PROJECT TIME PROJECT TIME MANAGEMENTMANAGEMENT
Ir. AGUNG NUGROHO, M.Kom
Teknik Elektro FT UNDIP
OVERVIEWOVERVIEW
What is A Project?A temporary endeavor undertaken to create a unique product, service, or result
(PMBOK, Third Edition)Temporary
Progressive Elaboration
Unique Deliverable
OVERVIEWOVERVIEW
Four Basic Type of Project
Project
Work
ProductCRAFT INTELECT
PHYSICAL (VISIBLE)
Physical-Craft Physical-Intellect
NON-PHYSICAL (INVISIBLE)
Non Physical -Craft
Non Physical - Intellect
OVERVIEWOVERVIEW
Project Management Process
Project Management Process menurut PMBOK@ Guide 2000 Edition
Project Management Process menurut PMBOK@ Guide Third Edition
OVERVIEWOVERVIEW
Project Management Knowledge AreaProject Management Knowledge Area
1. Project Integration Management2. Project Scope Management3. Project Time Management4. Project Cost Management5. Project Quality Management6. Project Human Resources Management7. Project Communication Management8. Project Procurement Management9. Project Risk Management
OVERVIEWOVERVIEW
How to Achieve Project Success?By balancing stakeholders’ competing demands for :
Time
Scope
Quality
Cost
Process required to accomplish timely completion of the project
Activity DefinitionActivity SequencingActivity Resources EstimatingActivity Duration EstimatingSchedule DevelopmentSchedule Control
PROJECT TIME MANAGEMENTPROJECT TIME MANAGEMENT
1. Activity Definition
2. Activity Sequencing
3. Activity Resource Estimating
4. Activity Duration Estimating
5. Schedule Development
6. Schedule Control
PROJECT TIME MANAGEMENTPROJECT TIME MANAGEMENT
PR
OC
ES
S F
LO
W D
IAG
RA
MP
RO
CE
SS
FL
OW
DIA
GR
AM
The process of identifying the specific schedule activities that need to be performed to produce the various deliverables
Inputs
q Enterprise environmental factors
q Organizational process assets
q Project scope statement
q Work breakdown structure
q WBS dictionary
q Project management plan
Outputs
q Activity list
q Activity attributes
q Milestone list
q Requested changes
Tools & Techniques
q Decomposition
q Templates
q Rolling wave planning
q Expert judgment
q Planning component
1. ACTIVITY DEFINITION1. ACTIVITY DEFINITION
Defining the schedule activities involves identifying and documenting the work that is planned to be performed
1.1. DecompositionDecomposition WBS
2.2. TemplatesTemplates
3.3. Rolling Wave PlanningRolling Wave Planning (Progressive Elaboration Planning where the work to be accomplished in the near term is planned in detail at a low level of WBS, the work far in the future is planned for WBS components that are at relatively high level of the WBS)
4.4. Expert JudgmentExpert Judgment
5.5. Planning ComponentPlanning Component
ACTIVITY DEFINITION : ACTIVITY DEFINITION : TOOLS & TECHNIQUETOOLS & TECHNIQUE
Identifying and documenting the logical relationships among schedule activities.
Inputs
q Project scope statement
q Activity list
q Activity attributes
q Milestone list
q Approved change requests
Outputs
q Project schedule network diagrams
q Activity list (updates)
q Activity attributes (updates)
q Requested changes
Tools & Techniques
q Precedence diagramming method (PDM)
q Arrow diagram method (ADM)
q Schedule network templates
q Dependency determination
q Applying leads and lags
2. ACTIVITY SEQUENCING2. ACTIVITY SEQUENCING
ACTIVITY SEQUENCINGACTIVITY SEQUENCING
Identifying and documenting interactivity dependencies
Activities must be sequenced accurately in order to support later development of a realistic and achievable schedule
can be performed with the aid of a computer or with manual techniques
1. FINISH TO START (FS) : the initiation of successor depends upon the completion of the predecessor
2. START TO START (SS) : the initiation of successor depends upon the initiation of the predecessor
3. FINISH TO FINISH (FF) : the completion of successor depends upon the completion of the predecessor
4. START TO FINISH (SF) : the completion of successor depends upon the initiation of the predecessor
TYPES OF SEQUENCESTYPES OF SEQUENCES
Activity A Activity B
Activity A
Activity B
Activity A
Activity B
Activity A
Activity B
1.Mandatory Dependencies (Hard Logic). Inherent in the nature of the work being done. (eq. You must design before you can construct)
2.Discretionary Dependencies (Preferred, Preferential or Soft Logic). Based on experience, desire or preference.
