Page 1: Module 2_ RFE1-V3

RFE1 SurveyRFE1 SurveyRFE1 SurveyRFE1 Survey

Page 2: Module 2_ RFE1-V3

• RFE stands for Ready for Electronics.

• RFE1 survey is done to check the site environment and infra readiness before carrying the installation of the system or network element .

• It’s a first step of deployment project in which we check all parameters

RFE1 Survey- Definition

2013 © Samsung Electronics 2

• It’s a first step of deployment project in which we check all parameters those are required for eNB installation like measuring lengths of cables, checking the grounding, power, space availability for network element.

Page 3: Module 2_ RFE1-V3

• Cable Lengths: – Short cable can delay the installation or if too long can affect the project cost &

quality.

• Site Infra: – Site Infra should be as per site requirement, if not, it affects the project timeline.

• To reconfirm the RF planning’s requirement and the data in TSSR

Need for RFE1 Survey!

2013 © Samsung Electronics 3

(Technical Site Survey Report).

• Note– P1 sites are the sites built and owned by RJIL, also called as ‘own’ sites. – RP1 sites are the sites that will be built by Rcom and also called as ‘Shared or Co-

Lo’.

Page 4: Module 2_ RFE1-V3

RFE1 Work Flowchart

Start

Site Allotment with site detail

& TSSR Report as applicable

Key collection from KCC

RFE 1 Survey with proper

Tools

2013 © Samsung Electronics 4

Tools

Submit the RFE1 report to

Samsung eNB Engg. & upload

in GIS within 24Hrs

Any

Issue

Yes

No

End

Page 5: Module 2_ RFE1-V3

Pre RFE1 Status

Summary of Pre RFE1:The pre RFE1 covers status of civil work, electricity board (EB) availability and utility commissioned.

2013 © Samsung Electronics 5

Page 6: Module 2_ RFE1-V3

Before going to the site, the engineer needs to make sure about the following important points:

– Route Plan• Address• Transportation

– Access Feasibility

Pre-requisites for RFE1

2013 © Samsung Electronics 6

• Company letter • I Card• Training I Card

– Tools– Required Documentation

• RFE1 site survey form• TSSR form (only for P1/own site)• IFC diagram (only for P1/own site)

Page 7: Module 2_ RFE1-V3

RFE1 Survey RFE1 Survey RFE1 Survey RFE1 Survey Tools Tools Tools Tools ListListListList

Page 8: Module 2_ RFE1-V3

The basic tools for RFI Survey are listed in the table below. • Helmet• Safety/Harness Belt (with two hooks)• Safety Shoes• Permanent Pen (Black)• Compass with mirror• GPS• Laser Meter

RFE1 Survey Tools List

2013 © Samsung Electronics 9

• Laser Meter• Digital Camera• Measuring Tape• Tilt Meter• Ruler Scale• Multimeter• Ladder• Torch

9

Page 9: Module 2_ RFE1-V3

RFE1 Survey Tools Description

Basic RFI Survey Tools

No. Name Specification Picture Purpose Make Suggested

1 Helmet Common Basic Safety Equipment PETER ISI

2 Safety/Harness belt50 x 2.0 x 1200mm,

W/Simple buckleBasic Safety Equipment PETER ISI

2013 © Samsung Electronics 10

W/Simple buckle

3 Safety shoes Basic Safety Equipment Standard

4Permanent Pen

(Black)

Should be marked

"Permanent" on the

pen

(Back Color)

To mark the site ID,

Name on the name

plate, etc..

(Not to erase

permanently)

Any Standard

Page 10: Module 2_ RFE1-V3

RFE1 Survey Tools Description

Basic RFI Survey Tools

No. Name Specification Picture Purpose Make Suggested

5Compass with

MirrorCommon

To check the

Azimuth

6 GPS Tracking systemTo locate the exact

locationTrex/Garmin

2013 © Samsung Electronics 11

location

7 Laser Meter

Should be able to

calculate distance

till 50m

To calculate

distanceStandard

8

Digital Camera

with data Cable

or memory card

reader

over the 10 Mega

pixels,

10x zoom

Take a picture

of TowerSamsung

Page 11: Module 2_ RFE1-V3

RFE1 Survey Tools Description

Basic RFI Survey Tools

No. Name Specification Picture Purpose Make Suggested

9

Tape Measure-

Cloth-50m

Metal-5m

5 m/50 m Basic Tool Any Standard

10 Tilt Meter To Measure Tilt Any Standard

2013 © Samsung Electronics 12

11 Ruler Scale 30cmTo calculate Pole

DiameterCamlin/Faber Castle

12 Ladder 3Mts

To access the

RTP/GBM to around

3m.

