of 70
8/6/2019 Msc Project Draft Report
1/70
8/6/2019 Msc Project Draft Report
2/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
1
Table of Content
Acknowledgment..........................................................................................................2
1. Introduction..............................................................................................................41.1 Background.............................................................................................. 4
1.2 Aims and Objectives ................................................................................ 41.3 Outline of Study....................................................................................... 5
2. Literature Review ....................................................................................................62.1 Background of Corrosion......................................................................... 6
2.2 The nature of reinforcing steel corrosion in concrete .............................. 7
2.2.1 Loss of Passivity by Carbonation......................................... 8
2.2.2 Loss of Passivity by Chloride .............................................. 9
2.2.3 Influence of cracking on concrete surface ............................ 11
2.3 Mitigation measure for contaminated reinforced concrete structures.... 12
2.3.1 Conventional concrete patch repair...................................... 12
2.3.2 Protective Coating/Barrier on Concrete Surface.................. 14
2.3.3 Electrochemical Treatment Cathodic Protection .............. 15
3. Implementation of Cathodic Protection System .................................................193.1 Design of Cathodic Protection System .................................................. 19
3.1.1 Structural assessment and field tests.................................... 19
3.1.2 Design consideration of cathodic protection system............ 20
3.1.3 Acceptance Criteria for Cathodic Protection System .......... 21
3.2 Technical Difficulties in implementation and operation........................ 21
3.2.1 Hydrogen Embrittlement of Prestressing steel .................... 21
3.2.2 Corrosion Interaction to surrounding structure.................... 23
3.2.3 Other potential side effect of cathodic protection system.... 24
3.2.4 Electrical Continuity of reinforcement ................................ 244. Case study of refurbishment of chloride contaminated Bridge.........................264.1 Background............................................................................................ 26
4.2 Structural Investigation.......................................................................... 26
4.3 Overview of Refurbishment scheme...................................................... 29
4.4 Site Constraints ...................................................................................... 31
4.5 Selection of Repair Methods.................................................................. 32
4.6 Cathodic Protection................................................................................ 34
4.7 Monitoring of CP systems ..................................................................... 35
4.8 Conclusion ............................................................................................. 36
5. Evaluation of Cathodic Protection System Performance...................................37
5.1 Background............................................................................................ 375.2 Investigation Data .................................................................................. 37
5.2.1 Survey Methodology.......................................................... 37
5.2.2 Testing Result .................................................................... 39
5.3 Discussions ............................................................................................ 42
5.4 Conclusion ............................................................................................. 44
6. Conclusion ..............................................................................................................45
7. Reference ................................................................................................................46
Appendix A Plan and Photo Record for Nettlehill Railway Bridge
Appendix B Breakout Window Record and Photo Record for HIT CP Investigation
8/6/2019 Msc Project Draft Report
3/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
2
Acknowledgment
I would like to express my highest gratitude to my supervisor, Dr. X.Y Li. He
provided me continuous encouragement, support and guidance during the process this
dissertation. He is so generous that to offer her time to give me her advice. Without
his advice, encouragement and support, this research would not be able to complete.
It is a difficult but invaluable experience during the process of data finding. I would
also like to thank to my employer company Maunsell Consultant Asia Ltd, in
providing me some useful information of the previous project. Being a member of the
construction industry, I am impressed by power of sharing experience and information
between different professionals within our industry. This experience taught me of how
importance of a teamwork and support from others of construction industry is. After
the dissertation, I think I am more equipped and confident to make further
advancement in my career in the construction industry.
8/6/2019 Msc Project Draft Report
4/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
3
Abstract
Reinforced concrete has become the most common materials for civil or building
construction over the last hundred years; the reason for reinforced concrete being so
popular are due to its mouldability / versatile, cheapness, fire-resistance and usuallydurable and strong, performing well throughout its service life. But sometimes it does
not perform adequately as a result of poor design, poor construction, inadequate
materials selection, or in a severe environment.
Many types of concrete structures are exposed to aggressive environments, especially
those with depassivating agents (e.g. Carbon Dioxide and Chloride), such as car parks,
marine facilities and bridges, it allows the corrosion process to proceed quickly. Most
of the problems with corrosion of steel in concrete are not due to loss of steel but the
growth of oxide. This leads to cracking and spalling of concrete cover. Concrete
damage would usually have to be well advanced before a reinforced concrete structure
is at risk.
In this study, a few commonly used corrosion control methods have been assessed on
its technical competence, financial implication and difficulties of implementation, and
aimed to find out the suitable solution for the chloride contaminated structure and thus
it could maintain / extend the service life of contaminated structures.
A case study on the refurbishment project of bridge structure at Scotland is assessed
base on the technical competence, financial implication and difficulties of
implementation for the cathodic protection system as a solution to corrosion problemin reinforced concrete structure.
In addition, performance evaluation for the existing cathodic protection system
installed at Hong Kong International Terminals berth 4 and 6 is presented, which
included some results and discussion from the investigation tests.
8/6/2019 Msc Project Draft Report
5/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
4
1. Introduction
1.1 Background
Rusting became a fact of life after human being started digging ores out of the ground
and refining them to produce iron or steel that we use so widely in the manufacturing
and construction industries. Nature sets about reversing the process of refining, the
refined iron/steel will react with non-metallic substances to form oxides, sulphates,
sulphides, chlorides, etc.
Reinforced concrete has become the most common materials for civil or building
construction over the last hundred years; the reason for reinforced concrete being so
popular are due to its mouldability / versatile, cheapness, fire-resistance and usually
durable and strong, performing well throughout its service life. But sometimes it does
not perform adequately as a result of poor design, poor construction, inadequate
materials selection, or in a severe environment.
Billions of dollars are spent every year in protecting, repairing and replacing corrosion
damages. Occasionally lives are lost when steel pipes, pressure vessels or structural
elements on bridges fail such as the Interstate 35W Bridge in United State collapsed
August 2007. The economic loss and damage caused by the corrosion of steel makes
it arguably the largest single infrastructure problem facing industrialized countries.
Those infrastructures are ageing, some can be replaced, others would cause great cost
and inconvenience if they were taken out of commission. It becomes crucial that the
existing structures perform to their design lives and limits and are maintained
effectively. The biggest causes of corrosion of steel are deicing salt on highways and
the chloride ingression at splash zone of marine environment.
There are two most commonly used repair strategies conventional patch concrete
repair and electrochemical treatment such as cathodic protection. In choosing the
repair options a number of factors including availability of budget, accessibility,
degree of disruption and loss of facility, anticipated remaining life of structure, future
intended use of structure etc. should be considered. In some cases, if the structure
which reached its design life, has been found in a fair condition on its structural
integrity through a detailed investigation, installation of cathodic protection system
could be a choice to extend its service life such as the South Hook LNG Terminal, the
cathodic protection system has been installed to extend the service life of the old
reinforced concrete jetty built in 1960s, and the jetty has been refurbished to be the
new approach way for LNG terminal. If the electrochemical treatment is furtherproved to be a cost effective option for refurbishment of old existing reinforced
concrete structure, it could significantly reduce the production of construction waste,
which is the most urgent problem faced by the government during the last two
decades, and minimize the impacts to the environments.
1.2 Aims and Objectives
Most of the Marine structures or other structures which are attacked by chloride
induced corrosion, the service life has been significantly shortened or extensive repair
work was required to maintain its structural integrity. These will produce huge amount
of construction wastes and burden the capacity of current landfill. Also due to the
frequency repair works, the service interruption was inevitable; citizen would requirepaying more for these indirect costs.
8/6/2019 Msc Project Draft Report
6/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
5
In this study, a few commonly used corrosion control methods have been assessed on
its technical competence, financial implication and difficulties of implementation, and
aimed to find out the suitable solution for the chloride contaminated structure and thus
it could maintain / extend the service life of contaminated structures.
