Monthly report August 2010 Monthly provisional values as of 21 January 2011 Eu ropean N e tw o rk o f T ransm iss ion S ys tem O pe ra to rs fo r E lec tr ic ity
Transcript
Page 1: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

Monthly report

August 2010 Monthly provisional values as of 21 January 2011

European Network of Transmission System Operators

for Electricity

Page 2: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

Table of contents Page

1 Electricity supply situation of the countries 2

2 Electricity supply representativity of the countries 3

3 Physical energy flows 4

4 Monthly imports and exports 5

5 Load flows (night) 6

6 Load flows (day) 7

7 Unavailability of international tie lines ( major events ) 8

8 Network reliability ( major events ) 10

9 Highest and lowest load on the 3rd Wednesday 11

10 Load diagrams on the 3rd Wednesday 12

11 Water reservoirs Nordic 13

12 Market information 14

General remarks and abbreviations used in the tables

- All values of production and consumption in chapter 1, 9, 10 and 11 are calculated to represent100% of the national values.

- UA_W Ukraine West represents the so-called Burshtyn Island synchronously interconnectedwith ENTSO-E

- CET Central European Time

Monthly provisional values from the ENTSO-E statistical database as of 16 December 2010

Page 3: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

ENTSO-E August 2010

1 Including deliveries from industry2 The reported figures are best estimates based on actual measurements and extrapolations.3 National monthly values as of August 20094 Operational data

1 Electricity supply situation of the countries

2

balanceCoun- Therm. Fossil Hydro Other of which Non variationtries nuclear fuels prod renew. wind identi- Total monthly [%]

fiable

AT 0 1245 4094 0 0 783 6122 -495 384 5243 5,0BA 0 555 292 0 0 0 847 97 0 944 7,4BE 4233 2667 131 423 101 0 7454 1 -544 161 6749 3,1BG 1399 1568 377 25 25 0 3369 -1042 88 2239 -5,5CH 1246 186 3985 117 2 0 5534 1 -340 296 4898 3,2CY 0 618 0 2 2 0 620 0 0 620 -1,5CZ 1944 3278 344 106 26 0 5672 1 -908 67 4697 4,1DE 11507 23037 2034 6027 2458 0 42605 1 958 740 42823 6,6DK 0 1261 1 744 539 0 2006 1 677 0 2683 n.a.EE 0 763 1 35 18 0 799 -272 0 527 n.a.ES 5421 11296 2210 4137 2794 28 23092 -766 277 22049 1,1FI 1661 1267 949 746 17 53 4676 1 1527 0 6203 n.a.FR 32391 1619 4354 1147 676 0 39511 -5881 542 33088 0,5GB 4230 17848 391 269 269 0 22738 1056 629 23165 n.a.GR 0 4206 420 179 149 0 4805 1 643 1 5447 13,0HR 0 441 378 11 9 0 830 631 9 1452 -1,4HU 1467 1393 0 0 0 0 2860 553 0 3413 11,9IE 0 1743 14 197 197 20 1974 1 38 0 2012 n.a.IS 0 1 1011 339 0 0 1351 0 0 1351 n.a.IT 0 17159 3923 1088 472 0 22170 2815 248 24737 -2,5LT 0 189 58 24 12 0 271 1 544 39 776 n.a.LU 0 216 81 20 5 0 317 258 111 464 5,0LV 0 229 94 7 3 0 330 216 0 546 n.a.ME 0 1 50 0 0 0 51 -254 0 -203 n.a.MK 0 340 121 0 0 0 461 152 0 613 0,0NI 0 448 0 61 56 1 510 184 0 694 n.a.NL 350 6538 0 686 347 0 7574 1189 0 8763 0,4NO 0 339 7373 56 56 0 7768 1 299 156 7911 n.a.PL 0 10770 293 148 126 0 11211 1 68 69 11210 4,9PT 0 2548 456 767 543 0 3771 1 628 53 4346 5,8RO 944 1809 1945 0 n.a. 0 4698 -401 8 4289 8,1RS 0 2211 776 0 0 0 2987 189 5 3171 -1,8SE 4619 68 5272 812 227 0 10771 1 -1129 0 9642 n.a.SI 507 339 323 0 0 0 1169 -208 0 961 6,9SK 1161 364 590 38 0 0 2153 1 -102 43 2008 2,9

ENTSO-E 73080 118560 42341 18211 9129 885 253077 1 380 3926 249531 n.a.UA_W 0 302 14 0 0 0 316 -6 0 310 21,1

Net generation in GWh Exchange Pump

in GWh in GWh

Consumption in GWh

2

4

3

Page 4: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

ENTSO-E August 2010

All representativities of the national generation and consumption values on page 2 used to calculatevalues at a representativity of 100% as stated in the table above:

Electricity supply representativity of the countries2

3

Coun- Thermal Fossil Hydro Other Non Consumptiontries nuclear fuels prod renew able identi-

fiable

AT 100 100 100 100 100 100BA 100 100 100 100 100 100BE 100 100 100 100 100 100BG 100 100 100 100 100 100CH 100 100 100 100 100 100CY 100 100 100 100 100 100CZ 100 100 100 100 100 100DE 100 100 100 100 100 100DK 100 100 100 100 100 100EE 100 100 100 100 100 100ES 100 97 100 95 100 98FI 100 100 100 100 100 100FR 100 100 100 100 100 100GB 100 100 100 100 100 100GR 100 100 100 100 100 100HR 100 100 100 100 100 100HU 100 100 100 100 100 100IE 100 100 100 100 100 100IS 100 100 100 100 100 100IT 100 100 100 100 100 100LT 100 99 98 99 100 100LU 100 100 100 100 100 100LV 100 100 100 100 100 100ME 100 100 100 100 100 100MK 100 100 100 100 100 100NI 100 100 100 100 100 100NL 100 100 100 100 100 100NO 100 100 100 100 100 100PL 100 100 100 100 100 100PT 100 95 100 100 100 97RO 100 100 100 100 100 100RS 100 100 100 100 100 100SE 100 100 100 100 100 100SI 100 100 100 100 100 100SK 100 100 100 100 100 100

UA_W 100 100 100 100 100 100

Representativities of the national values in %

Page 5: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

IS

FISENO

DK

DK

DE

LU

BE

BY

MD

RUIE

NI

GB

PT ES

CH

IT

SI

GRMK

RS

ME

BA

BG

RO

FR AT

CZ

SK

HU

HR

LV

LT

EE

PL

ENTSO-E members

Not ENTSO-E members

AL

NL

MA DZ TN

TR

RU

Values in GWh

CY

UA_W

UA

UA_W

UA

RU

BY

ENTSO-E August 2010

Not ENTSO-E members:Albania, Belarus, Morocco, Republic of Moldavia, Republic of Turkey, Russia, Ukraine and Ukraine West

These physical energy flows were measured on the cross-frontier transmission lines (< 110 kV) listed in tablecharacteristics of the cross-frontier lines published in the Statistical Yearbook. These values may differ from theofficial statistics and the exchange balances in chapter 1.

