+ All Categories
Home > Documents > MMeet with town to discuss expectations and pre- schedule inspections. Have Permits in hand MMeet...

MMeet with town to discuss expectations and pre- schedule inspections. Have Permits in hand MMeet...

Date post: 15-Dec-2015
Category:
Upload: vance-spilsbury
View: 213 times
Download: 0 times
Share this document with a friend
Popular Tags:
23
NON-STORE CLOSURE RENOVATION
Transcript

NON-STORE CLOSURE RENOVATION

Pre Construction Due Diligence Meet with town to discuss expectations and

pre-schedule inspections. Have Permits in hand

Meet with landlord to discuss dumpster & storage locations and to see if they have any site specific regulations This is especially important in mall locations

Complete the detailed construction schedule Cross reference the Material Schedules on

plan to the FFE Plan to the Items Ordered Sheet to look for discrepancies

Conduct pre-construction meeting with the SM, DM, CM and GC to alleviate apprehensions and go over expectations

Freehold, NJ Before & After

Typical Closing Schedule Day 1; Monday; 12:00 noon until 5:00 am (16 hours) Day 2; Tuesday; 12:00 noon until 5:00 am (16 hours) Day 3; Wednesday; 12:00 noon until 5:00 am (16 hours) Day 4; Thursday; 12:00 noon until 5:00 am (16 hours)

Not needed if floor is not being done Day 5; Friday; 6:00 pm close until 5:00 am (11 hours) Days 6 & 7; No work over the weekend (OPTIONAL) Day 8; Monday; 6:00 pm close until 5:00 am (11 hours) Day 9; Tuesday; 8:00 pm until 5:00 am (9 hours) Day 10; Wednesday; 8:00 pm until 5:00 am (9 hours) Thursday; Store is back to normal hours

Monday Day 1- Backline

Demo of back line/int. walls Rework electric & plumbing Build new walls/rock 1 side Blocking/install wall cubbies Set backline cabinets & counters

Re-set equipment Power and plumbing hook ups Clean and re-set store for a normal morning opening

Tuesday Day 2 - Frontline

Demo frontline, save pastry case Saw cutting for floor sink relo Re-work electric and plumbing Set new bar, POS, & pastry case Re-set all equipment Power and plumbing hook ups Seam Corian counters at the BL

Demo floor tiles to be replaced Scarify floor of thinset Prep for back splash wall tile Begin wall prep for paint Demo and set panels at 1st R. R. Clean and re-set this store for a normal morning opening

Wednesday Day 3 – Lighting/Ceiling

Rough framing inspection Re-locate/add wood soffit panels Install new ceiling lighting Finish first R.R. install Fixtures Install Banquette seating Continue wall prep

Demo existing chair rail Replace all damaged ceiling tiles Install R.R. accessories Clean and re-set store for a normal morning opening

Thursday Day 4 - Flooring

Install floor tile, base and grout Install backsplash tile and grout Continue wall prep Demo and set panels at 2nd R. R. Install under counter lights at cubbies Install FRP at the wet cabinets

Final ceiling prep for Friday paint Prep and install wall cladding at the accent wall Install custom wood trim at hallway door Clean and re-set this store for a normal morning opening

Friday Day 5 – Ceiling Paint Protection for ceiling paint Install BOH Eliason door Finish 2nd R.R. install fixtures Install R.R. accessories

Finish and sand all spackle Clean and re-set this store for a normal morning opening

Sat/Sun DAY 6 &7 No Work Over The Weekend

Monday Day 8 Install free-standing merchandise bays Build and set new condiment cart Begin wall paint, paint R.R. Install chair rail

Install new walk-off mat Install FRP & re-set BOH as per plan Install vinyl wainscoting Clean and re-set this store for a normal morning opening

Tuesday Day 9

Finish all wall painting Install custom shelving unit Install artwork/mural trim Install metal corner guards

Install mural Install artwork Silicone throughout Clean and re-set this store for a normal morning opening

Wednesday Day 10

Final electrical inspection Final plumbing inspection Build and set furniture General punch list Professional cleaning service

window cleaning mechanical floor

cleaning high dusting general cleaning

After today, the store is back to normal hours Final building and health inspections are done during the day on Thursday

Florham Park, NJ Store Expansion

BEFORE AFTER

OBJECTIVES: add Clover, claimed 500 square feet of unused square footage which increased customer seating from (18) to (32) seats, open-space feel with updated palette.

Before and After Floor Plans

Phasing Plan

Mercer Mall Ten Year Reno with a Restroom Relocation &

BOH Expansion,

BEFORE AFTER

OBJECTIVES; enlarge BOH and Managers area, get the full size refrigerator into the back of house, open up space, while increasing seating from (11) to (20) seats , we also replaced floor tile (tile over tile).

Before & After Floor Plans

Phasing Plan

Glen Rock, NJ Reno Using The Temporary Trailer

KEEPING THE CUSTOMER HAPPY WHILE INSIDE….

Setting Trailer Utility Hookups

General Guide Lines Trailer must fit the location

Get prior approval from the town

Safe & separate egress for

customers and workers

Plan on minimum 4 days to set

trailer with inspections (NJ)

Prior arrangements for ice

delivery and bulk milk storage

Prior coordination of data runs

for POS and brewing equipment

Temporary dry storage will be

required

We were able to open store and

then remove trailer in one day

This store was completed in 11 days working thru the weekend, turn over on Friday. We installed new floor tiles and did a full bar reversal. There were only a few hours of interrupted business.

Click icon to add picture

QUESTIONS


Recommended