3.External Dependencies. Based on the needs or desires of party outside the project. (eq. Government or suppliers)
TYPES OF DEPENDENCIESTYPES OF DEPENDENCIES
LAGS AND LEADSLAGS AND LEADS
LAGS Inserted waiting time between task For example: You must wait three days after pouring
concrete before you can construct the frame for a house Relationship : FS + 3: 3 days of Lag
LEADS Designated number of time of periods subtracted from start
or finish the activity. For example: Activity B start 2 days before the activity A
Complete Relationship : FS-2 : 2 days of lead
Arrow Diagramming Method (ADM) Arrow Diagramming Method (ADM) or Activity On Arrow (AOA) or Activity On Arrow (AOA) (1/2)(1/2)
A10 A20
A30
A40
A50 A60
Initial Design
10 days
Draft Drawing
20 days
Run Simulation
15 days
Final Design
10 days
•Only Finish to Start relationship between task
•May use dummies activity as inserted simply to show dependencies between tasks. They do not require work or take time
Arrow Diagramming Method (ADM) Arrow Diagramming Method (ADM) or Activity On Arrow (AOA) or Activity On Arrow (AOA) (2/2)(2/2)
Precedence Diagramming Method (PDM) Precedence Diagramming Method (PDM) or Activity On Node (AON) or Activity On Node (AON) (1/2)(1/2)
Activity Name
Duration
LS LF
ES EF
Activity Name
Duration
LS LF
ES EF
A110 Initial Design
10 days
A120 Draft Drawing
20 days
A130 Run Simulation
15 days
A140 Final Design
10 days
Notes:
LS : Latest Start
LF : Latest Finish
ES : Early Start
EF : Early Finish
Precedence Diagramming Method (PDM) Precedence Diagramming Method (PDM) or Activity On Node (AON) or Activity On Node (AON) (2/2)(2/2)
Inputs
q Enterprise environmental factors
q Organizational process assets
q Activity list
q Activity attributes
q Resource availability
q Project management plan
Outputs
q Activity resource requirements
q Activity attributes (updates)
q Resource breakdown structure
q Resource calendar (updates)
q Requested changes
Tools & Techniques
q Expert judgment
q Alternatives analysis
q Published estimating data
q Project management software
q Bottom-up estimating
3. ACTIVITY RESOURCES 3. ACTIVITY RESOURCES ESTIMATINGESTIMATING
Determining what resources (manpower, equipment, material) and what quantity of each resource will be used, when each resource will be available
What type of resources and in what quantities Those obtain from staff acquisition and procurement. Involves:
Manpower Direct or indirect Internal or outsource
Material Direct: hardware or software Indirect: consumables, supplies
Subcontract Information
RESOURCES REQUIREMENTRESOURCES REQUIREMENT
What resources, what quantities, and when needed Resources : People, Equipment, Materials Involves:
Review WBS Identify available Review historical information Review organizational policies Quantity resources requirement by task Develop plan what type of resources are needed,
what numbers, when
RESOURCES ESTIMATINGRESOURCES ESTIMATING
Inputs
q Enterprise environmental factors
q Organizational process assets
q Project scope statement
q Activity list
q Activity attributes
q Activity resource requirements
q Resource calendar
q Project management plan
Outputs
q Activity duration estimates
q Activity attributes (updates)
· Risk register
· Activity cost estimates
Tools & Techniques
q Expert judgment
q Analogous estimating
q Parametric estimating
q Three-point estimates
q Reserve analysis
4. ACTIVITY DURATION ESTIMATING4. ACTIVITY DURATION ESTIMATING
Estimating schedule activity duration uses information on schedule activity scope of work, required resource type, estimated resource quantities, and resource calendars with resource availabilities.
Estimating the number of work periods that will be needed to complete individual schedule activities.
InputsInputs Resources Requirement -Number of resources that will be assigned -Sometimes, too many resources will reduce productivity
Resources Capabilities -Level of skill, knowledge and experience (seniority)
Etc
ACTIVITY DURATION ESTIMATINGACTIVITY DURATION ESTIMATING
Expert JudgmentExpert Judgment.. Used when duration difficult to estimate because of number of factor (resource level, productivity)
Analogues Estimating.Analogues Estimating. Using the actual duration of previous activity that has similarity (top down)
Parametric EstimatingParametric Estimating.. Uses a statistical relationship between historical data and other variables. (e.q: Square footage in construction, lines of code in software development) to calculate an estimate for activity.