Total physical energy flows:

Sum of physical energy flows between ENTSO-E countries:

3 Physical energy flows

4

30391GWh

27698GWh

← 450 27 →←

702 168 →

← 93

← 111

210 →

8 →

← 12

6

52 →1168

← 4

80← 412

21 →

← 233

406

← 1

730← 246

← 3

82

← 56014

431 →733 →

←7

95

78 →

583

← 576

405 →

127

← 1

6615

5 →

132 →

45

75 →

← 691

← 43

478

786 →

2408 →

← 4

58839 →

← 220

213

← 114

206 →

← 104

← 14 9 →

← 1

5

11 →

9 →

← 96

11

20 →

← 7337 →

← 15277 →

← 2

14

← 1019 →

← 4

81

← 54

291 →

← 435

204

24 →

177 →

← 32

2

← 25

2

← 8

7

80 → ← 1

15

← 119

← 2

03

41 →

← 209← 76 18

← 948

1

02

570 →

← 504

7

8

415 →← 72

← 22 ← 5

396 →

64 →

← 96

← 1

6

← 11

1 →

← 382

← 4

86

← 23

← 990

78 →

← 11

← 18

3

← 4645 →

← 2

84

← 127

4

1297

← 357

17 →

12 →

← 34

2

3 →

6114 →

← 2

22

← 4

1

← 6

170 →

240

1

60

Page 6: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

ENTSO-E August 2010

Other III1: Albania, Belarus, Morocco, Republic of Moldavia, Republic of Turkey, Russia and Ukraine

Overview of the monthly imports and exports in GWh

Sum of the monthly imports and exports in GWh

Monthly imports and exports4

5

Importing countriesExporting countries

AT BA BE BG CH CZ DE DK EE ES FI FR GB GR HR HU IE IT LT LU LV ME MK NI NL NO PL PT RO RS SE SI SKUA_W

Other III1

AT - - - - 450 27 702 - - - - - - - - 168 - 93 - - - - - - - - - - - - - 170 - - -BA - - - - - - - - - - - - - - 111 - - - - - - 210 - - - - - - - 8 - - - - -BE - - - - - - - - - - - 126 - - - - - - - 52 - - - - 1168 - - - - - - - - - -BG - - - - - - - - - - - - - 480 - - - - - - - - 412 - - - - - 21 233 - - - - 0CH 14 - - - - - 406 - - - - 246 - - - - - 1730 - - - - - - - - - - - - - - - - -CZ 382 - - - - - 560 - - - - - - - - - - - - - - - - - - - 14 - - - - - 431 - -DE 733 - - - 795 78 - 583 - - - 0 - - - - - - - 435 - - - - 576 - 405 - - - 127 - - - -DK - - - - - - 166 - - - - - - - - - - - - - - - - - - 155 - - - - 132 - - - -EE - - - - - - - - - - 45 - - - - - - - - - 284 - - - - - - - - - - - - - 45ES - - - - - - - - - - - 75 - - - - - - - - - - - - - - - 691 - - - - - - 486FI - - - - - - - - 61 - - - - - - - - - - - - - - - - 0 - - - - 43 - - - 0FR - - 478 - 786 - 2408 - - 458 - - 1297 - - - - 839 - - - - - - - - - - - - - - - - -GB - - - - - - - - - - - 4 - - - - - - - - - - - 220 - - - - - - - - - - -GR - - - 0 - - - - - - - - - - - - - 213 - - - - 0 - - - - - - - - - - - 114HR - 206 - - - - - - - - - - - - - 3 - - - - - - - - - - - - - 0 - 104 - - -HU 14 - - - - - - - - - - - - - 342 - - - - - - - - - - - - - 9 15 - - 0 11 -IE - - - - - - - - - - - - - - - - - - - - - - - 17 - - - - - - - - - - -IT 2 - - - 9 - - - - - - 96 - 11 - - - - - - - - - - - - - - - - - 12 - - -LT - - - - - - - - - - - - - - - - - - - - 20 - - - - - - - - - - - - - 110LU - - 152 - - - 77 - - - - - - - - - - - - - - - - - - - - - - - - - - - -LV - - - - - - - - 0 - - - - - - - - - 214 - - - - - - - - - - - - - - - 0ME - 10 - - - - - - - - - - - - - - - - - - - - - - - - - - - 19 - - - - n.a.MK - - - 0 - - - - - - - - - 481 - - - - - - - - - - - - - - - 0 - - - - -NI - - - - - - - - - - - - 0 - - - 54 - - - - - - - - - - - - - - - - - -NL - - 183 - - - 291 - - - - - - - - - - - - - - - - - - 240 - - - - - - - - -NO - - - - - - - 204 - - 24 - - - - - - - - - - - - - 160 - - - - - 177 - - - 0PL - - - - - 322 25 - - - - - - - - - - - - - - - - - - - - - - - 2 - 87 - 0PT - - - - - - - - - 80 - - - - - - - - - - - - - - - - - - - - - - - - -RO - - - 115 - - - - - - - - - - - 119 - - - - - - - - - - - - - 203 - - - 41 0RS - 209 - 0 - - - - - - - - - - 76 18 - - - - - 94 222 - - - - - 8 - - - - - 41SE - - - - - - 102 357 - - 570 - - - - - - - - - - - - - - 504 78 - - - - - - - -SI 6 - - - - - - - - - - - - - 415 - - 72 - - - - - - - - - - - - - - - - -SK - - - - - 22 - - - - - - - - - 539 - - - - - - - - - - 6 - - - - - - 64 -

UA_W - - - - - - - - - - - - - - - 96 - - - - - - - - - - - - 16 - - - 11 - -Other III1 - - - 0 - - - - 46 0 990 - - 0 - - - - 460 - 127 n.a. - - - 11 0 - 23 1 - - - - -

import export import exportAT 1151 1610 IT 2947 130BA 425 329 LT 674 130BE 813 1346 LU 487 229BG 115 1146 LV 431 214CH 2040 2396 ME n.a. n.a.CZ 449 1387 MK 634 481DE 4737 3732 NI 237 54DK 1144 453 NL 1904 714EE 107 374 NO 910 565ES 538 1252 PL 503 436FI 1629 104 PT 691 80FR 547 6266 RO 77 478GB 1297 224 RS 479 668GR 972 327 SE 481 1611HR 944 313 SI 286 493HU 943 391 SK 529 631IE 54 17 UA_W 116 123

Page 7: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

AT

CH

ES

IT

FR

SI

BA

RS

HU

CZ

SK

LU

BE

NL

GB

DK

DE

PL

SE

BY

UA

_W

AL

GR

BG

RO

PT

HR

MK

MD TR

I = Import balanceE = Export balance

MA

DK

UA

ME

Synchronous operation with ENTSO-E region

LTR

U

LVEE

RU

NO

FIIE

NI

Sum of load flows in MW ENTSO-E = Total =

August 20105

6 ENTSO-E August 2010

Load flows (night) on 18.08.10 at 03:00 a.m. CET in MW

I = 9

2

E =

771

E =

1063

I = 9

19

E =

1254

E =

774

I = 5

56

E =

628

I = 1

731

E =

7302

I = 9

09

I = 5

58

I = 3

447

I = 5

74

I = 2

63

I = 2

72

n.a

.

