Page 1 of 10 CORK INSTITUTE OF TECHNOLOGY INSTITIÚID TEICNEOLAÍOCHTA CHORCAÍ Semester 2 Examinations 2008/09 Module Title: Process Plant Services Module Code: MECH8018 School: Mechanical Engineering. Programme Title: Bachelor of Science in Process Plant Technology Programme Code: EPPTE_8_Y4 External Examiner(s): Mr. Neil Kingston; Mr. Joe Phelan Internal Examiner(s): Mr. Willie Bateman (Section B) Mr. John Healy (Section A) Instructions: Answer any 3 questions. All questions carry equal marks. Answer Section A and Section B in seperate answer books. Duration: 2 hours. Sitting: Summer 2009 Requirements for this examination: Attachments to be provided, for student reference, with this exam paper. 1 Steam Pipeline Sizing Chart – Pressure Drop Q1 (with paper) 2 CIBSE Table C4.36. -Velocity press loss factors. Q3,Q4 (with paper) 3 CIBSE Table C4.11, Page 4-16 - “Water 75 C Medium Grade Steel”. Q3 (with paper) 4 Vapour Pressure V’s Water Temperature. Q3 (with paper) 5 CIBSE Table C4.11, Page 4-17- “Water 75 C Medium Grade Steel”. Q4 (with paper) 6 Lowara HTE-HTS Series 2 Pole pumps Data Sheet Q4 (with paper) Note to Candidates: Please check the Programme Title and the Module Title to ensure that you have received the correct examination paper. If in doubt please contact an Invigilator.
Transcript
Page 1: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 1 of 10

CORK INSTITUTE OF TECHNOLOGY INSTITIÚID TEICNEOLAÍOCHTA CHORCAÍ

Semester 2 Examinations 2008/09

Module Title: Process Plant Services

Module Code: MECH8018

School: Mechanical Engineering. Programme Title: Bachelor of Science in Process Plant Technology Programme Code: EPPTE_8_Y4 External Examiner(s): Mr. Neil Kingston; Mr. Joe Phelan Internal Examiner(s): Mr. Willie Bateman (Section B) Mr. John Healy (Section A) Instructions: Answer any 3 questions. All questions carry equal marks. Answer Section A and Section B in seperate answer books. Duration: 2 hours. Sitting: Summer 2009 Requirements for this examination: Attachments to be provided, for student reference, with this exam paper.

1 Steam Pipeline Sizing Chart – Pressure Drop Q1 (with paper) 2 CIBSE Table C4.36. -Velocity press loss factors. Q3,Q4 (with paper) 3 CIBSE Table C4.11, Page 4-16 - “Water 75 C Medium Grade

Steel”. Q3 (with paper)

4 Vapour Pressure V’s Water Temperature. Q3 (with paper) 5 CIBSE Table C4.11, Page 4-17- “Water 75 C Medium Grade

Steel”. Q4 (with paper)

6 Lowara HTE-HTS Series 2 Pole pumps Data Sheet Q4 (with paper) Note to Candidates: Please check the Programme Title and the Module Title to ensure that you have received the correct examination paper. If in doubt please contact an Invigilator.

Page 2: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 2 of 10

Section A – Steam & Refrigeration Q1 a) Compare and contrast the construction and operating characteristics of a Fire Tube Boiler

with those of a Water Tube Boiler. [5 marks] b) Why is boiler feed water pre-treatment necessary? [5 marks] c) Why does TDS build up inside a steam boiler? What negative effects can high TDS have on boiler operation? How are TDS levels controlled within a steam boiler? [5 marks]

d) Steam is generated at 10 Bar g pressure inside the boiler house. A new process 65m from the boiler house required 5000 kg/h at a minimum supply pressure of 9.0 bar g. Using the steam pipe sizing chart provided suggest the most suitable pipe diameter and calculate the actual pressure available at the point of use. NB design for a maximum pressure drop of 0.1 Bar / 100m.

Reference :- [5 marks] Steam Pipeline Sizing Chart – Pressure Drop Q1 (with paper)

Q2 a). Describe with the aid of a neat sketch a typical refrigeration circuit. Label the four major components. Indicate relative pressures and liquid / gas phases after each of the four major components.

