Modular LNG Tanks
John Powell and Brian Raine
Gastech 2017
Tokyo, 4-7 April 2017
2
Small to mid-scale LNG 0.5 MMTPA to 2.0 MMTPA
LNG Marine Fuels
LNG to Power
100MW power station needs 800m3 of LNG per day or 24,000m3 per month
Smaller LNG tanks required
Volumes between 10,000m3 to 100,000m3 are needed
These tanks must be delivered at lower cost
Economies of scale by volume stored is NOT the solution
Economies of scale by volume of production (number of units produced) IS the solution
Markets and Opportunities
(8) Long, B., Bigger and Cheaper LNG Tanks? Overcoming the obstacles confronting freestanding 9% Nickel Steel Tanks up to and beyond 200,000m3, LNG12, 1998, PS5.6
(9) Veliotis, P.T., Solution to the Series Production of Aluminum LNG Spheres, Society of Naval Architects and Marine Engineers Transactions, Volume 85, 1977, pp 481-504
Figure courtesy of Ref (8)
Figure courtesy of Ref (9)
3
Objectives for 10,000m3 to 100,000m3 LNG tanks
- Less than 24 months delivery schedule
- 20% lower CAPEX cost
Key drivers
- Standardize tank design by volume based on site specific seismic isolation
- Offsite tank pre-fabrication in parallel with foundation construction
- Dedicated fabrication yard leading to improved productivities and higher quality
- Offsite pre-commissioning of tank
- Reduced manhours executed on site
Target
- Plug and play capability
The Modular LNG Tank
4
Papers and Presentations
- Raine, B. Onshore Mid-Scale LNG Terminal Storage Modularization, Trinidad Oil and Gas Conference, May 2014
- Raine, B., Powell, J., Onshore Mid-Scale LNG Terminal Storage Modularization, Gastech 2015, Singapore, October 27, 2015
2014-2015
- In-house development work carried out
2015-2016
- pre-FEED design, execution planning, scheduling and cost estimating carried out for 40k tanks in US and Caribbean, working with fabricators and transportation contractors
2016-2017
- Further development focusing on standard design by volume for any location
Development of Modular Tank Concept
5
Remark Value
Number of LNG Storage Tanks 6
Main tank design standards NFPA59A, API625/620
LNG storage tank type Single containment
Foundation type Pile supported, elevated
Inner Tank
Material 9Ni ASTM A533 Type1
Net Capacity 40,000 m3
Gross Capacity 42,700 m3
Inner tank diameter (ambient) 37.5 m
Height (ambient) 39.4 m
Modular Tank Design Data
Remark Value
Outer Tank
Material Steel A36
Outer tank diameter 40.0 m
Min width annular space 1.25 m
Dome Roof
Material Steel A36
Spherical radius 40.0 m
Insulation material
Bottom Cellular Glass
Annular Expanded Perlite
Suspended deck Glass fiber blanket
6
Remark Value
LNG Product
Temperature -170 oC
Density (BOG) 440 kg/m3
Density (Max) 470 kg/m3
Latent heat of vaporization 511,000 J/gk
Design Boil off Rate (volume) 0.05 %/day
Maximum filling rate 850 m3/hr
Maximum outpumping rate 2,250 m3/hr
Pressures
Maximum design pressure 105 mbarg
Minimum design pressure -5 mbarg
Modular Tank Design Data
Remark Value
Seismic design
OBE (pga at 5% damping) 0.037 g
SSE (pga at 5% damping) 0.074 g
Wind
ASCE 7-05 63 m/s
Soils
VGLNG Calcasieu Pass
FERC RR13
very soft to firm cohesive 0-10 m
firm to stiff cohesive 10-30 m
slightly over consolidated >30 m
7
Design Modular Tank General Arrangement
40.0m ID
42
.3m
5.4
m
Tank Elevation Grillage Plan Foundation Plan(37 Pile caps, 185 piles)(235tons 50ksi steel)
W30 x 108 (secondary)
W40 x 215 (primary)
(590tons 9%Ni steel, ASTM A553 Type 1)
12 concrete slab(fc=5,000psi)
8
Design Modular Tank Details
3/4 (18mm) inner shell
5/16 (8mm) inner shell
3/8 (9mm) outer shell
5/8 (16mm) outer shell
1/4 (6mm) roof plate
+0.000 (TOS)
+0.900
+2.900 (NMOL)
+40.280 (U/S)
+39.902 (DMLL)
+38.352 (NMLL)
9
Side Wall Discharge
(11) Coers, D, (2005) Transshipping LNG Downscaling Field-Erected Storage Tanks for Lower Profile, 2005 (Presentation with photos provided by CB&I)
(A) Image courtesy of Cheniere
Image courtesy of Ref (A)Image courtesy of Ref (11)
10
Side Wall Discharge
(10) Antalffy, L. P., Aydogean, S., De la Vega, F. F., Malek, D. W., Martin, S., (1998) Technical-economic evaluation of pumping systems for LNG storage tanks with side and
top entry piping nozzles, LNG12, Perth, 4-7 May, 1998, Poster Session B.8
Side wall discharge significantly reduces the roof platform weight and cost
Tanks can be manifolded at ground level, reducing total number of pumps
Since the tank is elevated the pumps do not need to be recessed in a pit to achieve min NPSH rating
11
Tank prefabrication Tank Transportation Project Sites
Fabrication yard enabling works Supply of all heavy lift equipment Enabling works for receiving tank
Tank foundation line foundation Supply of all marine equipment Construction of tank foundation
Material procurement Load out at fabrication yard Hydrotesting
Steel grillage foundation Tow to project site Perlite insulation
