF = 115,300 lb.

Page 37: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

SAW-

mist-

-d-c

Page 38: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

cai

4co

cc

-4

cc)$-

4J

-

444

cli

0

r4

Page 39: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

IIn&

-7A-

C-,-

--- 4ml

LL-

Page 40: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

-o

'-4

4

(Vca

-4

46;

Page 41: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

4-J

c-

-z

4-4

cuj

Page 42: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

f,0

WALKWAYKWA

SCLER

8'. ~ PAT 1NE AE

Page 43: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Ix

~uJIx

mZu1

T ~040occ,

CC.L

CcC

-~1 0

C h Zr

PLATENIP2

Page 44: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

NV-ld I-CNOINNnhlJ.

-0.

*~LL 0 5~~ w

j..O-I-2 T 7

w -a

4-~14-

ao

PLATE3

Page 45: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

V)

'aa

41 a zo

I.' aN Z )

C,)

ww

w

41 z -J01 w

V) 0w (n

to wL C14- 0L N .

C O C L I l 0L

La-

.1 I.-

C141

LI'a

00 C

PLATE L4

Page 46: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

S=CLHa L

FREE UNCONTROLLED FLOW SUBMERGED UNCONTROLLED FLOW

() o ... =c ccH_ h c0 0 cHkc

FREE UNCONTROLLED FLOW SUBMERGED UNCONTROLLED FLOW(OVER THE GATE)* (OVER THE GATE)*

Q C 9L G 0,' -2 -HgQ=C CgsLh i2gAH

FREE CONTROLLED FLOW SUBMERGED CONTROLLED FLOW

NOTE. FLOW OVER GATE IS UNCONTROLLED

F LOW BECAUSE GATE ACTS AS AN

OGEE WEIR FIXED AT SEVERAL

ELEVATIONS.

SIX FLOW REGIMES

PLATE 5

Page 47: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

Z Z w.

0 0.

wj I

CU. cflC UL U

in zz

LA.4

0 0

-J-J

R -J-D

000z

00

4c.II>aw

GON iJNOUJVA313 100d H~ddfl

PLATE 6

Page 48: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

(I)

~0 w

0U CL 49I

ImI

LUNo N0A L 0 L.Lz

V) 0

In-

0 w c

LL

Cd,

I0Y

o c0 wco ro

GAO I:INIV 310 83dd

PLATE7

Page 49: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

(-

ZIL0 aa

OwO-jL--

W CC 4 I-

0

LU-

-j 0

V) LL L

uj.0W

z >

ZILLI-

C',, 2

(I, U>

a c'5

0 Ile

000

OADON li 'N0I1VA313 100d U~ddfl

PLATE 8

Page 50: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

OIL

'U>.

IZ 4 ILn0OI 'Up u -

a: -L

uJ b

w

I.-00>zU

IL

00

0

t -- I

-N o faw

GAO -JNUA313-00 3d

PLTo

Page 51: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

-AA

LL L

~~0 -

L

UJzo

00

acLU-

0 0 z

LLUF-J0L

Cl) LU

t9-

01

0 0

o ii

UU-

04

00 r 0

OAAON U lNOIIVA313 lO0d H3ddfl

PLATE 10

Page 52: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

I--

(3 u

(0 i.

w I-a; LL 0 f 3

z

(a 0 0

% uu

0 0. -J

0

r- Z0U

oI-j

C'))

Ip

COADN IA'NOIIVA313 100d E1ddfl

PLATE 1

Page 53: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

u-

U. 4>Zo0oI

r- -i

9, c cuu

0-- W

Co 0

00

N LP Z

0 9,00, 1-

0. ->LU

ILL-

LIt

0 co-1

0ANiANlV31 10 3d

PLT 12,

Page 54: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

4c -u0zcc,

OwOZ'U. ui -

Z a ~ILO0 .-

WUJZ

, ' 0

w

o

ww

00 CO

LL CI-

C>0-o

LL m

I I I LI-O

OACi O N~3lOdUdf

PLTE1

Page 55: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0 -o40 Zc

4.5 E-ZOU. 4 >ZOWOC30-u 3

wU i-j

2 CcNL

OD

2! I-

D U-

00

0 jL

00

00>

N 0 o00 0 r 0

aq w w

OASON IA NOIIVA313 100d 83ddfl

PLATE 14

Page 56: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

40wLwU-

U-L

LC) Zw<lCo o-0) 0

w <rr0

0

u0 L

<r <

-J 0 0o o L

00

t I

clcmw

LL <L

u 0-oz 0

00

co co

GAON iA'N0liJA313 100d 83ddfl

PLATE 15

Page 57: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

483

481

> 479zLI.

