1 2016 INDRAJEET KUMAR BRANCH -CIVIL ENGG. UNI.ROLL NO:-1243467 C SEMESTRIAL TRAINING
Transcript
Page 1: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 1

20 16

INDRAJEET KUMAR

BRANCH - CIVIL ENGG.

UNI.ROLL NO: - 1243467

C

SEMESTRIAL TRAINING

Page 2: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 2

Six-Laning of (Barwa-Adda-Panagarh)

Section of NH-2 Dhanbad

In The State Of Jharkhand

In the partial fulfillment of the requirements for the award of the

Degree

Of

Bachelors in Technology (B.Tech)

In Civil Engineering

Twelve Weeks Training

(From 22nd February 2016 to 21st May 2016)

SUBMITTED BY

Indrajeet Kumar Gorain

College Roll no.-120136

Univ. R.no-(1243467)

Civil Engineering Department

GURU NANAK DEV ENGINEERING COLLEGE, LUDHIANA

Page 3: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 3

STUDENT DECLARATION

This is to certify that I, Indrajeet Kumar, student of B.Tech Civil Engineering 8th Semester, University Roll no. – 1243467 has undergone Industrial Training in APCO Infratech Pvt. Ltd. “as required for the award of degree of B.Tech Civil Engineering”, Guru Nanak Dev Engineering College, Ludhiana and prepared the report entitled “6-Laning of Barwa-Adda-Panagarh section of NH-2 from 398.240 km to 441.564” which is an authentic record of my work carried out at project campus of APCO Infratech Dhanbad. If any discrepancy is found regarding the originality of this project I may be held responsible. I have not copied from any report submitted earlier this or any other university. It is purely original and authentic work. Indrajeet Kumar

Page 4: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 4

STUDENT PROFILE

Name: Indrajeet Kumar Gorain Father’s Name: Sopan Chandra Gorain College: Guru Nanak Dev Engineering

College, Ludhiana Branch: Civil Engineering Class Roll No.: 120136 Uni. Roll No: 1243467 Date of Birth: 24/04/1994 Session: 2012-16 Address: Vill- Deoli Post-Jangalpur P.S.-

Govindpur Dist- Dhanbad (Jharkhand)

Contact No: 8528220855 E-mail Id: [email protected] Name Of Organization: APCO Infratech Pvt. Ltd Period of Training: 22nd Feb 2016 to 22nd May 2016 Location of The Project: NH-2 (Barwa-adda-Panagarh)

Page 5: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 5

ACKNOWLEGEMENT

As the professional course not only require the theoretical knowledge but practical knowledge too,

that is why university started conducting training programs for the student, so that they can get

ample view of practical problems.

It is my privilege to express my profound ineptness, my deep sense of gratitude to APCO Infratech

Pvt. Ltd., for showing trust in me and assigning me such an important and interesting project and

also for sparing time from his schedule to discuss and clarify issues related to this project. I

sincerely thank to my project manager Er. Umesh Chand Singh (AGM) for guidance and

encouragement in carrying out this project work. My special thanks to each and every member of

this company for their kind co-operation in the completion of my project work.

I wish to express my sincere gratitude to Dr.J.N.Jha (H.O.D) of Civil Engineering Department of

Guru Nanak Dev Engineering College, Ludhiana for providing me an opportunity to do my project

work on widening of national highway (NH-2), Barwa-Adda- Panagarh under the supervision of

Apco infratech Pvt. Ltd.

I am also very thankful to my friends and family members who supported me, encouraged me all the time to go through this whole project.

Page 6: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 6

TABLE OF CONTENTS Sr.No Description Page

No. 1. General introduction 8

2. Information about the company 9

3. Brief detail of project 10-11

4. Location 12

5. About Survey 13-22 i. Introduction 13 ii. Instrument used for surveying 13 iii. Purpose of Surveying 15 a. For Topography 15 b. For construction Structural elements 18 c. For construction of pavement Layers 21

6. About Highway 23-49 i. Introduction 23 ii. Pavement and its purpose 25 iii. Types of pavement 25 iv. Properties of different layers of pavement 26 a. Subgrade Layer 26 b. Sub-base Layer 28 c. Base Course 31 d. Prime coat/Tack Coat 34 e. Surface Course 36 v. Material used 41 vi. Aims of Highway Engineering in our project 42 a. Widening of Road 42 b. Reconstruction of Road 42 c. Construction of Service road 43 vii. Steps of construction 43

7. About Structures 50-91

i. Introduction 50 ii. Aims of structural engineering in our project 51-53 iii. Methodology of Execution 53

Page 7: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 7

a. RFI 54 b. Site Clearance 61 c. Layout 61 d. Excavation 61 e. PCC Laying 63 f. Reinforcement 65 g. Formwork and Falsework 68 h. Concreting 70 i. Curing 74 iv. Complete constructional process of a structure 75 a. Construction of culvert with retaining wall 75 Introduction 75

Purpose 75

Types 75

Architectural Drawings 77

Way of construction 81

Estimation of the material used 87

8. Quality Check/ Quality Analysis 92-113 i. Introduction 92 ii. Laboratory Tests 93 a. Daily Program Report 94 b. Tests on Soil 95 c. Tests on Aggregates 101 d. Tests on Bitumen 105 e. Tests on Cement 109 f. Field Test 112 iii. Other Important Tests 113

j. Information about the Plants and Equipment 114-123

k. Safety Measures and campaign 124

l. Overall benefits of the training 131

m. Work Ethics and related issues 132

n. Conclusion 133

o. Reference and Bibliography 134

Page 8: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 8

GENERAL INTRODUCTION

The practical training conducted by the engineering student at the respective industrial units related

to their subjects is termed as “industrial training “.for example a civil engineering student requires

practical exposure at the building construction sites, road construction projects etc. the industry

institute interaction is a need of the hour. The industrial training is a part of continuous learning

process. So this field exposure that uplifts the knowledge and experience of student needs to be

properly documented in the form of report, which can be termed as “industrial report” a properly

prepared industrial training report can facilitate the presentation of the field experience is an

orderly, precise and interesting manner, which can off course well serve as a guide to the new

entrant engineers. The purpose of industrial training is:-

1) To provide field exposure to the student.

2) To have better understanding of engineering practices.

3) To make them adapt to industrial condition.

4) To provide opportunities to the student to handle tasks independently.

5) To help student to understand about the duties of an engineer and other supervisory

staff in an organization.

6) To make them aware with the common industrial problems.

7) To impart intensive training to the student to enable them to learn and use working of

latest field equipment machine.

Page 9: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 9

INFORMATION ABOUT THE COMPANY

Apco Infratech Pvt. Ltd. is a very well-known name in the construction industry across the country. It is an infrastructure, major with interests in the highways, energy, urban infrastructure, industrial development. Apco which came into existence in the year 1992, has established a very glorious record of steady growth, excellent performance and remarkable achievements on all parameter of success and mastery. APCO Infratech Ltd. (Formerly known as APCO Constructions Pvt. Ltd.) was incorporated by a visionary young man Mr. Anil Kumar Singh(Managing Director), who built up the company with dedication and hard work; creating a team of like-minded people, who has steered the infratech towards the path of glory. Ably assisted by a bunch of hardcore professionals who are extremely proficient and dedicated in their domain, the group has utilized their thorough expertise in crafting several splendorous structures that bear the hallmark of true excellence to the core.

Clients •IL&FS Transportation Networks Ltd. • U.P. Rajya Vidhyut Utpadan Nigam Ltd. (UPRVUNL) • Reliance Energy Limited. • Punj Lloyd Ltd. • Oriental Struct ural Engineers Lld. • Power Grid Corporation of India Ltd. • Rural Engineering Services, U.P. • Mecon Ltd. • Hindustan Construction Company. • Indian Oil Corporation Ltd. • Hindustan Petroleum Corporation Ltd. • Bharat Petroleum Co rporati on Ltd. • ABB Ltd. • Siemens Ltd.