I = 2

41

I = 1

550

I = 1

598

I = 5

7

E =

305

E =

388

E =

755

E =

18

E =

363

I = 0

E =

2009

I = 1

860

I = 1

11

I = 2

52E

= 10

6

I = 1

404

729

566

4484

88

235

170

27412

23

85

1380

536453

13

132

412

2488

46

1713

449

985

8

264

1434

1114

709 596

907

548

5

444

28

263

268

217616

1404

336

449 1325

2323

228

2006

1322

146

88

160

271

355

21

568

85

78

64

18

17

54

26815

0134

22

16

621

25

2

22715

8

54378

121

71

5 401

93277

67

31

72

409

1443

11

7

12

1

5

319

353

501

379

229

30

718

26

52

36327 MW 32998 MW

14

34

6

I = 1

60

Page 8: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

AT

CH

ES

IT

FR

SI

BA

RS

HU

CZ

SK

LU

BE

NL

GB

DK

DE

PL

SE

BY

UA

_W

AL

GR

BG

RO

PT

HR

MK

MD TR

I = Import balanceE = Export balance

MA

DK

UA

ME

Synchronous operation with ENTSO-E region

LTR

U

LVEE

RU

NO

FIIE

NI

Sum of load flows in MW ENTSO-E = Total =

August 20106

7ENTSO-E August 2010

Load flows (day) on 18.08.10 at 11:00 a.m. CET in MW

I = 6

6

I = 0

E =

1481

E =

847

E =

475

I = 3

884

I = 6

81E

= 36

4

E =

1508

I = 2

597

E =

7960

I = 1

603

I = 9

92

I = 1

026

I = 1

181

I = 2

37

I = 3

356

I = 7

00

I = 2

79

I = 3

06

n.a

.

I = 2

05

I = 1

52

I = 1

178

E =

1537

E =

101

I = 6

25

E =

561

E =

306

E =

715

E =

606

I = 1

07E

= 1

43

504

48

1599

281

244

204

126

3372

98

70

1573

633

562

77

520

470

68907

222

1966

310317

668

590

776

552 581

115

79825

194

410

348

194

710

701

110

28

1029 1036

3425

211992

1078

389

180

69

211

14

47

258

107

271

15

6

269

103

241

45

30

608

23

7

443

762

590

52

695

48

6

772

127

76

311

263

13103

320

163

89

84

251

7

1462

173

19

8

14143

1221

286

751

106

688

104

40433 MW 36288 MW

12

6

E =

191

2

Page 9: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

0,5 mm 2,0 mm 2,5 mm1,5 mm1,0 mm

20.02.01 08:21 AM21.02.01 08:29 AM22.02.01 10:03 AM23.02.01 08:27 AM

ENTSO-E August 2010 8

Unavailability of international tie lines( major events with sum over 1300 minutes ) 7

August 2010

11.05.09 05:47 AM R1

13.1.1

NL / -DE / Rommerskirchen 380

Maasbracht kV / 1698 MVA

6341 min

04.06.07 07:05 AM R3

163.1.1

NO / Kristiansand - DK_W / Tjele 250 MVA

26575 min

07.07.08 01:09 AM R9

163.1.2

NO / Kristiansand - DK_W / Tjele 250 MVA

5191 min

01.12.09 00:00 AM R1,R9

103.1.1

DE / Tiengen - CH / Beznau 380 kV / 1278 MVA

4944 min

09.12.09 07:31 AM R110.12.09 07:19 AM R1

104.1.1

DE / Kühmoos - CH / Asphard 380 kV / 1340 MVA

1145 min

04.07.09 08:58 AM R1

71.1.1

FR / Vigy - DE / Uchtelfangen 380 kV / 1790 MVA

20678 min

20.11.07 08:02 AM R1

161.2.1

DK_W / Kassø - DE / Flensburg 220 kV / 332 MVA

421 min

25.12.09 08:56 PM R8

124.1.1

CH / - IT / Gorlago 380

Robbia kV / 1340 MVA

827 min

14.08.07 08:23 AM R116.08.07 08:53 AM R1

91.1.2

FR / Albertville - IT / Rondissone 380 kV / 1745 MVA

2505 min

09.11.08 09:30 AM R120.11.08 07:41 AM R1

41.2.1

BE / Aubange - LU / Belval 150 kV / 157 MVA

5046 min

12.10.09 08:24 AM R1

83.1.1

FR / Sierentz - DE/CH / Asphard 380 kV / 1660 MVA

26213 min

14.02.09 00:55 AM R626.02.09 02:51 PM R6

164.1.1

NO / Kristiansand - DK_W / Tjele 350 MVA

3842 min

23.12.08 06:24 AM R7

72.1.1

FR / - DE / Eichstetten 220

Vogelgrün kV / 480 MVA

408 min

24.03.08 03:12 AM R6

163.1.1

NO / Kristiansand - DK_W / Tjele 250 MVA

768 min

08.09.08 07:55 AM R3

25.1.1

BE / Gramme - NL / Maasbracht 380 kV / 1207 MVA

4845 min

24.12.09 09:36 PM R8

93.1.1

FR / Villarodin - IT / Venaus 380 kV / 956 MVA

928 min

01.12.09 00:00 AM R1

102.3.2

DE / - CH / Laufenburg 380

Kühmoos kV / 1620 MVA

4936 min

01.09.08 00:00 AM R1

41.3.1

BE / Aubange - LU / Belval 150 kV / 157 MVA

43200 min

01.05.09 00:00 AM R1

191.3.1

LU / Flebour - DE / Bauler 220 kV / 492 MVA

10706 min

14.10.08 07:34 AM R10

161.3.2

DK_W / Kassø - DE / Audorf 380 kV / 1382 MVA

427 min

13.05.09 07:10 AM R119.05.09 07:00 AM R1

11.1.1

NL / Meeden - DE / Diele 380

kV / 1382 MVA

1275 min

16.12.09 07:37 AM R917.12.09 02:20 PM R9

14.12.09 07:23 AM R1

123.1.1

CH / Riddes - IT / Avise 220 kV / 331 MVA

3098 min

01.06.09 00:00 AM R1

82.2.1

FR / Gènissiat - CH / Verbois 220 kV / 428 MVA

2723 min

10.03.09 08:07 AM R117.03.09 00:59 PM R1

161.2.1

DK_W / Kassø - DE / Flensburg 220 kV / 332 MVA

507 min

18.08.09 01:05 PM R906.08.09 04:25 PM R2

27.1.1

NL / Eemshaven - NO / Feda 450 kV / 700 MVA

5060 min

01.11.09 00:00 AM R2

235.1.1

ES / Brovales - PT / Alqueva 400 kV / 1347 MVA

8005 min

16.12.09 07:19 AM R1

121.3.1

CH / Soazza - IT / Bulciago380 kV / 1340 MVA

643 min

14.12.09 07:31 AM R1

221.1.1

GB/ Sellindge - FR / Mandarins 270 kV / 1000 MVA

265 min

STENKULLEN

BENTWISCH

Reasons : R1 R2 - Repair

- Maintenance

R3 New constructions -R4 - Overload (also calculated break)R5 - False operation R6 - Failure in protection device or other element R7 Outside impacts (animals, trees, fire, avalanches, ...)R8 - Very exceptional conditions (weather, natural disaster, ...)