1.3 Outline of Study
In this report, the literature review of corrosion mechanism and influence factors for
the initiation of corrosion in reinforced concrete and the introduction of most
commonly adopted mitigation methods is mentioned in section 2.
In section 3, the general procedures and consideration of cathodic protection system,
also its difficulties and problem during implementation is discussed.
A case study on the refurbishment project of bridge structure at Scotland is included
in section 4 to have a overview on the cathodic protection system as a solution to
corrosion problem in reinforced concrete structure.
In section 5, performance evaluation for the existing cathodic protection system
installed at Hong Kong International Terminals berth 4 and 6 is presented, which
included some results and discussion from the investigation tests. Finally the overall
conclusion to summarized the whole study is contained in section 6
8/6/2019 Msc Project Draft Report
7/70
8/6/2019 Msc Project Draft Report
8/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
7
O2 + 2H2O + 4e- 4OH
-
Oxygen Water Electrons Hydroxyl ions
2H+
+ 2e- H2
Hydrogen ions Electrons Hydrogen gas
2H2O + 2e-
H2 + 2OH-
The first of these reactions occurs in the presence of dissolved oxygen and
near-neutral conditions. The second is favored by acidity (excess of hydrogen ions)
while the third is dominant at pH values greater than neutral.
In aerated near neutral condition (e.g in tidal zone of marine condition), the iron ions
produced at the anode react with the hydroxyl ions formed at the cathodic sites to
produce ferrous hydroxide:
Fe2+
+ 2OH- Fe(OH)2
The ferrous hydroxide is readily oxidized by dissolved oxygen to form hydrated ferric
oxide Fe2O3 H2O:
4 Fe(OH)2 + O2 H2O + Fe2O3 H2O
Thus the overall reaction which proceeds through a series of intermediate steps may
be written as:
4 Fe + 3O2 + 2 H2O Fe2O3 H2O (Hydrated ferric oxide -- rust)In practice the rate of corrosion is often determined by the rate at which the cathodic
reaction can be sustained. In near neutral anaerobic waterlogged environment sulfate
reducing bacteria may give rise to a further type of cathodic reaction in the corrosion
of iron and steel. These microbes reduce dissolved sulfates to sulfides possibly
through the reaction:
SO42-
+ 8 H+
+ 8 e- S
2-+ 4 H2O
And the corrosion is characterized by the fact that it occurs in the absence of air andsulfides are present in the corrosion products. From the composition of the actual
products formed it is probable that the corrosion mechanism involves cathodic
depolarization which may be represented by the simplified equation:
4 Fe + 4 H2O + SO42 3Fe(OH)2 + FeS + 2OH-
Stimulation of the cathodic reaction depends on the bacteria possessing an enzyme
(hydrogenase) to enable them to oxidize hydrogen found at the cathodic sites. The
sulfide ions produced by the reduction of sulfate can sometimes stimulate the anodic
process of iron dissolution.
2.2 The nature of reinforcing steel corrosion in concrete
Concrete normally provides embedded steel with a high degree of protection against
corrosion. It is because the pore solution in a hydrated Portland cement system
contain high concentrations of soluble calcium, sodium and potassium oxides, these
oxides form hydroxides, which are strong alkaline with a pH normally exceeding 12.
This means that the concrete surrounding the steel provides an alkaline environment
for the steel. This leads to a passive layer forming on the steel surface by stabilizes
the oxide or hydroxide (Assume that Passivation by films of Fe2O3 and Fe3O4) film. A
passive layer is very dense, thin layer of oxide that leads to a very slow rate of
oxidation (corrosion). Besides, surrounding concrete restrict the ingression of outside
elements which are aggressive to the steel. Consequently good quality, well placed
concrete with adequate cover to the steel provides a high degree of protection to thesteel reinforcement. However, the duration of this protection depends on number of
8/6/2019 Msc Project Draft Report
9/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
8
factors including the retention of high pH and physical integrity of the cover concrete,
and the efficiency of concrete acts as a barrier to aggressive species, the passivating
environment is not always maintained. Two processes can deteriorate the passivity of
steel in concrete. One is carbonation of concrete and other is chloride attack.
2.2.1 Loss of Passivity by
Carbonation
According to the pourbaix diagram for
iron, the metal is passive when pH is
above 9.5. Carbon dioxide, however,
will diffuse into the concrete and, in
the presence of moisture, react with the
hydrated cement to form calcium
carbonate. This will remove hydroxyl
ions from the pore solution and reduce
the pH of the concrete.
CO2 + H2O H2CO3
Gas Water Carbonic acid
H2CO3 + Ca(OH) 2 CaCO3 + 2H2O
Carbonic acid Pore solution Calcium carbonate
This carbonation process will
start at the surface, and then
slowly move deeper and
deeper into the concrete. It is
not detrimental to the integrity
of a concrete component until
it penetrates to the embedded
steel. If the object is cracked,
the carbon dioxide of the air
will be better able to penetrate
into the concrete. The
alkalinity of the concrete
surrounding the embedded steel is reduced over sufficient time to point below pH 9.5where passivation is lost and the steel will be vulnerable to corrosion if other
necessary components, water and oxygen, are present. Carbonation is common in old
structures, badly built structures with low cement content and very porous.
The rate of carbonation depends on the permeability of the concrete to ingress of
carbon dioxide, which is strongly influenced by the water/cement ratio, the moisture
level of the concrete and the total alkali content of the hydration products. A
carbonation front proceeds into the concrete roughly following the laws of diffusion.
These are most easily defined by the statement that the rate is inversely proportional
to the thickness: xD
dt
dx/=
Where x is distance, t is time and D is diffusion constant. The diffusion constant D is
8/6/2019 Msc Project Draft Report
10/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
9
determined by the concrete quality. The resistance of carbonation of reinforced
concrete is influenced by many factors. The carbonation rate / the time to carbonation
induced corrosion, is a function of cover thickness, so good cover is essential to resist
carbonation. As the process is one of neutralizing the alkalinity of concrete, high
cement content is needed. The diffusion process is made easier at concrete with open
pore structure, both good compaction and well curing concrete with small pores andlower connectivity of pores could provide good resistance to carbonation. In addition,
the wet/dry cycling on the concrete surface will accelerate carbonation by allowing
carbon dioxide gas in during the dry cycle and then supplying the water to dissolve it
in the wet cycle that is what occurring everyday at marine concrete structures.
It is generally accepted that Ficks first law of diffusion describes the depth of
carbonation front as a function of time. This states that the rate of movement is
inversely proportional to the distance from the surface, the result as shown in
equation:
dtx
C
ADdQcb
cb
=
Where Q is amount of diffusing carbon dioxide, A is penetrated area, Ccb isdifference between carbon dioxide concentration in the atmosphere and at the
carbonation front, x is distance between carbonation front and concrete surface, t is
time, Dcb is carbon dioxide diffusion coefficient.
The diffusing carbon dioxide reacts with calcium, potassium and sodium hydroxides
at the carbonation front. And the process is modeled by this equation: dxAadQ = ,
where a is carbon dioxide binding capacity for concrete. Then after the integration of
the combination of above two equation, the following equation is obtained :
ta
CDx cbcbcb
=
2
The binding capacity of carbon dioxide of concrete, which is determined by
following:
CaO
CO
hcCaOm
mCCa 275.0 =
Where CCaO is content of calcium oxide in cement, Cc is cement content in concrete,
h is degree of hydration, mco2 is molar mass of carbon dioxide, mCaO is molar mass of
calcium oxide. The typical value for the rate of movement of carbonation front isaround 1mm per year for poor concrete and 0.2mm per year for good quality concrete.
Once the carbonation front has penetrated to the steel, and moisture present, there is
risk of corrosion. The corrosion products formed in these circumstances will have a
volume several times greater than the volume of steel from which they derived. The
built up of corrosion product on the surface of the steel creates tensile forces in the
concrete, as the result, cracks were built up on the concrete surface and these would
further increase the carbonation rate and accelerate the deterioration of structures.
