Date post: | 22-Oct-2014 |
Category: |
Documents |
Upload: | stephen-crawford |
View: | 396 times |
Download: | 47 times |
Type MRTP
Supervision for AC Pilot Circuits
Service Manual
R8026F
CONTENTS
1 INSTALLATION 31.1 General considerations 31.2 Relay mounting 31.3 Unpacking 31.4 Storage 3
2 COMMISSIONING 42.1 Electrostatic discharges (esd) 42.2 Inspection 42.3 Wiring 42.4 Earthing 42.5 Insulation 42.6 Electrical tests 4
3 MAINTENANCE 7
4 PROBLEM ANALYSIS 74.1 DC circuits 74.2 AC circuits 94.3 Injection filter (MRTP 01 and MRTP 02) 9
5 SPARES 10
6 CALIBRATION AND TEST 10
7 COMMISSIONING TEST RECORD 11
REPAIR FORM 15
Page 2
ssincey
ort
eipt,
ngation
anduld beuld be
onsns
placeags
trior to
to the withture
Section 1 INSTALLATION
1.1 General considerations
Protective relays, although generally of robust construction, require carefultreatment prior to installation on site. Upon receipt, relays should be examinedimmediately, to ensure no damage has been sustained in transit.
When handling a relay, great care must be taken, particularly when the relay iremoved from its case. Touching the printed circuit board should be avoided, metal oxide semiconductor (mos) devices are used, which can be damaged belectrostatic discharges.
If damage has been sustained in transit, a claim should be made to the transpcontractors and AREVA T&D Limited should be promptly notified. Relayswhich are supplied unmounted and are not intended for immediate installationshould be returned to their protective polythene bags.
1.2 Relay mounting
Relays are despatched either individually or as part of a panel/rack mountingassembly. If the relays are to be installed into a panel/rack assembly after recthen construction details can be found in Publication R-7012.
For individually mounted relays an outline diagram is normally supplied showipanel cut-outs and hole centres, these dimensions will also be found in PublicR-6102.
1.3 Unpacking
Care must be taken when unpacking and installing the relays to avoid damagethey must at all times be handled by skilled persons only. The installation shoclean, dry and reasonably free from dust and excessive vibration. The site showell lit to facilitate inspection.
Relays which have been removed from their cases should not be left in situatiwhere they are exposed to dust or damp. This particularly applies to installatiowhich are being carried out at the same time as construction work.
1.4 Storage
If relays are not installed immediately upon receipt they should be stored in a free from dust and moisture in their original cartons and where de-humidifier bhave been included in the packing they should be retained. The action of thede-humidifier crystals will be impaired if the bag has been exposed to ambienconditions and may be restored by gently heating the bag for about an hour, preplacing it in the carton.
Dust which collects on a carton may, on subsequent unpacking, find its way inrelay; in damp conditions the carton and unpacking may become impregnatedmoisture and the de-humidifying agent will lose its efficiency. Storage tempera–25°C to +70°C.
Page 3
henandshould are
duringeully
e
nal
s theal that
ef the, 3, 5,lock
d to
e notpped must
Section 2 COMMISSIONING
2.1 Electrostatic discharges (esd)
The relay uses components which are sensitive to electrostatic discharges. Whandling the module, care should be taken to avoid contact with components electrical connections. When removed from the case for storage, the module be placed in an electrically conducting anti-static bag. Full handling guidelinesgiven inside the front cover of this manual.
2.2 Inspection
Carefully examine the module and case to see that no damage has occurred transit. Check that the relay serial numbers on the module, case and cover aridentical, and that the model number and rating information are correct. Carefremove any elasticbands/packing fitted for transportation purposes.
2.3 Wiring
Check that the external wiring is correct to the relevant relay diagram or schemdiagram. The relay diagram number appears inside the case.
Particular attention should be paid to the correct wiring and value of any exterresistors indicated on the wiring/relay rating information.
Note that the shorting switches on the relay diagram are fitted internally acrosrelevant case terminals and close when the module is withdrawn. It is essentisuch switches are fitted across all ct circuits.
If test block type MMLG is provided, the connections should be checked to thscheme diagram, particularly that the supply connections are to the live side otest block (coloured orange) and with terminals allocated with odd numbers (17 etc.). The auxiliary supply voltage to the scheme should be routed via test bterminals 13 and 15.