-

R9 - Other reasonsR10 - Unknown reasons

PT ES

FR

BE

LU

IE

NI

GBNL

DK

DE

CH

IT

SI

NO

MA

380 kV

±220 kV

±400 kV

±450 kV

±250 kV

350 kV ±285 kV

±270 kV

2

2

2

601

233

232

234

151

151

94

92

93

91

153

235

123

125

121

122

132 181

205

201

124

141

142112

111

162

82

8183

72

51

52

41

2513

15

11

27

163 164

166772

776

771

165168

167

170

161

26

71

192

221

222

225

191

104

102103

105

MELOUSSA 1

ALTO LINDOSO

LAGOAÇA

POCINHO

FALAGUEIRA

ALQUEVA

CARTELLE

ALDEADAVILA

SAUCELLE

CEDILLO

BROVALES

ARKALE

BIESCAS

VICH

HERNANI

PRAGNERES

BAIXAS

TRINITE VICTOR

LUCCIANA

ALBERTVILLE

VILLARODIN

CAMPOROSSO

SUVERETO

RONDISSONE

AVISE

CAGNO

MESE

LIENZ

PONTE

SIERENTZ

VOGELGRÜN

VIANDEN

FLEBOURAUBANGE

MAASBRACHT

HENGELO

MEEDEN

BORSSELE

EEMSHAVEN

ROOST

HEISDORF

VAN EYCKZANDVLIET

MONCEAU

AVELGEM ACHENE

MOULAINE

LONNY

CHOOZAVELIN

MASTAING

MANDARINS

AUCHENCROSH

TANDRAGEE

LOUTH

SELLINDGE

BALLYCRONANMORE

NIEDERSTEDEM

ROMMERSKIRCHEN

GRONAU

SIERSDORF

DIELE

GEERTRUIDENBERG

BAULERBELVAL

TRIER

QUINT

MÜHLBACH

ST AVOLD

VIGY

ENSDORF

AUDORF FLENSBURG

KASSO

TJELE

FEDA

ENSTED

UCHTELFANGEN

EICHSTETTEN KÜHMOOS

TROSSINGEN

GURTWEIL TIENGEN

BASSECOURTMAMBELIN

CHAMOSONBOIS TOLLOT

VERBOIS

ASPHARD

LAUFENBURG

BEZNAU

OBERMOOWEILER

WINKELN

MEININGEN

LINDOME

RITSEMOFOTEN

AJAURE

HASLE BORGVIK

NEDRE RØSSAGÅ

BJAEVERSKOV

HOVEGÅRD

MÖRAP 1 & 2

SÖDERÅSEN

BORRBY HASLE

VESTER HASSING

KRISTIANSAND

OBERSILACH

BÜRS

Y-MEININGEN

HERBERTIGEN

PRADELLA

GENISSIAT

ST. TRIPHON

RIDDES SERRA

CORNIER

VALLORCINE LA BÂTIAZ

VENAUS

VALPELLINE

PALLANZENO

MENDRISIO

LAVORGO

ROBBIA

MUSIGNANO

SOAZZA

BULCIAGO

GORLAGO

SOVERZENE

PADRICIANO

REDIPUGLIA

GALATINA

DIVAČA

PODLOG

SAN FIORANO

ALL’ACQUA

GORDUNO

ARGIA

PUERTO DE LA CRUZ

AT 01.11.09 00:00 AM R2

152.1.1

FR / Lac d'Oo - ES / Benós 110 kV / 76 MVA

12564 min

09.12.09 03:02 PM R917.12.09 10:35 PM R9

02.12.09 10:47 PM R605.12.09 01:05 AM R605.12.09 02:58 AM R6

221.2.1

GB/ Sellindge - FR / Mandarins 270 kV / 1000 MVA

464 min

1 0 0 A0 .1 0:0 M .07 0 R1

. .18 11

S e e B sF / tz / a s c rt R i r n - CH e ou

1V / 40 VA 380 k 3 M

4 m n1 5 i2 4

25.01.10 07:39 AM R1

72.1.1

FR / Vogelgrün - DE / Eichstetten 220 kV / 480 MVA

3484 min

06.03.10 07:16 AM R2

123.1.1

CH / Riddes - IT / Avise 220 kV / 331 MVA

4770 min

01.04.10 06:41 PM R503.04.10 00:05 AM R627.04.10 00:01 AM R1

221.2.1

GB/ Sellindge - FR / Mandarins 270 kV / 1000 MVA

8745 min

18.05.10 06:03 AM R918.05.10 09:00 PM R2

27.1.1

NL / Eemshaven - NO / Feda 450 kV / 700 MVA

14037 min

23.08.10 11:49 AM R3

232.2.1

PT / Lagoaça 3 - ES / Aldeadávila 220 kV / 389 MVA

12251 min

01.07.10 00:00 AM R1

222.2.1

NI / Ballycronanmore - GB/ Auchencrosh 250 kV / 250 MVA

9568 min

05.07.10 08:25 AM R1

102.4.1

CH/Laufenburg - DE/Kühmoos 380 kV / 1620 MVA

4798 min

29.04.10 07:19 AM R9

82.5.1

FR / Cornier - CH / Riddes 220 kV / 360 MVA

2101 min

15.02.10 08:20 AM R1

601.1.1

ES / P. de la Cruz - MA / Melloussa1 380 kV / 715 MVA

1583 min

24.06.10 07:46 AM R125.06.10 07:49 AM R128.06.10 09:18 AM R121.06.10 08:31 AM R129.06.10 07:57 AM R130.06.10 10:02 AM R1

15.1.2

NL / Hengelo - DE / Gronau 380 kV / 1790 MVA

2660 min

01.08.10 00:00 AM R9

71.2.1

FR / St-Avold - DE / Ensdorf 220 kV / 282 MVA

5336 min

01.03.10 09:59 AM R4

41.1.2

BE / Aubange - LU / Belval 220 kV / 358 MVA

29952 min

01.08.08 00:00 AM R104.08.08 07:22 AM R1

142.2.1

CH / Pradella - AT / Westtirol 380 kV / 1340 MVA

3063 min

01.08.08 00:00 AM R104.08.08 07:22 AM R1

142.2.1

CH / Pradella - AT / Westtirol 380 kV / 1340 MVA

3063 min

03.03.10 07:03 AM R9

141.2.1

CH / Winkeln - AT / Meiningen 220 kV / 776 MVA

2047 min01.08.10 00:00 AM R4

123.3.1

CH / Serra - IT / Pallanzeno 220 kV / 370 MVA

8308 min

27.03.10 07:19 AM R128.03.10 07:32 AM R1

25.1.2

NL / Maasbracht - BE / Van Eyck 380 kV / 1270 MVA

1023 min

01.06.10 10:54 AM R902.06.10 06:52 AM R929.06.10 06:54 AM R9

123.1.1

CH / Riddes - IT / Avise 220 kV / 331 MVA

1658 min

07.04.10 07:50 AM R115.04.10 03:31 PM R1

191.4.1

LU / Roost - DE / Bauler 220 kV / 490 MVA

953 min

30.03.10 07:28 AM R1

192.1.1

LU / Heisdorf - DE / Trier 220 kV / 492 MVA

493 min

03.05.10 07:02 AM R104.05.10 06:39 AM R105.05.10 06:48 AM R106.05.10 07:02 AM R107.05.10 06:52 AM R110.05.10 07:22 AM R111.05.10 06:49 AM R112.05.10 07:01 AM R117.05.10 08:03 AM R118.05.10 07:45 AM R119.05.10 07:16 AM R1

