Narayanpur Right Bank Canal Extension
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Location: Extension of Narayanpur Right Bank Canal from Km 95.00 to
168.50
Utilisation 18.952 TMC
Discharge @ Starting Point
33.725 Cumecs (1,191 Cusecs)
Main Canal Extension of NRBC from Km 95.00 to 168.50
Distributaries D-18A to D-52 Network
Command Area 56,100 Ha.
Potential created - Nil -.
Dist. / Taluks benefited Raichur Dist. : Raicur Taluk
Status of work
• NRBC Extension from Km 95.00 to 135.00 Almost completed. • NRBC from Km 135.00 to 168.50 – In progress. • Distry.No.23 Km 0.00 to 11.17 (including Aqueduct) in progress.
• Tail End Distry. Km 0.00 to 18.60 in progress.
Financial Details Updated Estimated Cost of Project : Rs.963.50 Crore. Expenditure incurred Upto March 2018 : Rs.176.50 Crore.
NRBC Km 1
Mallabad Lift Irrigation Scheme
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Location:
Lift No.1 – Off-take @ Km 20.00 of Jewargi Branch Canal.
Lift No.2 – Off-take @ Km 20.00 of Mudbal Branch Canal Lift No.3 – Off-take @ Km 5.40 of Shahapur Branch Canal
Utilisation 8.054 TMC
Components
3 No. Head Work Main Canal : Lift No.1 – From Km 0.00 to 9.00
Lift No.2 – From Km 0.00 to 16.40 Lift No.3 – From Km 0.00 to 17.40
Distr. Network under 3 Lifts for 33,752 Ha.
Command Area 33,730 Ha. (83,313 Acres)
Potential created Under Lift No.1 : 4,950 Ha.
Dist. / Taluks benefited Kalburgi Dist. : Jewargi Taluk Yadgir Dist. : Shorapur Taluk
Status of work
Head works :
Under Lift No.1 – Completed. Under Lift No.2 – Completed. Under Lift No.3 – Completed. Canal Network : Under Lift No.1 : Main Canal Km 0.00 to 9.00 completed. Distry.No.1 2, 4 & 5 completed. Distry.No.3 Km 0.00 to 6.00 (including Aqueduct) in progress.
Under Lift No.2 : Main Canal Km 0.00 to 16.40 Completed.
Under Lift No.3 : Main Canal Km 0.00 to 17.60 in progress.
Financial Details Updated Estimated Cost of Project : Rs. 578.27 Crore Expenditure incurred Upto March 2018 : Rs.165.30 Crore
Bhima Flank
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Location: Extension of SBC from Km 75.30 to 98.30
Utilisation 5.151 TMC
Components Main Canal : Extension of SBC from Km 75.30 to 98.30
Distry. Network for _21,572 Ha.
Command area 21,572 Ha.
Potential created Nil
Dist. / Taluks benefited Yadgir Dist. : Yadgir Taluka
Present status of the work
Main Canal : Extension of SBC from Km 78.30 to 98.30 in progress. Distry. Network Survey Investigation & Preparation of Estimates for Distry. Network in progress.
Financial Details Updated Estimated Cost of Project : Rs. 271.57 Crore Expenditure incurred Upto March 2018 : Rs. 01.00 Crore
Sonthi Lift Irrigation Scheme
SALIENT FEATURES OF FRESH PROJECT
Salient Features Photo
Location On the Upstream of Sothi Barrage across River Bhima near
Tarwarpet Village of Chittpur Taluk of Kalburgi Dist..
Utilisation 4.00 TMC
Components
Head Work - 1 No. Sonthi Main Canal : 40.00 Km Sonthi Branch Canal : 18.10 Km
Distry.No.1 : 13.50 Km Yargol Minor Canal : 9.90 Km Distry. Network on Sonthi Main Canal & Sonthi Branch Canal and Distry No 1
Command Area 16,100 Ha. (39,767 Acres).
Potential created 10266 Ha.
Dist. / Taluks to be benefited
Kalburgi Dist. ; Chitapur Taluk Yadgir Dist. : Yadgir Taluk
Commencement of Project
2007
Status of work
Head works: Completed Canal Network : Feeder Canal 1. Km including Railway crossing completed.
Sonthi Main Canal Km 0.00 to 18.00 Almost completed. Sonthi Main Canal Km 18.00 to 40.00 under three packages in
progress. Sonthi Branch Canal Km 0.00 to 18.10 - Almost completed. Distry.No.1 Km 0.00 to 13.50 - Almost completed. Yargol Minor Canal Km 0.00 to 9.90 in Progress. Distry. Network under Sonthi Main Canal & Branch Canal in various status of progress. Water let out in completed Canal Network of Sonthi Main Canal,
Sonthi Branch Canal & Distry.No.1. Submergence of Hurasgundagi Village : Rehabilitation & Resettlement of Hurasagundagi Village in backwater of Sonthi Barrage in progress.
