POWER MUARA TAWAR 5 – Indonesia 234 MW – KA13E2 Combined-Cycle Power Plant PROJECT FEATURES PROJECT HIGHLIGHTS - This project involves extension of the existing power plant with a fifth block. The new KA13E2 block adds an additional 234 MW to the current 1800 MW plant, helping the country to cope with the current electricity crisis on the Java/Bali grid. - The Alstom-Marubeni consortium already built combined-cycle block 1 and gas turbine peaking block 2 in 1995. - Alstom has already been a key player in the Indonesian power generation market since the 1960’s. It has supported the client PT PLN in meeting the growing energy demand of the country through the construction of gas, coal and hydro power plants. CUSTOMER BENEFITS - High availability and reliability thanks to the KA13E2 proven technology - Optimised base load through Plant Integratormethodology - High operational flexibility to meet the booming demand for power - An environmentally-responsible power solution with low emissions The power plant is located in Muara Tawar, 35 km from Jakarta, on the northern coast of Java Island, Indonesia. JAKARTA Bandung Surabaya Medan Ujung Pandang (Makassar) Palembang Semarang Kupang Padang Yogyakarta Banjarmasin Manila Koror Bangkok Kuala Lumpur Davao Darwin Bam We Da Nang Kuching Ipoh Dili Zamboanga Hô Chi Minh (Saigon) Phnom-Penh Rangoon Bandar Seri Begawan Manado Palu Gorontalo Pekanbaru Jambi Bandar Lampung Samarinda Pontianak Balikpapan Surakarta Malang Kendari Ambon Jayapura Manokwari Ternate Banda Aceh Bengkulu Denpasar Mataram Palangkaraya Serang Pangkalpinang Tanjungpinang Indonesia Plant IntegratorFactors Customer benefits INVESTMENT Optimised capital investment LEAD-TIME Shorter lead-times to produce electricity faster Higher plant efficiency for increased power output at a wide range of operational modes PERFORMANCE Reduced emissions to meet environmental concerns Lower Operating & Maintenance (O&M) costs AVAILABILITY & FLEXIBILITY Better reliability, availability and flexibility RETROFIT Better power plant economics through Integrated Retrofit Solutions LIFE EXTENSION Extended plant life options Our Plant Integratorapproach offers more value for customers The Plant Integratorconcept is Alstom’s unique way of creating more value for customers. We combine outstanding expertise at a component and plant level, as we are both an equipment designer and manufacturer. In addition, we are an Engineering, Procurement and Construction (EPC) contractor with extensive proven worldwide references. Through close collaboration, we guarantee that our customers meet their business objectives and serve their market more effectively. There are six Plant Integratorfactors , which help increase the Net Present Value for our customers. Customer: Perusahan Listrik Negara Limited (PT PLN) Notice to proceed: June 2008 Fuel: gas / oil back-up Cooling system: Seawater Application: Power Generation Unique Plant Integratorcapabilities to deliver a highly available and reliable power plant
Transcript
Page 1: MT05 fact sheet

POWER

MUARA TAWAR 5 – Indonesia 234 MW – KA13E2 Combined-Cycle Power Plant

PROJECT FEATURESPROJECT HIGHLIGHTS- This project involves extension of the existing power plant with a fifth block.

The new KA13E2 block adds an additional 234 MW to the current 1800 MW

plant, helping the country to cope with the current electricity crisis on the

Java/Bali grid.

- The Alstom-Marubeni consortium already built combined-cycle block 1 and gas

turbine peaking block 2 in 1995.

- Alstom has already been a key player in the Indonesian power generation

market since the 1960’s. It has supported the client PT PLN in meeting the

growing energy demand of the country through the construction of gas, coal

and hydro power plants.

CUSTOMER BENEFITS- High availability and reliability thanks to the KA13E2 proven technology

- Optimised base load through Plant Integrator™ methodology

- High operational flexibility to meet the booming demand for power

- An environmentally-responsible power solution with low emissions

The power plant is located in Muara Tawar,

35 km from Jakarta, on the northern coast of

Java Island, Indonesia.