192.2.1

LU / Heisdorf - DE / Quint 220 kV / 492 MVA

6083 min

01.07.10 00:00 AM R926.07.10 07:03 AM R1

82.5.1

FR / - CH / Riddes220

Cornier kV / 346 MVA

5786 min

23.08.10 08:05 AM R901.08.10 00:00 AM R3

111.2.1

DE / Herbertingen - AT / Bürs 220 kV / 389 MVA

20575 min

06.04.10 09:39 AM R1

151.3.1

FR / Argia - ES / Arkale 220 kV / 369 MVA

4597 min

07.06.10 08:53 AM R1

102.4.1

DE / - CH / Laufenburg 380

Kühmoos kV / 1620 MVA

3368 min

06.04.10 09:19 AM R1

92.1.1

FR / - IT / 220

Trinite Victor Camporosso kV / 320 MVA

4742 min

05.08.10 08:07 AM R1

124.1.2

CH / - IT / an Fiorano 380

Robbia S kV / 1340 MVA

14922 min

15.08.10 00:02 AM R9

82.1.2

FR / Bois-Tollot - CH / Chamoson 380 kV / 1564 MVA

1349 min

26.07.10 07:17 AM R1

102.1.1

DE/ - CH/Laufenburg 220

Gurtweil kV / 485 MVA

3329 min

03.06.10 09:32 AM R1

105.1.1

DE / - CH / Laufenburg 380

Trossingen kV / 1580 MVA

3011 min

01.04.10 08:37 AM R1

233.1.1

PT / Falagueira - ES / Cedillo 380 kV / 1621 MVA

622 min

02.08.10 07:25 AM R1,R2

52.1.1

BE / Aubange - FR / Moulaine 220 kV / 381 MVA

6379 min

01.06.10 00:01 AM R1

91.1.1

FR / Albertville - IT / Rondissone 380 kV / 1745 MVA

3972 min

23.05.10 07:52 AM R4

161.4.1 DK / Ensted - DE / Flensburg UW Nord 150 kV/ 150 MVA

1500 min

01.07.10 00:00 AM R3

222.1.1

NI / Ballycronanmore - GB/ Auchencrosh 250 kV / 250 MVA

9568 min

21.06.10 08:57 AM R1

51.1.1

BE / Monceau - FR / Chooz 220 kV / 362 MVA

4782 min

07.06.10 09:06 AM R1

102.2.1

DE / - CH / Laufenburg 220

Kühmoos kV / 469 MVA

3349 min

16.06.10 07:26 AM R117.06.10 07:34 AM R118.06.10 08:10 AM R121.06.10 08:31 AM R122.06.10 07:35 AM R123.06.10 08:23 AM R1

15.1.1

NL / Hengelo - DE / Gronau 380 kV / 1790 MVA

3028 min

12.07.10 09:19 AM R10

161.2.1

DK / Kassø - DE / Flensburg 220 kV / 332 MVA

4735 min

23.07.10 11:20 AM R1

123.2.1

CH / Riddes - IT / Valpelline 220 kV / 331 MVA

3265 min

14.06.10 07:56 AM R915.06.10 06:35 AM R9

102.3.1

DE / Kühmoos - CH / Laufenburg 220 kV / 469 MVA

1290 min

01.06.10 07:02 AM R2

103.1.1

DE / Tiengen - CH / Beznau 380 kV / 1278 MVA

35056 min

01.06.10 07:01 AM R1

103.1.2

DE / Tiengen - CH / Beznau 220 kV / 370 MVA

29478 min

19.07.10 07:23 AM R1

102.3.1

DE/Kühmoos - CH/Laufenburg 220 kV / 469 MVA

3156 min

16.08.10 07:11 AM R1

121.1.1

CH / Lavorgo - IT / Musignano 380 kV / 1278 MVA

16415 min

06.07.10 03:03 PM R1

82.2.2

FR / Génissiat - CH / Verbois 220 kV / 428 MVA

3110 min

21.07.10 11:27 AM R1

102.2.1

DE/ - CH/Laufenburg 220

Kühmoos kV / 492 MVA

2879 min

28.07.10 02:54 PM R1

102.1.2

DE/ - CH/Laufenburg 220

Gurtweil kV / 469 MVA

2694 min

2 . 0 : 0 AM 1 . 7 1 7 0 R0 0 1

.8 .2 11

S e e / L fe u gFR / i tz - CH au nbr n r

380 V 4 VA k 3 M/ 1 0

2 4 mi0 0 n

Page 10: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

0,5 mm 2,0 mm 2,5 mm1,5 mm1,0 mm

20.02.01 08:21 AM21.02.01 08:29 AM22.02.01 10:03 AM23.02.01 08:27 AM

Unavailability of international tie lines( major events with sum over 1300 minutes ) 7

August 2010

ENTSO-E August 20109

Reasons : R1 R2 - Repair

- Maintenance

R3 New constructions -R4 - Overload (also calculated break)R5 - False operation R6 - Failure in protection device or other element R7 Outside impacts animals, trees, fire, avalanches, ...)R8 - Very exceptional conditions (weather, natural disaster, ...)

