+ All Categories
Home > Business > Muckle LLP - Which contract should I be using?

Muckle LLP - Which contract should I be using?

Date post: 22-Apr-2015
Category:
Upload: association-for-project-management
View: 160 times
Download: 1 times
Share this document with a friend
Description:
This was a presentation delivered by Robert Langley, partner and head of the construction and engineering team at Muckle LLP, on Tuesday 7th October. The event was organised and hosted by the APM North East branch and was entitled 'Project contracts and how they support collaborative working'. It was held at the Radisson Blu hotel in Durham.
45
Which contract should I be using? Robert Langley Partner, Construction & Engineering team Muckle LLP
Transcript
Page 1: Muckle LLP - Which contract should I be using?

Which contract should I be using?

Robert Langley

Partner, Construction & Engineering team

Muckle LLP

Page 2: Muckle LLP - Which contract should I be using?

Collaboration

• “The Act or process of collaborating”

• “Co-laborare” – to work together (latin)

• Do we need to spell it out?

Page 3: Muckle LLP - Which contract should I be using?

NEC3

• 10.1 “The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this Contract and in a spirit of mutual trust and co-operation”

• JCT Optional Schedule 8

• the parties must work with each other and the Project Team “in good faith and in a spirit of trust and respect”

Page 4: Muckle LLP - Which contract should I be using?

Good faith – recent guidance

• TSG Building Services v South Anglia Housing

• “ACA Term Partnering 2005

• team members shall work together in a spirit of trust fairness and mutual co-operation for the benefit of the Programme”

• Mid-Essex NHS Trust v Compass

• “the Trust and the Contractor will co-operate with each other in good faith... for the efficient transmission of information... and to enable the Trust to derive the full benefit of the Contract”

Page 5: Muckle LLP - Which contract should I be using?

Good faith: conclusion from the case law

• General statements are of limited use

• Detailed provisions are more valuable

• e.g. provisions for reasonableness in JCT enabling PM to exercise judgment

• clear articulation of functions and controls in NEC3

Page 6: Muckle LLP - Which contract should I be using?

Various types of standard forms

• All generally issued as ‘suites’

• CIOB – Chartered Institute of Building

• Complex building and engineering projects

• Fidic – Federation Internationale de Ingenieurs Conseils

• Engineering, energy and process plant. Usually international

• IChemE

• Chemical and process engineering industries

Page 7: Muckle LLP - Which contract should I be using?

Various types of standard forms

• GC/Works

• primarily for government contracts

• ICC - Infrastructure Conditions of Contract

• typically civil engineering projects

• JCT

• most common form, typical on commercial property and development projects

• NEC3 – New Engineering Contracts

• general application, recommended by government

Page 8: Muckle LLP - Which contract should I be using?

Today’s focus

• IChemE

• JCT

• NEC3

• typical features

• differences

• points to note

Page 9: Muckle LLP - Which contract should I be using?

IChemE

• Specifically applicable to chemical and process engineering industries

• oil & gas, water & power, food technology, pharmaceuticals

• Results / performance based

• generally designed for projects that will need to be tested against defined criteria once constructed

Page 10: Muckle LLP - Which contract should I be using?

IChemE

• Balance of risk

• generally contain more exclusions of liability in favour of the contractor

• due to the nature of process plants – consequential losses as a result of defects can be enormous

• IChemE contracts include:

• requirement that Purchaser provides construction all risks insurance

• overall cap on liability

• final Certificate excludes further liability

• one year defects liability period

Page 11: Muckle LLP - Which contract should I be using?

IChemE

• 4 main UK contracts

• The Red Book – lump sum

• The Green Book – reimbursable

• The Burgundy Book – target cost

• The Orange Book – minor works

Page 12: Muckle LLP - Which contract should I be using?

The Red Book

• Turnkey contract

• contractor takes responsibility for design

• costs of completion at Contractor’s risk

• subject to contractual Variations

• The relationship between the parties is typically performance based

• caution against amending this in negotiations

• give careful thought to the schedules • sets out description of the works, purchaser’s own

responsibilities, scope of works

Page 13: Muckle LLP - Which contract should I be using?

The Green Book

• Very similar philosophy to Red Book

• turnkey contract

• contractor takes responsibility for design

• Contractor fully reimbursable for actual costs incurred

• this includes corrective costs arising from design & construction errors

• note – Contractor must use “reasonable skill and care to be expected of a properly qualified and competent Contractor”

Page 14: Muckle LLP - Which contract should I be using?