2.4 Earthing
Ensure that the case earthing connection above the rear terminal block, is useconnect the relay to the local earth bar.
2.5 Insulation
The relay and its associated wiring may be insulation tested between:
(i) all electrically isolated circuits.
(ii) all circuits and earth.
An electronic or brushless insulation tester should be used, having a dc voltagexceeding 1000V. Accessible terminals of the same circuit should be first stratogether. Deliberate circuit earthing links, removed for the tests, subsequentlybe replaced.
2.6 Electrical tests
DANGER:
DO NOT OPEN CIRCUIT THE SECONDARY CIRCUIT OF A CURRENTTRANSFORMER SINCE THE HIGH VOLTAGE PRODUCED MAY BELETHAL AND COULD DAMAGE INSULATION.
Page 4
ets
y
h aever, its and
ay be
TP 01motetage
tly
ly
green
teilot
fset
dicator
tions
holergetor. ifidered
t ofever
When type MMLG test block facilities are installed, it is important that the sockin the type MMLB01 test plug, which correspond to the current transformersecondary windings, are LINKED BEFORE THE TEST PLUG IS INSERTEDINTO THE TEST BLOCK. Similarly, a MMLB02 single finger test plug must beterminated with an ammeter BEFORE IT IS INSERTED to monitor ct secondarcurrents.
The instructions have been written assuming that not all schemes are fitted wittest block . Where a test block is used, the procedure is generally correct, howwill be necessary to determine the test block terminals for applying the voltagemonitoring relay operation from the scheme drawing.
– MMLB multi-way test plug, for MMLG test block (where fitted).
– Multi-range ammeter.
– Short (8") leads with 4mm plugs at each end: up to 26, ie.13 for each line mneeded.
When the protection scheme incorporates pilot supervision, there will be a MRor MRTP 03 relay provided at the local line end and a MRTP 02 relay at the reline end. When correctly connected and energised from the appropriate ac volthe relay will inject a dc supervision supply across a capacitor in series with thepilots. For 5kV pilots the capacitor is in the MRTP 01 relay, for 15kV pilots aMRTP 03 relay is used with the capacitor housed with the 15kV isolatingtransformer. The commissioning instruction for both types are given below, firsfor the 5kV version.
2.6.1 Monitor the current which should flow in the pilot using a dc milli-ammeter.
2.6.2 Apply the appropriate ac supply for the supervision circuit, and the normal dcsupply.
2.6.3 Note the reading on the dc milli-ammeter. This current should be approximate1.2mA dc and is the current flowing in the pilots.
2.6.4 On the MRTP 01 and MRTP 03 relays there are three red led indicators and aled indicator. The latter is primarily intended as an aid during the setting of theadjustable resistor marked SET (see 2.6.6 to 2.6.8). The top red led is to indicafailure of the ac supervision supply. The middle red led indicator is to indicate pfail open circuit whilst the lower one is to indicate pilot fail short circuit. If any othese indicators are operated, resetting should be attempted by pressing the rebutton.
Assuming that ac and dc supplies are present, the ac supervision supply fail inshould reset when the reset push button is pressed. Failure to reset is almostinvariably due to the absence of correct ac or dc supplies.
2.6.5 The pilot fail indicators may be in the operated or reset state but in both condiset the adjustable resistor as detailed in the following tests.
2.6.6 The adjustable resistor is changed by the use of a small screwdriver through ain the front plate marked SET. There is a worm drive to the resistor so that a lanumber of complete turns (approx. 25) is needed to completely adjust the resisTo facilitate the setting of the pilot supervision there is a test push button whichdepressed reduces the supervision band width inside which the pilots are conshealthy.
2.6.7 If it is considered desirable to monitor the position of the normally open contacthe pilot fail relay, connect a multimeter across terminals 1 & 3 or 2 & 4, which
Page 5
he
wiseehe
atter
uchcks
uld-
e test
es onately
sly andter
or
ly fail
f thes of on
ory ifn
the dcen
is more convenient. The meter must be suitably set either to measure volts if tcircuits are live or to measure ohms if there are no other connections to theterminals.
2.6.8 Adjust as follows:
2.6.8.1 With the screwdriver engaging the worm drive of the SET resistor, turn it clockfor 30 complete turns. The pilot fail open circuit red led indicator should now boperated, the green led lit and the contacts closed. If the green led is out and tcontacts open, check that the dc and ac supplies are present.