Page 10: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 10

BRIEF DETAIL OF PROJECT Project Review Our Project is mainly based on Widening of Existing Four Lane Barwa-AddaPanagarh Section NH-2 to Six Lane NH-2 from 398.240 km to 441.465 including Panagarh Bypass in the States of Jharkhand and West-Bengal along with provision of Service Roads, Grade Separator, Vehicular Under Pass (VUP), Pedestrian Under Pass (PUP), Overpass, Minor Bridges, Box Culvert, Slab Culvert, Hume Pipe Culvert. Salient Features Of Project

1 Name of Project 6-Laning of Barwa-AddaPanagarh Section of

NH-2 from 398.240 km to 521.120 km

including Panagarh Bypass in the States of

Jharkhand and West Bengal

Package1:398.240 km to 441.565

2 Total Length of Project under the Scope of EPC Contractor(Pkg-1)

PACKAGE-1 43.325 KM

3 Contract/Phase DBFOT/NHDP PHASE 5

4 Client/Authority IL & FS

5 Independent Engineer SA Infrastructure

6 Concessionaire Barwa Adda Expressway Limited

7 EPC Contractor APCO INFRATECH PVT. LTD

8 Date of signing of EPC Agreement 30-July-10

9 Appointed Date 12-Sep-11

10 Construction Completion Period 730 days

11 Concession Period 30 years

12 Contract Value 488 Cr.

13 Project Commencement Date 1-April-14

14 Project Completion Date 31-March-16(Delayed)

Page 11: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 11

PROJECT FEATURES

A ROAD

1 Total Length of Project 43.33 Km

2 Total Length of Service Road 29.13 Km

B STRUCTURE

1 Grade Separator 3 Nos

3 Minor Bridge 5 Nos

4 Vehicle Under Pass 7 Nos

5 Pedestrian Under Pass 6 Nos

6 Box Culvert 18 Nos

7 Slab Culvert 24 Nos

8 Hume Pipe 44 Nos

C Major Project Quantities

1 Earthwork 21.00 Lacs Cum

2 GSB 2.14 Lacs Cum

3 WMM 4.36 Lacs Cum

4 BT Work 1.17 Lacs Cum

5 Concrete 1.25 Lacs Cum

6 Steel 5732 MT

Page 12: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 12

LOCATION OF PROJECT

States of Jharkhand (Dhanbad) and West Bengal (Asansol) Section of NH-2 (Barwa-Adda-Panagarh) from 398.240 to 441.465 including Panagrah bypass in States of Jharkhand & West Bengal.

Mainly on the east direction of India

Page 13: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 13

ABOUT SURVEY

INTRODUCTION: Surveying is the art of determining the relative position of points on, above or beneath and surface of the earth by means of direct or indirect measurement of distance, direction and elevation. Surveying is the technique, profession, and science of accurately determining the terrestrial or three-dimensional position of points and the distances and angle between them, and member of various buildings. These points are usually on the surface of the earth, and they are often used to establish land maps, locations or other governmentally required for civil purposes. INSTRUMENT USED FOR SURVEYING:

Auto level: It is an instrument used to determine the elevation of any point or to maintain a proper level before any type of constructional work.

Page 14: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 14

Total station and Target Prism A total station is an electronic instrument used in modern surveying. It is integrated with an Electronic Distance Meter (EDM) to read the elevation of any particular point. A Target Prism is used which reflect the rays coming from Total Station and all the data i.e., Easting, Northing, Reduced level, Horizontal angle and vertical angle is collected. It also allows the operator to control the instrument via remotely i.e. without help of Target Prism as sometimes the prism is not accessible due to some hindrance.

TOTAL STATION TARGET PRISM

Measuring Tape : 1. To determine the exact offset from the Proposed C/L for the construction of Crash

Barrier, and the pavement design. 2. To determine the proper spacing and other measurement of structural work.

Page 15: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 15

PURPOSE OF SURVEYING IN OUR PROJECT

The commencement and completion of Highway Project depends upon the surveying. In

Transportation Engineering , surveying is an art that transfer the levels , locations , distances ,

offsets from centre line of road , positioning of structural elements and elements of Right Of Way

(i.e. Carriageway , kerbs , shoulders , medians , edge strips , pavement strip etc.) from the

Designed-drawings to the ground .

Thus the functions of surveying in our project report are detailed discussed as given below:

Topography Survey

For Construction of Structural Elements

For Construction of Road Pavement Layers

Topography Survey:

Topography survey is the base of Highway project. It is an essential requirement for preparing

drawings of existing highway (Four-Lane) and further planning for proposed right of way

(Six-Lane). The basic need of topography survey is to prepare a Base-Map. The map which

is showing the existing structural elements (i.e. Culverts, Pipe encasing , Bridges etc.) ,

locality (i.e. Cities , Villages , Buildings, Towers , Electric poles, Ponds , trees etc.) and

Reduced levels of Road Pavement at fixed intervals in terms of coordinates on the existing

four-Lane , is known as base map.

During Topography survey along the center line of road (on the medians) two TBM (temporary

bench-mark) are placed between 5 km of distance by use of GPS (Global positioning system)

up to the total length of road.

Between the 5 kms of distance further TBM’s are placed at fixed interval of 200 mtr by use of

Total station instrument. On these TBM’s a suitable markings are made according to their

chainage i.e. 417/A, 399/A, CP2WD.

In the office work a detailed data is prepared for each TBM along their chainage which shows

its coordinates and Reduced-Levels.

Page 16: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 16

Further by use of Total station, Topography is done .The all elements i.e. Buildings , Schools,

Towers , Trees , Electric poles and Ponds etc. , that becomes the cause of obstacles in the

Proposed Right Of Way (PROW) , their coordinates and reduced levels are recorded in the

Total Station.

Then this recorded data is transferred to the computer to prepare a detailed drawings by use of Auto-Cad and further planning of project.

NATIONAL HIGHWAY AUTHORITY OF INDIA Six Lanning of Barwa-Adda-Panagarh Section of NH-2 From Existing KM 398+240 to KM 521+120 including Panagarh Bypass on the state of Jharkhand & West Bengal under NHDP

phase V on Toll on DBFOT pattern

TBM LIST

SL. NO.

PILLAR NO

FINAL RL

OFFSET SIDE CH REMARKS

1 GPS-P244 244.661 17.4 RHS 398+200

2 GPS-244/R 243.550 23.7 RHS 398+240

3 TBM-398A 243.794 27.3 LHS 398+270

4 P-398/4 (N) 242.042 0 MEDIAN 398+400

5 P-398/6 239.404 28.7 LHS 398+600

6 P-398/8 239.604 31.2 RHS 398+800

7 P-399/0 241.017 24.2 LHS 399+000

8 TBM-399A 242.095 32.0 LHS 399+040

9 P-399/2 242.377 15.8 RHS 399+200

10 P-399/4 250.251 27.3 LHS 399+400

11 P-399/6 248.982 0 MEDIAN 399+600

12 P-399/8 244.735 0 MEDIAN 399+800

13 GPS-400/R 243.062 0 MEDIAN 399+975

14 GPS-400 242.743 0 MEDIAN 400+000

15 TBM-400A 241.988 29.0 LHS 400+185

16 P-400/2 (N) 243.131 0 MEDIAN 400+200

17 P-400/4 242.369 0 MEDIAN 400+400

18 P-400/6 241.559 0 MEDIAN 400+600

19 P-400/8 240.688 0 MEDIAN 400+800

20 TBM-400B 237.707 32.0 LHS 400+950

21 P-401/0 238.981 0 MEDIAN 401+000

22 P-401/2 237.043 0 MEDIAN 401+200

23 P-401/4 236.708 0 MEDIAN 401+400

24 P-401/6 234.368 0 MEDIAN 401+600

25 P-401/8 233.048 0 MEDIAN 401+800

Page 17: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 17

The position of existing building and other structures between 30m from the Proposed Centre line of the carriageway.

Page 18: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 18

For Construction of structural elements

In the layout of structural elements the surveyor provides the end-points and levels of structure to

be built on the ground by use of both Total- station and Auto level. Total-station is used to place

exact points on the ground in terms of coordinates while Auto-level is used to provide bottom level

of structure so that to guide the site engineer about depth of excavation.

A surveyor holds a TBM list always with him from which he easily found the nearby TBM on

ground.

Then he note down the coordinates and reduced level of that TBM and setup his TS by

bisecting towards the TBM.

Then surveyor has the specification of the structure to be build i.e. N-E coordinates, reduced

levels, bottom level of PCC for structure and final top level of structure etc.

Then he fix the end / corner points of structure.

Afterwards he provides the bottom level of the PCC of structure by use of Auto level. When

PCC has laid down then with reference of the fixed points the reinforcement is being cast and

shuttering work is done to raise the structure.

Providing the bottom level for foundation

Page 19: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 19

Providing the proper position of Crash Barrier

Measuring the offset distance of the crash barrier from the nail by Tape

Giving the proper alignment of crash barrier

Page 20: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 20

Details for RCC crash barrier at Ch: 420+250 to 421+070

Chainage

S.R. Inner

edge offset

from PCL

SR Inner

Edge level

PCC bottom

level or CT

BASE-Top

level

PCC top

level or AG

Top level

Crash

barrier top

level

420+250 -12.698 162.244 162.104 162.204 163.024

420+260 -12.664 162.433 162.293 162.393 163.213

420+270 -12.949 162.578 162.438 162.538 163.358

420+280 -13.087 162.718 162.578 162.678 163.498

420+290 -13.172 162.824 162.684 162.784 163.604

420+300 -13.340 162.884 162.744 162.844 163.664

420+310 -13.645 162.943 162.803 162.903 163.723

420+320 -13.520 163.010 162.870 162.970 163.790

420+330 -13.175 163.073 162.933 163.033 163.853

420+340 -13.107 163.091 162.951 163.051 163.871

420+350 -13.162 163.107 162.967 163.067 163.887

420+360 -13.284 163.169 163.029 163.129 163.949

420+370 -13.747 163.280 163.140 163.240 164.060

420+380 -13.522 163.271 163.131 163.231 164.051

420+390 -13.131 163.256 163.116 163.216 164.036

420+400 -13.110 163.296 163.156 163.256 164.076

420+410 -13.239 163.343 163.203 163.303 164.123

420+420 -13.340 163.390 163.250 163.350 164.170

420+430 -13.280 163.425 163.285 163.385 164.205

420+440 -13.251 163.515 163.375 163.475 164.295

420+450 -13.218 163.641 163.501 163.601 164.421

420+460 -13.120 163.792 163.652 163.752 164.572

420+470 -13.138 163.895 163.755 163.855 164.675

420+480 -13.224 163.953 163.813 163.913 164.733

420+490 -13.168 163.969 163.829 163.929 164.749

Page 21: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 21

For Construction of pavement layers

The layout of each layer i.e. GSB layer, CTSB, CTB, DBM, BC-layers is made on the basis of

offsets that are marked on the existing road pavement at 10 m from the center line at fixed

intervals of 20m.

