+ All Categories
Home > Engineering > Modelling Line of Balance Schedules with Start-Finish Relationships

Modelling Line of Balance Schedules with Start-Finish Relationships

Date post: 14-Apr-2017
Category:
Upload: felipe-moreira
View: 497 times
Download: 4 times
Share this document with a friend
40
(PS-1862) Modelling Line of Balance Schedules with Start- Finish Relationships Ricardo Viana Vargas Felipe Fernandes Moreira
Transcript
Page 1: Modelling Line of Balance Schedules with Start-Finish Relationships

(PS-1862) Modelling Line of Balance Schedules with Start-Finish Relationships

Ricardo Viana VargasFelipe Fernandes Moreira

Page 2: Modelling Line of Balance Schedules with Start-Finish Relationships

Authors

Ricardo Viana [email protected]@rvvargas/in/ricardovargas+45 4533 7673

Felipe Fernandes [email protected]/in/felipefmoreira@ffmot+55 85 32675722+55 85 86999108

Page 3: Modelling Line of Balance Schedules with Start-Finish Relationships

INTRODUCTION

3

Page 4: Modelling Line of Balance Schedules with Start-Finish Relationships

Project Planning

4

Activity List Precedence Diagram Method Network Diagram

Page 5: Modelling Line of Balance Schedules with Start-Finish Relationships

Activities Dependencies

5

PREDECESSOR

SUCCESSOR

Logical Relationships

≠ Chronological Relationships

Page 6: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method (LBSM)

• Absent from PMBOK (discusses the CPM network concepts most prominently);

• Technique used at construction industry at Brazil, Finland and Australia (HENRICH & KOSKELA, 2006);

• Related with Lean Construction and Last Planner System;

• Surging in recent years: need to go further than just the critical path;

• Drawback: lack of software support.

Page 7: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

• “Unit of Production x Time” Chart;• Different from the usual “Activity x Time” Gantt Chart;• Focus on the workflow;• Scheduling according to the rate of production;• Number of working units delivered by a working crew.

Page 8: Modelling Line of Balance Schedules with Start-Finish Relationships

OBJECTIVES

8

Page 9: Modelling Line of Balance Schedules with Start-Finish Relationships

Objectives

• Since LBSM lacks software support;• Propose a method for modelling a Line of Balance with

CPM calculations software;• Method involves the use of “Start-Finish” logical

relationship.

The main objective of this paper is to propose how to model a Line of Balance schedule, while the secondary objective is to investigate the “unexpected results” of

this sort of modelling.

Page 10: Modelling Line of Balance Schedules with Start-Finish Relationships

LINE OF BALANCE SCHEDULING METHOD

10

Page 11: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

• Scheduling according to the rate of production• Number of working units delivered by a working

crew

List of Activities

Page 12: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

Schedule using the Gantt chart

Page 13: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

Schedule using the LBSM

Page 14: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

Schedule using the LBSM

Rate of Activities

Production

Angular Coefficient of each line

0.25 units/day

0.50 units/day

0.33 units/day

Page 15: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

Balancing the linesMake the rate of production

of the activities to be as similar as possible

Reduce the Task 2 “speed”

(make its angular coefficient smaller)

Reduce its resources by half – increase duration from 2 to

4 days

Page 16: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

Balancing lines to achieve a schedule reduction

0.25 units/day

0.50 units/day

0.33 units/day

Project finishing earlier

Page 17: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

4 lines (4 production units)

12 lines(3 tasks for 4 floors)

Page 18: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

• Significant reduction of lines• The bigger the number of repetitions, the bigger

the reduction• Applicable at all sort of repetitive processes

– Eg.: Construction of 100 km, with 20 tasks for each kilometer

Page 19: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

• Construction industry: tasks are scheduled continuously (KENLEY & SEPPÄNEN, 2010)

• Could be scheduled without this restriction

Line of Balance without the continuity of repetition

Page 20: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

0.250 units/day

0.286 units/day

0.267 units/day

Page 21: Modelling Line of Balance Schedules with Start-Finish Relationships

3-day reduction

Line Balacing Schedule Reduction

Line Balacing is a “Crashing Method!”