2.2.2 Loss of Passivity by Chloride
Chlorides in concrete can come from several sources. They can be either cast into the
concrete (fixed chloride or free chloride) or diffuse in from the outside (mainly freechloride). The sources of chloride in fresh concrete include some admixtures, some
8/6/2019 Msc Project Draft Report
11/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
10
sources of aggregates (both inland and marine), and the cement. It is essential to
identify the source for introduction of chlorides during construction, such as the use of
calcium chloride as an admixture for reinforced concrete. With the current restriction
on chloride contaminants constituents in concrete mix, the risk of corrosion from
chlorides cast into current concrete construction is very low. However, chlorides from
the environment (e.g. sea water spray or direct wetting at marine environment anddeicing salts for highway) can also penetrate hardened concrete. A large portion of
these will stay as free chlorides in the pore water and are particularly aggressive to
embedded steel. Concrete exposed to such sources of chloride may need to be
especially designed and possibly given additional protection.
The depassivation mechanism for chloride attack is different from carbonation. The
chloride ions attack the passive layer by acting as the catalysts to corrosion. It is
generally accepted that passivity is maintained by dynamic balance between
breakdown by chloride ion and repair by hydroxyl ion of the film. Passive oxide layer
would be broken down when sufficient concentration of chloride reach the surface of
reinforcing steel and the broken down process is dominant. During the process,chloride is not consumed. The chloride threshold for corrosion given in terms of
chloride(Cl-) /hydroxyl(OH
-) concentration is 0.6. This ratio is approximately
equivalent to 0.4% of chloride by weight of cement content in concrete. If the ratio
exceeds the threshold level, corrosion would be observed. The localized deterioration
of passive layer would lead to the pitting corrosion. The pitting of steel was often
observed for those damaged reinforcing steel of marine concrete structure. At some
suitable site on the steel surface such as the location of insufficient cement paste, the
chloride ions was attached by electrochemical potential difference, and corrosion is
initiated and acids are formed (Hydrogen sulphide from the sulphide inclusion in steel
and HCl from the chloride ions). The Iron dissolves and reacts with water. The
process of chloride induced corrosion is illustrated in the following diagram.
As stated in previous, corrosion is proceeded by the formation of anodes and cathodes.
In the case of chloride attack, anodes and cathodes are always well separated, this is
known as marco-cell formation. Since the chloride attack is always accompanied with
high level of water in pores which facilitate the movement of free chloride and other
ions hence increased the conductivity of concrete. This high conductivity allows the
separation of anodic and cathodic reactions with large cathodic areas supporting small
concentrated anodic areas, thus a pit forms, rust may form over the pit, concentrating
8/6/2019 Msc Project Draft Report
12/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
11
the acid and excluding oxygen so that the iron stay in solution preventing the
formation of a protective oxide layer and accelerating corrosion. As a result, the
structural integrity of concrete structure would be significantly reduced without any
apparent sign of damage in such case.
Similar to carbonation, the chloride ingress rate into concrete is often approximated as
a diffusion process. However, the initial mechanism appears to be capillary flow/force,
the partially saturated surface zone is prone to accelerated chloride ingress due to
capillary forces. Besides, cracks and heterogeneity of concrete and the condition of
exposure would also affect the chloride ingress at surface zone, but it is generally
accepted that diffusion is the leading transport mechanism in concrete once the
chloride has passed the surface zone.
Chloride ingress is more complicated as it is dealing with structures exposed to
variable chloride concentrations. Also the chloride diffusion produces a concentration
gradient instead of a front for carbonation case. The usual form of the diffusion
equation used is Ficks second law:
2
2 ),(),(
x
txCD
t
txC
=
Where C(x,t) is the chloride concentration at depth x, at time t and D is the diffusion
coefficient, in atmospherically exposed concrete, it is difficult to obtain the surface
concentration as the chloride at the surface can vary greatly by wetting, drying,
evaporation and wash off etc. it is common to discard the first 5 mm. and in diffusion
calculations must use the depth from sampling depth, not the surface.
In some research, it pointed out that within defined mathematical limits the error
function expression for the diffusion coefficient can be approximated to the simple
parabolic function, and the solution of above equation becomes:
)4
()(),(Dt
xerfcCCCC isitx +=
Where Ci is the initial chloride concentration, Cs is the surface chloride concentration,
erfc() is the error function complement. By using approximation erf(z)=(1 - Z/3)2 ,the solution would become:
2
),( ]12
1)[(Dt
xCCCC
isitx +=
2.2.3 Influence of cracking on concrete surfaceReinforced concrete is
designed to allow several
degree of cracking on surface,
depending on the structure and
the exposure class, the design
limits the width of cracks,
under normal situation, up to
0.3mm. But crack width seems
to be less important to
corrosion risk than crack
frequency, cover depth and
8/6/2019 Msc Project Draft Report
13/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
12
concrete quality. Cracking will often initiate localized early corrosion under the effect
of carbonation, but the corrosion is unlikely to progress significantly. Cracks
coincident with a reinforcing bar will tend to expose a greater portion of reinforcing
bar to moisture and oxygen; the anodic and cathodic site areas are generally equal in
size, thus typical general corrosion occurs. In the case of cracks intersecting
reinforcing bars, the anodic areas are likely to be considerably small, thus this leads tolocalized corrosion.
When chloride penetrate the concrete through this crack from external source,
corrosion can be very significant because of the relatively small size of the anodic
zone. In this case, intensive localized corrosion of affected reinforcing bars can cause
very large losses of cross-sectional area. Clearly, the loss of a large proportion of the
cross-section area of adjacent reinforcing bars could seriously reduce the load
carrying capacity of a structure.
Many types of concrete structures are exposed to aggressive environments, especially
those with depassivating agents, such as car parks, marine facilities and bridges. Most
of the problems with corrosion of steel in concrete are not due to loss of steel but thegrowth of oxide. This leads to cracking and spalling of concrete cover. Concrete
damage would usually have to be well advanced before a reinforced concrete structure
is at risk.
2.3 Mitigation measure for contaminated reinforced concrete structures
The detailed knowledge of the condition of structural elements and a clear
understanding of the likely effectiveness of the rehabilitation options are essential for
any maintenance or rehabilitation projects. A repair strategy should be developed to
enable cost-effective repairs and maintenance.
2.3.1 Conventional concrete patch repairDetailed Procedures of Convention Patch Repair
Conventional concrete patch repair was the most common mitigation method for the
existing old structures in the past, but it was considered as a short term rehabilitation
method especially for those marine or chloride contaminated structures, as repeat
defects are likely to occur within a 3-4 year period. The conventional concrete patch
repair includes three main processes concrete removal, steel and substrate
preparation and concrete reinstatement. The common practice of concrete repair is
shown as follows
a) Pre-repair survey by visual inspection, delamination hammer taping; and mark outareas identified as defective;
b) Break out defective concrete to expose the reinforcing steel and a sound concretesubstrate and extending at least 25mm behind the exposed reinforcement;
c) Augment deteriorated steel if section loss of steel more than 10%d) Prepare all concrete surfaces that are to receive concrete repairs by cleaning to
remove loose or weak concrete, surface laitance and other contaminants;
e) Prepare all exposed reinforcement to remove rust productf) Apply primer to the cleaned reinforcementg) Apply bond coat to the substrate before reinstatement;h) Apply the repair mortar to reinstate concrete when the bond was still tacky;
i) Cure the repair mortar immediately following placement and surface finishing ofrepair
8/6/2019 Msc Project Draft Report
14/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
13
There are a number of methods for removing concrete; the most common techniques
are by hand held pneumatic hammers, hydro-jetting and milling machines. Depending
on the specification, budget and site constraints, suitable technique would be used for
repairing works.