From these offsets, the required width of road i.e. main carriageway to be widened and service

road width is measured.

After measuring the width at the end side of the road, pegs are driven at a distance of 750mm.

The pegs have also a horizontal steel beam whose length of 250mm. Thus the available distance

is 750-250 = 500mm.

Now the beam of the pegs is movable as it can be moved up and down.

Adjusting the beam of the peg

Page 22: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 22

Thus by the use of Auto-level and nearby TBM, the height of beam is maintained to the

required proposed road level.

Pegs with steel wire providing proposed R-level

Thus pegs are driven at fixed interval of 10m.

At the end of beam of pegs, a cut is provided on which a steel wire is tied throughout the length

up to layer is to be laid down.

According to the level of steel wire paver machine will be laid down the layer upto a depth of proposed level of road by its sensor system.

Paver Machine laying WMM layer

Page 23: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 23

ABOUT HIGHWAY

National Highways (NH) are main highways running through the length and breadth of India,

connecting major ports , foreign highways , capitals of large states and large industrial and

tourist centres including roads required strategic movements for the defense of India . The

responsibility of construction and maintenance of national highways was decided to be with

central government.

The surface of the roadway should be stable and non-yielding, to allow the heavy wheel loads

of traffic to move with least rolling resistance. The road surface should also be even along the

longitudinal profile to enable the fast vehicles to move safely and comfortably at the design

speed. The earth road may not be able to fulfil the requirements, especially during the varying

conditions of traffic and the weather changes. Therefor a pavement consisting of superior and

stronger materials is laid over the prepared earth surface which could fulfil all the requirements.

The objective of laying a pavement is to support the wheel loads and to transfer the load stresses

through a wider area on the so subgrade below.

A pavement layer material is considered more effective or superior, if it is able to distribute the

wheel load stress through a large area per unit thickness of the layer.

Highway engineering is the back bone of civil engineering. It helps us in understanding road phenomena’s i.e., shoulder, slope or camber for draining water, pavement thickness etc. So, during construction, we need to keep all the parameters in mind otherwise it may leads to severe discomforts. Therefore the construction of the road is to be done as per the Typical Cross Section (TCS) approved by the client. One of the Typical Cross Section is, as given below:

Page 24: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 24

Page 25: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 25

PAVEMENT: A pavement consists of few layers of materials, is constructed over a prepared soil subgrade to serve as a carriageway. A pavement carries a wheel loads and transfer the load stresses through a wider area on the soil subgrade. A pavement layer is considered more effective, if it is able to distribute the wheel load stress through a larger area per unit depth of the layer. The thickness design for pavement layers for the traffic between 2 and 30 msa is exactly as per IRC 37-2001.

PURPOSE: Load support Smoothness Drainage The surface of roadway should be stable and non-yielding to allow the heavy wheel loads

of traffic to move with least possible rolling resistance.

TYPES OF PAVEMENTS 1. Rigid pavement. 2. Flexible pavement.

RIGID PAVEMENT: Rigid pavement consist of a cement concrete slab, below which a granular base or sub-base

may be provided. It possess a noteworthy flexural strength and the stresses are not transferred

from grain to grain to the lower layers. . Rigid pavements has the ‘slab action’ and is capable

of transmitting the wheel load stresses through a much wider area below the pavement slab.

FLEXIBLE PAVEMENT: The flexible pavement consists of the bituminous concrete layer. It possess negligible flexural strength and transmit the vertical or compressive stresses to the lower layers by grain to grain transfer through the point of contact in the granular structure. It consists of the following layers:

1. Subgrade soil 2. Sub-base course 3. Base course 4. Surface Layer

Page 26: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 26

PROPERTIES OF DIFFERENT LAYERS OF PAVEMENT:

1. SUBGRADE LAYER: It is the native material underneath a pavement crust. It is the integral part of the road pavement

structure as it provides the support to the pavement from beneath. The main function of the

subgrade is to provide adequate support to the pavement and for this, subgrade should possess

sufficient stability under adverse and loading condition. The minimum thickness for subgrade to

be provided is 500mm.

Before the soil is used as a subgrade, its laboratory test is conducted as per its size, shape,

surface texture, load bearing capacity etc.

At first, it’s Free Swell Index and composition of silt, clay and sand is determined. If its

swelling value comes below the range of 50% and also content greater Composition of sand

then only it is accepted.

Further carried out for other tests i.e., max. Dry density, CBR value etc. for its purpose of

use. If the CBR value comes greater than 15%, the soil is used for the purpose of laying out

for the subgrade soil as well as for the embankment construction. And if it’s CBR comes

below 15% then it only used for embankment purpose.

Sometimes the native soil at the site may be too weak to support a structure, so the soil is

replaced by taking it from other borrows areas conforming the all laboratory tests.

Page 27: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 27

The various borrow areas which are used here for subgrade and embankment purposes are:

Page 28: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 28

2. SUB-BASE COURSE: These layers are used under the flexible pavement primarily to improve the load supporting

capacity by distributing a load to a finite thickness i.e., 200-250mm.

In all cases of this layer, the top 100mm thickness of Sub-base is to be porous and act as

drainage layer.

The thickness of these layers are also evaluated by IRC 37-2001 as per CBR value and the Average Annual Daily Traffic (in msa).

There are two types of Sub-base layers which are mostly used:

1. Granular Sub-base(GSB):

The Granular Sub-base layers are made of broken stones, bound or unbound aggregate or the granular soil with no cementatious quantity.

It is desirable to use smaller size graded aggregates or soil aggregate mix instead of large boulder stone. These layers are mainly provided in main carriageway. The summary test results for GSB layer materials is:

Summary of GSB Mix Design R-1-GSB-OPTION-2 Grain Size Analysis

I.S. Sieve (mm)

75 53 26.5 9.5 4.75 2.36 0.425 0.075

Avg % of Passing

100 94.52 70.77 50.27 39.57 30.70 17.54 6.13

Specification Limit As per MoRT&H Table 400-1 Grading I Limits 100 80-100 55-90 35-65 25-55 20-40 10-25 3-10

10 % Fines Value Test (IS - 2386, Part IV)

Average Value of 10 % Fines Value (KN)

79.56 % Specification Limit As per MoRT&H Clause N0401.2,2

WATER ABSORPTION FOR GSB MATERIAL (IS 2386 Part.III)

Average Value Water Absorption (%) 0.73 % Specification Limit As per MoRT&H Clause N0401.2,2

Page 29: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 29

2. Cementatious Sub-base (CTSB):

The cementatious Sub-base contains 2-3% of cement with proper sizes of Coarse

Aggregates and Fine Aggregates followed by MORTH section 400. In all cases of this

layer, the top 100mm thickness of Sub-base is to be porous and act as drainage layer.

The thickness of these layers are also evaluated by IRC 37-2001 as per CBR value and the

Average Annual Daily Traffic (in msa).

The laboratory test to be performed for CTSB layer is :

i. Sieve Analysis Test.

ii. Compressive Strength Test.

Page 30: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 30

Page 31: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 31

3. BASE-COURSE:

Base course is as the most important component of flexible pavement layer which sustain the wheel load stresses and disperses through large area onto the Sub-Base layer below.

The Base-Course primarily has the similar function as that of the Sub-Base course and is provided with superior materials than sub-base course. The function of the base course vary according to the type of pavement.

As per MORTH section 400, the aggregates used in base course should have low Aggregate Impact Value (less than 30 %).

The two main base-course which are used here are:

1. Wet Mix Macadam Layer (WMM): It consists of Coarse Aggregate with size of 40mm,

20mm, and 10mm and the Dust particles with no cement content. These layers are mainly

used for extending main carriage way only. It is laid over the sub base layer by at least two

number of layers each of having 125mm thick.

2. Cementatious Base Course (CTB): CTB is an improved base course treated with cement.

It contents the same size of aggregates as that of WMM in addition 4 to 5% of cement.

Here, these layers are mainly used in the construction of new roads i.e., service road, roads

on the fly over etc.

Page 32: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 32

The summary of the test results for WMM materials are as below:

Page 33: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 33

The laboratory test to be performed for CTB layer is:

i. Sieve Analysis test. ii. Compressive Strength Test.

Page 34: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 34

PRIME COAT:

Bituminous prime coat is the first application of a low viscosity liquid bituminous material over an existing porous pavement surface like the WMM, CTB etc.

