Model Estimating
Kevin R. MillerBYU Construction Management
Estimating todayWhen was the last time you estimate a set of plans that
were 100%?How do you perform quantity takeoff?How long did it take you to do the takeoffs?When you perform a takeoff, do you look at every sheet
simultaneously?
RiskWho bears the risk today if the plans aren’t complete?
How do you cope with plans that aren’t complete?Hard BidNegotiated, Design-Build
Benefits of Takeoff Process (Traditional Plans)Become familiar with the projectFind problem areas and identify risk and constructability
issuesValue engineering
Down side of Takeoff(Traditional Plans)Time consuming (Detailed Estimates)May miss somethingTransferring quantities from takeoff sheets to Estimating
software tedious and non productive
What do we want from the Model?Accurate quantities.Less takeoff time.Better visualization of project.Subs to understand the project and their scopes.More time verifying what is modeled is constructableInterference resolved before work in the field starts.Better understanding of design intent.
General Sales PitchPush the button.
Costs are generated.The 4/5 D model is generated.All the work is done.
Looks good, sales software.Not necessarily doable without a lot of extra work.
Model World TodayNot the magical pushing a button and the estimate is done.No such thing as a 100% ModelLook at the information that is relevant to your takeoffs, not
everything at once.Your costs come from your historical cost database or bids
not Means or some other sourceThe liability that exists with 2D drawings exist with 3D
modelsWith BIM – Risk shouldn’t change or shift
Estimating from the Model or Not?Do I really want to work from the Model?
No, I want static drawings that don’t change so there is an accurate history of the costs for the project.
No, I don’t want the potential to change the drawings because I’m and estimator, not a modeler.
No, the file size of the model would really slow me and my computer down.
DWF file (a read-only copy of the model) addresses the above concerns
What can we really get from the Model?CountsLengthsAreas
Be careful with areas and volumes Use Length * Height for areas Use Length * Height * Width for volumes
Do these concerns mean don’t use the model? NO, just understand how the quantities are being calculated.When in doubt, check the quantity calculation.
Timberline/MC2 OpportunitiesQTO integrates seamlessly into Timberline.QTO integrates with MC2.
Cleanup and optimize the estimating DBToo much legacy junk in estimating DB’sEvery item in the DB should have a formula in order to link
QTO integrates better with Timberline than Timberline does
What is needed to Estimate From the Model3D model2D modeled sheets
Allows you to perform takeoff for the things not modeled.DWF file formatMay use PDF, jpg etc files but they will not link to the 3D
model.
Model prep hintsIf there are more than 20,000 objects, things slow down.
If the model is too big to work on your computer, Section it
Most likely you will want the cost by building anyway.
If there are too many objects, turn off the ones that are not being taken off, like curtain wall mullions (9621 Objects) out of 28,015 objects in the entire project.
Estimating in the ClassroomTakeoffs taking less time
Students are understanding what is being taken off better in 3D than in 2D.
Test scores are going up and takeoffs more accurate.
Contact: Kevin R. Miller [email protected]