+ All Categories
Home > Documents > Moroccan Power Sector & Renewables Achievements, Challenges … · 2018. 4. 27. · Education SANTE...

Moroccan Power Sector & Renewables Achievements, Challenges … · 2018. 4. 27. · Education SANTE...

Date post: 31-Jan-2021
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
25
Moroccan Power Sector & Renewables Achievements, Challenges and Opportunities of Investment
Transcript
  • Moroccan Power Sector & RenewablesAchievements, Challenges and Opportunities of

    Investment

  • IPPGeneration

    Capacity: 2 812 MW

    Generation: 18 404 GWh(53,5%)

    ONEEGeneration

    Capacity : 4 942 MWGeneration: 10 010 GWh

    (29,1%)

    Interconnections

    Importations4 919 GWh

    (14,3%)

    Law 13-09Private Generation

    Capacity : 203 MWGeneration: 791 GWh

    (2,3%)

    Auto Generation

    Capacity : 37 MW

    (< 1%)

    ONEE-BE Single Buyer (except Law 13-09) Transmission System Operator

    Total Demand 35,4 TWh

    ONEE-BE (Direct Seller)

    (58%)

    Distribution MV/LV (43%)

    Public and private utilities

    (42%)

    Direct Customers VHV/HV (15%)

    MV/LV Customers (45%)

    ELECTRICITY SECTOR ORGANIZATION

    BALANCE OF SUPPLY-DEMAND 2016

    2

  • Coal49,0%

    Heavy Fuell

    6,0%

    Natural Gas

    16,6%

    Hydro6,6%

    Wind6,8%

    Importations14,8%

    Others

    0,2%

    Solar0,0%

    DIVERSIFIED POWER GENERATION

    Total Installed Capacity in 2016 MW %

    Classical Hydro 1 306 17%

    STEP 464 6%

    Total Hydro 1 770 22%

    Wind Farmes ONEE 205 3%

    Wind Farmes Privates (13-09 & Auto) 341 4%

    IPP Wind Farmes CED + Tarfaya 352 4%

    CCGT Ain Beni Mathar (Solar Part) 20 0,2%

    Ouarzazate Solar Power plant 160 2%

    Total Wind & Solar 1078 13%

    Total Thermal 5 411 65%

    Total Installed Capacity 8260 100%

    Energy consumption 35 400 GWh

    Total Installed Capacity8 260 MW

    3

  • A DEVELOPED AND RELIABLE TRANSMISSION GRID

    ▪ A developed Grid covering the Kingdom and

    connected to neighbours grids (Spain and

    Algeria):

    Transmission Network (400 kV, 225 kV, 60 kV) total length ≈ 29 000 km

    Transformation installed capacity ≈ 26 GVA

    A 400 KV corridor from Laayoune to Dakhla

    (540 Km) under development

    ▪ 2017-2020 Transmission Grid expansion:

    Additional 7 000 Km of HV and VHV transmission lines

    9 000 MVA of new transformation capacity

    Investments of 1,3 Billion US$

    4

  • Achieved

    Dakhla

    LâayouneAlgeria

    Portugal

    Morocco

    Mauritania

    Spain

    Boujdour

    MOROCCO : A POWER REGIONAL CROSSROADS

    Morocco has become a regional crossroads for power exchange between north and south

    In Progress

    Under study

    Commissioning in 1988 (2x 225kV lines)

    400 kV line in 2008

    Exchange capacity 1500 MW

    Morocco-Algeria interconnection

    Mise en service en 1997

    Doublement en 2006

    Capacité d’Echange: 1400 MW

    Capacité importée: 750 MW

    ONE: 4ème operateur sur le marché Espagnol depuis 1999

    Commissioning in 1997

    Capacity doubled in 2006

    Exchange capacity: 1400 MW

    Commercial capacity 900 MW

    ONEE has been the 4th operator in the Spanish market since 1999

    Studies of 3rd interconnection is in progress

    Morocco-Spain interconnection

    Expected Morocco-Mauritania interconnection :• Under study• As a first step, Laâyoune-Dakhla in

    Progress (400 kV)

    Expected Morocco-Portugal interconnection :• Under study

    5

  • A SUCCESSFUL RURAL ELECTRIFICATION PROGRAM

    A huge effort in terms of generalization of access to electricity

    - Electrification rate: >99%

    - >38600 villages (3800 villages

    photovoltaïques Kits)

    - More than 12 millions citizens

    - Investing more than ≈ 3 billion USD

    - Creating of 100,000 jobs

    A successful experience being shared with African neighbors (Two “electrification, distribution and operation” concessions have already been successfully

    implemented by ONEE in Senegal)

    ✓ Improvement of living conditions, particularly for female gender;

    ✓ Better sanitation and safety conditions in rural area;

    ✓ Improvement of education;

    ✓Development of local companies specialized in electrical fields and flourishing of smallbusinesses;

    ✓Mitigation of rural exodus.