The main objective of priming is to bond the loose material on the existing surface and to plug in the capillary voids of the porous surface, using a binder of low viscosity which can penetrates into the voids.

The bituminous primer is sprayed uniformly using using a mechanical sprayer at a

rate of 6 to 9 kg per 10m2 area, depending on the porosity of the surface. The primed surface is allowed to cure for at least 24 hours, during which period no traffic is allowed.

TACK COAT:

A tack coat is the second application of coating which is applied over the prime coat. Sometimes a tack coat is applied on the existing bituminous surface as the first coating without application of prime coat.

It is usually applied by spraying bituminous material of high viscosity like the hot bitumen at the rate of 2.5 to 3 kg per 10 m2 area depending upon the type of the surface.

The main objective of spraying the tack coat is to make an interface

between DBM and the WMM layer and also to make an impervious layer of seal coat. It is sprayed at least one hour before laying of DBM layer.

A way of spraying the prime coat

Page 35: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 35

Page 36: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 36

4. SURFACE COURSE:

The two types of Surface course which are used here for the pavement designs are:

1. Dense Bituminous Macadam(DBM)

2. Bituminous concrete All these mixes consists of mineral aggregates and appropriate bituminous binder, mix in

a hot mix plant and laid in a mechanized paver. The layer thickness, Number of layers

allowed and its purpose for these specifications are as given below:

Specification Purpose Number of

layers

Thickness of each

layer

Dense bituminous Macadam

(DBM)

Base/ Binder

Course/ Overlay

for strengthening

Single or

Multiple

50mm-100mm

Bituminous Concrete (BC)

Wearing Course Single 25mm/40mm/50mm

Page 37: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 37

1. Dense Graded Bituminous Macadam (DBM):

DBM is the layer just below the surface bituminous concrete.

As per MORTH section 500, There are two grades of DBM used in the pavement (i.e., Grade I and Grade II) depending upon the layer thickness of the pavement.

Page 38: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 38

Page 39: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 39

Bituminous Concrete Layer:

It is the top most layer of the pavement surface with well compacted to form a high quality pavement surface course.

It consists of a mixture of Coarse Aggregate, Fine Aggregate, Mineral filler and Bitumen as per the specification of MORTH section-500.

The thickness of the bituminous concrete surface layer usually ranges from 25 to 50 mm.

Page 40: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 40

Page 41: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 41

MATERIALS USED: • Bituminous Content: The different types of bitumen as per IRC:111-2009 used here

for pavement construction are: VG40: For DBM. PMB, VG30: For BC.

• Course Aggregate: The coarse aggregate shall consists of crushed rock, crushed gravel or other hard material retained on 2.36 mm sieve. It shall be clean, hard, durable and free from dust and soft organic and other deleterious substances. The aggregate should preferably be of low porosity. It satisfy the physical requirements as specified in IRC: 111-2009 Table-5.

• Fine Aggregate: It shall consist of crushed or naturally occurring mineral, materials or a combination of two, passing 2.36mm sieve and retained on 0.075mm sieve. No natural sand will be allowed in the binder and wearing courses and not more than 50% natural sand will be allowed in the base course. The fine aggregate shall be clean, hard, durable, dry and free from dust organic and other deleterious substances. The plasticity index of The fraction passing the 0.425mm sieve shall not exceed 4 when tested in accordance with IS: 2720 Part-5.

• Filler: Filler shall consist of finally divided minerals such as rock dust, or hydrated lime or cement approved by engineer. The filler shall be inert material free from organic impurities and have plasticity index not greater than4. The filler shall be graded within the limits indicated below:

IS SIEVE (mm) Cumulative % passing by weight of

total aggregate

0.6 100

0.3 95 – 100

0.075 85 - 100

Page 42: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 42

AIMS OF HIGHWAY ENGINEERING IN OUR PROJECT:

Perfect widening of road from four lane to six lane.

Reconstruction of existing road.

Provision of service road.

WIDENING OF ROAD

For the widening of roads, the structural components which are used for the pavement is as below:

Embankment

Subgrade

GSB (Granular Sub-base)

WMM-1 (Wet mix macadam)

WMM-2

DBM (Dense bituminous macadam)

BC (Bituminous Concrete)

RECONSTRUCTION OF EXISTING ROAD

Existing road is a four lane. It is reconstructed to meet the fulfillment of increased designed wheel

load. During the reconstruction, the layers which are used for the pavement design is as below:

Embankment

Subgrade

CTSB

CTB

Aggregate Layer

DBM (Dense Bituminous macadam)

BC (Bituminous Concrete)

Page 43: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 43

CONSTRUCTION OF SERVICE ROAD

It is one lane road provided on both sides of main carriageway for diversion of local traffic to the

local areas. During the construction of service road, the layers which are used for the pavement

design are as same as that of reconstruction of existing road:

Embankment

Subgrade

CTSB

CTB

Aggregate Layer

BC (Bituminous Concrete)

STEPS OF CONSTRUCTION

Steps for the widening and reconstruction of main carriageway and construction of

service road:

1. For Widening of main carriageway or construction of service road : Dismantling of local

built up areas is done and then clearing and grubbing to remove vegetation, roots, other organic

matter along the alignment up to bottom width of embankment is made .

2. For Reconstruction of road: The dismantling of existing road pavement by use of breaker

arrangement in the excavator up to the desired depth.

3. Optimum moisture content of OGL (original ground level) is determined by Rapid method,

required water is added and mixed thoroughly. Then soil layer is compacted adequately to

achieve the specified dry density of OGL.

Page 44: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 44

Determination of Optimum moisture content at the Chainage 420+600

4. The selected soil for subgrade in loose condition is spread to the required grade and cross

slope in layers of desired thickness using blade motor grader.

Way of spreading the subgrade layer by blade motor Grader

Page 45: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 45

5. By performing OMC test on this subgrade, the required quantity of water is added and mixed

thoroughly, and then compaction is done by vibratory roller as to meet desired dry density.

Way of spreading water by water tank and then compacting by vibratory roller

6. The dry density of each compacted layer is checked by taking 1 or 2 samples per 1000m2 of

compacted area.

7. The thickness of loose soil layer is kept as 20% more to obtain the desired thickness of soil

subgrade after fully compaction. It should not be less than 500mm.

8. GSB : Granular Sub Base

a) Then the GSB sub-base is spread to uniform thickness and specified cross sectional

slope using a motor grader by adjusting the blade of grader.

b) The moisture content of material is checked and the additional quantity of required

water is added.

c) Then the loose GSB layer is compacted by vibratory roller of static weight 10 tones

with rolling speed is limited to 5 km per hour.

d) Rolling is done starting from the lower edge and proceeded towards the upper edge

of road.

e) Rolling is continued till at least 98% of MDD is received.

Page 46: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 46

9. CTSB/CTB/WMM : Cementatious sub base / Cementatious base course / Wet Mix Macadam

is directly laid down by use of hydrostatic paver sensor machine as given below:

a) Pegs are driven at fixed interval of 10m. At the end of beam of pegs, a cut is

provided on which a steel wire is tied throughout the length up to layer to be laid

down.

b) The reduced level of steel wire is fixed by Auto level as per drawing.

c) According to the level of steel wire, paver machine will be laid down the layer up

to a depth of proposed level of road by its sensor system.

Page 47: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 47

d) The moisture content of material is checked and the additional quantity of required

water is added.

e) Then compaction is done by vibratory roller of static weight 10 tones with rolling

speed is limited to 5 km per hour

.

10. Prime Coat is sprayed uniformly using a mechanical sprayer at a rate of 6 to 9 kg per 10m2

area, depending on the porosity of the surface. The primed surface is allowed to cure for at

least 24 hours, during which period no traffic is allowed.

11. Before laying the DBM layer, a Tack Coat is applied by spraying bituminous material of high

viscosity like the hot bitumen at the rate of 2.5 to 3 kg per 10 m2 area depending upon the type

of the surface.

12. DBM work is to be taken up during dry weather. The receiving surface should be clean and

free from dust.

13. DBM mix is spread using a hydrostatic paver finisher with sensor at specified paving

temperature. Rolling is started in three layers.

1.) Using tandem wheel vibratory roller of dead weight 8 to 10 tones

2.) Intermediate rolling using pneumatic roller (5.6kg/cm2) of 12 to 15 tones.

3.) Finishing rolling with 6 to 8 tones smooth wheel rollers.

Page 48: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 48

14. The compacted density achieved is checked by taking 150 mm core samples, the density

shall be more than 92% of theoretical max density.

Page 49: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 49

15. The final BC surface is laid down by hydrostatic paver finisher with sensor system. During

laying of BC layer 20% extra thickness is kept which will be compacted at the same time by

vibratory roller.

Laying of BC Layer at Chainage 439+980 to 440+500

16. After 24 Hrs, we will check the level what we achieved and relate it from designed level.

RL of the BC layer

17. Traffic is allowed only after bituminous concrete surface has cooled down to the

ambient temperature.