[6 marks] b) Where does flash gas occur and how does it effect the fridge cycle? [4 marks] c) Draw a neat labelled sketch of a Split Unit air conditioning system, capable of heating and

cooling the air conditioned space, when it is operating in cooling mode. [6 marks] d) Give a brief explanation of each of the following terms in relation to a cooling tower.

Induced draught. Drift. Approach. Range. [4 marks]

Page 3: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 3 of 10

Section B – Pipe work systems. Q3 The following diagram shows a reactor vessel working under vacuum.

Determine if the pump shown will cavitate under the operating conditions shown. [20 marks]

Water80 Deg

PG

Pump DetailsQ=10 cubic m/hNPSHr = 2.0m

3.0 m

1.0

m

1.0 m

8.0

m

10.5

mPressure GaugeReading 0.5 Bar gvacuum

vessel to pumpSteel Pipe connecting

Welded mild steel elbows

Reference

2 CIBSE Table C4.36. -Velocity press loss factors. Q3 (with paper) 3 CIBSE Table C4.11, Page 4-16- “Water 75 C Medium Grade Steel”. Q3 (with paper) 4 Vapour Pressure V’s Water Temperature. Q3 (with paper)

Q4 A Cleaning In Place (CIP) pipe work system is shown on the next page. Pump and pipe work sizing required for transfer of 90000 l/h of water at 75 Deg C to one of

three points on T1003, T2002 or T3007. Only one route enable at any one time. Use CIBSE Charts for steel pipe and fittings. Use all welded joints.

Page 4: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 4 of 10

10 Deg CWater at

1 m

InletSteamCond

Outlet

dP 1.1 Bar

DrainFloor

1 m1 m

P.H.E

2,7

m3

m3

m

Tank G100

Ground Floor

1st Floor Tank 1003

2nd Floor Tank 2002

3rd Floor Tank 3007

0,4

m

0,4

m

2,2 m

0,4

m

Tank 1003 CIP nozzleresidual pressure of 3 barat inlet to nozzle.

Tank 2002 CIP nozzleresidual press of 3 barat inlet to nozzle.

Tank 3007 CIP spray ballresidual press of 1 barat inlet to nozzle.

w/d = 1.0.

CIP nozzles T1003, T2002residual pressure of 3 bar

For CIBSE Table C4.36.

at inlet to nozzle.

i.e. assume mild steel pipe work

also welded mild steel elbows

Diaphragm valvesAll valves are actuated

on all pipe runs

i.e from pump to one of

Water at 75 Deg CQ=90,000 l/hPumped Volume

Only one route in use

C. T3007 Spray Ball.B. T2002 CIP nozzle.A. T1003 CIP nozzle.

at any one time

Stainless Steel Pipe workon all pipe runs.No CIBSE Charts for SS.Use CIBSE Charts for Mild Steel

residual pressure of 1 barCIP spray ball T3007

at inlet to spay ball

use a target water flowwashing of pipes + PHETo facilitate agressive

of 3m/s for CIP systems.

NOTES

3,2 m

4,2 m

PIPE SIZING EXERCISECIP SYSTEM

a) Estimate which route will be the index run.

Without completing detailed calculations use the combined pressured drops associated with straight pipe, fittings, static head and residual head to estimate which run will be the index run. [6 marks]

b) Establish the pipe diameter, ∆pl and le for the index run. [4 marks] c) Specify overall flow and pressure requirements for the pump. [8 marks] d) Select a suitable pump from the Lowara pump data sheet attached. [2 marks] 3 CIBSE Table C4.36. -Velocity press loss factors. Q4 (with paper) 5 CIBSE Table C4.11, Page 4-17- “Water 75 C Medium Grade Steel”. Q4 (with paper) 6 Lowara HTE-HTS Series 2 Pole pumps Data Sheet Q4 (with paper)

Page 5: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 5 of 10

Page 6: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 6 of 10

Page 7: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 7 of 10

Page 8: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 8 of 10

Page 9: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 9 of 10

Page 10: Module Title: Process Plant Services - CIT - Cork ... Engineering/EPPTE_8_… · Module Title: Process Plant Services Module ... dP 1.1 Bar Drain Floor 1 m P.H.E 2,7 m ... Page 4-17-

Page 10 of 10


Recommended