    6

  • 7

    Average increase in demand of about 6%, resulting from sustained economic and social growth:o Widespread access to electricity (in rural and urban areas) “PERG”,o Development of major infrastructures projects,o Urbanization, Economical development and Improved standard of living of the population.

    Average Growth Rate: 5%

    POWER DEMAND GROWTH OVER THE LAST DECADE

    Average Growth Rate: 6%

    Demand growth(GWh)

    Growth of the Annual Electricity Consumptionper inhabitant (kWh/cap)

  • 8

    The load curve shifted from a single peak to a twice one and from winter’s pic to summer’s one ;

    The gap between the peak load and the day load became relatively smaller ;

    Due particularly to :

    ▪economic and industrial development across the Kingdom of Morocco ;

    ▪and modernization of life style (air conditioning, etc.).

    Emergence of a significant off-peak load(in terms of level and duration) requiring appropriate measures for its

    satisfaction

    Load curve Electricity daily evolution “Mutation 2006-2016”

    MOROCCAN POWER DEMAND STRUCTURE

  • 9

    MOROCCAN RENEWABLE ENERGY STRATEGY

    GOAL: RE 42% OF TOTAL INSTALLED CAPACITY IN 2020

    Morocco's Energy Strategy prioritize the diversification of the country’s energy sources with particular emphasis on the renewable energies.

    Evolution of renewables share in the energy mix Launching of important projects

    Appropriate institutional and legislative framework

    –The Moroccan Integrated Wind Energy Program 2 000MW by 2020

    –The Moroccan Integred solar Energy Project2 000 MW by 2020

    –The Moroccan Hydro Energy Program2 000 MW by 2020

    –Law n° 13-09 allowing the private sector to developrenewables energy projects, …

    –Fund Energy Development (7,3 billion dirhams)

    –Law n° 16-08, raised the ceiling for self-generation from10 MW to 50 MW and above 300 MW with access to thegrid

    –Creating special instances :

    MASEN, ADEREE, …

    Strong support in setting-up renewable energy development

    At the end of 2020 : 42% of the electricity capacityinstalled will be based on Renewable Energies

  • INTEGRATED WIND ENERGY PROGRAM

    AN INNOVATIVE & STRUCTURING WIND POWER PROGRAM

    • 2000 MWInstalled

    capacity by 2020

    • ≈ 6600 Gwh per year Generation

    • ≈3,8 Billion USDEstimated investment

    cost

    • 1,5 million of TOE per year (750 million USD per year)

    Fuel annual save

    • 5,6 millions Tons per year

    CO2 emissionavoided

    ▪ ONEE as a lead in the implementation of the wind Program

    ▪ Private producers under the RE Law « 13-09 »

    920 MW under operation

    470 MW under construction

    or Financial Closing

    PEI 850 MW under Financial

    Closing

    10

  • 140

    301

    5

    201

    220

    300

    900

    200

    100

    0

    500

    1000

    1500

    2000

    2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    MW

    147

    INTEGRATED WIND ENERGY PROGRAM

    AN INNOVATIVE & STRUCTURING WIND POWER PROGRAM

    Total Wind Capacity built until now : 920 MW

    Investment : 2 billion US$

    Total New Wind Capacity to build by 2020: 1700 MW

    Investment : 2,5 billion of US$

    Boujdour

    Jbel LahdidTiskrad, Tanger II

    KoudiaAftissatOualidia

    Taza et Midelt

    Khelladi

    Tarfaya

    Haouma+

    Akhfennir I

    +Laâyoune

    Abdelkhalek

    Torres+

    Amougdoul+

    Tanger I

    470 MW under construction or Financial Closing

    PEI 850 MW (under Financial Closing) The lowest Tarif in the World 3c$/kWh

    Akhfennir II

    11

  • SOLAR POWER GENERATION PROJECTS (MASEN)

    • 2000 MWInstalled capacity

    •≈ 4500 GwhGeneration

    •9 billion of US$Investement

    • 1 million TOEAnnual save

    •3,7 million TonsCO2 emissionavoided

    - Noor Ouarzazate 1 (160 MW, CSP) under operation- Noor Ouarzazate 2&3 (350MW, CSP) under construction, COD 2018-Noor PV I (170 MW, PV) under construction, COD S2 - 2018