Where spalling as a result of corrosion damage has occurred, preparation of the steel
will be required to remove corrosion products and remaining chlorides before making
good. Following surface preparation a primer or coating is applied to the bar, usually a
cement:polymer slurry, zinc rich epoxy or epoxy barrier coating. In addition,
supplementary steel may need to be added where there has been significant loss of
section in the damaged bar. In general terms the following application guide applies:
a) Corrosion arising from carbonation: this is more general over the surface of thebar and the worst of the corrosion products may be removed by mechanical means
to Swedish Standard ST3. Any remaining corrosion will be re-passivated by the
application of a sound, good quality, cementitious repair material.
b) Corrosion damage arising from chloride contamination leads to pitting type
corrosion. Chlorides can remain trapped in the pits and are difficult to remove bymechanical means as the brush or grinder cleans the surface of the steel only.
Abrasive techniques using particles fired at the steel surface are more appropriate
to give a finish consistent with Swedish Standard SA 2.5. These are generally
limited to grit blasting or high pressure water jetting with an abrasive material
(typically silica sand) drawn into the water jet. If grit blasting is used it is
preferable to water wash the steel and blow dry before coating to remove any
chloride salts that may be remaining. The most appropriate technique will depend
on the coating to be applied.
c) The use of epoxies, whether zinc rich or barrier type, requires a high standard ofsurface preparation. As mentioned at (b) above this is not always practical in
repairs to marine structures. The preferred primer is therefore a cement:polymerslurry which re-passivates and allows residual chlorides to diffuse into the general
repair material thus reducing concentrations to a level which does not lead to
corrosion.
Reinstatement of Breakout damaged areas may be achieved using various methods
depending on the extent, orientation and geometry of the areas to be replaced. These
include:
Hand application of polymer modified mortars applicable to small, shallow(preferably < 50mm, maximum 75mm) repairs.
Recasting using proprietary polymer modified micro-concretes applicable tolarger, deep (> 50mm) repairs.
Grouting using pre-packed aggregates and proprietary non-shrink grout applicable to larger, deep (> 50mm) repairs, but geometry likely to restrict the
flow.
Recasting using appropriate concrete applicable to complete or partialreplacement of whole elements.
Limitations of Convention Patch Repair
The key limitations to conventional patch repair methods are as follows:
a) Surface preparation is limited the space available behind the bar. Breakout has tobe limited to minimise disruption to the structure so the most that can be expected
is 20-25mm. This restricts the standards that can be achieved and it is likely that
8/6/2019 Msc Project Draft Report
15/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
14
the back of the bar will not, in some areas at least, meet the specified
requirements.
b) It is likely that areas adjacentto existing corrosion and
spalling have the potential for
corrosion (e.g. high chlorideconcentrations) but are being
protected by the corrosion
activity at the spall site. By
patching the spall, the steel at
that point is re-passivated and
made cathodic, thus leading
to corrosion commencing at
an adjacent area. This is
known as the incipient
anode effect. Coating the
whole structure to excludeoxygen and moisture will
retard this process but some
corrosion activity is likely to continue.
c) In order to remove corrosion products from behind the bar, breakout around itscircumference is required. For large areas of repair, propping or sequencing of the
breakout, perhaps combined with closure of the structure, will be required.
Depending on assessment of individual structures it may be necessary to unload
the element by jacking etc. before breakout commences. Any significant concrete
removal or corrosion damage must be assessed by structural engineer, since the
removal of concrete cover or concrete surrounding the steel redistributes the load
within the structure.
d) Chlorides can enter the patch area over time, both from sea water and backmigration that is diffusion of chlorides from the contaminated parent concrete into
the repair material and cause the recurrence of spalling.
2.3.2 Protective Coating/Barrier on Concrete Surface
Protective coating is not usually required for reinforced concrete structures, however
it can be beneficial in excluding undesirable species such as chlorides and carbon
dioxide. There is a huge range of coatings and sealers can be applied to concrete such
as anti-carbonation coating which should be applied after carbonation repairs to stop
further carbon dioxide ingress. But it is very unlikely that the chloride induced
corrosion could be stopped by coating. Protective coatings are applicable in a number
of circumstances to reinforced concrete in a marine environment:
a) The prevention or restriction of additional chlorides entering the concrete wouldbe the principal use of protective coatings. Chloride resistant coatings may be
applied to halt or retard the progress of the chloride ingress provided chloride
concentrations have not already reached critical levels (the corrosion threshold)
and/or the reservoir of chloride existing in the concrete is not predicted to cause
critical concentrations at reinforcement depth during the required life of the
structure (by diffusion) and any expected damage is not tolerable. These are
generally film forming barrier coatings or hydrophobic impregnation materials.
b) Anti-carbonation: where carbonation has not reached the majority of reinforcingsteel in a structure but is predicted to do so within the required life and the
8/6/2019 Msc Project Draft Report
16/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
15
expected damage is not tolerable, anti-carbonation coatings may be applied to halt
or retard the progress of the carbonation front. Clearly the application of such
coatings would probably be confined to drier areas of a pier where moisture
blockage of pores has not prevented penetration of the carbonation front.
c) Exclusion of oxygen and moisture: Where carbonation and/or chlorides have
reached the reinforcing steel and areas of the structure have yet to show visiblesigns of distress it may be appropriate to apply a coating which excludes oxygen
and moisture as a means of stifling the corrosion process as part of a medium term
patch, recast or sprayed concrete repair system.
Limitations of various types of coating
Generally coatings have a life less than that of the structure (typically 5-10 years) and
are likely to require overcoating at some stage as an ongoing maintenance
commitment. In relation to marine structures this is usually inconvenient and
expensive because of the need for special access. Specifically related to the types of
coating mentioned above, limitations include:
a) Film forming chloride barriers can trap moisture in the concrete and thereforerequire high bond strength to the concrete in order to resist the consequent build
up of vapour pressure during the temperature changes. This tends to limit the
generic type of coating to epoxies which are expensive, not environmentally
friendly and frequently have a limited colour range. These materials also require a
high standard of surface preparation to achieve the necessary bond strengths.
Hydrophobic impregnation materials require the substrate to be relatively dry in
order that they may penetrate the concrete to a depth sufficient to achieve the
desired function of excluding chlorides. This may be difficult to achieve in
practice on a marine structure.
b) Anti-carbonation coatings are formulated to exclude carbon dioxide but still allowwater vapour to escape from the concrete, they will not usually act as a barrier tochloride ingress.
c) Coatings to exclude oxygen and moisture are similar to the film forming chloridebarriers and the same comments apply. In addition they are unlikely to exclude all
oxygen and moisture and some corrosion may continue.
2.3.3 Electrochemical Treatment Cathodic Protection
For the reinforced concrete structure is planned to proceed with electrochemical
treatment, existing spalls and loose material have to be removed, reinforcement is
cleaned and damaged areas made good to original profile. There is no need to break
out behind the bar. In addition to concrete repair, electrical connections are made tothe reinforcement, following electrical continuity checks, and to an external anode
(inert metal mesh and cementitious overlay, conductive coating or flame spray metal)
applied to the concrete surface. A DC current is passed between the bar and the anode
protecting the bar from further corrosion. The details of principle and limitation would
be discussed in following section.
Principles of Impressed Current Cathodic Protection
The electrochemical treatment works by applying external anode and passing current
from it to the steel so that all of the steel is made into a cathode. The cathodic
protection could further divide into impressed current type and sacrificial type
8/6/2019 Msc Project Draft Report
17/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
16
Impressed current Cathodic
protection (ICCP) is the system
commonly used for
atmospherically exposed
reinforced concrete structures.
ICCP depends on the passage ofcurrent from an anode, through
an electrolyte onto the surface of
the metal to be protected. If the
magnitude of the current is
sufficient such that there is a net
current flow to all areas of the
metal surface, corrosion will not
occur. The passage of current onto the metal surface causes a change in the
electrochemical potential of the metal. A CP system is designed to convert the whole
of the reinforcing steel surface into a cathodic area, hence the name. The anodic
reaction is moved to a more durable material i.e. a specially manufactured anode. TheCP system limits further corrosion of the steel by the following actions:
a) A net positive ionic current flows through the concrete towards the steel
suppressing the flow of positive iron ions away from the surface.
b) Hydroxyl ions, which are formed at the steel surface, stimulate the formation of
a passive film that protects the steel by acting as a barrier to corrosion.