Page 50: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 50

ABOUT STRUCTURES

INTRODUCTION: Structural engineering is based upon the applied physical laws and empirical knowledge of the structural performance. It is derived from the latin word “Structra” which means “put together systematically” so any type of material when systematically arranged to support the external mass is known as structure. In civil engineering, the load carrying members when joined together to take several type of loads systematically and safely transfer to the ground is termed as structure.

Aims of Structural Engineering in Our Project

In our project Barwa-Adda-Panagarh NH2, structural engineering deals with the construction

of Minor Bridges, VUP, PUP, Box Culverts, Pipe Encasing, Retaining walls, laying of RE

blocks etc. A detailed introduction of each of above structure is given below in tabular form:

APCO INFRATECH LTD.

Six-laning of Barwa Adda - Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh bypass in the state of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT pattern

Structures List - Dhanbad section

S No.

Design Chainage

Proposed Strctural

Configuration Proposed Span LHS RHS Remarks

PUP Detail

1 398+495 6-Lane PUP 1 x 7.00 NC NC

2 399+230 6-Lane PUP 1 x 7.00 NC NC

3 409+088 6-Lane PUP 1 x 10.00 NC NC

4 407+400 6-Lane PUP 1 x 7.00 NC NC

5 417+953 6-Lane PUP 1 x 10.00 NC NC

6 424+500 6-Lane PUP 1 x 10.00 NC NC

RCC Box Culvert Detail

1 398+519 RCC Box 1 x 4.0 x 3.0 RC RC

2 398+786 RCC Box 1 x 3.0 x 3.0 RC RC

Page 51: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 51

3 403+335 RCC Box 1 x 3.0 x 3.0 RC RC

4 407+212 RCC Box 1 x 2.0 x 2.0 RC RC

5 407+422 RCC Box 1 x 2.0 x 3.0 RC RC

6 407+657 RCC Box 1 x 3.0 x 3.0 RHS WD RC

7 408+867 RCC Box 1 x 2.0 x 2.0 RC RC

8 409+060 RCC Box 2 x 3.0 x 3.0 RC RC

9 409+366 RCC Box 1 x 2.0 x 2.0 RC RC

10 411+332 RCC Box 1 x 3.0 x 3.0 RC RC

11 411+391 RCC Box 1 x 4.0 x 4.0 RC RC

12 417+933 RCC Box 1 x 4.0 x 4.0 RC RC

13 421+327 RCC Box 1 x 2.0 x 3.0 RC RC

14 421+497 RCC Box 1 x 2.0 x 2.0 RC RC

15 424+467 RCC Box 1 x 2.0 x 2.0 RC RC

16 427+882 RCC Box 1 x 2.5 x 2.0 RC RC

17 428+025 RCC Box 1 x 3.0 x 2.0 RC RC

Slab Culvert/HPC Detail

1 406+110 Slab Culvert 1 x 2.0 x 4.0 WD WD

2 406+471 Slab Culvert 1 x 4.5 x 4.5 WD WD

3 409+521 Slab Culvert 1 x 2.0 x 2.0 WD WD

4 411+752 Slab Culvert 1 x 2.5 x 3.0 WD WD

5 412+321 Slab Culvert 1 x 2.0 x 3.0 WD WD

6 412+613 Slab Culvert 1 x 2.3 x 3.0 WD WD

7 412+834 Slab Culvert 1 x 2.0 x 3.0 WD WD

8 413+353 Slab Culvert 1 x 2.3 x 2.5 WD WD

9 413+551 Slab Culvert 1 x 2.3 x 2.0 WD WD

10 413+926 Slab Culvert 2 x 2.0 x 2.0 WD WD

11 415+216 Slab Culvert 1 x 2.0 x 2.0 Retain RC

12 415+827 Slab Culvert 1 x 2.0 x 2.5 WD WD

13 416+280 Slab Culvert 1 x 2.3 x 2.5 WD WD

14 416+980 Slab Culvert 1 x 6.0 x WD WD

15 420+789 Slab Culvert 1 x 4.0 x WD WD

16 422+484 Slab Culvert 1 x 2.0 x 1.5 WD WD

Page 52: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 52

17 422+645 Slab Culvert 1 x 3.0 x 2.5 WD WD

18 423+025 Slab Culvert 1 x 3.0 x 2.5 WD WD

19 423+591 Slab Culvert 1 x 3.2 x 2.5 WD WD

20 423+985 Slab Culvert 1 x 1.4 x 2.0 WD WD

21 432+318 Slab Culvert 1 x 2.0 x 4.0 WD WD

22 435+915 HPC 1 x 0.6 LHS WD WD

23 436+129 HPC 1 x 1.0 WD WD

24 436+613 HPC 1 x 1.0 WD WD

25 438+313 HPC 2 x 1.0 WD WD

26 438+604 HPC 2 x 1.0 WD WD

27 438+862 HPC 2 x 1.0 WD WD

28 438+965 HPC 1 x 0.6 LHS WD WD

29 439+370 HPC 1 x 1.0 WD WD

30 439+709 HPC 2 x 1.0 WD WD

31 440+015 HPC 2 x 1.0 WD WD

32 440+095 HPC 1 x 1.0 WD WD

33 440+663 HPC 2 x 1.0 WD WD

34 440+851 HPC 2 x 1.0 WD WD

35 441+012 HPC 2 x 1.0 WD WD

VUP Detail

1 403+440 6-Lane VUP 1 x 12.00 NC NC

2 411+374 6-Lane VUP 1 x 12.00 NC NC

3 413+886 6-Lane VUP 1 x 12.00 NC NC

4 421+400 6-Lane VUP 1 x 12.00 NC NC

5 428+208 6-Lane VUP 1 x 12.00 NC NC

6 433+570 6-Lane VUP 1 x 12.00 NC NC

7 437+774 6-Lane VUP 1 x 1200 NC NC

3-Lane Flyover Detail

1 398+811 3-Lane Flyover 1 x 32.50 + 2 x 16.675 - NC

2 407+538 3-Lane Flyover 1 x 46.00 + 2 x 16.675 - NC

3 408+325 6-Lane Flyover 1 x 46.00 + 2 x 16.675 NC NC

3-Lane Bridge Detail

Page 53: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 53

1 405+340 New 3-Lane

Bridge 1 x 25.940 Retain RC

2 409+876 New 3-Lane

Bridge 15.495 + 15.100 +

15.495 Retain RC

3 415+115 New 3-Lane

Bridge 1 x 25.940 Retain RC

4 429+968 New 3-Lane

Bridge 2 x 15.495 + 1 x 15.100 Retain RC

5 437+050

New 3-Lane Bridge

1 x 25.940 Retain RC

METHODOLOGY OF EXECUTION

Every work is done by following some method and procedure for its perfect completion as required

.The methodology of construction of structure is given below:

Page 54: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 54

RFI

RFI is abbreviated as Request for Inspection. It includes all the necessary specification of

work to be made. It is the main proof of execution of work. Billing and payment is made on

the basis of RFI. It has two modules:

1. RFI Opening

2. RFI Closing

RFI opening means to make request to the client to visit your site as to inspect the work

which you execute. If he does satisfy then he will permit to proceed to complete the

work.

After completion of the work, you will have to go towards second module i.e. closing

of RFI that includes the measurement of work has done with attachment of necessary

documentation and sent to the client office for its billing and payment purposes .

Necessary documentation to be attached with RFI are given below:

1. RFI Performa

2. Concrete Pour Card

3. Concrete Measurement sheet

4. Check list For concrete work

5. Reinforcement Measurement Sheet

6. Check List for Reinforcement

Page 55: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 55

Page 56: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 56

Page 57: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 57

Page 58: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 58

Page 59: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 59

Page 60: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 60

Page 61: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 61

SITE CLEARANCE

This work consist of cutting , removing , and disposing off all materials such as trees , bush ,

sherbs , stumps , roots , grass , weeds , top organic soil not exceeding 150 mm in thickness

which in the opinion of the engineer are unsuitable for incorporation in the works . It include

necessary excavation, backfilling of pits resulting from uprooting of trees and stumps to

required compaction, handling and disposal of cleared materials with all lifts and leads.

Machinery used:

1. Excavator

2. Backhoe Loader

3. Dumper

LAYOUT

During the layout of structure the end coordinates points and levels of structure to be built on

the ground is provided. It is a responsibility of surveyor, the detailed procedure of layout is

already discussed in the section of layout of structural elements in which we observed the

bottom ground level of structure foundation and its exact location on the ground in terms of

coordinates.

EXCAVATION

Excavation is the process of cutting and removing earth including rock from its original

position, transporting and dumping it as a filler material.

The excavation needed in soil, soft rock or even in hard rock for constructing the sub

structure.

The depth of excavation is decided on the requirement of foundation bottom level as per

given drawing.

Page 62: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 62

Machinery used:

1. Excavator

2. Breaker

3. Dumper

EXCAVATION FOR ABUTMENT OF MINOR BRIDGE

DISMANTELLING OF HARD ROCK BY BREAKER

Page 63: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 63

PCC LAYING

Plain cement concrete is laid down before constructing foundation. It is laid first and over it

foundation is constructed. It provides a hard and levelled surface for foundation.

It is used to provide rigid impervious bed to RCC in foundation where earth is soft and

yielding.