Which to use?

• Red Book

• Where purchaser wants certainty on costs

• where full tender process is desired

• standard package is required, with a detailed specification and engineering information is available

Page 15: Muckle LLP - Which contract should I be using?

Which to use?

• Green Book

• Purchaser wants flexibility and is confident to get involved with the process

• more power to Project Manager

• where technology is less advanced – perhaps the performance and results of the process are uncertain

• if project relies on Purchaser’s specific knowledge or skills

Page 16: Muckle LLP - Which contract should I be using?

The Burgundy Book

• Target Cost contract

• attempts to promote co-operation and fairness between the parties through incentives

• Typical operation

• parties agree Target Cost for the works

• contract includes formula that incentivises Contractor to minimise costs overspends

• contractor records Actual Costs incurred on the project

Page 17: Muckle LLP - Which contract should I be using?

Pain share / gain share

• Target Cost and Actual Cost is compared

• any savings against the Target Cost are shared

• Contractor is paid half of the saving

• effectively a bonus for coming in under budget

• any overruns against the Target Cost are shared

• Contractor is only paid half of the overrun between the Target Cost and Actual Cost

• effectively a penalty for overrun

• Aim is to incentivise parties to achieve lowest Actual Costs possible

Page 18: Muckle LLP - Which contract should I be using?

Changes to costs

• Clause 16 – variations

• agreed variations allow an increase to the Target Cost

• except where work is necessary for the Plant to comply with the Specification – Contractor not entitled to increase to Target Cost

Page 19: Muckle LLP - Which contract should I be using?

Changes to costs

• Clause 37 – defects

• the remediation of defects is at Purchaser’s cost – i.e. Contractor’s Actual Costs is increased

• except where defect is due to Contractor’s failure to exercise reasonable skill and care

Page 20: Muckle LLP - Which contract should I be using?

Key considerations

• Detailed and accurate Specification is critical

• helps avoid costly variations arguments

• Extensive role for Project Manager

• important to select a strong and competent character to manage the project

• note that PM must act impartially between the parties

• Parties must be clear on Target & Actual Costs

• full recording procedures and mechanisms must be included in contract Schedules

Page 21: Muckle LLP - Which contract should I be using?

Case study

• Firstline Engineering Co v NLP Process Power

Page 22: Muckle LLP - Which contract should I be using?

JCT

• Most common form of building contract

• 5 forms:

• standard Building contract

• design and Build (DB) Building contract

• major Project Building contract

• Minor works

• intermediate

Page 23: Muckle LLP - Which contract should I be using?

Standard Building Contract

• 3 contracts in this category

• approximate Quantities (measurement)

• quantities (lump sum)

• Without quantities (lump sum)

• Provisions generally similar, main difference concerns way price is determined

• lump sum price will be altered where works are varied or delayed, where delay is due to Employer

• measurement changes to reflect the actual work carried out

Page 24: Muckle LLP - Which contract should I be using?

Standard Building Contract

• Typically used for larger construction projects

• complex engineering unlikely

• Architect has contract administration role

• supervise the day to day works and manage administration – crucially, notices

• Employer retains some responsibility

• termination notices for example

Page 25: Muckle LLP - Which contract should I be using?

Contractor’s Design Portion

• If Contractor is to carry out some design, CDP is implemented

• records the extent of the Contractor’s responsibility for certain elements of the works

• may often use specialist sub-contractors

Page 26: Muckle LLP - Which contract should I be using?

Design and Build

• Used on similar projects as Standard contracts

• Contractor assumes responsibility for design and build

• Contractor typically given Employer’s Requirements

• produces proposals for design on this basis

• Often design is produced by professional consultants, then novated to Contractor

• Contractor’s design liability can be capped

Page 27: Muckle LLP - Which contract should I be using?

Differences

• Contractor has design responsibility in DB

• not in Standard, unless a CDP is used

• note that Employer retains responsibility for Employers Requirements in DB – so not accurate that Contractor has ‘entire’ design responsibility wrap in DB

• DB does not utilise a Contract Administrator, instead uses an Employer’s Agent

Page 28: Muckle LLP - Which contract should I be using?

Differences

• Both contracts do not expressly deal with ground conditions

• assumption is that Contractor retains responsibility

• Note in DB – Employer retains responsibility for design within Employer’s Requirements (potentially leads to unexpected results)

Page 29: Muckle LLP - Which contract should I be using?