H2O + 1/2O2 + 2e- 2OH
-
c) Aggressive negative ions such as chlorides are transported away from the steel
surface as the result of the flow of ionic current in the concrete.
d) The potential of the steel is polarised towards more negative values which
inhibits the dissolution of positive iron ions.
e) To support the reactions occurring at the CP anode, oxygen is consumed at the
steel surface and is therefore not available to support anodic reactions occurring
on the steel.
The existence of effective cathodic protection can be validated by measuring the
change in electrochemical potential of the metal being protected and recording the
magnitude of the current required to effect this change.
Cathodic protection will halt or reduce corrosion on a metal surface by restore the
alkalinity and enhancing the passivity of the steel, but it cannot rehabilitate the steel or
return it to its original condition.
Typical components for ICCP systemAnodes
Anode is a critical part of the ICCP. It is usually the most expensive item. Available
Anodes systems used for reinforced concrete are as follows:
1 coating applied to the concrete surface;2 mixed metal-oxide coated titanium mesh anode embedded in a render overlayer
applied to the concrete surface;
3 mixed metal-oxide coated titanium ribbon anode placed in slots cut into theconcrete surface and filled with a cementitious filler;
4 zinc plates bonded to the concrete surface;5 Nickelized carbon cementitious anode overlay on the concrete;6 Flame sprayed anode systems; and7 Thin, conductive, sprayed coating with primary anodes.
8/6/2019 Msc Project Draft Report
18/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
17
8 Discrete anode with cementitious or graphite backfill.
Reinforcement continuity & bonding
A basic requirement of any system passing electrical current is that the conductor, in
this case the steel reinforcement, is electrically continuous. It has been found by
experience that only physical contact of reinforcement may produce a high resistanceor discontinuous joints. Reinforcement continuity shall be achieved by welding an
additional rebar to each reinforcement in the continuity breakout chases around the
structure.
Permanent reference electrodes
To determine the performance of the CP system, the potential of the reinforcing steel
should be measured relative to a reference electrode. For ease of testing and for
reproducibility of test data the potentials should be measured relative to permanent
reference electrodes embedded in the beams as close as possible to the reinforcing
steel. The reference electrode cables will be terminated inside a water-resistant
junction box. The associated cables would then run from these boxes to themonitoring facilities in Transformer Rectifier units.
Transformer Rectifier
It is the DC power supply that transforms mains AC to a lower voltage and rectifies it
to DC. The positive terminal is connected to anode and the negative to the cathode.
Negative return connections
To enable the current to return to the transformer rectifier and thus complete the
electrical circuit, a number of connections in the form of reinforcement connectors
will be connected to the electrically continuous reinforcement. Negative return cables
would connect these connectors to the negative point of the transformer rectifier.
Anode feed and negative return cables
Anode feed cables from the transformer rectifier to an anode, and negative return
cables will be installed.
Impressed current Cathodic protection is particularly applicable to where chloride
contamination is widespread on the structure or chlorides have penetrated well beyond
the cover to the reinforcing bar. Besides, at the situation that it is difficult or expensive
to erect access to the structure for repeat repair operations or it is not possible for
structural and/or operational reasons to have significant break out of concrete behind
the bar. Also cathodic protection system is usually applied to the existing structurewith remaining life greater than 10 years:
Limitation of Impressed Current Cathodic protection
Cathodic protection has the following limitations:
a) Cost restricts its use to applications requiring a remaining life greater than 10years.
b) It requires regular monitoring and adjustment to ensure optimum application ofcurrent (too high a current density can lead to problems, just as much as too low
allowing corrosion).
c) Permanent Power supply is required
8/6/2019 Msc Project Draft Report
19/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
18
d) It can not be used on structures with epoxy coating, injection or with poorelectrical continuity.
Sacrificial Cathodic
Protection is to directly
connect the steel to asacrificial or galvanic
anode such as zinc without
using any power supply.
This anode corrodes
preferentially, liberating
electrons with the same
effect as the impressed
current system.
For example: Zn Zn2+
+
2e-
The system is illustrated schematically in above figure. There are a number of
elements and their alloys which are more active than steel in the electrochemical
series. The main practical metals are zinc, aluminum and magnesium. All of these
metals are used, in alloy form, as sacrificial anodes for submerged steel structures. As
the power supply is not required, and this makes the system much cheaper and easier
in both implementation and operation. However the main restriction on this system is
that the zinc has only a small driving voltage when coupled to steel, therefore, the
resistance of the electrolyte is crucial to the performance of the system. The principal
advantage is the lack of power supply and this makes both implementation and
maintenance cost cheaper.
8/6/2019 Msc Project Draft Report
20/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
19
3. Implementation of Cathodic Protection System
3.1 Design of Cathodic Protection System
3.1.1 Structural assessment and field tests
Apart from the general structural assessment such as its material condition, itsstructural integrity, some additional investigation shall be undertaken in order to
confirm the suitability of cathodic protection and provide system design parameters.
The investigation shall generally include are shown in the following:
a) Records: All the available records during the construction and alternation shallbe retrieved and reviewed to assess the location, quantity, nature and continuity
of the reinforcement, and the constituents and quality of the concrete. These
information shall be further confirmed and supplemented by the site survey and
laboratory tests.
b) Visual inspection: Visual survey data shall be collected to ensure the type and
causes of defect. Besides, the features of the structure or its surroundingenvironment, which could influence the application and effectiveness of the
cathodic protection. Also all area of the structure which require to be protected
shall be examined especially those area have been previously repaired and the
repair methods and materials shall be identified.
c) Chloride content analysis: Dust/Core samples shall be removed from theconcrete elements at incremental levels and the chloride content can be
determined by acid extraction of powdered concrete, followed by a chemical
determination. The chloride concentration presents in concrete is particularly
important with respect to reinforcement corrosion. The presence of chloride
ions can depassivate steel reinforcement in concrete and promote corrosion.
d) Carbonation Depth: The depth and extend of carbonation should be assessedeither on site or in the laboratory. Phenolphthalein is used as an indicator to
determine the depth of carbonation on freshly fractured or drilled concrete
surface. Similar to the chloride content, it is used to determine the present
situation of concrete.
e) Concrete cover and rebar location: Concrete cover and reinforcement size andposition measurements shall be carried out to verify the information from the
construction records, or if the record was missed, to assess the anode/cathode
spacing will be adequate for the particular anode system and to identify dense
regions of reinforcement which may require high current density. Besides, it is
used to identify any shielding to the reinforcement to be protected, such as
embedded metal meshes, metal fibers or plastic sheets, also any possible shortcircuits site with extremely low concrete cover, which could impair the
efficiency of cathodic protection.
f) Reinforcement electrical continuity: the construction drawing s of reinforcementand other attached steel elements shall be checked for continuity. During site
investigation the continuity shall then be verified on site by measuring the
electrical resistance or potential difference between bars in locations across the
structure. The purpose of this test is to confirm the feasibility and provide design
information for cathodic protection system. The assessment shall include the
electrical continuity between elements of structure, reinforcement within element
and other ancillary steel items fixed on the structure. At the subsequent repair
stage, reinforcement electrical continuity shall be further checked at all exposed
reinforcement of concrete repair breakout.
8/6/2019 Msc Project Draft Report
21/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
20
g) Half-cell potential survey: electro-potential measurement is used to indicate theprobability of corrosion being active in reinforcement embedded in concrete. it is
found that there was 95% probability of corrosion in regions where the potential
was more negative than -350mV with respect to copper/copper sulphate half-cell
while only 5%where potential was less negative than -200mV. It is not necessary
to carry out the potential survey on entire structure, only representative areas ofboth damaged and apparently undamaged shall be surveyed for corrosion
activity.
h) Concrete electrical resistivity: since the corrosion is an electrochemical process,the electrical resistivity of the concrete will have a bearing on the corrosion rate
of the concrete as an ionic current must pass from the anodes to the cathodes.