Three Point EstimatesThree Point Estimates.. Uses three cost or duration estimates to represent the optimistic, most likely, and pessimistic scenarios. This technique is applied to improve the accuracy of the estimates of cost or duration when the underlying activity or cost component is uncertain. Average = (Optimistic + Most likely + Pessimistic) / 3
Reserve Analysis. The contingency reserve can be a percentage of the estimate activity duration, a fix number of work periods, or developed by quantitative schedule risk analysis.
ACTIVITY DURATION ESTIMATING : ACTIVITY DURATION ESTIMATING : TOOLS & TECHNIQUETOOLS & TECHNIQUE
Identify periods when work is allowed Project calendars affect all resources Define time units, length of work week, non working
period: Day (s) of the week Hours of the day Holidays or non-working period
All activities must be assigned a calendar
RESOURCES CALENDARSRESOURCES CALENDARS
Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule
Inputs
q Organizational process assets
q Project scope statement
q Activity list
q Activity attributes
q Project schedule network diagram
q Activity resource requirements
q Resource calendars
q Activity duration estimates
q Project management plan
Outputs
q Project schedule
q Schedule model data
q Schedule baseline
q Resource requirements (updates)
q Activity attributes (updates)
q Project calendar (updates)
q Requested changes
q Project management plan (updates)
· Risk register
Tools & Techniques
q Schedule network analysis
q Critical path method
q Schedule compression
q What-if scenario analysis
q Resource leveling
q Critical chain method
q Project management software
q Applying calendars
q Adjusting leads and lags
q Schedule model · Schedule management plan (updates)
5. SCHEDULE DEVELOPMENT5. SCHEDULE DEVELOPMENT
CRITICAL PATH METHODCRITICAL PATH METHOD
Critical Path:Critical Path: series of activities that determine the duration of the projects
It is Longest PathLongest Path through the project Calculating float to determine which activities have
The Least Scheduling FlexibilityThe Least Scheduling Flexibility Critical Path: Total Float = LS – ES = LF – EF = 0Total Float = LS – ES = LF – EF = 0
SCHEDULE DEVELOPMENT : SCHEDULE DEVELOPMENT : TOOLS & TECHNIQUE TOOLS & TECHNIQUE (1/3)(1/3)
SCHEDULE COMPRESSIONSCHEDULE COMPRESSION
1. Fast Tracking1. Fast Tracking Doing critical path task in parallel that were originally
planned in series Fast Tracking often results in rework, usually increases
risk and requires more attention to communications
2. Crashing2. Crashing Moving resources from non critical tasks or adding
extra resources to the task from outside project. Crashing almost result in increased costs.
SCHEDULE DEVELOPMENT : SCHEDULE DEVELOPMENT : TOOLS & TECHNIQUE TOOLS & TECHNIQUE (2/3)(2/3)
RESORCE LEVELINGRESORCE LEVELING Leveling lets schedule and cost slip in favor of having a
stable number of resources each month Allocate scarce resources to critical path activities first
CRITICAL CHAIN METHODCRITICAL CHAIN METHOD Focuses on managing the buffer activity durations and
the resources applied to planned schedule activities Combine deterministic and probabilistic approaches
SCHEDULE DEVELOPMENT : SCHEDULE DEVELOPMENT : TOOLS & TECHNIQUE TOOLS & TECHNIQUE (3/3)(3/3)
FloatFloat.. The amount of time a task can be delayed without delaying the project
Free Float.Free Float. The amount of time a task can be delayed without delaying the early start date of its successor
Total FloatTotal Float.. The amount of time a task can be delayed without delaying the project completion date
Project FloatProject Float.. The amount of time a project can be delayed without delaying the externally imposed project completion date required by customer or management
Negative FloatNegative Float.. Critical path task that are delayed or have dictated dates can result in negative float
FLOAT (SLACK)FLOAT (SLACK)
Activity Title Duration(days)
PrecedingActivities
A Mobilize 10 -B Obtain permits 15 -C Site works 8 AD Exterior utilities 12 AE Excavate catch basin 2 B,CF Excavate footers 5 B,CG Excavate foundation peers 6 B,CH Pour footers 8 D,E,F,GI Erect building frame 10 H
Arrow Diagramming Method (ADM)Arrow Diagramming Method (ADM) - - ExampleExample (1/7)(1/7)