z0P: 477

w-10o 475

NOTE: FLOW OVER ONE SUBMERSIBLE TAINTER GATE473

471

469 I0 1 2 3 4 5 6

DISCHARGE, THOUSANDS OF CFS

DISCHARGE RATING CURVEFOR FREE FLOW

OVER GATETYPE 1 SPILLWAY CREST

PLATE 16

Page 58: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

,I I II I I l l

,0\ b ,

483 -

481

> 479

z

477

w,-

o,.00 475

NOTE: FLOW OVER ONE SUBMERSIBLE TAINTER GATE473

471

469 II I I I0 1 2 3 4 5 6

DISCHARGE, THOUSANDS OF CFS

DISCHARGE RATING CURVEFOR FREE FLOW

OVER GATETYPE 2 SPILLWAY CREST

PLATE 17

Page 59: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

LL 0 >

LL~ >~wLM ui

,*U z z Z 0 4<U 1 w Z w z jZ

<D a (D 0 0 0 1

Wr LI LI- LI u u r C

.4J mI LI 2 1LeL

z~ in~ -D oio C

W c-oC/4

00a: i

0D >

LUO

z0 0<00Cc 0o. U.

0

> ~ ~~VDI

PLT 18

Page 60: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

LUJ

U

U. 0 0

U. >

Lu

0 4 0

wu LUJ wu L w LU Uu

< z z z0 wu Lu wu wu L

cr 0 C.D 0 ( C.9wu Lu Lu uj LU W LU

zz

LL U. F-. LA- LL-- L I U.

(V) r- C; C

cc 4 0

m> wD -i

U) OD W

z w

Lu

0-J

0 (-

00

zLL*CRV 13 100d 83ddfl VbV4U0N

u~ t c iC C4J cqJ

PLATE 19

Page 61: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0

I-z 0

ini

x wJ

i CN IL l-

00

-- 11

I. I

LU LU

00

0 LL

LU

z

0(z,<oww

u-cn

0 ~ wT

0

J CD

3 iN301JA33 39HVHOSICI MOI 011 O11OUILN03Nf 33:

PLATE 20

Page 62: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0

LL 1Lh..

wZU cc

o-

OiU.j

zu

0 L

0 Lu L

o 0

LL

0 0

o (0o -JJ

0 3:

00

0 I I('4 -x

0 cn

D ±NIDW3 ~UVH3IO ~ldOr11ULN3Nf ~0

PLAE 2

Page 63: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

CLI C= CCC.3

C3

'02c-

0.

j ~0 a =W

c00

co

o0u.I

c0

0 (0 0

-~~~ 0 0W

1-4 413 AbM11dS HJ. O O3H S0~ C.

H4 83M AVMISd 3HAO6 N O1V1I SSOb HidL

PI ATE 22

Page 64: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

-JLA-

COD)

LUL

T, = =

0 C.LLI 0 .

= IccCi

LLj

cYI

0

0-J L

o L

z 00 zz 0

~LL

U-j

D tD 0

0H UiMAVA11IS 3H NOO~H SOUHI~~~~~~~ML AVcISrOV U LV 1bi1 ~~

PLT 23

Page 65: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0

0L

S...

