Project Progress As On 7th Oct,2014
MY HOME ABHRA TOWER-”A” AS ON 07.10.14
1.1st Floor To 17th Floor Slabs Completed2.External Brick Work Completed & Plastering Completed
MY HOME ABHRA TOWER-”B” AS ON 07.10.141.1st Floor To 17th Floor Slabs Completed
2.External Brick Work & Plastering Completed
MY HOME ABHRA TOWER-”C” AS ON 07.10.14
1.1st Floor To 17th Floor Slabs Completed2.External Brick Work & Plastering Completed
MY HOME ABHRA TOWER-”D” AS ON 07.10.14
1.1st Floor To 17th Floor Slabs Completed2.External Brick Work & Plastering Completed
MY HOME ABHRA TOWER-”E” AS ON 07.10.14
1.1st Floor To 17th Floor Slabs Completed2.External Brick Work & Plastering Completed