2.6.8.2 Turn the screwdriver anti-clockwise until either the green led goes out and thecontacts open and the worm drive has been turned 30 complete turns. In the lcase, where the contacts have not opened, confirm that test 2.6.3 is definitelysatisfactory (a low dc current in the pilots indicates that the pilot resistance is mhigher than the limit of 1000 ohms) also check the dc supply. If both these cheare satisfactory, reference should be made to the fault finding instructions.
2.6.8.3 Reset the pilot fail circuit red led.
2.6.8.4 Depress the test button (which closes the supervision zone) the green led shocome on. With the test button held depressed, slowly turn the screwdriver anticlockwise until the green led extinguishes. Release the test button
2.6.8.5 Depress the test button again, the green led should not illuminate. Release thbutton. The pilot supervision is now correctly set.
2.6.8.6 Replace the relay cover and press the reset button.
2.6.8.7 It is advisable to check that if the pilots are open circuit that the green led cominstantaneously and the pilot fail open circuit indicator operates after approxim10 seconds. After restoring the pilots to normal reset the pilot fail open circuitindicator.
2.6.8.8 Check that if the pilots are short circuit, the green led comes on instantaneouthe pilot fail short circuit indicator operates after approximately 10 seconds. Afrestoring the pilots to normal, reset the pilot fail short circuit indicator.
2.6.8.9 Confirm that removal of ac supply operates the supervision supply fail indicatafter a delay of approximately 10 seconds. Approximately 5 seconds afterrestoration of the ac supply it should be possible to reset the supervision suppindicator.
This completes the tests on the supervision module. Disconnect themilli-ammeter from the pilots and restore pilot connections.
2.6.9 Where external matching/isolating transformers are used, the injection filters(comprising a capacitor, bridge rectifier and resistors) are assembled as part otransformers. The ac output from the MRTP 03 is taken from the rear terminalthe relay into a supervision isolating transformer and then to the injection filterthe isolating transformer. The supervision unit therefore supervises the pilotsbetween the isolating transformers and each line end. It would not be satisfactthere were any further isolating transformers in the pilot circuit since supervisiorelies on the circulation of dc around the complete pilot loop.
The testing procedure is generally similar to that described above except that milli-ammeter will need to be connected directly in series with the pilots, betwethe isolating transformers at each line end.
Page 6
, as
the
can
y
t
ay
Section 3 MAINTENANCE
Periodic maintenance is not necessary. However, periodic inspection and test isrecommended.
Routine testing of the relay can be performed by the secondary injection methoddetailed in the commissioning instructions.
During testing, the led indicators should be checked for operation. Operation of relay contacts should coincide with the respective led indicator illuminating.Check that operation is clean with no tendency to stick. Check also that the flagbe reset using the reset push button mounted in the relay cover.
Removal of the relay from its case.
To remove the relay from its case, loosen the cover nuts and remove the cover.The relay can now be slid out of the case by pulling on the handles.
Miniature printed circuit mounted relay The pcb mounted hinged armature relashould not require any maintenance andunless the unit is not operating correctly ishould be left undisturbed. The operationof the relay may be checked duringroutine injection tests.
Repair and replacements The pcb mounted hinged armature relcannot be repaired. If it is not operatingcorrectly the complete unit must bereplaced. Where possible we recommendthe complete module is returned toAREVA T&D for repair.
terallt
t nouitany
r..
als 13tton, ifL5
Section 4 PROBLEM ANALYSIS
The supervision circuit supplies an ac voltage to the injection filter, which thenrectifies the ac and feeds the resulting dc into the pilot circuit. The injection filcould fail resulting in open circuit pilots, which would also cause the differentirelay to operate incorrectly, otherwise any failure will only cause incorrect fauindication.
It is recommended that printed circuit boards are replaced as a whole and thaattempt should be made to remove and replace components on a printed circboard. This preserves the coating on the printed circuit boards, and prevents damage to the coating due to soldering etc.
For the above reason, the fault finding instructions do not go into detailedinstructions to fault find to component level.