Tank ring prefabrication Offload at project site Tank hook up
Tank erection Set down at project site on plinths Bund construction
Tank roof prefabrication Demobilization Final pre-commissioning of tank
Roof Erection Ready for cooldown
Pre-commissioning
Preparation for transportation
Execution Scope of Works
12
Envisage regional fabrication facilities
Existing fab yards will reduce start up costs
Plate delivered to yard, cut, bent and prepped
Grillage erected in place
Tanks erected as complete fabricated rings
Dome roof pre-assembled, no airlift
No hydrotest at fabrication yard
Pump platform pre-assembled lifted into place
Pump columns pre-installed on tank bottom lifted through roof after platform installation
Lifts made with 600te crawler crane
Fab yard bulkhead suitable for 5,000te loadout, but temporary ramps can span weak bulkheads
Execution Tank Fabrication
Images courtesy of Great Basin Industries and Mammoet
13
SPMTs used for moving tank
Extent of seafastenings route dependent
Sheltered water tows 300x100 barge
Open water use heavy transportation vessel or larger barge
Longer tows seek to transport multiple tanks
Execution Tank transportation
(B) Smith Group, Australia
(C) Mammoet
Image courtesy of Ref (B) Image courtesy of Ref (C)Figures courtesy of Ref (C)
14
Tank erection is not waiting on construction of the project site tank foundation
- No onsite construction before permits obtained
- Many projects require significant onsite enabling works
Tank fabrication and erection starts when material delivered to the fabrication yard
- Carbon steel material required first are on short lead times
- 9% Ni lead times of 12 to 18 months can be offset with material pre-ordering
- Established fabrication yard allows tank erection to start ahead of a stick built tank
Labor intensive activities transferred from the project site to a dedicated fabrication yard
- Project sites often remote from large resource centers
- Specialist welders 9% Ni tank incurs a further premium for remote sites
- Established fabrication yard can provide a more reliable resource
Improved productivities and quality at established fabrication yard
- Can invest in training and equipment to increase productivities and reduce costs
- Prefabrication of tank parts can be done in covered areas
Execution Plan Key Benefits
15
Project site tank design drivers
- Soils
- Seismicity
Bespoke foundation every time
Tank is elevated on bearings
Tune bearings to provide base isolation
Set target inertial loading based on 33% overstress on hydrostatic design case
Project site environmental conditions and tow route will influence tank design but are not significant for standard tank design benefits
Further Developments Base isolation enables standard tank design
(D) KOGAS
(13) Symans, M. D., Seismic Protective Systems: Seismic Isolation, FEMA, Instruction Material Complementing FEMA 451, Design Examples, Seismic Isolation 15-7-1
Figure courtesy of Ref (13) Image courtesy of Ref (D)
Figure courtesy of Ref (13)
16
Membrane tanks are well suited to modular concept
- Highly modular design based on 56 facets
- Stainless steel liner material short lead time
- Multiple suppliers for membrane system
- Only ONE structural tank using carbon steel
- Smaller insulation volume more LNG storage
- Tank does not require hydrotest
- Robust design for transportation
- Tank can undergo multiple warmup and cooldown
- Good leak detection using nitrogen purge
- Pump sump can be located in tank bottom
Further Developments Membrane Modular LNG Tanks
(E) GTT
Image courtesy of Ref (C)
17
dfd
Comparison of 9%Ni and Membrane Modular LNG Tanks
Dimension 9%Ni Modular LNG Tank Membrane Modular LNG Tank
Net LNG storage volume (m3) 40,000
Outer tank diameter (m) 40.0
Inner tank diameter (m) 37.5 38.8
Design Maximum Liquid Level (m) 38.8 36.3
Outer tank height to roof joint (m) 42.3 39.5
Roof rise (m) 5.4 5.4
Overall tank height from ground (m) 50.4 47.6
Tank weights total/transport (te) 4,250 / 3,800 3,350 / 3,350
Schedule from NTP to RFCD 22 months 20 months
Costs (9% Ni stick built = 100%) 90% 80%
18
Comparison of 9%Ni and Membrane Modular LNG Tanks
19
Technical feasibility of the modular LNG tank has been studied and proven
Membrane modular LNG tanks offer clear advantages over 9% Ni modular LNG tanks
Plug and Play capability is achievable
- based on a standard design that can be installed for any site, anywhere in the world
- resulting in cheaper and quicker prefabricated small to medium sized tanks
Not every site wants or can permit a Single Containment Modular LNG Tank design
Full Containment Modular LNG Tank designs are too heavy to transport cost effectively
Precast concrete full containment with membrane liner offers significant opportunities to reduce cost and schedule
The LNG to Power market needs cheaper tanks
Modular LNG tank designs addresses this need
Conclusions