JAKARTABandung Surabaya

Medan

Ujung Pandang(Makassar)

Palembang

Semarang

Kupang

Padang

Yogyakarta

Banjarmasin

Manila

Koror

Bangkok

Kuala Lumpur

Davao

Darwin

Bam

We

Da Nang

Kuching

Ipoh

Dili

Zamboanga

Hô Chi Minh(Saigon)

Phnom-Penh

Rangoon

Bandar Seri Begawan

Manado

Palu

GorontaloPekanbaru

Jambi

Bandar Lampung

SamarindaPontianak

Balikpapan

Surakarta

Malang

Kendari Ambon

Jayapura

Manokwari

Ternate

Banda Aceh

Bengkulu

Denpasar Mataram

Palangkaraya

Serang

Pangkalpinang

Tanjungpinang

Indonesia

Plant Integrator™ Factors Customer benefits

INVESTMENT Optimised capital investment

LEAD-TIME Shorter lead-times to produce electricity faster

Higher plant efficiency for increased power output at a wide range of operational modes

PERFORMANCE Reduced emissions to meet environmental concerns

Lower Operating & Maintenance (O&M) costs

AVAILABILITY & FLEXIBILITY Better reliability, availability and flexibility

RETROFIT Better power plant economics through Integrated Retrofit Solutions

LIFE EXTENSION Extended plant life options

Our Plant Integrator™ approach offers more value for customers

The Plant Integrator™ concept is Alstom’s unique way of creating more valuefor customers. We combine outstanding expertise at a component and plantlevel, as we are both an equipment designer and manufacturer. In addition, weare an Engineering, Procurement and Construction (EPC) contractor withextensive proven worldwide references. Through close collaboration, weguarantee that our customers meet their business objectives and serve theirmarket more effectively. There are six Plant Integrator™ factors , which helpincrease the Net Present Value for our customers.

Customer: Perusahan ListrikNegara Limited (PT PLN)

Notice to proceed: June 2008

Fuel: gas / oil back-up

Cooling system: Seawater

Application: Power Generation

Unique Plant Integrator™ capabilities to deliver a highlyavailable and reliable power plant

Page 2: MT05 fact sheet

POWER

PT-

PE/

BP

RO

S/M

RTW

PS0

8/en

g/P

PS/

04.0

8/FR

/647

3 -

allr

eady

- 5

00 3

85 4

89 R

CS

Lyo

n

MUARA TAWAR 5 – Indonesia 234 MW – KA13E2 – Combined-Cycle Power Plant

ALSTOM’s SCOPE• Turnkey Engineering Procurement Construction (EPC) contract for the power

island of a KA13E2 multi-shaft Combined-Cycle Power Plant including:

- overall plant engineering,

- global procurement & logistics,

- electrical and mechanical construction supervision,

- commissioning of the power plant.

• Alstom's proven equipment and mature technology is designed and

manufactured in-house:

- One highly reliable & clean power producing GT13E2 gas turbine with unique

EV (EnVironmental) burner technology,

- One horizontal dual pressure Heat Recovery Steam Generator,

- One COMAX steam turbine,

- One air-cooled TOPAIR turbogenerator for the gas turbine,

- One air-cooled TOPACK turbogenerator for the steam turbine,

- One seawater cooled condenser,

- ALSPA power control systems.

The Muara Tawar project benefits from superior integration throughAlstom’s project management skills, EPC capabilities and state-of-the-artkey components.

Meeting Perusahan Listrik

Negara Limited’s requirements

Demand for power has grownconsiderably in Indonesia, stimulatedby economic recovery. This increasein demand, combined withdecreasing generation capacities inageing existing power plants, couldhave led to a deteriorating demand-supply balance. To avoid such asituation, an investment programmewas launched to develop the existingMuara Tawar power plant. Thisproject will help the country to faceits present growth in power demand,while protecting the environmentwith clean power solutions.

With its environmental and economic advantages, this plant is another example of Alstom capability

to deliver clean integrated power solutions.

www.power.alstom.com

MUARA TAWAR 5 PLANT ARRANGEMENT


Recommended