Thickness of PCC:

The thickness of PCC is normally kept 150 mm for important work likewise Minor Bridge,

VUP, PUP, flyovers, retaining wall etc. and for crash barrier the thickness of PCC is kept as

100mm.

Material proportions for PCC:

M-15 design mix is used for laying Plain Cement Concrete. The proportions of M-15 design

mix are given below:

Grade of concrete : M-15

W/C : 0.50

Description Material Wt. (in Kg) at

SSD condition for 1m3

Percentage of agg. in

mix

Cement 270.000 -

C.A 20mm 628.590 26.10%

C.A 10mm 742.290 31.90%

Course sand 835.280 42.00%

Water 135.000 -

Admixture 3.780 -

Page 64: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 64

PCC Laying (CH. 412+834)

PCC laying for Frictional Slab (CH. 417+020)

Page 65: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 65

REINFORCEMENT

“Reinforcement is the Skelton of structure”. The tensile strength of cement concrete is just

about 10 percent of its compressive strength so steel bars are used to reinforce cement concrete

in the tension zone of flexural members to compensate for the low tensile strength of cement

concrete .

The original load carrying capacity of cement concrete is very much increased by providing

additional tensile strength by using steel bars.

The steel has high strength material as compared to concrete. The compressive yield strength

of ordinary steel bars is about 25 times, the compressive strength of cement concrete and

tensile strength of steel bars is about 70 times the tensile strength of cement concrete.

Reinforcement if suitably designed and placed, increases the strength of concrete as well as

controls the effect of shrinkage and temperature changes.

GRADE OF STEEL USED HERE – Fe 500D

REINFORCEMENT YARD

Page 66: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 66

Placing of reinforcement at site:

1. Bottom reinforcement for Raft of VUP

Chainage: 433+570

2. Top reinforcement of raft

Page 67: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 67

3. Showing vertical reinforcement of abutment of the minor bridge

4. A closer view of haunch reinforcement in wall

Page 68: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 68

Precaution to be kept in mind while installing reinforcement

Proper clear cover is provided by cover blocks.

Check vertical stirrups with proper hook.

Chairs of minimum 12mm dia. bars should be used.

Check the numbers of bars as per drawing.

The provision of lap splices should not be less than 56times of dia. of bars.

Each bar should be bonded with another by binding wires only.

All reinforcement should be free from loose rust and coats of paints, oil, or any other substances.

Proper spacing should be provided as per drawing/BBS.

FORMWORK AND FALSEWORK

Formwork for in-situ concrete may be described as a mould or box into which wet concrete

can be poured and compacted. It is temporary structure in the sense that is erected quickly,

highly loaded for a few hours during the concrete pour and within a few days disassembled for

the future reused.

False work is the horizontal and vertical load bearing members which supports the

formwork.

Component of false work and formwork:

1. Shuttering Plates

2. Soldier

3. Tie-Rods

4. Horizontal props & Vertical props

5. Cap-lock & laser pipe

6. U-Jack

7. Base-Jack

Page 69: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 69

Horizontal / Vertical Props & Shuttering Plates

View of Formwork and Falsework

Page 70: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 70

Form-work and falsework must fulfil the requirements as below:

Should be strong enough to support load of wet concrete i.e. 2400 kg per m3.

Must not able to deflect under load, which includes the loading of wet concrete, self-weight and

superimposed loads.

Must be accurately set out.

Have well - tight joints.

Should have bolting arrangement to joint adjacent shuttering plates.

Having well arrangement of Tie-rods in shoulder.

CONCRETING

Concrete is a mixture of cement, water, fine aggregates and coarse aggregates which when placed in

forms and allowed to cure becomes hard like stone. The hardening is caused by chemical reactions

between water and cement and concrete grown stronger with age. The weight of cement concrete is

24 KN / m 3.

It has a poor tensile strength and is liable to crack when subjected to tension. It also give rise to

shrinkage stresses.

To overcome the tensile stress plain cement concrete is reinforced with steel bars, these will

develop tensile strength in concrete in tension and known as Reinforced Cement Concrete.

Page 71: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 71

Type of Concrete Mix:

The proportion of concrete is done on the basis of design mix. In the design mix concrete the

proportion of cement, aggregates and water are determined by conducting preliminary tests on it for

achieving good durability, strength and economy.

Grade of concrete:

Type of

structure

Minor

Bridge

VUP Box

culvert

Retaining

Wall

Crash

Barrier

Kerb

PCC

Grade of

Concrete

M-30

M-25

M-25

M-20

M-15

Proportions For Design Mix Concrete

Material Units

M-15

(PCC)

M-20

(PCC)

M-20

(RCC)

M-20

(KERB)

M-25

(RCC)

M-30

(RCC)

M-35

(RCC)

M-40

(RCC)

W/C ratio % 0.5 0.5 0.45 0.5 0.43 0.39 0.38 0.36

Cement Kg 270 280 315 290 340 370 380 410

20mm

Aggregate Kg 628.59 621.82 579 595.88 735.24 730.29 748.21 734.79

10mm

Aggregate Kg 742.29 734.31 684 703.67 581.22 577.31 591.47 580.86

Coarse

Sand Kg 835.28 826.29 870 859.15 799.37 793.28 748.91 735.47

Water Kg 135 140 142 145 146.2 140.6 144.4 147.6

Admixture Kg 3.78 3.92 4.41 1.45 3.74 4.88 4.94 5.33

Page 72: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 72

Transporting and placing of concrete:

The process of carrying concrete mix from the place of its mixing to the final position to deposition is

called transportation of concrete. Transportation of concrete mix is very important because in

transportation, time factor is involved. The mix should be transported as quickly as possible.

The process of depositing the concrete in its required position is known as placement of concrete.

The quality of concrete also depends on the method of placing. If it is not placed properly segregation

will take place.

Machinery used:

1. Boom Placer (Concrete Pump)

2. Transit mixer

3. Needle vibrator

1. Concreting of VUP Raft by Boom Placer (433+570)

Page 73: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 73

2. Pouring of concrete

Precaution during placing of concrete:

The concrete should not be dropped from a height of more than 1 m to prevent segregation.

Oiling should be done properly on the internal surface of the steel formwork before placing

concrete so that the concrete may not stick to it.

After placing each layer of concrete, vibration should be done properly by inserting needle

vibrator vertically at points 0.45 to 0.75m apart to compact the concrete.

Over vibration should be avoided to avoid segregation.

During concreting, formwork should not be disturbed.

The concrete should be kept agitated in truck mixer so that it does not becomes stiff when

transportation is likely to take more time.

Chute should be used when concrete is to be placed below lower level and must be placed on

a slope sufficient steep to handle concrete of the least slump.

After 24 hrs deshuttering should be done and curing arrangement is made for at least 7 days.

Page 74: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 74

CURING:

The term 'curing' is used to include maintenance of concrete structures in favorable

environment for the continuation of chemical reactions, i.e. retention of moisture within, or

supplying moisture to the concrete from an external source and protection against extremes of

Temperature.

Curing of raft by ponding and Hassion clothes

Spraying of water on Crash Barrier Curing of the raft of Retaining Wall

Page 75: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 75

A COMPLETE COSTRUCTIONAL PROCESS OF A SRUCTURE

i.e.

CONSTRUCTION OF BOX CULVERT.

CONSTRUCTION OF RETAINING WALL.

A. Construction of Culvert with Retaining wall Introduction:

Culvert: A culvert is a structure that allows water to flow under a road, or other obstruction from one side to the other. It may be made of a pipe, reinforced concrete or other materials.

Retaining Wall: Retaining walls are structure designed to restrain soil to unnatural slopes. They are used to bound soil between two different elevations.

Purpose of Use of Culvert: To pass the drainage water. To pass the cable wire. To pass the water supply pipeline.

Types: In this project, according to the shape, three types of Culvert are used:

1. Slab Culvert 2. Box Culvert 3.Hume Pipe Culvert

Slab Culvert Box Culvert

Page 76: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 76

Hume Pipe Culvert And two types of Retaining Wall are used:

1. L-Type Retaining Wall 2. Invert T-Type Retaining Wall

L-Type Retaining Wall Invert T-Type Retaining Wall

Page 77: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 77

Complete Construction of Box Culvert (CH.412+834):

Architectural Drawing:

Page 78: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 78

Page 79: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 79

Page 80: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 80

Page 81: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 81

Way of Construction:

a. Site Clearance: Cutting , removing , and disposing off all materials such as trees , bush , sherbs , stumps , roots , grass , weeds , top organic soil etc. should be removed first.

b. Excavation: Here we are to extend the culvert from the existing culvert, so the mid-point

of the existing culvert is taken out by Tape and according to that, the excavation is carried out. It is carried out mechanically by backhoe loader. As the electric wire passes above the construction, adequate operation were taken to see that the excavator do not touches the wire. Excavation is carried out providing flat surface. The depth of the excavation is taken as per the RL of the drawing (i. e., 3.5m) from TBM point of the crash barrier.