D0 C

w es 0

w SCD-

z U

wO 0 L

0ow U

0-

0z

10

0

'3 I11ID:13OD 3ELSVHOSiaM01J cfl1OLLL8NOONr1 33~

PLATE 24

Page 66: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0

--

0)jU.,

U C

cc) :)

ZLU0

00

0- 0

LLr L

z Z)ca x

0 Q*U 0

0 0i

* 0* 00

zz ccI I

'3 L N3101=1h100 308VHOSIOMO-13 03-1-1ONOONfl 33:

PLATE 25

Page 67: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0-JL-

(noz~ 0)

Z'-iLL

O)Z cr -1

<CD,

CU)

w1 0

L) I

LU~ JZw

Ow wu

060~j isJ ~LL

zj /

o0

00J

I ow

Z zo

Iz0 C- 0 0z0 r,

H S3bO 31VE) 3HI NO 0V3H tS~jdE mL

NI S3HIC 31V!D 3Hi 3AOBV 831VMIIVI -AO Hld3C) U

PLATE 26

Page 68: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0.jL-

wJw

(JZ cr -

LUw(.

w Jcoo

00

U) 0u

a) 6

U) () U

OZ LL 00

0 F- . W u

w. 0 E

0 cI

LL o- o 6 6 6

0 w

0SU CiN CC1 NOOVHSSzSU ZLV 0H A8 iiMI1d l3

PLT 27

Page 69: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0.900

0.850 - G£ GATE

SYMBOL OPENING, FT& 20 3

om 0.800 0 4Cd U 5

I- 60 0 70 8U.. r 9

LL

o 0.750

ct

IS

0.700

O 0

-J

o 0.650I-

0Uui

U. 0.600

Q = C9 L Go 2%rg Hg

0.550

NOTE: FLOW THROUGH ONE 60-FT-WIDESUBMERSIBLE TAINTER GATE

0.500 I I I I I I I I I I I 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14

GROSS HEAD ON GATE Hg, FT

DISCHARGE COEFFICIENTSFOR FREE CONTROLLED FLOW

TYPE 1 SPILLWAY CREST

PLATE 28

Page 70: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0.900

0.850 - A A A

0.800I-.w

LLL-w

o 0.750 * *0Ip w W w

QLU

(.D

50.700

0--J

00.650z

ui i

w, - • • - -- - -

.L 0.600

A ATE

SYMBOL OPENING, FTNOTE: FLOW THROUGH ONE 60-FT-WIDE & 2

SUBMERSIBLE TAINTER GATE 30.550 U 4

* 56

O=Cg LG O VgHg 0 70 8O 9

0 .500 I I I I I I I I I I I

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

GROSS HEAD ON GATE Hg, FT

DISCHARGE COEFFICIENTSFOR FREE CONTROLLED FLOW

TYPE 2 SPILLWAY CREST

PLATE 29

Page 71: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

100

8060

L. 5040 GATE OPENINGS, FT

u 30 " - 7

.9! 2345618920

_j

- 108a-

z0 6o 5uj 4 -

xu,cn 3 -

0n- 2

1 I ,I I f I f l of I I I a J J I II I l !

0.1 0.2 0.30.4 0.60.81.0 2 3 4 5 6 7 10 20 30 4050 70 100DISCHARGE, THOUSANDS OF CFS

EL 469.85

TYPE 1 SPILLWAY CREST

DISCHARGE-HEAD RELATIONFOR FREE FLOW

TYPE 1 SPILLWAY CREST

PLATE 30

Page 72: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

100

70'-60

40 -GATE OPENINGS, FT

j 30 -7o 2 345689

346820

- 10"' 8z

o 6o 5

wi 4

LI) 3

0cr 2

0.1 0.2 0.3 0.4 0.6 0.81.0 2 3 4 5 678910 20 30 40 50 80 100

DISCHARGE, THOUSANDS OF CFS

FLOW H4N.EL 469.8

TYPE 2 SPILLWAY CREST

DISCHARGE-HEAD RELATIONFOR FREE FLOW

TYPE 2 SPILL WAY CREST

PLATE 31

Page 73: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

10.0 -9.08.0 -

7.0 -

6.0 -

5.0 -

4.0 -

. 3.0 •

UJ 2.0

. 1.0

co z oJ .9 _0 0.8

cr 0.7 -

-. 0.6 -

0.5

LL 0.4 -00

0.90.1 I

0.1 0.2 0.3 0.4 0.50.60.70.8 1.0

SUBMERGED CONTROLLED FLOW DISCMARGECOEFFICIENT C g,

DISCHARGE COEFFICIENTSFOR SUBMERGED CONTROLLED FLOW

TYPE 1 SPILLWAY CREST

PLATE 32

• • . i l I I

Page 74: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

10.0 -9.0 -8.0 -7.0 -

6.0 -

5.0 -

0 4. -

I-0LL 3.0 -

wCc

2.0> 2.0

W 0.