NOTE: The MRTP 01 contains both the supervision circuits and injection filteThey can be tested separately by reference to the appropriate section
4.1 DC circuits
4.1.1 Apply dc voltage as stated below via a dc milli-ammeter meter to case terminand 14 or TP10 and TP9, if any red led is illuminated press the reset push buany led remains illuminated the printed circuit board is faulty. Neither RL4 or R
Page 7
rrent
hould
t,ed
given
il
ult is
should operate for at least 6 seconds from application of the dc supply. The cudrawn from the supply without RL4 or RL5 operated is:
Auxiliary Voltage Current
Rated Applied
30/34V 30V 10mA
48/54V 50V 20mA
110/125V 125V 20mA
Table 4.1
If this current is not obtained, the printed circuit board is faulty.
4.1.2 Leave the dc voltage applied. After 6 to 10 seconds the supply fail relay RL5 soperate, the current will increase to:
Auxiliary Voltage Current
Rated Applied
30/34V 30V 100mA
48/54V 50V 70mA
110/125V 125V 50mA
Table 4.2
If this current is not obtained, or the relay fails to operate check the timer circuiSection 4.1.4. If the relay RL5 operates immediately the dc is applied, the printcircuit board is faulty.
4.1.3 Apply rated ac voltage to case terminals 27 and 28.
Check the supply fail relay resets. The current drawn by the relay should be asin Table 4.1.
Check the supply fail led maybe reset.
After approximately 5 seconds the pilot fail relay should pick up and the pilot faopen circuit led should illuminate. The current taken by the relay should be asindicated in Table 4.2.
Probable areas of a fault are:
4.1.3.1 If the supply fail relay fails to drop off, then T2 or the ac circuit on the printedcircuit board are faulty.
4.1.3.2 If the supply fail relay operates correctly, but the pilot fail relay does not, the fain either the pilot fail relay, T3 or the ac circuit on the printed circuit board.
4.1.3.3 If both relays operate correctly the fault is in either T3 or the ac circuits on theprinted circuit board.
Page 8
easure
.
tely
eer,
.2.1.ircuit
open
g
e of
7 and
4.2 AC circuits
4.2.1 T2
4.2.1.1 Apply rated ac voltage via an ac milli-ammeter to case terminals 27 and 28. Mthe current flowing into the relay.
Rated ac voltage Current
110V 50mA
127V 50mA
220V 50mA
240V 50mA
260V 50mA
Table 4.3
If this value of current is not obtained the fault is in T3 or the measuring circuit.
4.2.1.2 With rated ac applied, measure the voltage on TP2 and TP3, this should beapproximately 58V. If this value is obtained the fault is in the measuring circuit
4.2.1.3 Disconnect the secondary of T2 from the printed circuit board measure thesecondary voltage on the wires from the transformer; this should be approxima58V. If this value is obtained the fault is in the measuring circuits.
4.2.2 T3
4.2.2.1 With rated ac applied, measure the ac voltage on TP3 and TP4, this should bapproximately 30V. If this value is obtained the fault is in T3 or the injection filtif fitted.
4.2.2.4 Disconnect the primary of T3 from the printed circuit board and repeat test 4.2The value measured should still be approximately 30V. If it is not, the printed cboard is faulty.
4.3 Injection filter (MRTP 01 and MRTP 02)
For MRTP 01 relays, if the fault is located in T3 or the injection filter, theconnections between the secondary of T3 and the injection filter rectifier bridgemust be broken, and the tests below performed to prove the injection filter.
4.3.1 Apply 20V at rated frequency to case terminals 19 and 20. Connect a dcmilli-ammeter to case terminals 17 (+ve) and 18. The reading should be 2.3 to2.9mA.
If the current is low the fault is either a short circuit in one of the capacitors, ancircuit in the resistor or the bridge rectifier.
If the current is high the resistor is faulty or has been shorted.
4.3.2 Replace the dc milli-ammeter with a dc voltmeter and repeat 4.3.1. The readinshould be 25-30 volts.
If the voltage is low either the rectifier is faulty, the resistor is open circuit or onthe capacitors is leaking.
4.3.3 Disconnect the ac supply from terminals 19 and 20 and inject 100mA at ratedfrequency into terminals 17 and 18. Measure the ac voltage across terminals 118, this should be between 5 and 8V.
Page 9
If the voltage is less than 5V, then one of the 3 parallel capacitors is leaky.