1 7632 8
B
I10
H8
5 G6
4 F5
E2
D12
C8
15
A10
Arrow Diagramming Method (ADM) - Arrow Diagramming Method (ADM) - ExampleExample (2/7)(2/7)
Analyze Project Network to:Analyze Project Network to:
Find the Critical Path that establish the minimum duration of the project
calculate the Early Start time for each activity calculate the Late Start time for each activity calculate the Float, or time, available for delay
for each activity
Arrow Diagramming Method (ADM) - Arrow Diagramming Method (ADM) - ExampleExample (3/7)(3/7)
Forward-Pass AlgorithmForward-Pass Algorithm
1 7632 8
B
I10
H8
5 G6
4 F5
E2
D12
C8
15
A10
0 10
18
18
18 24 32 42
Arrow Diagramming Method (ADM) - Arrow Diagramming Method (ADM) - ExampleExample (4/7)(4/7)
Backward-Pass algorithmBackward-Pass algorithm
1 7632 8
B
I10
H8
5 G6
4 F5
E2
D12
C8
15
A10
0 10
18
18
18 24 32 42 423224
18
18
19
100
Arrow Diagramming Method (ADM) - Arrow Diagramming Method (ADM) - ExampleExample (5/7)(5/7)
Calculating floatCalculating float
1 7632 8
B
I10
H8
5 G6
4 F5
E2
D12
C8
15
A10
0 10
18
18
18 24 32 42 423224
18
18
19
100
0 0 0 0 0 0
0 0
1 1
0 04 4
2 2
3 3
FF TF
Note:
Arrow Diagramming Method (ADM) - Arrow Diagramming Method (ADM) - ExampleExample (6/7)(6/7)
Critical pathCritical path
1 7632 8
B
I10
H8
5 G6
4 F5
E2
D12
C8
15
A10
0 10
18
18
18 24 32 42 423224
18
18
19
100
0 0 0 0 0 0
0 0
1 1
0 04 4
2 2
3 3 Note:
Critical activity
Arrow Diagramming Method (ADM) - Arrow Diagramming Method (ADM) - ExampleExample (7/7)(7/7)
Milestone ChartsMilestone ChartsSimilar to bar charts but only show major events. Milestone have no duration. Milestone charts are good tools for reporting to management and customer
FlowchartsFlowchartsDepict workflow and process flow through a system. Used for quality or engineering.
Bar (Gantt) ChartsBar (Gantt) ChartsEffective tools for progress reporting and control. They are completed after WBS and a network diagram in the project management process.
Network DiagramNetwork DiagramShows how the project tasks will flow from beginning to end. Used for planning, organizing, controlling, crashing, and fast tracking the project
SCHEDULE CHARTSSCHEDULE CHARTS
SCHEDULE CHARTSSCHEDULE CHARTS
Project Management software makes an attempt to draw lines between tasks on a Gantt chart to show interdependencies. However, Gantt charts do not show task interdependencies or resources assigned. A Gantt chart looks similar to this:
01-Sep 08-Sep 15-Sep 22-Sep 29-Sep1 Start 0 1-Sep-06 1-Sep-062 D 4 1-Sep-06 4-Sep-063 A 6 1-Sep-06 6-Sep-064 C 7 3-Sep-06 9-Sep-065 B 8 2-Sep-06 9-Sep-066 E 12 10-Sep-06 21-Sep-067 Finish 0 21-Sep-06 21-Sep-06
FinishSeptember
ID Task Name Durations Start
BART (GANT) CHARTBART (GANT) CHART
BART (GANT) CHARTBART (GANT) CHART
SCHEDULE LEVELSSCHEDULE LEVELS
Inputs
q Schedule management plan
q Schedule baseline
q Performance reports
q Approved change requests
Outputs
q Schedule model data (updates)
q Schedule baseline (updates)
q Performance measurements
q Requested changes
q Recommended corrective actions
q Organizational process assets (updates)
q Activity list (updates)
q Activity attributes (updates)
q Project management plan (updates)
Tools & Techniques
q Progress reporting
q Schedule change control system
q Performance measurement
q Project management software
q Variance analysis
q Schedule comparison bar charts
6. SCHEDULE CONTROL6. SCHEDULE CONTROL
Controlling changes to the project schedule which includes determining the current status of the project schedule, influencing the factors that create schedule changes, determining that the project schedule has changed, and managing the actual changes.
Progress Reporting.Progress Reporting. Includes information such as actual start and finish dates and the remaining durations.
Schedule Change Control System.Schedule Change Control System. Includes the paperwork, tracking system, and approval levels necessary for authorizing changes.
Performance Measurement.Performance Measurement. Schedule Variance (SV) and Schedule Performance Index (SPI) Earned Value Analysis
Variance Analysis.Variance Analysis. Comparing target schedule dates with the actual/forecast finish dates.
SCHEDULE CONTROL : SCHEDULE CONTROL : TOOLS & TECHNIQUETOOLS & TECHNIQUE
Thank YouThank You