#UKPHC19 Moisture Risk Assessment using Wufi in Retrofit and New Build Toby Cambray, Greengauge
Transcript
  • #UKPHC19

    Moisture Risk Assessment using Wufi in Retrofit and New Build

    Toby Cambray, Greengauge

  • • Mould

    • Timber Decay

    • Corrosion

    • Efflorescence

    • Spalling

    • …

    Why Do We assess moisture risk?

  • 1. Standard Details and Principles-based design

    BS 5250

    2. The Glaser Method

    BS EN 13788

    3. Dynamic Heat and Moisture Transport

    BS EN 15026

    How Do We assess moisture risk?

    Can moisture get out faster than it gets in?

  • The Glaser method and its limitations

    • Moisture ingress (rain, rising damp)

    • Airflow from the interior (i.e. imperfect airtightness)

    • Variation of material properties with moisture content

    • Liquid moisture transport by capillary suction

    • Hygroscopic adsorption and storage

  • Storage and Transport of Moisture

  • Example: Retrofit IWI

    Vapour Diffusion

    Air Leaks

    Interstitial Condensation?

    EvaporationRain Ingress

    Capillary Suction

  • Setting up the simulation

  • Moisture Flux into and out of a piece of insulation at the ‘critical interface’

  • Results and Analysis

  • Example: New Build

  • Outputs

  • Refinement and conclusions

  • Thank you…