If the voltage is greater than 8V one of the capacitors is open circuit.
4.3.4 Repeat test 4.3.2 measuring the voltage across the dc terminals of the bridgerectifier; this should be approximately 27V.
If the voltage is less than 27V the bridge rectifier is faulty.
4.3.5 Measure the value of R1, this should be 10k ohms.
y
Section 5 SPARES
When ordering spare parts, the serial number and full model number of the relashould be included with the order.
Repairs
Should the need arise for the equipment to be returned to AREVA T&D Ltd. forrepair, then the form at the back of this manual should be completed and sent withthe equipment together with a copy of any commissioning test results.
n the
Section 6 CALIBRATION AND TEST
It is not necessary to calibrate the relay after replacement of any part other thaprinted circuit board. If the printed board is at fault the complete relay should bereturned toAREVA T&D Ltd.
The relay should be commissioned before being put back into service.
Page 10
____
____
____
V
V
mA
ed)
)
ed)
)
)
_____
_____
Section 7 COMMISSIONING TEST RECORD
MRTP AC PILOT CIRCUIT SUPERVISION RELAY
Site ___________________________ Circuit __________________________
Model no. ______________________ Serial No. _______________________
Rating AC V(n)_________________ V Diagram_________________________
DC V(x)_________________ V
1. Check Supplies – AC V(n) ______________________________________
– DC V(x) ______________________________________
2. Monitor pilot current ______________________________________
3. Set adjustable resistor ______________________________________
4. Monitor pilot fail contacts ______________________________________
5. Check indications ______________________________________
Pilot fail open circuit – instantaneous ________________________________ (green l
– 10s delay ________________________________ (red led
Pilot fail short circuit - instantaneous ________________________________ (green l
– 10s delay ________________________________ (red led
6. Check supervision supply fail ________________________________ (red led
Remarks:
__________________________________ ______________________________
Commissioning Engineer Customer Witness
__________________________________ ______________________________
Date Date
Page 11
Page 12
Not
e 1: (a
)C
T sh
ortin
g lin
ks m
ake
befo
re (b
) & (c
) dis
conn
ect.
(b)
Shor
t ter
min
als
brea
k be
fore
(c).
(c)
Long
term
inal
s.
12
34
56
78
910
1112
1314
1516
1718
1920
2122
2324
2526
2728
Cas
e ea
rth
Mod
ule
term
inal
blo
ckvi
ewed
from
rea
r
C4
C3
C2
C1
19181720
REC
T 1
1 2
R1
For
typi
cal a
pplic
atio
n di
agra
m s
ee F
igur
e 2
Fig
ure
1 A
pplic
atio
n di
agra
m: S
tatic
mod
ular
pilo
t sup
ervi
sion
and
inje
ctio
n fil
ter
Typ
e M
RT
P 0
2. T
rans
lay
‘S’.
Page 13
RL1 2
RL2 2 RL3 2
AC
pow
ersu
pply
DC
pow
ersu
pply
RL7 1 RL8 1 RL6 1
RL4 2 RL5 2
1
V V
27 2820 19 13 14
1 3 5
RL4-
1
2 4 6
RL4-
2
7 9 11
RL5-
1
8 10 12
RL5-
2
Out
put c
onta
cts
chan
ge s
tate
for
pilo
t fai
l.(S
ee N
ote
2)
Out
put c
onta
cts
chan
ge s
tate
for
supp
ly fa
il.(S
ee N
ote
2)RL
1-2
RL2-
2RL
3-2
RL1-
1RL
2-1
RL3-
1
Star
t
+ VE
tC
ase
earth
AC
auxi
liary
supp
ly Vx
MBC
I
Supp
lyfa
il
Pilo
tS/
C
Pilo
tO
/C
Not
e 2:
Con
tact
s ar
e sh
own
for
pilo
ts a
nd a
c su
pply
hea
lthy
or
dc o
ff.
MBC
I
Not
e 1: (a
)C
T sh
ortin
g lin
ks m
ake
befo
re (b
) & (c
) dis
conn
ect.
(b)
Shor
t ter
min
als
brea
k be
fore
(c).
(c)
Long
term
inal
s.