During Excavation

After Excavation

Shear Key excavation

Page 82: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 82

There are some points which should be kept in mind at the time of excavation. o The level of the depth of excavation should be checked by the auto level to avoid the

excess cutting. It helps the structure to be at proper level and minimize the consumption of concrete.

o The excavation should be done by taking at least one metre greater in length as per the dimensions of the drawing. It helps to layout the PCC properly and to make the shuttering easily.

o Bottom of the trench shall be cleaned, free of loose material, rock projection and the surface should be levelled and moistened uniformly before laying the PCC.

c. Laying of P.C.C. (Plain Cement Concrete): After the completion and labelling, laying of Plain Cement Concrete is done. A layer of 150mm thick PCC of grade M15 with 100mm projection was made in such a manner that it was not mixed with the soil. It provides a solid base for the raft foundation and a mix of 1:3:5 that is 1 part of cement to 3 parts of fine aggregates and 5 parts of coarse aggregate by weight were used in it.

PCC for the Box Culvert (CH. 412+834)

Page 83: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 83

d. Construction of Raft: i. Bar-binding: The bars for the raft was tied as according to structural

drawing up to the height determined from the framing plan. The proper binding of the bars gives the sufficient tensile strength to the structure.

ii. Formwork: The shuttering plate is cleaned and oiled properly and then it

is fixed around the raft. At bottom starter, keep shuttering in position and at top and middle, cover blocks are fixed so that proper cover could be provided to reinforce. The cover blocks of 75mm & 40mm should also be placed at the top of the PCC (i.e., below the bottom bars of rafting) and above the top bars of the raft respectively.

iii. Levelling, Pouring and Compaction of the raft: The exact level of the raft is marked on the shuttering plate i.e.,300mm from the top of the PCC with the help of measuring tape and according to that level, the concrete is poured with the help of pump and pipe. At the end of pipe a flexible hose is provided so as to facilitate the concrete placing process. Vibrators are also used to give a good compaction. After pouring, the surface is made smooth with the help of planner.

Page 84: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 84

iv. Removal of the Formwork: The very next day, the shuttering of columns is removed.

v. Curing: After the removal of the formwork, the date of raft casted is

marked on it and its surface of concrete is covered with the help of hassion clothes. The surface of concrete is kept wet for next seven days by sprinkling water continuously or by ponding.

Curing of the raft by Hassion Clothes and by ponding

Page 85: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 85

e. Construction of other Structures of the Culvert (Side Wall, Top slab and the Retaining Wall) : The other structures of the culvert are also constructed by same process as the raft is constructed i.e., from Bar-Binding to Curing.

Binding of the bars Fixing the Shutters

Pouring of Concrete

Page 86: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 86

Estimation of the Material used:

Page 87: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 87

Bar Bending Schedule

Page 88: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 88

Page 89: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 89

Page 90: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 90

Page 91: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 91

Page 92: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 92

QUALITY-CHECK/QUALITY-ANALYSIS

LABORATORY

INTRODUCTION

A laboratory provides such a facility in which measurements, experiments and designs are

performed in a controlled conditions so it is a basic need of any engineering project.

Laboratory tests on materials such as tests on soils used in the field for subgrade purpose, the

aggregates used in various pavement component layers and the bituminous binder and mixes

used in top layers of flexible pavements are very important need for a successful construction.

Some of the essential field tests which are to be carried out during the construction of

various component layers, are as the part of quality control check and some simple field

tests for structural and functional evaluation of pavements are done in the laboratory.

LABORATORY

Page 93: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 93

LABORATORY TESTS

DAILY PROGRAM REPORT

TEST ON SOIL

Grain Size Analysis Test Free Swell Index

Atterbergs Limits (Liquid Limit)

Modified Proctor Compaction Test (Maximum Dry Density)

California Bearing Ratio

TEST ON AGGREGATES

Aggregate Impact Value Test

Fineness Modulus and Sieve Analysis.

Flakiness and Elongation Indices.

TEST ON BITUMEN

Standard Penetration Test

Softening Point Test

Elastic Recovery Test

TEST ON CEMENT

Fineness test

Standard Consistency Test

Initial and Final Setting Time Test

Soundness Test

Compressive Strength Test

FIELD TEST

Field Dry Density

Page 94: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 94

DAILY LABORATORY PROGRAM

A daily laboratory program is a scheduled program that is made at the beginning of each day by

the assistant manager and passes it to the project manager for its approval. In the laboratory the

daily program aware about what material-designs and tests will be performed on the same day. It

also records the activities are made on that day. One of the daily labouratoy program is as shown

below.

Page 95: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 95

TESTS ON SOIL

Grain Size Analysis Test The soil with greater percentage of Sand gives greater stability to the structure.

Page 96: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 96

Free Swell Index

.

Page 97: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 97

Atterbergs Limits (Liquid Limit)

Casagrande’s Apparatus

Page 98: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 98

Modified Proctor Compaction Test (Maximum Dry Density)

MODIFIED PROCTOR TEST MOULD

Page 99: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 99

California Bearing Ratio Test

CBR Apparatus

Page 100: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 100

Page 101: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 101

TEST ON AGGREGATES

Aggregates Impact Value Test

Aggregate Impact Value Test Apparatus

Page 102: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 102

Fineness Modulus and Grain size distribution Test. a. Course aggregate

Page 103: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 103

a. Fine aggregate

Page 104: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 104

Flakiness and elongation indices of Course Aggregate a. To determine the flakiness index of course aggregate.

Page 105: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 105

TEST ON BITUMEN

Standard Penetration Test

Page 106: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 106

Softening Point Test

Page 107: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 107

Elastic Recovery Test

Ductility Testing Machine

Standard Briquette The elastic recovery of the tested specimen in percent may be computed as: Elastic Recovery, % = 100(10-X) 10 As per IRC, the requirements of minimum elastic recovery value for different modified binders are:

Types of Modified Bitumen Elastic Recovery at 15 oC. % Polymer modified bitumen 50

Natural rubber modified bitumen 30-50

Crumb rubber modified bitumen 50

Page 108: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 108

Page 109: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 109

TEST ON CEMENT

Fineness Test. Standard Consistency Test. Setting Time of the Cement

Vicat Apparatus Needle for Std. Consistency, initial &final setting time

Page 110: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 110

Soundness Test of Cement

Page 111: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 111

Compressive Strength of Cement

Compressive Testing Machine Mould of the Cement cube

Page 112: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 112

FIELD TEST

Field Dry Density

MATERIAL EXCAVATED

Page 113: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 113

OTHER IMPORTANT TESTS

The Other Important Tests which are performed are:

1. NATURAL MOISTURE CONTENT TEST.

2. RAPID MOISTURE METER TEST.

3. CORE CUTTER TEST.

4. CONCRETE MIX TRIAL.

5. CONCERETE STRENGTH TEST.

6. SPECIFIC GRAVITY OF CEMENT, SAND, C.A., BITUMEN.

7. BITUMEN EXTRACTION TEST.

8. VISCOSITY TEST OF BITUMEN.

9. WATER ABSORPTION TEST

10. BITUMINOUS MIX TRIAL etc.

Page 114: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 114

INFORMATION ABOUT THE PLANT AND EQUIPMENTS

The Plants, Equipment and the Vehicles used in this project are as below:

Concrete Mixer Plant: Mixer plant provides the facility to mix the various ingredients

of concrete in required proportions in the order to fulfil the quantities of concrete and without more lead distance. A concrete plant also known as a batch plant, is a device that combines various ingredients to form concrete. Some of these inputs include sand, water, aggregate, fly ash and cement and the Centre of the concrete batching plant is the mixture. These employ computer aided control to assist in fast, accurate measurement of input constituents or ingredients, as well as tie together the various parts and accessories for coordinate and safe operation. The Bituminous mixer plant is also there for the purpose of mixing the ingredients for flexible pavement layers i.e., Dense Bituminous Macadam and Surface Course.

Concrete Batching Plant Bituminous Hot Mix Plant

Page 115: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 115

Immersion or needle vibrators: This is perhaps the most commonly used vibrator.

It essentially consist of a steel tube called poker is connected to an electric motor or a diesel engine through a flexible tube. The normal radius of action of an immersion vibrator is 0.50 to 1.0m. However, it would be preferable to immerse the vibrator into concrete at intervals of not more than 600mm or 8 to 10 times the diameter of the poker.

Concrete Vibration Practices

Before starting a job, be sure to have a spare vibrator ready as a backup plan.

Don’t over vibrate concrete. Over vibration of concrete will lead to honeycombing instead of reducing it.

If you are pouring a low slump concrete, be sure not to under vibrate it, as honeycomb will also be a problem.

The vibrator shall be penetrated vertically to maximize its effects.

Do not over bend the vibrator, it will fail.

Concrete vibrator shall be hold at least 10 seconds into the concrete mix.

Every time the vibrator is inserted, its radius of action shall overlap from the previous one. Remember that every concrete vibrator has its own field of action. It is estimated that the field of action is four times the vibrator tip diameter.

The vibrator shall not be turned on outside of the concrete.