Financial Details Updated Estimated Cost of Project : Rs.673.90 Crore. Expenditure incurred Upto March 2018 : Rs.318.80 Crore
Head Work
Feeder Canal
Aqueduct on Sonthi Main Canal
NRBC Distry.No.9A
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Location: Off-take at Km 54.12 _ of NRBC – Right side.
Utilisation 3.75 TMC
Components
NRBC Distry. No.9A of 29.15 Km
Arkera Brabch Distry. of 22.87 Km & Network Wadvatti Branch Distry. of 28.77 Km & Network
Command area 15,250 Ha
Potential created 12,021 Ha. Ha.
Dist. / Taluks benefited
Raichur Dist : Deodurga & Manvi Taluks
Status of work
NRBC Distry. 9A Km 0.00 to 29.15 Completed & water let out for irrigation. Arkera Branch Distry. Km 0.00 to 22.87 & Network completed &
water let out for irrigation. Wadvatti Branch Distry. Km 0.00 to 10.00 completed & Km 10.00 to 28.17 in progress.
Financial Details Updated Estimated Cost of Project : Rs.225.00 Crore Expenditure incurred Upto March 2018 : Rs.221.15 Crore
Aqueduct on NRBC Distry. 9A
MANJRA BARRAGES IN BIDAR DIST
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Location: 4 No. Series of Barrages across river Manjra in Bidar Dist . in Aurad
& Bhalki Taluks.
Utilisation 4,80 TMC
Components
Construction of 4 No. Series of Barrages : 1) Jirgihal Bridge cum Barrage 2) Manikeshwar Bridge cum Barrage
3) Halhalli Bridge cum Barrage 4) Chandapur Bridge cum Barrage Barrages provided with Automatic Tilting Godbole Gates.
Command area 12,670 Ha. (Own Lift by Farmers from the storage accomplished at Barrages)
Dist. / Taluks
benefited Bidar Dist : Aurad & Bhalki Taluks
Status of work All Civil & Gate works of 4 No. Series of Barrages completed. Providing Low Level Friction Dampers works for all four Barrages in progress.
Financial Details Updated Estimated Cost of Project : Rs.300.00 Crore Expenditure incurred Upto March 2018 : Rs.279.80 Crore
Chandapur Bridge Cum
Barrage
Jirgihal Bridge Cu
JETTUR BRIDGE CUM BARRAGE
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Location: Across River Kagina near Jettur Village of Chincholi Taluk, Kalburgi Dist.
Length of Barrage 191.60 Mt
No. of Piers 36 No. Main Piers & 35 Dummy Piers.
Gates 420 No. Needle Gates of Size 2.25 Mt. x 0.50 Mt. (6 No. Needle Gates in Each vent)
Command area 500 Ha. (Own Lift by Farmers from the storage accomplished at Barrage)
Dist. / Taluks benefited
Kalburgi Dist. : Chincholi Taluk
Status of work
Excavation for foundation completed.
12 No. Main Piers & 12 No. Dummy Piers completed. 4 No. Main Piers & 4 No. Dummy Piers in progress. Fabrication of 32 No. Gates completed out of 70 Nos
Financial Details Updated Estimated Cost of Project : Rs.26.26 Crore Expenditure incurred Upto March 2018 : Rs. 7.50 Crore
FILLING UP OF 35 MI / ZP TANKS IN YADGIR DIST.
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Location Lifting water from backwater of Yadgir Barrage across River Bhima .
Components of the Scheme
Intake Canal 1st Head Work U/s of Yadgir Barrage 2nd Head Work near Dharmapur village 2nd Sub Raising Main, Gravity Main & Pipe Distribution Network for filling up of 35 MI / ZP Tanks
Delivery Chamber
Administrative Approval GO No.WRD/135/KBN/2017 Dtd:08.11.2017 for Rs.440.00 Crore
Intake Level RL : 344.00 Mt.
Delivery Level DC-1 : RL : 642.00 M DC-2 : RL : 406.00 Mt. DC-3 : RL : 417.00 Mt.
Commencement of work March 2018
Name of Tanks Filling
.