- (

R9 - Other reasonsR10 - Unknown reasons

01.09.09 00:00 AM R1

401.1.1

SE / Kruseberg - DE / Herrenwyk 450 kV / 600 MVA

5241 min

01.08.08 00:00 AM R104.08.08 07:22 AM R1

142.2.1

CH / Pradella - AT / Westtirol 380 kV / 1340 MVA

3063 min

07.05.08 07:00 AM R1

132.1.1

AT / - IT / 220 kV / 257 MVA

Lienz Soverzene

3480 min

21.09.09 09:08 AM R122.09.09 08:46 AM R123.09.09 08:35 AM R123.09.09 07:35 PM R124.09.09 08:12 AM R125.09.09 08:00 AM R1

271.1.1

RS / Nis - BG / Sofija Zapad 380 kV / 1309MVA

2751 min

01.09.09 00:00 AM R1

171.1.1

CZ / Sokolnice - AT / Bisamberg 220 kV / 269 MVA

2313 min

09.07.07 02:20 PM R916.07.07 01:20 PM R7

182.1.1

AT / Kainachtal- SI / Maribor 380 kV / 1540 MVA

541 min

13.12.08 20:07 AM R4

282.1.1

AL / Fierza - RS / Prizren 220 kV / 270 MVA

1103 min

07.05.07 00:00 AM R9

341.1.1

MK / Kr.Palanka - BG / Skakavica 110 kV / 123 MVA

18660min

01.09.08 00:00 AM R1

165.1.1

DK_W / V. Hassing - SE / Stenkullen 125 MVA

4184 min

01.08.09 08:00 AM R1

201.1.1

IT / Redipuglia - SI / Divaca 380 kV / 1619 MVA

39420 min

06.10.09 08:34 AM R108.10 09 08:13 AM R109.10.09 08:08 AM R1

391.3.1

RS / Kosovo B - MK / Skopje 5 380 kV / 1218 MVA

1722 min

12.11.08 10:24 AM R1

264.1.1

RS / Sip - RO / Gura Vãii 110 kV / 90 MVA

1550 min

04.11.09 07:14 AM R105.11.09 07:07 AM R1

115.10.1

DE / Pleinting - AT / St. Peter 220 kV / 518 MVA

1046 min

13.04.08 08:37 AM R114.04.08 08:00 AM R115.04.08 08:00 AM R116.04.08 08:00 AM R117.04.08 08:00 AM R118.04.08 08:00 AM R1

241.1.1

MK / Dubrovo - GR / Thessaloniki 380 kV / 1300 MVA

3443 min

14.04.09 08:26 AM R115.04.09 08:33 AM R116.04.09 08:07 AM R117.04.09 08:00 AM R121.04.09 08:12 AM R123.04.09 09:19 AM R1

242.1.1

MK / - GR / 400 kV / 1300 MVA

Bitola Meliti

2718 min

08.09.09 06:52 AM R109.09.09 06:54 AM R110.09.09 06:54 AM R111.09.09 07:05 AM R114.09.09 06:47 AM R116.09.09 06:52 AM R1

111.2.1

DE / Herbertingen - AT / Bürs 220 kV / 389 MVA

3648 min

03.08.09 07:50 AM R1

700.1.2

PL / Kr.Iskrzynia - SK / Lemešany 400 kV / 1252 MVA

6146 min

15.10.09 07:44 AM R9

142.1.1

CH / Pradella - AT / Westtirol 380 kV / 1340 MVA

1927 min

29.07.09 07:11 AM R230.07.09 06:52 AM R1

116.2.1

DE / Memmingen - AT / Westtirol 220 kV / 762 MVA

1151 min

384

06.07.09 11:40 AM R120.07.09 06:21 AM R123.07.09 09:02 AM R1

115.5.1

DE / Altheim - AT / St. Peter 220 kV / 301 MVA

1089 min

17.11.09 07:37 AM R1

111.2.1

DE / Herbertingen - AT / Bürs 220 kV / 389 MVA

637 min

12.05.09 06:29 AM R113.05.09 07:46 AM R126.05.09 06:37 AM R1

115.9.1

DE / Pirach - AT / St. Peter 220 kV / 518 MVA

1429 min

01.04.09 05:39 AM R1

753.1.1

RO / Isaccea - MD / Vulcanesti 400 kV / 1135 MVA

42861 min

17.06.09 09:33 PM R6

301.1.1

GR/Thessaloniki - BG/Blagoevgrad 400 kV / 1309 MVA

1298 min

15.06.09 07:22 AM R116.06.09 07:08 AM R117.06.09 07:18 AM R118.06.09 07:08 AM R122.06.09 07:26 AM R123.06.09 07:11 AM R124.06.09 07:06 AM R125.06.09 07:36 AM R126.06.09 07:18 AM R1

384.3.1

RS/Pozega - ME/Pljevlja 2 220 kV / 365 MVA

5442 min

07.09.09 07:10 AM R1

171.2.1

CZ / Sokolnice - AT / Bisamberg 220 kV / 269 MVA

4885 min

14.09.09 07:53 AM R115.09.09 08:20 AM R1

08.09.09 05:50 AM R7

291.1.1

AL / Elbassan - GR / Kardia400 kV / 1300 MVA

2476 min

+ + + +

DE

AT

PL

CZ

SK

SI

HU

HR

BA

ME

MK

RS

GR

BG

RO

UA_W

LT

LV

EE

FI

SE

TR

MD

UA

BY

RU

RU

AL

±450 kV

±400 kV

±400 kV 400 kV DC

181 182

352

251

364

371

332

331

383

205

382 384

391

281

282

292 241

301

342

273

761

760

272

263

264

262

750

753

741740

720

752

731

730

261

271

277 278 275

341

242

291

362

363

361

201

351

141

142

111

116

117

115172

321

322

501

502

401162

171

430 410 404

700

443444460

450

704

701

703

702

711710212

211

440

721

722

424

420

166772

776

771 773 777 801

780

800804

802

803

790

810

813

812

820

830 831

851

852

856 855

854

881882

880

850

853

861

860

864863

841

811

165168

167

169

170

883

751

OBERMOOWEILER

MEININGEN

MEMMINGEN

WESTTIROL

DELLMENSINGEN

LEUPOLZ

OBERBRUNN

SILZ

PLEINTING

ST. PETER

PŲEŠTICE

HRADEC ZÁPAD

HRADEC VÝCHOD

SŁUPSK

NOŠOVICE

LÍSKOVEC

KROSNO

DOBRZEN

WIELOPOLE

SOVETSK JURBARKAS

KRUONIO HAE

ŠIAULIAI/TELŠIAI BELORUSSKAYA

STÄRNÖ

KOPANINA

BUJAKÓW

ALBRECHTICE

ETZENRICHT

ROEHRSDORF

HERRENWYK

KRUSEBERG

RAUMO

KINGISEPP

KEMINMAA

PETÄJÄSKOSKI

OSSAUSKOSKI

VARANGERBOTN

KYMI

YLLIKKÄLÄ VIBORG

PÜSSI

SINDI

TEC-1 TEC-2

FORSMARK

SVARTBYN

LETSI

KALIX

IVALO

STENKULLEN

LINDOME

RITSEMOFOTEN

HALDENNEA

AJAURE

HASLE JÄRPSTRÖMMENBORGVIK

NEDRE RØSSAGÅ

SKOGSSTÄTER

BJAEVERSKOV

GØLØRSEGÅRDHOVEGÅRD

TEGLSTRUPGÅRD

MÖRAP 1 & 2

BORRBY HASLE

BENTWISCH

KRAJNIK

MIKUŁOWA

VIERRADEN

HAGENWERDER

PIRACH

ALTHEIM

SIMBACH

SCHÄRDING

OBERSILACH KAINACHTAL

BÜRS

PADRICIANO

REDIPUGLIA

GALATINA

DIVAČA

PODLOG MARIBOR

DÜRNROHR BISAMBERG

WIEN S.O.

NEUSIEDL

KISVARDA

TISZALÖK

ALBERTIRSA

ARAD

NADAB ROSIORI

ISACCEA VULCANESTI

MUKAČEVO

GYÖR GÖD

SLAVĢTICE

SOKOLNICE

STUPAVA

KRIŽOVANY

GABČIKOVO V.KAPUŠANY

SAJOSZÖGED

LEVICE

P. BYSTRICA

LEMEŠANY

RZESZÓW

ZAMOŚĆ

CHMIELNICKA

BIAŁYSTOK

PANEVĒŽYS

KLAIPĒDASMORGON

GRODNO

VILNIUS

ALYTUS

POLOCK

MOLODECHNO

AIZKRAUKLE

GROBINA

JELGAVE

LIKSNA

IAE

ROS

DOBROTWOR

VARIN

SENICA

KRŠKO TUMBRI

CIRKOVCE

PEHLIN

MELINA TUZLA

MEÐURIĆ

ŽERJAVINEC

ERNESTINOVO SR. MITROVICA

SANDORFALVASZONBATHELY

BÉKÉSCSABA

SUBOTICA 3

GRADAČAC

UGLJEVIK

VIŠEGRAD

SARAJEVO

PODGORICA

PERUCICA

RIBAREVINA

PLJEVLJA

POZEGA

KOSOVO B

KOSOVO A

SKOPLJE 5

STIP

NIŠ

SKOPLJE 1

DUBROVOBITOLA

KOZLODUI

ÐERDAP

TÂNTĀRENI

DOBRUDJA

ELBASAN

ARACHTHOS

THESSALONIKI

BLAGOEVGRAD

CERVENA MOGILA

MARITZA EAST 3

PORTILE DE FIER

ZAHIDNOUKRAINSKA

PIV. UKRAINSKA

HAMITABAT

BABAESKIPRIZREN

SOFIJA VARNA

FIJERZA

KARDIA MELTI

B. BASTA

VAU DEJES

PIVA

VARDIŠTE

HEVIZ

MRACLIN

ZAKUČAC

KONJSKO

ÐAKOVO

DUBROVNIK

PRIJEDOR

MOSTAR

TREBINJE

NO

IT

381

01.08.10 00:00 AM R9

391.1.1

RS / Kosovo A - MK / Skopje1 220 kV / 311 MVA

44640 min

01.08.10 00:00 AM R9

391.2.1

RS / Kosovo A - MK / Skopje1 220 kV / 311 MVA

44640 min

15.06.10 12:05 AM R1

883.1.1

RU / esterovo - LT / Kybartai 110 kV / 75 MVA

N

1793 min

30.08.10 09:01 AM R2

710.1.1

SK / Gabcikovo - HU / Györ 400 kV / 1330 MVA

2339 min

10.01.10 08:57 AM R206.01.10 04:20 AM R9

351.1.1

SI / Divaca - HR / Melina 400 kV / 1264 MVA

521 min

18.05.10 08:27 AM R119.05.10 08:17 AM R120.05.10 06:46 AM R121.05.10 07:03 AM R125.05.10 07:51 AM R126.05.10 07:27 AM R127.05.10 06:05 AM R128.05.10 06:58 AM R1