Any Standard

13 Multimeter

DC,AC

measurement

1.0~60 kgf.cm

To measure DC, AC

PowerMastec

Page 12: Module 2_ RFE1-V3

RFE1RFE1RFE1RFE1----Survey ReportSurvey ReportSurvey ReportSurvey Report

Page 13: Module 2_ RFE1-V3

RFE1 Survey Form

Microsoft Office

2013 © Samsung Electronics 14

Microsoft Office

Excel Worksheet

Page 14: Module 2_ RFE1-V3

RFE1 Survey Attributes to be Checked Carefully

Sr. No. Description

1 Pole Bending

2 Non availability of Outdoor Grounding Bar.

3Non availability of Internal Grounding Bar

with 3 holes free

4Non availability of Cable tray till

ODC (Roxtec and/ or Cable Inlet)

5Non availability of Ladder to access the

2013 © Samsung Electronics 2222

5ODC & Tower

6 Water Seepage in ODC

7 Non Availability of EB/SEB Supply Availability

8 Non Availability of Battery Bank

9 Non availability MCB-10A/25A

10 Lightning Arrestor covers the whole tower from top

11 RF Antenna Pole Position Not as per the TSSR

Page 15: Module 2_ RFE1-V3

Check List CSRCheck List CSRCheck List CSRCheck List CSR

Page 16: Module 2_ RFE1-V3

CSRCSRCSRCSR----ChecklistChecklistChecklistChecklist

Microsoft Office Microsoft Office

Excel Worksheet

Page 17: Module 2_ RFE1-V3

Tower Tower Tower Tower Detail Detail Detail Detail SnapsSnapsSnapsSnaps

Page 18: Module 2_ RFE1-V3

READY FOR ELECTRONICS1 SURVEY FORM

2013 © Samsung Electronics 26

Page 19: Module 2_ RFE1-V3

READY FOR ELECTRONICS1 SURVEY FORM

2013 © Samsung Electronics 27

Page 20: Module 2_ RFE1-V3

READY FOR ELECTRONICS1 SURVEY FORM

2013 © Samsung Electronics 28

Page 21: Module 2_ RFE1-V3

READY FOR ELECTRONICS1 SURVEY FORM

2013 © Samsung Electronics 29

Page 22: Module 2_ RFE1-V3

Obstruction FormObstruction FormObstruction FormObstruction Form

Page 23: Module 2_ RFE1-V3

READY FOR ELECTRONICS1 SURVEY FORMREADY FOR ELECTRONICS1 SURVEY FORM

On to be filled if survey engineer finds any obstruction

Circle :- Delhi

Site Name / IP Site Name ABC

Site ID / IP Site ID 123

Contact Person Address & Contact No.

0

10 m

15 m

5 m

Obstruction should be checked at Antenna Height

2013 © Samsung Electronics 31

Remarks (if any)

The distance from obstruction to be calculated with laser gun (for EMF analysis)

Azimuth (˚) Distance (m) Obstacle Ht. (m) - AGL Description

Alpha

Beta

Gamma

270

180

900 m

5 m

Page 24: Module 2_ RFE1-V3

GBM LayoutGBM LayoutGBM LayoutGBM Layout

Page 25: Module 2_ RFE1-V3

READY FOR ELECTRONICS1 SURVEY FORM

Entry to

top of tower

READY FOR ELECTRONICS1 SURVEY FORM

Circle :- Delhi Site Name / IP Site Name :- ABC Site ID / IP Site ID :- 123

Drawing should be with respect to North N=0°

2013 © Samsung Electronics 33

Samsung DU

in Rack

GBM

Samsung Antenna & RRH

SamsungAntenna & RRH

Samsung Antenna & RRH

Sec 3: 210 deg

at 20mSec 2: 100 deg

at 20m

Sec 1: 0 deg

at 20m

Road

Page 26: Module 2_ RFE1-V3

RTP Layout RTP Layout RTP Layout RTP Layout

Page 27: Module 2_ RFE1-V3

READY FOR ELECTRONICS1 SURVEY FORM

Circle: Delhi Site Name/IP Site Name: ABC Site ID/IP Site ID: 123

N=0°

Drawing should be with respect to North

2013 © Samsung Electronics 35

ROAD

2D

Page 28: Module 2_ RFE1-V3

RT Layout (if IFC provided)RT Layout (if IFC provided)RT Layout (if IFC provided)RT Layout (if IFC provided)