Major Building Contract

• Intended for the largest of projects

• Parties generally experience in large scale procurement

• Contractor responsible for design

• Shorter than DB contract, so suitable where parties have their own detailed procedures

• Can be used where sectional completion is required

Page 30: Muckle LLP - Which contract should I be using?

Minor works

• Two forms

• minor Works Building Contract

• minor Works Building Contract with Contractor’s design

• CPD used where discreet elements of design are required from Contactor

Page 31: Muckle LLP - Which contract should I be using?

Minor works

• Appropriate where works are simple in nature extensions, remodelling

• Architect / Contract Administrator is used

• Not suitable:

• where wholesale design is required from Contractor

• where bill of quantities are required

• If detailed control / costs procedures required

Page 32: Muckle LLP - Which contract should I be using?

Intermediate contracts

• Sit between Minor Works and Standard

• used for reasonably simple projects where the skills and trades involved are conventional

• Can utilise a CDP where Contractor is to do some design

• not suitable as a full DB contract though

Page 33: Muckle LLP - Which contract should I be using?

NEC3 suite

• Engineering and Construction Contract

• most common

• Professional Services Contract

• Engineering and Construction Short Contract

• Term Service Contract

• Framework Contract

Page 34: Muckle LLP - Which contract should I be using?

NEC3

• Completely new drafting philosophy

• different terminology used

• some concern that the drafting is not tried and tested?

• not lawyer friendly

• legal precision takes a back seat in favour of promoting proactive management processes

• Generally applicable to all types of works

• national infrastructure particularly

• Crossrail, Heathrow T2, London 2012

• Recommended and endorsed by government

Page 35: Muckle LLP - Which contract should I be using?

NEC3 philosophy

• Intended to be a project management tool

• aims to increase proactive risk management

• Parties need to adopt and ‘buy into’ the philosophy

• the look and feel of the contract is very different to typical forms

• intention was to move away from ‘adversarial forms’

Page 36: Muckle LLP - Which contract should I be using?

Key points and features

• Writing style

• plain English, written in present tense

• each clause stands alone – no cross referencing

• the word ‘shall’ on appears once – in clause 10.1

• Clause 10.1

• all parties agree to “act in a spirit of mutual trust and co-operation”

• underpins NEC philosophy

• concerns over legal interpretation

Page 37: Muckle LLP - Which contract should I be using?

Key points and features

• Project Manager takes extensive role

• responsible for championing the NEC values

• subject to clause 10.1

• high level of authority is required

• must get involved in indentifying and managing risk proactively – risk register under clause 11

Page 38: Muckle LLP - Which contract should I be using?

Key points and features

• Clause 11.2 (14) – risk register

• parties must compile a risk register at the start of the project

• must be continually updated as the project progresses

• register describes risk and lists steps take to mitigate

Page 39: Muckle LLP - Which contract should I be using?

Key points and features

• Clause 16 – early warning events

• Contractor and PM are required to give early warning notices “as soon as either becomes aware of any matter which could

• increase total of the Prices

• delay Completion

• delay meeting a Key Date

• impair the performance of the works in use”

• Wide ranging

• Not ‘could’ – designed to encourage early and open disclosure

Page 40: Muckle LLP - Which contract should I be using?

Key points and features

• Clause 60 – compensation events

• wide ranging, detailed list

• Clause 61.3 - Notification of compensation events

• “the Contractor notifies the Project Manager of an event which has happened or which he expects to happen as a Compensation event...”

• aimed at encouraging early disclosure so risk can be mitigated

Page 41: Muckle LLP - Which contract should I be using?

Amending the NEC3?

• Innovative approach means there is room for criticism – especially for lawyers!

• NEC advocates say this is deliberate – move away from the traditional approach

• Wholesale amendment is therefore discouraged

Page 42: Muckle LLP - Which contract should I be using?

Amending the NEC3?

• Some areas do require clarification

• specify which documents are Contract Documents and order of precedence

• no general obligation to comply with statutes

• compensation event procedure is often regarded as overly bureaucratic

• transfer of title provisions inadequate – especially where employer has paid for materials stored off site

• Matter for parties – but remember philosophy

Page 43: Muckle LLP - Which contract should I be using?

Any questions?

Page 44: Muckle LLP - Which contract should I be using?
Page 45: Muckle LLP - Which contract should I be using?

This presentation was delivered

at an APM event

To find out more about

upcoming events please visit our

website www.apm.org.uk/events


Recommended