From Jackwell Cum Pump House-1 (Raising Main-1)
1) Ramasamudram
2) Paspol
3) Gopalapur
4) Chintalapalli
5) Anapur
From Jackwell Cum Pump House-1 (Raising Main-3)
6) Lingeri
7) Haligeri
8) Nagalapur
9) Kilakera Rayan
10) Kalabelagundi
11) Madhwar tank
From Jackwell Cum Pump House-2 (Raising Main-2)
12) Dharmapur
From Delivery Chamber-1 under Pump House-1
13) Jangamakeri
14) Machalanacheruvu
15) Kakalwar Tank-1
16) Kakalwar Tank-2
17) Chandaraki
18) Guramitkal
19) Itakal Tank-1
20) Mothakapalli
21) Tulmamadi
22) Buragapalli
23) Madhwar Kotakunta
From Delivery Chamber-2 under Pump House-1
24) Nilahalli
25) Kanekal Rekalkunta
26) Gudalgunta
27) Sambra
28) Kadechur Eramma
29) Duppalli
From Delivery Chamber-3 under Pump House-1
30) Yelasatti
31) Nasalwayi
32) Goranur
33) Thoranatippa
34) Karanagi
35) Jegram
Dist. / Taluk benefited Yadgir Dist. : Yadgir Tq. Kalburgi Dist. : Chitapur Taluk
Project Estimated Cost : Rs.440.00 Crore
PROVOIDING VERTICAL LIFT GATE FOR YADGIR BRIDGE CUM BARRAGE ACROSS RIVER BHIMA
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Location: Near Yadgir Town across River Bhima
Utilisation 1.01 TMC
Command Area 1,935 Ha. (Own Lift by Farmers)
Length of Bridge 425 Mts
Cill Level RL 351.00 Mt.
FRL of Barrage RL 359.50 Mt
No. of Vents 24
Gates 24 No. Vertical Lift Gates of Size 15 Mt x 8 Mt.
Administrative Approval
GO No.WRD / 152 / KBN / 2017 Dtd: 04.10.2017 for Rs.58.00 Crore
Commencement of Project Work
April 2018.
Scope of the Project Providing Vertical Lift Gates with Mechanically Operated Hoisting
System by Extending alternate piers of existing Yadgir Barrage,
Present stage of work Concreting of Foundation Work on D/s of existing Barrage in progress. Fabrication of Vertical Lift Gates in progress.
Providing Vertical Lift Gates will ensure optimum utilization of water storage at barrage
Project Estimated Cost : Rs.58.00 Crore Expenditure Incurred : Rs.10.80 Crore
Existing Yadgir Barrage
Foundation
PROVOIDING VERTICAL LIFT GATE FOR JOLADADGI-GUDUR BARRAGE ACROSS RIVER BHIMA
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Location: 11 Km U/s of confluence of River Bhima & Krishna
Utilisation 1.29 TMC
Command Area 1,960 Ha. (Own Lift by Farmers)
Length of Bridge 550 Mts
Cill Level RL 340.20 Mt..
FRL of Barrage RL 347.20 Mt
No. of Vents 44
Gates 44 No. Vertical Lift Gates of Size 10.50 Mt x 7.00 Mt.
Administrative
Approval
GO No.WRD / 151 / KBN / 2017 Dtd: 04.10.2017 for Rs.57.00
Crore
Commencement of Project Work
April 2018.
Scope of the Project Providing Vertical Lift Gates with Mechanically Operated Hoisting System by Extending alternate piers of existing Joladadgi-Gudur Barrage,
Present stage of work
Excavation of Foundation Work on D/s of existing Barrage in
progress. Fabrication of Vertical Lift Gates in progress.
Providing Vertical Lift Gates will ensure optimum utilization of water storage at barrage
Project Estimated Cost : Rs.57.00 Crore
Expenditure Incurred : Rs.12.24 Crore
Existing Joladaggi-Gudur Barrage View
Remodeling of SBC, MBC & JBC under AIBP- PMKSY
SALIENT FEATURES OF COMPLETED PROJECT
Salient Features Photo
Scope of the Project:
Remodeling of Canal Networks under NLBC-ERM Project : a) Shahapur Branch Canal (SBC) b) Jewargi Branch Canal (JBC)
c) Mudbal Branch Canal (MBC)
Funding Under AIBP – PMKSY of GOI
Command Area Restoration of Command Area (Suffering Atchcut) under SBC, JBC & MBC
Components of the Scheme
a) Remodeling of Canal Network of SBC, JBC & MBC
b) SCADA Automation (Installation of Automated Integrated Gates) & GIS System for SBC, JBC & MBC Canal Network,
Commencement of Project
March 2014.
Present stage of the works
a) Remodeling of SBC, JBC & MBC Canal Network completed. b) Tender Invited for SCADA Automation System for SBC,
JBC & MBC Canal System in progress.
ERM of Canal Network facilitate Equitable Distribution of water & Improvement in Water Use Efficiency
Expenditure Incurred : Rs.1653.60 Crore.
Remodeling Done of SBC Main Canal Remdeling
Remodeling Done of MBC Main Canal
Remodeling Done of Distributary Ne