Page 29: Module 2_ RFE1-V3

READY FOR ELECTRONICS1 SURVEY FORM

Circle: Delhi Site Name/IP Site Name: ABC Site ID/IP Site ID: 123

2013 © Samsung Electronics 37

Page 30: Module 2_ RFE1-V3

Important PointsImportant PointsImportant PointsImportant Points

Page 31: Module 2_ RFE1-V3

α

BBBB

RTT Top View

βγ

Cable TrayRRU3m

RRU to Vertical Cable Tray=RRU(vertical Ht with Buffer) to A+AB+B to Cable Tray

AAAA CCCC

Cables

Page 32: Module 2_ RFE1-V3

Single Hole Pressure Terminal

2013 © Samsung Electronics 40

Page 33: Module 2_ RFE1-V3

Layout- 2 Door ODC

2013 © Samsung Electronics 41

Page 34: Module 2_ RFE1-V3

Layout- 3 Door ODC

2013 © Samsung Electronics 42

Page 35: Module 2_ RFE1-V3

Airmarking-2/3 Door ODC3 Door ODC Possible position of CDU & CSS

Units Equipments in Rack 3

40 FAN(1U)

39

Future (4U)38

37

36

35BBU/DU (2U)

34

33 GAP (1U)

32

AG1 (3U)31

30

29 GAP (1U)

28WiFi(2U)

27

26 GAP (1U)

25

24

2 Door ODC Possible position of CDU & CSS

Units Equipments in Rack1

40 FAN(1U)

39 GAP (1U)

38BBU/DU (2U)

37

36 GAP (1U)

35 CSS(1U)

34 GAP(1U)

33WiFi(2U)

32

31

FDP(4U)30

29

28

27

26

25

24

2013 © Samsung Electronics 43

DWDM (12U)

24

23

22

21

20

19

18

17

16

15

14

13 GAP (1U)

12

OLT(12U)

11

10

9

8

7

6

5

4

3

2

1

SMPS(13U-14U)

24

23

22

21

20

19

18

17

16

15

14

13

BB(12U)

12

11

10

9

8

7

6

5

4

3

2

1

Page 36: Module 2_ RFE1-V3

2 Door ODC Cable Position-Left hand side Roxtec

WiFi 2U

Samsung DU 2U

CSS

1U

Gap 1U

2m

DGPS Arrestor

If Roxtec on Left for

passing

CPRI,CNT-400 &

RRU Power A

RRU power

cables

CPRI cables

CNT-400 cable

DU grounding from

rear side

GPS ground cable

CNT-400 cable

ODC 2 Door Cable Routing with Roxtec on

Left side

2013 © Samsung Electronics 44

2m

0.65m

IGB-Electronics to be used to ground Samsung DU,GPS Surge Arrester & Cisco switch-CSS

Cable Inlet

CB

cables

SMPS with DCDB

either on left or right

side

cable

CNT-400

CPRI

RRU Power Cable

Ground Cable

DU Power Cable

DU Power Cable

DU position :37U & 38U in Rack 1

CSS position :35U in Rack 1

DU Ground Cable

Page 37: Module 2_ RFE1-V3

2 Door ODC Cable Position-Right Hand side Roxtec

WiFi

2U

Samsung DU 2U

CSS

1U

Gap 1U

2m

XDGPS Surge Arrestor

Roxtec on

Right for

passing

CPRI,CNT-

400 &

RRU Power SMPS with DCDB

either on left or right

side

GPS Surge

Arrestor Ground

cable

DU grounding

from rear side

CPRI cables

CNT-400

cable

ODC 2 Door Cable Routing with Roxtec on

Right side

2013 © Samsung Electronics 45

0.65m

Y

C

IGB-Electronics to be used to ground Samsung DU,GPS Surge Arrester & Cisco switch-CSS

Cable Inlet

DU ground

cable from rear

of DU

CNT-400

CPRI

RRU Power

CableGround Cable

DU Power

Cable

B

DU power cable RRU Power

Cables

DU position :37U & 38U in Rack 1

CSS position :35U in Rack 1

Page 38: Module 2_ RFE1-V3

3 Door ODC Cable Position

DU ground

cable from

Samsung CDU

2U

A

GPS

ArrestorAG1-3U

Roxtec No.1 position for

passing

CPRI & CNT-400

Roxtec No.2 will be

provided in future along

with Cable Tray to Pass

RRU Power cable

F

ODC 3 Door Cable Routing with only one Roxtec on

Right side

2013 © Samsung Electronics 46

DU power

cable

cable from

rear of DU

2m

IGB for

grounding

Samsung DU,

GPS Surge

ArrestorD

BC

Cable Inlet

position

Optional Path if Roxtec No.2 is not available/provided

CNT-400

CPRI

RRU Power Cable

Ground Cable

DU Power Cable

CE

DU position :34U-35U in Rack 3

AG1 position :30U-32U in Rack 3

RRU power

cables

DU power

cables

Page 39: Module 2_ RFE1-V3

Gamsahapnida

Thank You