The four probe resistivity meter was generally be used to determine the
resistivity of concrete. The measurement can be used to indicate the possible
corrosion activity if steel is depassivated. In general when the measured
resistivity above 20 K-ohm, it is considered with low corrosion risk, whiles the
measured value below 5 K-ohm, it is considered with very high corrosion risk.
The impact of variation in concrete resistivity shall be considered during thecathodic protection system design.
3.1.2 Design consideration of cathodic protection system
In the design of a cathodic protection system, the most import factors for the designer
is to consider the level of electrical current density on the steel and the current
distribution path. Beyond these requirements, there are several secondary concerns
such as cost, durability of system, life expectancy and the maintainability. Before the
design of cathodic protection system, the present situation of the structure and some
design parameters have to be obtained by some structural assessment and field tests.
Current Density requirementThe selection of a suitable current density output is critical for the cathodic protection
system design. The current density requirement is depending on the steel corrosion
state before cathodic protection is applied. According to the guidelines from British
standard, a typical current density of 2 20 mA/m2
for steel reinforcement is
sufficient for general aggressive environment such as the exposure to marine. For
some extreme cases, such as the industrial effluent, some trial shall be performed to
determine the current density requirement. In addition, for the case of cathodic
prevention that is the system installed in new structure, the typical value of current
density could be down to 0.2 2 mA/m2, it is because the electrochemical potential
for steel is less negative, also the passive steel is more easy to be polarized.
Choosing of suitable anode system
After determined the protective current density, then the current requirement for unit
area of element could be worked out. Based on the required output and on site
situation of the structure, the suitable anode system could be figure out. In the marine
exposure, the commonly used systems are titanium anode in overlay and titanium
ribbons in slots. The slot system is used on decks or beams where increase in load is
not acceptable or the required current density is too high for overlay system but
provided that the concrete cover is sufficient. The slot system will only be used for
site with these constraints, as it is an expensive and high difficulty option.
The main restrictions on the overlay type systems are caused by the cementitiousoverlay. The drawbacks are the increasing of dead load on the structure, the difficulty
8/6/2019 Msc Project Draft Report
22/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
21
for applying in complicated geometries and the limitation on the output current of
anode mesh on the concrete surface. It is essential that good quality control is
maintained to get a good quality, adherent overlay. For the structure would not be
exposed to wearing, conductive coating on concrete surface would be a good choice,
the advantages of this system are its negligible increase in dead load, it can be applied
too any geometry and it is cheap and simple to repair or replace.
Zone design of Cathodic protection system
In order to provide a efficiency cathodic protection system, individual areas where
there is a significant change in the environment of the steel reinforcement should be
protected by separate control circuits, that is so called zoning of cathodic protection
system. These changes are normally identified during the investigation survey by
large variation in the resistance of concrete and potential of steel. These can be
changes in moisture content, chloride content, concrete cover or geometry of the
component in a structure. Typically, zones of the order of 50-100m2
are recommended
to avoid excessive power loss in the cabling. For example in the marine structure, it is
common to split the structure into separate zones relative to the water level, such assplash zone, semi-submerged zone and submerged zone.
3.1.3 Acceptance Criteria for Cathodic Protection System
According to the British Standard, for any atmospherically exposed structure, any
representative point shall meet any one of the following criteria
a) An instant off potential (measured between 0.1s and 1s after switching the powersupply off) more negative than -720 mV with respect to Silver/Silver
Chloride/0.5M KCl reference electrode.
b) A potential decay over a maximum of 24 hours of at least 100mV from instant off.c) A potential decay over an extended period (typically 24 hour or longer) of at least
150 mV from the instant off subject to a continuing decay and the use of referenceelectrodes for the measurement extended beyond 24 hours.
The instant off potential are generally be used for assessment of cathodic protection,
as after switching off for instantaneous off (IR free) potential measurements,
sufficient time shall be allowed before measurement to avoid any transient voltage
arising from switching surges, capacitance or resistance effects that would affect the
measured values but this waiting period shall be sufficiently short to avoid significant
depolarization.
In practice, the best control criterion is based on a potential shift, which of 100 to 150
mV will reduce the corrosion rate by at least ten times. Field evaluation also had
shown that there is no further signs of corrosion damage in cathodically protected
structure achieved this criterion.
Besides, no instant off steel/concrete potential more negative than -1100 mV with
respect to Silver/Silver Chloride/0.5M KCl reference electrode shall be permitted for
plain reinforcing steel or -900 mV for prestressing steel to avoid hydrogen
embrittlement.
3.2 Technical Difficulties in implementation and operation
3.2.1 Hydrogen Embrittlement of Prestressing steel
The improper operation of cathodic protection to the steel in concrete may cause
hydrogen generation on the steel surface resulting in hydrogen charging of the steel if
the potential achieved is sufficiently negative. It is well known that hydrogen chargingcan cause embrittlement of high-strength steels.
8/6/2019 Msc Project Draft Report
23/70
8/6/2019 Msc Project Draft Report
24/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
23
(b) If corrosion related cracking and spalling is evident then the tendon should beexposed and inspected for uniform and localized corrosion. The structure is
qualified for cathodic protection if:
- the remaining cross-section is at least 85% in an area of uniform corrosion;- the remaining cross-section is at least 90% in areas of localized attack
(c) Measures to encourage uniform current distribution such as zoning of the anodesystem so that the IR drop within the anode system is less than 100mV and
matching the anode system layout to the density of the steel surface area in the
concrete.
(d) Installing reliable and stable reference electrodes near prestressed steel cables.(e) Installing a remote control and continuous monitoring system capable of adjusting
the system output and storing operating data. The system should be fitted with
failsafe current limiting devices.
3.2.2 Corrosion Interaction to surrounding structure
Cathodic protection of a structure may cause accelerated corrosion of neighboring
structures if that structure is in the same electrolyte. This is particularly observed forburied or immersed steel structures where the flow of cathodic protection current from
the anode to the structure through the earth or water can traverse other structures in
the vicinity. The corrosion rate on these neighboring structures increases where the
current leaves the structure to return to the cathodically protected structure.
The amount of damage likely to occur from stray current corrosion of a steel structure
can be calculated using Faradays law, and for 1 A passing for one year some 9kg of
steel will be corroded. In practice it is not possible to measure the amount of current
being discharged from a structure and so when testing for interaction a potential shift
criterion is adopted.
This is done by measuring the change of potential of the unprotected structure as the
cathodic protection system is energized. A change in the positive direction indicatescurrent leaving the structure at that point gives a maximum value of +20mV for all
structures apart from steel in concrete, before mitigation measures are required.
The position is more complex if the secondary structure is steel in concrete because
steel when immersed in a sufficiently caustic solution (around pH 11 and higher) can
be made to discharge current without any apparent metal loss. This is because the
current discharge leads to a loss of alkalinity in preference to the oxidation of steel
and the alkalinity from the bulk of the electrolyte. In practical terms however it is
often better to adopt a cautious approach and utilize the 20 mV criterion. This is
because the behaviour of steel may be affected by the presence of chlorides in the
concrete.
In general conditions, it is unlikely that above ground cathodically protected concrete
will create interaction problems with secondary structures. This is because of the dose
proximity of anode and cathode and the relatively high resistivity of the concrete. The
cathodic protection current will tend to flow between anode and cathode, i.e. between
the anode and the rebar, and is unlikely to flow into secondary structures.
However, if the anode system is some distance from the structure as could be the case
with buried reinforced structures, e.g. pile caps, prestressed concrete pipe etc., then
interaction is far more likely.