730.1.1 HU / Sandorfalva - RO / Arad 400 kV / 1330 MVA

4284 min

01.05.10 00:01 AM R2

430.1.1

CZ / Sokolnice - SK / Stupava 400 kV / 1363 MVA

2191 min

SÖDERÅSEN

869

28.06.10 10:09 AM R2

871.1.1

LT / eipalingis - BY / rodno 110 kV / 75 MVA

L G

3366 min

865

15.04.10 07:23 AM R119.04.10 07:43 AM R1

117.1.1

DE / Oberbrunn - AT / Silz 220 kV / 793 MVA

943 min

TSIRGULIINA

VALMIERA

882

01.02.10 07:06 AM R8

205.1.1

IT / Galatina - GR / Arachthos 380 kV / 500 MVA

8 min

02.08.10 05:58 AM R1

721.1.1

HU / Sajószöged - UA_W / Mukachevo 400 kV / 1390 MVA

6482 min

15.03.10 06:10 AM R1

740.1.1

UA_W / Mukacevo - RO / 400 kV / 1135 MVA

Rosiori

6480 min

16.08.10 06:11 AM R1

440.1.1

SK/ .Kapusany - UA_W/ ukachevo 400 kV / 1186 MVA

V M

6418 min

27.07.10 08:27 AM R9

424.1.1

CZ / Sokolnice - SK / Krizovany 400 kV / 1205 MVA

4649 min

21.07.10 09:40 AM R1

853.1.1

LV / iksna - LT / IAE 330 kV / 830 MVA

L

9346 min

23.08.10 07:38 AM R1

278.1.1

RO / Isaccea - BG / Dobrudja 400 kV / 1135 MVA

12502 min

09.08.10 09:59 AM R1

881.1.1

RU / ovetsk - LT / Jurbarkas 330 kV / 714 MVA

S

6190 min

01.05.10 00:01 AM R1

277.1.2

RO / Tântareni- BG / Kozlodui 400 kV / 1300 MVA

19649 min

22.04.10 09:15 PM R2

704.1.1

SE / - PL / Slupsk 450 kV / 600 MVA

Stärnö

2853 min

01.07.10 00:00 AM R1

502.1.1

DE / Hagenwerder - PL / Mikulowa 380 kV / 1660 MVA

12219 min

12.07.10 08:59 AM R113.07.10 07:31 AM R114.07.10 06:57 AM R127.07.10 06:29 AM R130.07.10 08:12 AM R1

501.1.2

DE / Vierraden - PL / Krajnik 220 kV / 410 MVA

2797 min

07.06.10 09:41 AM R103.06.10 07:48 AM R9

142.2.1

CH / Pradella - AT / Westtirol 380 kV / 1340 MVA

5705 min

30.08.10 10:04 AM R1

884.1.1

RU / ovetsk - LT / Pagegiai 110 kV / 75 MVA

S

2276 min

12.07.10 07:11 AM R126.07.10 06:11 AM R2

322.1.2

DE/Röhrsdorf - CZ/Hradec Vychod 400 kV / 1145 MVA

12518 min

24.05.10 04:16 PM R1

171.1.1

CZ / Sokolnice - AT / Bisamberg 220 kV / 269 MVA

5870 min

07.08.10 00:04 AM R2

871.1.1

LT / Leipalingis - BY / Grodno 110 kV / 75 MVA

4038 min

16.08.10 01:29 PM R121.08.10 10:58 AM R1

867.1.1

LT / idžiasalis - BY / aziani 110 kV / 44 MVA

D K

15435 min

01.08.10 00:00 AM R906.08.10 08:42 PM R913.08.10 09:07 PM R9

882.1.1 RU / ovetsk - LT / Kruonio HAE 330 kV / 714 MVA

S

8187 min

05.08.10 06:13 AM R1

444.1.1

PL / Wielopole - CZ / Nosovice 400 kV / 1205 MVA

1769 min

01.06.10 00:00 AM R107.06.10 06:47 AM R9

171.2.1 CZ / Sokolnice - AT / Bisamberg 220 kV / 269 MVA

4180 min

02.08.10 08:58 AM R2

172.1.1 CZ / Slavetice - AT / Dürnrohr 380 kV / 1642 MVA

4712 min

01.07.10 00:00 AM R9

850.1.1

LV/Jelgave(Viskali) - LT/ 330 kV / 714 MVA

Šiauliai/Telšiai

2366 min

26.07.10 06:05 AM R1

722.1.1 HU / Kisvárda - UA_W / Mukacevo 220 kV / 209 MVA

7864 min

16.07.10 09:05 PM R923.07.10 10:29 PM R930.07.10 08:25 PM R9

882.1.1

RU/ ovetsk - LT/Kruonio HAE 330 kV / 714 MVA

S

8507 min

02.08.10 12:54 AM R1

880.1.1

RU / ovetsk - LT / Klaipeda 330 kV / 679 MVA

S

6085 min

01.07.10 00:00 AM R213.07.10 03:10 PM R117.07.10 05:00 PM R127.07.10 10:00 AM R2

862.1.1

LT / AE - BY / elorusskaya 330 kV / 1786 MVA

I B

11748 min

14.06.10 08:11 AM R1

142.1.1

CH / Pradella - AT / Westtirol 380 kV / 1340 MVA

2001 min

21.08.10 06:29 AM R2

410.1.1

CZ / Liskovec - SK / P.Bystrica 220 kV / 221 MVA

10731 min

01.07.10 00:00 AM R1

863.1.1

LT / Vilnius - BY / Molodechno 330 kV / 714 MVA

12637 min

862

05.07.10 07:05 AM R119.07.10 06:57 AM R1

322.1.1

DE/Röhrsdorf - CZ/Hradec Vychod 400 kV / 1145 MVA

11202 min

868

20.07.10 10:20 AM R1

866.1.1

LT / AE - BY / idzi 110 kV / 63 MVA

I V

4594 min

867

03.08.10 08:19 AM R104.08.10 06:53 AM R105.08.10 06:38 AM R1

501.1.1

DE / Vierraden - PL / Krajnik 220 kV / 410 MVA

1667 min

06.08.10 07:33 AM R916.08.10 08:28 AM R918.08.10 06:37 AM R119.08.10 06:56 AM R123.08.10 07:45 AM R125.08.10 07:37 AM R126.08.10 07:20 AM R1

111.3.1

DE / Dellmensingen - AT / Bürs 220 kV / 492 MVA

5664 min 01.08.10 07:00 AM R

450.1.1 PL / Kopanina - CZ / Liskovec 220 kV / 400 MVA

3457 min

12.08.10 09:05 AM R113.08.10 07:29 AM R123.08.10 05:07 AM R1

443.1.1

PL / Dobrzen - CZ / Albrechtice 400 kV / 1205 MVA

1654 min

09.08.10 01:38 PM R111.08.10 01:37 PM R113.08.10 09:31 AM R1

117.1.1 DE / Oberbrunn - AT / Silz 220 kV / 793 MVA

1712 min

18.08.10 08:00 AM R1

869.1.1

LT / alveliai - BY / smena 110 kV / 63 MVA

K A

3508 min

Page 11: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

ENTSO-E August 2010

August 2010

BE DE

PL

RS

GR

FR

ESPT

SK

BA

NL

HU

CZ

CH

AT

SI

LU

HR

MK

IT

UA_W

RO

BG

DK

RS

ME

CY

GB

IE

NI

NO

EE

LT

LV

SE

FI

IS

1 ( year [in min] * energy not supplied ) / consumption last 12 months

Reasons:R4 Overload (also calculated break) R8 Very exceptional conditionsR5 False operation (weather, natural disaster, ...)R6 Failure in protection device or other element R9 Other reasonsR7 Outside impacts (animals, trees, fire, avalanches, ...) R10 Unknown reasons

Network reliability ( major events )8

10

Information about incidents in other countries are not shown with energy not supply equal zero or unavailable in the database.