CL 0.8 -0wu u 0.7-

< 0.6-0.5

ww 0.405

U,, 0.3

ui

0.2 -

0.1 |

0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.91.0SUBMERGED CONTROLLED FLOW DISCHARGE

COEFFICIENT Cg,

DISCHARGE COEFFICIENTSFOR SUBMERGED CONTROLLED FLOW

TYPE 2 SPILLWAY CREST

PLATE 33

Page 75: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

8,000 - o= 9.0 FT

7,000

6,000-Go=60F

5,000

LL,

CC 4,000

u

C,W

3,000

NON LWUDROE6-TWD

484 483 482 481 480 479 478 477 476 475 474 473 472 471 470

TAILWVATER ELEVATION, FT NGVD

EFFECT OF TAILWATERELEVATION ON DISCHARGE

TYPE 1 SPILLWAY CREST

PLATE 34.

Page 76: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

8,000 -Go = 9.0 FT

7,000

6,000-Go=60F

U. 5,000

") 4,000E

3,000

2,000 -Lu-J

NOTE: FLOW UNDER ONE 60-FT-WIDESUBMERSIBLE TAINTER GATE

0 1 1 1 1 I I

484 483 482 481 480 479 478 477 476 475 474 473 472 471 470

TAILWATER ELEVATION, FT NGVD

EFFECT OF TAIL WATERELEVATION ON DISCHARGE

TYPE 2 SPILLWAY CREST

PLATE 35

Page 77: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

15 4. 0

..J0

13 13 -- J I---J 2

o 0Z

I-. zLL 11 0Z"0 L"

>- 9 L

cn awo 7

'- J

o 7o<A

Il

U) 0o 5 0 C •

3NOTE: FLOW THROUGH ONE 60-FT-WIDE

GATE BAY

1I I I I I

0.1 0.3 0.5 0.7 0.9 1.1

DEPTH OF TAILWATER ABOVE SPILLWAY CREST, FT hGROSS HEAD ON SPILLWAY CREST, FT H

LEGEND

* TYPE 1 SPILLWAY CREST (SUBMERGED FLOW)

* TYPE 1 SPILLWAY CREST (FREE FLOW)O TYPE 2 SPILLWAY CREST (SUBMERGED FLOW)* TYPE 2 SPILLWAY CREST (FREE FLOW)

UNCONTROLLED FLOW REGIMESFOR FLOW OVER SPILLWAY

TYPES 1 AND 2 SPILLWAY CRESTS

PLATE 36

Page 78: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

CA~ cjh

CO)~

Orx

-i - J -J

a 00

Z ~ LL. LLA.._

<0--0- 0 a.a:.t > u3-

U..CbLI--

a.F r ) c:: z .

0 Zwww

:EzF 00 CW <L

(1) ogC/) w o< < <

0 LA- 3: 3 3: 3cc L z

a clO<

F- I-

CC -w)LL4u F-

I I I I

.LS~3 ~L9 NOcI~HSSCC

PLAT 37

Page 79: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

B -

00

7 SUBMERGED CONTROLLED

.6

5 GATE OPENING') 5

CC ( 2FT *TYPE FS SPILLWAY 4 FT

Z CREST 6 FT £

Zw 4 •0 2FT 0CL 0 _F00

PD 0 TYPE 2 4 FT [- U SPILLWAY

\ CREST 6FTa 8 FT 0

0 0 £ £0 2 a & 0

00 "21 "0 0 6-o a o

- FREE CONTROLLED

0 I I I I I I I

0 0.2 0.4 0.6 0.8 1.0 1.2 1.4

DEPTH OF TAILWATER ABOVE SPILLWAY CREST, FT hGROSS HEAD ON THE SPILLWAY CREST, FT H

NOTE: FLOW UNDER ONE 60-FT-WIDESUBMERSIBLE TAINTER GATE

CONTROLLED FLOW REGIMES

TYPES 1 AND 2 SPILLWAY CRESTS

PLATE 38

Page 80: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

0.35

.3 - SUBMERGED0.-

u- UNCONTROLLED3-

.