In all cases the risk of interaction should be considered at the design stage and the
design should cater for any high-risk items. Low-risk items can be tested when the
cathodic protection system is commissioned. If interaction does occur, then possibleremedial measures include making a resistive bond to the secondary structure to
8/6/2019 Msc Project Draft Report
25/70
8/6/2019 Msc Project Draft Report
26/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
25
film anode systems the resultant rust staining can be unsightly. Metallic anchors for
junction boxes and cable ducts also face a similar problem.
8/6/2019 Msc Project Draft Report
27/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
26
4. Case study of refurbishment of chloride contaminated Bridge
4.1 Background
The repair of corrosion damaged reinforced concrete structures is a problem facing
many owners of infrastructure in the United Kingdom.The Nettlehill Railway Bridge is situated in the Knightsridge area of Livingston and
carries the A899 Livingston Road over the Bathgate to Edinburgh railway line and a
pedestrian footpath. This is the main route into Livingston from the M8 Motorway
and is one of the busiest roads in West Lothian.
The bridge was built in 1967. It has two spans and consists of 2 decks, one for each
traffic direction. The decks are constructed with pre-cast, prestressed concrete
inverted T-beams with an in-situ reinforced concrete filling. Each deck is simply
supported on reinforced concrete abutments and central reinforced concrete piers. The
overall span of the bridge is 24.84m and its width 35.13m.Routine inspections noted
damage to the structure and detailed concrete investigations found extensive chloridecontamination.
In order to ensure the continued safe operation of the structure for and beyond the
design life repair and protection measures were necessary. The procurement and
delivery of such a project involves many parties; and in this instance required specific
attention to the constraints of a live railway, including carrying out work during night
time railway possessions.
4.2 Structural Investigation
Routine Inspections of the structure alerted the Council to the problems with the
structure and in 1999 an extensive concrete investigation was undertaken. Theinvestigation comprised:
- Visual examination
- Hammer tapping survey
- Covermeter survey
- Half cell testing
- Depth of carbonation
- Chloride content
- Reinforcement inspection
- Cement /Alkali
The investigation showed damage to the concrete abutments and piers mainly relatingto water ingress through the deck joints. As a result, in 2001 refurbishment works to
the deck were undertaken. The deck was waterproofed and the joints replaced. This
work was the minimum required to ensure that the deterioration of the sub-structure
was halted. Funding constraints did not permit sub-structure repairs to follow on
immediately.
In 2004 West Lothian Council provided an additional 7.5M to be spent on clearing
the backlog of repairs to council bridges. This increase in funds allowed the
refurbishment of Nettlehill Railway Bridge to be completed.
A principal inspection undertaken by the councils consultant, URS Corporation,
identified the extent of the work required. It found that the main composite deck wasin fair condition and confirmed that the abutments and central piers were in poor
8/6/2019 Msc Project Draft Report
28/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
27
condition with significant areas of delamination, cracking, spalling concrete and rust
staining. A further concrete investigation was undertaken to accurately identify the
extent of the repair work prior to any repair contract being undertaken.
Problems Identified by 1999 Concrete Investigation
The visual and hammer tapping survey found large areas of delamination, spalling andexposed reinforcement on both abutments and the piers. Some of the areas extended
from the abutment shelf down to ground level. It was later found that these areas
extended to the top of the foundations and double delamination was found in some
areas. When plotted out the shape of the delaminated areas appeared to coincide with
the pattern of water ingress from the joints.
LocationApproximate surface area
spalling and delaminated (%)
North Abutments 20
East Pier (south face) 2
West Pier (south face) 5East Pier (north face) 1
West Pier (north face) 20
South Abutments 20
This survey accurately identified the extent of the repair work prior to any contract
being undertaken. However, a full concrete investigation was required to accurately
identify the cause of the deterioration and any other potential problems.
The covermeter survey recorded the readings below and in general showed that thecover is adequate:
LocationMm. average cover in test
area (mm)
Max average cover in test
area (mm)
North Abutment 26 56
East Pier 52 61
West Pier 53 78
South Abutments 36 55
The half-cell potential survey found a large number of areas where reading indicated
an increased risk of corrosion. Readings more negative than -350mV with respect to
copper sulphate electrode (CSE) suggest a 95% risk of corrosion. These areas mostly
coincided with the areas where deterioration was already visible. Higher thanexpected results were also recorded due to leakage at some locations. The following
results are typical of what was found:
Location Test Area
% of readings more negative
than -350mV.CSE
Or Comments on corrosion risk
North West Abutment 5 / 6 81/20
North East Abutment 1 / 3 / (4) 33 / 67 / (ok)
East Pier 17 Increased risk but majority ok
West Pier 19/20/21 Increased risk on north face
South West Abutment 40 / 42 84 / 12South East Abutments 37 / 39 / 38 High / high / low risk
8/6/2019 Msc Project Draft Report
29/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
28
Depth of Carbonation measurements were carried out at 25 locations and the majority
of the test results were not greater than 5mm. Carbonation was limited to the surface
only and was not contributing to the deterioration of the structure.
Chloride content testing found that there was extensive contamination across the
whole structure. 0.4% weight of chloride to weight of cement is considered torepresent a high risk of corrosion. The figures below are often well above this
particularly in areas where water had been leaking through the deck joints. On all
parts of the structure samples taken from higher levels had higher concentrations. The
depth range clearly shows that reinforcement is well inside the contaminated concrete.
Reinforcement inspections were carried out at 16 locations. Moderate to severe pitting
corrosion was found at nine of the inspection locations with the remainder showing
slight to moderate general corrosion. All the pitting corrosion locations were situated
within areas of leakage and/or high chloride content on the abutments and the north
face of the pier.
Location Test Area Chloride Content
(%)
Depth Range
(mm)
North West Abutment General 1.82 2.05
0.27 0.49
5-30
120 -150
North East Abutment 3 (high level)
Low level
0.72
0.16
0.45
0.56
0.1
5 30
90 120
120 150
5 30
90 120
East Pier General 0.83 0.08
0.4 0.05
Surface
Reinforcement
West Pier 0.84 4.58
0.2
Reinforcement
120 150
South West Abutment
South East Abutments 1.01 -3.1
0.58 - 3.1
Surface
Reinforcement
Cement and alkali content testing concluded that the alkali contents of the eight
concrete samples are within normal limits.
In summary it was clear from the above testing that the substructure of NettlehillRailway Bridge needed urgent action to correct the defects before the structure
became unstable.
The cause of the defects could clearly be traced to the leakage through the movement
joints. The defects were worse at the top of the abutments and where the most water
ingress was noted. Frost damage, high half cell potentials and high chloride content
are all indicative of damage due to the ingress of water containing de-icing salts.
The other important factor revealed by the testing was that the problems are more than
superficial. There was deep penetration of chlorides, which if not treated would causefurther damage to the structure after repair.
8/6/2019 Msc Project Draft Report
30/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
29
4.3 Overview of Refurbishment scheme
Resource constraints, meant that the project could not be handled in-house and URS
Corporation was appointed as the councils consultants for the Refurbishment. Right
from the start this proved valuable as URS had recent experience of dealing with
Network Rail and First Engineering. First Engineering were brought in early in the
design process to advise on what requirements and restrictions Network Rail would
put on the works. Careful consideration was given to work required to be undertaken
during railway possessions.
Their first task was to carefully consider and cost out all the available repair options.
Various options were considered:
Option A Do nothing. Carry out regular inspections and allow deterioration to
continue. With the structure a long way from reaching its design life and serious
deterioration already evident this option was taken no further.
Option B Patch repairs. Breakout and repair the damaged and delaminated concrete
identified. This is no more than a cosmetic solution and would only provide a shortterm solution. Known areas of chloride contaminated concrete would be left in the
structures and would cause further deterioration to the structure.
Option C Cathodic protection. The installation of CP allows the chloride
contaminated concrete to remain in place and will halt the corrosion of steel
reinforcement. Only the damaged and delaminated concrete would be broken out and
replaced.