17 18
17 18
12
34
56
78
910
1112
1314
1516
1718
1920
2122
2324
2526
2728
Cas
e ea
rth
Mod
ule
term
inal
blo
ckvi
ewed
from
rea
r
Rese
t
OP
Rese
t
OP
Rese
t
OP
MRT
P 01
L N
1718
1718
19 20
Pilo
ts
Fig
ure
2 A
pplic
atio
n di
agra
m: S
tatic
mod
ular
pilo
t sup
ervi
sion
and
inje
ctio
n fil
ter
Typ
e M
RT
P 0
1. T
rans
lay
‘S’.
Page 14
Pilo
ts
RL1 2
RL2 2 RL3 2
AC
pow
ersu
pply
DC
pow
ersu
pply
RL7 1 RL8 1 RL6 1
RL4 2 RL5 2
1
V V
27 2820 19 13 14
1 3 5
RL4-
1
2 4 6
RL4-
2
7 9 11
RL5-
1
8 10 12
RL5-
2
Out
put c
onta
cts
chan
ge s
tate
for
pilo
t fai
l.(S
ee N
ote
2)
Out
put c
onta
cts
chan
ge s
tate
for
supp
ly fa
il.(S
ee N
ote
2)RL
1-2
RL2-
2RL
3-2
RL1-
1RL
2-1
RL3-
1
Star
t
+ VE
tC
ase
earth
AC
auxi
liary
supp
ly Vx
MBC
I
Pilo
t iso
latio
ntra
nsfo
rmer
Pilo
t iso
latio
ntra
nsfo
rmer
Supe
rvis
ion
isol
atio
ntra
nsfo
rmer
Supp
lyfa
il
Pilo
tS/
C
Pilo
tO
/C
Not
e 2:
Con
tact
s ar
e sh
own
for
pilo
ts a
nd a
c su
pply
hea
lthy
or
dc o
ff.
MBC
I
Not
e 1: (a
)C
T sh
ortin
g lin
ks m
ake
befo
re (b
) & (c
) dis
conn
ect.
(b)
Shor
t ter
min
als
brea
k be
fore
(c).
(c)
Long
term
inal
s.P6 P5 P4 P3 P2 P1
S2 X2 X1 S1
S1S2
P1P2
S1 X1 X2 S2P6P5 P4 P3 P2P1
17 18
17 18
12
34
56
78
910
1112
1314
1516
1718
1920
2122
2324
2526
2728
Cas
e ea
rth
Mod
ule
term
inal
blo
ckvi
ewed
from
rea
r
Rese
t
OP
Rese
t
OP
Rese
t
OP
MRT
P 03
L N
Fig
ure
3 A
pplic
atio
n di
agra
m: S
tatic
mod
ular
pilo
t sup
ervi
sion
5kV
isol
atio
n T
ype
MR
TP
03.
Tra
nsla
y ‘S
’.
_
__
___
___
___
___
___
___
___
___
✁
continued overleaf
REPAIR FORM
Please complete this form and return it to AREVA T&D Ltd with the equipment to berepaired. This form may also be used in the case of application queries.
AREVA T&D LimitedSt. Leonards WorksStaffordST17 4LX,England
For: After Sales Service Department
Customer Ref: __________________ Model No: ________________
AREVA Contract Ref __________________ Serial No: _______________
Date: __________________
1. What parameters were in use at the time the fault occurred?
AC volts _____________ Main VT/Test set
DC volts _____________ Battery/Power supply
AC current _____________ Main CT/Test set
Frequency _____________
2. Which type of test was being used? _____________________________________
3. Were all the external components fitted where required? Yes/No(Delete as appropriate.)
4. List the relay settings being used
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
5. What did you expect to happen?
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
Page 15
____
____
____
____
____
____
____
____
____
____
____
____
____
_____
_____
6. What did happen?
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
7. When did the fault occur?
Instant Yes/No Intermittent Yes/No
Time delayed Yes/No (Delete as appropriate).
By how long? __________
8. What indications if any did the relay show?
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
9. Was there any visual damage?
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
10. Any other remarks which may be useful:
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
___________________________________ _______________________________Signature Title
___________________________________ _______________________________Name (in capitals) Company name
Page 16
✁
AREVA T&D's Automation & Information Systems Business www.areva-td.com T&D Worldwide Contact Centre online 24 hours a day: +44 (0) 1785 25 00 70 http://www.areva-td.com/contactcentre/
Pub
licat
ion:
R80
26F