Page 116: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 116

Concrete Vibration Benefits: A good vibrator concrete will offer some benefits such as:

Have a higher compressive strength. A properly vibrated concrete will increase the bonding capacity between concrete and bars. Provide a better sealed concrete, it can order drier mixtures that require less cement. Offer greater durability. Bonding strength between layers of concrete will increase.

Bar Cutting machine: This machine is used for cutting the bar as per requirement in

large quantities. The machine can do the operation of cutting up to 12nn dia. And for bar having dia. Greater than 12mm then bar cutter is used.

Page 117: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 117

Bar Bending Machine: Bar Bending Machine is a semi-automatic, durable fast and

cost effective machine, used for bending reinforcement bars and various form of round bars. The automatic angle selection permits precise bend at a preset angle making it one step bending process for various forms of bends and stirrups. Bar Bending Machine is easy to use; the machine can be operated by a layman with minimal experience.

Transit mixer: It is used to transport the concrete from the place of production to the

site. Nominal capacity of transit mixture is 6m3 and total geometric volume is used for transporting the concrete from batching plant directly to the place where it is to be poured. It has a wide range of application especially for mass concreting works like high rise building construction and Dams and airports etc. The angle of drum is 150 and drum speed varies from 0-14 rpm. It optimized the position of spiral ensures maximum discharge of concrete. Weight of mixer is varies from 2500 kgs-3760 kgs. At our site there are 8 no of transit mixer which are used in different pocket.

Page 118: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 118

Excavator: Excavators are heavy construction equipment consisting of a boom, dipper,

bucket and cab on a rotating platform known as house. These are used for digging of trenches, holes, foundations, material handling, general gradding or landscaping etc.

Hydra (Cranes): These are used in taking off heavy objects and also to transport them

from one to other place at the site. A crane is a lifting machine that principally works with the use of pulley and cable. For the construction industries, cranes are valuable assets because they make working with heavy machinery and construction material easy. The invention of cranes made things easy for mankind because without loading, unloading and lifting had to be done by human hands, would consume more time, and the entire system was not efficient at all.

Page 119: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 119

Paver: A paver is a piece of construction equipment used to lay asphalt on road, bridges

and other such places. It lays the asphalt flat and provides minor compaction before it is compacted by roller.

Road Roller: A road roller is a compactor type engineering vehicle used to compact soil, gravel, asphalt in the construction of roads and foundation.

Page 120: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 120

Motor Grader: A grader is a machine with a long blade used to create a flat surface. Grader are commonly used in the construction and maintenance of dirt roads and gravel roads. In the construction of paved roads they are used to prepare the base course to create a wide flat surface for the asphalt to be placed on.

Water Tank Truck: These are used in highway construction for many purposes: For compaction of layers. For dust control. For curing the structure by spraying water etc.

Page 121: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 121

Loader: A loader is a type of tractor, usually wheeled, sometimes on tracks, that has a front-mounted square wide bucket connected to the end of two booms(arms) to scoop up loose material from the ground, such as dirt, sand or gravel and move it from one place to another without pushing the materials across the ground. It is also used to load and transport the coarse and fine aggregate to the hopper of the batching plant.

Dumper: A Dumper is a motor vehicle used to transport the WMM, CTSB, GSB, Surface course material etc. for the construction of pavement layers.

Page 122: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 122

Concrete Pump Vehicle (Boom Placer): A concrete pump is a machine used for transferring liquid concrete by pumping. It helps to cast the concrete structure to those places where there is not easily be accessible.

Crusher Machine: It is a machine used to crush the bigger stone to smaller size. These

smaller sizes of aggregates are used for constructional purpose. These crusher machine gives a size of 40mm, 20mm, 10mm of aggregates and dust.

Page 123: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 123

Kerb Laying Machine: Kerb laying machine are used to design the Kerb at the side end of the pavement. It consists of an L-type or I-type steel kerb mould, bucket and the sensor machine. The sensor machine is first adjusted to a proper level and then concrete is placed on the bucket with the help of Transit Mixer, the mould will automatically give the concrete as the shape of L-type or I-type kerb.

Front view with kerb mould Side view with concrete bucket

The other machines used here, are:

Used for spraying Prime Coat or Tack Coat

ZEEP:

Used for transporting labours and for inspection purpose

Page 124: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 124

SAFETY MEASURES AND COMPAIGN

In Civil Engineering Construction project, accidents cannot be avoided. A mishap can happen

any time and unexpectedly during construction. About 80 percent of accidents are mainly

caused due to unsafe practices and shear negligence of the workers. Safety measures are

necessary to motivate and encourage the workers to work at the given site or industry without

any fear, tension or worry in mind about his security of life. Good safety measures are essential

to increase the output of work by generating safety free environment sense of contentment

among the workers.

Safety measure can be efficiently handled by properly educating and training workers about

the safe rules and their importance. It is the foremost duty of construction management to

appoint separate safety engineer to undertake safety measure and to prevent the occurrence of

accidents. The causes of accidents should be properly investigated and suitable measures

should be adopted to control these accidents. Thus, safety measures help in;

Reduced worker’s compensation claims.

Reduced expenses related to injuries and illnesses.

Reduced absenteeism and lower employee complaints.

Loss of life and increased productivity.

Improved employee morale and satisfaction.

Reduction of hidden cost and reduced insurance cost.

Page 125: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 125

Personal Safety

Wear protective equipment like safety helmet, safety jacket and safety footwear at

construction site.

Do not drink or take drugs while working.

Pay attention to personal hygiene.

Do not play in the workplace.

Report to your supervisor immediately if you notice any unsafe act.

Safty shoes during concreting

Page 126: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 126

Public Safety

Pay attention to public safety. Members of the public are often unaware of or do not understand

the work carried out on construction sites and the hazards involved.

The Proper Sign Board with Red Band and Crash Barrier for the safety movement of vehicles

Safety stand Barriers provided near a service road construction

Page 127: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 127

Safety stands barriers provided near a culvert construction Ch.411+752

A safety Sign Board provided near the highway

Page 128: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 128

Safety Campaign

An organized movement launched by an enterprise or construction firm to advocate the

safety rules and regulations among its workers so to reduce the number of accidents is

termed as safety campaign. The following points should be kept in mind for launching

safety campaign.

The safety campaign must be placed under the charge of a very competent, experienced

and able manager, who may be termed as Safety Director.

The worker should be frequently addressed in a small group in their language or easy

accessible language to explain about safety rules.

Page 129: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 129

Awareness of safety to the labourers

Page 130: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 130

Do’s and Don’ts

Constructional work should be displayed in bold letter along with diagram on chart paper or

Borads.

Advertisement films, Documentaries and CD should be shown to the workers on off days,

explaining about the need for safety measures.

Training in first-aid should be provided to workers and supervisors for treating minor cuts and

injuries.

Safety journals should be brought about by the concerned management and distributed free of

cost to the workers.

Page 131: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 131

Overall Benefits of Training

Industrial Training is a class held at site to provide an enhanced understanding of the outside

working environment before the student graduation. Student of engineering and other fields

also take this practice. The main aim of this practice (industrial training) is to teach students

how to communicate professionally, to hone practical skills they learned, to upgrade the

theoretical knowledge, to improve their leadership skills and team playing skills etc. I have

acquired much knowledge in different areas. The experience gained will be helpful in

professional life ahead.

Page 132: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 132

Work ethics and related issues

The concept of the work ethics may be summarized as the overall quality in one’s behavior

towards appreciating the process of work flow and performing rather well on the job so that

this work will not be jeopardized in the long run. During my training program, I could say that

I have managed to do my side of the job description with a high spirit and enthusiasm so that

there was a smooth flow of activities both in the office and on construction site. Work ethics

involve such characteristics as honesty, responsibility, reliability, accountability and etc.

Punctuality is one of the major issues that could be raised when talking about work ethics and

on my side I tried to meet this criterion by going to the site in time so that there would not be

any delay on the activities planned for that day. The behavior that one shows towards his peers

and colleagues is also one manifestation of the concept of work ethics. Personally, I always

respected and gave priority to the employees of the company. Elements of work ethics that

worth mentioning are: - punctuality, honesty, reliability, office discipline, corporation and

responsibility.

Page 133: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 133

Conclusion

The entire period of Industrial Training has given me a good & important practical exposure

of construction work. At the end of the Industrial Training under Construction Company

APCO Infratech Pvt. Ltd, I feel myself better equipped and ready to face the field problems

related to Civil Engineering works. In these three months, I have learnt how to deal with

Authorities and workers under supervision and I have become familiar with the fact that the

field work is much difficult from theoretical knowledge. But until you don’t have the

theoretical knowledge, the practical work is very difficult to carry-out and understand.

Working with the experienced engineers has enhanced my technical skills to a great extent for

which I am grateful to them. Their professional approach towards work is appreciable.

The training has provided me with much needed field exposure to shape up my thinking in a

better way as a professional making me a lot more capable to face the challenges of life.

Page 134: most final report of industrial training for college

INDRAJEET KUMAR, GNDEC 134

References and Bibliography

Test include the details carried out through the Site engineers, Supervisors, labours and the lab

manual book.

Drawings shown above are made on AUTO CAD 2007

Images shown in the report are self-clicked images at various locations