Option D Concrete replacement. Breakout and repair all areas of defective concrete
including those areas identified as chloride contaminated. Up to 150mm of concrete
would have to be removed in many locations and ongoing testing would be required
to identify all the contaminated concrete. Accurate costing would be impossible attender stage.
Option E Demolish and Rebuild. This option is extremely expensive and
unacceptably disruptive.
Estimated Repair Costs
The identified options were costed. This showed that breakout and repair in
conjunction with CP provided best value, the estimates of each option are shown as
follows
Option Estimated Cost
A N/AB 699 606
C 879 606
D 1 230 590
E 3.5M - 4.5M
Corrosion Protection
A drawback with patch repair (option B) is that if any chloride contaminated concrete
is left in place it will continue to cause corrosion. In some cases it can even accelerate
corrosion in the steel adjacent to the repairs. This process is known as the incipient
anode effect. The only guarantee that corrosion will be stopped is to remove all the
contaminated concrete. This could be difficult to achieve and expensive.Cathodic protection can prevent the above and has a number of benefits:
8/6/2019 Msc Project Draft Report
31/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
30
- One off treatment with a design life of up to 60 years.
- Well varified technique
- Cost effective
- Potential cost saving
- Only damaged concrete is removed
- Contaminated concrete can remain- Avoids extensive temporary propping / closures
- Reduce the time taken for the repairs
- Prevent corrosion from reoccurring even if deck joints fail in future
In West Lothian four bridges had already been given cathodic protection. All of them
had suffered from similar problems to Nettlehill Railway Bridge. In each case CP was
adopted for its economic benefits.
Chosen Repair Scheme
The cathodic protection option was selected for Nettlehill Railway Bridge. It is theoption that provided Best Value, was the most cost effective solution and provided the
best long term solution for the structure. More importantly all the work could be done
without disrupting traffic on the A899 and the trains. As a Local Authority this final
issue is often as important as the engineering issues that are considered.
Proiect Procurement and Tendering
Having undertaken additional site investigation we were confident that the quantity of
concrete repair required was relatively accurate so an NEC contract with an activity
schedule was used. Tenderers were provided with a specification, drawings of the
structure including reinforced concrete details and drawings showing the extent of thework required. The CP was to be a contractor designed element along with any
necessary propping and temporary access. Also included in the tender were a set of
Railway Possessions that were pre-booked. The tenderers were permitted to use all of
these possessions and book further possession at their own expense.
The activity schedule form of contract allows the contractor to select the repair
techniques, materials and construction programme that they are most comfortable
working with. They are best placed to consider this having been involved with work
like this before. From the clients perspective there is some assurance that tenderers are
giving proper consideration to the work required when they compile their tender
return.
The local authority cannot specify specific products and sub-contractors. Tenderers
are free to use any product or supplier provided they fully comply with the
specification.
The interface with the railway was always going to be critical for the success of the
refurbishment scheme. The tenderers selected to bid for the work all had experience
working on railways and were registered on Constructionline.
The tendering process followed West Lothian Councils standard procedures and was
won by Freyssinet Ltd. They in turn appointed Corrosion Control Services as theirspecialist sub-contractor for the CP. The tender price was within budget and the
8/6/2019 Msc Project Draft Report
32/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
31
contract was awarded in July 2005. The work started on site on 25 July 2005 and was
complete by Christmas.
4.4 Site Constraints
Railway (Possessions)
The Bathgate to Edinburgh branch line passes below the Nettlehill Railway Bridgeand it is an important commuter route into the city. This means that the bulk of the
land below the bridge belongs to Network Rail and any work undertaken is subject to
approval and oversight by Network Rail. The north abutment and the piers are all in
this area.
The railway was the main constraint to the scheme that would govern how the works
would be undertaken and programmed so the consultant made early contract with
Network Rail and their contractor First Engineering. A site meeting was held, all the
practical issues were discussed and suitable working practises were agreed at the
design stage.
No disruption to train services on the line was permitted by Network Rail and
possessions were only permitted for short periods during the night or longer durations
at the weekend. The line could be closed from 00:15 to 09:Oohrs on Saturday night
and 00:15 to 06:15 on Sunday night. These times include the time it takes Network
Rail to close the track and can be subject to late cancellation.
West Lothian Council had to sign and agreement with Network Rail before the works
could commence. It is a standard document that indemnifies Network Rail against any
accidents or disruption caused by works being undertaken on their land by outside
parties.
A couple of factors worked in our favour, there is only a single track and it is not
electrified. In consultation it was agreed at the design stage which areas of the
structure could be worked on during the day and which could only be done during
possession working. These were as follows:
As there was enough space between the track and the north abutment, a safe working
zone was permitted. This area had to be fenced in to prevent operatives straying onto
the live railway and was established during the first overnight possession. Once in
place all the work was able to proceed within the zone at any time of day.
The south face of the piers was also designated a safe working zone. Fences were
built at either side of the bridge and full height containment was provided between the
two piers. Network Rail also permitted the creation of a temporary access through
their boundary fence for site access.
The north face of the piers was too close to the track and all work had to be
undertaken during possessions. It was agreed that props could remain in place, as it
was impractical to remove them after each possession.
In addition to the working zones Network Rail also required all the scaffolding to be
fully contained and all debris to be removed from the site. Their ballast was not to be
contaminated with any waste from the site.
Network Rail required their contractor to be on site whenever work was being
undertaken. Their supervisor gave every operative and visitor a briefing before
entering the site and inspected the works at regular intervals. Unfortunately the cost ofthis supervision had to be met by West Lothian Council.
8/6/2019 Msc Project Draft Report
33/70
Evaluation of Corrosion Control Methods forChloride contaminated Reinforced concrete structure MSc Project Draft Report
32
The good working relationship established by the consultant with Network Rail and
First Engineering carried on with the contractor, Freyssinet. They were able to
reorganise possessions to better suit their programme and were able to source
specialist plant from First Engineering. It was fortunate that none of the possessions
were cancelled.
Network Rails involvement with the scheme was to approve the CP installation. They
were concerned at the possibility of stray currents affecting their signaling equipment.
It was agreed that some inter-action testing should be carried out prior to the system
being switched on and fully energized.
Public Access
Pedestrians had to be given free access along the footpath beside the south abutment.
Closing the footpath was not considered practical, as the only safe alternative route
was a long diversion to a footbridge further down the A899. Inevitably people would
be tempted to try crossing the busy dual carriageway instead. The contractor was
required to undertake the repair work and guarantee the safety of pedestrians.
With properties close to the site, people were always going to have an interest in what
was going on. To comply with West Lothians Considerate Contractor Scheme,
adjacent houses were letter dropped and advance warning signs were posted giving
relevant information.
Unauthorised public access was also an issue that needed careful consideration, as
vandalism is now a widespread a problem. The site compound needed to be secure, as
did the working areas, particularly scaffolding when operatives were not on site.
Traffic & Traffic Loadings
The A899 is one of West Lothians busiest roads and is classed as traffic sensitive.
This means that no traffic Management is permitted on the road during the rush hours,
between 07:00 and 09:30hrs and 15:30 and 19:30.
No closure of the bridge was permitted as the knock on effect on adjacent roads and
given its proximity to the M8 any closure would have had severe consequences and
was not acceptable.
With the bulk of the repair work being on the substructure this was not a big issue on
this contract. However, there is always a risk when breaking out concrete close to the
bearing shelves that areas of the bridge could become unstable, In this instance a
bridge closure would have had a serious impact on traffic and trains and was an
unacceptable risk.The contractor was therefore required to provide props with enough capacity to
support the deck whenever work was to be undertaken in the area of the bearing
shelves.
4.5 Selection of Repair Methods
Concrete Repair
The areas of the piers and abutments that required repair were relatively extensive, in
particular on the abutments. However, generally the corrosion was limited to the outer
layer of reinforcement and the amount of reinf