Ene rgy Tota l Ave ra ge Equiva le ntNo Country S u b sta tio n Re a s on not s upplie d los s of pow e r inte r ruption tim e of

[ M W h ] [ M W ] dura tion [ m in ] inte r ruption1

1 DE Dief f len R5 4 38 6 0 ,004

2 DE Dief f len R5 3 40 5 0 ,003

1 2

Page 12: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

ENTSO-E August 2010

1 Variation as compared to corresponding month of the previous year2 The reported figures are best estimates based on actual measurements and extrapolations3 Only highest and lowest load value available4 Highest and lowest load values as of August 20095 Operational data

11

9 Highest and lowest load on the 3rd Wednesday

Highest and lowest load on the 18.08.2010 CET of each country

Highest Low estload variation load variationMW %1 MW %1 %

AT 7913 -0,9 4541 1,3 100BA 1579 6,8 967 9,4 100BE 11479 0,6 7727 -0,1 100BG 4576 6,0 3053 9,8 100CH 8453 0,2 5016 0,9 100CY 983 n.a. 627 n.a. 100CZ 7453 -1,1 5310 0,1 100DE 73976 10,8 49291 14,8 91DK 4888 n.a. 2760 n.a. 100EE 960 n.a. 583 n.a. 100ES 34599 -6,9 22333 -6,0 98FI 9525 n.a. 7229 n.a. 100FR 51550 -5,7 36206 -3,4 100GB 39071 n.a. 22892 n.a. 100GR 8849 11,8 5866 17,8 100HR 2496 -5,6 1437 -4,2 100HU 4817 -7,6 3284 -9,6 100IE 3392 n.a. 1850 n.a. 100IS 1891 n.a. 1753 n.a. 100IT 34913 -11,5 23288 -10,0 100LT 1299 n.a. 793 n.a. 100LU 775 -5,9 545 3,6 100LV 919 n.a. 511 n.a. 100ME 493 n.a. 296 n.a. 100MK 1083 20,1 645 21,9 100NI 1257 n.a. 645 n.a. 100NL 14910 0,3 9332 2,1 100NO 12464 n.a. 9447 n.a. 100PL 17817 1,9 12546 3,7 100PT 6568 -0,5 4474 4,3 97RO 6845 5,8 4987 7,7 100RS 4763 5,5 2802 2,8 100SE 28502 n.a. 11062 n.a. 100SI 1570 -4,5 1157 11,8 100SK 3279 -0,1 2491 2,4 100

ENTSO-E 404274 n.a. 268373 n.a.UA_W 640 18,7 366 19,6 100

representativityLoad

2

5

4

3

Page 13: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

ENTSO-E August 2010

Load diagrams on the 3rd Wednesday

12

10Consumption hourly load curves on 18.08.2010 CET Values in GW

4

8

12

16

20

PL

NO CH

NL

AT

0

20

40

60

80

FRDE

ESIT

SE

GB

0

1

2

3

4

5

RS

BA

LU

BG

DK

0

3

6

9

12

PT IE

HR

BE GR

0

1

2

LT

UA_W

IS

LV

0 2 4 6 8 10 12 14 16 18 20 22 h

0 2 4 6 8 10 12 14 16 18 20 22 h

0

1

2

EE

SI NI

MK

ME 4

0 2 4 6 8 10 12 14 16 18 20 22 h

0 2 4 6 8 10 12 14 16 18 20 22 h

0 2 4 6 8 10 12 14 16 18 20 22 h

0 2 4 6 8 10 12 14 16 18 20 22 h

240

300

360

420

ENTSO-E

0 2 4 6 8 10 12 14 16 18 20 22 h

2

4

6

8

10

FI

SK

ROCZ

HU

0 2 4 6 8 10 12 14 16 18 20 22 h

Page 14: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

ENTSO-E August 2010

11 Water reservoirs Nordic

13

Finland: Reservoir capacity: 5.530 GWhMinimum and maximum limits are based on values for the years 1990-2002

Norway: Reservoir capacity: 81.729 GWhThe statistics are supposed to cover 97.1 percent of the total reservoir capacity.The total reservoir capacity is 84 147 GWhMinimum and maximum limits are based on values for the years 1990-2003

Sweden: Reservoir capacity: 33.758 GWhMinimum and maximum limits are based on values for the years 1950-2006

1970-99

Finland

0

10

20

30

40

50

60

70

80

90

100

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52

maxmin20102009

Norway

0102030405060708090

100

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52

max

min

2010

2009

Sweden

0102030405060708090

100

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52

max

min

2010

2009

Page 15: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

ENTSO-E August 201014

Market information12Iberian Daily Market: prices and energy

August 2010

0

200.000

400.000

600.000

800.000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

MWh

30

50

70

€/MWh

Daily energy volumes Spanish arithmetical average daily pricePortuguese arithmetical average daily price

Iberian Intraday Market: prices and energyAugust 2010

20

40

60

80

100

120

140

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

€/MWh

0

20.000

40.000

60.000

80.000

100.000

120.000

140.000

MWh

Spanish arithmetical average daily price Portuguese arithmetical average daily priceDaily energy volumes

Source of the Iberian Market data: www.omel.es

Page 16: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

ENTSO-E August 2010

Market information12

15

EPEX Spot Market: prices and energyAugust 2010

0

20

40

60

80

100

120

140

160

180

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

€/MWh

0

60.000

120.000

180.000

240.000

300.000

360.000

420.000

480.000

540.000

600.000

660.000

720.000

MWh

AVG spot price MIN spot price MAX spot price Spot energy volumes

EPEX Intraday Market: prices and energyAugust 2010

-25

25

75

125

175

01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

€/MWh

-20.000

0

20.000

40.000

60.000

MWh

AVG Last Price MIN price MAX Price AVG Price Energy Volumes

Source of the EPEX Market data: www.eex.com

Page 17: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

August 2010

ENTSO-E August 2010

Market information12

16

Nord Pool Spot Market: prices and energyAugust 2010

0

20

40

60

80

100

120

140

160

180

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

€/MWh

0

100.000

200.000

300.000

400.000

500.000

600.000

700.000

800.000MWh

Elspot MIN Price Elspot MAX Price Elspot AVG Price Elspot Volumes

Source of Nord Pool Market data: www.nordpoolspot.com

Page 18: Monthly report - ENTSO-E · August 2010 ENTSO-E August 2010 1 Including deliveries from industry 2 The reported figures are best estimates based on actual measurements and extrapolations.

ContactAvenue de Cortenbergh, 100

B-1000 Brussels – BelgiumTel + 32 2 741 0950Fax + 32 2 741 0951

info @ entsoe.euwww.entsoe.eu


Recommended