Line of Balance Scheduling Method

Page 22: Modelling Line of Balance Schedules with Start-Finish Relationships

Breaking the continuity restriction will increase the total time of resource allocation!

16 days14 days 15 days

16 days 8 days 12 days

Line of Balance Scheduling Method

Page 23: Modelling Line of Balance Schedules with Start-Finish Relationships

Line of Balance Scheduling Method

Peculiarity: how to model this schedule?

Page 24: Modelling Line of Balance Schedules with Start-Finish Relationships

Two proposals

Network Approach

• Envolves CPM network calculations

Linear Scheduling Approach

• Drops the CPM network calculations

Page 25: Modelling Line of Balance Schedules with Start-Finish Relationships

NETWORK APPROACH

25

Page 26: Modelling Line of Balance Schedules with Start-Finish Relationships

The Network Approach

Task 1 on the 4th floor defines the start date of Task 2 on the 4th floor

The last task offers the time constraint for the task progression!

Task 2 faster than

Task 1

“FS relations”Connected at the 4th floor

Page 27: Modelling Line of Balance Schedules with Start-Finish Relationships

The Network Approach

Network Diagram with the logical relationship between tasks

Page 28: Modelling Line of Balance Schedules with Start-Finish Relationships

The Network Approach

Can’t use the “FS” relation

Time constraint is transmitted “downward” from 4th to 1st floor.

Done with the “SF” relation.

Page 29: Modelling Line of Balance Schedules with Start-Finish Relationships

The Network Approach

SF relation between the repetitions of Task 2

Page 30: Modelling Line of Balance Schedules with Start-Finish Relationships

The Network Approach

Connected at the 1st floor

4th floor is no longer the time constraint for the task progression.Time constraint move “upwards” using the “FS” relation!

Page 31: Modelling Line of Balance Schedules with Start-Finish Relationships

The Network Approach

Complete network diagram for the example

Important: PM softwares will show every task as critical

Page 32: Modelling Line of Balance Schedules with Start-Finish Relationships

The Network Approach

Task 2 on the 2nd, 3rd and 4th floor are not critical!

Page 33: Modelling Line of Balance Schedules with Start-Finish Relationships

The Network Approach

• “FS” logical relationships + As Late As Possible (ALAP)

Breaks the continuity

Results in a different schedule! Finishes earlier

Page 34: Modelling Line of Balance Schedules with Start-Finish Relationships

The Network Approach

• Both “SF” and “FS” + ALAP structures offer viable options for LBSM modelling;

• “SF”:– Ensures continuous task progressions;– No risk related to discontinuity.

• “FS” + ALAP:– Shorter Project duration;– Risks related with discontinuity.

Page 35: Modelling Line of Balance Schedules with Start-Finish Relationships

LINEAR SCHEDULE APPROACH

35

Page 36: Modelling Line of Balance Schedules with Start-Finish Relationships

The Linear Schedule Approach

• Drops the CPM network calculations;• Uses the software as a “graphical tool”;• Focus on the fundamentals: flow of work.

Page 37: Modelling Line of Balance Schedules with Start-Finish Relationships

The Linear Schedule Approach

• Control by flow? Avoid clashes

Clash = Rupture in the workflow

Page 38: Modelling Line of Balance Schedules with Start-Finish Relationships

• Modelling lines by chaining tasks and subordinating it to milestones.

“SF” relationships

“FS” relationships

Page 39: Modelling Line of Balance Schedules with Start-Finish Relationships

CONCLUSION

39

Page 40: Modelling Line of Balance Schedules with Start-Finish Relationships

Conclusion

• Line of Balance x Gantt Chart;• LBSM x CPM network;• Flow x Critical Path;• Utilization of “Start-Finish” on scheduling;• Line of Balance as a CPM network:

– “SF” relationships ensures the task progression continuity;– “FS” + ALAP potencially reduces the project duration at

the cost of higher risk;• CPM software as a “graphical tool”:

– End Milestones: “SF” relationships;– Start Milestones: “FS” relationships.


Recommended