    -Noor Midelt (800 MW), under bidding process

    Ouarzazate:

    580 MW

    ONEE’s assignments:

    - Off-taker for Noor I, II & III

    - Connection of solar projects and transmission of generated power

    - Interconnection to the Grid access for export

    12

    A total of 1480 MW

    Already 74% of the Target

  • IMPLEMENTATION THROUGH “INTEGRATED” PROJECTS

    13

    Our Vision: Optimize solar resource valorization

    ELECTRICITY PRODUCTION

    2000 MW by 2020

    and more by 2030

    INDUSTRIAL INTEGRATION LOCAL DEVELOPMENTRESEARCH &

    DEVELOPMENT AND

    TRAINING

    For a competitive industry

    For technology

    improvement and

    qualified resources

    For an inclusive

    development

    IMPLEMENTATION THROUGH “INTEGRATED” PROJECTS

  • NOOR, A MULTI-SITE AND MULTI-TECHNOLOGY PLAN

    NOOR

    Tata

    NOOR

    Midelt

    NOOR

    Laâyoune

    NOOR

    Ouarzazat

    e

    NOOR

    Boujdour

    CSP PV

    CSP PV

    PV

    PV

    CSP PV

    5 sites with a minimal capacity of 2 000 MW by 2020

    Technologies combination to answer to identified needs while

    optimizing the overall cost of the kilowatt hour and maximizing

    synergies

    NOOR, A MULTI-SITE AND MULTI-TECHNOLOGY PLAN

  • NOOR OUARZAZATE: A MULTI TECHNOLOGIES

    COMPLEX

    Capacity: 160 MW

    Technology: CSP trough

    Storage: 3 hours

    Price: 1,62 MAD/kWh

    CO2 emissions avoided:

    ~ 280 000 tCO2 / year

    Capacity: 200 MW

    Technology: CSP trough

    Storage: > 7 hours

    Price: 1,36 MAD/kWh

    CO2 emissions avoided:

    ~ 380 000 tCO2 / year

    Capacity: 150 MW

    Technology: CSP Tower

    Storage: > 7 hours

    Price: 1,42 MAD/kWh

    CO2 emissions avoided:

    ~ 250 000 tCO2 / year

    Capacity: 70 MW

    Technology: PV with

    tracking system

    NOORo I NOORo II NOORo III NOORo IV

    A SOLAR COMPLEX OF 580 MW COMBINING 3 DIFFERENT SOLAR

    TECHNOLOGIES

    PLANT IN OPERATIONPLANT UNDER

    CONSTRUCTION

    PLANT UNDER

    CONSTRUCTION

    WORKS TO BE LAUNCHED

    SOON

    CO2 emissions avoided:

    ~ 87 000 tCO2 / year

    Price: 0,44 MAD/kWh

    Industrial integration:

    30%*

    * Real industrial integration reached: 34%

    Industrial integration:

    35%Industrial integration:

    35%

    15

  • NOOR LAAYOUNE AND NOOR BOUJDOUR: WORKS TO BE LAUNCHED SOON

    NOOR

    BOUJDOUR

    Projects financed through green bonds for a total amount of 1 200 million dirhams

    NOOR

    LAAYOUNE

    Capacity: 80 MW

    Technology: PV with tracking

    system

    Price: 0,44 MAD/kWh

    CO2 emissions avoided:

    ~ 104 000 tCO2/yearCapacity: 20 MW

    Technology: PV with tracking

    system

    Price: 0,64 MAD/kWh

    CO2 emissions avoided:

    ~ 24 000 tCO2/kWh

    NOOR Laayoune and NOOR Boujdour: Under Construction

  • A DEDICATED SUPPORT FOR THE DEVELOPMENT OF A SOLARINDUSTRY

    DEVELOPMENT OF A COMPETITIVE

    MOROCCAN SOLAR INDUSTRY …

    Skills development

    Industrial

    capabilities

    reinforcement

    … through two missions

    Ambition Cluster supported by multisectorial institutions

    … and by well-known partners

    ~ 250 beneficiaries

    ~ 150 hours of trainings

    Excellence awards Summer school

    Conferences Seminaries

    CSP

    mission in

    Spain

    QHSE trainings, diagnostic,

    personal assistance

    Almeria intership

    Several actions

    17

    A DEDICATED SUPPORT FOR THE DEVELOPMENT OF A SOLAR INDUSTRY

  • PRINCIPALES ACTIONSSTRATEGIC AXES

    LOCAL DEVELOPMENT IN HARMONY WITH THE SOLARPOWER PROJECTS

    Guidelines

    Sustaining actionsCreate a local dynamismEnsure integration1 2 3

    AGRICULTURE

    Agriculture

    Entrepreneurship

    Development and facilitation of

    territories

    Education

    SANTE

    Health

    Improving the population’s social

    environment

    Territories’s opening up

    Basic infrastructures

    EducationSociocultural

    activitiesSports’ activities

    Health Infrastructures Agriculture

    More than 60 Actions and projects led since 2010

    More than 30 000 beneficiaries

    6 Areas of intervention

    18

    Employment

    Sponsorship / patronage

    LOCAL DEVELOPMENT IN HARMONY WITH THE SOLAR POWER PROJECTS

  • RESEARCH AND DEVELOPMENT, A COMPLEMENTARY AXIS OF NOOR PLAN

    R&D actions led alongside with national and international actors including:

    19

    – Qualify new solar technologies

    – Create a network between industrials and research institutions

    An R&D Platform, to

    This platform hosts:

    Demonstration projects in order to test, qualify,

    and improve plants’ components of all solar

    technologies

    Research projects to support technological

    transfer and know how on CSP and PV

    technologies

    Commercial services to industrials and

    universities for a global added value

    RESEARCH AND DEVELOPMENT, A COMPLEMENTARY AXIS OF NOOR

    PLAN

  • Hydro22%

    Wind10%

    Solar2%

    Heavy Fuel25%

    Coal31%

    Natural Gas10%

    2016

    Hydro12%

    Wind20%

    Solar20%

    Heavy Fuel4%

    Coal21%

    Natural Gas23%

    2030

    14 GW 22 GW

    Hydro14%

    Wind15%

    Solar14%

    Heavy Fuel13%

    Coal36%

    Natural Gas6%

    2020

    8,3 GW INSTALLED CAPACITY

    30 Billions US$: Total Investments in Power Sector between 2016 and 2030

    LONG TERM CAPACITY MIX IN MOROCCO

    43% 52%34%PART OF RENEWABLES

    RENEWABLES will increase up to 52% of the Capacity Mix by 2030

    3 GW

    20

  • To manage the

    intermittence

    generated by

    the massive

    introduction of

    renewables

    Interconnection

    (over 5000 MW)

    +

    Grid

    Development

    Capacity storage

    (2000 MW of

    Hydro Pump) +

    (over 1500 MW

    CSP)

    Nexus

    Power/Water

    (Desalination)

    Flexible Capacity

    Gas to Power

    RE Programs: an integrated and multidimensional vision

    21

    SUPPORTING THE “RENEWABLE ENERGY” STRATEGY – 2030 –

  • A REGIONAL AND INTERNATIONAL INTEGRATION TO MAKE MOROCCO A SOLAR HUB

    22

    SOUTH SOUTH COOPERATION1

    • Morocco, Hub of expertise in the energy

    field

    SOUTH NORTH COOPERATION2

    • Morocco, for a competitive green energy

    exchange

    MENA COOPERATION3

    • Collaboration agreements

    MASEN: PROMISING FUTURE PROSPECTS

  • Morocco today is :

    Universal access to electricity for Moroccan citizens (> 99%)

    11 GW operational assets

    Business friendly environment (Investment Grade) with a proven

    and bankable legal and contractual framework

    More than 20 years IPP history:

    ▪ 2 procurement schemes (IPP tendering, Merchant IPP plant Law 13-09)

    ▪ 13 IPPs successfully financed

    ▪ 6 GW operational assets

    ▪ Exceeding 13 b$ financing already closed

    ▪ More than 70 financiers (DFI, ECA, Commercial banks, …)

    Zero breaches of obligations

    Strong and competitive Local Banks

    Very competitive market (probably the lowest Tarif that has ever

    been offered in Wind) southern Mediterranean

    23

    CLOSING REMARKS

  • Morocco tomorrow is :

    14 GW operational in 2020, and 25 GW by 2030

    Almost 12 GW additional capacity to be developed by IPPs (2020-

    2030)

    52% Ren by 2030, more than 9 GW additional capacity (2017-2030)

    Large scale Gas to Power projects (5 bcm and 2,4 GW by 2025 and 6

    GW by 2030)

    Power regional crossroads (more than 5 GW interconnections)

    30 Billions US$ total investment (2016 and 2030) in the power sector

    CLOSING REMARKS

    24

  • 25

    Thank you for your attention


Recommended