0.25 -

w £-I-

< Z-J

I-- 0.2 -Lu

STYP 0.1 SLLEGEND ES

&TYPE 2 SPILLWAY CREST SUMRE

* * CONTROLLED0 0

0

. zI

Vo 0.05

C,,

0

0-I •YE PILA CREST

0.4 0.6 0.8 1.0 1.2 1.4

DEPTH OF TAILWATER ABOVE SPILLWAY CREST, FT h

GATE OPENING, FT G

NOTE. FLOW UNDER ONE 60-FT-WIDESUBMERSIBLE TAINTER GATE

SUBMERGED FLOW REGIMES

PLATE 39

Page 81: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

w

a- N-

C/)-I

Wo~u -J

C, :: ZC

w U CCCC 000 r coo

0J~C N- : 0

Cf)

000

00 0 co

0 r,8 c04w47Li

Co

(9 0,

GAON J4'NOII-VA313 E3l-VMIIV.±

PLATE 40

Page 82: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

wC)

~wi

0 C) CC)(

~~w 0Q

CL a.

C0 n2 n o It

DOW 0*<0

z f; a O C

LLJ Z cc D LL W01

(9 uj w CYz___ _ o__cc ___ __ ___ __Z__a.~

-j cc a 0

0ADN m~NIV~)3V1V

PLAT X11

Page 83: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

HWEL F5

483.17TW ELEL4 98 Go~ _ i ,I. ........ .........

TYPE 1 F '--

SPILL WAY CREST

RAISED GATEDEFINITION SKETCH

HW EL483. 17 F5

TYPE 2 -- _ ,

SPILLWAY CREST-.,, 2 ',, F, 7W EL

TYPE 1 it F2 Fj

SPILLWAY CREST

SUBMERGED GATEDEFINITION SKETCH

DEFINITION OF TERMS:

F1 DRY WEIGHT OF GATE SUPPORTED BY CABLES, LB

F2 TAILWATER DISPLACED BY GATE, LB

F4 MEASURED MAXIMUM LOADS DURING TESTS, LB

F5 FLOW-INDUCED LOAD ON CABLES, LB

HW EL = HEADWATER ELEVATION = 483.17 FT NGVDTW EL - TAILWATER ELEVATION, FT NGVD (VARIES)

PROFILE SKETCHOF

MODEL OPERATION

PLATE 42

Page 84: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

62,000 LB

RIGHTCABLE ZERO

Apt . 700 LB

LEFT 0,900 B

CABLE ZERO

SAMPLE OSCILLOGRAPH RECORD

SAMPLE CALCULATIONGIVEN: GATE SUBMERGENCE = 1 FT TW 470

TYPE 1 (ORIGINAL) APPROACHF1 - 115.300 LS Ap - Ap - 2

F2 - 2,900 LB Ap -700 + 700

F3 - F1 - F2 Ap - 1,400 LB

F3 - 115.300 - 2.900

3 " 1 1 2 400 LB ,

SF4" 132,900 LB

F5MAX - F4 - F3 DEFINITION OF TERMS:

F5MAX. 132.900-112.400 F3 - (F1 - F2 ). SUBMERGED WEIGHT OF GATE

SUPPORTED BY CABLES. LB

FSMAX " 20,500 B - AMPLITUDE OF LOAD FLUCTUATIONS, LB

FSMIN " F5MAX - Ap FSMAX - MAXIMUM FLOW-INDUCED LOAD ON CABLES

FSMIN - 20,500 LB - 1,400 LB (F 4 . F3). LB

FMIN 9.100,LB F5MIN . MINIMUM FLOW-INDUCED LOAD ON CABLES(FSMA x - A0, LB

- 3.4 HZ f. frequency of vibrationHZ - Hertz, cyles/sec

SAMPLE FORCE

CALCULATIONAND

OSCILLOGRAPH RECORD

PLATE 43

Page 85: MMARSEILLES - DTICacting on the lifting cables while the gatp is submerged. In addition, veri-fication of anticipated stilling basin performance for all probable operating conditions

wL0x

APPROXIMATELY 1'-6'-~ z

0

uJ<--- -- U0

I--

C-,

LJU

C-o,

IJU

PLATE uP


Recommended