For more information contact: Robert Ryan Queensland Operations Manager 07 3212 5111 | [email protected] | Comdaininfrastructure.com.au Mount Crosby Flash Mixers Project start date: October 2013 Project completion date: February 2014 Client Comdain’s role Project description Works undertaken Seqwater Primary Contractor Installation of submersible pumps in the occulation Inlet Chambers of each basins at East Bank WTP Installation of dry mounted end suction pumps at each of the basins at West Bank WTP Construction of DN200 SS Flash Mixer discharge pipe work Fabrication & installation of Flash Mixer nozzle and Deection cone for each of the four basins Installation of precast concrete chambers over existing incoming raw water inlet Associated electrical works including the Installation of electrical cabinets (indoor & outdoor) and power cabling Conguration and programming of PLC and SCADA All testing and commissioning works Fabrication and installation of Flash Mixers to the sedimentation basins at Mt Crosby’s East Bank Water Treatment Plant and West Bank Water Treatment Plant .
Transcript
Page 1: Mt Crosby Flash Mixers.pub

For more information contact:

Robert Ryan Queensland Operations Manager 07 3212 5111 | [email protected] | Comdaininfrastructure.com.au

Mount Crosby Flash Mixers Project start date: October 2013 Project completion date: February 2014

Client

Comdain’s role

Project description

Works undertaken

Seqwater

Primary Contractor

Installation of submersible pumps in the flocculation Inlet Chambers of each basins at East Bank WTP

Installation of dry mounted end suction pumps at each of the basins at West Bank WTP

Construction of DN200 SS Flash Mixer discharge pipe work

Fabrication & installation of Flash Mixer nozzle and Deflection cone for each of the four basins

Installation of precast concrete chambers over existing incoming raw water inlet

Associated electrical works including the Installation of electrical cabinets (indoor & outdoor) and power cabling

Configuration and programming of PLC and SCADA

All testing and commissioning works

Fabrication and installation of Flash Mixers to the sedimentation

basins at Mt Crosby’s East Bank Water Treatment Plant and West

Bank Water Treatment Plant .